SlideShare a Scribd company logo
CROSSTOWN LRT
Pharmacy-Kennedy CLC Meeting
September 25, 2018
• Old concrete removal at Kennedy Station
• New street light installation and civil works underway between Victoria Park Avenue and Pharmacy
• Excavation complete for Wilson Brook Culvert Stage 1 installation
• Stage 1 decks poured on Celestica Bridge
• Dry utility upgrades in Section 2 (DVP to Victoria Park) and Section 3 (Victoria Park to Birchmount)
ongoing.
• Mid-block median removals have resumed; Intersection work continues.
• Installation of temporary signals complete between Leslie Street and Kennedy Station.
• Road widening slated to start between Victoria Park Avenue to Kennedy Road
• Stage 1 Traffic installation from Victoria Park to Birchmount Road
Progress to Date
2
• Utility upgrades and relocations (THESL and telecom) continue between Pharmacy
and Birchmount and within the Kennedy Station zone of influence (ZOI).
• Wet utility upgrades and relocations continue within the Kennedy Station ZOI and
Section 4 (Rosemount to Kennedy).
• Wet utility upgrades in Section 3 (Victoria Park to Birchmount).
• Road works from Victoria Park to Pharmacy
• Green wall excavation and construction at E.T. Seton Park
• Eglinton Avenue road widening continues.
• Road construction within the East Portal
• Support of excavation for the Kennedy Portal/Station Box and tail track underway.
• TTC: West Ped Tunnel, East Ped Tunnel, TPSS; Support of excavation activities
within TTC ZOI underway.
• Reconstruction of Massey and Wilson Brook Creek Culverts.
• GO: GIMP Monitoring, SOE at Tail Track- North East platform, Rebar, formwork,
concrete at West Platform.
• Bridge rehabilitations: East Don River, Wynford and Celestica bridges.
Current Works
3
• Ongoing utility upgrades and relocations: Toronto Hydro relocations, Wet
utility relocations (water, sanitary sewer, storm sewer) and telecom on
Eglinton Avenue East and within the TTC ZOI.
• Start construction of the guideway, intersection works, and road widening.
• Stage 6 Traffic installation- Kennedy Station
• GO East Platform restoration, inspection and open to public
• Bus loop rehabilitation : Kennedy –Main Station Box
• Stage 7A Traffic installation –Science Centre
What’s coming in 2018
4
Wilson Brook Culvert- Future Sloane Stop
As part of the ongoing works to build the LRT system along Eglinton Avenue, work on the
Wilson Brook Culvert will be taking place on the south and north side of Eglinton Avenue in
front of 1730 Eglinton Avenue East. This work is began as early as Wednesday, August 16 and
will continue to December 15, 2018.
Crews will be building a temporary storm drain line, as well as excavating and replacing the
storm water culvert under Eglinton Ave East.
5
Storm & Sanitary relocation work in the vicinity of
Ionview Road and Kennedy Road
Ongoing storm and sanitary relocation work from Ionview to Kennedy is approaching
completion and along with the remaining manhole connections the work is expected to
be completed within a month and half.
6
Support of Excavation at Kennedy Station: Current Stage
In early April 2018, crews started support of excavation (SOE) work - also known as shoring -
for the future Kennedy Station. Currently SOE is underway on both the east and west sides of
Kennedy Road.
Shoring will be conducted in phases. The entire shoring process will take approximately
twelve (12) months.
Current traffic staging at Kennedy
Road and Eglinton Avenue East.
7
SOE Works at Kennedy GO Station Platform
To facilitate these improvements, installation of support of excavation are also being made to
the GO Transit Stouffville Corridor at Kennedy GO Station started as early as Saturday,
September 8, 2018.
Work will take approximately three (3) months to complete.
8
What to Expect in 2018
Kennedy Station: Summer/Fall 2018
9
Construction Progress Pictures
Rebar work Storm & Sanitary installation
10
Construction Progress Pictures
Road widening Traffic Light work
11

More Related Content

What's hot

Fall Virtual Open House: West - Mount Dennis to Avenue Stations
Fall Virtual Open House: West - Mount Dennis to Avenue StationsFall Virtual Open House: West - Mount Dennis to Avenue Stations
Fall Virtual Open House: West - Mount Dennis to Avenue Stations
Crosstown TO
 
Leaside laird clc - november 9, 2020
Leaside laird clc - november 9, 2020Leaside laird clc - november 9, 2020
Leaside laird clc - november 9, 2020
Crosstown TO
 
Pharmacy kennedy clc meeting - deck - march 26,2019
Pharmacy   kennedy clc meeting - deck - march 26,2019Pharmacy   kennedy clc meeting - deck - march 26,2019
Pharmacy kennedy clc meeting - deck - march 26,2019
Crosstown TO
 
Brentcliffe-Victoria Park Construction Liaison Committee (CLC) Meeting - May ...
Brentcliffe-Victoria Park Construction Liaison Committee (CLC) Meeting - May ...Brentcliffe-Victoria Park Construction Liaison Committee (CLC) Meeting - May ...
Brentcliffe-Victoria Park Construction Liaison Committee (CLC) Meeting - May ...
Crosstown TO
 
CLC Pharmacy to Kennedy 2021
CLC Pharmacy to Kennedy 2021CLC Pharmacy to Kennedy 2021
CLC Pharmacy to Kennedy 2021
Crosstown TO
 
Central Virtual Open House 28Apr2021
Central Virtual Open House 28Apr2021Central Virtual Open House 28Apr2021
Central Virtual Open House 28Apr2021
Crosstown TO
 
Pharmacy to Kennedy Construction Liaison Committee Meeting - Sept 2019
Pharmacy to Kennedy Construction Liaison Committee Meeting - Sept 2019Pharmacy to Kennedy Construction Liaison Committee Meeting - Sept 2019
Pharmacy to Kennedy Construction Liaison Committee Meeting - Sept 2019
Crosstown TO
 
CLC Deck Brentcliffe Road to Victoria Park Avenue (Sept 3, 2020)
CLC Deck Brentcliffe Road to Victoria Park Avenue (Sept 3, 2020)CLC Deck Brentcliffe Road to Victoria Park Avenue (Sept 3, 2020)
CLC Deck Brentcliffe Road to Victoria Park Avenue (Sept 3, 2020)
Crosstown TO
 
CLC presentation deck Brentcliffe to Victoria Park (July 9 2020)
CLC presentation deck Brentcliffe to Victoria Park (July 9 2020)CLC presentation deck Brentcliffe to Victoria Park (July 9 2020)
CLC presentation deck Brentcliffe to Victoria Park (July 9 2020)
Crosstown TO
 
Brentcliffe - Victoria Park Construction Liaison Committee (CLC) Meeting
Brentcliffe - Victoria Park Construction Liaison Committee (CLC) MeetingBrentcliffe - Victoria Park Construction Liaison Committee (CLC) Meeting
Brentcliffe - Victoria Park Construction Liaison Committee (CLC) Meeting
Crosstown TO
 
