SlideShare a Scribd company logo
1 of 29
Soe Naing Win
Email: snw1975@gmail.com
 Update a previously saved baseline plan.
 Record actual work for tasks and assignments.
 Record actual work by time period.
 Interrupt work on a task and specify the date
on which the task should start again
Recall that a baseline is a collection of important
values in a project plan, such as the planned start
dates, finish dates, and costs of tasks,
resources, and assignments. When you save
(or set) a baseline, Project takes a “snapshot” of
the existing values and saves it in the Project plan
for future comparison.
To keep an accurate baseline for later
comparison, you have several options:
• Update the baseline for the entire project. This simply
replaces the original baseline values with the currently
scheduled values.
• Update the baseline for selected tasks. This does not
affect the baseline values for other tasks or resource
baseline values in the project plan.
• Save a second or subsequent baseline. You can save up
to 11 baselines in a single plan. The first one is called
Baseline, and the rest are Baseline 1 through Baseline 10.
Exercise : compare the project plan as it is currently
scheduled with the baseline plan and update the baseline
for the project plan.
• View > Task Views > Gantt Chart > Tracking Gantt
 Task Name > task 18, Original art review > Scroll to
Task
 View > Zoom > Timescale > Weeks
To conclude this exercise, you will resave the baseline for
the project plan. Doing so will update all baseline
information for tasks, resources, and assignments prior to
tracking progress.
• Project > Schedule > Set Baseline > Set Baseline
Make sure that the Set
Baseline option is
selected. In the For
area, make sure that the
Entire project option is
selected
• Click OK to update the baseline.
• Project alerts you that you are about to overwrite the previously saved
baseline values.
• Click Yes.
Project updates the baseline values for the project plan.
Exercise, you record task-level and assignment-level
actuals and see how the information is rolled up or down
between tasks and assignments.
• Change to Task Usage.
• Task Name > task 18, Original art review > Scroll to Task.
• View tab > Data > Tables > Work.
For example,
• The work, total for task 18, 160 hours = the sum of Hany Morcos’
80 hours of work on the task and Jane Dow’s 80 hours.
Next, you’ll change the details shown on the timephased grid on the
right side of the view.
• Format > Details > Actual Work.
Next, you’ll enter task-level and assignment-level actual work values
and see how they are reflected in the timephased details.
• Using the mouse, drag the vertical divider bar to the right until you
can see all the columns in the Work table
In the Actual column for task 18, Original art review, type or click 90h,
and then press the Enter key
Several important things occurred when you pressed Enter:
Several important things occurred when you pressed Enter:
• Project applied change highlighting to the updated values in the table.
• The amount of actual work you entered was subtracted from the Remaining
column.
• The actual work was distributed to the two assignments on the task,
resulting in 44.5 hours of actual work being recorded for one resource and
45.5 hours for the other resource. (The difference in assignments is due to
Hany’s previously customized assignment values.) Likewise, the updated
remaining work value was recalculated for each assignment.
• The updated actual and remaining work values were rolled up to the
Acquisition summary task.
• The actual work values were also redistributed to the task and assignment
timephased values.
To conclude this exercise, you will enter actual work values at the
assignment level and see the effect on the task.
• In the Actual column for Hany Morcos’s assignment to task 18, type or
click 60h, and then press Enter.
Drag the vertical divider bar back to the left to see more of the updated
timephased values for the task.
Exercise C: you enter some actuals for tasks for specific time
periods.
Click the minus sign next to task 15, Acquisition, to collapse this phase of the
project plan.
• Task Name column > click the name of task 22, Organize manuscript for
copyedit > Scroll to Task.
Project scrolls the timephased grid to display the first scheduled work values
of the Editorial phase.
The first timephased actual work values that you will enter are at the
task level and not for specific assignments.
• In the timephased grid, click the cell at the intersection of the Wednesday,
May 23 column and the task 22 actual work row. The actual work row is
directly below the work row, which contains the value 12h.
• Type 9h, and then press the Tab key.
• In the Thursday, May 24 actual work cell, type 15h, and then press
Tab.
• For task 22, enter the following actual work values for the dates
listed.
Date Actual Hours
Friday, May 25 12
Monday, May 28 12
Tuesday, May 29 15
For task 23, Copyedit, you have weekly actual work values from the
assigned resource. The copyeditors have completed the task. For this
task, you’ll adjust the timescale to record weekly actual values.
• View tab > Zoom group > Timescale box > Weeks.
Enter the following actual work values into the timephased grid for the
Copyeditors’ assignment to task 23, Copyedit
 Date (Week of) Actual Hours
 May 27 60
 June 3 80
 June 10 48
The resource’s actual work values were rolled up to the task’s actual
work values. The original work values were saved in the baseline
should you ever need to refer to them later.
Here is how Project handles tasks in relation to the
rescheduled date:
• If the task does not have any actual work recorded for it prior
to the rescheduled date and does not have a constraint
applied, the entire task is rescheduled to begin after that
date.
• If the task has some actual work recorded prior to but none
after the rescheduled date, the task is split so that all
remaining work starts after the rescheduled date. The actual
work is not affected.
• If the task has some actual work recorded for it prior to as
well as after the rescheduled date, the task is not affected
Exercise D: you reschedule uncompleted work
• View tab > Gantt Chart.
• In the Task Name column, click the name of task 31, Proofread
and index > Scroll to Task
You have learned that over the weekend of July 28, a water pipe burst
in the proofreaders’ office. None of the project’s equipment or material
was damaged, but the cleanup will delay work until Wednesday,
August 1. This effectively stops work on the proofreading task for a
few days. Next, you will reschedule incomplete work so that the
project can begin again on Wednesday.
• Project > Status > Update Project.
• Select the Reschedule uncompleted work to start after option,
and in the text box, type or select 7/31/12.
• Project splits task 31 so that the incomplete portion of the task is
delayed until Wednesday

