SlideShare a Scribd company logo
SUMPNER’S TEST OF
TRANSFORMERS
Presented by-
Girin Chutia
Assam Engineering College
Introduction -
• The Sumpner's test (back to back test) is the very practical,
convenient, efficient and minimum power consumption test
which is done without actual loading to find regulation and
efficiency of large power transformer.
Two
Basic
Tests
Open
Circuit
Test
Short
Circuit
Test
Test to determine the iron loss/core
losses. In this test the secondary of the
transformer is kept open circuited.
Test to determine the copper losses.
In this test the secondary of the
transformer is kept short-circuited.
Already Two Tests..!
Why do we need Sumpner’s Test
to determine the same things …..??
• In O.C. test, there is no load on the transformer while in S.C. circuit
test only fractional load gets applied. In all O.C. and S.C. tests, the
loading conditions are absent. Hence the results are inaccurate.
• In open and short circuit test iron losses and copper losses are
determined separately but in actual use both losses occurs
simultaneously.
• The temperature rise in the transformer is due to total loss that
occurs simultaneously during actual use, it cant be determined by
O.C and S.C tests.
SUMPNER’S TEST
Its a improved method of testing transformer efficiency & other parameters.
This test gives the value of total loss accurately as it occurs when it is in actual
use. Sumpner's test or back to back test requires two transformers. Both
transformers are connected to supply in such a way that one transformer is
loaded on another.
Circuit diagram of Sampner’s test :
Operations of Sumpner’sTest :
• 1st the primaries of the two identical
transformers are connected in parallel
across the supply V1 and secondary's are
connected in series opposition.
• The switch S2 is opened and switch S1 is
closed. Now the no load current I0 flows
in primaries and I2 is zero.
• Then switch S2 also closed and the
voltage at the output of the regulating
transformer is varied until the full load
current I2 flows in the secondary circuit
loop.
• W1 = Core losses of both the
transformers, W2= Copper losses of both
transformers.
Advantages of the test:
• The power required to carry out the test is small.
• The transformers are tested at full-load conditions.
• As the test results gives the value of core and copper losses
occurring simultaneously so heat run test can be conducted on two
transformers.
• The secondary current(i.e I2) can be varied to any value using
regulating transformer. Hence we can determine the copper losses
at full load condition or at any load.
Drawbacks of the test:
Only limitation is that two identical transformers are required. In
practice exact identical transformers cannot be obtained and as two
transformers are required, the test is not economical.
CONCLUSION:
In many electrical machines its seen that sumpner's test or back to back test is
done in one or other way. As it is important to test every electrical machines at
its rated capacity and its inconvenient for machines of large rating to actually
fully load the equipment's and test. So for all electrical machines some form of
back to back test becomes important.
THANK YOU

More Related Content

What's hot

Power system stability
Power system stabilityPower system stability
Power system stability
Balaram Das
 
Symmetrical components
Symmetrical componentsSymmetrical components
Symmetrical components
Sirat Mahmood
 
Synchronous motor
Synchronous motorSynchronous motor
Synchronous motor
Sirat Mahmood
 
3 phase Induction Motor Torque-slip characteristics and Related problems
3 phase Induction Motor Torque-slip characteristics and Related problems3 phase Induction Motor Torque-slip characteristics and Related problems
3 phase Induction Motor Torque-slip characteristics and Related problems
karthi1017
 
Three phase voltage source inverter
Three phase voltage source inverterThree phase voltage source inverter
Three phase voltage source inverter
tamilnesaner
 
TRANSFORMERS and LOSSES
TRANSFORMERS and LOSSESTRANSFORMERS and LOSSES
TRANSFORMERS and LOSSES
Praveen Kumar
 
Distribution System Voltage Drop and Power Loss Calculation
Distribution System Voltage Drop and Power Loss CalculationDistribution System Voltage Drop and Power Loss Calculation
Distribution System Voltage Drop and Power Loss Calculation
Ameen San
 
Three phase transformers
Three phase transformersThree phase transformers
Three phase transformers
W3Edify
 
