MODULAR
VOLUMETRIC
CONSTRUCTION
June 2009
The purpose of this document is to review
the feasibility of using modular construction
techniques for hotel, housing and worker
accommodation developments.
We have highlighted the advantages and
disadvantages of a modular method of
construction. We believe that a volumetric
modular construction has the potential to be
one of the key solutions to rapidly construct
hotel, housing and worker accommodation
developments.
One big advantage is that the developer
can be given a clear fixed construction
budget for the majority of the building due to
the modular factory process.
Other advantages are speed of
construction, environmental impact and
quality control.
Executive summary
Modular Construction - what is it?
• Factory production of a fitted out room.
• Pre-engineered building units.
• Delivered to site as modular units and
assembled on site to form a building.
• It may comprise highly serviced rooms
such as plant, bathrooms or kitchens
or bedrooms, lounges, stairwells.
• It is a self supporting structure
Benefits include:
• Short construction time/programme
• High early return on capital investment
• Significant cash flow advantages over
traditional build
• Reduced need for skilled workforce on site
• Less waste
• High quality control
• Reliable delivery timescale
• Price certainty
• Sustainable - can be relocated or recycled
• Light weight gives foundation savings
Modular Construction - why use it?
Modular construction - when to use it?
• Short programming required
• Repetitive building type
• Skill shortage on site
• Certainty of delivery
• High quality
• Future relocation
• Weather conditions have limited effect
• Security issues
• Price certainty
Architectural aspects
• Rectangular or A high degree of
repetition is required
• High quality factory finished rooms
• Fully serviced rooms "ready to plug in"
via risers and corridor distribution
routes
• 90 minutes fire rating available with
double boards
• Outstanding sound attenuation
• Low rise or high rise projects
• Thermal insulation easily upgraded
• Maximum standard room width is
variable
• Cladding choices
• Variety of building shapes - usually
rectilinear but could be jutted out or
with balconies
• Roofing – Variety of methods and
products
• Rooms must have repetition and preferably
be rectangular
• For transportation, room sizes are flexible
• Rooms wider than 5m may need to be
subdivided into smaller width units
• Modules are lifted into place via a 4 or 6 point
lifting frame
• Sequence of design, fit out and delivery to
site to suit installation sequence to avoid
double handling.
Logistical requirements
• Hot dip galvanised coated G275 g/m²
steel
• Minimum 100 year design life expected for
most buildings
• A design life over 200 years can be
achieved with additional insulation
• In all cases normal building maintenance
is required to fabric and cladding
Durability and design life of Modular units
Acoustic performance
This Modular building system can be super
insulated with higher than usual building
regulation requirements for both thermal and
acoustic insulation.
In addition to this, the system incorporates a
method of separating each individual module
acoustically which means that noise cannot be
transmitted easily through the structure.
The benefits of using the modular system for overseas construction
• The ability to “template” all designs and specifications for generic types of
buildings
• Fast-track set-up and operation of assembly plants.
• Consistency of quality and build
• Cost benefits of design and specification consistency
• Reduction in design cost
• Plants can be utilised for other purposes
• Following the building
design freeze the
modules are
fabricated in jigs
made from
galvanised LGS
cages
• They have a design
life in excess of 100
years
Module fabrication
• Following delivery of
the modules to the fit-
out plant assembly is
commenced
• The modules are fitted
out in accordance with
the building system
standard processes
• Kitchens and
bathrooms are
installed along with
plumbing and
electrical systems
• Doors, windows and
flooring are also
installed to client’s
requirements
Module fit out
Module fit out
• Following assembly, the
modules are delivered to
site
• Modules are lifted into
position and connected
together
• All modules are
waterproof and
weatherproof immediately
• System design satisfies
Building Regulations
progressive collapse
requirements
Module placement
Once installed, the modules are
plugged and plumbed in
Module services connection
Following placement of the modules:
• The cladding and roofing go on
simultaneously
• Cladding could also be fitted in the
factory reducing on site programme.
• Balconies can be fitted
• External works are completed
• Services are commissioned
Module cladding and roofing
Modular construction - summary
Volumetric systems
• Standard size units
• Load bearing three dimensional frames
• Prefabricated and fitted out under factory conditions
• Each module self-contained
• Ideal for re-locatable applications
• Identical units, e.g. Villas, apartment units or hotel rooms
• Room sized units may serve as main structural components of an entire
building
Modular construction - summary
Light gauge steel frames provide:
• Inherent rigidity
• Can be built to strict tolerances
• Advantages over timber frame systems
• Dimensional stability
• Durability
• Modular systems are super-insulated
• Walls and floors typically give 53dB reduction for sound
• Typical u-values achieved for external walls are 0.21 W/m2k
Building type: Modular student accommodation
Located in the heart of Nottingham, this modular
project consists of a 6-storey, 300
bedroom, student accommodation building, and
the smaller 70 flats 4-storey Belgrave Suite.
.
Chaucer Street
Student accommodation
Located on the tight site in central
Manchester is the 600 bedroom a hall of
residence for the Royal Northern College of
Music, comprising single and double
bedrooms with en-suite bathrooms and
kitchens for each flat and common rooms.
The nine-storey block was totally
prefabricated off-site using the light gauge
modular system.
Royal Northern College of Music, Manchester
This site was extremely confined, with the
proposed construction filling the entire 12m wide
by 100m long
North Pole Road, London
North Pole Road, London - key worker housing
This site lies directly between a mainline railway
and a busy road and thus required high levels of
sound insulation, this was easily provided with
the modular framing solution. Offering very good
acoustic performance both against external
noise and also the transmittal of sound between
units internally.
Rodney Road, Twickenham - social & private housing
Rodney Road, Twickenham - social & private housing
Rodney Road, Twickenham - social & private housing
RNCM, Manchester
Wilmslow, Manchester
Wilmslow, Manchester
South Chase, Harlow - social & private housing
South Chase, Harlow - social & private housing
Traditionally clad to resembles traditional housing
Modular & Volumetric Ltd
Image House
72 Madison Ave
Birmingham, B36 8EQ, UK.
Tel: 0044 (0) 7753 675716
philwdm@aol.com

