SUMMER INDUSTRIAL TRAINING
DEEPAK CHANDAK-13EJIME032
JODHPUR INSTITUTE OF ENGINEERING
AND TECHNOLOGY(CO ED,MECHANICAL)
AT ONGC ANKLESHWAR
SUBMITTED TO-
HOD- M R BAID
(MECHANICAL)
OILAND NATURAL GAS CORPORATION
INDUSTRY- OILAND GAS
HEADQUARTER- TEL BHAVAN, DEHRADUN, UTTRAKHAND
CHAIRMAN & MD- DINESH KUMAR SARAF
OWNER- GOVERNMENT OF INDIA
PRODUCTS- PETROLEUM, NATURAL GAS, AND OTHER
PETROCHEICALS.
ABOUT ONGC
“to give world leadership in management of energy source, exploration of
energy sources, diversification of energy sources, technology in Underground
Coal Gasification, and above all, finding new ways of tapping energy
wherever it is, to meet the ever-growing demand of the country”
VISION STATEMENT
ONGC
33,560
EMPLOYEES
11 ASSETS(OIL & GAS)
7 BASINS(EXPLORATORY)
2 PLANTS(OIL REFINING)
SERVICES (DRILLING, WELL
SERVICES, LOGGING, )
7.1 BILLION TONNES OF
HYDROCARBONS (TILL
NOW)
11,000 KMS OF PIPE -
LINES OVER COUNTRY
PRODUCTS- CRUDE OIL,
GAS, LPG, NAPTHA, C2-C3
AND OTHER HYDRO-
CARBON’S PRODUCTS
ABOUT ONGC ANKLESHWAR ASSET
• STARTED IN 1960, PRODUCTION STARTED IN 1961.
• SITUATED AT ANKLESHWAR, BHARUCH, GUJRAT.
ANKLESHWAR
ASSET, ONGC
HAS 4 FIELDS OF OIL
-ANKLESHWAR(1960, well depth~1100m)
-GANDHAR(1984, well depth~3200m)
-JAMBHUSAR(1999, well depth~3800m)
-DAHEJ(2005, well depth~3500m)
HAS 11 GGS (GGS
1-7, GGS DAHEJ,
GGS JOLWA, GGS
DABKA, GGS
GANDHAR), 1 CTF
1 CPF, 1 MPH
HAS 7 NO. OF OIL RIGS:-
2 MOBILE RIGS(CWX, M-450)
4 ELECTRICAL( E-1400-3, E-
1400-7, E-760, E-2000)
1 VFD(EV-2000-2)
HAS MORE THAN
6000 WELLS
DRILLED TILL
DATE & MORE
THAN 300
ACTIVE WELLS
HAS VARIOUS
DEPARTEMENTS
LIKE DRILLING,
FISHING, LOGGING,
CASING, MATERIAL,
INTRUMENTATION,
SURFACE etc..
OUTSOURCING FOR
VARIOUS SERVICES
LIKE DIECTIONAL
DRILLING, FISHING,
DRILLING, WORK-
SHOP SERVICES FOR
MACHINES etc..
FORMATION OF OIL
PROCESS OF FORMATION OF OIL IN EARTH
1. E.g. PLANTS AND ANIMALS.
2. BURIED UNDER LAYER
OF SOIL.
3. DUE TO FORMATION OF MORE
SOIL LAYERS.
4. DUE TO HEAVY ROCKS
HIGH TEMPRETURE &
PRESSURE.
5.HIGH TEMPRETURE & PRESSURE
UNDER ROCKS FOR LONG TIME.
6.THE CONVERSION PRO-
CESS OVER YEARS.
LIVING
ORGANISM
DEAD
BODIES
BIOPOLYMER
GEOPOLYMER
(KEROGEN)
PETROLEUM
FOSSIL FUELS
BITUMEN
PROCESS OF OIL PRODUCTION
DATA FROM SATELLITE SEISMIC SURVEYS
RIG MOVING,BUILDING & LEVELLING
THE CHRISTMAS TREE DRILLING PROCESS
DRILLING RIG
A Rig is a complete Mechanical machine that consist of the structure and the
machines that were used for drilling of oil well.
DRILLING PROCESS
Readying of drilling
location (surface
leveling, water
sources, pipeline
setup etc).
Rig moving / Rig
building
If a free rig is there in
nearby area then rig
moving & rig building
else only rig building.
The drilling process
starts that includes
mud circulation,
casing, cementation,
inert of drill pipes,
fishing etc.
Various simultaneous
processes takes place
such as mud cleaning,
data handling of well
like temp. pressure
etc, maintenance of
various machines etc.
When it is get to
know that oil starts
coming, the rig is
removed and ‘The
Christmas Tree’ is
placed there in place
for oil production.
A continuous care
is taken of well
data like pressure,
temp., gas from
mud after drilling,
the required depth
of drilling etc.
THE DRILLING PROCESS (INSIDE VIEW)
Major Drilling Equipment
Divided Into Following Categories:
–Hoisting Equipment (used for raising and and
lowering of drill pipes)
–Rotary Equipment (used to give rotary power to
drill bit for cutting action)
–Circulating Equipment (for circulation of mud)
Hoisting Equipment
1. Draw works
One of the major drilling equipment on the rig
Raises or lowers drill string, casing and other equipment in well
TRAVELLING BLOCK HOOK
CROWN BLOCK
Rotating equipments
SWIVEL TOP DRIVE SYSTEM
SWIVEL IS CONNECTED BETWEEN DRILL PIPE AND HOOK
TOP DRIVE SYSTEM IS USED TO DRIVE THE WHOLE ROTARY SYSTEM
MUD CIRCULATION SYSTEM
TYPES OF DRILL BITS
MILLED TOOTH BIT
USED FOR CUTTING
OF UPPER LAYER OF
SAND (GENERALLY
UPTO 400-700 m.)
INSERT BIT
USED FOR CUTTING
OF ROCKS AND SAND
(DEPTH UPTO 1200m.)
POLYCRYSTALLINE
DIAMOND COMPACT
DRILL BIT
USED FOR CUTTING OF
HARD FORMATION OR
ROCKS (DEPTH 1000m.
AND ABOVE).