Transient in Power system
Transient in Power systemTransient in Power system
Transient in Power system
Preet_patel
 
Parallel Operation of a Single Phase Transformer
Parallel Operation of a Single Phase TransformerParallel Operation of a Single Phase Transformer
Parallel Operation of a Single Phase Transformer
Ridwanul Hoque
 
Starting method for 3 phase induction motor
Starting method for 3 phase induction motorStarting method for 3 phase induction motor
Starting method for 3 phase induction motor
Ahmed A.Hassan
 
Electrical power transmission system
Electrical power transmission systemElectrical power transmission system
Electrical power transmission system
Abdul Wahab Malik
 
GENERATING OF HIGH ALTERNATING VOLTAGE
GENERATING OF HIGH ALTERNATING VOLTAGEGENERATING OF HIGH ALTERNATING VOLTAGE
GENERATING OF HIGH ALTERNATING VOLTAGE
Jamil Abdullah
 
Protection of Transmission lines
Protection of Transmission linesProtection of Transmission lines
Protection of Transmission lines
Power System Operation
 
speed control of three phase induction motor
speed control of three phase induction motorspeed control of three phase induction motor
speed control of three phase induction motor
Ashvani Shukla
 
Resonant Converter
Resonant ConverterResonant Converter
Resonant Converter
pilurout
 
Bidirectional DC-DC isolated converter
Bidirectional DC-DC isolated converterBidirectional DC-DC isolated converter
Bidirectional DC-DC isolated converter
Vasudeva Guptha
 
Switchgear and protection 1
Switchgear and protection 1Switchgear and protection 1
Switchgear and protection 1
Md Irshad Ahmad
 
Simplified analysis of graetz circuit copy - copy
Simplified analysis of graetz circuit   copy - copySimplified analysis of graetz circuit   copy - copy
Simplified analysis of graetz circuit copy - copy
Vert Wheeler
 

What's hot (20)

Power system stability
Power system stabilityPower system stability
Power system stability
 
Reactive power compensation
Reactive power compensationReactive power compensation
Reactive power compensation
 
Symmetrical components
Symmetrical componentsSymmetrical components
Symmetrical components
 
Synchronous motor
Synchronous motorSynchronous motor
Synchronous motor
 
3 phase Induction Motor Torque-slip characteristics and Related problems
3 phase Induction Motor Torque-slip characteristics and Related problems3 phase Induction Motor Torque-slip characteristics and Related problems
3 phase Induction Motor Torque-slip characteristics and Related problems
 
Three phase voltage source inverter
Three phase voltage source inverterThree phase voltage source inverter
Three phase voltage source inverter
 
TRANSFORMERS and LOSSES
TRANSFORMERS and LOSSESTRANSFORMERS and LOSSES
TRANSFORMERS and LOSSES
 
Distribution System Voltage Drop and Power Loss Calculation
Distribution System Voltage Drop and Power Loss CalculationDistribution System Voltage Drop and Power Loss Calculation
Distribution System Voltage Drop and Power Loss Calculation
 
Three phase transformers
Three phase transformersThree phase transformers
Three phase transformers
 
Transient in Power system
Transient in Power systemTransient in Power system
Transient in Power system
 
Parallel Operation of a Single Phase Transformer
Parallel Operation of a Single Phase TransformerParallel Operation of a Single Phase Transformer
Parallel Operation of a Single Phase Transformer
 
Starting method for 3 phase induction motor
Starting method for 3 phase induction motorStarting method for 3 phase induction motor
Starting method for 3 phase induction motor
 
Electrical power transmission system
Electrical power transmission systemElectrical power transmission system
Electrical power transmission system
 
GENERATING OF HIGH ALTERNATING VOLTAGE
GENERATING OF HIGH ALTERNATING VOLTAGEGENERATING OF HIGH ALTERNATING VOLTAGE
GENERATING OF HIGH ALTERNATING VOLTAGE
 
