July 8, 2020
Eglinton Crosstown LRT
Chaplin-Avenue CLC
Chaplin Station
CHAPLIN STATION UPDATE
3INSERT FOOTER
Activity Location Approx. Date & Duration What to Expect
Dewatering System Maintenance
Cleaning of tanks using hydro-vacuum
truck
Latimer Ave and Eglinton Ave work
zone and Shoppers Drug Mart
parking lot
Weekly or as needed into 2021
5:00 a.m. – 8:00 a.m. for one (1) hour
• Noise from hydro-vacuum truck
• Occupancy of the Shoppers Drug
Mart parking lot
Extended Construction Hours for
Deep Excavation and Deliveries
Station Box beneath Eglinton Ave
from the Main and Tertiary
Entrances
Main Entrance:
• Structural steel deliveries
Mon – Sat, 5:00 a.m. – 1:00 a.m.
Through July 2020
• Rebar Installation
Mon – Fri, 4:00 a.m. start
Through July 2020 (as needed)
Tertiary Entrance:
• Deep excavation of station box,
loading and hauling
Mon – Sat, 5:00 a.m. – 1:00 a.m.
Through early July 2020
• Structural steel deliveries
Mon – Sat, 5:00 a.m. – 1:00 a.m.
Through early August 2020
• Early morning/late night noise from
construction activity
• Periodically chipping of hardened
material and concrete within the
excavation will be required – noise
and vibration may be experienced
• Truck activity around work zones
• Use of excavators, cranes and other
construction equipment
Tertiary Entrance Construction
Waterproofing, removal of separation
wall
South side of Eglinton Ave, east of
Chaplin Cres and adjacent Toronto
Fire Station 135
Underway into Winter 2021
CHAPLIN STATION UPDATE
4INSERT FOOTER
Activity Location Approx. Date & Duration What to Expect
Main Entrance Construction
Rebar installation and formwork
North side of Eglinton Ave between
Chaplin Cres and Gilgorm Rd
Through winter 2021
• Early morning/late night noise from
construction activity
• Truck activity around work zones
• Use of excavators, cranes and other
construction equipment
Concrete Works
Main and Tertiary Entrances; Station
Box
Periodically through 2020
• Use of concrete pumps
• Frequent concrete trucks
• Early morning/late night noise from
construction activity
Station Box Construction
Rebar installation, THESL work (roof)
Beneath Eglinton Ave Underway through spring 2021
• Truck activity around work zones
• Use of excavators, cranes and other
construction equipment
Chaplin Cres Closure of Traffic
Bridge Removal
Chaplin Cres between Eglinton Ave
and Russell Hill Rd
Extended to July 31, 2020
• Closure of Chaplin Cres
• TTC 14 Glencairn bus detour
CHAPLIN CRES ROAD CLOSURE
5
• Chaplin Cres will be closed between Eglinton Ave and Russell Hill Rd beginning June 8 for approximately six (6) weeks
• The closure is required to complete remove of the existing traffic bridge, back-fill the area, reinstate dry and wet utilities, pave the area
and line paint (note: this paving will be temporary – final road restoration will begin in mid 2021)
• One lane of traffic in each direction on Eglinton Ave will be maintained
• Southbound traffic on Chaplin Cres will have to turn right or left at Eglinton Ave
• Local access on Chaplin Cres will be maintained from the south end of the closure
• The Chaplin-Russell Hill laneway will be closed, local vehicle and pedestrian traffic excepted
• The west crosswalk will be temporary closed and the north crosswalk will be temporarily reinstated; the south crosswalk will be shifted
south
• TTC bus route 14 Glencairn will be on detour
• Parking on Russell Hill Rd will be temporarily prohibited to accommodate the bus detour
INSERT FOOTER
CURRENT TRAFFIC CONFIGURATION
6CENTRAL WEST WORKS MONTHLY MEETING
Until July 31, 2020
CONSTRUCTION PROGRESS PHOTOS
7CENTRAL WEST WORKS MONTHLY MEETING
WATERPROOFING
TERTIARY ENTRANCE
MAIN ENTRANCE
CONCOURSE SLAB
Avenue Station
AVENUE STATION UPDATE
9INSERT FOOTER
Activity Location Approx. Date & Duration What to Expect
Final lining
Waterproofing, rebar
installation, and mechanical
electrical works
Throughout all station areas Underway through to late-2020
• Deliveries at the main and
secondary entrances
Concrete Pours
Between the Main and Secondary
Entrances
Three times per week for approx.