CASING & CEMENTATION PROCESS
 Casing is large diameter pipe that is assembled and inserted into a recently
drilled section of a bore hole and typically held into place with cement.
The following casing intervals are typically used in an oil or gas well:
• Conductor casing
• Surface casing
• Intermediate casing (optional)
• Production casing
 The basic principle of cementing operations is the displacement of cement
slurry down the casing, tubing or drill pipe to a pre-specified point in the
well.
 The main functions of primary cementation are:-
• To bond and support the casing.
• Protecting the casing from corrosion.
• To restrict fluid movements between formations.
• Protecting the casing from shock loads during drilling of next zone.
• Sealing off problematic zone
TYPES OF CASING
COST ANALYSIS OF DRILLING RIG E-1400-7
Drilling Cost
Operating
Cost
Man Power
Diesel Cost
Well Cost
Mud cost
Casing cost
Drill bit cost
Out sourcing cost
Cementing cost
Maintenance
Cost
OPERATING COST
Net operating cost included two types of cost:
• Man power cost (assuming man power cost as a fixed cost)
• Variable cost
 It includes:
 Diesel cost
 Mud cost
 Casing Cost
 Drill Bit Cost
 Out Sourcing Cost
 Cementing Cost
 Maintenance cost
DIESEL COST
 Total available engines at the drilling site:4 nos
• Based on the operational requirement engines are
started. Sometimes operation are carried out with 3 or
4 engines or sometimes by one or two engines
• Diesel consumption is approx. 7000 liters per day (it
includes diesel consumption of all the engines)
• Net diesel consumption is 7000*30*3 (per well) =
630000 liters
• Diesel cost is Rs.58.84 per liter.
• Total diesel cost is 630000*58.84 = Rs.3,70,69,200
2.WELL COST
1. MUD COST
• Mud is the mixture of water, bantonite clay, thinner and lubricating oil.
• Its cost is around Rs.70 per liter.
• And 150000 liters of mud is used for drilling of a well of around 3000 meters depth.
• So total mud cost is 150000*70 = Rs.1, 05, 00,000.
2. CASING COST
• Cost of conductor casing is Rs. 3667.05 per meter.
So total cost of conductor casing is = 3667.05*200 = Rs. 7,33,410
• Cost of intermediate casing is Rs. 2015.31 per meter.
So total cost of intermediate casing is = 2015.31*1600 = Rs. 32,24,494
• Cost of production casing is Rs. 1311.51 per meter.
So total cost of production casing is = 1311.51*3233 = Rs. 42,40,139
• Total casing cost = 81, 98, 043 or approx. 82 lakhs.
3. DRILL BIT COST
 Generally two types of drilling bits are used
1. Fixed cutter and tri conical roller
2. PDC (Poly Crystalline Diamond Compact) bit
Cost of fixed cutter and tri conical roller is 15 lakhs per bit.
Cost of PDC is around 50 lakhs per bit.
One well consumes around one TCR and one PDC bit.
Total drill bit cost = Rs. 65 lakhs.
4. OUT SOURCING COST
Out sourcing means giving specific job to any private industry. For example: - Jindal,
Schlumberger and CAIRN etc.
For directional drilling ONGC out sources the job to different companies.
Cost of out sourcing is around 2 crore.
5. CEMENTING COST
TOTAL CEMENTING COST= Rs. 1954533 = 20 lacs.
3. Maintenance cost
• The maintenance budget of ONGC per year for 6 drilling rigs
is around 50 crore.
• Each rig drills average 5 wells per year.
• So maintenance cost per well is around 1.67 crore.
TOTAL DRILLING COST
• Operating Cost = 3.70 crore
• Well Cost = 4.72 crore
• Maintenance Cost = 1.67 crore
• Total cost = 10.09 = 10 crore
SITE VISITS
 The rigs that we have visited:
• CARDWELL-10
• M-450
• E-760-5
• E-2000-2
• E-1400-7
 GGS (Group Gathering Station)
 CTF (Central Tank Farm)
 MPH (Main Pump House)
PRODUCTION
• From 1 GGS around 1000
m^3/day liquid (oil +water) is
sent to CTF.
• And oil production in CTF from 1
GGS is around 150m^3/day
• LPG production per day is around
10 to 15 tones.
• Naptha production per day is
around 20 tones.
After summer training at ONGC ankleshwar,
I have known about the process of oil well drilling
from starting to finish, at the Ankleshwar field
and Gandhar field. We also visited GGS, CTF
and MPH. we also conducted one project work,
“COST ANALYSIS OF DRILLING RIG E1400-7”.
CONCLUSION
THANK YOU

