SlideShare a Scribd company logo
1 of 18
CROSSTOWN LRT
Construction Liaison
Committee
February 7, 2017
2
Chaplin Construction Updates
3
ACTIVITY AREA IMPACT DURATION START DATE
Support of
Excavation - Piling
Within northwest
work zone on Eglinton
Ave W
• Noise and vibration from drilling activity
Ongoing through
Winter 2018
Underway
Guidewall Removal
Within southeast
work zone on
Eglinton Ave W
• Noise and vibration from concrete breaking
activity
Periodically
through Winter
2018
Ongoing
Watermain Bypass
Within southwest
work zone on
Eglinton Ave W and
Chaplin Cres
• Noise from construction activity
Ongoing through
March 2018
Underway
Storm Sewer
Installation
Within southwest
work zone on
Eglinton Ave W and
Chaplin Cres
• Noise from construction activity
Ongoing through
March 2018
Underway
Traffic Change –
Temporary Driveway
Closure
North work zone on
Eglinton Ave W at 564
Eglinton Ave W
• Temporary driveway closure
• Relocation parking to Tertiary Entrance
One (1) month
As early as
February 6,
2018
Traffic Change –
Close Latimer
North side of Eglinton
Ave
• Extension of northeast work zone
• No access to Latimer Ave from Eglinton Ave W
• No access to Eglinton Ave W from Latimer Ave
• Shoppers Drug Mart southwest driveway closure
Approximately
one (1) month
As early as
February 20,
2018
Chaplin Station: What to Expect February 2018
4
Current Construction Staging
January 26, 2018 until February 20, 2018
5
Upcoming Construction Staging
February 20, 2018 for approximately one (1) month
6
Future Construction Staging
As early as March 20, 2018 through 2018
7
Avenue Construction Updates
8
Short Term Activities Area & Impacts Duration Tentative Date
Tunnel Connection
Boreholes and
Concrete Pouring
(Main Entrance)
• South side of
Eglinton, west of
Avenue Road across
from the Main
Entrance site
• A work zone will be set up on the
south side of Eglinton west of
Avenue Road and will remain in place
for the duration of the drilling.
• Sidewalk will be open, and
pedestrians will be routed around
the work temporarily.
• No on street parking on Eglinton
between Braemar and Avenue while
the work zone is set up.
Borehole drilling:
approx. 2-3 weeks
Concrete pouring:
approx. 2 weeks
Underway:
approx. 1 more
week remaining
for drilling
portion.
Dewatering work
(daytime) Installation
and trenching
• Eglinton north and south from
Oriole Pkwy to Lascelles
• Sidewalk, road and parking impacts
depending on location of trench and
equipment
• Pedestrians will be routed around
location of work
Approx. 4 weeks
remaining
Work will resume
in mid February
Avenue Station: What to Expect February 2018
9
Preparation for Mining at Main Entrance
Short Term Activities Area & Impacts Duration Tentative Date
Mining Equipment
Mobilization at the
Main Entrance
• A large mobile
crane will be on
site to lower the
heavy equipment in
to the excavated
entrance and
remove some
equipment
currently on site.
• One additional westbound lane will be
required. One west bound lane will be
maintained.
• On-street parking spaces on the north
side of Eglinton Avenue between Avenue
Road and the crosswalk will be
temporarily unavailable.
• The crosswalk will be temporarily
unavailable for pedestrians during this
time.
Approx.
48 hours
continuous
work (includes
overnight
periods)
Feb 23 to Feb
25, 2018
Crane Delivery and
Installation (Main
Entrance)
• A Gantry Crane will
be erected above
the Main Entrance
excavation shaft
• The crane will be delivered to the Main
Entrance site.
• Due to the size of the beams for the
crane supports, the deliveries may
temporarily delay traffic movements
while the truck enters the site to deliver
the materials.
Approx. 1 week Dates TBD
February –
March
10
Mining Equipment Mobilization
11
Watermain Lining & Temporary Water Service
Short Term
Activities
Area & Impacts Duration Tentative Date
Watermain lining • Properties from 282 Eglinton Ave to
the east will be serviced through the
laneway
• Properties from 284 Eglinton Ave to
the west will be serviced from the front
• Temporary water supply pipes will be
installed in the City right of way
• An area in front of each property will
be excavated to access the water
connection and it will be plated for the
duration of the lining (one to two
months)
• After the lining is completed, the area
will be restored and that will take
approximately one week
2 weeks to install
temporary
service
4 – 6 weeks for
lining
February / March
12
Temporary Water Service Installation (for watermain lining)
• Work is planned from 7pm to 7am (pending City Councillor approval)
• Excavation in front of each property (shown in blue)
• Parking will be unavailable during work hours (red hash marks)
• Pedestrians will have a 1.5m walkway around the work zone (shown in green)
• Minor trenching in laneway between 280 Eglinton Avenue and Oriole Parkway
and on Oriole Parkway from closure to laneway (shown in red)
13
Final Sewer Lining Section
ACTIVITY & AREA WHAT TO EXPECT DURATION TENTATIVE
DATE
Sewer Lining
East Sewer Section
ď‚· Sewer lining is done
to protect and
reinforce the sewer
pipes while we dig
out the future
station area beneath
them
• The remaining section (East Section)
runs along Eglinton between Oriole
Parkway and Lascelles.
• A work zone will be set up in the
roadway between Eastbourne and
Lascelles.
• Expect one lane in each direction on
Eglinton between Eastbourne and
Lascelles.
• No on street parking on Eglinton
between Eastbourne and Lascelles
while work zone is set up.
• Sewer lining work can have a chemical
smell; while unpleasant it is not
harmful. Please follow mitigation
instructions in the construction notice
in advance.
Approx. 1
week
Tentative week
of February 15
14
Final Sewer Lining Section
15
Short Term
Activities
Area & Impacts Duration Tentative Date
Monitoring Work
• Equipment is
installed in
various
locations
around the
station area to
monitor ground
movement
during
construction.
• To install the monitoring equipment in
the ground, crews move from location
to location around the station area.
Typically a drilling machine is used to
drill the hole where the monitor will be
installed.
• If on the sidewalk, pedestrians may
need to be routed around the work
zone (sidewalks stay open). If on the
roadway, a short term lane closure may
be required.
Installations
planned to be
complete in the
next few months.
Readings will be
taken regularly
for the duration
of the project.
Ongoing
Avenue Station: What to Expect February 2018
16
Avenue Station – Secondary Entrance
17
Avenue Station – Secondary Entrance
18
Avenue Station – Secondary Entrance