12 – 18 hours through to 2021
• Concrete truck activity
• Occupation of the westbound
curb lane during some pours
Eglinton Connects
Streetscape and Cycle Track
Construction
Eglinton Ave between Lascelles
Blvd and Duplex Ave
Underway through to early 2021
• Eglinton reduced to one lane
in each direction between
Lascelles Blvd & Duplex Ave
• Use of excavator, hydro-vac
and concrete trucks
Dewatering Well
Maintenance
Eglinton Ave between Braemar Ave
and Lascelles Blvd
Periodically through 2021; 9:00
a.m. – 4:00 p.m.
• Road occupancy around well
• Use of hydro-vac truck
Monitoring Work
Eglinton Ave between Braemar Ave
and Lascelles Blvd
Periodically through 2021 • Short-term road occupancy
CURRENT TRAFFIC CONFIGURATION
10
Through September 2021
INSERT FOOTER
EGLINTON CONNECTS – SCOPE OF WORK
11
• CTS will implement Eglinton Connects within immediate station areas and continuously
between Avenue Road and Holly Street
• Implementation of Eglinton Connects began July 7, 2020 between Lascelles Blvd and Duplex
Ave
• The scope work includes:
INSERT FOOTER
✓ Widened sidewalks
✓ Separated cycle tracks
✓ On-street parking
✓ Full restoration of the roadway, curbs and sidewalks along Eglinton Ave
✓ Increased greenery and street furnishings
✓ Reduced traffic lanes (to accommodate wider sidewalks and cycle tracks)
TRAFFIC CONFIGURATION – STAGE 1
12INSERT FOOTER
As of Tuesday, July 7, 2020
TRAFFIC CONFIGURATION – STAGE 2
13INSERT FOOTER
TRAFFIC CONFIGURATION – STAGE 3
14INSERT FOOTER
TRAFFIC CONFIGURATION – STAGE 4
15INSERT FOOTER
Through to early 2021
EGLINTON AVE FUTURE CONFIGURATION – ORIOLE PKWY TO LASCELLES BLVD
16INSERT FOOTER
EGLINTON AVE FUTURE CONFIGURATION – LASCELLES BLVD – DUPLEX AVE
17INSERT FOOTER
CONSTRUCTION OVERVIEW
18
• Construction of the new Eglinton Streetscape and Cycle Track between Avenue Rd and Duplex
Ave will take place in phases beginning with Phase 1 Edith Rd to Duplex Ave on July 6, 2020
• Construction will take place Monday – Saturday, 7:00 a.m. – 7:00 p.m. with periodic overnight
work
• Construction activities will include excavation of the roadway and sidewalk, utility reinstatement,
concrete work, paving, compaction, landscaping and installation of street furnishings
• Work will be carried out in several traffic stages with minor adjustments between stages as
required
• Construction of the new Eglinton Streetscape and Cycle Track between Avenue Rd and Duplex
Ave will continue into 2021
INSERT FOOTER
BIA FURNITURE REMOVALS
19
124 Eglinton Ave W:
INSERT FOOTER
1 2 3
6
54
7
BIA FURNITURE REMOVALS
20
174 Eglinton Ave W:
INSERT FOOTER
158 Eglinton Ave W:
1 1
TTC SHELTER REMOVALS
21INSERT FOOTER
75 Eglinton Ave W
• Temporary stops and ramps will be installed to maintain access for TTC riders
90 Eglinton Ave W 225 Eglinton Ave W
CONSTRUCTION PROGRESS PHOTOS
22INSERT FOOTER
ARCH WATERPROOFING ARCH CONCRETE WORKS
CONSTRUCTION PROGRESS PHOTOS
23INSERT FOOTER
AVENUE MAIN ENTRANCE
Avenue & Chaplin CLC - Construction Update: July 8, 2020

Avenue & Chaplin CLC - Construction Update: July 8, 2020

  • 1.
