SlideShare a Scribd company logo
Insulation co-ordination design
details
S. Naresh Ram
NRLDC
POSOCO
Why we need Arrestors ?
The arresters are designed for the worst case of 3-phase ground fault followed by the recovery saturation over
voltages.
This fault case gives the highest energy duty for the arrester
• MCOV (Maximum Continuous Operating Voltage)
The MCOV for equipment on the ac side of the converter station is the highest r.m.s. value, including harmonics, of the
sinusoidal voltage applied at the terminals of the equipment.
• CCOV (Crest value of the Continuous Operating Voltage)
The CCOV for equipment on the dc side of the converter station, stressed by a voltage with or without commutation
overshoots, is the highest continuous crest value of the voltage excluding commutation overshoots.
Both designations MCOV and CCOV will be used in order to describe the arrester operating voltage.
Why we need SIWL ?
• Ans Load Rejection / Re-energization 1kA<Icharg<3kA; Convertor commutation overshoots during TOV conditions
The SIWL(Switching Impulse Withstand Level) shall, in any case, not be below 1050 kV for all AC-side equipment( Voltage
wave front 50/2500 micro sec; Current wave front 36/90 micro sec)
Why we need LIWL ?
Ans Since Switchyard shielding limits direct strikes <20kA; Back flashover on first tower outside switchyard
The LIWL(Lightning Impulse withstand level) for circuit breakers, bushings and other equipment shall not be below
1425 kV (Voltage wave front 1.2/50 micro se; Current wave front 8/20 micro sec)
Basic Definitions
• Reasons for Switching Impulse:-
Circuit breaker operation; Protective Switching Equipment Energisation; Load Rejections;
Convertor switching transients
Reasons for Lightning Impulse:-
• Direct lightning stroke to line - rare on shielded systems
• Back flashover - lightning strikes pylon shield wires
Reasons FOW (Front of Wave) Impulse
(Current wave front: 1/2 micro sec )
Bushing flashovers within valve hall, causing discharge of stray capacitances through relatively
short lengths
of conductor.
LIWL= 1.4 times SIPL (Protection Level)
= 1.2 times LIPL (Protection Level)
• The SIWL shall not be less than 0.83 times the LIWL, nor below 1050 kV for
equipment connected to the 400 kV AC-bus
AC side fault of PMU plot
R phase to Earth fault; A/R attempted
but Un successfull
Over shoot in other phases
Commutation failure PMU plot
Transient Over Voltage , Due
to HVDC restart attempts
AC and DC side Arrestors
Arresters on AC side are
usually specified by their rated
voltage and maximum
continuous operating voltage
Peak value of voltage between
phase conductor &
earth or between phase conductors having
highest system voltage peak.
Arrestors on DC side rated voltage is
not defined and continuous
operating voltage is defined
differently.
PCOV (Peak Continuous Operating Voltage)
Typical Voltage Wave shapes at
various Locations
Voltage 12 pulse
The starting point of the insulation co-
ordination process within the valve hall
is the rating of the valve surge arrester
(V) by balancing continuous energy
absorption against protective level.
Arrestors
discharging
currents
Ground fault between valve and HV-bushing of
converter transformer during rectifier operation.
In this case the valve arresters type 'V1' protecting the 3-
pulse commutation group on the HV side,
could be stressed with high currents and energies.
This is due to the fact that the DC- current
on the faulted pole will go to zero, which corresponds to
a load rejection.
During this time these arresters will discharge the DC-
line through the smoothing reactor and converter
transformer.
This fault will be cleared by tripping the ac circuit
breakersCCOV= Transformer secondary
voltage * 1.414
For HVDC 500kV 1000MW ;
Type of
Arrestors
Max. voltage
across arrester
(SIPL)
SIWL Max.
energy
dissipated
in
arrester
V1 491 kV at 1.2
kA
1.15*491 2.12MJ
V2 495 at 1.05 1.15*495 0.54MJ
The highest stresses are expected if the transferred
switching surge appears between the phases
(e.g. R & Y), where only one valve of the involved phases is
conducting
R
Y
B
Designing criteria of Valve hall Surge arrestor
Arrestors
discharging
currents
Simulated result of fault For
HVDC 500kV 1000MW ;
R
Y
B
Stresses of Valve Arrester "V1" during
Ground Fault at Transformer Bushing,
rectifier
operation
1.2KA
Around 2MJ
Around 500KV
AC Side Arrestors
AC System consists of parallel connected
circuits and apart from some special cases the
requirement is to establish the insulation level
bet. phase to earth and phase to phase level
• SIWL at least 1.15 times the SIPL
• LIWL at least 1.25 times the SIPL
• FWWL at least 1.25 times the FWPL
Converter transformer:-A,A2 ( Max energy ,
generally used at Bus; whose fault current heavy)
valve side of the Yy transformer windings:- A2
• Max. voltage across arrester „A“ = 610 kV at 2 kA
• Max. energy dissipated in arrester „A“ = 3.3 MJ
• AC Filter Banks:- AA (For slower front time
surges the arrester type 'AA' energy is sharedwith
the converter transformer arrester type ‘A’)
AC-filters:- F ac
DC Side Arrestors
HVDC converter stations on the other hand consist of
series connected bridges, each bridge requiring a
different insulation strength to earth and within each
bridge the electric strength is different for the
various components
• SIWL at least 1.20 times the SIPL.
• LIWL at least 1.25 times the SIPL.
• FWWL at least 1.25 times the FWPL
12-pulse valve group:- C
Dc smoothing reactor :- D
DC-line :- D
DC-filters:- Fdc
12-pulse group and on the neutral line :- E
Thyristor valves connected to HV-side of the smoothing
reactor:- V1
Other Thyristors:- V2
Different types of Arrestors for different application
Type of
Arrestors
MCOV (in KV) CCOV SIPL (KV at
KA)
LIPL (KV at
KA)
Energy (KJ)
A 440/ 3 - 610 @2 714@20 6000
AA
(Filter)
440/ 3
- 610 @1.3 1 714@13.3
A2( 500KV
HVDC)
Transformer
secondary
voltage YY
(valve side)
530 946@1 1065@5 3200
A3 (500KV
HVDC)
Transformer
secondary
voltage YD
(valve side)
308 527@1 595@4 1800
For 400kV AC Station
(1) The coordinating current for switching surges for the AA arrester, which has the same protective level as the A arrester
is chosen to 2kA x 2/3 » 1.3kA, because the AA arrester consists of only 2 columns per arrester housing
Coordination with AC Line Arresters
The characteristics of the surge arresters connected to the 400 kV ac lines
• Rated arrester voltage: 390 kV
• Min. Switching Surge residual voltage (at 1 kA): 730 kV
• Max. Switching Surge residual voltage (at 1 kA): 780 kV
• Max. residual voltage / lightning surge (at 10 kA): 900 kV
• Max. residual voltage / lightning surge (at 20 kA): 975 kV
Switching Surge Protective Level Type 'A'/'AA': 610 kV at 2/1.3 kA.
Assuming minimum arrester characteristic of the ac line arresters and maximum
characteristic of the type 'A'/'AA' arrester it can be concluded that a minimum margin
(730 kV - 610 kV) / 610 kV = 19.7 % exists.
This margin is fully adequate to avoid any overstressing of the parallel connected 400 kV ac
line arresters.
Typically, a margin of >10% can be assumed to be sufficient
4m
3.5m
Minimum Air clearance; Phase to Ground=3.5m; Phase to phase= 4m.

