SlideShare a Scribd company logo
1 of 22
Soe Naing Win
Email: snw1975@gmail.com
In this chapter, you will learn how to:
Assign work resources to tasks.
Control how Project schedules additional resource
assignments.
Assign cost resources to tasks.
Open exercise file, and check Project Information
Note the current duration of 41 days and zero cost. After you assign
work and cost resources, you’ll check these values again.
Resource tab, Assignments group, Assign Resources.
Task Name column, click the name of task 2, Assign launch team
members.
Resource Name column in the Assign Resources dialog box, click
Carole Poland, and then click Assign.
Task Name column, click the name of task 3, Complete author
questionnaire.
the Resource Name column in the Assign Resources dialog box,
click Toni Poe, and then click Assign.
Next, you’ll take a closer look at the details of task 3. You’ll use a
handy view called the Task Form.
View tab, in the Split View group, click Details.
Next you’ll change the displayed details.
Click anywhere in the Task Form and then, on the Format tab, in
the Details group, click Work.
Using the Assign Resources dialog box, assign the following
resources to tasks
Note the Duration, Units, and Work values in the Task Form
Next, you will assign two resources to a single task
Task Name column, click the name of task 8, Kickoff book launch meeting.
In the Assign Resources dialog box, select the names of Sharon Salavaria
and Toby Nixon, and then click Assign .
To conclude this exercise, you’ll use a different means of assigning
resources
In the Gantt Chart view, drag the vertical divider bar to the right until the Resource
Names column is visible.
Click in the Resource Names column for task 9, Plan author’s travel itinerary, and
then click the arrow that appears.
In the list of resource names, click the check boxes for Jane Dow
and Zac Woodall, and then press the Enter key.
Click in the Resource Names column for task 10, Channel Sales
prep, and then click the arrow that appears. In the list of resource
names that appears, check Zac Woodall and then press the Enter
key.
Click in the Resource Names column for task 10, Channel Sales
prep, and then click the arrow that appears. In the list of resource
names that appears, check Zac Woodall and then press the Enter
key.
The Scheduling Formula: Duration, Units, and Work
After you create a task, but before you assign a resource to it, the
task has duration but no work associated with it. Why no work?
Work represents the amount of effort a resource or resources will
spend to complete a task. For example, if you have one person
working full time, the amount of time measured as work is the same
as the amount of time measured as duration. In general, the amount
of work will match the duration unless you assign more than one
resource to a task or the one resource you assign is not working full
time.
Project calculates work using what is sometimes called the
scheduling formula:
Duration × Units = Work
The scheduling formula for task looks like this:
40 hours (same as one week) task duration × 100% assignment
units = 40 hours of work
In other words, with Resource assigned to task at 100% units, the
task should require 40 hours of work.
Here’s a more complex example. You assigned two resources, Jane
Dow and Zac Woodall, to task 9, each at 100% assignment units.
The scheduling formula for task 9 looks like this:
24 hours (same as three days) task duration × 200% assignment
units = 48 hours of work
The 48 hours of work is the sum of Jane’s 24 hours of work plus
Zac’s 24 hours of work. In other words, as currently scheduled, both
resources will work full time on the task in parallel for its three-day
duration
Exercise: adjust resource assignments on tasks and tell Project how it
should adjust the tasks.
In the Gantt Chart view, click the name of task 5, Design and order
marketing material.
Currently, Toby is assigned to this task. A quick check of the
scheduling formula looks like this:
80 hours (the same as 10 days, or two weeks) task duration × 100%
of Toby’s assignment units = 80 hours of work
Toby needs some help with this task, so you’ll add a resource.
In the Resource Name column in the Assign Resources dialog
box, click Zac Woodall, and then click Assign .
Click the name of task 5, and then click the Actions button that
appears just to the left of the task name.
04 Assigning Resources to Tasks

