SINGLE MINUTE EXCHANGE OF
DIES (SMED)
WELCOME TO THE PRESENTATION OF
GROUP MEMBERS
INTRODUCTION
Changeover time
Definition: The time
elapsed between when the
last good piece of product
A comes off and the first
good piece of product B
starts.
INTRODUCTION- HISTORY
History : Land costs in Japan were very high, therefore it was not feasible
to store large inventories of vehicles.
Quick
Change Overs
“A rapid and efficient way of converting a process
from running the current product
to running the next product “
Developed by Shigeo Shingo
( in the late 1950’s and early
1960’s) chief engineer of Toyota.
Reduces the waste of inventory by creating shorter production runs
that better align with customer demand
QUICK CHANGEOVER IN LEAN
CONTINUOUS
IMPROVEMENT
Pull/Kanban Cellular/flow
POUS
TPM
Quality at Source
Standardized Work
Quick Changeover
Batch Reduction Teams
5S systems Plant LayoutVisual Controls
VALUE
STREAM
MAPPING
SINGLE MINUTE
EXCHANGE OF
DIE(SMED)
SMED: Concept that says all
setups should and can take
less than 10 minutes.
Traditional
SMED
SMED- REAL WORLD EXAMPLE
3000-ton Sheet metal stamping press:
Traditional
Time: 4 Hours
SMED
Time: 3 Minutes
Improvement: 98.7%, or a factor of 80
SMED- REAL WORLD EXAMPLE
400-ton LIM molding press with 16-cavity tool:
Traditional
Time: 3 Hours
SMED
Time: 5 Minutes 20 seconds
Increase in effective capacity equal to 15,544
additional parts
HOW TO REDUCE SET-UP COST?
By reducing
setup time
By reducing
wastages
By reducing
various costs
Present
desired
settings
Use quick
fasteners
Use locator
pins
Prevent
misalignm
ents
Eliminate
tools
Make
movements
easier
REDUCING SET-UP TIME
6 TRADITIONAL SETUP STEPS
Preparation
Ensures that all the tools are working properly and are in the right
location.
Extraction
The removal of the tooling, raw material, and support equipment
after the production lot is completed.
Mounting
The placement of the new tool, support equipment, and raw material
before the next production lot.
Establishing
Control
Setting all the process control settings prior to the production run.
First Run
Capability
This includes the necessary adjustments required after the first trial
pieces are produced.
Setup
Improvement
The time after processing during which the tooling, machinery is
cleaned, identified, and tested for functionality prior to storage.
THE SMED PROCESS
End with 5S.
Standardize changeover tasks.
Stay with the machine at all times.
Set and attach ( no fine tuning)
Work from specific positions & standards ( no adjusting).
Utilize Quick Connectors (No bolts needed).
Transfer Internal Time to External Time
Begin With 5S
Eight Rules for Quick Changeover:
Reduce
inventory
Reduce batch
sizes
Reduce
changeover
time
Reduce impact
on equipment
utilization
Improve
quality after
changeover
Improve
repeatability
Improve
throughput
Improve
flexibility
THE SMED PROCESS- GOALS
Observe
and Record
Separate
internal
and
external
activities
Convert
internal
activities to
external
activities
Streamline
all
activities
Document
internal
and
external
procedures
THE SMED PROCESS
STAGES OF
SMED
OBSERVE AND RECORD
We Should always:
Notify the party to be observed
ahead of time.
Explain why we are conducting
an observation
Explain the possible benefits
for them and the company
Review the observation with
the individual
1
❑ Identify internal and external
elements,
❑ waste/lost time,
❑ variances from the standard process
SEPARATE INTERNALAND
EXTERNALACTIVITIES 2
Internal elements
• Operations that must be
performed while the
machine/process is stopped
External elements
• Operations that can be
performed while the
machine/process is running
CONVERT INTERNALS TO
EXTERNALS ACTIVITIES
3
Eliminate Adjustment
CONVERT INTERNALS TO
EXTERNALS ACTIVITIES
3
Eliminate search-and-find work
Arrange tools & materials beforehand
Complete prep work before starting changeover
Standardize settings
Make visual marks vs. trial and error adjustments
Eliminate trial runs
Postpone “put away” work
STREAMLINE ALL
ACTIVITIES
4
STREAMLINE ALL
ACTIVITIES
4
STREAMLINE
INTERNAL PROCESS
•Create Parallel steps
– completed at the
same time
•Reduce complexity
and eliminate waste
STREAMLINE
EXTERNAL PROCESS
•Adopt functional
standards-Visual
factory locations for
tools, Color coding
,Standard set ups
Checklists
Document new process
•Create new work sheets that include
all the steps of the new process
•Get all needed approvals
•Train all workers
•Post the standardized work sheets
(STW)
DOCUMENT INTERNAL &
EXTERNAL PROCEDURES
5
Create new process
• Document who will do what and when
• Practice quick changeover (QCO) before doing it
Test new process
• Run pilot of new process
• Document steps of new process
• Time steps of new process
• Document improvement opportunities
• Videotape and look for additional opportunities
WHEN SHOULD
YOU AUTOMATE?
Criterion 1
• The operation has already
been dramatically simplified
Criterion 2
• Begin with semi automation to
achieve 80% benefit at 20%
cost
Criterion 3
• The automation is cost-
effective
SMED IN DAILY LIFE
Planted , Grown &
harvested Food
Fast Food , instant food,
frozen food.
Self Pick Up Delivery Services
Tie shoes Slip on shoes
In person registration Online registration
SHINGO PRIZE
The Shingo Prize
for Excellence in
Manufacturing
was established in
1988 in honor of
Shigeo Shingo.
The Prize
promotes world-
class
manufacturing
and recognizes
companies that
achieve superior
customer
satisfaction and
business results.
The philosophy of the
Shingo Prize is that
worldclass business
performance may be
achieved through focused
improvements in core
manufacturing and
business processes.
Thank You
If any questions ,feel free to ask us.