    July 8, 2020 EglintonCrosstown LRT Chaplin-Avenue CLC
  • 2.
  • 3.
    CHAPLIN STATION UPDATE 3INSERTFOOTER Activity Location Approx. Date & Duration What to Expect Dewatering System Maintenance Cleaning of tanks using hydro-vacuum truck Latimer Ave and Eglinton Ave work zone and Shoppers Drug Mart parking lot Weekly or as needed into 2021 5:00 a.m. – 8:00 a.m. for one (1) hour • Noise from hydro-vacuum truck • Occupancy of the Shoppers Drug Mart parking lot Extended Construction Hours for Deep Excavation and Deliveries Station Box beneath Eglinton Ave from the Main and Tertiary Entrances Main Entrance: • Structural steel deliveries Mon – Sat, 5:00 a.m. – 1:00 a.m. Through July 2020 • Rebar Installation Mon – Fri, 4:00 a.m. start Through July 2020 (as needed) Tertiary Entrance: • Deep excavation of station box, loading and hauling Mon – Sat, 5:00 a.m. – 1:00 a.m. Through early July 2020 • Structural steel deliveries Mon – Sat, 5:00 a.m. – 1:00 a.m. Through early August 2020 • Early morning/late night noise from construction activity • Periodically chipping of hardened material and concrete within the excavation will be required – noise and vibration may be experienced • Truck activity around work zones • Use of excavators, cranes and other construction equipment Tertiary Entrance Construction Waterproofing, removal of separation wall South side of Eglinton Ave, east of Chaplin Cres and adjacent Toronto Fire Station 135 Underway into Winter 2021
  • 4.
    CHAPLIN STATION UPDATE 4INSERTFOOTER Activity Location Approx. Date & Duration What to Expect Main Entrance Construction Rebar installation and formwork North side of Eglinton Ave between Chaplin Cres and Gilgorm Rd Through winter 2021 • Early morning/late night noise from construction activity • Truck activity around work zones • Use of excavators, cranes and other construction equipment Concrete Works Main and Tertiary Entrances; Station Box Periodically through 2020 • Use of concrete pumps • Frequent concrete trucks • Early morning/late night noise from construction activity Station Box Construction Rebar installation, THESL work (roof) Beneath Eglinton Ave Underway through spring 2021 • Truck activity around work zones • Use of excavators, cranes and other construction equipment Chaplin Cres Closure of Traffic Bridge Removal Chaplin Cres between Eglinton Ave and Russell Hill Rd Extended to July 31, 2020 • Closure of Chaplin Cres • TTC 14 Glencairn bus detour
  • 5.
    CHAPLIN CRES ROADCLOSURE 5 • Chaplin Cres will be closed between Eglinton Ave and Russell Hill Rd beginning June 8 for approximately six (6) weeks • The closure is required to complete remove of the existing traffic bridge, back-fill the area, reinstate dry and wet utilities, pave the area and line paint (note: this paving will be temporary – final road restoration will begin in mid 2021) • One lane of traffic in each direction on Eglinton Ave will be maintained • Southbound traffic on Chaplin Cres will have to turn right or left at Eglinton Ave • Local access on Chaplin Cres will be maintained from the south end of the closure • The Chaplin-Russell Hill laneway will be closed, local vehicle and pedestrian traffic excepted • The west crosswalk will be temporary closed and the north crosswalk will be temporarily reinstated; the south crosswalk will be shifted south • TTC bus route 14 Glencairn will be on detour • Parking on Russell Hill Rd will be temporarily prohibited to accommodate the bus detour INSERT FOOTER
  • 6.
    CURRENT TRAFFIC CONFIGURATION 6CENTRALWEST WORKS MONTHLY MEETING Until July 31, 2020
  • 7.
    CONSTRUCTION PROGRESS PHOTOS 7CENTRALWEST WORKS MONTHLY MEETING WATERPROOFING TERTIARY ENTRANCE MAIN ENTRANCE CONCOURSE SLAB
  • 8.
  • 9.
