This document discusses the commissioning process and tests for various electrical equipment, including current transformers, voltage transformers, circuit breakers, isolators, switchgear, busbars, cables, and protection relays. It provides checklists of tests and inspections to ensure equipment is properly installed and functioning correctly before being placed into service. These tests help demonstrate equipment was not damaged during transit, is installed correctly, meets specifications, and protections are correctly set based on calculations.
The apparatus used for switching, controlling & protecting the electrical circuits & equipments are known as switchgear.
The switchgear equipments is essentially used with switching & interrupting currents either under normal or abnormal operating condition.
It consists of devices such as switches, fuses, circuit breakers, relays etc.
Basically every electric circuit needs a switching device & a protecting device.
Cables are often the last component considered during system design even if in many situations cables are the true system’s lifeline: if a cable fails, the entire system may stop. Cable reliability is therefore extremely important, then a cable system should be engineered to last the life of the system in the installation environment for the required application. Environments in which cable systems are being used are often challenging, as extreme temperatures, chemicals, abrasion, and extensive flexing. These variables have a direct impact on the materials used for cable insulation and jacketing as well as the construction of the cable. Using a systematic approach will help ensure that designer select the best cable for the required application in the installation environment. This lessons will provide students main guidelines for perform this approach.
Unit I: Introduction to Protection System:
Introduction to protection system and its elements, functions of protective relaying, protective zones, primary and backup protection, desirable qualities of protective relaying, basic terminology.
Relays:
Electromagnetic, attracted and induction type relays, thermal relay, gas actuated relay, design considerations of electromagnetic relay.
Unit-II: Relay Application and Characteristics:
Amplitude and phase comparators, over current relays, directional relays, distance relays, differential relay.
Static Relays: Comparison with electromagnetic relay, classification and their description, over current relays, directional relay, distance relays, differential relay.
Unit-III Protection of Transmission Line:
Over current protection, distance protection, pilot wire protection, carrier current protection, protection of bus, auto re-closing,
Unit-IV: Circuit Breaking:
Properties of arc, arc extinction theories, re-striking voltage transient, current chopping, resistance switching, capacitive current interruption, short line interruption, circuit breaker ratings.
Testing Of Circuit Breaker: Classification, testing station and equipments, testing procedure, direct and indirect testing.
Unit-V Apparatus Protection:
Protection of Transformer, generator and motor.
Circuit Breaker: Operating modes, selection of circuit breakers, constructional features and operation of Bulk Oil, Minimum Oil, Air Blast, SF6, Vacuum and d. c. circuit breakers.
The apparatus used for switching, controlling & protecting the electrical circuits & equipments are known as switchgear.
The switchgear equipments is essentially used with switching & interrupting currents either under normal or abnormal operating condition.
It consists of devices such as switches, fuses, circuit breakers, relays etc.
Basically every electric circuit needs a switching device & a protecting device.
Cables are often the last component considered during system design even if in many situations cables are the true system’s lifeline: if a cable fails, the entire system may stop. Cable reliability is therefore extremely important, then a cable system should be engineered to last the life of the system in the installation environment for the required application. Environments in which cable systems are being used are often challenging, as extreme temperatures, chemicals, abrasion, and extensive flexing. These variables have a direct impact on the materials used for cable insulation and jacketing as well as the construction of the cable. Using a systematic approach will help ensure that designer select the best cable for the required application in the installation environment. This lessons will provide students main guidelines for perform this approach.
Unit I: Introduction to Protection System:
Introduction to protection system and its elements, functions of protective relaying, protective zones, primary and backup protection, desirable qualities of protective relaying, basic terminology.
Relays:
Electromagnetic, attracted and induction type relays, thermal relay, gas actuated relay, design considerations of electromagnetic relay.
Unit-II: Relay Application and Characteristics:
Amplitude and phase comparators, over current relays, directional relays, distance relays, differential relay.
Static Relays: Comparison with electromagnetic relay, classification and their description, over current relays, directional relay, distance relays, differential relay.
Unit-III Protection of Transmission Line:
Over current protection, distance protection, pilot wire protection, carrier current protection, protection of bus, auto re-closing,
Unit-IV: Circuit Breaking:
Properties of arc, arc extinction theories, re-striking voltage transient, current chopping, resistance switching, capacitive current interruption, short line interruption, circuit breaker ratings.
Testing Of Circuit Breaker: Classification, testing station and equipments, testing procedure, direct and indirect testing.