Eastern Virtual Open House Deck
Eastern Virtual Open House DeckEastern Virtual Open House Deck
Eastern Virtual Open House Deck
Crosstown TO
 
Avenue & Chaplin CLC - Construction Update: March 3, 2021
Avenue & Chaplin CLC - Construction Update: March 3, 2021Avenue & Chaplin CLC - Construction Update: March 3, 2021
Avenue & Chaplin CLC - Construction Update: March 3, 2021
Crosstown TO
 
Leaside Laird CLC November 2019 Presentation
Leaside Laird CLC November 2019 PresentationLeaside Laird CLC November 2019 Presentation
Leaside Laird CLC November 2019 Presentation
Crosstown TO
 
Pharmacy to kennedy construction liaison committee meeting - June 2018
Pharmacy to kennedy construction liaison committee meeting - June 2018Pharmacy to kennedy construction liaison committee meeting - June 2018
Pharmacy to kennedy construction liaison committee meeting - June 2018
Crosstown TO
 
Spring Virtual Open - Central West - April 21, 2021
Spring Virtual Open - Central West - April 21, 2021Spring Virtual Open - Central West - April 21, 2021
Spring Virtual Open - Central West - April 21, 2021
Crosstown TO
 
Leaside and Laird CLC - 10 May 2021
Leaside and Laird CLC - 10 May 2021 Leaside and Laird CLC - 10 May 2021
Leaside and Laird CLC - 10 May 2021
Crosstown TO
 
Chaplin-Avenue Construction Liaison Committee Meeting - May 2018
Chaplin-Avenue Construction Liaison Committee Meeting - May 2018Chaplin-Avenue Construction Liaison Committee Meeting - May 2018
Chaplin-Avenue Construction Liaison Committee Meeting - May 2018
Crosstown TO
 
Brentcliffe - Victoria Park Construction Liaison Committee Meeting
Brentcliffe - Victoria Park Construction Liaison Committee MeetingBrentcliffe - Victoria Park Construction Liaison Committee Meeting
Brentcliffe - Victoria Park Construction Liaison Committee Meeting
Crosstown TO
 
Fairbank-Oakwood Construction Update - November 2021
Fairbank-Oakwood Construction Update - November 2021Fairbank-Oakwood Construction Update - November 2021
Fairbank-Oakwood Construction Update - November 2021
Crosstown TO
 
Chaplin - Avenue Construction Liaison Committee - July 2018
Chaplin - Avenue Construction Liaison Committee - July 2018Chaplin - Avenue Construction Liaison Committee - July 2018
Chaplin - Avenue Construction Liaison Committee - July 2018
Crosstown TO
 

What's hot (20)

Fall Virtual Open House: West - Mount Dennis to Avenue Stations
Fall Virtual Open House: West - Mount Dennis to Avenue StationsFall Virtual Open House: West - Mount Dennis to Avenue Stations
Fall Virtual Open House: West - Mount Dennis to Avenue Stations
 
Leaside laird clc - november 9, 2020
Leaside laird clc - november 9, 2020Leaside laird clc - november 9, 2020
Leaside laird clc - november 9, 2020
 
Pharmacy kennedy clc meeting - deck - march 26,2019
Pharmacy   kennedy clc meeting - deck - march 26,2019Pharmacy   kennedy clc meeting - deck - march 26,2019
Pharmacy kennedy clc meeting - deck - march 26,2019
 
Brentcliffe-Victoria Park Construction Liaison Committee (CLC) Meeting - May ...
Brentcliffe-Victoria Park Construction Liaison Committee (CLC) Meeting - May ...Brentcliffe-Victoria Park Construction Liaison Committee (CLC) Meeting - May ...
Brentcliffe-Victoria Park Construction Liaison Committee (CLC) Meeting - May ...
 
CLC Pharmacy to Kennedy 2021
CLC Pharmacy to Kennedy 2021CLC Pharmacy to Kennedy 2021
CLC Pharmacy to Kennedy 2021
 
Central Virtual Open House 28Apr2021
Central Virtual Open House 28Apr2021Central Virtual Open House 28Apr2021
Central Virtual Open House 28Apr2021
 
Pharmacy to Kennedy Construction Liaison Committee Meeting - Sept 2019
Pharmacy to Kennedy Construction Liaison Committee Meeting - Sept 2019Pharmacy to Kennedy Construction Liaison Committee Meeting - Sept 2019
Pharmacy to Kennedy Construction Liaison Committee Meeting - Sept 2019
 
CLC Deck Brentcliffe Road to Victoria Park Avenue (Sept 3, 2020)
CLC Deck Brentcliffe Road to Victoria Park Avenue (Sept 3, 2020)CLC Deck Brentcliffe Road to Victoria Park Avenue (Sept 3, 2020)
CLC Deck Brentcliffe Road to Victoria Park Avenue (Sept 3, 2020)
 
CLC presentation deck Brentcliffe to Victoria Park (July 9 2020)
CLC presentation deck Brentcliffe to Victoria Park (July 9 2020)CLC presentation deck Brentcliffe to Victoria Park (July 9 2020)
CLC presentation deck Brentcliffe to Victoria Park (July 9 2020)
 
Brentcliffe - Victoria Park Construction Liaison Committee (CLC) Meeting
Brentcliffe - Victoria Park Construction Liaison Committee (CLC) MeetingBrentcliffe - Victoria Park Construction Liaison Committee (CLC) Meeting
Brentcliffe - Victoria Park Construction Liaison Committee (CLC) Meeting
 
Eastern Virtual Open House Deck
Eastern Virtual Open House DeckEastern Virtual Open House Deck
Eastern Virtual Open House Deck
 
Avenue & Chaplin CLC - Construction Update: March 3, 2021
Avenue & Chaplin CLC - Construction Update: March 3, 2021Avenue & Chaplin CLC - Construction Update: March 3, 2021
Avenue & Chaplin CLC - Construction Update: March 3, 2021
 
Leaside Laird CLC November 2019 Presentation
Leaside Laird CLC November 2019 PresentationLeaside Laird CLC November 2019 Presentation
Leaside Laird CLC November 2019 Presentation
 
Pharmacy to kennedy construction liaison committee meeting - June 2018
Pharmacy to kennedy construction liaison committee meeting - June 2018Pharmacy to kennedy construction liaison committee meeting - June 2018
Pharmacy to kennedy construction liaison committee meeting - June 2018
 
Spring Virtual Open - Central West - April 21, 2021
Spring Virtual Open - Central West - April 21, 2021Spring Virtual Open - Central West - April 21, 2021
Spring Virtual Open - Central West - April 21, 2021
 
Leaside and Laird CLC - 10 May 2021
Leaside and Laird CLC - 10 May 2021 Leaside and Laird CLC - 10 May 2021
Leaside and Laird CLC - 10 May 2021
 
