SlideShare a Scribd company logo
1
RUBNAWAZ
2015-UET-CCET-CIVIL-02
3rd SEMESTER
CIVIL ENGINEERING DEPARTMENT
February 2012
GOVERNMENT OF THE PUNJAB
COMMUNICATION & WORKS DEPARTMENT
Construction of Flyover on G.T Road
at Aziz Cross Gujranwala
February 2012
GOVERNMENT OF THE PUNJAB
CONSTRUCTION OF FLYOVER ON
G.T ROAD AT AZIZ CROSS GUJRANWALA
Construction of Flyover on G.T Road
at Aziz Cross Gujranwala
SALIENT FEATURE
 ADP (2016-17) Gr. Sr. No. 2775
 Approved Cost Rs. 6672 Million
 Construction Cost Rs. 3435 M
 Land Acquisition (80 Kanal) Rs. 2920 M
 Miscellaneous Rs. 317 M
 Consultant M/s NESPAK
 Contract M/s NLC
 Client C & W Dept
 Agreement Amount Rs.3115 M (9.35% below Est.cost)
 Date of Commencement 30.01.2016
 Date of Completion 29.11.2016
INTRODUCTION
 Aziz Cross project is a signal free interchange with partial clover
leaf system and two additional directional ramps.
Clover leaf interchange Partial Clover leaf
interchange with two
directional ramps instead
of loops
INTRODUCTION
 There are normally 32 conflicts at any interchange which are
completely resolved at Aziz Cross.
32 No. Traffic Conflicts
Traffic Count 2014
31,775
36,543
17,541
RAWALPINDI
LAHORE
GUJRANWALA
SIALKOT
13,000
NEW TRAFFIC DIRECTIONS & VOLUMES (ADT 2014)
BASIC COMPONENTS OF FLYOVER
Bridge cross-section can be divided
into two portions.
1. Super Structure
This portion receives the live load
directly. For example, Box Girder
2. Sub Structure
This Portion supports the entire
structure and live loads.
 Piles
 Pile cap
 Piers
 Abutments
Web
Web
Pier
Canopy
Pier
Shaft
Pile Cap
Pile
Pile
Pile
Super
Structure
Sub
Structure
CONCRETE PILES
A pile is a vertical structural element of a deep foundation which
transfers super structure loads to the earth farther down from the
surface to a subsurface layer.
PILE CAP
PILE CAP
Pile cap is a thick
reinforced concrete mat that
rests on concrete piles that
have been casted into ground.
concrete pile cap distributes the
load of the superstructure (from
piers and abutments into the
piles.
Pile Cap
Piles
Pier
PILE CAP AND PIER
PIER
A pier is a reinforced,
raised structure in form of
pillars typically supported by
well-spaced pile caps. It
transfers the loads from deck to
pile caps.
For this project, special shape
of pier is adopted. It as two
components
1. Pier Shaft as column
2. Pier Canopy as transom
Pier Canopy
Pier Shaft
Box Girder
Abutment refers to the substructure at the ends of a bridge span. It
supports;
 Super Structure load
 Live Load
 Lateral Earth Pressure
ABUTMENTS
Abutment
Pile Cap
Piles
REINFORCED EARTH WORK
 Reinforced earth wall is earth retaining structure and provided at
approaches (from road level to bridge level).
 The key components of a Reinforced Earth wall are geo-strips,
granular backfill and precast concrete facing panels.
 The frictional bond between the backfill supports the lateral earth
pressure and stresses induced due to traffic load.
ABUTMENT 01 ABUTMENT 06
LOOP 2 ABUTMENT 07
REINFORCED EARTH WORK
PRE-STRESSED BOX GIRDERS
Bottom View of Box Girder
Piers
 An optimal and most efficient design of beam is box girder. A box girder
consists of enclosed tube with multiple walls.
 The advantage of a box girder is that it better resists torsion. Having
multiple vertical webs, it can also carry more load than an I-shape girder
of equal height.
Pre-stressing Mechanism
SCOPE OF WORK
12/14/2016
Flyover 1
Length 301.5
Piles 80
P. Cap 15
Piers 15
Abt. 2
Spans 10Flyover 2
Length 301.5
Piles 66
P. Cap 11
Piers 12
Abt. 2
Spans 10
Flyover 5
Length 80.05
Piles 38
P. Cap 4
Piers 6
Abt. 2
Spans 3Flyover 3
Length 417.3
Piles 64
P. Cap 15
Piers 13
Abt. 2
Spans 14
Flyover 4
Length 564.41
Piles 84
P. Cap 20
Piers 18
Abt. 2
Spans 18
RWP
LHR
GRW
SKT
Pile= 332 Ramp 3 (L=361.14m) Ramp 6(L=369.39 m) Bridge approaches (841m)
Pile caps=65 Ramp 3A(L=573.11m) Ramp 7(L=369.39 m)
Abutment= 10 Ramp 4( L=379.35m) Loop 1(270.18m) Bridge Lengths(1664m)
Piers=60 Ramp 5 (L=846.94m) Loop 2(L=195.23) Road Length (4660m)
FLYOVER S– 1, 2, 3 & 4
 Piles 100 % Completed (294 out of 294)
 Pile Caps 100 % Completed (62 out of 62)
 Piers 100 % Completed (62 out of 62)
 Abutment 100 % Completed (8 out of 8)
 Box Girders 20% in progress (4 out of 17)
 Reinforce Earth Wall 50 % Completed (0.6 km out of 1.12 km)
 At Grade Roads 60% up to WBM (3 Km out of 5 Km)
RAILWAY BRIDGE
 Piles 100% Completed (38 out of 38)
 Pile Caps 100% Completed (4 out of 4)
 Piers 100% Completed (2 out of 2)
 Transoms 50% Completed (1 out of 2)
 Abutments 50% Completed (1 out of 2)
 Pre-cast Girders 100% Completed (21 out of 21)
PHYSICAL PROGRESS
Year Release Expr. %age Remarks
2014-15 2500 2500 100%
Payment made for land
acquisition.
2015-16 1555 1555 100%
Rs. 400 M land acquisition.
Rs. 215 M shifting of
services.
Rs. 940 M paid to NLC.
2016-17 1000 510 51% Rs. 510 M paid to NLC.
FINANCIAL PROGRESS
Presentation on Flyover at Aziz Cross on GT Road Gujranwala