More Related Content

What's hot

05 Formatting and Sharing Your Plan
05 Formatting and Sharing Your Plan 05 Formatting and Sharing Your Plan
05 Formatting and Sharing Your Plan Soe Naing Win
 
11 Organizing Project Details
11 Organizing Project Details11 Organizing Project Details
11 Organizing Project DetailsSoe Naing Win
 
03 Setting-up resources
03  Setting-up resources  03  Setting-up resources
03 Setting-up resources Soe Naing Win
 
Creating a task list
Creating a task listCreating a task list
Creating a task listahmed hamza
 
Ms project general introduction
Ms project general introductionMs project general introduction
Ms project general introductionKushal Patel
 
Ms Project 2007(advanced)
Ms Project 2007(advanced)Ms Project 2007(advanced)
Ms Project 2007(advanced)Dinesh Singh
 
Microsoft Project - MSP | 2013-2016
Microsoft Project - MSP | 2013-2016Microsoft Project - MSP | 2013-2016
Microsoft Project - MSP | 2013-2016Rajeev Sharma
 
Ms Project 2007(Basic)
Ms Project 2007(Basic)Ms Project 2007(Basic)
Ms Project 2007(Basic)Dinesh Singh
 
Microsoft project calender
Microsoft project calenderMicrosoft project calender
Microsoft project calenderMaheep Gupta
 
sMs project tutorial_iit
sMs project tutorial_iitsMs project tutorial_iit
sMs project tutorial_iitKushal Patel
 
Understanding Microsoft Project 'Calendars' ‘Working Time’, etc
Understanding Microsoft Project 'Calendars' ‘Working Time’, etcUnderstanding Microsoft Project 'Calendars' ‘Working Time’, etc
Understanding Microsoft Project 'Calendars' ‘Working Time’, etcKhalid Noor Mohammed
 
How to Create S-Curve by MS Project 2010
How to Create S-Curve by MS Project 2010How to Create S-Curve by MS Project 2010
How to Create S-Curve by MS Project 2010Ong-Art Sanpinit
 
2010 ms project 2010 (2)
2010 ms project 2010 (2)2010 ms project 2010 (2)
2010 ms project 2010 (2)douggillis
 
How to choose the right task type in Microsoft Project?
How to choose the right task type in Microsoft Project?How to choose the right task type in Microsoft Project?
How to choose the right task type in Microsoft Project?SPC Adriatics
 
204460 create s curve reports
204460 create s curve reports204460 create s curve reports
204460 create s curve reportsp6academy
 
MICROSOFT PROJECT
MICROSOFT PROJECTMICROSOFT PROJECT
MICROSOFT PROJECTSmit Patel
 

What's hot (20)

05 Formatting and Sharing Your Plan
05 Formatting and Sharing Your Plan 05 Formatting and Sharing Your Plan
05 Formatting and Sharing Your Plan
 
11 Organizing Project Details
11 Organizing Project Details11 Organizing Project Details
11 Organizing Project Details
 
03 Setting-up resources
03  Setting-up resources  03  Setting-up resources
03 Setting-up resources
 
Creating a task list
Creating a task listCreating a task list
Creating a task list
 
Ms project general introduction
Ms project general introductionMs project general introduction
Ms project general introduction
 
Ms Project 2007(advanced)
Ms Project 2007(advanced)Ms Project 2007(advanced)
Ms Project 2007(advanced)
 
Microsoft Project - MSP | 2013-2016
Microsoft Project - MSP | 2013-2016Microsoft Project - MSP | 2013-2016
Microsoft Project - MSP | 2013-2016
 
Ms Project 2007(Basic)
Ms Project 2007(Basic)Ms Project 2007(Basic)
Ms Project 2007(Basic)
 
Microsoft project calender
Microsoft project calenderMicrosoft project calender
Microsoft project calender
 
sMs project tutorial_iit
sMs project tutorial_iitsMs project tutorial_iit
sMs project tutorial_iit
 
Understanding Microsoft Project 'Calendars' ‘Working Time’, etc
Understanding Microsoft Project 'Calendars' ‘Working Time’, etcUnderstanding Microsoft Project 'Calendars' ‘Working Time’, etc
Understanding Microsoft Project 'Calendars' ‘Working Time’, etc
 
MS Project
MS ProjectMS Project
MS Project
 
MS Project 2007 Tips and Tricks
MS Project 2007 Tips and TricksMS Project 2007 Tips and Tricks
MS Project 2007 Tips and Tricks
 
Activity Duration Types Explained with example in Primavera
Activity Duration Types Explained with example in PrimaveraActivity Duration Types Explained with example in Primavera
Activity Duration Types Explained with example in Primavera
 
MS Project
MS Project MS Project
MS Project
 
How to Create S-Curve by MS Project 2010
How to Create S-Curve by MS Project 2010How to Create S-Curve by MS Project 2010
How to Create S-Curve by MS Project 2010
 
2010 ms project 2010 (2)
2010 ms project 2010 (2)2010 ms project 2010 (2)
2010 ms project 2010 (2)
 
How to choose the right task type in Microsoft Project?
How to choose the right task type in Microsoft Project?How to choose the right task type in Microsoft Project?
How to choose the right task type in Microsoft Project?
 
