SlideShare a Scribd company logo
1 of 24
Download to read offline
July 8, 2020
Eglinton Crosstown LRT
Chaplin-Avenue CLC
Chaplin Station
CHAPLIN STATION UPDATE
3INSERT FOOTER
Activity Location Approx. Date & Duration What to Expect
Dewatering System Maintenance
Cleaning of tanks using hydro-vacuum
truck
Latimer Ave and Eglinton Ave work
zone and Shoppers Drug Mart
parking lot
Weekly or as needed into 2021
5:00 a.m. โ€“ 8:00 a.m. for one (1) hour
โ€ข Noise from hydro-vacuum truck
โ€ข Occupancy of the Shoppers Drug
Mart parking lot
Extended Construction Hours for
Deep Excavation and Deliveries
Station Box beneath Eglinton Ave
from the Main and Tertiary
Entrances
Main Entrance:
โ€ข Structural steel deliveries
Mon โ€“ Sat, 5:00 a.m. โ€“ 1:00 a.m.
Through July 2020
โ€ข Rebar Installation
Mon โ€“ Fri, 4:00 a.m. start
Through July 2020 (as needed)
Tertiary Entrance:
โ€ข Deep excavation of station box,
loading and hauling
Mon โ€“ Sat, 5:00 a.m. โ€“ 1:00 a.m.
Through early July 2020
โ€ข Structural steel deliveries
Mon โ€“ Sat, 5:00 a.m. โ€“ 1:00 a.m.
Through early August 2020
โ€ข Early morning/late night noise from
construction activity
โ€ข Periodically chipping of hardened
material and concrete within the
excavation will be required โ€“ noise
and vibration may be experienced
โ€ข Truck activity around work zones
โ€ข Use of excavators, cranes and other
construction equipment
Tertiary Entrance Construction
Waterproofing, removal of separation
wall
South side of Eglinton Ave, east of
Chaplin Cres and adjacent Toronto
Fire Station 135
Underway into Winter 2021
CHAPLIN STATION UPDATE
4INSERT FOOTER
Activity Location Approx. Date & Duration What to Expect
Main Entrance Construction
Rebar installation and formwork
North side of Eglinton Ave between
Chaplin Cres and Gilgorm Rd
Through winter 2021
โ€ข Early morning/late night noise from
construction activity
โ€ข Truck activity around work zones
โ€ข Use of excavators, cranes and other
construction equipment
Concrete Works
Main and Tertiary Entrances; Station
Box
Periodically through 2020
โ€ข Use of concrete pumps
โ€ข Frequent concrete trucks
โ€ข Early morning/late night noise from
construction activity
Station Box Construction
Rebar installation, THESL work (roof)
Beneath Eglinton Ave Underway through spring 2021
โ€ข Truck activity around work zones
โ€ข Use of excavators, cranes and other
construction equipment
Chaplin Cres Closure of Traffic
Bridge Removal
Chaplin Cres between Eglinton Ave
and Russell Hill Rd
Extended to July 31, 2020
โ€ข Closure of Chaplin Cres
โ€ข TTC 14 Glencairn bus detour
CHAPLIN CRES ROAD CLOSURE
5
โ€ข Chaplin Cres will be closed between Eglinton Ave and Russell Hill Rd beginning June 8 for approximately six (6) weeks
โ€ข The closure is required to complete remove of the existing traffic bridge, back-fill the area, reinstate dry and wet utilities, pave the area
and line paint (note: this paving will be temporary โ€“ final road restoration will begin in mid 2021)
โ€ข One lane of traffic in each direction on Eglinton Ave will be maintained
โ€ข Southbound traffic on Chaplin Cres will have to turn right or left at Eglinton Ave
โ€ข Local access on Chaplin Cres will be maintained from the south end of the closure
โ€ข The Chaplin-Russell Hill laneway will be closed, local vehicle and pedestrian traffic excepted
โ€ข The west crosswalk will be temporary closed and the north crosswalk will be temporarily reinstated; the south crosswalk will be shifted
south
โ€ข TTC bus route 14 Glencairn will be on detour
โ€ข Parking on Russell Hill Rd will be temporarily prohibited to accommodate the bus detour
INSERT FOOTER
CURRENT TRAFFIC CONFIGURATION
6CENTRAL WEST WORKS MONTHLY MEETING
Until July 31, 2020
CONSTRUCTION PROGRESS PHOTOS
7CENTRAL WEST WORKS MONTHLY MEETING
WATERPROOFING
TERTIARY ENTRANCE
MAIN ENTRANCE
CONCOURSE SLAB
Avenue Station
AVENUE STATION UPDATE
9INSERT FOOTER
Activity Location Approx. Date & Duration What to Expect
Final lining
Waterproofing, rebar
installation, and mechanical
electrical works
Throughout all station areas Underway through to late-2020
โ€ข Deliveries at the main and
secondary entrances
Concrete Pours
Between the Main and Secondary
Entrances
Three times per week for approx.
12 โ€“ 18 hours through to 2021
โ€ข Concrete truck activity
โ€ข Occupation of the westbound
curb lane during some pours
Eglinton Connects
Streetscape and Cycle Track
Construction
Eglinton Ave between Lascelles
Blvd and Duplex Ave
Underway through to early 2021
โ€ข Eglinton reduced to one lane
in each direction between
Lascelles Blvd & Duplex Ave
โ€ข Use of excavator, hydro-vac
and concrete trucks
Dewatering Well
Maintenance
Eglinton Ave between Braemar Ave
and Lascelles Blvd
Periodically through 2021; 9:00
a.m. โ€“ 4:00 p.m.
โ€ข Road occupancy around well
โ€ข Use of hydro-vac truck
Monitoring Work
Eglinton Ave between Braemar Ave
and Lascelles Blvd
Periodically through 2021 โ€ข Short-term road occupancy
CURRENT TRAFFIC CONFIGURATION
10
Through September 2021
INSERT FOOTER
EGLINTON CONNECTS โ€“ SCOPE OF WORK
11
โ€ข CTS will implement Eglinton Connects within immediate station areas and continuously
between Avenue Road and Holly Street
โ€ข Implementation of Eglinton Connects began July 7, 2020 between Lascelles Blvd and Duplex
Ave
โ€ข The scope work includes:
INSERT FOOTER
โœ“ Widened sidewalks
โœ“ Separated cycle tracks
โœ“ On-street parking
โœ“ Full restoration of the roadway, curbs and sidewalks along Eglinton Ave
โœ“ Increased greenery and street furnishings
โœ“ Reduced traffic lanes (to accommodate wider sidewalks and cycle tracks)
TRAFFIC CONFIGURATION โ€“ STAGE 1
12INSERT FOOTER
As of Tuesday, July 7, 2020
TRAFFIC CONFIGURATION โ€“ STAGE 2
13INSERT FOOTER
TRAFFIC CONFIGURATION โ€“ STAGE 3
14INSERT FOOTER
TRAFFIC CONFIGURATION โ€“ STAGE 4
15INSERT FOOTER
Through to early 2021
EGLINTON AVE FUTURE CONFIGURATION โ€“ ORIOLE PKWY TO LASCELLES BLVD
16INSERT FOOTER
EGLINTON AVE FUTURE CONFIGURATION โ€“ LASCELLES BLVD โ€“ DUPLEX AVE
17INSERT FOOTER
CONSTRUCTION OVERVIEW
18
โ€ข Construction of the new Eglinton Streetscape and Cycle Track between Avenue Rd and Duplex
Ave will take place in phases beginning with Phase 1 Edith Rd to Duplex Ave on July 6, 2020
โ€ข Construction will take place Monday โ€“ Saturday, 7:00 a.m. โ€“ 7:00 p.m. with periodic overnight
work
โ€ข Construction activities will include excavation of the roadway and sidewalk, utility reinstatement,
concrete work, paving, compaction, landscaping and installation of street furnishings
โ€ข Work will be carried out in several traffic stages with minor adjustments between stages as
required
โ€ข Construction of the new Eglinton Streetscape and Cycle Track between Avenue Rd and Duplex
Ave will continue into 2021
INSERT FOOTER
BIA FURNITURE REMOVALS
19
124 Eglinton Ave W:
INSERT FOOTER
1 2 3
6
54
7
BIA FURNITURE REMOVALS
20
174 Eglinton Ave W:
INSERT FOOTER
158 Eglinton Ave W:
1 1
TTC SHELTER REMOVALS
21INSERT FOOTER
75 Eglinton Ave W
โ€ข Temporary stops and ramps will be installed to maintain access for TTC riders
90 Eglinton Ave W 225 Eglinton Ave W
CONSTRUCTION PROGRESS PHOTOS
22INSERT FOOTER
ARCH WATERPROOFING ARCH CONCRETE WORKS
CONSTRUCTION PROGRESS PHOTOS
23INSERT FOOTER
AVENUE MAIN ENTRANCE
Avenue & Chaplin CLC - Construction Update: July 8, 2020