Unit-V Apparatus Protection:
Protection of Transformer, generator and motor.
Circuit Breaker: Operating modes, selection of circuit breakers, constructional features and operation of Bulk Oil, Minimum Oil, Air Blast, SF6, Vacuum and d. c. circuit breakers.
A switchgear or electrical switchgear is a generic term which includes all the switching devices associated with mainly power system protection. It also includes all devices associated with control, metering and regulating of electrical power system. Assembly of such devices in a logical manner forms a switchgear. This is the very basic definition of switchgear.
⋗To get more with details
https://www.youtube.com/channel/UC2SvKI7eepP241VLoui1D5A
This Presentation is about l.v switch gear design, presented during the graduation project final discussion 15/7/2018.
It presented a good summary of switch gear components and types and practicing on AL.HAMOOL W.T.P M.D.B design using SIEMENS SIVACON S8
How to work safely while working with electricity or electrical equipment. what are the safety rules to be followed? what is the safe system of work while working on electrical equipment. what kind of safety components to be used in place?
Power cable selection, cable selection Methodology wessam alaslmi
Cable installation and Selection Methodology according to IEC code supported with an example of how to do so.
Explain what practical environment requires when establishing a new facility requires electricity.
explain the purpose of the selected cable.
explain when to use the cable carrier types.
explain how to carry out calculations of such thing.
The standard electromechanical RCCBs are designed to work with normal waveform power and cannot be guaranteed to work if any standard waveforms are generated by loads. The most common is the rectified half-wave waveform, sometimes referred to as pulsed direct current, generated by speed control devices, semiconductors, computers, and even dimmers.
Principles of Cable Sizing; current carrying capacity, voltage drop, short circuit.
Cables are often the last component considered during system design even if in many situations cables are the true system’s lifeline: if a cable fails, the entire system may stop. Cable reliability is therefore extremely important, then a cable system should be engineered to last the life of the system in the installation environment for the required application. Environments in which cable systems are being used are often challenging, as extreme temperatures, chemicals, abrasion, and extensive flexing. These variables have a direct impact on the materials used for cable insulation and jacketing as well as the construction of the cable. Using a systematic approach will help ensure that designer select the best cable for the required application in the installation environment. This lessons will provide students main guidelines for perform this approach.
Installation Operation & Maintenance of 33kV & 11kV SwitchgearSheikh Nazmul Islam
In-Country Training On Operation, Maintenance, Protection & Control of 33/11 kV Substation Project Name: Design, Supply, Installation, Testing & Commissioning of 33/11 kV sub-stations with source end feeder bays. Contract No: BREB/UREDS/W-01A-001/02/2016-2017 BREB/UREDS/W-01A-002/03/2016-2017 BREB/UREDS/W-01A-004/04/2016-2017
Over much of the 20th century, utilities, regulators and customers each relied upon lab and field meter testing efforts which were primarily focused upon the accuracy of the watt-hour meter and demand register. This focus is now changing with overwhelming deployment of electronic meters and significant deployment of AMR and AMI meters throughout the installed base in North America.
Meter Failure modes are changing. More meters are rejected for functional test failures than accuracy tests. One of the benefits of AMI is that utilities can spend less time on residential metering and focus their meter techs on their more complex metering operations. More time can and should be spent inspecting and testing the Transformer rated installations in each utilities service territory.
Presented at the Mid-South Electric Metering Association 2015.
A switchgear or electrical switchgear is a generic term which includes all the switching devices associated with mainly power system protection. It also includes all devices associated with control, metering and regulating of electrical power system. Assembly of such devices in a logical manner forms a switchgear. This is the very basic definition of switchgear.
⋗To get more with details
https://www.youtube.com/channel/UC2SvKI7eepP241VLoui1D5A
This Presentation is about l.v switch gear design, presented during the graduation project final discussion 15/7/2018.
It presented a good summary of switch gear components and types and practicing on AL.HAMOOL W.T.P M.D.B design using SIEMENS SIVACON S8
How to work safely while working with electricity or electrical equipment. what are the safety rules to be followed? what is the safe system of work while working on electrical equipment. what kind of safety components to be used in place?
Power cable selection, cable selection Methodology wessam alaslmi
Cable installation and Selection Methodology according to IEC code supported with an example of how to do so.
Explain what practical environment requires when establishing a new facility requires electricity.
explain the purpose of the selected cable.
explain when to use the cable carrier types.
explain how to carry out calculations of such thing.