More Related Content

What's hot

SMED or Single Minute Exchange of Dies and Set-up Reduction Process
SMED or Single Minute Exchange of Dies and Set-up Reduction ProcessSMED or Single Minute Exchange of Dies and Set-up Reduction Process
SMED or Single Minute Exchange of Dies and Set-up Reduction Process
W3 Group Canada Inc.
 
LEAN SMED TRAINING FOR SUPERVISORS AND OPERATORS
LEAN SMED TRAINING FOR SUPERVISORS AND OPERATORSLEAN SMED TRAINING FOR SUPERVISORS AND OPERATORS
LEAN SMED TRAINING FOR SUPERVISORS AND OPERATORS
Julian Kalac P.Eng
 
Lean Quick Changeover (SMED) Training Module
Lean Quick Changeover (SMED) Training ModuleLean Quick Changeover (SMED) Training Module
Lean Quick Changeover (SMED) Training Module
Frank-G. Adler
 
SMED
SMEDSMED
How to reduce changeover loss
How to reduce changeover lossHow to reduce changeover loss
How to reduce changeover loss
Winning Minds Solutions
 
SMED overview
SMED overviewSMED overview
5S Workshop &Visual management - Krishna Heda
5S Workshop &Visual management - Krishna Heda5S Workshop &Visual management - Krishna Heda
5S Workshop &Visual management - Krishna Heda
krishnaheda
 
PPT ON SINGLE MINUTE EXCHANGE OF DIES (SMED)
PPT ON SINGLE MINUTE EXCHANGE OF DIES (SMED)PPT ON SINGLE MINUTE EXCHANGE OF DIES (SMED)
PPT ON SINGLE MINUTE EXCHANGE OF DIES (SMED)
Inter Alliance Werardt
 
The 4 Phases to Visual Management - ADDVALUE - Nilesh Arora
The 4 Phases to Visual Management - ADDVALUE - Nilesh AroraThe 4 Phases to Visual Management - ADDVALUE - Nilesh Arora
The 4 Phases to Visual Management - ADDVALUE - Nilesh Arora
ADD VALUE CONSULTING Inc
 
8 WASTES IN LEAN MANUFACUTING & OVERVIEW OF VSM
8 WASTES IN LEAN MANUFACUTING & OVERVIEW OF VSM8 WASTES IN LEAN MANUFACUTING & OVERVIEW OF VSM
8 WASTES IN LEAN MANUFACUTING & OVERVIEW OF VSM
SedhuSiddarth
 
Lean Manufacturing Training
Lean Manufacturing TrainingLean Manufacturing Training
Lean Manufacturing Training
VISCAR INDUSTRIAL CAPACITY
 
Tools of lean mfg
Tools of lean mfgTools of lean mfg
Tools of lean mfg
Jitesh Gaurav
 
LEAN Setup Reduction (SMED) training for welding by JULIAN KALAC
LEAN Setup Reduction (SMED) training for welding by JULIAN KALACLEAN Setup Reduction (SMED) training for welding by JULIAN KALAC
LEAN Setup Reduction (SMED) training for welding by JULIAN KALAC
Julian Kalac P.Eng
 