Protection of Transmission lines
Protection of Transmission linesProtection of Transmission lines
Protection of Transmission lines
 
speed control of three phase induction motor
speed control of three phase induction motorspeed control of three phase induction motor
speed control of three phase induction motor
 
Resonant Converter
Resonant ConverterResonant Converter
Resonant Converter
 
Bidirectional DC-DC isolated converter
Bidirectional DC-DC isolated converterBidirectional DC-DC isolated converter
Bidirectional DC-DC isolated converter
 
Switchgear and protection 1
Switchgear and protection 1Switchgear and protection 1
Switchgear and protection 1
 
Simplified analysis of graetz circuit copy - copy
Simplified analysis of graetz circuit   copy - copySimplified analysis of graetz circuit   copy - copy
Simplified analysis of graetz circuit copy - copy
 

Viewers also liked

O.C & S.C Test, Sumpner or back to back Test, Condition for maximum efficienc...
O.C & S.C Test, Sumpner or back to back Test, Condition for maximum efficienc...O.C & S.C Test, Sumpner or back to back Test, Condition for maximum efficienc...
O.C & S.C Test, Sumpner or back to back Test, Condition for maximum efficienc...
Abhishek Choksi
 
Transformer testing
Transformer testingTransformer testing
Transformer testingajayknows
 
Calculating the efficiency and regulation of transformer using matlab
Calculating the efficiency and regulation of transformer using matlabCalculating the efficiency and regulation of transformer using matlab
Calculating the efficiency and regulation of transformer using matlab
Mafaz Ahmed
 
Sc and oc test on transformer
Sc and oc test on transformerSc and oc test on transformer
Sc and oc test on transformer
Pooja Dubey
 
Electrical machines 2 lab manual
Electrical machines 2 lab manualElectrical machines 2 lab manual
Electrical machines 2 lab manual
Naga Sai Chaitanya
 
Transformer
TransformerTransformer
Transformer
Sandeep Kumar
 
Testing of transformer
Testing of transformerTesting of transformer
Testing of transformer
vikasgupta1965
 
Transformer a short presentation
Transformer a short presentationTransformer a short presentation
Transformer a short presentation
shakil2604
 
Repulsion type motor
Repulsion type motorRepulsion type motor
Repulsion type motor
Hamdard University Bangladesh
 
Harmonics In Transformer pdf
Harmonics In Transformer  pdfHarmonics In Transformer  pdf
Harmonics In Transformer pdf
navreet singh
 
Machine lab manual
Machine lab manualMachine lab manual
Machine lab manual
DHEERAJ DHAKAR
 
Problems at independence
Problems at independenceProblems at independence
Problems at independence
Awais Idrees
 
What is the ASME Code and Why is it Important?
What is the ASME Code and Why is it Important?What is the ASME Code and Why is it Important?
What is the ASME Code and Why is it Important?
Mark Mitchell
 
Transformers class 12 PPT
Transformers class 12 PPTTransformers class 12 PPT
Transformers class 12 PPT
अयशकांत मिश्र
 
Post Partition Problems of Pakistan
Post Partition Problems of PakistanPost Partition Problems of Pakistan
Post Partition Problems of Pakistan
Amna Jalil
 
HIGH VOL TAGE TESTING OF TRANSFORMER BY HARI SHANKAR SINGH
HIGH VOL TAGE TESTING OF TRANSFORMER BY HARI SHANKAR SINGHHIGH VOL TAGE TESTING OF TRANSFORMER BY HARI SHANKAR SINGH
HIGH VOL TAGE TESTING OF TRANSFORMER BY HARI SHANKAR SINGHShankar Singh
 
Single phase induction motor
Single phase induction motorSingle phase induction motor
Single phase induction motor
Gowtham Packiaraj
 
Power electronics note
Power electronics notePower electronics note
Power electronics noteravalgautu
 
Lecture-1 : Introduction to Power Electronics
Lecture-1 : Introduction to Power ElectronicsLecture-1 : Introduction to Power Electronics
Lecture-1 : Introduction to Power Electronics
rsamurti
 

Viewers also liked (20)

O.C & S.C Test, Sumpner or back to back Test, Condition for maximum efficienc...
O.C & S.C Test, Sumpner or back to back Test, Condition for maximum efficienc...O.C & S.C Test, Sumpner or back to back Test, Condition for maximum efficienc...
O.C & S.C Test, Sumpner or back to back Test, Condition for maximum efficienc...
 