204460 create s curve reports
204460 create s curve reports204460 create s curve reports
204460 create s curve reports
 
MICROSOFT PROJECT
MICROSOFT PROJECTMICROSOFT PROJECT
MICROSOFT PROJECT
 

Viewers also liked

Tutorial 6: Multiple Worksheets and Workbooks
Tutorial 6: Multiple Worksheets and WorkbooksTutorial 6: Multiple Worksheets and Workbooks
Tutorial 6: Multiple Worksheets and Workbookscios135
 
Tutorial 2
Tutorial 2Tutorial 2
Tutorial 2cios135
 
Tutorial 4 Charts and Graphs
Tutorial 4 Charts and GraphsTutorial 4 Charts and Graphs
Tutorial 4 Charts and Graphscios135
 
Tutorial 5: Excel Tables, PivotTables, and Pivot Charts
Tutorial 5: Excel Tables, PivotTables, and Pivot ChartsTutorial 5: Excel Tables, PivotTables, and Pivot Charts
Tutorial 5: Excel Tables, PivotTables, and Pivot Chartscios135
 
Tutorial 3 Working with Formulas and Functions
Tutorial 3 Working with Formulas and FunctionsTutorial 3 Working with Formulas and Functions
Tutorial 3 Working with Formulas and Functionscios135
 
Tutorial 7: Advanced Functions and Conitional Formating
Tutorial 7: Advanced Functions and Conitional FormatingTutorial 7: Advanced Functions and Conitional Formating
Tutorial 7: Advanced Functions and Conitional Formatingcios135
 
00 Introduction of project scheduling
00 Introduction of project scheduling00 Introduction of project scheduling
00 Introduction of project schedulingSoe Naing Win
 
Tutorial 8: Developing an Excel Application
Tutorial 8: Developing an Excel ApplicationTutorial 8: Developing an Excel Application
Tutorial 8: Developing an Excel Applicationcios135
 

Viewers also liked (10)

Excel 2010.01 edited
Excel 2010.01 editedExcel 2010.01 edited
Excel 2010.01 edited
 
Tutorial 6: Multiple Worksheets and Workbooks
Tutorial 6: Multiple Worksheets and WorkbooksTutorial 6: Multiple Worksheets and Workbooks
Tutorial 6: Multiple Worksheets and Workbooks
 
Tutorial 2
Tutorial 2Tutorial 2
Tutorial 2
 
Tutorial 4 Charts and Graphs
Tutorial 4 Charts and GraphsTutorial 4 Charts and Graphs
Tutorial 4 Charts and Graphs
 
Tutorial 5: Excel Tables, PivotTables, and Pivot Charts
Tutorial 5: Excel Tables, PivotTables, and Pivot ChartsTutorial 5: Excel Tables, PivotTables, and Pivot Charts
Tutorial 5: Excel Tables, PivotTables, and Pivot Charts
 
Tutorial 3 Working with Formulas and Functions
Tutorial 3 Working with Formulas and FunctionsTutorial 3 Working with Formulas and Functions
Tutorial 3 Working with Formulas and Functions
 
Tutorial 7: Advanced Functions and Conitional Formating
Tutorial 7: Advanced Functions and Conitional FormatingTutorial 7: Advanced Functions and Conitional Formating
Tutorial 7: Advanced Functions and Conitional Formating
 
00 Introduction of project scheduling
00 Introduction of project scheduling00 Introduction of project scheduling
00 Introduction of project scheduling
 
Tutorial 8: Developing an Excel Application
Tutorial 8: Developing an Excel ApplicationTutorial 8: Developing an Excel Application
Tutorial 8: Developing an Excel Application
 
Microsoft excel 2010 useful formula & functions
Microsoft excel 2010   useful formula & functionsMicrosoft excel 2010   useful formula & functions
Microsoft excel 2010 useful formula & functions
 

Similar to 12 Tracking Progress on Tasks and Assignments

Project management course lecture Notes from Yom college
Project management course lecture Notes from Yom collegeProject management course lecture Notes from Yom college
Project management course lecture Notes from Yom collegeAbebaw31
 
SCM435 – Project Management MICROSOFT PROJECT ASSIGNMENT.docx
SCM435 – Project Management MICROSOFT PROJECT ASSIGNMENT.docxSCM435 – Project Management MICROSOFT PROJECT ASSIGNMENT.docx
SCM435 – Project Management MICROSOFT PROJECT ASSIGNMENT.docxbagotjesusa
 
Yom Institute Presentations lecture notes of project management
Yom Institute Presentations lecture notes of project managementYom Institute Presentations lecture notes of project management
Yom Institute Presentations lecture notes of project managementAbebaw31
 
Program Management 2.0: Burndown Charts
Program Management 2.0: Burndown ChartsProgram Management 2.0: Burndown Charts
Program Management 2.0: Burndown ChartsJohn Carter
 
Software Project Management lecture 9
Software Project Management lecture 9Software Project Management lecture 9
Software Project Management lecture 9Syed Muhammad Hammad
 
Project NameCommunication PlanOverviewEffective and .docx
Project NameCommunication PlanOverviewEffective and .docxProject NameCommunication PlanOverviewEffective and .docx
Project NameCommunication PlanOverviewEffective and .docxwkyra78
 
Ms project tutorial
Ms project tutorialMs project tutorial
Ms project tutorialRonald Oroya
 