More Related Content

What's hot

Chaplin Avenue CLC Presentation Deck - Jan 8 2020
  Chaplin Avenue CLC Presentation Deck - Jan 8 2020  Chaplin Avenue CLC Presentation Deck - Jan 8 2020
Chaplin Avenue CLC Presentation Deck - Jan 8 2020
Crosstown TO
ย 
Central West Open House
Central West Open HouseCentral West Open House
Central West Open House
Crosstown TO
ย 
Chaplin & Avenue CLC - Construction Update - April 4, 2018
Chaplin & Avenue CLC - Construction Update - April 4, 2018Chaplin & Avenue CLC - Construction Update - April 4, 2018
Chaplin & Avenue CLC - Construction Update - April 4, 2018
Crosstown TO
ย 
Eglinton & Mount Pleasant Construction Liaison Committee Meeting - March 2019
Eglinton & Mount Pleasant Construction Liaison Committee Meeting - March 2019Eglinton & Mount Pleasant Construction Liaison Committee Meeting - March 2019
Eglinton & Mount Pleasant Construction Liaison Committee Meeting - March 2019
Crosstown TO
ย 
Public Meeting of Facility Services Building at Eglinton Station - February 2018
Public Meeting of Facility Services Building at Eglinton Station - February 2018Public Meeting of Facility Services Building at Eglinton Station - February 2018
Public Meeting of Facility Services Building at Eglinton Station - February 2018
Crosstown TO
ย 
Avenue & Chaplin CLC - Construction Update: May 6, 2020
Avenue & Chaplin CLC - Construction Update: May 6, 2020Avenue & Chaplin CLC - Construction Update: May 6, 2020
Avenue & Chaplin CLC - Construction Update: May 6, 2020
Crosstown TO
ย 
Pharmacy to Kennedy Construction Liaison Committee Meeting - Sept 2019
Pharmacy to Kennedy Construction Liaison Committee Meeting - Sept 2019Pharmacy to Kennedy Construction Liaison Committee Meeting - Sept 2019
Pharmacy to Kennedy Construction Liaison Committee Meeting - Sept 2019
Crosstown TO
ย 
Chaplin - Avenue Construction Liaison Committee - July 2018
Chaplin - Avenue Construction Liaison Committee - July 2018Chaplin - Avenue Construction Liaison Committee - July 2018
Chaplin - Avenue Construction Liaison Committee - July 2018
Crosstown TO
ย 
Pharmacy - Kennedy Construction Liaison Committee Meeting - May 2018
Pharmacy - Kennedy Construction Liaison Committee Meeting - May 2018Pharmacy - Kennedy Construction Liaison Committee Meeting - May 2018
Pharmacy - Kennedy Construction Liaison Committee Meeting - May 2018
Crosstown TO
ย 
Central East Open House Spring 2019
Central East Open House Spring 2019Central East Open House Spring 2019
Central East Open House Spring 2019
Crosstown TO
ย 
CLC presentation deck Brentcliffe to Victoria Park (July 9 2020)
CLC presentation deck Brentcliffe to Victoria Park (July 9 2020)CLC presentation deck Brentcliffe to Victoria Park (July 9 2020)
CLC presentation deck Brentcliffe to Victoria Park (July 9 2020)
Crosstown TO
ย 
Pharmacy to kennedy construction liaison committee meeting - June 2018
Pharmacy to kennedy construction liaison committee meeting - June 2018Pharmacy to kennedy construction liaison committee meeting - June 2018
Pharmacy to kennedy construction liaison committee meeting - June 2018
Crosstown TO
ย 
Chaplin - Avenue Construction Liaison Committee Meeting - March 2018
Chaplin - Avenue Construction Liaison Committee Meeting - March 2018Chaplin - Avenue Construction Liaison Committee Meeting - March 2018
Chaplin - Avenue Construction Liaison Committee Meeting - March 2018
Crosstown TO
ย 