More Related Content

What's hot

2010 ms project 2010 (2)
2010 ms project 2010 (2)2010 ms project 2010 (2)
2010 ms project 2010 (2)
douggillis
 
Ms project management
Ms  project managementMs  project management
Ms project management
chinunki4
 

What's hot (20)

05 Formatting and Sharing Your Plan
05 Formatting and Sharing Your Plan 05 Formatting and Sharing Your Plan
05 Formatting and Sharing Your Plan
 
09 Fine-tuning Assignment Details
09 Fine-tuning Assignment Details09 Fine-tuning Assignment Details
09 Fine-tuning Assignment Details
 
Creating a task list
Creating a task listCreating a task list
Creating a task list
 
Microsoft Project - MSP | 2013-2016
Microsoft Project - MSP | 2013-2016Microsoft Project - MSP | 2013-2016
Microsoft Project - MSP | 2013-2016
 
Ms project general introduction
Ms project general introductionMs project general introduction
Ms project general introduction
 
MICROSOFT PROJECT TUTORIAL
MICROSOFT PROJECT TUTORIALMICROSOFT PROJECT TUTORIAL
MICROSOFT PROJECT TUTORIAL
 
MS Project
MS ProjectMS Project
MS Project
 
sMs project tutorial_iit
sMs project tutorial_iitsMs project tutorial_iit
sMs project tutorial_iit
 
How to Create S-Curve by MS Project 2010
How to Create S-Curve by MS Project 2010How to Create S-Curve by MS Project 2010
How to Create S-Curve by MS Project 2010
 
Project management software
Project management softwareProject management software
Project management software
 
Microsoft project 2010
Microsoft project 2010Microsoft project 2010
Microsoft project 2010
 
Devry proj 586 week 3 project guidelines microsoft project new
Devry proj 586 week 3 project guidelines microsoft project newDevry proj 586 week 3 project guidelines microsoft project new
Devry proj 586 week 3 project guidelines microsoft project new
 
Microsoft project calender
Microsoft project calenderMicrosoft project calender
Microsoft project calender
 
MS Project
MS Project MS Project
MS Project
 
2010 ms project 2010 (2)
2010 ms project 2010 (2)2010 ms project 2010 (2)
2010 ms project 2010 (2)
 
Ms Project 2007(advanced)
Ms Project 2007(advanced)Ms Project 2007(advanced)
Ms Project 2007(advanced)
 
Ms project management
Ms  project managementMs  project management
Ms project management
 
Ms Project 2007(Basic)
Ms Project 2007(Basic)Ms Project 2007(Basic)
Ms Project 2007(Basic)
 
Omni plan 2-manual
Omni plan 2-manualOmni plan 2-manual
Omni plan 2-manual
 
Understanding Microsoft Project 'Calendars' ‘Working Time’, etc
Understanding Microsoft Project 'Calendars' ‘Working Time’, etcUnderstanding Microsoft Project 'Calendars' ‘Working Time’, etc
Understanding Microsoft Project 'Calendars' ‘Working Time’, etc
 

Similar to 04 Assigning Resources to Tasks

Sheet1Points0ENGL510 Grading Rubric Group .docx
Sheet1Points0ENGL510 Grading Rubric                        Group .docxSheet1Points0ENGL510 Grading Rubric                        Group .docx
Sheet1Points0ENGL510 Grading Rubric Group .docx
lesleyryder69361
 
Creating events starttofinish
Creating events starttofinishCreating events starttofinish
Creating events starttofinish
Dixie Stephens
 
Project NameCommunication PlanOverviewEffective and .docx
Project NameCommunication PlanOverviewEffective and .docxProject NameCommunication PlanOverviewEffective and .docx
Project NameCommunication PlanOverviewEffective and .docx
wkyra78
 
BUS407 Week 3 Scenario Script Performance ModelSlide #SceneI.docx
BUS407 Week 3 Scenario Script Performance ModelSlide #SceneI.docxBUS407 Week 3 Scenario Script Performance ModelSlide #SceneI.docx
BUS407 Week 3 Scenario Script Performance ModelSlide #SceneI.docx
jasoninnes20
 
