MS Project
DEPARTMENT OF CIVIL ENGINEERING
CONSTRUCTION PROJECT MANAGEMENT
PARUL UNIVERSITY
VADODARA
AKSHAY AGRAWAL (170305216001)
AKSHAY AGRAWAL 2
Outline
1. MS Project Intro
2. Calendar
3. Project Summary
4. Network Diagram
5. WBS
6. Resources
7. Filter and Grouping
8. Customization
9. Constraint
10. Recurring Task
11. Resource Analysis and Levelling
12. Tracking
13. Earned Value Analysis
14. Reports
MS Project
Introduction
First, let's look
at the opening
screen so that
we can become
familiar with its
layout and
terminology,
how to create a
new file in
MSP?
AKSHAY AGRAWAL 3
Landing Page
 The Gantt Chart :
The Gantt chart is a
combination of the entry
sheet and the bar chart.
This is the main working
area of project.
 Entry Table :
It contains column like
indicator field, task
mode, Task name,
Duration, Start, Finish
etc.
There is also an option
for insert column
AKSHAY AGRAWAL 4
SelectAuto-
schedule Mode
Also you can do by
alternative
 Select column of
task mode
 Go to task
 Select auto schedule
AKSHAY AGRAWAL 5
Introduction to Calendar
CALENDAR
Base
Calendar
Standard
Night Shift
24 Hours
Based on
usage
Project
Calendar
Task
Calendar
Resource
Calendar
AKSHAY AGRAWAL 6
 Standard Calendar : Monday to Friday from 8:00 A.M. to 5:00
P.M. With one hour break(12:00 P.M. to 1:00P.M. )
 24 hour Calendar : It has no nonworking time. Its working time
is 12:00 A.M. to 12A.M. ,it schedules 24 hours a day, 7 days a
week.
 Night Shift : It covers graveyard shift schedule of Monday night
through Saturday morning, from 11PM. To 8AM. , with one hour
break (3:00 AM. to 4:00 AM.)
How to create a
Project Calendar ?
 Go to Project
 Click on Change
working time
 Open window as
shown on screen
 Click on create a
new calendar
 Give name of
calendar and Ok.
AKSHAY AGRAWAL 7
To be cont.…..
 Go to work weeks
 Click on Details
AKSHAY AGRAWAL 8
To be cont.…..
 Select Working days
AKSHAY AGRAWAL 9
To be cont.…..
 Click on “Set days to
this specific working
time”
AKSHAY AGRAWAL 10
To be cont.…..
 Select Non-working
days
 Then Click on “set
days to nonworking
time”
 Click on OK
AKSHAY AGRAWAL 11
To be cont.…..
If you want to set
holidays like republic
day, independence day,
holi, Diwali etc. ,
 Click on “Exception”
 Select day from
Calendar ( Exa. There
is Mahashivratri on
14th of February
which is selected
from calendar)
 Give description
 For reoccurrence of
holiday click on
“Details”
AKSHAY AGRAWAL 12
To be cont.…..
 Add one more
holiday for better
understanding.
AKSHAY AGRAWAL 13
To be cont.…..
 Specify work or non
work
 If work is ongoing
on holiday then click
0n working day and
Enter time
 Give reoccurrence
pattern if it comes on
particular date or any
day of month
 Give range of
occurrence as per
project span
 Ok
AKSHAY AGRAWAL 14
To be cont.…..
 Click on “Option”
AKSHAY AGRAWAL 15
To be cont.…..
 Click on “Schedule”
 Enter details like
start time, end time,
hours per day, per
week, per month etc.
 After filling all
details click on OK
AKSHAY AGRAWAL 16
To assign Project
Calendar
 Go to Project
 Click on Project
Information
AKSHAY AGRAWAL 17
To be cont.…..
 Check Start date and
time
 Assign Project
Calendar
 OK
AKSHAY AGRAWAL 18
To assign Project
Calendar Gantt
Chart
 Right click on Gantt
Chart
 Click on “Timescale”
AKSHAY AGRAWAL 19
To be cont.…..
 Select Non-Working
time
AKSHAY AGRAWAL 20
To be cont.…..
 Select colour of
nonworking time
 Assign “Project
Calendar”
 OK
AKSHAY AGRAWAL 21
Final View after
assigning Project
Calendar
AKSHAY AGRAWAL 22
Enter Activity
 Enter activity step by
step
 Enter duration of
activity
AKSHAY AGRAWAL 23
Relation-ship between Activities
Finish to Start
(FS)
Start to Start
(SS)
Finish to
Finish (FF)
Start to Finish
(SF)
AKSHAY AGRAWAL 24
Enter Relationship
 Enter Predecessor as
per activity.
 Observe the Gantt
chart to understand
relationship between
activity.
AKSHAY AGRAWAL 25
Project Summary
 Go to “Format”.
 Click on “Critical
Task”.
 Red Strip shows
critical activity.
 Click on “Project
Summary Task”.
 We can Know total
duration of Project.
AKSHAY AGRAWAL 26
Network
Diagram
 Go to “view”.
 Click on “Network
Diagram”.
 Each node contains
task name, duration,
task id, start date,
finish date, and if
assigned, the
resources
AKSHAY AGRAWAL 27
Work Breakdown
Structure
 WBS is called as
organized method of
dividing a activity
into sub activity.
 To create “WBS”
 Go to “Task”
 Select Sub-activities
for main activity
 Click on “Indent”
AKSHAY AGRAWAL 28
To be cont.…..
 To Show WBS
default Code,
 Right click on Entry
level on Entry Sheet
Top
 Insert a Column
”WBS”.
AKSHAY AGRAWAL 29
How to Define
Custom WBS
 Go to Project.
 Drop down WBS.
 Define Code.
 Give Sequence,
Length, Separator, as
per requirement
 After that, Go to
WBS
 Renumber to Entire
Project
AKSHAY AGRAWAL 30
How to add
Resources?
 Go to “View”.
 Click on “Resource
Sheet”
 Add Resources.
 Add maximum
availability of
resource.
 Add rate per hr or
day.
AKSHAY AGRAWAL 32
How to assign
resource to
activities?
 Go to Gantt-chart.
 Right click on
activity
 Click on “Assign
Resource”.
AKSHAY AGRAWAL 33
To be cont.…..
 Add resource as per
availability.
AKSHAY AGRAWAL 34
Cost after
assigning
Resources
 Assign all resources to
all activities.
 Insert a column of
“cost”.
 Gantt-chart shows all
assigned resources.
 Red mark in first
column shows over
allocation.
AKSHAY AGRAWAL 35
Filter & Grouping
Filter helps to focus on specific aspects of project.
There are two types of Filter: 1. Task Filter
2. Resource Filter
To apply filter an hide all other information, follow this step:
Go to view > Data Group > Click on Filter button >Choose the filter you want from Menu > Ok
AKSHAY AGRAWAL 36
Filter by Critical
Task
All critical activities
shown on screen.
AKSHAY AGRAWAL 37
Group by
Resources
AKSHAY AGRAWAL 38
All types of Filter
and Grouping
 If you want to create
a filter or group by
customize click on
New filter or New
Group.
AKSHAY AGRAWAL 39
Cost greater than
3000
 Click on More Filter
 Select cost greater
than…..
 Enter value 3000
 Then see result.
AKSHAY AGRAWAL 40
Customisation
You can set up a custom field and provide the information on any sheet associated with a task
oriented view of project.
1. Creating a custom field
2. Using a custom field
AKSHAY AGRAWAL 41
Creating a
custom field
 Go to Project.
 Click on “Custom
Field”.
 Rename text 1 with
Responsibility.
 Click on Look up
Table.
 Add some values
with description.
 Click on Import look
up table.
 Select
project1(current)
 Ok > Ok
AKSHAY AGRAWAL 42
Using a custom
field
 Add new column of
Responsibility.
 Assign responsibility
as per Task.
AKSHAY AGRAWAL 43
Constraints
Flexible type
As soon As possible(ASAP)
As late As Possible(ALAP)
AKSHAY AGRAWAL 44
Semi flexible type
Start No Earlier than
Start No Late than
Finish No Earlier than