More Related Content

What's hot

Prefabrication in construction
Prefabrication in constructionPrefabrication in construction
Prefabrication in construction
Shailja km
 
Modular construction ppt
Modular construction pptModular construction ppt
Modular construction ppt
vaibhav Nautiyal
 
Charles correa
Charles correaCharles correa
Charles correa
kd6388
 
Combined & Eccentric Footing
Combined & Eccentric FootingCombined & Eccentric Footing
Combined & Eccentric Footing
Parth Patil
 
Prefabricated structures
Prefabricated structuresPrefabricated structures
Prefabricated structures
Aishwarya Deopujari
 
ADVANCED TECHNIQUES IN CONSTRUCTIONS IN HIGH RISE BUILDINGS
ADVANCED TECHNIQUES IN CONSTRUCTIONS IN HIGH RISE BUILDINGSADVANCED TECHNIQUES IN CONSTRUCTIONS IN HIGH RISE BUILDINGS
ADVANCED TECHNIQUES IN CONSTRUCTIONS IN HIGH RISE BUILDINGS
ASHOK KUMAR TIWARY
 
Prestressed construction
Prestressed constructionPrestressed construction
Prestressed construction
Vishvendu pandey
 
Prefabrication
PrefabricationPrefabrication
Prefabrication
Bilal Ansari
 
Prefabrication
PrefabricationPrefabrication
Prefabrication
Kush Agarwal
 
Pre caste Concrete
Pre caste ConcretePre caste Concrete
Pre caste Concrete
University of Tikrit
 
Speedy construction presentation
Speedy construction presentationSpeedy construction presentation
Speedy construction presentation
somitra bhardwaj
 
Prefabricated Column
Prefabricated ColumnPrefabricated Column
Prefabricated Column
Anees Khan
 
Wall finishes
Wall finishesWall finishes
Wall finishes
padamatikona swapnika
 
Cost effective materials
Cost effective materialsCost effective materials
Cost effective materialsSarthak Kaura
 
Earthquake Resistance Structures
Earthquake Resistance  StructuresEarthquake Resistance  Structures
Earthquake Resistance Structures
akhiarane
 