More Related Content

What's hot

ROAD CONSTRUCTION(BITUMEN) SUMMER TRAINING REPORT
ROAD CONSTRUCTION(BITUMEN) SUMMER TRAINING REPORTROAD CONSTRUCTION(BITUMEN) SUMMER TRAINING REPORT
ROAD CONSTRUCTION(BITUMEN) SUMMER TRAINING REPORT
ssuser5fea8f
 
Benkelman beam deflection studies
Benkelman beam deflection studiesBenkelman beam deflection studies
Benkelman beam deflection studies
vikasravekar
 
Falling weight deflection test
Falling weight deflection testFalling weight deflection test
Falling weight deflection test
jagadish civil
 
Presentation on Summer internship on Road Construction
Presentation on Summer internship on Road ConstructionPresentation on Summer internship on Road Construction
Presentation on Summer internship on Road Construction
Self-employed
 
Bitumin road construction
Bitumin road constructionBitumin road construction
Bitumin road construction
ritwizkumar1
 
DESIGN PROJECT FOR PAVEMENT
DESIGN PROJECT FOR PAVEMENTDESIGN PROJECT FOR PAVEMENT
DESIGN PROJECT FOR PAVEMENT
Sukhdarshan Singh
 
Box Pushing Technique
Box Pushing TechniqueBox Pushing Technique
Box Pushing Technique
Seminar Links
 
Ppt u girder casting by l.k.prasad
Ppt u girder casting by l.k.prasadPpt u girder casting by l.k.prasad
Ppt u girder casting by l.k.prasad
Lachhmikant. Prasad
 
Construction Of Road
Construction Of RoadConstruction Of Road
Construction Of Road
Shahid Raza
 
TRAINING REPORT ON COSTRUCTION OF FLYOVER FROM MITHAPUR TO CHIRIYATAND (BIHAR)
TRAINING REPORT ON  COSTRUCTION OF FLYOVER FROM  MITHAPUR TO CHIRIYATAND (BIHAR)TRAINING REPORT ON  COSTRUCTION OF FLYOVER FROM  MITHAPUR TO CHIRIYATAND (BIHAR)
TRAINING REPORT ON COSTRUCTION OF FLYOVER FROM MITHAPUR TO CHIRIYATAND (BIHAR)
vishal prakash
 
GGBS
GGBSGGBS
Bituminous road construction
Bituminous road constructionBituminous road construction
Bituminous road construction
Anitha Jacob
 
BITUMINOUS ROAD PPT
BITUMINOUS ROAD PPTBITUMINOUS ROAD PPT
BITUMINOUS ROAD PPT
shubham paliwal
 
Roller - Compacted Concrete (RCC)
Roller - Compacted Concrete (RCC)Roller - Compacted Concrete (RCC)
Roller - Compacted Concrete (RCC)
SSudhaVelan
 
Inspection and maintenance of bridge
Inspection and maintenance of bridgeInspection and maintenance of bridge
Inspection and maintenance of bridge
AKASH SHAH
 
Precast Wings segment casting NHAI Spine
Precast Wings segment casting NHAI Spine Precast Wings segment casting NHAI Spine
Precast Wings segment casting NHAI Spine
Roshan Sharma
 
Summer Internship Presentation of Building
Summer Internship Presentation of Building Summer Internship Presentation of Building
Summer Internship Presentation of Building
Self-employed
 
Flyover construction
Flyover constructionFlyover construction
Flyover construction
Akhilesh Kumar
 
Roads design as per IRC 37
Roads design as per IRC 37Roads design as per IRC 37
Roads design as per IRC 37
Amardeep Singh
 
Shri
ShriShri

What's hot (20)

ROAD CONSTRUCTION(BITUMEN) SUMMER TRAINING REPORT
ROAD CONSTRUCTION(BITUMEN) SUMMER TRAINING REPORTROAD CONSTRUCTION(BITUMEN) SUMMER TRAINING REPORT
ROAD CONSTRUCTION(BITUMEN) SUMMER TRAINING REPORT
 
Benkelman beam deflection studies
Benkelman beam deflection studiesBenkelman beam deflection studies
Benkelman beam deflection studies
 
Falling weight deflection test
Falling weight deflection testFalling weight deflection test
Falling weight deflection test
 
Presentation on Summer internship on Road Construction
Presentation on Summer internship on Road ConstructionPresentation on Summer internship on Road Construction
Presentation on Summer internship on Road Construction
 
Bitumin road construction
Bitumin road constructionBitumin road construction
Bitumin road construction
 
DESIGN PROJECT FOR PAVEMENT
DESIGN PROJECT FOR PAVEMENTDESIGN PROJECT FOR PAVEMENT
DESIGN PROJECT FOR PAVEMENT
 
Box Pushing Technique
Box Pushing TechniqueBox Pushing Technique
Box Pushing Technique
 
Ppt u girder casting by l.k.prasad
Ppt u girder casting by l.k.prasadPpt u girder casting by l.k.prasad
Ppt u girder casting by l.k.prasad
 
Construction Of Road
Construction Of RoadConstruction Of Road
Construction Of Road
 
TRAINING REPORT ON COSTRUCTION OF FLYOVER FROM MITHAPUR TO CHIRIYATAND (BIHAR)
TRAINING REPORT ON  COSTRUCTION OF FLYOVER FROM  MITHAPUR TO CHIRIYATAND (BIHAR)TRAINING REPORT ON  COSTRUCTION OF FLYOVER FROM  MITHAPUR TO CHIRIYATAND (BIHAR)
TRAINING REPORT ON COSTRUCTION OF FLYOVER FROM MITHAPUR TO CHIRIYATAND (BIHAR)
 
GGBS
GGBSGGBS
GGBS
 
Bituminous road construction
Bituminous road constructionBituminous road construction
Bituminous road construction
 
BITUMINOUS ROAD PPT
BITUMINOUS ROAD PPTBITUMINOUS ROAD PPT
BITUMINOUS ROAD PPT
 
Roller - Compacted Concrete (RCC)
Roller - Compacted Concrete (RCC)Roller - Compacted Concrete (RCC)
Roller - Compacted Concrete (RCC)
 
Inspection and maintenance of bridge
Inspection and maintenance of bridgeInspection and maintenance of bridge
Inspection and maintenance of bridge
 
