Total Station
Mr. Momin Umarfarook H.
( B.E Civil , M.E Structure)
First question:How do you measure a distance of
30cm ?
What tools would you use ?
Ruler Steel tape
Hans Lippershey, a boss
of eyeglasses store in
Holand.
He invented the
telescope in seventeen
century .
From then on , the
method of measurement
on a new level.
Theodore Harold Maiman , an
American physical scientist , was
invented the
first laser in the world .
Basic Principle Classifications – Electro
optical system – measuring principle –
working principle, Sources of Error –
Infrared and Laser total station Instruments.
Microwave system , measuring principle,
working principle, sources of Errors,
Microwave total station
instruments,comparision between Electro
optical and Microwave system. Care and
maintenance of total station Instruments,
Modern positioning systems , Traversing
and Trilateration.
IT IS PROCESS OF
DETERMINING
EARTHEN FEATURES AND
RECORDING ITS RELATIVE
POSITION ON TO THE
PAPER
Types of survey
Traverse survey
Triangulation survey
Plane table survey
Which includes:
1. Linear Measurements
2. Angular Measurements
3. Height Measurements
Linear measurements we usually do with:
chain
Tape
Substance bar
EDM (Electronic distance measurement instrument)
GPS (Global Positioning System)
Angular measurements we usually do with:
Compass
Theodolite
Height we usually do with:
Dumpy level
Auto level
Theodolite & Digital leveler
Advantages of Digital levels
◦ Fatigue-free observation as visual staff reading
by the observer is not required.
◦ User friendly menus with easy to read, digital
display of results.
◦ Measurement of consistent precision and
reliability due to automation.
◦ Automatic data storage eliminates booking and
its associated errors.
Automatic reduction of data to produce ground
levels, thereby eliminating arithmetical errors.
◦ Fast, economic surveys resulting in saving in
time (up to 50% less effort has been claimed by
manufacturers)
◦ Data on the storage medium of the level can be
downloaded to a computer enabling quick data
reduction for various purposes.
Digital levels can also be used as conventional
levels with the help of dual marked staff (bar coded
on one side of the staff for automated reading and
conventional graduation on other side of the staff)
in case it is difficult to record readings digitally (e.g.
for long distances).
Capabilities of Digital levels
◦ measuring elevation
◦ measuring height difference
◦ measuring height difference with multiple
instrument positions
◦ levelling
◦ slope setting
◦ setting out with horizontal distance
levelling of ceilings
Total station is a combination of :
EDM
Theodolite
Auto Leveler
Microprocessor with specific memory
Battery/spare
which works about 5 working hours
About 100 models were released till now by
different firms.
Basic components
of
Total station
 Prism reflector:
It is a combination of ranging rod, staff and and
optical cuboidal mirror.
having 2/3 lifts with 5cms interval graduations.
adjustable height from 1.5m to 3.75m.
More number of prisms, will give more accuracy.
•GUN: data screen LCD
eye piece
telescope 24x to 43x
environmental box
microprocessor with memory card of 1 or 2 GB capacity
1MB can store 800 points.
•Tripod: with different material
Aluminum tripod weighs 13 to 14lbs
Wooden tripod will be about 18 lbs.
•Optical and Laser plumb bobs.
•Battery –as an external attachment
with indicators
1.5hours charged battery can work for 3to 5 hours
ACCURACY OF TOTAL STATION
More accuracy can be achieve by :
1. Careful Centering
2. Accurate pointing target
3. Average of multiple points
4. Better optical lense
5. Strong Tripod
6. Verticality of prism pole
1. Angular accuracy is from 1 to 20 Sec.
2. Linear accuracy is from 2mm to 10mm/per KM
3. Different instruments have different accuracy
Angular
Linear
With 1 Prism With 3 prisms
