SlideShare a Scribd company logo
1 of 33
Download to read offline
A PROJECT REPORT ON
CONSTRUCTION OF FLYOVER
For
Bihar Rajya Pul Nirman Nigam Limited.
Guided by :-
Mr. Arvind Prasad Gupta
( Project Engineer )
Project Name
Lohia Path Chakra
Submitted by:-
Prabhat Kumar Prashant Shaurabh
Civil Engineering VIIth Sem Civil Engineering VIIth Sem
Roll No:-14102024 Roll No:-14102025
DEPARTMENT OF CIVIL ENGINEERING
INSTITUTE OF TECHNOLOGY,GURU GHASIDAS VISHWAVIDYALAYA
BILASPUR, C.G.
REASON BEHIND GOING FOR A FLYOVER
As the traffic on the road goes on increasing and we don’t have any space left in both the dimensions, then
the only option left will be to go to the third dimension and that is done through Flyover construction.
There is so much traffic in the city so it takes around 45 to 60 minutes to go from saguna more to patna high
court even they are 12 kms apart,and of being the lifeline road of the city it is important to control the traffic
on this road.So the decision has been taken to construct a flyover so to reduce the travelling time to 15
minutes from 45 minutes.
Contents
Aknowledgement
Abstract
SECTION -A
Different stages of project
 Topographic survey and analysis
 Traffic survey and analysis
 Geotechnical aspects and analysis
 Planning and design
SECTION –B
Features of project
 Salient features
 Physical features
SECTION –C
Components involved
 Foundation
 Substructure
 Superstructure
SECTION –D
Machines and equipments used
 Air compressor
 Backhoe loader
 Crawler crane
 Excavator
 Genset
 Hydraullic rig machine
 Hydraullic crane
 Mini roller
 Pneumatic concrete breaker
 Transit mixer
 Tanks
 Augur
 Casing
 Treamie pipe
 Funnel
 Goliath Gantry Crane
SECTION –E
Construction Procedure & dimensions
 Pile
 Pile cap
 Pier
 Pier cap
 Girder
 Deck
 Bearing
 Crash barrier
 Installation of light
SECTION –F
Quality Control
 Test on aggregates
 Crushing test
 Impact test
 Shape test
 Bitumen adhesion test
 Test on Cement
 Date of packing
 Colour
 Rubbing
 Hand Insertion
 Float test
 Shape test
 Strength test
 Performance test
 Load test
 Capacity test
 Stress test
 Cube strength
 Slump cone test
SECTION –G
Conclusion
Acknowledgement
A vocational training is a golden opportunity for learning and self development.I consider myself very lucky
and honored to have so many wonderful people lead me through in completion of this project.
First of all I would like to thank all the families and friends that participate on my life and get me in this
intensityand individuals who support and share idea and also helping me to be like this.
I am very thankful to BIHAR RAJYA PUL NIRMAN NIGAM LIMITED(BRPNNL) and its managing director
RANJAN KUMAR for having given me the opportunity to undertake my one month summer training in their
working area.It was a very good learning experience for me to have worked at this area.I would like to
convey my heartiest thanks to Chief Engineer ARVIND KUMAR and all the Faculty members at Department
of Civil Engineering at Guru Ghasidas Vishwavidyalaya,who made it all possible.
I would also thank SUJEET SIR for his endless support at site and in his office by consulting me how to do
things at site,all teachers of Civil Engineering who brought me to my present performance and shape me
like this during the last Three successive years, special thank to my prof NIKHIL KUMAR VERMA for guiding
me to do training at BRPNNL.
Before I finish I would like to give my deepest thanks to all workers from thr contractor, S P Singla
Construction Private Limited and the consultant side starting from Engineers to daily labours.Also for those
who do not listed in the above but support me in different areas I would like thank all.
ABOUT BIHAR RAJYA PUL NIRMAAN NIGAM LTD.
Constitution and objectives
Bihar Rajya Pul Nirman Nigam (BRPNN) was formed on 11th June, 1975 under Indian Company Act,
1956 as a Govt. Company.
Its main objectives are -
 Construction of Bridges/Roads
 Maintenance of Bridges
 Toll Collection
The Nigam is registered as a Public Company under Indian Company Act, 1956 and it is a Govt.
Company as total share capital of Rs.500 Lakhs is pledged in the name of Governor of Bihar. The
Nigam is governed by Managing Director on behalf of Board of Directors nominated by the Govt.
under guidelines set by Memorandum of Association and Articles of Association along with work
rules mentioned therein.
Concept of Working
Bridges are constructed departmentally by the Nigam on the basis of current Schedule of Rates
(SoR) sanctioned for Works Department. As the work is done departmentally, cost incurred is less as
compared to work done by contractors.
ABOUT S P Singla Construction Pvt Ltd.
S. P. Singla Constructions Pvt. Ltd. collaboratively facilitate, engineer, and disseminate
construction services fostering the world’s ethical, social, economic, and intellectual growth,
using progressive and diverse techniques on the cutting edge of the construction industry.
Every aspect of how we work has been built to fulfil our mission to make lasting contributions to
our people, our communities, and the construction industry. From company’s commitment for its
valuable employee’s teamwork to a continued commitment to hard work and performing with
excellence, our values are obvious in every office and on every project site.
S. P. Singla Constructions Pvt. Ltd. collaboratively facilitate the construction services fostering
the world’s geographical growth, using progressive and diverse techniques on the cutting edge of
the construction industry and provides healthy professional environment which is unanimously
accepted by every associated employee of S. P. Singla Constructions Pvt. Ltd. we filter excellent
from best.
VISION
To build a progressive and creative organisation that constantly strives to improve its business &
construction practices and win clients’ trust by exceeding their expectations.
MISSION
To be pioneers in the field of Bridge construction by application of innovative solutions and
knowledge to work.
S. P. Singla Constructions Pvt. Ltd. is a company pioneering spirit. That pioneering spirit drives us to
constantly find new and smarter ways to build. Our construction services have been fine-tuned over
a century of building and during that time have embraced advances in technology that help us build
better and safer infrastructure and for a lower cost. Our experienced team applies today’s
technology to proven building principles.
WE ARE SPECIALISTS IN CONSTRUCTION OF:
 R.C.C. bridges
 Pre-stressed concrete bridges
 Cantilever bridges for construction of long span bridges
 Well foundations
 Pile foundations
 Flyovers
 Road / Rail over bridges
 Steel bridges including fabrication & launching
 Launch of pre-cast & pre-stressed concrete girder
 Roadwork with asphaltic concrete and mastic asphalt surfaces
 Segmental constructions
At S. P. Singla Constructions Pvt. Ltd., we are always striving to bring on board the latest of
technologies and equipment to meet the demands of today’s clients. While listed above are few of
the technologies we are presently working with, in near future we will be adding more to our list.
The technologies are updated time-to-time to deliver today what others hope to do tomorrow.
Abstract
The training report in broad spectrum contains six sections in which I try to explain my one month
learning experience in the running project, construction of LOHIA Path CHAKRA as a part of Bailey
Road Flyover. The content of all section is broadly explained and it is made from the practical basis
of the site work of weekly basis.
In section A I give all the details of different stages of the project. In this section I put all the details
of the work done in the same manner at the site for the completion of the project.
In section B I try to explain the features of the project like the project details, the cost involved, the
length of the flyover, no of piles involved, cost involved .etc.
In section C I try to explain the components involved in the Flyover construction. It has been
categorized into three parts the foundation part, the sub structure and the superstructure part.
In section D I try to explain all the machines and equipments used in the whole construction with
their respective pictures.
The section E is the most important chapter in which explains all the dimensions and the
construction procedure of the components involved with some practical images whatever I clicked
during the whole training period.
In the section F I try to explain all the related tests on the materials involved in the construction the
tests on the aggregates, cement, soil and, model testing of pile on the basis of which we decide the
size of different part of the bridge, which type of material is suitable for the construction process,
how we can minimize the cost on that particular project and also the load carrying capacity of pile.
After reading all the sections one can easily understand basics of flyover construction procedure,
dimension and minimization of the cost of the project.
SECTION –A
DIFFERENT STAGES OF PROJECT
1.SURVEY AND ANALYSIS
Each and every civil engineering project starts with survey. There are various stages of survey. The
first step of surveying is reconnaissance Then after that various maps of the site is studied. Only
after this detail survey of proposed project site is done.
Here in this project a detail survey of the site is done by the Total Station and various other
instruments of surveying and layout is drawn in Autocad. With help of this total space available for
construction, alignment of flyover and no. lanes of flyover & total carriageway.
It should be noted that surveying not only plays an important role in the design of the project but
also in the execution.
2. TRAFFIC SURVEY AND ANALYSIS
The main purposes of traffic survey are: traffic monitoring, traffic control and management, traffic
enforcement, traffic forecasting, model calibration and validating etc. The purposes of carrying out
traffic volume count are designing, improving traffic system, planning, management etc.
Traffic forecast predicts the future traffic volume levels on the project road. In this project, the
flyover is designed to meet the requirements of traffic for next 25 years.
From traffic survey it was decided to design the flyover for live load for a single lane of class 70R
or 2 lanes of class -A.
.3. GEOTECHNICAL ASPECTS AND ANALYSIS
It is very necessary to carry out thorough soil investigation of the site as the whole load of the
structure is ultimately taken by soil through foundation. Feasibility, design and safety of the
structure all depends upon load bearing capacity of the soil strata at the site.
For this purpose bore holes were drilled in the ground to get information about the sub-soil
strata. Boring was done at an interval of 40m along the alignment and depth of exploration was
39m. Samples were taken from the bore hole and tested in the laboratory and engineering
properties of the soil was investigated. Also some field test was carried out.
From these tests & investigations, it was concluded that the Soil Bearing Capacity (SBC) of the site
was 230 MPa.
4. PLANNING & DESIGN
All the results were taken into account and with help of Various IS Codes detailed planning and
design were prepared according to which execution is going through and the flyover is under
construction. From all available data a pile was designed and Initial Load Test for pile was done to
confirm the load carrying capacity of the single pile.
TECHNICAL DATAS :-
SAGUNA MORE TO PATNA HIGH COURT
Diameter of Pile 1200 mm
Verticle load capacity of pile 250T
Horizontal load capacity of pile 20T
Depth of pile cap 1800 mm
SECTION – B
Salient Features:-
Project Cost : 391.47cr
Agency : BRPNNL
Date of commencement : 9 Dec 2015
Target date of completion : 18 Dec 2017
Physical Features:-
Total length of Project 3.2 kM
Length of elevated part 1.7 kM
No.of piers 16
Type of superstructure PSC GIRDERS
Slope across bridge length 1 in 30
No.of underpasses 4
Elevated Bridges 1
Average traffick movement 2000 Vehicles/hour.
SECTION :-
COMPONENTS INVOLVED
FOUNDATION
Piles and the Pile cap comes under the Foundation part.
Piles:- The function of pile is to transfer the load to the soil.
Three types of pile are there:-
1. End bearing pile
2. Friction pile
3. End bearing and friction pile
In this project we used End bearing Pile,some parts of the load transferred by the pile by end of pile
and remaining load is by the friction between pile and the surface of soil around the pile.
Arrow in the above image denotes how load transferred to the ground
Pile cap reinforcement
Piles usually exists as a group which are all integrated by means of a pile cap as shown in figure.
Piles carrying very heavy point loads tend to produce high tensile stress at the pile cap.
Reinforcement is thus designed to provide: -
