VLSI Design
Introduction to the subject
Lecture 0
Rajesh Ghongade
VIIT
• Teaching Scheme
– Lectures: 3 Hrs/week
– Practical: 2 Hrs/Week
• Examination Scheme
– Paper: 100 Marks
– Practical: 50 Marks
– Oral: 25 Marks
Unit-I
VHDL Modeling and Design Flow
Introduction to VLSI: complete VLSI design flow
(with reference to an EDA tool). Sequential, Data
flow, and Structural Modeling. Functions.
Procedures, attributes. Test benches,
Synthesizable, and non synthesizable
statements; packages and configurations
Modeling in VHDL with examples of circuits such
as counters, shift registers, bidirectional bus, etc.
Unit 2
FSM And Sequential Logic Principles
Sequential Circuits, Meta-stability
Synchronization, Design of Finite State
Machines, and State minimization, FSM
CASE STUDIES - Traffic Light control. Lift
Control and UART STA and DTA
Unit 3
Programmable Logic Devices
Introduction to the CPLDs, Study of
architecture of CPLD. and Study of the
Architecture of FPGA
Unit 4
System On Chip
One, two phase clock, Clock distribution. Power
distribution. Power optimization, SRC and DRC,
Design validation, Global routing, Switch box
routing. Off chip connections, I/O Architectures,
Wire parasitics, EMI immune design. Study of
memory-Basics of memory includes types of
memory cells and memory architectures. Types of
memory, based on architecture specific and
application specific viz. SRAM, DRAM, SDRAM,
FLASH, FIFO.
Unit 5
CMOS VLSI
CMOS parasitics, equivalent circuit, body
effect, Technology Scaling, A. parameter.
Detail study of Inverter Characteristics,
power dissipation, power delay product,
CMOS combinational logic design and
W/L calculations. Transmission gates,
Introduction to CMOS layout.
Unit 6
Testability
Need of Design for testability, Introduction to
Fault Coverage, Testability. Design- for-
Testability, Controllability and Observability,
Stuck-at Fault Model. Stuck-Open and
Stuck-Short faults. Boundary Scan check.
JTAG technology; TAP Controller and TAP
Controller State Diagram. Scan path. Full
and Partial scan. BIST
Text Books
1. John F. Wakerly, "Digital Design, Principles
and Practices", Prentice Hall Publication
2. Neil H. E Weste and Kamran Eshraghian,
"Principles of CMOS VLSI Design".
3. Wayne Wolf, "Modern VLSI Design"
4. Sudhkar Yalamachalli, "Introductory VHDL from
simulation to Synthesis"
Reference Books
1. Perry "VHDL"
2. Charles Roth, "Digital System Design using VHDL". McGraw hill.
3. Xilinx Data Manual "The Programmable Logic Data Book".
4. Stephen Brown and Zvonko Vranesic, "Fundamentals of Digital
Logic with VHDL Design", Second Edition, McGraw-Hill, 2005.
5. Michael John Sebastian Smith, "Application-Specific Integrated
Circuits", Addison Wesley.
6. Wayne Wolf, "FPGA-Based System Design", Prentice Hall,
7. Miron Abramovici, "Digital Systems Testing and Testable Design",
Jaico Publishing.
8. Sung-Mo (Steve) kang, Yusuf Leblebici, " CMOS Digital
Integrated Circuit", Tata McGraw-Hill Publication.
LIST OF EXPERIMENTS
Any 8 assignments out of the following:
Simulation, Synthesis, and Implementation of:
1. 8: 1 Multiplexer, 2:4 Decoder, Comparator and Adder.
2. Flip Flop, Shift Register and Counter
3. Lift Controller /Traffic Light Controller/ UART. Anyone of the
three.
4. Parity generator and Checker.
5. Implementation of RAM/FIFO.
6. Ramp waveform generator using DAC
7. Bi-directional buffer
8. Temperature sensing using ADC, Displaying on 7-Segment
display and threshold setting using keyboard
9. Implementation of 4-bit RISC processor
EDA Tools
• Active-HDL 6.3 sp1
– (VHDL compiling and simulation)
• Synpilfy Pro 8.2
– Synthesis
• Xilinx Webpack 8.X
– Implementation
Alternate EDA Tools
• Libero Gold 6.2
– (VHDL compiling & implementation)
• Modelsim 6.0
– Simulation
• Synpilfy 8.2
– Synthesis
Hardware available
• Actel ProASIC PLUS evaluation board with APA300-PQ208 device
• Xilinx CPLD Dedicated Trainer XC 9572 PC 84
• Xilinx FPGA Dedicated Trainer XC 2S50 – TQ 144(Spartan II)
• Universal Trainer kit (BASE UNIT)
(ADD on Modules)
– Xilinx CPLD Module
• XC 95108 – PLCC 84
– Xilinx FPGA Module
• XC V100E – PQ 240 XC (Virtex)
– Altera Flex 10K Series FPGA
– Atmel CPLD Device ATF 150 4AS / ATF 1508 AS PC 84
– Cypress CPLD Module Device CY37064V PC84
Lecture 1
Introduction to VLSI
R.B.Ghongade
Microelectronics
Is the art, science and technology of
designing and fabricating integrated circuits
with small-dimension electronic devices
Areas of Microelectronics are :
• VLSI Design
• VLSI CAD Tools
• Technology & Fabrication
• Physics
• Modeling and Simulation
• Characterization
• Testing
Nearly all the advances in the modern day electronic systems
and devices are a direct outcome of VLSI technology
Some keywords!
• Very-large-scale-integration (VLSI) is defined as a
technology that allows the construction and
interconnection of large numbers (millions) of transistors
on a single integrated circuit.
• Integrated circuit is a collection of one or more gates
fabricated on a single silicon chip.
• Wafer is a thin slice of semiconductor material on which
semiconductor devices are made. Also called a slice or
substrate.
• Chip is a small piece of semiconductor material upon
which miniaturized electronic circuits can be built.
• Die is an individual circuit or subsystem that is one of
several identical chips that are produced after dicing up
a wafer.
If you use these key-words often, people will
think that you are an expert VLSI engineer!!!
• The origin of this terminology can be traced as the logical extension
to the integration techniques namely the Small Scale Integration, SSI
(the ICs which functioned as logic gates, flip-flops), the Medium
Scale Integration, MSI (multiplexers, decoders)., the Large Scale
Integration LSI (early microprocessors, small memories, PAL, GAL
Technology
Number of
gates/transistors*
per chip
Examples Year
SSI 1 to 20
74XX series,
4xxx series
60’s
MSI 100 to 1000
74XXX series,
45XX series
70’s
LSI
1000 to 10,000/100 to
100,000*
8085, 80’s
VLSI
10,000 to
100,000/1,000,000
*
CPLD, FPGA,
advanced
μC, SoC
90’s
Dividing line between LSI and VLSI is somewhat fuzzy hence
number of transistors provides a good criterion
The advances in the integration techniques can be attributed
directly to :
•Advances in photolithography techniques
•New designs of semiconductor devices
•Newer methods of metallization
The development of integration technology has followed the
famous Moore’s Law. It was stated by Gordon Moore, co-founder of
Intel, in the year 1965, that “the number of transistors per chip
would grow exponentially (double every 18 months)”. In fact the
doubling period has shortened to a mere 12 months!
Increasing transistor density
The number of transistors/gates that can fit in to the
semiconductor die dictates the complexity of the
functionality that the device can perform. The important
factors that fuel the research in VLSI technology can be
summarized as below:
• Increased functionality
• Higher reliability
• Small footprint
• Very low power consumption
• Increased speed of operation
• Re-programmability( except ASIC devices)
• Mass production
• Low cost
VLSI is thus a technology that can be
harnessed for various applications covering
analog, digital and mixed signal electronics.
The current trend is to reduce the entire
system design to a single chip solution
called as system on chip (SoC)
Building blocks of VLSI system on chip
Digital
MCU/MPU
Memory
MEMS
CCD sensors
microtransformers
microresonators
RF/Analog
Frequency generation
mixers
filters
VCO
LNA
RF power amplifiers
Opamps
Mixed-Signal DSP
Audio ,Video
circuits
MPEG engine
Power Management
converter
regulator
on-chip power supply
Applications
multimedia
computing
communications
biomedical
...
VLSI Design Process
VLSI technology thus provides a platform for developing
systems for various applications
The integrated circuits so developed can be further classified as :
ASIC
• An Application Specific Integrated Circuit
(ASIC) is a semiconductor device designed
especially for a particular customer (versus a
Standard Product, which is designed for general
use by any customer)
• The three major categories of ASIC Technology
are :
– Gate Array-Based
– Standard Cell-Based
– Full custom
Gate Arrays
• There are two types of gate arrays:
– a channeled gate array
– channel-less gate array
• A channeled gate-array is manufactured with single
or double rows of basic cells across the silicon
• A basic cell consists of a number of transistors
• The channels between the rows of cells are used for
interconnecting the basic cells during the final
customization process
• A channel-less gate array is manufactured with a
“sea” of basic cells across the silicon and there are
no dedicated channels for interconnection
• Gate arrays contain from a few thousand equivalent
gates to hundreds of thousand of equivalent gates
• Due to the limited routing space on channeled gate
arrays, typically only 70% to 90% of the total number
of available gates can be used
• The library of cells provided by a gate array
vendor will contain:
– primitive logic gates
– registers,
– hard-macros
– soft-macros
Hard-macros and soft-macros are usually of MSI and
LSI complexity, such as multiplexers, comparators
and counters.
Hard macros are defined by the manufacturer in terms
of cell primitives
Soft-macros are characterized by the designer, for
example, specifying the width of a particular counter
Standard Cell
• Standard cell devices do not have the concept of a basic
cell and no components are prefabricated on the silicon
chip
• The manufacturer creates custom masks for every stage
of the device’s process which leads to a more efficient
utilization of silicon as compared to gate arrays
• Manufacturers supply hard-macro and soft-macro
libraries containing elements of LSI and VLSI complexity,
such as controllers, ALUs and microprocessors.
• Additionally, soft-macro libraries contain RAM functions
that cannot be implemented efficiently in gate array
devices; ROM functions are more efficiently
implemented in cell primitives
The Characteristics of ASICs
The remarks that follow further discuss some
trade-offs of ASICs with respect to the
following categories:
• Complexity
• Silicon Efficiency
• Design Risks
• Prototype Turnaround
• NRE
• CAD / CAE Support
• Performance
Complexity
• Complexity here means the number of transistors (or the amount of
logic and/or memory) per given amount of area, plus the associated
interconnect capability
• Current Array-Based and Cell-Based chips accommodate as many
as 20,000,000 usable logic gates on a single die
• Array-Based designs -especially in a Channel-Free Array
technology - are capable of realizing functions that represent actual
system building blocks and incorporate system memory functions on
the same die
• The Array-Based memories do tend to be about 5 times less dense
than Cell-Based memories because they are constructed out of the
gates on the master slice. And full custom memories would provide
much higher densities than do Array-Based memories
• But in fact many designers who are using the Array-Based
technologies to get fast turn around tend to be using very small
“scratch pad” or “cache” types of memories which fit very well into
the ASIC concept
Silicon Efficiency
• Array-Based technologies focus on fast
implementation of logic integration onto a single
chip, rather than on absolute highest density.
• Cell-Based designs allow you to get more logic
onto a chip in a given area.
• Cell-Based designs feature transistors and
routing tracks whose gradations of size are finer
than those in Array-Based products. Thus Cell-
Based designs use silicon more efficiently than
Array-Based designs
NRE
• NRE (“Non-Recurring Engineering”) charges are
the costs associated with developing an ASIC
• NRE is based on a number of factors like:
– the complexity of the design,
– the technology chosen (# of masks required)
– the amount of work to be done by the customer and
by the silicon vendor
– the need for special cells or procedures
– the type of package required
– the schedule the number of layers of metal
– …
• The more work the silicon vendor does and the
more special the requirements, the higher will be
the NRE . The more work the customer does,
the lower the NRE !
• Array-Based designs require the fewest number
of design-specific masks and therefore offer the
lowest NRE to prototypes.
• Cell- Based designs require all masks to be
generated for the chosen process and therefore
the NRE charge will be higher for a Cell-Based
design than for an Array-Based design
Design Risks
• The penalty for discovering a design error
is higher for a Cell-Based ASIC than for an
Array-Based ASIC
• Mistakes after prototype fabrication in
Array-Based designs usually only require
that the metal mask layers be redone. On
the other hand, design changes for a Cell-
Based design may require that all masks
be redone !
Prototype Turnaround Time
(TAT)
• Designs that require a complete mask set (Cell-
Based) will always require more time to
manufacture than designs which use a basic set
of diffusion masks and only require
customization at the metal layers (Array-Based)
• This difference in time could be anywhere from
one week to 4 weeks depending on how fast the
silicon vendor can get masks from the mask
shop and depending on how long the FAB cycle
is for a given process
CAD / CAE Support
The use of EDA tools ensure:
• Clean documentation
• Reusable data
• Functional verification
• Easy modification
• Automated rule check
• Back-annotation (synchronization between
schematic and layout)
• Bill of material
Performance
• The two most critical parameters that have been used to
measure the worth of new technologies have been
speed and power
• High power circuits are normally fast, but the increased
power requires larger power supplies and tends to heat
up the junctions on silicon chips which slows the
devices.
• In today's most dominant ASIC technology - CMOS -
high power can cause accelerated junction temperatures
which can slow down speed
• One way to reduce the power and still maintain speed is
to develop circuits such as differential pairs that do not
switch from voltage rail to voltage rail
ASIC Design
Flow ARCHITECTURE DEFINITION
AND LOGIC DESIGN
SYSTEM REQUIREMENTS
VLSI DESIGN AND LAYOUT
DESIGN VERIFICATION
MASK GENERATION
SILICON PROCESSING
WAFER TESTING, PACKAGING,
RELIABILITY QUALIFICATION
FAIL
PASS
LOGIC DIAGRAM/DESCRIPTION
TECHNOLOGY
DESIGN RULES
DEVICE MODELS
DESIGN RULE CHECK
SIMULATION (SPICE)
INITIAL DESIGN REVIEW
DESIGN ENTRY
SIMULATION & POWER
ANALYSIS
LOGIC & TEST
SYNTHESIS
CLOCK PLANNING/
CLOCK TREE SYNTHESIS
FLOORPLANNING
GATE-LEVEL
SIMULATION
FORMAL
VERIFICATION
TEST STRUCTURE
VERIFICATION
POWER
ESTIMATION
STATIC TIMING
ANALYSIS
PRE-LAYOUT
TECHNOLOGY
CHECKS
RELEASE TO LAYOUT
TIMING DRIVEN
LAYOUT/OPTIMIZATION
STATIC TIMING
ANALYSIS
POST LAYOUT
TECHNOLOGY CHECKS
AUTOMATIC TEST-PATTERN
GENERATION
RELEASE TO
MANUFACTURING
TIMING
ASSERTIO
NS
DESIGN LANDMARKS
FRONT-END TOOLS
TEST& VERIFICATION
TOOLS
LAYOUT & PHYSICAL
VERIFICATION TOOLS
ASIC Design
Flow (detailed)
Programmable logic device
(PLD)
• It is an integrated circuit able to implement
combinational and/or sequential digital functions
defined by the designer and programmed into
this circuit
• There are a wide variety of ICs that can have
their logic function “programmed” into them after
they are manufactured. Most of these devices
use technology that also allows the function to
be reprogrammed
• Historically, programmable logic arrays (PLAs) were the
first programmable logic devices
• PLAs contained a two-level structure of AND and OR
gates with user-programmable connections
• Using this structure, a designer could accommodate any
logic function up to a certain level of complexity using the
well-known theory of logic synthesis and minimization
• PLA structure was enhanced and PLA costs were
reduced with the introduction of programmable array
logic (PAL) devices
• Today, such devices are generically called
programmable logic devices (PLDs), and are the “MSI”
of the programmable logic industry
• The ever-increasing capacity of integrated circuits
created an opportunity for IC manufacturers to design
larger PLDs for larger digital-design applications
• However, the basic two-level AND-OR structure of PLDs
could not be scaled to larger sizes. Instead, IC
manufacturers devised complex PLD (CPLD)
architectures to achieve the required scale
• A typical CPLD is merely a collection of multiple PLDs
and an interconnection structure, all on the same chip. In
addition to the individual PLDs, the on-chip
interconnection structure is also programmable,
providing a rich variety of design possibilities
• CPLDs can be scaled to larger sizes by increasing the
number of individual PLDs and the richness of the
interconnection structure on the CPLD chip
• At about the same time that CPLDs were being invented,
other IC manufacturers took a different approach to
scaling the size of programmable logic chips.
• Compared to a CPLD, a field-programmable gate arrays
(FPGA) contains a much larger number of smaller
individual logic blocks, and provides a large, distributed
interconnection structure that dominates the entire chip
CPLD and FPGA
Top-Down design methodology
• Means describing a complete system at an
abstract level using hardware description
language(HDL) and the use of EDA tools
like partitioners and synthesizers
• More time is spent on designing HDL
models, considering different architectures
and considering system test & testability
issues. Practically no time is spent on
designing at gate level
To consider a concept without
thinking of a specific example;
consider abstractly or theoretically.
ABSTRACT
Levels of behavioural abstractionINCREASINGBEHAVIOURALABSTRACTION
INCREASINGDETAILEDREALIZATION&COMPLEXITY
TRANSISTOR / SWITCH
GATE
RTL / DATAFLOW
ALGORITHM
SYSTEM
CONCEPT
The process of
formulating
general
concepts by
abstracting
common
properties of
instances
• System Level: All the specifications (input and output) are
described at this level. This level completely ignores the
hardware structure. However HDLs are not useful at this stage.
It simply treats the design like a black box.
• Algorithmic (also called behavioural) level: This is the highest
level of abstraction provided by most HDLs. A module can be
implemented in terms of the desired deign algorithm without the
concern of the hardware implementation details. Design at this
level is very similar to a conventional high level language
programming like C.
• RTL (Register Transfer Level) (also called dataflow): At this level
the module is designed by specifying the data flow between the
registers. The designer is aware of how data flows between
hardware registers and how the data is processed in the design.
• Gate Level: The module is implemented in terms of logic gates
and interconnections between these gates. Design at this level
is similar to describing a design in terms of gate-level logic
diagram.
• Transistor (also called Switch) Level: This is the lowest level of
abstraction. A module can be implemented in terms of switches,
storage nodes, and the interconnections between them. Design
at this level requires knowledge of switch-level implementation
details.
Lecture 2
Introduction to VHDL
R.B.Ghongade
PLD based design flow
•A decision has to be arrived at regarding the
selection of the type of a PLD since we have two
options the CPLD and the FPGA
•The selected device is then called the target
device
• Specifications
• Design Entry
• Compilation
• Functional Simulation/Verification
• Synthesis
• Post-synthesis simulation
• Implementation
• Timing Simulation
• Hardware Implementation
Steps involved:
SPECIFICATIONS
(STEP 1)
CREATE A DIGITAL DESIGN
BY
VHDL CODE
SCHEMATIC ENTRY
STATE DIAGRAM
(STEP 2)
COMPILATION
(STEP 3)
FUNCTIONAL SIMULATION
(STEP 4)
(SPECIFY TARGET DEVICE)
SYNTHESIS
(STEP 5)
SIMULATION
(POST SYNTHESIS)
(STEP 6)
IMPLEMENTATION
PLACE & ROUTE
Active-HDL
Xilinx ISE
Libero IDE
FPGA Advantage
Lattice ISP LEVER
Active-HDL
Modelsim
Xilinx XST
Synplify
Leonardo Spectrum
Active-HDL
Modelsim
(RTL Level)
Netlist
(Gate Level)
Optimized Netlist
(Gate Level)
(STEP 7)
SIMULATION
(TIMING ASPECTS)
Palace
Active-HDL
Modelsim
Xilinx IMPACT
Actel Flash Pro
(STEP 8)
HARDWARE
IMPLEMENTATION
HDL based design flow
Idea
Design Entry
(Schematic)
VHDL Template
Model
Generator
Target
Device
Library
Synthesis
(Synthesizer Tool)
Design Entry
(Text Editor)
Netlist
(EDIF,XNF,DSL...)
Functional Simulation
(VHDL Simulator)
Algorithmic Simulation
(VHDL)
Test Vectors
(Input Stimuli & Output
Expected)
Post- Simulation
(VHDL Simulator)
Structural VHDL
(VITAL primitives)
Timing Analysis
VITAL
Primitive
Library
SDF
(Delay Information)
Program Data
(Fuse Map: JED, HEX...)
Device Programming
JTAG-ISP
Chip
Placement & Routing
(Device Vendor's Tool)
Back-annotation
TO PLACE & ROUTE
NETLIST
Detailed HDL based design flow
• It may again include the input, output and ambient specifications
• Target device may be finalized
• Choice of target device as CPLD or FPGA depends on various factors
• Specific type of device may be selected by comparing the specifications
provided by the manufacturer in the datasheet and the actual design
requirements
6
3
31
5
5
15
11
24
Xilinx
Actel
Cypress
Altera
Lattice
AMD
AT&T
Others
• XILINX
• LATTICE
• LUCENT
• ALTERA
• ACTEL
• CYPRESS
• AT&T
• AMD
Specifications
Design Entry
• This is essentially the design entry point in an EDA tool
• It can be done by the following means:
• Block Diagram/Schematic capture
• State Diagram entry
• HDL code entry
Block Diagram/Schematic capture
• A schematic circuit is literally “drawn” in an appropriate graphical
editor
• The EDA tool associated with this task is called Schematic Capture
Tool
• An electrical rule check (ERC) is usually run
• The main job of the ERC tool is to check for incorrect electrical
connections for example if a VCC pin of an IC is accidentally shorted
to ground, then the ERC tool will point out such a discrepancy
• For this tool to be effective the IC pins have to be earlier declared as
power, ground, input, output, bidirectional etc.
• After removing the ERC errors a netlist is generated by the editor
• A netlist is a text file showing the nets i.e. a set of components
connected together
• It is also possible to generate VHDL netlist
Block Diagram/Schematic capture
State Diagram entry
• Many designs are most effectively described
/designed by state diagram approach.
• Effective for sequential designs
• The EDA tools provide a graphical interface so
that the designer can directly make an entry of
the state diagram and generate the netlist.
• This method is preferred since it is a fast way of
creating the design
State Diagram entry
HDL code entry
• A designer can enter his /her design using a hardware description
language (HDL)
• The HDLs prominent in the industry are “VHDL” and “Verilog”
• There is another language that is recently making ground called as
“System C”
• Being similar to C language gives it an advantage to be more user
friendly and comfortable to designers familiar with C
• Using the code entry method is the most preferred one since it
offers:
– Design flexibility
– Code re-use
– Easy modification
– Tighter control over resources
• A netlist is again created by compiling the HDL code
HDL code entry
Compilation
• At this stage the design is said to be at the Register
Transfer Level (RTL)
• All the data manipulation is done here at the register of
the host CPU or we can say that the design is not in
terms of the logic gates but “internal” to the environment
• After successful compilation of the design using any one
of the three methods a netlist is generated which is
called the gate-level netlist
• The design now is translated in terms of the logic gates
and modular entities like multiplexers, decoders. Thus
we now have the design at Gate-level
Functional
Simulation/Verification
• There are two very different tasks in digital
system development
– Verification is the process of determining
whether a design meets the specification and
performance goals
– It concerns the correctness of the initial
design as well as the refinement processes
– Testing is the process of detecting the
physical defects of a die or a package that
occurred during manufacturing
Functional
Simulation/Verification
• A functional test is done by simulating the gate-level design using
logic simulators that may be available as a built-in feature of the
EDA tool. There are two ways of functional verification:
– Interactive mode
• In the interactive mode the designer can change the input signals and
observe the corresponding output behaviour of the design. This method is
becomes cumbersome for designs involving large number of inputs and
outputs.
– Batch mode
• Batch mode uses the concept of test-benches (also a piece of VHDL code)
that generates test patterns and checks the validity of the output. This mode
is attractive for larger designs.
• If any undesirable behaviour is observed, the designer can correct
the flaw by going back to the design entry level
• It is important here to note that none of the timing aspects have
been considered during this simulation. Functional verification can
thus be compared to the algorithm testing in conventional
programming languages
Synthesis
• Synthesis means to properly put together so as to make
the whole complex design
• At this stage it is necessary to specify the target device,
since the synthesis tool (again dedicated software)
requires knowing the resources available with the target
device
• Synthesis optimally maps the design functionality (at the
gate-level) in to the actual devices available with the
target device
• For example if the design uses a four- input AND gate
but since this is not available with the target device, the
synthesis tool can break down the four- input AND gate
into two two-input AND gates and map correspondingly
• Optimization is very important otherwise the design may
get “blown-up” and the target device may prove too small
for the design
• Synthesis tools have built-in proprietary algorithms for
optimization
Post-synthesis simulation
• After synthesis the design needs to be re-
checked to confirm its functionality
• Simulation at this level ensures that the
mapped design behaves correctly as
desired
• A possibility may exist wherein, the
synthesis tool may incorrectly recompose
the design while mapping
• Again timing parameters are ignored here
Implementation
• This is the process of physical placing of the design into
the target device.
• Though it is a physical placement, it still takes place in
the virtual environment provided by the EDA tool
• A physical map of the target device is loaded into the
environment and the components are virtually fitted into
the target device.
• Again this process may have two phases:
– Physical synthesis
• Physical synthesis means optimal relocation of the design into the
target device. Proprietary software tools are available for this task
and may be quite costly. This phase is however optional.
– Place and route
• Place and route is the phase where the tool completes the task of
virtually placing the components of the design in to the target device
and then wiring the individual modules to complete the design.
Timing Simulation
• One most important change the design undergoes is
after the implementation.
• The modules in the design now may be physically placed
apart from each other.
• This factor introduces the delay aspect in the signal
propagation.
• Many synchronous circuits will fail if the timing aspects
are ignored, even though they appear to be functionally
perfect!
• Hence a simulation is necessary again to test the timing
behaviour of the design.
• This provides the designer with a better view of the
design functionality.
• In fact the real-world behaviour of the device can be very
accurately studied by the simulation with timing aspects
Hardware Implementation
• The final step in design is to “download”
the functionality into the actual hardware
i.e. the target device
• The synthesis tool generates the output in
terms of “bit-stream” that is used to
configure the target device
• Vendor specific tools can be used for
downloading the bit-stream into the
physical device
HDL
• A hardware description language (HDL) is a software coding
language used to model the intended operation of a piece of
hardware
• There are two aspects to the description of hardware that an HDL
facilitates:
– true abstract behaviour modeling
– hardware structure modeling
• Abstract behaviour modeling
– A hardware description language is declarative in order to facilitate the
abstract description of hardware behaviour for specification purpose.
This behaviour is not influenced by structural or design aspects of the
hardware intent.
• Hardware structure modeling
– Hardware structure is capable of being modeled in a hardware
description language irrespective of the design’s behaviour.
VHDL
• What is VHDL?
– Digital system design using Hardware
Description Language is an established
methodology in EDA
– VHDL stands for
“VERY HIGH SPEED INTEGRATED CIRCUITS
HARDWARE DESCRIPTION LANUAGE”
EDA stands for “ELECTRONIC DESIGN AUTOMATION”
FEATURES
• VHDL is an amalgamation of following
languages
– Concurrent language
– Sequential Language
– Timing Specification
– Simulation Language
– Test Language
• VHDL has got powerful language
constructs
– {if…else}, {with…select} etc
• Design hierarchies to create modular
designs
• Supports Design Libraries
• Facilitates device independent design and
portability
Concurrent Language
• Concurrent statements execute at the same time
in parallel as in hardware
Z <= C + X ;
X <= A + B ;
+
+
A
B
C
X
Z
Sequential Language
• Sequential statements execute one at a
time in sequence
• As the case with any conventional
programming language the sequence of
statements is important
Z <= C + X ;
X <= A + B;
X <= A + B;
Z <= C + X ;≠
Sequential statements are required to design sequential circuits
Timing Specification
• Providing timing attributes in a sequential digital
design is of prime importance since the
operations are synchronized to a common clock
• Example:
process
begin
clk <= ‘0’ ;
wait for 20 ns ;
clk <= ‘1’ ;
wait for 12 ns ;
end process ;
0 20 32 52 64
ns
84
Timing can be specified in a process only
Simulation language
• For analyzing a digital design it is
important the design be simulated
• Simulation has different flavours
– Functional simulation
– Post-synthesis simulation
– Post- layout simulation
• Any HDL should thus be equipped with
simulation capability for verification and
troubleshooting purposes
Test Language
• Testbench
– It is a part of a VHDL module that generates a
set of test vectors (test inputs) and sends
them to the module being tested
– It collects the responses generated by the
module under test and compares them
against a specification of correct results
– Thus testbench is required to ensure that the
design is correct and that the module is
operating as desired
Equivalent to checking of logical errors in any conventional programming
language
Testbench use
Test
tst_a
tst_b
tst_c
MODULE UNDER TEST
ABC.vhdABC_testbench.vhd
Equivalent to mechanical test jigs used for testing functionality of mass
produced pcbs as in TV sets or motherboards
Design Hierarchy
• Hierarchy can be represented using VHDL
• Example
– A full adder which is the top level module being
composed of three lower level modules that are; half
adder and OR gate
HALF
ADDER
HALF
ADDER
OR
A
B
Cin
SUM
CARRY
Design hierarchy simplifies the design procedure and manageability in case
of complex designs
Design Libraries
• Design Unit
– It is any block of VHDL code or collection of VHDL
codes that may be independently analyzed and
inserted into a design library
• Design Library
– It is a storage facility in which analysed VHDL
descriptions are stored for repeated uses
1
3
2
54
Design
Library
Simulator
Analyze
DESIGN UNIT
Logic systems
• Need for multi-valued logic system
– Conventional logic systems have only three values
i.e. ‘0’, ‘1’, ‘Z’
• Example
– Consider the truth-table for AND gate
A B Y
0 0 0
0 1 0
1 0 0
1 1 1
0 Z ?
HOW TO RESOLVE THIS CONDITION ?
• For this problem a 9-valued logic system
or package was developed that is called
“STD_LOGIC_1164” and it is accepted as
IEEE STD 1164-1993
• Multi-valued logic
– Unknown: value was known but not anymore
– Un-initialized: value was never known
– High impedance: net has no driver
– Drive strengths: handle different output
drivers
– Don’t care: value is immaterial
Levels of abstraction
• Different styles are adopted for writing VHDL
code
• Abstraction defines how much detail about the
design is specified in a particular description
• Four levels are:
– Layout level
– Logic level
– Register Transfer level
– Behavioral level LOGIC
LAYOUT
RTL
BEHAVIORAL
Layout Level
• This is the lowest level and describes the
CMOS layout level design on silicon
Logic Level
• Design has information about
– Function
– Architecture
– Technology
– Detailed timings
• Layout information and analog effects are
ignored
Register Transfer Level
• Using HDL every register in the design
and the logic in between is defined
• Design contains:
– Architecture information
– No details of technology
– No specification of absolute timing delays
Behavioral Level
• Describing function of a design using HDL
without specifying the architecture of
registers
• Contains timing information required to
represent a function
Basic building blocks of VHDL
code
• A VHDL design is composed of following
blocks:
– Library declarations
– Entity
– Architecture
– Configuration
Basic VHDL code
LIBRARY DECLARATIONS
ENTITY
ARCHITECTURE
CONFIGURATION
BASIC VHDL CODE
Detailed anatomy of VHDL code
Functions
Procedures
Types
Constants
Components
Package
Library
EntityGenerics Ports
Architecture
(Style I)
DATAFLOW
Architecture
(Style II)
BEHAVIOURAL
Architecture
(Style III)
STRUCTURAL
Concurrent
Statements
Concurrent
Statements
Process
Sequential
Statements
Elements of VHDL
R.B.Ghongade
Lecture 3
Basic building blocks
LIBRARY
DECLARATIONS
ENTITY
ARCHITECTURE
CONFIGURATION
BASIC VHDL CODE
Overview
Library
• It is a collection of compiled VHDL units
• It enables sharing of compiled designs and
hides the source code from the users
• Commonly used functions, procedures and
user data types can be compiled into a user
defined library for use with all designs
• Library should be declared before each
entity declaration even if it is in the same
VHDL file
Library
• To declare a library (i.e. to make it visible to the
design) two lines of code are needed , one
containing name of the library, the other a use
clause
• A library structure can be as follows:
FUNCTIONS
PROCEDURES
TYPES
CONSTANTS
COMPONENTS
LIBRARY
PACKAGE
Library syntax
LIBRARY library_name ;
USE library_name.package_name.package_parts ;
LIBRARY IEEE ; -- semicolon indicates
USE IEEE.std_logic_1164.all ; -- end of statement or
-- declaration
LIBRARY work ; -- double dash (--)
-- indicates a comment
USE work.all ;
Example
Library details
IEEE.MATH_COMPLEX.all This package defines a standard for designers
to use in describing VHDL models that make
use of common COMPLEX constants and
common COMPLEX mathematical functions and
operators.
IEEE.MATH_REAL.all This package defines a standard for designers
to use in describing VHDL models that make
use of common REAL constants and common
REAL elementary mathematical functions.
IEEE.NUMERIC_BIT.all This package defines numeric types and
arithmetic functions for use with synthesis tools.
Two numeric types are defined:
-- UNSIGNED: represents an UNSIGNED
number in vector form
-- SIGNED: represents a SIGNED number in
vector form
The base element type is type BIT.
Library details
IEEE.NUMERIC_STD.alll This package defines numeric types and
arithmetic functions for use with synthesis tools.
Two numeric types are defined:
-- UNSIGNED: represents UNSIGNED number in
vector form
-- SIGNED: represents a SIGNED number in
vector form
-- The base element type is type STD_LOGIC.
IEEE.STD_LOGIC_1164.all This package defines a standard for designers
to use in describing the interconnection data
types used in VHDL modeling.
Defines multi-value logic types and related
functions.
IEEE.STD_LOGIC_ARITH.all This package defines a set of arithmetic,
conversion, and comparison functions
for SIGNED, UNSIGNED, SMALL_INT,
INTEGER, STD_ULOGIC, STD_LOGIC, and
STD_LOGIC_VECTOR.
Library details
IEEE.STD_LOGIC_MISC.alll This package defines supplemental types,
subtypes, constants, and functions for the
Std_logic_1164 Package.
IEEE.STD_LOGIC_SIGNED.all This package defines a set of signed
arithmetic, conversion, and comparison
functions for STD_LOGIC_VECTOR.
IEEE.STD_LOGIC_TEXTIO.all This package overloads the standard
TEXTIO procedures READ and WRITE.
IEEE.STD_LOGIC_UNSIGNED.all This package defines a set of unsigned
arithmetic, conversion and comparison
functions for STD_LOGIC_VECTOR.