NIKON 1 Sec + 2 mm + 1 mm
LIEKA 1 Sec + 2 mm + 1 mm
SOKKIA 1 Sec 2 mm + 1 mm
Accuracy varies with Price
Distance measure with:
1.Single Prism – up to 2.5 Km
2.Two prisms - 5 to 7 Km
3.Three prisms - 10 to 12 Km
Functions of T.S:
1. It simultaneously measures angles & distances and Record
2. Correcting the measured distance with:
1. Prism constant
2. Atmospheric Pr.
3. Temperature
4. Curvature of earth
5. Refraction correction
3. Computing the point elevation
4. Computing the coordinates of every point
5. Remote elevation measurement
6. Remote distance measurement
7. Area calculations
8. Data Transferring facility from instrument to S/W and S/W
to instrument
9. Format of conversion of units
Application of Total station:
1. Updating mapping
2. Topographic survey
3. Hydrographic survey
4. Cadastral survey
5. Project construction survey
6. Road, Rail Survey
7. Mining survey
Operations involved while using Total Stations
:
1. Establishing the site Datum:
a) Selecting the site Datum
b) Establishing North
2. Setting up the Total station:
a) Placing and leveling Tripod on Datum
b) Placing and leveling the Gun on Tripod
c) Linking the data connector to Gun
3. Data collector options and setting
a) Main menu
b) Basic settings
4. Creating and Operating Job files:
a) Creating a new Job file
b) Opening an existing file
5. Shooting points
a) Identifying the important points to shoot
b) shooting points
c) Shooting additional points
d) Noting the special features
6.Post Processing – Data down loading,conversion
7.Plotting/Map generation.
Computer software packages
The following post processing computer software
packages are in use for various engineering
applications.
1.Arc Pad, arc view, arc info
-conversion from raster to vector form
2.Micro Station - Map generation
3.Erdas – Image processing s/w
4.Surfer, Auto plotter, Civil cad, Pythagarus
– preparation of contours
5. Survey aid – to draw c/s and l/s
The information received is to be analyzed depending
on the users requirement.
Limitations:
1. It is not a Rugged instrument (Sensitive).
2. Prism verticality is questionable.
3. Visibility is must.
4. More Expensive.
5. Requires calibration at every six months.
6. Amount of error is greater at short distances.
7. Height of instrument and prism is to fed.
8. Awareness on battery maintenance.
9. To establish north- compass is required.
SAFETY PRECAUTIONS
1. Focusing directly at the sun, can result - loss of eyesight
on the spot. Use a filter when observing the sun.
2. Never remove the hand grip carelessly. If the grip is
loosely or incompletely attached, the instrument could fall
and may cause a serious injury.
3. Make sure not to short the battery terminals. If these are
shorted, the resulting high current would not only damage
to the battery, but also start a fire.
4. If the instrument or battery comes in contact with water,
wipe it off as quickly as possible and set it in a dry place
for a while. When it is completely dry, put it back in the
case.
5. Never disassemble the instrument, if you find a problem.
Contact the dealer.
HOW TO SUPERVISE THE TOTAL STATION WORK
 Have keen observation on the prism boy’s attitude. When high precision is
required, use the prism tripod, to avoid human error.
 The position of prism shall always be on hard surface instead of soft soil.
 Focusing shall be exactly at the centre of prism, with the help of cross hairs
and prism plate.
 While measuring the instrument height and prism height, enough attention
shall be diverted. Also, have keen observation while entering the above
data.
 Note the location and coordinates of station point and back sight so that
specified intermediate points can be checked at later date.
 Obtain a soft copy of field work raw data from the survey agency so that the
results can be checked at any time.
 Obtain more number of points to get an average.

