SlideShare a Scribd company logo
Western Works CLC
Agenda
• Caledonia Station
• Keelesdale Station
• West Portal & Elevated Guideway
• Mount Dennis Station
• Railway Corridor
• Eglinton Maintenance & Storage Facility
2
Caledonia Station Update
Winter 2018
• Continue dewatering installation (first round is complete)
• Continue deep excavation
• Tunnel demolition
3
Long-term Construction Staging
4
Until 2021
TRUCK
ENTRY &
EGRESS
TRUCK
ENTRY &
EGRESS
Keelesdale Station: ongoing works
• Excavation under the deck, Main Entrance, 2nd Entrance, 3rd Entrance and TPSS
• Tieback installation level D started
• Second shift is intermittently working from 5:00 p.m. to 2:00 a.m. welding, and move
earth to entrances for removal during the day.
5
Tunnel break through section filling to springline Drilling Tiebacks Below the intersection at Level C Excavating at the Traction Power Substation Level D
6
West Portal: ongoing work
• Utility relocation works for Elevated Guideway – storm line is re-commissioned
• Elevated Guideway foundation work (ongoing), superstructure and piers to start early
January
• Cast in place retaining wall for the new Eglinton Ave realignment on going, walls and
foundations
• H Piling work to be completed by mid-February
Installing formwork at cast in place wall Concrete pour for pier 4 column Excavation and backfilling of cast in place wall
7
Elevated Guideway: Black Creek Drive Lane Closures
Construction Stage
• One (1) long-term median curb lane closure south of Eglinton Avenue
• Two (2) long-term lane closures north of Eglinton Avenue along Black Creek Drive
• Closures to occur late January for 8 months (pending City council approval)
• Widening of the curbs along the northeast and southwest corner are required to
facilitate truck/bus westbound right turns and provide adequate room for receiving
traffic.
• Complete closure Black Creek Drive – two (2) nights weekend 10:00 p.m. to 6:00 a.m.
(mid June 2018) will be required for girder erection and installation.
• North pedestrian crossing at the Eglinton Avenue and Black Creek Drive intersection
will be closed.
• Haul routes to be confirmed
8
Elevated Guideway: Black Creek Drive Lane Closures
Construction Stage
• West of Black Creek Drive to the West Portal girder installation and staging area
• Complete closure of Black Creek Drive to Municipal Drive for girder installation – two
(2) weekends Friday to Monday 10:00 p.m. to 5:00 a.m. (mid June 2018)
• Work to take approximately two (2) weeks
9
Elevated Guideway: Girder Installation
Mount Dennis Station: ongoing works
• Station box concrete structure & main entrance
• Structural steel starting at station box
• Photography Drive Bridge south abutment and center pier formwork and rebar
• Photography Drive Bridge girders mid-April, Eglinton Avenue shutdown required (two consecutives
weekend requires City Council approval), haul routes to be confirmed
• Building 9 foundations preparing permanent foundation
• Guestville ductbank works (see attached PPT.)
10
Closing formwork & prep for pour – retaining wall #1 Pedestrian tunnel – forming starter wall Tail Track Slab – South and West perimeter walls
11
Mount Dennis Station: Utility Installation Hollis Street
• Installing new sewer lines via a manhole in the intersection of Weston Rd and Hollis St,
road patching restoration.
• Lane closures of Hollis St at Weston Rd will be required.
• Sidewalks will remain open for pedestrians to access Hollis St and Scotia Bank.
• A paid-duty officer (PDO) will be in place to provide traffic control as required.
Date to be
confirmed as to
when this work will
start.
Railway Corridor: ongoing work
12
• Center temporary shoring wall excavation & tie-backs
• LRT and pedestrian tunnel construction excavation
• Work within the rail corridor will occur during the hours of 7:00 AM to 11:00 PM
• Precast tunnel sections – delivery March via Ray Avenue, minimal traffic disruptions (none on
Eglinton Avenue), haul route to be confirmed
Tie back installation ongoing for 2nd level Welding of walers on the centre shoring wallExcavation to bottom of 2nd level complete
13
Maintenance & Storage Facility : ongoing works
• Wall & roof cladding for Maintenance Building
• Formwork, rebar & concrete placement – floor slab in Maintenance Building
• Site services – ductbanks and Operations Control Centre foundations
• Yard Bridge construction – precast retaining wall erection
Concrete pour at Handover Platform Louvres installation at electrical room.Layout for Center Rail Columns in Pit #1

More Related Content

What's hot

Spring Virtual Open - Central West - April 21, 2021
Spring Virtual Open - Central West - April 21, 2021Spring Virtual Open - Central West - April 21, 2021
Spring Virtual Open - Central West - April 21, 2021
Crosstown TO
 
Cedarvale- Forest Hill Construction Update (July 29, 2020)
Cedarvale- Forest Hill Construction Update (July 29, 2020)Cedarvale- Forest Hill Construction Update (July 29, 2020)
Cedarvale- Forest Hill Construction Update (July 29, 2020)
Crosstown TO
 
Eglinton-Mount Pleasant Construction Liaison Committee Meeting - May 2018
Eglinton-Mount Pleasant Construction Liaison Committee Meeting - May 2018Eglinton-Mount Pleasant Construction Liaison Committee Meeting - May 2018
Eglinton-Mount Pleasant Construction Liaison Committee Meeting - May 2018
Crosstown TO
 
Eglinton & Mt Pleasant CLC - March 2020
Eglinton & Mt Pleasant CLC - March 2020 Eglinton & Mt Pleasant CLC - March 2020
Eglinton & Mt Pleasant CLC - March 2020
Crosstown TO
 
CLC presentation deck Brentcliffe to Victoria Park (July 9 2020)
CLC presentation deck Brentcliffe to Victoria Park (July 9 2020)CLC presentation deck Brentcliffe to Victoria Park (July 9 2020)
CLC presentation deck Brentcliffe to Victoria Park (July 9 2020)
Crosstown TO
 
Eglinton-Mt Pleasant Construction Liaison Committee July 8, 2020
Eglinton-Mt Pleasant Construction Liaison Committee July 8, 2020Eglinton-Mt Pleasant Construction Liaison Committee July 8, 2020
Eglinton-Mt Pleasant Construction Liaison Committee July 8, 2020
Crosstown TO
 
Cedarvale & Forest Hill Construction Update (September 30, 2020)
Cedarvale & Forest Hill Construction Update (September 30, 2020)Cedarvale & Forest Hill Construction Update (September 30, 2020)
Cedarvale & Forest Hill Construction Update (September 30, 2020)
Crosstown TO
 
Cedarvale & Forest Hill Construction Update - May 27, 2020
Cedarvale & Forest Hill Construction Update - May 27, 2020Cedarvale & Forest Hill Construction Update - May 27, 2020
Cedarvale & Forest Hill Construction Update - May 27, 2020
Crosstown TO
 
Cedarvale-Forest Hill CLC Presentation - November 27 2019
Cedarvale-Forest Hill CLC Presentation - November 27 2019Cedarvale-Forest Hill CLC Presentation - November 27 2019
Cedarvale-Forest Hill CLC Presentation - November 27 2019
Crosstown TO
 
