SlideShare a Scribd company logo
1
Commissioning of Electrical
Equipment/systems
By - Alemayehu Asmare
Mersa ATVET College, 2015 E.C
2
Significance of Commissioning
tests
Type Tests:
• To ensure compliance with the relevant
National and International specifications &
standards
• To ensure that the manufacturer’s
performance claims are met
• To ensure design validation
3
Routine Tests
• To check quality of compounds used in
manufacturing
• To conform that individual protection
equipments have been correctly
manufactured and set up
4
Commissioning Tests:
• To demonstrate that equipment has not been
damaged in transit and that it can be safely
and confidently connected to the system .
• To prove that the specified equipment has
been correctly installed
• To show that the characteristics of the
protections which are based on calculations
are correct
• To provide a set of test figures for future
reference when required
5
CURRENT TRANSFORMERS
COMMISSIONING CHECK LIIST
SYSTEM : ----------- LOCATION---------
MAKE OF CT & Serial NO:
1.0 CT Particulars:
Protection / Metering :
Ratio :
Accuracy & Burden :
Type : Oil filled / bar /wound / cast
Core balance / Current balance:
Any other details :
6
2.0 Visual Inspection:
3.0 Continuity:------ CT Resistance:----
4.0 Megger Test :---- volts -----M.ohms
5.0 High Voltage Tests
6.0 Polarity Check :
7.0 Ratio Test :
8.0 Magnetising Curve:
9.0 Oil Test results for BDV and Tan Delta
tests
7
VOLTAGE TRANSFORMER
SYSTEM:------- LOCATION:---
Make and Serial No:
1.0 PT Data:
Protection / Metering :
Ratio :--- Accuracy:---- Burden:----
Any other specific details:
2.0 Winding Continuity and Resistance:
3.0 Megger Test :
4.0 High voltage test:
8
5.0 Polarity Check:
6.0 Ratio Test :
7.0 Oil test results
9
HT / LT BREAKERS
SYSTEM: ---- LOCATION:---
Make and Serial No:
1.0 Breaker Details:
Breaker type:
Rated Voltage:-- Current:---
Breaking Capacity:
10
Checks on Breakers:
• Whether breaker rack in and out is smooth
• Breaker primary contacts are firm and tight on
bus bar
• Check automatic operation of the shutter
closing mechanism and ensure its effectiveness
for safe shielding
• Check that all the fuse holders,mechanical
position indicators are properly fitted
• Check that all indication meters,lamp holders
are fixed properly
11
• Check that shrouds are provided to prevent entry
of vermin when the breaker is withdrawn outside
• Check that the breaker is tested for high potential.
• Check limit switches are positioned and proper in
multiple operations
• Check breaker Main /Arcing contact alignments
are proper
• Check oil level in all three poles
• Check auxiliary contacts for positive and proper
operation
• Check spring charge mechanism Motor
12
• Check spring charging mechanism operation
is proper(Both manually and electrically)
• Check closing spring mechanism is in good
condition
• Check breaker close/open indicators are
firmly mounted and they indicate properly
• Check proper functioning of breaker
interlocks for Test / Service position
• Check breaker locking arrangement is
adequate
13
• Check breaker body contacts ,insulators and all
accessories mounted on breaker are thoroughly
observed for any physical damage
• Check interlock between link and breakers
• Check closing and opening operation manually and
mechanically
• Check the operation of the following interlock
mechanisms:
# Breaker cannot be withdrawn or racked in to
service position unless it is in “OFF “ condition
# Panel door can not be opened unless the breaker is
in OFF condition
14
# Panel door cannot be closed with the
breaker in ON condition
# Access flaps for operating the CB and
withdrawing CB can be independently locked
to prevent unauthorized operation.
• Check that panel door can be locked securely
• Check and record the following Values:
 Closing Coil Megger value
 Trip Coil Megger value
 Pick up and drop out values of closing and
opening coils for closing and opening operation
15
 Spring Charging Time:
 Insulation resistance between the following
values: Breaker poles (Breaker open condition) –
Breaker pole to earth Br. Closed condition)
 Breaker Closing Time:
Breaker Opening Time:
Resistance in Closing coil circuit and opening
coil circuit:
16
HT / LT SWITCHGEAR
Checks on BUS BARs:
• All bolted connections on the bus bar are checked
for tightness
• Phase to phase and phase to earth clearances are
adequate at all points
• Bus bars are adequately supported and clamped
• Bus bars are not mechanically stressed
• Megger values are bus bar
• High voltage test
17
Checks on Cubicles:
• All cubicles are properly bolted to each other and
to floor
• All extra opening are closed
• Doors operate freely,with out jerks and close
properly
• All gaskets for enclosures / doors etc are proper and
adequate
• All ventilation covers are unobstructed and clean
• Check tightness of all panel cover bolts and
mounting screws / bolts of PTs / CTs/Relays and
other apparatus
18
• Check TWO distinct earth connections from the
panel to earth mat.
Checks on Control and Protections:
(Relevant drawings are to be made available)
• Check control wires are connected firmly and no
damage done to TBs
• Check the control wiring is neatly dressed,grouped,
glanded, placed in cable channels with ferrules and
easily identifiable without disconnection
• Check relay connections and CT secondary
connections are firm and proper.
19
• Check control fuse ratings are of proper type as per
drawings.
• All blockings provided on relays are removed
• Control cables insulation tested
• Relays and settings with ranges available
Checks on Cables:
• The cables are properly sealed /grounded/connected
and extra openings are closed
• Non magnetic gland plates are provided for single
core cable entries
• No damage done to cable insulation while
removing the sheath
20
• Cable lug crimping is done properly and ensure
that no oxide paste is applied on cable core at the
time of crimping
• Cable are properly clamped to avoid strain on the
connecting bus / insulator
• Bolting holes in their lug suits the bolt
• Cable connection on the bus bars are tight and
corrosion inhibiting compound is applied at
dissimilar metal functions
• Check for single core core cable,the glands and
metal washers used are non magnetic
• HV test & Megger value
• Check for armour earthing
21
Checks on Relays:
Protection:---- Location:----
Relay designation:-----
• Relay Data:
 operating voltage / current:
 Make & Sl.No:
 Type :
 Time delay range: _-----(PU); ----- (DO)
 Settings:
 Range available
• Physical damage if any:
• Whether all blockings are removed
• Wirings are are checked
22
• Operating coil resistance:----
• Resetting coil resistance:----
• Main coil PU: ----- V / A / AC / DC / %
• Main coil DO:---- - do-
• Reset coil PU:--- -do-
• Reset coil DO:--- -do-
• CT ratio tap used:
• PT ratio tap used:
• Max. feeder load:
• Circuit voltage:
23
ISOLATORS
• Checking of Motor Operated Mechanism
box
• Checking of Isolator and earth switch
interlocks
• Checking of alignment of power
contacts,fixed contact assembly and moving
arm assembly.
24
• Check the healthiness of motor
• Check the operation of isolator for close and
open command
• Check the action of limit cut off for open and
close
• Measure the contact resistance of Main
contacts
• Check the isolator over traveling protection
mechanism
25
Questionnaire
1. Write two electrical tests to be conducted
on equipment insulating oil?
2. Which of the following equipment is
called as Instrument Transformers?
3. Identify the test which ids not common for
CT & PT
a. Megger b. Polarity Check
c. Magnetizing curve d. Ratio
26
4. What is MOCB?
5. What is SF6?
6. What is the difference between Isolator
and Breaker regarding usage?
7. Write one of the most important electrical
test on Isolator?
8. If a particular core secondary is not used
while taking into service,what precaution
is to be taken?
9. In any breaker,which operation time will
be higher?
27
10. Mention some of the Operating
Mechanisms of Breaker?
11. Any electrical panel or equipment should
have how many earthing provisions?
12. For any electrical systems,healthiness of
insulation is ensured by which test?
13. Protection relays are operated on which of
the following?
a. Voltage b. Current c.Both
14. Before taking up any work on reenergized
bus/switchgear,what should be done first?

