SlideShare a Scribd company logo
THE COPPERBELT UNIVERSITY
School of Mines and Mineral Sciences
Chemical Engineering Department
NAMES: BEELE WAMULUME 09198533
KALUMPILA MWANDILA 09196242
MULOSA JONATHAN 09194996
PROG: Beng Chemical 5
SUPERVISOR: MR C. BOTHA
© 2014
TITLE
HYDROMETALLURGICAL
COPPER PROCESSING
PLANT DESIGN
INTRODUCTION
 This project is about the design of a
Hydrometallurgical Copper Processing Plant
mainly for small scale miners.
 The project looks at a paradigm shift from the
conventional large scale processing of copper to
small scale processing of copper affordable to local
investors.
HYPOTHESIS
The plant to be designed will be able to
process 15 metric tonnes of copper ore per
day with 80% recovery. It will be economical,
cost effective and affordable for average local
investors.
AIM
The project was aimed at designing a
Hydrometallurgical Copper Processing
Plant on a small scale that would process
about 15 tons of copper oxide ore per day
and recover over 80% of copper.
SPECIFIC OBJECTIVES
1. To establish the most economical
hydrometallurgical technique for the treatment of
copper ore.
2. To carry out theoretical material balances of the
plant and to establish the feed rate required.
3. To carry out an energy balance of the
hydrometallurgical plant and establish the power
required to operate the plant.
4. To determine the types and sizes of the equipment
required.
5. To determine the capital cost of the plant.
Methodology
Part of the design work was based on the
laboratory experiments and the other part was
theoretical.
 The work was divided in the following phases:
 Data Collection
 Laboratory Experiments
 Process Design
 Mechanical Design
 Project Costing
Laboratory experiments
• Comminution –obtain optimum particle
size (75-100 microns)
• Leaching (determine leaching residence
time )
• Cu assays (determine extraction
efficiency)
• Batch settling tests (determine settling
rates for slurry)
Process design
The work in this stage involved;
• Determination of the appropriate feed rate
for a small scale plant.
• The theoretical material and energy
balances of the overall plant and the
individual units.
• Recovery, plant attainment and overall
efficiency
Mechanical design
The work involved in this stage included;
• Selection of appropriate equipment.
• Sizing of the equipment
• Selecting the appropriate materials of
construction to be used.
Mechanical design equations
• Reactor Volume…..
• Wall thickness of vessels
• Area of clarifier
• Power required for agitation
Project costing
• Cost of different equipment was obtained
from reliable internet vendors.
• The material costs for the equipment
fabricated on sight was also obtained
from the internet. 40% was added for
labor costs.
RESULTS
Summary of material and energy
balances
INPUT OUTPUT EFFICIENCY
Cu ore 1.5t/h (6wt%) 1.34t/h
(99.9wt%)
90%
Fresh water 35m3/hr 0 100%(assuming
no
spillages/leaks)
Sulphuric acid 1.6m3/hr 0.029m3/hr 98.2%
Organic solvent
(17.9% LIX
984N; 82.1%
diluent)
17m3 0 100% (recycle of
the organic)
Power
(13cents/kWh)
112kW - -
RESULTS
 Comminution Circuit
Model PE-150
Inlet Size (mm) 150×250
Maximum feeding size (mm) 125
Adjusting range of size (mm) 15-45
Capacity (t/h) 1.2-3.5
Motor (KW) 5.5
Weight (t) 0.8
Overall dimensions (L×W×H) (mm)
950x1100x1100
FOB Price (USD) 1650.00
Table 4.1 jaw crusher specifications
Cont…
Model 2YK 1237
Screen Spec (mm) 1200 × 3700
Maximum feeding size (mm) 200
Screen mesh size (mm) 4-50
Capacity (t/h) 15-86
Motor (KW) 15
Layers 2
Vibrating frequency (r/min) 960
FOB price (usd) 5000
Table 4.2 vibrating screen specifications
Cont…
Table 4.3 ball mill specifications
Cont.…
Model FX125
Diameter (mm) 125
Maximum feeding size
(mm)
0.6
Feeding Pressure
(MPa)
0.06-0.35
Capacity (m3) 8-15
Classification Size
(μm)
20-100
Weight (kg) 10
Overall dimensions
(L×W×H) (mm)
210x185x620
FOB price (usd) 100.00
Table 4.4 hydro cyclone specifications
Table 4.5 thickener design results
Parameter Dimensions
Diameter of thickener 10.0m
Height of cylindrical section 2.0m
Surface area of cylindrical section (m2) 62.8  63
Outlet diameter 1.0m
Volume of the cone 65.4m3
Surface area of the cone 25.868m2
Volume of the cylindrical section 157.1m3
Total surface are of thickener (m2)  90
Power requirement (kW) 0.12
Material of construction of shell Carbon steel
Thickness of shell 10mm
Material of construction of lining Vulcanized Latex
rubber
Thickness of lining (mm) 20
Total volume of shell (m3) 0.9 1
Total dead weight of thickener (t) 7.9 (steel shell) +
1.92 = 9.82  10
Total cost of rubber (mass of rubber (kg) × $2.50 (usd) 5000
Total cost of steel (hot rolled plate)(mass of steel (t) × $700
(usd)
5600
Total cost of thickener shell manufacture (usd) 15000
Cont.…
Mass of ore (Kg) 1500
Residence time (h) 3
Diameter of leach tank (m) 2
Height of leach tank (m) 2
Power (KW) 0.2
Torque (KW/rps) 0.03
Residue acid mass (pH=2) Kg 40.58
Tank thickness (mm) 9
Plate thickness (mm) 40
Impeller diameter (mm) 700
Table 4.6 Leaching Circuit
Cont.…
Over flow rate (m3/h) 1.5
Under flow rate (m3/h) 2.7
Copper Concentration In Overflow (g/l) 18.1
Average area (m2) 2.2
Diameter (m) 1.7
Cone angle (°) 30
Torque (Nm) 1530.2
Gearbox output speed (rpm) 0.378
Power (KW) 0.12
Clarifier thickness (mm) 10
Rubber lining thickness (mm) 5
Settling pond volume (m3) 302
Table 4.7 Solution Purification
Cont.…
Concentration of copper in PLS(g/l) 18.1
Extractant LIX 984N/LIX 973N
Mixing time (min) 15
Diameter of a mixer (m) 1
Height of a mixer (m) 2
Impeller diameter (mm) 330
Separation time (min) 30
Height of settler (m) 1
Length of settler (m) 6
Breadth of settler (m) 3
Mixer Construction material Carbon steel with PVC paint coating
Settler Construction material Concrete with PVC lining
Table 4.8 Solvent Extraction
Cont.…
Dimensions (L × W × H)m 4.2 × 1.25 × 1.5
Cost per cell K30 000
Total cost (15 cells) K154 000
Cost per stainless steel plate K16 800
Total cost (300 stainless steel plate) K5 040 000
Cost per anode plate K56
Total cost (315 anode plates) K K17 640
Cost of rectifier