Chaplin Avenue CLC Presentation Deck - Jan 8 2020
  Chaplin Avenue CLC Presentation Deck - Jan 8 2020  Chaplin Avenue CLC Presentation Deck - Jan 8 2020
Chaplin Avenue CLC Presentation Deck - Jan 8 2020
Crosstown TO
 
Eglinton and Mount Pleasant Construction Liaison Committee Meeting - Jan 2019
Eglinton and Mount Pleasant Construction Liaison Committee Meeting - Jan 2019Eglinton and Mount Pleasant Construction Liaison Committee Meeting - Jan 2019
Eglinton and Mount Pleasant Construction Liaison Committee Meeting - Jan 2019
Crosstown TO
 
Central Virtual Open House 28Apr2021
Central Virtual Open House 28Apr2021Central Virtual Open House 28Apr2021
Central Virtual Open House 28Apr2021
Crosstown TO
 
Eglinton-Mount Pleasant Construction update - May 2020
Eglinton-Mount Pleasant Construction update - May 2020Eglinton-Mount Pleasant Construction update - May 2020
Eglinton-Mount Pleasant Construction update - May 2020
Crosstown TO
 
Cedarvale & Forest Hill CLC - September 25, 2019
Cedarvale & Forest Hill CLC - September 25, 2019Cedarvale & Forest Hill CLC - September 25, 2019
Cedarvale & Forest Hill CLC - September 25, 2019
Crosstown TO
 
Eglinton & Mount Pleasant Construction Liaison Committee Meeting - February 2018
Eglinton & Mount Pleasant Construction Liaison Committee Meeting - February 2018Eglinton & Mount Pleasant Construction Liaison Committee Meeting - February 2018
Eglinton & Mount Pleasant Construction Liaison Committee Meeting - February 2018
Crosstown TO
 
Fairbank & Oakwood Construction Updates Deck - November 2020
Fairbank & Oakwood Construction Updates Deck - November 2020Fairbank & Oakwood Construction Updates Deck - November 2020
Fairbank & Oakwood Construction Updates Deck - November 2020
Crosstown TO
 
Central West Fall Open House Presentation Deck - October 14, 2020
Central West Fall Open House Presentation Deck - October 14, 2020Central West Fall Open House Presentation Deck - October 14, 2020
Central West Fall Open House Presentation Deck - October 14, 2020
Crosstown TO
 
Avenue & Chaplin CLC - Construction Update: January 6, 2021
Avenue & Chaplin CLC - Construction Update: January 6, 2021Avenue & Chaplin CLC - Construction Update: January 6, 2021
Avenue & Chaplin CLC - Construction Update: January 6, 2021
Crosstown TO
 
Cedarvale & Forest Hill Construction Update (May 28, 2021)
Cedarvale & Forest Hill Construction Update (May 28, 2021)Cedarvale & Forest Hill Construction Update (May 28, 2021)
Cedarvale & Forest Hill Construction Update (May 28, 2021)
Crosstown TO
 
Eglinton - Mount Pleasant Construction Liaison Committee - July 2018
Eglinton - Mount Pleasant Construction Liaison Committee - July 2018Eglinton - Mount Pleasant Construction Liaison Committee - July 2018
Eglinton - Mount Pleasant Construction Liaison Committee - July 2018
Crosstown TO
 

What's hot (20)

Spring Virtual Open - Central West - April 21, 2021
Spring Virtual Open - Central West - April 21, 2021Spring Virtual Open - Central West - April 21, 2021
Spring Virtual Open - Central West - April 21, 2021
 
Cedarvale- Forest Hill Construction Update (July 29, 2020)
Cedarvale- Forest Hill Construction Update (July 29, 2020)Cedarvale- Forest Hill Construction Update (July 29, 2020)
Cedarvale- Forest Hill Construction Update (July 29, 2020)
 
Eglinton-Mount Pleasant Construction Liaison Committee Meeting - May 2018
Eglinton-Mount Pleasant Construction Liaison Committee Meeting - May 2018Eglinton-Mount Pleasant Construction Liaison Committee Meeting - May 2018
Eglinton-Mount Pleasant Construction Liaison Committee Meeting - May 2018
 
Eglinton & Mt Pleasant CLC - March 2020
Eglinton & Mt Pleasant CLC - March 2020 Eglinton & Mt Pleasant CLC - March 2020
Eglinton & Mt Pleasant CLC - March 2020
 
CLC presentation deck Brentcliffe to Victoria Park (July 9 2020)
CLC presentation deck Brentcliffe to Victoria Park (July 9 2020)CLC presentation deck Brentcliffe to Victoria Park (July 9 2020)
CLC presentation deck Brentcliffe to Victoria Park (July 9 2020)
 
Eglinton-Mt Pleasant Construction Liaison Committee July 8, 2020
Eglinton-Mt Pleasant Construction Liaison Committee July 8, 2020Eglinton-Mt Pleasant Construction Liaison Committee July 8, 2020
Eglinton-Mt Pleasant Construction Liaison Committee July 8, 2020
 
Cedarvale & Forest Hill Construction Update (September 30, 2020)
Cedarvale & Forest Hill Construction Update (September 30, 2020)Cedarvale & Forest Hill Construction Update (September 30, 2020)
Cedarvale & Forest Hill Construction Update (September 30, 2020)
 
Cedarvale & Forest Hill Construction Update - May 27, 2020
Cedarvale & Forest Hill Construction Update - May 27, 2020Cedarvale & Forest Hill Construction Update - May 27, 2020
Cedarvale & Forest Hill Construction Update - May 27, 2020
 
Cedarvale-Forest Hill CLC Presentation - November 27 2019
Cedarvale-Forest Hill CLC Presentation - November 27 2019Cedarvale-Forest Hill CLC Presentation - November 27 2019
Cedarvale-Forest Hill CLC Presentation - November 27 2019
 
Chaplin Avenue CLC Presentation Deck - Jan 8 2020
  Chaplin Avenue CLC Presentation Deck - Jan 8 2020  Chaplin Avenue CLC Presentation Deck - Jan 8 2020
Chaplin Avenue CLC Presentation Deck - Jan 8 2020
 
Eglinton and Mount Pleasant Construction Liaison Committee Meeting - Jan 2019
Eglinton and Mount Pleasant Construction Liaison Committee Meeting - Jan 2019Eglinton and Mount Pleasant Construction Liaison Committee Meeting - Jan 2019
Eglinton and Mount Pleasant Construction Liaison Committee Meeting - Jan 2019
 
Central Virtual Open House 28Apr2021
Central Virtual Open House 28Apr2021Central Virtual Open House 28Apr2021
Central Virtual Open House 28Apr2021
 
Eglinton-Mount Pleasant Construction update - May 2020
Eglinton-Mount Pleasant Construction update - May 2020Eglinton-Mount Pleasant Construction update - May 2020
Eglinton-Mount Pleasant Construction update - May 2020
 