SMED Training
SMED Training SMED Training
SMED Training
lumensolutions
 
Lean manufacturing overview
Lean manufacturing overviewLean manufacturing overview
Lean manufacturing overview
Pruek Pinyo
 
Lean Manufacturing - An Overview
Lean Manufacturing - An OverviewLean Manufacturing - An Overview
Lean Manufacturing - An Overview
Kanzen Institute Asia-Pacific
 
Visual Management by Operational Excellence Consulting
Visual Management by Operational Excellence ConsultingVisual Management by Operational Excellence Consulting
Visual Management by Operational Excellence Consulting
Operational Excellence Consulting
 
Hourly Lean Introduction
Hourly Lean IntroductionHourly Lean Introduction
Hourly Lean Introduction
Harold Philbrick
 

What's hot (20)

SMED or Single Minute Exchange of Dies and Set-up Reduction Process
SMED or Single Minute Exchange of Dies and Set-up Reduction ProcessSMED or Single Minute Exchange of Dies and Set-up Reduction Process
SMED or Single Minute Exchange of Dies and Set-up Reduction Process
 
LEAN SMED TRAINING FOR SUPERVISORS AND OPERATORS
LEAN SMED TRAINING FOR SUPERVISORS AND OPERATORSLEAN SMED TRAINING FOR SUPERVISORS AND OPERATORS
LEAN SMED TRAINING FOR SUPERVISORS AND OPERATORS
 
Lean Quick Changeover (SMED) Training Module
Lean Quick Changeover (SMED) Training ModuleLean Quick Changeover (SMED) Training Module
Lean Quick Changeover (SMED) Training Module
 
SMED
SMEDSMED
SMED
 
How to reduce changeover loss
How to reduce changeover lossHow to reduce changeover loss
How to reduce changeover loss
 
SMED overview
SMED overviewSMED overview
SMED overview
 
Standard work
Standard workStandard work
Standard work
 
5S Workshop &Visual management - Krishna Heda
5S Workshop &Visual management - Krishna Heda5S Workshop &Visual management - Krishna Heda
5S Workshop &Visual management - Krishna Heda
 
PPT ON SINGLE MINUTE EXCHANGE OF DIES (SMED)
PPT ON SINGLE MINUTE EXCHANGE OF DIES (SMED)PPT ON SINGLE MINUTE EXCHANGE OF DIES (SMED)
PPT ON SINGLE MINUTE EXCHANGE OF DIES (SMED)
 
The 4 Phases to Visual Management - ADDVALUE - Nilesh Arora
The 4 Phases to Visual Management - ADDVALUE - Nilesh AroraThe 4 Phases to Visual Management - ADDVALUE - Nilesh Arora
The 4 Phases to Visual Management - ADDVALUE - Nilesh Arora
 
8 WASTES IN LEAN MANUFACUTING & OVERVIEW OF VSM
8 WASTES IN LEAN MANUFACUTING & OVERVIEW OF VSM8 WASTES IN LEAN MANUFACUTING & OVERVIEW OF VSM
8 WASTES IN LEAN MANUFACUTING & OVERVIEW OF VSM
 
Lean Manufacturing Training
Lean Manufacturing TrainingLean Manufacturing Training
Lean Manufacturing Training
 
Tools of lean mfg
Tools of lean mfgTools of lean mfg
Tools of lean mfg
 
Visual control
Visual controlVisual control
Visual control
 
LEAN Setup Reduction (SMED) training for welding by JULIAN KALAC
LEAN Setup Reduction (SMED) training for welding by JULIAN KALACLEAN Setup Reduction (SMED) training for welding by JULIAN KALAC
LEAN Setup Reduction (SMED) training for welding by JULIAN KALAC
 
SMED Training
SMED Training SMED Training
SMED Training
 
Lean manufacturing overview
Lean manufacturing overviewLean manufacturing overview
Lean manufacturing overview
 
Lean Manufacturing - An Overview
Lean Manufacturing - An OverviewLean Manufacturing - An Overview
Lean Manufacturing - An Overview
 
Visual Management by Operational Excellence Consulting
Visual Management by Operational Excellence ConsultingVisual Management by Operational Excellence Consulting
Visual Management by Operational Excellence Consulting
 
Hourly Lean Introduction
Hourly Lean IntroductionHourly Lean Introduction
Hourly Lean Introduction
 

Similar to Single Minute Exchange of Dies

SMED - 6.pptx.pptx
SMED - 6.pptx.pptxSMED - 6.pptx.pptx
SMED - 6.pptx.pptx
ssuser820b7a
 