More Related Content

What's hot

Total station topcon exp procedures
Total station topcon exp proceduresTotal station topcon exp procedures
Total station topcon exp procedures
NAGESH KUMAR GUTURU
 

What's hot (20)

Advance surveying equipments
Advance surveying equipmentsAdvance surveying equipments
Advance surveying equipments
 
Surveying,ADVANCE EQUIPMENT IN SURVEY
Surveying,ADVANCE EQUIPMENT  IN SURVEYSurveying,ADVANCE EQUIPMENT  IN SURVEY
Surveying,ADVANCE EQUIPMENT IN SURVEY
 
EDM ( Electronic distance meter)
EDM ( Electronic distance meter)EDM ( Electronic distance meter)
EDM ( Electronic distance meter)
 
Lecture 1 introdcution to engineering surveying
Lecture 1 introdcution to engineering surveyingLecture 1 introdcution to engineering surveying
Lecture 1 introdcution to engineering surveying
 
9. MORDAN SURVEYING INSTRUMENTS (SUR) 3140601 GTU
9. MORDAN SURVEYING INSTRUMENTS (SUR) 3140601 GTU9. MORDAN SURVEYING INSTRUMENTS (SUR) 3140601 GTU
9. MORDAN SURVEYING INSTRUMENTS (SUR) 3140601 GTU
 
Total Station & GPS
 Total Station & GPS Total Station & GPS
Total Station & GPS
 
Modern surveying techniques
Modern surveying techniquesModern surveying techniques
Modern surveying techniques
 
GPS Surveying
GPS SurveyingGPS Surveying
GPS Surveying
 
Global positioning system_Surveying, Civil Engineering
Global positioning system_Surveying, Civil EngineeringGlobal positioning system_Surveying, Civil Engineering
Global positioning system_Surveying, Civil Engineering
 
Aerial photogrammetry ppt 1
Aerial photogrammetry ppt 1Aerial photogrammetry ppt 1
Aerial photogrammetry ppt 1
 
Total station
Total stationTotal station
Total station
 
Tacheometric surveying ppt
Tacheometric surveying pptTacheometric surveying ppt
Tacheometric surveying ppt
 
EDM
EDMEDM
EDM
 
Gps
GpsGps
Gps
 
Total station
Total stationTotal station
Total station
 
Modern Surveying
Modern Surveying Modern Surveying
Modern Surveying
 
Total Station surveying
Total Station surveyingTotal Station surveying
Total Station surveying
 
Total station topcon exp procedures
Total station topcon exp proceduresTotal station topcon exp procedures
Total station topcon exp procedures
 
Levelling, terms related to levelling, methods of levelling
Levelling, terms related to levelling, methods of levellingLevelling, terms related to levelling, methods of levelling
Levelling, terms related to levelling, methods of levelling
 
Theodolite Surveying
Theodolite Surveying Theodolite Surveying
Theodolite Surveying
 

Similar to Total station

Similar to Total station (20)

Tot.st 1
Tot.st 1Tot.st 1
Tot.st 1
 
Tot.st 1
Tot.st 1Tot.st 1
Tot.st 1
 
Total Station by Denis Jangeed.pdf
Total Station by Denis Jangeed.pdfTotal Station by Denis Jangeed.pdf
Total Station by Denis Jangeed.pdf
 
Total station
Total stationTotal station
Total station
 
Total station .pdf
Total station .pdfTotal station .pdf
Total station .pdf
 
MODERN SURVEYING TECHNIQUES.pptx
 MODERN SURVEYING TECHNIQUES.pptx MODERN SURVEYING TECHNIQUES.pptx
MODERN SURVEYING TECHNIQUES.pptx
 
TOTAL STATION: THEORY, USES AND APPLICATIONS.
TOTAL STATION: THEORY, USES AND APPLICATIONS. TOTAL STATION: THEORY, USES AND APPLICATIONS.
TOTAL STATION: THEORY, USES AND APPLICATIONS.
 