More Related Content

What's hot

Le.h insulation coordination - Digsilent
Le.h insulation coordination - DigsilentLe.h insulation coordination - Digsilent
Le.h insulation coordination - Digsilent
Gilberto Mejía
 
Surge Arresters construction and working
Surge Arresters construction and workingSurge Arresters construction and working
Surge Arresters construction and working
Muhammad Faisal Ikram
 
Electrical testing
Electrical testingElectrical testing
Electrical testing
Aarjun Singh Panesar
 
surge arrester
surge arrestersurge arrester
surge arrester
shubham kumar
 
Generator grounding
Generator groundingGenerator grounding
Generator grounding
michaeljmack
 
Earthing Arrangements
Earthing  ArrangementsEarthing  Arrangements
Earthing ArrangementsPaul Holden
 
Vignettes in Grounding
Vignettes in GroundingVignettes in Grounding
Vignettes in Grounding
michaeljmack
 
Electrical Systems Safety
Electrical Systems SafetyElectrical Systems Safety
Electrical Systems SafetyTalia Carbis
 
Guide to Surge Protection Devices
Guide to Surge Protection DevicesGuide to Surge Protection Devices
Guide to Surge Protection Devices
Jason Koffler
 
Using High Resistance Grounding to Mitigate Arc Flash Hazards
Using High Resistance Grounding to Mitigate Arc Flash HazardsUsing High Resistance Grounding to Mitigate Arc Flash Hazards
Using High Resistance Grounding to Mitigate Arc Flash Hazards
michaeljmack
 
Protection against over voltage
Protection against over voltageProtection against over voltage
Protection against over voltage
MuhammedArifTanoli
 
Overview of Grounding for Industrial and Commercial Power Systems
Overview of Grounding for Industrial and Commercial Power SystemsOverview of Grounding for Industrial and Commercial Power Systems
Overview of Grounding for Industrial and Commercial Power Systems
michaeljmack
 
Behaviour of ZnO surge arrester in pollution
Behaviour of ZnO surge arrester in pollutionBehaviour of ZnO surge arrester in pollution
Behaviour of ZnO surge arrester in pollution
Mukesh Kumar Tanwar
 
Over voltage(Switch Gear and Protection)
Over voltage(Switch Gear and Protection)Over voltage(Switch Gear and Protection)
Over voltage(Switch Gear and Protection)
Jaydeep Chauhan
 
Application Considerations for Power System Grounding
Application Considerations for Power System GroundingApplication Considerations for Power System Grounding
Application Considerations for Power System Grounding
michaeljmack
 