Entity
– It is the design’s interface to the external
circuitry
– Equivalent to pinout /package of an IC
– VHDL design must include one and only one
entity per module
– It can be used as a component in other
entities after being compiled into a library
Entity declaration
• Defines the input and output ports of the design
• Name of the entity can be anything other than
the reserved VHDL word
• Each port in the port list must be allotted:
– a name ( should be self-explanatory that provides
information about its function
– data flow direction or mode
– a type
• Ports should be well documented with
comments at the end of line providing additional
information about the signal
Entity syntax
entity entity_name is
port ( port_name : signal_mode signal_type ;
port_name : signal_mode signal_type ;
port_name : signal_mode signal_type ) ;
end entity_name ;
Modes
• Ports in the portlist have modes which
indicate the driver direction
• Mode also indicates whether or not the
port can be read from within the entity
• Four modes are available:
– Mode IN
– Mode OUT
– Mode INOUT
– Mode BUFFER
• Mode IN
Value can be read from but not assigned to (by
the entity)
ENTITY
Port signal A
Drivers reside
outside the entity
port ( A : in std_logic ) ;
• Mode OUT
Value can be assigned to but not read from (by
the entity)
port ( B : out std_logic ) ;
ENTITY
Port signal B
Drivers reside
inside the entity
• Mode INOUT
Bi-directional , value can be assigned to as well
as read from (by the entity)
port ( C : inout std_logic ) ;
ENTITY
Port signal C
Drivers reside both
inside and
outside the entity
• Mode BUFFER
Output port with internal read capability
port ( D : buffer std_logic ) ;
ENTITY
Port signal D
Drivers reside
inside the entity
Signal can be read inside the entityDO NOT USE UNLESS REQUIRED
Entity example
entity and_gate is
port ( 1A , 2A , 3A, 4A : in std_logic ;
1B , 2B , 3B, 4B : in std_logic ;
1Y , 2Y , 3Y, 4Y : out std_logic ) ;
end and_gate ;
1A
1
1B
2
1Y
3
2A
4
2B
5
2Y
6
GND
7
3Y
8
3A
9
3B
10
4Y
11
4A
12
4B
13
VCC
14
Entity example
entity ALU is
port ( In1 : in std_logic_vector ( 3 downto 0) ; -- 1st operand
In2 ; in std_logic_vector ( 3 downto 0) ; -- 2nd operand
Opsel : in std_logic_vector ( 3 downto 0) ; -- opn select
Cin : in std_logic ;
Mode : in std_logic ;
Result : out std_logic_vector ( 3 downto 0 ) ;
Cout : out std_logic ;
Equal : out std_logic ) ;
end ALU ;
ALU
In1 In2
Op
sel
Result
Cout
Mode
Cin
Equal
Architecture
It specifies
• Behaviour
• Function
• Relationship between inputs and outputs of an entity
Syntax
architecture achitecture_name of entity_name is
[declarations] -- optional
begin
code -- concurrent statements only
end achitecture_name ;
• Architecture can contain only concurrent
statements
• A design can be described in an
architecture using various levels of
abstraction
• An entity can have more than one
architectures since a function can be
implemented in a number of ways
• There can be no architecture without an
entity
Architectural bodies
• Behavioural
– It is the high-level description
– It contains a set of assignment statements to represent
behaviour
– No need to focus on the gate-level implementation of a design
Example:
architecture behave of and_gate is
begin
process ( a, b )
if a=‘1’ and b=‘1’ then
c <= ‘1’ ;
else
c <=‘0’ ;
end if ;
end process ;
end behave ;
• Dataflow
– It uses concurrent signal assignment
statements
Example:
architecture dataflow of and_gate is
begin
c<= a and b ;
end dataflow ;
• Structural
– Components from libraries are connected
together
– Designs are hierarchical
– each component can be individually simulated
– it makes use of component instantiation
HALF
ADDER
HALF
ADDER
OR
A
B
Cin
SUM
CARRY
Functional units
Top level design
Configuration
• Since a number of architectures can exist
for an entity , using configuration
statement we can bind a particular
architecture to the entity
configuration CONFIGURATION_NAME of ENTITY_NAME is
for ARCHITECTURE_NAME
end for;
end CONFIGURATION_NAME;
Syntax
Language elements
Next class
Language Elements I
R.B.Ghongade
Lecture 4
• VHDL is a strongly typed language
– Designers have to declare the type before
using it
• VHDL is not case sensitive ( but avoid
mixed cases as a good programming
practice)
• VHDL supports a wide variety of data
types and operators
– OBJECTS
– OPERATORS
– AGGREGATES
Objects
• They are used to represent and store the
data in the design being described
• Object contains a value of specific type
Class Object Data type
SIGNAL COUNT : INTEGER
This results in an object called COUNT that holds
INTEGER value that belongs to class SIGNAL
• The name given to the object is called as
identifier
• Do not use reserved words as identifiers
• Each object has a data type and class
• Class indicates how the object is used in the
module and what can be done with that object
• Type indicates what type of data the object
contains
• Each object belongs to one of the following class:
– CONSTANT
– SIGNAL
– VARIABLE
– FILES
CONSTANT SIGNAL VARIABLE
CLASS
FILES
Data Types
• In order to write VHDL code efficiently it is
necessary to study the specification and use of
data types
• Following are the categories of data types:
– Pre-defined
– User defined
– Subtypes
– Arrays
– Port arrays
– Records
– Signed and unsigned
Pre-defined data types
• Specified by IEEE 1076 and IEEE 1164
Package Library Type/Functions
standard std BIT, BOOLEAN,
INTEGER, REAL
std_logic_1164 ieee STD_LOGIC,
STD_ULOGIC
std_logic_arith ieee SIGNED, UNSIGNED /
data conversion functions
std_logic_signed ieee Functions that allow
operations with
STD_LOGIC_VECTOR
std_logic_unsigned ieee
BIT (and BIT_VECTOR): 2 level logic (‘0’, ‘1’)
Examples:
SIGNAL X : BIT ;
X is declared
as a one-
digit SIGNAL
of type BIT
SIGNAL Y : BIT_VECTOR (3 downto 0);
Y is 4-bit
vector,
leftmost bit
is MSB
SIGNAL W : BIT_VECTOR (0 to 7);
W is 8-bit
vector,
rightmost bit
is MSB
• To assign a value to the signal use the
operator “ < = ”
• Assignment examples:
X <= ‘1’ ;
X is a single bit SIGNAL whose value is ‘1’
Note that single quotes are used for a single bit
Y <= “0111” ;
Y is a 4- bit SIGNAL whose value
is “0111” . Note that double
quotes are used for vectors
W <= “01110001” ;
W is an 8- bit SIGNAL whose
value is “0111001” . MSB is ‘1’
STD_LOGIC (and STD_LOGIC_VECTOR):
8 valued logic (introduced in IEEE 1164 standard)
Symbol Description Remark
‘X’ Forcing unknown Synthesizable unknown
‘0’ Forcing low Synthesizable logic ‘0’
‘1’ Forcing high Synthesizable logic ‘1’
‘Z’ High impedance Synthesizable tri-state buffer
‘W’ Weak unknown
‘L’ Weak low
‘H’ Weak high
‘-’ Don’t care
Examples:
SIGNAL X : STD_LOGIC ;
X is declared as a one-digit
(scalar) SIGNAL of type
STD_LOGIC
SIGNAL Y : STD_LOGIC_VECTOR (3 downto 0);
Y is 4-bit
vector, leftmost
bit is MSB
SIGNAL Y : STD_LOGIC_VECTOR (3 downto 0) : = “0001”
for (optional)
initial value use
“ := ”
Most of std_logic levels are intended for simulation
only. However ‘0’, ‘1’ and ‘Z’ are synthesizable with
no restrictions
• With respect to
“weak” values, they
are resolved in favour
of the “forcing” values
in multiple-driven
nodes. If any two
std_logic signals are
connected to the
same node, then
conflicting logic levels
are resolved by using
the shown table
X 0 1 Z W L H -
X X X X X X X X X
0 X 0 X 0 0 0 0 X
1 X X 1 1 1 1 1 X
Z X 0 1 Z W L H Z
W X 0 1 W W W W X
L X 0 1 L W L W X
H X 0 1 H W W H X
- X X X X X X X X
•The STD_ULOGIC has 9 valued logic levels : additional
value is ‘U’ for “Un-resolved or ”Un-initialized”
• Other types
BOOLEAN TRUE, FALSE
INTEGER 32-bit integers (from - 2,147,483,647 to +
2,147,483,647
NATURAL Non-negative numbers (from 0 to
2,147,483,647
REAL Real numbers (from -1.0E-38 to +1.0E38)
Physical
literals
Used to inform physical quantities like , time,
voltage etc. Useful for simulation but not
synthesizable
Character
literals
Single ASCII character or a string of such
characters. Not synthesizable
SIGNED,
UNSIGNED
They have appearance of
STD_LOGIC_VECTOR, but accept arithmetic
operations which are typical of INTEGER data
type
User defined data types
• VHDL allows user defined data types
• Two categories of this data type are:
– Integer
– Enumerated
• User defined integer type
TYPE my_integer IS RANGE -32 to +32 ;
TYPE student_grade IS RANGE 0 to 100 ;
• User defined enumerated type
TYPE my_logic IS (‘0’, ‘1’, ‘Z’ );
TYPE my_state IS ( idle, forward, backward, stop) ;
An enumerated type, typically used
in state machines
• The encoding of enumerated types is done
sequentially and automatically
• Since here there are 4 states only two bits
are required hence “00” is assigned to first
state ( idle), “01” to second state (forward)
and so on.
Subtypes
• A SUBTYPE is a TYPE with a constraint
• Though operations between data of
different types are not allowed, they are
allowed between the subtype and its
corresponding base type
SUBTYPE sub_state IS my_state RANGE idle to backward ;
This means that the subtype
sub_state =(idle, forward, backward)
Arrays
• Arrays are collections of objects of same type
• Can be 1-dimensional, 2-dimensional or
1D X 1D
• Higher dimensional arrays are possible but not
synthesizable
0 0 1 0 0
1 0 1 0
1 1 0 0
0 1 0 0
1 1 0 1
0 1 0 1 0
1 0 1 1 0
0 1 0 1 0
Scalar
1D
1D x 1D
2D data array
Array syntax
TYPE type_name IS ARRAY (specification) OF data_type ;
To specify an array :
SIGNAL signal_name : type_name [:= initial_value]
To use an array :
Example : 1D x 1D array
– We want to build an array containing 4
vectors, each of size 8 bits
– we will call each vector as row and the
complete array as matrix
TYPE row IS ARRAY (7 downto 0 ) OF STD_LOGIC ;
TYPE matrix IS ARRAY (3 downto 0 ) OF row ;
SIGNAL X : matrix ;
1D x 1D SIGNAL
Example : 2D array
– This array will be created with scalars only
TYPE matrix2D IS ARRAY (0 TO 3, 7 DOWNTO 0 ) OF STD_LOGIC ;
L
M L
M
ROWS
COLUMNS
Port Arrays
• In the specification of the input or output
pins (PORTS) of a circuit (which is made in
the ENTITY), we might need to specify the
ports as arrays of vectors.
• Since TYPE declarations are not allowed
in an ENTITY, the solution is to declare
user-defined data types in a PACKAGE,
which will then be visible to the whole
design (thus including the ENTITY)
------- Package: --------------------------
LIBRARY ieee;
USE ieee.std_logic_1164.all;
----------------------------
PACKAGE my_data_types IS
TYPE vector_array IS ARRAY (NATURAL RANGE <>) OF
STD_LOGIC_VECTOR(7 DOWNTO 0);
END my_data_types;
--------------------------------------------
------- Main code: -------------------------
LIBRARY ieee;
USE ieee.std_logic_1164.all;
USE work.my_data_types.all; -- user-defined package
---------------------------
ENTITY mux IS
PORT (inp: IN VECTOR_ARRAY (0 TO 3);
... );
END mux;
... ;
--------------------------------------------
• As can be seen in the example above, a user-
defined data type, called vector_array,was
created, which can contain an indefinite number
of vectors of size eight bits each (NATURAL
RANGE <> signifies that the range is not fixed,
with the only restriction that it must fall within the
NATURAL range, which goes from 0 to
+2,147,483,647)
• The data type was saved in a PACKAGE called
my_data_types, and later used in an ENTITY to
specify a PORT called inp
• Notice in the main code the inclusion of an
additional USE clause to make the user-defined
package my_data_types visible to the design.
Records
• Records are similar to arrays, with the only
difference that they contain objects of
different types.
TYPE birthday IS RECORD
day: INTEGER RANGE 1 TO 31;
month: month_name;
END RECORD;
Signed and Unsigned data types
• These types are defined in the
std_logic_arith package of the ieee library
Examples:
SIGNAL x: SIGNED (7 DOWNTO 0);
SIGNAL y: UNSIGNED (0 TO 3);
• An UNSIGNED value is a number never lower
than zero. For example, ‘‘0101’’
represents the decimal 5, while ‘‘1101’’ signifies
13.
• If type SIGNED is used instead, the value can
be positive or negative (in two’s complement
format). Therefore,‘‘0101’’ would represent the
decimal 5, while ‘‘1101’’ would mean 3.
• To use SIGNED or UNSIGNED data types, the
std_logic_arith package, of the ieee library, must
be declared
Next class
Language Elements II
Language Elements II
R.B.Ghongade
Lecture 5
Operators
• VHDL provides several kinds of pre-
defined operators
– Assignment operators
– Logical operators
– Arithmetic operators
– Relational operators
– Shift operators
– Concatenation operators
Assignment operators
• Are used to assign values to signals, variables,
and constants.
<= Used to assign a value to a SIGNAL
:=
Used to assign a value to a
VARIABLE, CONSTANT, or
GENERIC
Used also for establishing initial values
=> Used to assign values to individual
vector elements or with OTHERS
SIGNAL x : STD_LOGIC;
VARIABLE y : STD_LOGIC_VECTOR(3 DOWNTO 0);
SIGNAL w: STD_LOGIC_VECTOR(0 TO 7);
x <= '1'; -- '1' is assigned to SIGNAL x using "<="
y := "0000"; -- "0000" is assigned to VARIABLE y using
--":="
w <= "10000000"; -- LSB is '1', the others are '0'
w <= (0 =>'1', OTHERS =>'0'); -- LSB is '1', the others
-- are '0'
Then the following assignments are legal:
Logical operators
• Used to perform logical operations.
• The data must be of type:
– BIT, STD_LOGIC
– STD_ULOGIC
– BIT_VECTOR
– STD_LOGIC_VECTOR
– STD_ULOGIC_VECTOR
• The logical operators
are:
– NOT
– AND
– OR
– NAND
– NOR
– XOR
– XNOR
The NOT
operator has
precedence
over the
others
Examples:
y <= NOT a AND b; -- (a'.b)
y <= NOT (a AND b); -- (a.b)'
y <= a NAND b; -- (a.b)'
Arithmetic operators
• Used to perform arithmetic operations. The data
can be of type INTEGER, SIGNED, UNSIGNED,
or REAL (the last cannot be synthesized
directly).
• Also, if the std_logic_signed or the
std_logic_unsigned package of the ieee library is
used, then STD_LOGIC_VECTOR can also be
employed directly in addition and subtraction
operations
+ ( Addition)
- (Subtraction)
* (Multiplication)
/ (Division)
** (Exponentiation)
MOD ( Modulus)
REM ( Remainder)
ABS ( Absolute value)
•There are no synthesis restrictions regarding addition and
subtraction, and the same is generally true for multiplication
•For division, only power of two dividers (shift operation) are
allowed
•For exponentiation, only static values of base and exponent
are accepted
•Regarding the mod and rem operators, y mod x returns the
remainder of y/x with the signal of x, while y rem x returns the
remainder of y/x with the signal of y
•Finally, abs returns the absolute value
For mod, rem, abs , there
generally is little or no
synthesis support
Comparison operators
= Equal to
/= Not equal to
< Less than
> Greater than
<= Less than or equal to
>= Greater than or equal to
Also called RELATIONAL
operators
Shift operators
sll shift left logical
srl shift right logical
sla shift left arithmetic
sra shift right arithmetic
ror rotate left logical
rol rotate right logical
0
0
LOGICAL
SHIFTING
ARITHMETIC SHIFTING
(retains sign bit)
ROTATE
• LOGICAL
• ARITHMETIC
• ROTATE
Concatenation operator
• Operands can be one-dimensional array type
or element type
• “ &” works on vectors only
& Concatenation
Example:
SIGNAL a : STD_LOGIC_VECTOR ( 5 DOWNTO 0 ) ;
SIGNAL b,c,d : STD_LOGIC_VECTOR ( 2 DOWNTO 0 ) ;
BEGIN
b <= ‘0’ & c(1) & d(2) ;
a <= c & d ;
. . .
Operator summary
Operator type Operators Data types
Logical
NOT, AND, AND
OR, NOR, XOR,
XNOR
BIT, BIT_VECTOR, STD_LOGIC,
STD_LOGIC_VECTOR, STD_ULOGIC,
STD_ULOGIC_VECTOR
Arithmetic
+, -,*,/,**
(mod, rem , abs)
INTEGER, SIGNED, UNSIGNED
Comparison =, /=, <, >, <=, >= All above
Shift
sll, srl, sla, sra,
rol, ror
BIT_VECTOR
Concatenation &, ( , , , )
Same as for logical operators, plus
SIGNED and UNSIGNED
Operator overloading
• Operators can be user-defined
• Let us consider the pre-defined arithmetic
operators seen earlier (+,- , *, /, etc.). They
specify arithmetic operations between data
of certain types (INTEGER, for example)
• For instance, the pre-defined ‘‘+’’ operator
does not allow addition between data of
type BIT.
• We can define our own operators, using
the same name as the pre-defined ones
• For example, we could use ‘‘+’’ to indicate
a new kind of addition, this time between
values of type BIT_VECTOR. This
technique is called operator overloading
• Example: Consider that we want to add an
integer to a binary 1-bit number. Then the
following FUNCTION could be used
FUNCTION "+" (a: INTEGER, b: BIT) RETURN INTEGER IS
BEGIN
IF (b='1') THEN RETURN a+1;
ELSE RETURN a;
END IF;
END "+";
A call to the function above could thus be the
following:
SIGNAL inp1, outp: INTEGER RANGE 0 TO
15;
SIGNAL inp2: BIT;
(...)
outp <= 3 + inp1 + inp2;
(...)
• In ‘‘outp<=3+inp1+inp2;’’, the first ‘‘+’’ is the pre-
defined addition operator (adds two integers),
while the second is the overloaded user-defined
addition operator (adds an integer and a bit).
Aggregates
• It assigns values to elements of an array
a <= (OTHERS => ‘0’ ) ; a <= “0000” ;
• We can assign values to some bits in a
vector and use “OTHERS” clause to assign
default values to remaining bits
a <= (0 => ‘1’, 2 => ‘1’, OTHERS => ‘0’ ) ;
is equivalent to
a <= “00101” ;
Useful when we are
dealing with large vectors
• Each object has a data type and class
• Class indicates how the object is used in the
module and what can be done with that object
• Type indicates what type of data the object
contains
• Each object belongs to one of the following class:
– CONSTANT
– SIGNAL
– VARIABLE
CONSTANT SIGNAL VARIABLE
CLASS
Classes re-visited
Constants
• These are identifiers with fixed values
• The value is assigned only once when
declared
• Values cannot be changed during
simulation
CONSTANT bus_width : INTEGER :=16 ;
CONSTANT CLK_PERIOD : TIME :=15 ns ;
• Constants make the design description
more readable
• Design changed at later time becomes
easy
Signals
Equivalent to wires
within a circuit
Example:
architecture and_gate of myand is
signal TEMP : STD_LOGIC ;
begin
U1 : AND2 portmap ( a, b, TEMP ) ;
U2 : AND2 portmap (TEMP, c , d ) ;
end and_gate ;
a
b
AND2
TEMP
c
AND2
d
• Thus signals are used :
– to connect design entities together and
communicate changes in values within a
design
– instead of INOUT mode
• Each signal has a history of values i.e.
they hold a list of values which include
current value of the signal and a set of
possible future values that can appear on
the signal
• Computed value is assigned to signal after
specified delay called DELTA DELAY
Variables
• These are objects with single current
value
• They are used to store the intermediate
values between the sequential statements
• Variable assignment occurs immediately
• Variables can be declared and used inside
the process statement only. But they retain
their value throughout the entire simulation
process ( a )
variable count : INTEGER : = 1 ;
begin
count : = count+ 1 ;
end process ;
Example :
count contains the total
number of events that
occurred on signal a
Language elements III
Next class
Language Elements III
R.B.Ghongade
Lecture 6
Attributes
• An attribute is data that are attached to VHDL
objects or predefined data about VHDL objects
• Examples are the current drive capability of a
buffer or the maximum operating temperature of
the device
• Types are
– Data Attributes
– Signal Attributes
– User-defined Attributes
Data Attributes
The pre-defined, synthesizable data attributes
are the following:
• d’LOW : Returns lower array index
• d’HIGH : Returns upper array index
• d’LEFT : Returns leftmost array index
• d’RIGHT : Returns rightmost array index
• d’LENGTH : Returns vector size
• d’RANGE : Returns vector range
• d’REVERSE_RANGE: Returns vector range
in reverse order
Example
Consider the following signal:
SIGNAL d : STD_LOGIC_VECTOR (7 DOWNTO 0);
Then:
d'LOW=0, d'HIGH=7, d'LEFT=7, d'RIGHT=0,
d'LENGTH=8, d'RANGE=(7 downto 0),
d'REVERSE_RANGE=(0 to 7)
If the signal is of enumerated type, then:
• d’VAL(pos) : Returns value in the position
specified
• d’POS(value) : Returns position of the
value specified
• d’LEFTOF(value) : Returns value in the
position to the left of the value specified
• d’VAL(row, column) : Returns value in the
position specified; etc
There is little or no synthesis support for
enumerated data type attributes
Signal Attributes
Let us consider a signal s
Then:
• s’EVENT : Returns true when an event occurs
on s
• s’STABLE : Returns true if no event has
occurred on s
• s’ACTIVE : Returns true if s = ‘1’
• s’QUIET <time> : Returns true if no event has
occurred during the time specified
• s’LAST_EVENT : Returns the time elapsed since last
event
• s’LAST_ACTIVE: Returns the time elapsed since
last s=‘1’
• s’LAST_VALUE : Returns the value of s before the
last event; etc.
Example
All four assignments shown below are synthesizable
and equivalent. They return TRUE when an event (a
change) occurs on clk, AND if such event is upward
(in other words, when a rising edge occurs on clk)
IF (clk'EVENT AND clk='1')... -- EVENT attribute
-- used with IF
IF (NOT clk'STABLE AND clk='1')... -- STABLE
--attribute used
-- with IF
WAIT UNTIL (clk'EVENT AND clk='1'); -- EVENT
--attribute used
-- with WAIT
IF RISING_EDGE(clk)... -- call to a function
User-defined Attributes
• VHDL also allows the construction of user-defined
attributes
• To employ a user-defined attribute, it must be
declared and specified
Attribute Declaration:
ATTRIBUTE attribute_name: attribute_type ;
Attribute Specification:
ATTRIBUTE attribute_name OF target_name: class IS value;
where:
attribute_type: any data type (BIT, INTEGER, STD_LOGIC_VECTOR, etc.)
class: TYPE, SIGNAL, FUNCTION, etc.
value: ‘0’, 27, ‘‘00 11 10 01’’, etc.
Example
ATTRIBUTE number_of_inputs: INTEGER;
ATTRIBUTE number_of_inputs OF nand3: SIGNAL IS 3;
...
inputs <= nand3'number_of_inputs; -- attribute call,
-- returns 3
Generics
• As the name suggests, GENERIC is a way
of specifying a generic parameter
• a static parameter that can be easily
modified and adapted to different
applications
• The purpose is to make the code more
flexible and reusable
• must be declared in the ENTITY
• More than one GENERIC parameter can
be specified in an ENTITY
Syntax
GENERIC (parameter_name : parameter_type := parameter_value);
The GENERIC statement below specifies a parameter called n, of type
INTEGER, whose default value is 8. Therefore, whenever n is found in
the ENTITY itself or in the ARCHITECTURE (one or more) that follows,
its value will be assumed to be 8
ENTITY my_entity IS
GENERIC (n : INTEGER := 8; vector: BIT_VECTOR := "00001111");
PORT (...);
END my_entity;
ARCHITECTURE my_architecture OF my_entity IS
...
END my_architecture;
Example
ARCHITECTURE generic_decoder OF decoder IS
BEGIN
PROCESS (ena, sel)
VARIABLE temp1 : STD_LOGIC_VECTOR (x'HIGH DOWNTO 0);
VARIABLE temp2 : INTEGER RANGE 0 TO x'HIGH;
....
Example
Delays in VHDL
• In VHDL, there are three types of delay
that are encountered
– Inertial delay
– Transport delay
– Delta delay
Inertial Delay
• Inertial delay is the default in VHDL
• Behaves similarly to the actual device
• Output signal of the device has inertia,
which must be overcome for the signal to
change value
• The inertial delay model is by far the most
commonly used in all currently available
simulators
Inertial delay prevents prolific propagation of
spikes throughout the circuit
LIBRARY IEEE;
USE IEEE.std_logic_1164.ALL;
ENTITY buf IS
PORT ( a : IN std_logic;
PORT ( b : OUT std_logic);
END buf;
ARCHITECTURE buf OF buf IS
BEGIN
b <= a AFTER 20 ns;
END buf;
Due to inertial delay pulse is
swallowed up
Transport Delay
• It represents a wire delay in which any
pulse, no matter how small, is propagated
to the output signal delayed by the delay
value specified
• Especially useful for modeling delay line
devices, wire delays on a PCB, and path
delays on an ASIC
LIBRARY IEEE;
USE IEEE.std_logic_1164.ALL;
ENTITY delay_line IS
PORT ( a : IN std_logic;
PORT ( b : OUT std_logic);
END delay_line;
ARCHITECTURE delay_line OF delay_line IS
BEGIN
b <= TRANSPORT a AFTER 20 ns;
END delay_line;
Pulse is simply delayed
Delta delay
• These are used since the PC that
processes and simulates a concurrent
phenomenon is basically a sequential
machine
• The simulation program mimics
concurrency by scheduling events in some
order
• Simulation deltas are used to order some
types of events during a simulation
• Specifically, zero delay events must be
ordered to produce consistent results
Circuit that shows the difference!
CLK
D
E
Q'
Q
DFF
CLK
A
B
C
F
D
Zero delay components
CLK=‘1’
A=‘1’
Assumptions
Problem when no delta delay concept is used
CLK
D
E
Q'
Q
DFF
CLK
A
B
C
F
CLK
D
E
Q'
Q
DFF
CLK
A
B
C
F
CLK
D
E
Q'
Q
DFF
CLK
A
B
C
F
1) A becomes 0
2) Evaluate inverter
3) B <= 1
4) Evaluate AND with C=1
5) D<=1
6) Evaluate NAND
7) C<=0CLK
D
E
Q'
Q
DFF
CLK
A
B
C
F
8) Evaluate AND
9) D<=0
CLK
D
E
Q'
Q
DFF
CLK
A
B
C
F
D
Unwanted D assertion
DD
Problem when no delta delay concept is used
CLK
D
E
Q'
Q
DFF
CLK
A
B
C
F
DD
1) A becomes 0
2) Evaluate inverter
3) B <= 1
4) Evaluate NAND
5) C<=0
6) Evaluate AND
7) D<=0
CLK
D
E
Q'
Q
DFF
CLK
A
B
C
F
CLK
D
E
Q'
Q
DFF
CLK
A
B
C
F
D
CLK
D
E
Q'
Q
DFF
CLK
A
B
C
F
Delta delay use
Delta 1
Delta 2
Delta 3
Delta 4
10 ns
11 ns
A<=0
Evaluate inverter
B<=0
Evaluate AND
Evaluate NAND
D<= 1
C<=0
Evaluate AND
D<= 0
To summarize, simulation deltas are
an infinitesimal amount of time
used as a synchronization
mechanism when 0 delay events are
present.
Concurrent Statements
and
Constructs
Combinational vs. Sequential Logic
The output of the circuit
depends solely on the
current inputs
Output does depend on
previous inputs hence
storage elements are
required
Combinational Logic
outputinput
Storage
Elements
Present
State
Next
State
Combinational Logic outputinput
Concurrent Code
• Consider the following
statement:
X = X + Y ;
In conventional software
X and Y are register
locations hence contents
of X and Y are added and
stored in X
Register X Register Y
+
Difference in VHDL
• In VHDL the same statement will mean a
feedback in a purely combinational logic which is
invalid
+
X Y
• VHDL code is inherently concurrent (parallel)
• Only statements placed inside a PROCESS,
FUNCTION, or PROCEDURE are sequential
• Concurrent code is also called dataflow code
• Order does not matter
• We can only build combinational logic circuits
with concurrent code
• Concurrent assignment produces one driver for
each assignment statement
z <= a;
a z
Multiple driver assignment
architecture ABC of XYZ is
signal z,a,b,c,d : std_logic ;
begin
z <= a and b;
z <= c and d;
. . .
?
a
b
c
d
z
Care has to be taken
to handle such conditions
with a hi-impedance state
Concurrent constructs
Next Class
Concurrent Constructs
R.B.Ghongade
Lecture 7
Types of concurrent constructs
• when … else
• with … select
These constructs need not be in the process
when…else
• A concurrent statement which assigns one of
several expressions to a signal, depending on the
values of Boolean conditions which are tested in
sequence
• Equivalent to a process containing an if statement
Syntax
[Label:] Target <= [Options]
Expression [after TimeExpression] when Condition
else
Expression [after TimeExpression] when Condition
else
...
Expression [after TimeExpression] [when Condition];
Where to use ?
architecture – begin – HERE - end
block – begin – HERE - end
generate – begin – HERE - end
Rules:
• The reserved word guarded may only appear in a
signal assignment within a guarded block. A
guarded assignment only executes when the
guard expression on the surrounding block is
true
• An Expression on the right hand side may be
replaced by the reserved word “unaffected”
Synthesis
• Conditional signal assignments are synthesized to
combinational logic
• The Expressions on the right hand side are multiplexed
onto the Target signal
• The resulting logic will be priority encoded, because the
conditions are tested in sequence
Remarks:
• Conditional and selected signal assignments are a
concise way to describe combinational logic in
Register Transfer Level descriptions, although
processes can be easier to read and maintain in some
cases
• A conditional assignment is a neat way to convert from
a Boolean condition to the type Std_logic
Example
z <= a when s1=‘1’
else
b when s2=‘1’
else
c ;
c
b
a
s2
s1
z
MUX21
MUX21
Example (Tri-state Buffer)
architecture tri_buff of tri_buff_part is
begin
out1 <= in1 when control=‘1’
else
‘z’;
end tri_buff ;
in1 out1
control
with…select
• A concurrent statement which assigns
one of several expressions to a signal,
depending on the value of the expression at
the top.
• Equivalent to a process containing a case
statement
Syntax
[Label:] with Expression select
Target <= [Options]
Expression [after TimeExpression] when Choices,
Expression [after TimeExpression] when Choices,
Expression when others;
Where to use ?
architecture – begin – HERE – end
block – begin – HERE – end
generate – begin – HERE – end
Rules:
• Every case of the Expression at the top must be
covered once and only once by the choices
• An Expression on the right hand side may be
replaced by the reserved word “unaffected”
• All possible choices must be enumerated
• “others” clause is important since we have 9-
valued logic
Synthesis
• Selected signal assignments are
synthesized to combinational logic
• The Expressions on the right hand side
are multiplexed onto the Target signal
Remarks:
• Conditional and selected signal
assignments are a good way to describe
combinational logic in Register Transfer
Level descriptions
Example (Multiplexer)
architecture mux41 of mux is -- Assumptions
begin -- a,b,c,d,z are
with control select -- std_logic
z <= a when “00” , -- control is
b when “01” ,-- std_logic_vector(1 downto 0)
c when “10” ,
d when “11” ,
‘Z’ when others ;
end mux41 ;
control
a
b
c
d
z
MUX41
Block
• There are two types of blocks
– Simple
– Guarded
Simple block
• The BLOCK statement, in its simple form,
represents only a way of locally
partitioning the code
• It allows a set of concurrent statements to
be clustered into a BLOCK, with the
purpose of turning the overall code more
readable and more manageable (which
might be helpful when dealing with long
codes)
Syntax
label: BLOCK
[declarative part]
BEGIN
(concurrent statements)
END BLOCK label;
ARCHITECTURE example
...
BEGIN
...
block1: BLOCK
BEGIN
...
END BLOCK block1 ;
...
block2: BLOCK
BEGIN
...
END BLOCK block2 ;
...
END example ;
General form of
architecture using
block for partitioning
• Block can be nested inside another block
Syntax
label1: BLOCK
[declarative part of top block]
BEGIN
[concurrent statements of top block]
label2: BLOCK
[declarative part nested block]
BEGIN
(concurrent statements of nested block)
END BLOCK label2;
[more concurrent statements of top block]
END BLOCK label1;
Guarded block
• A guarded BLOCK is a special kind of
BLOCK, which includes an additional
expression, called guard expression
• A guarded statement in a guarded BLOCK is
executed only when the guard expression is
TRUE
Syntax
label: BLOCK (guard expression)
[declarative part]
BEGIN
(concurrent guarded and unguarded statements)
END BLOCK label;
• Even though only concurrent statements
can be written within a BLOCK, with a
guarded BLOCK even sequential circuits
can be constructed
LIBRARY ieee;
USE ieee.std_logic_1164.all;
ENTITY latch IS
PORT (d, clk: IN STD_LOGIC;
q: OUT STD_LOGIC);
END latch;
ARCHITECTURE latch OF latch IS
BEGIN
b1: BLOCK (clk='1')
BEGIN
q <= GUARDED d;
END BLOCK b1;
END latch;
Latch
LIBRARY ieee;
USE ieee.std_logic_1164.all;
ENTITY DFF IS
PORT (d, clk, rst: IN STD_LOGIC;
q: OUT STD_LOGIC);
END DFF;
ARCHITECTURE DFF OF DFF IS
BEGIN
b1: BLOCK (clk’EVENT AND clk='1')
BEGIN
q <= GUARDED ‘0’ WHEN rst=‘1’ ELSE d;
END BLOCK b1;
END DFF;
Here, a positive-edge sensitive D-type flip-flop, with synchronous
reset, is designed.
In it, clk'EVENT AND clk='1' is the guard expression, while
q <= GUARDED '0‘ WHEN rst='1' is a guarded statement. Therefore,
q<='0' will occur when the guard expression is true and rst is ‘1’
DFF
Homework Problems
1)Generic encoder
2) 8- bit ALU
For ALU in problem 2
sel Operation Function Unit
0000 y <= a Transfer a
Arithmetic
0001 y <= a+1 Increment a
0010 y <= a-1 Decrement a
0011 y <= b Transfer b
0100 y <= b+1 Increment b
0101 y <= b-1 Decrement b
0110 y <= a + b Add a and b
0111 y <= a + b + cin Add a and b with carry
1000 y <= NOT a Complement a
Logic
1001 y <= NOT b Complement b
1010 y <= a AND b AND
1011 y <= a OR b OR
1100 y <= a NAND b NAND
1101 y <= a NOR b NOR
1110 y <= a XOR b XOR
1111 y <= a XNOR b XNOR
3) Priority Encoder
The circuit must encode the address of the input bit of
highest order that is active. ‘‘000’’ should indicate that
there is no request at the input (no bit active)
Expected waveform for Problem 3
Component Instantiation
Next Class
DO NOT MISS
IN ANY CASE !
Component Instantiation
R.B.Ghongade
Lecture 8,9,10
Component
• A component is analogous to a chip socket; it gives an
indirect way to use one hierarchical block within another
• A component is instantiated within an architecture, and
is associated with a (lower level) entity and architecture
during elaboration using information from a
configuration.
• A component declaration is similar in form to an entity
declaration, in that it includes the required ports and
parameters of the component
• The difference is that it refers to a design described in a
separate VHDL file
• The ports and parameters in the component declaration
may be a subset of those in the component file, but they
must have the same names
Component can be declared in the
main code itself
Component can be declared in a
package
Syntax :
COMPONENT component_name
GENERIC ( parameter_name : string := default_value ;
parameter_name : integer := default_value);
PORT (input_name, input_name : IN STD_LOGIC;
bidir_name, bidir_name : INOUT STD_LOGIC;
output_name, output_name : OUT STD_LOGIC);
END COMPONENT;
Where :
package - <HERE> - end
architecture - is - <HERE> - begin - end
block - <HERE> - begin - end
generate - <HERE> - begin - end
Rules:
• For default configuration, the component
name must match the name of the
corresponding entity to be used in its
place, and generics and ports must also
match in name, mode and type
Synthesis:
• A component without a corresponding
design entity is synthesized as a black
box
In VHDL'93, components are not necessary. It is
possible instead to directly instantiate an entity
within an architecture.
