SlideShare a Scribd company logo
Waste Treatment Plant Project
Lessons Learned
Construction
Electrical
Ron Clements P.E, PMP
Lead Electrical Engineer Temporary Power
October 6, 2009
2
Syllabus
 Project Inspection Records
 Material Acquisitions (Procurement)
 Sub-Contractor Equipment
 NEC Common Pitfalls
 Arc-Flash
 Grounding Assurance
 Conex Box Electrical Violations
 Medium Voltage Program
 Performance Improvements
2
3
Project Records
 Project Start/Stop
 Lost or missing inspection records
 Time loss
 Re-work
3
4
Material Acquisitions (Procurement)
 Supplier compliance with NEC
requirements
 Lack of UL or other NRTL
listings for equipment
 Code compliant issues with
components and assemblies
 Foreign equipment (i.e., Potain
Cranes/Material Lifts)
 NRTL inspections and
corresponding corrective
actions for supplier equipment
4
5
Sub-Contractor Equipment
 NEC code requirements issues
 Concrete batch plant
 OCPD sizing
 Conductor sizing
 Grounding
 Aging equipment
6
NEC Common Pitfalls
 Article 110.3(B) requires listed or labeled equipment to
be installed and used in accordance with any
instructions included in the listing or labeling.
 Article 110.22 requires each disconnecting means to be
legibly marked to indicate its purpose.
 Article 110.26(A)(1) requires a three-foot working
clearance in front of the panelboards. (A)(2) Requires
width of the working space in front of the electric
equipment to be the width of the equipment or 30 inches,
whichever is greater. (A)(3) Requires the work space to
be clear and extend from the grade, floor, or platform to
6½ feet, or where the equipment exceeds 6½ feet, the
minimum headroom shall not be less than the height of
the equipment.
7
NEC Common Pitfalls (cont)
 Article 240.5 requires flexible cord and flexible cable to
be protected by an overcurrent device in accordance
with their ampacity as specified in Table 400.5(A) and
Table 400.5(B).
 Article 250.122 requires the equipment grounding
conductor to be sized based off the overcurrent device
ahead of the equipment.
 Article 700.12(E)(4) requires the branch circuit feeding
the emergency lighting to be the same branch circuit as
that serving the normal lighting in that area.
 Article 725 (A) requires cables and conductors of Class
2 and Class 3 circuits to not be placed in any cable,
cable tray, compartment, enclosure, manhole, outlet box,
raceway, or similar fitting with conductors of electric light,
power, and Class 1 circuits.
8
Arc-Flash
 Evolution of WTP Arc-Flash
 Hanford Calculator
 ETAP Software
 Field evaluations
 Identify equipment type
 Fuse studies
 Circuit breaker studies
 Single-line verification
 ETAP software data Input
 Cross checking performed during data input
9
ETAP Arc-Flash Single-Line
10
ETAP Arc-Flash Network
11
ETAP Arc-Flash Report
12
Grounding Assurance
 Grounding requirements for 240 and 480 volt cord sets
 480 volt heater cord set wiring
 Manufacturer cord and cap (burned in field)
 Replaced with a 30A cord cap and #10 wire
13
Grounding Assurance
14
WTP Conex
15
WTP Conex
16
Conex Box Electrical Violations
 Systematic control of temporary power to these types of
temporary structures
 Multiple source feeds to conex
 Extension cords being ran through door ways or
windows
 Bonding/grounding not in accordance to NEC
 No proper disconnecting means
 No procedure in place to control temporary power in
these conex’s
17
Medium Voltage Program
 WTP Substations 1-16
 OSHA 29 CFR 1910.269
 Medium Voltage training (Manual/Non-Manual)
 Use of 13.8KV testing equipment
 Installation of Grounding clusters
 LO/TO (Capacitive Test Points) – In ability of voltage
verification during LO/TO process
 Replacement of dead breaks (allows for voltage
measurement on each feeder and the ability to install
a grounding cluster
18
WTP Substation and Switchboard
19
WTP Substation
20
Summary
 Implementing of enhanced supplier electrical equipment
code inspection oversight
 NEC inspectors designated to each facility
 NRTL certified inspector designated for construction
equipment
 Implementing NEC code compliant inspections of
temporary power and sub-contractor electrical
installations; this includes developing a comprehensive
NEC inspection training program that has emphasized
lessons learned from past problems at the WTP
 Improving electrical design code compliance
performance by emphasizing code requirements and
providing lessons-learned feedback from previous WTP
compliance issues
21
Summary
 Procuring medium voltage equipment and
implementing medium voltage training to electrical craft
and supervision
 Improving the WTP LO/TO program to go beyond
typical required construction LO/TO to that required by
operation organizations (29 CFR 1910 vs. 29 CFR
1926)
 Fully implementing the NFPA
worker safety requirements
21
22
WTP August 2009
Pretreatment Facility
Administration
Building
Temporary
Warehouse
Temporary Combination
& Fabrication Shop
High-Level Waste Facility
Low-Activity
Waste Facility
Two Concrete
Batch Plants
Analytical Lab

More Related Content

What's hot

33/11 KV SUBSTATION
33/11 KV SUBSTATION33/11 KV SUBSTATION
33/11 KV SUBSTATION
k,l polytechnic roorkee
 
1.substation layouts
1.substation  layouts1.substation  layouts
1.substation layouts
ayyadurai SHANMUGAM
 
Transmission & distribution of electrical power
Transmission & distribution of electrical powerTransmission & distribution of electrical power
Transmission & distribution of electrical power
priyanka1432
 
33kv substation
33kv substation33kv substation
33kv substation
Abhishek Dawachya
 
Electrical SUBSTATION ppt
Electrical SUBSTATION pptElectrical SUBSTATION ppt
Electrical SUBSTATION ppt
TanvirkabirShishir
 
Construction EHV Transmission Line
Construction EHV Transmission LineConstruction EHV Transmission Line
Construction EHV Transmission Line
SURESH GOPAL
 
Power System Protection basics
Power System Protection basicsPower System Protection basics
Power System Protection basics
Rajan Singh Tanwar
 