More Related Content

What's hot

What's hot (20)

Reservoir dive mechanisms
Reservoir dive mechanismsReservoir dive mechanisms
Reservoir dive mechanisms
 
Summer training project on drilling fluid at ongc ppt
Summer training project on drilling fluid at ongc pptSummer training project on drilling fluid at ongc ppt
Summer training project on drilling fluid at ongc ppt
 
Exploration and Production of Hydrocarbons(OIL and Natural Gas) in india
Exploration and Production of Hydrocarbons(OIL and Natural Gas) in indiaExploration and Production of Hydrocarbons(OIL and Natural Gas) in india
Exploration and Production of Hydrocarbons(OIL and Natural Gas) in india
 
Le 03 Natural Gas (NG) Transportation and Distribution
Le 03 Natural Gas (NG) Transportation and DistributionLe 03 Natural Gas (NG) Transportation and Distribution
Le 03 Natural Gas (NG) Transportation and Distribution
 
Heater treater
Heater treaterHeater treater
Heater treater
 
Refinery process
Refinery process Refinery process
Refinery process
 
Iocl training
Iocl trainingIocl training
Iocl training
 
Drilling fluids
Drilling fluidsDrilling fluids
Drilling fluids
 
Petroleum classification physical properties
Petroleum classification physical propertiesPetroleum classification physical properties
Petroleum classification physical properties
 
Introduction to Gas Transportation
Introduction to Gas TransportationIntroduction to Gas Transportation
Introduction to Gas Transportation
 
Fundamentals of Petroleum Engineering Module 6
Fundamentals of Petroleum Engineering Module 6Fundamentals of Petroleum Engineering Module 6
Fundamentals of Petroleum Engineering Module 6
 
Introduction to oil and gas industry
Introduction to oil and gas industryIntroduction to oil and gas industry
Introduction to oil and gas industry
 
Unconventional reservoirs
Unconventional reservoirsUnconventional reservoirs
Unconventional reservoirs
 
quality analysis of crude oil and drilling fluids
quality analysis of crude oil and drilling fluids quality analysis of crude oil and drilling fluids
quality analysis of crude oil and drilling fluids
 
Training report Oil India Limited LPG, Duliajan by upal jb
Training report Oil India Limited LPG, Duliajan by upal jbTraining report Oil India Limited LPG, Duliajan by upal jb
Training report Oil India Limited LPG, Duliajan by upal jb
 