The standard electromechanical RCCBs are designed to work with normal waveform power and cannot be guaranteed to work if any standard waveforms are generated by loads. The most common is the rectified half-wave waveform, sometimes referred to as pulsed direct current, generated by speed control devices, semiconductors, computers, and even dimmers.
Principles of Cable Sizing; current carrying capacity, voltage drop, short circuit.
Cables are often the last component considered during system design even if in many situations cables are the true system’s lifeline: if a cable fails, the entire system may stop. Cable reliability is therefore extremely important, then a cable system should be engineered to last the life of the system in the installation environment for the required application. Environments in which cable systems are being used are often challenging, as extreme temperatures, chemicals, abrasion, and extensive flexing. These variables have a direct impact on the materials used for cable insulation and jacketing as well as the construction of the cable. Using a systematic approach will help ensure that designer select the best cable for the required application in the installation environment. This lessons will provide students main guidelines for perform this approach.
Installation Operation & Maintenance of 33kV & 11kV SwitchgearSheikh Nazmul Islam
In-Country Training On Operation, Maintenance, Protection & Control of 33/11 kV Substation Project Name: Design, Supply, Installation, Testing & Commissioning of 33/11 kV sub-stations with source end feeder bays. Contract No: BREB/UREDS/W-01A-001/02/2016-2017 BREB/UREDS/W-01A-002/03/2016-2017 BREB/UREDS/W-01A-004/04/2016-2017
Over much of the 20th century, utilities, regulators and customers each relied upon lab and field meter testing efforts which were primarily focused upon the accuracy of the watt-hour meter and demand register. This focus is now changing with overwhelming deployment of electronic meters and significant deployment of AMR and AMI meters throughout the installed base in North America.
Meter Failure modes are changing. More meters are rejected for functional test failures than accuracy tests. One of the benefits of AMI is that utilities can spend less time on residential metering and focus their meter techs on their more complex metering operations. More time can and should be spent inspecting and testing the Transformer rated installations in each utilities service territory.
Presented at the Mid-South Electric Metering Association 2015.
Over much of the 20th century, utilities, regulators and customers each relied upon lab and field meter testing efforts which were primarily focused upon the accuracy of the watt-hour meter and demand register.
This focus is now changing with overwhelming deployment of electronic meters and significant deployment of AMR and AMI meters throughout the installed base in North America.
The focus has now shifted to the metering installation as a whole and not the accuracy of the meter.
Over much of the 20th century, utilities, regulators and customers each relied upon lab and field meter testing efforts which were primarily focused upon the accuracy of the watt-hour meter and demand register.
This focus is now changing with overwhelming deployment of electronic meters and significant deployment of AMR and AMI meters throughout the installed base in North America.
The focus has now shifted to the metering installation as a whole and not the accuracy of the meter.
In this presentation, you will learn the basics - differences between self contained and transformer or instrument rated meter sites, transformer rated meter forms, test switches and CT's, meter accuracy testing in the field, checking the health of your CT's and PT's, and site verification
Over much of the 20th century, utilities, regulators and customers each relied upon lab and field meter testing efforts which were primarily focused upon the accuracy of the watt-hour meter and demand register.
This focus is now changing with overwhelming deployment of electronic meters and significant deployment of AMR and AMI meters throughout the installed base in North America.
The focus has now shifted to the metering installation as a whole and not the accuracy of the meter.
Presented at the North Carolina Electric Meter School. 6/2013
Over much of the 20th century, utilities, regulators and customers each relied upon lab and field meter testing efforts which were primarily focused upon the accuracy of the watt-hour meter and demand register. This focus is now changing with overwhelming deployment of electronic meters and significant deployment of AMR and AMI meters throughout the installed base in North America. The focus has now shifted to the metering installation as a whole and not the accuracy of the meter.
Over much of the 20th century, utilities, regulators and customers each relied upon lab and field meter testing efforts which were primarily focused upon the accuracy of the watt-hour meter and demand register.
This focus is now changing with overwhelming deployment of electronic meters and significant deployment of AMR and AMI meters throughout the installed base in North America.
The focus has now shifted to the metering installation as a whole and not the accuracy of the meter.
This presentation was given during the 2023 Southeastern Meter School in Auburn, AL. Understand the need and best practices for instrument transformer testing in an AMI world, including why and how to test, and what range of tests and checks to perform in the shop and in the field.