Transformer testing
Transformer testingTransformer testing
Transformer testing
 
Calculating the efficiency and regulation of transformer using matlab
Calculating the efficiency and regulation of transformer using matlabCalculating the efficiency and regulation of transformer using matlab
Calculating the efficiency and regulation of transformer using matlab
 
Sc and oc test on transformer
Sc and oc test on transformerSc and oc test on transformer
Sc and oc test on transformer
 
Electrical machines 2 lab manual
Electrical machines 2 lab manualElectrical machines 2 lab manual
Electrical machines 2 lab manual
 
Transformer
TransformerTransformer
Transformer
 
Testing of transformer
Testing of transformerTesting of transformer
Testing of transformer
 
Transformer a short presentation
Transformer a short presentationTransformer a short presentation
Transformer a short presentation
 
Repulsion type motor
Repulsion type motorRepulsion type motor
Repulsion type motor
 
Harmonics In Transformer pdf
Harmonics In Transformer  pdfHarmonics In Transformer  pdf
Harmonics In Transformer pdf
 
Transformers
TransformersTransformers
Transformers
 
Machine lab manual
Machine lab manualMachine lab manual
Machine lab manual
 
Problems at independence
Problems at independenceProblems at independence
Problems at independence
 
What is the ASME Code and Why is it Important?
What is the ASME Code and Why is it Important?What is the ASME Code and Why is it Important?
What is the ASME Code and Why is it Important?
 
Transformers class 12 PPT
Transformers class 12 PPTTransformers class 12 PPT
Transformers class 12 PPT
 
Post Partition Problems of Pakistan
Post Partition Problems of PakistanPost Partition Problems of Pakistan
Post Partition Problems of Pakistan
 
HIGH VOL TAGE TESTING OF TRANSFORMER BY HARI SHANKAR SINGH
HIGH VOL TAGE TESTING OF TRANSFORMER BY HARI SHANKAR SINGHHIGH VOL TAGE TESTING OF TRANSFORMER BY HARI SHANKAR SINGH
HIGH VOL TAGE TESTING OF TRANSFORMER BY HARI SHANKAR SINGH
 
Single phase induction motor
Single phase induction motorSingle phase induction motor
Single phase induction motor
 
Power electronics note
Power electronics notePower electronics note
Power electronics note
 
Lecture-1 : Introduction to Power Electronics
Lecture-1 : Introduction to Power ElectronicsLecture-1 : Introduction to Power Electronics
Lecture-1 : Introduction to Power Electronics
 

Similar to Sumpners Test of Transformers

Sumpner Test on Transformers
Sumpner Test on TransformersSumpner Test on Transformers
Sumpner Test on Transformers
Soham Gajjar
 
32.open circuit and short circuit test .ppt
32.open circuit and short circuit test .ppt32.open circuit and short circuit test .ppt
32.open circuit and short circuit test .ppt
NANDHAKUMARA10
 
Open circuit and Short circuit test on transformer
Open circuit and Short circuit test on transformerOpen circuit and Short circuit test on transformer
Open circuit and Short circuit test on transformer
Harshit Khandelwal
 
Power transformer
Power transformerPower transformer
Power transformer
ZunAib Ali
 
Akshay kumar
Akshay kumarAkshay kumar
Akshay kumar
akshay1234kumar
 
Transformers
TransformersTransformers
Transformers
Siva Kumar
 
Ac machines-lab-manual
Ac machines-lab-manualAc machines-lab-manual
Ac machines-lab-manual
Rao Umar
 
