2. Agenda
• Caledonia Station
• Keelesdale Station
• West Portal & Elevated Guideway
• Tunnel Fit Out
• Mount Dennis Station
• Railway Corridor
• Eglinton Maintenance & Storage Facility
2
3. 3
Caledonia Station Update
November – December 2017
• Dewatering (ongoing throughout construction period)
• Deep excavation (starting at 6:00 a.m.)
• Tunnel demolition (starting November 29 for approx. three months)
6. Keelesdale Concept: Aerial View
1
2
3
4
5
1. Main Entrance
4. Traction Power Substation (TPSS)
2. Third Entrance
5. Bus Loop
3. Secondary Entrance
6
7. Keelesdale Station: ongoing works
• Excavation under the deck at Main, 2nd and 3rd Entrance
• Tieback installation level C ongoing
• Second shift is intermittently working from 5:00 p.m. to 2:00 a.m welding, and move
earth to entrances for removal during the day
• Getting ready to break through the tunnels to excavate for the station platform
7
9. 9
West Portal: ongoing work
• Utility relocation works for Elevated Guideway – Storm line is re-commissioned and
foundation work (ongoing)
• To follow: Cast in Place Retaining Wall is to start for the New Eglinton Realignment and
the Elevated Guideway formwork is schedule to start middle of November
10. Tunnel Fit Out: ongoing work
10
• Mid to late in 2017, small portion of track installed in tunnel (TBD between the West
Portal and Keelesdale Station)
• This section of track will be the test section for the tunnel fit out.
• Majority of track will be installed in the tunnels after the station box construction
completion across the line
11. 1
2
3
4
5
6 7
8
Mount Dennis Station Concept: Aerial View
1. Main Entrance
5. Third Entrance
2. Bus Loop
6. Secondary Entrance
3. Operations Building
7. Photography Drive Bridge
4. Maintenance Building
8. Rail Corridor
11
12. Mount Dennis Station: ongoing works
• Foundations – Mount Dennis station box concrete structure & main entrance (ongoing)
• Photography Drive Bridge – south abutment piling (ongoing)
• Building 9 foundations ( Building moved back on Nov 13th )
12
14. Railway Corridor: ongoing work
14
Phase 3
• Center Temporary Shoring Wall Excavation &
Tie-backs (ongoing)
• LRT and Pedestrian Tunnel Construction
Excavation (ongoing)
• Work within the rail corridor will occur
during the hours of 7:00 AM to 11:00 PM
15. Maintenance & Storage Facility Concept: Aerial View
1
2
3
4
1. Vehicle Cleaning Staff Building
4. Operations Control Centre
2. Vehicle Cleaning & Inspection Facility (VCIF)
5. Operations Company (OPSCO)
5
3. Maintenance Building
15
16. 16
Maintenance & Storage Facility : ongoing works
• Wall & Roof Cladding for Maintenance Building (ongoing)
• Formwork, rebar and concrete placement for floor slab in Maintenance Building
(ongoing)
• Site Services – Ductbanks and OCS Foundations (ongoing)
• Yard Bridge Construction – Precast Retaining Wall Erection (ongoing)
17. 17
• Installation of Ballasted track and Special Track work
• Production of Continuous Welded Rail through Flash butt Welding process
• Thermite Welding Activities
• Installation of the first meter of track in the VCIF Building
Maintenance & Storage Facility: Track Installation