Finish No Late than
Inflexible type
Must Start On
Must Finish On
How to Give
Constraint?
 Select activity >
Right click >
Information >
Advanced in
dialogue box
 You can give
Constraint as your
requirement.
AKSHAY AGRAWAL 45
Example
Activity 6
Constarint : Start No
Earlier Than
Date : 27th February
OK
It display as the second
Picture shown in slide.
AKSHAY AGRAWAL 46
Recurring Task
A task that Repeat at certain interval.
You can create a recurring task that repeats for a fixed no of times or that ends by a specific
date.
Examples: Weekly staff meeting
Quarterly report
Monthly Safety meeting
Monthly budget review
Inspection
AKSHAY AGRAWAL 47
Exa: Recurring of
Safety Inspection
for Excavation
 Select activity below
whom you want to
give Recurring task
 Go to Task Toolbar.
 Dropdown Task >
Recurring Task
 One Dialogue box
will open
 Give Task Name
 Give duration
 Select Recurrence
pattern
 Give Range
 OK
AKSHAY AGRAWAL 48
AKSHAY AGRAWAL 49
Resource Analysis and Levelling
Once resource are assigned for each task in project, it is necessary to check whether there is any
over allocated resource.
The over allocation is indicated in an indicator field in Gantt table and Resource Sheet, it is
also indicated in
Task Usage
Resource Usage
Team Planner
Resource graph
Resource Sheet
AKSHAY AGRAWAL 50
Gantt chart View
Over allocation
Indicators
AKSHAY AGRAWAL 51
Resource Sheet
View
Over allocated
Resources in Red Colour
AKSHAY AGRAWAL 52
Task Usage View
 Go to “View”
 Click on “Task
Usage”
Advantage
 Main Purpose is to
show the resources
assigned to each
Task
 It helps in organise
resources by task,
calculate work effort
and cost by task
AKSHAY AGRAWAL 53
Resource Usage
View
 Go to “View”
 Click on “Resource
Usage”
Advantage
 To check Over-
allocation Problem
 Calculate no. of Hours
of Each Resource
 Calculate the time of
additional work is
assigned to particular
resource
AKSHAY AGRAWAL 54
Team Planner
View
 Identify of Over-
allocation is become
easy.
AKSHAY AGRAWAL 55
Resource Graph
View
 View > Other View>
Resource Graph
 It clearly shows over
allocation.
 Easy to identify the
Problem in
Graphical
Representation
 It shows how a
resource used
 Note: It shows
information of only
one resource at a
time.
 Click the scroll
arrow that appear
below left pane of
this window
AKSHAY AGRAWAL 56
Resource Form
View
It shows work, cost,
schedule etc, aspects of
particular resource.
AKSHAY AGRAWAL 57
Based on Work Based on Cost
Resource Levelling
Techniques of Resource Levelling
Automatic
By Splitting
By Delaying
Manual
Stretching
Crunching
AKSHAY AGRAWAL 58
Automatic
Levelling
 Go to Resource
 Click on Levelling
Option
 Select Automatic
 Level Entire Project
 Level All
 OK
AKSHAY AGRAWAL 59
Manual Levelling
 Manual Levelling
can be carried out
from
 resource usage
or
 resource sheets
or
Resource Graphs
Note : We can Also
levelling by Split the
Task, Delay the Task,
Overtime in Resource
Form.
AKSHAY AGRAWAL 60
Ex: Manual Levelling By Resource Graph
Tracking
 Tracking is the process of collecting, entering and analysing of actual project performance
values, such as work on tasks and actual durations,
 Tracking is the second major phase of Project Management.
 Tracking means Recording the project details such as what work was done by whom, when the
8work was done and what it cost . These details are called as actual.
 Estimates v/s Actuals
 Baseline : It is snapshot of Project that you take when you complete planning phase or some
critical phase. Base line is a set of data saved in the same file where you track actual progress
data.
 Project enables you to save up to 11 baseline and equal no of interim plans during project.
AKSHAY AGRAWAL 61
Create Baseline
 Go to Project
 Dropdown Set
Baseline
 Tick on Baseline or
Interim Baseline
 Tick on Entire
Project > OK
Note: Interim Plan is
Similar as a Baseline
But it save only start
and finish date of
activity
AKSHAY AGRAWAL 62
To Show
Baseline in Gantt
Chart
 Right click on Gantt
Chart
 Click on Show/Hide
Bar-style
 Base Line
 Select Baseline
AKSHAY AGRAWAL 63
View Before Save the Baseline View After Save the Baseline
Updating Task and Actual Performance
Using Variety of techniques, you can record actual information for a project by filling in the
following field for each task and that tracks the progress of your project.
Actual start date | Actual Finish date | Actual Duration | Remaining Duration | percentage
Complete
Entering Task’s Completion Percentage
AKSHAY AGRAWAL 64
To Track or
Update Task
 Go to Project
 Update Project
 Give Status Date
 Tick on 0-100%
Complete
 Entire Project
 OK
AKSHAY AGRAWAL 65
To show Status
Date on Gantt
Chart
 Right Click on Gantt
Chart
 Select Gridline
 Select Status Date
 Give Type and
Colour
 OK
AKSHAY AGRAWAL 66
Status Line
To Show %
Complete
 Right click on Data
Entry Sheet.
 Insert a Column
 %complete
 %work complete
 Physical %Work
Complete
AKSHAY AGRAWAL 67
Based on
Duration
Based on
Work
Based on
Actual
Site
Condition
Tracking Table
 Go to View
 Dropdown Table
 Select Tracking
AKSHAY AGRAWAL 68
Tracking Table
Tracking Gantt
Chart
 Go to Task
 Dropdown Gantt
chart
 Select Tracking
Gantt Chart
AKSHAY AGRAWAL 69
Tracking Gantt Chart
Actual Site
Condition
 Select Activity
 Go to Task
 Dropdown Mark on
Track
 Update Task
 Either change
%complete OR
change duration/date
 OK
AKSHAY AGRAWAL 70
Comparison after
updating
AKSHAY AGRAWAL 71
Before Update
After Update
Earned Value Analysis
BCWS - Budgeted Cost Work Schedule (Plan Value)
BCWP - Budgeted Cost Work Performed (Earned Value)
ACWP – Actual Cost Work Performed (Actual Cost)
Cost Variance = BCWP – ACWP Schedule Variance = BCWP - BCWS
CV% = CV / BCWP SV% = SV / BCWS
CPI = BCWP / ACWP SPI = BCWP / BCWS
Where , CPI=Cost Performance Index Where, SPI = Schedule Performance Index
AKSHAY AGRAWAL 72
Results
Cost Performance
Index
Schedule
Performance Index
Less than 1 (<1) Over Budget Behind the Schedule
Equal to 1 (=1) No Profit No Loss On Schedule
Greater than 1 (>1) Under Budget Ahead of Schedule
AKSHAY AGRAWAL 73
Cost Variance Schedule Variance
Negative (<0) Over Budget Behind the Schedule
Equal to (=0) No Profit No Loss On Schedule
Positive (>0) Under Budget Ahead of Schedule
To be cont….
Estimate At Completion
EAC = AC + (BAC – EV)/CPI
Estimated Time at Completion = Original Time at Completion / SPI
AKSHAY AGRAWAL 74
Earned Value
Table
 Go to view > Table >
more table >Earned
Value
 Excavation is
completed 12%
instead of 33% so
there is schedule
variance which is
negative and shows
task behind the
schedule.
AKSHAY AGRAWAL 75
Reports
Select Report into Main Status bar >
AKSHAY AGRAWAL 76
AKSHAY AGRAWAL 77
AKSHAY AGRAWAL 78
AKSHAY AGRAWAL 79
AKSHAY AGRAWAL 80
AKSHAY AGRAWAL 81
AKSHAY AGRAWAL 82
AKSHAY AGRAWAL 83
AKSHAY AGRAWAL 84
AKSHAY AGRAWAL 85

