SlideShare a Scribd company logo
1 of 62
Download to read offline
INTERNATIONAL SEMINAR ON 
MASS RAPID TRANSIT SYSTEM(MRTS) 
4th‐5th November 2014 
REVIEW AND ASSESSMENT OF CHALLENGES 
DURING CONSTRUCTION OF CHENNAI 
METRO
CONTENT 
y PROJECT DETAILS 
y PROJECT DESCRIPTION 
y GEOLOGICAL AND GEOTECHNICAL OVERVIEW 
y TUNNELLING PERFORMANCE (TBM ADVANCE/EXCAVATION) 
y TUNNELING THROUGH STATION 
y TUNNEL – STATION INTERFACE 
y CROSS PASSAGE SOIL TREATMENT
DESIGN AND CONSTRUCTION OF UNDERGROUND 
AND ASSOCIATED TUNNELS FOR UAA‐01 & UAA‐05 
OF CHENNAI METRO 
CLIENT :CHENNAI METRO RAIL LTD 
GENERAL CONSULTANT :EMBYE 
CONTRACTOR :TRANSTONNELSTORY‐AFCONS JV 
DESIGNER :PARSONS BRINCKERHOFF 
SOURCE OF FUND :FUNDED BY JICA 
Total Twin Tunnel Length : 17.5 KM
UAA 01 
UAA ‐‐ 05 
‐ Afcons Project
SITE LAYOUT OF THE PROJECT 
UAA 01 
UAA 05
EPBM –– Main Body 
20# shove rams
Transportation of TBM From Port to Site
View of EOT at Washermanpet
Tail Skin Lowering for TBM 718 at Shenoy Nagar Station
Front & middle Shields ready for lowering into Shaft
TBM Assembly
Trial of Muck Tilting Divice
VIEW OF 1ST TUNNEL ‐ SHENOY NAGAR STATION
View of Twin Tunnel
Casting shed & View of Commissioned Moulds
Segment casting at casting Yard
View of Segment stacking
Cutter Head / Cutting Tools
Sample TBM Data Record 
Types of reports/records 
•TBM Steering & alignment 
•TBM Excavation volume control 
•Tunnel grouting records 
•Ring survey & orientation record 
•Ring build record (steps, cracks, 
damage etc) 
•TBM Operational Data record
Typical Soil Profile ‐ Packages 05
Typical Mixed Soil Profile ‐ Packages 01 
Ground Level : +2.855 
Roof Top level : -0.420 
Concourse Level : -6.420 
Base Slab Level : -14.135 
D-Wall Tip level : -24.600
Mixed Ground
Typical Rock Soil Profile ‐ Packages 01
Soil Profile‐Mannadi Station 
Project UAA 01
Soil Profile‐ Chennai Central Station 
Project UAA 01
Core Details
Surface Constraints 
Saint Andrew’s Church 
SHIFTING OF MONUMENT AT RIPPON 
BUILDING AREA
High Court Mannadi
Surface Constraint 
Chennai Central
Surface Constraint Chennai Central 
SHC Shaft
Surface Constraint ‐Egmore
Surface Constraint - Railway tracks on the stretch High Court – 
Chennai Central and geological Profile
Surface Constrain - Railway tracks on the stretch 
Chennai Central ‐ Mayday Park Tunnel
View of Locomotive ‐ Mayday Park 
Tunnelling beneath Coovam River 
Under Coovam River
100% 
TYPICAL GEOLOGICAL PROFILE VARIATION 
60% 
80% 
Percent 
age 
Expected 
W1 W2 W3 W4 
20% 
40% 
0% 
4842.0133 
4847 
4862.9 
4880 
4891 
4903 
4910.4 
4915 
4923 
4934 
4940 
4951 
4956 
4967 
4977 
4992 
100% 
Chainage 
60% 
80% 
entage 
Actual Profile 
0% 
20% 
40% 
3 
7 
9 
0 
1 
3 
4 
5 
3 
4 
0 
1 
6 
7 
7 
2 
Perce 
4842.0133 
4847 
4862.9 
4880 
4891 
4903 
4910.4 
4915 
4923 
4934 
4940 
4951 
4956 
4967 
4977 
4992 
Chainage W1‐Fresh Rock 
W2‐Slightly weathered Rock 
W3‐M Weathered Rock 
W4‐ Highly Weathered Rock
Geological Variation Results: 
Cutter Consumption & Frequency of Intervention
TBM retrieval in wet condition
CHENNAI CENTRAL 
(Overlapping of Two Corridor)
Retrieval Shaft at SCC ‐ Mayday Park Tunnel
Obstacles during Tunnel Operation 
Ground Level 
CL 
Red 
Zone 
Ora 
Zon 
Gr 
Zone 
L 
TUNNEL 
A 
ange 
ne 
reen Zone 
Green Z 
Orange 
Zone 
TUNNEL 
B 
1.0 mt 1.0 mt 
Bore well influence 1mt from Extrados of Tunnel 
Segment
Obstacles during Tunnel Operation 
UAA 01 
NO. OF EXISTING WELLS IN DIFFERENT ZONES: UAA01 
Project 
RED ZONE 
(11.355 m. 
f T l 
ORANGE ZONE 
(5.15 m. from RED 
GREEN ZONE 
( 4.5 m. from 
TOTAL R + O + 
G 
from Tunnel 
CL) 
5. 5 R 
ZONE) 
ORANGE ZONE) 
Package 01 304 98 90 492 
Package 05 
61 24 60 145 
Total 365 122 150 637
BUILDING CONDITION SURVEY 
BUILDING CONDITION SURVEY
TUNNELLING PERFORMANCE 
The TBMS are normally operated on a 24 hr basis, working 2 
shifts per day. 
The following main results have been achieved: 
¾ Average Daily Production:.12 ..Rings =16.8 m 
¾¾ Best Day(09/02/2013): 39rings=54.6 m 
¾ Best week(04/02/2013 to 09/02/2013): 139 rings=182 m 
¾ Best Month ( Oct 2013): 525 rings= 735 m 
¾We have achieved 39 Rings Boring in a day first time in 
the World 
Considering that all the 5 TBMs have been operated in a very sensitive urban 
environment, almost always in closed mode, these results can be regarded as very 
positive and above the usual standard.
Heave pressure verification 
3 50 
4.00 
4.50 
5.00 
2.00 
2.50 
3.00 
3.50 
ressures (bar) 
0.50 
1.00 
1.50 
Pr 
Cohesive material 
0.00 
0+220 
0+260 
0+300 
0+340 
0+380 
0+420 
0+460 
0+500 
0+540 
0+580 
0+620 
0+660 
0+700 
0+740 
0+780 
0+820 
0+860 
0+900 
0+940 
0+980 
1+020 
1+060 
1+100 
1+140 
1+180 
1+220 
1+260 
1+300 
1+340 
1+380 
1+420 
1+460 
1+500 
1+540 
1+580 
CHAINAGE 
Heave pressure (by Jancsez th.) Recommended Max. Pressure
Recommended EPB pressure and 
Grout Injection Pressure 
3.00 
2.00 
2.50 
ar) 
Pressures (b 
1 00 
1.50 
0.50 
1.00 
0.00 
1+580 
1+620 
1+660 
1+700 
1+740 
1+780 
1+820 
1+860 
1+900 
1+940 
1+980 
2+020 
2+060 
2+100 
2+140 
2+180 
2+220 
2+260 
2+300 
2+340 
2+380 
2+420 
2+460 
2+500 
CHAINAGE 
Recommended pressure Min.pressure Max.pressure Grout injection system
Earth Pressure Monitoring 
3 
2.5 
2 
1.5 
1 
Pressure (bar) 
0.5 
0 
0 200 400 600 800 1000 1200 1400 1600 1800 2000 
Earth P 
Mannadi Station Ring No. 
D'W ll C tti 
High Court 
D'Wall Cutting Station Area 
3.5 
3 
2.5 
ure (bar) 
2 
1.5 
1 
0.5 
Earth Pressu 
0 
0 200 400 600 800 1000 1200 1400 1600 1800 2000 
Ring No.
Typical Machining Parameters 
monitoring 
30000 
25000 
20000 
orce 
Thrust Force(kN) 
3.5 
3 
2.5 
2 
M 
Cutting wheel Rotation (rpm) 
15000 
10000 
5000 
0 
0 500 1000 1500 2000 
Thrust Fo 
1.5 
1 
0.5 
0 
0 500 1000 1500 2000 
RPM 
Ring No. 
Ring No. 
Torque(MN.m) Advance Speed (mm/Min) 
4 
3.5 
3 
2.5 
2 
que 
60 
50 
40 
30 
eed()mm/Min. 
1.5 
1 
0.5 
0 
Torq 
20 
10 
0 
0 500 1000 1500 2000 
Advance Spe 
0 500 1000 1500 2000 
Ring No. 
Ring No.
Operation steps in Mechanized Tunneling 
¾Making Launching Shaft 
¾¾Assembly of TBM ¾ i i Sh f 
¾Initial Drive 
¾Muck Out 
Receiving Shaft 
¾Tunnel Break through 
¾Dissemble TBM 
¾Boring 
¾Assembly of Lining 
¾Grouting 
¾Segment Lining 
¾Close of Launching shaft 
upon Completion 
¾Retrieval of TBM to Groundt 
¾Close of receiving shaft 
p p 
Segment yard 
™Casting of Segment
Type of TBM 
EPBM‐Mixed Ground Type EPB‐Soft Ground Type 
UAA 01 
Washermanpet to Chennai 
Central 
M f t H k ht 
UAA 05 
Shenoy Nagar to 
Thirumangalam 
Manufacture‐Herrenknecht Manufacture‐ 
Herrenknecht 
UAA 01 
May day Park to Chennai 
EPB‐Rock/Mixed Face 
Central 
Manufacture‐Robbins
TBM Confinement
Breaking Out Through Confinement
Interface Tunnel ‐ Station 
Mining Through D Th h 
UAA 01 Drag Through 
Mining Through Station Trag Through 
Break In Break Out Break In Break Out 
Break In 
Break Out 
UAA 05 
Mining Through h h 
reak 
hrough 
Drag Through Drag Through 
Br 
Th 
Break In 
Break Out Break In Break Out Break In
TBM 717 Break In – Anna Nagar TBM Break In Shenoy Nagar Station 
Tower 
In‐
View of 1st Tunnel & TBM 718 ‐ Shenoy Nagar Station
Mining Through Station 
Plan 
Elevation
TBM Drag through
TBM Break through 
717
718 
711 
710 711 717 710
Tunnel Boring Machine Specification 
TBM’s 
Cost of each TBM & backup equipment 33.5Cr 
TBM total weight 290 T 
Excavation diameter 6.6 m 
Overall length 9.7 m 
Electrical power 940 kW 
Left & right rotation speed Max 4.57 rpm 
Ram advance speed Max. 80 mm/min 
Ram jacks 32 # 
Total advance thrust force 42000 KN 
Earth pressure sensors 6 #
Cross Passage Soil 
Treatment
Chennai Metro Tunnel Construction Challenges