Training at 132 kv substation
Training at 132 kv substation Training at 132 kv substation
Training at 132 kv substation
Tejveer Choudhary
 
Inplant training about 110kv/11kv substation
Inplant training about 110kv/11kv substationInplant training about 110kv/11kv substation
Inplant training about 110kv/11kv substation
shivashankar307
 
Equipments of power transmission
Equipments of power transmissionEquipments of power transmission
Equipments of power transmission
Rasika Ghongade
 
Switchgear and protection lecture 1
Switchgear and protection lecture 1Switchgear and protection lecture 1
Switchgear and protection lecture 1
anuphowlader1
 
Substation
Substation Substation
presentation on substation layout and BUS bar arrangement.
presentation on substation layout and BUS bar arrangement.presentation on substation layout and BUS bar arrangement.
presentation on substation layout and BUS bar arrangement.
Hemendra Kumar Rajput
 
Principles of Cable Sizing
Principles of Cable SizingPrinciples of Cable Sizing
Principles of Cable Sizing
Leonardo ENERGY
 
Siemens MV GIS Switchgear
Siemens MV GIS SwitchgearSiemens MV GIS Switchgear
Siemens MV GIS Switchgear
michaeljmack
 
Overhead line work ppt
Overhead line work pptOverhead line work ppt
Overhead line work ppt
Demsew Mitiku
 
Practical handbook-for-relay-protection-engineers
Practical handbook-for-relay-protection-engineersPractical handbook-for-relay-protection-engineers
Practical handbook-for-relay-protection-engineers
SARAVANAN A
 
Selective Coordination
Selective CoordinationSelective Coordination
Selective Coordination
michaeljmack
 
FUNDAMENTALS OF POWER SYSTEM PROTECTION
FUNDAMENTALS OF POWER SYSTEM PROTECTIONFUNDAMENTALS OF POWER SYSTEM PROTECTION
FUNDAMENTALS OF POWER SYSTEM PROTECTION
Power System Operation
 
Fault Level Calculation
Fault Level CalculationFault Level Calculation
Fault Level CalculationDinesh Sarda
 

What's hot (20)

33/11 KV SUBSTATION
33/11 KV SUBSTATION33/11 KV SUBSTATION
33/11 KV SUBSTATION
 
1.substation layouts
1.substation  layouts1.substation  layouts
1.substation layouts
 
Transmission & distribution of electrical power
Transmission & distribution of electrical powerTransmission & distribution of electrical power
Transmission & distribution of electrical power
 
33kv substation
33kv substation33kv substation
33kv substation
 
Electrical SUBSTATION ppt
Electrical SUBSTATION pptElectrical SUBSTATION ppt
Electrical SUBSTATION ppt
 
Construction EHV Transmission Line
Construction EHV Transmission LineConstruction EHV Transmission Line
Construction EHV Transmission Line
 
Power System Protection basics
Power System Protection basicsPower System Protection basics
Power System Protection basics
 
Training at 132 kv substation
Training at 132 kv substation Training at 132 kv substation
Training at 132 kv substation
 
Inplant training about 110kv/11kv substation
Inplant training about 110kv/11kv substationInplant training about 110kv/11kv substation
Inplant training about 110kv/11kv substation
 
Equipments of power transmission
Equipments of power transmissionEquipments of power transmission
Equipments of power transmission
 
Switchgear and protection lecture 1
Switchgear and protection lecture 1Switchgear and protection lecture 1
Switchgear and protection lecture 1
 
Substation
Substation Substation
Substation
 
presentation on substation layout and BUS bar arrangement.
presentation on substation layout and BUS bar arrangement.presentation on substation layout and BUS bar arrangement.
presentation on substation layout and BUS bar arrangement.
 
Principles of Cable Sizing
Principles of Cable SizingPrinciples of Cable Sizing
Principles of Cable Sizing
 
Siemens MV GIS Switchgear
Siemens MV GIS SwitchgearSiemens MV GIS Switchgear
Siemens MV GIS Switchgear
 
Overhead line work ppt
Overhead line work pptOverhead line work ppt
Overhead line work ppt
 
Practical handbook-for-relay-protection-engineers
Practical handbook-for-relay-protection-engineersPractical handbook-for-relay-protection-engineers
Practical handbook-for-relay-protection-engineers
 
Selective Coordination
Selective CoordinationSelective Coordination
Selective Coordination
 
FUNDAMENTALS OF POWER SYSTEM PROTECTION
FUNDAMENTALS OF POWER SYSTEM PROTECTIONFUNDAMENTALS OF POWER SYSTEM PROTECTION
FUNDAMENTALS OF POWER SYSTEM PROTECTION
 
Fault Level Calculation
Fault Level CalculationFault Level Calculation
Fault Level Calculation
 

Viewers also liked

Power system slide notes
Power system slide notesPower system slide notes
Power system slide notes
michaeljmack
 
Ge generator and ups problems
Ge generator and ups problemsGe generator and ups problems
Ge generator and ups problems
michaeljmack
 
2015 x472 class 01 - intro and system overview
2015 x472 class 01 - intro and system overview2015 x472 class 01 - intro and system overview
2015 x472 class 01 - intro and system overview
michaeljmack
 
Service cabinetandtransformerbreakersizing1082004
Service cabinetandtransformerbreakersizing1082004Service cabinetandtransformerbreakersizing1082004
Service cabinetandtransformerbreakersizing1082004
michaeljmack
 
Pullbox sizing
Pullbox sizingPullbox sizing
Pullbox sizing
michaeljmack
 
Substation design guideliness
Substation design guidelinessSubstation design guideliness
Substation design guideliness
michaeljmack
 
2015 x472 class 04 - central and specialty
2015 x472 class 04 - central and specialty2015 x472 class 04 - central and specialty
2015 x472 class 04 - central and specialty
michaeljmack
 
2015 x472 class 10 - lcca
2015 x472 class 10 - lcca2015 x472 class 10 - lcca
2015 x472 class 10 - lcca
michaeljmack
 