What's hot (20)

Chaplin Avenue CLC Presentation Deck - Jan 8 2020
  Chaplin Avenue CLC Presentation Deck - Jan 8 2020  Chaplin Avenue CLC Presentation Deck - Jan 8 2020
Chaplin Avenue CLC Presentation Deck - Jan 8 2020
ย 
Central West Open House
Central West Open HouseCentral West Open House
Central West Open House
ย 
Chaplin & Avenue CLC - Construction Update - April 4, 2018
Chaplin & Avenue CLC - Construction Update - April 4, 2018Chaplin & Avenue CLC - Construction Update - April 4, 2018
Chaplin & Avenue CLC - Construction Update - April 4, 2018
ย 
Central West Spring Open House Presentation Deck - March 3, 2020
Central West Spring Open House Presentation Deck - March 3, 2020 Central West Spring Open House Presentation Deck - March 3, 2020
Central West Spring Open House Presentation Deck - March 3, 2020
ย 
Central Spring Open House Presentation Deck - March 23 2020
Central Spring Open House Presentation Deck - March 23 2020Central Spring Open House Presentation Deck - March 23 2020
Central Spring Open House Presentation Deck - March 23 2020
ย 
Avenue & Chaplin CLC - Construction Update: March 3, 2021
Avenue & Chaplin CLC - Construction Update: March 3, 2021Avenue & Chaplin CLC - Construction Update: March 3, 2021
Avenue & Chaplin CLC - Construction Update: March 3, 2021
ย 
Eglinton & Mount Pleasant Construction Liaison Committee Meeting - March 2019
Eglinton & Mount Pleasant Construction Liaison Committee Meeting - March 2019Eglinton & Mount Pleasant Construction Liaison Committee Meeting - March 2019
Eglinton & Mount Pleasant Construction Liaison Committee Meeting - March 2019
ย 
Fall Virtual Open House: West - Mount Dennis to Avenue Stations
Fall Virtual Open House: West - Mount Dennis to Avenue StationsFall Virtual Open House: West - Mount Dennis to Avenue Stations
Fall Virtual Open House: West - Mount Dennis to Avenue Stations
ย 
Public Meeting of Facility Services Building at Eglinton Station - February 2018
Public Meeting of Facility Services Building at Eglinton Station - February 2018Public Meeting of Facility Services Building at Eglinton Station - February 2018
Public Meeting of Facility Services Building at Eglinton Station - February 2018
ย 
Brentcliffe - Victoria Park Construction Liaison Committee Meeting
Brentcliffe - Victoria Park Construction Liaison Committee MeetingBrentcliffe - Victoria Park Construction Liaison Committee Meeting
Brentcliffe - Victoria Park Construction Liaison Committee Meeting
ย 
Avenue & Chaplin CLC - Construction Update: May 6, 2020
Avenue & Chaplin CLC - Construction Update: May 6, 2020Avenue & Chaplin CLC - Construction Update: May 6, 2020
Avenue & Chaplin CLC - Construction Update: May 6, 2020
ย 
Pharmacy to Kennedy Construction Liaison Committee Meeting - Sept 2019
Pharmacy to Kennedy Construction Liaison Committee Meeting - Sept 2019Pharmacy to Kennedy Construction Liaison Committee Meeting - Sept 2019
Pharmacy to Kennedy Construction Liaison Committee Meeting - Sept 2019
ย 
Chaplin - Avenue Construction Liaison Committee - July 2018
Chaplin - Avenue Construction Liaison Committee - July 2018Chaplin - Avenue Construction Liaison Committee - July 2018
Chaplin - Avenue Construction Liaison Committee - July 2018
ย 
Pharmacy - Kennedy Construction Liaison Committee Meeting - May 2018
Pharmacy - Kennedy Construction Liaison Committee Meeting - May 2018Pharmacy - Kennedy Construction Liaison Committee Meeting - May 2018
Pharmacy - Kennedy Construction Liaison Committee Meeting - May 2018
ย 
Central East Open House Spring 2019
Central East Open House Spring 2019Central East Open House Spring 2019
Central East Open House Spring 2019
ย 
Pharmacy to Kennedy Construction Liaison Committee Meeting
Pharmacy to Kennedy Construction Liaison Committee MeetingPharmacy to Kennedy Construction Liaison Committee Meeting
Pharmacy to Kennedy Construction Liaison Committee Meeting
ย 
CLC presentation deck Brentcliffe to Victoria Park (July 9 2020)
CLC presentation deck Brentcliffe to Victoria Park (July 9 2020)CLC presentation deck Brentcliffe to Victoria Park (July 9 2020)
CLC presentation deck Brentcliffe to Victoria Park (July 9 2020)
ย 
Eastern Works Open House - October 24, 2019
Eastern Works Open House  - October 24, 2019Eastern Works Open House  - October 24, 2019
Eastern Works Open House - October 24, 2019
ย 
Pharmacy to kennedy construction liaison committee meeting - June 2018
Pharmacy to kennedy construction liaison committee meeting - June 2018Pharmacy to kennedy construction liaison committee meeting - June 2018
Pharmacy to kennedy construction liaison committee meeting - June 2018
ย 
Chaplin - Avenue Construction Liaison Committee Meeting - March 2018
Chaplin - Avenue Construction Liaison Committee Meeting - March 2018Chaplin - Avenue Construction Liaison Committee Meeting - March 2018
Chaplin - Avenue Construction Liaison Committee Meeting - March 2018
ย 