More Related Content

What's hot

Protection & switchgear
Protection & switchgear   Protection & switchgear
Protection & switchgear
johny renoald
 
Power system protection topic 1
Power system protection topic 1Power system protection topic 1
Power system protection topic 1
Siswoyo Edo
 
Switchgear - complete guide
Switchgear - complete guideSwitchgear - complete guide
Switchgear - complete guide
Slides Hub
 
Switchgear and protection lecture 1
Switchgear and protection lecture 1Switchgear and protection lecture 1
Switchgear and protection lecture 1
anuphowlader1
 
Transformer protection
Transformer protectionTransformer protection
Transformer protection
jawaharramaya
 
Switchgear presentation
Switchgear presentationSwitchgear presentation
Switchgear presentation
Ahmed Saada, (PRMG)
 
Lv switchgear & lv cable sizing
Lv switchgear & lv cable sizingLv switchgear & lv cable sizing
Lv switchgear & lv cable sizing
Asif Eqbal
 
Electrical safety
Electrical safetyElectrical safety
Electrical safety
1186429
 
Grounding,Earthing,Bonding
Grounding,Earthing,BondingGrounding,Earthing,Bonding
Grounding,Earthing,Bonding
Ko Winnwe
 
Electrical safety.pptx
Electrical safety.pptxElectrical safety.pptx
Electrical safety.pptx
NarayanaMurthy79
 
Switchyard
SwitchyardSwitchyard
Switchyard
I.E.T. lucknow
 
Transformer design and protection
Transformer design and protectionTransformer design and protection
Transformer design and protectionashwin fcc
 
Electrical grounding and earthing systems
Electrical grounding and earthing systemsElectrical grounding and earthing systems
Electrical grounding and earthing systemsBiswajit Pratihari
 
Power cable selection, cable selection Methodology
Power cable selection, cable selection Methodology Power cable selection, cable selection Methodology
Power cable selection, cable selection Methodology
wessam alaslmi
 