MM-UNIT-V.pptx
MM-UNIT-V.pptxMM-UNIT-V.pptx
MM-UNIT-V.pptx
 
UNIT-V.pptx
UNIT-V.pptxUNIT-V.pptx
UNIT-V.pptx
 
total station topo III.pptx
total station topo III.pptxtotal station topo III.pptx
total station topo III.pptx
 
Total station .pptx
Total station .pptxTotal station .pptx
Total station .pptx
 
Total station For Btech Engineering Students
Total station For Btech Engineering StudentsTotal station For Btech Engineering Students
Total station For Btech Engineering Students
 
group-3-a21-traverse-report.pdf
group-3-a21-traverse-report.pdfgroup-3-a21-traverse-report.pdf
group-3-a21-traverse-report.pdf
 
Total station surveying and its application
Total station surveying and its applicationTotal station surveying and its application
Total station surveying and its application
 
UNIT 3.ppt
UNIT 3.pptUNIT 3.ppt
UNIT 3.ppt
 
Civil survey camp traning report file 2018 git jaipur (8741828148)
Civil survey camp traning report file 2018 git jaipur (8741828148)Civil survey camp traning report file 2018 git jaipur (8741828148)
Civil survey camp traning report file 2018 git jaipur (8741828148)
 
Advanced surveying equipment ppt
Advanced surveying equipment pptAdvanced surveying equipment ppt
Advanced surveying equipment ppt
 
DATA LOGGER
DATA LOGGER DATA LOGGER
DATA LOGGER
 
Modern Survey Techniques
Modern Survey TechniquesModern Survey Techniques
Modern Survey Techniques
 
Lecture-5-gamma-cameras.pdf
Lecture-5-gamma-cameras.pdfLecture-5-gamma-cameras.pdf
Lecture-5-gamma-cameras.pdf
 

Recently uploaded

Introduction to Robotics in Mechanical Engineering.pptx
Introduction to Robotics in Mechanical Engineering.pptxIntroduction to Robotics in Mechanical Engineering.pptx
Introduction to Robotics in Mechanical Engineering.pptx
hublikarsn
 
"Lesotho Leaps Forward: A Chronicle of Transformative Developments"
"Lesotho Leaps Forward: A Chronicle of Transformative Developments""Lesotho Leaps Forward: A Chronicle of Transformative Developments"
"Lesotho Leaps Forward: A Chronicle of Transformative Developments"
mphochane1998
 
Standard vs Custom Battery Packs - Decoding the Power Play
Standard vs Custom Battery Packs - Decoding the Power PlayStandard vs Custom Battery Packs - Decoding the Power Play
Standard vs Custom Battery Packs - Decoding the Power Play
Epec Engineered Technologies
 
Cara Menggugurkan Sperma Yang Masuk Rahim Biyar Tidak Hamil
Cara Menggugurkan Sperma Yang Masuk Rahim Biyar Tidak HamilCara Menggugurkan Sperma Yang Masuk Rahim Biyar Tidak Hamil
Cara Menggugurkan Sperma Yang Masuk Rahim Biyar Tidak Hamil
Cara Menggugurkan Kandungan 087776558899
 

Recently uploaded (20)

Augmented Reality (AR) with Augin Software.pptx
Augmented Reality (AR) with Augin Software.pptxAugmented Reality (AR) with Augin Software.pptx
Augmented Reality (AR) with Augin Software.pptx
 
PE 459 LECTURE 2- natural gas basic concepts and properties
PE 459 LECTURE 2- natural gas basic concepts and propertiesPE 459 LECTURE 2- natural gas basic concepts and properties
PE 459 LECTURE 2- natural gas basic concepts and properties
 
Introduction to Robotics in Mechanical Engineering.pptx
Introduction to Robotics in Mechanical Engineering.pptxIntroduction to Robotics in Mechanical Engineering.pptx
Introduction to Robotics in Mechanical Engineering.pptx
 
Ground Improvement Technique: Earth Reinforcement
Ground Improvement Technique: Earth ReinforcementGround Improvement Technique: Earth Reinforcement
Ground Improvement Technique: Earth Reinforcement
 
School management system project Report.pdf
School management system project Report.pdfSchool management system project Report.pdf
School management system project Report.pdf
 