Cedarvale & Forest Hill CLC - September 25, 2019
Cedarvale & Forest Hill CLC - September 25, 2019Cedarvale & Forest Hill CLC - September 25, 2019
Cedarvale & Forest Hill CLC - September 25, 2019
 
Eglinton & Mount Pleasant Construction Liaison Committee Meeting - February 2018
Eglinton & Mount Pleasant Construction Liaison Committee Meeting - February 2018Eglinton & Mount Pleasant Construction Liaison Committee Meeting - February 2018
Eglinton & Mount Pleasant Construction Liaison Committee Meeting - February 2018
 
Fairbank & Oakwood Construction Updates Deck - November 2020
Fairbank & Oakwood Construction Updates Deck - November 2020Fairbank & Oakwood Construction Updates Deck - November 2020
Fairbank & Oakwood Construction Updates Deck - November 2020
 
Central West Fall Open House Presentation Deck - October 14, 2020
Central West Fall Open House Presentation Deck - October 14, 2020Central West Fall Open House Presentation Deck - October 14, 2020
Central West Fall Open House Presentation Deck - October 14, 2020
 
Avenue & Chaplin CLC - Construction Update: January 6, 2021
Avenue & Chaplin CLC - Construction Update: January 6, 2021Avenue & Chaplin CLC - Construction Update: January 6, 2021
Avenue & Chaplin CLC - Construction Update: January 6, 2021
 
Cedarvale & Forest Hill Construction Update (May 28, 2021)
Cedarvale & Forest Hill Construction Update (May 28, 2021)Cedarvale & Forest Hill Construction Update (May 28, 2021)
Cedarvale & Forest Hill Construction Update (May 28, 2021)
 
Eglinton - Mount Pleasant Construction Liaison Committee - July 2018
Eglinton - Mount Pleasant Construction Liaison Committee - July 2018Eglinton - Mount Pleasant Construction Liaison Committee - July 2018
Eglinton - Mount Pleasant Construction Liaison Committee - July 2018
 

Similar to Western Works Construction Liaison Committee Meeting - January 2018

Western Works Construction Liaison Committee Meeting - March 2018
Western Works Construction Liaison Committee Meeting - March 2018Western Works Construction Liaison Committee Meeting - March 2018
Western Works Construction Liaison Committee Meeting - March 2018
Crosstown TO
 
Western Works Construction Liaison Committee Meeting - September 2017
Western Works Construction Liaison Committee Meeting - September 2017Western Works Construction Liaison Committee Meeting - September 2017
Western Works Construction Liaison Committee Meeting - September 2017
Crosstown TO
 
Western Works - Construction Liaison Committee Meeting - May 2017
Western Works - Construction Liaison Committee Meeting - May 2017Western Works - Construction Liaison Committee Meeting - May 2017
Western Works - Construction Liaison Committee Meeting - May 2017
Crosstown TO
 
Pharmacy to Kennedy Construction Liaison Committee Meeting
Pharmacy to Kennedy Construction Liaison Committee MeetingPharmacy to Kennedy Construction Liaison Committee Meeting
Pharmacy to Kennedy Construction Liaison Committee Meeting
Crosstown TO
 
Brentcliffe - Victoria Park Construction Liaison Committee Meeting
Brentcliffe - Victoria Park Construction Liaison Committee MeetingBrentcliffe - Victoria Park Construction Liaison Committee Meeting
Brentcliffe - Victoria Park Construction Liaison Committee Meeting
Crosstown TO
 
Avenue & Chaplin CLC - Construction Update: July 8, 2020
Avenue & Chaplin CLC - Construction Update: July 8, 2020Avenue & Chaplin CLC - Construction Update: July 8, 2020
Avenue & Chaplin CLC - Construction Update: July 8, 2020
Crosstown TO
 
Brentcliffe - Victoria Park Construction Liaison Committee Meeting
Brentcliffe - Victoria Park Construction Liaison Committee MeetingBrentcliffe - Victoria Park Construction Liaison Committee Meeting
Brentcliffe - Victoria Park Construction Liaison Committee Meeting
Crosstown TO
 
Pharmacy to Kennedy Construction Liaision Committee Meeting - Sep 2020
Pharmacy to Kennedy Construction Liaision Committee Meeting - Sep 2020Pharmacy to Kennedy Construction Liaision Committee Meeting - Sep 2020
Pharmacy to Kennedy Construction Liaision Committee Meeting - Sep 2020
Crosstown TO
 
Brentcliffe-Victoria Park Construction Liaison Committee (CLC) Meeting - May ...
Brentcliffe-Victoria Park Construction Liaison Committee (CLC) Meeting - May ...Brentcliffe-Victoria Park Construction Liaison Committee (CLC) Meeting - May ...
Brentcliffe-Victoria Park Construction Liaison Committee (CLC) Meeting - May ...
Crosstown TO
 
Western Works Construction Liaison Committee - November 2017
Western Works Construction Liaison Committee - November 2017Western Works Construction Liaison Committee - November 2017
Western Works Construction Liaison Committee - November 2017
Crosstown TO
 
Chaplin-Avenue Construction Liaison Committee Meeting - October 2017
Chaplin-Avenue Construction Liaison Committee Meeting - October 2017Chaplin-Avenue Construction Liaison Committee Meeting - October 2017
Chaplin-Avenue Construction Liaison Committee Meeting - October 2017
Crosstown TO
 
Brentcliffe - Victoria Park Construction Liaison Committee (CLC) Meeting
Brentcliffe - Victoria Park Construction Liaison Committee (CLC) MeetingBrentcliffe - Victoria Park Construction Liaison Committee (CLC) Meeting
Brentcliffe - Victoria Park Construction Liaison Committee (CLC) Meeting
Crosstown TO
 
Leaside laird clc - november 9, 2020
Leaside laird clc - november 9, 2020Leaside laird clc - november 9, 2020
Leaside laird clc - november 9, 2020
Crosstown TO
 
CLC Deck Brentcliffe Road to Victoria Park Avenue (Sept 3, 2020)
CLC Deck Brentcliffe Road to Victoria Park Avenue (Sept 3, 2020)CLC Deck Brentcliffe Road to Victoria Park Avenue (Sept 3, 2020)
CLC Deck Brentcliffe Road to Victoria Park Avenue (Sept 3, 2020)
Crosstown TO
 
CLC Deck Brentcliffe Road to Victoria Park Avenue (Sept 3, 2020)
CLC Deck Brentcliffe Road to Victoria Park Avenue (Sept 3, 2020)CLC Deck Brentcliffe Road to Victoria Park Avenue (Sept 3, 2020)
CLC Deck Brentcliffe Road to Victoria Park Avenue (Sept 3, 2020)
Crosstown TO
 
Avenue & Chaplin CLC - Construction Update: May 6, 2020
Avenue & Chaplin CLC - Construction Update: May 6, 2020Avenue & Chaplin CLC - Construction Update: May 6, 2020
Avenue & Chaplin CLC - Construction Update: May 6, 2020
Crosstown TO
 
