The document provides construction updates for the Cedarvale-Forest Hill stations of the Eglinton Crosstown LRT. For Cedarvale Station, deep excavation and extended construction hours are underway through July 2020. Major concrete pours for the station box will take place throughout 2020-2021. Traffic configurations and bus loop closures are also outlined. For Forest Hill Station, extended hours for deep excavation and tunnel demolition are underway through May 2020. Secondary entrance construction and station box work are scheduled to continue into fall 2020 and beyond. Progress photos from both stations are included.