Total cost (K) K5 300 000
OPERATION
Cathode production (tonnes /yr.) 518
Electrolytic cell
Total number 80
Construction material Polymer concrete
Length × width × depth(inside), m 4.8 × 1.25 × 1.5
Anodes, cathodes per cell 20/21
Spaces between anodes and cathodes, mm 95
Anode
Material % 98.4%Pb, 1.5%Sn, 0.08%Ca, 0.02%Al
Table 4.9 Electrowinning
Length × width × thickness, m 1.1 × 0.9 × 0.006
Center – to - center spacing in cell, mm 95
Life, yr. 5
Cathode
Type Stainless steel
Length × width × thickness, m 1.2 × 1.0 × 0.003
Side edge strip material PVC
Bottom strip material PVC/RUBBER
Plating time, days 10
Mass Cu plated on blank, Kg 60
Stripping method Hand stripping
Power and energy
Cathode current density, A/m2
280
Cathode current efficiency, % 98
Cell voltage, V 1.98-2
Cell current, kilo amperes 30
Power kW 60
Electrolyte
Cont.…
Cont.…
Cu, Kg/m3 45-55
H2SO4, Kg/m3 180-190
Temperature, °C 60-65
Out of cells
Cu, Kg/m3 40
H2SO4, Kg/m3 200
Temperature, °C 65
Addition rates, g/per tonne of cathode
Guar gum, ppm 250
Cobalt sulfate, ppm< 150
Chloride ions, ppm < 30
Electrolyte treatments before entering
tank house
Gamet / anthracite filtration, heat exchanger
Site location
• The overriding factor when selecting the
site for this plant was the proximity to the
main raw material- copper oxide ores.
• Other factors considered included source
of electricity, water and proximity to acid
source
• Areas suitable for this plant include
Kasempa, Mufumbwe and Mumbwa
DISCUSSION
Comminution Circuit
 Wet grinding was employed in this plant to reduce
energy usage, facilitate removal of material and to
suppress dust.
 Three hydrocyclones were used to increase efficiency of
the plant and also to allow room for expansion of the
plant.
 The thickener serves two purposes; allows the slurry to
be of required density for optimum extraction during
leaching and serves as a recycle line for the water to
minimize fresh water usage.
Cont…
Leaching Circuit
 pH was maintained between 1.8-2 to ensure proper extraction
of copper in the leach tank.
 Four tanks in parallel were used to achieve a continuous
process.
Cont…
Solid-Liquid Separation Circuit
 The separation of solids from the metal laden liquid was the
most difficult separation process to achieve. In the lab, the
separation was effectively using a leaf filter and the washing
done using hot water.
 However, on a commercial scale, the raffinate will be used to
wash the gangue solids
 The thickener will employed to facilitate the continuous
separation of solids from the metal laden liquid.
Cont…
Solvent Extraction Circuit
 The circuit is made up of 2 extraction stages and 1-
stripping stages.
 The PVC material will be used for lining the settler which
will be made of concrete.
Electrowinning
 The number of cathodes was determined for a 10 days
standard for electroplating 60 kg of copper on each
cathode to be 22 per cell.
 Polymer concrete cells were used.
Cont…
Summary
 The total cost of the plant was determined to be $1.1
million (K5.8million). Adding 40% for installation, civil
works and electrical works the total comes to about $1.5
million dollars (K8.5 million).
CONCLUSIONS
 A material balances and energy balances of the plant was
conducted and the plant was determined to have an
efficiency of at least 90%. The feed rate for the copper ore
was determined to be 1.5 tonnes per hour. The power
requirements of the plant was about 120kW (costing the
plant K2000/day on energy). The total copper output of the
plant is about 1,900kg copper per day giving an annual
output of 583 tonnes.
 The capital cost of the plant was determined to be
$1.5million dollars (K8.5 million).
 Small scale hydrometallurgical processing is a very viable
project for a developing country like Zambia. It will enable
empowerment of Zambians in an industry dominated by
foreign multinational companies.
RECOMMENDATIONS
 Small scale hydrometallurgical processing is a very
viable project. And This can easily be achieved if a team
of different specialists come together to start the plant.
 The use of plant design software will help optimize the
plant more accurately.
 The structural and mechanical design of the plant should
be carried out by more specialized structural and
mechanical engineers.
 Other areas which require specialists include
instrumentation, civil works, electrical works and detailed
costing.
REFERENCES
1. Brownell, L.E., and Young, E.H. (1959) Process Equipment Design,
New York, John Wiley and Sons, Inc.
2. Chiranjib, K.G. (2003) Chemical Metallurgy, (1sted), Mumbai, India:
John Wiley publishers.
3. Davenport W.G. (2002) extractive metallurgy of copper, (4thed),
university of Missouri, USA.
4. Greenwood, N.N. and Earnshaw, A. (1984) Chemistry of the
Elements, (2nded), U.K., Reed Education and Profession Publishing
Ltd.
5. Kolthoff, Sandell, and Meehan. (1969) Quantitative Chemical Analysis,
(4th edition), U.S.A, The MacMillan Company.
6. Mark, E. eta’l (2004) Extractive Metallurgy of copper, (5thed),
Amsterdam, Netherlands: Elsevier.
7. Martin, R. (2008) Introduction to particle technology, (2nd edition),
Monash university, Australia: John Wiley & sons.
Cont…
8. Max, S.P., and Klaus D.T. (1991)Plant Design and Economics for
Chemical Engineers, (4thed),New York St. Louis, McGraw-Hill, Inc.
9. McCabe, W.L., Smith, J.C., and Harriott, P., (1987) Unit Operations of
Chemical Engineering, (4thed), Singapore, McGraw-Hill Book Company.
10.Pierce, Haenisch, and Sawyer. (1958) Quantitative Analysis, (4thed),
U.S.A., John Wiley and Sons, Inc.
11.Sinnot, R.K. (2005) Chemical Engineering Design, (volume 6), London,
Elsevier Butterworth Heinemann
12.Speight, J.G. (2002) Chemical and Process Design Handbook, New
York, McGraw - Hill.
13.Steve, M. (2004) The IDC Engineers pocket Guide, (5th edition), West
Perth, Australia: IDC Technologies
14.Strouts, C.R., Wilson, H.N., and Parry, R.T. (1967) Chemical Analysis,
(Vol. 2), U.K., Oxford University Press.
15.Swift, E.N. (1972) Quantitative Measurements and Chemical Equilibria,
USA, W.H. Freeman and Company.
THE END
Thank you…!