1.Resistance to tensile bending forces in the bottom of the cap.
2.Resistance to the vertical shear.
SUBSTRUCTURE
Pier and Pier-cap
Support of superstructure, transfer dead and live load to pile.It also carries its own considerable
weight.
Pier
It is a raised structure typically supported by well-spaced piles or the pile cap. It can be made by wooden
concrete, steel, mixed, but in this project we use concrete pier with well-maintained iron rod.
Pier cap
The upper or bearing part of the pier, usually made of concrete or hard stone; designed to distribute
concentrated loads evenly over the area of pier.The width of pier cap depends upon the width of
carriageway, its size depends upon the live load and dead load bridge capacity.
SUPERSTRUCTURE
Wearing surface
consists of the deck structure itself, which support the direct loads due to traffic and all the other
permanent and variable leads to which the structure is subjected. Also known as carriageway.
Width of carriageway depends upon number of lane of flyover. For intermediate carriage -5.5 m and
for two lane-7.5 m.
Bearing
Bridge bearings are used to transfer forces from the superstructure to substructure, allowing the
following types of movements of the superstructure :-
Translational movements; are displacements in vertical and horizontal directions due to in-place or out-of-
place forces like wind and self-weight.
Rotational movements; cause due to moments. Until the middle of this century, the bearings used
considered of following types: - pin, roller, rocker, metal sliding etc.
Girder
It is support of carriageway between two piers, it is of many types like box shape, Z shape,I-shape and many
other forms.
In this flyover, I-shape pre-stressed beam used .
Crash barrier
A strong fence at the side of carriageway, intended to reduce the risk of serious accidents.
It is of various types ex: - wooden, tin, steel, cable, wire, concrete.
Concrete barrier is strongest one and cheap as well.
Now these days in flyover concrete crash barrier is preferred generally.
SECTION -D
Machines and equipments used
Air Compressor Backhoe Loader
Crawler crane Excavator
Genset Hydraullic Rig Machine
Hydraullic Crane Mini Roller
Pneumatic concrete breaker Transit Mixer
Tanks Bullet Augur
Bucket Augur Casing
Treamie Pipe Funnel
Goliath Gantry Crane
SECTION -E
CONSTRUCTION PROCEDURES AND DIMENSIONS
PILE :-
In this particular project, we use rotary hammer machine for drilling purpose.
1.Pile boring procedure
Set up the Location of Bored Pile.
We use Total Station instrument to survey each pile point.
The dia of the pile is 1.2m and the depth is 32m.
2. Drilling Using MAIT machine
3. Insert Casing
After Casing is inserted the bore is filled
W with the bentonite clay mixed with water to
Prevent the soil from the sides to fall down to
Bottom.
4. Insertion of Steel Cage
5. Insertion of Tremie Pipe & Pouring of Concrete
Number of piles: number of piles required for a particular pier is depends upon the spam, length
number of lane of carriage way, capacity of a particular pile and type of bridge it is.
Capacity of each pile in this project is 230 tones
PILE CAP
A pile cap is thick concrete mat that rests on piles to provide a suitable foundation.
It forms the part of the foundation of structure.
This pile cap distributes the load to piles uniformly.
Pile capping Procedure
1. Shuttering and Reinforcement
2. Concreting
3. Curing
Dimension of pile cap varies as number of piles and type of soil at that particular
place, Carry a height in the rage of 10-15 feet. In this project the height is taken as
10feet.
DESIGN AND SPECIFICATIONS OF FOUNDATION
 Pile foundation with pile cap
 No. of piles – 4 for Abutments & 9 for piers
 M35 Grade Concrete is used for casting piles & pile cap
 Depth of pile 32000 mm & Dia of pile 1200 mm
 Depth of pile cap is 3000 mm
 Bars used – Fe 500 Tor Steel Bar of Dia 28 mm & Dia 32 mm
 Sand filling is done around pier caps to control & minimize expansion & contraction of
structure and sand is economical also.
PIER :-
A part of substructure which transfers the load to pile followed by pile cap, its construction is a
normal process of filling concrete mixture with steel rod arranged in particular manner as shown in
picture .
The dimensions and construction details of the cast-in-situ piers are given below.
Every single pier consists of Reinforcement bars of different dia (max upto 32mm)
 Casted by using M35 grade Concrete.
 Internal vibrators are used for compaction of concrete.
PIER CAP –
Main function is to distribute concentrated loads evenly over the area of pier.
Pier cap carry a standard shape of inverse triangle shape, which behave like a truss of compression
and tension member. I tried to show it in the picture below, tension member by dotted line and
compression member by bold line. P1, P2, P3, P4, P5 shows the vehicle load of the carriageway.
Its dimension varies as number of lane required for that particular carriageway. Also calculation of length
and width can be done by using the length of tension and compression member.
I-GIRDER –
It is a pre-stressed beam of having a shape of I. that’s why also called as I-girder. There are so
many factor are considering for its construction.
Its dimension varies as the dead and live load of carriageway. It is only for low spam Length Bridge.
Its length varies 20- 40 m.
Here are some pictures which explain how to assemble it in bridge.
Lower part of I girder is of 600 mm, upper part is of 700 mm and middle part is 500 mm.
DECK –
The part of superstructure which carry the load of vehicle, also known as wearing surface.
Also support the crash barrier and light installation.
Its construction is of simple molding of concrete and steel bar (in well-arranged manner).
Takes 28 days in fully settings of concrete. Daily and enough water is required for setting.
CRASH BARRIER –
Main purpose is to prevent the vehicle by ride of from the road, prevent the accident and also used as
holder of light installation.
It is of size lower part 500 mm and upper part is of 200 mm in parabolic shape w.r.t vertical line.
LIGHT INSTALLATION –
Installation of light is different aspects of bridge construction, but we have to leave space
according to its decoration. But in some project it comes in under it.
I haven’t seen the process of installation of light,construction of crash barrier and installation of
deck in this one-month training period so don’t have too much idea about the processes.
SECTION -F
QUALITY CONTROL
Test on aggregates: -
Aggregate plays an important role in pavement construction, pile construction, pile construction.
Aggregates influence, to a great extent, the load transfer capability of pavements. Hence it is
essential that they should be thoroughly tested before using for construction. Not only that
aggregates should be strong and durable, they should also possess proper shape and size to make
The pavement act monolithically. Aggregates are tested for strength, toughness, hardness, and
shape and water absorption.
1. Crushing test - Used to determine the strength of aggregates.
The test consists of subjecting the specimen of aggregate in standard mould to a compression test
under standard load conditions. Dry aggregates passing through 12.5mm sieves and retained 10 mm
sieves are filled in a cylindrical measure of 11.5 mm diameter and a8 cm height in three layers. Each
layer is tamped 25 times with at standard rod. The test sample is weighted and placed in the test
cylinder in three layers each layer being tamped again. The specimen is subjected to a compressive
load of 40 tones gradually applied at the rate of 4 tones per minute. Then crushed aggregates are
then sieved through 2.36 m sieve and weight of passing material is expressed as percentages of the
total sample which is aggregate crushing value.
A value less than 10 signifies an exceptionally strong aggregate.
2. Impact test: -
The aggregate impact test is carried out to evaluate the resistance to impact of aggregates.
Aggregate passing 12.5 mm sieve and retained 10 mm sieve is filled in a cylinder steel cup of internal
diameter 10.2 mm and depth of 5 cm which is attached to a metal base of impact testing machine.
3. Shape test: - Flakiness and Elongation test
Flakiness index is defined as the percentage by weight of aggregate particles whose least dimension
less than .6 times their size. Flakiness gauge is used for this test.
The elongation index of an aggregate is defined as the percentage by weight of particles whose great
dimension is 1.8 times their mean dimension. This test is applicable to aggregate larger than 6.3 mm.
Elongation gauge is used for this test.
4. Bitumen adhesion test: -
Bitumen adheres well to all normal types of road aggregates provided they are dry and free from
dust. In the absence of water there is practically no adhesion problem of bituminous construction.
Adhesion problems occur when the aggregate is wet and cold. This problem can be dealt with by removing
moisture from the aggregates by drying and increasing and mixing temperature.
TEST ON CEMENT
A. Date of packing: - Date of manufacturing should be seen on the bag, it is important because the
strength of cement reduces with age.
B. Color: - The cement should be uniform in color. In general, the color of cement is grey with a
light greenish shade. The color of cement gives an indication of excess lime or clay and the
degree of burning.
C. Rubbing: -we take a pinch of cement between fingers and rub it. It should feel smooth while
rubbing. If it is rough, that means adulteration with sand.
D. Hand insertion: - Thrust hand into the cement bag and it should give cool feeling. It indicates
that no hydration reaction is taking place in the bag.
E. Float test: - throw a small quantity of cement in a bucket of water. It should sink and should not
float on the surface.
F. Shape test: - Take 100g of cement and make a stiff paste prepare a cake with sharp edges and
put on the glass plate. Immerse this plate in water. Observe that the shape shouldn’t get disturb
while setting. It should be able to set and attain strength. Cement is capable of setting under
water also and that is why it is also called “hydraulic cement”.
G. Strength test: - A block of cement 25 mm* 25 mm and 200 mm long is prepared and it is
immersed for 7 days in water. It is then placed on supports 15000 mm apart and it is loaded with
a weight of 340 N. The block should not show any sign of failure.
PERFORMANCE TEST
Load test: load tests on piles are conducted on completion of 28 days after casting of piles. Two
types of tests namely initial and routine test, for each type of loading ex: - vertical, horizontal are
performed
Initial test on pile: The test is performed to confirm the design load calculation and to provide
guidelines for setting up the limits of acceptance for routine tests. It also gives an idea of the
suitability of the pilling system. Test on pile are to be carried out at one or more locations depending
on the number of piles required. Load test for the initial load test is 2.5 times (safety factor) the safe
carrying capacity of the pile.
Routine test: selection of piles for the routine test is done based on the number of piles required
subjected to maximum of ½ of total number of piles required. The number of test may be increased
to 2% depending on the nature/type of structure. The test load applied 3/2 times the safe carrying
capacity of pile.
This test will be performed for the following purpose:
a) To ensure the safe load capacity of the piles
b) Defection of any unusual performance contrary to the finding of the initial test.
Vertical load test:
Pile head- The pile head shall be chipped of till sound concrete is met wherever applicable. The
reinforcement shall be cut and head leveled with plaster of Paris. A bearings plate with a hole shall
be placed on the head for the jack to rest.
Initial tests: it can be done in two steps;
1. 2/3 of the final load at which the total displacement attains value of 12 mm unless otherwise
requires on the basis of nature and type of structure in which case, the safe load should be
corresponding to the stated total displacement permissible.
2. 50 % of the final load at which the total displacement equals 10 % of the pile diameter in case
of uniform diameter piles or 7.5 % of the bulb diameter in case of under reamed piles.
SECTION -G
CONCLUSION
After the completion of this project, flyovers would benefit the commutators going to kankarbagh
, Gandhi Maidan ,Mithapur Bus Stand From Danapur, IIT, AIIMS . Anyone can travel from R Block to
Gandhi Maidan without facing heavy traffic jam in between.
This project will prove a great asset to mankind as it will prevent chronic jams in traffic gridlock in areas like
New Market, Patna Junction & Bailey Road and hence will save considerable amount of fuel & time.
*********************************THANKS**********************************
*