Functions of drilling rig components Presentation
Functions of drilling rig components PresentationFunctions of drilling rig components Presentation
Functions of drilling rig components Presentation
 
NATURAL GAS DEHYDRATION
NATURAL GAS DEHYDRATION NATURAL GAS DEHYDRATION
NATURAL GAS DEHYDRATION
 
Unconventional Petroleum
Unconventional PetroleumUnconventional Petroleum
Unconventional Petroleum
 
Gas Lift Design: Comparative Study of Continuous and Intermittent Gas Lift (C...
Gas Lift Design: Comparative Study of Continuous and Intermittent Gas Lift (C...Gas Lift Design: Comparative Study of Continuous and Intermittent Gas Lift (C...
Gas Lift Design: Comparative Study of Continuous and Intermittent Gas Lift (C...
 
Natural gas processing technology separation
Natural gas processing technology    separationNatural gas processing technology    separation
Natural gas processing technology separation
 

Viewers also liked (6)

Tuberia, Conceptos y fundamentos tecnicos.
Tuberia, Conceptos y fundamentos tecnicos.Tuberia, Conceptos y fundamentos tecnicos.
Tuberia, Conceptos y fundamentos tecnicos.
 
Drilling Engineering - Drilling Economics
Drilling Engineering - Drilling EconomicsDrilling Engineering - Drilling Economics
Drilling Engineering - Drilling Economics
 
Rig types.
Rig types.Rig types.
Rig types.
 
ongc project
ongc projectongc project
ongc project
 
ONGC final ppt
ONGC final pptONGC final ppt
ONGC final ppt
 
Como colocar as referências segundo a abnt
Como colocar as referências segundo a abntComo colocar as referências segundo a abnt
Como colocar as referências segundo a abnt
 

Similar to Ongc drilling services introduction

Design and fabrication of oil skimmer PPT .pptx
Design and fabrication of oil skimmer  PPT .pptxDesign and fabrication of oil skimmer  PPT .pptx
Design and fabrication of oil skimmer PPT .pptx
SriJp1
 
Mine planning process A Madowe SAIMM paper
Mine planning process A Madowe SAIMM paperMine planning process A Madowe SAIMM paper
Mine planning process A Madowe SAIMM paper
Alfred Madowe
 
Manufacturing of liquid propellant tank
Manufacturing of liquid propellant tankManufacturing of liquid propellant tank
Manufacturing of liquid propellant tank
Sai Malleswar
 

Similar to Ongc drilling services introduction (20)

Jonathan Mulosa ET'Al
Jonathan Mulosa ET'AlJonathan Mulosa ET'Al
Jonathan Mulosa ET'Al
 
Reportongc
ReportongcReportongc
Reportongc
 
Planning and deployment of CSM at moderate depth opencast mines-a blast free ...
Planning and deployment of CSM at moderate depth opencast mines-a blast free ...Planning and deployment of CSM at moderate depth opencast mines-a blast free ...
Planning and deployment of CSM at moderate depth opencast mines-a blast free ...
 
Bsp sail project
Bsp sail projectBsp sail project
Bsp sail project
 
Iocl summer treaining report PANKIT MISHRA (UP) allahabad
Iocl summer treaining report PANKIT MISHRA   (UP) allahabadIocl summer treaining report PANKIT MISHRA   (UP) allahabad
Iocl summer treaining report PANKIT MISHRA (UP) allahabad
 
Oil & gas course
Oil & gas courseOil & gas course
Oil & gas course
 
Erdmp.essaroilltd.mr.jayaraman
Erdmp.essaroilltd.mr.jayaramanErdmp.essaroilltd.mr.jayaraman
Erdmp.essaroilltd.mr.jayaraman
 
Design and fabrication of oil skimmer PPT .pptx
Design and fabrication of oil skimmer  PPT .pptxDesign and fabrication of oil skimmer  PPT .pptx
Design and fabrication of oil skimmer PPT .pptx
 
Mine planning process A Madowe SAIMM paper
Mine planning process A Madowe SAIMM paperMine planning process A Madowe SAIMM paper
Mine planning process A Madowe SAIMM paper
 
Manufacturing of liquid propellant tank
Manufacturing of liquid propellant tankManufacturing of liquid propellant tank
Manufacturing of liquid propellant tank
 