More Related Content

What's hot

Chaplin - Avenue Construction Liaison Committee - June 2018
Chaplin - Avenue Construction Liaison Committee - June 2018Chaplin - Avenue Construction Liaison Committee - June 2018
Chaplin - Avenue Construction Liaison Committee - June 2018Crosstown TO
 
Eglinton & Mount Pleasant Stations Construction Liaison Committee Meeting - J...
Eglinton & Mount Pleasant Stations Construction Liaison Committee Meeting - J...Eglinton & Mount Pleasant Stations Construction Liaison Committee Meeting - J...
Eglinton & Mount Pleasant Stations Construction Liaison Committee Meeting - J...Crosstown TO
 
Chaplin & Avenue Stations Construction Liaison Committee Meeting - January 2018
Chaplin & Avenue Stations Construction Liaison Committee Meeting - January 2018Chaplin & Avenue Stations Construction Liaison Committee Meeting - January 2018
Chaplin & Avenue Stations Construction Liaison Committee Meeting - January 2018Crosstown TO
 
Cedarvale & Forest Hill Construction Update (September 30, 2020)
Cedarvale & Forest Hill Construction Update (September 30, 2020)Cedarvale & Forest Hill Construction Update (September 30, 2020)
Cedarvale & Forest Hill Construction Update (September 30, 2020)Crosstown TO
 
Fairbank & Oakwood Stations Construction Liaison Committee Meeting - Aug 2017
Fairbank & Oakwood Stations Construction Liaison Committee Meeting - Aug 2017Fairbank & Oakwood Stations Construction Liaison Committee Meeting - Aug 2017
Fairbank & Oakwood Stations Construction Liaison Committee Meeting - Aug 2017Crosstown TO
 
Eglinton & Mount Pleasant Construction Liaison Committee Meeting - September ...
Eglinton & Mount Pleasant Construction Liaison Committee Meeting - September ...Eglinton & Mount Pleasant Construction Liaison Committee Meeting - September ...
Eglinton & Mount Pleasant Construction Liaison Committee Meeting - September ...Crosstown TO
 
Cedarvale & Forest Hill CLC - Construction Update - Oct 25, 2017
Cedarvale & Forest Hill CLC - Construction Update - Oct 25, 2017Cedarvale & Forest Hill CLC - Construction Update - Oct 25, 2017
Cedarvale & Forest Hill CLC - Construction Update - Oct 25, 2017Crosstown TO
 
Central Virtual Open House 28Apr2021
Central Virtual Open House 28Apr2021Central Virtual Open House 28Apr2021
Central Virtual Open House 28Apr2021Crosstown TO
 
Chaplin - Avenue Construction Liaison Committee - July 2018
Chaplin - Avenue Construction Liaison Committee - July 2018Chaplin - Avenue Construction Liaison Committee - July 2018
Chaplin - Avenue Construction Liaison Committee - July 2018Crosstown TO
 
Chaplin & Avenue CLC - Construction Update - April 4, 2018
Chaplin & Avenue CLC - Construction Update - April 4, 2018Chaplin & Avenue CLC - Construction Update - April 4, 2018
Chaplin & Avenue CLC - Construction Update - April 4, 2018Crosstown TO
 
Eglinton and Mount Pleasant Construction Liaison Committee Meeting - October ...
Eglinton and Mount Pleasant Construction Liaison Committee Meeting - October ...Eglinton and Mount Pleasant Construction Liaison Committee Meeting - October ...
Eglinton and Mount Pleasant Construction Liaison Committee Meeting - October ...Crosstown TO
 
Eglinton - Mount Pleasant CLC 13 Jan 2021
Eglinton - Mount Pleasant CLC 13 Jan 2021Eglinton - Mount Pleasant CLC 13 Jan 2021
Eglinton - Mount Pleasant CLC 13 Jan 2021Crosstown TO
 
Brentcliffe-Victoria Park CLC Meeting
Brentcliffe-Victoria Park CLC MeetingBrentcliffe-Victoria Park CLC Meeting
Brentcliffe-Victoria Park CLC MeetingCrosstown TO
 
Cedarvale & Forest Hill Construction Update - May 27, 2020
Cedarvale & Forest Hill Construction Update - May 27, 2020Cedarvale & Forest Hill Construction Update - May 27, 2020
Cedarvale & Forest Hill Construction Update - May 27, 2020Crosstown TO
 
Central West Fall Open House Presentation Deck - October 14, 2020
Central West Fall Open House Presentation Deck - October 14, 2020Central West Fall Open House Presentation Deck - October 14, 2020
Central West Fall Open House Presentation Deck - October 14, 2020Crosstown TO
 
Cedarvale & Forest Hill Construction Update (May 28, 2021)
Cedarvale & Forest Hill Construction Update (May 28, 2021)Cedarvale & Forest Hill Construction Update (May 28, 2021)
Cedarvale & Forest Hill Construction Update (May 28, 2021)Crosstown TO
 
Eglinton-Mt Pleasant Construction Liaison Committee - November 202011 2020
Eglinton-Mt Pleasant Construction Liaison Committee - November 202011 2020Eglinton-Mt Pleasant Construction Liaison Committee - November 202011 2020
Eglinton-Mt Pleasant Construction Liaison Committee - November 202011 2020Crosstown TO
 
Eglinton and Mount Pleasant Construction Liaison Committee Meeting - Jan 2019
Eglinton and Mount Pleasant Construction Liaison Committee Meeting - Jan 2019Eglinton and Mount Pleasant Construction Liaison Committee Meeting - Jan 2019
Eglinton and Mount Pleasant Construction Liaison Committee Meeting - Jan 2019Crosstown TO
 
