January 13, 2021
Eglinton Crosstown LRT
Eglinton – Mt Pleasant CLC
SNOW REMOVAL ROUTES – EGLINTON STATION
2
INSERT FOOTER
SNOW REMOVAL ROUTES – MT PLEASANT STATION
3
INSERT FOOTER
Eglinton Station
EGLINTON STATION UPDATE
5
CENTRAL WEST WORKS MONTHLY MEETING
Activity Location Approx. Date & Duration
Extended Hours for Station Box
Construction
Rebar, conduit, steel installations, and final
grading works
Beneath Eglinton Avenue and Eglinton TTC
Station
Underway through early 2021
Monday – Friday, 24 hours
Berwick Portal Construction
• Structural steel installations and architectural
works
Berwick Avenue and Eglinton TTC Station
Through 2021
• Berwick Ave closures subject to TTC approval
• Structural steel deliveries occur as early as 6:00
a.m.
TTC Eglinton Station Works
• North platform relocation works, escalator
installations and elevator construction
Eglinton TTC Station
(Elevator construction ongoing at 2200
Yonge St – former Smoke’s Poutinerie)
Periodically through 2021; subject to TTC
approval
Tunnel Ventilation Shaft Construction
Center of Yonge St between Eglinton Ave
and Roehampton Ave
Underway through early 2021
Concrete Works Throughout all station areas Through 2021
CURRENT TRAFFIC CONFIGURATION
6
CENTRAL WEST WORKS MONTHLY MEETING
Through early 2021
CONSTRUCTION PROGRESS PHOTOS
7
FORMWORK INSTALLATIONS –
STATION BOX
COMPLETED EXCAVATION -
BELOW THE TTC STATION
Mount Pleasant Station
MOUNT PLEASANT STATION UPDATE
9
Activity Location Approx. Date & Duration
Excavation and Chipping Main Entrance site
Underway for approximately one (1)
week
Utility Reinstatement Works North and south sides of Eglinton Avenue Underway through 2021
Formwork, waterproofing, rebar, steel and
conduit installations
Secondary Entrance and Station Box (below
Eglinton Ave)
Underway through mid 2021
Activities will begin at the Main Entrance site
as early as January 18, 2021
Concrete Works
• Shotcrete application and concrete pours
Throughout all station areas Underway through 2021
Structural Steel Installations
• Welding of structural steel beams above
ground.
• Periodic use of a mobile crane within the 801 Mt
Pleasant Rd parking lot.
Secondary Entrance site and adjacent
parking lot at 801 Mt Pleasant Road.
Mid January 2021 for approximately
three (3) weeks.
CURRENT TRAFFIC CONFIGURATION
10
Through summer 2021
STRUCTURAL STEEL INSTALLATIONS
11
As early as January 20, 2021
CONSTRUCTION PROGRESS PHOTOS
12
CENTRAL WEST WORKS MONTHLY MEETING
CONDUIT INSTALLATIONS –
CONCOURSE LEVEL STATION BOX
CONCRETE POUR –
PLATFORM LEVEL
Eglinton - Mount Pleasant CLC 13 Jan 2021

Eglinton - Mount Pleasant CLC 13 Jan 2021

  • 1.
    January 13, 2021 EglintonCrosstown LRT Eglinton – Mt Pleasant CLC
  • 2.
    SNOW REMOVAL ROUTES– EGLINTON STATION 2 INSERT FOOTER
  • 3.
    SNOW REMOVAL ROUTES– MT PLEASANT STATION 3 INSERT FOOTER
  • 4.
  • 5.
    EGLINTON STATION UPDATE 5 CENTRALWEST WORKS MONTHLY MEETING Activity Location Approx. Date & Duration Extended Hours for Station Box Construction Rebar, conduit, steel installations, and final grading works Beneath Eglinton Avenue and Eglinton TTC Station Underway through early 2021 Monday – Friday, 24 hours Berwick Portal Construction • Structural steel installations and architectural works Berwick Avenue and Eglinton TTC Station Through 2021 • Berwick Ave closures subject to TTC approval • Structural steel deliveries occur as early as 6:00 a.m. TTC Eglinton Station Works • North platform relocation works, escalator installations and elevator construction Eglinton TTC Station (Elevator construction ongoing at 2200 Yonge St – former Smoke’s Poutinerie) Periodically through 2021; subject to TTC approval Tunnel Ventilation Shaft Construction Center of Yonge St between Eglinton Ave and Roehampton Ave Underway through early 2021 Concrete Works Throughout all station areas Through 2021
  • 6.
    CURRENT TRAFFIC CONFIGURATION 6 CENTRALWEST WORKS MONTHLY MEETING Through early 2021
  • 7.
    CONSTRUCTION PROGRESS PHOTOS 7 FORMWORKINSTALLATIONS – STATION BOX COMPLETED EXCAVATION - BELOW THE TTC STATION
  • 8.
  • 9.
    MOUNT PLEASANT STATIONUPDATE 9 Activity Location Approx. Date & Duration Excavation and Chipping Main Entrance site Underway for approximately one (1) week Utility Reinstatement Works North and south sides of Eglinton Avenue Underway through 2021 Formwork, waterproofing, rebar, steel and conduit installations Secondary Entrance and Station Box (below Eglinton Ave) Underway through mid 2021 Activities will begin at the Main Entrance site as early as January 18, 2021 Concrete Works • Shotcrete application and concrete pours Throughout all station areas Underway through 2021 Structural Steel Installations • Welding of structural steel beams above ground. • Periodic use of a mobile crane within the 801 Mt Pleasant Rd parking lot. Secondary Entrance site and adjacent parking lot at 801 Mt Pleasant Road. Mid January 2021 for approximately three (3) weeks.
  • 10.
  • 11.
    STRUCTURAL STEEL INSTALLATIONS 11 Asearly as January 20, 2021
  • 12.
    CONSTRUCTION PROGRESS PHOTOS 12 CENTRALWEST WORKS MONTHLY MEETING CONDUIT INSTALLATIONS – CONCOURSE LEVEL STATION BOX CONCRETE POUR – PLATFORM LEVEL