    AVENUE STATION UPDATE 9INSERTFOOTER Activity Location Approx. Date & Duration What to Expect Final lining Waterproofing, rebar installation, and mechanical electrical works Throughout all station areas Underway through to late-2020 • Deliveries at the main and secondary entrances Concrete Pours Between the Main and Secondary Entrances Three times per week for approx. 12 – 18 hours through to 2021 • Concrete truck activity • Occupation of the westbound curb lane during some pours Eglinton Connects Streetscape and Cycle Track Construction Eglinton Ave between Lascelles Blvd and Duplex Ave Underway through to early 2021 • Eglinton reduced to one lane in each direction between Lascelles Blvd & Duplex Ave • Use of excavator, hydro-vac and concrete trucks Dewatering Well Maintenance Eglinton Ave between Braemar Ave and Lascelles Blvd Periodically through 2021; 9:00 a.m. – 4:00 p.m. • Road occupancy around well • Use of hydro-vac truck Monitoring Work Eglinton Ave between Braemar Ave and Lascelles Blvd Periodically through 2021 • Short-term road occupancy
  • 10.
    CURRENT TRAFFIC CONFIGURATION 10 ThroughSeptember 2021 INSERT FOOTER
  • 11.
    EGLINTON CONNECTS –SCOPE OF WORK 11 • CTS will implement Eglinton Connects within immediate station areas and continuously between Avenue Road and Holly Street • Implementation of Eglinton Connects began July 7, 2020 between Lascelles Blvd and Duplex Ave • The scope work includes: INSERT FOOTER ✓ Widened sidewalks ✓ Separated cycle tracks ✓ On-street parking ✓ Full restoration of the roadway, curbs and sidewalks along Eglinton Ave ✓ Increased greenery and street furnishings ✓ Reduced traffic lanes (to accommodate wider sidewalks and cycle tracks)
  • 12.
    TRAFFIC CONFIGURATION –STAGE 1 12INSERT FOOTER As of Tuesday, July 7, 2020
  • 13.
    TRAFFIC CONFIGURATION –STAGE 2 13INSERT FOOTER
  • 14.
    TRAFFIC CONFIGURATION –STAGE 3 14INSERT FOOTER
  • 15.
    TRAFFIC CONFIGURATION –STAGE 4 15INSERT FOOTER Through to early 2021
  • 16.
    EGLINTON AVE FUTURECONFIGURATION – ORIOLE PKWY TO LASCELLES BLVD 16INSERT FOOTER
  • 17.
    EGLINTON AVE FUTURECONFIGURATION – LASCELLES BLVD – DUPLEX AVE 17INSERT FOOTER
  • 18.
    CONSTRUCTION OVERVIEW 18 • Constructionof the new Eglinton Streetscape and Cycle Track between Avenue Rd and Duplex Ave will take place in phases beginning with Phase 1 Edith Rd to Duplex Ave on July 6, 2020 • Construction will take place Monday – Saturday, 7:00 a.m. – 7:00 p.m. with periodic overnight work • Construction activities will include excavation of the roadway and sidewalk, utility reinstatement, concrete work, paving, compaction, landscaping and installation of street furnishings • Work will be carried out in several traffic stages with minor adjustments between stages as required • Construction of the new Eglinton Streetscape and Cycle Track between Avenue Rd and Duplex Ave will continue into 2021 INSERT FOOTER
  • 19.
    BIA FURNITURE REMOVALS 19 124Eglinton Ave W: INSERT FOOTER 1 2 3 6 54 7
  • 20.
    BIA FURNITURE REMOVALS 20 174Eglinton Ave W: INSERT FOOTER 158 Eglinton Ave W: 1 1
  • 21.
    TTC SHELTER REMOVALS 21INSERTFOOTER 75 Eglinton Ave W • Temporary stops and ramps will be installed to maintain access for TTC riders 90 Eglinton Ave W 225 Eglinton Ave W
  • 22.
    CONSTRUCTION PROGRESS PHOTOS 22INSERTFOOTER ARCH WATERPROOFING ARCH CONCRETE WORKS
  • 23.
    CONSTRUCTION PROGRESS PHOTOS 23INSERTFOOTER AVENUE MAIN ENTRANCE