More Related Content

What's hot

INDUSTRIAL TRAINING OF FLYOVER CONSTRUCTION
INDUSTRIAL TRAINING OF FLYOVER CONSTRUCTIONINDUSTRIAL TRAINING OF FLYOVER CONSTRUCTION
INDUSTRIAL TRAINING OF FLYOVER CONSTRUCTIONBhavek Sharma
 
CONSTRUCTION OF OVERHEAD BRIDGE
CONSTRUCTION OF OVERHEAD BRIDGECONSTRUCTION OF OVERHEAD BRIDGE
CONSTRUCTION OF OVERHEAD BRIDGEAnkit Gautam
 
Construction equipments
Construction equipmentsConstruction equipments
Construction equipmentsMohit Dagar
 
flyover internship 2
flyover internship 2flyover internship 2
flyover internship 2Ravi Mehta
 
Job layout per
Job layout perJob layout per
Job layout perraj balar
 
CIVIL ENGINEERING INTERNSHIP FULL REPORT ON BUILDING CONSTRUCTION
CIVIL ENGINEERING INTERNSHIP FULL REPORT ON BUILDING CONSTRUCTION CIVIL ENGINEERING INTERNSHIP FULL REPORT ON BUILDING CONSTRUCTION
CIVIL ENGINEERING INTERNSHIP FULL REPORT ON BUILDING CONSTRUCTION L&W BUILDING SOLUTIONS PVT. LMT.
 