High rise structure & core
High rise  structure & coreHigh rise  structure & core
High rise structure & core
Meer Musabber ali (joyous)
 
Earthquake and effect in building types precaution
Earthquake and effect in building types precaution Earthquake and effect in building types precaution
Earthquake and effect in building types precaution
Aditya Sanyal
 
Waffle slab
Waffle slabWaffle slab
Waffle slab
Yazid Hamoda
 
Composite construction
Composite constructionComposite construction
Composite construction
Hashim D. Hassan
 
Precast and Prefabricated components and structures and the connection betwee...
Precast and Prefabricated components and structures and the connection betwee...Precast and Prefabricated components and structures and the connection betwee...
Precast and Prefabricated components and structures and the connection betwee...
nishant patyal
 

What's hot (20)

Prefabrication in construction
Prefabrication in constructionPrefabrication in construction
Prefabrication in construction
 
Modular construction ppt
Modular construction pptModular construction ppt
Modular construction ppt
 
Charles correa
Charles correaCharles correa
Charles correa
 
Combined & Eccentric Footing
Combined & Eccentric FootingCombined & Eccentric Footing
Combined & Eccentric Footing
 
Prefabricated structures
Prefabricated structuresPrefabricated structures
Prefabricated structures
 
ADVANCED TECHNIQUES IN CONSTRUCTIONS IN HIGH RISE BUILDINGS
ADVANCED TECHNIQUES IN CONSTRUCTIONS IN HIGH RISE BUILDINGSADVANCED TECHNIQUES IN CONSTRUCTIONS IN HIGH RISE BUILDINGS
ADVANCED TECHNIQUES IN CONSTRUCTIONS IN HIGH RISE BUILDINGS
 
Prestressed construction
Prestressed constructionPrestressed construction
Prestressed construction
 
Prefabrication
PrefabricationPrefabrication
Prefabrication
 
Prefabrication
PrefabricationPrefabrication
Prefabrication
 
Pre caste Concrete
Pre caste ConcretePre caste Concrete
Pre caste Concrete
 
Speedy construction presentation
Speedy construction presentationSpeedy construction presentation
Speedy construction presentation
 
Prefabricated Column
Prefabricated ColumnPrefabricated Column
Prefabricated Column
 
Wall finishes
Wall finishesWall finishes
Wall finishes
 
Cost effective materials
Cost effective materialsCost effective materials
Cost effective materials
 
Earthquake Resistance Structures
Earthquake Resistance  StructuresEarthquake Resistance  Structures
Earthquake Resistance Structures
 
High rise structure & core
High rise  structure & coreHigh rise  structure & core
High rise structure & core
 
Earthquake and effect in building types precaution
Earthquake and effect in building types precaution Earthquake and effect in building types precaution
Earthquake and effect in building types precaution
 
Waffle slab
Waffle slabWaffle slab
Waffle slab
 
Composite construction
Composite constructionComposite construction
Composite construction
 
Precast and Prefabricated components and structures and the connection betwee...
Precast and Prefabricated components and structures and the connection betwee...Precast and Prefabricated components and structures and the connection betwee...
Precast and Prefabricated components and structures and the connection betwee...
 

Similar to Volumetric Construction.pdf

Modular Volumetric Construction
Modular Volumetric ConstructionModular Volumetric Construction
Modular Volumetric Construction
philwdm
 
Panel Built Information Packet
Panel Built Information PacketPanel Built Information Packet
Panel Built Information Packet
Panel Built
 
PREFAB CONSTRUCTION .pdf
PREFAB CONSTRUCTION .pdfPREFAB CONSTRUCTION .pdf
PREFAB CONSTRUCTION .pdf
GourhariBiswas1
 
Modular Buildings
Modular BuildingsModular Buildings
Modular Buildings
Rohan Dasgupta
 
LiveIn Quarters
LiveIn QuartersLiveIn Quarters
LiveIn Quarters
clicknow
 
Pre Engineered buildings
Pre Engineered buildingsPre Engineered buildings
Pre Engineered buildings
Yamini K
 