Chaplin-Avenue Construction Liaison Committee Meeting - May 2018
Chaplin-Avenue Construction Liaison Committee Meeting - May 2018Chaplin-Avenue Construction Liaison Committee Meeting - May 2018
Chaplin-Avenue Construction Liaison Committee Meeting - May 2018
 
Brentcliffe - Victoria Park Construction Liaison Committee Meeting
Brentcliffe - Victoria Park Construction Liaison Committee MeetingBrentcliffe - Victoria Park Construction Liaison Committee Meeting
Brentcliffe - Victoria Park Construction Liaison Committee Meeting
 
Fairbank-Oakwood Construction Update - November 2021
Fairbank-Oakwood Construction Update - November 2021Fairbank-Oakwood Construction Update - November 2021
Fairbank-Oakwood Construction Update - November 2021
 
Chaplin - Avenue Construction Liaison Committee - July 2018
Chaplin - Avenue Construction Liaison Committee - July 2018Chaplin - Avenue Construction Liaison Committee - July 2018
Chaplin - Avenue Construction Liaison Committee - July 2018
 

Similar to Pharmacy to Kennedy Construction Liaison Committee Meeting

Pharmacy - Kennedy Construction Liaison Committee Meeting - May 2018
Pharmacy - Kennedy Construction Liaison Committee Meeting - May 2018Pharmacy - Kennedy Construction Liaison Committee Meeting - May 2018
Pharmacy - Kennedy Construction Liaison Committee Meeting - May 2018
Crosstown TO
 
Pharmacy kennedy clc meeting -january 29 2019
Pharmacy kennedy clc meeting -january 29 2019Pharmacy kennedy clc meeting -january 29 2019
Pharmacy kennedy clc meeting -january 29 2019
Crosstown TO
 
Brentcliffe-Victoria Park Construction Liaison Committee Meeting - July 2017
Brentcliffe-Victoria Park Construction Liaison Committee Meeting - July 2017Brentcliffe-Victoria Park Construction Liaison Committee Meeting - July 2017
Brentcliffe-Victoria Park Construction Liaison Committee Meeting - July 2017
Crosstown TO
 
Pharmacy to Kennedy Construction Liaison Committee Meeting - April 2018
Pharmacy  to Kennedy Construction Liaison Committee Meeting - April 2018Pharmacy  to Kennedy Construction Liaison Committee Meeting - April 2018
Pharmacy to Kennedy Construction Liaison Committee Meeting - April 2018
Crosstown TO
 
Brentcliffe to Victoria Park Construction Liaison Committee Meeting - January...
Brentcliffe to Victoria Park Construction Liaison Committee Meeting - January...Brentcliffe to Victoria Park Construction Liaison Committee Meeting - January...
Brentcliffe to Victoria Park Construction Liaison Committee Meeting - January...
Crosstown TO
 
Pharmacy to Kennedy Construction Liaison Committee Meeting - March 2018
Pharmacy to Kennedy Construction Liaison Committee Meeting - March 2018Pharmacy to Kennedy Construction Liaison Committee Meeting - March 2018
Pharmacy to Kennedy Construction Liaison Committee Meeting - March 2018
Crosstown TO
 
Western Works Construction Liaison Committee Meeting - January 2018
Western Works Construction Liaison Committee Meeting - January 2018Western Works Construction Liaison Committee Meeting - January 2018
Western Works Construction Liaison Committee Meeting - January 2018
Crosstown TO
 
Brentcliffe-Victoria Park Construction Liaison Committee Meeting - October 2017
Brentcliffe-Victoria Park Construction Liaison Committee Meeting - October 2017Brentcliffe-Victoria Park Construction Liaison Committee Meeting - October 2017
Brentcliffe-Victoria Park Construction Liaison Committee Meeting - October 2017
Crosstown TO
 
Brentcliffe - Vctoria Park Construction Liaison Committee Meeting - March 2018
Brentcliffe - Vctoria Park Construction Liaison Committee Meeting -  March 2018 Brentcliffe - Vctoria Park Construction Liaison Committee Meeting -  March 2018
Brentcliffe - Vctoria Park Construction Liaison Committee Meeting - March 2018
Crosstown TO
 
Brentcliffe to Victoria Park Construction Liaison Committee Meeting - March 2018
Brentcliffe to Victoria Park Construction Liaison Committee Meeting - March 2018Brentcliffe to Victoria Park Construction Liaison Committee Meeting - March 2018
Brentcliffe to Victoria Park Construction Liaison Committee Meeting - March 2018
Crosstown TO
 
Brentcliffe to Victoria Park Construction Liaison Committee Meeting - Novembe...
Brentcliffe to Victoria Park Construction Liaison Committee Meeting - Novembe...Brentcliffe to Victoria Park Construction Liaison Committee Meeting - Novembe...
Brentcliffe to Victoria Park Construction Liaison Committee Meeting - Novembe...
Crosstown TO
 
Brentcliffe - Victoria Park Construction Liaison Committee Meeting
Brentcliffe - Victoria Park Construction Liaison Committee MeetingBrentcliffe - Victoria Park Construction Liaison Committee Meeting
Brentcliffe - Victoria Park Construction Liaison Committee Meeting
Crosstown TO
 
Pharmacy to Kennedy Construction Liaison Committee Meeting - January 2018
Pharmacy to Kennedy Construction Liaison Committee Meeting - January 2018Pharmacy to Kennedy Construction Liaison Committee Meeting - January 2018
Pharmacy to Kennedy Construction Liaison Committee Meeting - January 2018
Crosstown TO
 
Western Works Construction Liaison Committee Meeting - March 2018
Western Works Construction Liaison Committee Meeting - March 2018Western Works Construction Liaison Committee Meeting - March 2018
Western Works Construction Liaison Committee Meeting - March 2018
Crosstown TO
 
Brentcliffe - Victoria Park Construction Liaison Committee (CLC) Meeting
Brentcliffe - Victoria Park Construction Liaison Committee (CLC) MeetingBrentcliffe - Victoria Park Construction Liaison Committee (CLC) Meeting
Brentcliffe - Victoria Park Construction Liaison Committee (CLC) Meeting
Crosstown TO
 
Pharmacy to Kennedy Construction Liaison Committee Meeting - February 2018
Pharmacy to Kennedy Construction Liaison Committee Meeting - February 2018Pharmacy to Kennedy Construction Liaison Committee Meeting - February 2018
Pharmacy to Kennedy Construction Liaison Committee Meeting - February 2018
Crosstown TO
 
Virtual Open House: Eastern Works
Virtual Open House: Eastern WorksVirtual Open House: Eastern Works
Virtual Open House: Eastern Works
Crosstown TO
 
Western Segment Open House Slides
 Western Segment  Open House Slides Western Segment  Open House Slides
Western Segment Open House Slides
Crosstown TO
 
Fall18 Open House Western Segment Works
Fall18 Open House   Western Segment WorksFall18 Open House   Western Segment Works
Fall18 Open House Western Segment Works
Crosstown TO
 