Quick Smed Sample
Quick Smed SampleQuick Smed Sample
Quick Smed Sample
ahmad bassiouny
 
Implémentation Méthode Single Minute Exchange of Dies(SMED)
Implémentation Méthode Single Minute Exchange of Dies(SMED)Implémentation Méthode Single Minute Exchange of Dies(SMED)
Implémentation Méthode Single Minute Exchange of Dies(SMED)
MohammedLahssaini1
 
The SMED Method by CLT Services
The SMED Method by CLT ServicesThe SMED Method by CLT Services
The SMED Method by CLT Services
CLT Valuebased Services
 
Just in time and Lean systems
Just in time and Lean systemsJust in time and Lean systems
Just in time and Lean systems
Ayman Aljahdali
 
Lean - PPT (Lean manufacturing and six sigma)
Lean - PPT (Lean manufacturing and six sigma)Lean - PPT (Lean manufacturing and six sigma)
Lean - PPT (Lean manufacturing and six sigma)
Blankdevil
 
StdWork_sample
StdWork_sampleStdWork_sample
StdWork_sample
ahmad bassiouny
 
Std Work Sample
Std Work SampleStd Work Sample
Std Work Sample
ahmad bassiouny
 
Lean 101 2 Hour 2011
Lean 101 2 Hour 2011Lean 101 2 Hour 2011
Lean 101 2 Hour 2011
LCI1998
 
layout planning
layout planninglayout planning
layout planning
Radhika Itkan
 
Operations Management power point Chapter Five
Operations Management power point Chapter FiveOperations Management power point Chapter Five
Operations Management power point Chapter Five
AYNETUTEREFE1
 
Equipment reliability l1
Equipment reliability l1Equipment reliability l1
Equipment reliability l1
Matthew Clemens
 
TPM PRECISION CHANGEOVERS
TPM PRECISION CHANGEOVERSTPM PRECISION CHANGEOVERS
TPM PRECISION CHANGEOVERS
Max Lyons
 
Lean manufacturing basics
Lean manufacturing basicsLean manufacturing basics
Lean manufacturing basics
sarah bridge
 
Generic Lean Overview For Future Employer Of Alan S Desrocher
Generic Lean Overview For Future Employer Of Alan S DesrocherGeneric Lean Overview For Future Employer Of Alan S Desrocher
Generic Lean Overview For Future Employer Of Alan S DesrocherAlan Desrocher
 
Lean Introduction.pptx
Lean Introduction.pptxLean Introduction.pptx
Lean Introduction.pptx
SathriyanSathi
 
TOYOTA PRODUCTION SYSTEM (TPS)
TOYOTA PRODUCTION SYSTEM (TPS)TOYOTA PRODUCTION SYSTEM (TPS)
TOYOTA PRODUCTION SYSTEM (TPS)
Prasanna3804
 
Just In Time
Just In TimeJust In Time
Just In Time
dvyvjy
 
VSM (Lean Manufacturing) Project PPT
VSM (Lean Manufacturing) Project PPTVSM (Lean Manufacturing) Project PPT
VSM (Lean Manufacturing) Project PPTFASI93
 

Similar to Single Minute Exchange of Dies (20)

SMED - 6.pptx.pptx
SMED - 6.pptx.pptxSMED - 6.pptx.pptx
SMED - 6.pptx.pptx
 
Quick Smed Sample
Quick Smed SampleQuick Smed Sample
Quick Smed Sample
 
Implémentation Méthode Single Minute Exchange of Dies(SMED)
Implémentation Méthode Single Minute Exchange of Dies(SMED)Implémentation Méthode Single Minute Exchange of Dies(SMED)
Implémentation Méthode Single Minute Exchange of Dies(SMED)
 
The SMED Method by CLT Services
The SMED Method by CLT ServicesThe SMED Method by CLT Services
The SMED Method by CLT Services
 
Just in time and Lean systems
Just in time and Lean systemsJust in time and Lean systems
Just in time and Lean systems
 
Lean - PPT (Lean manufacturing and six sigma)
Lean - PPT (Lean manufacturing and six sigma)Lean - PPT (Lean manufacturing and six sigma)
Lean - PPT (Lean manufacturing and six sigma)
 
