The document provides updates on construction activities at the Chaplin and Avenue stations for the Crosstown LRT project in January and February 2020. At Chaplin Station, dewatering well installation, extended hours for deep excavation of the main entrance, and shallow excavation and roof construction will occur through February. Concrete pouring of the south station box is scheduled for January 24. Deep excavation of the station box from the main entrance will take place from February for approximately three months. At Avenue Station, mining excavation east of the secondary entrance will continue through July 2020, with overnight noise and potential road impacts. Concrete pours between the main and secondary entrances will occur weekly through 2020. Borehole drilling and other monitoring work will also temporarily impact