PRIMAVERA P6 manual.pptx
PRIMAVERA P6 manual.pptxPRIMAVERA P6 manual.pptx
PRIMAVERA P6 manual.pptxGracePentinio1
 
MS Project Management (Overviews) | Software Mange Tool | Software Project Ma...
MS Project Management (Overviews) | Software Mange Tool | Software Project Ma...MS Project Management (Overviews) | Software Mange Tool | Software Project Ma...
MS Project Management (Overviews) | Software Mange Tool | Software Project Ma...Kuldeep Kumar
 
2009 ms project 2010 (2)
2009 ms project 2010 (2)2009 ms project 2010 (2)
2009 ms project 2010 (2)constancemccrea
 
Devry proj 586 week 3 project guidelines microsoft project new
Devry proj 586 week 3 project guidelines microsoft project newDevry proj 586 week 3 project guidelines microsoft project new
Devry proj 586 week 3 project guidelines microsoft project newuopassignment
 

Similar to 12 Tracking Progress on Tasks and Assignments (20)

Project management course lecture Notes from Yom college
Project management course lecture Notes from Yom collegeProject management course lecture Notes from Yom college
Project management course lecture Notes from Yom college
 
SCM435 – Project Management MICROSOFT PROJECT ASSIGNMENT.docx
SCM435 – Project Management MICROSOFT PROJECT ASSIGNMENT.docxSCM435 – Project Management MICROSOFT PROJECT ASSIGNMENT.docx
SCM435 – Project Management MICROSOFT PROJECT ASSIGNMENT.docx
 
Yom Institute Presentations lecture notes of project management
Yom Institute Presentations lecture notes of project managementYom Institute Presentations lecture notes of project management
Yom Institute Presentations lecture notes of project management
 
Schedule management
Schedule managementSchedule management
Schedule management
 
Program Management 2.0: Burndown Charts
Program Management 2.0: Burndown ChartsProgram Management 2.0: Burndown Charts
Program Management 2.0: Burndown Charts
 
Software Project Management lecture 9
Software Project Management lecture 9Software Project Management lecture 9
Software Project Management lecture 9
 
Project NameCommunication PlanOverviewEffective and .docx
Project NameCommunication PlanOverviewEffective and .docxProject NameCommunication PlanOverviewEffective and .docx
Project NameCommunication PlanOverviewEffective and .docx
 
Omni plan 2-manual
Omni plan 2-manualOmni plan 2-manual
Omni plan 2-manual
 
Ms project lectures
Ms project lecturesMs project lectures
Ms project lectures
 
Ms project tutorial
Ms project tutorialMs project tutorial
Ms project tutorial
 
PRIMAVERA P6 manual.pptx
PRIMAVERA P6 manual.pptxPRIMAVERA P6 manual.pptx
PRIMAVERA P6 manual.pptx
 
MS Project Guide.pdf
MS Project Guide.pdfMS Project Guide.pdf
MS Project Guide.pdf
 
MS Project Management (Overviews) | Software Mange Tool | Software Project Ma...
MS Project Management (Overviews) | Software Mange Tool | Software Project Ma...MS Project Management (Overviews) | Software Mange Tool | Software Project Ma...
MS Project Management (Overviews) | Software Mange Tool | Software Project Ma...
 
2009 ms project 2010 (2)
2009 ms project 2010 (2)2009 ms project 2010 (2)
2009 ms project 2010 (2)
 
Devry proj 586 week 3 project guidelines microsoft project new
Devry proj 586 week 3 project guidelines microsoft project newDevry proj 586 week 3 project guidelines microsoft project new
Devry proj 586 week 3 project guidelines microsoft project new
 
Project management software
Project management softwareProject management software
Project management software
 
Progress in Projects
Progress in ProjectsProgress in Projects
Progress in Projects
 
Oracle Primavera P6 PRO R8 Tips & tricks
Oracle Primavera P6 PRO R8 Tips & tricksOracle Primavera P6 PRO R8 Tips & tricks
Oracle Primavera P6 PRO R8 Tips & tricks
 
Ppsi pertemuan-3
Ppsi pertemuan-3Ppsi pertemuan-3
Ppsi pertemuan-3
 
Microsoft Project Foundations Course.pptx
Microsoft Project Foundations Course.pptxMicrosoft Project Foundations Course.pptx
Microsoft Project Foundations Course.pptx
 

Recently uploaded

What is Model Inheritance in Odoo 17 ERP
What is Model Inheritance in Odoo 17 ERPWhat is Model Inheritance in Odoo 17 ERP
What is Model Inheritance in Odoo 17 ERPCeline George
 
Atmosphere science 7 quarter 4 .........
Atmosphere science 7 quarter 4 .........Atmosphere science 7 quarter 4 .........
Atmosphere science 7 quarter 4 .........LeaCamillePacle
 
Types of Journalistic Writing Grade 8.pptx
Types of Journalistic Writing Grade 8.pptxTypes of Journalistic Writing Grade 8.pptx
Types of Journalistic Writing Grade 8.pptxEyham Joco
 
Influencing policy (training slides from Fast Track Impact)
Influencing policy (training slides from Fast Track Impact)Influencing policy (training slides from Fast Track Impact)
Influencing policy (training slides from Fast Track Impact)Mark Reed
 
Solving Puzzles Benefits Everyone (English).pptx
Solving Puzzles Benefits Everyone (English).pptxSolving Puzzles Benefits Everyone (English).pptx
Solving Puzzles Benefits Everyone (English).pptxOH TEIK BIN
 