Transformers 31.03.2020.pptx
Transformers 31.03.2020.pptxTransformers 31.03.2020.pptx
Transformers 31.03.2020.pptx
PraveenKumarB30
 
Transformers 25.02.2020.pptx
Transformers 25.02.2020.pptxTransformers 25.02.2020.pptx
Transformers 25.02.2020.pptx
PraveenKumarB30
 
EN_lab1.pdf
EN_lab1.pdfEN_lab1.pdf
EN_lab1.pdf
gamemaster21
 
H06 elo g
H06 elo g H06 elo g
H06 elo g
phase3-120A
 
transformers.ppt
transformers.ppttransformers.ppt
transformers.ppt
jamla1
 
2.4 & 2.7
2.4 & 2.72.4 & 2.7
2.4 & 2.7
W3Edify
 
Transformer
TransformerTransformer
Transformer
Rishikesh Borse
 
Two marks
Two marksTwo marks
Two marks
balaji1986
 
Power converter lab manual by chaturvedula
Power converter lab manual by chaturvedulaPower converter lab manual by chaturvedula
Power converter lab manual by chaturvedula
KumarChaturvedula
 
Electrical power ecx3232 lab report
Electrical power ecx3232 lab reportElectrical power ecx3232 lab report
Electrical power ecx3232 lab reportSandun Perera
 
Em manual 1
Em manual 1Em manual 1
Em manual 1
sahebrao chakor
 
Meduim Voltage Switchgear.pptx
Meduim Voltage Switchgear.pptxMeduim Voltage Switchgear.pptx
Meduim Voltage Switchgear.pptx
MAHMOUDMOHAMED431205
 

Similar to Sumpners Test of Transformers (20)

Sumpner Test on Transformers
Sumpner Test on TransformersSumpner Test on Transformers
Sumpner Test on Transformers
 
32.open circuit and short circuit test .ppt
32.open circuit and short circuit test .ppt32.open circuit and short circuit test .ppt
32.open circuit and short circuit test .ppt
 
Open circuit and Short circuit test on transformer
Open circuit and Short circuit test on transformerOpen circuit and Short circuit test on transformer
Open circuit and Short circuit test on transformer
 
Power transformer
Power transformerPower transformer
Power transformer
 
Akshay kumar
Akshay kumarAkshay kumar
Akshay kumar
 
Transformers
TransformersTransformers
Transformers
 
Ac machines-lab-manual
Ac machines-lab-manualAc machines-lab-manual
Ac machines-lab-manual
 
Transformers 31.03.2020.pptx
Transformers 31.03.2020.pptxTransformers 31.03.2020.pptx
Transformers 31.03.2020.pptx
 
Transformers 25.02.2020.pptx
Transformers 25.02.2020.pptxTransformers 25.02.2020.pptx
Transformers 25.02.2020.pptx
 
EN_lab1.pdf
EN_lab1.pdfEN_lab1.pdf
EN_lab1.pdf
 
H06 elo g
H06 elo g H06 elo g
H06 elo g
 
transformers.ppt
transformers.ppttransformers.ppt
transformers.ppt
 
Transformer
TransformerTransformer
Transformer
 
2.4 & 2.7
2.4 & 2.72.4 & 2.7
2.4 & 2.7
 
Transformer
TransformerTransformer
Transformer
 
Two marks
Two marksTwo marks
Two marks
 
Power converter lab manual by chaturvedula
Power converter lab manual by chaturvedulaPower converter lab manual by chaturvedula
Power converter lab manual by chaturvedula
 
Electrical power ecx3232 lab report
Electrical power ecx3232 lab reportElectrical power ecx3232 lab report
Electrical power ecx3232 lab report
 
Em manual 1
Em manual 1Em manual 1
Em manual 1
 
Meduim Voltage Switchgear.pptx
Meduim Voltage Switchgear.pptxMeduim Voltage Switchgear.pptx
Meduim Voltage Switchgear.pptx
 

Recently uploaded

Courier management system project report.pdf
Courier management system project report.pdfCourier management system project report.pdf
Courier management system project report.pdf
Kamal Acharya
 