StdWork_sample
StdWork_sampleStdWork_sample
StdWork_sample
 
Std Work Sample
Std Work SampleStd Work Sample
Std Work Sample
 
Lean 101 2 Hour 2011
Lean 101 2 Hour 2011Lean 101 2 Hour 2011
Lean 101 2 Hour 2011
 
layout planning
layout planninglayout planning
layout planning
 
Ch9 Jit
Ch9 JitCh9 Jit
Ch9 Jit
 
Operations Management power point Chapter Five
Operations Management power point Chapter FiveOperations Management power point Chapter Five
Operations Management power point Chapter Five
 
Equipment reliability l1
Equipment reliability l1Equipment reliability l1
Equipment reliability l1
 
TPM PRECISION CHANGEOVERS
TPM PRECISION CHANGEOVERSTPM PRECISION CHANGEOVERS
TPM PRECISION CHANGEOVERS
 
Lean manufacturing basics
Lean manufacturing basicsLean manufacturing basics
Lean manufacturing basics
 
Generic Lean Overview For Future Employer Of Alan S Desrocher
Generic Lean Overview For Future Employer Of Alan S DesrocherGeneric Lean Overview For Future Employer Of Alan S Desrocher
Generic Lean Overview For Future Employer Of Alan S Desrocher
 
Lean Introduction.pptx
Lean Introduction.pptxLean Introduction.pptx
Lean Introduction.pptx
 
TOYOTA PRODUCTION SYSTEM (TPS)
TOYOTA PRODUCTION SYSTEM (TPS)TOYOTA PRODUCTION SYSTEM (TPS)
TOYOTA PRODUCTION SYSTEM (TPS)
 
Just In Time
Just In TimeJust In Time
Just In Time
 
VSM (Lean Manufacturing) Project PPT
VSM (Lean Manufacturing) Project PPTVSM (Lean Manufacturing) Project PPT
VSM (Lean Manufacturing) Project PPT
 

More from Md. Nazmul Hasan Dipu

Presentation on Solar Energy in Bangladesh.
Presentation on Solar Energy in Bangladesh.Presentation on Solar Energy in Bangladesh.
Presentation on Solar Energy in Bangladesh.
Md. Nazmul Hasan Dipu
 
Presentation on Locating and Locator.
Presentation on Locating and Locator.Presentation on Locating and Locator.
Presentation on Locating and Locator.
Md. Nazmul Hasan Dipu
 
G Code M code
G Code M codeG Code M code
G Code M code
Md. Nazmul Hasan Dipu
 
Controller
ControllerController
Electron Beam Machining
Electron Beam MachiningElectron Beam Machining
Electron Beam Machining
Md. Nazmul Hasan Dipu
 
Presentation on Economic Change in Bangladesh in Last Decade.
Presentation on Economic Change in Bangladesh in Last Decade.Presentation on Economic Change in Bangladesh in Last Decade.
Presentation on Economic Change in Bangladesh in Last Decade.
Md. Nazmul Hasan Dipu
 

More from Md. Nazmul Hasan Dipu (6)

Presentation on Solar Energy in Bangladesh.
Presentation on Solar Energy in Bangladesh.Presentation on Solar Energy in Bangladesh.
Presentation on Solar Energy in Bangladesh.
 
Presentation on Locating and Locator.
Presentation on Locating and Locator.Presentation on Locating and Locator.
Presentation on Locating and Locator.
 
G Code M code
G Code M codeG Code M code
G Code M code
 
Controller
ControllerController
Controller
 
Electron Beam Machining
Electron Beam MachiningElectron Beam Machining
Electron Beam Machining
 
Presentation on Economic Change in Bangladesh in Last Decade.
Presentation on Economic Change in Bangladesh in Last Decade.Presentation on Economic Change in Bangladesh in Last Decade.
Presentation on Economic Change in Bangladesh in Last Decade.
 

Recently uploaded

Democratizing Fuzzing at Scale by Abhishek Arya
Democratizing Fuzzing at Scale by Abhishek AryaDemocratizing Fuzzing at Scale by Abhishek Arya
Democratizing Fuzzing at Scale by Abhishek Arya
abh.arya
 
Cosmetic shop management system project report.pdf
Cosmetic shop management system project report.pdfCosmetic shop management system project report.pdf
Cosmetic shop management system project report.pdf
Kamal Acharya
 
ethical hacking in wireless-hacking1.ppt
ethical hacking in wireless-hacking1.pptethical hacking in wireless-hacking1.ppt
ethical hacking in wireless-hacking1.ppt
Jayaprasanna4
 
NO1 Uk best vashikaran specialist in delhi vashikaran baba near me online vas...
NO1 Uk best vashikaran specialist in delhi vashikaran baba near me online vas...NO1 Uk best vashikaran specialist in delhi vashikaran baba near me online vas...
NO1 Uk best vashikaran specialist in delhi vashikaran baba near me online vas...
Amil Baba Dawood bangali
 