Introduction to mv switchgear
Introduction to mv switchgearIntroduction to mv switchgear
Introduction to mv switchgear
Modal Holong Education
 
Electrical Wiring Practices and Diagrams
Electrical Wiring Practices and DiagramsElectrical Wiring Practices and Diagrams
Electrical Wiring Practices and Diagrams
Practicing In Some Infra Company
 
What is the Difference Between MCB, MCCB, ELCB and RCCB?
What is the Difference Between MCB, MCCB, ELCB and RCCB?What is the Difference Between MCB, MCCB, ELCB and RCCB?
What is the Difference Between MCB, MCCB, ELCB and RCCB?
BurraqEngineeringSol
 
Load list calculation
Load list calculationLoad list calculation
Load list calculation
Wiwit Purwanto
 
Substations
SubstationsSubstations
Substations
itfakash
 
Principles of Cable Sizing
Principles of Cable SizingPrinciples of Cable Sizing
Principles of Cable Sizing
Leonardo ENERGY
 

What's hot (20)

Protection & switchgear
Protection & switchgear   Protection & switchgear
Protection & switchgear
 
Power system protection topic 1
Power system protection topic 1Power system protection topic 1
Power system protection topic 1
 
Switchgear - complete guide
Switchgear - complete guideSwitchgear - complete guide
Switchgear - complete guide
 
Switchgear and protection lecture 1
Switchgear and protection lecture 1Switchgear and protection lecture 1
Switchgear and protection lecture 1
 
Transformer protection
Transformer protectionTransformer protection
Transformer protection
 
Switchgear presentation
Switchgear presentationSwitchgear presentation
Switchgear presentation
 
Lv switchgear & lv cable sizing
Lv switchgear & lv cable sizingLv switchgear & lv cable sizing
Lv switchgear & lv cable sizing
 
Electrical safety
Electrical safetyElectrical safety
Electrical safety
 
Grounding,Earthing,Bonding
Grounding,Earthing,BondingGrounding,Earthing,Bonding
Grounding,Earthing,Bonding
 
Electrical safety.pptx
Electrical safety.pptxElectrical safety.pptx
Electrical safety.pptx
 
Switchyard
SwitchyardSwitchyard
Switchyard
 
Transformer design and protection
Transformer design and protectionTransformer design and protection
Transformer design and protection
 
Electrical grounding and earthing systems
Electrical grounding and earthing systemsElectrical grounding and earthing systems
Electrical grounding and earthing systems
 
Power cable selection, cable selection Methodology
Power cable selection, cable selection Methodology Power cable selection, cable selection Methodology
Power cable selection, cable selection Methodology
 
Introduction to mv switchgear
Introduction to mv switchgearIntroduction to mv switchgear
Introduction to mv switchgear
 
Electrical Wiring Practices and Diagrams
Electrical Wiring Practices and DiagramsElectrical Wiring Practices and Diagrams
Electrical Wiring Practices and Diagrams
 
What is the Difference Between MCB, MCCB, ELCB and RCCB?
What is the Difference Between MCB, MCCB, ELCB and RCCB?What is the Difference Between MCB, MCCB, ELCB and RCCB?
What is the Difference Between MCB, MCCB, ELCB and RCCB?
 
Load list calculation
Load list calculationLoad list calculation
Load list calculation
 
Substations
SubstationsSubstations
Substations
 
Principles of Cable Sizing
Principles of Cable SizingPrinciples of Cable Sizing
Principles of Cable Sizing
 

Similar to Commissioning of Electrical Equipment or systems.ppt

Installation Operation & Maintenance of 33kV & 11kV Switchgear
Installation   Operation & Maintenance of 33kV & 11kV SwitchgearInstallation   Operation & Maintenance of 33kV & 11kV Switchgear
Installation Operation & Maintenance of 33kV & 11kV Switchgear
Sheikh Nazmul Islam
 
Site Inspections - Looking for Dangerous Installations or Incorrect Billing
Site Inspections - Looking for Dangerous Installations or Incorrect BillingSite Inspections - Looking for Dangerous Installations or Incorrect Billing
Site Inspections - Looking for Dangerous Installations or Incorrect Billing
TESCO - The Eastern Specialty Company
 
SD.pptx
SD.pptxSD.pptx
SD.pptx
hemant9402
 
Field Testing
Field TestingField Testing
Site Verification - Protocols & Tools for Complex Metering Installations
Site Verification - Protocols & Tools for Complex Metering InstallationsSite Verification - Protocols & Tools for Complex Metering Installations
Site Verification - Protocols & Tools for Complex Metering Installations
TESCO - The Eastern Specialty Company
 
Fundamentals of Transformer Rated Field Meter Testing and Site Verification
Fundamentals of Transformer Rated Field Meter Testing and Site VerificationFundamentals of Transformer Rated Field Meter Testing and Site Verification
Fundamentals of Transformer Rated Field Meter Testing and Site Verification
TESCO - The Eastern Specialty Company
 
Site Verification - Protocols & Tools for Complex Metering Installations
Site Verification - Protocols & Tools for Complex Metering InstallationsSite Verification - Protocols & Tools for Complex Metering Installations
Site Verification - Protocols & Tools for Complex Metering Installations
TESCO - The Eastern Specialty Company
 