Eglinton and Mount Pleasant CLC - March 10, 2021
Eglinton and Mount Pleasant CLC - March 10, 2021Eglinton and Mount Pleasant CLC - March 10, 2021
Eglinton and Mount Pleasant CLC - March 10, 2021
Crosstown TO
 
Brentcliffe - Victoria Park Construction Liaison Committee (CLC) Meeting
Brentcliffe - Victoria Park Construction Liaison Committee (CLC) MeetingBrentcliffe - Victoria Park Construction Liaison Committee (CLC) Meeting
Brentcliffe - Victoria Park Construction Liaison Committee (CLC) Meeting
Crosstown TO
 
Leaside/ Laird CLC Construction Update - January 2019
Leaside/ Laird CLC Construction Update - January 2019Leaside/ Laird CLC Construction Update - January 2019
Leaside/ Laird CLC Construction Update - January 2019
Crosstown TO
 
Chaplin & Avenue Construction Liaison Committee Meeting - July 2017
Chaplin & Avenue Construction Liaison Committee Meeting - July 2017Chaplin & Avenue Construction Liaison Committee Meeting - July 2017
Chaplin & Avenue Construction Liaison Committee Meeting - July 2017
Crosstown TO
 

Similar to Western Works Construction Liaison Committee Meeting - January 2018 (20)

Western Works Construction Liaison Committee Meeting - March 2018
Western Works Construction Liaison Committee Meeting - March 2018Western Works Construction Liaison Committee Meeting - March 2018
Western Works Construction Liaison Committee Meeting - March 2018
 
Western Works Construction Liaison Committee Meeting - September 2017
Western Works Construction Liaison Committee Meeting - September 2017Western Works Construction Liaison Committee Meeting - September 2017
Western Works Construction Liaison Committee Meeting - September 2017
 
Western Works - Construction Liaison Committee Meeting - May 2017
Western Works - Construction Liaison Committee Meeting - May 2017Western Works - Construction Liaison Committee Meeting - May 2017
Western Works - Construction Liaison Committee Meeting - May 2017
 
Pharmacy to Kennedy Construction Liaison Committee Meeting
Pharmacy to Kennedy Construction Liaison Committee MeetingPharmacy to Kennedy Construction Liaison Committee Meeting
Pharmacy to Kennedy Construction Liaison Committee Meeting
 
Brentcliffe - Victoria Park Construction Liaison Committee Meeting
Brentcliffe - Victoria Park Construction Liaison Committee MeetingBrentcliffe - Victoria Park Construction Liaison Committee Meeting
Brentcliffe - Victoria Park Construction Liaison Committee Meeting
 
Avenue & Chaplin CLC - Construction Update: July 8, 2020
Avenue & Chaplin CLC - Construction Update: July 8, 2020Avenue & Chaplin CLC - Construction Update: July 8, 2020
Avenue & Chaplin CLC - Construction Update: July 8, 2020
 
Brentcliffe - Victoria Park Construction Liaison Committee Meeting
Brentcliffe - Victoria Park Construction Liaison Committee MeetingBrentcliffe - Victoria Park Construction Liaison Committee Meeting
Brentcliffe - Victoria Park Construction Liaison Committee Meeting
 
Pharmacy to Kennedy Construction Liaision Committee Meeting - Sep 2020
Pharmacy to Kennedy Construction Liaision Committee Meeting - Sep 2020Pharmacy to Kennedy Construction Liaision Committee Meeting - Sep 2020
Pharmacy to Kennedy Construction Liaision Committee Meeting - Sep 2020
 
Brentcliffe-Victoria Park Construction Liaison Committee (CLC) Meeting - May ...
Brentcliffe-Victoria Park Construction Liaison Committee (CLC) Meeting - May ...Brentcliffe-Victoria Park Construction Liaison Committee (CLC) Meeting - May ...
Brentcliffe-Victoria Park Construction Liaison Committee (CLC) Meeting - May ...
 
Western Works Construction Liaison Committee - November 2017
Western Works Construction Liaison Committee - November 2017Western Works Construction Liaison Committee - November 2017
Western Works Construction Liaison Committee - November 2017
 
Chaplin-Avenue Construction Liaison Committee Meeting - October 2017
Chaplin-Avenue Construction Liaison Committee Meeting - October 2017Chaplin-Avenue Construction Liaison Committee Meeting - October 2017
Chaplin-Avenue Construction Liaison Committee Meeting - October 2017
 
Brentcliffe - Victoria Park Construction Liaison Committee (CLC) Meeting
Brentcliffe - Victoria Park Construction Liaison Committee (CLC) MeetingBrentcliffe - Victoria Park Construction Liaison Committee (CLC) Meeting
Brentcliffe - Victoria Park Construction Liaison Committee (CLC) Meeting
 
Leaside laird clc - november 9, 2020
Leaside laird clc - november 9, 2020Leaside laird clc - november 9, 2020
Leaside laird clc - november 9, 2020
 
CLC Deck Brentcliffe Road to Victoria Park Avenue (Sept 3, 2020)
CLC Deck Brentcliffe Road to Victoria Park Avenue (Sept 3, 2020)CLC Deck Brentcliffe Road to Victoria Park Avenue (Sept 3, 2020)
CLC Deck Brentcliffe Road to Victoria Park Avenue (Sept 3, 2020)
 
CLC Deck Brentcliffe Road to Victoria Park Avenue (Sept 3, 2020)
CLC Deck Brentcliffe Road to Victoria Park Avenue (Sept 3, 2020)CLC Deck Brentcliffe Road to Victoria Park Avenue (Sept 3, 2020)
CLC Deck Brentcliffe Road to Victoria Park Avenue (Sept 3, 2020)
 
Avenue & Chaplin CLC - Construction Update: May 6, 2020
Avenue & Chaplin CLC - Construction Update: May 6, 2020Avenue & Chaplin CLC - Construction Update: May 6, 2020
Avenue & Chaplin CLC - Construction Update: May 6, 2020
 
Eglinton and Mount Pleasant CLC - March 10, 2021
Eglinton and Mount Pleasant CLC - March 10, 2021Eglinton and Mount Pleasant CLC - March 10, 2021
Eglinton and Mount Pleasant CLC - March 10, 2021
 
Brentcliffe - Victoria Park Construction Liaison Committee (CLC) Meeting
Brentcliffe - Victoria Park Construction Liaison Committee (CLC) MeetingBrentcliffe - Victoria Park Construction Liaison Committee (CLC) Meeting
Brentcliffe - Victoria Park Construction Liaison Committee (CLC) Meeting
 
Leaside/ Laird CLC Construction Update - January 2019
Leaside/ Laird CLC Construction Update - January 2019Leaside/ Laird CLC Construction Update - January 2019
Leaside/ Laird CLC Construction Update - January 2019
 
Chaplin & Avenue Construction Liaison Committee Meeting - July 2017
Chaplin & Avenue Construction Liaison Committee Meeting - July 2017Chaplin & Avenue Construction Liaison Committee Meeting - July 2017
Chaplin & Avenue Construction Liaison Committee Meeting - July 2017
 

