This document provides updates on ongoing construction works along several sections of the Crosstown LRT project in Toronto:
1) Caledonia, Keelesdale, and Mount Dennis stations are undergoing excavation, tunnel demolition, structural works, and utility relocation.
2) Construction of the elevated guideway is ongoing at West Portal, with foundation works, retaining walls, and pile installation. Lane closures on Black Creek Drive are planned for girder installation.
3) Works at the Eglinton Maintenance and Storage Facility include building construction, site services installation, and yard bridge works.
Central West Fall Open House Presentation Deck - October 14, 2020Crosstown TO
Metrolinx & Eglinton Crosstown LRT Project: Presentation material for the Central West Fall Virtual Open House, held on the Metrolinx Engage website, on October 14, 2020. Stations covered: Fairbank, Oakwood, Cedarvale, Forest Hill, Chaplin, Avenue, Eglinton.
Central West Fall Open House Presentation Deck - October 14, 2020Crosstown TO
Metrolinx & Eglinton Crosstown LRT Project: Presentation material for the Central West Fall Virtual Open House, held on the Metrolinx Engage website, on October 14, 2020. Stations covered: Fairbank, Oakwood, Cedarvale, Forest Hill, Chaplin, Avenue, Eglinton.
Eglinton and Mount Pleasant CLC - March 10, 2021Crosstown TO
A bi-monthly meeting to provide construction updates regarding Eglinton and Mount Pleasant Stations . The attached presentation materials were shared with the group.
CLC Deck - Brentcliffe to Victoria Park - January 12, 2023 - Compressed.pptxCrosstown TO
This is a meeting invite for the Brentcliffe-Victoria Park CLC (Construction Liaison Committee) Monthly Meeting, covering the Brentcliffe Portal, Sunnybrook Park, Science Centre, Aga Khan, Wynford, Sloane and O’ Connor Stops.
CLC Deck - Brentcliffe to Victoria Park - November 3 2022.pdfCrosstown TO
Construction updates for the following locations/stops: Brentcliffe Portal, Sunnybrook Park, Science Centre, Aga Khan Park & Museum, Wynford, Sloane and O'Connor.
ZGB - The Role of Generative AI in Government transformation.pdfSaeed Al Dhaheri
This keynote was presented during the the 7th edition of the UAE Hackathon 2024. It highlights the role of AI and Generative AI in addressing government transformation to achieve zero government bureaucracy
A process server is a authorized person for delivering legal documents, such as summons, complaints, subpoenas, and other court papers, to peoples involved in legal proceedings.
Canadian Immigration Tracker March 2024 - Key SlidesAndrew Griffith
Highlights
Permanent Residents decrease along with percentage of TR2PR decline to 52 percent of all Permanent Residents.
March asylum claim data not issued as of May 27 (unusually late). Irregular arrivals remain very small.
Study permit applications experiencing sharp decrease as a result of announced caps over 50 percent compared to February.
Citizenship numbers remain stable.
Slide 3 has the overall numbers and change.
What is the point of small housing associations.pptxPaul Smith
Given the small scale of housing associations and their relative high cost per home what is the point of them and how do we justify their continued existance
This session provides a comprehensive overview of the latest updates to the Uniform Administrative Requirements, Cost Principles, and Audit Requirements for Federal Awards (commonly known as the Uniform Guidance) outlined in the 2 CFR 200.
With a focus on the 2024 revisions issued by the Office of Management and Budget (OMB), participants will gain insight into the key changes affecting federal grant recipients. The session will delve into critical regulatory updates, providing attendees with the knowledge and tools necessary to navigate and comply with the evolving landscape of federal grant management.
Learning Objectives:
- Understand the rationale behind the 2024 updates to the Uniform Guidance outlined in 2 CFR 200, and their implications for federal grant recipients.
- Identify the key changes and revisions introduced by the Office of Management and Budget (OMB) in the 2024 edition of 2 CFR 200.
- Gain proficiency in applying the updated regulations to ensure compliance with federal grant requirements and avoid potential audit findings.
- Develop strategies for effectively implementing the new guidelines within the grant management processes of their respective organizations, fostering efficiency and accountability in federal grant administration.
Many ways to support street children.pptxSERUDS INDIA
By raising awareness, providing support, advocating for change, and offering assistance to children in need, individuals can play a crucial role in improving the lives of street children and helping them realize their full potential
Donate Us
https://serudsindia.org/how-individuals-can-support-street-children-in-india/
#donatefororphan, #donateforhomelesschildren, #childeducation, #ngochildeducation, #donateforeducation, #donationforchildeducation, #sponsorforpoorchild, #sponsororphanage #sponsororphanchild, #donation, #education, #charity, #educationforchild, #seruds, #kurnool, #joyhome
Jennifer Schaus and Associates hosts a complimentary webinar series on The FAR in 2024. Join the webinars on Wednesdays and Fridays at noon, eastern.
Recordings are on YouTube and the company website.
https://www.youtube.com/@jenniferschaus/videos
Presentation by Jared Jageler, David Adler, Noelia Duchovny, and Evan Herrnstadt, analysts in CBO’s Microeconomic Studies and Health Analysis Divisions, at the Association of Environmental and Resource Economists Summer Conference.
Russian anarchist and anti-war movement in the third year of full-scale warAntti Rautiainen
Anarchist group ANA Regensburg hosted my online-presentation on 16th of May 2024, in which I discussed tactics of anti-war activism in Russia, and reasons why the anti-war movement has not been able to make an impact to change the course of events yet. Cases of anarchists repressed for anti-war activities are presented, as well as strategies of support for political prisoners, and modest successes in supporting their struggles.