Extending Open Cast Mine to Underground Mine Planning
Extending Open Cast Mine to Underground Mine PlanningExtending Open Cast Mine to Underground Mine Planning
Extending Open Cast Mine to Underground Mine Planning
 
Nitin
NitinNitin
Nitin
 
Amit pandit presentaion gautambuddha university
Amit pandit presentaion gautambuddha universityAmit pandit presentaion gautambuddha university
Amit pandit presentaion gautambuddha university
 
Drilling efficiency optimization at hassai site
Drilling efficiency optimization at hassai siteDrilling efficiency optimization at hassai site
Drilling efficiency optimization at hassai site
 
Ready mix concrete project ppt
Ready mix concrete project pptReady mix concrete project ppt
Ready mix concrete project ppt
 
CESC-TGS REPORT
CESC-TGS REPORTCESC-TGS REPORT
CESC-TGS REPORT
 
MULTI CAVITY DIE PREPARATION, ANALYSIS AND MANUFACTURING PROCESS OF DIESEL EN...
MULTI CAVITY DIE PREPARATION, ANALYSIS AND MANUFACTURING PROCESS OF DIESEL EN...MULTI CAVITY DIE PREPARATION, ANALYSIS AND MANUFACTURING PROCESS OF DIESEL EN...
MULTI CAVITY DIE PREPARATION, ANALYSIS AND MANUFACTURING PROCESS OF DIESEL EN...
 
Petroleum Cycle.pdf
Petroleum Cycle.pdfPetroleum Cycle.pdf
Petroleum Cycle.pdf
 
Internship report
Internship reportInternship report
Internship report
 
IRJET- A Case Study and Design Approach for Sewage Treatment Plant in Kakuman...
IRJET- A Case Study and Design Approach for Sewage Treatment Plant in Kakuman...IRJET- A Case Study and Design Approach for Sewage Treatment Plant in Kakuman...
IRJET- A Case Study and Design Approach for Sewage Treatment Plant in Kakuman...
 

Recently uploaded

Paint shop management system project report.pdf
Paint shop management system project report.pdfPaint shop management system project report.pdf
Paint shop management system project report.pdf
Kamal Acharya
 
Laundry management system project report.pdf
Laundry management system project report.pdfLaundry management system project report.pdf
Laundry management system project report.pdf
Kamal Acharya
 
Activity Planning: Objectives, Project Schedule, Network Planning Model. Time...
Activity Planning: Objectives, Project Schedule, Network Planning Model. Time...Activity Planning: Objectives, Project Schedule, Network Planning Model. Time...
Activity Planning: Objectives, Project Schedule, Network Planning Model. Time...
Lovely Professional University
 
Teachers record management system project report..pdf
Teachers record management system project report..pdfTeachers record management system project report..pdf
Teachers record management system project report..pdf
Kamal Acharya
 

Recently uploaded (20)

2024 DevOps Pro Europe - Growing at the edge
2024 DevOps Pro Europe - Growing at the edge2024 DevOps Pro Europe - Growing at the edge
2024 DevOps Pro Europe - Growing at the edge
 
Software Engineering - Modelling Concepts + Class Modelling + Building the An...
Software Engineering - Modelling Concepts + Class Modelling + Building the An...Software Engineering - Modelling Concepts + Class Modelling + Building the An...
Software Engineering - Modelling Concepts + Class Modelling + Building the An...
 
Electrical shop management system project report.pdf
Electrical shop management system project report.pdfElectrical shop management system project report.pdf
Electrical shop management system project report.pdf
 
Lect 2 - Design of slender column-2.pptx
Lect 2 - Design of slender column-2.pptxLect 2 - Design of slender column-2.pptx
Lect 2 - Design of slender column-2.pptx
 
Paint shop management system project report.pdf
Paint shop management system project report.pdfPaint shop management system project report.pdf
Paint shop management system project report.pdf
 
Natalia Rutkowska - BIM School Course in Kraków
Natalia Rutkowska - BIM School Course in KrakówNatalia Rutkowska - BIM School Course in Kraków
Natalia Rutkowska - BIM School Course in Kraków
 
Dairy management system project report..pdf
Dairy management system project report..pdfDairy management system project report..pdf
Dairy management system project report..pdf
 
KIT-601 Lecture Notes-UNIT-5.pdf Frame Works and Visualization
KIT-601 Lecture Notes-UNIT-5.pdf Frame Works and VisualizationKIT-601 Lecture Notes-UNIT-5.pdf Frame Works and Visualization
KIT-601 Lecture Notes-UNIT-5.pdf Frame Works and Visualization
 