More from Crosstown TO

Western Works CLC - January 17, 2023.pdf
Western Works CLC - January 17, 2023.pdfWestern Works CLC - January 17, 2023.pdf
Western Works CLC - January 17, 2023.pdf
Crosstown TO
 
Western Works CLC - May 16, 2023
 Western Works CLC - May 16, 2023 Western Works CLC - May 16, 2023
Western Works CLC - May 16, 2023
Crosstown TO
 
Western Works CLC - March, 21 2023
Western Works CLC - March, 21 2023 Western Works CLC - March, 21 2023
Western Works CLC - March, 21 2023
Crosstown TO
 
Leaside-Laird CLC - May 8, 2023.pdf
Leaside-Laird CLC - May 8, 2023.pdfLeaside-Laird CLC - May 8, 2023.pdf
Leaside-Laird CLC - May 8, 2023.pdf
Crosstown TO
 
Eglinton - Mt Pleasant CLC - May 10, 2023.pdf
Eglinton - Mt Pleasant CLC - May 10, 2023.pdfEglinton - Mt Pleasant CLC - May 10, 2023.pdf
Eglinton - Mt Pleasant CLC - May 10, 2023.pdf
Crosstown TO
 
Chaplin-Avenue CLC - May 3 2023 Updated.pptx
Chaplin-Avenue CLC - May 3 2023 Updated.pptxChaplin-Avenue CLC - May 3 2023 Updated.pptx
Chaplin-Avenue CLC - May 3 2023 Updated.pptx
Crosstown TO
 
CLC Deck - Brentcliffe to Victoria Park - May 4 2023 - Compressed.pptx
CLC Deck - Brentcliffe to Victoria Park - May 4 2023 - Compressed.pptxCLC Deck - Brentcliffe to Victoria Park - May 4 2023 - Compressed.pptx
CLC Deck - Brentcliffe to Victoria Park - May 4 2023 - Compressed.pptx
Crosstown TO
 
Pharmacy to Kennedy CLC presentation deck - Janaury 31, 2023.pptx
Pharmacy to Kennedy CLC presentation deck - Janaury 31, 2023.pptxPharmacy to Kennedy CLC presentation deck - Janaury 31, 2023.pptx
Pharmacy to Kennedy CLC presentation deck - Janaury 31, 2023.pptx
Crosstown TO
 
CLC Pharmacy to Kennedy - March 28, 2023 - Compressed.pptx
CLC Pharmacy to Kennedy - March 28, 2023 - Compressed.pptxCLC Pharmacy to Kennedy - March 28, 2023 - Compressed.pptx
CLC Pharmacy to Kennedy - March 28, 2023 - Compressed.pptx
Crosstown TO
 
CLC Deck - Brentcliffe to Victoria Park - March 2, 2023 - Compressed.pptx
CLC Deck - Brentcliffe to Victoria Park - March 2, 2023 - Compressed.pptxCLC Deck - Brentcliffe to Victoria Park - March 2, 2023 - Compressed.pptx
CLC Deck - Brentcliffe to Victoria Park - March 2, 2023 - Compressed.pptx
Crosstown TO
 
Chaplin-Avenue CLC - March 1, 2023.pptx
Chaplin-Avenue CLC - March 1, 2023.pptxChaplin-Avenue CLC - March 1, 2023.pptx
Chaplin-Avenue CLC - March 1, 2023.pptx
Crosstown TO
 
Leaside-Laird CLC - March 13, 2023.pdf
Leaside-Laird CLC - March 13, 2023.pdfLeaside-Laird CLC - March 13, 2023.pdf
Leaside-Laird CLC - March 13, 2023.pdf
Crosstown TO
 
CLC Deck - Brentcliffe to Victoria Park - March 2, 2023 - Compressed.pptx
CLC Deck - Brentcliffe to Victoria Park - March 2, 2023 - Compressed.pptxCLC Deck - Brentcliffe to Victoria Park - March 2, 2023 - Compressed.pptx
CLC Deck - Brentcliffe to Victoria Park - March 2, 2023 - Compressed.pptx
Crosstown TO
 
Eglinton - Mount Pleasant CLC - March 8, 2023.pdf
Eglinton - Mount Pleasant CLC - March 8, 2023.pdfEglinton - Mount Pleasant CLC - March 8, 2023.pdf
Eglinton - Mount Pleasant CLC - March 8, 2023.pdf
Crosstown TO
 
Chaplin-Avenue CLC - November 2 2022 compressed.pptx
Chaplin-Avenue CLC - November 2 2022 compressed.pptxChaplin-Avenue CLC - November 2 2022 compressed.pptx
Chaplin-Avenue CLC - November 2 2022 compressed.pptx
Crosstown TO
 
Chaplin-Avenue CLC - January 11 2023 (002).pptx
Chaplin-Avenue CLC - January 11 2023 (002).pptxChaplin-Avenue CLC - January 11 2023 (002).pptx
Chaplin-Avenue CLC - January 11 2023 (002).pptx
Crosstown TO
 
CLC Deck - Brentcliffe to Victoria Park - January 12, 2023 - Compressed.pptx
CLC Deck - Brentcliffe to Victoria Park - January 12, 2023 - Compressed.pptxCLC Deck - Brentcliffe to Victoria Park - January 12, 2023 - Compressed.pptx
CLC Deck - Brentcliffe to Victoria Park - January 12, 2023 - Compressed.pptx
Crosstown TO
 
Eglinton - Mt Pleasant CLC - January 11, 2023.pdf
Eglinton - Mt Pleasant CLC - January 11, 2023.pdfEglinton - Mt Pleasant CLC - January 11, 2023.pdf
Eglinton - Mt Pleasant CLC - January 11, 2023.pdf
Crosstown TO
 
Leaside-Laird CLC - January 9, 2023.pdf
Leaside-Laird CLC - January 9, 2023.pdfLeaside-Laird CLC - January 9, 2023.pdf
Leaside-Laird CLC - January 9, 2023.pdf
Crosstown TO
 
CLC Deck - Brentcliffe to Victoria Park - November 3 2022.pdf
CLC Deck - Brentcliffe to Victoria Park - November 3 2022.pdfCLC Deck - Brentcliffe to Victoria Park - November 3 2022.pdf
CLC Deck - Brentcliffe to Victoria Park - November 3 2022.pdf
Crosstown TO
 

More from Crosstown TO (20)

Western Works CLC - January 17, 2023.pdf
Western Works CLC - January 17, 2023.pdfWestern Works CLC - January 17, 2023.pdf
Western Works CLC - January 17, 2023.pdf
 
Western Works CLC - May 16, 2023
 Western Works CLC - May 16, 2023 Western Works CLC - May 16, 2023
Western Works CLC - May 16, 2023
 
Western Works CLC - March, 21 2023
Western Works CLC - March, 21 2023 Western Works CLC - March, 21 2023
Western Works CLC - March, 21 2023
 
Leaside-Laird CLC - May 8, 2023.pdf
Leaside-Laird CLC - May 8, 2023.pdfLeaside-Laird CLC - May 8, 2023.pdf
Leaside-Laird CLC - May 8, 2023.pdf
 