Precast Wings segment casting NHAI Spine
Precast Wings segment casting NHAI Spine Precast Wings segment casting NHAI Spine
Precast Wings segment casting NHAI Spine
 
Summer Internship Presentation of Building
Summer Internship Presentation of Building Summer Internship Presentation of Building
Summer Internship Presentation of Building
 
Flyover construction
Flyover constructionFlyover construction
Flyover construction
 
Roads design as per IRC 37
Roads design as per IRC 37Roads design as per IRC 37
Roads design as per IRC 37
 
Shri
ShriShri
Shri
 

Viewers also liked

Highway Construction
Highway Construction  Highway Construction
Highway Construction
zapada rahul
 
Highway construction PPT
Highway construction PPTHighway construction PPT
Highway construction PPT
Vikas Sukhwal
 
LIFT IRRIGATION SYSTEM
LIFT IRRIGATION SYSTEMLIFT IRRIGATION SYSTEM
LIFT IRRIGATION SYSTEM
Anup Kude
 
JAPAN: NEW STRATEGIES FOR A NEW REALITY
JAPAN: NEW STRATEGIES FOR A NEW REALITYJAPAN: NEW STRATEGIES FOR A NEW REALITY
JAPAN: NEW STRATEGIES FOR A NEW REALITYAnkita Kolamkar
 
Seminar on Environmental Impact Assessment
Seminar on Environmental Impact AssessmentSeminar on Environmental Impact Assessment
Seminar on Environmental Impact Assessment
ashwinpand90
 
Highway construction or Road work report
Highway construction or Road work reportHighway construction or Road work report
Highway construction or Road work report
Abdul rahman kureshi
 
Under water concreting
Under water concretingUnder water concreting
Under water concreting
Agnesh Shetty
 
Design of flyover elements
Design of flyover elementsDesign of flyover elements
Design of flyover elements
subbu lakshmi
 
(mr. akash kolamkar) Rajapeth ROB Flyover seminar amravati an detailed struct...
(mr. akash kolamkar) Rajapeth ROB Flyover seminar amravati an detailed struct...(mr. akash kolamkar) Rajapeth ROB Flyover seminar amravati an detailed struct...
(mr. akash kolamkar) Rajapeth ROB Flyover seminar amravati an detailed struct...
Bharat Badre
 
Skybus metro as a mode of transportation
Skybus metro as a mode of transportationSkybus metro as a mode of transportation
Skybus metro as a mode of transportation
Pramod Chinchansur
 
Highway failure & their maintenance seminar report
Highway failure & their maintenance seminar reportHighway failure & their maintenance seminar report
Highway failure & their maintenance seminar report
Being Deepak
 
Recent construction technologies
Recent construction technologiesRecent construction technologies
Recent construction technologies
Chandana Yadav
 
PWD, national highway
PWD, national highwayPWD, national highway
PWD, national highway
Shivam Srivastava
 
Underground construction Techniques civil final year seminar
Underground construction Techniques civil final year seminarUnderground construction Techniques civil final year seminar
Underground construction Techniques civil final year seminar
Pavan Kumar N
 
Piling of a flyover (AUST 2.2 A)
Piling of a flyover (AUST 2.2 A)Piling of a flyover (AUST 2.2 A)
Piling of a flyover (AUST 2.2 A)
Shakhawat Hossain Mehran
 
Highway failure & their maintenance ppt
 Highway failure & their maintenance ppt Highway failure & their maintenance ppt
Highway failure & their maintenance ppt
Being Deepak
 
Geological challenges & ecological effects of highway construction
Geological challenges & ecological effects of highway constructionGeological challenges & ecological effects of highway construction
Geological challenges & ecological effects of highway construction
Abhinav Anand
 
Presentation on Traffic Volume Survey
Presentation on Traffic Volume SurveyPresentation on Traffic Volume Survey
Presentation on Traffic Volume SurveyFiroz Ovi
 
Lift irrigation
Lift irrigationLift irrigation
Lift irrigation
Sk Rabial
 

Viewers also liked (20)

Chapter1
Chapter1Chapter1
Chapter1
 
Highway Construction
Highway Construction  Highway Construction
Highway Construction
 
Highway construction PPT
Highway construction PPTHighway construction PPT
Highway construction PPT
 
LIFT IRRIGATION SYSTEM
LIFT IRRIGATION SYSTEMLIFT IRRIGATION SYSTEM
LIFT IRRIGATION SYSTEM
 
JAPAN: NEW STRATEGIES FOR A NEW REALITY
JAPAN: NEW STRATEGIES FOR A NEW REALITYJAPAN: NEW STRATEGIES FOR A NEW REALITY
JAPAN: NEW STRATEGIES FOR A NEW REALITY
 
Seminar on Environmental Impact Assessment
Seminar on Environmental Impact AssessmentSeminar on Environmental Impact Assessment
Seminar on Environmental Impact Assessment
 
Highway construction or Road work report
Highway construction or Road work reportHighway construction or Road work report
Highway construction or Road work report
 
Under water concreting
Under water concretingUnder water concreting
Under water concreting
 
Design of flyover elements
Design of flyover elementsDesign of flyover elements
Design of flyover elements
 
(mr. akash kolamkar) Rajapeth ROB Flyover seminar amravati an detailed struct...
(mr. akash kolamkar) Rajapeth ROB Flyover seminar amravati an detailed struct...(mr. akash kolamkar) Rajapeth ROB Flyover seminar amravati an detailed struct...
(mr. akash kolamkar) Rajapeth ROB Flyover seminar amravati an detailed struct...
 