PRECAST.pptx
PRECAST.pptxPRECAST.pptx
PRECAST.pptx
Amitsonwane2
 
rapid walls- modular construction technology
rapid walls- modular construction technologyrapid walls- modular construction technology
rapid walls- modular construction technology
Anjith Augustine
 
PRECAST.pdf
PRECAST.pdfPRECAST.pdf
PRECAST.pdf
Amitsonwane2
 
PREFABRICATION.pdf
PREFABRICATION.pdfPREFABRICATION.pdf
PREFABRICATION.pdf
Mohammad Salman
 
MODERN CONSTRUCTION TECHNOLOGIES IN ENGINEERING PERSPECTIVE
MODERN CONSTRUCTION TECHNOLOGIES IN ENGINEERING PERSPECTIVEMODERN CONSTRUCTION TECHNOLOGIES IN ENGINEERING PERSPECTIVE
MODERN CONSTRUCTION TECHNOLOGIES IN ENGINEERING PERSPECTIVE
Dr K M SONI
 
Modular housing/building
Modular housing/buildingModular housing/building
Modular housing/building
yogiraj bhandari
 
The National Eco House Oman
The National Eco House OmanThe National Eco House Oman
The National Eco House Oman
MECandPMV
 
Prefab Building CR ppt.pptx
Prefab Building CR ppt.pptxPrefab Building CR ppt.pptx
Prefab Building CR ppt.pptx
dharmveersingh60
 
Construction technology (process)
Construction technology (process)Construction technology (process)
Construction technology (process)
Ain Ridzuan
 
Monolithic concrete construction system
Monolithic concrete construction systemMonolithic concrete construction system
Monolithic concrete construction system
chirag aggarwal
 
Prebarication
PrebaricationPrebarication
Prebarication
mayurgoel13
 
Prefabrication system
Prefabrication systemPrefabrication system
Prefabrication system
Arun Arun
 
Use Enerfrees Bi-Folding Doors to Transform Your Space
Use Enerfrees Bi-Folding Doors to Transform Your SpaceUse Enerfrees Bi-Folding Doors to Transform Your Space
Use Enerfrees Bi-Folding Doors to Transform Your Space
enerfreeswindowandwa
 
Aerocon bricks
Aerocon bricksAerocon bricks
Aerocon bricks
Aglaia Connect
 

Similar to Volumetric Construction.pdf (20)

Modular Volumetric Construction
Modular Volumetric ConstructionModular Volumetric Construction
Modular Volumetric Construction
 
Panel Built Information Packet
Panel Built Information PacketPanel Built Information Packet
Panel Built Information Packet
 
PREFAB CONSTRUCTION .pdf
PREFAB CONSTRUCTION .pdfPREFAB CONSTRUCTION .pdf
PREFAB CONSTRUCTION .pdf
 
Modular Buildings
Modular BuildingsModular Buildings
Modular Buildings
 
LiveIn Quarters
LiveIn QuartersLiveIn Quarters
LiveIn Quarters
 
Pre Engineered buildings
Pre Engineered buildingsPre Engineered buildings
Pre Engineered buildings
 
PRECAST.pptx
PRECAST.pptxPRECAST.pptx
PRECAST.pptx
 
rapid walls- modular construction technology
rapid walls- modular construction technologyrapid walls- modular construction technology
rapid walls- modular construction technology
 
PRECAST.pdf
PRECAST.pdfPRECAST.pdf
PRECAST.pdf
 
PREFABRICATION.pdf
PREFABRICATION.pdfPREFABRICATION.pdf
PREFABRICATION.pdf
 
MODERN CONSTRUCTION TECHNOLOGIES IN ENGINEERING PERSPECTIVE
MODERN CONSTRUCTION TECHNOLOGIES IN ENGINEERING PERSPECTIVEMODERN CONSTRUCTION TECHNOLOGIES IN ENGINEERING PERSPECTIVE
MODERN CONSTRUCTION TECHNOLOGIES IN ENGINEERING PERSPECTIVE
 
Modular housing/building
Modular housing/buildingModular housing/building
Modular housing/building
 
The National Eco House Oman
The National Eco House OmanThe National Eco House Oman
The National Eco House Oman
 
Prefab Building CR ppt.pptx
Prefab Building CR ppt.pptxPrefab Building CR ppt.pptx
Prefab Building CR ppt.pptx
 