Example
component Counter
generic (N: INTEGER);
port (Clock, Reset, Enable: in Std_logic;
Q: buffer Std_logic_vector (N-1 downto 0));
end component ;
Instantiation
• A concurrent statement used to define the
design hierarchy by making a copy of a
lower level design entity within an
architecture
• In VHDL'93, a direct instantiation of an
entity bypasses the component and
configuration
Syntax:
InstanceLabel: [component] ComponentName
[GenericMap] [PortMap];
InstanceLabel: entity
EntityName[(ArchitectureName)]
[GenericMap] [PortMap];
InstanceLabel: configuration ConfigurationName
[GenericMap] [PortMap];
Where:
architecture – begin - <HERE> - end
block – begin - <HERE> - end
generate – begin - <HERE> - end
Rules:
• An entity, architecture or configuration
must be compiled into a library before the
corresponding instance can be compiled
• However, an instance of a component can
be compiled before the corresponding
design entity has even been written
Example :
G1: NAND2 generic map (1.2 ns)
port map (N1, N2, N3);
G2: entity WORK.Counter(RTL)
port map (Clk, Rst, Count);
Generic Map
• Used to define the values of generics
• Usually given in an Instance, but may also
appear in a configuration
Syntax
generic map ([Formal =>] Actual, ...)
Formal = {either} Name FunctionCall
Actual = Expression
Where :
Label : ComponentName <HERE> port map (…);
for - use - <HERE> port map (…)
block – generic (…); <HERE> ; port – begin - end
Rules :
The two forms of syntax (ordered list or
explicitly named choices) can be mixed, but the
ordered list must come before the named choices
A generic map does not end with a semicolon!
Example:
architecture Structure of Ent is
component NAND2
generic (TPLH, TPHL: TIME := 0 NS);
port (A, B: in STD_LOGIC;
F : out STD_LOGIC);
end component;
begin
G1: NAND2 generic map (1.9 NS, 2.8 NS)
port map (N1, N2, N3);
G2: NAND2 generic map (TPLH => 2 NS, TPHL => 3 NS)
port map (N4, N5, N6);
end Structure;
Port Map
• A port map is typically used to define the
interconnection between instances in a
structural description (or netlist)
• A port map maps signals in an
architecture to ports on an instance within
that architecture
• Port maps can also appear in a
configuration or a block
Syntax:
port map ([Formal =>] Actual, ...);
Formal = {either} Name FunctionCall
Actual = {either} Name FunctionCall open
Where:
Label : ComponentName generic map (…) <HERE>;
for - use - generic map (…) <HERE>;
block - port (…) ; <HERE>; - begin - end
Rules:
• The two forms of syntax (ordered list or explicitly named
ports) can be mixed, but the ordered list must come
before the named ports
• Within an instance, the formals are ports on the
component or entity being instanced, the actuals are
signals visible in the architecture containing the instance
• Within a configuration, the formals are ports on the
entity, the actuals are ports on the component
• If the actual is a conversion function, this is called
implicitly as values are passed in
• If the formal is a conversion function, this is called
implicitly as values are passed out
Use the port names rather than order to improve readability and
reduce the risk of making connection errors
Example:
component COUNTER
port (CLK, RESET: in Std_logic;
UpDown: in Std_logic := '0';-- default value
Q: out Std_logic_vector(3 downto 0));
end component;
...
-- Positional association...
G1: COUNTER port map (Clk32MHz, RST, open, Count);
-- Named association (order doesn't matter)...
G2: COUNTER port map ( RESET => RST,
CLK => Clk32MHz,
Q(3) => Q2MHz,
Q(2) => open, -- unconnected
Q(1 downto 0) => Cnt2,
UpDown => open);
Top Level Entity and Lower Level Entity
TOP LEVEL ENTITY
Clk32MHz Q2MHz
Cnt2
RST
COUNT
COUNTER
(LOWER LEVEL ENTITY)
CLK
RESET
Q
Updown
TOP LEVEL ENTITY
Clk32MHz
Q2MHz
Cnt2
RST
COUNT
G1
CLK
RESET
Q
Updown
G2
CLK
RESET
Q(3)
Updown
Q(0)
CLK => Clk32MHz
Q(3) => Q2MHz
UpDown => open
RESET => RST
A still simpler example
entity ND4 is
port (in1,in2,in3,in4 : in std_logic ;
z : out std_logic);
end ND4;
architecture ND4_CI of ND4 is
component ND2
port (a , b : in std_logic;
c : out std_logic);
end component ;
signal temp1, temp2 : std_logic;
begin
U1 : ND2 port map (a => in1 , b => in2 , c => temp1);
U2 : ND2 port map (a => in3 , b => in4 , c => temp2);
U3 : ND2 port map (a => temp1 , b => temp2 , c => z);
end ND4_CI ;
infers…
ND4
U1
U3
U2
IN1
IN2
IN3
IN4
Z
a
a
b
b
a
b
c
c
c
c => temp1 for U1
a => temp1 for U3
c => temp2 for U2
b => temp2 for U3
Generate statement
• A concurrent statement used to create
regular structures or conditional structures
during elaboration
• Used to create multiple copies of
components , processes or blocks
• It provides a compact description of
regular structures such as memories ,
registers and counters
• Two flavours of generate statement are:
– for … generate
• Number of copies is determined by a discrete
range
– if … generate
• Zero or one copy is made conditionally
• Range must be a computable integer in any
of the following forms:
– integer_expression to integer_expression
– integer_expression downto integer_expression
– Each integer_expression evaluates to an integer
Syntax :
Label: for ParameterName in Range generate
[Declarations...
begin]
ConcurrentStatements...
end generate [Label];
Label: if Condition generate
[Declarations...
begin]
ConcurrentStatements...
end generate [Label];
Where:
architecture – begin - <HERE> - end
block – begin - <HERE> - end
generate – begin - <HERE> - end
Rules :
• The Range and Condition must both be
static, i.e. they cannot include signals
• The Label at the beginning of the generate
statement cannot be omitted
Synthesis:
• Synthesis is straightforward, but not all
synthesis tools support generate!
Example:
architecture ABC of full_add4 is
component full_add
port (PA , PB , PC : in std_logic ;
PCOUT , PSUM : out std_logic) ;
end component ;
signal c: std_logic_vector(4 downto 0);
begin
c(0) <= cin ; -- cin is declared in entity
GK : for k in 3 downto 0 generate
FA :full_add port map(A(k),B(k),C(k),C(k+1),SUM(k);
end generate GK ;
cout <= c(4) ; -- cout is declared in entity
end ABC ;
infers…
FA2
A(2) B(2)
C(2)
SUM(2)
FA3
A(3) B(3)
Cout
SUM(3)
FA0
A(0) B(0)
Cin
C(1)
SUM(0)
FA1
A(1) B(1)
SUM(1)
C(3)
architecture SHIFTER_ARCH of SHIFTER is
component DFF
port (D , CLK : in std_logic ;
Q : out std_logic) ;
end component ;
begin
GK : for k in 0 to 3 generate
GK0 : IF k=0 generate
DFILPFLOP : DFF port map (count , clock , Q(k));
end generate GK0 ;
GK1_3 : if k > 0 generate
DFILPFLOP : DFF port map (Q(k-1), clock , Q(k));
end generate GK1_3 ;
end generate GK ;
end SHIFTER_ARCH ;
Another example
infers…
DF1DF0 DF3DF2
CLOCK
COUNT
Q(0) Q(1) Q(2) Q(3)
Ways to describe a circuit!
• Three types of descriptions possible with
VHDL
– Structural
– Dataflow
– Behavioral
Structural Method
• At the structural level, which is the lowest level, you
have to first manually design the circuit.
• Use VHDL to specify the components and gates that
are needed by the circuit and how they are
connected together by following your circuit exactly
• Synthesizing a structural VHDL description of a
circuit will produce a netlist that is exactly like your
original circuit
• The advantage of working at the structural level is
that you have full control as to what components are
used and how they are connected.
• But you need to first come up with the circuit and so
the full capabilities of the synthesizer are not utilized
Dataflow Method
• At the dataflow level, you use the built-in logical
functions of VHDL in signal assignment statements
to describe a circuit, which again you have to first
design manually
• Boolean functions that describe a circuit can be
easily converted to signal assignment statements
using the built-in logical functions
• The only drawback is that the built-in logical
functions such as the AND and OR function only
take two operands. This is like having only 2-input
gates to work with !
All the statements use in the structural and dataflow
level are executed concurrently
Behavioral Method
• Describing a circuit at the behavioral level is
most similar to writing a computer program
• You have all the standard high-level
programming constructs such as the FOR
LOOP, WHILE LOOP, IF THEN ELSE,
CASE, and variable assignments
• The statements are enclosed in a process
block and are executed sequentially
Example
BCD to 7- segment display decoder
a
b
c
d
e
f
g
BCD to 7-segment
display decoder
I3
I2
I1
I0
segs(6) {seg 'a'}
segs(5) {seg 'b'}
segs(4) {seg 'c'}
segs(3) {seg 'd'}
segs(2) {seg 'e'}
segs(1) {seg 'f'}
segs(0) {seg 'g'}
Truth-table
Logic Equations
2 1 0
3 1 2 0
'
'
2 1 0
' ' ' ' '
1 0 2 0 2 1 2 1 0
' ' '
1 0 2 0
' ' ' '
3 2 1 2 0 1 0
'
3 2 1 1 0
( )
( )
( )
a I I I I
b I I I
c I I I
d I I I I I I I I I
e I I I I
f I I I I I I I
g I I I I I
= + +
= +
= + +
= + + +
= +
= + + +
= + ⊕ +
Logic gates
Structural VHDL description
ENTITY myxnor2 IS PORT(i1, i2: IN BIT;o: OUT BIT);
END myxnor2;
ARCHITECTURE Dataflow OF myxnor2 IS
BEGIN
o <= not(i1 XOR i2);
END Dataflow;
ENTITY myxor2 IS PORT(i1, i2: IN BIT;o: OUT BIT);
END myxor2;
ARCHITECTURE Dataflow OF myxor2 IS
BEGIN
o <= i1 XOR i2;
END Dataflow;
ENTITY myand2 IS PORT(i1, i2: IN BIT;o: OUT BIT);
END myand2;
ARCHITECTURE Dataflow OF myand2 IS
BEGIN
o <= i1 AND i2;
END Dataflow;
ENTITY myand3 IS PORT(i1, i2, i3: IN BIT; o: OUT BIT);
END myand3;
ARCHITECTURE Dataflow OF myand3 IS
BEGIN
o <= (i1 AND i2 AND i3);
END Dataflow;
ENTITY myor2 IS PORT(i1, i2: IN BIT;o: OUT BIT);
END myor2;
ARCHITECTURE Dataflow OF myor2 IS
BEGIN
o <= i1 OR i2;
END Dataflow;
ENTITY myor3 IS PORT(i1, i2, i3: IN BIT;o: OUT BIT);
END myor3;
ARCHITECTURE Dataflow OF myor3 IS
BEGIN
o <= i1 OR i2 OR i3;
END Dataflow;
ENTITY myor4 IS PORT(i1, i2, i3, i4: IN BIT; o: OUT BIT);
END myor4;
ARCHITECTURE Dataflow OF myor4 IS
BEGIN
o <= i1 OR i2 OR i3 OR i4;
END Dataflow;
ENTITY inv IS PORT (i: IN BIT; o: OUT BIT);
END inv;
ARCHITECTURE Dataflow OF inv IS
BEGIN
o <= not i;
END Dataflow;
LIBRARY ieee;
USE ieee.std_logic_1164.all;
ENTITY bcd IS PORT(i0, i1, i2, i3: IN BIT;
a, b, c, d, e, f, g: OUT BIT);
END bcd;
ARCHITECTURE Structural OF bcd IS
COMPONENT inv PORT (i: IN BIT ;o: OUT BIT);
END COMPONENT;
COMPONENT myand2 PORT(i1, i2: IN BIT;o: OUT BIT);
END COMPONENT;
COMPONENT myand3 PORT(i1, i2, i3: IN BIT;o: OUT BIT);
END COMPONENT;
COMPONENT myor2 PORT(i1, i2: IN BIT;o: OUT BIT);
END COMPONENT;
COMPONENT myor3 PORT(i1, i2, i3: IN BIT;o: OUT BIT);
END COMPONENT;
COMPONENT myor4 PORT(i1, i2, i3, i4: IN BIT;o: OUT BIT);
END COMPONENT;
COMPONENT myxnor2 PORT(i1, i2: IN BIT;o: OUT BIT);
END COMPONENT;
COMPONENT myxor2 PORT(i1, i2: IN BIT;o: OUT BIT);
END COMPONENT;
SIGNAL j,k,l,m,n,o,p,q,r,s,t,u,v,w,x,y,z: BIT;
BEGIN
U1: INV port map(i2,j);
U2: INV port map(i1,k);
U3: INV port map(i0,l);
U4: myXNOR2 port map(i2, i0, z);
U5: myOR3 port map(i3, i1, z, a);
U6: myXNOR2 port map(i1, i0, y);
U7: myOR2 port map(j, y, b);
U8: myOR3 port map(i2, k, i0, c);
U9: myAND2 port map(i1, l, x);
U10: myAND2 port map(j, l, w);
U11: myAND2 port map(j, i1, v);
U12: myAND3 port map(i2, k, i0, t);
U13: myOR4 port map(x, w, v, t, d);
U14: myAND2 port map(i1, l, s);
U15: myAND2 port map(j, l, r);
U16: myOR2 port map(s, r, e);
U17: myAND2 port map(i2, k, q);
U18: myAND2 port map(i2, l, p);
U19: myAND2 port map(k, l, o);
U20: myOR4 port map(i3, q, p, o, f);
U21: myXOR2 port map(i2, i1, n);
U22: myAND2 port map(i1, l, m);
U23: myOR3 port map(i3, n, m, g);
END Structural;
Dataflow VHDL description
LIBRARY ieee;
USE ieee.std_logic_1164.all;
ENTITY bcd IS PORT (
I: IN STD_LOGIC_VECTOR (3 DOWNTO 0);
Segs: OUT std_logic_vector (1 TO 7));
END bcd;
ARCHITECTURE Dataflow OF bcd IS
BEGIN
Segs(1) <= I(3) OR I(1) OR NOT (I(2) XOR I(0)); -- seg a
Segs(2) <= (NOT I(2)) OR NOT (I(1) XOR I(0)); -- seg b
Segs(3) <= I(2) OR (NOT I(1)) OR I(0); -- seg c
Segs(4) <= (I(1) AND NOT I(0)) OR (NOT I(2) AND NOT I(0)) -- seg d
OR (NOT I(2) AND I(1)) OR (I(2) AND NOT I(1) AND I(0));
Segs(5) <= (I(1) AND NOT I(0)) OR (NOT I(2) AND NOT I(0)); -- seg e
Segs(6) <= I(3) OR (I(2) AND NOT I(1)) -- seg f
OR (I(2) AND NOT I(0)) OR (NOT I(1) AND NOT I(0));
Segs(7) <= I(3) OR (I(2) XOR I(1)) OR (I(1) AND NOT I(0)); -- seg g
END Dataflow;
Behavioral VHDL description
library IEEE;
use IEEE.STD_LOGIC_1164.all;
entity BCD is
port( I : in STD_LOGIC_VECTOR(3 downto 0);
segs : out STD_LOGIC_VECTOR(6 downto 0) );
end BCD;
architecture Behavioral of BCD is
begin
with I select
Segs <= "1111110" when "0000",
"0110000" when "0001",
"1101001" when "0010",
"1111001" when "0011",
"0110011" when "0100",
"1011011" when "0101",
"1011111" when "0110",
"1110000" when "0111",
"1111111" when "1000",
"1110011" when "1001",
"0000000" when others;
end Behavioral;
Output
Equations for carry_generate(G) and
carry_propagate(P) for ALU 74181
Carry Lookahead Logic
xi
yi
xi-1
x0
yi-1
y0
c0
ci
hsi
si
gi= xi . yi
pi=xi + yi
ci+1= gi + pi . ci
Assignment No 3
c1= g0 + p0 . c0
c2= g1 + p1 . g0 + p1.p0.c0
c3= g2 + p2 . g1 + p2.p1.g0+p2.p1.p0.c0
c4= g3 + p3 . g2 + p3.p2.g1+p3.p2.p1.g0+p3.p2.p1.p0.c0
Additional Information
G_L= (g3+p3.g2+p3.p2.g1+p3.p2.p1.g0)’
P_L=(p3.p2.p1.p0)’
Implement the Carry_Generate and Carry_Propagate
outputs also to complete the ALU assignment
Equations for implementation of G_L , P_L
outputs
Sequential Statements
Next Class
‘generate’d doubt !
fulladder
GK.0.FA
fulladder
GK.3.FA
fulladder
GK.2.FA
fulladder
GK.1.FA
COUT
[4]
SUM[3:0]
[3:0]
Cin
B[3:0] [3:0]
A[3:0] [3:0]
[0]
PA
[0]
PB
PC
[1]
PCOUT
[0]
PSUM
[3]
PA
[3]
PB
[3]
PC
[4]
PCOUT
[3]
PSUM
[2]
PA
[2]
PB
[2]
PC
[3]
PCOUT
[2]
PSUM
[1]
PA
[1]
PB
[1]
PC
[2]
PCOUT
[1]
PSUM
fulladder
GK.3.FAfulladder
GK.0.FA
fulladder
GK.1.FA
fulladder
GK.2.FA
COUT
[4]
SUM[3:0]
[3:0]
Cin
B[3:0] [3:0]
A[3:0] [3:0]
[3]
PA
[3]
PB
[3]
PC
[4]
PCOUT
[3]
PSUM
[0]
PA
[0]
PB
PC
[1]
PCOUT
[0]
PSUM
[1]
PA
[1]
PB
[1]
PC
[2]
PCOUT
[1]
PSUM
[2]
PA
[2]
PB
[2]
PC
[3]
PCOUT
[2]
PSUM
GK : for k in 3 downto 0 generate GK : for k in 0 to 3 generate=
Sequential Statements
R.B.Ghongade
Lecture 12
Sequential Statements
• VHDL code is inherently concurrent
• Sections of code that are executed
sequentially are :
– PROCESS
– FUNCTION
– PROCEDURE
• One important aspect of sequential code is that it is
not limited to sequential logic
• We can build sequential circuits as well as
combinational circuits
• Sequential code is also called behavioral code
• Thus a PROCESS is a concurrent statement which
describes behaviour
• Sequential statements are allowed only
inside PROCESSES, FUNCTIONS, or
PROCEDURES
• Sequential statements are:
– IF
– WAIT
– CASE
– LOOP
• VARIABLES are also restricted to be used
in sequential code only
VARIABLE can never be global, so its value
can not be passed out directly
SIGNALS and VARIABLES revisited !
• VHDL has two ways of passing non-static values around:
by means of a SIGNAL or by means of a VARIABLE
• A SIGNAL can be declared in a PACKAGE, ENTITY or
ARCHITECTURE (in its declarative part), while a
VARIABLE can only be declared inside a piece of
sequential code
• SIGNAL is global while VARIABLE is local
• The value of a VARIABLE can never be passed out of
the PROCESS directly; if necessary, then it must be
assigned to a SIGNAL
• Update of VARIABLE is immediate whereas new value
for SIGNAL is generally only guaranteed to be available
after the conclusion of the present run of the PROCESS
• Assignment operator for SIGNAL is “<= “ while that for
VARIABLE is “ : = “
Process
• A PROCESS is a sequential section of
VHDL code
• It is characterized by the presence of IF,
WAIT, CASE, or LOOP, and by a
sensitivity list (except when WAIT is used)
• A PROCESS must be installed in the main
code, and is executed every time a signal
in the sensitivity list changes (or the
condition related to WAIT is fulfilled)
Syntax
[label:] [postponed] PROCESS (sensitivity list)
[VARIABLE name type [range] [:= initial_value;]]
BEGIN
(sequential code)
END [postponed] PROCESS [label];
entity - begin - <HERE> - end
architecture - begin - <HERE> - end
block - begin - <HERE> - end
generate - begin - <HERE> - end
Where “POSTPONED”
is a reserved
VHDL word
Rules
• A process must contain either a sensitivity
list or wait statements, but not both
• Every process executes once during
initialization, before simulation starts
• A postponed process is not executed until
the final simulation cycle of a particular
simulation time, and thus sees the stable
values of signals and variables
A process with neither a sensitivity list nor a wait
will loop forever !
• To construct a synchronous circuit,
monitoring a signal (clock, for example) is
necessary
• A common way of detecting a signal change
is by means of the EVENT attribute
• For instance, if clk is a signal to be
monitored, then clk ’ EVENT returns TRUE
when a change on clk occurs (rising or
falling edge)
Using EVENT attribute
IF construct
• A sequential statement which executes one
branch from a set of branches dependent
upon the conditions, which are tested in
sequence
Syntax
[Label:] if Condition then
SequentialStatements...
[elsif Condition then
SequentialStatements...]
... {any number of elsif parts}
[else
SequentialStatements...]
end if [Label];
Be careful about the spelling of elsif and end if
Synthesis
• Assignments within if statements generally
synthesize to multiplexers
• Incomplete assignments, where outputs remain
unchanged for certain input conditions,
synthesize to transparent latches in unclocked
processes, and to flip-flops in clocked
processes
• In some circumstances, nested if statements
synthesize to multiple logic levels. This can be
avoided by using a case statement instead
• A set of elsif branches can be used to
impart priority to the conditions tested first
• To decode a value without giving priority to
certain conditions, use a case statement
instead
Example
IF (x<y) THEN temp:="11111111";
ELSIF (x=y AND w='0') THEN
temp := "11110000";
ELSE temp:=(OTHERS =>'0');
D Flip-Flop with asynchronous reset
• A D-type flip-flop is the most basic building block
in sequential logic circuits. In it, the output must
copy the input at either the positive or negative
transition of the clock signal (rising or falling
edge)
If rst = ‘1’, then the output
must be q = ‘0’ ,regardless of
the status of clk.
Otherwise, the output must
copy the input (that is, q = d)
at the positive edge of clk
LIBRARY ieee;
USE ieee.std_logic_1164.all;
ENTITY dff IS
PORT (d, clk, rst: IN STD_LOGIC;
q: OUT STD_LOGIC);
END dff;
ARCHITECTURE behavior OF dff IS
BEGIN
PROCESS (clk, rst)
BEGIN
IF (rst='1') THEN
q <= '0';
ELSIF (clk'EVENT AND clk='1') THEN
q <= d;
END IF;
END PROCESS;
END behavior;
Output
q
R
q
rst
clk
d Q[0]D[0]
q
R
q
rst
clk
d Q[0]D[0]
Changing the statement
ELSIF (clk'EVENT AND clk=‘0') THEN
One Digit counter example
Progressive 1-digit
decimal counter
(0 -> 9 ->0)
Single bit input (clk)
and a 4-bit output
(digit).
LIBRARY ieee;
USE ieee.std_logic_1164.all;
ENTITY counter IS
PORT (clk : IN STD_LOGIC; digit : OUT INTEGER
RANGE 0 TO 9);
END counter;
ARCHITECTURE counter OF counter IS
BEGIN
count: PROCESS (clk)
VARIABLE temp : INTEGER RANGE 0 TO 10;
BEGIN
IF (clk'EVENT AND clk='1') THEN
temp := temp + 1;
IF (temp=10) THEN temp := 0;
END IF;
END IF;
digit <= temp;
END PROCESS count;
END counter;
Output
In a counter like circuits always use comparison
statements with constant values
This ensures simple comparator inference as against
full comparator inference for comparison with unknown
values
digit[3:0]
clk
[3]
[30]
[1]
[32]
[3]
[30]
[1]
[32]
un2_temp[29:32]
+
count.un1_temp
<
temp_3[1]
0
1
temp_3[3]
0
1
count.temp[3:0]
[3:0]
[29:32]1
[29:32]
1010 0
[1][31]
0
[3][29]
[3:0]
Q[3:0]D[3:0]
[3]
[1]
[32]
[29]
[31:32]
[3]
[1]
[32]
un2_temp[29:32]
+
count.un9_temp temp_3[1]
0
1
temp_3[3]
0
1
count.temp[3:0]
[3:0]
1
[0]
[31]
[29]
[31]
[1]0
[29]
[3]0
[3:0]
Q[3:0]D[3:0]
digit[3:0]
clk
Changing the statement IF (temp>=10) THEN temp := 0;
Extra Hardware
Sequential Statements cont..
Next Class
Sequential Statements II
R.B.Ghongade
Lecture 13
Wait statement
• The operation of WAIT is sometimes
similar to that of IF
• PROCESS cannot have a sensitivity list
when WAIT is employed
• Three flavours of WAIT statements are:
– WAIT UNTIL
– WAIT ON
– WAIT FOR
Syntax
WAIT UNTIL signal_condition;
• The WAIT UNTIL statement accepts only one signal,
thus being more appropriate for synchronous code
than asynchronous
• Since the PROCESS has no sensitivity list in this
case, WAIT UNTIL must be the first statement in the
PROCESS
• The PROCESS will be executed every time the
condition is met
Example ( 8-bit register )
PROCESS -- no sensitivity list
BEGIN
WAIT UNTIL (clk'EVENT AND clk='1');
IF (rst='1') THEN
op <= "00000000";
ELSIF (clk'EVENT AND clk='1') THEN
op <= inp;
END IF;
END PROCESS;
Output and Inference
op[7:0]
op[7:0]
[7:0]
inp[7:0] [7:0]
rst
clk
[7:0]
Q[7:0]
[7:0]
D[7:0]
R
Output changes
only with clk
Syntax
WAIT ON signal1 [, signal2, ... ];
• The WAIT ON statement accepts multiple
signals
• The PROCESS is put on hold until any of the
signals listed changes
Example ( 8-bit register )
PROCESS
BEGIN
WAIT ON clk, rst;
IF (rst='1') THEN
op <= "00000000";
ELSIF (clk'EVENT AND clk='1') THEN
op <= inp;
END IF;
END PROCESS;
Output and Inference
op[7:0]
R
op[7:0]
[7:0]
inp[7:0] [7:0]
rst
clk
[7:0]
Q[7:0]
[7:0]
D[7:0]
Output changes
with clk and rst
DFF revisited with WAIT!
LIBRARY ieee;
USE ieee.std_logic_1164.all;
ENTITY dff IS
PORT (d, clk, rst: IN STD_LOGIC; q: OUT
STD_LOGIC);
END dff;
ARCHITECTURE dff OF dff IS
BEGIN
PROCESS
BEGIN
WAIT ON rst, clk;
IF (rst='1') THEN
q <= '0';
ELSIF (clk'EVENT AND clk='1') THEN
q <= d;
END IF;
END PROCESS;
END dff;
Output and Inference
q
R
q
rst
clk
d Q[0]D[0]
Infers exactly the same hardware as the earlier design
As a homework problem repeat the one digit counter with WAIT statement
Syntax
WAIT FOR time;
• WAIT FOR is intended for simulation only
(waveform generation for test-benches)
Case statement
• CASE is another statement intended exclusively
for sequential code
• The CASE statement (sequential) is very similar
to WHEN (combinational)
• All permutations must be tested, so the keyword
OTHERS is often helpful
• Another important keyword is NULL (the
counterpart of UNAFFECTED), which should be
used when no action is to take place
• CASE allows multiple assignments for each test
condition while WHEN allows only one
[Label:] case Expression is
when Choices =>
SequentialStatements...
when Choices =>
SequentialStatements...
... {any number of when parts}
end case [Label];
Syntax
Choices = Choice | Choice | ...
Choice = {either}
ConstantExpression
Range
others {the last branch}
Where
process – begin - <HERE> - end
function – begin - <HERE> - end
procedure – begin - <HERE> - end
if – then - <HERE> - elsif – then - <HERE>-
else - <HERE> - end
case - => - <HERE> - when - => - <HERE>-
end
loop-<HERE>-end
Rules
• The Expression must not be enclosed in
parenthesis
• The type of the Expression must be
enumeration, integer, physical, or a one
dimensional array
• Every case of the Expression must be
covered once and only once by the
Choices
Synthesis
• Assignments within case statements
generally synthesize to multiplexers
• Incomplete assignments (i.e. where
outputs remain unassigned for certain
input conditions) in unclocked processes
synthesize to transparent latches
• Incomplete assignments in clocked
processes synthesize to recirculation
around registers
Example
case ADDRESS is
when 0 => -- Select a single value
A <= '1';
when 1 =>
A <= '1'; -- More than one statement in a
-- branch
B <= '1';
when 2 to 15 => -- Select a range of ADDRESS
-- values
C <= '1';
when 16 | 20 | 24 => -- Pick out several
-- ADDRESS values
B <= '1';
C <= '1';
D <= '1';
when others => -- Mop up the rest
null;
end case;
2 - digit counter with SSD output
COUNTER
a
b
c
d
e
f
g
a
b
c
d
e
f
g
DIGIT 1
7 BITS
CLK
RST
DIGIT 2
Progressive 2-digit decimal counter
(0-> 99-> 0) , with external asynchronous
reset plus binary-coded decimal (BCD) to
seven-segment display (SSD) conversion
LIBRARY ieee;
USE ieee.std_logic_1164.all;
ENTITY counter IS
PORT (clk, rst : IN STD_LOGIC;
digit1, digit2 : OUT STD_LOGIC_VECTOR (6 DOWNTO 0));
END counter;
ARCHITECTURE counter OF counter IS
BEGIN
PROCESS (clk, rst)
VARIABLE temp1: INTEGER RANGE 0 TO 10;
VARIABLE temp2: INTEGER RANGE 0 TO 10;
BEGIN
IF (rst='1') THEN
temp1 := 0;
temp2 := 0;
ELSIF (clk'EVENT AND clk='1') THEN
temp1 := temp1 + 1;
IF (temp1=10) THEN
temp1 := 0;
temp2 := temp2 + 1;
IF (temp2=10) THEN
temp2 := 0;
END IF;
END IF;
END IF;
CASE temp1 IS
WHEN 0 => digit1 <= "1111110"; --7E
WHEN 1 => digit1 <= "0110000"; --30
WHEN 2 => digit1 <= "1101101"; --6D
WHEN 3 => digit1 <= "1111001"; --79
WHEN 4 => digit1 <= "0110011"; --33
WHEN 5 => digit1 <= "1011011"; --5B
WHEN 6 => digit1 <= "1011111"; --5F
WHEN 7 => digit1 <= "1110000"; --70
WHEN 8 => digit1 <= "1111111"; --7F
WHEN 9 => digit1 <= "1111011"; --7B
WHEN OTHERS => NULL;
END CASE;
CASE temp2 IS
WHEN 0 => digit2 <= "1111110"; --7E
WHEN 1 => digit2 <= "0110000"; --30
WHEN 2 => digit2 <= "1101101"; --6D
WHEN 3 => digit2 <= "1111001"; --79
WHEN 4 => digit2 <= "0110011"; --33
WHEN 5 => digit2 <= "1011011"; --5B
WHEN 6 => digit2 <= "1011111"; --5F
WHEN 7 => digit2 <= "1110000"; --70
WHEN 8 => digit2 <= "1111111"; --7F
WHEN 9 => digit2 <= "1111011"; --7B
WHEN OTHERS => NULL;
END CASE;
END PROCESS;
END counter;
Output
Inference
DO NOT TRY TO WORK OUT HOW
THIS CIRCUIT WORKS !!!
Test !!!
Next Class
Sequential Statements III
R.B.Ghongade
Lecture 14
Loop statement
• LOOP is useful when a piece of code must
be instantiated several times
• Like IF, WAIT, and CASE, LOOP is
intended exclusively for sequential code,
so it too can only be used inside a
PROCESS, FUNCTION, or
PROCEDURE.
• There are several ways of using LOOP
• A loop is an infinite loop (and thus an
error) unless it contains an exit or wait
statement
FOR / LOOP: The loop is repeated a fixed number of
times
[label:] FOR identifier IN range LOOP
(sequential statements)
END LOOP [label];
WHILE / LOOP: The loop is repeated until a condition no
longer holds
[label:] WHILE condition LOOP
(sequential statements)
END LOOP [label];
[label:] LOOP
(SequentialStatements)
END LOOP [label];
Syntax
EXIT: Used for ending the loop
[label:] EXIT [label] [WHEN condition];
NEXT: Used for skipping loop steps
[label:] NEXT [loop_label] [WHEN condition];
WAIT : Continue looping until..
FOR i IN 0 TO 5 LOOP
x(i) <= enable AND w(i+2);
y(0, i) <= w(i);
END LOOP;
The loop will be repeated
unconditionally until i
reaches 5
(that is, six times)
• One important remark regarding FOR /
LOOP is that both limits of the range must
be static
• Thus a declaration of the type
"FOR i IN 0 TO choice LOOP",
where choice is an input (non-static)
parameter, is generally not synthesizable
Example of FOR / LOOP:
WHILE (i < 10) LOOP
WAIT UNTIL clk'EVENT AND clk='1';
(other statements)
END LOOP;
In this example, LOOP
will keep repeating
while i < 10
Example of WHILE / LOOP:
LOOP
WAIT UNTIL Clock = '1';
EXIT WHEN Reset = '1';
Div2 <= NOT Div2;
END LOOP;
Example of WAIT in LOOP :
FOR i IN data'RANGE LOOP
CASE data(i) IS
WHEN '0' => count:=count+1;
WHEN OTHERS => EXIT;
END CASE;
END LOOP;
Example of EXIT :
EXIT implies not an escape from the current iteration of
the loop, but rather a definite exit (that is, even if i is still
within the data range, the LOOP statement will be
considered as concluded).
In this case, the loop will end as soon as a value
different from ‘0’ is found in the data vector
FOR i IN 0 TO 15 LOOP
NEXT WHEN i=skip; -- jumps to next iteration
(...)
END LOOP;
Example with NEXT:
NEXT causes LOOP to skip one iteration
when i = skip
Synthesis
• Not generally synthesizable. Some tools
do allow loops containing wait statements
to describe implicit finite state machines,
but this is not a recommended practice
Example : 8-bit unsigned Carry Ripple Adder
+
a b
s
cin cout
+
a0 b0
c0 c1
s0
+
a1 b1
c2
+
a7 b7
s7
c8
s1
c7cin cout
a b
s
TOP LEVEL
LOWERLEVEL
sj = aj XOR bj XOR cj
cj+1 = (aj AND bj) OR (aj AND cj) OR (bj AND cj)
LIBRARY ieee;
USE ieee.std_logic_1164.all;
ENTITY adder IS
GENERIC (length : INTEGER := 8);
PORT ( a, b: IN STD_LOGIC_VECTOR (length-1 DOWNTO 0);
cin: IN STD_LOGIC; s: OUT STD_LOGIC_VECTOR (length-1 DOWNTO 0);
cout: OUT STD_LOGIC);
END adder;
ARCHITECTURE adder OF adder IS
BEGIN
PROCESS (a, b, cin)
VARIABLE carry : STD_LOGIC_VECTOR (length DOWNTO 0);
BEGIN
carry(0) := cin;
FOR i IN 0 TO length-1 LOOP
s(i) <= a(i) XOR b(i) XOR carry(i);
carry(i+1) := (a(i) AND b(i)) OR (a(i) AND
carry(i)) OR (b(i) AND carry(i));
END LOOP;
cout <= carry(length);
END PROCESS;
END adder;
Output
Example: Leading Zeros
The circuit should count the
number of leading zeros in
a binary vector, starting from
the left end
0 0 0 1 1 0 0 0
0123
LIBRARY ieee;
USE ieee.std_logic_1164.all;
ENTITY LeadingZeros IS
PORT ( data: IN STD_LOGIC_VECTOR (7 DOWNTO 0);
zeros: OUT INTEGER RANGE 0 TO 8);
END LeadingZeros;
ARCHITECTURE behavior OF LeadingZeros IS
BEGIN
PROCESS (data)
VARIABLE count: INTEGER RANGE 0 TO 8;
BEGIN
count := 0;
FOR i IN data'RANGE LOOP
CASE data(i) IS
WHEN '0' => count := count + 1;
WHEN OTHERS => EXIT;
END CASE;
END LOOP;
zeros <= count;
END PROCESS;
END behavior;
Output
Modify the design for trailing zeros !