2015 x472 class 02 - generation systems
2015 x472 class 02 - generation systems2015 x472 class 02 - generation systems
2015 x472 class 02 - generation systems
michaeljmack
 
2015 x472 class 02 - generation systems
2015 x472 class 02 - generation systems2015 x472 class 02 - generation systems
2015 x472 class 02 - generation systems
michaeljmack
 
2015 x472 class 05 - system selection
2015 x472 class 05 - system selection2015 x472 class 05 - system selection
2015 x472 class 05 - system selection
michaeljmack
 
2015 x472 class 06- special building types
2015 x472 class 06- special building types2015 x472 class 06- special building types
2015 x472 class 06- special building types
michaeljmack
 
2006 01-16 evap techniques r seidl
2006 01-16 evap techniques r seidl2006 01-16 evap techniques r seidl
2006 01-16 evap techniques r seidl
michaeljmack
 
Grounding and bonding testing
Grounding and bonding testingGrounding and bonding testing
Grounding and bonding testing
michaeljmack
 
2015 x472 class 8 - codes, construction documentation and coordination
2015 x472 class 8 - codes, construction documentation and coordination2015 x472 class 8 - codes, construction documentation and coordination
2015 x472 class 8 - codes, construction documentation and coordination
michaeljmack
 
2015 x472 class 03 - distribution systems
2015 x472 class 03 - distribution systems2015 x472 class 03 - distribution systems
2015 x472 class 03 - distribution systems
michaeljmack
 
Nfpa 110 review
Nfpa 110 reviewNfpa 110 review
Nfpa 110 review
michaeljmack
 
Understanding overcurrent protection
Understanding overcurrent protectionUnderstanding overcurrent protection
Understanding overcurrent protection
michaeljmack
 
Nec emergency requirements
Nec emergency requirementsNec emergency requirements
Nec emergency requirements
michaeljmack
 
2015 x472 class 07 - system selection ii - pre-class
2015 x472 class 07 - system selection ii - pre-class2015 x472 class 07 - system selection ii - pre-class
2015 x472 class 07 - system selection ii - pre-class
michaeljmack
 

Viewers also liked (20)

Power system slide notes
Power system slide notesPower system slide notes
Power system slide notes
 
Ge generator and ups problems
Ge generator and ups problemsGe generator and ups problems
Ge generator and ups problems
 
2015 x472 class 01 - intro and system overview
2015 x472 class 01 - intro and system overview2015 x472 class 01 - intro and system overview
2015 x472 class 01 - intro and system overview
 
Service cabinetandtransformerbreakersizing1082004
Service cabinetandtransformerbreakersizing1082004Service cabinetandtransformerbreakersizing1082004
Service cabinetandtransformerbreakersizing1082004
 
Pullbox sizing
Pullbox sizingPullbox sizing
Pullbox sizing
 
Substation design guideliness
Substation design guidelinessSubstation design guideliness
Substation design guideliness
 
2015 x472 class 04 - central and specialty
2015 x472 class 04 - central and specialty2015 x472 class 04 - central and specialty
2015 x472 class 04 - central and specialty
 
2015 x472 class 10 - lcca
2015 x472 class 10 - lcca2015 x472 class 10 - lcca
2015 x472 class 10 - lcca
 
2015 x472 class 02 - generation systems
2015 x472 class 02 - generation systems2015 x472 class 02 - generation systems
2015 x472 class 02 - generation systems
 
2015 x472 class 02 - generation systems
2015 x472 class 02 - generation systems2015 x472 class 02 - generation systems
2015 x472 class 02 - generation systems
 
2015 x472 class 05 - system selection
2015 x472 class 05 - system selection2015 x472 class 05 - system selection
2015 x472 class 05 - system selection
 
2015 x472 class 06- special building types
2015 x472 class 06- special building types2015 x472 class 06- special building types
2015 x472 class 06- special building types
 
2006 01-16 evap techniques r seidl
2006 01-16 evap techniques r seidl2006 01-16 evap techniques r seidl
2006 01-16 evap techniques r seidl
 
Grounding and bonding testing
Grounding and bonding testingGrounding and bonding testing
Grounding and bonding testing
 
2015 x472 class 8 - codes, construction documentation and coordination
2015 x472 class 8 - codes, construction documentation and coordination2015 x472 class 8 - codes, construction documentation and coordination
2015 x472 class 8 - codes, construction documentation and coordination
 
2015 x472 class 03 - distribution systems
2015 x472 class 03 - distribution systems2015 x472 class 03 - distribution systems
2015 x472 class 03 - distribution systems
 
Nfpa 110 review
Nfpa 110 reviewNfpa 110 review
Nfpa 110 review
 
Understanding overcurrent protection
Understanding overcurrent protectionUnderstanding overcurrent protection
Understanding overcurrent protection
 
Nec emergency requirements
Nec emergency requirementsNec emergency requirements
Nec emergency requirements
 
2015 x472 class 07 - system selection ii - pre-class
2015 x472 class 07 - system selection ii - pre-class2015 x472 class 07 - system selection ii - pre-class
2015 x472 class 07 - system selection ii - pre-class
 

Similar to Electrical Lessons learned

ELECTRICITYWIRING REGULATION for safety of
ELECTRICITYWIRING REGULATION for safety ofELECTRICITYWIRING REGULATION for safety of
ELECTRICITYWIRING REGULATION for safety of
abdirahman gure
 
2005 16 autumn_wiring_matters__complete_no_adverts
2005 16 autumn_wiring_matters__complete_no_adverts2005 16 autumn_wiring_matters__complete_no_adverts
2005 16 autumn_wiring_matters__complete_no_advertsKhalid Sithari
 
CRITERIA FOR OVERHEAD TRANSMISSION LINE AMPACITY RATINGS
CRITERIA FOR OVERHEAD TRANSMISSION LINE AMPACITY RATINGSCRITERIA FOR OVERHEAD TRANSMISSION LINE AMPACITY RATINGS
CRITERIA FOR OVERHEAD TRANSMISSION LINE AMPACITY RATINGS
Archili Kokhtashvili
 