More Related Content

What's hot

Scheduling by using microsoft project 2013
Scheduling by using microsoft project 2013Scheduling by using microsoft project 2013
Scheduling by using microsoft project 2013Chetanraj M
 
MICROSOFT PROJECT TUTORIAL
MICROSOFT PROJECT TUTORIALMICROSOFT PROJECT TUTORIAL
MICROSOFT PROJECT TUTORIALVismay Shah
 
Introduction to MS project
Introduction to MS projectIntroduction to MS project
Introduction to MS projectSamir Paralikar
 
Primavera - Tutorial
Primavera - TutorialPrimavera - Tutorial
Primavera - TutorialRajeev Sharma
 
MS Project Presentation
MS Project PresentationMS Project Presentation
MS Project PresentationKhem Singh
 
Introduction to Microsoft Project 2010
Introduction to Microsoft Project 2010Introduction to Microsoft Project 2010
Introduction to Microsoft Project 2010Bhishma Bhatti
 
How to create S-Curve by MS Project 2013
How to create S-Curve by MS Project 2013How to create S-Curve by MS Project 2013
How to create S-Curve by MS Project 2013Ong-Art Sanpinit
 
PRIMAVERA P6 manual.pptx
PRIMAVERA P6 manual.pptxPRIMAVERA P6 manual.pptx
PRIMAVERA P6 manual.pptxGracePentinio1
 
Ms project 2010 tutorial 1
Ms project 2010 tutorial   1Ms project 2010 tutorial   1
Ms project 2010 tutorial 1learningquotient
 
Introduction To Primavera (P6)
Introduction To Primavera (P6)Introduction To Primavera (P6)
Introduction To Primavera (P6)Sandip Kumar Verma
 
Microsoft Project - MSP | 2013-2016
Microsoft Project - MSP | 2013-2016Microsoft Project - MSP | 2013-2016
Microsoft Project - MSP | 2013-2016Rajeev Sharma
 
Primavara
PrimavaraPrimavara
Primavaradanabl
 
MICROSOFT PROJECT
MICROSOFT PROJECTMICROSOFT PROJECT
MICROSOFT PROJECTSmit Patel
 
Primavera presentation
Primavera presentationPrimavera presentation
Primavera presentationNithin Dev
 
How to create a work breakdown structure (wbs)
How to create a work breakdown structure (wbs)How to create a work breakdown structure (wbs)
How to create a work breakdown structure (wbs)Insaf Ali Soomro PMP
 

What's hot (20)

MS Project 2010 Training
MS Project 2010 TrainingMS Project 2010 Training
MS Project 2010 Training
 
Scheduling by using microsoft project 2013
Scheduling by using microsoft project 2013Scheduling by using microsoft project 2013
Scheduling by using microsoft project 2013
 