Energy crisis and conservation
Energy crisis and conservationEnergy crisis and conservation
Energy crisis and conservationKrunal Gaigole
 
Surge arrester ppt
Surge arrester pptSurge arrester ppt
Surge arrester ppt
IrinElsa
 
study of lightning arrester
study of lightning arresterstudy of lightning arrester
study of lightning arrester
Malikasad thaheem
 

What's hot (20)

Le.h insulation coordination - Digsilent
Le.h insulation coordination - DigsilentLe.h insulation coordination - Digsilent
Le.h insulation coordination - Digsilent
 
Surge Arresters construction and working
Surge Arresters construction and workingSurge Arresters construction and working
Surge Arresters construction and working
 
Electrical testing
Electrical testingElectrical testing
Electrical testing
 
surge arrester
surge arrestersurge arrester
surge arrester
 
Generator grounding
Generator groundingGenerator grounding
Generator grounding
 
Earthing Arrangements
Earthing  ArrangementsEarthing  Arrangements
Earthing Arrangements
 
Vignettes in Grounding
Vignettes in GroundingVignettes in Grounding
Vignettes in Grounding
 
Electrical Systems Safety
Electrical Systems SafetyElectrical Systems Safety
Electrical Systems Safety
 
Guide to Surge Protection Devices
Guide to Surge Protection DevicesGuide to Surge Protection Devices
Guide to Surge Protection Devices
 
Using High Resistance Grounding to Mitigate Arc Flash Hazards
Using High Resistance Grounding to Mitigate Arc Flash HazardsUsing High Resistance Grounding to Mitigate Arc Flash Hazards
Using High Resistance Grounding to Mitigate Arc Flash Hazards
 
Lighting arrester
Lighting arresterLighting arrester
Lighting arrester
 
Aresster
AressterAresster
Aresster
 
Protection against over voltage
Protection against over voltageProtection against over voltage
Protection against over voltage
 
Overview of Grounding for Industrial and Commercial Power Systems
Overview of Grounding for Industrial and Commercial Power SystemsOverview of Grounding for Industrial and Commercial Power Systems
Overview of Grounding for Industrial and Commercial Power Systems
 
Behaviour of ZnO surge arrester in pollution
Behaviour of ZnO surge arrester in pollutionBehaviour of ZnO surge arrester in pollution
Behaviour of ZnO surge arrester in pollution
 
Over voltage(Switch Gear and Protection)
Over voltage(Switch Gear and Protection)Over voltage(Switch Gear and Protection)
Over voltage(Switch Gear and Protection)
 
Application Considerations for Power System Grounding
Application Considerations for Power System GroundingApplication Considerations for Power System Grounding
Application Considerations for Power System Grounding
 
Energy crisis and conservation
Energy crisis and conservationEnergy crisis and conservation
Energy crisis and conservation
 
Surge arrester ppt
Surge arrester pptSurge arrester ppt
Surge arrester ppt
 
study of lightning arrester
study of lightning arresterstudy of lightning arrester
study of lightning arrester
 

Similar to Insulation co cordination design

Pamphlet on important psi parameters rdso
Pamphlet on important psi parameters rdsoPamphlet on important psi parameters rdso
Pamphlet on important psi parameters rdso
sonu200186
 
Introduction to mv switchgear
Introduction to mv switchgearIntroduction to mv switchgear
Introduction to mv switchgear
Modal Holong Education
 
Reactors
ReactorsReactors
Reactors
Molla Morshad
 
Original Transistor NPN MJE13003 KSE13003 E13003 13003 1.5A 400V TO-126 New
Original Transistor NPN MJE13003 KSE13003 E13003 13003 1.5A 400V TO-126 NewOriginal Transistor NPN MJE13003 KSE13003 E13003 13003 1.5A 400V TO-126 New
Original Transistor NPN MJE13003 KSE13003 E13003 13003 1.5A 400V TO-126 New
AUTHELECTRONIC
 
GENERATION OF HVDC 17.8.16 (2).ppt
GENERATION OF HVDC  17.8.16 (2).pptGENERATION OF HVDC  17.8.16 (2).ppt
GENERATION OF HVDC 17.8.16 (2).ppt
ssuser4b87fd
 
presentation_transformers_1489551826_236516.ppt
presentation_transformers_1489551826_236516.pptpresentation_transformers_1489551826_236516.ppt
presentation_transformers_1489551826_236516.ppt
KrishnaBhalerao2
 
Transformer basic
Transformer basicTransformer basic
Transformer basic
BHAGWAN PRASAD
 
Power Distribution Report of THE NEOTIA UNIVERSITY CAMPUS
Power Distribution Report of  THE NEOTIA UNIVERSITY CAMPUSPower Distribution Report of  THE NEOTIA UNIVERSITY CAMPUS
Power Distribution Report of THE NEOTIA UNIVERSITY CAMPUS
Saikat Bhandari
 