Highway construction or Road work report
Highway construction or Road work reportHighway construction or Road work report
Highway construction or Road work reportAbdul rahman kureshi
 
PRESENTATION ON SUMMER INTERNSHIP ON MULTISTOREY BUILDING CONSTRUCTION
PRESENTATION ON SUMMER INTERNSHIP ON MULTISTOREY BUILDING CONSTRUCTION PRESENTATION ON SUMMER INTERNSHIP ON MULTISTOREY BUILDING CONSTRUCTION
PRESENTATION ON SUMMER INTERNSHIP ON MULTISTOREY BUILDING CONSTRUCTION Ved Jangid
 
Civil engineering internship report
Civil engineering internship reportCivil engineering internship report
Civil engineering internship reportMd Mohsin Mohsin
 
Design of flexible pavement
Design of flexible pavementDesign of flexible pavement
Design of flexible pavementBhavik A Shah
 
Bituminous road construction
Bituminous road constructionBituminous road construction
Bituminous road constructionAnitha Jacob
 
Summer Internship Presentation of Building
Summer Internship Presentation of Building Summer Internship Presentation of Building
Summer Internship Presentation of Building Self-employed
 
Construction of flexible pavements
Construction of flexible pavementsConstruction of flexible pavements
Construction of flexible pavementspradip dangar
 
Industrial Training Report of Construction Site in Civil Engineering
Industrial Training Report of Construction Site in Civil EngineeringIndustrial Training Report of Construction Site in Civil Engineering
Industrial Training Report of Construction Site in Civil EngineeringRAVI KUMAR
 
Internship Report Construction Site and Office Work
Internship Report Construction Site and Office WorkInternship Report Construction Site and Office Work
Internship Report Construction Site and Office WorkAkshathaBhandary
 

What's hot (20)

Boussinesq'S theory
Boussinesq'S theoryBoussinesq'S theory
Boussinesq'S theory
 
INDUSTRIAL TRAINING OF FLYOVER CONSTRUCTION
INDUSTRIAL TRAINING OF FLYOVER CONSTRUCTIONINDUSTRIAL TRAINING OF FLYOVER CONSTRUCTION
INDUSTRIAL TRAINING OF FLYOVER CONSTRUCTION
 
CONSTRUCTION OF OVERHEAD BRIDGE
CONSTRUCTION OF OVERHEAD BRIDGECONSTRUCTION OF OVERHEAD BRIDGE
CONSTRUCTION OF OVERHEAD BRIDGE
 
Construction equipments
Construction equipmentsConstruction equipments
Construction equipments
 
flyover internship 2
flyover internship 2flyover internship 2
flyover internship 2
 
Deck slab bridge
Deck slab bridgeDeck slab bridge
Deck slab bridge
 
Job layout per
Job layout perJob layout per
Job layout per
 
Design of rigid pavements
Design of rigid pavementsDesign of rigid pavements
Design of rigid pavements
 
CIVIL ENGINEERING INTERNSHIP FULL REPORT ON BUILDING CONSTRUCTION
CIVIL ENGINEERING INTERNSHIP FULL REPORT ON BUILDING CONSTRUCTION CIVIL ENGINEERING INTERNSHIP FULL REPORT ON BUILDING CONSTRUCTION
CIVIL ENGINEERING INTERNSHIP FULL REPORT ON BUILDING CONSTRUCTION
 
Highway construction or Road work report
Highway construction or Road work reportHighway construction or Road work report
Highway construction or Road work report
 
Pile load test
Pile load testPile load test
Pile load test
 
PRESENTATION ON SUMMER INTERNSHIP ON MULTISTOREY BUILDING CONSTRUCTION
PRESENTATION ON SUMMER INTERNSHIP ON MULTISTOREY BUILDING CONSTRUCTION PRESENTATION ON SUMMER INTERNSHIP ON MULTISTOREY BUILDING CONSTRUCTION
PRESENTATION ON SUMMER INTERNSHIP ON MULTISTOREY BUILDING CONSTRUCTION
 
Civil engineering internship report
Civil engineering internship reportCivil engineering internship report
Civil engineering internship report
 
Pile foundations
Pile foundationsPile foundations
Pile foundations
 
Design of flexible pavement
Design of flexible pavementDesign of flexible pavement
Design of flexible pavement
 
Bituminous road construction
Bituminous road constructionBituminous road construction
Bituminous road construction
 
Summer Internship Presentation of Building
Summer Internship Presentation of Building Summer Internship Presentation of Building
Summer Internship Presentation of Building
 
Construction of flexible pavements
Construction of flexible pavementsConstruction of flexible pavements
Construction of flexible pavements
 
Industrial Training Report of Construction Site in Civil Engineering
Industrial Training Report of Construction Site in Civil EngineeringIndustrial Training Report of Construction Site in Civil Engineering
Industrial Training Report of Construction Site in Civil Engineering
 
Internship Report Construction Site and Office Work
Internship Report Construction Site and Office WorkInternship Report Construction Site and Office Work
Internship Report Construction Site and Office Work
 

Similar to A project report on flyover internship bihar rajya pul nirman nigam limited patna.

Report on Industrial training at BRPNNL Patna
Report on Industrial training at BRPNNL PatnaReport on Industrial training at BRPNNL Patna
Report on Industrial training at BRPNNL PatnaNarayan Gupta
 
Synopsis for insustrial training of Civil engineering
Synopsis for insustrial training of Civil engineering Synopsis for insustrial training of Civil engineering
Synopsis for insustrial training of Civil engineering Ram1239
 
most final report of industrial training for college
most final report of industrial training for collegemost final report of industrial training for college
most final report of industrial training for collegeindrajeet kumar
 
Internship report on mechanical engineering
Internship report on mechanical engineeringInternship report on mechanical engineering
Internship report on mechanical engineeringmalavadedarshan25
 
Central Public Works Department (CPWD) summer training report
Central Public Works Department (CPWD) summer training reportCentral Public Works Department (CPWD) summer training report
Central Public Works Department (CPWD) summer training reportAman Gupta
 
Training project report NHAI by Amit Kumar
Training project report NHAI by Amit KumarTraining project report NHAI by Amit Kumar
Training project report NHAI by Amit KumarAmitKumar7069
 
Summer internship report on soil testing,Bitumen & aggregate
Summer internship report on soil testing,Bitumen & aggregateSummer internship report on soil testing,Bitumen & aggregate
Summer internship report on soil testing,Bitumen & aggregateAnup singh
 

Similar to A project report on flyover internship bihar rajya pul nirman nigam limited patna. (20)

Final Project
Final ProjectFinal Project
Final Project
 
Report on Industrial training at BRPNNL Patna
Report on Industrial training at BRPNNL PatnaReport on Industrial training at BRPNNL Patna
Report on Industrial training at BRPNNL Patna
 
RCD INTERNSHIP REPORT
RCD INTERNSHIP REPORTRCD INTERNSHIP REPORT
RCD INTERNSHIP REPORT
 
Synopsis for insustrial training of Civil engineering
Synopsis for insustrial training of Civil engineering Synopsis for insustrial training of Civil engineering
Synopsis for insustrial training of Civil engineering
 
most final report of industrial training for college
most final report of industrial training for collegemost final report of industrial training for college
most final report of industrial training for college
 
“DESIGN AND DEVELOPMENT OF FIXTURE FOR FIXING BEARING IN CRANK-CASE
“DESIGN AND DEVELOPMENT OF FIXTURE FOR  FIXING BEARING IN CRANK-CASE“DESIGN AND DEVELOPMENT OF FIXTURE FOR  FIXING BEARING IN CRANK-CASE
“DESIGN AND DEVELOPMENT OF FIXTURE FOR FIXING BEARING IN CRANK-CASE
 
Internship report on mechanical engineering
Internship report on mechanical engineeringInternship report on mechanical engineering
Internship report on mechanical engineering
 
Project Report
Project ReportProject Report
Project Report
 
Internship Report
Internship ReportInternship Report
Internship Report
 
Central Public Works Department (CPWD) summer training report
Central Public Works Department (CPWD) summer training reportCentral Public Works Department (CPWD) summer training report
Central Public Works Department (CPWD) summer training report
 
Cv amit
Cv amitCv amit
Cv amit
 
Cv amit
Cv amitCv amit
Cv amit
 
Training project report NHAI by Amit Kumar
Training project report NHAI by Amit KumarTraining project report NHAI by Amit Kumar
Training project report NHAI by Amit Kumar
 
resume.b
resume.bresume.b
resume.b
 
Summer internship report on soil testing,Bitumen & aggregate
Summer internship report on soil testing,Bitumen & aggregateSummer internship report on soil testing,Bitumen & aggregate
Summer internship report on soil testing,Bitumen & aggregate
 