Fulham Reach Block G Risk Review Presentation For review
Fulham Reach Block G Risk Review Presentation For reviewFulham Reach Block G Risk Review Presentation For review
Fulham Reach Block G Risk Review Presentation For reviewMark Platten
 
Instrument Transformer Testing in them Shop and Field_Tom Lawton 2023
Instrument Transformer Testing in them Shop and Field_Tom Lawton 2023Instrument Transformer Testing in them Shop and Field_Tom Lawton 2023
Instrument Transformer Testing in them Shop and Field_Tom Lawton 2023
TESCO - The Eastern Specialty Company
 
Site Verification - Protocols & Tools for Complex Metering Installations
Site Verification - Protocols & Tools for Complex Metering InstallationsSite Verification - Protocols & Tools for Complex Metering Installations
Site Verification - Protocols & Tools for Complex Metering Installations
TESCO - The Eastern Specialty Company
 
AMI Site Verification - Protocols & Tools for Complex Metering Installations
AMI Site Verification - Protocols & Tools for Complex Metering InstallationsAMI Site Verification - Protocols & Tools for Complex Metering Installations
AMI Site Verification - Protocols & Tools for Complex Metering Installations
TESCO - The Eastern Specialty Company
 
Instrument Transformer Testing in the Shop and Field
Instrument Transformer Testing in the Shop and FieldInstrument Transformer Testing in the Shop and Field
Instrument Transformer Testing in the Shop and Field
TESCO - The Eastern Specialty Company
 
Fundamentals of Field Testing Meters
Fundamentals of Field Testing MetersFundamentals of Field Testing Meters
Fundamentals of Field Testing Meters
TESCO - The Eastern Specialty Company
 
Instrument Transformer Testing
Instrument Transformer TestingInstrument Transformer Testing
Instrument Transformer Testing
TESCO - The Eastern Specialty Company
 
Unit 06 - Substation and maintenance
Unit 06 - Substation and maintenanceUnit 06 - Substation and maintenance
Unit 06 - Substation and maintenance
PremanandDesai
 
Areva "Manufacturing of transformer, uses & it’s accessories"
Areva "Manufacturing of transformer, uses & it’s accessories"Areva "Manufacturing of transformer, uses & it’s accessories"
Areva "Manufacturing of transformer, uses & it’s accessories"
Harshit Srivastava
 
SubstationCommissioning.pdf
SubstationCommissioning.pdfSubstationCommissioning.pdf
SubstationCommissioning.pdf
AnithaSyam
 

Similar to Commissioning of Electrical Equipment or systems.ppt (20)

Installation Operation & Maintenance of 33kV & 11kV Switchgear
Installation   Operation & Maintenance of 33kV & 11kV SwitchgearInstallation   Operation & Maintenance of 33kV & 11kV Switchgear
Installation Operation & Maintenance of 33kV & 11kV Switchgear
 
Site Inspections - Looking for Dangerous Installations or Incorrect Billing
Site Inspections - Looking for Dangerous Installations or Incorrect BillingSite Inspections - Looking for Dangerous Installations or Incorrect Billing
Site Inspections - Looking for Dangerous Installations or Incorrect Billing
 
Standards
StandardsStandards
Standards
 
SD.pptx
SD.pptxSD.pptx
SD.pptx
 
Field Testing
Field TestingField Testing
Field Testing
 
Site Verification - Protocols & Tools for Complex Metering Installations
Site Verification - Protocols & Tools for Complex Metering InstallationsSite Verification - Protocols & Tools for Complex Metering Installations
Site Verification - Protocols & Tools for Complex Metering Installations
 
Fundamentals of Transformer Rated Field Meter Testing and Site Verification
Fundamentals of Transformer Rated Field Meter Testing and Site VerificationFundamentals of Transformer Rated Field Meter Testing and Site Verification
Fundamentals of Transformer Rated Field Meter Testing and Site Verification
 
Site Verification - Protocols & Tools for Complex Metering Installations
Site Verification - Protocols & Tools for Complex Metering InstallationsSite Verification - Protocols & Tools for Complex Metering Installations
Site Verification - Protocols & Tools for Complex Metering Installations
 
Fulham Reach Block G Risk Review Presentation For review
Fulham Reach Block G Risk Review Presentation For reviewFulham Reach Block G Risk Review Presentation For review
Fulham Reach Block G Risk Review Presentation For review
 
Instrument Transformer Testing in them Shop and Field_Tom Lawton 2023
Instrument Transformer Testing in them Shop and Field_Tom Lawton 2023Instrument Transformer Testing in them Shop and Field_Tom Lawton 2023
Instrument Transformer Testing in them Shop and Field_Tom Lawton 2023
 
EIT_Presentation
EIT_PresentationEIT_Presentation
EIT_Presentation
 
Site Verification - Protocols & Tools for Complex Metering Installations
Site Verification - Protocols & Tools for Complex Metering InstallationsSite Verification - Protocols & Tools for Complex Metering Installations
Site Verification - Protocols & Tools for Complex Metering Installations
 