Michael HricikENG 162This assignment will be about 2-3 double-sp.docx
Michael HricikENG 162This assignment will be about 2-3 double-sp.docxMichael HricikENG 162This assignment will be about 2-3 double-sp.docx
Michael HricikENG 162This assignment will be about 2-3 double-sp.docx
ARIV4
 
MS Project - Lesson #2 - Managing Project ResourcesObjectives - .docx
MS Project - Lesson #2 - Managing Project ResourcesObjectives - .docxMS Project - Lesson #2 - Managing Project ResourcesObjectives - .docx
MS Project - Lesson #2 - Managing Project ResourcesObjectives - .docx
rosemarybdodson23141
 
Setting up resources
Setting up resourcesSetting up resources
Setting up resources
ahmed hamza
 
Setting up resources
Setting up resourcesSetting up resources
Setting up resources
ahmed hamza
 

Similar to 04 Assigning Resources to Tasks (20)

Sheet1Points0ENGL510 Grading Rubric Group .docx
Sheet1Points0ENGL510 Grading Rubric                        Group .docxSheet1Points0ENGL510 Grading Rubric                        Group .docx
Sheet1Points0ENGL510 Grading Rubric Group .docx
 
08 Fine-Tuning Resource Details
08 Fine-Tuning Resource Details08 Fine-Tuning Resource Details
08 Fine-Tuning Resource Details
 
Ppsi pertemuan-3
Ppsi pertemuan-3Ppsi pertemuan-3
Ppsi pertemuan-3
 
Ms project tutorial
Ms project tutorialMs project tutorial
Ms project tutorial
 
Yom Institute Presentation project management course
Yom Institute Presentation project management courseYom Institute Presentation project management course
Yom Institute Presentation project management course
 
Creating events starttofinish
Creating events starttofinishCreating events starttofinish
Creating events starttofinish
 
Project Management Quick Reference Guide
Project Management Quick Reference GuideProject Management Quick Reference Guide
Project Management Quick Reference Guide
 
Project Management Quick Reference Guide For Microsoft Project 2007
Project Management Quick Reference Guide For Microsoft Project 2007Project Management Quick Reference Guide For Microsoft Project 2007
Project Management Quick Reference Guide For Microsoft Project 2007
 
MS Project Guide.pdf
MS Project Guide.pdfMS Project Guide.pdf
MS Project Guide.pdf
 
Project NameCommunication PlanOverviewEffective and .docx
Project NameCommunication PlanOverviewEffective and .docxProject NameCommunication PlanOverviewEffective and .docx
Project NameCommunication PlanOverviewEffective and .docx
 
Iaq paper
Iaq paperIaq paper
Iaq paper
 
Lab report watson
Lab report watsonLab report watson
Lab report watson
 
BUS407 Week 3 Scenario Script Performance ModelSlide #SceneI.docx
BUS407 Week 3 Scenario Script Performance ModelSlide #SceneI.docxBUS407 Week 3 Scenario Script Performance ModelSlide #SceneI.docx
BUS407 Week 3 Scenario Script Performance ModelSlide #SceneI.docx
 
Project Management Quick Reference Guide for Microsoft Project 2007
Project Management Quick Reference Guide for Microsoft Project 2007Project Management Quick Reference Guide for Microsoft Project 2007
Project Management Quick Reference Guide for Microsoft Project 2007
 
3. Problem Analysis
3. Problem Analysis3. Problem Analysis
3. Problem Analysis
 
BUS 611 MART Inspiring Innovation--bus611mart.com
 BUS 611 MART Inspiring Innovation--bus611mart.com BUS 611 MART Inspiring Innovation--bus611mart.com
BUS 611 MART Inspiring Innovation--bus611mart.com
 