Switchgear & Rectifier ppt
Switchgear & Rectifier pptSwitchgear & Rectifier ppt
Switchgear & Rectifier ppt
vikas kumar
 
Installation testing and_commissioning_o (1)
Installation testing and_commissioning_o (1)Installation testing and_commissioning_o (1)
Installation testing and_commissioning_o (1)
FunExplode
 
Transformers.ppt
Transformers.pptTransformers.ppt
Transformers.ppt
aditya40570
 
C.S.P.D.C.L.AMBIKAPUR (TOWN)
C.S.P.D.C.L.AMBIKAPUR (TOWN)C.S.P.D.C.L.AMBIKAPUR (TOWN)
C.S.P.D.C.L.AMBIKAPUR (TOWN)saurabhVEC
 
Deltatron or Engetron
Deltatron or EngetronDeltatron or Engetron
Deltatron or Engetron
Abdul Rahman Ibrahim
 
industrial training on 132 kv substation
industrial training on 132 kv substationindustrial training on 132 kv substation
industrial training on 132 kv substation
pk130992
 
Mit ppt 132/33kv ppt
Mit ppt 132/33kv pptMit ppt 132/33kv ppt
Mit ppt 132/33kv ppt
Mithilesh Kumar
 
Introduction to power transformers
Introduction to power transformersIntroduction to power transformers
Introduction to power transformers
Leonardo ENERGY
 
Aec manual for III SEM ECE Students VTU
Aec manual for III SEM ECE Students VTUAec manual for III SEM ECE Students VTU
Aec manual for III SEM ECE Students VTU
Gopal Krishna Murthy C R
 
Sub station training
Sub station trainingSub station training
Sub station training
Durga Prasad, IES
 
HVE UNIT III GENERATION OF HIGH VOLTAGES AND HIGH CURRENTS.pptx
HVE UNIT III  GENERATION OF HIGH VOLTAGES AND HIGH CURRENTS.pptxHVE UNIT III  GENERATION OF HIGH VOLTAGES AND HIGH CURRENTS.pptx
HVE UNIT III GENERATION OF HIGH VOLTAGES AND HIGH CURRENTS.pptx
MuthuKumar158260
 
fdocuments.in_presentation-on-substation-220-kv.pptx
fdocuments.in_presentation-on-substation-220-kv.pptxfdocuments.in_presentation-on-substation-220-kv.pptx
fdocuments.in_presentation-on-substation-220-kv.pptx
AkshaiSai2
 

Similar to Insulation co cordination design (20)

Pamphlet on important psi parameters rdso
Pamphlet on important psi parameters rdsoPamphlet on important psi parameters rdso
Pamphlet on important psi parameters rdso
 
Introduction to mv switchgear
Introduction to mv switchgearIntroduction to mv switchgear
Introduction to mv switchgear
 
Reactors
ReactorsReactors
Reactors
 
Original Transistor NPN MJE13003 KSE13003 E13003 13003 1.5A 400V TO-126 New
Original Transistor NPN MJE13003 KSE13003 E13003 13003 1.5A 400V TO-126 NewOriginal Transistor NPN MJE13003 KSE13003 E13003 13003 1.5A 400V TO-126 New
Original Transistor NPN MJE13003 KSE13003 E13003 13003 1.5A 400V TO-126 New
 
GENERATION OF HVDC 17.8.16 (2).ppt
GENERATION OF HVDC  17.8.16 (2).pptGENERATION OF HVDC  17.8.16 (2).ppt
GENERATION OF HVDC 17.8.16 (2).ppt
 
presentation_transformers_1489551826_236516.ppt
presentation_transformers_1489551826_236516.pptpresentation_transformers_1489551826_236516.ppt
presentation_transformers_1489551826_236516.ppt
 
Transformer basic
Transformer basicTransformer basic
Transformer basic
 
Power Distribution Report of THE NEOTIA UNIVERSITY CAMPUS
Power Distribution Report of  THE NEOTIA UNIVERSITY CAMPUSPower Distribution Report of  THE NEOTIA UNIVERSITY CAMPUS
Power Distribution Report of THE NEOTIA UNIVERSITY CAMPUS
 
Switchgear & Rectifier ppt
Switchgear & Rectifier pptSwitchgear & Rectifier ppt
Switchgear & Rectifier ppt
 
Installation testing and_commissioning_o (1)
Installation testing and_commissioning_o (1)Installation testing and_commissioning_o (1)
Installation testing and_commissioning_o (1)
 
Transformers.ppt
Transformers.pptTransformers.ppt
Transformers.ppt
 
C.S.P.D.C.L.AMBIKAPUR (TOWN)
C.S.P.D.C.L.AMBIKAPUR (TOWN)C.S.P.D.C.L.AMBIKAPUR (TOWN)
C.S.P.D.C.L.AMBIKAPUR (TOWN)
 
Deltatron or Engetron
Deltatron or EngetronDeltatron or Engetron
Deltatron or Engetron
 
industrial training on 132 kv substation
industrial training on 132 kv substationindustrial training on 132 kv substation
industrial training on 132 kv substation
 