Avenue & Chaplin CLC - Construction Update: January 6, 2021
Avenue & Chaplin CLC - Construction Update: January 6, 2021Avenue & Chaplin CLC - Construction Update: January 6, 2021
Avenue & Chaplin CLC - Construction Update: January 6, 2021Crosstown TO
 
Eglinton-Mount Pleasant Construction Liaison Committee Meeting - May 2018
Eglinton-Mount Pleasant Construction Liaison Committee Meeting - May 2018Eglinton-Mount Pleasant Construction Liaison Committee Meeting - May 2018
Eglinton-Mount Pleasant Construction Liaison Committee Meeting - May 2018Crosstown TO
 

What's hot (20)

Chaplin - Avenue Construction Liaison Committee - June 2018
Chaplin - Avenue Construction Liaison Committee - June 2018Chaplin - Avenue Construction Liaison Committee - June 2018
Chaplin - Avenue Construction Liaison Committee - June 2018
 
Eglinton & Mount Pleasant Stations Construction Liaison Committee Meeting - J...
Eglinton & Mount Pleasant Stations Construction Liaison Committee Meeting - J...Eglinton & Mount Pleasant Stations Construction Liaison Committee Meeting - J...
Eglinton & Mount Pleasant Stations Construction Liaison Committee Meeting - J...
 
Chaplin & Avenue Stations Construction Liaison Committee Meeting - January 2018
Chaplin & Avenue Stations Construction Liaison Committee Meeting - January 2018Chaplin & Avenue Stations Construction Liaison Committee Meeting - January 2018
Chaplin & Avenue Stations Construction Liaison Committee Meeting - January 2018
 
Cedarvale & Forest Hill Construction Update (September 30, 2020)
Cedarvale & Forest Hill Construction Update (September 30, 2020)Cedarvale & Forest Hill Construction Update (September 30, 2020)
Cedarvale & Forest Hill Construction Update (September 30, 2020)
 
Fairbank & Oakwood Stations Construction Liaison Committee Meeting - Aug 2017
Fairbank & Oakwood Stations Construction Liaison Committee Meeting - Aug 2017Fairbank & Oakwood Stations Construction Liaison Committee Meeting - Aug 2017
Fairbank & Oakwood Stations Construction Liaison Committee Meeting - Aug 2017
 
Eglinton & Mount Pleasant Construction Liaison Committee Meeting - September ...
Eglinton & Mount Pleasant Construction Liaison Committee Meeting - September ...Eglinton & Mount Pleasant Construction Liaison Committee Meeting - September ...
Eglinton & Mount Pleasant Construction Liaison Committee Meeting - September ...
 
Cedarvale & Forest Hill CLC - Construction Update - Oct 25, 2017
Cedarvale & Forest Hill CLC - Construction Update - Oct 25, 2017Cedarvale & Forest Hill CLC - Construction Update - Oct 25, 2017
Cedarvale & Forest Hill CLC - Construction Update - Oct 25, 2017
 
Central Virtual Open House 28Apr2021
Central Virtual Open House 28Apr2021Central Virtual Open House 28Apr2021
Central Virtual Open House 28Apr2021
 
Chaplin - Avenue Construction Liaison Committee - July 2018
Chaplin - Avenue Construction Liaison Committee - July 2018Chaplin - Avenue Construction Liaison Committee - July 2018
Chaplin - Avenue Construction Liaison Committee - July 2018
 
Chaplin & Avenue CLC - Construction Update - April 4, 2018
Chaplin & Avenue CLC - Construction Update - April 4, 2018Chaplin & Avenue CLC - Construction Update - April 4, 2018
Chaplin & Avenue CLC - Construction Update - April 4, 2018
 
Eglinton and Mount Pleasant Construction Liaison Committee Meeting - October ...
Eglinton and Mount Pleasant Construction Liaison Committee Meeting - October ...Eglinton and Mount Pleasant Construction Liaison Committee Meeting - October ...
Eglinton and Mount Pleasant Construction Liaison Committee Meeting - October ...
 
Eglinton - Mount Pleasant CLC 13 Jan 2021
Eglinton - Mount Pleasant CLC 13 Jan 2021Eglinton - Mount Pleasant CLC 13 Jan 2021
Eglinton - Mount Pleasant CLC 13 Jan 2021
 
Brentcliffe-Victoria Park CLC Meeting
Brentcliffe-Victoria Park CLC MeetingBrentcliffe-Victoria Park CLC Meeting
Brentcliffe-Victoria Park CLC Meeting
 
Cedarvale & Forest Hill Construction Update - May 27, 2020
Cedarvale & Forest Hill Construction Update - May 27, 2020Cedarvale & Forest Hill Construction Update - May 27, 2020
Cedarvale & Forest Hill Construction Update - May 27, 2020
 
Central West Fall Open House Presentation Deck - October 14, 2020
Central West Fall Open House Presentation Deck - October 14, 2020Central West Fall Open House Presentation Deck - October 14, 2020
Central West Fall Open House Presentation Deck - October 14, 2020
 
Cedarvale & Forest Hill Construction Update (May 28, 2021)
Cedarvale & Forest Hill Construction Update (May 28, 2021)Cedarvale & Forest Hill Construction Update (May 28, 2021)
Cedarvale & Forest Hill Construction Update (May 28, 2021)
 
Eglinton-Mt Pleasant Construction Liaison Committee - November 202011 2020
Eglinton-Mt Pleasant Construction Liaison Committee - November 202011 2020Eglinton-Mt Pleasant Construction Liaison Committee - November 202011 2020
Eglinton-Mt Pleasant Construction Liaison Committee - November 202011 2020
 
Eglinton and Mount Pleasant Construction Liaison Committee Meeting - Jan 2019
Eglinton and Mount Pleasant Construction Liaison Committee Meeting - Jan 2019Eglinton and Mount Pleasant Construction Liaison Committee Meeting - Jan 2019
Eglinton and Mount Pleasant Construction Liaison Committee Meeting - Jan 2019
 
Avenue & Chaplin CLC - Construction Update: January 6, 2021
Avenue & Chaplin CLC - Construction Update: January 6, 2021Avenue & Chaplin CLC - Construction Update: January 6, 2021
Avenue & Chaplin CLC - Construction Update: January 6, 2021
 
