RISK SCORE CALCULATOR
Use the Risk Score Calculator to Determine the Level of Risk of each Hazard
What would be the
CONSEQUENCE
of an occurrence be? What is the LIKELIHOOD of an occurrence? Hierarchy of Controls
Frequent/Almost certain (5)
Continuous or will happen frequently Often (4)
6 to 12 times a year Likely (3)
1 to 5 times a year Possible (2)
Once every 5 years Rarely (1)
Less than once every 5 years Can the hazard be Eliminated or removed from the work place?
Catastrophic (5)
Multiple Fatalities High 25 High 20 High 15 Medium 10 Medium 5 Can the product or process be substituted for a less hazardous alternative?
Serious (4)
Class 1 single fatality High 20 High 16 High 12 Medium 8 Low 4 Can the hazard be engineered away with guards or barriers?
Moderate (3)
Class2 (AWI or LTI) or Class 1 Permanently disabling effects High 15 High 12 Medium 9 Medium 6 Low 3 Can Administration Controls be adopted
I.e. procedures, job rotation etc.
Minor (2)
Medical attention needed, no work restrictions. MTI Medium10 Medium 8 Medium 6 Low 4 Low 2 Can Personal Protective Equipment & Clothing be worn to safe guard against hazards?
Insignificant (1)
FAI Medium10 Medium 4 Low 3 Low 2 Low 1
Project Name: xxx
RA Ref No.: xxx
RA compilation Date: Review date:
Date:
Compiled by:
Reviewed by:
Approved by:
Overall Task Details
Excavation on site greater than 1.2 depth for Non Disruptive Road Crossing (NDRC). Use of excavator and pipe thrust boring equipment
Classed as Temporary Works Relevant Applicable MAS:
• 00246 – Excavations;
• 01413 – Underground services;
• 00940 – Plant Operators. Additional Training required:
Temporary Works Coordinator to be designated NOC’s Required for task:
Municipality
No Specific Task Step
(In sequence of works) Hazard Details Consequence/Risk Initial Risk Rating Control Measures Residual Risks Additional Control Measures RR
L C RR
1 Planned excavation for NDRC pit in areas where live services may be present including:
• Electrical;
• Water;
• Sewerage;
• Gas;
• Telecoms;
PRIOR TO WORKS • Presence of live underground services;
• Services not in area specified on drawings;
• Heavy plant or vehicles accessing work area;
• Presence of unmarked services;
• Risk of explosion due to gas line rupture;
• Risk of flooding of excavation and adjacent areas due to water main damage;
• Risk of electrocution or fire due to cable strike;
• Risk of hazardous waste entering excavation or water systems due to live sewerage damage;
• Risk of damage to low depth underground services from heavy vehicles;
• Risk of vehicles / Plant entering open excavation; 4 5 20
HIGH i. All existing utility service drawings reviewed for known service details and position;
ii. NOC and Utility provider and ATC Excavation permits to be completed, unique number added and recorded in log;
iii. Work Area, including access route for plant, to be CAT scanned to locate exact position of service by competent persons;
iv. Service clearly marked
31 NDRC operations within Excavations (Temporary Works) Risk Assessment Templates.docx
1. HEALTH SAFETY AND ENVIRONMENT Author: Approved:
RISK ASSESSMENT: ACT/HSE/RA 001 NDRC operations within Excavations (Temporary Works)
Issued: Rev. Date:
Revision: 0
Page 1 of 4 HSEQ -Rev-01(Jan-2023)
No
Specific Task Step
(In sequence of
works)
Hazard Details Consequence/Risk
Initial Risk
Rating Control Measures Residual Risks
Additional Control
Measures
RR
L C RR
1
Planned excavation for
NDRC pit in areas
where live services
may be present
including:
Electrical;
Water;
Sewerage;
Gas;
Telecoms;
PRIOR TO
WORKS
Presence of live
underground services;
Services not in area
specified on drawings;
Heavy plant or
vehicles accessing
work area;
Presence of
unmarked services;
Risk of explosion due to gas line
rupture;
Risk of flooding of excavation and
adjacent areas due to water main
damage;
Risk of electrocution or fire due to