Mit ppt 132/33kv ppt
Mit ppt 132/33kv pptMit ppt 132/33kv ppt
Mit ppt 132/33kv ppt
 
Introduction to power transformers
Introduction to power transformersIntroduction to power transformers
Introduction to power transformers
 
Aec manual for III SEM ECE Students VTU
Aec manual for III SEM ECE Students VTUAec manual for III SEM ECE Students VTU
Aec manual for III SEM ECE Students VTU
 
Sub station training
Sub station trainingSub station training
Sub station training
 
HVE UNIT III GENERATION OF HIGH VOLTAGES AND HIGH CURRENTS.pptx
HVE UNIT III  GENERATION OF HIGH VOLTAGES AND HIGH CURRENTS.pptxHVE UNIT III  GENERATION OF HIGH VOLTAGES AND HIGH CURRENTS.pptx
HVE UNIT III GENERATION OF HIGH VOLTAGES AND HIGH CURRENTS.pptx
 
fdocuments.in_presentation-on-substation-220-kv.pptx
fdocuments.in_presentation-on-substation-220-kv.pptxfdocuments.in_presentation-on-substation-220-kv.pptx
fdocuments.in_presentation-on-substation-220-kv.pptx
 

Recently uploaded

Modelagem de um CSTR com reação endotermica.pdf
Modelagem de um CSTR com reação endotermica.pdfModelagem de um CSTR com reação endotermica.pdf
Modelagem de um CSTR com reação endotermica.pdf
camseq
 
Design and Analysis of Algorithms-DP,Backtracking,Graphs,B&B
Design and Analysis of Algorithms-DP,Backtracking,Graphs,B&BDesign and Analysis of Algorithms-DP,Backtracking,Graphs,B&B
Design and Analysis of Algorithms-DP,Backtracking,Graphs,B&B
Sreedhar Chowdam
 
[JPP-1] - (JEE 3.0) - Kinematics 1D - 14th May..pdf
[JPP-1] - (JEE 3.0) - Kinematics 1D - 14th May..pdf[JPP-1] - (JEE 3.0) - Kinematics 1D - 14th May..pdf
[JPP-1] - (JEE 3.0) - Kinematics 1D - 14th May..pdf
awadeshbabu
 
RAT: Retrieval Augmented Thoughts Elicit Context-Aware Reasoning in Long-Hori...
RAT: Retrieval Augmented Thoughts Elicit Context-Aware Reasoning in Long-Hori...RAT: Retrieval Augmented Thoughts Elicit Context-Aware Reasoning in Long-Hori...
RAT: Retrieval Augmented Thoughts Elicit Context-Aware Reasoning in Long-Hori...
thanhdowork
 
TOP 10 B TECH COLLEGES IN JAIPUR 2024.pptx
TOP 10 B TECH COLLEGES IN JAIPUR 2024.pptxTOP 10 B TECH COLLEGES IN JAIPUR 2024.pptx
TOP 10 B TECH COLLEGES IN JAIPUR 2024.pptx
nikitacareer3
 
一比一原版(Otago毕业证)奥塔哥大学毕业证成绩单如何办理
一比一原版(Otago毕业证)奥塔哥大学毕业证成绩单如何办理一比一原版(Otago毕业证)奥塔哥大学毕业证成绩单如何办理
一比一原版(Otago毕业证)奥塔哥大学毕业证成绩单如何办理
dxobcob
 
A review on techniques and modelling methodologies used for checking electrom...
A review on techniques and modelling methodologies used for checking electrom...A review on techniques and modelling methodologies used for checking electrom...
A review on techniques and modelling methodologies used for checking electrom...
nooriasukmaningtyas
 
digital fundamental by Thomas L.floydl.pdf
digital fundamental by Thomas L.floydl.pdfdigital fundamental by Thomas L.floydl.pdf
digital fundamental by Thomas L.floydl.pdf
drwaing
 
AIR POLLUTION lecture EnE203 updated.pdf
AIR POLLUTION lecture EnE203 updated.pdfAIR POLLUTION lecture EnE203 updated.pdf
AIR POLLUTION lecture EnE203 updated.pdf
RicletoEspinosa1
 
spirit beverages ppt without graphics.pptx
spirit beverages ppt without graphics.pptxspirit beverages ppt without graphics.pptx
spirit beverages ppt without graphics.pptx
Madan Karki
 
一比一原版(UofT毕业证)多伦多大学毕业证成绩单如何办理
一比一原版(UofT毕业证)多伦多大学毕业证成绩单如何办理一比一原版(UofT毕业证)多伦多大学毕业证成绩单如何办理
一比一原版(UofT毕业证)多伦多大学毕业证成绩单如何办理
ydteq
 
一比一原版(UMich毕业证)密歇根大学|安娜堡分校毕业证成绩单专业办理
一比一原版(UMich毕业证)密歇根大学|安娜堡分校毕业证成绩单专业办理一比一原版(UMich毕业证)密歇根大学|安娜堡分校毕业证成绩单专业办理
一比一原版(UMich毕业证)密歇根大学|安娜堡分校毕业证成绩单专业办理
zwunae
 