Eglinton-Mount Pleasant Construction Liaison Committee Meeting - May 2018
Eglinton-Mount Pleasant Construction Liaison Committee Meeting - May 2018Eglinton-Mount Pleasant Construction Liaison Committee Meeting - May 2018
Eglinton-Mount Pleasant Construction Liaison Committee Meeting - May 2018
 

Similar to Chaplin & Avenue CLC - Construction Update - February 7, 2018

Chaplin-Avenue Construction Liaison Committee Meeting - May 2018
Chaplin-Avenue Construction Liaison Committee Meeting - May 2018Chaplin-Avenue Construction Liaison Committee Meeting - May 2018
Chaplin-Avenue Construction Liaison Committee Meeting - May 2018Crosstown TO
 
Chaplin - Avenue Construction Liaison Committee Meeting - March 2018
Chaplin - Avenue Construction Liaison Committee Meeting - March 2018Chaplin - Avenue Construction Liaison Committee Meeting - March 2018
Chaplin - Avenue Construction Liaison Committee Meeting - March 2018Crosstown TO
 
Fairbank & Oakwood Stations Construction Liaison Committee - Feb 2018
Fairbank & Oakwood Stations Construction Liaison Committee - Feb 2018Fairbank & Oakwood Stations Construction Liaison Committee - Feb 2018
Fairbank & Oakwood Stations Construction Liaison Committee - Feb 2018Crosstown TO
 
Chaplin-Avenue Construction Liaison Committee Meeting - October 2017
Chaplin-Avenue Construction Liaison Committee Meeting - October 2017Chaplin-Avenue Construction Liaison Committee Meeting - October 2017
Chaplin-Avenue Construction Liaison Committee Meeting - October 2017Crosstown TO
 
Brentcliffe - Victoria Park Construction Liaison Committee Meeting
Brentcliffe - Victoria Park Construction Liaison Committee MeetingBrentcliffe - Victoria Park Construction Liaison Committee Meeting
Brentcliffe - Victoria Park Construction Liaison Committee MeetingCrosstown TO
 
Leaside open house sep 2014 Slides
Leaside open house sep 2014 SlidesLeaside open house sep 2014 Slides
Leaside open house sep 2014 SlidesCrosstown TO
 
Leaside open house sep 2014 slides
Leaside open house sep 2014   slidesLeaside open house sep 2014   slides
Leaside open house sep 2014 slidesCrosstown TO
 
Fairbank & Oakwood Construction Liaison Committee July 2018
Fairbank & Oakwood Construction Liaison Committee July 2018Fairbank & Oakwood Construction Liaison Committee July 2018
Fairbank & Oakwood Construction Liaison Committee July 2018Crosstown TO
 
Chaplin & Avenue Construction Liaison Committee Meeting - November 2017
Chaplin & Avenue Construction Liaison Committee Meeting - November 2017Chaplin & Avenue Construction Liaison Committee Meeting - November 2017
Chaplin & Avenue Construction Liaison Committee Meeting - November 2017Crosstown TO
 
Brentcliffe - Victoria Park Construction Liaison Committee Meeting
Brentcliffe - Victoria Park Construction Liaison Committee MeetingBrentcliffe - Victoria Park Construction Liaison Committee Meeting
Brentcliffe - Victoria Park Construction Liaison Committee MeetingCrosstown TO
 
Pharmacy to Kennedy Construction Liaison Committee Meeting
Pharmacy to Kennedy Construction Liaison Committee MeetingPharmacy to Kennedy Construction Liaison Committee Meeting
Pharmacy to Kennedy Construction Liaison Committee MeetingCrosstown TO
 
Leaside & Laird Construction Liaison Committee Meeting - September 2017
Leaside & Laird Construction Liaison Committee Meeting - September 2017Leaside & Laird Construction Liaison Committee Meeting - September 2017
Leaside & Laird Construction Liaison Committee Meeting - September 2017Crosstown TO
 
Chaplin & Avenue Construction Liaison Committee Meeting - July 2017
Chaplin & Avenue Construction Liaison Committee Meeting - July 2017Chaplin & Avenue Construction Liaison Committee Meeting - July 2017
Chaplin & Avenue Construction Liaison Committee Meeting - July 2017Crosstown TO
 
Mount Pleasant Station Open House - April 2017
Mount Pleasant Station Open House - April 2017Mount Pleasant Station Open House - April 2017
Mount Pleasant Station Open House - April 2017Crosstown TO
 
Chaplin Avenue CLC Presentation Deck - Jan 8 2020
  Chaplin Avenue CLC Presentation Deck - Jan 8 2020  Chaplin Avenue CLC Presentation Deck - Jan 8 2020
Chaplin Avenue CLC Presentation Deck - Jan 8 2020Crosstown TO
 
Leaside & Laird Construction Liaison Committee Meeting - January 2018
Leaside & Laird Construction Liaison Committee Meeting - January 2018Leaside & Laird Construction Liaison Committee Meeting - January 2018
Leaside & Laird Construction Liaison Committee Meeting - January 2018Crosstown TO
 
Brentcliffe - Victoria Park Construction Liaison Committee Meeting
Brentcliffe - Victoria Park Construction Liaison Committee MeetingBrentcliffe - Victoria Park Construction Liaison Committee Meeting
Brentcliffe - Victoria Park Construction Liaison Committee MeetingCrosstown TO
 
Leaside - Laird Construction Liaison Committee Meeting - March 2018
Leaside - Laird Construction Liaison Committee Meeting - March 2018Leaside - Laird Construction Liaison Committee Meeting - March 2018
Leaside - Laird Construction Liaison Committee Meeting - March 2018Crosstown TO
 
Fairbank & Oakwood Stations Open House - April 2017
Fairbank & Oakwood Stations Open House - April 2017Fairbank & Oakwood Stations Open House - April 2017
Fairbank & Oakwood Stations Open House - April 2017Crosstown TO
 