Skybus metro as a mode of transportation
Skybus metro as a mode of transportationSkybus metro as a mode of transportation
Skybus metro as a mode of transportation
 
Highway failure & their maintenance seminar report
Highway failure & their maintenance seminar reportHighway failure & their maintenance seminar report
Highway failure & their maintenance seminar report
 
Recent construction technologies
Recent construction technologiesRecent construction technologies
Recent construction technologies
 
PWD, national highway
PWD, national highwayPWD, national highway
PWD, national highway
 
Underground construction Techniques civil final year seminar
Underground construction Techniques civil final year seminarUnderground construction Techniques civil final year seminar
Underground construction Techniques civil final year seminar
 
Piling of a flyover (AUST 2.2 A)
Piling of a flyover (AUST 2.2 A)Piling of a flyover (AUST 2.2 A)
Piling of a flyover (AUST 2.2 A)
 
Highway failure & their maintenance ppt
 Highway failure & their maintenance ppt Highway failure & their maintenance ppt
Highway failure & their maintenance ppt
 
Geological challenges & ecological effects of highway construction
Geological challenges & ecological effects of highway constructionGeological challenges & ecological effects of highway construction
Geological challenges & ecological effects of highway construction
 
Presentation on Traffic Volume Survey
Presentation on Traffic Volume SurveyPresentation on Traffic Volume Survey
Presentation on Traffic Volume Survey
 
Lift irrigation
Lift irrigationLift irrigation
Lift irrigation
 

Similar to Presentation on Flyover at Aziz Cross on GT Road Gujranwala

Construction of Box Girders, Piers, Piles and Roads by Engineer Muhammad K...
 Construction of Box Girders, Piers, Piles and Roads   by Engineer Muhammad K... Construction of Box Girders, Piers, Piles and Roads   by Engineer Muhammad K...
Construction of Box Girders, Piers, Piles and Roads by Engineer Muhammad K...
Kamal787
 
Saurabhk601
Saurabhk601Saurabhk601
Saurabhk601
Saurabh601
 
Floating Bridge
Floating BridgeFloating Bridge
Floating Bridge
Budi Suryanto
 
Presentation on construction of cable stay bridge - a modern technique for su...
Presentation on construction of cable stay bridge - a modern technique for su...Presentation on construction of cable stay bridge - a modern technique for su...
Presentation on construction of cable stay bridge - a modern technique for su...
Rajesh Prasad
 
Summer Training Report =Bihar Rajya pul Nirman Nigam
Summer Training Report =Bihar Rajya pul Nirman NigamSummer Training Report =Bihar Rajya pul Nirman Nigam
Summer Training Report =Bihar Rajya pul Nirman Nigam
Raju kumar Gautam
 
training report LMRC
training report LMRCtraining report LMRC
training report LMRC
Kamesh Tripathi
 
Cable Stay Bridge construction at Bardhman using LARSA and LUSAS four dimensi...
Cable Stay Bridge construction at Bardhman using LARSA and LUSAS four dimensi...Cable Stay Bridge construction at Bardhman using LARSA and LUSAS four dimensi...
Cable Stay Bridge construction at Bardhman using LARSA and LUSAS four dimensi...
Rajesh Prasad
 
Presentation about Ircon's SGEDT project in Malaysia.
Presentation about Ircon's SGEDT project in Malaysia.Presentation about Ircon's SGEDT project in Malaysia.
Presentation about Ircon's SGEDT project in Malaysia.
Hitesh Khanna
 
IIBE ppt at Lucknow dt 25.05.18
IIBE ppt at Lucknow dt 25.05.18IIBE ppt at Lucknow dt 25.05.18
IIBE ppt at Lucknow dt 25.05.18
Rajesh Prasad
 
IIBE ppt at Lucknow dt 25.05.18
IIBE ppt at Lucknow dt 25.05.18IIBE ppt at Lucknow dt 25.05.18
IIBE ppt at Lucknow dt 25.05.18
Rajesh Prasad
 
Design Proposal for a Single and Double Span Bridge using Cost Analysis
Design Proposal for a Single and Double Span Bridge using Cost AnalysisDesign Proposal for a Single and Double Span Bridge using Cost Analysis
Design Proposal for a Single and Double Span Bridge using Cost AnalysisMichael Masi, Jr. Eng.
 
Larsen and Toubro (Lucknow Metro Project) Summer Internship Presentation
Larsen and Toubro (Lucknow Metro Project) Summer Internship PresentationLarsen and Toubro (Lucknow Metro Project) Summer Internship Presentation
Larsen and Toubro (Lucknow Metro Project) Summer Internship Presentation
ShuBham RaNa
 
Kearney Precast Concrete Deck Panel Bridge Project
Kearney Precast Concrete Deck Panel Bridge ProjectKearney Precast Concrete Deck Panel Bridge Project
Kearney Precast Concrete Deck Panel Bridge Project
Jill Reeves
 
Kearney Precast Concrete Deck Panel Bridge Project
Kearney Precast Concrete Deck Panel Bridge ProjectKearney Precast Concrete Deck Panel Bridge Project
Kearney Precast Concrete Deck Panel Bridge Project
Jill Reeves
 
IRJET- Seismic Analysis of Curve Cable-Stayed Bridge
IRJET- Seismic Analysis of Curve Cable-Stayed BridgeIRJET- Seismic Analysis of Curve Cable-Stayed Bridge
IRJET- Seismic Analysis of Curve Cable-Stayed Bridge
IRJET Journal
 
ANALYSIS OF PRE-STRESSED BRIDGE CONSTRUCTION
ANALYSIS OF PRE-STRESSED BRIDGE CONSTRUCTIONANALYSIS OF PRE-STRESSED BRIDGE CONSTRUCTION
ANALYSIS OF PRE-STRESSED BRIDGE CONSTRUCTION
atchitect and design
 
Turga PSP_Lower Dam.pptx
Turga PSP_Lower Dam.pptxTurga PSP_Lower Dam.pptx
Turga PSP_Lower Dam.pptx
ssuserde6364
 
Dragline Planning
Dragline PlanningDragline Planning
Dragline Planning
VR M
 

Similar to Presentation on Flyover at Aziz Cross on GT Road Gujranwala (20)

Construction of Box Girders, Piers, Piles and Roads by Engineer Muhammad K...
 Construction of Box Girders, Piers, Piles and Roads   by Engineer Muhammad K... Construction of Box Girders, Piers, Piles and Roads   by Engineer Muhammad K...
Construction of Box Girders, Piers, Piles and Roads by Engineer Muhammad K...
 
Saurabhk601
Saurabhk601Saurabhk601
Saurabhk601
 
Floating Bridge
Floating BridgeFloating Bridge
Floating Bridge
 
Presentation on construction of cable stay bridge - a modern technique for su...
Presentation on construction of cable stay bridge - a modern technique for su...Presentation on construction of cable stay bridge - a modern technique for su...
Presentation on construction of cable stay bridge - a modern technique for su...
 
