The document discusses the construction challenges faced during the construction of the Chennai Metro rail project. Some key challenges discussed include:
- Tunnelling through varied and unpredictable soil and ground conditions including mixed soil, weathered rock, and fresh rock. This led to variations in cutter consumption and frequency of interventions.
- Tunnelling in a dense urban environment with constraints at the surface like buildings, monuments, railway tracks etc. Precise tunnelling control was required.
- Breaking into and out of underground metro stations posed challenges due to confinement and ensuring structural integrity of station areas. Specialized tunnelling techniques like drag-through mining were used.
- Ground control challenges due to presence
★ CALL US 9953330565 ( HOT Young Call Girls In Badarpur delhi NCR
Chennai Metro Tunnel Construction Challenges
1. INTERNATIONAL SEMINAR ON
MASS RAPID TRANSIT SYSTEM(MRTS)
4th‐5th November 2014
REVIEW AND ASSESSMENT OF CHALLENGES
DURING CONSTRUCTION OF CHENNAI
METRO
2. CONTENT
y PROJECT DETAILS
y PROJECT DESCRIPTION
y GEOLOGICAL AND GEOTECHNICAL OVERVIEW
y TUNNELLING PERFORMANCE (TBM ADVANCE/EXCAVATION)
y TUNNELING THROUGH STATION
y TUNNEL – STATION INTERFACE
y CROSS PASSAGE SOIL TREATMENT
3. DESIGN AND CONSTRUCTION OF UNDERGROUND
AND ASSOCIATED TUNNELS FOR UAA‐01 & UAA‐05
OF CHENNAI METRO
CLIENT :CHENNAI METRO RAIL LTD
GENERAL CONSULTANT :EMBYE
CONTRACTOR :TRANSTONNELSTORY‐AFCONS JV
DESIGNER :PARSONS BRINCKERHOFF
SOURCE OF FUND :FUNDED BY JICA
Total Twin Tunnel Length : 17.5 KM
19. Sample TBM Data Record
Types of reports/records
•TBM Steering & alignment
•TBM Excavation volume control
•Tunnel grouting records
•Ring survey & orientation record
•Ring build record (steps, cracks,
damage etc)
•TBM Operational Data record
41. Obstacles during Tunnel Operation
Ground Level
CL
Red
Zone
Ora
Zon
Gr
Zone
L
TUNNEL
A
ange
ne
reen Zone
Green Z
Orange
Zone
TUNNEL
B
1.0 mt 1.0 mt
Bore well influence 1mt from Extrados of Tunnel
Segment
42. Obstacles during Tunnel Operation
UAA 01
NO. OF EXISTING WELLS IN DIFFERENT ZONES: UAA01
Project
RED ZONE
(11.355 m.
f T l
ORANGE ZONE
(5.15 m. from RED
GREEN ZONE
( 4.5 m. from
TOTAL R + O +
G
from Tunnel
CL)
5. 5 R
ZONE)
ORANGE ZONE)
Package 01 304 98 90 492
Package 05
61 24 60 145
Total 365 122 150 637
44. TUNNELLING PERFORMANCE
The TBMS are normally operated on a 24 hr basis, working 2
shifts per day.
The following main results have been achieved:
¾ Average Daily Production:.12 ..Rings =16.8 m
¾¾ Best Day(09/02/2013): 39rings=54.6 m
¾ Best week(04/02/2013 to 09/02/2013): 139 rings=182 m
¾ Best Month ( Oct 2013): 525 rings= 735 m
¾We have achieved 39 Rings Boring in a day first time in
the World
Considering that all the 5 TBMs have been operated in a very sensitive urban
environment, almost always in closed mode, these results can be regarded as very
positive and above the usual standard.
49. Operation steps in Mechanized Tunneling
¾Making Launching Shaft
¾¾Assembly of TBM ¾ i i Sh f
¾Initial Drive
¾Muck Out
Receiving Shaft
¾Tunnel Break through
¾Dissemble TBM
¾Boring
¾Assembly of Lining
¾Grouting
¾Segment Lining
¾Close of Launching shaft
upon Completion
¾Retrieval of TBM to Groundt
¾Close of receiving shaft
p p
Segment yard
™Casting of Segment
50. Type of TBM
EPBM‐Mixed Ground Type EPB‐Soft Ground Type
UAA 01
Washermanpet to Chennai
Central
M f t H k ht
UAA 05
Shenoy Nagar to
Thirumangalam
Manufacture‐Herrenknecht Manufacture‐
Herrenknecht
UAA 01
May day Park to Chennai
EPB‐Rock/Mixed Face
Central
Manufacture‐Robbins
53. Interface Tunnel ‐ Station
Mining Through D Th h
UAA 01 Drag Through
Mining Through Station Trag Through
Break In Break Out Break In Break Out
Break In
Break Out
UAA 05
Mining Through h h
reak
hrough
Drag Through Drag Through
Br
Th
Break In
Break Out Break In Break Out Break In
54. TBM 717 Break In – Anna Nagar TBM Break In Shenoy Nagar Station
Tower
In‐
55. View of 1st Tunnel & TBM 718 ‐ Shenoy Nagar Station
60. Tunnel Boring Machine Specification
TBM’s
Cost of each TBM & backup equipment 33.5Cr
TBM total weight 290 T
Excavation diameter 6.6 m
Overall length 9.7 m
Electrical power 940 kW
Left & right rotation speed Max 4.57 rpm
Ram advance speed Max. 80 mm/min
Ram jacks 32 #
Total advance thrust force 42000 KN
Earth pressure sensors 6 #