CPUC - General Orders 95, 128 & 165
CPUC - General Orders 95, 128 & 165CPUC - General Orders 95, 128 & 165
CPUC - General Orders 95, 128 & 165
michaeljmack
 
file-9.pptx
file-9.pptxfile-9.pptx
file-9.pptx
UdayMujumdar
 
file-9.pptx
file-9.pptxfile-9.pptx
file-9.pptx
SheelKapar1
 
20150209111021 tech spn dtd 29.jan 2015
20150209111021 tech spn dtd 29.jan 201520150209111021 tech spn dtd 29.jan 2015
20150209111021 tech spn dtd 29.jan 2015
JOTHIMANIKKAM SOMASUNDARAM
 
Engineer Mr. AR.Mohamed Iqbal Resume
Engineer Mr. AR.Mohamed Iqbal ResumeEngineer Mr. AR.Mohamed Iqbal Resume
Engineer Mr. AR.Mohamed Iqbal ResumeIqbal Mohamed
 
ITU-T K21 guide
ITU-T K21 guideITU-T K21 guide
ITU-T K21 guide
Flavio Dotta
 
Adoption of Best Practices for Cable Testing and Condition Monitoring In The ...
Adoption of Best Practices for Cable Testing and Condition Monitoring In The ...Adoption of Best Practices for Cable Testing and Condition Monitoring In The ...
Adoption of Best Practices for Cable Testing and Condition Monitoring In The ...
Thorne & Derrick International
 
Guidelines for electrical wiring in residential buildings
Guidelines for electrical wiring in residential buildings Guidelines for electrical wiring in residential buildings
Guidelines for electrical wiring in residential buildings Vijay Kumar
 
Assuring Reliability of Critical Power Cable Systems
Assuring Reliability of Critical Power Cable SystemsAssuring Reliability of Critical Power Cable Systems
Assuring Reliability of Critical Power Cable Systems
michaeljmack
 
P D Measurements On H V Joints
P D  Measurements On  H V JointsP D  Measurements On  H V Joints
P D Measurements On H V JointsAol_Amil
 
Fluke1748 - power quality measurements on overhead lines
Fluke1748 - power quality measurements  on overhead lines Fluke1748 - power quality measurements  on overhead lines
Fluke1748 - power quality measurements on overhead lines
Karol Bielecki
 
A study on IEC 60947- 2 amendments
A study on IEC 60947- 2 amendmentsA study on IEC 60947- 2 amendments
A study on IEC 60947- 2 amendments
richa diptisikha
 
Underground Cable Fault Detection Using Arduino
Underground Cable Fault Detection Using ArduinoUnderground Cable Fault Detection Using Arduino
Underground Cable Fault Detection Using Arduino
IRJET Journal
 
Time current curves
Time current curvesTime current curves
Time current curves
Rabah Zaimeddine
 
Bs 3871 mcb and mccb in ac circuits
Bs 3871 mcb and mccb in ac circuitsBs 3871 mcb and mccb in ac circuits
Bs 3871 mcb and mccb in ac circuits
Vasudev Mogili
 
Code questions
Code questionsCode questions
Code questions
michaeljmack
 
2311 s5500 checkout & comm. of elec. equip, rev. a 8
2311 s5500 checkout & comm. of elec. equip, rev. a 82311 s5500 checkout & comm. of elec. equip, rev. a 8
2311 s5500 checkout & comm. of elec. equip, rev. a 8
Olusegun Abode
 

Similar to Electrical Lessons learned (20)

ELECTRICITYWIRING REGULATION for safety of
ELECTRICITYWIRING REGULATION for safety ofELECTRICITYWIRING REGULATION for safety of
ELECTRICITYWIRING REGULATION for safety of
 
2005 16 autumn_wiring_matters__complete_no_adverts
2005 16 autumn_wiring_matters__complete_no_adverts2005 16 autumn_wiring_matters__complete_no_adverts
2005 16 autumn_wiring_matters__complete_no_adverts
 
CRITERIA FOR OVERHEAD TRANSMISSION LINE AMPACITY RATINGS
CRITERIA FOR OVERHEAD TRANSMISSION LINE AMPACITY RATINGSCRITERIA FOR OVERHEAD TRANSMISSION LINE AMPACITY RATINGS
CRITERIA FOR OVERHEAD TRANSMISSION LINE AMPACITY RATINGS
 
CPUC - General Orders 95, 128 & 165
CPUC - General Orders 95, 128 & 165CPUC - General Orders 95, 128 & 165
CPUC - General Orders 95, 128 & 165
 
file-9.pptx
file-9.pptxfile-9.pptx
file-9.pptx
 
file-9.pptx
file-9.pptxfile-9.pptx
file-9.pptx
 
20150209111021 tech spn dtd 29.jan 2015
20150209111021 tech spn dtd 29.jan 201520150209111021 tech spn dtd 29.jan 2015
20150209111021 tech spn dtd 29.jan 2015
 
Engineer Mr. AR.Mohamed Iqbal Resume
Engineer Mr. AR.Mohamed Iqbal ResumeEngineer Mr. AR.Mohamed Iqbal Resume
Engineer Mr. AR.Mohamed Iqbal Resume
 
ITU-T K21 guide
ITU-T K21 guideITU-T K21 guide
ITU-T K21 guide
 
Adoption of Best Practices for Cable Testing and Condition Monitoring In The ...
Adoption of Best Practices for Cable Testing and Condition Monitoring In The ...Adoption of Best Practices for Cable Testing and Condition Monitoring In The ...
Adoption of Best Practices for Cable Testing and Condition Monitoring In The ...
 