Event Management System Vb Net Project Report.pdf
Event Management System Vb Net  Project Report.pdfEvent Management System Vb Net  Project Report.pdf
Event Management System Vb Net Project Report.pdf
Kamal Acharya
 
LIGA(E)11111111111111111111111111111111111111111.ppt
LIGA(E)11111111111111111111111111111111111111111.pptLIGA(E)11111111111111111111111111111111111111111.ppt
LIGA(E)11111111111111111111111111111111111111111.ppt
ssuser9bd3ba
 
Democratizing Fuzzing at Scale by Abhishek Arya
Democratizing Fuzzing at Scale by Abhishek AryaDemocratizing Fuzzing at Scale by Abhishek Arya
Democratizing Fuzzing at Scale by Abhishek Arya
abh.arya
 
WATER CRISIS and its solutions-pptx 1234
WATER CRISIS and its solutions-pptx 1234WATER CRISIS and its solutions-pptx 1234
WATER CRISIS and its solutions-pptx 1234
AafreenAbuthahir2
 
The role of big data in decision making.
The role of big data in decision making.The role of big data in decision making.
The role of big data in decision making.
ankuprajapati0525
 
HYDROPOWER - Hydroelectric power generation
HYDROPOWER - Hydroelectric power generationHYDROPOWER - Hydroelectric power generation
HYDROPOWER - Hydroelectric power generation
Robbie Edward Sayers
 
Vaccine management system project report documentation..pdf
Vaccine management system project report documentation..pdfVaccine management system project report documentation..pdf
Vaccine management system project report documentation..pdf
Kamal Acharya
 
Automobile Management System Project Report.pdf
Automobile Management System Project Report.pdfAutomobile Management System Project Report.pdf
Automobile Management System Project Report.pdf
Kamal Acharya
 
MCQ Soil mechanics questions (Soil shear strength).pdf
MCQ Soil mechanics questions (Soil shear strength).pdfMCQ Soil mechanics questions (Soil shear strength).pdf
MCQ Soil mechanics questions (Soil shear strength).pdf
Osamah Alsalih
 
Design and Analysis of Algorithms-DP,Backtracking,Graphs,B&B
Design and Analysis of Algorithms-DP,Backtracking,Graphs,B&BDesign and Analysis of Algorithms-DP,Backtracking,Graphs,B&B
Design and Analysis of Algorithms-DP,Backtracking,Graphs,B&B
Sreedhar Chowdam
 
Planning Of Procurement o different goods and services
Planning Of Procurement o different goods and servicesPlanning Of Procurement o different goods and services
Planning Of Procurement o different goods and services
JoytuBarua2
 
weather web application report.pdf
weather web application report.pdfweather web application report.pdf
weather web application report.pdf
Pratik Pawar
 
The Benefits and Techniques of Trenchless Pipe Repair.pdf
The Benefits and Techniques of Trenchless Pipe Repair.pdfThe Benefits and Techniques of Trenchless Pipe Repair.pdf
The Benefits and Techniques of Trenchless Pipe Repair.pdf
Pipe Restoration Solutions
 
Industrial Training at Shahjalal Fertilizer Company Limited (SFCL)
Industrial Training at Shahjalal Fertilizer Company Limited (SFCL)Industrial Training at Shahjalal Fertilizer Company Limited (SFCL)
Industrial Training at Shahjalal Fertilizer Company Limited (SFCL)
MdTanvirMahtab2
 
TECHNICAL TRAINING MANUAL GENERAL FAMILIARIZATION COURSE
TECHNICAL TRAINING MANUAL   GENERAL FAMILIARIZATION COURSETECHNICAL TRAINING MANUAL   GENERAL FAMILIARIZATION COURSE
TECHNICAL TRAINING MANUAL GENERAL FAMILIARIZATION COURSE
DuvanRamosGarzon1
 
Student information management system project report ii.pdf
Student information management system project report ii.pdfStudent information management system project report ii.pdf
Student information management system project report ii.pdf
Kamal Acharya
 