More Related Content

What's hot

Cementformulae handbook v2
Cementformulae handbook v2Cementformulae handbook v2
Cementformulae handbook v2
cesar hernandez
 
Modular coal washing plant application
Modular coal washing plant applicationModular coal washing plant application
Modular coal washing plant application
Jing Zhang
 
Movable modular coal preparation plant
Movable modular coal preparation plantMovable modular coal preparation plant
Movable modular coal preparation plant
Jing Zhang
 
Oil palm shell concrete
Oil palm shell concreteOil palm shell concrete
Oil palm shell concrete
SwamyNadh3
 
Mihelič - Performanse novog iverača u čišćenju rečnog korita
Mihelič - Performanse novog iverača u čišćenju rečnog koritaMihelič - Performanse novog iverača u čišćenju rečnog korita
Mihelič - Performanse novog iverača u čišćenju rečnog korita
Dusan Stojnic
 
Effectiveness of Some Techniques for Fly Ash Beneficiation
Effectiveness of Some Techniques for Fly Ash BeneficiationEffectiveness of Some Techniques for Fly Ash Beneficiation
Effectiveness of Some Techniques for Fly Ash Beneficiation
IRJET Journal
 
Analysis of Various Cement grinding Systems with Respect to Power Consumption...
Analysis of Various Cement grinding Systems with Respect to Power Consumption...Analysis of Various Cement grinding Systems with Respect to Power Consumption...
Analysis of Various Cement grinding Systems with Respect to Power Consumption...
Karan Walia
 
D012332832
D012332832D012332832
D012332832
IOSR Journals
 
IRJET-Testing of Fluidized Bed Combustor for Foundry Sand Reclamation
IRJET-Testing of Fluidized Bed Combustor for Foundry Sand ReclamationIRJET-Testing of Fluidized Bed Combustor for Foundry Sand Reclamation
IRJET-Testing of Fluidized Bed Combustor for Foundry Sand Reclamation
IRJET Journal
 
Rapid control of exhaust emissions and enhancement of retention time in the c...
Rapid control of exhaust emissions and enhancement of retention time in the c...Rapid control of exhaust emissions and enhancement of retention time in the c...
Rapid control of exhaust emissions and enhancement of retention time in the c...prjpublications
 
IRJET- Partial Replacement of Cement Clinker with Limestone and Low Quality C...
IRJET- Partial Replacement of Cement Clinker with Limestone and Low Quality C...IRJET- Partial Replacement of Cement Clinker with Limestone and Low Quality C...
IRJET- Partial Replacement of Cement Clinker with Limestone and Low Quality C...
IRJET Journal
 
Hardgrove grindability index (HGI)
Hardgrove grindability index (HGI)Hardgrove grindability index (HGI)
Hardgrove grindability index (HGI)KOMAL AROOSH
 
Sanjay_Kumar_BRS_Leuven
Sanjay_Kumar_BRS_LeuvenSanjay_Kumar_BRS_Leuven
Sanjay_Kumar_BRS_LeuvenSanjay Kumar
 
SERI presentation1-5-10
SERI presentation1-5-10SERI presentation1-5-10
SERI presentation1-5-10Julie Rouse
 
P130302102107
P130302102107P130302102107
P130302102107
IOSR Journals
 
Session 2 module 2 coal properties and effect on cobustion
Session 2 module 2 coal properties and effect on cobustionSession 2 module 2 coal properties and effect on cobustion
Session 2 module 2 coal properties and effect on cobustionABDUL RAZZAQ SHAHID
 
emission factors for continuous fixed chimney bull trench brick kiln (fcbtk) ...
emission factors for continuous fixed chimney bull trench brick kiln (fcbtk) ...emission factors for continuous fixed chimney bull trench brick kiln (fcbtk) ...
emission factors for continuous fixed chimney bull trench brick kiln (fcbtk) ...
INFOGAIN PUBLICATION
 
Bauxite Residue – Red Mud
Bauxite Residue – Red MudBauxite Residue – Red Mud
Bauxite Residue – Red MudAdriaan Gie
 
Columbian Chemicals At Emtec 2007
Columbian Chemicals At Emtec 2007Columbian Chemicals At Emtec 2007
Columbian Chemicals At Emtec 2007
Stewart McKenzie
 