MICROSOFT PROJECT TUTORIAL
MICROSOFT PROJECT TUTORIALMICROSOFT PROJECT TUTORIAL
MICROSOFT PROJECT TUTORIAL
 
tcc primavera
tcc primaveratcc primavera
tcc primavera
 
Introduction to MS project
Introduction to MS projectIntroduction to MS project
Introduction to MS project
 
Ms project training ver 01
Ms project training ver 01Ms project training ver 01
Ms project training ver 01
 
Primavera - Tutorial
Primavera - TutorialPrimavera - Tutorial
Primavera - Tutorial
 
MS Project Presentation
MS Project PresentationMS Project Presentation
MS Project Presentation
 
Introduction to Microsoft Project 2010
Introduction to Microsoft Project 2010Introduction to Microsoft Project 2010
Introduction to Microsoft Project 2010
 
Microsoft Project
Microsoft ProjectMicrosoft Project
Microsoft Project
 
How to create S-Curve by MS Project 2013
How to create S-Curve by MS Project 2013How to create S-Curve by MS Project 2013
How to create S-Curve by MS Project 2013
 
PRIMAVERA P6 manual.pptx
PRIMAVERA P6 manual.pptxPRIMAVERA P6 manual.pptx
PRIMAVERA P6 manual.pptx
 
Ms project 2010 tutorial 1
Ms project 2010 tutorial   1Ms project 2010 tutorial   1
Ms project 2010 tutorial 1
 
Introduction To Primavera (P6)
Introduction To Primavera (P6)Introduction To Primavera (P6)
Introduction To Primavera (P6)
 
Microsoft Project - MSP | 2013-2016
Microsoft Project - MSP | 2013-2016Microsoft Project - MSP | 2013-2016
Microsoft Project - MSP | 2013-2016
 
Primavara
PrimavaraPrimavara
Primavara
 
MICROSOFT PROJECT
MICROSOFT PROJECTMICROSOFT PROJECT
MICROSOFT PROJECT
 
Primavera Training P6
Primavera Training P6Primavera Training P6
Primavera Training P6
 
Primavera presentation
Primavera presentationPrimavera presentation
Primavera presentation
 
How to create a work breakdown structure (wbs)
How to create a work breakdown structure (wbs)How to create a work breakdown structure (wbs)
How to create a work breakdown structure (wbs)
 

Similar to MS Project

MProjectTutorial.pdf
MProjectTutorial.pdfMProjectTutorial.pdf
MProjectTutorial.pdfdhansingh21
 
How to Create S Curve by MS Project 2013
How to Create S Curve by MS Project 2013How to Create S Curve by MS Project 2013
How to Create S Curve by MS Project 2013Ong-Art Sanpinit
 
EA261_2015_Exercises
EA261_2015_ExercisesEA261_2015_Exercises
EA261_2015_ExercisesLuc Vanrobays
 
Project Management Quick Reference Guide for Microsoft Project 2007
Project Management Quick Reference Guide for Microsoft Project 2007Project Management Quick Reference Guide for Microsoft Project 2007
Project Management Quick Reference Guide for Microsoft Project 2007Toney Sisk
 
IMPACT/myGrid Hackathon - Introduction to Taverna
IMPACT/myGrid Hackathon - Introduction to TavernaIMPACT/myGrid Hackathon - Introduction to Taverna
IMPACT/myGrid Hackathon - Introduction to TavernaIMPACT Centre of Competence
 
Ms project tutorial
Ms project tutorialMs project tutorial
Ms project tutorialRonald Oroya
 
sMs project tutorial_iit
sMs project tutorial_iitsMs project tutorial_iit
sMs project tutorial_iitKushal Patel
 
The olap tutorial 2012
The olap tutorial 2012The olap tutorial 2012
The olap tutorial 2012Amin Jalali
 
Project Management Quick Reference Guide For Microsoft Project 2007
Project Management Quick Reference Guide For Microsoft Project 2007Project Management Quick Reference Guide For Microsoft Project 2007
Project Management Quick Reference Guide For Microsoft Project 2007Toney Sisk
 
Project Web Access Quick Reference Guide For Team Members
Project Web Access Quick Reference Guide For Team MembersProject Web Access Quick Reference Guide For Team Members
Project Web Access Quick Reference Guide For Team MembersToney Sisk
 

Similar to MS Project (20)

MProjectTutorial.pdf
MProjectTutorial.pdfMProjectTutorial.pdf
MProjectTutorial.pdf
 
Primavera P6 Notes for Beginners
Primavera P6 Notes for Beginners Primavera P6 Notes for Beginners
Primavera P6 Notes for Beginners
 
MS Project Guide.pdf
MS Project Guide.pdfMS Project Guide.pdf
MS Project Guide.pdf
 
How to Create S Curve by MS Project 2013
How to Create S Curve by MS Project 2013How to Create S Curve by MS Project 2013
How to Create S Curve by MS Project 2013
 
Pras s curve final
Pras s curve finalPras s curve final
Pras s curve final
 
S Curves Made Easy With Primavera P6
S Curves Made Easy With Primavera P6S Curves Made Easy With Primavera P6
S Curves Made Easy With Primavera P6
 
Pras s curve final
Pras s curve finalPras s curve final
Pras s curve final
 
EA261_2015_Exercises
EA261_2015_ExercisesEA261_2015_Exercises
EA261_2015_Exercises
 
Dbi h315
Dbi h315Dbi h315
Dbi h315
 
Project Management Quick Reference Guide for Microsoft Project 2007
Project Management Quick Reference Guide for Microsoft Project 2007Project Management Quick Reference Guide for Microsoft Project 2007
Project Management Quick Reference Guide for Microsoft Project 2007
 
IMPACT/myGrid Hackathon - Introduction to Taverna
IMPACT/myGrid Hackathon - Introduction to TavernaIMPACT/myGrid Hackathon - Introduction to Taverna
IMPACT/myGrid Hackathon - Introduction to Taverna
 
Ms project tutorial
Ms project tutorialMs project tutorial
Ms project tutorial
 
sMs project tutorial_iit
sMs project tutorial_iitsMs project tutorial_iit
sMs project tutorial_iit
 
Omni plan 2-manual
Omni plan 2-manualOmni plan 2-manual
Omni plan 2-manual
 
The olap tutorial 2012
The olap tutorial 2012The olap tutorial 2012
The olap tutorial 2012
 
Project Management Quick Reference Guide
Project Management Quick Reference GuideProject Management Quick Reference Guide
Project Management Quick Reference Guide
 