Immunizing Image Classifiers Against Localized Adversary Attacks
Immunizing Image Classifiers Against Localized Adversary AttacksImmunizing Image Classifiers Against Localized Adversary Attacks
Immunizing Image Classifiers Against Localized Adversary Attacks
gerogepatton
 
H.Seo, ICLR 2024, MLILAB, KAIST AI.pdf
H.Seo,  ICLR 2024, MLILAB,  KAIST AI.pdfH.Seo,  ICLR 2024, MLILAB,  KAIST AI.pdf
H.Seo, ICLR 2024, MLILAB, KAIST AI.pdf
MLILAB
 
Standard Reomte Control Interface - Neometrix
Standard Reomte Control Interface - NeometrixStandard Reomte Control Interface - Neometrix
Standard Reomte Control Interface - Neometrix
Neometrix_Engineering_Pvt_Ltd
 
Railway Signalling Principles Edition 3.pdf
Railway Signalling Principles Edition 3.pdfRailway Signalling Principles Edition 3.pdf
Railway Signalling Principles Edition 3.pdf
TeeVichai
 
Hybrid optimization of pumped hydro system and solar- Engr. Abdul-Azeez.pdf
Hybrid optimization of pumped hydro system and solar- Engr. Abdul-Azeez.pdfHybrid optimization of pumped hydro system and solar- Engr. Abdul-Azeez.pdf
Hybrid optimization of pumped hydro system and solar- Engr. Abdul-Azeez.pdf
fxintegritypublishin
 
Automobile Management System Project Report.pdf
Automobile Management System Project Report.pdfAutomobile Management System Project Report.pdf
Automobile Management System Project Report.pdf
Kamal Acharya
 
addressing modes in computer architecture
addressing modes  in computer architectureaddressing modes  in computer architecture
addressing modes in computer architecture
ShahidSultan24
 
ASME IX(9) 2007 Full Version .pdf
ASME IX(9)  2007 Full Version       .pdfASME IX(9)  2007 Full Version       .pdf
ASME IX(9) 2007 Full Version .pdf
AhmedHussein950959
 
Gen AI Study Jams _ For the GDSC Leads in India.pdf
Gen AI Study Jams _ For the GDSC Leads in India.pdfGen AI Study Jams _ For the GDSC Leads in India.pdf
Gen AI Study Jams _ For the GDSC Leads in India.pdf
gdsczhcet
 
LIGA(E)11111111111111111111111111111111111111111.ppt
LIGA(E)11111111111111111111111111111111111111111.pptLIGA(E)11111111111111111111111111111111111111111.ppt
LIGA(E)11111111111111111111111111111111111111111.ppt
ssuser9bd3ba
 
Nuclear Power Economics and Structuring 2024
Nuclear Power Economics and Structuring 2024Nuclear Power Economics and Structuring 2024
Nuclear Power Economics and Structuring 2024
Massimo Talia
 
Courier management system project report.pdf
Courier management system project report.pdfCourier management system project report.pdf
Courier management system project report.pdf
Kamal Acharya
 
Final project report on grocery store management system..pdf
Final project report on grocery store management system..pdfFinal project report on grocery store management system..pdf
Final project report on grocery store management system..pdf
Kamal Acharya
 
Forklift Classes Overview by Intella Parts
Forklift Classes Overview by Intella PartsForklift Classes Overview by Intella Parts
Forklift Classes Overview by Intella Parts
Intella Parts
 
Planning Of Procurement o different goods and services
Planning Of Procurement o different goods and servicesPlanning Of Procurement o different goods and services
Planning Of Procurement o different goods and services
JoytuBarua2
 
The role of big data in decision making.
The role of big data in decision making.The role of big data in decision making.
The role of big data in decision making.
ankuprajapati0525
 

Recently uploaded (20)

Democratizing Fuzzing at Scale by Abhishek Arya
Democratizing Fuzzing at Scale by Abhishek AryaDemocratizing Fuzzing at Scale by Abhishek Arya
Democratizing Fuzzing at Scale by Abhishek Arya
 
Cosmetic shop management system project report.pdf
Cosmetic shop management system project report.pdfCosmetic shop management system project report.pdf
Cosmetic shop management system project report.pdf
 
ethical hacking in wireless-hacking1.ppt
ethical hacking in wireless-hacking1.pptethical hacking in wireless-hacking1.ppt
ethical hacking in wireless-hacking1.ppt
 
NO1 Uk best vashikaran specialist in delhi vashikaran baba near me online vas...
NO1 Uk best vashikaran specialist in delhi vashikaran baba near me online vas...NO1 Uk best vashikaran specialist in delhi vashikaran baba near me online vas...
NO1 Uk best vashikaran specialist in delhi vashikaran baba near me online vas...
 
