This document provides an update on construction progress for the Eglinton Crosstown LRT project. For Eglinton Station, recent works include subway closure works at Berwick Avenue and ongoing shoring. Upcoming works include Toronto Hydro relocation and additional weekend subway closures. For Mount Pleasant Station, renderings show the concept and entrance locations. Current construction activities include piling, storm sewer installation, and utility relocation. Traffic changes and construction staging shifts are planned for mid-March and early April to accommodate ongoing work.