This presentation covers why meters are tested and the type of tests that are performed on meters. An overview of field test methods and field equipment is also included. 01/28/2019
This presentation was given during the 2022 Southeastern Meter School in Auburn, AL. Understand the need and best practices for instrument transformer testing in an AMI world, including why and how to test, and what range of tests and checks to perform in the shop and in the field.
Instructions for Submissions thorugh G- Classroom.pptxJheel Barad
This presentation provides a briefing on how to upload submissions and documents in Google Classroom. It was prepared as part of an orientation for new Sainik School in-service teacher trainees. As a training officer, my goal is to ensure that you are comfortable and proficient with this essential tool for managing assignments and fostering student engagement.
Macroeconomics- Movie Location
This will be used as part of your Personal Professional Portfolio once graded.
Objective:
Prepare a presentation or a paper using research, basic comparative analysis, data organization and application of economic information. You will make an informed assessment of an economic climate outside of the United States to accomplish an entertainment industry objective.
Palestine last event orientationfvgnh .pptxRaedMohamed3
An EFL lesson about the current events in Palestine. It is intended to be for intermediate students who wish to increase their listening skills through a short lesson in power point.
Model Attribute Check Company Auto PropertyCeline George
In Odoo, the multi-company feature allows you to manage multiple companies within a single Odoo database instance. Each company can have its own configurations while still sharing common resources such as products, customers, and suppliers.
Synthetic Fiber Construction in lab .pptxPavel ( NSTU)
Synthetic fiber production is a fascinating and complex field that blends chemistry, engineering, and environmental science. By understanding these aspects, students can gain a comprehensive view of synthetic fiber production, its impact on society and the environment, and the potential for future innovations. Synthetic fibers play a crucial role in modern society, impacting various aspects of daily life, industry, and the environment. ynthetic fibers are integral to modern life, offering a range of benefits from cost-effectiveness and versatility to innovative applications and performance characteristics. While they pose environmental challenges, ongoing research and development aim to create more sustainable and eco-friendly alternatives. Understanding the importance of synthetic fibers helps in appreciating their role in the economy, industry, and daily life, while also emphasizing the need for sustainable practices and innovation.
How to Make a Field invisible in Odoo 17Celine George
It is possible to hide or invisible some fields in odoo. Commonly using “invisible” attribute in the field definition to invisible the fields. This slide will show how to make a field invisible in odoo 17.
Acetabularia Information For Class 9 .docxvaibhavrinwa19
Acetabularia acetabulum is a single-celled green alga that in its vegetative state is morphologically differentiated into a basal rhizoid and an axially elongated stalk, which bears whorls of branching hairs. The single diploid nucleus resides in the rhizoid.
Francesca Gottschalk - How can education support child empowerment.pptxEduSkills OECD
Francesca Gottschalk from the OECD’s Centre for Educational Research and Innovation presents at the Ask an Expert Webinar: How can education support child empowerment?
Read| The latest issue of The Challenger is here! We are thrilled to announce that our school paper has qualified for the NATIONAL SCHOOLS PRESS CONFERENCE (NSPC) 2024. Thank you for your unwavering support and trust. Dive into the stories that made us stand out!
The Roman Empire A Historical Colossus.pdfkaushalkr1407
The Roman Empire, a vast and enduring power, stands as one of history's most remarkable civilizations, leaving an indelible imprint on the world. It emerged from the Roman Republic, transitioning into an imperial powerhouse under the leadership of Augustus Caesar in 27 BCE. This transformation marked the beginning of an era defined by unprecedented territorial expansion, architectural marvels, and profound cultural influence.
The empire's roots lie in the city of Rome, founded, according to legend, by Romulus in 753 BCE. Over centuries, Rome evolved from a small settlement to a formidable republic, characterized by a complex political system with elected officials and checks on power. However, internal strife, class conflicts, and military ambitions paved the way for the end of the Republic. Julius Caesar’s dictatorship and subsequent assassination in 44 BCE created a power vacuum, leading to a civil war. Octavian, later Augustus, emerged victorious, heralding the Roman Empire’s birth.
Under Augustus, the empire experienced the Pax Romana, a 200-year period of relative peace and stability. Augustus reformed the military, established efficient administrative systems, and initiated grand construction projects. The empire's borders expanded, encompassing territories from Britain to Egypt and from Spain to the Euphrates. Roman legions, renowned for their discipline and engineering prowess, secured and maintained these vast territories, building roads, fortifications, and cities that facilitated control and integration.