Eglinton- Mount Pleasant Construction Liaison Committee Meeting - July 2017
Eglinton- Mount Pleasant Construction Liaison Committee Meeting - July 2017Eglinton- Mount Pleasant Construction Liaison Committee Meeting - July 2017
Eglinton- Mount Pleasant Construction Liaison Committee Meeting - July 2017Crosstown TO
 

Similar to Chaplin & Avenue CLC - Construction Update - February 7, 2018 (20)

Chaplin-Avenue Construction Liaison Committee Meeting - May 2018
Chaplin-Avenue Construction Liaison Committee Meeting - May 2018Chaplin-Avenue Construction Liaison Committee Meeting - May 2018
Chaplin-Avenue Construction Liaison Committee Meeting - May 2018
 
Chaplin - Avenue Construction Liaison Committee Meeting - March 2018
Chaplin - Avenue Construction Liaison Committee Meeting - March 2018Chaplin - Avenue Construction Liaison Committee Meeting - March 2018
Chaplin - Avenue Construction Liaison Committee Meeting - March 2018
 
Fairbank & Oakwood Stations Construction Liaison Committee - Feb 2018
Fairbank & Oakwood Stations Construction Liaison Committee - Feb 2018Fairbank & Oakwood Stations Construction Liaison Committee - Feb 2018
Fairbank & Oakwood Stations Construction Liaison Committee - Feb 2018
 
Chaplin-Avenue Construction Liaison Committee Meeting - October 2017
Chaplin-Avenue Construction Liaison Committee Meeting - October 2017Chaplin-Avenue Construction Liaison Committee Meeting - October 2017
Chaplin-Avenue Construction Liaison Committee Meeting - October 2017
 
Brentcliffe - Victoria Park Construction Liaison Committee Meeting
Brentcliffe - Victoria Park Construction Liaison Committee MeetingBrentcliffe - Victoria Park Construction Liaison Committee Meeting
Brentcliffe - Victoria Park Construction Liaison Committee Meeting
 
Leaside open house sep 2014 Slides
Leaside open house sep 2014 SlidesLeaside open house sep 2014 Slides
Leaside open house sep 2014 Slides
 
Leaside open house sep 2014 slides
Leaside open house sep 2014   slidesLeaside open house sep 2014   slides
Leaside open house sep 2014 slides
 
Fairbank & Oakwood Construction Liaison Committee July 2018
Fairbank & Oakwood Construction Liaison Committee July 2018Fairbank & Oakwood Construction Liaison Committee July 2018
Fairbank & Oakwood Construction Liaison Committee July 2018
 
Chaplin & Avenue Construction Liaison Committee Meeting - November 2017
Chaplin & Avenue Construction Liaison Committee Meeting - November 2017Chaplin & Avenue Construction Liaison Committee Meeting - November 2017
Chaplin & Avenue Construction Liaison Committee Meeting - November 2017
 
Brentcliffe - Victoria Park Construction Liaison Committee Meeting
Brentcliffe - Victoria Park Construction Liaison Committee MeetingBrentcliffe - Victoria Park Construction Liaison Committee Meeting
Brentcliffe - Victoria Park Construction Liaison Committee Meeting
 
Pharmacy to Kennedy Construction Liaison Committee Meeting
Pharmacy to Kennedy Construction Liaison Committee MeetingPharmacy to Kennedy Construction Liaison Committee Meeting
Pharmacy to Kennedy Construction Liaison Committee Meeting
 
Leaside & Laird Construction Liaison Committee Meeting - September 2017
Leaside & Laird Construction Liaison Committee Meeting - September 2017Leaside & Laird Construction Liaison Committee Meeting - September 2017
Leaside & Laird Construction Liaison Committee Meeting - September 2017
 
Chaplin & Avenue Construction Liaison Committee Meeting - July 2017
Chaplin & Avenue Construction Liaison Committee Meeting - July 2017Chaplin & Avenue Construction Liaison Committee Meeting - July 2017
Chaplin & Avenue Construction Liaison Committee Meeting - July 2017
 
Mount Pleasant Station Open House - April 2017
Mount Pleasant Station Open House - April 2017Mount Pleasant Station Open House - April 2017
Mount Pleasant Station Open House - April 2017
 
Chaplin Avenue CLC Presentation Deck - Jan 8 2020
  Chaplin Avenue CLC Presentation Deck - Jan 8 2020  Chaplin Avenue CLC Presentation Deck - Jan 8 2020
Chaplin Avenue CLC Presentation Deck - Jan 8 2020
 
Leaside & Laird Construction Liaison Committee Meeting - January 2018
Leaside & Laird Construction Liaison Committee Meeting - January 2018Leaside & Laird Construction Liaison Committee Meeting - January 2018
Leaside & Laird Construction Liaison Committee Meeting - January 2018
 
Brentcliffe - Victoria Park Construction Liaison Committee Meeting
Brentcliffe - Victoria Park Construction Liaison Committee MeetingBrentcliffe - Victoria Park Construction Liaison Committee Meeting
Brentcliffe - Victoria Park Construction Liaison Committee Meeting
 
Leaside - Laird Construction Liaison Committee Meeting - March 2018
Leaside - Laird Construction Liaison Committee Meeting - March 2018Leaside - Laird Construction Liaison Committee Meeting - March 2018
Leaside - Laird Construction Liaison Committee Meeting - March 2018
 
Fairbank & Oakwood Stations Open House - April 2017
Fairbank & Oakwood Stations Open House - April 2017Fairbank & Oakwood Stations Open House - April 2017
Fairbank & Oakwood Stations Open House - April 2017
 
Eglinton- Mount Pleasant Construction Liaison Committee Meeting - July 2017
Eglinton- Mount Pleasant Construction Liaison Committee Meeting - July 2017Eglinton- Mount Pleasant Construction Liaison Committee Meeting - July 2017
Eglinton- Mount Pleasant Construction Liaison Committee Meeting - July 2017
 

Recently uploaded

(SUHANI) Call Girls Pimple Saudagar ( 7001035870 ) HI-Fi Pune Escorts Service
(SUHANI) Call Girls Pimple Saudagar ( 7001035870 ) HI-Fi Pune Escorts Service(SUHANI) Call Girls Pimple Saudagar ( 7001035870 ) HI-Fi Pune Escorts Service
(SUHANI) Call Girls Pimple Saudagar ( 7001035870 ) HI-Fi Pune Escorts Serviceranjana rawat
 