CLC Deck Brentcliffe Road to Victoria Park Avenue (Sept 3, 2020)
CLC Deck Brentcliffe Road to Victoria Park Avenue (Sept 3, 2020)CLC Deck Brentcliffe Road to Victoria Park Avenue (Sept 3, 2020)
CLC Deck Brentcliffe Road to Victoria Park Avenue (Sept 3, 2020)
Crosstown TO
 

Similar to Pharmacy to Kennedy Construction Liaison Committee Meeting (20)

Pharmacy - Kennedy Construction Liaison Committee Meeting - May 2018
Pharmacy - Kennedy Construction Liaison Committee Meeting - May 2018Pharmacy - Kennedy Construction Liaison Committee Meeting - May 2018
Pharmacy - Kennedy Construction Liaison Committee Meeting - May 2018
 
Pharmacy kennedy clc meeting -january 29 2019
Pharmacy kennedy clc meeting -january 29 2019Pharmacy kennedy clc meeting -january 29 2019
Pharmacy kennedy clc meeting -january 29 2019
 
Brentcliffe-Victoria Park Construction Liaison Committee Meeting - July 2017
Brentcliffe-Victoria Park Construction Liaison Committee Meeting - July 2017Brentcliffe-Victoria Park Construction Liaison Committee Meeting - July 2017
Brentcliffe-Victoria Park Construction Liaison Committee Meeting - July 2017
 
Pharmacy to Kennedy Construction Liaison Committee Meeting - April 2018
Pharmacy  to Kennedy Construction Liaison Committee Meeting - April 2018Pharmacy  to Kennedy Construction Liaison Committee Meeting - April 2018
Pharmacy to Kennedy Construction Liaison Committee Meeting - April 2018
 
Brentcliffe to Victoria Park Construction Liaison Committee Meeting - January...
Brentcliffe to Victoria Park Construction Liaison Committee Meeting - January...Brentcliffe to Victoria Park Construction Liaison Committee Meeting - January...
Brentcliffe to Victoria Park Construction Liaison Committee Meeting - January...
 
Pharmacy to Kennedy Construction Liaison Committee Meeting - March 2018
Pharmacy to Kennedy Construction Liaison Committee Meeting - March 2018Pharmacy to Kennedy Construction Liaison Committee Meeting - March 2018
Pharmacy to Kennedy Construction Liaison Committee Meeting - March 2018
 
Western Works Construction Liaison Committee Meeting - January 2018
Western Works Construction Liaison Committee Meeting - January 2018Western Works Construction Liaison Committee Meeting - January 2018
Western Works Construction Liaison Committee Meeting - January 2018
 
Brentcliffe-Victoria Park Construction Liaison Committee Meeting - October 2017
Brentcliffe-Victoria Park Construction Liaison Committee Meeting - October 2017Brentcliffe-Victoria Park Construction Liaison Committee Meeting - October 2017
Brentcliffe-Victoria Park Construction Liaison Committee Meeting - October 2017
 
Brentcliffe - Vctoria Park Construction Liaison Committee Meeting - March 2018
Brentcliffe - Vctoria Park Construction Liaison Committee Meeting -  March 2018 Brentcliffe - Vctoria Park Construction Liaison Committee Meeting -  March 2018
Brentcliffe - Vctoria Park Construction Liaison Committee Meeting - March 2018
 
Brentcliffe to Victoria Park Construction Liaison Committee Meeting - March 2018
Brentcliffe to Victoria Park Construction Liaison Committee Meeting - March 2018Brentcliffe to Victoria Park Construction Liaison Committee Meeting - March 2018
Brentcliffe to Victoria Park Construction Liaison Committee Meeting - March 2018
 
Brentcliffe to Victoria Park Construction Liaison Committee Meeting - Novembe...
Brentcliffe to Victoria Park Construction Liaison Committee Meeting - Novembe...Brentcliffe to Victoria Park Construction Liaison Committee Meeting - Novembe...
Brentcliffe to Victoria Park Construction Liaison Committee Meeting - Novembe...
 
Brentcliffe - Victoria Park Construction Liaison Committee Meeting
Brentcliffe - Victoria Park Construction Liaison Committee MeetingBrentcliffe - Victoria Park Construction Liaison Committee Meeting
Brentcliffe - Victoria Park Construction Liaison Committee Meeting
 
Pharmacy to Kennedy Construction Liaison Committee Meeting - January 2018
Pharmacy to Kennedy Construction Liaison Committee Meeting - January 2018Pharmacy to Kennedy Construction Liaison Committee Meeting - January 2018
Pharmacy to Kennedy Construction Liaison Committee Meeting - January 2018
 
Western Works Construction Liaison Committee Meeting - March 2018
Western Works Construction Liaison Committee Meeting - March 2018Western Works Construction Liaison Committee Meeting - March 2018
Western Works Construction Liaison Committee Meeting - March 2018
 
Brentcliffe - Victoria Park Construction Liaison Committee (CLC) Meeting
Brentcliffe - Victoria Park Construction Liaison Committee (CLC) MeetingBrentcliffe - Victoria Park Construction Liaison Committee (CLC) Meeting
Brentcliffe - Victoria Park Construction Liaison Committee (CLC) Meeting
 
Pharmacy to Kennedy Construction Liaison Committee Meeting - February 2018
Pharmacy to Kennedy Construction Liaison Committee Meeting - February 2018Pharmacy to Kennedy Construction Liaison Committee Meeting - February 2018
Pharmacy to Kennedy Construction Liaison Committee Meeting - February 2018
 
Virtual Open House: Eastern Works
Virtual Open House: Eastern WorksVirtual Open House: Eastern Works
Virtual Open House: Eastern Works
 
Western Segment Open House Slides
 Western Segment  Open House Slides Western Segment  Open House Slides
Western Segment Open House Slides
 
Fall18 Open House Western Segment Works
Fall18 Open House   Western Segment WorksFall18 Open House   Western Segment Works
Fall18 Open House Western Segment Works
 
CLC Deck Brentcliffe Road to Victoria Park Avenue (Sept 3, 2020)
CLC Deck Brentcliffe Road to Victoria Park Avenue (Sept 3, 2020)CLC Deck Brentcliffe Road to Victoria Park Avenue (Sept 3, 2020)
CLC Deck Brentcliffe Road to Victoria Park Avenue (Sept 3, 2020)
 

More from Crosstown TO

Western Works CLC - January 17, 2023.pdf
Western Works CLC - January 17, 2023.pdfWestern Works CLC - January 17, 2023.pdf
Western Works CLC - January 17, 2023.pdf
Crosstown TO
 
Western Works CLC - May 16, 2023
 Western Works CLC - May 16, 2023 Western Works CLC - May 16, 2023
Western Works CLC - May 16, 2023
Crosstown TO
 
Western Works CLC - March, 21 2023
Western Works CLC - March, 21 2023 Western Works CLC - March, 21 2023
Western Works CLC - March, 21 2023
Crosstown TO
 