Michael HricikENG 162This assignment will be about 2-3 double-sp.docx
Michael HricikENG 162This assignment will be about 2-3 double-sp.docxMichael HricikENG 162This assignment will be about 2-3 double-sp.docx
Michael HricikENG 162This assignment will be about 2-3 double-sp.docx
 
MS Project - Lesson #2 - Managing Project ResourcesObjectives - .docx
MS Project - Lesson #2 - Managing Project ResourcesObjectives - .docxMS Project - Lesson #2 - Managing Project ResourcesObjectives - .docx
MS Project - Lesson #2 - Managing Project ResourcesObjectives - .docx
 
Setting up resources
Setting up resourcesSetting up resources
Setting up resources
 
Setting up resources
Setting up resourcesSetting up resources
Setting up resources
 

04 Assigning Resources to Tasks

  • 1. Soe Naing Win Email: snw1975@gmail.com
  • 2. In this chapter, you will learn how to: Assign work resources to tasks. Control how Project schedules additional resource assignments. Assign cost resources to tasks.
  • 3. Open exercise file, and check Project Information Note the current duration of 41 days and zero cost. After you assign work and cost resources, you’ll check these values again.
  • 4. Resource tab, Assignments group, Assign Resources.
  • 5. Task Name column, click the name of task 2, Assign launch team members. Resource Name column in the Assign Resources dialog box, click Carole Poland, and then click Assign.
  • 6. Task Name column, click the name of task 3, Complete author questionnaire. the Resource Name column in the Assign Resources dialog box, click Toni Poe, and then click Assign.
  • 7. Next, you’ll take a closer look at the details of task 3. You’ll use a handy view called the Task Form. View tab, in the Split View group, click Details.
  • 8. Next you’ll change the displayed details. Click anywhere in the Task Form and then, on the Format tab, in the Details group, click Work.
  • 9. Using the Assign Resources dialog box, assign the following resources to tasks
  • 10. Note the Duration, Units, and Work values in the Task Form
  • 11. Next, you will assign two resources to a single task Task Name column, click the name of task 8, Kickoff book launch meeting. In the Assign Resources dialog box, select the names of Sharon Salavaria and Toby Nixon, and then click Assign .
  • 12. To conclude this exercise, you’ll use a different means of assigning resources In the Gantt Chart view, drag the vertical divider bar to the right until the Resource Names column is visible. Click in the Resource Names column for task 9, Plan author’s travel itinerary, and then click the arrow that appears.
  • 13. In the list of resource names, click the check boxes for Jane Dow and Zac Woodall, and then press the Enter key.
  • 14. Click in the Resource Names column for task 10, Channel Sales prep, and then click the arrow that appears. In the list of resource names that appears, check Zac Woodall and then press the Enter key.
  • 15. Click in the Resource Names column for task 10, Channel Sales prep, and then click the arrow that appears. In the list of resource names that appears, check Zac Woodall and then press the Enter key.
  • 16.
  • 17. The Scheduling Formula: Duration, Units, and Work After you create a task, but before you assign a resource to it, the task has duration but no work associated with it. Why no work? Work represents the amount of effort a resource or resources will spend to complete a task. For example, if you have one person working full time, the amount of time measured as work is the same as the amount of time measured as duration. In general, the amount of work will match the duration unless you assign more than one resource to a task or the one resource you assign is not working full time. Project calculates work using what is sometimes called the scheduling formula: Duration × Units = Work
  • 18. The scheduling formula for task looks like this: 40 hours (same as one week) task duration × 100% assignment units = 40 hours of work In other words, with Resource assigned to task at 100% units, the task should require 40 hours of work. Here’s a more complex example. You assigned two resources, Jane Dow and Zac Woodall, to task 9, each at 100% assignment units. The scheduling formula for task 9 looks like this: 24 hours (same as three days) task duration × 200% assignment units = 48 hours of work The 48 hours of work is the sum of Jane’s 24 hours of work plus Zac’s 24 hours of work. In other words, as currently scheduled, both resources will work full time on the task in parallel for its three-day duration
  • 19. Exercise: adjust resource assignments on tasks and tell Project how it should adjust the tasks. In the Gantt Chart view, click the name of task 5, Design and order marketing material. Currently, Toby is assigned to this task. A quick check of the scheduling formula looks like this: 80 hours (the same as 10 days, or two weeks) task duration × 100% of Toby’s assignment units = 80 hours of work Toby needs some help with this task, so you’ll add a resource.
  • 20. In the Resource Name column in the Assign Resources dialog box, click Zac Woodall, and then click Assign .
  • 21. Click the name of task 5, and then click the Actions button that appears just to the left of the task name.

