Summer training presentation from BRPNNL by Randhir Kumar(1503050)
This document summarizes the construction of a flyover connecting three roads in Patna, Bihar, India. It describes the project details including the total length of the elevated structure and flyover, number of lanes and arms. It then outlines the sequence of construction including piling, substructure work, and launching of segments. It provides photos from the construction site showing pile foundations, pile caps, pier reinforcement, and curing of piers. It also discusses material and quality control tests including concrete strength and pile load tests. Safety measures on site such as barricading and safety equipment for workers are highlighted.
Overview of the project submission by Randhir Kumar, guided by Er. Rakesh Kumar. Training duration 25-05-2018 to 05-07-2018 at Bihar Rajya Pul Nirman Nigam.
List of topics included in the project: title, details, construction sequence, foundation, materials, safety.
Project title involves construction of a flyover connecting two points, with Bihar Rajya Pul Nigman Nigam Ltd. as the client and Rachna Construction Co. as the contractor.
Definition of a flyover as a bridge structure that allows uninterrupted cross traffic, emphasizing its functionality.
Introduction to the different structural and functional components that make up a flyover.
Key specifications: Elevated structure length 1262.653 m, Total flyover length 1748.763 m, spans and lane distribution.
Prototypical layout plan of the project illustrated via AutoCAD drawings.
Detailed sequence of construction, from surveying to the launch of segments and final road construction.
Description of the steps involved in bored in-situ piling for the foundation of the flyover.
Visual representation of pile foundation activities currently executed on-site.
Visual representation of pile cap work being undertaken at the construction site.
Overview of the types of substructure, quantities, and material grades specified for pier construction.
Current status of pier reinforcement activities on-site showcasing structural integrity measures.
Specifications of concrete grades used in project components like Pile, Pier, and Pile Cap.
Guidelines on lap lengths for reinforcements in different structural elements.
Quality control practices for concrete mixing, workability, and reinforcement compliance.
Methods and techniques used for curing piers to ensure concrete quality.
Various testing methods for concrete quality and pile load capacity as per industry standards.
Image depicting the process and setups involved in pile load testing.
Safety measures prioritized on site, emphasizing worker protection and job site safety equipment.
Illustration of safety features including barricading and instruction boards at the construction site.
Citations of relevant IS codes and guidelines used as standards for construction practices.
Final slide thanking audience and closing the presentation.
Summer training presentation from BRPNNL by Randhir Kumar(1503050)
1.
Submitted by
RANDHIR KUMAR(1503050)
Under the guidance of
Er. Rakesh Kumar
(Project engineer BRPNNL Patna)
Training undertaken at
Bihar Rajya Pul Nirman Nigam Limited Patna
25-05-2018 to 05-07-2018
DEPARTMENT OF CIVIL ENGINEERING
NATIONAL INSTITUTE OF TECHNOLOGY PATNA
2.
Content
Project title
Flyover and its components
Project details & layout
Sequence of construction
Pile foundation
Substructure construction
Material and quality control
Tests on site
Safety
References
3.
Project Title
“Construction offlyover Connecting Mithapur flyover to
Bhikhari Thakur flyover via R-Block junction with
elevated rotary”.
Client-
Bihar Rajya Pul Nirman Nigam Ltd. Patna
Contractor-
Rachna Construction Co. Bharuch, Gujrat
4.
Flyover
“A bridge overanother road for allowing cross traffic
without interruption with its approaches on both sides is
commonly called as Flyover”
Project details
ELEVAYEDSTRUCTURE LENGTH : 1262.653 m
Total Flyover Length : 1748.763 m
Span : 54 Spans
No. Of Lanes : 4 (2x7.5 m)
ARM NOMENCLATURE DETAILS AS PER SITE
LOCATION :
ARM-01 : From GPO to R-block junction (628.62m)
ARM-02 : From Bhikhari Thakur Bridge to R-block
junction(464.106 m)
ARM-03 : From Miller High School to R-block (490.498m)
Rotary Junction : Over R- Block Junction (124.109 m)
Merging Point : Two Lane merging in Bhikhari Thakur
Bridge(41.43m)
Sequence of construction
Surveying
Analysis and design of the structure
Piling and Pile cap Construction
Construction of Pier shaft and Pier cap
Construction of Pedestal
Launching and gluing of segments
Construction of road over bridge
9.