Comparison between
Concurrent and Sequential
Constructs
R.B.Ghongade
Lecture 15
CASE versus IF
• Though in principle the presence of ELSE in the
IF/ELSE statement might infer the
implementation of a priority decoder (which
would never occur with CASE), this will generally
not happen
• When IF (a sequential statement) is used to
implement a fully combinational circuit, a
multiplexer might be inferred instead
• Therefore, after optimization, the general
tendency is for a circuit synthesized from a
VHDL code based on IF not to differ from that
based on CASE
Same inference !
---- With IF: --------------
IF (sel="00") THEN x<=a;
ELSIF (sel="01") THEN x<=b;
ELSIF (sel="10") THEN x<=c;
ELSE x<=d;
---- With CASE: ------------
CASE sel IS
WHEN "00" => x<=a;
WHEN "01" => x<=b;
WHEN "10" => x<=c;
WHEN OTHERS => x<=d;
END CASE;
CASE versus WHEN
• CASE and WHEN are very similar. However,
while one is concurrent (WHEN), the other is
sequential (CASE)
WHEN CASE
Statement type Concurrent Sequential
Usage
Only outside
PROCESSES,
FUNCTIONS, or
PROCEDURES
Only inside
PROCESSES,
FUNCTIONS, or
PROCEDURES
All permutations must
be tested
Yes for
WITH/SELECT/WHEN
Yes
Max. # of assignments
per test
One Any
No-action keyword UNAFFECTED NULL
Same functionality !
---- With WHEN: ----------------
WITH sel SELECT
x <= aWHEN "000",
b WHEN "001",
c WHEN "010",
UNAFFECTED WHEN OTHERS;
---- With CASE: ----------------
CASE sel IS
WHEN "000" => x<=a;
WHEN "001" => x<=b;
WHEN "010" => x<=c;
WHEN OTHERS => NULL;
END CASE;
Using Sequential Code to Design
Combinational Circuits
• Sequential code can be used to implement
either sequential or combinational circuits
• Registers are for sequential circuits necessary,
so will be inferred by the compiler
• This should not happen for combinational
circuits
• Also for a combinational circuit, the complete
truth-table should be clearly specified in the
code
Rules to be followed while using sequential
code for designing combinational circuits
• Rule 1: Make sure that all input signals used
(read) in the PROCESS appear in its sensitivity
list
• Rule 2: Make sure that all combinations of the
input/output signals are included in the code;
that is, make sure that, by looking at the code,
the circuit’s complete truth-table can be obtained
(indeed, this is true for both sequential as well as
concurrent code)
• Failing to comply with rule 1 will generally cause
the compiler to simply issue a warning saying
that a given input signal was not included in the
sensitivity list, and then proceed as if the signal
were included. Even though no damage is
caused to the design in this case, it is a good
design practice to always take rule 1 into
consideration
• With respect to rule 2, however, the
consequences can be more serious because
incomplete specifications of the output signals
might cause the synthesizer to infer latches in
order to hold their previous values
Bad Combinational Design
x should behave as a multiplexer; that is, should
be equal to the input selected by sel;
y, on the other hand, should be equal to ‘0’ when
sel = ‘‘00’’, or ‘1’ if sel = ‘‘01’’
LIBRARY ieee;
USE ieee.std_logic_1164.all;
ENTITY example IS
PORT (a, b, c, d: IN STD_LOGIC; sel: IN INTEGER RANGE 0 TO 3;
x,y: OUT STD_LOGIC);
END example;
ARCHITECTURE example OF example IS
BEGIN
PROCESS (a, b, c, d, sel)
BEGIN
IF (sel=0) THEN
x<=a;
y<=‘0’;
ELSIF (sel=1) THEN
x<=b;
y<=‘1’;
ELSIF (sel=2) THEN
x<=c;
ELSE
x<=d;
END IF;
END PROCESS;
END example;
Output
Value of y remains ‘1’ which is not expected
Cure for the problem: y<='X'; must be included for
other conditions of sel i.e. 2 & 3
Some templates for use!
process (Inputs) -- All inputs in sensitivity list
begin
... -- Outputs assigned for all input conditions
... -- No feedback
end process; -- Gives pure combinational logic
process (Inputs) -- All inputs in sensitivity list
begin
if Enable = '1' then
... -- Latched actions
end if;
end process; -- Gives transparent latches + logic
process (Clock) -- Clock only in sensitivity list
begin
if Rising_edge(Clock) then -- Test clock edge only
... -- Synchronous actions
end if;
end process; -- Gives flipflops + logic
process (Clock, Reset) -- Clock and reset only in
-- sensitivity list
begin
if Reset = '0' then -- Test active level of
-- asynchronous reset
... -- Asynchronous actions
elsif Rising_edge(Clock) then -- Test clock edge
-- only
... -- Synchronous actions
end if;
end process; -- Gives flipflops + logic
process -- No sensitivity list
begin
wait until Rising_edge(Clock);
... -- Synchronous actions
end process; -- Gives flipflops + logic
Implementing RAM
• The circuit has a data input bus (data_in), a data output bus
(data_out), an address bus (addr), plus clock (clk) and write
enable (wr_ena) pins
• When wr_ena is asserted, at the next rising edge of clk the
vector present at data_in must be stored in the position
specified by addr
• The output, data_out, on the other hand, must constantly
display the data selected by addr
LIBRARY ieee;
USE ieee.std_logic_1164.all;
ENTITY ram IS
GENERIC ( bits: INTEGER := 8; -- # of bits per word
words: INTEGER := 16); -- # of words in the memory
PORT ( wr_ena, clk: IN STD_LOGIC; addr: IN INTEGER RANGE 0 TO words-1;
data_in: IN STD_LOGIC_VECTOR (bits-1 DOWNTO 0);
data_out: OUT STD_LOGIC_VECTOR (bits-1 DOWNTO 0));
END ram;
ARCHITECTURE ram OF ram IS
TYPE vector_array IS ARRAY (0 TO words-1) OF
STD_LOGIC_VECTOR (bits-1 DOWNTO 0);
SIGNAL memory: vector_array;
BEGIN
PROCESS (clk, wr_ena)
BEGIN
IF (wr_ena='1') THEN
IF (clk'EVENT AND clk='1') THEN
memory(addr) <= data_in;
END IF;
END IF;
END PROCESS;
data_out <= memory(addr);
END ram;
Output
ram1
memory[7:0]
data_out[7:0]
[7:0]
data_in[7:0] [7:0]
addr[3:0] [3:0]
clk
wr_ena
[3:0]
RADDR[3:0]
[7:0]
DATA[7:0]
[7:0]
DOUT[7:0][3:0]
WADDR[3:0]
WE[0]
CLK
Packages, Functions and
Procedures
R.B.Ghongade
Lecture 16,17
Fundamental units of VHDL code
COVERED SO FAR
Packages
• Frequently used pieces of VHDL code are usually written
in the form of COMPONENTS, FUNCTIONS, or
PROCEDURES
• Such codes are then placed inside a PACKAGE and
compiled into the destination LIBRARY
• Packages allow code partitioning, code sharing, and
code reuse
• Besides COMPONENTS, FUNCTIONS, and
PROCEDURES, it can also contain TYPE and
CONSTANT definitions
• A package is split into a declaration and a body
• The package declaration defines the external interface to
the package, the package body typically contains the
bodies of any functions or procedures defined in the
package declaration
Syntax
{declaration}
package PackageName is
Declarations...
end [package] [PackageName];
{body}
package body PackageName is
Declarations...
end [package body] [PackageName];
• Where a function or procedure is placed in
a package, the declaration and body must
conform, i.e. the parameters must be
identical between the two
• Only definitions placed in the package
declaration are visible outside the package
REMEMBER THIS !
Common, shared declarations of types, subtypes, constants,
procedures, functions and components are best put in a
package
A simple package
LIBRARY ieee;
USE ieee.std_logic_1164.all;
PACKAGE my_package IS
TYPE state IS (st1, st2, st3, st4);
TYPE color IS (red, green, blue);
CONSTANT vec: STD_LOGIC_VECTOR(7 DOWNTO 0) := "11111111";
END my_package;
The example above shows a PACKAGE called my_package. It contains
only TYPE and CONSTANT declarations, so a PACKAGE BODY is not
necessary
LIBRARY ieee;
USE ieee.std_logic_1164.all;
PACKAGE my_package IS
TYPE state IS (st1, st2, st3, st4);
TYPE color IS (red, green, blue);
CONSTANT vec: STD_LOGIC_VECTOR(7 DOWNTO 0) := "11111111";
FUNCTION positive_edge(SIGNAL s: STD_LOGIC) RETURN BOOLEAN;
END my_package;
PACKAGE BODY my_package IS
FUNCTION positive_edge(SIGNAL s: STD_LOGIC) RETURN BOOLEAN IS
BEGIN
RETURN (s'EVENT AND s='1');
END positive_edge;
END my_package;
Example
• This example contains, besides TYPE and CONSTANT
declarations, a FUNCTION.
• Therefore, a PACKAGE BODY is now needed
• This function returns TRUE when a positive edge occurs on clk
• Any of the PACKAGES in the previous examples can
now be compiled, becoming then part of our work
LIBRARY (or any other)
• To make use of it in a VHDL code, we have to add a new
USE clause to the main code
(USE work.my_package.all), as shown below:
LIBRARY ieee;
USE ieee.std_logic_1164.all;
USE work.my_package.all;
ENTITY
...
...
ARCHITECTURE
...
...
Functions & Procedures
• FUNCTIONS and PROCEDURES are
collectively called subprograms
• They are very similar to a PROCESS , for they
are the only pieces of sequential VHDL code,
and thus employ the same sequential
statements (IF, CASE, and LOOP; WAIT is not
allowed)
• PROCESS is intended for immediate use in the
main code, FUNCTIONS & PROCEDURES are
intended mainly for LIBRARY allocation, that is,
their purpose is to store commonly used pieces
of code, so they can be reused or shared by
other projects.
• A FUNCTION or PROCEDURE can also be
installed in the main code itself
Functions
• Used to group together executable,
sequential statements to define new
mathematical or logical functions
• Also used to define bus resolution
functions, operators, and conversion
functions between data types
• When defined in a package, the function
must be split into a declaration and a body
FUNCTION function_name [<parameter list>] RETURN data_type IS
[declarations]
BEGIN
(sequential statements)
END function_name;
<parameter list> = [CONSTANT] constant_name : constant_type ;
or
<parameter list> = SIGNAL signal_name : signal_type ;
Syntax: Function Body
Where :(FUNCTION DECLARATION)
package - <HERE> - end
package body - <HERE> - end
entity – is - <HERE> - begin - end
architecture –is - <HERE> - begin- end
block - <HERE> - begin - end
generate - <HERE> - begin - end
process - <HERE> - begin - end
function – is - <HERE> - begin - end
procedure – is - <HERE> - begin - end
Function Body is NOT allowed inside a Package
Rules :
• The function_name may be an identifier or
an operator
• Functions cannot assign signals or
variables defined outside themselves, nor
can then contain wait statements
• A function must execute a return
statement
• Pure functions cannot have side effects -
they must do nothing but return a value
• There can be any number of such parameters
(even zero), can only be CONSTANT (default)
or SIGNAL (VARIABLES are not allowed).
• Their types can be any of the synthesizable
data types (BOOLEAN,STD_LOGIC,
INTEGER, etc.)
• No range specification should be included
(for example, do not enter RANGE when
using INTEGER, or TO/DOWNTO when using
STD_LOGIC_VECTOR)
• On the other hand, there is only one return
value, whose type is specified by data_type
• The return type must be a name; it cannot
include a constraint
• Variables defined inside a function are
initialized each time the function is called
• The declaration and body must conform,
i.e. the parameters and return type must
be identical between the two
• The function declaration ends with a ";",
whereas the function body has is at the
corresponding point in the syntax
REMEMBER THIS !
Synthesis :
• Each call to a function is synthesized as a separate
block of combinational logic
FUNCTION f1 (a, b: INTEGER; SIGNAL c: STD_LOGIC_VECTOR)
RETURN BOOLEAN IS
BEGIN
(sequential statements)
END f1;
Example :
• The function, named f1, receives three parameters (a, b, and c)
• a and b are CONSTANTS (notice that the word CONSTANT can be
omitted, for it is the default object), while c is a SIGNAL.
• a and b are of type INTEGER, while c is of type STD_LOGIC_VECTOR
• Notice that neither RANGE nor DOWNTO was specified.
• The output parameter (there can be only one) is of type BOOLEAN
Function Call
• A function is called as part of an expression. The
expression can obviously appear by itself or
associated to a statement (either concurrent or
sequential)
x <= conv_integer(a); -- converts a to an integer
-- (expression appears by
-- itself)
y <= maximum(a, b); -- returns the largest of a
-- and b
-- (expression appears by itself)
IF x > maximum(a, b) ... -- compares x to the
-- largest of a, b
-- (expression associated to a
-- statement)
Examples of function calls:
Function positive_edge( )
• The FUNCTION below detects a positive
(rising) clock edge.
• It is similar to the
IF (clk’EVENT and clk = ‘1’) statement
------ Function body: -----------------------------
FUNCTION positive_edge(SIGNAL s: STD_LOGIC) RETURN
BOOLEAN IS
BEGIN
RETURN (s'EVENT AND s='1');
END positive_edge;
------ Function call: -----------------------------
...
IF positive_edge(clk) THEN...
...
Function locations
FUNCTION/PROCEDURE
LOCATION
PACKAGE
+
(PACKAGE BODY)
MAIN CODE
LIBRARY
ENTITY
ARCHITECTURE
DECLARATIVE
PART
• Though a FUNCTION is usually placed in a
PACKAGE (for code partitioning, code reuse,
and code sharing purposes), it can also be
located in the main code (either inside the
ARCHITECTURE or inside the ENTITY)
• When placed in a PACKAGE, then a
PACKAGE BODY is necessary, which must
contain the body of each FUNCTION (or
PROCEDURE) declared in the declarative
part of the PACKAGE
FUNCTION Located in the Main Code
LIBRARY ieee;
USE ieee.std_logic_1164.all;
ENTITY dff IS
PORT ( d, clk, rst: IN STD_LOGIC; q: OUT STD_LOGIC);
END dff;
ARCHITECTURE my_arch OF dff IS
FUNCTION positive_edge(SIGNAL s: STD_LOGIC)
RETURN BOOLEAN IS
BEGIN
RETURN s'EVENT AND s='1';
END positive_edge;
BEGIN
PROCESS (clk, rst)
BEGIN
IF (rst='1') THEN q <= '0';
ELSIF positive_edge(clk) THEN q <= d;
END IF;
END PROCESS;
END my_arch;
FUNCTION Located in a PACKAGE
LIBRARY ieee;
USE ieee.std_logic_1164.all;
PACKAGE my_package IS
FUNCTION positive_edge(SIGNAL s:
STD_LOGIC) RETURN BOOLEAN;
END my_package;
PACKAGE BODY my_package IS
FUNCTION positive_edge(SIGNAL s: STD_LOGIC)
RETURN BOOLEAN IS
BEGIN
RETURN s'EVENT AND s='1';
END positive_edge;
END my_package;
LIBRARY ieee;
USE ieee.std_logic_1164.all;
USE work.my_package.all;
ENTITY dff IS
PORT ( d, clk, rst: IN STD_LOGIC;
q: OUT STD_LOGIC);
END dff;
ARCHITECTURE my_arch OF dff IS
BEGIN
PROCESS (clk, rst)
BEGIN
IF (rst='1') THEN q <= '0';
ELSIF positive_edge(clk) THEN q <= d;
END IF;
END PROCESS;
END my_arch;
WORK DESIGN SPACE
SHOULD BE VISIBLE TO
THE TOP-LEVEL ENTITY
Function conv_integer( )
LIBRARY ieee;
USE ieee.std_logic_1164.all;
PACKAGE my_package IS
FUNCTION conv_integer (SIGNAL vector:
STD_LOGIC_VECTOR) RETURN INTEGER;
END my_package;
PACKAGE BODY my_package IS
FUNCTION conv_integer (SIGNAL vector:
STD_LOGIC_VECTOR) RETURN INTEGER IS
VARIABLE result: INTEGER RANGE 0 TO 2**vector'LENGTH-1;
BEGIN
IF (vector ( vector'HIGH )='1') THEN result:=1;
ELSE result:=0;
END IF;
FOR i IN (vector'HIGH-1) DOWNTO (vector'LOW) LOOP
result:=result*2;
IF(vector(i)='1') THEN result:=result+1;
END IF;
END LOOP;
RETURN result;
END conv_integer;
END my_package;
conv_integer( ) function converts
a STD_LOGIC_VECTOR value
into an INTEGER value
Algorithm
3 2 1 0
0 1 0 1 vector
Iteration 1:
vector’LENGTH=4
vector’HIGH=3
vector ( vector'HIGH )= 0
result=0 Since ‘ vector ( vector'HIGH )= 0 ’
3 downto 0 ( i = 2 to start with )
result= 0 x 2
result= 0 + 1 since vector(2)= 1
Iteration 2: ( i = 1)
result= 1 x 2
result= 2 + 0 since vector(1)= 0
Iteration 3: ( i = 0)
result= 2 x 2
result= 4 + 1 since vector(0)= 1
RETURNED : result = 5
LIBRARY ieee;
USE ieee.std_logic_1164.all;
USE work.my_package.all;
ENTITY conv_int2 IS
PORT ( a: IN STD_LOGIC_VECTOR(0 TO 3);
y: OUT INTEGER RANGE 0 TO 15);
END conv_int2;
ARCHITECTURE my_arch OF conv_int2 IS
BEGIN
y <= conv_integer(a);
END my_arch;
PROCEDURE
• A PROCEDURE is very similar to a FUNCTION
and has the same basic purposes
• A procedure can return more than one value
• Like a FUNCTION, two parts are necessary to
construct and use a PROCEDURE:
– the procedure itself (procedure body)
– procedure call
Procedure Body
PROCEDURE procedure_name [<parameter list>] IS
[declarations]
BEGIN
(sequential statements)
END procedure_name;
<parameter list> = [CONSTANT] constant_name: mode type;
<parameter list> = SIGNAL signal_name: mode type;
<parameter list> = VARIABLE variable_name: mode type;
• A PROCEDURE can have any number of IN, OUT, or
INOUT parameters, which can be SIGNALS,
VARIABLES, or CONSTANTS. For input signals
(mode IN), the default is CONSTANT, whereas for
output signals (mode OUT or INOUT) the default is
VARIABLE
• WAIT, SIGNAL declarations, and COMPONENTS are
not synthesizable when used in a FUNCTION. The
same is true for a PROCEDURE, with the exception
that a SIGNAL can be declared, but then the
PROCEDURE must be declared in a PROCESS.
• Moreover, besides WAIT, any other edge detection is
also not synthesizable with a PROCEDURE (that is,
contrary to a function, a synthesizable procedure
should not infer registers)
Example
PROCEDURE my_procedure ( a: IN BIT; SIGNAL b,
c: IN BIT;
SIGNAL x: OUT BIT_VECTOR(7 DOWNTO 0);
SIGNAL y: INOUT INTEGER RANGE 0 TO 99) IS
BEGIN
...
END my_procedure;
• The PROCEDURE has three inputs, a, b, and c (mode IN)
• a is a CONSTANT of type BIT, while b and c are SIGNALS, also
of type BIT. Notice that the word CONSTANT can be omitted
for input parameters, for it is the default object (recall,
however, that for outputs the default object is VARIABLE)
• There are also two return signals, x (mode OUT, type
BIT_VECTOR) and y (mode INOUT, type INTEGER)
Procedure Call
• Contrary to a FUNCTION, which is called as
part of an expression, a PROCEDURE call is a
statement on its own
• It can appear by itself or associated to a
statement (either concurrent or sequential)
Examples of procedure calls:
compute_min_max(in1, in2, 1n3, out1, out2);
-- statement by itself
divide (dividend, divisor, quotient, remainder);
-- statement by itself
IF (a>b) THEN compute_min_max(in1, in2, 1n3,
out1, out2);
-- procedure call
-- associated to another
-- statement
SIMULATION ISSUES
R.B.Ghongade
Lecture 20,21,22
SIMULATION ISSUES
• SIMULATION
• SIMULATION PROCESS
• DELAY MODELING
• TYPES OF SIMULATION
Simulation
• Simulation is a functional emulation of a
circuit design through software programs,
that use models to replicate how a device
will perform in terms of timing and results
Simulation
• Simulation eliminates the time-consuming
need for constant physical prototyping
• Simulation can be performed during ALL
stages of verification
• Motivation of simulation comes from the
need to verify that the HDL code is
correctly implementing the design
• Simply verify that the design meets its
required specification
Flavours of Simulation
• Functional Simulation: Is functional verification
of the design without any delays
• Pre- Layout simulation: Is functional verification
of the design including logic cell delays
• Post- Layout simulation: Is performed after
physical place and route( interconnect delays are
taken into account)
Simulation at different Levels
a1
1
a2
2
3
a3
4
a4
b1
b2
b3
b4
5
6
7
8
Vcc1
0
GND
0
a1
1
a2
2
3
a3
4
a4
b1
b2
b3
b4
5
6
7
8
Vcc1
0
GND
0
a1
1
a2
2
3
a34
a4
b1
b2
b3
b4
5
6
7
8
Vcc1
0
GND
0
a1
1
a2
2
3
a34
a4
b1
b2
b3
b4
5
6
7
8
Vcc1
0
GND
0
A
D
Q1
Q4
ENB
Register
Long card
Module Subsystem Chip System
Comparison for simulation
Module Subsystem Chip System
Stimuli Development
Simulation Efficiency
Nature of detected problems
Bug correction time
Time in project
Difficult
Higher
Low level
Low
Early
Easier
Low
All kinds
Higher
Late
Steps in simulation
ELABORATION
INITIALISATION
EXECUTION
Steps in Simulation
• COMPILATION
* Checks VHDL source code to check syntax and
semantic rules of VHDL
* If a syntax or semantic error occurs, then the
compiler flags off an error message
* Else the compiler generates an intermediate
code
SEMANTICS SYNTAX
SCIENCE OF
MEANING
MECHANISM
OF
LANGUAGE
Steps in Simulation cont...
• ELABORATION
* Ports are created for each instance of a
component
* Memory storage is allocated for the required
signal
* Interconnections among the port signals are
specified
* Mechanism is established for executing the
VHDL process in proper sequence
Steps in Simulation cont...
• INITIALIZATION
* Initial values preset in the declarations
statements are assigned to signals/variables
Steps in Simulation cont...
* Every process is executed until it suspends.
Signal values are updated only after this.
* Simulator accepts simulation commands
like: RUN, ASSIGN,WATCH , which
control the simulation of the system
• EXECUTION
* Simulation ends when all signals have been
updated and new values have been assigned
to the signals
SIMULATION PROCESS
BASIC DEFINITIONS
•EVENT
A CHANGE ON COMPONENT OUTPUT THAT
WILL BE PROPAGATED
•TRANSACTION
A CHANGE ON COMPONENT INPUT THAT
DOES NOT PROPAGATE
SIMULATION PROCESS
BASIC DEFINITIONS cont.
•SCHEDULING
FUTURE EVENTS GENERATED BY
EVALUATION OF A PROCESS
•EVALUATION
CALCULATING THE OUTPUTS OF
COMPONENTS BASED ON INPUTS AND
CURRENT STATE
SIMULATION PROCESS
Time Jargon
Real Time Simulation Time
(As it happens…) (Relative to some arbitrary t=0)
SIMULATION PROCESS
Simulation executes as follows:
At t=0 , all gate outputs are set to an unknown value
Two queues are set up
SIGNALS TO BE UPDATED PROCESSES TO BE EXECUTED
SIMULATION PROCESS
• When Simulation time is incremented :
• Signal is updated
• All processes sensitive to that signal are
placed on the process execution queue
• Each resumed process is executed until it suspends
• Effects of the logic changes that have
occurred as a result of process execution
are evaluated
• Simulation time is set to the next event in queue or
halted if simulation time gets exhausted
One loop is
called DELTA
CYCLE
SIMULATION DELTA
• What is simulation delta?
•Several logic changes occur simultaneously in a circuit
(concurrent operations)
•But simulator being run by a sequential machine,
hence it cannot process events concurrently.
•To take care this, time is frozen within the simulator.
•The real time the simulator takes to complete all
concurrent operations in the queue is called
SIMULATION DELTA
SIMULATION DELTA
t=0 ns t=1 ns
Zero simulation time
t=2 ns t=3 ns t=4 ns
Many delta cycles can occur
Real Time
The minimum time interval possible for the simulator is
assumed to be 1 ns here
SIMULATION DELTA
• SUMMARY
Simulation deltas allow ordering of events that occur
at the same simulation time during simulation
Simulation deltas are infinitesimal amount of time used
as synchronism mechanism when zero delay events are
present
DELAY MODELING
Delays are timing parameters given by the user for
modeling physical characteristics of hardware
Types of delays
INERTIAL DELAY TRANSPORT DELAY
Delays are specified in signal assignment statements only
Delays should NOT be used in variable assignments
INERTIAL DELAY
• It is used to model the inherent inertia of
physical devices
• Example:
– The input value must be stable for a specified
minimum pulse duration before the value is
allowed to propagate to the output
– If the input is not stable for the specified limit,
no output change occurs
TRANSPORT DELAY
• It represents pure propagation delay i.e.,
wires and interconnect delays
• Signal value is assigned with a specified
delay independent of the width of the input
waveform
DELAYS
10 ns 3 ns
10 ns
2 ns
6 ns
X
Z1
Z2
Z3
TYPES OF SIMULATION
• FUNCTIONAL SIMULATION
• BEHAVIORAL SIMULATION
• STATIC TIMING SIMULATION
• GATE-LEVEL SIMULATION
• SWITCH-LEVEL SIMULATION
• TRANSISTOR-LEVEL OR CIRCUIT-
LEVEL SIMULATION
TYPES OF SIMULATION
• FUNCTIONAL SIMULATION
It ignores timing aspects
Verifies only the functionality of the design
• BEHAVIORAL SIMULATION
A given functionality is modeled using HDL
Timing aspects are considered
TYPES OF SIMULATION
• STATIC TIMING SIMULATION
A built in tool that computes delay for each
timing path
Does not require input stimuli
• GATE-LEVEL SIMULATION
Is used to check the timing performance of design
Delay parameters of logic cells are used to
verify things
TYPES OF SIMULATION
• SWITCH-LEVEL SIMULATION
Is one level below the gate level simulation
It models transistors as switches
It provides more accurate timing predictions
than gate-level simulation
TYPES OF SIMULATION
• TRANSISTOR-LEVEL SIMULATION
Requires transistor models. Circuit is described in
terms of resistances, capacitances and voltage and
current sources
A set of mathematical equations relating current and
voltages is setup and solved numerically
Gives analog results and is most accurate
Requires large amount of computing resources
And finally!!
Simulation time depends on :
• Simulation levels of logic
• Physical Memory of PC
• Speed of PC
THANK YOU !!!
Test benches in VHDL
Copyright, R.B.Ghongade
R.B.Ghongade
Lecture 18,19
• A design is always incomplete without
verification
• There are several ways to verify VHDL
designs
• Test benches are one of them
• Test benches are also called Test cases
Introduction
• A testbench is an environment, where
a design ( called design or unit under
test UUT) is checked
– applying signals (stimuli)
– monitoring its responses by signal probes
and monitors
• A testbench substitutes the design’s
environment in such a way that the
behaviour of the design can be
observed and analyzed.
A testbench always consists of
following elements:
– a socket for the unit under test (UUT)
– a stimuli generator (a subsystem that
applies stimuli to UUT, either generating
them internally or reading from an
external source)
– tools for observing UUT responses to the
stimuli
Concept of Testbench
• A VHDL test bench is just another specification with its
own
• entity
• architecture
• In addition, it has special structure with some elements
that are characteristic to this type of specification:
• Test bench entity has no ports,
• UUT component instantiation - the relationship
between the test bench and UUT is specified through
component instantiation and structural-type
specification,
• Stimuli - it is a set of signals that are declared
internally in the test bench architecture and assigned
to UUT's ports in its instantiation. The stimuli are
defined as waveforms in one or more behavioral
processes.
Elements of a VHDL Test Bench
Using Test Benches
• The design must be verifiable.
• It is much more convenient to use a test bench for design
verification.
• Writing a test bench -> very complex task
• Therefore some guidelines for future stimuli development
should be written as you progress with the design.
• It is the test bench which is simulated, not the unit under test.
• The UUT is only one of the components instantiated in a test
bench.
• There is no limitation on the test bench size.
• The only limitation is the VHDL simulator used capability.
DESIGN
VERIFICATIONThe design process consists of design and
verification phases The objective of the first one is
to create a new VHDL specification that meets the
system requirements.
Design Specification
Stimuli Definitions
Test bench Specifications
Test bench Simulation
Simulation of the test bench is the last
phase of a design process. Here you
will receive an answer to the question;
"does the system behave as
expected?" Remember that the answer
received from simulating test bench is
reliable only to the extent determined
by the test bench accuracy and
coverage area. The better a test bench
is, the more confident you can be that
your system is properly designed.
Writing stimuli can be performed
concurrently with writing
specifications for each new design
block. The stimuli set should
contain such set of input (and state)
signal values that covers as much
real life situations as possible.
When stimuli are specified, a test
bench specification can be written
It will contain the stimuli and an
instantiation of the designed
system (unit under test). It is the
test bench and not design that will
be simulated during the verification
phase.
Example : Multiplexer
Example : J-K FlipFlop
Closer look at Testbench
UUT: 2- bit Multiplexer
Testbench
Waveforms
Testbench : Using assert…report
Waveforms
Error Report
SUMMARY
• A Test bench thus is an effective built-
in tool for verifying VHDL designs
•Troubleshooting becomes easier and
faster because of the ASSERT…REPORT
clause
•Automation of verification is possible
because of the seamless integration of
language elements.
Synthesis Issues
R.B.Ghongade
Lecture 19
Agenda
• What is synthesis ?
• Synthesis Tools : Expectations
• Synthesis Tools : Features
• Hardware modeling examples
• Good coding Practices
• Synthesis guidelines
What is synthesis ?
• Synthesis is an automatic process that
converts user’s hardware description into
structural logic description
• When we use VHDL as textual file, the
process is called VHDL Synthesis
• Synthesis is a means of converting HDL
into real world hardware
• Synthesis tools generate a gate-level
netlist for the target technology
What is synthesis ?
x <= ( a and b ) or ( c and d );
SYNTHESIS = TRANSLATION + OPTIMIZATION
a
b
c
d
x
a
b
c
d
x
LUT
a
b
c
d
x
• Synthesis is target device technology specific
• Synthesizer will try to use the best architectural
resource available with the target
Several steps work out behind the
scene!
• Translation ( language synthesis ) : Design at higher level
of description is compiled into known language elements
• Optimization : Algorithms are applied to make the design
compact and fast
• Design is mapped using architecture specific techniques
Translation
Optimization
Mapping
Hardware
Description - written
with hardware in
mind
Mix of Boolean ,
other operations
and memory
elements
Gate Level –
Technology
Specific
Synthesis process – design flow
HDL behavioral description
RTL Synthesis
RTL Optimization
High-level
description with
Boolean equations
Netlist
Logic extraction
Structured
Boolean equations
Logic Optimization
Structured
Boolean equations
Technology mapping
Gate-level
optimization
Optimized Netlist
• Translation : Inputs are transformed into a description based
Boolean equations
– If the input data consists of gate level netlist then it is
necessary to extract Boolean equations to determine
functionality of all used gates
• Technology independent logic optimization: This process aims
to improve structure of Boolean equations by applying rules of
Boolean algebra . This removes the redundant logic and
reduces the space requirement
• Technology Mapping: This is the process of transforming
technology independent netlist into technology dependent one.
During mapping , timing and area information of all usable
gates of the target technology must be available. It is split into
two phases
– Flattening
– Structuring
Synthesis process
Flattening
• The aim is to generate Boolean equations for each
output of module in such a way that the output value is a
direct function of inputs. These equations reflect two
level logic in SOP form.
• Resulting equations do not imply any structure
• Good optimization results are obtained
• Caution: In case of structured logic this process would
destroy the characteristic structure and its associated
properties . e.g. carry look ahead adder
• Flattening cannot be applied to every logic circuit
because the number of product terms may become very
large
Structuring
• New intermediate variables are inserted
during the structuring process
• E.g. If (A’.B’.C’) occurs 10 times then the
tool may assign X= (A’.B’.C’) and use X
everywhere
• Finally , the sub-functions are substituted
into original equations
• Compared to the logic before structuring,
the resulting area is reduced
Synthesis process- review
SYNTHESIS
DESIGN
CONSTRAINT(area , speed)
LIBRARIES
NETLIST REPORT
•Translation process
converts RTL to a Boolean
form
•Optimization is done on the
converted Boolean
equations
•Optimized logic is mapped
to technology library
•Flattening is a process where all the design hierarchy is
removed, the entire design is transformed into a flat , generic ,
SOP form
•Structuring is the opposite of flattening, its adds structure to the
generic design by extracting common logic factors and
representing them as intermediate nodes to produce compact
logic
Synthesis tool : expectations
A good synthesis tool should
– perform technology specific optimizations i.e. vendor
specific FPGAs and CPLds
– have best optimization techniques
– allow designer control
– have broad language coverage
– provide user friendly debugging environment
– have fast compile times
– provide clean and seamless link with backend tools
Synthesis Tools - features
Tool cost depends on features provided by it
Desirable features are:
– Replicating the logic
– Duplicate flip-flops, remove unused logic
– optimization across design hierarchy
– resource sharing of adders , incrementors,
multipliers
– automatic RAM inference (RAM logic is
automatically mapped to technology specific
RAM cells)
Replicate logic
– Replicate logic to
meet fan-out
demands
– E.g. WR’ may be
connected to 100
points hence add
buffers to split
internally
BUF
BUF
BUF
BUF
BUF
BUF
Duplicating logic
• We can duplicate the logic which generates the
signal , for minimizing fan-out
• Trade-off : Loading effect of signals is reduced
hence lowering propagation delay but at the
cost of logic and interconnect complexity
D Q D Q
D Q
Resource sharing
• Some synthesis tools automatically perform a
limited amount of resource sharing ( for
arithmetic expressions that are mutually
exclusive)
• Consider the code:
ADDSEL: process( sel, a ,b,c,d)
begin
if (sel=‘1’ ) then
y<= a + b ;
else
y<= c + d ;
end if ;
end process ADDSEL ;
Resource sharing
+
a
b
+
c
d
sel
+
y
a
c
b
d
sel
y
Before resource
sharing
After resource
sharing
An adder requires more floor space than a multiplexer
Simulation vs. Synthesis
• Some simulation constructs are not
supported by synthesis tools
– e.g. wait statements
• Synthesis tools ignore initial values
• Care should be taken so that simulation-
synthesis mismatch does not occur
Using Signals or Variables
• Variables are used only for convenience of
describing behaviour
• Variables are used and declared in a process
however it cannot be used to communicate
between processes
• Variable assignments are done immediately and
are executed sequentially
• Variables may or may not represent physical
wires
• Signal assignments are done at the end of
process
• Signals represent physical wires in the circuit
• Use variables in combinational processes
because there is less simulation overhead
• Order dependency
– Signal assignments are order independent
– Variable assignments are order dependent
– Signal assignments under a clocked process are
translated into registers
– Variable assignments under a clocked process may
or may not be translated into registers
Using Signals or Variables
process (clk, a, b, c, d)
variable y, x, w : std_logic ;
begin
if (clk=‘1’ and clk’event) then
z1<= y ;
y : = x ;
x : = a and b ;
w : = c and d ;
z2<= w ;
end if;
end process ;
Signals or Variables
variables are read
before being written
to , this infers a
memory element
Hardware inferred
Same process with order of statements
changed
process (clk, a, b, c, d)
variable y, x, w : std_logic ;
begin
if (clk='1' and clk'event) then
x := a and b ;
y := x ;
z1<= y ;
z2<= w ;
w := c and d ;
end if;
end process ;
variables are read
before being written
to , this infers a
memory element
Hardware inferred
Hardware modeling examples
“For loop”
process(word)
variable result : std_logic;
begin
result:='0';
for i in 0 to 7 loop
result := result xor word(i);
end loop;
op<=result;
end process;
Multiplexer optimization
case sel is
when “000” => y<= data(0);
when “001” => y<= data(1);
when “010” => y<= data(2);
when “011” => y<= data(3);
1) when others => y<= ‘0’;
2) when others => y<= ‘Z’;
3) when others => y<= ‘X’;
4) when others => NULL;
end case;
The hardware inferred depends on the
condition given in the “when others” clause
Case 1
when others => y<= ‘0’;
Case 2
when others => y<= ‘Z’;
Case 3
when others => y<= ‘X’;
Case 4
when others => NULL;
Good coding practices
• Good coding style means that the synthesis tool can
identify constructs within your code that it can easily
map to technology features
• All programmable devices may have their unique
architectural resources e.g. Xilinx Virtex series has
built-in RAM
• Coding for performance :
– common mistake is to ignore hardware and start
coding as if programming. To achieve best
performance the designer must think about
hardware
Good coding practices
• Improve performance by
– avoiding unnecessary priority structures
in logic
– optimizing logic for late arriving signals
– structuring arithmetic for performance
– avoiding area inefficient code
– buffering high fan-out signals
• Use “constants” to enhance readability and code
maintenance
• Comparison with a constant is preferred since it
is much “cheaper” to implement
• To avoid accidental latches
– specify all clauses of “if” and “case” statements
– specify all outputs
• Use “case” rather than “if-then-else” whenever
possible
• Use parentheses for better operation
• Never use mode “buffer”
Good coding practices
Design constraints
• Constraining designs:
– constraints are means of communicating our
requirements to the synthesis and back-end tools
• Categories of constraints are :
– Timing constraints
• maximum frequency
• duty cycle
• input delays
• output delays
– Layout constraints
Design constraints
• Avoid over-constraining the design
• Consequences of over-constraining are:
– Design performance suffers:
• critical timing paths get the best placement and
fastest routing options
• as the number of critical paths increase , the ability
to obtain the design performance objectives
decrease
– Run times increase
Synthesis guidelines
• Simulate your design before synthesis
• Avoid combinational loops in processes
• If a port is declared to be an integer data
type, the range should be specified, else
the synthesis tool will infer a 32-bit port
• Avoid mixed clock edges
– if a large number of both positive and
negative edge flip-flops are required they
should be placed in different modules
Synthesis guidelines
• For best results:
– use technology primitives (macros) from the target
technology libraries wherever possible
– try small designs on target technology to find its
limitations and strengths
– Partition the design correctly
• eliminate glue logic at the top level
• partition block size based on the logic function, CPU
resources and memory
• separate random logic from structured logic
• separate timing-sensitive modules from area -sensitive ones
CPLDs and FPGAs
Next class

Vlsi design

  • 1.