"Lesotho Leaps Forward: A Chronicle of Transformative Developments"
"Lesotho Leaps Forward: A Chronicle of Transformative Developments""Lesotho Leaps Forward: A Chronicle of Transformative Developments"
"Lesotho Leaps Forward: A Chronicle of Transformative Developments"
 
Path loss model, OKUMURA Model, Hata Model
Path loss model, OKUMURA Model, Hata ModelPath loss model, OKUMURA Model, Hata Model
Path loss model, OKUMURA Model, Hata Model
 
8th International Conference on Soft Computing, Mathematics and Control (SMC ...
8th International Conference on Soft Computing, Mathematics and Control (SMC ...8th International Conference on Soft Computing, Mathematics and Control (SMC ...
8th International Conference on Soft Computing, Mathematics and Control (SMC ...
 
Linux Systems Programming: Inter Process Communication (IPC) using Pipes
Linux Systems Programming: Inter Process Communication (IPC) using PipesLinux Systems Programming: Inter Process Communication (IPC) using Pipes
Linux Systems Programming: Inter Process Communication (IPC) using Pipes
 
Convergence of Robotics and Gen AI offers excellent opportunities for Entrepr...
Convergence of Robotics and Gen AI offers excellent opportunities for Entrepr...Convergence of Robotics and Gen AI offers excellent opportunities for Entrepr...
Convergence of Robotics and Gen AI offers excellent opportunities for Entrepr...
 
Max. shear stress theory-Maximum Shear Stress Theory ​ Maximum Distortional ...
Max. shear stress theory-Maximum Shear Stress Theory ​  Maximum Distortional ...Max. shear stress theory-Maximum Shear Stress Theory ​  Maximum Distortional ...
Max. shear stress theory-Maximum Shear Stress Theory ​ Maximum Distortional ...
 
fitting shop and tools used in fitting shop .ppt
fitting shop and tools used in fitting shop .pptfitting shop and tools used in fitting shop .ppt
fitting shop and tools used in fitting shop .ppt
 
AIRCANVAS[1].pdf mini project for btech students
AIRCANVAS[1].pdf mini project for btech studentsAIRCANVAS[1].pdf mini project for btech students
AIRCANVAS[1].pdf mini project for btech students
 
8086 Microprocessor Architecture: 16-bit microprocessor
8086 Microprocessor Architecture: 16-bit microprocessor8086 Microprocessor Architecture: 16-bit microprocessor
8086 Microprocessor Architecture: 16-bit microprocessor
 
Introduction to Data Visualization,Matplotlib.pdf
Introduction to Data Visualization,Matplotlib.pdfIntroduction to Data Visualization,Matplotlib.pdf
Introduction to Data Visualization,Matplotlib.pdf
 
NO1 Top No1 Amil Baba In Azad Kashmir, Kashmir Black Magic Specialist Expert ...
NO1 Top No1 Amil Baba In Azad Kashmir, Kashmir Black Magic Specialist Expert ...NO1 Top No1 Amil Baba In Azad Kashmir, Kashmir Black Magic Specialist Expert ...
NO1 Top No1 Amil Baba In Azad Kashmir, Kashmir Black Magic Specialist Expert ...
 
Standard vs Custom Battery Packs - Decoding the Power Play
Standard vs Custom Battery Packs - Decoding the Power PlayStandard vs Custom Battery Packs - Decoding the Power Play
Standard vs Custom Battery Packs - Decoding the Power Play
 
Theory of Time 2024 (Universal Theory for Everything)
Theory of Time 2024 (Universal Theory for Everything)Theory of Time 2024 (Universal Theory for Everything)
Theory of Time 2024 (Universal Theory for Everything)
 
Cara Menggugurkan Sperma Yang Masuk Rahim Biyar Tidak Hamil
Cara Menggugurkan Sperma Yang Masuk Rahim Biyar Tidak HamilCara Menggugurkan Sperma Yang Masuk Rahim Biyar Tidak Hamil
Cara Menggugurkan Sperma Yang Masuk Rahim Biyar Tidak Hamil
 