Project Management Quick Reference Guide For Microsoft Project 2007
Project Management Quick Reference Guide For Microsoft Project 2007Project Management Quick Reference Guide For Microsoft Project 2007
Project Management Quick Reference Guide For Microsoft Project 2007
 
ssis lab
ssis labssis lab
ssis lab
 
Project Web Access Quick Reference Guide For Team Members
Project Web Access Quick Reference Guide For Team MembersProject Web Access Quick Reference Guide For Team Members
Project Web Access Quick Reference Guide For Team Members
 
B-Project Report-SSAS
B-Project Report-SSASB-Project Report-SSAS
B-Project Report-SSAS
 

Recently uploaded

(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...ranjana rawat
 
Call Girls Service Nagpur Tanvi Call 7001035870 Meet With Nagpur Escorts
Call Girls Service Nagpur Tanvi Call 7001035870 Meet With Nagpur EscortsCall Girls Service Nagpur Tanvi Call 7001035870 Meet With Nagpur Escorts
Call Girls Service Nagpur Tanvi Call 7001035870 Meet With Nagpur EscortsCall Girls in Nagpur High Profile
 
CCS335 _ Neural Networks and Deep Learning Laboratory_Lab Complete Record
CCS335 _ Neural Networks and Deep Learning Laboratory_Lab Complete RecordCCS335 _ Neural Networks and Deep Learning Laboratory_Lab Complete Record
CCS335 _ Neural Networks and Deep Learning Laboratory_Lab Complete RecordAsst.prof M.Gokilavani
 
UNIT - IV - Air Compressors and its Performance
UNIT - IV - Air Compressors and its PerformanceUNIT - IV - Air Compressors and its Performance
UNIT - IV - Air Compressors and its Performancesivaprakash250
 
result management system report for college project
result management system report for college projectresult management system report for college project
result management system report for college projectTonystark477637
 
University management System project report..pdf
University management System project report..pdfUniversity management System project report..pdf
University management System project report..pdfKamal Acharya
 
UNIT-II FMM-Flow Through Circular Conduits
UNIT-II FMM-Flow Through Circular ConduitsUNIT-II FMM-Flow Through Circular Conduits
UNIT-II FMM-Flow Through Circular Conduitsrknatarajan
 
Russian Call Girls in Nagpur Grishma Call 7001035870 Meet With Nagpur Escorts
Russian Call Girls in Nagpur Grishma Call 7001035870 Meet With Nagpur EscortsRussian Call Girls in Nagpur Grishma Call 7001035870 Meet With Nagpur Escorts
Russian Call Girls in Nagpur Grishma Call 7001035870 Meet With Nagpur EscortsCall Girls in Nagpur High Profile
 
Call for Papers - Educational Administration: Theory and Practice, E-ISSN: 21...
Call for Papers - Educational Administration: Theory and Practice, E-ISSN: 21...Call for Papers - Educational Administration: Theory and Practice, E-ISSN: 21...
Call for Papers - Educational Administration: Theory and Practice, E-ISSN: 21...Christo Ananth
 
Extrusion Processes and Their Limitations
Extrusion Processes and Their LimitationsExtrusion Processes and Their Limitations
Extrusion Processes and Their Limitations120cr0395
 
(SHREYA) Chakan Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Esc...
(SHREYA) Chakan Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Esc...(SHREYA) Chakan Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Esc...
(SHREYA) Chakan Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Esc...ranjana rawat
 
Introduction to IEEE STANDARDS and its different types.pptx
Introduction to IEEE STANDARDS and its different types.pptxIntroduction to IEEE STANDARDS and its different types.pptx
Introduction to IEEE STANDARDS and its different types.pptxupamatechverse
 
High Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur EscortsHigh Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur EscortsCall Girls in Nagpur High Profile
 
Introduction and different types of Ethernet.pptx
Introduction and different types of Ethernet.pptxIntroduction and different types of Ethernet.pptx
Introduction and different types of Ethernet.pptxupamatechverse
 
Coefficient of Thermal Expansion and their Importance.pptx
Coefficient of Thermal Expansion and their Importance.pptxCoefficient of Thermal Expansion and their Importance.pptx
Coefficient of Thermal Expansion and their Importance.pptxAsutosh Ranjan
 
UNIT-III FMM. DIMENSIONAL ANALYSIS
UNIT-III FMM.        DIMENSIONAL ANALYSISUNIT-III FMM.        DIMENSIONAL ANALYSIS
UNIT-III FMM. DIMENSIONAL ANALYSISrknatarajan
 
UNIT-V FMM.HYDRAULIC TURBINE - Construction and working
UNIT-V FMM.HYDRAULIC TURBINE - Construction and workingUNIT-V FMM.HYDRAULIC TURBINE - Construction and working
UNIT-V FMM.HYDRAULIC TURBINE - Construction and workingrknatarajan
 
Introduction to Multiple Access Protocol.pptx
Introduction to Multiple Access Protocol.pptxIntroduction to Multiple Access Protocol.pptx
Introduction to Multiple Access Protocol.pptxupamatechverse
 
Call for Papers - African Journal of Biological Sciences, E-ISSN: 2663-2187, ...
Call for Papers - African Journal of Biological Sciences, E-ISSN: 2663-2187, ...Call for Papers - African Journal of Biological Sciences, E-ISSN: 2663-2187, ...
Call for Papers - African Journal of Biological Sciences, E-ISSN: 2663-2187, ...Christo Ananth
 

Recently uploaded (20)

(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
 
Call Girls Service Nagpur Tanvi Call 7001035870 Meet With Nagpur Escorts
Call Girls Service Nagpur Tanvi Call 7001035870 Meet With Nagpur EscortsCall Girls Service Nagpur Tanvi Call 7001035870 Meet With Nagpur Escorts
Call Girls Service Nagpur Tanvi Call 7001035870 Meet With Nagpur Escorts
 
(INDIRA) Call Girl Aurangabad Call Now 8617697112 Aurangabad Escorts 24x7
(INDIRA) Call Girl Aurangabad Call Now 8617697112 Aurangabad Escorts 24x7(INDIRA) Call Girl Aurangabad Call Now 8617697112 Aurangabad Escorts 24x7
(INDIRA) Call Girl Aurangabad Call Now 8617697112 Aurangabad Escorts 24x7
 