Leaside-Laird CLC - May 8, 2023.pdf
Leaside-Laird CLC - May 8, 2023.pdfLeaside-Laird CLC - May 8, 2023.pdf
Leaside-Laird CLC - May 8, 2023.pdf
Crosstown TO
 
Eglinton - Mt Pleasant CLC - May 10, 2023.pdf
Eglinton - Mt Pleasant CLC - May 10, 2023.pdfEglinton - Mt Pleasant CLC - May 10, 2023.pdf
Eglinton - Mt Pleasant CLC - May 10, 2023.pdf
Crosstown TO
 
Chaplin-Avenue CLC - May 3 2023 Updated.pptx
Chaplin-Avenue CLC - May 3 2023 Updated.pptxChaplin-Avenue CLC - May 3 2023 Updated.pptx
Chaplin-Avenue CLC - May 3 2023 Updated.pptx
Crosstown TO
 
CLC Deck - Brentcliffe to Victoria Park - May 4 2023 - Compressed.pptx
CLC Deck - Brentcliffe to Victoria Park - May 4 2023 - Compressed.pptxCLC Deck - Brentcliffe to Victoria Park - May 4 2023 - Compressed.pptx
CLC Deck - Brentcliffe to Victoria Park - May 4 2023 - Compressed.pptx
Crosstown TO
 
Pharmacy to Kennedy CLC presentation deck - Janaury 31, 2023.pptx
Pharmacy to Kennedy CLC presentation deck - Janaury 31, 2023.pptxPharmacy to Kennedy CLC presentation deck - Janaury 31, 2023.pptx
Pharmacy to Kennedy CLC presentation deck - Janaury 31, 2023.pptx
Crosstown TO
 
CLC Pharmacy to Kennedy - March 28, 2023 - Compressed.pptx
CLC Pharmacy to Kennedy - March 28, 2023 - Compressed.pptxCLC Pharmacy to Kennedy - March 28, 2023 - Compressed.pptx
CLC Pharmacy to Kennedy - March 28, 2023 - Compressed.pptx
Crosstown TO
 
CLC Deck - Brentcliffe to Victoria Park - March 2, 2023 - Compressed.pptx
CLC Deck - Brentcliffe to Victoria Park - March 2, 2023 - Compressed.pptxCLC Deck - Brentcliffe to Victoria Park - March 2, 2023 - Compressed.pptx
CLC Deck - Brentcliffe to Victoria Park - March 2, 2023 - Compressed.pptx
Crosstown TO
 
Chaplin-Avenue CLC - March 1, 2023.pptx
Chaplin-Avenue CLC - March 1, 2023.pptxChaplin-Avenue CLC - March 1, 2023.pptx
Chaplin-Avenue CLC - March 1, 2023.pptx
Crosstown TO
 
Leaside-Laird CLC - March 13, 2023.pdf
Leaside-Laird CLC - March 13, 2023.pdfLeaside-Laird CLC - March 13, 2023.pdf
Leaside-Laird CLC - March 13, 2023.pdf
Crosstown TO
 
CLC Deck - Brentcliffe to Victoria Park - March 2, 2023 - Compressed.pptx
CLC Deck - Brentcliffe to Victoria Park - March 2, 2023 - Compressed.pptxCLC Deck - Brentcliffe to Victoria Park - March 2, 2023 - Compressed.pptx
CLC Deck - Brentcliffe to Victoria Park - March 2, 2023 - Compressed.pptx
Crosstown TO
 
Eglinton - Mount Pleasant CLC - March 8, 2023.pdf
Eglinton - Mount Pleasant CLC - March 8, 2023.pdfEglinton - Mount Pleasant CLC - March 8, 2023.pdf
Eglinton - Mount Pleasant CLC - March 8, 2023.pdf
Crosstown TO
 
Chaplin-Avenue CLC - November 2 2022 compressed.pptx
Chaplin-Avenue CLC - November 2 2022 compressed.pptxChaplin-Avenue CLC - November 2 2022 compressed.pptx
Chaplin-Avenue CLC - November 2 2022 compressed.pptx
Crosstown TO
 
Chaplin-Avenue CLC - January 11 2023 (002).pptx
Chaplin-Avenue CLC - January 11 2023 (002).pptxChaplin-Avenue CLC - January 11 2023 (002).pptx
Chaplin-Avenue CLC - January 11 2023 (002).pptx
Crosstown TO
 
CLC Deck - Brentcliffe to Victoria Park - January 12, 2023 - Compressed.pptx
CLC Deck - Brentcliffe to Victoria Park - January 12, 2023 - Compressed.pptxCLC Deck - Brentcliffe to Victoria Park - January 12, 2023 - Compressed.pptx
CLC Deck - Brentcliffe to Victoria Park - January 12, 2023 - Compressed.pptx
Crosstown TO
 
Eglinton - Mt Pleasant CLC - January 11, 2023.pdf
Eglinton - Mt Pleasant CLC - January 11, 2023.pdfEglinton - Mt Pleasant CLC - January 11, 2023.pdf
Eglinton - Mt Pleasant CLC - January 11, 2023.pdf
Crosstown TO
 
Leaside-Laird CLC - January 9, 2023.pdf
Leaside-Laird CLC - January 9, 2023.pdfLeaside-Laird CLC - January 9, 2023.pdf
Leaside-Laird CLC - January 9, 2023.pdf
Crosstown TO
 
CLC Deck - Brentcliffe to Victoria Park - November 3 2022.pdf
CLC Deck - Brentcliffe to Victoria Park - November 3 2022.pdfCLC Deck - Brentcliffe to Victoria Park - November 3 2022.pdf
CLC Deck - Brentcliffe to Victoria Park - November 3 2022.pdf
Crosstown TO
 

More from Crosstown TO (20)

Western Works CLC - January 17, 2023.pdf
Western Works CLC - January 17, 2023.pdfWestern Works CLC - January 17, 2023.pdf
Western Works CLC - January 17, 2023.pdf
 
Western Works CLC - May 16, 2023
 Western Works CLC - May 16, 2023 Western Works CLC - May 16, 2023
Western Works CLC - May 16, 2023
 
Western Works CLC - March, 21 2023
Western Works CLC - March, 21 2023 Western Works CLC - March, 21 2023
Western Works CLC - March, 21 2023
 
Leaside-Laird CLC - May 8, 2023.pdf
Leaside-Laird CLC - May 8, 2023.pdfLeaside-Laird CLC - May 8, 2023.pdf
Leaside-Laird CLC - May 8, 2023.pdf
 
Eglinton - Mt Pleasant CLC - May 10, 2023.pdf
Eglinton - Mt Pleasant CLC - May 10, 2023.pdfEglinton - Mt Pleasant CLC - May 10, 2023.pdf
Eglinton - Mt Pleasant CLC - May 10, 2023.pdf
 
Chaplin-Avenue CLC - May 3 2023 Updated.pptx
Chaplin-Avenue CLC - May 3 2023 Updated.pptxChaplin-Avenue CLC - May 3 2023 Updated.pptx
Chaplin-Avenue CLC - May 3 2023 Updated.pptx
 