Worksharing and 3D Modeling with Revit.pptx
Worksharing and 3D Modeling with Revit.pptxWorksharing and 3D Modeling with Revit.pptx
Worksharing and 3D Modeling with Revit.pptx
 

Total station

  • 1. Total Station Mr. Momin Umarfarook H. ( B.E Civil , M.E Structure)
  • 2. First question:How do you measure a distance of 30cm ? What tools would you use ? Ruler Steel tape
  • 3. Hans Lippershey, a boss of eyeglasses store in Holand. He invented the telescope in seventeen century . From then on , the method of measurement on a new level.
  • 4. Theodore Harold Maiman , an American physical scientist , was invented the first laser in the world .
  • 5. Basic Principle Classifications – Electro optical system – measuring principle – working principle, Sources of Error – Infrared and Laser total station Instruments. Microwave system , measuring principle, working principle, sources of Errors, Microwave total station instruments,comparision between Electro optical and Microwave system. Care and maintenance of total station Instruments, Modern positioning systems , Traversing and Trilateration.
  • 6.
  • 7.
  • 8. IT IS PROCESS OF DETERMINING EARTHEN FEATURES AND RECORDING ITS RELATIVE POSITION ON TO THE PAPER
  • 9. Types of survey Traverse survey Triangulation survey Plane table survey Which includes: 1. Linear Measurements 2. Angular Measurements 3. Height Measurements
  • 10. Linear measurements we usually do with: chain Tape Substance bar EDM (Electronic distance measurement instrument) GPS (Global Positioning System) Angular measurements we usually do with: Compass Theodolite Height we usually do with: Dumpy level Auto level Theodolite & Digital leveler
  • 11. Advantages of Digital levels ◦ Fatigue-free observation as visual staff reading by the observer is not required. ◦ User friendly menus with easy to read, digital display of results. ◦ Measurement of consistent precision and reliability due to automation. ◦ Automatic data storage eliminates booking and its associated errors. Automatic reduction of data to produce ground levels, thereby eliminating arithmetical errors.
  • 12. ◦ Fast, economic surveys resulting in saving in time (up to 50% less effort has been claimed by manufacturers) ◦ Data on the storage medium of the level can be downloaded to a computer enabling quick data reduction for various purposes. Digital levels can also be used as conventional levels with the help of dual marked staff (bar coded on one side of the staff for automated reading and conventional graduation on other side of the staff) in case it is difficult to record readings digitally (e.g. for long distances).
  • 13. Capabilities of Digital levels ◦ measuring elevation ◦ measuring height difference ◦ measuring height difference with multiple instrument positions ◦ levelling ◦ slope setting ◦ setting out with horizontal distance levelling of ceilings
  • 14. Total station is a combination of : EDM Theodolite Auto Leveler Microprocessor with specific memory Battery/spare which works about 5 working hours About 100 models were released till now by different firms.
  • 15. Basic components of Total station  Prism reflector: It is a combination of ranging rod, staff and and optical cuboidal mirror. having 2/3 lifts with 5cms interval graduations. adjustable height from 1.5m to 3.75m. More number of prisms, will give more accuracy.
  • 16. •GUN: data screen LCD eye piece telescope 24x to 43x environmental box microprocessor with memory card of 1 or 2 GB capacity 1MB can store 800 points. •Tripod: with different material Aluminum tripod weighs 13 to 14lbs Wooden tripod will be about 18 lbs. •Optical and Laser plumb bobs. •Battery –as an external attachment with indicators 1.5hours charged battery can work for 3to 5 hours