More Related Content

What's hot

MASS RAPID TRANSIT SYSTEM
MASS RAPID TRANSIT SYSTEMMASS RAPID TRANSIT SYSTEM
MASS RAPID TRANSIT SYSTEMChandanPadhi3
 
Ahmedabad metro.
Ahmedabad metro.Ahmedabad metro.
Ahmedabad metro.Axay Sharma
 
Design of Foot Over Bridge
Design of Foot Over BridgeDesign of Foot Over Bridge
Design of Foot Over Bridgejupallipavan2911
 
Agent Based Pedestrian Modeling for Evaluation MRT Jakarta Underground Statio...
Agent Based Pedestrian Modeling for Evaluation MRT Jakarta Underground Statio...Agent Based Pedestrian Modeling for Evaluation MRT Jakarta Underground Statio...
Agent Based Pedestrian Modeling for Evaluation MRT Jakarta Underground Statio...Akhmad Hidayatno
 
Pune transport solutions
Pune transport solutionsPune transport solutions
Pune transport solutionsPriya Raj
 
Hyderabad Metro Rail - an Urban Redesign Opportunity - Mr. NVS Reddy
Hyderabad Metro Rail - an Urban Redesign Opportunity - Mr. NVS ReddyHyderabad Metro Rail - an Urban Redesign Opportunity - Mr. NVS Reddy
Hyderabad Metro Rail - an Urban Redesign Opportunity - Mr. NVS ReddyIPPAI
 
Construction sequence for metro Project (Elevated and Underground) and Time c...
Construction sequence for metro Project (Elevated and Underground) and Time c...Construction sequence for metro Project (Elevated and Underground) and Time c...
Construction sequence for metro Project (Elevated and Underground) and Time c...Akhilesh Shukla
 
Tunnel Construction (VJTI MUMBAI)
Tunnel Construction (VJTI MUMBAI)Tunnel Construction (VJTI MUMBAI)
Tunnel Construction (VJTI MUMBAI)Mayur Rahangdale
 
DELHI METRO UNDERGROUND TUNNELING : SHAHBAZ KHAN DMRC
DELHI METRO UNDERGROUND TUNNELING : SHAHBAZ KHAN DMRCDELHI METRO UNDERGROUND TUNNELING : SHAHBAZ KHAN DMRC
DELHI METRO UNDERGROUND TUNNELING : SHAHBAZ KHAN DMRCAl Hakam Khan
 
Depots presentation
Depots presentationDepots presentation
Depots presentationKumar M.
 