Immunizing Image Classifiers Against Localized Adversary Attacks
Immunizing Image Classifiers Against Localized Adversary AttacksImmunizing Image Classifiers Against Localized Adversary Attacks
Immunizing Image Classifiers Against Localized Adversary Attacks
 
H.Seo, ICLR 2024, MLILAB, KAIST AI.pdf
H.Seo,  ICLR 2024, MLILAB,  KAIST AI.pdfH.Seo,  ICLR 2024, MLILAB,  KAIST AI.pdf
H.Seo, ICLR 2024, MLILAB, KAIST AI.pdf
 
Standard Reomte Control Interface - Neometrix
Standard Reomte Control Interface - NeometrixStandard Reomte Control Interface - Neometrix
Standard Reomte Control Interface - Neometrix
 
Railway Signalling Principles Edition 3.pdf
Railway Signalling Principles Edition 3.pdfRailway Signalling Principles Edition 3.pdf
Railway Signalling Principles Edition 3.pdf
 
Hybrid optimization of pumped hydro system and solar- Engr. Abdul-Azeez.pdf
Hybrid optimization of pumped hydro system and solar- Engr. Abdul-Azeez.pdfHybrid optimization of pumped hydro system and solar- Engr. Abdul-Azeez.pdf
Hybrid optimization of pumped hydro system and solar- Engr. Abdul-Azeez.pdf
 
Automobile Management System Project Report.pdf
Automobile Management System Project Report.pdfAutomobile Management System Project Report.pdf
Automobile Management System Project Report.pdf
 
addressing modes in computer architecture
addressing modes  in computer architectureaddressing modes  in computer architecture
addressing modes in computer architecture
 
ASME IX(9) 2007 Full Version .pdf
ASME IX(9)  2007 Full Version       .pdfASME IX(9)  2007 Full Version       .pdf
ASME IX(9) 2007 Full Version .pdf
 
Gen AI Study Jams _ For the GDSC Leads in India.pdf
Gen AI Study Jams _ For the GDSC Leads in India.pdfGen AI Study Jams _ For the GDSC Leads in India.pdf
Gen AI Study Jams _ For the GDSC Leads in India.pdf
 
LIGA(E)11111111111111111111111111111111111111111.ppt
LIGA(E)11111111111111111111111111111111111111111.pptLIGA(E)11111111111111111111111111111111111111111.ppt
LIGA(E)11111111111111111111111111111111111111111.ppt
 
Nuclear Power Economics and Structuring 2024
Nuclear Power Economics and Structuring 2024Nuclear Power Economics and Structuring 2024
Nuclear Power Economics and Structuring 2024
 
Courier management system project report.pdf
Courier management system project report.pdfCourier management system project report.pdf
Courier management system project report.pdf
 
Final project report on grocery store management system..pdf
Final project report on grocery store management system..pdfFinal project report on grocery store management system..pdf
Final project report on grocery store management system..pdf
 
Forklift Classes Overview by Intella Parts
Forklift Classes Overview by Intella PartsForklift Classes Overview by Intella Parts
Forklift Classes Overview by Intella Parts
 
Planning Of Procurement o different goods and services
Planning Of Procurement o different goods and servicesPlanning Of Procurement o different goods and services
Planning Of Procurement o different goods and services
 
The role of big data in decision making.
The role of big data in decision making.The role of big data in decision making.
The role of big data in decision making.
 