Guidelines for electrical wiring in residential buildings
Guidelines for electrical wiring in residential buildings Guidelines for electrical wiring in residential buildings
Guidelines for electrical wiring in residential buildings
 
Assuring Reliability of Critical Power Cable Systems
Assuring Reliability of Critical Power Cable SystemsAssuring Reliability of Critical Power Cable Systems
Assuring Reliability of Critical Power Cable Systems
 
P D Measurements On H V Joints
P D  Measurements On  H V JointsP D  Measurements On  H V Joints
P D Measurements On H V Joints
 
Fluke1748 - power quality measurements on overhead lines
Fluke1748 - power quality measurements  on overhead lines Fluke1748 - power quality measurements  on overhead lines
Fluke1748 - power quality measurements on overhead lines
 
A study on IEC 60947- 2 amendments
A study on IEC 60947- 2 amendmentsA study on IEC 60947- 2 amendments
A study on IEC 60947- 2 amendments
 
Underground Cable Fault Detection Using Arduino
Underground Cable Fault Detection Using ArduinoUnderground Cable Fault Detection Using Arduino
Underground Cable Fault Detection Using Arduino
 
Time current curves
Time current curvesTime current curves
Time current curves
 
Bs 3871 mcb and mccb in ac circuits
Bs 3871 mcb and mccb in ac circuitsBs 3871 mcb and mccb in ac circuits
Bs 3871 mcb and mccb in ac circuits
 
Code questions
Code questionsCode questions
Code questions
 
2311 s5500 checkout & comm. of elec. equip, rev. a 8
2311 s5500 checkout & comm. of elec. equip, rev. a 82311 s5500 checkout & comm. of elec. equip, rev. a 8
2311 s5500 checkout & comm. of elec. equip, rev. a 8
 

More from michaeljmack

Auburn, NY - 200 Years of History 1793-1993
Auburn, NY - 200 Years of History  1793-1993Auburn, NY - 200 Years of History  1793-1993
Auburn, NY - 200 Years of History 1793-1993
michaeljmack
 
Auburn High School, Auburn, NY, 1982 Yearbook
Auburn High School, Auburn, NY, 1982 YearbookAuburn High School, Auburn, NY, 1982 Yearbook
Auburn High School, Auburn, NY, 1982 Yearbook
michaeljmack
 
Auburn High School, Auburn, NY, 1980 Yearbook
Auburn High School, Auburn, NY, 1980 YearbookAuburn High School, Auburn, NY, 1980 Yearbook
Auburn High School, Auburn, NY, 1980 Yearbook
michaeljmack
 
Surge Protection
Surge ProtectionSurge Protection
Surge Protection
michaeljmack
 
Diesel Particulate Filters Control Systems
Diesel Particulate Filters Control SystemsDiesel Particulate Filters Control Systems
Diesel Particulate Filters Control Systems
michaeljmack
 
Understanding Arc Flash
Understanding Arc FlashUnderstanding Arc Flash
Understanding Arc Flash
michaeljmack
 
Fundamentals of transformer inrush
Fundamentals of transformer inrushFundamentals of transformer inrush
Fundamentals of transformer inrush
michaeljmack
 
Building information modeling
Building information modelingBuilding information modeling
Building information modeling
michaeljmack
 
15 years of experience stator ground fault protection
15 years of experience stator ground fault protection15 years of experience stator ground fault protection
15 years of experience stator ground fault protection
michaeljmack
 
Emergency, Legally Required and Optional Standby Systems
Emergency, Legally Required and Optional Standby SystemsEmergency, Legally Required and Optional Standby Systems
Emergency, Legally Required and Optional Standby Systems
michaeljmack
 
Lighting Control Solutions for Daylit Spaces
Lighting Control Solutions for Daylit SpacesLighting Control Solutions for Daylit Spaces
Lighting Control Solutions for Daylit Spaces
michaeljmack
 
COPS: An Arresting Look at NEC Article 708
COPS: An Arresting Look at NEC Article 708COPS: An Arresting Look at NEC Article 708
COPS: An Arresting Look at NEC Article 708
michaeljmack
 
Seismic Compliance of Electrical Distribution
Seismic Compliance of Electrical DistributionSeismic Compliance of Electrical Distribution
Seismic Compliance of Electrical Distribution
michaeljmack
 
Generator Set Transient Performance
Generator Set Transient PerformanceGenerator Set Transient Performance
Generator Set Transient Performance
michaeljmack
 
Modeling of a digital protective relay in a RT Digital Simulator
Modeling of a digital protective relay in a RT Digital SimulatorModeling of a digital protective relay in a RT Digital Simulator
Modeling of a digital protective relay in a RT Digital Simulator
michaeljmack
 
Facts on Grid Friendly Wind Plants
Facts on Grid Friendly Wind PlantsFacts on Grid Friendly Wind Plants
Facts on Grid Friendly Wind Plants
michaeljmack
 
Power Plant Horror Stories
Power Plant Horror StoriesPower Plant Horror Stories
Power Plant Horror Stories
michaeljmack
 
Blackout Avoidance & Undervoltage Load Shedding
Blackout Avoidance & Undervoltage Load SheddingBlackout Avoidance & Undervoltage Load Shedding
Blackout Avoidance & Undervoltage Load Shedding
michaeljmack
 
Transformer Fundamentals
Transformer FundamentalsTransformer Fundamentals
Transformer Fundamentals
michaeljmack
 
Arc Flash
Arc FlashArc Flash
Arc Flash
michaeljmack
 

More from michaeljmack (20)

Auburn, NY - 200 Years of History 1793-1993
Auburn, NY - 200 Years of History  1793-1993Auburn, NY - 200 Years of History  1793-1993
Auburn, NY - 200 Years of History 1793-1993
 
Auburn High School, Auburn, NY, 1982 Yearbook
Auburn High School, Auburn, NY, 1982 YearbookAuburn High School, Auburn, NY, 1982 Yearbook
Auburn High School, Auburn, NY, 1982 Yearbook
 
Auburn High School, Auburn, NY, 1980 Yearbook
Auburn High School, Auburn, NY, 1980 YearbookAuburn High School, Auburn, NY, 1980 Yearbook
Auburn High School, Auburn, NY, 1980 Yearbook
 
Surge Protection
Surge ProtectionSurge Protection
Surge Protection
 
Diesel Particulate Filters Control Systems
Diesel Particulate Filters Control SystemsDiesel Particulate Filters Control Systems
Diesel Particulate Filters Control Systems
 
Understanding Arc Flash
Understanding Arc FlashUnderstanding Arc Flash
Understanding Arc Flash
 