DfMAy 2024 - key insights and contributions
DfMAy 2024 - key insights and contributionsDfMAy 2024 - key insights and contributions
DfMAy 2024 - key insights and contributions
gestioneergodomus
 
一比一原版(IIT毕业证)伊利诺伊理工大学毕业证成绩单专业办理
一比一原版(IIT毕业证)伊利诺伊理工大学毕业证成绩单专业办理一比一原版(IIT毕业证)伊利诺伊理工大学毕业证成绩单专业办理
一比一原版(IIT毕业证)伊利诺伊理工大学毕业证成绩单专业办理
zwunae
 
Governing Equations for Fundamental Aerodynamics_Anderson2010.pdf
Governing Equations for Fundamental Aerodynamics_Anderson2010.pdfGoverning Equations for Fundamental Aerodynamics_Anderson2010.pdf
Governing Equations for Fundamental Aerodynamics_Anderson2010.pdf
WENKENLI1
 
sieving analysis and results interpretation
sieving analysis and results interpretationsieving analysis and results interpretation
sieving analysis and results interpretation
ssuser36d3051
 
Swimming pool mechanical components design.pptx
Swimming pool  mechanical components design.pptxSwimming pool  mechanical components design.pptx
Swimming pool mechanical components design.pptx
yokeleetan1
 
Self-Control of Emotions by Slidesgo.pptx
Self-Control of Emotions by Slidesgo.pptxSelf-Control of Emotions by Slidesgo.pptx
Self-Control of Emotions by Slidesgo.pptx
iemerc2024
 
Building Electrical System Design & Installation
Building Electrical System Design & InstallationBuilding Electrical System Design & Installation
Building Electrical System Design & Installation
symbo111
 
ACRP 4-09 Risk Assessment Method to Support Modification of Airfield Separat...
ACRP 4-09 Risk Assessment Method to Support Modification of Airfield Separat...ACRP 4-09 Risk Assessment Method to Support Modification of Airfield Separat...
ACRP 4-09 Risk Assessment Method to Support Modification of Airfield Separat...
Mukeshwaran Balu
 

Recently uploaded (20)

Modelagem de um CSTR com reação endotermica.pdf
Modelagem de um CSTR com reação endotermica.pdfModelagem de um CSTR com reação endotermica.pdf
Modelagem de um CSTR com reação endotermica.pdf
 
Design and Analysis of Algorithms-DP,Backtracking,Graphs,B&B
Design and Analysis of Algorithms-DP,Backtracking,Graphs,B&BDesign and Analysis of Algorithms-DP,Backtracking,Graphs,B&B
Design and Analysis of Algorithms-DP,Backtracking,Graphs,B&B
 
[JPP-1] - (JEE 3.0) - Kinematics 1D - 14th May..pdf
[JPP-1] - (JEE 3.0) - Kinematics 1D - 14th May..pdf[JPP-1] - (JEE 3.0) - Kinematics 1D - 14th May..pdf
[JPP-1] - (JEE 3.0) - Kinematics 1D - 14th May..pdf
 
RAT: Retrieval Augmented Thoughts Elicit Context-Aware Reasoning in Long-Hori...
RAT: Retrieval Augmented Thoughts Elicit Context-Aware Reasoning in Long-Hori...RAT: Retrieval Augmented Thoughts Elicit Context-Aware Reasoning in Long-Hori...
RAT: Retrieval Augmented Thoughts Elicit Context-Aware Reasoning in Long-Hori...
 
TOP 10 B TECH COLLEGES IN JAIPUR 2024.pptx
TOP 10 B TECH COLLEGES IN JAIPUR 2024.pptxTOP 10 B TECH COLLEGES IN JAIPUR 2024.pptx
TOP 10 B TECH COLLEGES IN JAIPUR 2024.pptx
 
一比一原版(Otago毕业证)奥塔哥大学毕业证成绩单如何办理
一比一原版(Otago毕业证)奥塔哥大学毕业证成绩单如何办理一比一原版(Otago毕业证)奥塔哥大学毕业证成绩单如何办理
一比一原版(Otago毕业证)奥塔哥大学毕业证成绩单如何办理
 
A review on techniques and modelling methodologies used for checking electrom...
A review on techniques and modelling methodologies used for checking electrom...A review on techniques and modelling methodologies used for checking electrom...
A review on techniques and modelling methodologies used for checking electrom...
 
digital fundamental by Thomas L.floydl.pdf
digital fundamental by Thomas L.floydl.pdfdigital fundamental by Thomas L.floydl.pdf
digital fundamental by Thomas L.floydl.pdf
 
AIR POLLUTION lecture EnE203 updated.pdf
AIR POLLUTION lecture EnE203 updated.pdfAIR POLLUTION lecture EnE203 updated.pdf
AIR POLLUTION lecture EnE203 updated.pdf
 
spirit beverages ppt without graphics.pptx
spirit beverages ppt without graphics.pptxspirit beverages ppt without graphics.pptx
spirit beverages ppt without graphics.pptx
 