Bus terminal+commercial complex+isbt+india ppt show
Bus terminal+commercial complex+isbt+india ppt showBus terminal+commercial complex+isbt+india ppt show
Bus terminal+commercial complex+isbt+india ppt showkiranightly
 

What's hot (20)

Cut and cover
Cut and coverCut and cover
Cut and cover
 
TOD Presentation-PDF_-part-I
TOD Presentation-PDF_-part-ITOD Presentation-PDF_-part-I
TOD Presentation-PDF_-part-I
 
Transit hub
Transit hub Transit hub
Transit hub
 
Transit Oriented Development.
Transit Oriented Development.Transit Oriented Development.
Transit Oriented Development.
 
TOD in India
TOD in IndiaTOD in India
TOD in India
 
MASS RAPID TRANSIT SYSTEM
MASS RAPID TRANSIT SYSTEMMASS RAPID TRANSIT SYSTEM
MASS RAPID TRANSIT SYSTEM
 
Ahmedabad metro.
Ahmedabad metro.Ahmedabad metro.
Ahmedabad metro.
 
Design of Foot Over Bridge
Design of Foot Over BridgeDesign of Foot Over Bridge
Design of Foot Over Bridge
 
Agent Based Pedestrian Modeling for Evaluation MRT Jakarta Underground Statio...
Agent Based Pedestrian Modeling for Evaluation MRT Jakarta Underground Statio...Agent Based Pedestrian Modeling for Evaluation MRT Jakarta Underground Statio...
Agent Based Pedestrian Modeling for Evaluation MRT Jakarta Underground Statio...
 
Earnest Money
Earnest MoneyEarnest Money
Earnest Money
 
lucknow metro ppt
lucknow metro pptlucknow metro ppt
lucknow metro ppt
 
Pune transport solutions
Pune transport solutionsPune transport solutions
Pune transport solutions
 
Hyderabad Metro Rail - an Urban Redesign Opportunity - Mr. NVS Reddy
Hyderabad Metro Rail - an Urban Redesign Opportunity - Mr. NVS ReddyHyderabad Metro Rail - an Urban Redesign Opportunity - Mr. NVS Reddy
Hyderabad Metro Rail - an Urban Redesign Opportunity - Mr. NVS Reddy
 
Construction sequence for metro Project (Elevated and Underground) and Time c...
Construction sequence for metro Project (Elevated and Underground) and Time c...Construction sequence for metro Project (Elevated and Underground) and Time c...
Construction sequence for metro Project (Elevated and Underground) and Time c...
 
Tunnel Construction (VJTI MUMBAI)
Tunnel Construction (VJTI MUMBAI)Tunnel Construction (VJTI MUMBAI)
Tunnel Construction (VJTI MUMBAI)
 
metro station planning ar.ravi sankar alumni(auce architecture)
metro station planning ar.ravi sankar alumni(auce architecture)metro station planning ar.ravi sankar alumni(auce architecture)
metro station planning ar.ravi sankar alumni(auce architecture)
 
DELHI METRO UNDERGROUND TUNNELING : SHAHBAZ KHAN DMRC
DELHI METRO UNDERGROUND TUNNELING : SHAHBAZ KHAN DMRCDELHI METRO UNDERGROUND TUNNELING : SHAHBAZ KHAN DMRC
DELHI METRO UNDERGROUND TUNNELING : SHAHBAZ KHAN DMRC
 
Depots presentation
Depots presentationDepots presentation
Depots presentation
 
Contracts and-tenders
Contracts and-tendersContracts and-tenders
Contracts and-tenders
 
Bus terminal+commercial complex+isbt+india ppt show
Bus terminal+commercial complex+isbt+india ppt showBus terminal+commercial complex+isbt+india ppt show
Bus terminal+commercial complex+isbt+india ppt show
 

Viewers also liked

Metro Rail in India ppt
Metro Rail in India pptMetro Rail in India ppt
Metro Rail in India pptNikita James
 
Chennai metro rail
Chennai metro railChennai metro rail
Chennai metro railkarthik1923
 
Chennai metro rail
Chennai metro railChennai metro rail
Chennai metro raillibin paul
 
Metro rail seminor
Metro rail seminor Metro rail seminor
Metro rail seminor Joseph Jincy
 
Formulation of detailed project report(final)
Formulation of detailed project report(final)Formulation of detailed project report(final)
Formulation of detailed project report(final)Parag Chaubey
 
Mumbai metro project Phase I
Mumbai metro project Phase IMumbai metro project Phase I
Mumbai metro project Phase IKaran Shah
 
Metro stations all over world
Metro stations all over worldMetro stations all over world
Metro stations all over worldSai Swaroop
 
The MRT In Taipei
The MRT In TaipeiThe MRT In Taipei
The MRT In TaipeiTomMitW
 
Taipei MRT Signage Study
Taipei MRT Signage StudyTaipei MRT Signage Study
Taipei MRT Signage Studykelake
 
Mass Rapid Transit (Bangkok, Thailand)
Mass Rapid Transit (Bangkok, Thailand)Mass Rapid Transit (Bangkok, Thailand)
Mass Rapid Transit (Bangkok, Thailand)Muhammad Ali
 
L&T Inplant training at chennai metro report
L&T Inplant training at chennai metro reportL&T Inplant training at chennai metro report
L&T Inplant training at chennai metro reporthemanth kumar
 
Beyond Buses - Creating a better Public Transport System through Marketing, C...
Beyond Buses - Creating a better Public Transport System through Marketing, C...Beyond Buses - Creating a better Public Transport System through Marketing, C...
Beyond Buses - Creating a better Public Transport System through Marketing, C...WRI Ross Center for Sustainable Cities
 
Metro train prototype
Metro train prototypeMetro train prototype
Metro train prototypekajikho9
 

Viewers also liked (20)

Metro Rail in India ppt
Metro Rail in India pptMetro Rail in India ppt
Metro Rail in India ppt
 