Similar to Avenue & Chaplin CLC - Construction Update: July 8, 2020

CLC Deck Brentcliffe Road to Victoria Park Avenue (Sept 3, 2020)
CLC Deck Brentcliffe Road to Victoria Park Avenue (Sept 3, 2020)CLC Deck Brentcliffe Road to Victoria Park Avenue (Sept 3, 2020)
CLC Deck Brentcliffe Road to Victoria Park Avenue (Sept 3, 2020)
Crosstown TO
ย 
Pharmacy to Kennedy Construction Liaision Committee Meeting - Sep 2020
Pharmacy to Kennedy Construction Liaision Committee Meeting - Sep 2020Pharmacy to Kennedy Construction Liaision Committee Meeting - Sep 2020
Pharmacy to Kennedy Construction Liaision Committee Meeting - Sep 2020
Crosstown TO
ย 
Pharmacy to Kennedy Construction Liaison Meeting - July 2020
Pharmacy to Kennedy Construction Liaison Meeting - July 2020Pharmacy to Kennedy Construction Liaison Meeting - July 2020
Pharmacy to Kennedy Construction Liaison Meeting - July 2020
Crosstown TO
ย 
Brentcliffe-Victoria Park Construction Liaison Committee (CLC) Meeting - May ...
Brentcliffe-Victoria Park Construction Liaison Committee (CLC) Meeting - May ...Brentcliffe-Victoria Park Construction Liaison Committee (CLC) Meeting - May ...
Brentcliffe-Victoria Park Construction Liaison Committee (CLC) Meeting - May ...
Crosstown TO
ย 
Central open house - oct 2019
Central open house - oct 2019Central open house - oct 2019
Central open house - oct 2019
Crosstown TO
ย 

Similar to Avenue & Chaplin CLC - Construction Update: July 8, 2020 (20)

CLC Deck Brentcliffe Road to Victoria Park Avenue (Sept 3, 2020)
CLC Deck Brentcliffe Road to Victoria Park Avenue (Sept 3, 2020)CLC Deck Brentcliffe Road to Victoria Park Avenue (Sept 3, 2020)
CLC Deck Brentcliffe Road to Victoria Park Avenue (Sept 3, 2020)
ย 
CLC Deck Brentcliffe Road to Victoria Park Avenue (Sept 3, 2020)
CLC Deck Brentcliffe Road to Victoria Park Avenue (Sept 3, 2020)CLC Deck Brentcliffe Road to Victoria Park Avenue (Sept 3, 2020)
CLC Deck Brentcliffe Road to Victoria Park Avenue (Sept 3, 2020)
ย 
Leaside laird clc - november 9, 2020
Leaside laird clc - november 9, 2020Leaside laird clc - november 9, 2020
Leaside laird clc - november 9, 2020
ย 
Brentcliffe - Victoria Park Construction Liaison Committee (CLC) Meeting
Brentcliffe - Victoria Park Construction Liaison Committee (CLC) MeetingBrentcliffe - Victoria Park Construction Liaison Committee (CLC) Meeting
Brentcliffe - Victoria Park Construction Liaison Committee (CLC) Meeting
ย 
Pharmacy to Kennedy Construction Liaision Committee Meeting - Sep 2020
Pharmacy to Kennedy Construction Liaision Committee Meeting - Sep 2020Pharmacy to Kennedy Construction Liaision Committee Meeting - Sep 2020
Pharmacy to Kennedy Construction Liaision Committee Meeting - Sep 2020
ย 
Pharmacy to Kennedy Construction Liaison Meeting - July 2020
Pharmacy to Kennedy Construction Liaison Meeting - July 2020Pharmacy to Kennedy Construction Liaison Meeting - July 2020
Pharmacy to Kennedy Construction Liaison Meeting - July 2020
ย 
Chaplin-Avenue CLC - May 4 2022-compressed.pptx
Chaplin-Avenue CLC - May 4 2022-compressed.pptxChaplin-Avenue CLC - May 4 2022-compressed.pptx
Chaplin-Avenue CLC - May 4 2022-compressed.pptx
ย 
Cedarvale- Forest Hill Construction Update (July 29, 2020)
Cedarvale- Forest Hill Construction Update (July 29, 2020)Cedarvale- Forest Hill Construction Update (July 29, 2020)
Cedarvale- Forest Hill Construction Update (July 29, 2020)
ย 
Central Eastern Works Open House - October 2019
Central Eastern Works Open House - October 2019Central Eastern Works Open House - October 2019
Central Eastern Works Open House - October 2019
ย 
Brentcliffe-Victoria Park Construction Liaison Committee (CLC) Meeting - May ...
Brentcliffe-Victoria Park Construction Liaison Committee (CLC) Meeting - May ...Brentcliffe-Victoria Park Construction Liaison Committee (CLC) Meeting - May ...
Brentcliffe-Victoria Park Construction Liaison Committee (CLC) Meeting - May ...
ย 
Chaplin-Avenue CLC - March 2, 2022-compressed.pptx
Chaplin-Avenue CLC - March 2, 2022-compressed.pptxChaplin-Avenue CLC - March 2, 2022-compressed.pptx
Chaplin-Avenue CLC - March 2, 2022-compressed.pptx
ย 
Chaplin-Avenue CLC - Presentation Deck - July 6, 2022.pdf
Chaplin-Avenue CLC - Presentation Deck - July 6, 2022.pdfChaplin-Avenue CLC - Presentation Deck - July 6, 2022.pdf
Chaplin-Avenue CLC - Presentation Deck - July 6, 2022.pdf
ย 
Brentcliffe - Victoria Park Construction Liaison Committee Meeting
Brentcliffe - Victoria Park Construction Liaison Committee MeetingBrentcliffe - Victoria Park Construction Liaison Committee Meeting
Brentcliffe - Victoria Park Construction Liaison Committee Meeting
ย 
Avenue & Chaplin CLC - Construction Update: November 4, 2020
Avenue & Chaplin CLC - Construction Update: November 4, 2020Avenue & Chaplin CLC - Construction Update: November 4, 2020
Avenue & Chaplin CLC - Construction Update: November 4, 2020
ย 
Leaside - Laird Construction Liaison Committee (CLC) Meeting - May 2020
Leaside - Laird Construction Liaison Committee (CLC) Meeting - May 2020Leaside - Laird Construction Liaison Committee (CLC) Meeting - May 2020
Leaside - Laird Construction Liaison Committee (CLC) Meeting - May 2020
ย 
Brentcliffe - Victoria Park Construction Liaison Committee (CLC) Meeting
Brentcliffe - Victoria Park Construction Liaison Committee (CLC) MeetingBrentcliffe - Victoria Park Construction Liaison Committee (CLC) Meeting
Brentcliffe - Victoria Park Construction Liaison Committee (CLC) Meeting
ย 
Central open house - oct 2019
Central open house - oct 2019Central open house - oct 2019
Central open house - oct 2019
ย 
Eglinton and Mount Pleasant CLC - March 10, 2021
Eglinton and Mount Pleasant CLC - March 10, 2021Eglinton and Mount Pleasant CLC - March 10, 2021
Eglinton and Mount Pleasant CLC - March 10, 2021
ย 
Avenue & Chaplin CLC - Construction Update: May 5, 2021
Avenue & Chaplin CLC - Construction Update: May 5, 2021Avenue & Chaplin CLC - Construction Update: May 5, 2021
Avenue & Chaplin CLC - Construction Update: May 5, 2021
ย 
Avenue & Chaplin CLC - Construction Update: September 1, 2021
Avenue & Chaplin CLC - Construction Update: September 1, 2021Avenue & Chaplin CLC - Construction Update: September 1, 2021
Avenue & Chaplin CLC - Construction Update: September 1, 2021
ย 

