A PROJECT REPORT ON FLYOVER CONSTRUCTION
AT
BIHAR RAJYA POOL NIRMAN NIGAM LTD.GOVT OF
BIHAR
SUBMITTED BY:- SUBMITTED TO;-
AKHILASH KUMAR DR.SHEETAL AGARWAL
CIVIL ENGG.(VIIth sem.) ( HOD OF CIVIL ENGG.)
ROLL NO:-12EAYCE005
DEPARTMENT OF CIVIL ENGINEERING
ARYA COLLEGE OF ENGINEERING &RESEARCH CENTRE
SP-40, RIICO INDUSTRIAL AREA, KUKAS, JAIPUR, RAJASTHAN
RAJASTHAN TECHNICAL UNIVERSITY, KOTA
Company : BIHAR RAJYA POOL NIRMAN NIGAM LTD.
Project Name : FLYOVER CONSTRUCTION
Location : MITHAPUR FLYOVER TO CHIRAIYATAND
&
CHIRAIYATAND TO GANDHI MAIDAN
Estimated cost : 100 Cr.
PROJECT DETAILS
PILE
As we know PILE is a column (of reinforced
concrete) which transfers the load of
superstructure directly to the soil strata.
The piling is necessary to make the foundation as
well as soil strata reliable to withstand the load
conditions more safely.
Before installation of END BEARING PILE,
settlement under Pile Load Test was observed in
between 6-12mm which shows the green signal to
install.
NOTE- In pile foundation, 10% cement more is
required.
PILE
PILE –CAP
A thick concrete mat that rests on piles
collectively to provide a suitable stable
foundation is Pile Cap.
It is 1.8m thick and 5.2m wide.
PILE –CAP
PIER
A vertical supporting structure over pile cap is
Pier Shaft.
The thickness is provided according to
drawings.
NOTE-
Shaft dimension is 1500mm x1500mm at
Exhibition road site.
PIER
ABUTMENT & A.CAP
Abutment are typically used where column
lengths on multi-column piers will require
larger column sizes due to slenderness.
Abutment are also an option where stream
flow could result in debris build-up between
columns of a multicolumn.
ABUTMENT
PEDESTAL
Pedestal is an independent support to bearings,
over Pier/Abutment Caps.
NOTE-
• Pedestal dimension is 950mm x850mm
x250mm.
• The number of Pedestal over a Pier Cap is 4.
• The number of Pedestal over a Abutment
Cap is Wall. 2 with a Dirt
PEDESTAL
BEARING
The bearings used in the construction are Pot
Bearings. Pot bearing is named so because bearing
is confined in a steel pot.
Although it has some specific characteristics
which tend an engineer to use it. These are as-
• Negligible vertical deflection as only 0.06”.
• Uniform loading acceptability.
• Minimal load eccentricity as up to 3% of the
disc diameter.
• Having least resistance in the range of 0.01 to
0.022 radians.
• Lower peak pressure on bearing seats due to
hydraulic design principle, characteristic load
distribution curve is flatter.
• High horizontal load capacity.
BEARING
SEGMENT
A flyover segment is the roadway surface of the
flyover.
These segments have shuttering formwork made
of high strength steel which are cast in casting
yard.
SHUTTERING
FORMWORK OF
SEGMENTS
These precast units are installed through a Bridge
Launcher Machine.
SEGMENTS INSTALLED
BY LAUNCHER
MACHINE
GLUING BETWEEN SEGMENTS
After gluing, the segments are connected through
strand bars (15.2mm dia.). The process is termed
technically as “Threading”
STRAND BARS
NOTE-
• There are 10 holes on each face of the segment.
• Each hole comprises of 19 bars of 15.2mm dia.
• The overall threading of a span is parabolic due
to variation of hole’s position of segments lying
over the span.
• After this post tensioning is done to make it a
pre stress unit using tendons.
CRASH BARRIER
The barrier which checks errant vehicles from
jumping outside from the flyover is called as Crash
Barrier/Traffic Barrier.
The width of Crash Barrier is 500mm.
FACIA PANEL
The facia panel is the smallest unit of reinforced
earth wall.
It is a precast unit containing bricks and concrete
with covering.
REINFORCED EARTH WALL
The Reinforced Earth wall is made up of facia
panels. These panels are arranged in the same way
as of brick’s bonds.
This Reinforced Earth Wall provides 25% more
safety to the superstructure.
GEOGRID
Geogrid is a geopolythene material, used to provide
the levelling of sand stratum at its level. There is a
Hook embeded in panel connecting its two front
wall’s hooks with Geogrid by a connecting rod in
each hook.
SAND COMPACTION
• Sand compaction is an important work in flyover
a ramp.
• The sand is get self compacted by sprinkling
water over it.
• The compactor machine compacts with 8kN/m2
at the middle.
• The sides are compacted with 1Kn/m2 by a baby
roller or plate vibrator.
SAND COMPCTION
DIRT WALL /BALLAST WALL
The dirt wall is a wall which stands on the
Abutment cap end to end apart from pedestals.
This wall bears the load of ramp next to RE Wall
on the abutment.
NOTE- The end sides of the dirt wall should be
matched properly with the ends of R E Wall and
thus in the same way till crash barrier.
Thank you!
ANY QUERIES ?
Courtesy : Akhilesh Kumar

Flyover construction

  • 1.