Eglinton - Mt Pleasant CLC - May 10, 2023.pdf
Eglinton - Mt Pleasant CLC - May 10, 2023.pdfEglinton - Mt Pleasant CLC - May 10, 2023.pdf
Eglinton - Mt Pleasant CLC - May 10, 2023.pdf
 
Chaplin-Avenue CLC - May 3 2023 Updated.pptx
Chaplin-Avenue CLC - May 3 2023 Updated.pptxChaplin-Avenue CLC - May 3 2023 Updated.pptx
Chaplin-Avenue CLC - May 3 2023 Updated.pptx
 
CLC Deck - Brentcliffe to Victoria Park - May 4 2023 - Compressed.pptx
CLC Deck - Brentcliffe to Victoria Park - May 4 2023 - Compressed.pptxCLC Deck - Brentcliffe to Victoria Park - May 4 2023 - Compressed.pptx
CLC Deck - Brentcliffe to Victoria Park - May 4 2023 - Compressed.pptx
 
Pharmacy to Kennedy CLC presentation deck - Janaury 31, 2023.pptx
Pharmacy to Kennedy CLC presentation deck - Janaury 31, 2023.pptxPharmacy to Kennedy CLC presentation deck - Janaury 31, 2023.pptx
Pharmacy to Kennedy CLC presentation deck - Janaury 31, 2023.pptx
 
CLC Pharmacy to Kennedy - March 28, 2023 - Compressed.pptx
CLC Pharmacy to Kennedy - March 28, 2023 - Compressed.pptxCLC Pharmacy to Kennedy - March 28, 2023 - Compressed.pptx
CLC Pharmacy to Kennedy - March 28, 2023 - Compressed.pptx
 
CLC Deck - Brentcliffe to Victoria Park - March 2, 2023 - Compressed.pptx
CLC Deck - Brentcliffe to Victoria Park - March 2, 2023 - Compressed.pptxCLC Deck - Brentcliffe to Victoria Park - March 2, 2023 - Compressed.pptx
CLC Deck - Brentcliffe to Victoria Park - March 2, 2023 - Compressed.pptx
 
Chaplin-Avenue CLC - March 1, 2023.pptx
Chaplin-Avenue CLC - March 1, 2023.pptxChaplin-Avenue CLC - March 1, 2023.pptx
Chaplin-Avenue CLC - March 1, 2023.pptx
 
Leaside-Laird CLC - March 13, 2023.pdf
Leaside-Laird CLC - March 13, 2023.pdfLeaside-Laird CLC - March 13, 2023.pdf
Leaside-Laird CLC - March 13, 2023.pdf
 
CLC Deck - Brentcliffe to Victoria Park - March 2, 2023 - Compressed.pptx
CLC Deck - Brentcliffe to Victoria Park - March 2, 2023 - Compressed.pptxCLC Deck - Brentcliffe to Victoria Park - March 2, 2023 - Compressed.pptx
CLC Deck - Brentcliffe to Victoria Park - March 2, 2023 - Compressed.pptx
 
Eglinton - Mount Pleasant CLC - March 8, 2023.pdf
Eglinton - Mount Pleasant CLC - March 8, 2023.pdfEglinton - Mount Pleasant CLC - March 8, 2023.pdf
Eglinton - Mount Pleasant CLC - March 8, 2023.pdf
 
Chaplin-Avenue CLC - November 2 2022 compressed.pptx
Chaplin-Avenue CLC - November 2 2022 compressed.pptxChaplin-Avenue CLC - November 2 2022 compressed.pptx
Chaplin-Avenue CLC - November 2 2022 compressed.pptx
 
Chaplin-Avenue CLC - January 11 2023 (002).pptx
Chaplin-Avenue CLC - January 11 2023 (002).pptxChaplin-Avenue CLC - January 11 2023 (002).pptx
Chaplin-Avenue CLC - January 11 2023 (002).pptx
 
CLC Deck - Brentcliffe to Victoria Park - January 12, 2023 - Compressed.pptx
CLC Deck - Brentcliffe to Victoria Park - January 12, 2023 - Compressed.pptxCLC Deck - Brentcliffe to Victoria Park - January 12, 2023 - Compressed.pptx
CLC Deck - Brentcliffe to Victoria Park - January 12, 2023 - Compressed.pptx
 
Eglinton - Mt Pleasant CLC - January 11, 2023.pdf
Eglinton - Mt Pleasant CLC - January 11, 2023.pdfEglinton - Mt Pleasant CLC - January 11, 2023.pdf
Eglinton - Mt Pleasant CLC - January 11, 2023.pdf
 
Leaside-Laird CLC - January 9, 2023.pdf
Leaside-Laird CLC - January 9, 2023.pdfLeaside-Laird CLC - January 9, 2023.pdf
Leaside-Laird CLC - January 9, 2023.pdf
 
CLC Deck - Brentcliffe to Victoria Park - November 3 2022.pdf
CLC Deck - Brentcliffe to Victoria Park - November 3 2022.pdfCLC Deck - Brentcliffe to Victoria Park - November 3 2022.pdf
CLC Deck - Brentcliffe to Victoria Park - November 3 2022.pdf
 

Recently uploaded

PACT launching workshop presentation-Final.pdf
PACT launching workshop presentation-Final.pdfPACT launching workshop presentation-Final.pdf
PACT launching workshop presentation-Final.pdf
Mohammed325561
 
一比一原版(ANU毕业证)澳大利亚国立大学毕业证成绩单
一比一原版(ANU毕业证)澳大利亚国立大学毕业证成绩单一比一原版(ANU毕业证)澳大利亚国立大学毕业证成绩单
一比一原版(ANU毕业证)澳大利亚国立大学毕业证成绩单
ehbuaw
 
一比一原版(QUT毕业证)昆士兰科技大学毕业证成绩单
一比一原版(QUT毕业证)昆士兰科技大学毕业证成绩单一比一原版(QUT毕业证)昆士兰科技大学毕业证成绩单
一比一原版(QUT毕业证)昆士兰科技大学毕业证成绩单
ukyewh
 
ZGB - The Role of Generative AI in Government transformation.pdf
ZGB - The Role of Generative AI in Government transformation.pdfZGB - The Role of Generative AI in Government transformation.pdf
ZGB - The Role of Generative AI in Government transformation.pdf
Saeed Al Dhaheri
 
一比一原版(Adelaide毕业证)阿德莱德大学毕业证成绩单
一比一原版(Adelaide毕业证)阿德莱德大学毕业证成绩单一比一原版(Adelaide毕业证)阿德莱德大学毕业证成绩单
一比一原版(Adelaide毕业证)阿德莱德大学毕业证成绩单
ehbuaw
 
The Role of a Process Server in real estate
The Role of a Process Server in real estateThe Role of a Process Server in real estate
The Role of a Process Server in real estate
oklahomajudicialproc1
 
PPT Item # 8 - Tuxedo Columbine 3way Stop
PPT Item # 8 - Tuxedo Columbine 3way StopPPT Item # 8 - Tuxedo Columbine 3way Stop
PPT Item # 8 - Tuxedo Columbine 3way Stop
ahcitycouncil
 