More from Crosstown TO

More from Crosstown TO (20)

Western Works CLC - January 17, 2023.pdf
Western Works CLC - January 17, 2023.pdfWestern Works CLC - January 17, 2023.pdf
Western Works CLC - January 17, 2023.pdf
ย 
Western Works CLC - May 16, 2023
 Western Works CLC - May 16, 2023 Western Works CLC - May 16, 2023
Western Works CLC - May 16, 2023
ย 
Western Works CLC - March, 21 2023
Western Works CLC - March, 21 2023 Western Works CLC - March, 21 2023
Western Works CLC - March, 21 2023
ย 
Leaside-Laird CLC - May 8, 2023.pdf
Leaside-Laird CLC - May 8, 2023.pdfLeaside-Laird CLC - May 8, 2023.pdf
Leaside-Laird CLC - May 8, 2023.pdf
ย 
Eglinton - Mt Pleasant CLC - May 10, 2023.pdf
Eglinton - Mt Pleasant CLC - May 10, 2023.pdfEglinton - Mt Pleasant CLC - May 10, 2023.pdf
Eglinton - Mt Pleasant CLC - May 10, 2023.pdf
ย 
Chaplin-Avenue CLC - May 3 2023 Updated.pptx
Chaplin-Avenue CLC - May 3 2023 Updated.pptxChaplin-Avenue CLC - May 3 2023 Updated.pptx
Chaplin-Avenue CLC - May 3 2023 Updated.pptx
ย 
CLC Deck - Brentcliffe to Victoria Park - May 4 2023 - Compressed.pptx
CLC Deck - Brentcliffe to Victoria Park - May 4 2023 - Compressed.pptxCLC Deck - Brentcliffe to Victoria Park - May 4 2023 - Compressed.pptx
CLC Deck - Brentcliffe to Victoria Park - May 4 2023 - Compressed.pptx
ย 
Pharmacy to Kennedy CLC presentation deck - Janaury 31, 2023.pptx
Pharmacy to Kennedy CLC presentation deck - Janaury 31, 2023.pptxPharmacy to Kennedy CLC presentation deck - Janaury 31, 2023.pptx
Pharmacy to Kennedy CLC presentation deck - Janaury 31, 2023.pptx
ย 
CLC Pharmacy to Kennedy - March 28, 2023 - Compressed.pptx
CLC Pharmacy to Kennedy - March 28, 2023 - Compressed.pptxCLC Pharmacy to Kennedy - March 28, 2023 - Compressed.pptx
CLC Pharmacy to Kennedy - March 28, 2023 - Compressed.pptx
ย 
CLC Deck - Brentcliffe to Victoria Park - March 2, 2023 - Compressed.pptx
CLC Deck - Brentcliffe to Victoria Park - March 2, 2023 - Compressed.pptxCLC Deck - Brentcliffe to Victoria Park - March 2, 2023 - Compressed.pptx
CLC Deck - Brentcliffe to Victoria Park - March 2, 2023 - Compressed.pptx
ย 
Chaplin-Avenue CLC - March 1, 2023.pptx
Chaplin-Avenue CLC - March 1, 2023.pptxChaplin-Avenue CLC - March 1, 2023.pptx
Chaplin-Avenue CLC - March 1, 2023.pptx
ย 
Leaside-Laird CLC - March 13, 2023.pdf
Leaside-Laird CLC - March 13, 2023.pdfLeaside-Laird CLC - March 13, 2023.pdf
Leaside-Laird CLC - March 13, 2023.pdf
ย 
CLC Deck - Brentcliffe to Victoria Park - March 2, 2023 - Compressed.pptx
CLC Deck - Brentcliffe to Victoria Park - March 2, 2023 - Compressed.pptxCLC Deck - Brentcliffe to Victoria Park - March 2, 2023 - Compressed.pptx
CLC Deck - Brentcliffe to Victoria Park - March 2, 2023 - Compressed.pptx
ย 
Eglinton - Mount Pleasant CLC - March 8, 2023.pdf
Eglinton - Mount Pleasant CLC - March 8, 2023.pdfEglinton - Mount Pleasant CLC - March 8, 2023.pdf
Eglinton - Mount Pleasant CLC - March 8, 2023.pdf
ย 
Chaplin-Avenue CLC - November 2 2022 compressed.pptx
Chaplin-Avenue CLC - November 2 2022 compressed.pptxChaplin-Avenue CLC - November 2 2022 compressed.pptx
Chaplin-Avenue CLC - November 2 2022 compressed.pptx
ย 
Chaplin-Avenue CLC - January 11 2023 (002).pptx
Chaplin-Avenue CLC - January 11 2023 (002).pptxChaplin-Avenue CLC - January 11 2023 (002).pptx
Chaplin-Avenue CLC - January 11 2023 (002).pptx
ย 
CLC Deck - Brentcliffe to Victoria Park - January 12, 2023 - Compressed.pptx
CLC Deck - Brentcliffe to Victoria Park - January 12, 2023 - Compressed.pptxCLC Deck - Brentcliffe to Victoria Park - January 12, 2023 - Compressed.pptx
CLC Deck - Brentcliffe to Victoria Park - January 12, 2023 - Compressed.pptx
ย 
Eglinton - Mt Pleasant CLC - January 11, 2023.pdf
Eglinton - Mt Pleasant CLC - January 11, 2023.pdfEglinton - Mt Pleasant CLC - January 11, 2023.pdf
Eglinton - Mt Pleasant CLC - January 11, 2023.pdf
ย 
Leaside-Laird CLC - January 9, 2023.pdf
Leaside-Laird CLC - January 9, 2023.pdfLeaside-Laird CLC - January 9, 2023.pdf
Leaside-Laird CLC - January 9, 2023.pdf
ย 
CLC Deck - Brentcliffe to Victoria Park - November 3 2022.pdf
CLC Deck - Brentcliffe to Victoria Park - November 3 2022.pdfCLC Deck - Brentcliffe to Victoria Park - November 3 2022.pdf
CLC Deck - Brentcliffe to Victoria Park - November 3 2022.pdf
ย 