Furniture showroom management system project.pdf
Furniture showroom management system project.pdfFurniture showroom management system project.pdf
Furniture showroom management system project.pdf
 
Research Methodolgy & Intellectual Property Rights Series 2
Research Methodolgy & Intellectual Property Rights Series 2Research Methodolgy & Intellectual Property Rights Series 2
Research Methodolgy & Intellectual Property Rights Series 2
 
RM&IPR M5 notes.pdfResearch Methodolgy & Intellectual Property Rights Series 5
RM&IPR M5 notes.pdfResearch Methodolgy & Intellectual Property Rights Series 5RM&IPR M5 notes.pdfResearch Methodolgy & Intellectual Property Rights Series 5
RM&IPR M5 notes.pdfResearch Methodolgy & Intellectual Property Rights Series 5
 
internship exam ppt.pptx on embedded system and IOT
internship exam ppt.pptx on embedded system and IOTinternship exam ppt.pptx on embedded system and IOT
internship exam ppt.pptx on embedded system and IOT
 
Attraction and Repulsion type Moving Iron Instruments.pptx
Attraction and Repulsion type Moving Iron Instruments.pptxAttraction and Repulsion type Moving Iron Instruments.pptx
Attraction and Repulsion type Moving Iron Instruments.pptx
 
Pharmacy management system project report..pdf
Pharmacy management system project report..pdfPharmacy management system project report..pdf
Pharmacy management system project report..pdf
 
Laundry management system project report.pdf
Laundry management system project report.pdfLaundry management system project report.pdf
Laundry management system project report.pdf
 
Activity Planning: Objectives, Project Schedule, Network Planning Model. Time...
Activity Planning: Objectives, Project Schedule, Network Planning Model. Time...Activity Planning: Objectives, Project Schedule, Network Planning Model. Time...
Activity Planning: Objectives, Project Schedule, Network Planning Model. Time...
 
RM&IPR M4.pdfResearch Methodolgy & Intellectual Property Rights Series 4
RM&IPR M4.pdfResearch Methodolgy & Intellectual Property Rights Series 4RM&IPR M4.pdfResearch Methodolgy & Intellectual Property Rights Series 4
RM&IPR M4.pdfResearch Methodolgy & Intellectual Property Rights Series 4
 
Teachers record management system project report..pdf
Teachers record management system project report..pdfTeachers record management system project report..pdf
Teachers record management system project report..pdf
 
Construction method of steel structure space frame .pptx
Construction method of steel structure space frame .pptxConstruction method of steel structure space frame .pptx
Construction method of steel structure space frame .pptx
 
Online resume builder management system project report.pdf
Online resume builder management system project report.pdfOnline resume builder management system project report.pdf
Online resume builder management system project report.pdf
 