Crayon Activity Handout For the Crayon A
Crayon Activity Handout For the Crayon ACrayon Activity Handout For the Crayon A
Crayon Activity Handout For the Crayon AUnboundStockton
 
Like-prefer-love -hate+verb+ing & silent letters & citizenship text.pdf
Like-prefer-love -hate+verb+ing & silent letters & citizenship text.pdfLike-prefer-love -hate+verb+ing & silent letters & citizenship text.pdf
Like-prefer-love -hate+verb+ing & silent letters & citizenship text.pdfMr Bounab Samir
 
AmericanHighSchoolsprezentacijaoskolama.
AmericanHighSchoolsprezentacijaoskolama.AmericanHighSchoolsprezentacijaoskolama.
AmericanHighSchoolsprezentacijaoskolama.arsicmarija21
 
DATA STRUCTURE AND ALGORITHM for beginners
DATA STRUCTURE AND ALGORITHM for beginnersDATA STRUCTURE AND ALGORITHM for beginners
DATA STRUCTURE AND ALGORITHM for beginnersSabitha Banu
 
Earth Day Presentation wow hello nice great
Earth Day Presentation wow hello nice greatEarth Day Presentation wow hello nice great
Earth Day Presentation wow hello nice greatYousafMalik24
 
How to Configure Email Server in Odoo 17
How to Configure Email Server in Odoo 17How to Configure Email Server in Odoo 17
How to Configure Email Server in Odoo 17Celine George
 
Introduction to ArtificiaI Intelligence in Higher Education
Introduction to ArtificiaI Intelligence in Higher EducationIntroduction to ArtificiaI Intelligence in Higher Education
Introduction to ArtificiaI Intelligence in Higher Educationpboyjonauth
 
ROOT CAUSE ANALYSIS PowerPoint Presentation
ROOT CAUSE ANALYSIS PowerPoint PresentationROOT CAUSE ANALYSIS PowerPoint Presentation
ROOT CAUSE ANALYSIS PowerPoint PresentationAadityaSharma884161
 
ENGLISH6-Q4-W3.pptxqurter our high choom
ENGLISH6-Q4-W3.pptxqurter our high choomENGLISH6-Q4-W3.pptxqurter our high choom
ENGLISH6-Q4-W3.pptxqurter our high choomnelietumpap1
 
ACC 2024 Chronicles. Cardiology. Exam.pdf
ACC 2024 Chronicles. Cardiology. Exam.pdfACC 2024 Chronicles. Cardiology. Exam.pdf
ACC 2024 Chronicles. Cardiology. Exam.pdfSpandanaRallapalli
 
ENGLISH 7_Q4_LESSON 2_ Employing a Variety of Strategies for Effective Interp...
ENGLISH 7_Q4_LESSON 2_ Employing a Variety of Strategies for Effective Interp...ENGLISH 7_Q4_LESSON 2_ Employing a Variety of Strategies for Effective Interp...
ENGLISH 7_Q4_LESSON 2_ Employing a Variety of Strategies for Effective Interp...JhezDiaz1
 
ECONOMIC CONTEXT - PAPER 1 Q3: NEWSPAPERS.pptx
ECONOMIC CONTEXT - PAPER 1 Q3: NEWSPAPERS.pptxECONOMIC CONTEXT - PAPER 1 Q3: NEWSPAPERS.pptx
ECONOMIC CONTEXT - PAPER 1 Q3: NEWSPAPERS.pptxiammrhaywood
 
Roles & Responsibilities in Pharmacovigilance
Roles & Responsibilities in PharmacovigilanceRoles & Responsibilities in Pharmacovigilance
Roles & Responsibilities in PharmacovigilanceSamikshaHamane
 
How to do quick user assign in kanban in Odoo 17 ERP
How to do quick user assign in kanban in Odoo 17 ERPHow to do quick user assign in kanban in Odoo 17 ERP
How to do quick user assign in kanban in Odoo 17 ERPCeline George
 

Recently uploaded (20)

What is Model Inheritance in Odoo 17 ERP
What is Model Inheritance in Odoo 17 ERPWhat is Model Inheritance in Odoo 17 ERP
What is Model Inheritance in Odoo 17 ERP
 
Atmosphere science 7 quarter 4 .........
Atmosphere science 7 quarter 4 .........Atmosphere science 7 quarter 4 .........
Atmosphere science 7 quarter 4 .........
 
9953330565 Low Rate Call Girls In Rohini Delhi NCR
9953330565 Low Rate Call Girls In Rohini  Delhi NCR9953330565 Low Rate Call Girls In Rohini  Delhi NCR
9953330565 Low Rate Call Girls In Rohini Delhi NCR
 
Types of Journalistic Writing Grade 8.pptx
Types of Journalistic Writing Grade 8.pptxTypes of Journalistic Writing Grade 8.pptx
Types of Journalistic Writing Grade 8.pptx
 
Influencing policy (training slides from Fast Track Impact)
Influencing policy (training slides from Fast Track Impact)Influencing policy (training slides from Fast Track Impact)
Influencing policy (training slides from Fast Track Impact)
 
Solving Puzzles Benefits Everyone (English).pptx
Solving Puzzles Benefits Everyone (English).pptxSolving Puzzles Benefits Everyone (English).pptx
Solving Puzzles Benefits Everyone (English).pptx
 
Crayon Activity Handout For the Crayon A
Crayon Activity Handout For the Crayon ACrayon Activity Handout For the Crayon A
Crayon Activity Handout For the Crayon A
 
Like-prefer-love -hate+verb+ing & silent letters & citizenship text.pdf
Like-prefer-love -hate+verb+ing & silent letters & citizenship text.pdfLike-prefer-love -hate+verb+ing & silent letters & citizenship text.pdf
Like-prefer-love -hate+verb+ing & silent letters & citizenship text.pdf
 
AmericanHighSchoolsprezentacijaoskolama.
AmericanHighSchoolsprezentacijaoskolama.AmericanHighSchoolsprezentacijaoskolama.
AmericanHighSchoolsprezentacijaoskolama.
 