    VLSI Design Introduction tothe subject Lecture 0 Rajesh Ghongade VIIT
  • 2.
    • Teaching Scheme –Lectures: 3 Hrs/week – Practical: 2 Hrs/Week • Examination Scheme – Paper: 100 Marks – Practical: 50 Marks – Oral: 25 Marks
  • 3.
    Unit-I VHDL Modeling andDesign Flow Introduction to VLSI: complete VLSI design flow (with reference to an EDA tool). Sequential, Data flow, and Structural Modeling. Functions. Procedures, attributes. Test benches, Synthesizable, and non synthesizable statements; packages and configurations Modeling in VHDL with examples of circuits such as counters, shift registers, bidirectional bus, etc.
  • 4.
    Unit 2 FSM AndSequential Logic Principles Sequential Circuits, Meta-stability Synchronization, Design of Finite State Machines, and State minimization, FSM CASE STUDIES - Traffic Light control. Lift Control and UART STA and DTA
  • 5.
    Unit 3 Programmable LogicDevices Introduction to the CPLDs, Study of architecture of CPLD. and Study of the Architecture of FPGA
  • 6.
    Unit 4 System OnChip One, two phase clock, Clock distribution. Power distribution. Power optimization, SRC and DRC, Design validation, Global routing, Switch box routing. Off chip connections, I/O Architectures, Wire parasitics, EMI immune design. Study of memory-Basics of memory includes types of memory cells and memory architectures. Types of memory, based on architecture specific and application specific viz. SRAM, DRAM, SDRAM, FLASH, FIFO.
  • 7.
    Unit 5 CMOS VLSI CMOSparasitics, equivalent circuit, body effect, Technology Scaling, A. parameter. Detail study of Inverter Characteristics, power dissipation, power delay product, CMOS combinational logic design and W/L calculations. Transmission gates, Introduction to CMOS layout.
  • 8.
    Unit 6 Testability Need ofDesign for testability, Introduction to Fault Coverage, Testability. Design- for- Testability, Controllability and Observability, Stuck-at Fault Model. Stuck-Open and Stuck-Short faults. Boundary Scan check. JTAG technology; TAP Controller and TAP Controller State Diagram. Scan path. Full and Partial scan. BIST
  • 9.
    Text Books 1. JohnF. Wakerly, "Digital Design, Principles and Practices", Prentice Hall Publication 2. Neil H. E Weste and Kamran Eshraghian, "Principles of CMOS VLSI Design". 3. Wayne Wolf, "Modern VLSI Design" 4. Sudhkar Yalamachalli, "Introductory VHDL from simulation to Synthesis"
  • 10.
    Reference Books 1. Perry"VHDL" 2. Charles Roth, "Digital System Design using VHDL". McGraw hill. 3. Xilinx Data Manual "The Programmable Logic Data Book". 4. Stephen Brown and Zvonko Vranesic, "Fundamentals of Digital Logic with VHDL Design", Second Edition, McGraw-Hill, 2005. 5. Michael John Sebastian Smith, "Application-Specific Integrated Circuits", Addison Wesley. 6. Wayne Wolf, "FPGA-Based System Design", Prentice Hall, 7. Miron Abramovici, "Digital Systems Testing and Testable Design", Jaico Publishing. 8. Sung-Mo (Steve) kang, Yusuf Leblebici, " CMOS Digital Integrated Circuit", Tata McGraw-Hill Publication.
  • 11.
    LIST OF EXPERIMENTS Any8 assignments out of the following: Simulation, Synthesis, and Implementation of: 1. 8: 1 Multiplexer, 2:4 Decoder, Comparator and Adder. 2. Flip Flop, Shift Register and Counter 3. Lift Controller /Traffic Light Controller/ UART. Anyone of the three. 4. Parity generator and Checker. 5. Implementation of RAM/FIFO. 6. Ramp waveform generator using DAC 7. Bi-directional buffer 8. Temperature sensing using ADC, Displaying on 7-Segment display and threshold setting using keyboard 9. Implementation of 4-bit RISC processor
  • 12.
    EDA Tools • Active-HDL6.3 sp1 – (VHDL compiling and simulation) • Synpilfy Pro 8.2 – Synthesis • Xilinx Webpack 8.X – Implementation
  • 13.
    Alternate EDA Tools •Libero Gold 6.2 – (VHDL compiling & implementation) • Modelsim 6.0 – Simulation • Synpilfy 8.2 – Synthesis
  • 14.
    Hardware available • ActelProASIC PLUS evaluation board with APA300-PQ208 device • Xilinx CPLD Dedicated Trainer XC 9572 PC 84 • Xilinx FPGA Dedicated Trainer XC 2S50 – TQ 144(Spartan II) • Universal Trainer kit (BASE UNIT) (ADD on Modules) – Xilinx CPLD Module • XC 95108 – PLCC 84 – Xilinx FPGA Module • XC V100E – PQ 240 XC (Virtex) – Altera Flex 10K Series FPGA – Atmel CPLD Device ATF 150 4AS / ATF 1508 AS PC 84 – Cypress CPLD Module Device CY37064V PC84
  • 15.
    Lecture 1 Introduction toVLSI R.B.Ghongade
  • 16.
    Microelectronics Is the art,science and technology of designing and fabricating integrated circuits with small-dimension electronic devices Areas of Microelectronics are : • VLSI Design • VLSI CAD Tools • Technology & Fabrication • Physics • Modeling and Simulation • Characterization • Testing Nearly all the advances in the modern day electronic systems and devices are a direct outcome of VLSI technology
  • 17.
    Some keywords! • Very-large-scale-integration(VLSI) is defined as a technology that allows the construction and interconnection of large numbers (millions) of transistors on a single integrated circuit. • Integrated circuit is a collection of one or more gates fabricated on a single silicon chip. • Wafer is a thin slice of semiconductor material on which semiconductor devices are made. Also called a slice or substrate. • Chip is a small piece of semiconductor material upon which miniaturized electronic circuits can be built. • Die is an individual circuit or subsystem that is one of several identical chips that are produced after dicing up a wafer. If you use these key-words often, people will think that you are an expert VLSI engineer!!!
  • 18.
    • The originof this terminology can be traced as the logical extension to the integration techniques namely the Small Scale Integration, SSI (the ICs which functioned as logic gates, flip-flops), the Medium Scale Integration, MSI (multiplexers, decoders)., the Large Scale Integration LSI (early microprocessors, small memories, PAL, GAL Technology Number of gates/transistors* per chip Examples Year SSI 1 to 20 74XX series, 4xxx series 60’s MSI 100 to 1000 74XXX series, 45XX series 70’s LSI 1000 to 10,000/100 to 100,000* 8085, 80’s VLSI 10,000 to 100,000/1,000,000 * CPLD, FPGA, advanced μC, SoC 90’s Dividing line between LSI and VLSI is somewhat fuzzy hence number of transistors provides a good criterion
  • 19.
    The advances inthe integration techniques can be attributed directly to : •Advances in photolithography techniques •New designs of semiconductor devices •Newer methods of metallization The development of integration technology has followed the famous Moore’s Law. It was stated by Gordon Moore, co-founder of Intel, in the year 1965, that “the number of transistors per chip would grow exponentially (double every 18 months)”. In fact the doubling period has shortened to a mere 12 months!
  • 20.
  • 21.
    The number oftransistors/gates that can fit in to the semiconductor die dictates the complexity of the functionality that the device can perform. The important factors that fuel the research in VLSI technology can be summarized as below: • Increased functionality • Higher reliability • Small footprint • Very low power consumption • Increased speed of operation • Re-programmability( except ASIC devices) • Mass production • Low cost
  • 22.
    VLSI is thusa technology that can be harnessed for various applications covering analog, digital and mixed signal electronics. The current trend is to reduce the entire system design to a single chip solution called as system on chip (SoC)
  • 23.
    Building blocks ofVLSI system on chip Digital MCU/MPU Memory MEMS CCD sensors microtransformers microresonators RF/Analog Frequency generation mixers filters VCO LNA RF power amplifiers Opamps Mixed-Signal DSP Audio ,Video circuits MPEG engine Power Management converter regulator on-chip power supply Applications multimedia computing communications biomedical ...
  • 24.
    VLSI Design Process VLSItechnology thus provides a platform for developing systems for various applications The integrated circuits so developed can be further classified as :
  • 25.
    ASIC • An ApplicationSpecific Integrated Circuit (ASIC) is a semiconductor device designed especially for a particular customer (versus a Standard Product, which is designed for general use by any customer) • The three major categories of ASIC Technology are : – Gate Array-Based – Standard Cell-Based – Full custom
  • 26.
    Gate Arrays • Thereare two types of gate arrays: – a channeled gate array – channel-less gate array • A channeled gate-array is manufactured with single or double rows of basic cells across the silicon • A basic cell consists of a number of transistors • The channels between the rows of cells are used for interconnecting the basic cells during the final customization process • A channel-less gate array is manufactured with a “sea” of basic cells across the silicon and there are no dedicated channels for interconnection • Gate arrays contain from a few thousand equivalent gates to hundreds of thousand of equivalent gates • Due to the limited routing space on channeled gate arrays, typically only 70% to 90% of the total number of available gates can be used
  • 27.
    • The libraryof cells provided by a gate array vendor will contain: – primitive logic gates – registers, – hard-macros – soft-macros Hard-macros and soft-macros are usually of MSI and LSI complexity, such as multiplexers, comparators and counters. Hard macros are defined by the manufacturer in terms of cell primitives Soft-macros are characterized by the designer, for example, specifying the width of a particular counter
  • 28.
    Standard Cell • Standardcell devices do not have the concept of a basic cell and no components are prefabricated on the silicon chip • The manufacturer creates custom masks for every stage of the device’s process which leads to a more efficient utilization of silicon as compared to gate arrays • Manufacturers supply hard-macro and soft-macro libraries containing elements of LSI and VLSI complexity, such as controllers, ALUs and microprocessors. • Additionally, soft-macro libraries contain RAM functions that cannot be implemented efficiently in gate array devices; ROM functions are more efficiently implemented in cell primitives
  • 29.
    The Characteristics ofASICs The remarks that follow further discuss some trade-offs of ASICs with respect to the following categories: • Complexity • Silicon Efficiency • Design Risks • Prototype Turnaround • NRE • CAD / CAE Support • Performance
  • 30.
    Complexity • Complexity heremeans the number of transistors (or the amount of logic and/or memory) per given amount of area, plus the associated interconnect capability • Current Array-Based and Cell-Based chips accommodate as many as 20,000,000 usable logic gates on a single die • Array-Based designs -especially in a Channel-Free Array technology - are capable of realizing functions that represent actual system building blocks and incorporate system memory functions on the same die • The Array-Based memories do tend to be about 5 times less dense than Cell-Based memories because they are constructed out of the gates on the master slice. And full custom memories would provide much higher densities than do Array-Based memories • But in fact many designers who are using the Array-Based technologies to get fast turn around tend to be using very small “scratch pad” or “cache” types of memories which fit very well into the ASIC concept
  • 31.
    Silicon Efficiency • Array-Basedtechnologies focus on fast implementation of logic integration onto a single chip, rather than on absolute highest density. • Cell-Based designs allow you to get more logic onto a chip in a given area. • Cell-Based designs feature transistors and routing tracks whose gradations of size are finer than those in Array-Based products. Thus Cell- Based designs use silicon more efficiently than Array-Based designs
  • 32.
    NRE • NRE (“Non-RecurringEngineering”) charges are the costs associated with developing an ASIC • NRE is based on a number of factors like: – the complexity of the design, – the technology chosen (# of masks required) – the amount of work to be done by the customer and by the silicon vendor – the need for special cells or procedures – the type of package required – the schedule the number of layers of metal – …
  • 33.
    • The morework the silicon vendor does and the more special the requirements, the higher will be the NRE . The more work the customer does, the lower the NRE ! • Array-Based designs require the fewest number of design-specific masks and therefore offer the lowest NRE to prototypes. • Cell- Based designs require all masks to be generated for the chosen process and therefore the NRE charge will be higher for a Cell-Based design than for an Array-Based design
  • 34.
    Design Risks • Thepenalty for discovering a design error is higher for a Cell-Based ASIC than for an Array-Based ASIC • Mistakes after prototype fabrication in Array-Based designs usually only require that the metal mask layers be redone. On the other hand, design changes for a Cell- Based design may require that all masks be redone !
  • 35.
    Prototype Turnaround Time (TAT) •Designs that require a complete mask set (Cell- Based) will always require more time to manufacture than designs which use a basic set of diffusion masks and only require customization at the metal layers (Array-Based) • This difference in time could be anywhere from one week to 4 weeks depending on how fast the silicon vendor can get masks from the mask shop and depending on how long the FAB cycle is for a given process
  • 36.
    CAD / CAESupport The use of EDA tools ensure: • Clean documentation • Reusable data • Functional verification • Easy modification • Automated rule check • Back-annotation (synchronization between schematic and layout) • Bill of material
  • 37.
    Performance • The twomost critical parameters that have been used to measure the worth of new technologies have been speed and power • High power circuits are normally fast, but the increased power requires larger power supplies and tends to heat up the junctions on silicon chips which slows the devices. • In today's most dominant ASIC technology - CMOS - high power can cause accelerated junction temperatures which can slow down speed • One way to reduce the power and still maintain speed is to develop circuits such as differential pairs that do not switch from voltage rail to voltage rail
  • 38.
    ASIC Design Flow ARCHITECTUREDEFINITION AND LOGIC DESIGN SYSTEM REQUIREMENTS VLSI DESIGN AND LAYOUT DESIGN VERIFICATION MASK GENERATION SILICON PROCESSING WAFER TESTING, PACKAGING, RELIABILITY QUALIFICATION FAIL PASS LOGIC DIAGRAM/DESCRIPTION TECHNOLOGY DESIGN RULES DEVICE MODELS DESIGN RULE CHECK SIMULATION (SPICE)
  • 39.
    INITIAL DESIGN REVIEW DESIGNENTRY SIMULATION & POWER ANALYSIS LOGIC & TEST SYNTHESIS CLOCK PLANNING/ CLOCK TREE SYNTHESIS FLOORPLANNING GATE-LEVEL SIMULATION FORMAL VERIFICATION TEST STRUCTURE VERIFICATION POWER ESTIMATION STATIC TIMING ANALYSIS PRE-LAYOUT TECHNOLOGY CHECKS RELEASE TO LAYOUT TIMING DRIVEN LAYOUT/OPTIMIZATION STATIC TIMING ANALYSIS POST LAYOUT TECHNOLOGY CHECKS AUTOMATIC TEST-PATTERN GENERATION RELEASE TO MANUFACTURING TIMING ASSERTIO NS DESIGN LANDMARKS FRONT-END TOOLS TEST& VERIFICATION TOOLS LAYOUT & PHYSICAL VERIFICATION TOOLS ASIC Design Flow (detailed)
  • 40.
    Programmable logic device (PLD) •It is an integrated circuit able to implement combinational and/or sequential digital functions defined by the designer and programmed into this circuit • There are a wide variety of ICs that can have their logic function “programmed” into them after they are manufactured. Most of these devices use technology that also allows the function to be reprogrammed
  • 41.
    • Historically, programmablelogic arrays (PLAs) were the first programmable logic devices • PLAs contained a two-level structure of AND and OR gates with user-programmable connections • Using this structure, a designer could accommodate any logic function up to a certain level of complexity using the well-known theory of logic synthesis and minimization • PLA structure was enhanced and PLA costs were reduced with the introduction of programmable array logic (PAL) devices • Today, such devices are generically called programmable logic devices (PLDs), and are the “MSI” of the programmable logic industry • The ever-increasing capacity of integrated circuits created an opportunity for IC manufacturers to design larger PLDs for larger digital-design applications • However, the basic two-level AND-OR structure of PLDs could not be scaled to larger sizes. Instead, IC manufacturers devised complex PLD (CPLD) architectures to achieve the required scale
  • 42.
    • A typicalCPLD is merely a collection of multiple PLDs and an interconnection structure, all on the same chip. In addition to the individual PLDs, the on-chip interconnection structure is also programmable, providing a rich variety of design possibilities • CPLDs can be scaled to larger sizes by increasing the number of individual PLDs and the richness of the interconnection structure on the CPLD chip • At about the same time that CPLDs were being invented, other IC manufacturers took a different approach to scaling the size of programmable logic chips. • Compared to a CPLD, a field-programmable gate arrays (FPGA) contains a much larger number of smaller individual logic blocks, and provides a large, distributed interconnection structure that dominates the entire chip
  • 43.
  • 44.
    Top-Down design methodology •Means describing a complete system at an abstract level using hardware description language(HDL) and the use of EDA tools like partitioners and synthesizers • More time is spent on designing HDL models, considering different architectures and considering system test & testability issues. Practically no time is spent on designing at gate level To consider a concept without thinking of a specific example; consider abstractly or theoretically. ABSTRACT
  • 45.
    Levels of behaviouralabstractionINCREASINGBEHAVIOURALABSTRACTION INCREASINGDETAILEDREALIZATION&COMPLEXITY TRANSISTOR / SWITCH GATE RTL / DATAFLOW ALGORITHM SYSTEM CONCEPT The process of formulating general concepts by abstracting common properties of instances
  • 46.
    • System Level:All the specifications (input and output) are described at this level. This level completely ignores the hardware structure. However HDLs are not useful at this stage. It simply treats the design like a black box. • Algorithmic (also called behavioural) level: This is the highest level of abstraction provided by most HDLs. A module can be implemented in terms of the desired deign algorithm without the concern of the hardware implementation details. Design at this level is very similar to a conventional high level language programming like C. • RTL (Register Transfer Level) (also called dataflow): At this level the module is designed by specifying the data flow between the registers. The designer is aware of how data flows between hardware registers and how the data is processed in the design. • Gate Level: The module is implemented in terms of logic gates and interconnections between these gates. Design at this level is similar to describing a design in terms of gate-level logic diagram. • Transistor (also called Switch) Level: This is the lowest level of abstraction. A module can be implemented in terms of switches, storage nodes, and the interconnections between them. Design at this level requires knowledge of switch-level implementation details.
  • 47.
    Lecture 2 Introduction toVHDL R.B.Ghongade
  • 48.
    PLD based designflow •A decision has to be arrived at regarding the selection of the type of a PLD since we have two options the CPLD and the FPGA •The selected device is then called the target device • Specifications • Design Entry • Compilation • Functional Simulation/Verification • Synthesis • Post-synthesis simulation • Implementation • Timing Simulation • Hardware Implementation Steps involved:
  • 49.
    SPECIFICATIONS (STEP 1) CREATE ADIGITAL DESIGN BY VHDL CODE SCHEMATIC ENTRY STATE DIAGRAM (STEP 2) COMPILATION (STEP 3) FUNCTIONAL SIMULATION (STEP 4) (SPECIFY TARGET DEVICE) SYNTHESIS (STEP 5) SIMULATION (POST SYNTHESIS) (STEP 6) IMPLEMENTATION PLACE & ROUTE Active-HDL Xilinx ISE Libero IDE FPGA Advantage Lattice ISP LEVER Active-HDL Modelsim Xilinx XST Synplify Leonardo Spectrum Active-HDL Modelsim (RTL Level) Netlist (Gate Level) Optimized Netlist (Gate Level) (STEP 7) SIMULATION (TIMING ASPECTS) Palace Active-HDL Modelsim Xilinx IMPACT Actel Flash Pro (STEP 8) HARDWARE IMPLEMENTATION HDL based design flow
  • 50.
    Idea Design Entry (Schematic) VHDL Template Model Generator Target Device Library Synthesis (SynthesizerTool) Design Entry (Text Editor) Netlist (EDIF,XNF,DSL...) Functional Simulation (VHDL Simulator) Algorithmic Simulation (VHDL) Test Vectors (Input Stimuli & Output Expected) Post- Simulation (VHDL Simulator) Structural VHDL (VITAL primitives) Timing Analysis VITAL Primitive Library SDF (Delay Information) Program Data (Fuse Map: JED, HEX...) Device Programming JTAG-ISP Chip Placement & Routing (Device Vendor's Tool) Back-annotation TO PLACE & ROUTE NETLIST Detailed HDL based design flow
  • 51.
    • It mayagain include the input, output and ambient specifications • Target device may be finalized • Choice of target device as CPLD or FPGA depends on various factors • Specific type of device may be selected by comparing the specifications provided by the manufacturer in the datasheet and the actual design requirements 6 3 31 5 5 15 11 24 Xilinx Actel Cypress Altera Lattice AMD AT&T Others • XILINX • LATTICE • LUCENT • ALTERA • ACTEL • CYPRESS • AT&T • AMD Specifications
  • 52.
    Design Entry • Thisis essentially the design entry point in an EDA tool • It can be done by the following means: • Block Diagram/Schematic capture • State Diagram entry • HDL code entry
  • 53.
    Block Diagram/Schematic capture •A schematic circuit is literally “drawn” in an appropriate graphical editor • The EDA tool associated with this task is called Schematic Capture Tool • An electrical rule check (ERC) is usually run • The main job of the ERC tool is to check for incorrect electrical connections for example if a VCC pin of an IC is accidentally shorted to ground, then the ERC tool will point out such a discrepancy • For this tool to be effective the IC pins have to be earlier declared as power, ground, input, output, bidirectional etc. • After removing the ERC errors a netlist is generated by the editor • A netlist is a text file showing the nets i.e. a set of components connected together • It is also possible to generate VHDL netlist
  • 54.
  • 55.
    State Diagram entry •Many designs are most effectively described /designed by state diagram approach. • Effective for sequential designs • The EDA tools provide a graphical interface so that the designer can directly make an entry of the state diagram and generate the netlist. • This method is preferred since it is a fast way of creating the design
  • 56.
  • 57.
    HDL code entry •A designer can enter his /her design using a hardware description language (HDL) • The HDLs prominent in the industry are “VHDL” and “Verilog” • There is another language that is recently making ground called as “System C” • Being similar to C language gives it an advantage to be more user friendly and comfortable to designers familiar with C • Using the code entry method is the most preferred one since it offers: – Design flexibility – Code re-use – Easy modification – Tighter control over resources • A netlist is again created by compiling the HDL code
  • 58.
  • 59.
    Compilation • At thisstage the design is said to be at the Register Transfer Level (RTL) • All the data manipulation is done here at the register of the host CPU or we can say that the design is not in terms of the logic gates but “internal” to the environment • After successful compilation of the design using any one of the three methods a netlist is generated which is called the gate-level netlist • The design now is translated in terms of the logic gates and modular entities like multiplexers, decoders. Thus we now have the design at Gate-level
  • 60.
    Functional Simulation/Verification • There aretwo very different tasks in digital system development – Verification is the process of determining whether a design meets the specification and performance goals – It concerns the correctness of the initial design as well as the refinement processes – Testing is the process of detecting the physical defects of a die or a package that occurred during manufacturing
  • 61.
    Functional Simulation/Verification • A functionaltest is done by simulating the gate-level design using logic simulators that may be available as a built-in feature of the EDA tool. There are two ways of functional verification: – Interactive mode • In the interactive mode the designer can change the input signals and observe the corresponding output behaviour of the design. This method is becomes cumbersome for designs involving large number of inputs and outputs. – Batch mode • Batch mode uses the concept of test-benches (also a piece of VHDL code) that generates test patterns and checks the validity of the output. This mode is attractive for larger designs. • If any undesirable behaviour is observed, the designer can correct the flaw by going back to the design entry level • It is important here to note that none of the timing aspects have been considered during this simulation. Functional verification can thus be compared to the algorithm testing in conventional programming languages
  • 62.
    Synthesis • Synthesis meansto properly put together so as to make the whole complex design • At this stage it is necessary to specify the target device, since the synthesis tool (again dedicated software) requires knowing the resources available with the target device • Synthesis optimally maps the design functionality (at the gate-level) in to the actual devices available with the target device • For example if the design uses a four- input AND gate but since this is not available with the target device, the synthesis tool can break down the four- input AND gate into two two-input AND gates and map correspondingly • Optimization is very important otherwise the design may get “blown-up” and the target device may prove too small for the design • Synthesis tools have built-in proprietary algorithms for optimization
  • 63.
    Post-synthesis simulation • Aftersynthesis the design needs to be re- checked to confirm its functionality • Simulation at this level ensures that the mapped design behaves correctly as desired • A possibility may exist wherein, the synthesis tool may incorrectly recompose the design while mapping • Again timing parameters are ignored here
  • 64.
    Implementation • This isthe process of physical placing of the design into the target device. • Though it is a physical placement, it still takes place in the virtual environment provided by the EDA tool • A physical map of the target device is loaded into the environment and the components are virtually fitted into the target device. • Again this process may have two phases: – Physical synthesis • Physical synthesis means optimal relocation of the design into the target device. Proprietary software tools are available for this task and may be quite costly. This phase is however optional. – Place and route • Place and route is the phase where the tool completes the task of virtually placing the components of the design in to the target device and then wiring the individual modules to complete the design.
  • 65.
    Timing Simulation • Onemost important change the design undergoes is after the implementation. • The modules in the design now may be physically placed apart from each other. • This factor introduces the delay aspect in the signal propagation. • Many synchronous circuits will fail if the timing aspects are ignored, even though they appear to be functionally perfect! • Hence a simulation is necessary again to test the timing behaviour of the design. • This provides the designer with a better view of the design functionality. • In fact the real-world behaviour of the device can be very accurately studied by the simulation with timing aspects
  • 66.
    Hardware Implementation • Thefinal step in design is to “download” the functionality into the actual hardware i.e. the target device • The synthesis tool generates the output in terms of “bit-stream” that is used to configure the target device • Vendor specific tools can be used for downloading the bit-stream into the physical device
  • 67.
    HDL • A hardwaredescription language (HDL) is a software coding language used to model the intended operation of a piece of hardware • There are two aspects to the description of hardware that an HDL facilitates: – true abstract behaviour modeling – hardware structure modeling • Abstract behaviour modeling – A hardware description language is declarative in order to facilitate the abstract description of hardware behaviour for specification purpose. This behaviour is not influenced by structural or design aspects of the hardware intent. • Hardware structure modeling – Hardware structure is capable of being modeled in a hardware description language irrespective of the design’s behaviour.
  • 68.
    VHDL • What isVHDL? – Digital system design using Hardware Description Language is an established methodology in EDA – VHDL stands for “VERY HIGH SPEED INTEGRATED CIRCUITS HARDWARE DESCRIPTION LANUAGE” EDA stands for “ELECTRONIC DESIGN AUTOMATION”
  • 69.
    FEATURES • VHDL isan amalgamation of following languages – Concurrent language – Sequential Language – Timing Specification – Simulation Language – Test Language
  • 70.
    • VHDL hasgot powerful language constructs – {if…else}, {with…select} etc • Design hierarchies to create modular designs • Supports Design Libraries • Facilitates device independent design and portability
  • 71.
    Concurrent Language • Concurrentstatements execute at the same time in parallel as in hardware Z <= C + X ; X <= A + B ; + + A B C X Z
  • 72.
    Sequential Language • Sequentialstatements execute one at a time in sequence • As the case with any conventional programming language the sequence of statements is important Z <= C + X ; X <= A + B; X <= A + B; Z <= C + X ;≠ Sequential statements are required to design sequential circuits
  • 73.
    Timing Specification • Providingtiming attributes in a sequential digital design is of prime importance since the operations are synchronized to a common clock • Example: process begin clk <= ‘0’ ; wait for 20 ns ; clk <= ‘1’ ; wait for 12 ns ; end process ; 0 20 32 52 64 ns 84 Timing can be specified in a process only
  • 74.
    Simulation language • Foranalyzing a digital design it is important the design be simulated • Simulation has different flavours – Functional simulation – Post-synthesis simulation – Post- layout simulation • Any HDL should thus be equipped with simulation capability for verification and troubleshooting purposes
  • 75.
    Test Language • Testbench –It is a part of a VHDL module that generates a set of test vectors (test inputs) and sends them to the module being tested – It collects the responses generated by the module under test and compares them against a specification of correct results – Thus testbench is required to ensure that the design is correct and that the module is operating as desired Equivalent to checking of logical errors in any conventional programming language
  • 76.
    Testbench use Test tst_a tst_b tst_c MODULE UNDERTEST ABC.vhdABC_testbench.vhd Equivalent to mechanical test jigs used for testing functionality of mass produced pcbs as in TV sets or motherboards
  • 77.
    Design Hierarchy • Hierarchycan be represented using VHDL • Example – A full adder which is the top level module being composed of three lower level modules that are; half adder and OR gate HALF ADDER HALF ADDER OR A B Cin SUM CARRY Design hierarchy simplifies the design procedure and manageability in case of complex designs
  • 78.
    Design Libraries • DesignUnit – It is any block of VHDL code or collection of VHDL codes that may be independently analyzed and inserted into a design library • Design Library – It is a storage facility in which analysed VHDL descriptions are stored for repeated uses 1 3 2 54 Design Library Simulator Analyze DESIGN UNIT
  • 79.
    Logic systems • Needfor multi-valued logic system – Conventional logic systems have only three values i.e. ‘0’, ‘1’, ‘Z’ • Example – Consider the truth-table for AND gate A B Y 0 0 0 0 1 0 1 0 0 1 1 1 0 Z ? HOW TO RESOLVE THIS CONDITION ?
  • 80.
    • For thisproblem a 9-valued logic system or package was developed that is called “STD_LOGIC_1164” and it is accepted as IEEE STD 1164-1993 • Multi-valued logic – Unknown: value was known but not anymore – Un-initialized: value was never known – High impedance: net has no driver – Drive strengths: handle different output drivers – Don’t care: value is immaterial
  • 81.
    Levels of abstraction •Different styles are adopted for writing VHDL code • Abstraction defines how much detail about the design is specified in a particular description • Four levels are: – Layout level – Logic level – Register Transfer level – Behavioral level LOGIC LAYOUT RTL BEHAVIORAL
  • 82.
    Layout Level • Thisis the lowest level and describes the CMOS layout level design on silicon
  • 83.
    Logic Level • Designhas information about – Function – Architecture – Technology – Detailed timings • Layout information and analog effects are ignored
  • 84.
    Register Transfer Level •Using HDL every register in the design and the logic in between is defined • Design contains: – Architecture information – No details of technology – No specification of absolute timing delays
  • 85.
    Behavioral Level • Describingfunction of a design using HDL without specifying the architecture of registers • Contains timing information required to represent a function
  • 86.
    Basic building blocksof VHDL code • A VHDL design is composed of following blocks: – Library declarations – Entity – Architecture – Configuration
  • 87.
    Basic VHDL code LIBRARYDECLARATIONS ENTITY ARCHITECTURE CONFIGURATION BASIC VHDL CODE
  • 88.
    Detailed anatomy ofVHDL code Functions Procedures Types Constants Components Package Library EntityGenerics Ports Architecture (Style I) DATAFLOW Architecture (Style II) BEHAVIOURAL Architecture (Style III) STRUCTURAL Concurrent Statements Concurrent Statements Process Sequential Statements
  • 89.
  • 90.
  • 91.
  • 92.
    Library • It isa collection of compiled VHDL units • It enables sharing of compiled designs and hides the source code from the users • Commonly used functions, procedures and user data types can be compiled into a user defined library for use with all designs • Library should be declared before each entity declaration even if it is in the same VHDL file
  • 93.
    Library • To declarea library (i.e. to make it visible to the design) two lines of code are needed , one containing name of the library, the other a use clause • A library structure can be as follows: FUNCTIONS PROCEDURES TYPES CONSTANTS COMPONENTS LIBRARY PACKAGE
  • 94.
    Library syntax LIBRARY library_name; USE library_name.package_name.package_parts ; LIBRARY IEEE ; -- semicolon indicates USE IEEE.std_logic_1164.all ; -- end of statement or -- declaration LIBRARY work ; -- double dash (--) -- indicates a comment USE work.all ; Example
  • 95.
    Library details IEEE.MATH_COMPLEX.all Thispackage defines a standard for designers to use in describing VHDL models that make use of common COMPLEX constants and common COMPLEX mathematical functions and operators. IEEE.MATH_REAL.all This package defines a standard for designers to use in describing VHDL models that make use of common REAL constants and common REAL elementary mathematical functions. IEEE.NUMERIC_BIT.all This package defines numeric types and arithmetic functions for use with synthesis tools. Two numeric types are defined: -- UNSIGNED: represents an UNSIGNED number in vector form -- SIGNED: represents a SIGNED number in vector form The base element type is type BIT.
  • 96.
    Library details IEEE.NUMERIC_STD.alll Thispackage defines numeric types and arithmetic functions for use with synthesis tools. Two numeric types are defined: -- UNSIGNED: represents UNSIGNED number in vector form -- SIGNED: represents a SIGNED number in vector form -- The base element type is type STD_LOGIC. IEEE.STD_LOGIC_1164.all This package defines a standard for designers to use in describing the interconnection data types used in VHDL modeling. Defines multi-value logic types and related functions. IEEE.STD_LOGIC_ARITH.all This package defines a set of arithmetic, conversion, and comparison functions for SIGNED, UNSIGNED, SMALL_INT, INTEGER, STD_ULOGIC, STD_LOGIC, and STD_LOGIC_VECTOR.