Summer Training Report =Bihar Rajya pul Nirman Nigam
Summer Training Report =Bihar Rajya pul Nirman NigamSummer Training Report =Bihar Rajya pul Nirman Nigam
Summer Training Report =Bihar Rajya pul Nirman Nigam
 
training report LMRC
training report LMRCtraining report LMRC
training report LMRC
 
Cable Stay Bridge construction at Bardhman using LARSA and LUSAS four dimensi...
Cable Stay Bridge construction at Bardhman using LARSA and LUSAS four dimensi...Cable Stay Bridge construction at Bardhman using LARSA and LUSAS four dimensi...
Cable Stay Bridge construction at Bardhman using LARSA and LUSAS four dimensi...
 
Presentation about Ircon's SGEDT project in Malaysia.
Presentation about Ircon's SGEDT project in Malaysia.Presentation about Ircon's SGEDT project in Malaysia.
Presentation about Ircon's SGEDT project in Malaysia.
 
IIBE ppt at Lucknow dt 25.05.18
IIBE ppt at Lucknow dt 25.05.18IIBE ppt at Lucknow dt 25.05.18
IIBE ppt at Lucknow dt 25.05.18
 
IIBE ppt at Lucknow dt 25.05.18
IIBE ppt at Lucknow dt 25.05.18IIBE ppt at Lucknow dt 25.05.18
IIBE ppt at Lucknow dt 25.05.18
 
Design Proposal for a Single and Double Span Bridge using Cost Analysis
Design Proposal for a Single and Double Span Bridge using Cost AnalysisDesign Proposal for a Single and Double Span Bridge using Cost Analysis
Design Proposal for a Single and Double Span Bridge using Cost Analysis
 
Larsen and Toubro (Lucknow Metro Project) Summer Internship Presentation
Larsen and Toubro (Lucknow Metro Project) Summer Internship PresentationLarsen and Toubro (Lucknow Metro Project) Summer Internship Presentation
Larsen and Toubro (Lucknow Metro Project) Summer Internship Presentation
 
Kearney Precast Concrete Deck Panel Bridge Project
Kearney Precast Concrete Deck Panel Bridge ProjectKearney Precast Concrete Deck Panel Bridge Project
Kearney Precast Concrete Deck Panel Bridge Project
 
Kearney Precast Concrete Deck Panel Bridge Project
Kearney Precast Concrete Deck Panel Bridge ProjectKearney Precast Concrete Deck Panel Bridge Project
Kearney Precast Concrete Deck Panel Bridge Project
 
IRJET- Seismic Analysis of Curve Cable-Stayed Bridge
IRJET- Seismic Analysis of Curve Cable-Stayed BridgeIRJET- Seismic Analysis of Curve Cable-Stayed Bridge
IRJET- Seismic Analysis of Curve Cable-Stayed Bridge
 
New mandovi bridge
New mandovi bridgeNew mandovi bridge
New mandovi bridge
 
ANALYSIS OF PRE-STRESSED BRIDGE CONSTRUCTION
ANALYSIS OF PRE-STRESSED BRIDGE CONSTRUCTIONANALYSIS OF PRE-STRESSED BRIDGE CONSTRUCTION
ANALYSIS OF PRE-STRESSED BRIDGE CONSTRUCTION
 
Turga PSP_Lower Dam.pptx
Turga PSP_Lower Dam.pptxTurga PSP_Lower Dam.pptx
Turga PSP_Lower Dam.pptx
 
Dragline Planning
Dragline PlanningDragline Planning
Dragline Planning
 
Training PPT
Training PPTTraining PPT
Training PPT
 

More from Rubnawaz Bhatti

BRT.pptx
BRT.pptxBRT.pptx
BRT.pptx
Rubnawaz Bhatti
 
Hydro Power Plants of Pakistan
Hydro Power Plants of PakistanHydro Power Plants of Pakistan
Hydro Power Plants of Pakistan
Rubnawaz Bhatti
 
Characteristics of effective technical communication
Characteristics of effective technical communicationCharacteristics of effective technical communication
Characteristics of effective technical communication
Rubnawaz Bhatti
 
Hydropower plants of pakistan
Hydropower plants of pakistanHydropower plants of pakistan
Hydropower plants of pakistan
Rubnawaz Bhatti
 
Seasonal calendar Sindh Pakistan
Seasonal calendar Sindh PakistanSeasonal calendar Sindh Pakistan
Seasonal calendar Sindh Pakistan
Rubnawaz Bhatti
 
Rivers of Pakistan
Rivers of PakistanRivers of Pakistan
Rivers of Pakistan
Rubnawaz Bhatti
 
Role of project management in construction industry
Role of project management in construction industryRole of project management in construction industry
Role of project management in construction industry
Rubnawaz Bhatti
 
Neelum jhelum hydroelectric project ( NJHEP)
Neelum jhelum hydroelectric project ( NJHEP)Neelum jhelum hydroelectric project ( NJHEP)
Neelum jhelum hydroelectric project ( NJHEP)
Rubnawaz Bhatti
 
Al bairaj al bait
Al bairaj al bait  Al bairaj al bait
Al bairaj al bait
Rubnawaz Bhatti
 
Report on Neelum Jhelum Hyrdoelectic project
Report on Neelum Jhelum Hyrdoelectic projectReport on Neelum Jhelum Hyrdoelectic project
Report on Neelum Jhelum Hyrdoelectic project
Rubnawaz Bhatti
 
Scaffolding & Its Hazards (Civil Engineering)
Scaffolding & Its Hazards (Civil Engineering)Scaffolding & Its Hazards (Civil Engineering)
Scaffolding & Its Hazards (Civil Engineering)
Rubnawaz Bhatti
 
Religious Extremism in Pakistan
Religious Extremism in PakistanReligious Extremism in Pakistan
Religious Extremism in Pakistan
Rubnawaz Bhatti
 

More from Rubnawaz Bhatti (12)

BRT.pptx
BRT.pptxBRT.pptx
BRT.pptx
 
Hydro Power Plants of Pakistan
Hydro Power Plants of PakistanHydro Power Plants of Pakistan
Hydro Power Plants of Pakistan
 
Characteristics of effective technical communication
Characteristics of effective technical communicationCharacteristics of effective technical communication
Characteristics of effective technical communication
 
Hydropower plants of pakistan
Hydropower plants of pakistanHydropower plants of pakistan
Hydropower plants of pakistan
 