Recently uploaded

Top profile Call Girls In Haldia [ 7014168258 ] Call Me For Genuine Models We...
Top profile Call Girls In Haldia [ 7014168258 ] Call Me For Genuine Models We...Top profile Call Girls In Haldia [ 7014168258 ] Call Me For Genuine Models We...
Top profile Call Girls In Haldia [ 7014168258 ] Call Me For Genuine Models We...
gajnagarg
ย 
Nagerbazar @ Independent Call Girls Kolkata - 450+ Call Girl Cash Payment 800...
Nagerbazar @ Independent Call Girls Kolkata - 450+ Call Girl Cash Payment 800...Nagerbazar @ Independent Call Girls Kolkata - 450+ Call Girl Cash Payment 800...
Nagerbazar @ Independent Call Girls Kolkata - 450+ Call Girl Cash Payment 800...
HyderabadDolls
ย 
Competitive Advantage slide deck___.pptx
Competitive Advantage slide deck___.pptxCompetitive Advantage slide deck___.pptx
Competitive Advantage slide deck___.pptx
ScottMeyers35
ย 
Call Girls in North Sikkim 9332606886 HOT & SEXY Models beautiful and charmi...
Call Girls in North Sikkim  9332606886 HOT & SEXY Models beautiful and charmi...Call Girls in North Sikkim  9332606886 HOT & SEXY Models beautiful and charmi...
Call Girls in North Sikkim 9332606886 HOT & SEXY Models beautiful and charmi...
Sareena Khatun
ย 
Fun all Day Call Girls in Erode { 9332606886 } VVIP NISHA Call Girls Near 5 S...
Fun all Day Call Girls in Erode { 9332606886 } VVIP NISHA Call Girls Near 5 S...Fun all Day Call Girls in Erode { 9332606886 } VVIP NISHA Call Girls Near 5 S...
Fun all Day Call Girls in Erode { 9332606886 } VVIP NISHA Call Girls Near 5 S...
Sareena Khatun
ย 
Call girls Service Budhwar Peth - 8250092165 Our call girls are sure to provi...
Call girls Service Budhwar Peth - 8250092165 Our call girls are sure to provi...Call girls Service Budhwar Peth - 8250092165 Our call girls are sure to provi...
Call girls Service Budhwar Peth - 8250092165 Our call girls are sure to provi...
Sareena Khatun
ย 

Recently uploaded (20)