MSC SOW
MSC SOWMSC SOW
MSC SOW
 
AMI Site Verification - Protocols & Tools for Complex Metering Installations
AMI Site Verification - Protocols & Tools for Complex Metering InstallationsAMI Site Verification - Protocols & Tools for Complex Metering Installations
AMI Site Verification - Protocols & Tools for Complex Metering Installations
 
Instrument Transformer Testing in the Shop and Field
Instrument Transformer Testing in the Shop and FieldInstrument Transformer Testing in the Shop and Field
Instrument Transformer Testing in the Shop and Field
 
Fundamentals of Field Testing Meters
Fundamentals of Field Testing MetersFundamentals of Field Testing Meters
Fundamentals of Field Testing Meters
 
Instrument Transformer Testing
Instrument Transformer TestingInstrument Transformer Testing
Instrument Transformer Testing
 
Unit 06 - Substation and maintenance
Unit 06 - Substation and maintenanceUnit 06 - Substation and maintenance
Unit 06 - Substation and maintenance
 
Areva "Manufacturing of transformer, uses & it’s accessories"
Areva "Manufacturing of transformer, uses & it’s accessories"Areva "Manufacturing of transformer, uses & it’s accessories"
Areva "Manufacturing of transformer, uses & it’s accessories"
 
SubstationCommissioning.pdf
SubstationCommissioning.pdfSubstationCommissioning.pdf
SubstationCommissioning.pdf
 

Recently uploaded

Supporting (UKRI) OA monographs at Salford.pptx
Supporting (UKRI) OA monographs at Salford.pptxSupporting (UKRI) OA monographs at Salford.pptx
Supporting (UKRI) OA monographs at Salford.pptx
Jisc
 
BÀI TẬP BỔ TRỢ TIẾNG ANH GLOBAL SUCCESS LỚP 3 - CẢ NĂM (CÓ FILE NGHE VÀ ĐÁP Á...
BÀI TẬP BỔ TRỢ TIẾNG ANH GLOBAL SUCCESS LỚP 3 - CẢ NĂM (CÓ FILE NGHE VÀ ĐÁP Á...BÀI TẬP BỔ TRỢ TIẾNG ANH GLOBAL SUCCESS LỚP 3 - CẢ NĂM (CÓ FILE NGHE VÀ ĐÁP Á...
BÀI TẬP BỔ TRỢ TIẾNG ANH GLOBAL SUCCESS LỚP 3 - CẢ NĂM (CÓ FILE NGHE VÀ ĐÁP Á...
Nguyen Thanh Tu Collection
 
Language Across the Curriculm LAC B.Ed.
Language Across the  Curriculm LAC B.Ed.Language Across the  Curriculm LAC B.Ed.
Language Across the Curriculm LAC B.Ed.
Atul Kumar Singh
 
aaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaa
aaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaa
aaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaa
siemaillard
 
Overview on Edible Vaccine: Pros & Cons with Mechanism
Overview on Edible Vaccine: Pros & Cons with MechanismOverview on Edible Vaccine: Pros & Cons with Mechanism
Overview on Edible Vaccine: Pros & Cons with Mechanism
DeeptiGupta154
 
Mule 4.6 & Java 17 Upgrade | MuleSoft Mysore Meetup #46
Mule 4.6 & Java 17 Upgrade | MuleSoft Mysore Meetup #46Mule 4.6 & Java 17 Upgrade | MuleSoft Mysore Meetup #46
Mule 4.6 & Java 17 Upgrade | MuleSoft Mysore Meetup #46
MysoreMuleSoftMeetup
 
Instructions for Submissions thorugh G- Classroom.pptx
Instructions for Submissions thorugh G- Classroom.pptxInstructions for Submissions thorugh G- Classroom.pptx
Instructions for Submissions thorugh G- Classroom.pptx
Jheel Barad
 
1.4 modern child centered education - mahatma gandhi-2.pptx
1.4 modern child centered education - mahatma gandhi-2.pptx1.4 modern child centered education - mahatma gandhi-2.pptx
1.4 modern child centered education - mahatma gandhi-2.pptx
JosvitaDsouza2
 
CACJapan - GROUP Presentation 1- Wk 4.pdf
CACJapan - GROUP Presentation 1- Wk 4.pdfCACJapan - GROUP Presentation 1- Wk 4.pdf
CACJapan - GROUP Presentation 1- Wk 4.pdf
camakaiclarkmusic
 
Palestine last event orientationfvgnh .pptx
Palestine last event orientationfvgnh .pptxPalestine last event orientationfvgnh .pptx
Palestine last event orientationfvgnh .pptx
RaedMohamed3
 
Model Attribute Check Company Auto Property
Model Attribute  Check Company Auto PropertyModel Attribute  Check Company Auto Property
Model Attribute Check Company Auto Property
Celine George
 