cable strike;
Risk of hazardous waste entering
excavation or water systems due to
live sewerage damage;
Risk of damage to low depth
underground services from heavy
vehicles;
Risk of vehicles / Plant entering open
excavation;
4 5
20
HIGH
i. All existing utility service drawings reviewed for known service details and
position;
ii. NOC and Utility provider and ATC Excavation permits to be completed,
unique number added and recorded in log;
iii. Work Area, including access route for plant, to be CAT scanned to locate
exact position of service by competent persons;
iv. Service clearly marked on ground, using posts, tags etc.;
v. Plant access route to be indicated;
vi. Any unidentified services marked on ground and drawing by Temporary
Works Coordinator or Temporary Works Supervisor;
vii. All services clearly communicated to all workers at briefings and TBT’s,
signed off and recorded;
viii. Permit/NOC/JSEA/Approved design Drawings copies to be with task
supervisor in work area for review;
ix. Supervision and Plant Operators instructed to stay within designated area
and access route; All excavation barriers to be planned and to RTA Traffic
Management Manual if adjacent to live roads;
Workers not
complying with
controls
All supervision to monitor
operation;
Regular topic in TBT’s
LOW
2
Use of Excavator for
excavating NDRC Pit
and backfilling
Working with plant in
vicinity of workers;
Working in vicinity of
underground services;
Untrained operator;
Excavator used for
lifting operations;
Workers struck by operating plant;
Worker struck by reversing plant;
Underground service strike;
Material falling into excavation;
Damage to machine;
Collapse of excavation due to
incorrect design/digging;
Use of incorrect lifting points;
4 4
16
HIGH
i. Supervision and Plant operators instructed not to machine excavate within
1.5m of marked service;
ii. Hand digging only to expose services communicated, only use shovels
marked at 1.2m for guidance;
iii. All operators to be Third Party approved for the type of machine, licence
available for review at all times;
iv. Machine in – Men out mantra to be adhered to. No personnel shall be
inside the excavation when the excavator is working, when personnel are
inside the excavation the excavator shall rotate away and be isolated;
v. No personnel in excavation when pipes etc. are being lowered into
position, to stand outside of excavation;
vi. Banksman to control excavator movements; Spotter to assist operator to
observe and warn of any unidentified services;
vii. All lifting points used on excavators for lifting pipes etc. into position shall
be specified and designated lifting points only;
Damage to
undetected
underground
services
Machine
breakdown
Hydraulic fluid spill
ATC Engineer shall
immediately contact
DEWA/Etisalat/Du as required
for action.
Area isolated.
Machine isolated and
quarantined until repaired.
Spoil removed and treated as
hazardous waste
LOW
RISK SCORE CALCULATOR
Use the Risk Score Calculator to Determine the Level of Risk of each Hazard
What would be the
CONSEQUENCE
of an occurrence be?
What is the LIKELIHOOD of an occurrence? Hierarchy of Controls
Frequent/Almost certain (5)
Continuous or will happen
frequently
Often (4)
6 to 12 times a year
Likely (3)
1 to 5 times a year
Possible (2)
Once every 5 years
Rarely (1)
Less than once every 5
years
Can the hazard be Eliminated or removed
from the work place?
Catastrophic (5)
Multiple Fatalities
High 25 High 20 High 15 Medium 10 Medium 5
Can the product or process be substituted for
a less hazardous alternative?
Serious (4)
Class 1 single fatality
High 20 High 16 High 12 Medium 8 Low 4
Can the hazard be engineered away with
guards or barriers?
Moderate (3)
Class2 (AWI or LTI) or Class 1
Permanently disabling effects
High 15 High 12 Medium 9 Medium 6 Low 3
Can Administration Controls be adopted
I.e. procedures, job rotation etc.