Call Girl In Prayagraj Call Girls Service ๐Ÿ‘‰ 6378878445 ๐Ÿ‘‰ Just๐Ÿ“ฒ Call Ruhi Call...
Call Girl In Prayagraj Call Girls Service ๐Ÿ‘‰ 6378878445 ๐Ÿ‘‰ Just๐Ÿ“ฒ Call Ruhi Call...Call Girl In Prayagraj Call Girls Service ๐Ÿ‘‰ 6378878445 ๐Ÿ‘‰ Just๐Ÿ“ฒ Call Ruhi Call...
Call Girl In Prayagraj Call Girls Service ๐Ÿ‘‰ 6378878445 ๐Ÿ‘‰ Just๐Ÿ“ฒ Call Ruhi Call...
ย 
2024: The FAR, Federal Acquisition Regulations, Part 32
2024: The FAR, Federal Acquisition Regulations, Part 322024: The FAR, Federal Acquisition Regulations, Part 32
2024: The FAR, Federal Acquisition Regulations, Part 32
ย 
Top profile Call Girls In Haldia [ 7014168258 ] Call Me For Genuine Models We...
Top profile Call Girls In Haldia [ 7014168258 ] Call Me For Genuine Models We...Top profile Call Girls In Haldia [ 7014168258 ] Call Me For Genuine Models We...
Top profile Call Girls In Haldia [ 7014168258 ] Call Me For Genuine Models We...
ย 
Nagerbazar @ Independent Call Girls Kolkata - 450+ Call Girl Cash Payment 800...
Nagerbazar @ Independent Call Girls Kolkata - 450+ Call Girl Cash Payment 800...Nagerbazar @ Independent Call Girls Kolkata - 450+ Call Girl Cash Payment 800...
Nagerbazar @ Independent Call Girls Kolkata - 450+ Call Girl Cash Payment 800...
ย 
Cheap Call Girls In Hyderabad Phone No ๐Ÿ“ž 9352988975 ๐Ÿ“ž Elite Escort Service Av...
Cheap Call Girls In Hyderabad Phone No ๐Ÿ“ž 9352988975 ๐Ÿ“ž Elite Escort Service Av...Cheap Call Girls In Hyderabad Phone No ๐Ÿ“ž 9352988975 ๐Ÿ“ž Elite Escort Service Av...
Cheap Call Girls In Hyderabad Phone No ๐Ÿ“ž 9352988975 ๐Ÿ“ž Elite Escort Service Av...
ย 
Spring 2024 Issue Punitive and Productive Suffering
Spring 2024 Issue Punitive and Productive SufferingSpring 2024 Issue Punitive and Productive Suffering
Spring 2024 Issue Punitive and Productive Suffering
ย 
Competitive Advantage slide deck___.pptx
Competitive Advantage slide deck___.pptxCompetitive Advantage slide deck___.pptx
Competitive Advantage slide deck___.pptx
ย 
2024: The FAR, Federal Acquisition Regulations, Part 31
2024: The FAR, Federal Acquisition Regulations, Part 312024: The FAR, Federal Acquisition Regulations, Part 31
2024: The FAR, Federal Acquisition Regulations, Part 31
ย 
Financing strategies for adaptation. Presentation for CANCC
Financing strategies for adaptation. Presentation for CANCCFinancing strategies for adaptation. Presentation for CANCC
Financing strategies for adaptation. Presentation for CANCC
ย 
Sustainability by Design: Assessment Tool for Just Energy Transition Plans
Sustainability by Design: Assessment Tool for Just Energy Transition PlansSustainability by Design: Assessment Tool for Just Energy Transition Plans
Sustainability by Design: Assessment Tool for Just Energy Transition Plans
ย 
Call Girls Service Vijayawada {6378878445} โค๏ธVVIP POOJA Call Girls
Call Girls Service Vijayawada {6378878445} โค๏ธVVIP POOJA Call GirlsCall Girls Service Vijayawada {6378878445} โค๏ธVVIP POOJA Call Girls
Call Girls Service Vijayawada {6378878445} โค๏ธVVIP POOJA Call Girls
ย 
Call Girls in North Sikkim 9332606886 HOT & SEXY Models beautiful and charmi...
Call Girls in North Sikkim  9332606886 HOT & SEXY Models beautiful and charmi...Call Girls in North Sikkim  9332606886 HOT & SEXY Models beautiful and charmi...
Call Girls in North Sikkim 9332606886 HOT & SEXY Models beautiful and charmi...
ย 
2024 UN Civil Society Conference in Support of the Summit of the Future.
2024 UN Civil Society Conference in Support of the Summit of the Future.2024 UN Civil Society Conference in Support of the Summit of the Future.
2024 UN Civil Society Conference in Support of the Summit of the Future.
ย 
Fun all Day Call Girls in Erode { 9332606886 } VVIP NISHA Call Girls Near 5 S...
Fun all Day Call Girls in Erode { 9332606886 } VVIP NISHA Call Girls Near 5 S...Fun all Day Call Girls in Erode { 9332606886 } VVIP NISHA Call Girls Near 5 S...
Fun all Day Call Girls in Erode { 9332606886 } VVIP NISHA Call Girls Near 5 S...
ย 
YHRGeorgetown Spring 2024 America should Take Her Share
YHRGeorgetown Spring 2024 America should Take Her ShareYHRGeorgetown Spring 2024 America should Take Her Share
YHRGeorgetown Spring 2024 America should Take Her Share
ย 
Call girls Service Budhwar Peth - 8250092165 Our call girls are sure to provi...
Call girls Service Budhwar Peth - 8250092165 Our call girls are sure to provi...Call girls Service Budhwar Peth - 8250092165 Our call girls are sure to provi...
Call girls Service Budhwar Peth - 8250092165 Our call girls are sure to provi...
ย 
Call Girls Umbergaon / 8250092165 Genuine Call girls with real Photos and Number
Call Girls Umbergaon / 8250092165 Genuine Call girls with real Photos and NumberCall Girls Umbergaon / 8250092165 Genuine Call girls with real Photos and Number
Call Girls Umbergaon / 8250092165 Genuine Call girls with real Photos and Number
ย 
tOld settlement register shouldnotaffect BTR
tOld settlement register shouldnotaffect BTRtOld settlement register shouldnotaffect BTR
tOld settlement register shouldnotaffect BTR
ย 
AHMR volume 10 number 1 January-April 2024
AHMR volume 10 number 1 January-April 2024AHMR volume 10 number 1 January-April 2024
AHMR volume 10 number 1 January-April 2024
ย 
Bhubaneswar Call Girls Chandrashekharpur ๐Ÿ‘‰๐Ÿ‘‰ 9777949614 Top Class Call Girl S...
Bhubaneswar Call Girls Chandrashekharpur  ๐Ÿ‘‰๐Ÿ‘‰ 9777949614 Top Class Call Girl S...Bhubaneswar Call Girls Chandrashekharpur  ๐Ÿ‘‰๐Ÿ‘‰ 9777949614 Top Class Call Girl S...
Bhubaneswar Call Girls Chandrashekharpur ๐Ÿ‘‰๐Ÿ‘‰ 9777949614 Top Class Call Girl S...
ย 