DESIGN A COTTON SEED SEPARATION MACHINE.docx
DESIGN A COTTON SEED SEPARATION MACHINE.docxDESIGN A COTTON SEED SEPARATION MACHINE.docx
DESIGN A COTTON SEED SEPARATION MACHINE.docx
FluxPrime1
 
Architectural Portfolio Sean Lockwood
Architectural Portfolio Sean LockwoodArchitectural Portfolio Sean Lockwood
Architectural Portfolio Sean Lockwood
seandesed
 
Water Industry Process Automation and Control Monthly - May 2024.pdf
Water Industry Process Automation and Control Monthly - May 2024.pdfWater Industry Process Automation and Control Monthly - May 2024.pdf
Water Industry Process Automation and Control Monthly - May 2024.pdf
Water Industry Process Automation & Control
 

Recently uploaded (20)

Courier management system project report.pdf
Courier management system project report.pdfCourier management system project report.pdf
Courier management system project report.pdf
 
Event Management System Vb Net Project Report.pdf
Event Management System Vb Net  Project Report.pdfEvent Management System Vb Net  Project Report.pdf
Event Management System Vb Net Project Report.pdf
 
LIGA(E)11111111111111111111111111111111111111111.ppt
LIGA(E)11111111111111111111111111111111111111111.pptLIGA(E)11111111111111111111111111111111111111111.ppt
LIGA(E)11111111111111111111111111111111111111111.ppt
 
Democratizing Fuzzing at Scale by Abhishek Arya
Democratizing Fuzzing at Scale by Abhishek AryaDemocratizing Fuzzing at Scale by Abhishek Arya
Democratizing Fuzzing at Scale by Abhishek Arya
 
WATER CRISIS and its solutions-pptx 1234
WATER CRISIS and its solutions-pptx 1234WATER CRISIS and its solutions-pptx 1234
WATER CRISIS and its solutions-pptx 1234
 
The role of big data in decision making.
The role of big data in decision making.The role of big data in decision making.
The role of big data in decision making.
 
HYDROPOWER - Hydroelectric power generation
HYDROPOWER - Hydroelectric power generationHYDROPOWER - Hydroelectric power generation
HYDROPOWER - Hydroelectric power generation
 
Vaccine management system project report documentation..pdf
Vaccine management system project report documentation..pdfVaccine management system project report documentation..pdf
Vaccine management system project report documentation..pdf
 
Automobile Management System Project Report.pdf
Automobile Management System Project Report.pdfAutomobile Management System Project Report.pdf
Automobile Management System Project Report.pdf
 
MCQ Soil mechanics questions (Soil shear strength).pdf
MCQ Soil mechanics questions (Soil shear strength).pdfMCQ Soil mechanics questions (Soil shear strength).pdf
MCQ Soil mechanics questions (Soil shear strength).pdf
 
Design and Analysis of Algorithms-DP,Backtracking,Graphs,B&B
Design and Analysis of Algorithms-DP,Backtracking,Graphs,B&BDesign and Analysis of Algorithms-DP,Backtracking,Graphs,B&B
Design and Analysis of Algorithms-DP,Backtracking,Graphs,B&B
 
Planning Of Procurement o different goods and services
Planning Of Procurement o different goods and servicesPlanning Of Procurement o different goods and services
Planning Of Procurement o different goods and services
 
weather web application report.pdf
weather web application report.pdfweather web application report.pdf
weather web application report.pdf
 
The Benefits and Techniques of Trenchless Pipe Repair.pdf
The Benefits and Techniques of Trenchless Pipe Repair.pdfThe Benefits and Techniques of Trenchless Pipe Repair.pdf
The Benefits and Techniques of Trenchless Pipe Repair.pdf
 
Industrial Training at Shahjalal Fertilizer Company Limited (SFCL)
Industrial Training at Shahjalal Fertilizer Company Limited (SFCL)Industrial Training at Shahjalal Fertilizer Company Limited (SFCL)
Industrial Training at Shahjalal Fertilizer Company Limited (SFCL)
 