"Protectable subject matters, Protection in biotechnology, Protection of othe...
"Protectable subject matters, Protection in biotechnology, Protection of othe..."Protectable subject matters, Protection in biotechnology, Protection of othe...
"Protectable subject matters, Protection in biotechnology, Protection of othe...
SACHIN R KONDAGURI
 
Synthetic Fiber Construction in lab .pptx
Synthetic Fiber Construction in lab .pptxSynthetic Fiber Construction in lab .pptx
Synthetic Fiber Construction in lab .pptx
Pavel ( NSTU)
 
The Accursed House by Émile Gaboriau.pptx
The Accursed House by Émile Gaboriau.pptxThe Accursed House by Émile Gaboriau.pptx
The Accursed House by Émile Gaboriau.pptx
DhatriParmar
 
How to Make a Field invisible in Odoo 17
How to Make a Field invisible in Odoo 17How to Make a Field invisible in Odoo 17
How to Make a Field invisible in Odoo 17
Celine George
 
Acetabularia Information For Class 9 .docx
Acetabularia Information For Class 9  .docxAcetabularia Information For Class 9  .docx
Acetabularia Information For Class 9 .docx
vaibhavrinwa19
 
Francesca Gottschalk - How can education support child empowerment.pptx
Francesca Gottschalk - How can education support child empowerment.pptxFrancesca Gottschalk - How can education support child empowerment.pptx
Francesca Gottschalk - How can education support child empowerment.pptx
EduSkills OECD
 
The Challenger.pdf DNHS Official Publication
The Challenger.pdf DNHS Official PublicationThe Challenger.pdf DNHS Official Publication
The Challenger.pdf DNHS Official Publication
Delapenabediema
 
The Roman Empire A Historical Colossus.pdf
The Roman Empire A Historical Colossus.pdfThe Roman Empire A Historical Colossus.pdf
The Roman Empire A Historical Colossus.pdf
kaushalkr1407
 
special B.ed 2nd year old paper_20240531.pdf
special B.ed 2nd year old paper_20240531.pdfspecial B.ed 2nd year old paper_20240531.pdf
special B.ed 2nd year old paper_20240531.pdf
Special education needs
 

Recently uploaded (20)

Supporting (UKRI) OA monographs at Salford.pptx
Supporting (UKRI) OA monographs at Salford.pptxSupporting (UKRI) OA monographs at Salford.pptx
Supporting (UKRI) OA monographs at Salford.pptx
 
BÀI TẬP BỔ TRỢ TIẾNG ANH GLOBAL SUCCESS LỚP 3 - CẢ NĂM (CÓ FILE NGHE VÀ ĐÁP Á...
BÀI TẬP BỔ TRỢ TIẾNG ANH GLOBAL SUCCESS LỚP 3 - CẢ NĂM (CÓ FILE NGHE VÀ ĐÁP Á...BÀI TẬP BỔ TRỢ TIẾNG ANH GLOBAL SUCCESS LỚP 3 - CẢ NĂM (CÓ FILE NGHE VÀ ĐÁP Á...
BÀI TẬP BỔ TRỢ TIẾNG ANH GLOBAL SUCCESS LỚP 3 - CẢ NĂM (CÓ FILE NGHE VÀ ĐÁP Á...
 
Language Across the Curriculm LAC B.Ed.
Language Across the  Curriculm LAC B.Ed.Language Across the  Curriculm LAC B.Ed.
Language Across the Curriculm LAC B.Ed.
 
aaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaa
aaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaa
aaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaa
 
Overview on Edible Vaccine: Pros & Cons with Mechanism
Overview on Edible Vaccine: Pros & Cons with MechanismOverview on Edible Vaccine: Pros & Cons with Mechanism
Overview on Edible Vaccine: Pros & Cons with Mechanism
 
Mule 4.6 & Java 17 Upgrade | MuleSoft Mysore Meetup #46
Mule 4.6 & Java 17 Upgrade | MuleSoft Mysore Meetup #46Mule 4.6 & Java 17 Upgrade | MuleSoft Mysore Meetup #46
Mule 4.6 & Java 17 Upgrade | MuleSoft Mysore Meetup #46
 
Instructions for Submissions thorugh G- Classroom.pptx
Instructions for Submissions thorugh G- Classroom.pptxInstructions for Submissions thorugh G- Classroom.pptx
Instructions for Submissions thorugh G- Classroom.pptx
 
1.4 modern child centered education - mahatma gandhi-2.pptx
1.4 modern child centered education - mahatma gandhi-2.pptx1.4 modern child centered education - mahatma gandhi-2.pptx
1.4 modern child centered education - mahatma gandhi-2.pptx
 
CACJapan - GROUP Presentation 1- Wk 4.pdf
CACJapan - GROUP Presentation 1- Wk 4.pdfCACJapan - GROUP Presentation 1- Wk 4.pdf
CACJapan - GROUP Presentation 1- Wk 4.pdf
 
Palestine last event orientationfvgnh .pptx
Palestine last event orientationfvgnh .pptxPalestine last event orientationfvgnh .pptx
Palestine last event orientationfvgnh .pptx
 
Model Attribute Check Company Auto Property
Model Attribute  Check Company Auto PropertyModel Attribute  Check Company Auto Property
Model Attribute Check Company Auto Property
 
"Protectable subject matters, Protection in biotechnology, Protection of othe...
"Protectable subject matters, Protection in biotechnology, Protection of othe..."Protectable subject matters, Protection in biotechnology, Protection of othe...
"Protectable subject matters, Protection in biotechnology, Protection of othe...
 