What's hot (20)

Cementformulae handbook v2
Cementformulae handbook v2Cementformulae handbook v2
Cementformulae handbook v2
 
Modular coal washing plant application
Modular coal washing plant applicationModular coal washing plant application
Modular coal washing plant application
 
Movable modular coal preparation plant
Movable modular coal preparation plantMovable modular coal preparation plant
Movable modular coal preparation plant
 
Oil palm shell concrete
Oil palm shell concreteOil palm shell concrete
Oil palm shell concrete
 
Mihelič - Performanse novog iverača u čišćenju rečnog korita
Mihelič - Performanse novog iverača u čišćenju rečnog koritaMihelič - Performanse novog iverača u čišćenju rečnog korita
Mihelič - Performanse novog iverača u čišćenju rečnog korita
 
Effectiveness of Some Techniques for Fly Ash Beneficiation
Effectiveness of Some Techniques for Fly Ash BeneficiationEffectiveness of Some Techniques for Fly Ash Beneficiation
Effectiveness of Some Techniques for Fly Ash Beneficiation
 
Analysis of Various Cement grinding Systems with Respect to Power Consumption...
Analysis of Various Cement grinding Systems with Respect to Power Consumption...Analysis of Various Cement grinding Systems with Respect to Power Consumption...
Analysis of Various Cement grinding Systems with Respect to Power Consumption...
 
D012332832
D012332832D012332832
D012332832
 
IRJET-Testing of Fluidized Bed Combustor for Foundry Sand Reclamation
IRJET-Testing of Fluidized Bed Combustor for Foundry Sand ReclamationIRJET-Testing of Fluidized Bed Combustor for Foundry Sand Reclamation
IRJET-Testing of Fluidized Bed Combustor for Foundry Sand Reclamation
 
Rapid control of exhaust emissions and enhancement of retention time in the c...
Rapid control of exhaust emissions and enhancement of retention time in the c...Rapid control of exhaust emissions and enhancement of retention time in the c...
Rapid control of exhaust emissions and enhancement of retention time in the c...
 
IRJET- Partial Replacement of Cement Clinker with Limestone and Low Quality C...
IRJET- Partial Replacement of Cement Clinker with Limestone and Low Quality C...IRJET- Partial Replacement of Cement Clinker with Limestone and Low Quality C...
IRJET- Partial Replacement of Cement Clinker with Limestone and Low Quality C...
 
Hardgrove grindability index (HGI)
Hardgrove grindability index (HGI)Hardgrove grindability index (HGI)
Hardgrove grindability index (HGI)
 
Sanjay_Kumar_BRS_Leuven
Sanjay_Kumar_BRS_LeuvenSanjay_Kumar_BRS_Leuven
Sanjay_Kumar_BRS_Leuven
 
SERI presentation1-5-10
SERI presentation1-5-10SERI presentation1-5-10
SERI presentation1-5-10
 
P130302102107
P130302102107P130302102107
P130302102107
 
Session 2 module 2 coal properties and effect on cobustion
Session 2 module 2 coal properties and effect on cobustionSession 2 module 2 coal properties and effect on cobustion
Session 2 module 2 coal properties and effect on cobustion
 
emission factors for continuous fixed chimney bull trench brick kiln (fcbtk) ...
emission factors for continuous fixed chimney bull trench brick kiln (fcbtk) ...emission factors for continuous fixed chimney bull trench brick kiln (fcbtk) ...
emission factors for continuous fixed chimney bull trench brick kiln (fcbtk) ...
 
Bauxite Residue – Red Mud
Bauxite Residue – Red MudBauxite Residue – Red Mud
Bauxite Residue – Red Mud
 
JOPO SCI-3
JOPO SCI-3JOPO SCI-3
JOPO SCI-3
 
Columbian Chemicals At Emtec 2007
Columbian Chemicals At Emtec 2007Columbian Chemicals At Emtec 2007
Columbian Chemicals At Emtec 2007
 

Viewers also liked

Advant fully furnished office noida expressway
Advant fully furnished office noida expresswayAdvant fully furnished office noida expressway
Advant fully furnished office noida expressway
saurabh manchanda
 
Sin título 1
Sin título 1Sin título 1
Sin título 1
TeknoEsteban
 
Med Ped
Med PedMed Ped
Med Ped
cnreyno
 
Inspiration and moodboard
Inspiration and moodboardInspiration and moodboard
Inspiration and moodboard
millieiron
 
Time planning
Time planningTime planning
Time planning
millieiron
 
Dr. Moscato
Dr. MoscatoDr. Moscato
Dr. Moscato
mimivilmenay
 
Клуб бухгалтеров НКО: Обзорный семинар 28.01.2015 на ВДНХ
Клуб бухгалтеров НКО: Обзорный семинар 28.01.2015 на ВДНХКлуб бухгалтеров НКО: Обзорный семинар 28.01.2015 на ВДНХ
Клуб бухгалтеров НКО: Обзорный семинар 28.01.2015 на ВДНХ
Pavel Gamolskiy
 
STC Comercial
STC ComercialSTC Comercial
STC Comercial
edgarvieyra
 
What you need to know about fasfa
What you need to know about fasfaWhat you need to know about fasfa
What you need to know about fasfa
youthdiscovery
 
El alcohol
El alcoholEl alcohol
Suresh_ System administrator.doc
Suresh_ System administrator.docSuresh_ System administrator.doc
Suresh_ System administrator.docSuresh Annadurai
 
Cifosis para defender
Cifosis para defenderCifosis para defender
Cifosis para defender
UPTAEB
 
Linkedin personal resume 20150128
Linkedin personal resume 20150128Linkedin personal resume 20150128
Linkedin personal resume 20150128
Edward Chao
 
Dr. Chao profile in Linkedin (May-2016)
Dr. Chao profile in Linkedin (May-2016)Dr. Chao profile in Linkedin (May-2016)
Dr. Chao profile in Linkedin (May-2016)
Edward Chao
 