VIP High Profile Call Girls Gorakhpur Aarushi 8250192130 Independent Escort S...
VIP High Profile Call Girls Gorakhpur Aarushi 8250192130 Independent Escort S...VIP High Profile Call Girls Gorakhpur Aarushi 8250192130 Independent Escort S...
VIP High Profile Call Girls Gorakhpur Aarushi 8250192130 Independent Escort S...Suhani Kapoor
 
VIP High Class Call Girls Amravati Anushka 8250192130 Independent Escort Serv...
VIP High Class Call Girls Amravati Anushka 8250192130 Independent Escort Serv...VIP High Class Call Girls Amravati Anushka 8250192130 Independent Escort Serv...
VIP High Class Call Girls Amravati Anushka 8250192130 Independent Escort Serv...Suhani Kapoor
 
DNV publication: China Energy Transition Outlook 2024
DNV publication: China Energy Transition Outlook 2024DNV publication: China Energy Transition Outlook 2024
DNV publication: China Energy Transition Outlook 2024Energy for One World
 
Call Girls Service AECS Layout Just Call 7001305949 Enjoy College Girls Service
Call Girls Service AECS Layout Just Call 7001305949 Enjoy College Girls ServiceCall Girls Service AECS Layout Just Call 7001305949 Enjoy College Girls Service
Call Girls Service AECS Layout Just Call 7001305949 Enjoy College Girls Servicenarwatsonia7
 
GFE Call Girls Service Indira Nagar Lucknow \ 9548273370 Indian Call Girls Se...
GFE Call Girls Service Indira Nagar Lucknow \ 9548273370 Indian Call Girls Se...GFE Call Girls Service Indira Nagar Lucknow \ 9548273370 Indian Call Girls Se...
GFE Call Girls Service Indira Nagar Lucknow \ 9548273370 Indian Call Girls Se...Delhi Call Girls
 
(TARA) Call Girls Chakan ( 7001035870 ) HI-Fi Pune Escorts Service
(TARA) Call Girls Chakan ( 7001035870 ) HI-Fi Pune Escorts Service(TARA) Call Girls Chakan ( 7001035870 ) HI-Fi Pune Escorts Service
(TARA) Call Girls Chakan ( 7001035870 ) HI-Fi Pune Escorts Serviceranjana rawat
 
(SHINA) Call Girls Khed ( 7001035870 ) HI-Fi Pune Escorts Service
(SHINA) Call Girls Khed ( 7001035870 ) HI-Fi Pune Escorts Service(SHINA) Call Girls Khed ( 7001035870 ) HI-Fi Pune Escorts Service
(SHINA) Call Girls Khed ( 7001035870 ) HI-Fi Pune Escorts Serviceranjana rawat
 
Item # 4 - 231 Encino Ave (Significance Only).pdf
Item # 4 - 231 Encino Ave (Significance Only).pdfItem # 4 - 231 Encino Ave (Significance Only).pdf
Item # 4 - 231 Encino Ave (Significance Only).pdfahcitycouncil
 
VIP Kolkata Call Girl Jatin Das Park 👉 8250192130 Available With Room
VIP Kolkata Call Girl Jatin Das Park 👉 8250192130  Available With RoomVIP Kolkata Call Girl Jatin Das Park 👉 8250192130  Available With Room
VIP Kolkata Call Girl Jatin Das Park 👉 8250192130 Available With Roomishabajaj13
 
Lucknow đź’‹ Russian Call Girls Lucknow â‚ą7.5k Pick Up & Drop With Cash Payment 8...
Lucknow đź’‹ Russian Call Girls Lucknow â‚ą7.5k Pick Up & Drop With Cash Payment 8...Lucknow đź’‹ Russian Call Girls Lucknow â‚ą7.5k Pick Up & Drop With Cash Payment 8...
Lucknow đź’‹ Russian Call Girls Lucknow â‚ą7.5k Pick Up & Drop With Cash Payment 8...anilsa9823
 
Incident Command System xxxxxxxxxxxxxxxxxxxxxxxxx
Incident Command System xxxxxxxxxxxxxxxxxxxxxxxxxIncident Command System xxxxxxxxxxxxxxxxxxxxxxxxx
Incident Command System xxxxxxxxxxxxxxxxxxxxxxxxxPeter Miles
 
How the Congressional Budget Office Assists Lawmakers
How the Congressional Budget Office Assists LawmakersHow the Congressional Budget Office Assists Lawmakers
How the Congressional Budget Office Assists LawmakersCongressional Budget Office
 
##9711199012 Call Girls Delhi Rs-5000 UpTo 10 K Hauz Khas Whats Up Number
##9711199012 Call Girls Delhi Rs-5000 UpTo 10 K Hauz Khas  Whats Up Number##9711199012 Call Girls Delhi Rs-5000 UpTo 10 K Hauz Khas  Whats Up Number
##9711199012 Call Girls Delhi Rs-5000 UpTo 10 K Hauz Khas Whats Up NumberMs Riya
 
2024: The FAR, Federal Acquisition Regulations - Part 27
2024: The FAR, Federal Acquisition Regulations - Part 272024: The FAR, Federal Acquisition Regulations - Part 27
2024: The FAR, Federal Acquisition Regulations - Part 27JSchaus & Associates
 
Climate change and occupational safety and health.
Climate change and occupational safety and health.Climate change and occupational safety and health.
Climate change and occupational safety and health.Christina Parmionova
 
Climate change and safety and health at work
Climate change and safety and health at workClimate change and safety and health at work
Climate change and safety and health at workChristina Parmionova
 

Recently uploaded (20)

(SUHANI) Call Girls Pimple Saudagar ( 7001035870 ) HI-Fi Pune Escorts Service
(SUHANI) Call Girls Pimple Saudagar ( 7001035870 ) HI-Fi Pune Escorts Service(SUHANI) Call Girls Pimple Saudagar ( 7001035870 ) HI-Fi Pune Escorts Service
(SUHANI) Call Girls Pimple Saudagar ( 7001035870 ) HI-Fi Pune Escorts Service
 
VIP High Profile Call Girls Gorakhpur Aarushi 8250192130 Independent Escort S...
VIP High Profile Call Girls Gorakhpur Aarushi 8250192130 Independent Escort S...VIP High Profile Call Girls Gorakhpur Aarushi 8250192130 Independent Escort S...
VIP High Profile Call Girls Gorakhpur Aarushi 8250192130 Independent Escort S...
 