CLC Deck - Brentcliffe to Victoria Park - May 4 2023 - Compressed.pptx
CLC Deck - Brentcliffe to Victoria Park - May 4 2023 - Compressed.pptxCLC Deck - Brentcliffe to Victoria Park - May 4 2023 - Compressed.pptx
CLC Deck - Brentcliffe to Victoria Park - May 4 2023 - Compressed.pptx
 
Pharmacy to Kennedy CLC presentation deck - Janaury 31, 2023.pptx
Pharmacy to Kennedy CLC presentation deck - Janaury 31, 2023.pptxPharmacy to Kennedy CLC presentation deck - Janaury 31, 2023.pptx
Pharmacy to Kennedy CLC presentation deck - Janaury 31, 2023.pptx
 
CLC Pharmacy to Kennedy - March 28, 2023 - Compressed.pptx
CLC Pharmacy to Kennedy - March 28, 2023 - Compressed.pptxCLC Pharmacy to Kennedy - March 28, 2023 - Compressed.pptx
CLC Pharmacy to Kennedy - March 28, 2023 - Compressed.pptx
 
CLC Deck - Brentcliffe to Victoria Park - March 2, 2023 - Compressed.pptx
CLC Deck - Brentcliffe to Victoria Park - March 2, 2023 - Compressed.pptxCLC Deck - Brentcliffe to Victoria Park - March 2, 2023 - Compressed.pptx
CLC Deck - Brentcliffe to Victoria Park - March 2, 2023 - Compressed.pptx
 
Chaplin-Avenue CLC - March 1, 2023.pptx
Chaplin-Avenue CLC - March 1, 2023.pptxChaplin-Avenue CLC - March 1, 2023.pptx
Chaplin-Avenue CLC - March 1, 2023.pptx
 
Leaside-Laird CLC - March 13, 2023.pdf
Leaside-Laird CLC - March 13, 2023.pdfLeaside-Laird CLC - March 13, 2023.pdf
Leaside-Laird CLC - March 13, 2023.pdf
 
CLC Deck - Brentcliffe to Victoria Park - March 2, 2023 - Compressed.pptx
CLC Deck - Brentcliffe to Victoria Park - March 2, 2023 - Compressed.pptxCLC Deck - Brentcliffe to Victoria Park - March 2, 2023 - Compressed.pptx
CLC Deck - Brentcliffe to Victoria Park - March 2, 2023 - Compressed.pptx
 
Eglinton - Mount Pleasant CLC - March 8, 2023.pdf
Eglinton - Mount Pleasant CLC - March 8, 2023.pdfEglinton - Mount Pleasant CLC - March 8, 2023.pdf
Eglinton - Mount Pleasant CLC - March 8, 2023.pdf
 
Chaplin-Avenue CLC - November 2 2022 compressed.pptx
Chaplin-Avenue CLC - November 2 2022 compressed.pptxChaplin-Avenue CLC - November 2 2022 compressed.pptx
Chaplin-Avenue CLC - November 2 2022 compressed.pptx
 
Chaplin-Avenue CLC - January 11 2023 (002).pptx
Chaplin-Avenue CLC - January 11 2023 (002).pptxChaplin-Avenue CLC - January 11 2023 (002).pptx
Chaplin-Avenue CLC - January 11 2023 (002).pptx
 
CLC Deck - Brentcliffe to Victoria Park - January 12, 2023 - Compressed.pptx
CLC Deck - Brentcliffe to Victoria Park - January 12, 2023 - Compressed.pptxCLC Deck - Brentcliffe to Victoria Park - January 12, 2023 - Compressed.pptx
CLC Deck - Brentcliffe to Victoria Park - January 12, 2023 - Compressed.pptx
 
Eglinton - Mt Pleasant CLC - January 11, 2023.pdf
Eglinton - Mt Pleasant CLC - January 11, 2023.pdfEglinton - Mt Pleasant CLC - January 11, 2023.pdf
Eglinton - Mt Pleasant CLC - January 11, 2023.pdf
 
Leaside-Laird CLC - January 9, 2023.pdf
Leaside-Laird CLC - January 9, 2023.pdfLeaside-Laird CLC - January 9, 2023.pdf
Leaside-Laird CLC - January 9, 2023.pdf
 
CLC Deck - Brentcliffe to Victoria Park - November 3 2022.pdf
CLC Deck - Brentcliffe to Victoria Park - November 3 2022.pdfCLC Deck - Brentcliffe to Victoria Park - November 3 2022.pdf
CLC Deck - Brentcliffe to Victoria Park - November 3 2022.pdf
 

Recently uploaded

如何办理(uoit毕业证书)加拿大安大略理工大学毕业证文凭证书录取通知原版一模一样
如何办理(uoit毕业证书)加拿大安大略理工大学毕业证文凭证书录取通知原版一模一样如何办理(uoit毕业证书)加拿大安大略理工大学毕业证文凭证书录取通知原版一模一样
如何办理(uoit毕业证书)加拿大安大略理工大学毕业证文凭证书录取通知原版一模一样
850fcj96
 
Russian anarchist and anti-war movement in the third year of full-scale war
Russian anarchist and anti-war movement in the third year of full-scale warRussian anarchist and anti-war movement in the third year of full-scale war
Russian anarchist and anti-war movement in the third year of full-scale war
Antti Rautiainen
 
PPT Item # 5 - 5330 Broadway ARB Case # 930F
PPT Item # 5 - 5330 Broadway ARB Case # 930FPPT Item # 5 - 5330 Broadway ARB Case # 930F
PPT Item # 5 - 5330 Broadway ARB Case # 930F
ahcitycouncil
 
PNRR MADRID GREENTECH FOR BROWN NETWORKS NETWORKS MUR_MUSA_TEBALDI.pdf
PNRR MADRID GREENTECH FOR BROWN NETWORKS NETWORKS MUR_MUSA_TEBALDI.pdfPNRR MADRID GREENTECH FOR BROWN NETWORKS NETWORKS MUR_MUSA_TEBALDI.pdf
PNRR MADRID GREENTECH FOR BROWN NETWORKS NETWORKS MUR_MUSA_TEBALDI.pdf
ClaudioTebaldi2
 
PPT Item # 8 - Tuxedo Columbine 3way Stop
PPT Item # 8 - Tuxedo Columbine 3way StopPPT Item # 8 - Tuxedo Columbine 3way Stop
PPT Item # 8 - Tuxedo Columbine 3way Stop
ahcitycouncil
 
一比一原版(WSU毕业证)西悉尼大学毕业证成绩单
一比一原版(WSU毕业证)西悉尼大学毕业证成绩单一比一原版(WSU毕业证)西悉尼大学毕业证成绩单
一比一原版(WSU毕业证)西悉尼大学毕业证成绩单
evkovas
 
PPT Item # 9 - 2024 Street Maintenance Program(SMP) Amendment
PPT Item # 9 - 2024 Street Maintenance Program(SMP) AmendmentPPT Item # 9 - 2024 Street Maintenance Program(SMP) Amendment
PPT Item # 9 - 2024 Street Maintenance Program(SMP) Amendment
ahcitycouncil
 