Viewers also liked (15)

Advant fully furnished office noida expressway
Advant fully furnished office noida expresswayAdvant fully furnished office noida expressway
Advant fully furnished office noida expressway
 
Sin título 1
Sin título 1Sin título 1
Sin título 1
 
Med Ped
Med PedMed Ped
Med Ped
 
Inspiration and moodboard
Inspiration and moodboardInspiration and moodboard
Inspiration and moodboard
 
Time planning
Time planningTime planning
Time planning
 
Dr. Moscato
Dr. MoscatoDr. Moscato
Dr. Moscato
 
Клуб бухгалтеров НКО: Обзорный семинар 28.01.2015 на ВДНХ
Клуб бухгалтеров НКО: Обзорный семинар 28.01.2015 на ВДНХКлуб бухгалтеров НКО: Обзорный семинар 28.01.2015 на ВДНХ
Клуб бухгалтеров НКО: Обзорный семинар 28.01.2015 на ВДНХ
 
STC Comercial
STC ComercialSTC Comercial
STC Comercial
 
What you need to know about fasfa
What you need to know about fasfaWhat you need to know about fasfa
What you need to know about fasfa
 
El alcohol
El alcoholEl alcohol
El alcohol
 
Vitamin
VitaminVitamin
Vitamin
 
Suresh_ System administrator.doc
Suresh_ System administrator.docSuresh_ System administrator.doc
Suresh_ System administrator.doc
 
Cifosis para defender
Cifosis para defenderCifosis para defender
Cifosis para defender
 
Linkedin personal resume 20150128
Linkedin personal resume 20150128Linkedin personal resume 20150128
Linkedin personal resume 20150128
 
Dr. Chao profile in Linkedin (May-2016)
Dr. Chao profile in Linkedin (May-2016)Dr. Chao profile in Linkedin (May-2016)
Dr. Chao profile in Linkedin (May-2016)
 

Similar to Jonathan Mulosa ET'Al

Presentation of thermal_power_plant
Presentation of thermal_power_plantPresentation of thermal_power_plant
Presentation of thermal_power_plantprakash2704
 
D1 (B2) Jan Suchorzewski - Combined carbonation-frost resistance of sustainab...
D1 (B2) Jan Suchorzewski - Combined carbonation-frost resistance of sustainab...D1 (B2) Jan Suchorzewski - Combined carbonation-frost resistance of sustainab...
D1 (B2) Jan Suchorzewski - Combined carbonation-frost resistance of sustainab...
Svenska Betongföreningen
 
2016.12.14 DryFining Coal Gen presentation FINAL
2016.12.14 DryFining Coal Gen presentation FINAL2016.12.14 DryFining Coal Gen presentation FINAL
2016.12.14 DryFining Coal Gen presentation FINALSandra Broekema
 
Plasma Treatment of Air Pollution Control Residues
Plasma Treatment of Air Pollution Control ResiduesPlasma Treatment of Air Pollution Control Residues
Plasma Treatment of Air Pollution Control Residues
Jessica Smith
 
cement industry
cement industrycement industry
cement industry
dijo2014
 
Plasma arc tech ppt
Plasma arc tech pptPlasma arc tech ppt
Plasma arc tech ppt
DarsanaD1
 
IRJET- Assessment of Coal Through Analysis of Various Properties of Coal Samp...
IRJET- Assessment of Coal Through Analysis of Various Properties of Coal Samp...IRJET- Assessment of Coal Through Analysis of Various Properties of Coal Samp...
IRJET- Assessment of Coal Through Analysis of Various Properties of Coal Samp...
IRJET Journal
 
04-Hermes-Apresentacao-Tecnored.pt.en.pdf
04-Hermes-Apresentacao-Tecnored.pt.en.pdf04-Hermes-Apresentacao-Tecnored.pt.en.pdf
04-Hermes-Apresentacao-Tecnored.pt.en.pdf
Maqeri1
 
Extracting Value from Mine Ores & Wastes using DC Arc Plasma Technology
Extracting Value from Mine Ores & Wastes using DC Arc Plasma TechnologyExtracting Value from Mine Ores & Wastes using DC Arc Plasma Technology
Extracting Value from Mine Ores & Wastes using DC Arc Plasma Technology
Jessica Smith
 
Energy crisis of nepal and efficiency measures in industries
Energy crisis of nepal and efficiency measures in industriesEnergy crisis of nepal and efficiency measures in industries
Energy crisis of nepal and efficiency measures in industries
Dr Ramhari Poudyal
 
Red mud presentation tms2014 balomenos et al
Red mud presentation tms2014 balomenos et alRed mud presentation tms2014 balomenos et al
Red mud presentation tms2014 balomenos et al
Victor James
 
PROPOSAL OF 1x30MVA SILICON METAL FURNACE PROJECT
PROPOSAL OF 1x30MVA SILICON METAL FURNACE PROJECTPROPOSAL OF 1x30MVA SILICON METAL FURNACE PROJECT
PROPOSAL OF 1x30MVA SILICON METAL FURNACE PROJECTGuo ke
 
Amrt technology overview september 2014
Amrt technology overview september 2014Amrt technology overview september 2014
Amrt technology overview september 2014
Victor James
 
Generation of electricity from coal parul
Generation of electricity from coal  parulGeneration of electricity from coal  parul
Generation of electricity from coal parulSwapnil Sharma
 
Low carbon footprint metal extraction
Low carbon footprint metal extractionLow carbon footprint metal extraction
Low carbon footprint metal extractionPiyush Verma
 
OPTIMUM DOSAGE OF GGBFS, BROKEN CERAMIC TILES AND COPPER SLAG IN THE PRODUCTI...
OPTIMUM DOSAGE OF GGBFS, BROKEN CERAMIC TILES AND COPPER SLAG IN THE PRODUCTI...OPTIMUM DOSAGE OF GGBFS, BROKEN CERAMIC TILES AND COPPER SLAG IN THE PRODUCTI...
OPTIMUM DOSAGE OF GGBFS, BROKEN CERAMIC TILES AND COPPER SLAG IN THE PRODUCTI...
IRJET Journal
 