Seasonal calendar Sindh Pakistan
Seasonal calendar Sindh PakistanSeasonal calendar Sindh Pakistan
Seasonal calendar Sindh Pakistan
 
Rivers of Pakistan
Rivers of PakistanRivers of Pakistan
Rivers of Pakistan
 
Role of project management in construction industry
Role of project management in construction industryRole of project management in construction industry
Role of project management in construction industry
 
Neelum jhelum hydroelectric project ( NJHEP)
Neelum jhelum hydroelectric project ( NJHEP)Neelum jhelum hydroelectric project ( NJHEP)
Neelum jhelum hydroelectric project ( NJHEP)
 
Al bairaj al bait
Al bairaj al bait  Al bairaj al bait
Al bairaj al bait
 
Report on Neelum Jhelum Hyrdoelectic project
Report on Neelum Jhelum Hyrdoelectic projectReport on Neelum Jhelum Hyrdoelectic project
Report on Neelum Jhelum Hyrdoelectic project
 
Scaffolding & Its Hazards (Civil Engineering)
Scaffolding & Its Hazards (Civil Engineering)Scaffolding & Its Hazards (Civil Engineering)
Scaffolding & Its Hazards (Civil Engineering)
 
Religious Extremism in Pakistan
Religious Extremism in PakistanReligious Extremism in Pakistan
Religious Extremism in Pakistan
 

Recently uploaded

Design and Analysis of Algorithms-DP,Backtracking,Graphs,B&B
Design and Analysis of Algorithms-DP,Backtracking,Graphs,B&BDesign and Analysis of Algorithms-DP,Backtracking,Graphs,B&B
Design and Analysis of Algorithms-DP,Backtracking,Graphs,B&B
Sreedhar Chowdam
 
Pile Foundation by Venkatesh Taduvai (Sub Geotechnical Engineering II)-conver...
Pile Foundation by Venkatesh Taduvai (Sub Geotechnical Engineering II)-conver...Pile Foundation by Venkatesh Taduvai (Sub Geotechnical Engineering II)-conver...
Pile Foundation by Venkatesh Taduvai (Sub Geotechnical Engineering II)-conver...
AJAYKUMARPUND1
 
space technology lecture notes on satellite
space technology lecture notes on satellitespace technology lecture notes on satellite
space technology lecture notes on satellite
ongomchris
 
Sachpazis:Terzaghi Bearing Capacity Estimation in simple terms with Calculati...
Sachpazis:Terzaghi Bearing Capacity Estimation in simple terms with Calculati...Sachpazis:Terzaghi Bearing Capacity Estimation in simple terms with Calculati...
Sachpazis:Terzaghi Bearing Capacity Estimation in simple terms with Calculati...
Dr.Costas Sachpazis
 
Final project report on grocery store management system..pdf
Final project report on grocery store management system..pdfFinal project report on grocery store management system..pdf
Final project report on grocery store management system..pdf
Kamal Acharya
 
Architectural Portfolio Sean Lockwood
Architectural Portfolio Sean LockwoodArchitectural Portfolio Sean Lockwood
Architectural Portfolio Sean Lockwood
seandesed
 
ethical hacking in wireless-hacking1.ppt
ethical hacking in wireless-hacking1.pptethical hacking in wireless-hacking1.ppt
ethical hacking in wireless-hacking1.ppt
Jayaprasanna4
 
Gen AI Study Jams _ For the GDSC Leads in India.pdf
Gen AI Study Jams _ For the GDSC Leads in India.pdfGen AI Study Jams _ For the GDSC Leads in India.pdf
Gen AI Study Jams _ For the GDSC Leads in India.pdf
gdsczhcet
 
AKS UNIVERSITY Satna Final Year Project By OM Hardaha.pdf
AKS UNIVERSITY Satna Final Year Project By OM Hardaha.pdfAKS UNIVERSITY Satna Final Year Project By OM Hardaha.pdf
AKS UNIVERSITY Satna Final Year Project By OM Hardaha.pdf
SamSarthak3
 
ASME IX(9) 2007 Full Version .pdf
ASME IX(9)  2007 Full Version       .pdfASME IX(9)  2007 Full Version       .pdf
ASME IX(9) 2007 Full Version .pdf
AhmedHussein950959
 
在线办理(ANU毕业证书)澳洲国立大学毕业证录取通知书一模一样
在线办理(ANU毕业证书)澳洲国立大学毕业证录取通知书一模一样在线办理(ANU毕业证书)澳洲国立大学毕业证录取通知书一模一样
在线办理(ANU毕业证书)澳洲国立大学毕业证录取通知书一模一样
obonagu
 
block diagram and signal flow graph representation
block diagram and signal flow graph representationblock diagram and signal flow graph representation
block diagram and signal flow graph representation
Divya Somashekar
 
road safety engineering r s e unit 3.pdf
road safety engineering  r s e unit 3.pdfroad safety engineering  r s e unit 3.pdf
road safety engineering r s e unit 3.pdf
VENKATESHvenky89705
 
一比一原版(IIT毕业证)伊利诺伊理工大学毕业证成绩单专业办理
一比一原版(IIT毕业证)伊利诺伊理工大学毕业证成绩单专业办理一比一原版(IIT毕业证)伊利诺伊理工大学毕业证成绩单专业办理
一比一原版(IIT毕业证)伊利诺伊理工大学毕业证成绩单专业办理
zwunae
 
一比一原版(SFU毕业证)西蒙菲莎大学毕业证成绩单如何办理
一比一原版(SFU毕业证)西蒙菲莎大学毕业证成绩单如何办理一比一原版(SFU毕业证)西蒙菲莎大学毕业证成绩单如何办理
一比一原版(SFU毕业证)西蒙菲莎大学毕业证成绩单如何办理
bakpo1
 
Hierarchical Digital Twin of a Naval Power System
Hierarchical Digital Twin of a Naval Power SystemHierarchical Digital Twin of a Naval Power System
Hierarchical Digital Twin of a Naval Power System
Kerry Sado
 
Top 10 Oil and Gas Projects in Saudi Arabia 2024.pdf
Top 10 Oil and Gas Projects in Saudi Arabia 2024.pdfTop 10 Oil and Gas Projects in Saudi Arabia 2024.pdf
Top 10 Oil and Gas Projects in Saudi Arabia 2024.pdf
Teleport Manpower Consultant
 