Construction technology (process)
Construction technology (process)Construction technology (process)
Construction technology (process)
 
Monolithic concrete construction system
Monolithic concrete construction systemMonolithic concrete construction system
Monolithic concrete construction system
 
Prebarication
PrebaricationPrebarication
Prebarication
 
Prefabrication system
Prefabrication systemPrefabrication system
Prefabrication system
 
Use Enerfrees Bi-Folding Doors to Transform Your Space
Use Enerfrees Bi-Folding Doors to Transform Your SpaceUse Enerfrees Bi-Folding Doors to Transform Your Space
Use Enerfrees Bi-Folding Doors to Transform Your Space
 
Aerocon bricks
Aerocon bricksAerocon bricks
Aerocon bricks
 

Recently uploaded

TECHNICAL TRAINING MANUAL GENERAL FAMILIARIZATION COURSE
TECHNICAL TRAINING MANUAL   GENERAL FAMILIARIZATION COURSETECHNICAL TRAINING MANUAL   GENERAL FAMILIARIZATION COURSE
TECHNICAL TRAINING MANUAL GENERAL FAMILIARIZATION COURSE
DuvanRamosGarzon1
 
WATER CRISIS and its solutions-pptx 1234
WATER CRISIS and its solutions-pptx 1234WATER CRISIS and its solutions-pptx 1234
WATER CRISIS and its solutions-pptx 1234
AafreenAbuthahir2
 
Student information management system project report ii.pdf
Student information management system project report ii.pdfStudent information management system project report ii.pdf
Student information management system project report ii.pdf
Kamal Acharya
 
J.Yang, ICLR 2024, MLILAB, KAIST AI.pdf
J.Yang,  ICLR 2024, MLILAB, KAIST AI.pdfJ.Yang,  ICLR 2024, MLILAB, KAIST AI.pdf
J.Yang, ICLR 2024, MLILAB, KAIST AI.pdf
MLILAB
 
H.Seo, ICLR 2024, MLILAB, KAIST AI.pdf
H.Seo,  ICLR 2024, MLILAB,  KAIST AI.pdfH.Seo,  ICLR 2024, MLILAB,  KAIST AI.pdf
H.Seo, ICLR 2024, MLILAB, KAIST AI.pdf
MLILAB
 
CME397 Surface Engineering- Professional Elective
CME397 Surface Engineering- Professional ElectiveCME397 Surface Engineering- Professional Elective
CME397 Surface Engineering- Professional Elective
karthi keyan
 
Forklift Classes Overview by Intella Parts
Forklift Classes Overview by Intella PartsForklift Classes Overview by Intella Parts
Forklift Classes Overview by Intella Parts
Intella Parts
 
Water Industry Process Automation and Control Monthly - May 2024.pdf
Water Industry Process Automation and Control Monthly - May 2024.pdfWater Industry Process Automation and Control Monthly - May 2024.pdf
Water Industry Process Automation and Control Monthly - May 2024.pdf
Water Industry Process Automation & Control
 
block diagram and signal flow graph representation
block diagram and signal flow graph representationblock diagram and signal flow graph representation
block diagram and signal flow graph representation
Divya Somashekar
 
DESIGN A COTTON SEED SEPARATION MACHINE.docx
DESIGN A COTTON SEED SEPARATION MACHINE.docxDESIGN A COTTON SEED SEPARATION MACHINE.docx
DESIGN A COTTON SEED SEPARATION MACHINE.docx
FluxPrime1
 
Halogenation process of chemical process industries
Halogenation process of chemical process industriesHalogenation process of chemical process industries
Halogenation process of chemical process industries
MuhammadTufail242431
 
Vaccine management system project report documentation..pdf
Vaccine management system project report documentation..pdfVaccine management system project report documentation..pdf
Vaccine management system project report documentation..pdf
Kamal Acharya
 
CFD Simulation of By-pass Flow in a HRSG module by R&R Consult.pptx
CFD Simulation of By-pass Flow in a HRSG module by R&R Consult.pptxCFD Simulation of By-pass Flow in a HRSG module by R&R Consult.pptx
CFD Simulation of By-pass Flow in a HRSG module by R&R Consult.pptx
R&R Consult
 