Fundamentals of transformer inrush
Fundamentals of transformer inrushFundamentals of transformer inrush
Fundamentals of transformer inrush
 
Building information modeling
Building information modelingBuilding information modeling
Building information modeling
 
15 years of experience stator ground fault protection
15 years of experience stator ground fault protection15 years of experience stator ground fault protection
15 years of experience stator ground fault protection
 
Emergency, Legally Required and Optional Standby Systems
Emergency, Legally Required and Optional Standby SystemsEmergency, Legally Required and Optional Standby Systems
Emergency, Legally Required and Optional Standby Systems
 
Lighting Control Solutions for Daylit Spaces
Lighting Control Solutions for Daylit SpacesLighting Control Solutions for Daylit Spaces
Lighting Control Solutions for Daylit Spaces
 
COPS: An Arresting Look at NEC Article 708
COPS: An Arresting Look at NEC Article 708COPS: An Arresting Look at NEC Article 708
COPS: An Arresting Look at NEC Article 708
 
Seismic Compliance of Electrical Distribution
Seismic Compliance of Electrical DistributionSeismic Compliance of Electrical Distribution
Seismic Compliance of Electrical Distribution
 
Generator Set Transient Performance
Generator Set Transient PerformanceGenerator Set Transient Performance
Generator Set Transient Performance
 
Modeling of a digital protective relay in a RT Digital Simulator
Modeling of a digital protective relay in a RT Digital SimulatorModeling of a digital protective relay in a RT Digital Simulator
Modeling of a digital protective relay in a RT Digital Simulator
 
Facts on Grid Friendly Wind Plants
Facts on Grid Friendly Wind PlantsFacts on Grid Friendly Wind Plants
Facts on Grid Friendly Wind Plants
 
Power Plant Horror Stories
Power Plant Horror StoriesPower Plant Horror Stories
Power Plant Horror Stories
 
Blackout Avoidance & Undervoltage Load Shedding
Blackout Avoidance & Undervoltage Load SheddingBlackout Avoidance & Undervoltage Load Shedding
Blackout Avoidance & Undervoltage Load Shedding
 
Transformer Fundamentals
Transformer FundamentalsTransformer Fundamentals
Transformer Fundamentals
 
Arc Flash
Arc FlashArc Flash
Arc Flash
 

Recently uploaded

Student information management system project report ii.pdf
Student information management system project report ii.pdfStudent information management system project report ii.pdf
Student information management system project report ii.pdf
Kamal Acharya
 
AKS UNIVERSITY Satna Final Year Project By OM Hardaha.pdf
AKS UNIVERSITY Satna Final Year Project By OM Hardaha.pdfAKS UNIVERSITY Satna Final Year Project By OM Hardaha.pdf
AKS UNIVERSITY Satna Final Year Project By OM Hardaha.pdf
SamSarthak3
 
Hierarchical Digital Twin of a Naval Power System
Hierarchical Digital Twin of a Naval Power SystemHierarchical Digital Twin of a Naval Power System
Hierarchical Digital Twin of a Naval Power System
Kerry Sado
 
Top 10 Oil and Gas Projects in Saudi Arabia 2024.pdf
Top 10 Oil and Gas Projects in Saudi Arabia 2024.pdfTop 10 Oil and Gas Projects in Saudi Arabia 2024.pdf
Top 10 Oil and Gas Projects in Saudi Arabia 2024.pdf
Teleport Manpower Consultant
 
Swimming pool mechanical components design.pptx
Swimming pool  mechanical components design.pptxSwimming pool  mechanical components design.pptx
Swimming pool mechanical components design.pptx
yokeleetan1
 
DfMAy 2024 - key insights and contributions
DfMAy 2024 - key insights and contributionsDfMAy 2024 - key insights and contributions
DfMAy 2024 - key insights and contributions
gestioneergodomus
 
Pile Foundation by Venkatesh Taduvai (Sub Geotechnical Engineering II)-conver...
Pile Foundation by Venkatesh Taduvai (Sub Geotechnical Engineering II)-conver...Pile Foundation by Venkatesh Taduvai (Sub Geotechnical Engineering II)-conver...
Pile Foundation by Venkatesh Taduvai (Sub Geotechnical Engineering II)-conver...
AJAYKUMARPUND1
 
Final project report on grocery store management system..pdf
Final project report on grocery store management system..pdfFinal project report on grocery store management system..pdf
Final project report on grocery store management system..pdf
Kamal Acharya
 
An Approach to Detecting Writing Styles Based on Clustering Techniques
An Approach to Detecting Writing Styles Based on Clustering TechniquesAn Approach to Detecting Writing Styles Based on Clustering Techniques
An Approach to Detecting Writing Styles Based on Clustering Techniques
ambekarshweta25
 
Modelagem de um CSTR com reação endotermica.pdf
Modelagem de um CSTR com reação endotermica.pdfModelagem de um CSTR com reação endotermica.pdf
Modelagem de um CSTR com reação endotermica.pdf
camseq
 
一比一原版(IIT毕业证)伊利诺伊理工大学毕业证成绩单专业办理
一比一原版(IIT毕业证)伊利诺伊理工大学毕业证成绩单专业办理一比一原版(IIT毕业证)伊利诺伊理工大学毕业证成绩单专业办理
一比一原版(IIT毕业证)伊利诺伊理工大学毕业证成绩单专业办理
zwunae
 
Design and Analysis of Algorithms-DP,Backtracking,Graphs,B&B
Design and Analysis of Algorithms-DP,Backtracking,Graphs,B&BDesign and Analysis of Algorithms-DP,Backtracking,Graphs,B&B
Design and Analysis of Algorithms-DP,Backtracking,Graphs,B&B
Sreedhar Chowdam
 
MCQ Soil mechanics questions (Soil shear strength).pdf
MCQ Soil mechanics questions (Soil shear strength).pdfMCQ Soil mechanics questions (Soil shear strength).pdf
MCQ Soil mechanics questions (Soil shear strength).pdf
Osamah Alsalih
 