Avenue & Chaplin CLC - Construction Update: July 8, 2020

  • 1. July 8, 2020 Eglinton Crosstown LRT Chaplin-Avenue CLC
  • 3. CHAPLIN STATION UPDATE 3INSERT FOOTER Activity Location Approx. Date & Duration What to Expect Dewatering System Maintenance Cleaning of tanks using hydro-vacuum truck Latimer Ave and Eglinton Ave work zone and Shoppers Drug Mart parking lot Weekly or as needed into 2021 5:00 a.m. โ€“ 8:00 a.m. for one (1) hour โ€ข Noise from hydro-vacuum truck โ€ข Occupancy of the Shoppers Drug Mart parking lot Extended Construction Hours for Deep Excavation and Deliveries Station Box beneath Eglinton Ave from the Main and Tertiary Entrances Main Entrance: โ€ข Structural steel deliveries Mon โ€“ Sat, 5:00 a.m. โ€“ 1:00 a.m. Through July 2020 โ€ข Rebar Installation Mon โ€“ Fri, 4:00 a.m. start Through July 2020 (as needed) Tertiary Entrance: โ€ข Deep excavation of station box, loading and hauling Mon โ€“ Sat, 5:00 a.m. โ€“ 1:00 a.m. Through early July 2020 โ€ข Structural steel deliveries Mon โ€“ Sat, 5:00 a.m. โ€“ 1:00 a.m. Through early August 2020 โ€ข Early morning/late night noise from construction activity โ€ข Periodically chipping of hardened material and concrete within the excavation will be required โ€“ noise and vibration may be experienced โ€ข Truck activity around work zones โ€ข Use of excavators, cranes and other construction equipment Tertiary Entrance Construction Waterproofing, removal of separation wall South side of Eglinton Ave, east of Chaplin Cres and adjacent Toronto Fire Station 135 Underway into Winter 2021
  • 4. CHAPLIN STATION UPDATE 4INSERT FOOTER Activity Location Approx. Date & Duration What to Expect Main Entrance Construction Rebar installation and formwork North side of Eglinton Ave between Chaplin Cres and Gilgorm Rd Through winter 2021 โ€ข Early morning/late night noise from construction activity โ€ข Truck activity around work zones โ€ข Use of excavators, cranes and other construction equipment Concrete Works Main and Tertiary Entrances; Station Box Periodically through 2020 โ€ข Use of concrete pumps โ€ข Frequent concrete trucks โ€ข Early morning/late night noise from construction activity Station Box Construction Rebar installation, THESL work (roof) Beneath Eglinton Ave Underway through spring 2021 โ€ข Truck activity around work zones โ€ข Use of excavators, cranes and other construction equipment Chaplin Cres Closure of Traffic Bridge Removal Chaplin Cres between Eglinton Ave and Russell Hill Rd Extended to July 31, 2020 โ€ข Closure of Chaplin Cres โ€ข TTC 14 Glencairn bus detour
  • 5. CHAPLIN CRES ROAD CLOSURE 5 โ€ข Chaplin Cres will be closed between Eglinton Ave and Russell Hill Rd beginning June 8 for approximately six (6) weeks โ€ข The closure is required to complete remove of the existing traffic bridge, back-fill the area, reinstate dry and wet utilities, pave the area and line paint (note: this paving will be temporary โ€“ final road restoration will begin in mid 2021) โ€ข One lane of traffic in each direction on Eglinton Ave will be maintained โ€ข Southbound traffic on Chaplin Cres will have to turn right or left at Eglinton Ave โ€ข Local access on Chaplin Cres will be maintained from the south end of the closure โ€ข The Chaplin-Russell Hill laneway will be closed, local vehicle and pedestrian traffic excepted โ€ข The west crosswalk will be temporary closed and the north crosswalk will be temporarily reinstated; the south crosswalk will be shifted south โ€ข TTC bus route 14 Glencairn will be on detour โ€ข Parking on Russell Hill Rd will be temporarily prohibited to accommodate the bus detour INSERT FOOTER
  • 6. CURRENT TRAFFIC CONFIGURATION 6CENTRAL WEST WORKS MONTHLY MEETING Until July 31, 2020
  • 7. CONSTRUCTION PROGRESS PHOTOS 7CENTRAL WEST WORKS MONTHLY MEETING WATERPROOFING TERTIARY ENTRANCE MAIN ENTRANCE CONCOURSE SLAB
  • 9. AVENUE STATION UPDATE 9INSERT FOOTER Activity Location Approx. Date & Duration What to Expect Final lining Waterproofing, rebar installation, and mechanical electrical works Throughout all station areas Underway through to late-2020 โ€ข Deliveries at the main and secondary entrances Concrete Pours Between the Main and Secondary Entrances Three times per week for approx. 12 โ€“ 18 hours through to 2021 โ€ข Concrete truck activity โ€ข Occupation of the westbound curb lane during some pours Eglinton Connects Streetscape and Cycle Track Construction Eglinton Ave between Lascelles Blvd and Duplex Ave Underway through to early 2021 โ€ข Eglinton reduced to one lane in each direction between Lascelles Blvd & Duplex Ave โ€ข Use of excavator, hydro-vac and concrete trucks Dewatering Well Maintenance Eglinton Ave between Braemar Ave and Lascelles Blvd Periodically through 2021; 9:00 a.m. โ€“ 4:00 p.m. โ€ข Road occupancy around well โ€ข Use of hydro-vac truck Monitoring Work Eglinton Ave between Braemar Ave and Lascelles Blvd Periodically through 2021 โ€ข Short-term road occupancy
  • 10. CURRENT TRAFFIC CONFIGURATION 10 Through September 2021 INSERT FOOTER
  • 11. EGLINTON CONNECTS โ€“ SCOPE OF WORK 11 โ€ข CTS will implement Eglinton Connects within immediate station areas and continuously between Avenue Road and Holly Street โ€ข Implementation of Eglinton Connects began July 7, 2020 between Lascelles Blvd and Duplex Ave โ€ข The scope work includes: INSERT FOOTER โœ“ Widened sidewalks โœ“ Separated cycle tracks โœ“ On-street parking โœ“ Full restoration of the roadway, curbs and sidewalks along Eglinton Ave โœ“ Increased greenery and street furnishings โœ“ Reduced traffic lanes (to accommodate wider sidewalks and cycle tracks)
  • 12. TRAFFIC CONFIGURATION โ€“ STAGE 1 12INSERT FOOTER As of Tuesday, July 7, 2020
  • 13. TRAFFIC CONFIGURATION โ€“ STAGE 2 13INSERT FOOTER
  • 14. TRAFFIC CONFIGURATION โ€“ STAGE 3 14INSERT FOOTER
  • 15. TRAFFIC CONFIGURATION โ€“ STAGE 4 15INSERT FOOTER Through to early 2021
  • 16. EGLINTON AVE FUTURE CONFIGURATION โ€“ ORIOLE PKWY TO LASCELLES BLVD 16INSERT FOOTER
  • 17. EGLINTON AVE FUTURE CONFIGURATION โ€“ LASCELLES BLVD โ€“ DUPLEX AVE 17INSERT FOOTER
  • 18. CONSTRUCTION OVERVIEW 18 โ€ข Construction of the new Eglinton Streetscape and Cycle Track between Avenue Rd and Duplex Ave will take place in phases beginning with Phase 1 Edith Rd to Duplex Ave on July 6, 2020 โ€ข Construction will take place Monday โ€“ Saturday, 7:00 a.m. โ€“ 7:00 p.m. with periodic overnight work โ€ข Construction activities will include excavation of the roadway and sidewalk, utility reinstatement, concrete work, paving, compaction, landscaping and installation of street furnishings โ€ข Work will be carried out in several traffic stages with minor adjustments between stages as required โ€ข Construction of the new Eglinton Streetscape and Cycle Track between Avenue Rd and Duplex Ave will continue into 2021 INSERT FOOTER
  • 19. BIA FURNITURE REMOVALS 19 124 Eglinton Ave W: INSERT FOOTER 1 2 3 6 54 7
  • 20. BIA FURNITURE REMOVALS 20 174 Eglinton Ave W: INSERT FOOTER 158 Eglinton Ave W: 1 1
  • 21. TTC SHELTER REMOVALS 21INSERT FOOTER 75 Eglinton Ave W โ€ข Temporary stops and ramps will be installed to maintain access for TTC riders 90 Eglinton Ave W 225 Eglinton Ave W
  • 22. CONSTRUCTION PROGRESS PHOTOS 22INSERT FOOTER ARCH WATERPROOFING ARCH CONCRETE WORKS
  • 23. CONSTRUCTION PROGRESS PHOTOS 23INSERT FOOTER AVENUE MAIN ENTRANCE