Synthetic Fiber Construction in lab .pptx
Synthetic Fiber Construction in lab .pptxSynthetic Fiber Construction in lab .pptx
Synthetic Fiber Construction in lab .pptx
 
The Accursed House by Émile Gaboriau.pptx
The Accursed House by Émile Gaboriau.pptxThe Accursed House by Émile Gaboriau.pptx
The Accursed House by Émile Gaboriau.pptx
 
How to Make a Field invisible in Odoo 17
How to Make a Field invisible in Odoo 17How to Make a Field invisible in Odoo 17
How to Make a Field invisible in Odoo 17
 
Acetabularia Information For Class 9 .docx
Acetabularia Information For Class 9  .docxAcetabularia Information For Class 9  .docx
Acetabularia Information For Class 9 .docx
 
Francesca Gottschalk - How can education support child empowerment.pptx
Francesca Gottschalk - How can education support child empowerment.pptxFrancesca Gottschalk - How can education support child empowerment.pptx
Francesca Gottschalk - How can education support child empowerment.pptx
 
The Challenger.pdf DNHS Official Publication
The Challenger.pdf DNHS Official PublicationThe Challenger.pdf DNHS Official Publication
The Challenger.pdf DNHS Official Publication
 
The Roman Empire A Historical Colossus.pdf
The Roman Empire A Historical Colossus.pdfThe Roman Empire A Historical Colossus.pdf
The Roman Empire A Historical Colossus.pdf
 
special B.ed 2nd year old paper_20240531.pdf
special B.ed 2nd year old paper_20240531.pdfspecial B.ed 2nd year old paper_20240531.pdf
special B.ed 2nd year old paper_20240531.pdf
 