DATA STRUCTURE AND ALGORITHM for beginners
DATA STRUCTURE AND ALGORITHM for beginnersDATA STRUCTURE AND ALGORITHM for beginners
DATA STRUCTURE AND ALGORITHM for beginners
 
Earth Day Presentation wow hello nice great
Earth Day Presentation wow hello nice greatEarth Day Presentation wow hello nice great
Earth Day Presentation wow hello nice great
 
How to Configure Email Server in Odoo 17
How to Configure Email Server in Odoo 17How to Configure Email Server in Odoo 17
How to Configure Email Server in Odoo 17
 
Introduction to ArtificiaI Intelligence in Higher Education
Introduction to ArtificiaI Intelligence in Higher EducationIntroduction to ArtificiaI Intelligence in Higher Education
Introduction to ArtificiaI Intelligence in Higher Education
 
ROOT CAUSE ANALYSIS PowerPoint Presentation
ROOT CAUSE ANALYSIS PowerPoint PresentationROOT CAUSE ANALYSIS PowerPoint Presentation
ROOT CAUSE ANALYSIS PowerPoint Presentation
 
ENGLISH6-Q4-W3.pptxqurter our high choom
ENGLISH6-Q4-W3.pptxqurter our high choomENGLISH6-Q4-W3.pptxqurter our high choom
ENGLISH6-Q4-W3.pptxqurter our high choom
 
ACC 2024 Chronicles. Cardiology. Exam.pdf
ACC 2024 Chronicles. Cardiology. Exam.pdfACC 2024 Chronicles. Cardiology. Exam.pdf
ACC 2024 Chronicles. Cardiology. Exam.pdf
 
ENGLISH 7_Q4_LESSON 2_ Employing a Variety of Strategies for Effective Interp...
ENGLISH 7_Q4_LESSON 2_ Employing a Variety of Strategies for Effective Interp...ENGLISH 7_Q4_LESSON 2_ Employing a Variety of Strategies for Effective Interp...
ENGLISH 7_Q4_LESSON 2_ Employing a Variety of Strategies for Effective Interp...
 
ECONOMIC CONTEXT - PAPER 1 Q3: NEWSPAPERS.pptx
ECONOMIC CONTEXT - PAPER 1 Q3: NEWSPAPERS.pptxECONOMIC CONTEXT - PAPER 1 Q3: NEWSPAPERS.pptx
ECONOMIC CONTEXT - PAPER 1 Q3: NEWSPAPERS.pptx
 
Roles & Responsibilities in Pharmacovigilance
Roles & Responsibilities in PharmacovigilanceRoles & Responsibilities in Pharmacovigilance
Roles & Responsibilities in Pharmacovigilance
 
How to do quick user assign in kanban in Odoo 17 ERP
How to do quick user assign in kanban in Odoo 17 ERPHow to do quick user assign in kanban in Odoo 17 ERP
How to do quick user assign in kanban in Odoo 17 ERP
 