Civil Engineer
Civil EngineerCivil Engineer
Civil Engineer
 
Civil Engineer
Civil EngineerCivil Engineer
Civil Engineer
 
CV Shubham Bhargava
CV  Shubham BhargavaCV  Shubham Bhargava
CV Shubham Bhargava
 
cv.dchand copy
cv.dchand copycv.dchand copy
cv.dchand copy
 
Intern report
Intern reportIntern report
Intern report
 

Recently uploaded

Introduction-To-Agricultural-Surveillance-Rover.pptx
Introduction-To-Agricultural-Surveillance-Rover.pptxIntroduction-To-Agricultural-Surveillance-Rover.pptx
Introduction-To-Agricultural-Surveillance-Rover.pptxk795866
 
Arduino_CSE ece ppt for working and principal of arduino.ppt
Arduino_CSE ece ppt for working and principal of arduino.pptArduino_CSE ece ppt for working and principal of arduino.ppt
Arduino_CSE ece ppt for working and principal of arduino.pptSAURABHKUMAR892774
 
Decoding Kotlin - Your guide to solving the mysterious in Kotlin.pptx
Decoding Kotlin - Your guide to solving the mysterious in Kotlin.pptxDecoding Kotlin - Your guide to solving the mysterious in Kotlin.pptx
Decoding Kotlin - Your guide to solving the mysterious in Kotlin.pptxJoão Esperancinha
 
UNIT III ANALOG ELECTRONICS (BASIC ELECTRONICS)
UNIT III ANALOG ELECTRONICS (BASIC ELECTRONICS)UNIT III ANALOG ELECTRONICS (BASIC ELECTRONICS)
UNIT III ANALOG ELECTRONICS (BASIC ELECTRONICS)Dr SOUNDIRARAJ N
 
pipeline in computer architecture design
pipeline in computer architecture  designpipeline in computer architecture  design
pipeline in computer architecture designssuser87fa0c1
 
DATA ANALYTICS PPT definition usage example
DATA ANALYTICS PPT definition usage exampleDATA ANALYTICS PPT definition usage example
DATA ANALYTICS PPT definition usage examplePragyanshuParadkar1
 
Biology for Computer Engineers Course Handout.pptx
Biology for Computer Engineers Course Handout.pptxBiology for Computer Engineers Course Handout.pptx
Biology for Computer Engineers Course Handout.pptxDeepakSakkari2
 
CCS355 Neural Networks & Deep Learning Unit 1 PDF notes with Question bank .pdf
CCS355 Neural Networks & Deep Learning Unit 1 PDF notes with Question bank .pdfCCS355 Neural Networks & Deep Learning Unit 1 PDF notes with Question bank .pdf
CCS355 Neural Networks & Deep Learning Unit 1 PDF notes with Question bank .pdfAsst.prof M.Gokilavani
 
Concrete Mix Design - IS 10262-2019 - .pptx
Concrete Mix Design - IS 10262-2019 - .pptxConcrete Mix Design - IS 10262-2019 - .pptx
Concrete Mix Design - IS 10262-2019 - .pptxKartikeyaDwivedi3
 
Gurgaon ✡️9711147426✨Call In girls Gurgaon Sector 51 escort service
Gurgaon ✡️9711147426✨Call In girls Gurgaon Sector 51 escort serviceGurgaon ✡️9711147426✨Call In girls Gurgaon Sector 51 escort service
Gurgaon ✡️9711147426✨Call In girls Gurgaon Sector 51 escort servicejennyeacort
 
EduAI - E learning Platform integrated with AI
EduAI - E learning Platform integrated with AIEduAI - E learning Platform integrated with AI
EduAI - E learning Platform integrated with AIkoyaldeepu123
 
Call Girls Delhi {Jodhpur} 9711199012 high profile service
Call Girls Delhi {Jodhpur} 9711199012 high profile serviceCall Girls Delhi {Jodhpur} 9711199012 high profile service
Call Girls Delhi {Jodhpur} 9711199012 high profile servicerehmti665
 
Architect Hassan Khalil Portfolio for 2024
Architect Hassan Khalil Portfolio for 2024Architect Hassan Khalil Portfolio for 2024
Architect Hassan Khalil Portfolio for 2024hassan khalil
 
Study on Air-Water & Water-Water Heat Exchange in a Finned Tube Exchanger
Study on Air-Water & Water-Water Heat Exchange in a Finned Tube ExchangerStudy on Air-Water & Water-Water Heat Exchange in a Finned Tube Exchanger
Study on Air-Water & Water-Water Heat Exchange in a Finned Tube ExchangerAnamika Sarkar
 
IVE Industry Focused Event - Defence Sector 2024
IVE Industry Focused Event - Defence Sector 2024IVE Industry Focused Event - Defence Sector 2024
IVE Industry Focused Event - Defence Sector 2024Mark Billinghurst
 
Effects of rheological properties on mixing
Effects of rheological properties on mixingEffects of rheological properties on mixing
Effects of rheological properties on mixingviprabot1
 
Heart Disease Prediction using machine learning.pptx
Heart Disease Prediction using machine learning.pptxHeart Disease Prediction using machine learning.pptx
Heart Disease Prediction using machine learning.pptxPoojaBan
 

Recently uploaded (20)

Introduction-To-Agricultural-Surveillance-Rover.pptx
Introduction-To-Agricultural-Surveillance-Rover.pptxIntroduction-To-Agricultural-Surveillance-Rover.pptx
Introduction-To-Agricultural-Surveillance-Rover.pptx
 
Exploring_Network_Security_with_JA3_by_Rakesh Seal.pptx
Exploring_Network_Security_with_JA3_by_Rakesh Seal.pptxExploring_Network_Security_with_JA3_by_Rakesh Seal.pptx
Exploring_Network_Security_with_JA3_by_Rakesh Seal.pptx
 
Arduino_CSE ece ppt for working and principal of arduino.ppt
Arduino_CSE ece ppt for working and principal of arduino.pptArduino_CSE ece ppt for working and principal of arduino.ppt
Arduino_CSE ece ppt for working and principal of arduino.ppt
 
Decoding Kotlin - Your guide to solving the mysterious in Kotlin.pptx
Decoding Kotlin - Your guide to solving the mysterious in Kotlin.pptxDecoding Kotlin - Your guide to solving the mysterious in Kotlin.pptx
Decoding Kotlin - Your guide to solving the mysterious in Kotlin.pptx
 
UNIT III ANALOG ELECTRONICS (BASIC ELECTRONICS)
UNIT III ANALOG ELECTRONICS (BASIC ELECTRONICS)UNIT III ANALOG ELECTRONICS (BASIC ELECTRONICS)
UNIT III ANALOG ELECTRONICS (BASIC ELECTRONICS)
 
pipeline in computer architecture design
pipeline in computer architecture  designpipeline in computer architecture  design
pipeline in computer architecture design
 
DATA ANALYTICS PPT definition usage example
DATA ANALYTICS PPT definition usage exampleDATA ANALYTICS PPT definition usage example
DATA ANALYTICS PPT definition usage example
 
Biology for Computer Engineers Course Handout.pptx
Biology for Computer Engineers Course Handout.pptxBiology for Computer Engineers Course Handout.pptx
Biology for Computer Engineers Course Handout.pptx
 
CCS355 Neural Networks & Deep Learning Unit 1 PDF notes with Question bank .pdf
CCS355 Neural Networks & Deep Learning Unit 1 PDF notes with Question bank .pdfCCS355 Neural Networks & Deep Learning Unit 1 PDF notes with Question bank .pdf
CCS355 Neural Networks & Deep Learning Unit 1 PDF notes with Question bank .pdf
 
🔝9953056974🔝!!-YOUNG call girls in Rajendra Nagar Escort rvice Shot 2000 nigh...
🔝9953056974🔝!!-YOUNG call girls in Rajendra Nagar Escort rvice Shot 2000 nigh...🔝9953056974🔝!!-YOUNG call girls in Rajendra Nagar Escort rvice Shot 2000 nigh...
🔝9953056974🔝!!-YOUNG call girls in Rajendra Nagar Escort rvice Shot 2000 nigh...
 