Similar to Jonathan Mulosa ET'Al (20)

Presentation of thermal_power_plant
Presentation of thermal_power_plantPresentation of thermal_power_plant
Presentation of thermal_power_plant
 
presentation
presentationpresentation
presentation
 
Presentation final 2.0
Presentation final 2.0Presentation final 2.0
Presentation final 2.0
 
My report vfd
My  report vfdMy  report vfd
My report vfd
 
D1 (B2) Jan Suchorzewski - Combined carbonation-frost resistance of sustainab...
D1 (B2) Jan Suchorzewski - Combined carbonation-frost resistance of sustainab...D1 (B2) Jan Suchorzewski - Combined carbonation-frost resistance of sustainab...
D1 (B2) Jan Suchorzewski - Combined carbonation-frost resistance of sustainab...
 
2016.12.14 DryFining Coal Gen presentation FINAL
2016.12.14 DryFining Coal Gen presentation FINAL2016.12.14 DryFining Coal Gen presentation FINAL
2016.12.14 DryFining Coal Gen presentation FINAL
 
Plasma Treatment of Air Pollution Control Residues
Plasma Treatment of Air Pollution Control ResiduesPlasma Treatment of Air Pollution Control Residues
Plasma Treatment of Air Pollution Control Residues
 
cement industry
cement industrycement industry
cement industry
 
Plasma arc tech ppt
Plasma arc tech pptPlasma arc tech ppt
Plasma arc tech ppt
 
IRJET- Assessment of Coal Through Analysis of Various Properties of Coal Samp...
IRJET- Assessment of Coal Through Analysis of Various Properties of Coal Samp...IRJET- Assessment of Coal Through Analysis of Various Properties of Coal Samp...
IRJET- Assessment of Coal Through Analysis of Various Properties of Coal Samp...
 
04-Hermes-Apresentacao-Tecnored.pt.en.pdf
04-Hermes-Apresentacao-Tecnored.pt.en.pdf04-Hermes-Apresentacao-Tecnored.pt.en.pdf
04-Hermes-Apresentacao-Tecnored.pt.en.pdf
 
Extracting Value from Mine Ores & Wastes using DC Arc Plasma Technology
Extracting Value from Mine Ores & Wastes using DC Arc Plasma TechnologyExtracting Value from Mine Ores & Wastes using DC Arc Plasma Technology
Extracting Value from Mine Ores & Wastes using DC Arc Plasma Technology
 
Energy crisis of nepal and efficiency measures in industries
Energy crisis of nepal and efficiency measures in industriesEnergy crisis of nepal and efficiency measures in industries
Energy crisis of nepal and efficiency measures in industries
 
Red mud presentation tms2014 balomenos et al
Red mud presentation tms2014 balomenos et alRed mud presentation tms2014 balomenos et al
Red mud presentation tms2014 balomenos et al
 
PROPOSAL OF 1x30MVA SILICON METAL FURNACE PROJECT
PROPOSAL OF 1x30MVA SILICON METAL FURNACE PROJECTPROPOSAL OF 1x30MVA SILICON METAL FURNACE PROJECT
PROPOSAL OF 1x30MVA SILICON METAL FURNACE PROJECT
 
Amrt technology overview september 2014
Amrt technology overview september 2014Amrt technology overview september 2014
Amrt technology overview september 2014
 
Generation of electricity from coal parul
Generation of electricity from coal  parulGeneration of electricity from coal  parul
Generation of electricity from coal parul
 
Low carbon footprint metal extraction
Low carbon footprint metal extractionLow carbon footprint metal extraction
Low carbon footprint metal extraction
 
sail bokaro
sail bokarosail bokaro
sail bokaro
 
OPTIMUM DOSAGE OF GGBFS, BROKEN CERAMIC TILES AND COPPER SLAG IN THE PRODUCTI...
OPTIMUM DOSAGE OF GGBFS, BROKEN CERAMIC TILES AND COPPER SLAG IN THE PRODUCTI...OPTIMUM DOSAGE OF GGBFS, BROKEN CERAMIC TILES AND COPPER SLAG IN THE PRODUCTI...
OPTIMUM DOSAGE OF GGBFS, BROKEN CERAMIC TILES AND COPPER SLAG IN THE PRODUCTI...
 