  • 97.
    Library details IEEE.STD_LOGIC_MISC.alll Thispackage defines supplemental types, subtypes, constants, and functions for the Std_logic_1164 Package. IEEE.STD_LOGIC_SIGNED.all This package defines a set of signed arithmetic, conversion, and comparison functions for STD_LOGIC_VECTOR. IEEE.STD_LOGIC_TEXTIO.all This package overloads the standard TEXTIO procedures READ and WRITE. IEEE.STD_LOGIC_UNSIGNED.all This package defines a set of unsigned arithmetic, conversion and comparison functions for STD_LOGIC_VECTOR.
  • 98.
    Entity – It isthe design’s interface to the external circuitry – Equivalent to pinout /package of an IC – VHDL design must include one and only one entity per module – It can be used as a component in other entities after being compiled into a library
  • 99.
    Entity declaration • Definesthe input and output ports of the design • Name of the entity can be anything other than the reserved VHDL word • Each port in the port list must be allotted: – a name ( should be self-explanatory that provides information about its function – data flow direction or mode – a type • Ports should be well documented with comments at the end of line providing additional information about the signal
  • 100.
    Entity syntax entity entity_nameis port ( port_name : signal_mode signal_type ; port_name : signal_mode signal_type ; port_name : signal_mode signal_type ) ; end entity_name ;
  • 101.
    Modes • Ports inthe portlist have modes which indicate the driver direction • Mode also indicates whether or not the port can be read from within the entity • Four modes are available: – Mode IN – Mode OUT – Mode INOUT – Mode BUFFER
  • 102.
    • Mode IN Valuecan be read from but not assigned to (by the entity) ENTITY Port signal A Drivers reside outside the entity port ( A : in std_logic ) ;
  • 103.
    • Mode OUT Valuecan be assigned to but not read from (by the entity) port ( B : out std_logic ) ; ENTITY Port signal B Drivers reside inside the entity
  • 104.
    • Mode INOUT Bi-directional, value can be assigned to as well as read from (by the entity) port ( C : inout std_logic ) ; ENTITY Port signal C Drivers reside both inside and outside the entity
  • 105.
    • Mode BUFFER Outputport with internal read capability port ( D : buffer std_logic ) ; ENTITY Port signal D Drivers reside inside the entity Signal can be read inside the entityDO NOT USE UNLESS REQUIRED
  • 106.
    Entity example entity and_gateis port ( 1A , 2A , 3A, 4A : in std_logic ; 1B , 2B , 3B, 4B : in std_logic ; 1Y , 2Y , 3Y, 4Y : out std_logic ) ; end and_gate ; 1A 1 1B 2 1Y 3 2A 4 2B 5 2Y 6 GND 7 3Y 8 3A 9 3B 10 4Y 11 4A 12 4B 13 VCC 14
  • 107.
    Entity example entity ALUis port ( In1 : in std_logic_vector ( 3 downto 0) ; -- 1st operand In2 ; in std_logic_vector ( 3 downto 0) ; -- 2nd operand Opsel : in std_logic_vector ( 3 downto 0) ; -- opn select Cin : in std_logic ; Mode : in std_logic ; Result : out std_logic_vector ( 3 downto 0 ) ; Cout : out std_logic ; Equal : out std_logic ) ; end ALU ; ALU In1 In2 Op sel Result Cout Mode Cin Equal
  • 108.
    Architecture It specifies • Behaviour •Function • Relationship between inputs and outputs of an entity Syntax architecture achitecture_name of entity_name is [declarations] -- optional begin code -- concurrent statements only end achitecture_name ;
  • 109.
    • Architecture cancontain only concurrent statements • A design can be described in an architecture using various levels of abstraction • An entity can have more than one architectures since a function can be implemented in a number of ways • There can be no architecture without an entity
  • 110.
    Architectural bodies • Behavioural –It is the high-level description – It contains a set of assignment statements to represent behaviour – No need to focus on the gate-level implementation of a design Example: architecture behave of and_gate is begin process ( a, b ) if a=‘1’ and b=‘1’ then c <= ‘1’ ; else c <=‘0’ ; end if ; end process ; end behave ;
  • 111.
    • Dataflow – Ituses concurrent signal assignment statements Example: architecture dataflow of and_gate is begin c<= a and b ; end dataflow ;
  • 112.
    • Structural – Componentsfrom libraries are connected together – Designs are hierarchical – each component can be individually simulated – it makes use of component instantiation HALF ADDER HALF ADDER OR A B Cin SUM CARRY Functional units Top level design
  • 113.
    Configuration • Since anumber of architectures can exist for an entity , using configuration statement we can bind a particular architecture to the entity configuration CONFIGURATION_NAME of ENTITY_NAME is for ARCHITECTURE_NAME end for; end CONFIGURATION_NAME; Syntax
  • 114.
  • 115.
  • 116.
    • VHDL isa strongly typed language – Designers have to declare the type before using it • VHDL is not case sensitive ( but avoid mixed cases as a good programming practice) • VHDL supports a wide variety of data types and operators – OBJECTS – OPERATORS – AGGREGATES
  • 117.
    Objects • They areused to represent and store the data in the design being described • Object contains a value of specific type Class Object Data type SIGNAL COUNT : INTEGER This results in an object called COUNT that holds INTEGER value that belongs to class SIGNAL • The name given to the object is called as identifier • Do not use reserved words as identifiers
  • 118.
    • Each objecthas a data type and class • Class indicates how the object is used in the module and what can be done with that object • Type indicates what type of data the object contains • Each object belongs to one of the following class: – CONSTANT – SIGNAL – VARIABLE – FILES CONSTANT SIGNAL VARIABLE CLASS FILES
  • 119.
    Data Types • Inorder to write VHDL code efficiently it is necessary to study the specification and use of data types • Following are the categories of data types: – Pre-defined – User defined – Subtypes – Arrays – Port arrays – Records – Signed and unsigned
  • 120.
    Pre-defined data types •Specified by IEEE 1076 and IEEE 1164 Package Library Type/Functions standard std BIT, BOOLEAN, INTEGER, REAL std_logic_1164 ieee STD_LOGIC, STD_ULOGIC std_logic_arith ieee SIGNED, UNSIGNED / data conversion functions std_logic_signed ieee Functions that allow operations with STD_LOGIC_VECTOR std_logic_unsigned ieee
  • 121.
    BIT (and BIT_VECTOR):2 level logic (‘0’, ‘1’) Examples: SIGNAL X : BIT ; X is declared as a one- digit SIGNAL of type BIT SIGNAL Y : BIT_VECTOR (3 downto 0); Y is 4-bit vector, leftmost bit is MSB SIGNAL W : BIT_VECTOR (0 to 7); W is 8-bit vector, rightmost bit is MSB
  • 122.
    • To assigna value to the signal use the operator “ < = ” • Assignment examples: X <= ‘1’ ; X is a single bit SIGNAL whose value is ‘1’ Note that single quotes are used for a single bit Y <= “0111” ; Y is a 4- bit SIGNAL whose value is “0111” . Note that double quotes are used for vectors W <= “01110001” ; W is an 8- bit SIGNAL whose value is “0111001” . MSB is ‘1’
  • 123.
    STD_LOGIC (and STD_LOGIC_VECTOR): 8valued logic (introduced in IEEE 1164 standard) Symbol Description Remark ‘X’ Forcing unknown Synthesizable unknown ‘0’ Forcing low Synthesizable logic ‘0’ ‘1’ Forcing high Synthesizable logic ‘1’ ‘Z’ High impedance Synthesizable tri-state buffer ‘W’ Weak unknown ‘L’ Weak low ‘H’ Weak high ‘-’ Don’t care
  • 124.
    Examples: SIGNAL X :STD_LOGIC ; X is declared as a one-digit (scalar) SIGNAL of type STD_LOGIC SIGNAL Y : STD_LOGIC_VECTOR (3 downto 0); Y is 4-bit vector, leftmost bit is MSB SIGNAL Y : STD_LOGIC_VECTOR (3 downto 0) : = “0001” for (optional) initial value use “ := ” Most of std_logic levels are intended for simulation only. However ‘0’, ‘1’ and ‘Z’ are synthesizable with no restrictions
  • 125.
    • With respectto “weak” values, they are resolved in favour of the “forcing” values in multiple-driven nodes. If any two std_logic signals are connected to the same node, then conflicting logic levels are resolved by using the shown table X 0 1 Z W L H - X X X X X X X X X 0 X 0 X 0 0 0 0 X 1 X X 1 1 1 1 1 X Z X 0 1 Z W L H Z W X 0 1 W W W W X L X 0 1 L W L W X H X 0 1 H W W H X - X X X X X X X X •The STD_ULOGIC has 9 valued logic levels : additional value is ‘U’ for “Un-resolved or ”Un-initialized”
  • 126.
    • Other types BOOLEANTRUE, FALSE INTEGER 32-bit integers (from - 2,147,483,647 to + 2,147,483,647 NATURAL Non-negative numbers (from 0 to 2,147,483,647 REAL Real numbers (from -1.0E-38 to +1.0E38) Physical literals Used to inform physical quantities like , time, voltage etc. Useful for simulation but not synthesizable Character literals Single ASCII character or a string of such characters. Not synthesizable SIGNED, UNSIGNED They have appearance of STD_LOGIC_VECTOR, but accept arithmetic operations which are typical of INTEGER data type
  • 127.
    User defined datatypes • VHDL allows user defined data types • Two categories of this data type are: – Integer – Enumerated • User defined integer type TYPE my_integer IS RANGE -32 to +32 ; TYPE student_grade IS RANGE 0 to 100 ;
  • 128.
    • User definedenumerated type TYPE my_logic IS (‘0’, ‘1’, ‘Z’ ); TYPE my_state IS ( idle, forward, backward, stop) ; An enumerated type, typically used in state machines • The encoding of enumerated types is done sequentially and automatically • Since here there are 4 states only two bits are required hence “00” is assigned to first state ( idle), “01” to second state (forward) and so on.
  • 129.
    Subtypes • A SUBTYPEis a TYPE with a constraint • Though operations between data of different types are not allowed, they are allowed between the subtype and its corresponding base type SUBTYPE sub_state IS my_state RANGE idle to backward ; This means that the subtype sub_state =(idle, forward, backward)
  • 130.
    Arrays • Arrays arecollections of objects of same type • Can be 1-dimensional, 2-dimensional or 1D X 1D • Higher dimensional arrays are possible but not synthesizable 0 0 1 0 0 1 0 1 0 1 1 0 0 0 1 0 0 1 1 0 1 0 1 0 1 0 1 0 1 1 0 0 1 0 1 0 Scalar 1D 1D x 1D 2D data array
  • 131.
    Array syntax TYPE type_nameIS ARRAY (specification) OF data_type ; To specify an array : SIGNAL signal_name : type_name [:= initial_value] To use an array :
  • 132.
    Example : 1Dx 1D array – We want to build an array containing 4 vectors, each of size 8 bits – we will call each vector as row and the complete array as matrix TYPE row IS ARRAY (7 downto 0 ) OF STD_LOGIC ; TYPE matrix IS ARRAY (3 downto 0 ) OF row ; SIGNAL X : matrix ; 1D x 1D SIGNAL
  • 133.
    Example : 2Darray – This array will be created with scalars only TYPE matrix2D IS ARRAY (0 TO 3, 7 DOWNTO 0 ) OF STD_LOGIC ; L M L M ROWS COLUMNS
  • 134.
    Port Arrays • Inthe specification of the input or output pins (PORTS) of a circuit (which is made in the ENTITY), we might need to specify the ports as arrays of vectors. • Since TYPE declarations are not allowed in an ENTITY, the solution is to declare user-defined data types in a PACKAGE, which will then be visible to the whole design (thus including the ENTITY)
  • 135.
    ------- Package: -------------------------- LIBRARYieee; USE ieee.std_logic_1164.all; ---------------------------- PACKAGE my_data_types IS TYPE vector_array IS ARRAY (NATURAL RANGE <>) OF STD_LOGIC_VECTOR(7 DOWNTO 0); END my_data_types; -------------------------------------------- ------- Main code: ------------------------- LIBRARY ieee; USE ieee.std_logic_1164.all; USE work.my_data_types.all; -- user-defined package --------------------------- ENTITY mux IS PORT (inp: IN VECTOR_ARRAY (0 TO 3); ... ); END mux; ... ; --------------------------------------------
  • 136.
    • As canbe seen in the example above, a user- defined data type, called vector_array,was created, which can contain an indefinite number of vectors of size eight bits each (NATURAL RANGE <> signifies that the range is not fixed, with the only restriction that it must fall within the NATURAL range, which goes from 0 to +2,147,483,647) • The data type was saved in a PACKAGE called my_data_types, and later used in an ENTITY to specify a PORT called inp • Notice in the main code the inclusion of an additional USE clause to make the user-defined package my_data_types visible to the design.
  • 137.
    Records • Records aresimilar to arrays, with the only difference that they contain objects of different types. TYPE birthday IS RECORD day: INTEGER RANGE 1 TO 31; month: month_name; END RECORD;
  • 138.
    Signed and Unsigneddata types • These types are defined in the std_logic_arith package of the ieee library Examples: SIGNAL x: SIGNED (7 DOWNTO 0); SIGNAL y: UNSIGNED (0 TO 3);
  • 139.
    • An UNSIGNEDvalue is a number never lower than zero. For example, ‘‘0101’’ represents the decimal 5, while ‘‘1101’’ signifies 13. • If type SIGNED is used instead, the value can be positive or negative (in two’s complement format). Therefore,‘‘0101’’ would represent the decimal 5, while ‘‘1101’’ would mean 3. • To use SIGNED or UNSIGNED data types, the std_logic_arith package, of the ieee library, must be declared
  • 140.
  • 141.
  • 142.
    Operators • VHDL providesseveral kinds of pre- defined operators – Assignment operators – Logical operators – Arithmetic operators – Relational operators – Shift operators – Concatenation operators
  • 143.
    Assignment operators • Areused to assign values to signals, variables, and constants. <= Used to assign a value to a SIGNAL := Used to assign a value to a VARIABLE, CONSTANT, or GENERIC Used also for establishing initial values => Used to assign values to individual vector elements or with OTHERS
  • 144.
    SIGNAL x :STD_LOGIC; VARIABLE y : STD_LOGIC_VECTOR(3 DOWNTO 0); SIGNAL w: STD_LOGIC_VECTOR(0 TO 7); x <= '1'; -- '1' is assigned to SIGNAL x using "<=" y := "0000"; -- "0000" is assigned to VARIABLE y using --":=" w <= "10000000"; -- LSB is '1', the others are '0' w <= (0 =>'1', OTHERS =>'0'); -- LSB is '1', the others -- are '0' Then the following assignments are legal:
  • 145.
    Logical operators • Usedto perform logical operations. • The data must be of type: – BIT, STD_LOGIC – STD_ULOGIC – BIT_VECTOR – STD_LOGIC_VECTOR – STD_ULOGIC_VECTOR
  • 146.
    • The logicaloperators are: – NOT – AND – OR – NAND – NOR – XOR – XNOR The NOT operator has precedence over the others Examples: y <= NOT a AND b; -- (a'.b) y <= NOT (a AND b); -- (a.b)' y <= a NAND b; -- (a.b)'
  • 147.
    Arithmetic operators • Usedto perform arithmetic operations. The data can be of type INTEGER, SIGNED, UNSIGNED, or REAL (the last cannot be synthesized directly). • Also, if the std_logic_signed or the std_logic_unsigned package of the ieee library is used, then STD_LOGIC_VECTOR can also be employed directly in addition and subtraction operations
  • 148.
    + ( Addition) -(Subtraction) * (Multiplication) / (Division) ** (Exponentiation) MOD ( Modulus) REM ( Remainder) ABS ( Absolute value) •There are no synthesis restrictions regarding addition and subtraction, and the same is generally true for multiplication •For division, only power of two dividers (shift operation) are allowed •For exponentiation, only static values of base and exponent are accepted •Regarding the mod and rem operators, y mod x returns the remainder of y/x with the signal of x, while y rem x returns the remainder of y/x with the signal of y •Finally, abs returns the absolute value For mod, rem, abs , there generally is little or no synthesis support
  • 149.
    Comparison operators = Equalto /= Not equal to < Less than > Greater than <= Less than or equal to >= Greater than or equal to Also called RELATIONAL operators
  • 150.
    Shift operators sll shiftleft logical srl shift right logical sla shift left arithmetic sra shift right arithmetic ror rotate left logical rol rotate right logical 0 0 LOGICAL SHIFTING ARITHMETIC SHIFTING (retains sign bit) ROTATE • LOGICAL • ARITHMETIC • ROTATE
  • 151.
    Concatenation operator • Operandscan be one-dimensional array type or element type • “ &” works on vectors only & Concatenation Example: SIGNAL a : STD_LOGIC_VECTOR ( 5 DOWNTO 0 ) ; SIGNAL b,c,d : STD_LOGIC_VECTOR ( 2 DOWNTO 0 ) ; BEGIN b <= ‘0’ & c(1) & d(2) ; a <= c & d ; . . .
  • 152.
    Operator summary Operator typeOperators Data types Logical NOT, AND, AND OR, NOR, XOR, XNOR BIT, BIT_VECTOR, STD_LOGIC, STD_LOGIC_VECTOR, STD_ULOGIC, STD_ULOGIC_VECTOR Arithmetic +, -,*,/,** (mod, rem , abs) INTEGER, SIGNED, UNSIGNED Comparison =, /=, <, >, <=, >= All above Shift sll, srl, sla, sra, rol, ror BIT_VECTOR Concatenation &, ( , , , ) Same as for logical operators, plus SIGNED and UNSIGNED
  • 153.
    Operator overloading • Operatorscan be user-defined • Let us consider the pre-defined arithmetic operators seen earlier (+,- , *, /, etc.). They specify arithmetic operations between data of certain types (INTEGER, for example) • For instance, the pre-defined ‘‘+’’ operator does not allow addition between data of type BIT. • We can define our own operators, using the same name as the pre-defined ones
  • 154.
    • For example,we could use ‘‘+’’ to indicate a new kind of addition, this time between values of type BIT_VECTOR. This technique is called operator overloading • Example: Consider that we want to add an integer to a binary 1-bit number. Then the following FUNCTION could be used FUNCTION "+" (a: INTEGER, b: BIT) RETURN INTEGER IS BEGIN IF (b='1') THEN RETURN a+1; ELSE RETURN a; END IF; END "+";
  • 155.
    A call tothe function above could thus be the following: SIGNAL inp1, outp: INTEGER RANGE 0 TO 15; SIGNAL inp2: BIT; (...) outp <= 3 + inp1 + inp2; (...) • In ‘‘outp<=3+inp1+inp2;’’, the first ‘‘+’’ is the pre- defined addition operator (adds two integers), while the second is the overloaded user-defined addition operator (adds an integer and a bit).
  • 156.
    Aggregates • It assignsvalues to elements of an array a <= (OTHERS => ‘0’ ) ; a <= “0000” ; • We can assign values to some bits in a vector and use “OTHERS” clause to assign default values to remaining bits a <= (0 => ‘1’, 2 => ‘1’, OTHERS => ‘0’ ) ; is equivalent to a <= “00101” ; Useful when we are dealing with large vectors
  • 157.
    • Each objecthas a data type and class • Class indicates how the object is used in the module and what can be done with that object • Type indicates what type of data the object contains • Each object belongs to one of the following class: – CONSTANT – SIGNAL – VARIABLE CONSTANT SIGNAL VARIABLE CLASS Classes re-visited
  • 158.
    Constants • These areidentifiers with fixed values • The value is assigned only once when declared • Values cannot be changed during simulation CONSTANT bus_width : INTEGER :=16 ; CONSTANT CLK_PERIOD : TIME :=15 ns ; • Constants make the design description more readable • Design changed at later time becomes easy
  • 159.
    Signals Equivalent to wires withina circuit Example: architecture and_gate of myand is signal TEMP : STD_LOGIC ; begin U1 : AND2 portmap ( a, b, TEMP ) ; U2 : AND2 portmap (TEMP, c , d ) ; end and_gate ; a b AND2 TEMP c AND2 d
  • 160.
    • Thus signalsare used : – to connect design entities together and communicate changes in values within a design – instead of INOUT mode • Each signal has a history of values i.e. they hold a list of values which include current value of the signal and a set of possible future values that can appear on the signal • Computed value is assigned to signal after specified delay called DELTA DELAY
  • 161.
    Variables • These areobjects with single current value • They are used to store the intermediate values between the sequential statements • Variable assignment occurs immediately • Variables can be declared and used inside the process statement only. But they retain their value throughout the entire simulation
  • 162.
    process ( a) variable count : INTEGER : = 1 ; begin count : = count+ 1 ; end process ; Example : count contains the total number of events that occurred on signal a
  • 163.
  • 164.
  • 165.
    Attributes • An attributeis data that are attached to VHDL objects or predefined data about VHDL objects • Examples are the current drive capability of a buffer or the maximum operating temperature of the device • Types are – Data Attributes – Signal Attributes – User-defined Attributes
  • 166.
    Data Attributes The pre-defined,synthesizable data attributes are the following: • d’LOW : Returns lower array index • d’HIGH : Returns upper array index • d’LEFT : Returns leftmost array index • d’RIGHT : Returns rightmost array index • d’LENGTH : Returns vector size • d’RANGE : Returns vector range • d’REVERSE_RANGE: Returns vector range in reverse order
  • 167.
    Example Consider the followingsignal: SIGNAL d : STD_LOGIC_VECTOR (7 DOWNTO 0); Then: d'LOW=0, d'HIGH=7, d'LEFT=7, d'RIGHT=0, d'LENGTH=8, d'RANGE=(7 downto 0), d'REVERSE_RANGE=(0 to 7)
  • 168.
    If the signalis of enumerated type, then: • d’VAL(pos) : Returns value in the position specified • d’POS(value) : Returns position of the value specified • d’LEFTOF(value) : Returns value in the position to the left of the value specified • d’VAL(row, column) : Returns value in the position specified; etc There is little or no synthesis support for enumerated data type attributes
  • 169.
    Signal Attributes Let usconsider a signal s Then: • s’EVENT : Returns true when an event occurs on s • s’STABLE : Returns true if no event has occurred on s • s’ACTIVE : Returns true if s = ‘1’ • s’QUIET <time> : Returns true if no event has occurred during the time specified • s’LAST_EVENT : Returns the time elapsed since last event • s’LAST_ACTIVE: Returns the time elapsed since last s=‘1’ • s’LAST_VALUE : Returns the value of s before the last event; etc.
  • 170.
    Example All four assignmentsshown below are synthesizable and equivalent. They return TRUE when an event (a change) occurs on clk, AND if such event is upward (in other words, when a rising edge occurs on clk) IF (clk'EVENT AND clk='1')... -- EVENT attribute -- used with IF IF (NOT clk'STABLE AND clk='1')... -- STABLE --attribute used -- with IF WAIT UNTIL (clk'EVENT AND clk='1'); -- EVENT --attribute used -- with WAIT IF RISING_EDGE(clk)... -- call to a function
  • 171.
    User-defined Attributes • VHDLalso allows the construction of user-defined attributes • To employ a user-defined attribute, it must be declared and specified Attribute Declaration: ATTRIBUTE attribute_name: attribute_type ; Attribute Specification: ATTRIBUTE attribute_name OF target_name: class IS value; where: attribute_type: any data type (BIT, INTEGER, STD_LOGIC_VECTOR, etc.) class: TYPE, SIGNAL, FUNCTION, etc. value: ‘0’, 27, ‘‘00 11 10 01’’, etc.
  • 172.
    Example ATTRIBUTE number_of_inputs: INTEGER; ATTRIBUTEnumber_of_inputs OF nand3: SIGNAL IS 3; ... inputs <= nand3'number_of_inputs; -- attribute call, -- returns 3
  • 173.
    Generics • As thename suggests, GENERIC is a way of specifying a generic parameter • a static parameter that can be easily modified and adapted to different applications • The purpose is to make the code more flexible and reusable • must be declared in the ENTITY • More than one GENERIC parameter can be specified in an ENTITY
  • 174.
    Syntax GENERIC (parameter_name :parameter_type := parameter_value); The GENERIC statement below specifies a parameter called n, of type INTEGER, whose default value is 8. Therefore, whenever n is found in the ENTITY itself or in the ARCHITECTURE (one or more) that follows, its value will be assumed to be 8 ENTITY my_entity IS GENERIC (n : INTEGER := 8; vector: BIT_VECTOR := "00001111"); PORT (...); END my_entity; ARCHITECTURE my_architecture OF my_entity IS ... END my_architecture; Example
  • 175.
    ARCHITECTURE generic_decoder OFdecoder IS BEGIN PROCESS (ena, sel) VARIABLE temp1 : STD_LOGIC_VECTOR (x'HIGH DOWNTO 0); VARIABLE temp2 : INTEGER RANGE 0 TO x'HIGH; .... Example
  • 176.
    Delays in VHDL •In VHDL, there are three types of delay that are encountered – Inertial delay – Transport delay – Delta delay
  • 177.
    Inertial Delay • Inertialdelay is the default in VHDL • Behaves similarly to the actual device • Output signal of the device has inertia, which must be overcome for the signal to change value • The inertial delay model is by far the most commonly used in all currently available simulators
  • 178.
    Inertial delay preventsprolific propagation of spikes throughout the circuit LIBRARY IEEE; USE IEEE.std_logic_1164.ALL; ENTITY buf IS PORT ( a : IN std_logic; PORT ( b : OUT std_logic); END buf; ARCHITECTURE buf OF buf IS BEGIN b <= a AFTER 20 ns; END buf; Due to inertial delay pulse is swallowed up
  • 179.
    Transport Delay • Itrepresents a wire delay in which any pulse, no matter how small, is propagated to the output signal delayed by the delay value specified • Especially useful for modeling delay line devices, wire delays on a PCB, and path delays on an ASIC
  • 180.
    LIBRARY IEEE; USE IEEE.std_logic_1164.ALL; ENTITYdelay_line IS PORT ( a : IN std_logic; PORT ( b : OUT std_logic); END delay_line; ARCHITECTURE delay_line OF delay_line IS BEGIN b <= TRANSPORT a AFTER 20 ns; END delay_line; Pulse is simply delayed
  • 181.
    Delta delay • Theseare used since the PC that processes and simulates a concurrent phenomenon is basically a sequential machine • The simulation program mimics concurrency by scheduling events in some order • Simulation deltas are used to order some types of events during a simulation • Specifically, zero delay events must be ordered to produce consistent results
  • 182.
    Circuit that showsthe difference! CLK D E Q' Q DFF CLK A B C F D Zero delay components CLK=‘1’ A=‘1’ Assumptions
  • 183.
    Problem when nodelta delay concept is used CLK D E Q' Q DFF CLK A B C F CLK D E Q' Q DFF CLK A B C F CLK D E Q' Q DFF CLK A B C F 1) A becomes 0 2) Evaluate inverter 3) B <= 1 4) Evaluate AND with C=1 5) D<=1 6) Evaluate NAND 7) C<=0CLK D E Q' Q DFF CLK A B C F 8) Evaluate AND 9) D<=0 CLK D E Q' Q DFF CLK A B C F D Unwanted D assertion DD
  • 184.
    Problem when nodelta delay concept is used CLK D E Q' Q DFF CLK A B C F DD 1) A becomes 0 2) Evaluate inverter 3) B <= 1 4) Evaluate NAND 5) C<=0 6) Evaluate AND 7) D<=0 CLK D E Q' Q DFF CLK A B C F CLK D E Q' Q DFF CLK A B C F D CLK D E Q' Q DFF CLK A B C F
  • 185.
    Delta delay use Delta1 Delta 2 Delta 3 Delta 4 10 ns 11 ns A<=0 Evaluate inverter B<=0 Evaluate AND Evaluate NAND D<= 1 C<=0 Evaluate AND D<= 0 To summarize, simulation deltas are an infinitesimal amount of time used as a synchronization mechanism when 0 delay events are present.
  • 186.
  • 187.
    Combinational vs. SequentialLogic The output of the circuit depends solely on the current inputs Output does depend on previous inputs hence storage elements are required Combinational Logic outputinput Storage Elements Present State Next State Combinational Logic outputinput
  • 188.
    Concurrent Code • Considerthe following statement: X = X + Y ; In conventional software X and Y are register locations hence contents of X and Y are added and stored in X Register X Register Y +
  • 189.
    Difference in VHDL •In VHDL the same statement will mean a feedback in a purely combinational logic which is invalid + X Y
  • 190.
    • VHDL codeis inherently concurrent (parallel) • Only statements placed inside a PROCESS, FUNCTION, or PROCEDURE are sequential • Concurrent code is also called dataflow code • Order does not matter • We can only build combinational logic circuits with concurrent code • Concurrent assignment produces one driver for each assignment statement z <= a; a z
  • 191.
    Multiple driver assignment architectureABC of XYZ is signal z,a,b,c,d : std_logic ; begin z <= a and b; z <= c and d; . . . ? a b c d z Care has to be taken to handle such conditions with a hi-impedance state
  • 192.
  • 193.
  • 194.
    Types of concurrentconstructs • when … else • with … select These constructs need not be in the process
  • 195.
    when…else • A concurrentstatement which assigns one of several expressions to a signal, depending on the values of Boolean conditions which are tested in sequence • Equivalent to a process containing an if statement Syntax [Label:] Target <= [Options] Expression [after TimeExpression] when Condition else Expression [after TimeExpression] when Condition else ... Expression [after TimeExpression] [when Condition];
  • 196.
    Where to use? architecture – begin – HERE - end block – begin – HERE - end generate – begin – HERE - end Rules: • The reserved word guarded may only appear in a signal assignment within a guarded block. A guarded assignment only executes when the guard expression on the surrounding block is true • An Expression on the right hand side may be replaced by the reserved word “unaffected”
  • 197.
    Synthesis • Conditional signalassignments are synthesized to combinational logic • The Expressions on the right hand side are multiplexed onto the Target signal • The resulting logic will be priority encoded, because the conditions are tested in sequence Remarks: • Conditional and selected signal assignments are a concise way to describe combinational logic in Register Transfer Level descriptions, although processes can be easier to read and maintain in some cases • A conditional assignment is a neat way to convert from a Boolean condition to the type Std_logic
  • 198.
    Example z <= awhen s1=‘1’ else b when s2=‘1’ else c ; c b a s2 s1 z MUX21 MUX21
  • 199.
    Example (Tri-state Buffer) architecturetri_buff of tri_buff_part is begin out1 <= in1 when control=‘1’ else ‘z’; end tri_buff ; in1 out1 control
  • 200.
    with…select • A concurrentstatement which assigns one of several expressions to a signal, depending on the value of the expression at the top. • Equivalent to a process containing a case statement Syntax [Label:] with Expression select Target <= [Options] Expression [after TimeExpression] when Choices, Expression [after TimeExpression] when Choices, Expression when others;
  • 201.
    Where to use? architecture – begin – HERE – end block – begin – HERE – end generate – begin – HERE – end Rules: • Every case of the Expression at the top must be covered once and only once by the choices • An Expression on the right hand side may be replaced by the reserved word “unaffected” • All possible choices must be enumerated • “others” clause is important since we have 9- valued logic
  • 202.
    Synthesis • Selected signalassignments are synthesized to combinational logic • The Expressions on the right hand side are multiplexed onto the Target signal Remarks: • Conditional and selected signal assignments are a good way to describe combinational logic in Register Transfer Level descriptions
  • 203.
    Example (Multiplexer) architecture mux41of mux is -- Assumptions begin -- a,b,c,d,z are with control select -- std_logic z <= a when “00” , -- control is b when “01” ,-- std_logic_vector(1 downto 0) c when “10” , d when “11” , ‘Z’ when others ; end mux41 ; control a b c d z MUX41
  • 204.
    Block • There aretwo types of blocks – Simple – Guarded
  • 205.
    Simple block • TheBLOCK statement, in its simple form, represents only a way of locally partitioning the code • It allows a set of concurrent statements to be clustered into a BLOCK, with the purpose of turning the overall code more readable and more manageable (which might be helpful when dealing with long codes)
  • 206.
    Syntax label: BLOCK [declarative part] BEGIN (concurrentstatements) END BLOCK label; ARCHITECTURE example ... BEGIN ... block1: BLOCK BEGIN ... END BLOCK block1 ; ... block2: BLOCK BEGIN ... END BLOCK block2 ; ... END example ; General form of architecture using block for partitioning
  • 207.
    • Block canbe nested inside another block Syntax label1: BLOCK [declarative part of top block] BEGIN [concurrent statements of top block] label2: BLOCK [declarative part nested block] BEGIN (concurrent statements of nested block) END BLOCK label2; [more concurrent statements of top block] END BLOCK label1;
  • 208.
    Guarded block • Aguarded BLOCK is a special kind of BLOCK, which includes an additional expression, called guard expression • A guarded statement in a guarded BLOCK is executed only when the guard expression is TRUE Syntax label: BLOCK (guard expression) [declarative part] BEGIN (concurrent guarded and unguarded statements) END BLOCK label;
  • 209.
    • Even thoughonly concurrent statements can be written within a BLOCK, with a guarded BLOCK even sequential circuits can be constructed LIBRARY ieee; USE ieee.std_logic_1164.all; ENTITY latch IS PORT (d, clk: IN STD_LOGIC; q: OUT STD_LOGIC); END latch; ARCHITECTURE latch OF latch IS BEGIN b1: BLOCK (clk='1') BEGIN q <= GUARDED d; END BLOCK b1; END latch; Latch
  • 210.
    LIBRARY ieee; USE ieee.std_logic_1164.all; ENTITYDFF IS PORT (d, clk, rst: IN STD_LOGIC; q: OUT STD_LOGIC); END DFF; ARCHITECTURE DFF OF DFF IS BEGIN b1: BLOCK (clk’EVENT AND clk='1') BEGIN q <= GUARDED ‘0’ WHEN rst=‘1’ ELSE d; END BLOCK b1; END DFF; Here, a positive-edge sensitive D-type flip-flop, with synchronous reset, is designed. In it, clk'EVENT AND clk='1' is the guard expression, while q <= GUARDED '0‘ WHEN rst='1' is a guarded statement. Therefore, q<='0' will occur when the guard expression is true and rst is ‘1’ DFF
  • 211.
  • 212.
    For ALU inproblem 2 sel Operation Function Unit 0000 y <= a Transfer a Arithmetic 0001 y <= a+1 Increment a 0010 y <= a-1 Decrement a 0011 y <= b Transfer b 0100 y <= b+1 Increment b 0101 y <= b-1 Decrement b 0110 y <= a + b Add a and b 0111 y <= a + b + cin Add a and b with carry 1000 y <= NOT a Complement a Logic 1001 y <= NOT b Complement b 1010 y <= a AND b AND 1011 y <= a OR b OR 1100 y <= a NAND b NAND 1101 y <= a NOR b NOR 1110 y <= a XOR b XOR 1111 y <= a XNOR b XNOR
  • 213.
    3) Priority Encoder Thecircuit must encode the address of the input bit of highest order that is active. ‘‘000’’ should indicate that there is no request at the input (no bit active)
  • 214.
  • 215.
  • 216.
  • 217.
    Component • A componentis analogous to a chip socket; it gives an indirect way to use one hierarchical block within another • A component is instantiated within an architecture, and is associated with a (lower level) entity and architecture during elaboration using information from a configuration. • A component declaration is similar in form to an entity declaration, in that it includes the required ports and parameters of the component • The difference is that it refers to a design described in a separate VHDL file • The ports and parameters in the component declaration may be a subset of those in the component file, but they must have the same names
  • 218.
    Component can bedeclared in the main code itself
  • 219.
    Component can bedeclared in a package
  • 220.