Canadian Immigration Tracker March 2024 - Key Slides
Canadian Immigration Tracker March 2024 - Key SlidesCanadian Immigration Tracker March 2024 - Key Slides
Canadian Immigration Tracker March 2024 - Key Slides
Andrew Griffith
 
PPT Item # 9 - 2024 Street Maintenance Program(SMP) Amendment
PPT Item # 9 - 2024 Street Maintenance Program(SMP) AmendmentPPT Item # 9 - 2024 Street Maintenance Program(SMP) Amendment
PPT Item # 9 - 2024 Street Maintenance Program(SMP) Amendment
ahcitycouncil
 
What is the point of small housing associations.pptx
What is the point of small housing associations.pptxWhat is the point of small housing associations.pptx
What is the point of small housing associations.pptx
Paul Smith
 
Uniform Guidance 3.0 - The New 2 CFR 200
Uniform Guidance 3.0 - The New 2 CFR 200Uniform Guidance 3.0 - The New 2 CFR 200
Uniform Guidance 3.0 - The New 2 CFR 200
GrantManagementInsti
 
一比一原版(WSU毕业证)西悉尼大学毕业证成绩单
一比一原版(WSU毕业证)西悉尼大学毕业证成绩单一比一原版(WSU毕业证)西悉尼大学毕业证成绩单
一比一原版(WSU毕业证)西悉尼大学毕业证成绩单
evkovas
 
Many ways to support street children.pptx
Many ways to support street children.pptxMany ways to support street children.pptx
Many ways to support street children.pptx
SERUDS INDIA
 
2024: The FAR - Federal Acquisition Regulations, Part 36
2024: The FAR - Federal Acquisition Regulations, Part 362024: The FAR - Federal Acquisition Regulations, Part 36
2024: The FAR - Federal Acquisition Regulations, Part 36
JSchaus & Associates
 
PD-1602-as-amended-by-RA-9287-Anti-Illegal-Gambling-Law.pptx
PD-1602-as-amended-by-RA-9287-Anti-Illegal-Gambling-Law.pptxPD-1602-as-amended-by-RA-9287-Anti-Illegal-Gambling-Law.pptx
PD-1602-as-amended-by-RA-9287-Anti-Illegal-Gambling-Law.pptx
RIDPRO11
 
Effects of Extreme Temperatures From Climate Change on the Medicare Populatio...
Effects of Extreme Temperatures From Climate Change on the Medicare Populatio...Effects of Extreme Temperatures From Climate Change on the Medicare Populatio...
Effects of Extreme Temperatures From Climate Change on the Medicare Populatio...
Congressional Budget Office
 
Russian anarchist and anti-war movement in the third year of full-scale war
Russian anarchist and anti-war movement in the third year of full-scale warRussian anarchist and anti-war movement in the third year of full-scale war
Russian anarchist and anti-war movement in the third year of full-scale war
Antti Rautiainen
 
Get Government Grants and Assistance Program
Get Government Grants and Assistance ProgramGet Government Grants and Assistance Program
Get Government Grants and Assistance Program
Get Government Grants
 
快速制作(ocad毕业证书)加拿大安大略艺术设计学院毕业证本科学历雅思成绩单原版一模一样
快速制作(ocad毕业证书)加拿大安大略艺术设计学院毕业证本科学历雅思成绩单原版一模一样快速制作(ocad毕业证书)加拿大安大略艺术设计学院毕业证本科学历雅思成绩单原版一模一样
快速制作(ocad毕业证书)加拿大安大略艺术设计学院毕业证本科学历雅思成绩单原版一模一样
850fcj96
 
如何办理(uoit毕业证书)加拿大安大略理工大学毕业证文凭证书录取通知原版一模一样
如何办理(uoit毕业证书)加拿大安大略理工大学毕业证文凭证书录取通知原版一模一样如何办理(uoit毕业证书)加拿大安大略理工大学毕业证文凭证书录取通知原版一模一样
如何办理(uoit毕业证书)加拿大安大略理工大学毕业证文凭证书录取通知原版一模一样
850fcj96
 

Recently uploaded (20)

PACT launching workshop presentation-Final.pdf
PACT launching workshop presentation-Final.pdfPACT launching workshop presentation-Final.pdf
PACT launching workshop presentation-Final.pdf
 
一比一原版(ANU毕业证)澳大利亚国立大学毕业证成绩单
一比一原版(ANU毕业证)澳大利亚国立大学毕业证成绩单一比一原版(ANU毕业证)澳大利亚国立大学毕业证成绩单
一比一原版(ANU毕业证)澳大利亚国立大学毕业证成绩单
 
一比一原版(QUT毕业证)昆士兰科技大学毕业证成绩单
一比一原版(QUT毕业证)昆士兰科技大学毕业证成绩单一比一原版(QUT毕业证)昆士兰科技大学毕业证成绩单
一比一原版(QUT毕业证)昆士兰科技大学毕业证成绩单
 
ZGB - The Role of Generative AI in Government transformation.pdf
ZGB - The Role of Generative AI in Government transformation.pdfZGB - The Role of Generative AI in Government transformation.pdf
ZGB - The Role of Generative AI in Government transformation.pdf
 
一比一原版(Adelaide毕业证)阿德莱德大学毕业证成绩单
一比一原版(Adelaide毕业证)阿德莱德大学毕业证成绩单一比一原版(Adelaide毕业证)阿德莱德大学毕业证成绩单
一比一原版(Adelaide毕业证)阿德莱德大学毕业证成绩单
 
The Role of a Process Server in real estate
The Role of a Process Server in real estateThe Role of a Process Server in real estate
The Role of a Process Server in real estate
 
PPT Item # 8 - Tuxedo Columbine 3way Stop
PPT Item # 8 - Tuxedo Columbine 3way StopPPT Item # 8 - Tuxedo Columbine 3way Stop
PPT Item # 8 - Tuxedo Columbine 3way Stop
 
Canadian Immigration Tracker March 2024 - Key Slides
Canadian Immigration Tracker March 2024 - Key SlidesCanadian Immigration Tracker March 2024 - Key Slides
Canadian Immigration Tracker March 2024 - Key Slides
 
PPT Item # 9 - 2024 Street Maintenance Program(SMP) Amendment
PPT Item # 9 - 2024 Street Maintenance Program(SMP) AmendmentPPT Item # 9 - 2024 Street Maintenance Program(SMP) Amendment
PPT Item # 9 - 2024 Street Maintenance Program(SMP) Amendment
 
What is the point of small housing associations.pptx
What is the point of small housing associations.pptxWhat is the point of small housing associations.pptx
What is the point of small housing associations.pptx
 
Uniform Guidance 3.0 - The New 2 CFR 200
Uniform Guidance 3.0 - The New 2 CFR 200Uniform Guidance 3.0 - The New 2 CFR 200
Uniform Guidance 3.0 - The New 2 CFR 200
 