9953056974 Call Girls In South Ex, Escorts (Delhi) NCR.pdf
9953056974 Call Girls In South Ex, Escorts (Delhi) NCR.pdf9953056974 Call Girls In South Ex, Escorts (Delhi) NCR.pdf
9953056974 Call Girls In South Ex, Escorts (Delhi) NCR.pdf
 
Concrete Mix Design - IS 10262-2019 - .pptx
Concrete Mix Design - IS 10262-2019 - .pptxConcrete Mix Design - IS 10262-2019 - .pptx
Concrete Mix Design - IS 10262-2019 - .pptx
 
Gurgaon ✡️9711147426✨Call In girls Gurgaon Sector 51 escort service
Gurgaon ✡️9711147426✨Call In girls Gurgaon Sector 51 escort serviceGurgaon ✡️9711147426✨Call In girls Gurgaon Sector 51 escort service
Gurgaon ✡️9711147426✨Call In girls Gurgaon Sector 51 escort service
 
EduAI - E learning Platform integrated with AI
EduAI - E learning Platform integrated with AIEduAI - E learning Platform integrated with AI
EduAI - E learning Platform integrated with AI
 
Call Girls Delhi {Jodhpur} 9711199012 high profile service
Call Girls Delhi {Jodhpur} 9711199012 high profile serviceCall Girls Delhi {Jodhpur} 9711199012 high profile service
Call Girls Delhi {Jodhpur} 9711199012 high profile service
 
Architect Hassan Khalil Portfolio for 2024
Architect Hassan Khalil Portfolio for 2024Architect Hassan Khalil Portfolio for 2024
Architect Hassan Khalil Portfolio for 2024
 
Study on Air-Water & Water-Water Heat Exchange in a Finned Tube Exchanger
Study on Air-Water & Water-Water Heat Exchange in a Finned Tube ExchangerStudy on Air-Water & Water-Water Heat Exchange in a Finned Tube Exchanger
Study on Air-Water & Water-Water Heat Exchange in a Finned Tube Exchanger
 
IVE Industry Focused Event - Defence Sector 2024
IVE Industry Focused Event - Defence Sector 2024IVE Industry Focused Event - Defence Sector 2024
IVE Industry Focused Event - Defence Sector 2024
 
Effects of rheological properties on mixing
Effects of rheological properties on mixingEffects of rheological properties on mixing
Effects of rheological properties on mixing
 
Heart Disease Prediction using machine learning.pptx
Heart Disease Prediction using machine learning.pptxHeart Disease Prediction using machine learning.pptx
Heart Disease Prediction using machine learning.pptx
 

A project report on flyover internship bihar rajya pul nirman nigam limited patna.