    Syntax : COMPONENT component_name GENERIC( parameter_name : string := default_value ; parameter_name : integer := default_value); PORT (input_name, input_name : IN STD_LOGIC; bidir_name, bidir_name : INOUT STD_LOGIC; output_name, output_name : OUT STD_LOGIC); END COMPONENT; Where : package - <HERE> - end architecture - is - <HERE> - begin - end block - <HERE> - begin - end generate - <HERE> - begin - end
  • 221.
    Rules: • For defaultconfiguration, the component name must match the name of the corresponding entity to be used in its place, and generics and ports must also match in name, mode and type Synthesis: • A component without a corresponding design entity is synthesized as a black box In VHDL'93, components are not necessary. It is possible instead to directly instantiate an entity within an architecture.
  • 222.
    Example component Counter generic (N:INTEGER); port (Clock, Reset, Enable: in Std_logic; Q: buffer Std_logic_vector (N-1 downto 0)); end component ;
  • 223.
    Instantiation • A concurrentstatement used to define the design hierarchy by making a copy of a lower level design entity within an architecture • In VHDL'93, a direct instantiation of an entity bypasses the component and configuration
  • 224.
    Syntax: InstanceLabel: [component] ComponentName [GenericMap][PortMap]; InstanceLabel: entity EntityName[(ArchitectureName)] [GenericMap] [PortMap]; InstanceLabel: configuration ConfigurationName [GenericMap] [PortMap]; Where: architecture – begin - <HERE> - end block – begin - <HERE> - end generate – begin - <HERE> - end
  • 225.
    Rules: • An entity,architecture or configuration must be compiled into a library before the corresponding instance can be compiled • However, an instance of a component can be compiled before the corresponding design entity has even been written Example : G1: NAND2 generic map (1.2 ns) port map (N1, N2, N3); G2: entity WORK.Counter(RTL) port map (Clk, Rst, Count);
  • 226.
    Generic Map • Usedto define the values of generics • Usually given in an Instance, but may also appear in a configuration Syntax generic map ([Formal =>] Actual, ...) Formal = {either} Name FunctionCall Actual = Expression
  • 227.
    Where : Label :ComponentName <HERE> port map (…); for - use - <HERE> port map (…) block – generic (…); <HERE> ; port – begin - end Rules : The two forms of syntax (ordered list or explicitly named choices) can be mixed, but the ordered list must come before the named choices A generic map does not end with a semicolon!
  • 228.
    Example: architecture Structure ofEnt is component NAND2 generic (TPLH, TPHL: TIME := 0 NS); port (A, B: in STD_LOGIC; F : out STD_LOGIC); end component; begin G1: NAND2 generic map (1.9 NS, 2.8 NS) port map (N1, N2, N3); G2: NAND2 generic map (TPLH => 2 NS, TPHL => 3 NS) port map (N4, N5, N6); end Structure;
  • 229.
    Port Map • Aport map is typically used to define the interconnection between instances in a structural description (or netlist) • A port map maps signals in an architecture to ports on an instance within that architecture • Port maps can also appear in a configuration or a block
  • 230.
    Syntax: port map ([Formal=>] Actual, ...); Formal = {either} Name FunctionCall Actual = {either} Name FunctionCall open Where: Label : ComponentName generic map (…) <HERE>; for - use - generic map (…) <HERE>; block - port (…) ; <HERE>; - begin - end
  • 231.
    Rules: • The twoforms of syntax (ordered list or explicitly named ports) can be mixed, but the ordered list must come before the named ports • Within an instance, the formals are ports on the component or entity being instanced, the actuals are signals visible in the architecture containing the instance • Within a configuration, the formals are ports on the entity, the actuals are ports on the component • If the actual is a conversion function, this is called implicitly as values are passed in • If the formal is a conversion function, this is called implicitly as values are passed out Use the port names rather than order to improve readability and reduce the risk of making connection errors
  • 232.
    Example: component COUNTER port (CLK,RESET: in Std_logic; UpDown: in Std_logic := '0';-- default value Q: out Std_logic_vector(3 downto 0)); end component; ... -- Positional association... G1: COUNTER port map (Clk32MHz, RST, open, Count); -- Named association (order doesn't matter)... G2: COUNTER port map ( RESET => RST, CLK => Clk32MHz, Q(3) => Q2MHz, Q(2) => open, -- unconnected Q(1 downto 0) => Cnt2, UpDown => open);
  • 233.
    Top Level Entityand Lower Level Entity TOP LEVEL ENTITY Clk32MHz Q2MHz Cnt2 RST COUNT COUNTER (LOWER LEVEL ENTITY) CLK RESET Q Updown
  • 234.
  • 235.
    A still simplerexample entity ND4 is port (in1,in2,in3,in4 : in std_logic ; z : out std_logic); end ND4; architecture ND4_CI of ND4 is component ND2 port (a , b : in std_logic; c : out std_logic); end component ; signal temp1, temp2 : std_logic; begin U1 : ND2 port map (a => in1 , b => in2 , c => temp1); U2 : ND2 port map (a => in3 , b => in4 , c => temp2); U3 : ND2 port map (a => temp1 , b => temp2 , c => z); end ND4_CI ;
  • 236.
    infers… ND4 U1 U3 U2 IN1 IN2 IN3 IN4 Z a a b b a b c c c c => temp1for U1 a => temp1 for U3 c => temp2 for U2 b => temp2 for U3
  • 237.
    Generate statement • Aconcurrent statement used to create regular structures or conditional structures during elaboration • Used to create multiple copies of components , processes or blocks • It provides a compact description of regular structures such as memories , registers and counters
  • 238.
    • Two flavoursof generate statement are: – for … generate • Number of copies is determined by a discrete range – if … generate • Zero or one copy is made conditionally • Range must be a computable integer in any of the following forms: – integer_expression to integer_expression – integer_expression downto integer_expression – Each integer_expression evaluates to an integer
  • 239.
    Syntax : Label: forParameterName in Range generate [Declarations... begin] ConcurrentStatements... end generate [Label]; Label: if Condition generate [Declarations... begin] ConcurrentStatements... end generate [Label];
  • 240.
    Where: architecture – begin- <HERE> - end block – begin - <HERE> - end generate – begin - <HERE> - end Rules : • The Range and Condition must both be static, i.e. they cannot include signals • The Label at the beginning of the generate statement cannot be omitted Synthesis: • Synthesis is straightforward, but not all synthesis tools support generate!
  • 241.
    Example: architecture ABC offull_add4 is component full_add port (PA , PB , PC : in std_logic ; PCOUT , PSUM : out std_logic) ; end component ; signal c: std_logic_vector(4 downto 0); begin c(0) <= cin ; -- cin is declared in entity GK : for k in 3 downto 0 generate FA :full_add port map(A(k),B(k),C(k),C(k+1),SUM(k); end generate GK ; cout <= c(4) ; -- cout is declared in entity end ABC ;
  • 242.
    infers… FA2 A(2) B(2) C(2) SUM(2) FA3 A(3) B(3) Cout SUM(3) FA0 A(0)B(0) Cin C(1) SUM(0) FA1 A(1) B(1) SUM(1) C(3)
  • 243.
    architecture SHIFTER_ARCH ofSHIFTER is component DFF port (D , CLK : in std_logic ; Q : out std_logic) ; end component ; begin GK : for k in 0 to 3 generate GK0 : IF k=0 generate DFILPFLOP : DFF port map (count , clock , Q(k)); end generate GK0 ; GK1_3 : if k > 0 generate DFILPFLOP : DFF port map (Q(k-1), clock , Q(k)); end generate GK1_3 ; end generate GK ; end SHIFTER_ARCH ; Another example
  • 244.
  • 245.
    Ways to describea circuit! • Three types of descriptions possible with VHDL – Structural – Dataflow – Behavioral
  • 246.
    Structural Method • Atthe structural level, which is the lowest level, you have to first manually design the circuit. • Use VHDL to specify the components and gates that are needed by the circuit and how they are connected together by following your circuit exactly • Synthesizing a structural VHDL description of a circuit will produce a netlist that is exactly like your original circuit • The advantage of working at the structural level is that you have full control as to what components are used and how they are connected. • But you need to first come up with the circuit and so the full capabilities of the synthesizer are not utilized
  • 247.
    Dataflow Method • Atthe dataflow level, you use the built-in logical functions of VHDL in signal assignment statements to describe a circuit, which again you have to first design manually • Boolean functions that describe a circuit can be easily converted to signal assignment statements using the built-in logical functions • The only drawback is that the built-in logical functions such as the AND and OR function only take two operands. This is like having only 2-input gates to work with ! All the statements use in the structural and dataflow level are executed concurrently
  • 248.
    Behavioral Method • Describinga circuit at the behavioral level is most similar to writing a computer program • You have all the standard high-level programming constructs such as the FOR LOOP, WHILE LOOP, IF THEN ELSE, CASE, and variable assignments • The statements are enclosed in a process block and are executed sequentially
  • 249.
    Example BCD to 7-segment display decoder a b c d e f g BCD to 7-segment display decoder I3 I2 I1 I0 segs(6) {seg 'a'} segs(5) {seg 'b'} segs(4) {seg 'c'} segs(3) {seg 'd'} segs(2) {seg 'e'} segs(1) {seg 'f'} segs(0) {seg 'g'}
  • 250.
  • 251.
    Logic Equations 2 10 3 1 2 0 ' ' 2 1 0 ' ' ' ' ' 1 0 2 0 2 1 2 1 0 ' ' ' 1 0 2 0 ' ' ' ' 3 2 1 2 0 1 0 ' 3 2 1 1 0 ( ) ( ) ( ) a I I I I b I I I c I I I d I I I I I I I I I e I I I I f I I I I I I I g I I I I I = + + = + = + + = + + + = + = + + + = + ⊕ +
  • 252.
  • 253.
    Structural VHDL description ENTITYmyxnor2 IS PORT(i1, i2: IN BIT;o: OUT BIT); END myxnor2; ARCHITECTURE Dataflow OF myxnor2 IS BEGIN o <= not(i1 XOR i2); END Dataflow; ENTITY myxor2 IS PORT(i1, i2: IN BIT;o: OUT BIT); END myxor2; ARCHITECTURE Dataflow OF myxor2 IS BEGIN o <= i1 XOR i2; END Dataflow; ENTITY myand2 IS PORT(i1, i2: IN BIT;o: OUT BIT); END myand2; ARCHITECTURE Dataflow OF myand2 IS BEGIN o <= i1 AND i2; END Dataflow;
  • 254.
    ENTITY myand3 ISPORT(i1, i2, i3: IN BIT; o: OUT BIT); END myand3; ARCHITECTURE Dataflow OF myand3 IS BEGIN o <= (i1 AND i2 AND i3); END Dataflow; ENTITY myor2 IS PORT(i1, i2: IN BIT;o: OUT BIT); END myor2; ARCHITECTURE Dataflow OF myor2 IS BEGIN o <= i1 OR i2; END Dataflow; ENTITY myor3 IS PORT(i1, i2, i3: IN BIT;o: OUT BIT); END myor3; ARCHITECTURE Dataflow OF myor3 IS BEGIN o <= i1 OR i2 OR i3; END Dataflow;
  • 255.
    ENTITY myor4 ISPORT(i1, i2, i3, i4: IN BIT; o: OUT BIT); END myor4; ARCHITECTURE Dataflow OF myor4 IS BEGIN o <= i1 OR i2 OR i3 OR i4; END Dataflow; ENTITY inv IS PORT (i: IN BIT; o: OUT BIT); END inv; ARCHITECTURE Dataflow OF inv IS BEGIN o <= not i; END Dataflow;
  • 256.
    LIBRARY ieee; USE ieee.std_logic_1164.all; ENTITYbcd IS PORT(i0, i1, i2, i3: IN BIT; a, b, c, d, e, f, g: OUT BIT); END bcd; ARCHITECTURE Structural OF bcd IS COMPONENT inv PORT (i: IN BIT ;o: OUT BIT); END COMPONENT; COMPONENT myand2 PORT(i1, i2: IN BIT;o: OUT BIT); END COMPONENT; COMPONENT myand3 PORT(i1, i2, i3: IN BIT;o: OUT BIT); END COMPONENT; COMPONENT myor2 PORT(i1, i2: IN BIT;o: OUT BIT); END COMPONENT; COMPONENT myor3 PORT(i1, i2, i3: IN BIT;o: OUT BIT); END COMPONENT; COMPONENT myor4 PORT(i1, i2, i3, i4: IN BIT;o: OUT BIT); END COMPONENT; COMPONENT myxnor2 PORT(i1, i2: IN BIT;o: OUT BIT); END COMPONENT; COMPONENT myxor2 PORT(i1, i2: IN BIT;o: OUT BIT); END COMPONENT;
  • 257.
    SIGNAL j,k,l,m,n,o,p,q,r,s,t,u,v,w,x,y,z: BIT; BEGIN U1:INV port map(i2,j); U2: INV port map(i1,k); U3: INV port map(i0,l); U4: myXNOR2 port map(i2, i0, z); U5: myOR3 port map(i3, i1, z, a); U6: myXNOR2 port map(i1, i0, y); U7: myOR2 port map(j, y, b); U8: myOR3 port map(i2, k, i0, c); U9: myAND2 port map(i1, l, x); U10: myAND2 port map(j, l, w); U11: myAND2 port map(j, i1, v); U12: myAND3 port map(i2, k, i0, t); U13: myOR4 port map(x, w, v, t, d); U14: myAND2 port map(i1, l, s); U15: myAND2 port map(j, l, r); U16: myOR2 port map(s, r, e); U17: myAND2 port map(i2, k, q); U18: myAND2 port map(i2, l, p); U19: myAND2 port map(k, l, o); U20: myOR4 port map(i3, q, p, o, f); U21: myXOR2 port map(i2, i1, n); U22: myAND2 port map(i1, l, m); U23: myOR3 port map(i3, n, m, g); END Structural;
  • 258.
    Dataflow VHDL description LIBRARYieee; USE ieee.std_logic_1164.all; ENTITY bcd IS PORT ( I: IN STD_LOGIC_VECTOR (3 DOWNTO 0); Segs: OUT std_logic_vector (1 TO 7)); END bcd; ARCHITECTURE Dataflow OF bcd IS BEGIN Segs(1) <= I(3) OR I(1) OR NOT (I(2) XOR I(0)); -- seg a Segs(2) <= (NOT I(2)) OR NOT (I(1) XOR I(0)); -- seg b Segs(3) <= I(2) OR (NOT I(1)) OR I(0); -- seg c Segs(4) <= (I(1) AND NOT I(0)) OR (NOT I(2) AND NOT I(0)) -- seg d OR (NOT I(2) AND I(1)) OR (I(2) AND NOT I(1) AND I(0)); Segs(5) <= (I(1) AND NOT I(0)) OR (NOT I(2) AND NOT I(0)); -- seg e Segs(6) <= I(3) OR (I(2) AND NOT I(1)) -- seg f OR (I(2) AND NOT I(0)) OR (NOT I(1) AND NOT I(0)); Segs(7) <= I(3) OR (I(2) XOR I(1)) OR (I(1) AND NOT I(0)); -- seg g END Dataflow;
  • 259.
    Behavioral VHDL description libraryIEEE; use IEEE.STD_LOGIC_1164.all; entity BCD is port( I : in STD_LOGIC_VECTOR(3 downto 0); segs : out STD_LOGIC_VECTOR(6 downto 0) ); end BCD; architecture Behavioral of BCD is begin with I select Segs <= "1111110" when "0000", "0110000" when "0001", "1101001" when "0010", "1111001" when "0011", "0110011" when "0100", "1011011" when "0101", "1011111" when "0110", "1110000" when "0111", "1111111" when "1000", "1110011" when "1001", "0000000" when others; end Behavioral;
  • 260.
  • 261.
    Equations for carry_generate(G)and carry_propagate(P) for ALU 74181 Carry Lookahead Logic xi yi xi-1 x0 yi-1 y0 c0 ci hsi si gi= xi . yi pi=xi + yi ci+1= gi + pi . ci Assignment No 3
  • 262.
    c1= g0 +p0 . c0 c2= g1 + p1 . g0 + p1.p0.c0 c3= g2 + p2 . g1 + p2.p1.g0+p2.p1.p0.c0 c4= g3 + p3 . g2 + p3.p2.g1+p3.p2.p1.g0+p3.p2.p1.p0.c0 Additional Information
  • 263.
    G_L= (g3+p3.g2+p3.p2.g1+p3.p2.p1.g0)’ P_L=(p3.p2.p1.p0)’ Implement theCarry_Generate and Carry_Propagate outputs also to complete the ALU assignment Equations for implementation of G_L , P_L outputs
  • 264.
  • 265.
    ‘generate’d doubt ! fulladder GK.0.FA fulladder GK.3.FA fulladder GK.2.FA fulladder GK.1.FA COUT [4] SUM[3:0] [3:0] Cin B[3:0][3:0] A[3:0] [3:0] [0] PA [0] PB PC [1] PCOUT [0] PSUM [3] PA [3] PB [3] PC [4] PCOUT [3] PSUM [2] PA [2] PB [2] PC [3] PCOUT [2] PSUM [1] PA [1] PB [1] PC [2] PCOUT [1] PSUM fulladder GK.3.FAfulladder GK.0.FA fulladder GK.1.FA fulladder GK.2.FA COUT [4] SUM[3:0] [3:0] Cin B[3:0] [3:0] A[3:0] [3:0] [3] PA [3] PB [3] PC [4] PCOUT [3] PSUM [0] PA [0] PB PC [1] PCOUT [0] PSUM [1] PA [1] PB [1] PC [2] PCOUT [1] PSUM [2] PA [2] PB [2] PC [3] PCOUT [2] PSUM GK : for k in 3 downto 0 generate GK : for k in 0 to 3 generate=
  • 266.
  • 267.
    Sequential Statements • VHDLcode is inherently concurrent • Sections of code that are executed sequentially are : – PROCESS – FUNCTION – PROCEDURE • One important aspect of sequential code is that it is not limited to sequential logic • We can build sequential circuits as well as combinational circuits • Sequential code is also called behavioral code • Thus a PROCESS is a concurrent statement which describes behaviour
  • 268.
    • Sequential statementsare allowed only inside PROCESSES, FUNCTIONS, or PROCEDURES • Sequential statements are: – IF – WAIT – CASE – LOOP • VARIABLES are also restricted to be used in sequential code only VARIABLE can never be global, so its value can not be passed out directly
  • 269.
    SIGNALS and VARIABLESrevisited ! • VHDL has two ways of passing non-static values around: by means of a SIGNAL or by means of a VARIABLE • A SIGNAL can be declared in a PACKAGE, ENTITY or ARCHITECTURE (in its declarative part), while a VARIABLE can only be declared inside a piece of sequential code • SIGNAL is global while VARIABLE is local • The value of a VARIABLE can never be passed out of the PROCESS directly; if necessary, then it must be assigned to a SIGNAL • Update of VARIABLE is immediate whereas new value for SIGNAL is generally only guaranteed to be available after the conclusion of the present run of the PROCESS • Assignment operator for SIGNAL is “<= “ while that for VARIABLE is “ : = “
  • 270.
    Process • A PROCESSis a sequential section of VHDL code • It is characterized by the presence of IF, WAIT, CASE, or LOOP, and by a sensitivity list (except when WAIT is used) • A PROCESS must be installed in the main code, and is executed every time a signal in the sensitivity list changes (or the condition related to WAIT is fulfilled)
  • 271.
    Syntax [label:] [postponed] PROCESS(sensitivity list) [VARIABLE name type [range] [:= initial_value;]] BEGIN (sequential code) END [postponed] PROCESS [label]; entity - begin - <HERE> - end architecture - begin - <HERE> - end block - begin - <HERE> - end generate - begin - <HERE> - end Where “POSTPONED” is a reserved VHDL word
  • 272.
    Rules • A processmust contain either a sensitivity list or wait statements, but not both • Every process executes once during initialization, before simulation starts • A postponed process is not executed until the final simulation cycle of a particular simulation time, and thus sees the stable values of signals and variables A process with neither a sensitivity list nor a wait will loop forever !
  • 273.
    • To constructa synchronous circuit, monitoring a signal (clock, for example) is necessary • A common way of detecting a signal change is by means of the EVENT attribute • For instance, if clk is a signal to be monitored, then clk ’ EVENT returns TRUE when a change on clk occurs (rising or falling edge) Using EVENT attribute
  • 274.
    IF construct • Asequential statement which executes one branch from a set of branches dependent upon the conditions, which are tested in sequence Syntax [Label:] if Condition then SequentialStatements... [elsif Condition then SequentialStatements...] ... {any number of elsif parts} [else SequentialStatements...] end if [Label]; Be careful about the spelling of elsif and end if
  • 275.
    Synthesis • Assignments withinif statements generally synthesize to multiplexers • Incomplete assignments, where outputs remain unchanged for certain input conditions, synthesize to transparent latches in unclocked processes, and to flip-flops in clocked processes • In some circumstances, nested if statements synthesize to multiple logic levels. This can be avoided by using a case statement instead
  • 276.
    • A setof elsif branches can be used to impart priority to the conditions tested first • To decode a value without giving priority to certain conditions, use a case statement instead Example IF (x<y) THEN temp:="11111111"; ELSIF (x=y AND w='0') THEN temp := "11110000"; ELSE temp:=(OTHERS =>'0');
  • 277.
    D Flip-Flop withasynchronous reset • A D-type flip-flop is the most basic building block in sequential logic circuits. In it, the output must copy the input at either the positive or negative transition of the clock signal (rising or falling edge) If rst = ‘1’, then the output must be q = ‘0’ ,regardless of the status of clk. Otherwise, the output must copy the input (that is, q = d) at the positive edge of clk
  • 278.
    LIBRARY ieee; USE ieee.std_logic_1164.all; ENTITYdff IS PORT (d, clk, rst: IN STD_LOGIC; q: OUT STD_LOGIC); END dff; ARCHITECTURE behavior OF dff IS BEGIN PROCESS (clk, rst) BEGIN IF (rst='1') THEN q <= '0'; ELSIF (clk'EVENT AND clk='1') THEN q <= d; END IF; END PROCESS; END behavior;
  • 279.
  • 280.
    q R q rst clk d Q[0]D[0] Changing thestatement ELSIF (clk'EVENT AND clk=‘0') THEN
  • 281.
    One Digit counterexample Progressive 1-digit decimal counter (0 -> 9 ->0) Single bit input (clk) and a 4-bit output (digit).
  • 282.
    LIBRARY ieee; USE ieee.std_logic_1164.all; ENTITYcounter IS PORT (clk : IN STD_LOGIC; digit : OUT INTEGER RANGE 0 TO 9); END counter; ARCHITECTURE counter OF counter IS BEGIN count: PROCESS (clk) VARIABLE temp : INTEGER RANGE 0 TO 10; BEGIN IF (clk'EVENT AND clk='1') THEN temp := temp + 1; IF (temp=10) THEN temp := 0; END IF; END IF; digit <= temp; END PROCESS count; END counter;
  • 283.
    Output In a counterlike circuits always use comparison statements with constant values This ensures simple comparator inference as against full comparator inference for comparison with unknown values
  • 284.
  • 285.
  • 286.
  • 287.
    Wait statement • Theoperation of WAIT is sometimes similar to that of IF • PROCESS cannot have a sensitivity list when WAIT is employed • Three flavours of WAIT statements are: – WAIT UNTIL – WAIT ON – WAIT FOR
  • 288.
    Syntax WAIT UNTIL signal_condition; •The WAIT UNTIL statement accepts only one signal, thus being more appropriate for synchronous code than asynchronous • Since the PROCESS has no sensitivity list in this case, WAIT UNTIL must be the first statement in the PROCESS • The PROCESS will be executed every time the condition is met
  • 289.
    Example ( 8-bitregister ) PROCESS -- no sensitivity list BEGIN WAIT UNTIL (clk'EVENT AND clk='1'); IF (rst='1') THEN op <= "00000000"; ELSIF (clk'EVENT AND clk='1') THEN op <= inp; END IF; END PROCESS;
  • 290.
    Output and Inference op[7:0] op[7:0] [7:0] inp[7:0][7:0] rst clk [7:0] Q[7:0] [7:0] D[7:0] R Output changes only with clk
  • 291.
    Syntax WAIT ON signal1[, signal2, ... ]; • The WAIT ON statement accepts multiple signals • The PROCESS is put on hold until any of the signals listed changes
  • 292.
    Example ( 8-bitregister ) PROCESS BEGIN WAIT ON clk, rst; IF (rst='1') THEN op <= "00000000"; ELSIF (clk'EVENT AND clk='1') THEN op <= inp; END IF; END PROCESS;
  • 293.
    Output and Inference op[7:0] R op[7:0] [7:0] inp[7:0][7:0] rst clk [7:0] Q[7:0] [7:0] D[7:0] Output changes with clk and rst
  • 294.
    DFF revisited withWAIT! LIBRARY ieee; USE ieee.std_logic_1164.all; ENTITY dff IS PORT (d, clk, rst: IN STD_LOGIC; q: OUT STD_LOGIC); END dff; ARCHITECTURE dff OF dff IS BEGIN PROCESS BEGIN WAIT ON rst, clk; IF (rst='1') THEN q <= '0'; ELSIF (clk'EVENT AND clk='1') THEN q <= d; END IF; END PROCESS; END dff;
  • 295.
    Output and Inference q R q rst clk dQ[0]D[0] Infers exactly the same hardware as the earlier design As a homework problem repeat the one digit counter with WAIT statement
  • 296.
    Syntax WAIT FOR time; •WAIT FOR is intended for simulation only (waveform generation for test-benches)
  • 297.
    Case statement • CASEis another statement intended exclusively for sequential code • The CASE statement (sequential) is very similar to WHEN (combinational) • All permutations must be tested, so the keyword OTHERS is often helpful • Another important keyword is NULL (the counterpart of UNAFFECTED), which should be used when no action is to take place • CASE allows multiple assignments for each test condition while WHEN allows only one
  • 298.
    [Label:] case Expressionis when Choices => SequentialStatements... when Choices => SequentialStatements... ... {any number of when parts} end case [Label]; Syntax Choices = Choice | Choice | ... Choice = {either} ConstantExpression Range others {the last branch}
  • 299.
    Where process – begin- <HERE> - end function – begin - <HERE> - end procedure – begin - <HERE> - end if – then - <HERE> - elsif – then - <HERE>- else - <HERE> - end case - => - <HERE> - when - => - <HERE>- end loop-<HERE>-end
  • 300.
    Rules • The Expressionmust not be enclosed in parenthesis • The type of the Expression must be enumeration, integer, physical, or a one dimensional array • Every case of the Expression must be covered once and only once by the Choices
  • 301.
    Synthesis • Assignments withincase statements generally synthesize to multiplexers • Incomplete assignments (i.e. where outputs remain unassigned for certain input conditions) in unclocked processes synthesize to transparent latches • Incomplete assignments in clocked processes synthesize to recirculation around registers
  • 302.
    Example case ADDRESS is when0 => -- Select a single value A <= '1'; when 1 => A <= '1'; -- More than one statement in a -- branch B <= '1'; when 2 to 15 => -- Select a range of ADDRESS -- values C <= '1'; when 16 | 20 | 24 => -- Pick out several -- ADDRESS values B <= '1'; C <= '1'; D <= '1'; when others => -- Mop up the rest null; end case;
  • 303.
    2 - digitcounter with SSD output COUNTER a b c d e f g a b c d e f g DIGIT 1 7 BITS CLK RST DIGIT 2 Progressive 2-digit decimal counter (0-> 99-> 0) , with external asynchronous reset plus binary-coded decimal (BCD) to seven-segment display (SSD) conversion
  • 304.
    LIBRARY ieee; USE ieee.std_logic_1164.all; ENTITYcounter IS PORT (clk, rst : IN STD_LOGIC; digit1, digit2 : OUT STD_LOGIC_VECTOR (6 DOWNTO 0)); END counter; ARCHITECTURE counter OF counter IS BEGIN PROCESS (clk, rst) VARIABLE temp1: INTEGER RANGE 0 TO 10; VARIABLE temp2: INTEGER RANGE 0 TO 10; BEGIN IF (rst='1') THEN temp1 := 0; temp2 := 0; ELSIF (clk'EVENT AND clk='1') THEN temp1 := temp1 + 1; IF (temp1=10) THEN temp1 := 0; temp2 := temp2 + 1; IF (temp2=10) THEN temp2 := 0; END IF; END IF; END IF;
  • 305.
    CASE temp1 IS WHEN0 => digit1 <= "1111110"; --7E WHEN 1 => digit1 <= "0110000"; --30 WHEN 2 => digit1 <= "1101101"; --6D WHEN 3 => digit1 <= "1111001"; --79 WHEN 4 => digit1 <= "0110011"; --33 WHEN 5 => digit1 <= "1011011"; --5B WHEN 6 => digit1 <= "1011111"; --5F WHEN 7 => digit1 <= "1110000"; --70 WHEN 8 => digit1 <= "1111111"; --7F WHEN 9 => digit1 <= "1111011"; --7B WHEN OTHERS => NULL; END CASE; CASE temp2 IS WHEN 0 => digit2 <= "1111110"; --7E WHEN 1 => digit2 <= "0110000"; --30 WHEN 2 => digit2 <= "1101101"; --6D WHEN 3 => digit2 <= "1111001"; --79 WHEN 4 => digit2 <= "0110011"; --33 WHEN 5 => digit2 <= "1011011"; --5B WHEN 6 => digit2 <= "1011111"; --5F WHEN 7 => digit2 <= "1110000"; --70 WHEN 8 => digit2 <= "1111111"; --7F WHEN 9 => digit2 <= "1111011"; --7B WHEN OTHERS => NULL; END CASE; END PROCESS; END counter;
  • 306.
  • 307.
    Inference DO NOT TRYTO WORK OUT HOW THIS CIRCUIT WORKS !!!
  • 308.
  • 309.
  • 310.
    Loop statement • LOOPis useful when a piece of code must be instantiated several times • Like IF, WAIT, and CASE, LOOP is intended exclusively for sequential code, so it too can only be used inside a PROCESS, FUNCTION, or PROCEDURE. • There are several ways of using LOOP • A loop is an infinite loop (and thus an error) unless it contains an exit or wait statement
  • 311.
    FOR / LOOP:The loop is repeated a fixed number of times [label:] FOR identifier IN range LOOP (sequential statements) END LOOP [label]; WHILE / LOOP: The loop is repeated until a condition no longer holds [label:] WHILE condition LOOP (sequential statements) END LOOP [label]; [label:] LOOP (SequentialStatements) END LOOP [label]; Syntax
  • 312.
    EXIT: Used forending the loop [label:] EXIT [label] [WHEN condition]; NEXT: Used for skipping loop steps [label:] NEXT [loop_label] [WHEN condition]; WAIT : Continue looping until..
  • 313.
    FOR i IN0 TO 5 LOOP x(i) <= enable AND w(i+2); y(0, i) <= w(i); END LOOP; The loop will be repeated unconditionally until i reaches 5 (that is, six times) • One important remark regarding FOR / LOOP is that both limits of the range must be static • Thus a declaration of the type "FOR i IN 0 TO choice LOOP", where choice is an input (non-static) parameter, is generally not synthesizable Example of FOR / LOOP:
  • 314.
    WHILE (i <10) LOOP WAIT UNTIL clk'EVENT AND clk='1'; (other statements) END LOOP; In this example, LOOP will keep repeating while i < 10 Example of WHILE / LOOP: LOOP WAIT UNTIL Clock = '1'; EXIT WHEN Reset = '1'; Div2 <= NOT Div2; END LOOP; Example of WAIT in LOOP :
  • 315.
    FOR i INdata'RANGE LOOP CASE data(i) IS WHEN '0' => count:=count+1; WHEN OTHERS => EXIT; END CASE; END LOOP; Example of EXIT : EXIT implies not an escape from the current iteration of the loop, but rather a definite exit (that is, even if i is still within the data range, the LOOP statement will be considered as concluded). In this case, the loop will end as soon as a value different from ‘0’ is found in the data vector
  • 316.
    FOR i IN0 TO 15 LOOP NEXT WHEN i=skip; -- jumps to next iteration (...) END LOOP; Example with NEXT: NEXT causes LOOP to skip one iteration when i = skip
  • 317.
    Synthesis • Not generallysynthesizable. Some tools do allow loops containing wait statements to describe implicit finite state machines, but this is not a recommended practice
  • 318.
    Example : 8-bitunsigned Carry Ripple Adder + a b s cin cout + a0 b0 c0 c1 s0 + a1 b1 c2 + a7 b7 s7 c8 s1 c7cin cout a b s TOP LEVEL LOWERLEVEL sj = aj XOR bj XOR cj cj+1 = (aj AND bj) OR (aj AND cj) OR (bj AND cj)
  • 319.
    LIBRARY ieee; USE ieee.std_logic_1164.all; ENTITYadder IS GENERIC (length : INTEGER := 8); PORT ( a, b: IN STD_LOGIC_VECTOR (length-1 DOWNTO 0); cin: IN STD_LOGIC; s: OUT STD_LOGIC_VECTOR (length-1 DOWNTO 0); cout: OUT STD_LOGIC); END adder; ARCHITECTURE adder OF adder IS BEGIN PROCESS (a, b, cin) VARIABLE carry : STD_LOGIC_VECTOR (length DOWNTO 0); BEGIN carry(0) := cin; FOR i IN 0 TO length-1 LOOP s(i) <= a(i) XOR b(i) XOR carry(i); carry(i+1) := (a(i) AND b(i)) OR (a(i) AND carry(i)) OR (b(i) AND carry(i)); END LOOP; cout <= carry(length); END PROCESS; END adder;
  • 320.
  • 321.
    Example: Leading Zeros Thecircuit should count the number of leading zeros in a binary vector, starting from the left end 0 0 0 1 1 0 0 0 0123
  • 322.
    LIBRARY ieee; USE ieee.std_logic_1164.all; ENTITYLeadingZeros IS PORT ( data: IN STD_LOGIC_VECTOR (7 DOWNTO 0); zeros: OUT INTEGER RANGE 0 TO 8); END LeadingZeros; ARCHITECTURE behavior OF LeadingZeros IS BEGIN PROCESS (data) VARIABLE count: INTEGER RANGE 0 TO 8; BEGIN count := 0; FOR i IN data'RANGE LOOP CASE data(i) IS WHEN '0' => count := count + 1; WHEN OTHERS => EXIT; END CASE; END LOOP; zeros <= count; END PROCESS; END behavior;
  • 323.
    Output Modify the designfor trailing zeros !
  • 324.
    Comparison between Concurrent andSequential Constructs R.B.Ghongade Lecture 15
  • 325.
    CASE versus IF •Though in principle the presence of ELSE in the IF/ELSE statement might infer the implementation of a priority decoder (which would never occur with CASE), this will generally not happen • When IF (a sequential statement) is used to implement a fully combinational circuit, a multiplexer might be inferred instead • Therefore, after optimization, the general tendency is for a circuit synthesized from a VHDL code based on IF not to differ from that based on CASE
  • 326.
    Same inference ! ----With IF: -------------- IF (sel="00") THEN x<=a; ELSIF (sel="01") THEN x<=b; ELSIF (sel="10") THEN x<=c; ELSE x<=d; ---- With CASE: ------------ CASE sel IS WHEN "00" => x<=a; WHEN "01" => x<=b; WHEN "10" => x<=c; WHEN OTHERS => x<=d; END CASE;
  • 327.
    CASE versus WHEN •CASE and WHEN are very similar. However, while one is concurrent (WHEN), the other is sequential (CASE) WHEN CASE Statement type Concurrent Sequential Usage Only outside PROCESSES, FUNCTIONS, or PROCEDURES Only inside PROCESSES, FUNCTIONS, or PROCEDURES All permutations must be tested Yes for WITH/SELECT/WHEN Yes Max. # of assignments per test One Any No-action keyword UNAFFECTED NULL
  • 328.