一比一原版(UofT毕业证)多伦多大学毕业证成绩单如何办理
一比一原版(UofT毕业证)多伦多大学毕业证成绩单如何办理一比一原版(UofT毕业证)多伦多大学毕业证成绩单如何办理
一比一原版(UofT毕业证)多伦多大学毕业证成绩单如何办理
 
一比一原版(UMich毕业证)密歇根大学|安娜堡分校毕业证成绩单专业办理
一比一原版(UMich毕业证)密歇根大学|安娜堡分校毕业证成绩单专业办理一比一原版(UMich毕业证)密歇根大学|安娜堡分校毕业证成绩单专业办理
一比一原版(UMich毕业证)密歇根大学|安娜堡分校毕业证成绩单专业办理
 
DfMAy 2024 - key insights and contributions
DfMAy 2024 - key insights and contributionsDfMAy 2024 - key insights and contributions
DfMAy 2024 - key insights and contributions
 
一比一原版(IIT毕业证)伊利诺伊理工大学毕业证成绩单专业办理
一比一原版(IIT毕业证)伊利诺伊理工大学毕业证成绩单专业办理一比一原版(IIT毕业证)伊利诺伊理工大学毕业证成绩单专业办理
一比一原版(IIT毕业证)伊利诺伊理工大学毕业证成绩单专业办理
 
Governing Equations for Fundamental Aerodynamics_Anderson2010.pdf
Governing Equations for Fundamental Aerodynamics_Anderson2010.pdfGoverning Equations for Fundamental Aerodynamics_Anderson2010.pdf
Governing Equations for Fundamental Aerodynamics_Anderson2010.pdf
 
sieving analysis and results interpretation
sieving analysis and results interpretationsieving analysis and results interpretation
sieving analysis and results interpretation
 
Swimming pool mechanical components design.pptx
Swimming pool  mechanical components design.pptxSwimming pool  mechanical components design.pptx
Swimming pool mechanical components design.pptx
 
Self-Control of Emotions by Slidesgo.pptx
Self-Control of Emotions by Slidesgo.pptxSelf-Control of Emotions by Slidesgo.pptx
Self-Control of Emotions by Slidesgo.pptx
 
Building Electrical System Design & Installation
Building Electrical System Design & InstallationBuilding Electrical System Design & Installation
Building Electrical System Design & Installation
 
ACRP 4-09 Risk Assessment Method to Support Modification of Airfield Separat...
ACRP 4-09 Risk Assessment Method to Support Modification of Airfield Separat...ACRP 4-09 Risk Assessment Method to Support Modification of Airfield Separat...
ACRP 4-09 Risk Assessment Method to Support Modification of Airfield Separat...
 