  • 1. A PROJECT REPORT ON CONSTRUCTION OF FLYOVER For Bihar Rajya Pul Nirman Nigam Limited. Guided by :- Mr. Arvind Prasad Gupta ( Project Engineer ) Project Name Lohia Path Chakra Submitted by:- Prabhat Kumar Prashant Shaurabh Civil Engineering VIIth Sem Civil Engineering VIIth Sem Roll No:-14102024 Roll No:-14102025 DEPARTMENT OF CIVIL ENGINEERING INSTITUTE OF TECHNOLOGY,GURU GHASIDAS VISHWAVIDYALAYA BILASPUR, C.G.
  • 2. REASON BEHIND GOING FOR A FLYOVER As the traffic on the road goes on increasing and we don’t have any space left in both the dimensions, then the only option left will be to go to the third dimension and that is done through Flyover construction. There is so much traffic in the city so it takes around 45 to 60 minutes to go from saguna more to patna high court even they are 12 kms apart,and of being the lifeline road of the city it is important to control the traffic on this road.So the decision has been taken to construct a flyover so to reduce the travelling time to 15 minutes from 45 minutes.
  • 3. Contents Aknowledgement Abstract SECTION -A Different stages of project  Topographic survey and analysis  Traffic survey and analysis  Geotechnical aspects and analysis  Planning and design SECTION –B Features of project  Salient features  Physical features SECTION –C Components involved  Foundation  Substructure  Superstructure SECTION –D Machines and equipments used  Air compressor  Backhoe loader  Crawler crane  Excavator  Genset  Hydraullic rig machine  Hydraullic crane  Mini roller
  • 4.  Pneumatic concrete breaker  Transit mixer  Tanks  Augur  Casing  Treamie pipe  Funnel  Goliath Gantry Crane SECTION –E Construction Procedure & dimensions  Pile  Pile cap  Pier  Pier cap  Girder  Deck  Bearing  Crash barrier  Installation of light SECTION –F Quality Control  Test on aggregates  Crushing test  Impact test  Shape test  Bitumen adhesion test  Test on Cement  Date of packing  Colour  Rubbing  Hand Insertion  Float test
  • 5.  Shape test  Strength test  Performance test  Load test  Capacity test  Stress test  Cube strength  Slump cone test SECTION –G Conclusion
  • 6. Acknowledgement A vocational training is a golden opportunity for learning and self development.I consider myself very lucky and honored to have so many wonderful people lead me through in completion of this project. First of all I would like to thank all the families and friends that participate on my life and get me in this intensityand individuals who support and share idea and also helping me to be like this. I am very thankful to BIHAR RAJYA PUL NIRMAN NIGAM LIMITED(BRPNNL) and its managing director RANJAN KUMAR for having given me the opportunity to undertake my one month summer training in their working area.It was a very good learning experience for me to have worked at this area.I would like to convey my heartiest thanks to Chief Engineer ARVIND KUMAR and all the Faculty members at Department of Civil Engineering at Guru Ghasidas Vishwavidyalaya,who made it all possible. I would also thank SUJEET SIR for his endless support at site and in his office by consulting me how to do things at site,all teachers of Civil Engineering who brought me to my present performance and shape me like this during the last Three successive years, special thank to my prof NIKHIL KUMAR VERMA for guiding me to do training at BRPNNL. Before I finish I would like to give my deepest thanks to all workers from thr contractor, S P Singla Construction Private Limited and the consultant side starting from Engineers to daily labours.Also for those who do not listed in the above but support me in different areas I would like thank all.
  • 7. ABOUT BIHAR RAJYA PUL NIRMAAN NIGAM LTD. Constitution and objectives Bihar Rajya Pul Nirman Nigam (BRPNN) was formed on 11th June, 1975 under Indian Company Act, 1956 as a Govt. Company. Its main objectives are -  Construction of Bridges/Roads  Maintenance of Bridges  Toll Collection The Nigam is registered as a Public Company under Indian Company Act, 1956 and it is a Govt. Company as total share capital of Rs.500 Lakhs is pledged in the name of Governor of Bihar. The Nigam is governed by Managing Director on behalf of Board of Directors nominated by the Govt. under guidelines set by Memorandum of Association and Articles of Association along with work rules mentioned therein. Concept of Working Bridges are constructed departmentally by the Nigam on the basis of current Schedule of Rates (SoR) sanctioned for Works Department. As the work is done departmentally, cost incurred is less as compared to work done by contractors. ABOUT S P Singla Construction Pvt Ltd. S. P. Singla Constructions Pvt. Ltd. collaboratively facilitate, engineer, and disseminate construction services fostering the world’s ethical, social, economic, and intellectual growth, using progressive and diverse techniques on the cutting edge of the construction industry. Every aspect of how we work has been built to fulfil our mission to make lasting contributions to our people, our communities, and the construction industry. From company’s commitment for its valuable employee’s teamwork to a continued commitment to hard work and performing with excellence, our values are obvious in every office and on every project site. S. P. Singla Constructions Pvt. Ltd. collaboratively facilitate the construction services fostering the world’s geographical growth, using progressive and diverse techniques on the cutting edge of the construction industry and provides healthy professional environment which is unanimously
  • 8. accepted by every associated employee of S. P. Singla Constructions Pvt. Ltd. we filter excellent from best. VISION To build a progressive and creative organisation that constantly strives to improve its business & construction practices and win clients’ trust by exceeding their expectations. MISSION To be pioneers in the field of Bridge construction by application of innovative solutions and knowledge to work. S. P. Singla Constructions Pvt. Ltd. is a company pioneering spirit. That pioneering spirit drives us to constantly find new and smarter ways to build. Our construction services have been fine-tuned over a century of building and during that time have embraced advances in technology that help us build better and safer infrastructure and for a lower cost. Our experienced team applies today’s technology to proven building principles. WE ARE SPECIALISTS IN CONSTRUCTION OF:  R.C.C. bridges  Pre-stressed concrete bridges  Cantilever bridges for construction of long span bridges  Well foundations  Pile foundations  Flyovers  Road / Rail over bridges  Steel bridges including fabrication & launching  Launch of pre-cast & pre-stressed concrete girder  Roadwork with asphaltic concrete and mastic asphalt surfaces  Segmental constructions At S. P. Singla Constructions Pvt. Ltd., we are always striving to bring on board the latest of technologies and equipment to meet the demands of today’s clients. While listed above are few of the technologies we are presently working with, in near future we will be adding more to our list. The technologies are updated time-to-time to deliver today what others hope to do tomorrow.
  • 9. Abstract The training report in broad spectrum contains six sections in which I try to explain my one month learning experience in the running project, construction of LOHIA Path CHAKRA as a part of Bailey Road Flyover. The content of all section is broadly explained and it is made from the practical basis of the site work of weekly basis. In section A I give all the details of different stages of the project. In this section I put all the details of the work done in the same manner at the site for the completion of the project. In section B I try to explain the features of the project like the project details, the cost involved, the length of the flyover, no of piles involved, cost involved .etc. In section C I try to explain the components involved in the Flyover construction. It has been categorized into three parts the foundation part, the sub structure and the superstructure part. In section D I try to explain all the machines and equipments used in the whole construction with their respective pictures. The section E is the most important chapter in which explains all the dimensions and the construction procedure of the components involved with some practical images whatever I clicked during the whole training period. In the section F I try to explain all the related tests on the materials involved in the construction the tests on the aggregates, cement, soil and, model testing of pile on the basis of which we decide the size of different part of the bridge, which type of material is suitable for the construction process, how we can minimize the cost on that particular project and also the load carrying capacity of pile. After reading all the sections one can easily understand basics of flyover construction procedure, dimension and minimization of the cost of the project.
  • 10. SECTION –A DIFFERENT STAGES OF PROJECT 1.SURVEY AND ANALYSIS Each and every civil engineering project starts with survey. There are various stages of survey. The first step of surveying is reconnaissance Then after that various maps of the site is studied. Only after this detail survey of proposed project site is done. Here in this project a detail survey of the site is done by the Total Station and various other instruments of surveying and layout is drawn in Autocad. With help of this total space available for construction, alignment of flyover and no. lanes of flyover & total carriageway. It should be noted that surveying not only plays an important role in the design of the project but also in the execution. 2. TRAFFIC SURVEY AND ANALYSIS The main purposes of traffic survey are: traffic monitoring, traffic control and management, traffic enforcement, traffic forecasting, model calibration and validating etc. The purposes of carrying out traffic volume count are designing, improving traffic system, planning, management etc. Traffic forecast predicts the future traffic volume levels on the project road. In this project, the flyover is designed to meet the requirements of traffic for next 25 years. From traffic survey it was decided to design the flyover for live load for a single lane of class 70R or 2 lanes of class -A. .3. GEOTECHNICAL ASPECTS AND ANALYSIS It is very necessary to carry out thorough soil investigation of the site as the whole load of the structure is ultimately taken by soil through foundation. Feasibility, design and safety of the structure all depends upon load bearing capacity of the soil strata at the site.
  • 11. For this purpose bore holes were drilled in the ground to get information about the sub-soil strata. Boring was done at an interval of 40m along the alignment and depth of exploration was 39m. Samples were taken from the bore hole and tested in the laboratory and engineering properties of the soil was investigated. Also some field test was carried out. From these tests & investigations, it was concluded that the Soil Bearing Capacity (SBC) of the site was 230 MPa. 4. PLANNING & DESIGN All the results were taken into account and with help of Various IS Codes detailed planning and design were prepared according to which execution is going through and the flyover is under construction. From all available data a pile was designed and Initial Load Test for pile was done to confirm the load carrying capacity of the single pile. TECHNICAL DATAS :- SAGUNA MORE TO PATNA HIGH COURT Diameter of Pile 1200 mm Verticle load capacity of pile 250T Horizontal load capacity of pile 20T Depth of pile cap 1800 mm SECTION – B Salient Features:- Project Cost : 391.47cr Agency : BRPNNL
  • 12. Date of commencement : 9 Dec 2015 Target date of completion : 18 Dec 2017 Physical Features:- Total length of Project 3.2 kM Length of elevated part 1.7 kM No.of piers 16 Type of superstructure PSC GIRDERS Slope across bridge length 1 in 30 No.of underpasses 4 Elevated Bridges 1 Average traffick movement 2000 Vehicles/hour. SECTION :- COMPONENTS INVOLVED FOUNDATION Piles and the Pile cap comes under the Foundation part. Piles:- The function of pile is to transfer the load to the soil. Three types of pile are there:- 1. End bearing pile 2. Friction pile 3. End bearing and friction pile In this project we used End bearing Pile,some parts of the load transferred by the pile by end of pile and remaining load is by the friction between pile and the surface of soil around the pile.
  • 13. Arrow in the above image denotes how load transferred to the ground Pile cap reinforcement Piles usually exists as a group which are all integrated by means of a pile cap as shown in figure. Piles carrying very heavy point loads tend to produce high tensile stress at the pile cap. Reinforcement is thus designed to provide: - 1.Resistance to tensile bending forces in the bottom of the cap. 2.Resistance to the vertical shear. SUBSTRUCTURE Pier and Pier-cap Support of superstructure, transfer dead and live load to pile.It also carries its own considerable weight.