TECHNICAL TRAINING MANUAL GENERAL FAMILIARIZATION COURSE
TECHNICAL TRAINING MANUAL   GENERAL FAMILIARIZATION COURSETECHNICAL TRAINING MANUAL   GENERAL FAMILIARIZATION COURSE
TECHNICAL TRAINING MANUAL GENERAL FAMILIARIZATION COURSE
 
Student information management system project report ii.pdf
Student information management system project report ii.pdfStudent information management system project report ii.pdf
Student information management system project report ii.pdf
 
DESIGN A COTTON SEED SEPARATION MACHINE.docx
DESIGN A COTTON SEED SEPARATION MACHINE.docxDESIGN A COTTON SEED SEPARATION MACHINE.docx
DESIGN A COTTON SEED SEPARATION MACHINE.docx
 
Architectural Portfolio Sean Lockwood
Architectural Portfolio Sean LockwoodArchitectural Portfolio Sean Lockwood
Architectural Portfolio Sean Lockwood
 
Water Industry Process Automation and Control Monthly - May 2024.pdf
Water Industry Process Automation and Control Monthly - May 2024.pdfWater Industry Process Automation and Control Monthly - May 2024.pdf
Water Industry Process Automation and Control Monthly - May 2024.pdf
 

Sumpners Test of Transformers

  • 1. SUMPNER’S TEST OF TRANSFORMERS Presented by- Girin Chutia Assam Engineering College
  • 2. Introduction - • The Sumpner's test (back to back test) is the very practical, convenient, efficient and minimum power consumption test which is done without actual loading to find regulation and efficiency of large power transformer.
  • 3. Two Basic Tests Open Circuit Test Short Circuit Test Test to determine the iron loss/core losses. In this test the secondary of the transformer is kept open circuited. Test to determine the copper losses. In this test the secondary of the transformer is kept short-circuited.
  • 4. Already Two Tests..! Why do we need Sumpner’s Test to determine the same things …..??
  • 5. • In O.C. test, there is no load on the transformer while in S.C. circuit test only fractional load gets applied. In all O.C. and S.C. tests, the loading conditions are absent. Hence the results are inaccurate. • In open and short circuit test iron losses and copper losses are determined separately but in actual use both losses occurs simultaneously. • The temperature rise in the transformer is due to total loss that occurs simultaneously during actual use, it cant be determined by O.C and S.C tests.
  • 6. SUMPNER’S TEST Its a improved method of testing transformer efficiency & other parameters. This test gives the value of total loss accurately as it occurs when it is in actual use. Sumpner's test or back to back test requires two transformers. Both transformers are connected to supply in such a way that one transformer is loaded on another.
  • 7. Circuit diagram of Sampner’s test :
  • 8. Operations of Sumpner’sTest : • 1st the primaries of the two identical transformers are connected in parallel across the supply V1 and secondary's are connected in series opposition. • The switch S2 is opened and switch S1 is closed. Now the no load current I0 flows in primaries and I2 is zero. • Then switch S2 also closed and the voltage at the output of the regulating transformer is varied until the full load current I2 flows in the secondary circuit loop. • W1 = Core losses of both the transformers, W2= Copper losses of both transformers.
  • 9. Advantages of the test: • The power required to carry out the test is small. • The transformers are tested at full-load conditions. • As the test results gives the value of core and copper losses occurring simultaneously so heat run test can be conducted on two transformers. • The secondary current(i.e I2) can be varied to any value using regulating transformer. Hence we can determine the copper losses at full load condition or at any load. Drawbacks of the test: Only limitation is that two identical transformers are required. In practice exact identical transformers cannot be obtained and as two transformers are required, the test is not economical.
  • 10. CONCLUSION: In many electrical machines its seen that sumpner's test or back to back test is done in one or other way. As it is important to test every electrical machines at its rated capacity and its inconvenient for machines of large rating to actually fully load the equipment's and test. So for all electrical machines some form of back to back test becomes important.