Insulation co cordination design

  • 2. Why we need Arrestors ? The arresters are designed for the worst case of 3-phase ground fault followed by the recovery saturation over voltages. This fault case gives the highest energy duty for the arrester • MCOV (Maximum Continuous Operating Voltage) The MCOV for equipment on the ac side of the converter station is the highest r.m.s. value, including harmonics, of the sinusoidal voltage applied at the terminals of the equipment. • CCOV (Crest value of the Continuous Operating Voltage) The CCOV for equipment on the dc side of the converter station, stressed by a voltage with or without commutation overshoots, is the highest continuous crest value of the voltage excluding commutation overshoots. Both designations MCOV and CCOV will be used in order to describe the arrester operating voltage. Why we need SIWL ? • Ans Load Rejection / Re-energization 1kA<Icharg<3kA; Convertor commutation overshoots during TOV conditions The SIWL(Switching Impulse Withstand Level) shall, in any case, not be below 1050 kV for all AC-side equipment( Voltage wave front 50/2500 micro sec; Current wave front 36/90 micro sec) Why we need LIWL ? Ans Since Switchyard shielding limits direct strikes <20kA; Back flashover on first tower outside switchyard The LIWL(Lightning Impulse withstand level) for circuit breakers, bushings and other equipment shall not be below 1425 kV (Voltage wave front 1.2/50 micro se; Current wave front 8/20 micro sec) Basic Definitions
  • 3. • Reasons for Switching Impulse:- Circuit breaker operation; Protective Switching Equipment Energisation; Load Rejections; Convertor switching transients Reasons for Lightning Impulse:- • Direct lightning stroke to line - rare on shielded systems • Back flashover - lightning strikes pylon shield wires Reasons FOW (Front of Wave) Impulse (Current wave front: 1/2 micro sec ) Bushing flashovers within valve hall, causing discharge of stray capacitances through relatively short lengths of conductor. LIWL= 1.4 times SIPL (Protection Level) = 1.2 times LIPL (Protection Level) • The SIWL shall not be less than 0.83 times the LIWL, nor below 1050 kV for equipment connected to the 400 kV AC-bus
  • 4. AC side fault of PMU plot R phase to Earth fault; A/R attempted but Un successfull Over shoot in other phases
  • 5. Commutation failure PMU plot Transient Over Voltage , Due to HVDC restart attempts
  • 6. AC and DC side Arrestors Arresters on AC side are usually specified by their rated voltage and maximum continuous operating voltage Peak value of voltage between phase conductor & earth or between phase conductors having highest system voltage peak. Arrestors on DC side rated voltage is not defined and continuous operating voltage is defined differently. PCOV (Peak Continuous Operating Voltage)
  • 7. Typical Voltage Wave shapes at various Locations Voltage 12 pulse The starting point of the insulation co- ordination process within the valve hall is the rating of the valve surge arrester (V) by balancing continuous energy absorption against protective level.
  • 8. Arrestors discharging currents Ground fault between valve and HV-bushing of converter transformer during rectifier operation. In this case the valve arresters type 'V1' protecting the 3- pulse commutation group on the HV side, could be stressed with high currents and energies. This is due to the fact that the DC- current on the faulted pole will go to zero, which corresponds to a load rejection. During this time these arresters will discharge the DC- line through the smoothing reactor and converter transformer. This fault will be cleared by tripping the ac circuit breakersCCOV= Transformer secondary voltage * 1.414 For HVDC 500kV 1000MW ; Type of Arrestors Max. voltage across arrester (SIPL) SIWL Max. energy dissipated in arrester V1 491 kV at 1.2 kA 1.15*491 2.12MJ V2 495 at 1.05 1.15*495 0.54MJ The highest stresses are expected if the transferred switching surge appears between the phases (e.g. R & Y), where only one valve of the involved phases is conducting R Y B Designing criteria of Valve hall Surge arrestor
  • 9. Arrestors discharging currents Simulated result of fault For HVDC 500kV 1000MW ; R Y B Stresses of Valve Arrester "V1" during Ground Fault at Transformer Bushing, rectifier operation 1.2KA Around 2MJ Around 500KV
  • 10. AC Side Arrestors AC System consists of parallel connected circuits and apart from some special cases the requirement is to establish the insulation level bet. phase to earth and phase to phase level • SIWL at least 1.15 times the SIPL • LIWL at least 1.25 times the SIPL • FWWL at least 1.25 times the FWPL Converter transformer:-A,A2 ( Max energy , generally used at Bus; whose fault current heavy) valve side of the Yy transformer windings:- A2 • Max. voltage across arrester „A“ = 610 kV at 2 kA • Max. energy dissipated in arrester „A“ = 3.3 MJ • AC Filter Banks:- AA (For slower front time surges the arrester type 'AA' energy is sharedwith the converter transformer arrester type ‘A’) AC-filters:- F ac DC Side Arrestors HVDC converter stations on the other hand consist of series connected bridges, each bridge requiring a different insulation strength to earth and within each bridge the electric strength is different for the various components • SIWL at least 1.20 times the SIPL. • LIWL at least 1.25 times the SIPL. • FWWL at least 1.25 times the FWPL 12-pulse valve group:- C Dc smoothing reactor :- D DC-line :- D DC-filters:- Fdc 12-pulse group and on the neutral line :- E Thyristor valves connected to HV-side of the smoothing reactor:- V1 Other Thyristors:- V2 Different types of Arrestors for different application
  • 11. Type of Arrestors MCOV (in KV) CCOV SIPL (KV at KA) LIPL (KV at KA) Energy (KJ) A 440/ 3 - 610 @2 714@20 6000 AA (Filter) 440/ 3 - 610 @1.3 1 714@13.3 A2( 500KV HVDC) Transformer secondary voltage YY (valve side) 530 946@1 1065@5 3200 A3 (500KV HVDC) Transformer secondary voltage YD (valve side) 308 527@1 595@4 1800 For 400kV AC Station (1) The coordinating current for switching surges for the AA arrester, which has the same protective level as the A arrester is chosen to 2kA x 2/3 » 1.3kA, because the AA arrester consists of only 2 columns per arrester housing
  • 12. Coordination with AC Line Arresters The characteristics of the surge arresters connected to the 400 kV ac lines • Rated arrester voltage: 390 kV • Min. Switching Surge residual voltage (at 1 kA): 730 kV • Max. Switching Surge residual voltage (at 1 kA): 780 kV • Max. residual voltage / lightning surge (at 10 kA): 900 kV • Max. residual voltage / lightning surge (at 20 kA): 975 kV Switching Surge Protective Level Type 'A'/'AA': 610 kV at 2/1.3 kA. Assuming minimum arrester characteristic of the ac line arresters and maximum characteristic of the type 'A'/'AA' arrester it can be concluded that a minimum margin (730 kV - 610 kV) / 610 kV = 19.7 % exists. This margin is fully adequate to avoid any overstressing of the parallel connected 400 kV ac line arresters. Typically, a margin of >10% can be assumed to be sufficient
  • 13. 4m 3.5m Minimum Air clearance; Phase to Ground=3.5m; Phase to phase= 4m.