LIGA(E)11111111111111111111111111111111111111111.ppt
LIGA(E)11111111111111111111111111111111111111111.pptLIGA(E)11111111111111111111111111111111111111111.ppt
LIGA(E)11111111111111111111111111111111111111111.ppt
ssuser9bd3ba
 
Courier management system project report.pdf
Courier management system project report.pdfCourier management system project report.pdf
Courier management system project report.pdf
Kamal Acharya
 
Cosmetic shop management system project report.pdf
Cosmetic shop management system project report.pdfCosmetic shop management system project report.pdf
Cosmetic shop management system project report.pdf
Kamal Acharya
 
Planning Of Procurement o different goods and services
Planning Of Procurement o different goods and servicesPlanning Of Procurement o different goods and services
Planning Of Procurement o different goods and services
JoytuBarua2
 
Sachpazis:Terzaghi Bearing Capacity Estimation in simple terms with Calculati...
Sachpazis:Terzaghi Bearing Capacity Estimation in simple terms with Calculati...Sachpazis:Terzaghi Bearing Capacity Estimation in simple terms with Calculati...
Sachpazis:Terzaghi Bearing Capacity Estimation in simple terms with Calculati...
Dr.Costas Sachpazis
 
Final project report on grocery store management system..pdf
Final project report on grocery store management system..pdfFinal project report on grocery store management system..pdf
Final project report on grocery store management system..pdf
Kamal Acharya
 
Industrial Training at Shahjalal Fertilizer Company Limited (SFCL)
Industrial Training at Shahjalal Fertilizer Company Limited (SFCL)Industrial Training at Shahjalal Fertilizer Company Limited (SFCL)
Industrial Training at Shahjalal Fertilizer Company Limited (SFCL)
MdTanvirMahtab2
 

Recently uploaded (20)

TECHNICAL TRAINING MANUAL GENERAL FAMILIARIZATION COURSE
TECHNICAL TRAINING MANUAL   GENERAL FAMILIARIZATION COURSETECHNICAL TRAINING MANUAL   GENERAL FAMILIARIZATION COURSE
TECHNICAL TRAINING MANUAL GENERAL FAMILIARIZATION COURSE
 
WATER CRISIS and its solutions-pptx 1234
WATER CRISIS and its solutions-pptx 1234WATER CRISIS and its solutions-pptx 1234
WATER CRISIS and its solutions-pptx 1234
 
Student information management system project report ii.pdf
Student information management system project report ii.pdfStudent information management system project report ii.pdf
Student information management system project report ii.pdf
 
J.Yang, ICLR 2024, MLILAB, KAIST AI.pdf
J.Yang,  ICLR 2024, MLILAB, KAIST AI.pdfJ.Yang,  ICLR 2024, MLILAB, KAIST AI.pdf
J.Yang, ICLR 2024, MLILAB, KAIST AI.pdf
 
H.Seo, ICLR 2024, MLILAB, KAIST AI.pdf
H.Seo,  ICLR 2024, MLILAB,  KAIST AI.pdfH.Seo,  ICLR 2024, MLILAB,  KAIST AI.pdf
H.Seo, ICLR 2024, MLILAB, KAIST AI.pdf
 
CME397 Surface Engineering- Professional Elective
CME397 Surface Engineering- Professional ElectiveCME397 Surface Engineering- Professional Elective
CME397 Surface Engineering- Professional Elective
 
Forklift Classes Overview by Intella Parts
Forklift Classes Overview by Intella PartsForklift Classes Overview by Intella Parts
Forklift Classes Overview by Intella Parts
 
Water Industry Process Automation and Control Monthly - May 2024.pdf
Water Industry Process Automation and Control Monthly - May 2024.pdfWater Industry Process Automation and Control Monthly - May 2024.pdf
Water Industry Process Automation and Control Monthly - May 2024.pdf
 
block diagram and signal flow graph representation
block diagram and signal flow graph representationblock diagram and signal flow graph representation
block diagram and signal flow graph representation
 