12 Tracking Progress on Tasks and Assignments

  • 1. Soe Naing Win Email: snw1975@gmail.com
  • 2.  Update a previously saved baseline plan.  Record actual work for tasks and assignments.  Record actual work by time period.  Interrupt work on a task and specify the date on which the task should start again
  • 3. Recall that a baseline is a collection of important values in a project plan, such as the planned start dates, finish dates, and costs of tasks, resources, and assignments. When you save (or set) a baseline, Project takes a “snapshot” of the existing values and saves it in the Project plan for future comparison.
  • 4. To keep an accurate baseline for later comparison, you have several options: • Update the baseline for the entire project. This simply replaces the original baseline values with the currently scheduled values. • Update the baseline for selected tasks. This does not affect the baseline values for other tasks or resource baseline values in the project plan. • Save a second or subsequent baseline. You can save up to 11 baselines in a single plan. The first one is called Baseline, and the rest are Baseline 1 through Baseline 10.
  • 5. Exercise : compare the project plan as it is currently scheduled with the baseline plan and update the baseline for the project plan. • View > Task Views > Gantt Chart > Tracking Gantt
  • 6.  Task Name > task 18, Original art review > Scroll to Task  View > Zoom > Timescale > Weeks
  • 7. To conclude this exercise, you will resave the baseline for the project plan. Doing so will update all baseline information for tasks, resources, and assignments prior to tracking progress. • Project > Schedule > Set Baseline > Set Baseline Make sure that the Set Baseline option is selected. In the For area, make sure that the Entire project option is selected
  • 8. • Click OK to update the baseline. • Project alerts you that you are about to overwrite the previously saved baseline values. • Click Yes. Project updates the baseline values for the project plan.
  • 9. Exercise, you record task-level and assignment-level actuals and see how the information is rolled up or down between tasks and assignments. • Change to Task Usage. • Task Name > task 18, Original art review > Scroll to Task. • View tab > Data > Tables > Work.
  • 10. For example, • The work, total for task 18, 160 hours = the sum of Hany Morcos’ 80 hours of work on the task and Jane Dow’s 80 hours.
  • 11. Next, you’ll change the details shown on the timephased grid on the right side of the view. • Format > Details > Actual Work.
  • 12. Next, you’ll enter task-level and assignment-level actual work values and see how they are reflected in the timephased details. • Using the mouse, drag the vertical divider bar to the right until you can see all the columns in the Work table
  • 13. In the Actual column for task 18, Original art review, type or click 90h, and then press the Enter key
  • 14. Several important things occurred when you pressed Enter:
  • 15. Several important things occurred when you pressed Enter: • Project applied change highlighting to the updated values in the table. • The amount of actual work you entered was subtracted from the Remaining column. • The actual work was distributed to the two assignments on the task, resulting in 44.5 hours of actual work being recorded for one resource and 45.5 hours for the other resource. (The difference in assignments is due to Hany’s previously customized assignment values.) Likewise, the updated remaining work value was recalculated for each assignment. • The updated actual and remaining work values were rolled up to the Acquisition summary task. • The actual work values were also redistributed to the task and assignment timephased values.
  • 16. To conclude this exercise, you will enter actual work values at the assignment level and see the effect on the task. • In the Actual column for Hany Morcos’s assignment to task 18, type or click 60h, and then press Enter.
  • 17. Drag the vertical divider bar back to the left to see more of the updated timephased values for the task.
  • 18. Exercise C: you enter some actuals for tasks for specific time periods. Click the minus sign next to task 15, Acquisition, to collapse this phase of the project plan. • Task Name column > click the name of task 22, Organize manuscript for copyedit > Scroll to Task. Project scrolls the timephased grid to display the first scheduled work values of the Editorial phase.
  • 19. The first timephased actual work values that you will enter are at the task level and not for specific assignments. • In the timephased grid, click the cell at the intersection of the Wednesday, May 23 column and the task 22 actual work row. The actual work row is directly below the work row, which contains the value 12h.
  • 20. • Type 9h, and then press the Tab key.
  • 21. • In the Thursday, May 24 actual work cell, type 15h, and then press Tab.
  • 22. • For task 22, enter the following actual work values for the dates listed. Date Actual Hours Friday, May 25 12 Monday, May 28 12 Tuesday, May 29 15
  • 23. For task 23, Copyedit, you have weekly actual work values from the assigned resource. The copyeditors have completed the task. For this task, you’ll adjust the timescale to record weekly actual values. • View tab > Zoom group > Timescale box > Weeks. Enter the following actual work values into the timephased grid for the Copyeditors’ assignment to task 23, Copyedit  Date (Week of) Actual Hours  May 27 60  June 3 80  June 10 48
  • 24. The resource’s actual work values were rolled up to the task’s actual work values. The original work values were saved in the baseline should you ever need to refer to them later.
  • 25. Here is how Project handles tasks in relation to the rescheduled date: • If the task does not have any actual work recorded for it prior to the rescheduled date and does not have a constraint applied, the entire task is rescheduled to begin after that date. • If the task has some actual work recorded prior to but none after the rescheduled date, the task is split so that all remaining work starts after the rescheduled date. The actual work is not affected. • If the task has some actual work recorded for it prior to as well as after the rescheduled date, the task is not affected
  • 26. Exercise D: you reschedule uncompleted work • View tab > Gantt Chart. • In the Task Name column, click the name of task 31, Proofread and index > Scroll to Task
  • 27. You have learned that over the weekend of July 28, a water pipe burst in the proofreaders’ office. None of the project’s equipment or material was damaged, but the cleanup will delay work until Wednesday, August 1. This effectively stops work on the proofreading task for a few days. Next, you will reschedule incomplete work so that the project can begin again on Wednesday. • Project > Status > Update Project.
  • 28. • Select the Reschedule uncompleted work to start after option, and in the text box, type or select 7/31/12.
  • 29. • Project splits task 31 so that the incomplete portion of the task is delayed until Wednesday