Minor (2)
Medical attention needed, no work
restrictions. MTI
Medium10 Medium 8 Medium 6 Low 4 Low 2 Can Personal Protective Equipment &
Clothing be worn to safe guard against
hazards?
Insignificant (1)
FAI
Medium10 Medium 4 Low 3 Low 2 Low 1
Project Name: xxx
RA Ref No.: xxx
RA compilation
Date:
Review date:
Date:
Compiled by:
Reviewed by:
Approved by:
Overall Task Details
Excavation on site greater than 1.2 depth for Non Disruptive Road Crossing
(NDRC). Use of excavator and pipe thrust boring equipment
Classed as Temporary Works
Relevant Applicable MAS:
00246 – Excavations;
01413 – Underground services;
00940 – Plant Operators.
Additional Training required:
Temporary Works Coordinator to be designated
NOC’s Required for task:
Municipality
2. HEALTH SAFETY AND ENVIRONMENT Author: Approved:
RISK ASSESSMENT: ACT/HSE/RA 001 NDRC operations within Excavations (Temporary Works)
Issued: Rev. Date:
Revision: 0
Page 2 of 4 HSEQ -Rev-01(Jan-2023)
No
Specific Task Step
(In sequence of
works)
Hazard Details Consequence/Risk
Initial Risk
Rating Control Measures Residual Risks
Additional Control
Measures
RR
L C RR
viii. Daily checks on machine undertaken prior to commencing work;
3
Excavation open in site
area
Excavation in
working areas with
live traffic
movements and
pedestrians;
Unprotected
excavation area;
Excavation not to
approved design;
Damage to exposed existing live
underground services;
Trench/excavation collapse;
Falling/slipping into trenches;
Overturning of Truck / machinery into
excavation;
Incident due to poor illumination;
Incident due to hazardous gas/fumes
entering excavation;
Collapse/damage of structures due to
undermining;
Difficulty rescuing injured or collapsed
worker from deep excavation;
4 4
16
High
i. Temporary Works Coordinator / Construction Team to ensure Permit to
Excavate has been issued, communicated and signed by personnel prior
to any excavation work;
ii. Excavation safety buffer, protection, design and traffic signs to be to ATC
Minimum Acceptable Standard, RTA Manual Chapter 3 requirements (as
applicable) and DM Code of Practice -Section 9;
iii. Any exposed services to be protected and adequately supported to avoid
damage;
iv. Any unidentified services discovered to be immediately communicated to
management and work stopped;
v. All spoil to be maintained at least 2m from excavation;
vi. Trench boxes to be used where practicable, backfilled behind;
vii. All shoring, trench sheet supports etc. to be as per approved design,
following correct working procedures;
viii. Temporary Works Coordinator to ensure excavation design adhered to at
all times;
ix. On deep excavations where a suitable ramp cannot be created, a
platform with winch to be established to facilitate emergency rescue of
workers;
x. Provide access ladders or ramps that suitable to the size and location of
excavation. Access and egress ladders/steps to be secured, every 20m
on long runs, or steps dug into soil, suitably supported;
xi. All excavations below 1.2m depth to be benched/battered back to MAS
standards;
xii. Excavation to be inspected daily with written inspection report weekly by
Temporary Works Supervisor;
xiii. Daily briefings to workers on working in excavations requirements by
supervision;
xiv. Use of stop blocks, barriers and other suitable means of protection used
to prevent vehicles entering excavations, warning tape is not to be used
as primary protection;
xv. Where practicable, access roads and pedestrian walkways to be
established away from excavations;
xvi. Suitable and sufficient signage introduced to excavations;
xvii. Backfilling of trenches/excavations to be undertaken as soon as possible
after verification or completion of works;
xviii. Excavation to be suitably illuminated during night times;
xix. No changes to excavations without re-submittal of design reviewed by
the TWC, NOC and Permits;
Vehicle entering
excavation
Excavation
collapse
Incident due to
barrier removal
Emergency services called,
area cleared
Secure area
No removal of protection
barriers without prior approval
from management.