Commissioning of Electrical Equipment or systems.ppt

  • 1. 1 Commissioning of Electrical Equipment/systems By - Alemayehu Asmare Mersa ATVET College, 2015 E.C
  • 2. 2 Significance of Commissioning tests Type Tests: • To ensure compliance with the relevant National and International specifications & standards • To ensure that the manufacturer’s performance claims are met • To ensure design validation
  • 3. 3 Routine Tests • To check quality of compounds used in manufacturing • To conform that individual protection equipments have been correctly manufactured and set up
  • 4. 4 Commissioning Tests: • To demonstrate that equipment has not been damaged in transit and that it can be safely and confidently connected to the system . • To prove that the specified equipment has been correctly installed • To show that the characteristics of the protections which are based on calculations are correct • To provide a set of test figures for future reference when required
  • 5. 5 CURRENT TRANSFORMERS COMMISSIONING CHECK LIIST SYSTEM : ----------- LOCATION--------- MAKE OF CT & Serial NO: 1.0 CT Particulars: Protection / Metering : Ratio : Accuracy & Burden : Type : Oil filled / bar /wound / cast Core balance / Current balance: Any other details :
  • 6. 6 2.0 Visual Inspection: 3.0 Continuity:------ CT Resistance:---- 4.0 Megger Test :---- volts -----M.ohms 5.0 High Voltage Tests 6.0 Polarity Check : 7.0 Ratio Test : 8.0 Magnetising Curve: 9.0 Oil Test results for BDV and Tan Delta tests
  • 7. 7 VOLTAGE TRANSFORMER SYSTEM:------- LOCATION:--- Make and Serial No: 1.0 PT Data: Protection / Metering : Ratio :--- Accuracy:---- Burden:---- Any other specific details: 2.0 Winding Continuity and Resistance: 3.0 Megger Test : 4.0 High voltage test:
  • 8. 8 5.0 Polarity Check: 6.0 Ratio Test : 7.0 Oil test results
  • 9. 9 HT / LT BREAKERS SYSTEM: ---- LOCATION:--- Make and Serial No: 1.0 Breaker Details: Breaker type: Rated Voltage:-- Current:--- Breaking Capacity:
  • 10. 10 Checks on Breakers: • Whether breaker rack in and out is smooth • Breaker primary contacts are firm and tight on bus bar • Check automatic operation of the shutter closing mechanism and ensure its effectiveness for safe shielding • Check that all the fuse holders,mechanical position indicators are properly fitted • Check that all indication meters,lamp holders are fixed properly
  • 11. 11 • Check that shrouds are provided to prevent entry of vermin when the breaker is withdrawn outside • Check that the breaker is tested for high potential. • Check limit switches are positioned and proper in multiple operations • Check breaker Main /Arcing contact alignments are proper • Check oil level in all three poles • Check auxiliary contacts for positive and proper operation • Check spring charge mechanism Motor
  • 12. 12 • Check spring charging mechanism operation is proper(Both manually and electrically) • Check closing spring mechanism is in good condition • Check breaker close/open indicators are firmly mounted and they indicate properly • Check proper functioning of breaker interlocks for Test / Service position • Check breaker locking arrangement is adequate
  • 13. 13 • Check breaker body contacts ,insulators and all accessories mounted on breaker are thoroughly observed for any physical damage • Check interlock between link and breakers • Check closing and opening operation manually and mechanically • Check the operation of the following interlock mechanisms: # Breaker cannot be withdrawn or racked in to service position unless it is in “OFF “ condition # Panel door can not be opened unless the breaker is in OFF condition
  • 14. 14 # Panel door cannot be closed with the breaker in ON condition # Access flaps for operating the CB and withdrawing CB can be independently locked to prevent unauthorized operation. • Check that panel door can be locked securely • Check and record the following Values:  Closing Coil Megger value  Trip Coil Megger value  Pick up and drop out values of closing and opening coils for closing and opening operation
  • 15. 15  Spring Charging Time:  Insulation resistance between the following values: Breaker poles (Breaker open condition) – Breaker pole to earth Br. Closed condition)  Breaker Closing Time: Breaker Opening Time: Resistance in Closing coil circuit and opening coil circuit:
  • 16. 16 HT / LT SWITCHGEAR Checks on BUS BARs: • All bolted connections on the bus bar are checked for tightness • Phase to phase and phase to earth clearances are adequate at all points • Bus bars are adequately supported and clamped • Bus bars are not mechanically stressed • Megger values are bus bar • High voltage test
  • 17. 17 Checks on Cubicles: • All cubicles are properly bolted to each other and to floor • All extra opening are closed • Doors operate freely,with out jerks and close properly • All gaskets for enclosures / doors etc are proper and adequate • All ventilation covers are unobstructed and clean • Check tightness of all panel cover bolts and mounting screws / bolts of PTs / CTs/Relays and other apparatus
  • 18. 18 • Check TWO distinct earth connections from the panel to earth mat. Checks on Control and Protections: (Relevant drawings are to be made available) • Check control wires are connected firmly and no damage done to TBs • Check the control wiring is neatly dressed,grouped, glanded, placed in cable channels with ferrules and easily identifiable without disconnection • Check relay connections and CT secondary connections are firm and proper.
  • 19. 19 • Check control fuse ratings are of proper type as per drawings. • All blockings provided on relays are removed • Control cables insulation tested • Relays and settings with ranges available Checks on Cables: • The cables are properly sealed /grounded/connected and extra openings are closed • Non magnetic gland plates are provided for single core cable entries • No damage done to cable insulation while removing the sheath
  • 20. 20 • Cable lug crimping is done properly and ensure that no oxide paste is applied on cable core at the time of crimping • Cable are properly clamped to avoid strain on the connecting bus / insulator • Bolting holes in their lug suits the bolt • Cable connection on the bus bars are tight and corrosion inhibiting compound is applied at dissimilar metal functions • Check for single core core cable,the glands and metal washers used are non magnetic • HV test & Megger value • Check for armour earthing
  • 21. 21 Checks on Relays: Protection:---- Location:---- Relay designation:----- • Relay Data:  operating voltage / current:  Make & Sl.No:  Type :  Time delay range: _-----(PU); ----- (DO)  Settings:  Range available • Physical damage if any: • Whether all blockings are removed • Wirings are are checked
  • 22. 22 • Operating coil resistance:---- • Resetting coil resistance:---- • Main coil PU: ----- V / A / AC / DC / % • Main coil DO:---- - do- • Reset coil PU:--- -do- • Reset coil DO:--- -do- • CT ratio tap used: • PT ratio tap used: • Max. feeder load: • Circuit voltage:
  • 23. 23 ISOLATORS • Checking of Motor Operated Mechanism box • Checking of Isolator and earth switch interlocks • Checking of alignment of power contacts,fixed contact assembly and moving arm assembly.
  • 24. 24 • Check the healthiness of motor • Check the operation of isolator for close and open command • Check the action of limit cut off for open and close • Measure the contact resistance of Main contacts • Check the isolator over traveling protection mechanism
  • 25. 25 Questionnaire 1. Write two electrical tests to be conducted on equipment insulating oil? 2. Which of the following equipment is called as Instrument Transformers? 3. Identify the test which ids not common for CT & PT a. Megger b. Polarity Check c. Magnetizing curve d. Ratio
  • 26. 26 4. What is MOCB? 5. What is SF6? 6. What is the difference between Isolator and Breaker regarding usage? 7. Write one of the most important electrical test on Isolator? 8. If a particular core secondary is not used while taking into service,what precaution is to be taken? 9. In any breaker,which operation time will be higher?
  • 27. 27 10. Mention some of the Operating Mechanisms of Breaker? 11. Any electrical panel or equipment should have how many earthing provisions? 12. For any electrical systems,healthiness of insulation is ensured by which test? 13. Protection relays are operated on which of the following? a. Voltage b. Current c.Both 14. Before taking up any work on reenergized bus/switchgear,what should be done first?