Editor's Notes

  1. In the previous three chapters, you have focused on details about tasks, resources, and assignments. Now, you will examine the results of your previous work on the schedule and dive deeper into resource assignments. You’ll also observe the overall project duration and cost.
  2. Keep in mind that the purpose of the baseline is to record what you expected the project plan to look like at one point in time. As time passes, however, you might need to change your expectations. After saving an initial baseline plan, you might need to fine-tune the project plan by adding or removing tasks or assignments, and so on
  3. In the previous three chapters, you have focused on details about tasks, resources, and assignments. Now, you will examine the results of your previous work on the schedule and dive deeper into resource assignments. You’ll also observe the overall project duration and cost.
  4. In the chart portion of this view, the tasks as they are currently scheduled appear as blue bars (if they are not critical tasks) or red bars (if they are critical). Below them, the baseline values of each task appear as gray bars. Tip In Gantt Chart views, the colors, patterns, and shapes of the bars represent specific things. To see what any item on the Gantt chart represents, just point your mouse pointer at it and a description will appear in a ScreenTip. To see a complete legend of Gantt chart items and their formatting, on the Format tab, in the Bar Styles group, click Format and then click Bar Styles.
  5. The Tracking Gantt view scrolls to display the Gantt bar for task 18, Original art review. This task was added to the plan after the initial baseline was saved. As you can see in the Tracking Gantt view, this task has no baseline bar, indicating that it has no baseline values. To get a broader look at the project plan’s baseline, you’ll adjust the zoom level. You can see that currently none of the later tasks in the project plan match their baselines.
  6. This project plan includes a previously saved baseline that you will now overwrite. That’s fine at this stage of the new book project, where the planning is complete and you’d like to have the most up-to-date baseline before recording any actual work. However, after work has been recorded, you should be careful about overwriting any previously saved baseline values. Once you overwrite a baseline, the original values are replaced and cannot be retrieved. Saving additional baselines is often a better strategy after work on the project has begun.
  7. Task 18 now has a baseline, and all of the other tasks’ baseline values now match their scheduled values.
  8. The Task Usage view appears. As you may recall from Chapter 7, “Fine-Tuning Task Details,” the two sides of the usage view are split by a vertical divider bar. The Task Usage view lists resources under the tasks to which they’re assigned. This information appears in the table on the left side. On the right side, you see rows organized under a timescale. The rows on the right side show you the scheduled work values for each task or assigned resource. The Task Usage view color-codes the rows on the right side: task rows have a shaded background, and assignment rows have a white background.
  9. This table includes the Actual Work and Remaining Work columns that you will work with shortly, although they might not yet be visible. The values in the Work column are the task and assignment totals for scheduled work. Note that each task’s work value is the sum of its assignment work values. For example, the work
  10. This table includes the Actual Work and Remaining Work columns that you will work with shortly, although they might not yet be visible. The values in the Work column are the task and assignment totals for scheduled work. Note that each task’s work value is the sum of its assignment work values. For example, the work
  11. This table includes the Actual Work and Remaining Work columns that you will work with shortly, although they might not yet be visible. The values in the Work column are the task and assignment totals for scheduled work. Note that each task’s work value is the sum of its assignment work values. For example, the work
  12. This table includes the Actual Work and Remaining Work columns that you will work with shortly, although they might not yet be visible. The values in the Work column are the task and assignment totals for scheduled work. Note that each task’s work value is the sum of its assignment work values. For example, the work
  13. In the timephased grid side of the view, you can see the daily scheduled work and actual work values for the three resources through Thursday, April 26. Because you entered an actual work value for the entire task, Project assumes that the work was done as scheduled and records these timephased values for the resource assignments.
  14. In the timephased grid side of the view, you can see the daily scheduled work and actual work values for the three resources through Thursday, April 26. Because you entered an actual work value for the entire task, Project assumes that the work was done as scheduled and records these timephased values for the resource assignments.
  15. Hany’s actual and remaining work values are updated, and those updates also roll up to the task and its summary task (Project highlights the changed values). However, the actual and remaining work values for Jane Dow, the other resource assigned to the task, are not affected
  16. Again, Project assumes that the actual work value that you entered for Hany was completed as scheduled; therefore, her work and actual work timephased values match through Monday, April 30.
  17. Entering timephased actuals requires more work on the project manager’s part and might require more work from resources to inform the project manager of their daily or weekly actuals. However, doing so gives you far more detail about the project’s task and resource status than the other methods used for entering actuals. Entering timephased values might be the best approach to take if you have a group of tasks or an entire project that includes the following: ● High-risk tasks ● Relatively short-duration tasks in which a variance of even one day could put the overall project at risk Tasks for which you’d like to develop or validate throughput metrics, or rates at which a given quantity of a deliverable can be completed over a given time period, such as copyedit 3000 words per day ● Tasks in which sponsors or other stakeholders have an especially strong interest ● Tasks that require hourly billing for labor
  18. At this point in the new book project, the Acquisition work has been completed, and the Editorial phase has just begun. Because of the larger number of resources involved and the variability of the editorial work, these tasks are the riskiest ones so far in the project.
  19. As soon as you entered the first actual value for the task, the scheduled work value changed to match it. Both work and actual work values rolled up to the summary task levels and were distributed among the specific assignments to the task. You can see this happen in the timephased grid on the right and the table on the left.
  20. As soon as you entered the first actual value for the task, the scheduled work value changed to match it. Both work and actual work values rolled up to the summary task levels and were distributed among the specific assignments to the task. You can see this happen in the timephased grid on the right and the table on the left.
  21. This step concludes the actual work for this task. Next, you’ll enter actual work values for the assignments on the next task.
  22. This step concludes the actual work for this task. Next, you’ll enter actual work values for the assignments on the next task.
  23. The resource’s actual work values were rolled up to the task’s actual work values. The original work values were saved in the baseline should you ever need to refer to them later.
  24. At this point in the new book project, work on the Editorial phase has been completed, and the team has started work on the next phase, Design and Production. However, you need to troubleshoot a delay in work caused by an unforeseen problem.
  25. The Gantt Chart view scrolls to display the Gantt bar for task 31, Proofread and index. Currently, this task has two days of actual work completed and several days of scheduled work remaining
  26. At this point in the new book project, work on the Editorial phase has been completed, and the team has started work on the next phase, Design and Production. However, you need to troubleshoot a delay in work caused by an unforeseen problem.
  27. Project splits task 31 so that the incomplete portion of the task is delayed until Wednesday
  28. Project splits task 31 so that the incomplete portion of the task is delayed until Wednesday. As you can see, although the duration of task 31 remains 10.4 working days, its finish date and subsequent start dates for successor tasks have been pushed out. Although we have addressed a specific problem, in doing so, we have created other problems in the remainder of the project. You will address this and other problems in the project plan in later chapters.