Recycled Concrete Aggregate in Construction Part III
Recycled Concrete Aggregate in Construction Part IIIRecycled Concrete Aggregate in Construction Part III
Recycled Concrete Aggregate in Construction Part III
Aditya Rajan Patra
 
Online aptitude test management system project report.pdf
Online aptitude test management system project report.pdfOnline aptitude test management system project report.pdf
Online aptitude test management system project report.pdf
Kamal Acharya
 
Unbalanced Three Phase Systems and circuits.pptx
Unbalanced Three Phase Systems and circuits.pptxUnbalanced Three Phase Systems and circuits.pptx
Unbalanced Three Phase Systems and circuits.pptx
ChristineTorrepenida1
 
一比一原版(UMich毕业证)密歇根大学|安娜堡分校毕业证成绩单专业办理
一比一原版(UMich毕业证)密歇根大学|安娜堡分校毕业证成绩单专业办理一比一原版(UMich毕业证)密歇根大学|安娜堡分校毕业证成绩单专业办理
一比一原版(UMich毕业证)密歇根大学|安娜堡分校毕业证成绩单专业办理
zwunae
 
Sachpazis:Terzaghi Bearing Capacity Estimation in simple terms with Calculati...
Sachpazis:Terzaghi Bearing Capacity Estimation in simple terms with Calculati...Sachpazis:Terzaghi Bearing Capacity Estimation in simple terms with Calculati...
Sachpazis:Terzaghi Bearing Capacity Estimation in simple terms with Calculati...
Dr.Costas Sachpazis
 
一比一原版(SFU毕业证)西蒙菲莎大学毕业证成绩单如何办理
一比一原版(SFU毕业证)西蒙菲莎大学毕业证成绩单如何办理一比一原版(SFU毕业证)西蒙菲莎大学毕业证成绩单如何办理
一比一原版(SFU毕业证)西蒙菲莎大学毕业证成绩单如何办理
bakpo1
 
Technical Drawings introduction to drawing of prisms
Technical Drawings introduction to drawing of prismsTechnical Drawings introduction to drawing of prisms
Technical Drawings introduction to drawing of prisms
heavyhaig
 

Recently uploaded (20)

Student information management system project report ii.pdf
Student information management system project report ii.pdfStudent information management system project report ii.pdf
Student information management system project report ii.pdf
 
AKS UNIVERSITY Satna Final Year Project By OM Hardaha.pdf
AKS UNIVERSITY Satna Final Year Project By OM Hardaha.pdfAKS UNIVERSITY Satna Final Year Project By OM Hardaha.pdf
AKS UNIVERSITY Satna Final Year Project By OM Hardaha.pdf
 
Hierarchical Digital Twin of a Naval Power System
Hierarchical Digital Twin of a Naval Power SystemHierarchical Digital Twin of a Naval Power System
Hierarchical Digital Twin of a Naval Power System
 
Top 10 Oil and Gas Projects in Saudi Arabia 2024.pdf
Top 10 Oil and Gas Projects in Saudi Arabia 2024.pdfTop 10 Oil and Gas Projects in Saudi Arabia 2024.pdf
Top 10 Oil and Gas Projects in Saudi Arabia 2024.pdf
 
Swimming pool mechanical components design.pptx
Swimming pool  mechanical components design.pptxSwimming pool  mechanical components design.pptx
Swimming pool mechanical components design.pptx
 
DfMAy 2024 - key insights and contributions
DfMAy 2024 - key insights and contributionsDfMAy 2024 - key insights and contributions
DfMAy 2024 - key insights and contributions
 
Pile Foundation by Venkatesh Taduvai (Sub Geotechnical Engineering II)-conver...
Pile Foundation by Venkatesh Taduvai (Sub Geotechnical Engineering II)-conver...Pile Foundation by Venkatesh Taduvai (Sub Geotechnical Engineering II)-conver...
Pile Foundation by Venkatesh Taduvai (Sub Geotechnical Engineering II)-conver...
 
Final project report on grocery store management system..pdf
Final project report on grocery store management system..pdfFinal project report on grocery store management system..pdf
Final project report on grocery store management system..pdf
 
An Approach to Detecting Writing Styles Based on Clustering Techniques
An Approach to Detecting Writing Styles Based on Clustering TechniquesAn Approach to Detecting Writing Styles Based on Clustering Techniques
An Approach to Detecting Writing Styles Based on Clustering Techniques
 
Modelagem de um CSTR com reação endotermica.pdf
Modelagem de um CSTR com reação endotermica.pdfModelagem de um CSTR com reação endotermica.pdf
Modelagem de um CSTR com reação endotermica.pdf
 
一比一原版(IIT毕业证)伊利诺伊理工大学毕业证成绩单专业办理
一比一原版(IIT毕业证)伊利诺伊理工大学毕业证成绩单专业办理一比一原版(IIT毕业证)伊利诺伊理工大学毕业证成绩单专业办理
一比一原版(IIT毕业证)伊利诺伊理工大学毕业证成绩单专业办理
 
Design and Analysis of Algorithms-DP,Backtracking,Graphs,B&B
Design and Analysis of Algorithms-DP,Backtracking,Graphs,B&BDesign and Analysis of Algorithms-DP,Backtracking,Graphs,B&B
Design and Analysis of Algorithms-DP,Backtracking,Graphs,B&B
 
MCQ Soil mechanics questions (Soil shear strength).pdf
MCQ Soil mechanics questions (Soil shear strength).pdfMCQ Soil mechanics questions (Soil shear strength).pdf
MCQ Soil mechanics questions (Soil shear strength).pdf
 
Recycled Concrete Aggregate in Construction Part III
Recycled Concrete Aggregate in Construction Part IIIRecycled Concrete Aggregate in Construction Part III
Recycled Concrete Aggregate in Construction Part III
 
Online aptitude test management system project report.pdf
Online aptitude test management system project report.pdfOnline aptitude test management system project report.pdf
Online aptitude test management system project report.pdf
 
Unbalanced Three Phase Systems and circuits.pptx
Unbalanced Three Phase Systems and circuits.pptxUnbalanced Three Phase Systems and circuits.pptx
Unbalanced Three Phase Systems and circuits.pptx
 
一比一原版(UMich毕业证)密歇根大学|安娜堡分校毕业证成绩单专业办理
一比一原版(UMich毕业证)密歇根大学|安娜堡分校毕业证成绩单专业办理一比一原版(UMich毕业证)密歇根大学|安娜堡分校毕业证成绩单专业办理
一比一原版(UMich毕业证)密歇根大学|安娜堡分校毕业证成绩单专业办理
 
Sachpazis:Terzaghi Bearing Capacity Estimation in simple terms with Calculati...
Sachpazis:Terzaghi Bearing Capacity Estimation in simple terms with Calculati...Sachpazis:Terzaghi Bearing Capacity Estimation in simple terms with Calculati...
Sachpazis:Terzaghi Bearing Capacity Estimation in simple terms with Calculati...
 