Construction of Pilefoundation
Steps involved in bored in-situ piling
Setting out exact position of pile on the ground using
surveying equipments.
Drilling with the help of boring auger.
Provide temporary metal casing with depth 3-6m.
Provide reinforcement cage.
With the help of tremie pipe, concreting is done.
Before concrete gets harden, casing is removed.
Removal of top 1m of pile with the help of jack
hammer.
SUB STRUCTURE WORKON SITE
Types of sub structure : Single Solid Pier
Shape of sub structure : Rectangular and Circular
Grade of concrete : M-50
Total Nos. Of Pier : 74
a. In ARM -01 : 17 (Rectangular)
b. In ARM -02 : 16 (Rectangular)
c. In ARM -03 : 09 (Rectangular)
d. In Rotary : 14 (Rectangular)
e. In Merging Portion : 18 (Circular)
Total Nos. Of Pier Cap & Portal Cap : 58
In ARM -01 : 17
In ARM -02 : 14
In ARM -03 : 10
In Rotary : 08
In Merging Portion : 09
MATERIAL AND QUALITYCONTROL
Concrete material
Pile M 35
PCC M 15
Pile cape M 40
Pier shaft M 50
Clear cover to the reinforcement shall be
Pile cape - 75mm
Pile - 75mm
Pier - 50/75mm
STEEL- TMT bar (Fe 500D)
15.
MATERIAL AND QUALITYCONTROL
Lap length
Pile = 54d
Pile cape = 51d
( for bottom and side face reinforcement)
=78d (for top face reinforcement)
Pier = 44d
d- Diameter of smaller bar being lapped
16.
MATERIAL AND QUALITYCONTROL
Quality of Concrete
workability and strength
compaction of concrete
curing
Steel
Reinforcement as per drawing and BBS, diameter and
length of bar, spacing of bar, lap
length, binding of bar, development length, coupler,
clear cover.
Tests
Workability -Slump cone test
Compressive strength- Compressive Strength of concrete is
defined as the Characteristic strength of 150mm size concrete cubes
tested at 28 days. Sample is collected before casting and sent to lab for
testing. Sample is kept in same environment and same curing at site for
28 days then they are checked at lab.
Pile load test- Routine test is done as per IS 2911 (part 4):1985. It
is carried out on a working pile with a view to check whether pile is
capable of taking the working load assigned to it.
Maximum allowable settlement is 12 mm.
Safety
“Safety first” Everyconstruction work is done with this
line keeping in mind. Safety of
people should be the first priority of any construction
work.
Helmet, jacket and shoes for all employs and worker.
Barricading, Instruction board, light, reflector, safety
cone, flag.
safety belt is used if any worker is at height more than
2m from ground.
References
IS 456:2000,Code of practice for plain and reinforced concrete,
Bureau of Indian Standards, New Delhi.
IS 2911 (Part 1/Sec 2):2010, Design and construction of pile
foundations-code of practice (bored cast in-situ concrete piles),
Bureau of Indian Standards, New Delhi.
IS 2911 (part 4):1985, Codes of practice for design and
construction of pile foundations – load test on piles, Bureau of
Indian Standards, New Delhi.
IS 14893:2001, Non-destructive integrity testing of piles (NDT) –
Guidelines, Bureau of Indian Standards, New Delhi.
IS 3558:1983, Code of practice for use of immersion vibrators for
consolidating concrete, Bureau of Indian Standards, New Delhi.
IRC SP 90:2010, Manual for grade separators & elevated
structures, Indian Roads Congress, New Delhi.
Google map, www.gmap.com