DESIGN A COTTON SEED SEPARATION MACHINE.docx
DESIGN A COTTON SEED SEPARATION MACHINE.docxDESIGN A COTTON SEED SEPARATION MACHINE.docx
DESIGN A COTTON SEED SEPARATION MACHINE.docx
 
Halogenation process of chemical process industries
Halogenation process of chemical process industriesHalogenation process of chemical process industries
Halogenation process of chemical process industries
 
Vaccine management system project report documentation..pdf
Vaccine management system project report documentation..pdfVaccine management system project report documentation..pdf
Vaccine management system project report documentation..pdf
 
CFD Simulation of By-pass Flow in a HRSG module by R&R Consult.pptx
CFD Simulation of By-pass Flow in a HRSG module by R&R Consult.pptxCFD Simulation of By-pass Flow in a HRSG module by R&R Consult.pptx
CFD Simulation of By-pass Flow in a HRSG module by R&R Consult.pptx
 
LIGA(E)11111111111111111111111111111111111111111.ppt
LIGA(E)11111111111111111111111111111111111111111.pptLIGA(E)11111111111111111111111111111111111111111.ppt
LIGA(E)11111111111111111111111111111111111111111.ppt
 
Courier management system project report.pdf
Courier management system project report.pdfCourier management system project report.pdf
Courier management system project report.pdf
 
Cosmetic shop management system project report.pdf
Cosmetic shop management system project report.pdfCosmetic shop management system project report.pdf
Cosmetic shop management system project report.pdf
 
Planning Of Procurement o different goods and services
Planning Of Procurement o different goods and servicesPlanning Of Procurement o different goods and services
Planning Of Procurement o different goods and services
 
Sachpazis:Terzaghi Bearing Capacity Estimation in simple terms with Calculati...
Sachpazis:Terzaghi Bearing Capacity Estimation in simple terms with Calculati...Sachpazis:Terzaghi Bearing Capacity Estimation in simple terms with Calculati...
Sachpazis:Terzaghi Bearing Capacity Estimation in simple terms with Calculati...
 
Final project report on grocery store management system..pdf
Final project report on grocery store management system..pdfFinal project report on grocery store management system..pdf
Final project report on grocery store management system..pdf
 
Industrial Training at Shahjalal Fertilizer Company Limited (SFCL)
Industrial Training at Shahjalal Fertilizer Company Limited (SFCL)Industrial Training at Shahjalal Fertilizer Company Limited (SFCL)
Industrial Training at Shahjalal Fertilizer Company Limited (SFCL)
 