Chennai metro rail
Chennai metro railChennai metro rail
Chennai metro rail
 
Chennai metro rail
Chennai metro railChennai metro rail
Chennai metro rail
 
Metro rail seminor
Metro rail seminor Metro rail seminor
Metro rail seminor
 
Cmrl ppt
Cmrl pptCmrl ppt
Cmrl ppt
 
.Chennai metro rail-2
.Chennai metro rail-2.Chennai metro rail-2
.Chennai metro rail-2
 
Metro train prototype
Metro train prototypeMetro train prototype
Metro train prototype
 
Formulation of detailed project report(final)
Formulation of detailed project report(final)Formulation of detailed project report(final)
Formulation of detailed project report(final)
 
Mumbai metro project Phase I
Mumbai metro project Phase IMumbai metro project Phase I
Mumbai metro project Phase I
 
Modern Methods of Construction
Modern Methods of ConstructionModern Methods of Construction
Modern Methods of Construction
 
Narasimhan 7537
Narasimhan 7537Narasimhan 7537
Narasimhan 7537
 
Metro stations all over world
Metro stations all over worldMetro stations all over world
Metro stations all over world
 
The MRT In Taipei
The MRT In TaipeiThe MRT In Taipei
The MRT In Taipei
 
Taipei MRT Signage Study
Taipei MRT Signage StudyTaipei MRT Signage Study
Taipei MRT Signage Study
 
Mass Rapid Transit (Bangkok, Thailand)
Mass Rapid Transit (Bangkok, Thailand)Mass Rapid Transit (Bangkok, Thailand)
Mass Rapid Transit (Bangkok, Thailand)
 
L&T Inplant training at chennai metro report
L&T Inplant training at chennai metro reportL&T Inplant training at chennai metro report
L&T Inplant training at chennai metro report
 
Beyond Buses - Creating a better Public Transport System through Marketing, C...
Beyond Buses - Creating a better Public Transport System through Marketing, C...Beyond Buses - Creating a better Public Transport System through Marketing, C...
Beyond Buses - Creating a better Public Transport System through Marketing, C...
 
Tp metro
Tp metroTp metro
Tp metro
 
Metro train prototype
Metro train prototypeMetro train prototype
Metro train prototype
 
Automatic Metro
Automatic MetroAutomatic Metro
Automatic Metro
 

Similar to Chennai Metro Tunnel Construction Challenges

Feasibility and Economic Design of Pumped Storage Hydropower Station
Feasibility and Economic Design of Pumped Storage Hydropower StationFeasibility and Economic Design of Pumped Storage Hydropower Station
Feasibility and Economic Design of Pumped Storage Hydropower StationAwais Marwat
 
Dragline Planning
Dragline PlanningDragline Planning
Dragline PlanningVR M
 
PPT CAVITY Tunnel P1 610M--05.02.2021.pptx
PPT CAVITY Tunnel P1 610M--05.02.2021.pptxPPT CAVITY Tunnel P1 610M--05.02.2021.pptx
PPT CAVITY Tunnel P1 610M--05.02.2021.pptxAGNIVORAY1
 
TRAINING REPORT ON COSTRUCTION OF FLYOVER FROM MITHAPUR TO CHIRIYATAND (BIHAR)
TRAINING REPORT ON  COSTRUCTION OF FLYOVER FROM  MITHAPUR TO CHIRIYATAND (BIHAR)TRAINING REPORT ON  COSTRUCTION OF FLYOVER FROM  MITHAPUR TO CHIRIYATAND (BIHAR)
TRAINING REPORT ON COSTRUCTION OF FLYOVER FROM MITHAPUR TO CHIRIYATAND (BIHAR)vishal prakash
 
ilovepdf_#تواصل_تطوير المحاضرة رقم 187 أستاذ دكتور / مدحت كمال عبدالله عنوان ...
ilovepdf_#تواصل_تطوير المحاضرة رقم 187 أستاذ دكتور / مدحت كمال عبدالله عنوان ...ilovepdf_#تواصل_تطوير المحاضرة رقم 187 أستاذ دكتور / مدحت كمال عبدالله عنوان ...
ilovepdf_#تواصل_تطوير المحاضرة رقم 187 أستاذ دكتور / مدحت كمال عبدالله عنوان ...Egyptian Engineers Association
 
Nhpc training report civil engineerimg_bit_mesra_ISHANT GAUTAM
Nhpc training report civil engineerimg_bit_mesra_ISHANT GAUTAMNhpc training report civil engineerimg_bit_mesra_ISHANT GAUTAM
Nhpc training report civil engineerimg_bit_mesra_ISHANT GAUTAMIshant Gautam.
 
Tunnel T80 across Pir Panjal Mountain Range: The Longest Transportation Tunne...
Tunnel T80 across Pir Panjal Mountain Range: The Longest Transportation Tunne...Tunnel T80 across Pir Panjal Mountain Range: The Longest Transportation Tunne...
Tunnel T80 across Pir Panjal Mountain Range: The Longest Transportation Tunne...Hitesh Khanna
 
Report work on retaining wall
Report work on retaining wallReport work on retaining wall
Report work on retaining wallvikas Meena
 
Analyzing the role of Segmental lining in the tunnels with Tunnel Boring Mach...
Analyzing the role of Segmental lining in the tunnels with Tunnel Boring Mach...Analyzing the role of Segmental lining in the tunnels with Tunnel Boring Mach...
Analyzing the role of Segmental lining in the tunnels with Tunnel Boring Mach...IRJET Journal
 
NATM Tunneling ppt
NATM Tunneling pptNATM Tunneling ppt
NATM Tunneling pptSuman Paul
 
2.1 port of miami tunnel cei
2.1 port of miami tunnel cei2.1 port of miami tunnel cei
2.1 port of miami tunnel ceiascemiami-dade
 
Construction Presentations 2019
Construction Presentations 2019Construction Presentations 2019
Construction Presentations 2019David H Moloney
 
101024 Mafraq_Presentation_Javad_Akhtar
101024 Mafraq_Presentation_Javad_Akhtar101024 Mafraq_Presentation_Javad_Akhtar
101024 Mafraq_Presentation_Javad_AkhtarJavad Akhtar
 
Uses of special kind of technologies for implementation of special kind of st...
Uses of special kind of technologies for implementation of special kind of st...Uses of special kind of technologies for implementation of special kind of st...
Uses of special kind of technologies for implementation of special kind of st...Rajesh Prasad
 