DESIGN A COTTON SEED SEPARATION MACHINE.docx
DESIGN A COTTON SEED SEPARATION MACHINE.docxDESIGN A COTTON SEED SEPARATION MACHINE.docx
DESIGN A COTTON SEED SEPARATION MACHINE.docx
FluxPrime1
 
MCQ Soil mechanics questions (Soil shear strength).pdf
MCQ Soil mechanics questions (Soil shear strength).pdfMCQ Soil mechanics questions (Soil shear strength).pdf
MCQ Soil mechanics questions (Soil shear strength).pdf
Osamah Alsalih
 
H.Seo, ICLR 2024, MLILAB, KAIST AI.pdf
H.Seo,  ICLR 2024, MLILAB,  KAIST AI.pdfH.Seo,  ICLR 2024, MLILAB,  KAIST AI.pdf
H.Seo, ICLR 2024, MLILAB, KAIST AI.pdf
MLILAB
 

Recently uploaded (20)

Design and Analysis of Algorithms-DP,Backtracking,Graphs,B&B
Design and Analysis of Algorithms-DP,Backtracking,Graphs,B&BDesign and Analysis of Algorithms-DP,Backtracking,Graphs,B&B
Design and Analysis of Algorithms-DP,Backtracking,Graphs,B&B
 
Pile Foundation by Venkatesh Taduvai (Sub Geotechnical Engineering II)-conver...
Pile Foundation by Venkatesh Taduvai (Sub Geotechnical Engineering II)-conver...Pile Foundation by Venkatesh Taduvai (Sub Geotechnical Engineering II)-conver...
Pile Foundation by Venkatesh Taduvai (Sub Geotechnical Engineering II)-conver...
 
space technology lecture notes on satellite
space technology lecture notes on satellitespace technology lecture notes on satellite
space technology lecture notes on satellite
 
Sachpazis:Terzaghi Bearing Capacity Estimation in simple terms with Calculati...
Sachpazis:Terzaghi Bearing Capacity Estimation in simple terms with Calculati...Sachpazis:Terzaghi Bearing Capacity Estimation in simple terms with Calculati...
Sachpazis:Terzaghi Bearing Capacity Estimation in simple terms with Calculati...
 
Final project report on grocery store management system..pdf
Final project report on grocery store management system..pdfFinal project report on grocery store management system..pdf
Final project report on grocery store management system..pdf
 
Architectural Portfolio Sean Lockwood
Architectural Portfolio Sean LockwoodArchitectural Portfolio Sean Lockwood
Architectural Portfolio Sean Lockwood
 
ethical hacking in wireless-hacking1.ppt
ethical hacking in wireless-hacking1.pptethical hacking in wireless-hacking1.ppt
ethical hacking in wireless-hacking1.ppt
 
Gen AI Study Jams _ For the GDSC Leads in India.pdf
Gen AI Study Jams _ For the GDSC Leads in India.pdfGen AI Study Jams _ For the GDSC Leads in India.pdf
Gen AI Study Jams _ For the GDSC Leads in India.pdf
 
AKS UNIVERSITY Satna Final Year Project By OM Hardaha.pdf
AKS UNIVERSITY Satna Final Year Project By OM Hardaha.pdfAKS UNIVERSITY Satna Final Year Project By OM Hardaha.pdf
AKS UNIVERSITY Satna Final Year Project By OM Hardaha.pdf
 
ASME IX(9) 2007 Full Version .pdf
ASME IX(9)  2007 Full Version       .pdfASME IX(9)  2007 Full Version       .pdf
ASME IX(9) 2007 Full Version .pdf
 
在线办理(ANU毕业证书)澳洲国立大学毕业证录取通知书一模一样
在线办理(ANU毕业证书)澳洲国立大学毕业证录取通知书一模一样在线办理(ANU毕业证书)澳洲国立大学毕业证录取通知书一模一样
在线办理(ANU毕业证书)澳洲国立大学毕业证录取通知书一模一样
 
block diagram and signal flow graph representation
block diagram and signal flow graph representationblock diagram and signal flow graph representation
block diagram and signal flow graph representation
 
road safety engineering r s e unit 3.pdf
road safety engineering  r s e unit 3.pdfroad safety engineering  r s e unit 3.pdf
road safety engineering r s e unit 3.pdf
 
一比一原版(IIT毕业证)伊利诺伊理工大学毕业证成绩单专业办理
一比一原版(IIT毕业证)伊利诺伊理工大学毕业证成绩单专业办理一比一原版(IIT毕业证)伊利诺伊理工大学毕业证成绩单专业办理
一比一原版(IIT毕业证)伊利诺伊理工大学毕业证成绩单专业办理
 
一比一原版(SFU毕业证)西蒙菲莎大学毕业证成绩单如何办理
一比一原版(SFU毕业证)西蒙菲莎大学毕业证成绩单如何办理一比一原版(SFU毕业证)西蒙菲莎大学毕业证成绩单如何办理
一比一原版(SFU毕业证)西蒙菲莎大学毕业证成绩单如何办理
 
Hierarchical Digital Twin of a Naval Power System
Hierarchical Digital Twin of a Naval Power SystemHierarchical Digital Twin of a Naval Power System
Hierarchical Digital Twin of a Naval Power System
 
Top 10 Oil and Gas Projects in Saudi Arabia 2024.pdf
Top 10 Oil and Gas Projects in Saudi Arabia 2024.pdfTop 10 Oil and Gas Projects in Saudi Arabia 2024.pdf
Top 10 Oil and Gas Projects in Saudi Arabia 2024.pdf
 
DESIGN A COTTON SEED SEPARATION MACHINE.docx
DESIGN A COTTON SEED SEPARATION MACHINE.docxDESIGN A COTTON SEED SEPARATION MACHINE.docx
DESIGN A COTTON SEED SEPARATION MACHINE.docx
 
MCQ Soil mechanics questions (Soil shear strength).pdf
MCQ Soil mechanics questions (Soil shear strength).pdfMCQ Soil mechanics questions (Soil shear strength).pdf
MCQ Soil mechanics questions (Soil shear strength).pdf
 
H.Seo, ICLR 2024, MLILAB, KAIST AI.pdf
H.Seo,  ICLR 2024, MLILAB,  KAIST AI.pdfH.Seo,  ICLR 2024, MLILAB,  KAIST AI.pdf
H.Seo, ICLR 2024, MLILAB, KAIST AI.pdf
 