    Same functionality ! ----With WHEN: ---------------- WITH sel SELECT x <= aWHEN "000", b WHEN "001", c WHEN "010", UNAFFECTED WHEN OTHERS; ---- With CASE: ---------------- CASE sel IS WHEN "000" => x<=a; WHEN "001" => x<=b; WHEN "010" => x<=c; WHEN OTHERS => NULL; END CASE;
  • 329.
    Using Sequential Codeto Design Combinational Circuits • Sequential code can be used to implement either sequential or combinational circuits • Registers are for sequential circuits necessary, so will be inferred by the compiler • This should not happen for combinational circuits • Also for a combinational circuit, the complete truth-table should be clearly specified in the code
  • 330.
    Rules to befollowed while using sequential code for designing combinational circuits • Rule 1: Make sure that all input signals used (read) in the PROCESS appear in its sensitivity list • Rule 2: Make sure that all combinations of the input/output signals are included in the code; that is, make sure that, by looking at the code, the circuit’s complete truth-table can be obtained (indeed, this is true for both sequential as well as concurrent code)
  • 331.
    • Failing tocomply with rule 1 will generally cause the compiler to simply issue a warning saying that a given input signal was not included in the sensitivity list, and then proceed as if the signal were included. Even though no damage is caused to the design in this case, it is a good design practice to always take rule 1 into consideration • With respect to rule 2, however, the consequences can be more serious because incomplete specifications of the output signals might cause the synthesizer to infer latches in order to hold their previous values
  • 332.
    Bad Combinational Design xshould behave as a multiplexer; that is, should be equal to the input selected by sel; y, on the other hand, should be equal to ‘0’ when sel = ‘‘00’’, or ‘1’ if sel = ‘‘01’’
  • 333.
    LIBRARY ieee; USE ieee.std_logic_1164.all; ENTITYexample IS PORT (a, b, c, d: IN STD_LOGIC; sel: IN INTEGER RANGE 0 TO 3; x,y: OUT STD_LOGIC); END example; ARCHITECTURE example OF example IS BEGIN PROCESS (a, b, c, d, sel) BEGIN IF (sel=0) THEN x<=a; y<=‘0’; ELSIF (sel=1) THEN x<=b; y<=‘1’; ELSIF (sel=2) THEN x<=c; ELSE x<=d; END IF; END PROCESS; END example;
  • 334.
    Output Value of yremains ‘1’ which is not expected Cure for the problem: y<='X'; must be included for other conditions of sel i.e. 2 & 3
  • 335.
    Some templates foruse! process (Inputs) -- All inputs in sensitivity list begin ... -- Outputs assigned for all input conditions ... -- No feedback end process; -- Gives pure combinational logic process (Inputs) -- All inputs in sensitivity list begin if Enable = '1' then ... -- Latched actions end if; end process; -- Gives transparent latches + logic
  • 336.
    process (Clock) --Clock only in sensitivity list begin if Rising_edge(Clock) then -- Test clock edge only ... -- Synchronous actions end if; end process; -- Gives flipflops + logic process (Clock, Reset) -- Clock and reset only in -- sensitivity list begin if Reset = '0' then -- Test active level of -- asynchronous reset ... -- Asynchronous actions elsif Rising_edge(Clock) then -- Test clock edge -- only ... -- Synchronous actions end if; end process; -- Gives flipflops + logic
  • 337.
    process -- Nosensitivity list begin wait until Rising_edge(Clock); ... -- Synchronous actions end process; -- Gives flipflops + logic
  • 338.
    Implementing RAM • Thecircuit has a data input bus (data_in), a data output bus (data_out), an address bus (addr), plus clock (clk) and write enable (wr_ena) pins • When wr_ena is asserted, at the next rising edge of clk the vector present at data_in must be stored in the position specified by addr • The output, data_out, on the other hand, must constantly display the data selected by addr
  • 339.
    LIBRARY ieee; USE ieee.std_logic_1164.all; ENTITYram IS GENERIC ( bits: INTEGER := 8; -- # of bits per word words: INTEGER := 16); -- # of words in the memory PORT ( wr_ena, clk: IN STD_LOGIC; addr: IN INTEGER RANGE 0 TO words-1; data_in: IN STD_LOGIC_VECTOR (bits-1 DOWNTO 0); data_out: OUT STD_LOGIC_VECTOR (bits-1 DOWNTO 0)); END ram; ARCHITECTURE ram OF ram IS TYPE vector_array IS ARRAY (0 TO words-1) OF STD_LOGIC_VECTOR (bits-1 DOWNTO 0); SIGNAL memory: vector_array; BEGIN PROCESS (clk, wr_ena) BEGIN IF (wr_ena='1') THEN IF (clk'EVENT AND clk='1') THEN memory(addr) <= data_in; END IF; END IF; END PROCESS; data_out <= memory(addr); END ram;
  • 340.
  • 341.
  • 342.
    Fundamental units ofVHDL code COVERED SO FAR
  • 343.
    Packages • Frequently usedpieces of VHDL code are usually written in the form of COMPONENTS, FUNCTIONS, or PROCEDURES • Such codes are then placed inside a PACKAGE and compiled into the destination LIBRARY • Packages allow code partitioning, code sharing, and code reuse • Besides COMPONENTS, FUNCTIONS, and PROCEDURES, it can also contain TYPE and CONSTANT definitions • A package is split into a declaration and a body • The package declaration defines the external interface to the package, the package body typically contains the bodies of any functions or procedures defined in the package declaration
  • 344.
    Syntax {declaration} package PackageName is Declarations... end[package] [PackageName]; {body} package body PackageName is Declarations... end [package body] [PackageName];
  • 345.
    • Where afunction or procedure is placed in a package, the declaration and body must conform, i.e. the parameters must be identical between the two • Only definitions placed in the package declaration are visible outside the package REMEMBER THIS ! Common, shared declarations of types, subtypes, constants, procedures, functions and components are best put in a package
  • 346.
    A simple package LIBRARYieee; USE ieee.std_logic_1164.all; PACKAGE my_package IS TYPE state IS (st1, st2, st3, st4); TYPE color IS (red, green, blue); CONSTANT vec: STD_LOGIC_VECTOR(7 DOWNTO 0) := "11111111"; END my_package; The example above shows a PACKAGE called my_package. It contains only TYPE and CONSTANT declarations, so a PACKAGE BODY is not necessary
  • 347.
    LIBRARY ieee; USE ieee.std_logic_1164.all; PACKAGEmy_package IS TYPE state IS (st1, st2, st3, st4); TYPE color IS (red, green, blue); CONSTANT vec: STD_LOGIC_VECTOR(7 DOWNTO 0) := "11111111"; FUNCTION positive_edge(SIGNAL s: STD_LOGIC) RETURN BOOLEAN; END my_package; PACKAGE BODY my_package IS FUNCTION positive_edge(SIGNAL s: STD_LOGIC) RETURN BOOLEAN IS BEGIN RETURN (s'EVENT AND s='1'); END positive_edge; END my_package; Example • This example contains, besides TYPE and CONSTANT declarations, a FUNCTION. • Therefore, a PACKAGE BODY is now needed • This function returns TRUE when a positive edge occurs on clk
  • 348.
    • Any ofthe PACKAGES in the previous examples can now be compiled, becoming then part of our work LIBRARY (or any other) • To make use of it in a VHDL code, we have to add a new USE clause to the main code (USE work.my_package.all), as shown below: LIBRARY ieee; USE ieee.std_logic_1164.all; USE work.my_package.all; ENTITY ... ... ARCHITECTURE ... ...
  • 349.
    Functions & Procedures •FUNCTIONS and PROCEDURES are collectively called subprograms • They are very similar to a PROCESS , for they are the only pieces of sequential VHDL code, and thus employ the same sequential statements (IF, CASE, and LOOP; WAIT is not allowed) • PROCESS is intended for immediate use in the main code, FUNCTIONS & PROCEDURES are intended mainly for LIBRARY allocation, that is, their purpose is to store commonly used pieces of code, so they can be reused or shared by other projects. • A FUNCTION or PROCEDURE can also be installed in the main code itself
  • 350.
    Functions • Used togroup together executable, sequential statements to define new mathematical or logical functions • Also used to define bus resolution functions, operators, and conversion functions between data types • When defined in a package, the function must be split into a declaration and a body
  • 351.
    FUNCTION function_name [<parameterlist>] RETURN data_type IS [declarations] BEGIN (sequential statements) END function_name; <parameter list> = [CONSTANT] constant_name : constant_type ; or <parameter list> = SIGNAL signal_name : signal_type ; Syntax: Function Body
  • 352.
    Where :(FUNCTION DECLARATION) package- <HERE> - end package body - <HERE> - end entity – is - <HERE> - begin - end architecture –is - <HERE> - begin- end block - <HERE> - begin - end generate - <HERE> - begin - end process - <HERE> - begin - end function – is - <HERE> - begin - end procedure – is - <HERE> - begin - end Function Body is NOT allowed inside a Package
  • 353.
    Rules : • Thefunction_name may be an identifier or an operator • Functions cannot assign signals or variables defined outside themselves, nor can then contain wait statements • A function must execute a return statement • Pure functions cannot have side effects - they must do nothing but return a value
  • 354.
    • There canbe any number of such parameters (even zero), can only be CONSTANT (default) or SIGNAL (VARIABLES are not allowed). • Their types can be any of the synthesizable data types (BOOLEAN,STD_LOGIC, INTEGER, etc.) • No range specification should be included (for example, do not enter RANGE when using INTEGER, or TO/DOWNTO when using STD_LOGIC_VECTOR) • On the other hand, there is only one return value, whose type is specified by data_type
  • 355.
    • The returntype must be a name; it cannot include a constraint • Variables defined inside a function are initialized each time the function is called • The declaration and body must conform, i.e. the parameters and return type must be identical between the two • The function declaration ends with a ";", whereas the function body has is at the corresponding point in the syntax REMEMBER THIS !
  • 356.
    Synthesis : • Eachcall to a function is synthesized as a separate block of combinational logic FUNCTION f1 (a, b: INTEGER; SIGNAL c: STD_LOGIC_VECTOR) RETURN BOOLEAN IS BEGIN (sequential statements) END f1; Example : • The function, named f1, receives three parameters (a, b, and c) • a and b are CONSTANTS (notice that the word CONSTANT can be omitted, for it is the default object), while c is a SIGNAL. • a and b are of type INTEGER, while c is of type STD_LOGIC_VECTOR • Notice that neither RANGE nor DOWNTO was specified. • The output parameter (there can be only one) is of type BOOLEAN
  • 357.
    Function Call • Afunction is called as part of an expression. The expression can obviously appear by itself or associated to a statement (either concurrent or sequential) x <= conv_integer(a); -- converts a to an integer -- (expression appears by -- itself) y <= maximum(a, b); -- returns the largest of a -- and b -- (expression appears by itself) IF x > maximum(a, b) ... -- compares x to the -- largest of a, b -- (expression associated to a -- statement) Examples of function calls:
  • 358.
    Function positive_edge( ) •The FUNCTION below detects a positive (rising) clock edge. • It is similar to the IF (clk’EVENT and clk = ‘1’) statement ------ Function body: ----------------------------- FUNCTION positive_edge(SIGNAL s: STD_LOGIC) RETURN BOOLEAN IS BEGIN RETURN (s'EVENT AND s='1'); END positive_edge; ------ Function call: ----------------------------- ... IF positive_edge(clk) THEN... ...
  • 359.
  • 360.
    • Though aFUNCTION is usually placed in a PACKAGE (for code partitioning, code reuse, and code sharing purposes), it can also be located in the main code (either inside the ARCHITECTURE or inside the ENTITY) • When placed in a PACKAGE, then a PACKAGE BODY is necessary, which must contain the body of each FUNCTION (or PROCEDURE) declared in the declarative part of the PACKAGE
  • 361.
    FUNCTION Located inthe Main Code LIBRARY ieee; USE ieee.std_logic_1164.all; ENTITY dff IS PORT ( d, clk, rst: IN STD_LOGIC; q: OUT STD_LOGIC); END dff; ARCHITECTURE my_arch OF dff IS FUNCTION positive_edge(SIGNAL s: STD_LOGIC) RETURN BOOLEAN IS BEGIN RETURN s'EVENT AND s='1'; END positive_edge; BEGIN PROCESS (clk, rst) BEGIN IF (rst='1') THEN q <= '0'; ELSIF positive_edge(clk) THEN q <= d; END IF; END PROCESS; END my_arch;
  • 362.
    FUNCTION Located ina PACKAGE LIBRARY ieee; USE ieee.std_logic_1164.all; PACKAGE my_package IS FUNCTION positive_edge(SIGNAL s: STD_LOGIC) RETURN BOOLEAN; END my_package; PACKAGE BODY my_package IS FUNCTION positive_edge(SIGNAL s: STD_LOGIC) RETURN BOOLEAN IS BEGIN RETURN s'EVENT AND s='1'; END positive_edge; END my_package;
  • 363.
    LIBRARY ieee; USE ieee.std_logic_1164.all; USEwork.my_package.all; ENTITY dff IS PORT ( d, clk, rst: IN STD_LOGIC; q: OUT STD_LOGIC); END dff; ARCHITECTURE my_arch OF dff IS BEGIN PROCESS (clk, rst) BEGIN IF (rst='1') THEN q <= '0'; ELSIF positive_edge(clk) THEN q <= d; END IF; END PROCESS; END my_arch; WORK DESIGN SPACE SHOULD BE VISIBLE TO THE TOP-LEVEL ENTITY
  • 364.
    Function conv_integer( ) LIBRARYieee; USE ieee.std_logic_1164.all; PACKAGE my_package IS FUNCTION conv_integer (SIGNAL vector: STD_LOGIC_VECTOR) RETURN INTEGER; END my_package; PACKAGE BODY my_package IS FUNCTION conv_integer (SIGNAL vector: STD_LOGIC_VECTOR) RETURN INTEGER IS VARIABLE result: INTEGER RANGE 0 TO 2**vector'LENGTH-1; BEGIN IF (vector ( vector'HIGH )='1') THEN result:=1; ELSE result:=0; END IF; FOR i IN (vector'HIGH-1) DOWNTO (vector'LOW) LOOP result:=result*2; IF(vector(i)='1') THEN result:=result+1; END IF; END LOOP; RETURN result; END conv_integer; END my_package; conv_integer( ) function converts a STD_LOGIC_VECTOR value into an INTEGER value
  • 365.
    Algorithm 3 2 10 0 1 0 1 vector Iteration 1: vector’LENGTH=4 vector’HIGH=3 vector ( vector'HIGH )= 0 result=0 Since ‘ vector ( vector'HIGH )= 0 ’ 3 downto 0 ( i = 2 to start with ) result= 0 x 2 result= 0 + 1 since vector(2)= 1 Iteration 2: ( i = 1) result= 1 x 2 result= 2 + 0 since vector(1)= 0 Iteration 3: ( i = 0) result= 2 x 2 result= 4 + 1 since vector(0)= 1 RETURNED : result = 5
  • 366.
    LIBRARY ieee; USE ieee.std_logic_1164.all; USEwork.my_package.all; ENTITY conv_int2 IS PORT ( a: IN STD_LOGIC_VECTOR(0 TO 3); y: OUT INTEGER RANGE 0 TO 15); END conv_int2; ARCHITECTURE my_arch OF conv_int2 IS BEGIN y <= conv_integer(a); END my_arch;
  • 367.
    PROCEDURE • A PROCEDUREis very similar to a FUNCTION and has the same basic purposes • A procedure can return more than one value • Like a FUNCTION, two parts are necessary to construct and use a PROCEDURE: – the procedure itself (procedure body) – procedure call
  • 368.
    Procedure Body PROCEDURE procedure_name[<parameter list>] IS [declarations] BEGIN (sequential statements) END procedure_name; <parameter list> = [CONSTANT] constant_name: mode type; <parameter list> = SIGNAL signal_name: mode type; <parameter list> = VARIABLE variable_name: mode type;
  • 369.
    • A PROCEDUREcan have any number of IN, OUT, or INOUT parameters, which can be SIGNALS, VARIABLES, or CONSTANTS. For input signals (mode IN), the default is CONSTANT, whereas for output signals (mode OUT or INOUT) the default is VARIABLE • WAIT, SIGNAL declarations, and COMPONENTS are not synthesizable when used in a FUNCTION. The same is true for a PROCEDURE, with the exception that a SIGNAL can be declared, but then the PROCEDURE must be declared in a PROCESS. • Moreover, besides WAIT, any other edge detection is also not synthesizable with a PROCEDURE (that is, contrary to a function, a synthesizable procedure should not infer registers)
  • 370.
    Example PROCEDURE my_procedure (a: IN BIT; SIGNAL b, c: IN BIT; SIGNAL x: OUT BIT_VECTOR(7 DOWNTO 0); SIGNAL y: INOUT INTEGER RANGE 0 TO 99) IS BEGIN ... END my_procedure; • The PROCEDURE has three inputs, a, b, and c (mode IN) • a is a CONSTANT of type BIT, while b and c are SIGNALS, also of type BIT. Notice that the word CONSTANT can be omitted for input parameters, for it is the default object (recall, however, that for outputs the default object is VARIABLE) • There are also two return signals, x (mode OUT, type BIT_VECTOR) and y (mode INOUT, type INTEGER)
  • 371.
    Procedure Call • Contraryto a FUNCTION, which is called as part of an expression, a PROCEDURE call is a statement on its own • It can appear by itself or associated to a statement (either concurrent or sequential) Examples of procedure calls: compute_min_max(in1, in2, 1n3, out1, out2); -- statement by itself divide (dividend, divisor, quotient, remainder); -- statement by itself IF (a>b) THEN compute_min_max(in1, in2, 1n3, out1, out2); -- procedure call -- associated to another -- statement
  • 372.
  • 373.
    SIMULATION ISSUES • SIMULATION •SIMULATION PROCESS • DELAY MODELING • TYPES OF SIMULATION
  • 374.
    Simulation • Simulation isa functional emulation of a circuit design through software programs, that use models to replicate how a device will perform in terms of timing and results
  • 375.
    Simulation • Simulation eliminatesthe time-consuming need for constant physical prototyping • Simulation can be performed during ALL stages of verification • Motivation of simulation comes from the need to verify that the HDL code is correctly implementing the design • Simply verify that the design meets its required specification
  • 376.
    Flavours of Simulation •Functional Simulation: Is functional verification of the design without any delays • Pre- Layout simulation: Is functional verification of the design including logic cell delays • Post- Layout simulation: Is performed after physical place and route( interconnect delays are taken into account)
  • 377.
    Simulation at differentLevels a1 1 a2 2 3 a3 4 a4 b1 b2 b3 b4 5 6 7 8 Vcc1 0 GND 0 a1 1 a2 2 3 a3 4 a4 b1 b2 b3 b4 5 6 7 8 Vcc1 0 GND 0 a1 1 a2 2 3 a34 a4 b1 b2 b3 b4 5 6 7 8 Vcc1 0 GND 0 a1 1 a2 2 3 a34 a4 b1 b2 b3 b4 5 6 7 8 Vcc1 0 GND 0 A D Q1 Q4 ENB Register Long card Module Subsystem Chip System
  • 378.
    Comparison for simulation ModuleSubsystem Chip System Stimuli Development Simulation Efficiency Nature of detected problems Bug correction time Time in project Difficult Higher Low level Low Early Easier Low All kinds Higher Late
  • 379.
  • 380.
    Steps in Simulation •COMPILATION * Checks VHDL source code to check syntax and semantic rules of VHDL * If a syntax or semantic error occurs, then the compiler flags off an error message * Else the compiler generates an intermediate code SEMANTICS SYNTAX SCIENCE OF MEANING MECHANISM OF LANGUAGE
  • 381.
    Steps in Simulationcont... • ELABORATION * Ports are created for each instance of a component * Memory storage is allocated for the required signal * Interconnections among the port signals are specified * Mechanism is established for executing the VHDL process in proper sequence
  • 382.
    Steps in Simulationcont... • INITIALIZATION * Initial values preset in the declarations statements are assigned to signals/variables
  • 383.
    Steps in Simulationcont... * Every process is executed until it suspends. Signal values are updated only after this. * Simulator accepts simulation commands like: RUN, ASSIGN,WATCH , which control the simulation of the system • EXECUTION * Simulation ends when all signals have been updated and new values have been assigned to the signals
  • 384.
    SIMULATION PROCESS BASIC DEFINITIONS •EVENT ACHANGE ON COMPONENT OUTPUT THAT WILL BE PROPAGATED •TRANSACTION A CHANGE ON COMPONENT INPUT THAT DOES NOT PROPAGATE
  • 385.
    SIMULATION PROCESS BASIC DEFINITIONScont. •SCHEDULING FUTURE EVENTS GENERATED BY EVALUATION OF A PROCESS •EVALUATION CALCULATING THE OUTPUTS OF COMPONENTS BASED ON INPUTS AND CURRENT STATE
  • 386.
    SIMULATION PROCESS Time Jargon RealTime Simulation Time (As it happens…) (Relative to some arbitrary t=0)
  • 387.
    SIMULATION PROCESS Simulation executesas follows: At t=0 , all gate outputs are set to an unknown value Two queues are set up SIGNALS TO BE UPDATED PROCESSES TO BE EXECUTED
  • 388.
    SIMULATION PROCESS • WhenSimulation time is incremented : • Signal is updated • All processes sensitive to that signal are placed on the process execution queue • Each resumed process is executed until it suspends • Effects of the logic changes that have occurred as a result of process execution are evaluated • Simulation time is set to the next event in queue or halted if simulation time gets exhausted One loop is called DELTA CYCLE
  • 389.
    SIMULATION DELTA • Whatis simulation delta? •Several logic changes occur simultaneously in a circuit (concurrent operations) •But simulator being run by a sequential machine, hence it cannot process events concurrently. •To take care this, time is frozen within the simulator. •The real time the simulator takes to complete all concurrent operations in the queue is called SIMULATION DELTA
  • 390.
    SIMULATION DELTA t=0 nst=1 ns Zero simulation time t=2 ns t=3 ns t=4 ns Many delta cycles can occur Real Time The minimum time interval possible for the simulator is assumed to be 1 ns here
  • 391.
    SIMULATION DELTA • SUMMARY Simulationdeltas allow ordering of events that occur at the same simulation time during simulation Simulation deltas are infinitesimal amount of time used as synchronism mechanism when zero delay events are present
  • 392.
    DELAY MODELING Delays aretiming parameters given by the user for modeling physical characteristics of hardware Types of delays INERTIAL DELAY TRANSPORT DELAY Delays are specified in signal assignment statements only Delays should NOT be used in variable assignments
  • 393.
    INERTIAL DELAY • Itis used to model the inherent inertia of physical devices • Example: – The input value must be stable for a specified minimum pulse duration before the value is allowed to propagate to the output – If the input is not stable for the specified limit, no output change occurs
  • 394.
    TRANSPORT DELAY • Itrepresents pure propagation delay i.e., wires and interconnect delays • Signal value is assigned with a specified delay independent of the width of the input waveform
  • 395.
    DELAYS 10 ns 3ns 10 ns 2 ns 6 ns X Z1 Z2 Z3
  • 396.
    TYPES OF SIMULATION •FUNCTIONAL SIMULATION • BEHAVIORAL SIMULATION • STATIC TIMING SIMULATION • GATE-LEVEL SIMULATION • SWITCH-LEVEL SIMULATION • TRANSISTOR-LEVEL OR CIRCUIT- LEVEL SIMULATION
  • 397.
    TYPES OF SIMULATION •FUNCTIONAL SIMULATION It ignores timing aspects Verifies only the functionality of the design • BEHAVIORAL SIMULATION A given functionality is modeled using HDL Timing aspects are considered
  • 398.
    TYPES OF SIMULATION •STATIC TIMING SIMULATION A built in tool that computes delay for each timing path Does not require input stimuli • GATE-LEVEL SIMULATION Is used to check the timing performance of design Delay parameters of logic cells are used to verify things
  • 399.
    TYPES OF SIMULATION •SWITCH-LEVEL SIMULATION Is one level below the gate level simulation It models transistors as switches It provides more accurate timing predictions than gate-level simulation
  • 400.
    TYPES OF SIMULATION •TRANSISTOR-LEVEL SIMULATION Requires transistor models. Circuit is described in terms of resistances, capacitances and voltage and current sources A set of mathematical equations relating current and voltages is setup and solved numerically Gives analog results and is most accurate Requires large amount of computing resources
  • 401.
    And finally!! Simulation timedepends on : • Simulation levels of logic • Physical Memory of PC • Speed of PC
  • 402.
  • 403.
    Test benches inVHDL Copyright, R.B.Ghongade R.B.Ghongade Lecture 18,19
  • 404.
    • A designis always incomplete without verification • There are several ways to verify VHDL designs • Test benches are one of them • Test benches are also called Test cases Introduction
  • 405.
    • A testbenchis an environment, where a design ( called design or unit under test UUT) is checked – applying signals (stimuli) – monitoring its responses by signal probes and monitors • A testbench substitutes the design’s environment in such a way that the behaviour of the design can be observed and analyzed.
  • 406.
    A testbench alwaysconsists of following elements: – a socket for the unit under test (UUT) – a stimuli generator (a subsystem that applies stimuli to UUT, either generating them internally or reading from an external source) – tools for observing UUT responses to the stimuli
  • 407.
  • 408.
    • A VHDLtest bench is just another specification with its own • entity • architecture • In addition, it has special structure with some elements that are characteristic to this type of specification: • Test bench entity has no ports, • UUT component instantiation - the relationship between the test bench and UUT is specified through component instantiation and structural-type specification, • Stimuli - it is a set of signals that are declared internally in the test bench architecture and assigned to UUT's ports in its instantiation. The stimuli are defined as waveforms in one or more behavioral processes. Elements of a VHDL Test Bench
  • 410.
    Using Test Benches •The design must be verifiable. • It is much more convenient to use a test bench for design verification. • Writing a test bench -> very complex task • Therefore some guidelines for future stimuli development should be written as you progress with the design. • It is the test bench which is simulated, not the unit under test. • The UUT is only one of the components instantiated in a test bench. • There is no limitation on the test bench size. • The only limitation is the VHDL simulator used capability.
  • 411.
    DESIGN VERIFICATIONThe design processconsists of design and verification phases The objective of the first one is to create a new VHDL specification that meets the system requirements. Design Specification Stimuli Definitions Test bench Specifications Test bench Simulation Simulation of the test bench is the last phase of a design process. Here you will receive an answer to the question; "does the system behave as expected?" Remember that the answer received from simulating test bench is reliable only to the extent determined by the test bench accuracy and coverage area. The better a test bench is, the more confident you can be that your system is properly designed. Writing stimuli can be performed concurrently with writing specifications for each new design block. The stimuli set should contain such set of input (and state) signal values that covers as much real life situations as possible. When stimuli are specified, a test bench specification can be written It will contain the stimuli and an instantiation of the designed system (unit under test). It is the test bench and not design that will be simulated during the verification phase.
  • 412.
  • 413.
    Example : J-KFlipFlop
  • 414.
    Closer look atTestbench UUT: 2- bit Multiplexer
  • 415.
  • 416.
  • 417.
    Testbench : Usingassert…report
  • 418.
  • 419.
  • 420.
    SUMMARY • A Testbench thus is an effective built- in tool for verifying VHDL designs •Troubleshooting becomes easier and faster because of the ASSERT…REPORT clause •Automation of verification is possible because of the seamless integration of language elements.
  • 421.
  • 422.
    Agenda • What issynthesis ? • Synthesis Tools : Expectations • Synthesis Tools : Features • Hardware modeling examples • Good coding Practices • Synthesis guidelines
  • 423.
    What is synthesis? • Synthesis is an automatic process that converts user’s hardware description into structural logic description • When we use VHDL as textual file, the process is called VHDL Synthesis • Synthesis is a means of converting HDL into real world hardware • Synthesis tools generate a gate-level netlist for the target technology
  • 424.
    What is synthesis? x <= ( a and b ) or ( c and d ); SYNTHESIS = TRANSLATION + OPTIMIZATION a b c d x a b c d x LUT a b c d x • Synthesis is target device technology specific • Synthesizer will try to use the best architectural resource available with the target
  • 425.
    Several steps workout behind the scene! • Translation ( language synthesis ) : Design at higher level of description is compiled into known language elements • Optimization : Algorithms are applied to make the design compact and fast • Design is mapped using architecture specific techniques Translation Optimization Mapping Hardware Description - written with hardware in mind Mix of Boolean , other operations and memory elements Gate Level – Technology Specific
  • 426.
    Synthesis process –design flow HDL behavioral description RTL Synthesis RTL Optimization High-level description with Boolean equations Netlist Logic extraction Structured Boolean equations Logic Optimization Structured Boolean equations Technology mapping Gate-level optimization Optimized Netlist
  • 427.
    • Translation :Inputs are transformed into a description based Boolean equations – If the input data consists of gate level netlist then it is necessary to extract Boolean equations to determine functionality of all used gates • Technology independent logic optimization: This process aims to improve structure of Boolean equations by applying rules of Boolean algebra . This removes the redundant logic and reduces the space requirement • Technology Mapping: This is the process of transforming technology independent netlist into technology dependent one. During mapping , timing and area information of all usable gates of the target technology must be available. It is split into two phases – Flattening – Structuring Synthesis process
  • 428.
    Flattening • The aimis to generate Boolean equations for each output of module in such a way that the output value is a direct function of inputs. These equations reflect two level logic in SOP form. • Resulting equations do not imply any structure • Good optimization results are obtained • Caution: In case of structured logic this process would destroy the characteristic structure and its associated properties . e.g. carry look ahead adder • Flattening cannot be applied to every logic circuit because the number of product terms may become very large
  • 429.
    Structuring • New intermediatevariables are inserted during the structuring process • E.g. If (A’.B’.C’) occurs 10 times then the tool may assign X= (A’.B’.C’) and use X everywhere • Finally , the sub-functions are substituted into original equations • Compared to the logic before structuring, the resulting area is reduced
  • 430.
    Synthesis process- review SYNTHESIS DESIGN CONSTRAINT(area, speed) LIBRARIES NETLIST REPORT •Translation process converts RTL to a Boolean form •Optimization is done on the converted Boolean equations •Optimized logic is mapped to technology library •Flattening is a process where all the design hierarchy is removed, the entire design is transformed into a flat , generic , SOP form •Structuring is the opposite of flattening, its adds structure to the generic design by extracting common logic factors and representing them as intermediate nodes to produce compact logic
  • 431.
    Synthesis tool :expectations A good synthesis tool should – perform technology specific optimizations i.e. vendor specific FPGAs and CPLds – have best optimization techniques – allow designer control – have broad language coverage – provide user friendly debugging environment – have fast compile times – provide clean and seamless link with backend tools
  • 432.
    Synthesis Tools -features Tool cost depends on features provided by it Desirable features are: – Replicating the logic – Duplicate flip-flops, remove unused logic – optimization across design hierarchy – resource sharing of adders , incrementors, multipliers – automatic RAM inference (RAM logic is automatically mapped to technology specific RAM cells)
  • 433.
    Replicate logic – Replicatelogic to meet fan-out demands – E.g. WR’ may be connected to 100 points hence add buffers to split internally BUF BUF BUF BUF BUF BUF
  • 434.
    Duplicating logic • Wecan duplicate the logic which generates the signal , for minimizing fan-out • Trade-off : Loading effect of signals is reduced hence lowering propagation delay but at the cost of logic and interconnect complexity D Q D Q D Q
  • 435.
    Resource sharing • Somesynthesis tools automatically perform a limited amount of resource sharing ( for arithmetic expressions that are mutually exclusive) • Consider the code: ADDSEL: process( sel, a ,b,c,d) begin if (sel=‘1’ ) then y<= a + b ; else y<= c + d ; end if ; end process ADDSEL ;
  • 436.
    Resource sharing + a b + c d sel + y a c b d sel y Before resource sharing Afterresource sharing An adder requires more floor space than a multiplexer
  • 437.
    Simulation vs. Synthesis •Some simulation constructs are not supported by synthesis tools – e.g. wait statements • Synthesis tools ignore initial values • Care should be taken so that simulation- synthesis mismatch does not occur
  • 438.
    Using Signals orVariables • Variables are used only for convenience of describing behaviour • Variables are used and declared in a process however it cannot be used to communicate between processes • Variable assignments are done immediately and are executed sequentially • Variables may or may not represent physical wires • Signal assignments are done at the end of process • Signals represent physical wires in the circuit
  • 439.
    • Use variablesin combinational processes because there is less simulation overhead • Order dependency – Signal assignments are order independent – Variable assignments are order dependent – Signal assignments under a clocked process are translated into registers – Variable assignments under a clocked process may or may not be translated into registers Using Signals or Variables
  • 440.
    process (clk, a,b, c, d) variable y, x, w : std_logic ; begin if (clk=‘1’ and clk’event) then z1<= y ; y : = x ; x : = a and b ; w : = c and d ; z2<= w ; end if; end process ; Signals or Variables variables are read before being written to , this infers a memory element
  • 441.
  • 442.
    Same process withorder of statements changed process (clk, a, b, c, d) variable y, x, w : std_logic ; begin if (clk='1' and clk'event) then x := a and b ; y := x ; z1<= y ; z2<= w ; w := c and d ; end if; end process ; variables are read before being written to , this infers a memory element
  • 443.
  • 444.
    Hardware modeling examples “Forloop” process(word) variable result : std_logic; begin result:='0'; for i in 0 to 7 loop result := result xor word(i); end loop; op<=result; end process;
  • 445.
    Multiplexer optimization case selis when “000” => y<= data(0); when “001” => y<= data(1); when “010” => y<= data(2); when “011” => y<= data(3); 1) when others => y<= ‘0’; 2) when others => y<= ‘Z’; 3) when others => y<= ‘X’; 4) when others => NULL; end case; The hardware inferred depends on the condition given in the “when others” clause
  • 446.
    Case 1 when others=> y<= ‘0’; Case 2 when others => y<= ‘Z’;
  • 447.
    Case 3 when others=> y<= ‘X’; Case 4 when others => NULL;
  • 448.
    Good coding practices •Good coding style means that the synthesis tool can identify constructs within your code that it can easily map to technology features • All programmable devices may have their unique architectural resources e.g. Xilinx Virtex series has built-in RAM • Coding for performance : – common mistake is to ignore hardware and start coding as if programming. To achieve best performance the designer must think about hardware
  • 449.
    Good coding practices •Improve performance by – avoiding unnecessary priority structures in logic – optimizing logic for late arriving signals – structuring arithmetic for performance – avoiding area inefficient code – buffering high fan-out signals
  • 450.
    • Use “constants”to enhance readability and code maintenance • Comparison with a constant is preferred since it is much “cheaper” to implement • To avoid accidental latches – specify all clauses of “if” and “case” statements – specify all outputs • Use “case” rather than “if-then-else” whenever possible • Use parentheses for better operation • Never use mode “buffer” Good coding practices
  • 451.
    Design constraints • Constrainingdesigns: – constraints are means of communicating our requirements to the synthesis and back-end tools • Categories of constraints are : – Timing constraints • maximum frequency • duty cycle • input delays • output delays – Layout constraints
  • 452.
    Design constraints • Avoidover-constraining the design • Consequences of over-constraining are: – Design performance suffers: • critical timing paths get the best placement and fastest routing options • as the number of critical paths increase , the ability to obtain the design performance objectives decrease – Run times increase
  • 453.
    Synthesis guidelines • Simulateyour design before synthesis • Avoid combinational loops in processes • If a port is declared to be an integer data type, the range should be specified, else the synthesis tool will infer a 32-bit port • Avoid mixed clock edges – if a large number of both positive and negative edge flip-flops are required they should be placed in different modules
  • 454.
    Synthesis guidelines • Forbest results: – use technology primitives (macros) from the target technology libraries wherever possible – try small designs on target technology to find its limitations and strengths – Partition the design correctly • eliminate glue logic at the top level • partition block size based on the logic function, CPU resources and memory • separate random logic from structured logic • separate timing-sensitive modules from area -sensitive ones
  • 455.