HDPE Pipes By Perfect Prime Piping & Agritech Private Limited, Rajasthan
HDPE Pipes By Perfect Prime Piping & Agritech Private Limited, RajasthanHDPE Pipes By Perfect Prime Piping & Agritech Private Limited, Rajasthan
HDPE Pipes By Perfect Prime Piping & Agritech Private Limited, RajasthanIndiaMART InterMESH Limited
 
Structural and stability assessment for ex-pit dump toe (final)
Structural and stability assessment for ex-pit dump toe (final)Structural and stability assessment for ex-pit dump toe (final)
Structural and stability assessment for ex-pit dump toe (final)John Latilla
 
tunnelling scope, construction techniques and necessity
tunnelling scope, construction techniques and necessitytunnelling scope, construction techniques and necessity
tunnelling scope, construction techniques and necessityShashank Gaurav
 

Similar to Chennai Metro Tunnel Construction Challenges (20)

Feasibility and Economic Design of Pumped Storage Hydropower Station
Feasibility and Economic Design of Pumped Storage Hydropower StationFeasibility and Economic Design of Pumped Storage Hydropower Station
Feasibility and Economic Design of Pumped Storage Hydropower Station
 
Dragline Planning
Dragline PlanningDragline Planning
Dragline Planning
 
PPT CAVITY Tunnel P1 610M--05.02.2021.pptx
PPT CAVITY Tunnel P1 610M--05.02.2021.pptxPPT CAVITY Tunnel P1 610M--05.02.2021.pptx
PPT CAVITY Tunnel P1 610M--05.02.2021.pptx
 
TRAINING REPORT ON COSTRUCTION OF FLYOVER FROM MITHAPUR TO CHIRIYATAND (BIHAR)
TRAINING REPORT ON  COSTRUCTION OF FLYOVER FROM  MITHAPUR TO CHIRIYATAND (BIHAR)TRAINING REPORT ON  COSTRUCTION OF FLYOVER FROM  MITHAPUR TO CHIRIYATAND (BIHAR)
TRAINING REPORT ON COSTRUCTION OF FLYOVER FROM MITHAPUR TO CHIRIYATAND (BIHAR)
 
ilovepdf_#تواصل_تطوير المحاضرة رقم 187 أستاذ دكتور / مدحت كمال عبدالله عنوان ...
ilovepdf_#تواصل_تطوير المحاضرة رقم 187 أستاذ دكتور / مدحت كمال عبدالله عنوان ...ilovepdf_#تواصل_تطوير المحاضرة رقم 187 أستاذ دكتور / مدحت كمال عبدالله عنوان ...
ilovepdf_#تواصل_تطوير المحاضرة رقم 187 أستاذ دكتور / مدحت كمال عبدالله عنوان ...
 
Nhpc training report civil engineerimg_bit_mesra_ISHANT GAUTAM
Nhpc training report civil engineerimg_bit_mesra_ISHANT GAUTAMNhpc training report civil engineerimg_bit_mesra_ISHANT GAUTAM
Nhpc training report civil engineerimg_bit_mesra_ISHANT GAUTAM
 
Project 4 Presentation
Project 4 PresentationProject 4 Presentation
Project 4 Presentation
 
Tunnel T80 across Pir Panjal Mountain Range: The Longest Transportation Tunne...
Tunnel T80 across Pir Panjal Mountain Range: The Longest Transportation Tunne...Tunnel T80 across Pir Panjal Mountain Range: The Longest Transportation Tunne...
Tunnel T80 across Pir Panjal Mountain Range: The Longest Transportation Tunne...
 
Report work on retaining wall
Report work on retaining wallReport work on retaining wall
Report work on retaining wall
 
Nbc cso apwa expo july 8 t12
Nbc cso apwa expo july 8 t12Nbc cso apwa expo july 8 t12
Nbc cso apwa expo july 8 t12
 
Analyzing the role of Segmental lining in the tunnels with Tunnel Boring Mach...
Analyzing the role of Segmental lining in the tunnels with Tunnel Boring Mach...Analyzing the role of Segmental lining in the tunnels with Tunnel Boring Mach...
Analyzing the role of Segmental lining in the tunnels with Tunnel Boring Mach...
 
NATM Tunneling ppt
NATM Tunneling pptNATM Tunneling ppt
NATM Tunneling ppt
 
2.1 port of miami tunnel cei
2.1 port of miami tunnel cei2.1 port of miami tunnel cei
2.1 port of miami tunnel cei
 
Construction Presentations 2019
Construction Presentations 2019Construction Presentations 2019
Construction Presentations 2019
 
101024 Mafraq_Presentation_Javad_Akhtar
101024 Mafraq_Presentation_Javad_Akhtar101024 Mafraq_Presentation_Javad_Akhtar
101024 Mafraq_Presentation_Javad_Akhtar
 
Uses of special kind of technologies for implementation of special kind of st...
Uses of special kind of technologies for implementation of special kind of st...Uses of special kind of technologies for implementation of special kind of st...
Uses of special kind of technologies for implementation of special kind of st...
 
HDPE Pipes By Perfect Prime Piping & Agritech Private Limited, Rajasthan
HDPE Pipes By Perfect Prime Piping & Agritech Private Limited, RajasthanHDPE Pipes By Perfect Prime Piping & Agritech Private Limited, Rajasthan
HDPE Pipes By Perfect Prime Piping & Agritech Private Limited, Rajasthan
 
Site visit presentation: Kwun Tong line extension
Site visit presentation: Kwun Tong line extensionSite visit presentation: Kwun Tong line extension
Site visit presentation: Kwun Tong line extension
 
Structural and stability assessment for ex-pit dump toe (final)
Structural and stability assessment for ex-pit dump toe (final)Structural and stability assessment for ex-pit dump toe (final)
Structural and stability assessment for ex-pit dump toe (final)
 
tunnelling scope, construction techniques and necessity
tunnelling scope, construction techniques and necessitytunnelling scope, construction techniques and necessity
tunnelling scope, construction techniques and necessity
 

Recently uploaded

Gfe Mayur Vihar Call Girls Service WhatsApp -> 9999965857 Available 24x7 ^ De...
Gfe Mayur Vihar Call Girls Service WhatsApp -> 9999965857 Available 24x7 ^ De...Gfe Mayur Vihar Call Girls Service WhatsApp -> 9999965857 Available 24x7 ^ De...
Gfe Mayur Vihar Call Girls Service WhatsApp -> 9999965857 Available 24x7 ^ De...srsj9000
 
APPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICS
APPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICSAPPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICS
APPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICSKurinjimalarL3
 