The Roman Empire’s society was hierarchical, with a rigid class system. At the top were the patricians, wealthy elites who held significant political power. Below them were the plebeians, free citizens with limited political influence, and the vast numbers of slaves who formed the backbone of the economy. The family unit was central, governed by the paterfamilias, the male head who held absolute authority.
Culturally, the Romans were eclectic, absorbing and adapting elements from the civilizations they encountered, particularly the Greeks. Roman art, literature, and philosophy reflected this synthesis, creating a rich cultural tapestry. Latin, the Roman language, became the lingua franca of the Western world, influencing numerous modern languages.
Roman architecture and engineering achievements were monumental. They perfected the arch, vault, and dome, constructing enduring structures like the Colosseum, Pantheon, and aqueducts. These engineering marvels not only showcased Roman ingenuity but also served practical purposes, from public entertainment to water supply.
2. 2
Significance of Commissioning
tests
Type Tests:
• To ensure compliance with the relevant
National and International specifications &
standards
• To ensure that the manufacturer’s
performance claims are met
• To ensure design validation
3. 3
Routine Tests
• To check quality of compounds used in
manufacturing
• To conform that individual protection
equipments have been correctly
manufactured and set up
4. 4
Commissioning Tests:
• To demonstrate that equipment has not been
damaged in transit and that it can be safely
and confidently connected to the system .
• To prove that the specified equipment has
been correctly installed
• To show that the characteristics of the
protections which are based on calculations
are correct
• To provide a set of test figures for future
reference when required
5. 5
CURRENT TRANSFORMERS
COMMISSIONING CHECK LIIST
SYSTEM : ----------- LOCATION---------
MAKE OF CT & Serial NO:
1.0 CT Particulars:
Protection / Metering :
Ratio :
Accuracy & Burden :
Type : Oil filled / bar /wound / cast
Core balance / Current balance:
Any other details :
6. 6
2.0 Visual Inspection:
3.0 Continuity:------ CT Resistance:----
4.0 Megger Test :---- volts -----M.ohms
5.0 High Voltage Tests
6.0 Polarity Check :
7.0 Ratio Test :
8.0 Magnetising Curve:
9.0 Oil Test results for BDV and Tan Delta
tests
7. 7
VOLTAGE TRANSFORMER
SYSTEM:------- LOCATION:---
Make and Serial No:
1.0 PT Data:
Protection / Metering :
Ratio :--- Accuracy:---- Burden:----
Any other specific details:
2.0 Winding Continuity and Resistance:
3.0 Megger Test :
4.0 High voltage test:
9. 9
HT / LT BREAKERS
SYSTEM: ---- LOCATION:---
Make and Serial No:
1.0 Breaker Details:
Breaker type:
Rated Voltage:-- Current:---
Breaking Capacity:
10. 10
Checks on Breakers:
• Whether breaker rack in and out is smooth
• Breaker primary contacts are firm and tight on
bus bar
• Check automatic operation of the shutter
closing mechanism and ensure its effectiveness
for safe shielding
• Check that all the fuse holders,mechanical
position indicators are properly fitted
• Check that all indication meters,lamp holders
are fixed properly
11. 11
• Check that shrouds are provided to prevent entry
of vermin when the breaker is withdrawn outside
• Check that the breaker is tested for high potential.
• Check limit switches are positioned and proper in
multiple operations
• Check breaker Main /Arcing contact alignments
are proper
• Check oil level in all three poles
• Check auxiliary contacts for positive and proper
operation
• Check spring charge mechanism Motor
12. 12
• Check spring charging mechanism operation
is proper(Both manually and electrically)
• Check closing spring mechanism is in good
condition
• Check breaker close/open indicators are
firmly mounted and they indicate properly
• Check proper functioning of breaker
interlocks for Test / Service position
• Check breaker locking arrangement is
adequate
13. 13
• Check breaker body contacts ,insulators and all
accessories mounted on breaker are thoroughly
observed for any physical damage
• Check interlock between link and breakers
• Check closing and opening operation manually and
mechanically
• Check the operation of the following interlock
mechanisms:
# Breaker cannot be withdrawn or racked in to
service position unless it is in “OFF “ condition
# Panel door can not be opened unless the breaker is
in OFF condition
14. 14
# Panel door cannot be closed with the
breaker in ON condition
# Access flaps for operating the CB and
withdrawing CB can be independently locked
to prevent unauthorized operation.