Presentation on Flyover at Aziz Cross on GT Road Gujranwala

  • 1. 1
  • 3. February 2012 GOVERNMENT OF THE PUNJAB COMMUNICATION & WORKS DEPARTMENT Construction of Flyover on G.T Road at Aziz Cross Gujranwala
  • 4. February 2012 GOVERNMENT OF THE PUNJAB CONSTRUCTION OF FLYOVER ON G.T ROAD AT AZIZ CROSS GUJRANWALA Construction of Flyover on G.T Road at Aziz Cross Gujranwala
  • 5. SALIENT FEATURE  ADP (2016-17) Gr. Sr. No. 2775  Approved Cost Rs. 6672 Million  Construction Cost Rs. 3435 M  Land Acquisition (80 Kanal) Rs. 2920 M  Miscellaneous Rs. 317 M  Consultant M/s NESPAK  Contract M/s NLC  Client C & W Dept  Agreement Amount Rs.3115 M (9.35% below Est.cost)  Date of Commencement 30.01.2016  Date of Completion 29.11.2016
  • 6. INTRODUCTION  Aziz Cross project is a signal free interchange with partial clover leaf system and two additional directional ramps. Clover leaf interchange Partial Clover leaf interchange with two directional ramps instead of loops
  • 7. INTRODUCTION  There are normally 32 conflicts at any interchange which are completely resolved at Aziz Cross. 32 No. Traffic Conflicts Traffic Count 2014
  • 9. BASIC COMPONENTS OF FLYOVER Bridge cross-section can be divided into two portions. 1. Super Structure This portion receives the live load directly. For example, Box Girder 2. Sub Structure This Portion supports the entire structure and live loads.  Piles  Pile cap  Piers  Abutments Web Web Pier Canopy Pier Shaft Pile Cap Pile Pile Pile Super Structure Sub Structure
  • 10. CONCRETE PILES A pile is a vertical structural element of a deep foundation which transfers super structure loads to the earth farther down from the surface to a subsurface layer.
  • 11.
  • 12.
  • 13.
  • 14. PILE CAP PILE CAP Pile cap is a thick reinforced concrete mat that rests on concrete piles that have been casted into ground. concrete pile cap distributes the load of the superstructure (from piers and abutments into the piles. Pile Cap Piles Pier
  • 15.
  • 16.
  • 17.
  • 18.
  • 19.
  • 20.
  • 21. PILE CAP AND PIER PIER A pier is a reinforced, raised structure in form of pillars typically supported by well-spaced pile caps. It transfers the loads from deck to pile caps. For this project, special shape of pier is adopted. It as two components 1. Pier Shaft as column 2. Pier Canopy as transom Pier Canopy Pier Shaft Box Girder
  • 22.
  • 23.
  • 24.
  • 25.
  • 26. Abutment refers to the substructure at the ends of a bridge span. It supports;  Super Structure load  Live Load  Lateral Earth Pressure ABUTMENTS Abutment Pile Cap Piles
  • 27.
  • 28.
  • 29.
  • 30. REINFORCED EARTH WORK  Reinforced earth wall is earth retaining structure and provided at approaches (from road level to bridge level).  The key components of a Reinforced Earth wall are geo-strips, granular backfill and precast concrete facing panels.  The frictional bond between the backfill supports the lateral earth pressure and stresses induced due to traffic load.
  • 31. ABUTMENT 01 ABUTMENT 06 LOOP 2 ABUTMENT 07
  • 33. PRE-STRESSED BOX GIRDERS Bottom View of Box Girder Piers  An optimal and most efficient design of beam is box girder. A box girder consists of enclosed tube with multiple walls.  The advantage of a box girder is that it better resists torsion. Having multiple vertical webs, it can also carry more load than an I-shape girder of equal height. Pre-stressing Mechanism
  • 34.
  • 35.
  • 36.
  • 37.
  • 38.
  • 39.
  • 40.
  • 41. SCOPE OF WORK 12/14/2016 Flyover 1 Length 301.5 Piles 80 P. Cap 15 Piers 15 Abt. 2 Spans 10Flyover 2 Length 301.5 Piles 66 P. Cap 11 Piers 12 Abt. 2 Spans 10 Flyover 5 Length 80.05 Piles 38 P. Cap 4 Piers 6 Abt. 2 Spans 3Flyover 3 Length 417.3 Piles 64 P. Cap 15 Piers 13 Abt. 2 Spans 14 Flyover 4 Length 564.41 Piles 84 P. Cap 20 Piers 18 Abt. 2 Spans 18 RWP LHR GRW SKT Pile= 332 Ramp 3 (L=361.14m) Ramp 6(L=369.39 m) Bridge approaches (841m) Pile caps=65 Ramp 3A(L=573.11m) Ramp 7(L=369.39 m) Abutment= 10 Ramp 4( L=379.35m) Loop 1(270.18m) Bridge Lengths(1664m) Piers=60 Ramp 5 (L=846.94m) Loop 2(L=195.23) Road Length (4660m)
  • 42. FLYOVER S– 1, 2, 3 & 4  Piles 100 % Completed (294 out of 294)  Pile Caps 100 % Completed (62 out of 62)  Piers 100 % Completed (62 out of 62)  Abutment 100 % Completed (8 out of 8)  Box Girders 20% in progress (4 out of 17)  Reinforce Earth Wall 50 % Completed (0.6 km out of 1.12 km)  At Grade Roads 60% up to WBM (3 Km out of 5 Km) RAILWAY BRIDGE  Piles 100% Completed (38 out of 38)  Pile Caps 100% Completed (4 out of 4)  Piers 100% Completed (2 out of 2)  Transoms 50% Completed (1 out of 2)  Abutments 50% Completed (1 out of 2)  Pre-cast Girders 100% Completed (21 out of 21) PHYSICAL PROGRESS
  • 43. Year Release Expr. %age Remarks 2014-15 2500 2500 100% Payment made for land acquisition. 2015-16 1555 1555 100% Rs. 400 M land acquisition. Rs. 215 M shifting of services. Rs. 940 M paid to NLC. 2016-17 1000 510 51% Rs. 510 M paid to NLC. FINANCIAL PROGRESS