CCS335 _ Neural Networks and Deep Learning Laboratory_Lab Complete Record
CCS335 _ Neural Networks and Deep Learning Laboratory_Lab Complete RecordCCS335 _ Neural Networks and Deep Learning Laboratory_Lab Complete Record
CCS335 _ Neural Networks and Deep Learning Laboratory_Lab Complete Record
 
UNIT - IV - Air Compressors and its Performance
UNIT - IV - Air Compressors and its PerformanceUNIT - IV - Air Compressors and its Performance
UNIT - IV - Air Compressors and its Performance
 
result management system report for college project
result management system report for college projectresult management system report for college project
result management system report for college project
 
University management System project report..pdf
University management System project report..pdfUniversity management System project report..pdf
University management System project report..pdf
 
UNIT-II FMM-Flow Through Circular Conduits
UNIT-II FMM-Flow Through Circular ConduitsUNIT-II FMM-Flow Through Circular Conduits
UNIT-II FMM-Flow Through Circular Conduits
 
Russian Call Girls in Nagpur Grishma Call 7001035870 Meet With Nagpur Escorts
Russian Call Girls in Nagpur Grishma Call 7001035870 Meet With Nagpur EscortsRussian Call Girls in Nagpur Grishma Call 7001035870 Meet With Nagpur Escorts
Russian Call Girls in Nagpur Grishma Call 7001035870 Meet With Nagpur Escorts
 
Call for Papers - Educational Administration: Theory and Practice, E-ISSN: 21...
Call for Papers - Educational Administration: Theory and Practice, E-ISSN: 21...Call for Papers - Educational Administration: Theory and Practice, E-ISSN: 21...
Call for Papers - Educational Administration: Theory and Practice, E-ISSN: 21...
 
Extrusion Processes and Their Limitations
Extrusion Processes and Their LimitationsExtrusion Processes and Their Limitations
Extrusion Processes and Their Limitations
 
(SHREYA) Chakan Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Esc...
(SHREYA) Chakan Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Esc...(SHREYA) Chakan Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Esc...
(SHREYA) Chakan Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Esc...
 
Introduction to IEEE STANDARDS and its different types.pptx
Introduction to IEEE STANDARDS and its different types.pptxIntroduction to IEEE STANDARDS and its different types.pptx
Introduction to IEEE STANDARDS and its different types.pptx
 
High Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur EscortsHigh Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur Escorts
 
Introduction and different types of Ethernet.pptx
Introduction and different types of Ethernet.pptxIntroduction and different types of Ethernet.pptx
Introduction and different types of Ethernet.pptx
 
Coefficient of Thermal Expansion and their Importance.pptx
Coefficient of Thermal Expansion and their Importance.pptxCoefficient of Thermal Expansion and their Importance.pptx
Coefficient of Thermal Expansion and their Importance.pptx
 
UNIT-III FMM. DIMENSIONAL ANALYSIS
UNIT-III FMM.        DIMENSIONAL ANALYSISUNIT-III FMM.        DIMENSIONAL ANALYSIS
UNIT-III FMM. DIMENSIONAL ANALYSIS
 
UNIT-V FMM.HYDRAULIC TURBINE - Construction and working
UNIT-V FMM.HYDRAULIC TURBINE - Construction and workingUNIT-V FMM.HYDRAULIC TURBINE - Construction and working
UNIT-V FMM.HYDRAULIC TURBINE - Construction and working
 
Introduction to Multiple Access Protocol.pptx
Introduction to Multiple Access Protocol.pptxIntroduction to Multiple Access Protocol.pptx
Introduction to Multiple Access Protocol.pptx
 
Call for Papers - African Journal of Biological Sciences, E-ISSN: 2663-2187, ...
Call for Papers - African Journal of Biological Sciences, E-ISSN: 2663-2187, ...Call for Papers - African Journal of Biological Sciences, E-ISSN: 2663-2187, ...
Call for Papers - African Journal of Biological Sciences, E-ISSN: 2663-2187, ...
 