Introduction to IEEE STANDARDS and its different types.pptx
Introduction to IEEE STANDARDS and its different types.pptxIntroduction to IEEE STANDARDS and its different types.pptx
Introduction to IEEE STANDARDS and its different types.pptxupamatechverse
 
The Most Attractive Pune Call Girls Budhwar Peth 8250192130 Will You Miss Thi...
The Most Attractive Pune Call Girls Budhwar Peth 8250192130 Will You Miss Thi...The Most Attractive Pune Call Girls Budhwar Peth 8250192130 Will You Miss Thi...
The Most Attractive Pune Call Girls Budhwar Peth 8250192130 Will You Miss Thi...ranjana rawat
 
Decoding Kotlin - Your guide to solving the mysterious in Kotlin.pptx
Decoding Kotlin - Your guide to solving the mysterious in Kotlin.pptxDecoding Kotlin - Your guide to solving the mysterious in Kotlin.pptx
Decoding Kotlin - Your guide to solving the mysterious in Kotlin.pptxJoão Esperancinha
 
HARDNESS, FRACTURE TOUGHNESS AND STRENGTH OF CERAMICS
HARDNESS, FRACTURE TOUGHNESS AND STRENGTH OF CERAMICSHARDNESS, FRACTURE TOUGHNESS AND STRENGTH OF CERAMICS
HARDNESS, FRACTURE TOUGHNESS AND STRENGTH OF CERAMICSRajkumarAkumalla
 
(PRIYA) Rajgurunagar Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(PRIYA) Rajgurunagar Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...(PRIYA) Rajgurunagar Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(PRIYA) Rajgurunagar Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...ranjana rawat
 
Porous Ceramics seminar and technical writing
Porous Ceramics seminar and technical writingPorous Ceramics seminar and technical writing
Porous Ceramics seminar and technical writingrakeshbaidya232001
 
SPICE PARK APR2024 ( 6,793 SPICE Models )
SPICE PARK APR2024 ( 6,793 SPICE Models )SPICE PARK APR2024 ( 6,793 SPICE Models )
SPICE PARK APR2024 ( 6,793 SPICE Models )Tsuyoshi Horigome
 
Processing & Properties of Floor and Wall Tiles.pptx
Processing & Properties of Floor and Wall Tiles.pptxProcessing & Properties of Floor and Wall Tiles.pptx
Processing & Properties of Floor and Wall Tiles.pptxpranjaldaimarysona
 
College Call Girls Nashik Nehal 7001305949 Independent Escort Service Nashik
College Call Girls Nashik Nehal 7001305949 Independent Escort Service NashikCollege Call Girls Nashik Nehal 7001305949 Independent Escort Service Nashik
College Call Girls Nashik Nehal 7001305949 Independent Escort Service NashikCall Girls in Nagpur High Profile
 
GDSC ASEB Gen AI study jams presentation
GDSC ASEB Gen AI study jams presentationGDSC ASEB Gen AI study jams presentation
GDSC ASEB Gen AI study jams presentationGDSCAESB
 
chaitra-1.pptx fake news detection using machine learning
chaitra-1.pptx  fake news detection using machine learningchaitra-1.pptx  fake news detection using machine learning
chaitra-1.pptx fake news detection using machine learningmisbanausheenparvam
 
(ANJALI) Dange Chowk Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(ANJALI) Dange Chowk Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...(ANJALI) Dange Chowk Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(ANJALI) Dange Chowk Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...ranjana rawat
 
the ladakh protest in leh ladakh 2024 sonam wangchuk.pptx
the ladakh protest in leh ladakh 2024 sonam wangchuk.pptxthe ladakh protest in leh ladakh 2024 sonam wangchuk.pptx
the ladakh protest in leh ladakh 2024 sonam wangchuk.pptxhumanexperienceaaa
 
OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...
OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...
OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...Soham Mondal
 
Model Call Girl in Narela Delhi reach out to us at 🔝8264348440🔝
Model Call Girl in Narela Delhi reach out to us at 🔝8264348440🔝Model Call Girl in Narela Delhi reach out to us at 🔝8264348440🔝
Model Call Girl in Narela Delhi reach out to us at 🔝8264348440🔝soniya singh
 
main PPT.pptx of girls hostel security using rfid
main PPT.pptx of girls hostel security using rfidmain PPT.pptx of girls hostel security using rfid
main PPT.pptx of girls hostel security using rfidNikhilNagaraju
 

Recently uploaded (20)

Gfe Mayur Vihar Call Girls Service WhatsApp -> 9999965857 Available 24x7 ^ De...
Gfe Mayur Vihar Call Girls Service WhatsApp -> 9999965857 Available 24x7 ^ De...Gfe Mayur Vihar Call Girls Service WhatsApp -> 9999965857 Available 24x7 ^ De...
Gfe Mayur Vihar Call Girls Service WhatsApp -> 9999965857 Available 24x7 ^ De...
 
APPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICS
APPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICSAPPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICS
APPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICS
 
Introduction to IEEE STANDARDS and its different types.pptx
Introduction to IEEE STANDARDS and its different types.pptxIntroduction to IEEE STANDARDS and its different types.pptx
Introduction to IEEE STANDARDS and its different types.pptx
 
The Most Attractive Pune Call Girls Budhwar Peth 8250192130 Will You Miss Thi...
The Most Attractive Pune Call Girls Budhwar Peth 8250192130 Will You Miss Thi...The Most Attractive Pune Call Girls Budhwar Peth 8250192130 Will You Miss Thi...
The Most Attractive Pune Call Girls Budhwar Peth 8250192130 Will You Miss Thi...
 
Decoding Kotlin - Your guide to solving the mysterious in Kotlin.pptx
Decoding Kotlin - Your guide to solving the mysterious in Kotlin.pptxDecoding Kotlin - Your guide to solving the mysterious in Kotlin.pptx
Decoding Kotlin - Your guide to solving the mysterious in Kotlin.pptx
 
HARDNESS, FRACTURE TOUGHNESS AND STRENGTH OF CERAMICS
HARDNESS, FRACTURE TOUGHNESS AND STRENGTH OF CERAMICSHARDNESS, FRACTURE TOUGHNESS AND STRENGTH OF CERAMICS
HARDNESS, FRACTURE TOUGHNESS AND STRENGTH OF CERAMICS
 
(PRIYA) Rajgurunagar Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(PRIYA) Rajgurunagar Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...(PRIYA) Rajgurunagar Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(PRIYA) Rajgurunagar Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
 
Porous Ceramics seminar and technical writing
Porous Ceramics seminar and technical writingPorous Ceramics seminar and technical writing
Porous Ceramics seminar and technical writing
 