Volumetric Construction.pdf

  • 2. The purpose of this document is to review the feasibility of using modular construction techniques for hotel, housing and worker accommodation developments. We have highlighted the advantages and disadvantages of a modular method of construction. We believe that a volumetric modular construction has the potential to be one of the key solutions to rapidly construct hotel, housing and worker accommodation developments. One big advantage is that the developer can be given a clear fixed construction budget for the majority of the building due to the modular factory process. Other advantages are speed of construction, environmental impact and quality control. Executive summary
  • 3. Modular Construction - what is it? • Factory production of a fitted out room. • Pre-engineered building units. • Delivered to site as modular units and assembled on site to form a building. • It may comprise highly serviced rooms such as plant, bathrooms or kitchens or bedrooms, lounges, stairwells. • It is a self supporting structure
  • 4.
  • 5. Benefits include: • Short construction time/programme • High early return on capital investment • Significant cash flow advantages over traditional build • Reduced need for skilled workforce on site • Less waste • High quality control • Reliable delivery timescale • Price certainty • Sustainable - can be relocated or recycled • Light weight gives foundation savings Modular Construction - why use it?
  • 6. Modular construction - when to use it? • Short programming required • Repetitive building type • Skill shortage on site • Certainty of delivery • High quality • Future relocation • Weather conditions have limited effect • Security issues • Price certainty
  • 7. Architectural aspects • Rectangular or A high degree of repetition is required • High quality factory finished rooms • Fully serviced rooms "ready to plug in" via risers and corridor distribution routes • 90 minutes fire rating available with double boards • Outstanding sound attenuation • Low rise or high rise projects • Thermal insulation easily upgraded • Maximum standard room width is variable • Cladding choices • Variety of building shapes - usually rectilinear but could be jutted out or with balconies • Roofing – Variety of methods and products
  • 8. • Rooms must have repetition and preferably be rectangular • For transportation, room sizes are flexible • Rooms wider than 5m may need to be subdivided into smaller width units • Modules are lifted into place via a 4 or 6 point lifting frame • Sequence of design, fit out and delivery to site to suit installation sequence to avoid double handling. Logistical requirements
  • 9. • Hot dip galvanised coated G275 g/m² steel • Minimum 100 year design life expected for most buildings • A design life over 200 years can be achieved with additional insulation • In all cases normal building maintenance is required to fabric and cladding Durability and design life of Modular units
  • 10. Acoustic performance This Modular building system can be super insulated with higher than usual building regulation requirements for both thermal and acoustic insulation. In addition to this, the system incorporates a method of separating each individual module acoustically which means that noise cannot be transmitted easily through the structure.
  • 11. The benefits of using the modular system for overseas construction • The ability to “template” all designs and specifications for generic types of buildings • Fast-track set-up and operation of assembly plants. • Consistency of quality and build • Cost benefits of design and specification consistency • Reduction in design cost • Plants can be utilised for other purposes
  • 12. • Following the building design freeze the modules are fabricated in jigs made from galvanised LGS cages • They have a design life in excess of 100 years Module fabrication
  • 13. • Following delivery of the modules to the fit- out plant assembly is commenced • The modules are fitted out in accordance with the building system standard processes • Kitchens and bathrooms are installed along with plumbing and electrical systems • Doors, windows and flooring are also installed to client’s requirements Module fit out
  • 15. • Following assembly, the modules are delivered to site • Modules are lifted into position and connected together • All modules are waterproof and weatherproof immediately • System design satisfies Building Regulations progressive collapse requirements Module placement
  • 16. Once installed, the modules are plugged and plumbed in Module services connection
  • 17. Following placement of the modules: • The cladding and roofing go on simultaneously • Cladding could also be fitted in the factory reducing on site programme. • Balconies can be fitted • External works are completed • Services are commissioned Module cladding and roofing
  • 18. Modular construction - summary Volumetric systems • Standard size units • Load bearing three dimensional frames • Prefabricated and fitted out under factory conditions • Each module self-contained • Ideal for re-locatable applications • Identical units, e.g. Villas, apartment units or hotel rooms • Room sized units may serve as main structural components of an entire building
  • 19. Modular construction - summary Light gauge steel frames provide: • Inherent rigidity • Can be built to strict tolerances • Advantages over timber frame systems • Dimensional stability • Durability • Modular systems are super-insulated • Walls and floors typically give 53dB reduction for sound • Typical u-values achieved for external walls are 0.21 W/m2k
  • 20. Building type: Modular student accommodation Located in the heart of Nottingham, this modular project consists of a 6-storey, 300 bedroom, student accommodation building, and the smaller 70 flats 4-storey Belgrave Suite. . Chaucer Street
  • 21. Student accommodation Located on the tight site in central Manchester is the 600 bedroom a hall of residence for the Royal Northern College of Music, comprising single and double bedrooms with en-suite bathrooms and kitchens for each flat and common rooms. The nine-storey block was totally prefabricated off-site using the light gauge modular system. Royal Northern College of Music, Manchester
  • 22. This site was extremely confined, with the proposed construction filling the entire 12m wide by 100m long North Pole Road, London
  • 23. North Pole Road, London - key worker housing
  • 24. This site lies directly between a mainline railway and a busy road and thus required high levels of sound insulation, this was easily provided with the modular framing solution. Offering very good acoustic performance both against external noise and also the transmittal of sound between units internally. Rodney Road, Twickenham - social & private housing
  • 25. Rodney Road, Twickenham - social & private housing
  • 26. Rodney Road, Twickenham - social & private housing
  • 30. South Chase, Harlow - social & private housing
  • 31. South Chase, Harlow - social & private housing Traditionally clad to resembles traditional housing
  • 32. Modular & Volumetric Ltd Image House 72 Madison Ave Birmingham, B36 8EQ, UK. Tel: 0044 (0) 7753 675716 philwdm@aol.com