Single Minute Exchange of Dies

  • 1.
  • 2. SINGLE MINUTE EXCHANGE OF DIES (SMED) WELCOME TO THE PRESENTATION OF
  • 4. INTRODUCTION Changeover time Definition: The time elapsed between when the last good piece of product A comes off and the first good piece of product B starts.
  • 5. INTRODUCTION- HISTORY History : Land costs in Japan were very high, therefore it was not feasible to store large inventories of vehicles. Quick Change Overs “A rapid and efficient way of converting a process from running the current product to running the next product “ Developed by Shigeo Shingo ( in the late 1950’s and early 1960’s) chief engineer of Toyota. Reduces the waste of inventory by creating shorter production runs that better align with customer demand
  • 6. QUICK CHANGEOVER IN LEAN CONTINUOUS IMPROVEMENT Pull/Kanban Cellular/flow POUS TPM Quality at Source Standardized Work Quick Changeover Batch Reduction Teams 5S systems Plant LayoutVisual Controls VALUE STREAM MAPPING
  • 7. SINGLE MINUTE EXCHANGE OF DIE(SMED) SMED: Concept that says all setups should and can take less than 10 minutes. Traditional SMED
  • 8. SMED- REAL WORLD EXAMPLE 3000-ton Sheet metal stamping press: Traditional Time: 4 Hours SMED Time: 3 Minutes Improvement: 98.7%, or a factor of 80
  • 9. SMED- REAL WORLD EXAMPLE 400-ton LIM molding press with 16-cavity tool: Traditional Time: 3 Hours SMED Time: 5 Minutes 20 seconds Increase in effective capacity equal to 15,544 additional parts
  • 10. HOW TO REDUCE SET-UP COST? By reducing setup time By reducing wastages By reducing various costs
  • 12. 6 TRADITIONAL SETUP STEPS Preparation Ensures that all the tools are working properly and are in the right location. Extraction The removal of the tooling, raw material, and support equipment after the production lot is completed. Mounting The placement of the new tool, support equipment, and raw material before the next production lot. Establishing Control Setting all the process control settings prior to the production run. First Run Capability This includes the necessary adjustments required after the first trial pieces are produced. Setup Improvement The time after processing during which the tooling, machinery is cleaned, identified, and tested for functionality prior to storage.
  • 13. THE SMED PROCESS End with 5S. Standardize changeover tasks. Stay with the machine at all times. Set and attach ( no fine tuning) Work from specific positions & standards ( no adjusting). Utilize Quick Connectors (No bolts needed). Transfer Internal Time to External Time Begin With 5S Eight Rules for Quick Changeover:
  • 14. Reduce inventory Reduce batch sizes Reduce changeover time Reduce impact on equipment utilization Improve quality after changeover Improve repeatability Improve throughput Improve flexibility THE SMED PROCESS- GOALS
  • 17. OBSERVE AND RECORD We Should always: Notify the party to be observed ahead of time. Explain why we are conducting an observation Explain the possible benefits for them and the company Review the observation with the individual 1 ❑ Identify internal and external elements, ❑ waste/lost time, ❑ variances from the standard process
  • 18. SEPARATE INTERNALAND EXTERNALACTIVITIES 2 Internal elements • Operations that must be performed while the machine/process is stopped External elements • Operations that can be performed while the machine/process is running
  • 19. CONVERT INTERNALS TO EXTERNALS ACTIVITIES 3 Eliminate Adjustment
  • 20. CONVERT INTERNALS TO EXTERNALS ACTIVITIES 3 Eliminate search-and-find work Arrange tools & materials beforehand Complete prep work before starting changeover Standardize settings Make visual marks vs. trial and error adjustments Eliminate trial runs Postpone “put away” work
  • 22. STREAMLINE ALL ACTIVITIES 4 STREAMLINE INTERNAL PROCESS •Create Parallel steps – completed at the same time •Reduce complexity and eliminate waste STREAMLINE EXTERNAL PROCESS •Adopt functional standards-Visual factory locations for tools, Color coding ,Standard set ups Checklists
  • 23. Document new process •Create new work sheets that include all the steps of the new process •Get all needed approvals •Train all workers •Post the standardized work sheets (STW) DOCUMENT INTERNAL & EXTERNAL PROCEDURES 5 Create new process • Document who will do what and when • Practice quick changeover (QCO) before doing it Test new process • Run pilot of new process • Document steps of new process • Time steps of new process • Document improvement opportunities • Videotape and look for additional opportunities
  • 24. WHEN SHOULD YOU AUTOMATE? Criterion 1 • The operation has already been dramatically simplified Criterion 2 • Begin with semi automation to achieve 80% benefit at 20% cost Criterion 3 • The automation is cost- effective
  • 25. SMED IN DAILY LIFE Planted , Grown & harvested Food Fast Food , instant food, frozen food. Self Pick Up Delivery Services Tie shoes Slip on shoes In person registration Online registration
  • 26. SHINGO PRIZE The Shingo Prize for Excellence in Manufacturing was established in 1988 in honor of Shigeo Shingo. The Prize promotes world- class manufacturing and recognizes companies that achieve superior customer satisfaction and business results. The philosophy of the Shingo Prize is that worldclass business performance may be achieved through focused improvements in core manufacturing and business processes.
  • 27. Thank You If any questions ,feel free to ask us.