一比一原版(SFU毕业证)西蒙菲莎大学毕业证成绩单如何办理
一比一原版(SFU毕业证)西蒙菲莎大学毕业证成绩单如何办理一比一原版(SFU毕业证)西蒙菲莎大学毕业证成绩单如何办理
一比一原版(SFU毕业证)西蒙菲莎大学毕业证成绩单如何办理
 
Technical Drawings introduction to drawing of prisms
Technical Drawings introduction to drawing of prismsTechnical Drawings introduction to drawing of prisms
Technical Drawings introduction to drawing of prisms
 

Electrical Lessons learned

  • 1. Waste Treatment Plant Project Lessons Learned Construction Electrical Ron Clements P.E, PMP Lead Electrical Engineer Temporary Power October 6, 2009
  • 2. 2 Syllabus  Project Inspection Records  Material Acquisitions (Procurement)  Sub-Contractor Equipment  NEC Common Pitfalls  Arc-Flash  Grounding Assurance  Conex Box Electrical Violations  Medium Voltage Program  Performance Improvements 2
  • 3. 3 Project Records  Project Start/Stop  Lost or missing inspection records  Time loss  Re-work 3
  • 4. 4 Material Acquisitions (Procurement)  Supplier compliance with NEC requirements  Lack of UL or other NRTL listings for equipment  Code compliant issues with components and assemblies  Foreign equipment (i.e., Potain Cranes/Material Lifts)  NRTL inspections and corresponding corrective actions for supplier equipment 4
  • 5. 5 Sub-Contractor Equipment  NEC code requirements issues  Concrete batch plant  OCPD sizing  Conductor sizing  Grounding  Aging equipment
  • 6. 6 NEC Common Pitfalls  Article 110.3(B) requires listed or labeled equipment to be installed and used in accordance with any instructions included in the listing or labeling.  Article 110.22 requires each disconnecting means to be legibly marked to indicate its purpose.  Article 110.26(A)(1) requires a three-foot working clearance in front of the panelboards. (A)(2) Requires width of the working space in front of the electric equipment to be the width of the equipment or 30 inches, whichever is greater. (A)(3) Requires the work space to be clear and extend from the grade, floor, or platform to 6½ feet, or where the equipment exceeds 6½ feet, the minimum headroom shall not be less than the height of the equipment.
  • 7. 7 NEC Common Pitfalls (cont)  Article 240.5 requires flexible cord and flexible cable to be protected by an overcurrent device in accordance with their ampacity as specified in Table 400.5(A) and Table 400.5(B).  Article 250.122 requires the equipment grounding conductor to be sized based off the overcurrent device ahead of the equipment.  Article 700.12(E)(4) requires the branch circuit feeding the emergency lighting to be the same branch circuit as that serving the normal lighting in that area.  Article 725 (A) requires cables and conductors of Class 2 and Class 3 circuits to not be placed in any cable, cable tray, compartment, enclosure, manhole, outlet box, raceway, or similar fitting with conductors of electric light, power, and Class 1 circuits.
  • 8. 8 Arc-Flash  Evolution of WTP Arc-Flash  Hanford Calculator  ETAP Software  Field evaluations  Identify equipment type  Fuse studies  Circuit breaker studies  Single-line verification  ETAP software data Input  Cross checking performed during data input
  • 12. 12 Grounding Assurance  Grounding requirements for 240 and 480 volt cord sets  480 volt heater cord set wiring  Manufacturer cord and cap (burned in field)  Replaced with a 30A cord cap and #10 wire
  • 16. 16 Conex Box Electrical Violations  Systematic control of temporary power to these types of temporary structures  Multiple source feeds to conex  Extension cords being ran through door ways or windows  Bonding/grounding not in accordance to NEC  No proper disconnecting means  No procedure in place to control temporary power in these conex’s
  • 17. 17 Medium Voltage Program  WTP Substations 1-16  OSHA 29 CFR 1910.269  Medium Voltage training (Manual/Non-Manual)  Use of 13.8KV testing equipment  Installation of Grounding clusters  LO/TO (Capacitive Test Points) – In ability of voltage verification during LO/TO process  Replacement of dead breaks (allows for voltage measurement on each feeder and the ability to install a grounding cluster
  • 18. 18 WTP Substation and Switchboard
  • 20. 20 Summary  Implementing of enhanced supplier electrical equipment code inspection oversight  NEC inspectors designated to each facility  NRTL certified inspector designated for construction equipment  Implementing NEC code compliant inspections of temporary power and sub-contractor electrical installations; this includes developing a comprehensive NEC inspection training program that has emphasized lessons learned from past problems at the WTP  Improving electrical design code compliance performance by emphasizing code requirements and providing lessons-learned feedback from previous WTP compliance issues
  • 21. 21 Summary  Procuring medium voltage equipment and implementing medium voltage training to electrical craft and supervision  Improving the WTP LO/TO program to go beyond typical required construction LO/TO to that required by operation organizations (29 CFR 1910 vs. 29 CFR 1926)  Fully implementing the NFPA worker safety requirements 21
  • 22. 22 WTP August 2009 Pretreatment Facility Administration Building Temporary Warehouse Temporary Combination & Fabrication Shop High-Level Waste Facility Low-Activity Waste Facility Two Concrete Batch Plants Analytical Lab