SPICE PARK APR2024 ( 6,793 SPICE Models )
SPICE PARK APR2024 ( 6,793 SPICE Models )SPICE PARK APR2024 ( 6,793 SPICE Models )
SPICE PARK APR2024 ( 6,793 SPICE Models )
 
Processing & Properties of Floor and Wall Tiles.pptx
Processing & Properties of Floor and Wall Tiles.pptxProcessing & Properties of Floor and Wall Tiles.pptx
Processing & Properties of Floor and Wall Tiles.pptx
 
College Call Girls Nashik Nehal 7001305949 Independent Escort Service Nashik
College Call Girls Nashik Nehal 7001305949 Independent Escort Service NashikCollege Call Girls Nashik Nehal 7001305949 Independent Escort Service Nashik
College Call Girls Nashik Nehal 7001305949 Independent Escort Service Nashik
 
GDSC ASEB Gen AI study jams presentation
GDSC ASEB Gen AI study jams presentationGDSC ASEB Gen AI study jams presentation
GDSC ASEB Gen AI study jams presentation
 
chaitra-1.pptx fake news detection using machine learning
chaitra-1.pptx  fake news detection using machine learningchaitra-1.pptx  fake news detection using machine learning
chaitra-1.pptx fake news detection using machine learning
 
(ANJALI) Dange Chowk Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(ANJALI) Dange Chowk Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...(ANJALI) Dange Chowk Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(ANJALI) Dange Chowk Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
 
Roadmap to Membership of RICS - Pathways and Routes
Roadmap to Membership of RICS - Pathways and RoutesRoadmap to Membership of RICS - Pathways and Routes
Roadmap to Membership of RICS - Pathways and Routes
 
the ladakh protest in leh ladakh 2024 sonam wangchuk.pptx
the ladakh protest in leh ladakh 2024 sonam wangchuk.pptxthe ladakh protest in leh ladakh 2024 sonam wangchuk.pptx
the ladakh protest in leh ladakh 2024 sonam wangchuk.pptx
 
OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...
OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...
OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...
 
Model Call Girl in Narela Delhi reach out to us at 🔝8264348440🔝
Model Call Girl in Narela Delhi reach out to us at 🔝8264348440🔝Model Call Girl in Narela Delhi reach out to us at 🔝8264348440🔝
Model Call Girl in Narela Delhi reach out to us at 🔝8264348440🔝
 
main PPT.pptx of girls hostel security using rfid
main PPT.pptx of girls hostel security using rfidmain PPT.pptx of girls hostel security using rfid
main PPT.pptx of girls hostel security using rfid
 
★ CALL US 9953330565 ( HOT Young Call Girls In Badarpur delhi NCR
★ CALL US 9953330565 ( HOT Young Call Girls In Badarpur delhi NCR★ CALL US 9953330565 ( HOT Young Call Girls In Badarpur delhi NCR
★ CALL US 9953330565 ( HOT Young Call Girls In Badarpur delhi NCR
 