Ongc drilling services introduction

  • 1. SUMMER INDUSTRIAL TRAINING DEEPAK CHANDAK-13EJIME032 JODHPUR INSTITUTE OF ENGINEERING AND TECHNOLOGY(CO ED,MECHANICAL) AT ONGC ANKLESHWAR SUBMITTED TO- HOD- M R BAID (MECHANICAL)
  • 2. OILAND NATURAL GAS CORPORATION INDUSTRY- OILAND GAS HEADQUARTER- TEL BHAVAN, DEHRADUN, UTTRAKHAND CHAIRMAN & MD- DINESH KUMAR SARAF OWNER- GOVERNMENT OF INDIA PRODUCTS- PETROLEUM, NATURAL GAS, AND OTHER PETROCHEICALS.
  • 3. ABOUT ONGC “to give world leadership in management of energy source, exploration of energy sources, diversification of energy sources, technology in Underground Coal Gasification, and above all, finding new ways of tapping energy wherever it is, to meet the ever-growing demand of the country” VISION STATEMENT ONGC 33,560 EMPLOYEES 11 ASSETS(OIL & GAS) 7 BASINS(EXPLORATORY) 2 PLANTS(OIL REFINING) SERVICES (DRILLING, WELL SERVICES, LOGGING, ) 7.1 BILLION TONNES OF HYDROCARBONS (TILL NOW) 11,000 KMS OF PIPE - LINES OVER COUNTRY PRODUCTS- CRUDE OIL, GAS, LPG, NAPTHA, C2-C3 AND OTHER HYDRO- CARBON’S PRODUCTS
  • 4. ABOUT ONGC ANKLESHWAR ASSET • STARTED IN 1960, PRODUCTION STARTED IN 1961. • SITUATED AT ANKLESHWAR, BHARUCH, GUJRAT. ANKLESHWAR ASSET, ONGC HAS 4 FIELDS OF OIL -ANKLESHWAR(1960, well depth~1100m) -GANDHAR(1984, well depth~3200m) -JAMBHUSAR(1999, well depth~3800m) -DAHEJ(2005, well depth~3500m) HAS 11 GGS (GGS 1-7, GGS DAHEJ, GGS JOLWA, GGS DABKA, GGS GANDHAR), 1 CTF 1 CPF, 1 MPH HAS 7 NO. OF OIL RIGS:- 2 MOBILE RIGS(CWX, M-450) 4 ELECTRICAL( E-1400-3, E- 1400-7, E-760, E-2000) 1 VFD(EV-2000-2) HAS MORE THAN 6000 WELLS DRILLED TILL DATE & MORE THAN 300 ACTIVE WELLS HAS VARIOUS DEPARTEMENTS LIKE DRILLING, FISHING, LOGGING, CASING, MATERIAL, INTRUMENTATION, SURFACE etc.. OUTSOURCING FOR VARIOUS SERVICES LIKE DIECTIONAL DRILLING, FISHING, DRILLING, WORK- SHOP SERVICES FOR MACHINES etc..
  • 5. FORMATION OF OIL PROCESS OF FORMATION OF OIL IN EARTH 1. E.g. PLANTS AND ANIMALS. 2. BURIED UNDER LAYER OF SOIL. 3. DUE TO FORMATION OF MORE SOIL LAYERS. 4. DUE TO HEAVY ROCKS HIGH TEMPRETURE & PRESSURE. 5.HIGH TEMPRETURE & PRESSURE UNDER ROCKS FOR LONG TIME. 6.THE CONVERSION PRO- CESS OVER YEARS. LIVING ORGANISM DEAD BODIES BIOPOLYMER GEOPOLYMER (KEROGEN) PETROLEUM FOSSIL FUELS BITUMEN
  • 6. PROCESS OF OIL PRODUCTION DATA FROM SATELLITE SEISMIC SURVEYS RIG MOVING,BUILDING & LEVELLING THE CHRISTMAS TREE DRILLING PROCESS
  • 7. DRILLING RIG A Rig is a complete Mechanical machine that consist of the structure and the machines that were used for drilling of oil well.
  • 8. DRILLING PROCESS Readying of drilling location (surface leveling, water sources, pipeline setup etc). Rig moving / Rig building If a free rig is there in nearby area then rig moving & rig building else only rig building. The drilling process starts that includes mud circulation, casing, cementation, inert of drill pipes, fishing etc. Various simultaneous processes takes place such as mud cleaning, data handling of well like temp. pressure etc, maintenance of various machines etc. When it is get to know that oil starts coming, the rig is removed and ‘The Christmas Tree’ is placed there in place for oil production. A continuous care is taken of well data like pressure, temp., gas from mud after drilling, the required depth of drilling etc.
  • 9. THE DRILLING PROCESS (INSIDE VIEW)
  • 10. Major Drilling Equipment Divided Into Following Categories: –Hoisting Equipment (used for raising and and lowering of drill pipes) –Rotary Equipment (used to give rotary power to drill bit for cutting action) –Circulating Equipment (for circulation of mud)
  • 11. Hoisting Equipment 1. Draw works One of the major drilling equipment on the rig Raises or lowers drill string, casing and other equipment in well
  • 13. Rotating equipments SWIVEL TOP DRIVE SYSTEM SWIVEL IS CONNECTED BETWEEN DRILL PIPE AND HOOK TOP DRIVE SYSTEM IS USED TO DRIVE THE WHOLE ROTARY SYSTEM
  • 15. TYPES OF DRILL BITS MILLED TOOTH BIT USED FOR CUTTING OF UPPER LAYER OF SAND (GENERALLY UPTO 400-700 m.) INSERT BIT USED FOR CUTTING OF ROCKS AND SAND (DEPTH UPTO 1200m.) POLYCRYSTALLINE DIAMOND COMPACT DRILL BIT USED FOR CUTTING OF HARD FORMATION OR ROCKS (DEPTH 1000m. AND ABOVE).