MS Project

  • 1. MS Project DEPARTMENT OF CIVIL ENGINEERING CONSTRUCTION PROJECT MANAGEMENT PARUL UNIVERSITY VADODARA AKSHAY AGRAWAL (170305216001)
  • 2. AKSHAY AGRAWAL 2 Outline 1. MS Project Intro 2. Calendar 3. Project Summary 4. Network Diagram 5. WBS 6. Resources 7. Filter and Grouping 8. Customization 9. Constraint 10. Recurring Task 11. Resource Analysis and Levelling 12. Tracking 13. Earned Value Analysis 14. Reports
  • 3. MS Project Introduction First, let's look at the opening screen so that we can become familiar with its layout and terminology, how to create a new file in MSP? AKSHAY AGRAWAL 3
  • 4. Landing Page  The Gantt Chart : The Gantt chart is a combination of the entry sheet and the bar chart. This is the main working area of project.  Entry Table : It contains column like indicator field, task mode, Task name, Duration, Start, Finish etc. There is also an option for insert column AKSHAY AGRAWAL 4
  • 5. SelectAuto- schedule Mode Also you can do by alternative  Select column of task mode  Go to task  Select auto schedule AKSHAY AGRAWAL 5
  • 6. Introduction to Calendar CALENDAR Base Calendar Standard Night Shift 24 Hours Based on usage Project Calendar Task Calendar Resource Calendar AKSHAY AGRAWAL 6  Standard Calendar : Monday to Friday from 8:00 A.M. to 5:00 P.M. With one hour break(12:00 P.M. to 1:00P.M. )  24 hour Calendar : It has no nonworking time. Its working time is 12:00 A.M. to 12A.M. ,it schedules 24 hours a day, 7 days a week.  Night Shift : It covers graveyard shift schedule of Monday night through Saturday morning, from 11PM. To 8AM. , with one hour break (3:00 AM. to 4:00 AM.)
  • 7. How to create a Project Calendar ?  Go to Project  Click on Change working time  Open window as shown on screen  Click on create a new calendar  Give name of calendar and Ok. AKSHAY AGRAWAL 7
  • 8. To be cont.…..  Go to work weeks  Click on Details AKSHAY AGRAWAL 8
  • 9. To be cont.…..  Select Working days AKSHAY AGRAWAL 9
  • 10. To be cont.…..  Click on “Set days to this specific working time” AKSHAY AGRAWAL 10
  • 11. To be cont.…..  Select Non-working days  Then Click on “set days to nonworking time”  Click on OK AKSHAY AGRAWAL 11
  • 12. To be cont.….. If you want to set holidays like republic day, independence day, holi, Diwali etc. ,  Click on “Exception”  Select day from Calendar ( Exa. There is Mahashivratri on 14th of February which is selected from calendar)  Give description  For reoccurrence of holiday click on “Details” AKSHAY AGRAWAL 12
  • 13. To be cont.…..  Add one more holiday for better understanding. AKSHAY AGRAWAL 13
  • 14. To be cont.…..  Specify work or non work  If work is ongoing on holiday then click 0n working day and Enter time  Give reoccurrence pattern if it comes on particular date or any day of month  Give range of occurrence as per project span  Ok AKSHAY AGRAWAL 14
  • 15. To be cont.…..  Click on “Option” AKSHAY AGRAWAL 15
  • 16. To be cont.…..  Click on “Schedule”  Enter details like start time, end time, hours per day, per week, per month etc.  After filling all details click on OK AKSHAY AGRAWAL 16
  • 17. To assign Project Calendar  Go to Project  Click on Project Information AKSHAY AGRAWAL 17
  • 18. To be cont.…..  Check Start date and time  Assign Project Calendar  OK AKSHAY AGRAWAL 18
  • 19. To assign Project Calendar Gantt Chart  Right click on Gantt Chart  Click on “Timescale” AKSHAY AGRAWAL 19
  • 20. To be cont.…..  Select Non-Working time AKSHAY AGRAWAL 20
  • 21. To be cont.…..  Select colour of nonworking time  Assign “Project Calendar”  OK AKSHAY AGRAWAL 21
  • 22. Final View after assigning Project Calendar AKSHAY AGRAWAL 22
  • 23. Enter Activity  Enter activity step by step  Enter duration of activity AKSHAY AGRAWAL 23
  • 24. Relation-ship between Activities Finish to Start (FS) Start to Start (SS) Finish to Finish (FF) Start to Finish (SF) AKSHAY AGRAWAL 24
  • 25. Enter Relationship  Enter Predecessor as per activity.  Observe the Gantt chart to understand relationship between activity. AKSHAY AGRAWAL 25
  • 26. Project Summary  Go to “Format”.  Click on “Critical Task”.  Red Strip shows critical activity.  Click on “Project Summary Task”.  We can Know total duration of Project. AKSHAY AGRAWAL 26
  • 27. Network Diagram  Go to “view”.  Click on “Network Diagram”.  Each node contains task name, duration, task id, start date, finish date, and if assigned, the resources AKSHAY AGRAWAL 27
  • 28. Work Breakdown Structure  WBS is called as organized method of dividing a activity into sub activity.  To create “WBS”  Go to “Task”  Select Sub-activities for main activity  Click on “Indent” AKSHAY AGRAWAL 28
  • 29. To be cont.…..  To Show WBS default Code,  Right click on Entry level on Entry Sheet Top  Insert a Column ”WBS”. AKSHAY AGRAWAL 29
  • 30. How to Define Custom WBS  Go to Project.  Drop down WBS.  Define Code.  Give Sequence, Length, Separator, as per requirement  After that, Go to WBS  Renumber to Entire Project AKSHAY AGRAWAL 30
  • 31.
  • 32. How to add Resources?  Go to “View”.  Click on “Resource Sheet”  Add Resources.  Add maximum availability of resource.  Add rate per hr or day. AKSHAY AGRAWAL 32
  • 33. How to assign resource to activities?  Go to Gantt-chart.  Right click on activity  Click on “Assign Resource”. AKSHAY AGRAWAL 33
  • 34. To be cont.…..  Add resource as per availability. AKSHAY AGRAWAL 34
  • 35. Cost after assigning Resources  Assign all resources to all activities.  Insert a column of “cost”.  Gantt-chart shows all assigned resources.  Red mark in first column shows over allocation. AKSHAY AGRAWAL 35
  • 36. Filter & Grouping Filter helps to focus on specific aspects of project. There are two types of Filter: 1. Task Filter 2. Resource Filter To apply filter an hide all other information, follow this step: Go to view > Data Group > Click on Filter button >Choose the filter you want from Menu > Ok AKSHAY AGRAWAL 36
  • 37. Filter by Critical Task All critical activities shown on screen. AKSHAY AGRAWAL 37
  • 39. All types of Filter and Grouping  If you want to create a filter or group by customize click on New filter or New Group. AKSHAY AGRAWAL 39
  • 40. Cost greater than 3000  Click on More Filter  Select cost greater than…..  Enter value 3000  Then see result. AKSHAY AGRAWAL 40
  • 41. Customisation You can set up a custom field and provide the information on any sheet associated with a task oriented view of project. 1. Creating a custom field 2. Using a custom field AKSHAY AGRAWAL 41
  • 42. Creating a custom field  Go to Project.  Click on “Custom Field”.  Rename text 1 with Responsibility.  Click on Look up Table.  Add some values with description.  Click on Import look up table.  Select project1(current)  Ok > Ok AKSHAY AGRAWAL 42
  • 43. Using a custom field  Add new column of Responsibility.  Assign responsibility as per Task. AKSHAY AGRAWAL 43