LOW
4
Confined space
working – deep
excavation for NDRC
Workers required to
work in confined
space;
Excess or lack of oxygen;
Presence of Toxic gases;
Ingress of water or other substances;
Explosion due to build-up of gases;
Sudden water ingress into excavation;
Restricted emergency evacuation.
4 4
16
High
i. Permit to be issued & gas monitoring undertaken if required before works
commence;
ii. Adequate air circulation & lighting to be maintained in work areas;
iii. Equipment which may release excess oxygen or carbon monoxide gases
shall not be used in confined space areas without adequate extraction;
iv. Local weather forecast should be noted to watch for heavy rains which
may cause flooding;
v. Special consideration to be given to any hot works or work using toxic
substances inside a confined space;
vi. Materials to be stored well away from confined space area;
vii. Top man to be appointed at the entry of the confined space area as
required;
viii. Workers should be physically fit and competent to enter and undertake
the work in confined spaces;
ix. Rescue platform to be established with tripod;
Workers not
adhering to
requirements;
Gas detector not
calibrated
resulting in
incorrect reading
Supervision to constantly
monitor workers;
Regular TBT’s & Trainings to
be given on working Confined
space;
Gas detector to be calibrated
to standards and
manufacturers
recommendations.
Low
3. HEALTH SAFETY AND ENVIRONMENT Author: Approved:
RISK ASSESSMENT: ACT/HSE/RA 001 NDRC operations within Excavations (Temporary Works)
Issued: Rev. Date:
Revision: 0
Page 3 of 4 HSEQ -Rev-01(Jan-2023)
No
Specific Task Step
(In sequence of
works)
Hazard Details Consequence/Risk
Initial Risk
Rating Control Measures Residual Risks
Additional Control
Measures
RR
L C RR
5
NDRC – Thrust boring
operation
Use of lifting
equipment to lower
machine;
Concrete pumping
within excavation
Lifting operations, fall of material and
over-sailing workers;
Electrical connections; 4 4
16
HIGH
i. Follow RA12 – Mobile crane for lifting Ops;
ii. Follow RA14 – Use of concrete pump;
iii. Dewatering pump to be set up as required;
iv. When excavation is complete, blinding concrete shall be cast in the base
of the pit to provide stable level ground for the boring machine;
v. If required, concrete thrust wall to be cast, to provide pressure plate for
the machine;
vi. Emergency rescue procedures to be established, with area designated
for rescue tripod on deep excavations;
vii. The temporary electrical supply to the borer is to be to accepted
standards with correct connections, fittings and earthing, undertaken by
competent electrician;
viii. All members of the boring team are to be trained and experienced in the
use of the equipment;
ix. Consideration shall be taken regarding the removal of spoil from the
boring pit;
x. No guards to be removed from the equipment;
xi. At no time will workers be allowed to enter pipework without correct
precautions in place;
xii. No lone working inside pit;
Injury to worker
inside pit
Rescue drills to be undertaken
to ensure effective rescue
Low
6
Pipe electric welding
inside pit
Use of Arc welding
equipment;
Risk of fire;
Risk of damage to integrity of dust
protection;
Risk of electric shock through
equipment fault;
Workers exposed to welding flash;
3 4
12
HIGH
i. ATC PTW implemented;
ii. Fire extinguishers and Fire watchman in area, and will maintain 1 hour
fire watch after completion of work
iii. All welding equipment shall be tested by a competent electrician and to
standards, correct earth grounding shall be implemented;
iv. All leads shall be undamaged, with correct connections fitted;
v. Welder to be competent and experienced in the task;
vi. Welding set raised off the ground to prevent contact with groundwater,
placed outside pit if practicable;
vii. If welding generator is used, drip tray to be fitted, with additional
grounding added;
viii. Refuelling of generator, correct fuel cans/pumps used;
ix. Flash screen implemented to ensure other workers not exposed to flash
inside pit;
x. Welder to wear correct protection, gloves, apron etc.;
Welding leads
damaged
Fuel spillage
Quarantine welding set.
Replace leads
Remove contaminated soil and
treat as hazardous waste
Low
7.