Thumbnail picture is by MediaZona, you may read their report on anti-war arson attacks in Russia here: https://en.zona.media/article/2022/10/13/burn-map
Links:
Autonomous Action
http://Avtonom.org
Anarchist Black Cross Moscow
http://Avtonom.org/abc
Solidarity Zone
https://t.me/solidarity_zone
Memorial
https://memopzk.org/, https://t.me/pzk_memorial
OVD-Info
https://en.ovdinfo.org/antiwar-ovd-info-guide
RosUznik
https://rosuznik.org/
Uznik Online
http://uznikonline.tilda.ws/
Russian Reader
https://therussianreader.com/
ABC Irkutsk
https://abc38.noblogs.org/
Send mail to prisoners from abroad:
http://Prisonmail.online
YouTube: https://youtu.be/c5nSOdU48O8
Spotify: https://podcasters.spotify.com/pod/show/libertarianlifecoach/episodes/Russian-anarchist-and-anti-war-movement-in-the-third-year-of-full-scale-war-e2k8ai4
2. Agenda
• Caledonia Station
• Keelesdale Station
• West Portal & Elevated Guideway
• Mount Dennis Station
• Railway Corridor
• Eglinton Maintenance & Storage Facility
2
3. Caledonia Station Update
Winter 2018
• Continue dewatering installation (first round is complete)
• Continue deep excavation
• Tunnel demolition
3
5. Keelesdale Station: ongoing works
• Excavation under the deck, Main Entrance, 2nd Entrance, 3rd Entrance and TPSS
• Tieback installation level D started
• Second shift is intermittently working from 5:00 p.m. to 2:00 a.m. welding, and move
earth to entrances for removal during the day.
5
Tunnel break through section filling to springline Drilling Tiebacks Below the intersection at Level C Excavating at the Traction Power Substation Level D
6. 6
West Portal: ongoing work
• Utility relocation works for Elevated Guideway – storm line is re-commissioned
• Elevated Guideway foundation work (ongoing), superstructure and piers to start early
January
• Cast in place retaining wall for the new Eglinton Ave realignment on going, walls and
foundations
• H Piling work to be completed by mid-February
Installing formwork at cast in place wall Concrete pour for pier 4 column Excavation and backfilling of cast in place wall
7. 7
Elevated Guideway: Black Creek Drive Lane Closures
Construction Stage
• One (1) long-term median curb lane closure south of Eglinton Avenue
• Two (2) long-term lane closures north of Eglinton Avenue along Black Creek Drive
• Closures to occur late January for 8 months (pending City council approval)
• Widening of the curbs along the northeast and southwest corner are required to
facilitate truck/bus westbound right turns and provide adequate room for receiving
traffic.
• Complete closure Black Creek Drive – two (2) nights weekend 10:00 p.m. to 6:00 a.m.
(mid June 2018) will be required for girder erection and installation.
• North pedestrian crossing at the Eglinton Avenue and Black Creek Drive intersection
will be closed.
• Haul routes to be confirmed
9. Construction Stage
• West of Black Creek Drive to the West Portal girder installation and staging area
• Complete closure of Black Creek Drive to Municipal Drive for girder installation – two
(2) weekends Friday to Monday 10:00 p.m. to 5:00 a.m. (mid June 2018)
• Work to take approximately two (2) weeks
9
Elevated Guideway: Girder Installation
10. Mount Dennis Station: ongoing works
• Station box concrete structure & main entrance
• Structural steel starting at station box
• Photography Drive Bridge south abutment and center pier formwork and rebar
• Photography Drive Bridge girders mid-April, Eglinton Avenue shutdown required (two consecutives
weekend requires City Council approval), haul routes to be confirmed
• Building 9 foundations preparing permanent foundation
• Guestville ductbank works (see attached PPT.)
10
Closing formwork & prep for pour – retaining wall #1 Pedestrian tunnel – forming starter wall Tail Track Slab – South and West perimeter walls
11. 11
Mount Dennis Station: Utility Installation Hollis Street
• Installing new sewer lines via a manhole in the intersection of Weston Rd and Hollis St,
road patching restoration.
• Lane closures of Hollis St at Weston Rd will be required.
• Sidewalks will remain open for pedestrians to access Hollis St and Scotia Bank.
• A paid-duty officer (PDO) will be in place to provide traffic control as required.
Date to be
confirmed as to
when this work will
start.
12. Railway Corridor: ongoing work
12
• Center temporary shoring wall excavation & tie-backs
• LRT and pedestrian tunnel construction excavation
• Work within the rail corridor will occur during the hours of 7:00 AM to 11:00 PM
• Precast tunnel sections – delivery March via Ray Avenue, minimal traffic disruptions (none on
Eglinton Avenue), haul route to be confirmed
Tie back installation ongoing for 2nd level Welding of walers on the centre shoring wallExcavation to bottom of 2nd level complete
13. 13
Maintenance & Storage Facility : ongoing works
• Wall & roof cladding for Maintenance Building
• Formwork, rebar & concrete placement – floor slab in Maintenance Building
• Site services – ductbanks and Operations Control Centre foundations
• Yard Bridge construction – precast retaining wall erection
Concrete pour at Handover Platform Louvres installation at electrical room.Layout for Center Rail Columns in Pit #1