Jonathan Mulosa ET'Al

  • 1. THE COPPERBELT UNIVERSITY School of Mines and Mineral Sciences Chemical Engineering Department NAMES: BEELE WAMULUME 09198533 KALUMPILA MWANDILA 09196242 MULOSA JONATHAN 09194996 PROG: Beng Chemical 5 SUPERVISOR: MR C. BOTHA © 2014
  • 3. INTRODUCTION  This project is about the design of a Hydrometallurgical Copper Processing Plant mainly for small scale miners.  The project looks at a paradigm shift from the conventional large scale processing of copper to small scale processing of copper affordable to local investors.
  • 4. HYPOTHESIS The plant to be designed will be able to process 15 metric tonnes of copper ore per day with 80% recovery. It will be economical, cost effective and affordable for average local investors.
  • 5. AIM The project was aimed at designing a Hydrometallurgical Copper Processing Plant on a small scale that would process about 15 tons of copper oxide ore per day and recover over 80% of copper.
  • 6. SPECIFIC OBJECTIVES 1. To establish the most economical hydrometallurgical technique for the treatment of copper ore. 2. To carry out theoretical material balances of the plant and to establish the feed rate required. 3. To carry out an energy balance of the hydrometallurgical plant and establish the power required to operate the plant. 4. To determine the types and sizes of the equipment required. 5. To determine the capital cost of the plant.
  • 7. Methodology Part of the design work was based on the laboratory experiments and the other part was theoretical.  The work was divided in the following phases:  Data Collection  Laboratory Experiments  Process Design  Mechanical Design  Project Costing
  • 8. Laboratory experiments • Comminution –obtain optimum particle size (75-100 microns) • Leaching (determine leaching residence time ) • Cu assays (determine extraction efficiency) • Batch settling tests (determine settling rates for slurry)
  • 9. Process design The work in this stage involved; • Determination of the appropriate feed rate for a small scale plant. • The theoretical material and energy balances of the overall plant and the individual units. • Recovery, plant attainment and overall efficiency
  • 10. Mechanical design The work involved in this stage included; • Selection of appropriate equipment. • Sizing of the equipment • Selecting the appropriate materials of construction to be used.
  • 11. Mechanical design equations • Reactor Volume….. • Wall thickness of vessels • Area of clarifier • Power required for agitation
  • 12. Project costing • Cost of different equipment was obtained from reliable internet vendors. • The material costs for the equipment fabricated on sight was also obtained from the internet. 40% was added for labor costs.
  • 14. Summary of material and energy balances INPUT OUTPUT EFFICIENCY Cu ore 1.5t/h (6wt%) 1.34t/h (99.9wt%) 90% Fresh water 35m3/hr 0 100%(assuming no spillages/leaks) Sulphuric acid 1.6m3/hr 0.029m3/hr 98.2% Organic solvent (17.9% LIX 984N; 82.1% diluent) 17m3 0 100% (recycle of the organic) Power (13cents/kWh) 112kW - -
  • 15. RESULTS  Comminution Circuit Model PE-150 Inlet Size (mm) 150×250 Maximum feeding size (mm) 125 Adjusting range of size (mm) 15-45 Capacity (t/h) 1.2-3.5 Motor (KW) 5.5 Weight (t) 0.8 Overall dimensions (L×W×H) (mm) 950x1100x1100 FOB Price (USD) 1650.00 Table 4.1 jaw crusher specifications
  • 16. Cont… Model 2YK 1237 Screen Spec (mm) 1200 × 3700 Maximum feeding size (mm) 200 Screen mesh size (mm) 4-50 Capacity (t/h) 15-86 Motor (KW) 15 Layers 2 Vibrating frequency (r/min) 960 FOB price (usd) 5000 Table 4.2 vibrating screen specifications
  • 17. Cont… Table 4.3 ball mill specifications
  • 18. Cont.… Model FX125 Diameter (mm) 125 Maximum feeding size (mm) 0.6 Feeding Pressure (MPa) 0.06-0.35 Capacity (m3) 8-15 Classification Size (μm) 20-100 Weight (kg) 10 Overall dimensions (L×W×H) (mm) 210x185x620 FOB price (usd) 100.00 Table 4.4 hydro cyclone specifications
  • 19. Table 4.5 thickener design results Parameter Dimensions Diameter of thickener 10.0m Height of cylindrical section 2.0m Surface area of cylindrical section (m2) 62.8  63 Outlet diameter 1.0m Volume of the cone 65.4m3 Surface area of the cone 25.868m2 Volume of the cylindrical section 157.1m3 Total surface are of thickener (m2)  90 Power requirement (kW) 0.12 Material of construction of shell Carbon steel Thickness of shell 10mm Material of construction of lining Vulcanized Latex rubber Thickness of lining (mm) 20 Total volume of shell (m3) 0.9 1 Total dead weight of thickener (t) 7.9 (steel shell) + 1.92 = 9.82  10 Total cost of rubber (mass of rubber (kg) × $2.50 (usd) 5000 Total cost of steel (hot rolled plate)(mass of steel (t) × $700 (usd) 5600 Total cost of thickener shell manufacture (usd) 15000
  • 20. Cont.… Mass of ore (Kg) 1500 Residence time (h) 3 Diameter of leach tank (m) 2 Height of leach tank (m) 2 Power (KW) 0.2 Torque (KW/rps) 0.03 Residue acid mass (pH=2) Kg 40.58 Tank thickness (mm) 9 Plate thickness (mm) 40 Impeller diameter (mm) 700 Table 4.6 Leaching Circuit
  • 21. Cont.… Over flow rate (m3/h) 1.5 Under flow rate (m3/h) 2.7 Copper Concentration In Overflow (g/l) 18.1 Average area (m2) 2.2 Diameter (m) 1.7 Cone angle (°) 30 Torque (Nm) 1530.2 Gearbox output speed (rpm) 0.378 Power (KW) 0.12 Clarifier thickness (mm) 10 Rubber lining thickness (mm) 5 Settling pond volume (m3) 302 Table 4.7 Solution Purification
  • 22. Cont.… Concentration of copper in PLS(g/l) 18.1 Extractant LIX 984N/LIX 973N Mixing time (min) 15 Diameter of a mixer (m) 1 Height of a mixer (m) 2 Impeller diameter (mm) 330 Separation time (min) 30 Height of settler (m) 1 Length of settler (m) 6 Breadth of settler (m) 3 Mixer Construction material Carbon steel with PVC paint coating Settler Construction material Concrete with PVC lining Table 4.8 Solvent Extraction