    A PROJECT REPORTON FLYOVER CONSTRUCTION AT BIHAR RAJYA POOL NIRMAN NIGAM LTD.GOVT OF BIHAR SUBMITTED BY:- SUBMITTED TO;- AKHILASH KUMAR DR.SHEETAL AGARWAL CIVIL ENGG.(VIIth sem.) ( HOD OF CIVIL ENGG.) ROLL NO:-12EAYCE005 DEPARTMENT OF CIVIL ENGINEERING ARYA COLLEGE OF ENGINEERING &RESEARCH CENTRE SP-40, RIICO INDUSTRIAL AREA, KUKAS, JAIPUR, RAJASTHAN RAJASTHAN TECHNICAL UNIVERSITY, KOTA
  • 2.
    Company : BIHARRAJYA POOL NIRMAN NIGAM LTD. Project Name : FLYOVER CONSTRUCTION Location : MITHAPUR FLYOVER TO CHIRAIYATAND & CHIRAIYATAND TO GANDHI MAIDAN Estimated cost : 100 Cr. PROJECT DETAILS
  • 3.
    PILE As we knowPILE is a column (of reinforced concrete) which transfers the load of superstructure directly to the soil strata. The piling is necessary to make the foundation as well as soil strata reliable to withstand the load conditions more safely. Before installation of END BEARING PILE, settlement under Pile Load Test was observed in between 6-12mm which shows the green signal to install. NOTE- In pile foundation, 10% cement more is required.
  • 4.
  • 5.
    PILE –CAP A thickconcrete mat that rests on piles collectively to provide a suitable stable foundation is Pile Cap. It is 1.8m thick and 5.2m wide.
  • 6.
  • 7.
    PIER A vertical supportingstructure over pile cap is Pier Shaft. The thickness is provided according to drawings. NOTE- Shaft dimension is 1500mm x1500mm at Exhibition road site.
  • 8.
  • 9.
    ABUTMENT & A.CAP Abutmentare typically used where column lengths on multi-column piers will require larger column sizes due to slenderness. Abutment are also an option where stream flow could result in debris build-up between columns of a multicolumn.
  • 10.
  • 11.
    PEDESTAL Pedestal is anindependent support to bearings, over Pier/Abutment Caps. NOTE- • Pedestal dimension is 950mm x850mm x250mm. • The number of Pedestal over a Pier Cap is 4. • The number of Pedestal over a Abutment Cap is Wall. 2 with a Dirt
  • 12.
  • 13.
    BEARING The bearings usedin the construction are Pot Bearings. Pot bearing is named so because bearing is confined in a steel pot. Although it has some specific characteristics which tend an engineer to use it. These are as-
  • 14.
    • Negligible verticaldeflection as only 0.06”. • Uniform loading acceptability. • Minimal load eccentricity as up to 3% of the disc diameter. • Having least resistance in the range of 0.01 to 0.022 radians. • Lower peak pressure on bearing seats due to hydraulic design principle, characteristic load distribution curve is flatter. • High horizontal load capacity.
  • 15.
  • 16.
    SEGMENT A flyover segmentis the roadway surface of the flyover.
  • 17.
    These segments haveshuttering formwork made of high strength steel which are cast in casting yard. SHUTTERING FORMWORK OF SEGMENTS
  • 18.
    These precast unitsare installed through a Bridge Launcher Machine. SEGMENTS INSTALLED BY LAUNCHER MACHINE
  • 19.
    GLUING BETWEEN SEGMENTS Aftergluing, the segments are connected through strand bars (15.2mm dia.). The process is termed technically as “Threading” STRAND BARS
  • 20.
    NOTE- • There are10 holes on each face of the segment. • Each hole comprises of 19 bars of 15.2mm dia. • The overall threading of a span is parabolic due to variation of hole’s position of segments lying over the span. • After this post tensioning is done to make it a pre stress unit using tendons.
  • 21.
    CRASH BARRIER The barrierwhich checks errant vehicles from jumping outside from the flyover is called as Crash Barrier/Traffic Barrier. The width of Crash Barrier is 500mm.
  • 22.
    FACIA PANEL The faciapanel is the smallest unit of reinforced earth wall. It is a precast unit containing bricks and concrete with covering.
  • 23.
    REINFORCED EARTH WALL TheReinforced Earth wall is made up of facia panels. These panels are arranged in the same way as of brick’s bonds. This Reinforced Earth Wall provides 25% more safety to the superstructure.
  • 24.
    GEOGRID Geogrid is ageopolythene material, used to provide the levelling of sand stratum at its level. There is a Hook embeded in panel connecting its two front wall’s hooks with Geogrid by a connecting rod in each hook.
  • 25.
    SAND COMPACTION • Sandcompaction is an important work in flyover a ramp. • The sand is get self compacted by sprinkling water over it. • The compactor machine compacts with 8kN/m2 at the middle. • The sides are compacted with 1Kn/m2 by a baby roller or plate vibrator.
  • 26.
  • 27.
    DIRT WALL /BALLASTWALL The dirt wall is a wall which stands on the Abutment cap end to end apart from pedestals. This wall bears the load of ramp next to RE Wall on the abutment. NOTE- The end sides of the dirt wall should be matched properly with the ends of R E Wall and thus in the same way till crash barrier.
  • 28.
    Thank you! ANY QUERIES? Courtesy : Akhilesh Kumar