  • 17. ACCURACY OF TOTAL STATION More accuracy can be achieve by : 1. Careful Centering 2. Accurate pointing target 3. Average of multiple points 4. Better optical lense 5. Strong Tripod 6. Verticality of prism pole 1. Angular accuracy is from 1 to 20 Sec. 2. Linear accuracy is from 2mm to 10mm/per KM 3. Different instruments have different accuracy Angular Linear With 1 Prism With 3 prisms NIKON 1 Sec + 2 mm + 1 mm LIEKA 1 Sec + 2 mm + 1 mm SOKKIA 1 Sec 2 mm + 1 mm Accuracy varies with Price Distance measure with: 1.Single Prism – up to 2.5 Km 2.Two prisms - 5 to 7 Km 3.Three prisms - 10 to 12 Km
  • 18. Functions of T.S: 1. It simultaneously measures angles & distances and Record 2. Correcting the measured distance with: 1. Prism constant 2. Atmospheric Pr. 3. Temperature 4. Curvature of earth 5. Refraction correction 3. Computing the point elevation 4. Computing the coordinates of every point 5. Remote elevation measurement 6. Remote distance measurement 7. Area calculations 8. Data Transferring facility from instrument to S/W and S/W to instrument 9. Format of conversion of units
  • 19. Application of Total station: 1. Updating mapping 2. Topographic survey 3. Hydrographic survey 4. Cadastral survey 5. Project construction survey 6. Road, Rail Survey 7. Mining survey
  • 20. Operations involved while using Total Stations : 1. Establishing the site Datum: a) Selecting the site Datum b) Establishing North 2. Setting up the Total station: a) Placing and leveling Tripod on Datum b) Placing and leveling the Gun on Tripod c) Linking the data connector to Gun 3. Data collector options and setting a) Main menu b) Basic settings
  • 21. 4. Creating and Operating Job files: a) Creating a new Job file b) Opening an existing file 5. Shooting points a) Identifying the important points to shoot b) shooting points c) Shooting additional points d) Noting the special features 6.Post Processing – Data down loading,conversion 7.Plotting/Map generation.
  • 22. Computer software packages The following post processing computer software packages are in use for various engineering applications. 1.Arc Pad, arc view, arc info -conversion from raster to vector form 2.Micro Station - Map generation 3.Erdas – Image processing s/w 4.Surfer, Auto plotter, Civil cad, Pythagarus – preparation of contours 5. Survey aid – to draw c/s and l/s The information received is to be analyzed depending on the users requirement.
  • 23. Limitations: 1. It is not a Rugged instrument (Sensitive). 2. Prism verticality is questionable. 3. Visibility is must. 4. More Expensive. 5. Requires calibration at every six months. 6. Amount of error is greater at short distances. 7. Height of instrument and prism is to fed. 8. Awareness on battery maintenance. 9. To establish north- compass is required.
  • 24. SAFETY PRECAUTIONS 1. Focusing directly at the sun, can result - loss of eyesight on the spot. Use a filter when observing the sun. 2. Never remove the hand grip carelessly. If the grip is loosely or incompletely attached, the instrument could fall and may cause a serious injury. 3. Make sure not to short the battery terminals. If these are shorted, the resulting high current would not only damage to the battery, but also start a fire. 4. If the instrument or battery comes in contact with water, wipe it off as quickly as possible and set it in a dry place for a while. When it is completely dry, put it back in the case. 5. Never disassemble the instrument, if you find a problem. Contact the dealer.
  • 25. HOW TO SUPERVISE THE TOTAL STATION WORK  Have keen observation on the prism boy’s attitude. When high precision is required, use the prism tripod, to avoid human error.  The position of prism shall always be on hard surface instead of soft soil.  Focusing shall be exactly at the centre of prism, with the help of cross hairs and prism plate.  While measuring the instrument height and prism height, enough attention shall be diverted. Also, have keen observation while entering the above data.  Note the location and coordinates of station point and back sight so that specified intermediate points can be checked at later date.  Obtain a soft copy of field work raw data from the survey agency so that the results can be checked at any time.  Obtain more number of points to get an average.