  • 23. Cont.… Dimensions (L × W × H)m 4.2 × 1.25 × 1.5 Cost per cell K30 000 Total cost (15 cells) K154 000 Cost per stainless steel plate K16 800 Total cost (300 stainless steel plate) K5 040 000 Cost per anode plate K56 Total cost (315 anode plates) K K17 640 Cost of rectifier Total cost (K) K5 300 000 OPERATION Cathode production (tonnes /yr.) 518 Electrolytic cell Total number 80 Construction material Polymer concrete Length × width × depth(inside), m 4.8 × 1.25 × 1.5 Anodes, cathodes per cell 20/21 Spaces between anodes and cathodes, mm 95 Anode Material % 98.4%Pb, 1.5%Sn, 0.08%Ca, 0.02%Al Table 4.9 Electrowinning
  • 24. Length × width × thickness, m 1.1 × 0.9 × 0.006 Center – to - center spacing in cell, mm 95 Life, yr. 5 Cathode Type Stainless steel Length × width × thickness, m 1.2 × 1.0 × 0.003 Side edge strip material PVC Bottom strip material PVC/RUBBER Plating time, days 10 Mass Cu plated on blank, Kg 60 Stripping method Hand stripping Power and energy Cathode current density, A/m2 280 Cathode current efficiency, % 98 Cell voltage, V 1.98-2 Cell current, kilo amperes 30 Power kW 60 Electrolyte Cont.…
  • 25. Cont.… Cu, Kg/m3 45-55 H2SO4, Kg/m3 180-190 Temperature, °C 60-65 Out of cells Cu, Kg/m3 40 H2SO4, Kg/m3 200 Temperature, °C 65 Addition rates, g/per tonne of cathode Guar gum, ppm 250 Cobalt sulfate, ppm< 150 Chloride ions, ppm < 30 Electrolyte treatments before entering tank house Gamet / anthracite filtration, heat exchanger
  • 26. Site location • The overriding factor when selecting the site for this plant was the proximity to the main raw material- copper oxide ores. • Other factors considered included source of electricity, water and proximity to acid source • Areas suitable for this plant include Kasempa, Mufumbwe and Mumbwa
  • 27. DISCUSSION Comminution Circuit  Wet grinding was employed in this plant to reduce energy usage, facilitate removal of material and to suppress dust.  Three hydrocyclones were used to increase efficiency of the plant and also to allow room for expansion of the plant.  The thickener serves two purposes; allows the slurry to be of required density for optimum extraction during leaching and serves as a recycle line for the water to minimize fresh water usage.
  • 28. Cont… Leaching Circuit  pH was maintained between 1.8-2 to ensure proper extraction of copper in the leach tank.  Four tanks in parallel were used to achieve a continuous process.
  • 29. Cont… Solid-Liquid Separation Circuit  The separation of solids from the metal laden liquid was the most difficult separation process to achieve. In the lab, the separation was effectively using a leaf filter and the washing done using hot water.  However, on a commercial scale, the raffinate will be used to wash the gangue solids  The thickener will employed to facilitate the continuous separation of solids from the metal laden liquid.
  • 30. Cont… Solvent Extraction Circuit  The circuit is made up of 2 extraction stages and 1- stripping stages.  The PVC material will be used for lining the settler which will be made of concrete. Electrowinning  The number of cathodes was determined for a 10 days standard for electroplating 60 kg of copper on each cathode to be 22 per cell.  Polymer concrete cells were used.
  • 31. Cont… Summary  The total cost of the plant was determined to be $1.1 million (K5.8million). Adding 40% for installation, civil works and electrical works the total comes to about $1.5 million dollars (K8.5 million).
  • 32. CONCLUSIONS  A material balances and energy balances of the plant was conducted and the plant was determined to have an efficiency of at least 90%. The feed rate for the copper ore was determined to be 1.5 tonnes per hour. The power requirements of the plant was about 120kW (costing the plant K2000/day on energy). The total copper output of the plant is about 1,900kg copper per day giving an annual output of 583 tonnes.  The capital cost of the plant was determined to be $1.5million dollars (K8.5 million).  Small scale hydrometallurgical processing is a very viable project for a developing country like Zambia. It will enable empowerment of Zambians in an industry dominated by foreign multinational companies.
  • 33. RECOMMENDATIONS  Small scale hydrometallurgical processing is a very viable project. And This can easily be achieved if a team of different specialists come together to start the plant.  The use of plant design software will help optimize the plant more accurately.  The structural and mechanical design of the plant should be carried out by more specialized structural and mechanical engineers.  Other areas which require specialists include instrumentation, civil works, electrical works and detailed costing.
  • 34. REFERENCES 1. Brownell, L.E., and Young, E.H. (1959) Process Equipment Design, New York, John Wiley and Sons, Inc. 2. Chiranjib, K.G. (2003) Chemical Metallurgy, (1sted), Mumbai, India: John Wiley publishers. 3. Davenport W.G. (2002) extractive metallurgy of copper, (4thed), university of Missouri, USA. 4. Greenwood, N.N. and Earnshaw, A. (1984) Chemistry of the Elements, (2nded), U.K., Reed Education and Profession Publishing Ltd. 5. Kolthoff, Sandell, and Meehan. (1969) Quantitative Chemical Analysis, (4th edition), U.S.A, The MacMillan Company. 6. Mark, E. eta’l (2004) Extractive Metallurgy of copper, (5thed), Amsterdam, Netherlands: Elsevier. 7. Martin, R. (2008) Introduction to particle technology, (2nd edition), Monash university, Australia: John Wiley & sons.
  • 35. Cont… 8. Max, S.P., and Klaus D.T. (1991)Plant Design and Economics for Chemical Engineers, (4thed),New York St. Louis, McGraw-Hill, Inc. 9. McCabe, W.L., Smith, J.C., and Harriott, P., (1987) Unit Operations of Chemical Engineering, (4thed), Singapore, McGraw-Hill Book Company. 10.Pierce, Haenisch, and Sawyer. (1958) Quantitative Analysis, (4thed), U.S.A., John Wiley and Sons, Inc. 11.Sinnot, R.K. (2005) Chemical Engineering Design, (volume 6), London, Elsevier Butterworth Heinemann 12.Speight, J.G. (2002) Chemical and Process Design Handbook, New York, McGraw - Hill. 13.Steve, M. (2004) The IDC Engineers pocket Guide, (5th edition), West Perth, Australia: IDC Technologies 14.Strouts, C.R., Wilson, H.N., and Parry, R.T. (1967) Chemical Analysis, (Vol. 2), U.K., Oxford University Press. 15.Swift, E.N. (1972) Quantitative Measurements and Chemical Equilibria, USA, W.H. Freeman and Company.