Chennai Metro Tunnel Construction Challenges

  • 1. INTERNATIONAL SEMINAR ON MASS RAPID TRANSIT SYSTEM(MRTS) 4th‐5th November 2014 REVIEW AND ASSESSMENT OF CHALLENGES DURING CONSTRUCTION OF CHENNAI METRO
  • 2. CONTENT y PROJECT DETAILS y PROJECT DESCRIPTION y GEOLOGICAL AND GEOTECHNICAL OVERVIEW y TUNNELLING PERFORMANCE (TBM ADVANCE/EXCAVATION) y TUNNELING THROUGH STATION y TUNNEL – STATION INTERFACE y CROSS PASSAGE SOIL TREATMENT
  • 3. DESIGN AND CONSTRUCTION OF UNDERGROUND AND ASSOCIATED TUNNELS FOR UAA‐01 & UAA‐05 OF CHENNAI METRO CLIENT :CHENNAI METRO RAIL LTD GENERAL CONSULTANT :EMBYE CONTRACTOR :TRANSTONNELSTORY‐AFCONS JV DESIGNER :PARSONS BRINCKERHOFF SOURCE OF FUND :FUNDED BY JICA Total Twin Tunnel Length : 17.5 KM
  • 4. UAA 01 UAA ‐‐ 05 ‐ Afcons Project
  • 5. SITE LAYOUT OF THE PROJECT UAA 01 UAA 05
  • 6. EPBM –– Main Body 20# shove rams
  • 7. Transportation of TBM From Port to Site
  • 8. View of EOT at Washermanpet
  • 9. Tail Skin Lowering for TBM 718 at Shenoy Nagar Station
  • 10. Front & middle Shields ready for lowering into Shaft
  • 12. Trial of Muck Tilting Divice
  • 13. VIEW OF 1ST TUNNEL ‐ SHENOY NAGAR STATION
  • 14. View of Twin Tunnel
  • 15. Casting shed & View of Commissioned Moulds
  • 16. Segment casting at casting Yard
  • 17. View of Segment stacking
  • 18. Cutter Head / Cutting Tools
  • 19. Sample TBM Data Record Types of reports/records •TBM Steering & alignment •TBM Excavation volume control •Tunnel grouting records •Ring survey & orientation record •Ring build record (steps, cracks, damage etc) •TBM Operational Data record
  • 20. Typical Soil Profile ‐ Packages 05
  • 21. Typical Mixed Soil Profile ‐ Packages 01 Ground Level : +2.855 Roof Top level : -0.420 Concourse Level : -6.420 Base Slab Level : -14.135 D-Wall Tip level : -24.600
  • 23. Typical Rock Soil Profile ‐ Packages 01
  • 25. Soil Profile‐ Chennai Central Station Project UAA 01
  • 27. Surface Constraints Saint Andrew’s Church SHIFTING OF MONUMENT AT RIPPON BUILDING AREA
  • 30. Surface Constraint Chennai Central SHC Shaft
  • 32. Surface Constraint - Railway tracks on the stretch High Court – Chennai Central and geological Profile
  • 33.
  • 34. Surface Constrain - Railway tracks on the stretch Chennai Central ‐ Mayday Park Tunnel
  • 35. View of Locomotive ‐ Mayday Park Tunnelling beneath Coovam River Under Coovam River
  • 36. 100% TYPICAL GEOLOGICAL PROFILE VARIATION 60% 80% Percent age Expected W1 W2 W3 W4 20% 40% 0% 4842.0133 4847 4862.9 4880 4891 4903 4910.4 4915 4923 4934 4940 4951 4956 4967 4977 4992 100% Chainage 60% 80% entage Actual Profile 0% 20% 40% 3 7 9 0 1 3 4 5 3 4 0 1 6 7 7 2 Perce 4842.0133 4847 4862.9 4880 4891 4903 4910.4 4915 4923 4934 4940 4951 4956 4967 4977 4992 Chainage W1‐Fresh Rock W2‐Slightly weathered Rock W3‐M Weathered Rock W4‐ Highly Weathered Rock
  • 37. Geological Variation Results: Cutter Consumption & Frequency of Intervention
  • 38. TBM retrieval in wet condition
  • 39. CHENNAI CENTRAL (Overlapping of Two Corridor)
  • 40. Retrieval Shaft at SCC ‐ Mayday Park Tunnel
  • 41. Obstacles during Tunnel Operation Ground Level CL Red Zone Ora Zon Gr Zone L TUNNEL A ange ne reen Zone Green Z Orange Zone TUNNEL B 1.0 mt 1.0 mt Bore well influence 1mt from Extrados of Tunnel Segment
  • 42. Obstacles during Tunnel Operation UAA 01 NO. OF EXISTING WELLS IN DIFFERENT ZONES: UAA01 Project RED ZONE (11.355 m. f T l ORANGE ZONE (5.15 m. from RED GREEN ZONE ( 4.5 m. from TOTAL R + O + G from Tunnel CL) 5. 5 R ZONE) ORANGE ZONE) Package 01 304 98 90 492 Package 05 61 24 60 145 Total 365 122 150 637
  • 43. BUILDING CONDITION SURVEY BUILDING CONDITION SURVEY
  • 44. TUNNELLING PERFORMANCE The TBMS are normally operated on a 24 hr basis, working 2 shifts per day. The following main results have been achieved: ¾ Average Daily Production:.12 ..Rings =16.8 m ¾¾ Best Day(09/02/2013): 39rings=54.6 m ¾ Best week(04/02/2013 to 09/02/2013): 139 rings=182 m ¾ Best Month ( Oct 2013): 525 rings= 735 m ¾We have achieved 39 Rings Boring in a day first time in the World Considering that all the 5 TBMs have been operated in a very sensitive urban environment, almost always in closed mode, these results can be regarded as very positive and above the usual standard.
  • 45. Heave pressure verification 3 50 4.00 4.50 5.00 2.00 2.50 3.00 3.50 ressures (bar) 0.50 1.00 1.50 Pr Cohesive material 0.00 0+220 0+260 0+300 0+340 0+380 0+420 0+460 0+500 0+540 0+580 0+620 0+660 0+700 0+740 0+780 0+820 0+860 0+900 0+940 0+980 1+020 1+060 1+100 1+140 1+180 1+220 1+260 1+300 1+340 1+380 1+420 1+460 1+500 1+540 1+580 CHAINAGE Heave pressure (by Jancsez th.) Recommended Max. Pressure
  • 46. Recommended EPB pressure and Grout Injection Pressure 3.00 2.00 2.50 ar) Pressures (b 1 00 1.50 0.50 1.00 0.00 1+580 1+620 1+660 1+700 1+740 1+780 1+820 1+860 1+900 1+940 1+980 2+020 2+060 2+100 2+140 2+180 2+220 2+260 2+300 2+340 2+380 2+420 2+460 2+500 CHAINAGE Recommended pressure Min.pressure Max.pressure Grout injection system
  • 47. Earth Pressure Monitoring 3 2.5 2 1.5 1 Pressure (bar) 0.5 0 0 200 400 600 800 1000 1200 1400 1600 1800 2000 Earth P Mannadi Station Ring No. D'W ll C tti High Court D'Wall Cutting Station Area 3.5 3 2.5 ure (bar) 2 1.5 1 0.5 Earth Pressu 0 0 200 400 600 800 1000 1200 1400 1600 1800 2000 Ring No.
  • 48. Typical Machining Parameters monitoring 30000 25000 20000 orce Thrust Force(kN) 3.5 3 2.5 2 M Cutting wheel Rotation (rpm) 15000 10000 5000 0 0 500 1000 1500 2000 Thrust Fo 1.5 1 0.5 0 0 500 1000 1500 2000 RPM Ring No. Ring No. Torque(MN.m) Advance Speed (mm/Min) 4 3.5 3 2.5 2 que 60 50 40 30 eed()mm/Min. 1.5 1 0.5 0 Torq 20 10 0 0 500 1000 1500 2000 Advance Spe 0 500 1000 1500 2000 Ring No. Ring No.
  • 49. Operation steps in Mechanized Tunneling ¾Making Launching Shaft ¾¾Assembly of TBM ¾ i i Sh f ¾Initial Drive ¾Muck Out Receiving Shaft ¾Tunnel Break through ¾Dissemble TBM ¾Boring ¾Assembly of Lining ¾Grouting ¾Segment Lining ¾Close of Launching shaft upon Completion ¾Retrieval of TBM to Groundt ¾Close of receiving shaft p p Segment yard ™Casting of Segment
  • 50. Type of TBM EPBM‐Mixed Ground Type EPB‐Soft Ground Type UAA 01 Washermanpet to Chennai Central M f t H k ht UAA 05 Shenoy Nagar to Thirumangalam Manufacture‐Herrenknecht Manufacture‐ Herrenknecht UAA 01 May day Park to Chennai EPB‐Rock/Mixed Face Central Manufacture‐Robbins
  • 52. Breaking Out Through Confinement
  • 53. Interface Tunnel ‐ Station Mining Through D Th h UAA 01 Drag Through Mining Through Station Trag Through Break In Break Out Break In Break Out Break In Break Out UAA 05 Mining Through h h reak hrough Drag Through Drag Through Br Th Break In Break Out Break In Break Out Break In
  • 54. TBM 717 Break In – Anna Nagar TBM Break In Shenoy Nagar Station Tower In‐
  • 55. View of 1st Tunnel & TBM 718 ‐ Shenoy Nagar Station
  • 56. Mining Through Station Plan Elevation
  • 59. 718 711 710 711 717 710
  • 60. Tunnel Boring Machine Specification TBM’s Cost of each TBM & backup equipment 33.5Cr TBM total weight 290 T Excavation diameter 6.6 m Overall length 9.7 m Electrical power 940 kW Left & right rotation speed Max 4.57 rpm Ram advance speed Max. 80 mm/min Ram jacks 32 # Total advance thrust force 42000 KN Earth pressure sensors 6 #
  • 61. Cross Passage Soil Treatment