Call Girls Service Connaught Place @9999965857 Delhi 🫦 No Advance VVIP 🍎 SER...
Call Girls Service Connaught Place @9999965857 Delhi 🫦 No Advance  VVIP 🍎 SER...Call Girls Service Connaught Place @9999965857 Delhi 🫦 No Advance  VVIP 🍎 SER...
Call Girls Service Connaught Place @9999965857 Delhi 🫦 No Advance VVIP 🍎 SER...
 
The Federal Budget and Health Care Policy
The Federal Budget and Health Care PolicyThe Federal Budget and Health Care Policy
The Federal Budget and Health Care Policy
 
VIP High Class Call Girls Amravati Anushka 8250192130 Independent Escort Serv...
VIP High Class Call Girls Amravati Anushka 8250192130 Independent Escort Serv...VIP High Class Call Girls Amravati Anushka 8250192130 Independent Escort Serv...
VIP High Class Call Girls Amravati Anushka 8250192130 Independent Escort Serv...
 
DNV publication: China Energy Transition Outlook 2024
DNV publication: China Energy Transition Outlook 2024DNV publication: China Energy Transition Outlook 2024
DNV publication: China Energy Transition Outlook 2024
 
Call Girls Service AECS Layout Just Call 7001305949 Enjoy College Girls Service
Call Girls Service AECS Layout Just Call 7001305949 Enjoy College Girls ServiceCall Girls Service AECS Layout Just Call 7001305949 Enjoy College Girls Service
Call Girls Service AECS Layout Just Call 7001305949 Enjoy College Girls Service
 
GFE Call Girls Service Indira Nagar Lucknow \ 9548273370 Indian Call Girls Se...
GFE Call Girls Service Indira Nagar Lucknow \ 9548273370 Indian Call Girls Se...GFE Call Girls Service Indira Nagar Lucknow \ 9548273370 Indian Call Girls Se...
GFE Call Girls Service Indira Nagar Lucknow \ 9548273370 Indian Call Girls Se...
 
(TARA) Call Girls Chakan ( 7001035870 ) HI-Fi Pune Escorts Service
(TARA) Call Girls Chakan ( 7001035870 ) HI-Fi Pune Escorts Service(TARA) Call Girls Chakan ( 7001035870 ) HI-Fi Pune Escorts Service
(TARA) Call Girls Chakan ( 7001035870 ) HI-Fi Pune Escorts Service
 
(SHINA) Call Girls Khed ( 7001035870 ) HI-Fi Pune Escorts Service
(SHINA) Call Girls Khed ( 7001035870 ) HI-Fi Pune Escorts Service(SHINA) Call Girls Khed ( 7001035870 ) HI-Fi Pune Escorts Service
(SHINA) Call Girls Khed ( 7001035870 ) HI-Fi Pune Escorts Service
 
Item # 4 - 231 Encino Ave (Significance Only).pdf
Item # 4 - 231 Encino Ave (Significance Only).pdfItem # 4 - 231 Encino Ave (Significance Only).pdf
Item # 4 - 231 Encino Ave (Significance Only).pdf
 
VIP Kolkata Call Girl Jatin Das Park 👉 8250192130 Available With Room
VIP Kolkata Call Girl Jatin Das Park 👉 8250192130  Available With RoomVIP Kolkata Call Girl Jatin Das Park 👉 8250192130  Available With Room
VIP Kolkata Call Girl Jatin Das Park 👉 8250192130 Available With Room
 
Lucknow đź’‹ Russian Call Girls Lucknow â‚ą7.5k Pick Up & Drop With Cash Payment 8...
Lucknow đź’‹ Russian Call Girls Lucknow â‚ą7.5k Pick Up & Drop With Cash Payment 8...Lucknow đź’‹ Russian Call Girls Lucknow â‚ą7.5k Pick Up & Drop With Cash Payment 8...
Lucknow đź’‹ Russian Call Girls Lucknow â‚ą7.5k Pick Up & Drop With Cash Payment 8...
 
Incident Command System xxxxxxxxxxxxxxxxxxxxxxxxx
Incident Command System xxxxxxxxxxxxxxxxxxxxxxxxxIncident Command System xxxxxxxxxxxxxxxxxxxxxxxxx
Incident Command System xxxxxxxxxxxxxxxxxxxxxxxxx
 
Delhi Russian Call Girls In Connaught Place ➡️9999965857 India's Finest Model...
Delhi Russian Call Girls In Connaught Place ➡️9999965857 India's Finest Model...Delhi Russian Call Girls In Connaught Place ➡️9999965857 India's Finest Model...
Delhi Russian Call Girls In Connaught Place ➡️9999965857 India's Finest Model...
 
How the Congressional Budget Office Assists Lawmakers
How the Congressional Budget Office Assists LawmakersHow the Congressional Budget Office Assists Lawmakers
How the Congressional Budget Office Assists Lawmakers
 
##9711199012 Call Girls Delhi Rs-5000 UpTo 10 K Hauz Khas Whats Up Number
##9711199012 Call Girls Delhi Rs-5000 UpTo 10 K Hauz Khas  Whats Up Number##9711199012 Call Girls Delhi Rs-5000 UpTo 10 K Hauz Khas  Whats Up Number
##9711199012 Call Girls Delhi Rs-5000 UpTo 10 K Hauz Khas Whats Up Number
 
2024: The FAR, Federal Acquisition Regulations - Part 27
2024: The FAR, Federal Acquisition Regulations - Part 272024: The FAR, Federal Acquisition Regulations - Part 27
2024: The FAR, Federal Acquisition Regulations - Part 27
 
Climate change and occupational safety and health.
Climate change and occupational safety and health.Climate change and occupational safety and health.
Climate change and occupational safety and health.
 