Get Government Grants and Assistance Program
Get Government Grants and Assistance ProgramGet Government Grants and Assistance Program
Get Government Grants and Assistance Program
Get Government Grants
 
2024: The FAR - Federal Acquisition Regulations, Part 36
2024: The FAR - Federal Acquisition Regulations, Part 362024: The FAR - Federal Acquisition Regulations, Part 36
2024: The FAR - Federal Acquisition Regulations, Part 36
JSchaus & Associates
 
PPT Item # 6 - 7001 Broadway ARB Case # 933F
PPT Item # 6 - 7001 Broadway ARB Case # 933FPPT Item # 6 - 7001 Broadway ARB Case # 933F
PPT Item # 6 - 7001 Broadway ARB Case # 933F
ahcitycouncil
 
Many ways to support street children.pptx
Many ways to support street children.pptxMany ways to support street children.pptx
Many ways to support street children.pptx
SERUDS INDIA
 
What is the point of small housing associations.pptx
What is the point of small housing associations.pptxWhat is the point of small housing associations.pptx
What is the point of small housing associations.pptx
Paul Smith
 
一比一原版(ANU毕业证)澳大利亚国立大学毕业证成绩单
一比一原版(ANU毕业证)澳大利亚国立大学毕业证成绩单一比一原版(ANU毕业证)澳大利亚国立大学毕业证成绩单
一比一原版(ANU毕业证)澳大利亚国立大学毕业证成绩单
ehbuaw
 
快速制作(ocad毕业证书)加拿大安大略艺术设计学院毕业证本科学历雅思成绩单原版一模一样
快速制作(ocad毕业证书)加拿大安大略艺术设计学院毕业证本科学历雅思成绩单原版一模一样快速制作(ocad毕业证书)加拿大安大略艺术设计学院毕业证本科学历雅思成绩单原版一模一样
快速制作(ocad毕业证书)加拿大安大略艺术设计学院毕业证本科学历雅思成绩单原版一模一样
850fcj96
 
一比一原版(Adelaide毕业证)阿德莱德大学毕业证成绩单
一比一原版(Adelaide毕业证)阿德莱德大学毕业证成绩单一比一原版(Adelaide毕业证)阿德莱德大学毕业证成绩单
一比一原版(Adelaide毕业证)阿德莱德大学毕业证成绩单
ehbuaw
 
PACT launching workshop presentation-Final.pdf
PACT launching workshop presentation-Final.pdfPACT launching workshop presentation-Final.pdf
PACT launching workshop presentation-Final.pdf
Mohammed325561
 
PD-1602-as-amended-by-RA-9287-Anti-Illegal-Gambling-Law.pptx
PD-1602-as-amended-by-RA-9287-Anti-Illegal-Gambling-Law.pptxPD-1602-as-amended-by-RA-9287-Anti-Illegal-Gambling-Law.pptx
PD-1602-as-amended-by-RA-9287-Anti-Illegal-Gambling-Law.pptx
RIDPRO11
 
Uniform Guidance 3.0 - The New 2 CFR 200
Uniform Guidance 3.0 - The New 2 CFR 200Uniform Guidance 3.0 - The New 2 CFR 200
Uniform Guidance 3.0 - The New 2 CFR 200
GrantManagementInsti
 
一比一原版(QUT毕业证)昆士兰科技大学毕业证成绩单
一比一原版(QUT毕业证)昆士兰科技大学毕业证成绩单一比一原版(QUT毕业证)昆士兰科技大学毕业证成绩单
一比一原版(QUT毕业证)昆士兰科技大学毕业证成绩单
ukyewh
 
Canadian Immigration Tracker March 2024 - Key Slides
Canadian Immigration Tracker March 2024 - Key SlidesCanadian Immigration Tracker March 2024 - Key Slides
Canadian Immigration Tracker March 2024 - Key Slides
Andrew Griffith
 

Recently uploaded (20)

如何办理(uoit毕业证书)加拿大安大略理工大学毕业证文凭证书录取通知原版一模一样
如何办理(uoit毕业证书)加拿大安大略理工大学毕业证文凭证书录取通知原版一模一样如何办理(uoit毕业证书)加拿大安大略理工大学毕业证文凭证书录取通知原版一模一样
如何办理(uoit毕业证书)加拿大安大略理工大学毕业证文凭证书录取通知原版一模一样
 
Russian anarchist and anti-war movement in the third year of full-scale war
Russian anarchist and anti-war movement in the third year of full-scale warRussian anarchist and anti-war movement in the third year of full-scale war
Russian anarchist and anti-war movement in the third year of full-scale war
 
PPT Item # 5 - 5330 Broadway ARB Case # 930F
PPT Item # 5 - 5330 Broadway ARB Case # 930FPPT Item # 5 - 5330 Broadway ARB Case # 930F
PPT Item # 5 - 5330 Broadway ARB Case # 930F
 
PNRR MADRID GREENTECH FOR BROWN NETWORKS NETWORKS MUR_MUSA_TEBALDI.pdf
PNRR MADRID GREENTECH FOR BROWN NETWORKS NETWORKS MUR_MUSA_TEBALDI.pdfPNRR MADRID GREENTECH FOR BROWN NETWORKS NETWORKS MUR_MUSA_TEBALDI.pdf
PNRR MADRID GREENTECH FOR BROWN NETWORKS NETWORKS MUR_MUSA_TEBALDI.pdf
 
PPT Item # 8 - Tuxedo Columbine 3way Stop
PPT Item # 8 - Tuxedo Columbine 3way StopPPT Item # 8 - Tuxedo Columbine 3way Stop
PPT Item # 8 - Tuxedo Columbine 3way Stop
 
一比一原版(WSU毕业证)西悉尼大学毕业证成绩单
一比一原版(WSU毕业证)西悉尼大学毕业证成绩单一比一原版(WSU毕业证)西悉尼大学毕业证成绩单
一比一原版(WSU毕业证)西悉尼大学毕业证成绩单
 
PPT Item # 9 - 2024 Street Maintenance Program(SMP) Amendment
PPT Item # 9 - 2024 Street Maintenance Program(SMP) AmendmentPPT Item # 9 - 2024 Street Maintenance Program(SMP) Amendment
PPT Item # 9 - 2024 Street Maintenance Program(SMP) Amendment
 
Get Government Grants and Assistance Program
Get Government Grants and Assistance ProgramGet Government Grants and Assistance Program
Get Government Grants and Assistance Program
 
2024: The FAR - Federal Acquisition Regulations, Part 36
2024: The FAR - Federal Acquisition Regulations, Part 362024: The FAR - Federal Acquisition Regulations, Part 36
2024: The FAR - Federal Acquisition Regulations, Part 36
 