Editor's Notes

  1. On the Resource tab, in the Assignments group, click Assign Resources. The Assign Resources dialog box appears
  2. On the Resource tab, in the Assignments group, click Assign Resources. The Assign Resources dialog box appears
  3. On the View tab, in the Split View group, click Details
  4. On the View tab, in the Split View group, click Details
  5. If you completed Chapter 3, you may recognize that the Task Form is similar to the Resource Form but shows different details. In this type of split view, the details about the selected item in the upper view (a task, in this case) appear in the lower view, similar to the Resource Form. The Task Form displays one of several details
  6. Now, in the Task Form, you can see the essential scheduling values for this task: 1 week duration, 40 hours of work, and 100% assignment units. Because the Task Form is a handy way to see a task’s duration, units, and work values, you’ll leave it displayed for now.
  7. Let’s look at a specific example and find these values in the Task Form. The duration of task 3 is one week, or five working days. For our book launch project, five days equals 40 hours. When you assigned Toni Poe to task 3, Project applied 100 percent of Toni’s working time to this task. The scheduling formula for task 3 looks like this: 40 hours (same as one week) task duration × 100% assignment units = 40 hours of work In other words, with Toni assigned to task 3 at 100% units, the task should require 40 hours of work. Here’s a more complex example. You assigned two resources, Jane Dow and Zac Woodall, to task 9, each at 100% assignment units. The scheduling formula for task 9 looks like this: 24 hours (same as three days) task duration × 200% assignment units = 48 hours of work The 48 hours of work is the sum of Jane’s 24 hours of work plus Zac’s 24 hours of work. In other words, as currently scheduled, both resources will work full time on the task in parallel for its three-day duration
  8. Let’s look at a specific example and find these values in the Task Form. The duration of task 3 is one week, or five working days. For our book launch project, five days equals 40 hours. When you assigned Toni Poe to task 3, Project applied 100 percent of Toni’s working time to this task. The scheduling formula for task 3 looks like this: 40 hours (same as one week) task duration × 100% assignment units = 40 hours of work In other words, with Toni assigned to task 3 at 100% units, the task should require 40 hours of work. Here’s a more complex example. You assigned two resources, Jane Dow and Zac Woodall, to task 9, each at 100% assignment units. The scheduling formula for task 9 looks like this: 24 hours (same as three days) task duration × 200% assignment units = 48 hours of work The 48 hours of work is the sum of Jane’s 24 hours of work plus Zac’s 24 hours of work. In other words, as currently scheduled, both resources will work full time on the task in parallel for its three-day duration
  9. In the Resource Name column in the Assign Resources dialog box, click any resource, and then click Assign.
  10. Zac is added to the task and Project updates the scheduling formula values: 80 hours (the same as 10 days, or two weeks) task duration × 200% (that is, the sum of Toby’s and Zac’s assignment units) = 160 hours work
  11. Next, you will use a feature called the Actions list to control how Project schedules the work on a task when adding or removing resources. Note the small triangle in the upper-left corner of the name of task 5. This is a graphical indicator that an action is now available. Until you perform another action, you can use the Actions list to choose how you want Project to handle the additional resource assignment