The document provides updates on construction progress at the Cedarvale and Forest Hill stations for the Eglinton Crosstown project in January 2018. At Cedarvale station, crossover section construction was complete and noise monitoring and traffic deck installation were ongoing, with backfill and shoring work upcoming. At Forest Hill station, support of excavation for the south station box was ongoing for three more months and wet utility relocation was continuing through 2018, with hydro utility relocation in February 2018 and north station box support of excavation beginning in June 2018.