一比一原版(WSU毕业证)西悉尼大学毕业证成绩单
一比一原版(WSU毕业证)西悉尼大学毕业证成绩单一比一原版(WSU毕业证)西悉尼大学毕业证成绩单
一比一原版(WSU毕业证)西悉尼大学毕业证成绩单
 
Many ways to support street children.pptx
Many ways to support street children.pptxMany ways to support street children.pptx
Many ways to support street children.pptx
 
2024: The FAR - Federal Acquisition Regulations, Part 36
2024: The FAR - Federal Acquisition Regulations, Part 362024: The FAR - Federal Acquisition Regulations, Part 36
2024: The FAR - Federal Acquisition Regulations, Part 36
 
PD-1602-as-amended-by-RA-9287-Anti-Illegal-Gambling-Law.pptx
PD-1602-as-amended-by-RA-9287-Anti-Illegal-Gambling-Law.pptxPD-1602-as-amended-by-RA-9287-Anti-Illegal-Gambling-Law.pptx
PD-1602-as-amended-by-RA-9287-Anti-Illegal-Gambling-Law.pptx
 
Effects of Extreme Temperatures From Climate Change on the Medicare Populatio...
Effects of Extreme Temperatures From Climate Change on the Medicare Populatio...Effects of Extreme Temperatures From Climate Change on the Medicare Populatio...
Effects of Extreme Temperatures From Climate Change on the Medicare Populatio...
 
Russian anarchist and anti-war movement in the third year of full-scale war
Russian anarchist and anti-war movement in the third year of full-scale warRussian anarchist and anti-war movement in the third year of full-scale war
Russian anarchist and anti-war movement in the third year of full-scale war
 
Get Government Grants and Assistance Program
Get Government Grants and Assistance ProgramGet Government Grants and Assistance Program
Get Government Grants and Assistance Program
 
快速制作(ocad毕业证书)加拿大安大略艺术设计学院毕业证本科学历雅思成绩单原版一模一样
快速制作(ocad毕业证书)加拿大安大略艺术设计学院毕业证本科学历雅思成绩单原版一模一样快速制作(ocad毕业证书)加拿大安大略艺术设计学院毕业证本科学历雅思成绩单原版一模一样
快速制作(ocad毕业证书)加拿大安大略艺术设计学院毕业证本科学历雅思成绩单原版一模一样
 
如何办理(uoit毕业证书)加拿大安大略理工大学毕业证文凭证书录取通知原版一模一样
如何办理(uoit毕业证书)加拿大安大略理工大学毕业证文凭证书录取通知原版一模一样如何办理(uoit毕业证书)加拿大安大略理工大学毕业证文凭证书录取通知原版一模一样
如何办理(uoit毕业证书)加拿大安大略理工大学毕业证文凭证书录取通知原版一模一样
 

Western Works Construction Liaison Committee Meeting - January 2018

  • 2. Agenda • Caledonia Station • Keelesdale Station • West Portal & Elevated Guideway • Mount Dennis Station • Railway Corridor • Eglinton Maintenance & Storage Facility 2
  • 3. Caledonia Station Update Winter 2018 • Continue dewatering installation (first round is complete) • Continue deep excavation • Tunnel demolition 3
  • 4. Long-term Construction Staging 4 Until 2021 TRUCK ENTRY & EGRESS TRUCK ENTRY & EGRESS
  • 5. Keelesdale Station: ongoing works • Excavation under the deck, Main Entrance, 2nd Entrance, 3rd Entrance and TPSS • Tieback installation level D started • Second shift is intermittently working from 5:00 p.m. to 2:00 a.m. welding, and move earth to entrances for removal during the day. 5 Tunnel break through section filling to springline Drilling Tiebacks Below the intersection at Level C Excavating at the Traction Power Substation Level D
  • 6. 6 West Portal: ongoing work • Utility relocation works for Elevated Guideway – storm line is re-commissioned • Elevated Guideway foundation work (ongoing), superstructure and piers to start early January • Cast in place retaining wall for the new Eglinton Ave realignment on going, walls and foundations • H Piling work to be completed by mid-February Installing formwork at cast in place wall Concrete pour for pier 4 column Excavation and backfilling of cast in place wall
  • 7. 7 Elevated Guideway: Black Creek Drive Lane Closures Construction Stage • One (1) long-term median curb lane closure south of Eglinton Avenue • Two (2) long-term lane closures north of Eglinton Avenue along Black Creek Drive • Closures to occur late January for 8 months (pending City council approval) • Widening of the curbs along the northeast and southwest corner are required to facilitate truck/bus westbound right turns and provide adequate room for receiving traffic. • Complete closure Black Creek Drive – two (2) nights weekend 10:00 p.m. to 6:00 a.m. (mid June 2018) will be required for girder erection and installation. • North pedestrian crossing at the Eglinton Avenue and Black Creek Drive intersection will be closed. • Haul routes to be confirmed
  • 8. 8 Elevated Guideway: Black Creek Drive Lane Closures
  • 9. Construction Stage • West of Black Creek Drive to the West Portal girder installation and staging area • Complete closure of Black Creek Drive to Municipal Drive for girder installation – two (2) weekends Friday to Monday 10:00 p.m. to 5:00 a.m. (mid June 2018) • Work to take approximately two (2) weeks 9 Elevated Guideway: Girder Installation
  • 10. Mount Dennis Station: ongoing works • Station box concrete structure & main entrance • Structural steel starting at station box • Photography Drive Bridge south abutment and center pier formwork and rebar • Photography Drive Bridge girders mid-April, Eglinton Avenue shutdown required (two consecutives weekend requires City Council approval), haul routes to be confirmed • Building 9 foundations preparing permanent foundation • Guestville ductbank works (see attached PPT.) 10 Closing formwork & prep for pour – retaining wall #1 Pedestrian tunnel – forming starter wall Tail Track Slab – South and West perimeter walls
  • 11. 11 Mount Dennis Station: Utility Installation Hollis Street • Installing new sewer lines via a manhole in the intersection of Weston Rd and Hollis St, road patching restoration. • Lane closures of Hollis St at Weston Rd will be required. • Sidewalks will remain open for pedestrians to access Hollis St and Scotia Bank. • A paid-duty officer (PDO) will be in place to provide traffic control as required. Date to be confirmed as to when this work will start.
  • 12. Railway Corridor: ongoing work 12 • Center temporary shoring wall excavation & tie-backs • LRT and pedestrian tunnel construction excavation • Work within the rail corridor will occur during the hours of 7:00 AM to 11:00 PM • Precast tunnel sections – delivery March via Ray Avenue, minimal traffic disruptions (none on Eglinton Avenue), haul route to be confirmed Tie back installation ongoing for 2nd level Welding of walers on the centre shoring wallExcavation to bottom of 2nd level complete
  • 13. 13 Maintenance & Storage Facility : ongoing works • Wall & roof cladding for Maintenance Building • Formwork, rebar & concrete placement – floor slab in Maintenance Building • Site services – ductbanks and Operations Control Centre foundations • Yard Bridge construction – precast retaining wall erection Concrete pour at Handover Platform Louvres installation at electrical room.Layout for Center Rail Columns in Pit #1