  • 16. CASING & CEMENTATION PROCESS  Casing is large diameter pipe that is assembled and inserted into a recently drilled section of a bore hole and typically held into place with cement. The following casing intervals are typically used in an oil or gas well: • Conductor casing • Surface casing • Intermediate casing (optional) • Production casing  The basic principle of cementing operations is the displacement of cement slurry down the casing, tubing or drill pipe to a pre-specified point in the well.  The main functions of primary cementation are:- • To bond and support the casing. • Protecting the casing from corrosion. • To restrict fluid movements between formations. • Protecting the casing from shock loads during drilling of next zone. • Sealing off problematic zone
  • 18. COST ANALYSIS OF DRILLING RIG E-1400-7 Drilling Cost Operating Cost Man Power Diesel Cost Well Cost Mud cost Casing cost Drill bit cost Out sourcing cost Cementing cost Maintenance Cost
  • 19. OPERATING COST Net operating cost included two types of cost: • Man power cost (assuming man power cost as a fixed cost) • Variable cost  It includes:  Diesel cost  Mud cost  Casing Cost  Drill Bit Cost  Out Sourcing Cost  Cementing Cost  Maintenance cost
  • 20. DIESEL COST  Total available engines at the drilling site:4 nos • Based on the operational requirement engines are started. Sometimes operation are carried out with 3 or 4 engines or sometimes by one or two engines • Diesel consumption is approx. 7000 liters per day (it includes diesel consumption of all the engines) • Net diesel consumption is 7000*30*3 (per well) = 630000 liters • Diesel cost is Rs.58.84 per liter. • Total diesel cost is 630000*58.84 = Rs.3,70,69,200
  • 21. 2.WELL COST 1. MUD COST • Mud is the mixture of water, bantonite clay, thinner and lubricating oil. • Its cost is around Rs.70 per liter. • And 150000 liters of mud is used for drilling of a well of around 3000 meters depth. • So total mud cost is 150000*70 = Rs.1, 05, 00,000. 2. CASING COST • Cost of conductor casing is Rs. 3667.05 per meter. So total cost of conductor casing is = 3667.05*200 = Rs. 7,33,410 • Cost of intermediate casing is Rs. 2015.31 per meter. So total cost of intermediate casing is = 2015.31*1600 = Rs. 32,24,494 • Cost of production casing is Rs. 1311.51 per meter. So total cost of production casing is = 1311.51*3233 = Rs. 42,40,139 • Total casing cost = 81, 98, 043 or approx. 82 lakhs. 3. DRILL BIT COST  Generally two types of drilling bits are used 1. Fixed cutter and tri conical roller 2. PDC (Poly Crystalline Diamond Compact) bit
  • 22. Cost of fixed cutter and tri conical roller is 15 lakhs per bit. Cost of PDC is around 50 lakhs per bit. One well consumes around one TCR and one PDC bit. Total drill bit cost = Rs. 65 lakhs. 4. OUT SOURCING COST Out sourcing means giving specific job to any private industry. For example: - Jindal, Schlumberger and CAIRN etc. For directional drilling ONGC out sources the job to different companies. Cost of out sourcing is around 2 crore. 5. CEMENTING COST TOTAL CEMENTING COST= Rs. 1954533 = 20 lacs.
  • 23. 3. Maintenance cost • The maintenance budget of ONGC per year for 6 drilling rigs is around 50 crore. • Each rig drills average 5 wells per year. • So maintenance cost per well is around 1.67 crore. TOTAL DRILLING COST • Operating Cost = 3.70 crore • Well Cost = 4.72 crore • Maintenance Cost = 1.67 crore • Total cost = 10.09 = 10 crore
  • 24. SITE VISITS  The rigs that we have visited: • CARDWELL-10 • M-450 • E-760-5 • E-2000-2 • E-1400-7  GGS (Group Gathering Station)  CTF (Central Tank Farm)  MPH (Main Pump House) PRODUCTION • From 1 GGS around 1000 m^3/day liquid (oil +water) is sent to CTF. • And oil production in CTF from 1 GGS is around 150m^3/day • LPG production per day is around 10 to 15 tones. • Naptha production per day is around 20 tones.
  • 25. After summer training at ONGC ankleshwar, I have known about the process of oil well drilling from starting to finish, at the Ankleshwar field and Gandhar field. We also visited GGS, CTF and MPH. we also conducted one project work, “COST ANALYSIS OF DRILLING RIG E1400-7”. CONCLUSION