PPT Item # 6 - 7001 Broadway ARB Case # 933F
PPT Item # 6 - 7001 Broadway ARB Case # 933FPPT Item # 6 - 7001 Broadway ARB Case # 933F
PPT Item # 6 - 7001 Broadway ARB Case # 933F
 
Many ways to support street children.pptx
Many ways to support street children.pptxMany ways to support street children.pptx
Many ways to support street children.pptx
 
What is the point of small housing associations.pptx
What is the point of small housing associations.pptxWhat is the point of small housing associations.pptx
What is the point of small housing associations.pptx
 
一比一原版(ANU毕业证)澳大利亚国立大学毕业证成绩单
一比一原版(ANU毕业证)澳大利亚国立大学毕业证成绩单一比一原版(ANU毕业证)澳大利亚国立大学毕业证成绩单
一比一原版(ANU毕业证)澳大利亚国立大学毕业证成绩单
 
快速制作(ocad毕业证书)加拿大安大略艺术设计学院毕业证本科学历雅思成绩单原版一模一样
快速制作(ocad毕业证书)加拿大安大略艺术设计学院毕业证本科学历雅思成绩单原版一模一样快速制作(ocad毕业证书)加拿大安大略艺术设计学院毕业证本科学历雅思成绩单原版一模一样
快速制作(ocad毕业证书)加拿大安大略艺术设计学院毕业证本科学历雅思成绩单原版一模一样
 
一比一原版(Adelaide毕业证)阿德莱德大学毕业证成绩单
一比一原版(Adelaide毕业证)阿德莱德大学毕业证成绩单一比一原版(Adelaide毕业证)阿德莱德大学毕业证成绩单
一比一原版(Adelaide毕业证)阿德莱德大学毕业证成绩单
 
PACT launching workshop presentation-Final.pdf
PACT launching workshop presentation-Final.pdfPACT launching workshop presentation-Final.pdf
PACT launching workshop presentation-Final.pdf
 
PD-1602-as-amended-by-RA-9287-Anti-Illegal-Gambling-Law.pptx
PD-1602-as-amended-by-RA-9287-Anti-Illegal-Gambling-Law.pptxPD-1602-as-amended-by-RA-9287-Anti-Illegal-Gambling-Law.pptx
PD-1602-as-amended-by-RA-9287-Anti-Illegal-Gambling-Law.pptx
 
Uniform Guidance 3.0 - The New 2 CFR 200
Uniform Guidance 3.0 - The New 2 CFR 200Uniform Guidance 3.0 - The New 2 CFR 200
Uniform Guidance 3.0 - The New 2 CFR 200
 
一比一原版(QUT毕业证)昆士兰科技大学毕业证成绩单
一比一原版(QUT毕业证)昆士兰科技大学毕业证成绩单一比一原版(QUT毕业证)昆士兰科技大学毕业证成绩单
一比一原版(QUT毕业证)昆士兰科技大学毕业证成绩单
 
Canadian Immigration Tracker March 2024 - Key Slides
Canadian Immigration Tracker March 2024 - Key SlidesCanadian Immigration Tracker March 2024 - Key Slides
Canadian Immigration Tracker March 2024 - Key Slides
 

Pharmacy to Kennedy Construction Liaison Committee Meeting

  • 1. CROSSTOWN LRT Pharmacy-Kennedy CLC Meeting September 25, 2018
  • 2. • Old concrete removal at Kennedy Station • New street light installation and civil works underway between Victoria Park Avenue and Pharmacy • Excavation complete for Wilson Brook Culvert Stage 1 installation • Stage 1 decks poured on Celestica Bridge • Dry utility upgrades in Section 2 (DVP to Victoria Park) and Section 3 (Victoria Park to Birchmount) ongoing. • Mid-block median removals have resumed; Intersection work continues. • Installation of temporary signals complete between Leslie Street and Kennedy Station. • Road widening slated to start between Victoria Park Avenue to Kennedy Road • Stage 1 Traffic installation from Victoria Park to Birchmount Road Progress to Date 2
  • 3. • Utility upgrades and relocations (THESL and telecom) continue between Pharmacy and Birchmount and within the Kennedy Station zone of influence (ZOI). • Wet utility upgrades and relocations continue within the Kennedy Station ZOI and Section 4 (Rosemount to Kennedy). • Wet utility upgrades in Section 3 (Victoria Park to Birchmount). • Road works from Victoria Park to Pharmacy • Green wall excavation and construction at E.T. Seton Park • Eglinton Avenue road widening continues. • Road construction within the East Portal • Support of excavation for the Kennedy Portal/Station Box and tail track underway. • TTC: West Ped Tunnel, East Ped Tunnel, TPSS; Support of excavation activities within TTC ZOI underway. • Reconstruction of Massey and Wilson Brook Creek Culverts. • GO: GIMP Monitoring, SOE at Tail Track- North East platform, Rebar, formwork, concrete at West Platform. • Bridge rehabilitations: East Don River, Wynford and Celestica bridges. Current Works 3
  • 4. • Ongoing utility upgrades and relocations: Toronto Hydro relocations, Wet utility relocations (water, sanitary sewer, storm sewer) and telecom on Eglinton Avenue East and within the TTC ZOI. • Start construction of the guideway, intersection works, and road widening. • Stage 6 Traffic installation- Kennedy Station • GO East Platform restoration, inspection and open to public • Bus loop rehabilitation : Kennedy –Main Station Box • Stage 7A Traffic installation –Science Centre What’s coming in 2018 4
  • 5. Wilson Brook Culvert- Future Sloane Stop As part of the ongoing works to build the LRT system along Eglinton Avenue, work on the Wilson Brook Culvert will be taking place on the south and north side of Eglinton Avenue in front of 1730 Eglinton Avenue East. This work is began as early as Wednesday, August 16 and will continue to December 15, 2018. Crews will be building a temporary storm drain line, as well as excavating and replacing the storm water culvert under Eglinton Ave East. 5
  • 6. Storm & Sanitary relocation work in the vicinity of Ionview Road and Kennedy Road Ongoing storm and sanitary relocation work from Ionview to Kennedy is approaching completion and along with the remaining manhole connections the work is expected to be completed within a month and half. 6
  • 7. Support of Excavation at Kennedy Station: Current Stage In early April 2018, crews started support of excavation (SOE) work - also known as shoring - for the future Kennedy Station. Currently SOE is underway on both the east and west sides of Kennedy Road. Shoring will be conducted in phases. The entire shoring process will take approximately twelve (12) months. Current traffic staging at Kennedy Road and Eglinton Avenue East. 7
  • 8. SOE Works at Kennedy GO Station Platform To facilitate these improvements, installation of support of excavation are also being made to the GO Transit Stouffville Corridor at Kennedy GO Station started as early as Saturday, September 8, 2018. Work will take approximately three (3) months to complete. 8
  • 9. What to Expect in 2018 Kennedy Station: Summer/Fall 2018 9
  • 10. Construction Progress Pictures Rebar work Storm & Sanitary installation 10
  • 11. Construction Progress Pictures Road widening Traffic Light work 11