HDPE Welding inside
pit
Fusion Welding;
Confined space;
Risk of Fire or Explosion in Gaseous
environments;
Failure of equipment;
Incorrect and insufficient welded joint
causing breaking of pipe when
shifting into position – risk of injury;
Injury due to untrained personnel;
Electric shock due to damaged wiring
of equipment;
Injury due to unguarded clamps and
cutting blades;
Risk of manual handling injuries while
transporting equip
Risk of burns form contact with hot
parts;
3 4
12
HIGH
i. Caution to be used when used inside excavations, gas testing and PTW
in place;
ii. All personnel trained and certificated in the use of the equipment;
iii. Manufacturers protocols and operating procedures communicated;
iv. Test certificates available and in-date;
v. PAT test completed and equipment tagged;
vi. All guards to be in place;
vii. All gases to be vented and levels checked with gas meter before
electro-fusion takes place;
viii. Some equipment delivers up to 48V AC via the output connector and
lead. The unit output power must not be energized without proper
connection of the correct fitting type;
ix. Avoid walking or standing on cables and ensure that the cables are
safely routed;
x. Where practicable mechanical lift to be used to transport the equipment
at all times;
Injury to worker
inside pit
Rescue drills to be undertaken
to ensure effective rescue
Low
4. HEALTH SAFETY AND ENVIRONMENT Author: Approved:
RISK ASSESSMENT: ACT/HSE/RA 001 NDRC operations within Excavations (Temporary Works)
Issued: Rev. Date:
Revision: 0
Page 4 of 4 HSEQ -Rev-01(Jan-2023)
No
Specific Task Step
(In sequence of
works)
Hazard Details Consequence/Risk
Initial Risk
Rating Control Measures Residual Risks
Additional Control
Measures
RR
L C RR
Risk of injury due to incorrect fusion
welding of joint resulting in injury
during lifting into situ;
Risk of injury through poor
maintenance of welder;
Risk of eye injury;
Risk of damage to cables;
Risk of tripping;
xi. The process of Electro-fusion jointing generates heat in the fitting. Heat
resistant gloves are to be used at all times when working with hot
components;
xii. Hands and feet to be kept clear of clamps, emergency stop switch must
be functioning and within reach at all times;
xiii. Ensure correct pipe alignment to avoid failure of joint with injury potential
during lifting;
xiv. Ensure Heat Soak time is as manufacturers requirement to avoid failure
of joint during lifting;
xv. Maintenance schedule to be adhered to and available for inspection;
xvi. Ensure dwell time is correct to avoid joint failure;
xvii. Eye protection to be worn at all times;
xviii. All protective equipment to be worn at all times;
8
Maintenance of NDRC
Excavation
Adverse weather;
Excavations open for
long periods;
Unapproved
amendments to
design;
Collapse of excavation due to
alterations;
Damage to excavations due to
incident or adverse weather;
Incident due to removal of barriers
3 3
9
Med
i. Excavation checked after heavy rains, severe winds etc., stand by
pumps to be available as required;
ii. Weekly recorded inspections undertaken;
iii. Implemented warning signage maintained;
iv. Housekeeping inside excavation to be maintained, all rubbish and waste
material to be removed daily;
Low
9
Worker exposure to
direct sun
(as applicable)
Workers exposed to
high summer
temperatures;
Worker ill health due to:
Heat exhaustion,
Heat stroke;
Heat Stress.
3 4
12
High
i. Summer Hour Working plan to be designed and implemented;
ii. Municipality summer working hours observed and implemented
(12.30pm to 3.00pm restricted in direct sunlight);
iii. Workers instructed regarding working in the heat and signs of heat
exhaustion etc. at Induction;
iv. Recovery cool rooms established on site;
v. Cool welfare areas established in all locations;
vi. Cool fresh water and electrolyte supplements to be maintained in all
areas;
vii. Pipe welders etc. provided with localised shelters;
New workers
bought onto site
Regular topic in Toolbox Talks Low