Climate change and safety and health at work
Climate change and safety and health at workClimate change and safety and health at work
Climate change and safety and health at work
 

Chaplin & Avenue CLC - Construction Update - February 7, 2018

  • 3. 3 ACTIVITY AREA IMPACT DURATION START DATE Support of Excavation - Piling Within northwest work zone on Eglinton Ave W • Noise and vibration from drilling activity Ongoing through Winter 2018 Underway Guidewall Removal Within southeast work zone on Eglinton Ave W • Noise and vibration from concrete breaking activity Periodically through Winter 2018 Ongoing Watermain Bypass Within southwest work zone on Eglinton Ave W and Chaplin Cres • Noise from construction activity Ongoing through March 2018 Underway Storm Sewer Installation Within southwest work zone on Eglinton Ave W and Chaplin Cres • Noise from construction activity Ongoing through March 2018 Underway Traffic Change – Temporary Driveway Closure North work zone on Eglinton Ave W at 564 Eglinton Ave W • Temporary driveway closure • Relocation parking to Tertiary Entrance One (1) month As early as February 6, 2018 Traffic Change – Close Latimer North side of Eglinton Ave • Extension of northeast work zone • No access to Latimer Ave from Eglinton Ave W • No access to Eglinton Ave W from Latimer Ave • Shoppers Drug Mart southwest driveway closure Approximately one (1) month As early as February 20, 2018 Chaplin Station: What to Expect February 2018
  • 4. 4 Current Construction Staging January 26, 2018 until February 20, 2018
  • 5. 5 Upcoming Construction Staging February 20, 2018 for approximately one (1) month
  • 6. 6 Future Construction Staging As early as March 20, 2018 through 2018
  • 8. 8 Short Term Activities Area & Impacts Duration Tentative Date Tunnel Connection Boreholes and Concrete Pouring (Main Entrance) • South side of Eglinton, west of Avenue Road across from the Main Entrance site • A work zone will be set up on the south side of Eglinton west of Avenue Road and will remain in place for the duration of the drilling. • Sidewalk will be open, and pedestrians will be routed around the work temporarily. • No on street parking on Eglinton between Braemar and Avenue while the work zone is set up. Borehole drilling: approx. 2-3 weeks Concrete pouring: approx. 2 weeks Underway: approx. 1 more week remaining for drilling portion. Dewatering work (daytime) Installation and trenching • Eglinton north and south from Oriole Pkwy to Lascelles • Sidewalk, road and parking impacts depending on location of trench and equipment • Pedestrians will be routed around location of work Approx. 4 weeks remaining Work will resume in mid February Avenue Station: What to Expect February 2018
  • 9. 9 Preparation for Mining at Main Entrance Short Term Activities Area & Impacts Duration Tentative Date Mining Equipment Mobilization at the Main Entrance • A large mobile crane will be on site to lower the heavy equipment in to the excavated entrance and remove some equipment currently on site. • One additional westbound lane will be required. One west bound lane will be maintained. • On-street parking spaces on the north side of Eglinton Avenue between Avenue Road and the crosswalk will be temporarily unavailable. • The crosswalk will be temporarily unavailable for pedestrians during this time. Approx. 48 hours continuous work (includes overnight periods) Feb 23 to Feb 25, 2018 Crane Delivery and Installation (Main Entrance) • A Gantry Crane will be erected above the Main Entrance excavation shaft • The crane will be delivered to the Main Entrance site. • Due to the size of the beams for the crane supports, the deliveries may temporarily delay traffic movements while the truck enters the site to deliver the materials. Approx. 1 week Dates TBD February – March
  • 11. 11 Watermain Lining & Temporary Water Service Short Term Activities Area & Impacts Duration Tentative Date Watermain lining • Properties from 282 Eglinton Ave to the east will be serviced through the laneway • Properties from 284 Eglinton Ave to the west will be serviced from the front • Temporary water supply pipes will be installed in the City right of way • An area in front of each property will be excavated to access the water connection and it will be plated for the duration of the lining (one to two months) • After the lining is completed, the area will be restored and that will take approximately one week 2 weeks to install temporary service 4 – 6 weeks for lining February / March
  • 12. 12 Temporary Water Service Installation (for watermain lining) • Work is planned from 7pm to 7am (pending City Councillor approval) • Excavation in front of each property (shown in blue) • Parking will be unavailable during work hours (red hash marks) • Pedestrians will have a 1.5m walkway around the work zone (shown in green) • Minor trenching in laneway between 280 Eglinton Avenue and Oriole Parkway and on Oriole Parkway from closure to laneway (shown in red)
  • 13. 13 Final Sewer Lining Section ACTIVITY & AREA WHAT TO EXPECT DURATION TENTATIVE DATE Sewer Lining East Sewer Section ď‚· Sewer lining is done to protect and reinforce the sewer pipes while we dig out the future station area beneath them • The remaining section (East Section) runs along Eglinton between Oriole Parkway and Lascelles. • A work zone will be set up in the roadway between Eastbourne and Lascelles. • Expect one lane in each direction on Eglinton between Eastbourne and Lascelles. • No on street parking on Eglinton between Eastbourne and Lascelles while work zone is set up. • Sewer lining work can have a chemical smell; while unpleasant it is not harmful. Please follow mitigation instructions in the construction notice in advance. Approx. 1 week Tentative week of February 15
  • 15. 15 Short Term Activities Area & Impacts Duration Tentative Date Monitoring Work • Equipment is installed in various locations around the station area to monitor ground movement during construction. • To install the monitoring equipment in the ground, crews move from location to location around the station area. Typically a drilling machine is used to drill the hole where the monitor will be installed. • If on the sidewalk, pedestrians may need to be routed around the work zone (sidewalks stay open). If on the roadway, a short term lane closure may be required. Installations planned to be complete in the next few months. Readings will be taken regularly for the duration of the project. Ongoing Avenue Station: What to Expect February 2018
  • 16. 16 Avenue Station – Secondary Entrance
  • 17. 17 Avenue Station – Secondary Entrance
  • 18. 18 Avenue Station – Secondary Entrance