• Check that panel door can be locked securely
• Check and record the following Values:
Closing Coil Megger value
Trip Coil Megger value
Pick up and drop out values of closing and
opening coils for closing and opening operation
15. 15
Spring Charging Time:
Insulation resistance between the following
values: Breaker poles (Breaker open condition) –
Breaker pole to earth Br. Closed condition)
Breaker Closing Time:
Breaker Opening Time:
Resistance in Closing coil circuit and opening
coil circuit:
16. 16
HT / LT SWITCHGEAR
Checks on BUS BARs:
• All bolted connections on the bus bar are checked
for tightness
• Phase to phase and phase to earth clearances are
adequate at all points
• Bus bars are adequately supported and clamped
• Bus bars are not mechanically stressed
• Megger values are bus bar
• High voltage test
17. 17
Checks on Cubicles:
• All cubicles are properly bolted to each other and
to floor
• All extra opening are closed
• Doors operate freely,with out jerks and close
properly
• All gaskets for enclosures / doors etc are proper and
adequate
• All ventilation covers are unobstructed and clean
• Check tightness of all panel cover bolts and
mounting screws / bolts of PTs / CTs/Relays and
other apparatus
18. 18
• Check TWO distinct earth connections from the
panel to earth mat.
Checks on Control and Protections:
(Relevant drawings are to be made available)
• Check control wires are connected firmly and no
damage done to TBs
• Check the control wiring is neatly dressed,grouped,
glanded, placed in cable channels with ferrules and
easily identifiable without disconnection
• Check relay connections and CT secondary
connections are firm and proper.
19. 19
• Check control fuse ratings are of proper type as per
drawings.
• All blockings provided on relays are removed
• Control cables insulation tested
• Relays and settings with ranges available
Checks on Cables:
• The cables are properly sealed /grounded/connected
and extra openings are closed
• Non magnetic gland plates are provided for single
core cable entries
• No damage done to cable insulation while
removing the sheath
20. 20
• Cable lug crimping is done properly and ensure
that no oxide paste is applied on cable core at the
time of crimping
• Cable are properly clamped to avoid strain on the
connecting bus / insulator
• Bolting holes in their lug suits the bolt
• Cable connection on the bus bars are tight and
corrosion inhibiting compound is applied at
dissimilar metal functions
• Check for single core core cable,the glands and
metal washers used are non magnetic
• HV test & Megger value
• Check for armour earthing
21. 21
Checks on Relays:
Protection:---- Location:----
Relay designation:-----
• Relay Data:
operating voltage / current:
Make & Sl.No:
Type :
Time delay range: _-----(PU); ----- (DO)
Settings:
Range available
• Physical damage if any:
• Whether all blockings are removed
• Wirings are are checked
22. 22
• Operating coil resistance:----
• Resetting coil resistance:----
• Main coil PU: ----- V / A / AC / DC / %
• Main coil DO:---- - do-
• Reset coil PU:--- -do-
• Reset coil DO:--- -do-
• CT ratio tap used:
• PT ratio tap used:
• Max. feeder load:
• Circuit voltage:
23. 23
ISOLATORS
• Checking of Motor Operated Mechanism
box
• Checking of Isolator and earth switch
interlocks
• Checking of alignment of power
contacts,fixed contact assembly and moving
arm assembly.
24. 24
• Check the healthiness of motor
• Check the operation of isolator for close and
open command
• Check the action of limit cut off for open and
close
• Measure the contact resistance of Main
contacts
• Check the isolator over traveling protection
mechanism
25. 25
Questionnaire
1. Write two electrical tests to be conducted
on equipment insulating oil?
2. Which of the following equipment is
called as Instrument Transformers?
3. Identify the test which ids not common for
CT & PT
a. Megger b. Polarity Check
c. Magnetizing curve d. Ratio
26. 26
4. What is MOCB?
5. What is SF6?
6. What is the difference between Isolator
and Breaker regarding usage?
7. Write one of the most important electrical
test on Isolator?
8. If a particular core secondary is not used
while taking into service,what precaution
is to be taken?
9. In any breaker,which operation time will
be higher?
27. 27
10. Mention some of the Operating
Mechanisms of Breaker?
11. Any electrical panel or equipment should
have how many earthing provisions?
12. For any electrical systems,healthiness of
insulation is ensured by which test?
13. Protection relays are operated on which of
the following?
a. Voltage b. Current c.Both
14. Before taking up any work on reenergized
bus/switchgear,what should be done first?