  • 44. Constraints Flexible type As soon As possible(ASAP) As late As Possible(ALAP) AKSHAY AGRAWAL 44 Semi flexible type Start No Earlier than Start No Late than Finish No Earlier than Finish No Late than Inflexible type Must Start On Must Finish On
  • 45. How to Give Constraint?  Select activity > Right click > Information > Advanced in dialogue box  You can give Constraint as your requirement. AKSHAY AGRAWAL 45
  • 46. Example Activity 6 Constarint : Start No Earlier Than Date : 27th February OK It display as the second Picture shown in slide. AKSHAY AGRAWAL 46
  • 47. Recurring Task A task that Repeat at certain interval. You can create a recurring task that repeats for a fixed no of times or that ends by a specific date. Examples: Weekly staff meeting Quarterly report Monthly Safety meeting Monthly budget review Inspection AKSHAY AGRAWAL 47
  • 48. Exa: Recurring of Safety Inspection for Excavation  Select activity below whom you want to give Recurring task  Go to Task Toolbar.  Dropdown Task > Recurring Task  One Dialogue box will open  Give Task Name  Give duration  Select Recurrence pattern  Give Range  OK AKSHAY AGRAWAL 48
  • 50. Resource Analysis and Levelling Once resource are assigned for each task in project, it is necessary to check whether there is any over allocated resource. The over allocation is indicated in an indicator field in Gantt table and Resource Sheet, it is also indicated in Task Usage Resource Usage Team Planner Resource graph Resource Sheet AKSHAY AGRAWAL 50
  • 51. Gantt chart View Over allocation Indicators AKSHAY AGRAWAL 51
  • 52. Resource Sheet View Over allocated Resources in Red Colour AKSHAY AGRAWAL 52
  • 53. Task Usage View  Go to “View”  Click on “Task Usage” Advantage  Main Purpose is to show the resources assigned to each Task  It helps in organise resources by task, calculate work effort and cost by task AKSHAY AGRAWAL 53
  • 54. Resource Usage View  Go to “View”  Click on “Resource Usage” Advantage  To check Over- allocation Problem  Calculate no. of Hours of Each Resource  Calculate the time of additional work is assigned to particular resource AKSHAY AGRAWAL 54
  • 55. Team Planner View  Identify of Over- allocation is become easy. AKSHAY AGRAWAL 55
  • 56. Resource Graph View  View > Other View> Resource Graph  It clearly shows over allocation.  Easy to identify the Problem in Graphical Representation  It shows how a resource used  Note: It shows information of only one resource at a time.  Click the scroll arrow that appear below left pane of this window AKSHAY AGRAWAL 56
  • 57. Resource Form View It shows work, cost, schedule etc, aspects of particular resource. AKSHAY AGRAWAL 57 Based on Work Based on Cost
  • 58. Resource Levelling Techniques of Resource Levelling Automatic By Splitting By Delaying Manual Stretching Crunching AKSHAY AGRAWAL 58
  • 59. Automatic Levelling  Go to Resource  Click on Levelling Option  Select Automatic  Level Entire Project  Level All  OK AKSHAY AGRAWAL 59
  • 60. Manual Levelling  Manual Levelling can be carried out from  resource usage or  resource sheets or Resource Graphs Note : We can Also levelling by Split the Task, Delay the Task, Overtime in Resource Form. AKSHAY AGRAWAL 60 Ex: Manual Levelling By Resource Graph
  • 61. Tracking  Tracking is the process of collecting, entering and analysing of actual project performance values, such as work on tasks and actual durations,  Tracking is the second major phase of Project Management.  Tracking means Recording the project details such as what work was done by whom, when the 8work was done and what it cost . These details are called as actual.  Estimates v/s Actuals  Baseline : It is snapshot of Project that you take when you complete planning phase or some critical phase. Base line is a set of data saved in the same file where you track actual progress data.  Project enables you to save up to 11 baseline and equal no of interim plans during project. AKSHAY AGRAWAL 61
  • 62. Create Baseline  Go to Project  Dropdown Set Baseline  Tick on Baseline or Interim Baseline  Tick on Entire Project > OK Note: Interim Plan is Similar as a Baseline But it save only start and finish date of activity AKSHAY AGRAWAL 62
  • 63. To Show Baseline in Gantt Chart  Right click on Gantt Chart  Click on Show/Hide Bar-style  Base Line  Select Baseline AKSHAY AGRAWAL 63 View Before Save the Baseline View After Save the Baseline
  • 64. Updating Task and Actual Performance Using Variety of techniques, you can record actual information for a project by filling in the following field for each task and that tracks the progress of your project. Actual start date | Actual Finish date | Actual Duration | Remaining Duration | percentage Complete Entering Task’s Completion Percentage AKSHAY AGRAWAL 64
  • 65. To Track or Update Task  Go to Project  Update Project  Give Status Date  Tick on 0-100% Complete  Entire Project  OK AKSHAY AGRAWAL 65
  • 66. To show Status Date on Gantt Chart  Right Click on Gantt Chart  Select Gridline  Select Status Date  Give Type and Colour  OK AKSHAY AGRAWAL 66 Status Line
  • 67. To Show % Complete  Right click on Data Entry Sheet.  Insert a Column  %complete  %work complete  Physical %Work Complete AKSHAY AGRAWAL 67 Based on Duration Based on Work Based on Actual Site Condition
  • 68. Tracking Table  Go to View  Dropdown Table  Select Tracking AKSHAY AGRAWAL 68 Tracking Table
  • 69. Tracking Gantt Chart  Go to Task  Dropdown Gantt chart  Select Tracking Gantt Chart AKSHAY AGRAWAL 69 Tracking Gantt Chart
  • 70. Actual Site Condition  Select Activity  Go to Task  Dropdown Mark on Track  Update Task  Either change %complete OR change duration/date  OK AKSHAY AGRAWAL 70
  • 71. Comparison after updating AKSHAY AGRAWAL 71 Before Update After Update
  • 72. Earned Value Analysis BCWS - Budgeted Cost Work Schedule (Plan Value) BCWP - Budgeted Cost Work Performed (Earned Value) ACWP – Actual Cost Work Performed (Actual Cost) Cost Variance = BCWP – ACWP Schedule Variance = BCWP - BCWS CV% = CV / BCWP SV% = SV / BCWS CPI = BCWP / ACWP SPI = BCWP / BCWS Where , CPI=Cost Performance Index Where, SPI = Schedule Performance Index AKSHAY AGRAWAL 72
  • 73. Results Cost Performance Index Schedule Performance Index Less than 1 (<1) Over Budget Behind the Schedule Equal to 1 (=1) No Profit No Loss On Schedule Greater than 1 (>1) Under Budget Ahead of Schedule AKSHAY AGRAWAL 73 Cost Variance Schedule Variance Negative (<0) Over Budget Behind the Schedule Equal to (=0) No Profit No Loss On Schedule Positive (>0) Under Budget Ahead of Schedule
  • 74. To be cont…. Estimate At Completion EAC = AC + (BAC – EV)/CPI Estimated Time at Completion = Original Time at Completion / SPI AKSHAY AGRAWAL 74
  • 75. Earned Value Table  Go to view > Table > more table >Earned Value  Excavation is completed 12% instead of 33% so there is schedule variance which is negative and shows task behind the schedule. AKSHAY AGRAWAL 75
  • 76. Reports Select Report into Main Status bar > AKSHAY AGRAWAL 76