  • 14. Pier It is a raised structure typically supported by well-spaced piles or the pile cap. It can be made by wooden concrete, steel, mixed, but in this project we use concrete pier with well-maintained iron rod. Pier cap The upper or bearing part of the pier, usually made of concrete or hard stone; designed to distribute concentrated loads evenly over the area of pier.The width of pier cap depends upon the width of carriageway, its size depends upon the live load and dead load bridge capacity. SUPERSTRUCTURE Wearing surface consists of the deck structure itself, which support the direct loads due to traffic and all the other permanent and variable leads to which the structure is subjected. Also known as carriageway. Width of carriageway depends upon number of lane of flyover. For intermediate carriage -5.5 m and for two lane-7.5 m. Bearing Bridge bearings are used to transfer forces from the superstructure to substructure, allowing the following types of movements of the superstructure :- Translational movements; are displacements in vertical and horizontal directions due to in-place or out-of- place forces like wind and self-weight.
  • 15. Rotational movements; cause due to moments. Until the middle of this century, the bearings used considered of following types: - pin, roller, rocker, metal sliding etc. Girder It is support of carriageway between two piers, it is of many types like box shape, Z shape,I-shape and many other forms. In this flyover, I-shape pre-stressed beam used . Crash barrier A strong fence at the side of carriageway, intended to reduce the risk of serious accidents. It is of various types ex: - wooden, tin, steel, cable, wire, concrete. Concrete barrier is strongest one and cheap as well. Now these days in flyover concrete crash barrier is preferred generally. SECTION -D Machines and equipments used Air Compressor Backhoe Loader
  • 16. Crawler crane Excavator Genset Hydraullic Rig Machine Hydraullic Crane Mini Roller
  • 17. Pneumatic concrete breaker Transit Mixer Tanks Bullet Augur Bucket Augur Casing
  • 19. SECTION -E CONSTRUCTION PROCEDURES AND DIMENSIONS PILE :- In this particular project, we use rotary hammer machine for drilling purpose. 1.Pile boring procedure Set up the Location of Bored Pile. We use Total Station instrument to survey each pile point. The dia of the pile is 1.2m and the depth is 32m. 2. Drilling Using MAIT machine
  • 21. After Casing is inserted the bore is filled W with the bentonite clay mixed with water to Prevent the soil from the sides to fall down to Bottom. 4. Insertion of Steel Cage
  • 22. 5. Insertion of Tremie Pipe & Pouring of Concrete Number of piles: number of piles required for a particular pier is depends upon the spam, length number of lane of carriage way, capacity of a particular pile and type of bridge it is. Capacity of each pile in this project is 230 tones PILE CAP A pile cap is thick concrete mat that rests on piles to provide a suitable foundation. It forms the part of the foundation of structure. This pile cap distributes the load to piles uniformly. Pile capping Procedure 1. Shuttering and Reinforcement 2. Concreting 3. Curing
  • 23. Dimension of pile cap varies as number of piles and type of soil at that particular place, Carry a height in the rage of 10-15 feet. In this project the height is taken as 10feet. DESIGN AND SPECIFICATIONS OF FOUNDATION  Pile foundation with pile cap  No. of piles – 4 for Abutments & 9 for piers  M35 Grade Concrete is used for casting piles & pile cap  Depth of pile 32000 mm & Dia of pile 1200 mm  Depth of pile cap is 3000 mm  Bars used – Fe 500 Tor Steel Bar of Dia 28 mm & Dia 32 mm  Sand filling is done around pier caps to control & minimize expansion & contraction of structure and sand is economical also.
  • 24. PIER :- A part of substructure which transfers the load to pile followed by pile cap, its construction is a normal process of filling concrete mixture with steel rod arranged in particular manner as shown in picture . The dimensions and construction details of the cast-in-situ piers are given below. Every single pier consists of Reinforcement bars of different dia (max upto 32mm)  Casted by using M35 grade Concrete.  Internal vibrators are used for compaction of concrete.
  • 25. PIER CAP – Main function is to distribute concentrated loads evenly over the area of pier. Pier cap carry a standard shape of inverse triangle shape, which behave like a truss of compression and tension member. I tried to show it in the picture below, tension member by dotted line and compression member by bold line. P1, P2, P3, P4, P5 shows the vehicle load of the carriageway. Its dimension varies as number of lane required for that particular carriageway. Also calculation of length and width can be done by using the length of tension and compression member.
  • 26. I-GIRDER – It is a pre-stressed beam of having a shape of I. that’s why also called as I-girder. There are so many factor are considering for its construction. Its dimension varies as the dead and live load of carriageway. It is only for low spam Length Bridge. Its length varies 20- 40 m. Here are some pictures which explain how to assemble it in bridge. Lower part of I girder is of 600 mm, upper part is of 700 mm and middle part is 500 mm. DECK – The part of superstructure which carry the load of vehicle, also known as wearing surface. Also support the crash barrier and light installation. Its construction is of simple molding of concrete and steel bar (in well-arranged manner). Takes 28 days in fully settings of concrete. Daily and enough water is required for setting.
  • 27. CRASH BARRIER – Main purpose is to prevent the vehicle by ride of from the road, prevent the accident and also used as holder of light installation.
  • 28. It is of size lower part 500 mm and upper part is of 200 mm in parabolic shape w.r.t vertical line. LIGHT INSTALLATION – Installation of light is different aspects of bridge construction, but we have to leave space according to its decoration. But in some project it comes in under it. I haven’t seen the process of installation of light,construction of crash barrier and installation of deck in this one-month training period so don’t have too much idea about the processes. SECTION -F QUALITY CONTROL Test on aggregates: - Aggregate plays an important role in pavement construction, pile construction, pile construction. Aggregates influence, to a great extent, the load transfer capability of pavements. Hence it is essential that they should be thoroughly tested before using for construction. Not only that aggregates should be strong and durable, they should also possess proper shape and size to make
  • 29. The pavement act monolithically. Aggregates are tested for strength, toughness, hardness, and shape and water absorption. 1. Crushing test - Used to determine the strength of aggregates. The test consists of subjecting the specimen of aggregate in standard mould to a compression test under standard load conditions. Dry aggregates passing through 12.5mm sieves and retained 10 mm sieves are filled in a cylindrical measure of 11.5 mm diameter and a8 cm height in three layers. Each layer is tamped 25 times with at standard rod. The test sample is weighted and placed in the test cylinder in three layers each layer being tamped again. The specimen is subjected to a compressive load of 40 tones gradually applied at the rate of 4 tones per minute. Then crushed aggregates are then sieved through 2.36 m sieve and weight of passing material is expressed as percentages of the total sample which is aggregate crushing value. A value less than 10 signifies an exceptionally strong aggregate. 2. Impact test: - The aggregate impact test is carried out to evaluate the resistance to impact of aggregates. Aggregate passing 12.5 mm sieve and retained 10 mm sieve is filled in a cylinder steel cup of internal diameter 10.2 mm and depth of 5 cm which is attached to a metal base of impact testing machine. 3. Shape test: - Flakiness and Elongation test Flakiness index is defined as the percentage by weight of aggregate particles whose least dimension less than .6 times their size. Flakiness gauge is used for this test.
  • 30. The elongation index of an aggregate is defined as the percentage by weight of particles whose great dimension is 1.8 times their mean dimension. This test is applicable to aggregate larger than 6.3 mm. Elongation gauge is used for this test. 4. Bitumen adhesion test: - Bitumen adheres well to all normal types of road aggregates provided they are dry and free from dust. In the absence of water there is practically no adhesion problem of bituminous construction. Adhesion problems occur when the aggregate is wet and cold. This problem can be dealt with by removing moisture from the aggregates by drying and increasing and mixing temperature. TEST ON CEMENT A. Date of packing: - Date of manufacturing should be seen on the bag, it is important because the strength of cement reduces with age. B. Color: - The cement should be uniform in color. In general, the color of cement is grey with a light greenish shade. The color of cement gives an indication of excess lime or clay and the degree of burning. C. Rubbing: -we take a pinch of cement between fingers and rub it. It should feel smooth while rubbing. If it is rough, that means adulteration with sand. D. Hand insertion: - Thrust hand into the cement bag and it should give cool feeling. It indicates that no hydration reaction is taking place in the bag. E. Float test: - throw a small quantity of cement in a bucket of water. It should sink and should not float on the surface.
  • 31. F. Shape test: - Take 100g of cement and make a stiff paste prepare a cake with sharp edges and put on the glass plate. Immerse this plate in water. Observe that the shape shouldn’t get disturb while setting. It should be able to set and attain strength. Cement is capable of setting under water also and that is why it is also called “hydraulic cement”. G. Strength test: - A block of cement 25 mm* 25 mm and 200 mm long is prepared and it is immersed for 7 days in water. It is then placed on supports 15000 mm apart and it is loaded with a weight of 340 N. The block should not show any sign of failure. PERFORMANCE TEST Load test: load tests on piles are conducted on completion of 28 days after casting of piles. Two types of tests namely initial and routine test, for each type of loading ex: - vertical, horizontal are performed Initial test on pile: The test is performed to confirm the design load calculation and to provide guidelines for setting up the limits of acceptance for routine tests. It also gives an idea of the suitability of the pilling system. Test on pile are to be carried out at one or more locations depending on the number of piles required. Load test for the initial load test is 2.5 times (safety factor) the safe carrying capacity of the pile. Routine test: selection of piles for the routine test is done based on the number of piles required subjected to maximum of ½ of total number of piles required. The number of test may be increased to 2% depending on the nature/type of structure. The test load applied 3/2 times the safe carrying capacity of pile. This test will be performed for the following purpose: a) To ensure the safe load capacity of the piles b) Defection of any unusual performance contrary to the finding of the initial test. Vertical load test: Pile head- The pile head shall be chipped of till sound concrete is met wherever applicable. The reinforcement shall be cut and head leveled with plaster of Paris. A bearings plate with a hole shall be placed on the head for the jack to rest. Initial tests: it can be done in two steps; 1. 2/3 of the final load at which the total displacement attains value of 12 mm unless otherwise requires on the basis of nature and type of structure in which case, the safe load should be corresponding to the stated total displacement permissible.
  • 32. 2. 50 % of the final load at which the total displacement equals 10 % of the pile diameter in case of uniform diameter piles or 7.5 % of the bulb diameter in case of under reamed piles.
  • 33. SECTION -G CONCLUSION After the completion of this project, flyovers would benefit the commutators going to kankarbagh , Gandhi Maidan ,Mithapur Bus Stand From Danapur, IIT, AIIMS . Anyone can travel from R Block to Gandhi Maidan without facing heavy traffic jam in between. This project will prove a great asset to mankind as it will prevent chronic jams in traffic gridlock in areas like New Market, Patna Junction & Bailey Road and hence will save considerable amount of fuel & time. *********************************THANKS********************************** *