SlideShare a Scribd company logo
Repetitive Scheduling Method
INTRODUCTION
1
2
YouTube
What is RSM?
• It is a scheduling method that focuses on “Continuous Resource Utilization” in repetitive construction.
• It is a graphical method unlike LRA and URL which are calculation methods.
What is its Objective?
• Schedule resources -specific skilled workers/equipment- to work continuously without interruption (idle time)
There are 3 main constraints in RSM:
1. Activity Precedence Constraint, in most scheduling methods such as CPM and PERT
2. Resource Availability Constraint, such as in Limited Resource Allocation (LRA)
3. Resource Continuity Constraint, such as in Line-of-Balance (LOB)
Introduction to Repetitive Scheduling Method (RSM)
3
Repetitive Scheduling Method
Projects with Repeating Activities
(Repetitive Projects)
4
Projects with Repeating Activities
• Housing projects (multiple houses):
• Structure & Exterior for the 1st house, the 2nd house, …
• HVAC for the 1st house, the 2nd house, …
• Interior & Finishing for the 1st house, the 2nd house, …
• High-rise Buildings (multiple floors):
• Structure for the 1st floor, the 2nd floor, …
• HVAC for the 1st floor, the 2nd floor, …
• Interior for the 1st floor, the 2nd floor, …
• Roads & Highways (multiple stations):
• Excavation for the 1st station, for the 2nd station, …
• Backfill for the 1st station, for the 2nd station, …
• Layers for the 1st station, for the 2nd station, …
5
S2
H2
I2
Only with
Precedence Constraints.
No need to finish
House 1 before House 2.
S1
H1
I1
House1House2
A housing projects (2 houses)
• Structure & Exterior for the 1st house, the 2nd house
• HVAC for the 1st house, the 2nd house
• Interior & Finishing for the 1st house, the 2nd house
Given there is only one crew for each activity.
6
S1
H1
I1
S2
H2
I2
S1
H1
I1
S2
H2
I2
Only with
Precedence Constraints.
No need to finish
House 1 before House 2.
H1-H2
I1-I2
With
Precedence Constraints
Availability Constraints
S1
H1
I1
S2
H2
I2
With
Precedence Constraints
Availability Constraints
Continuity Constraints
House1House2House1House2House1House2
Repetitive Scheduling Method
Representations
Bar Chart, AON, and RSM Diagram
7
8
S1
H1
I1
S2
H2
I2
Only with
Precedence Constraints.
No need to finish
House 1 before House 2.
House1House2
S1
3
H1
2
I1
1
Precedence Precedence
S2
3
H2
2
I2
1
Precedence Precedence
9
S1
H1
I1
S2
H2
I2
Only with
Precedence Constraints.
No need to finish
House 1 before House 2.
House1House2
S1
H1
I1
S2
H2
I2
H1-H2
I1-I2
With
Precedence Constraints
Availability Constraints
House1House2
S1
3
H1
2
I1
1
Precedence Precedence
S2
3
H2
2
I2
1
Precedence Precedence
S1
3
H1
2
I1
1
Precedence Precedence
S2
3
H2
2
I2
1
Precedence Precedence
10
S1
H1
I1
S2
H2
I2
S1
H1
I1
S2
H2
I2
Only with
Precedence Constraints.
No need to finish
House 1 before House 2.
H Idle Time
I Idle Time
With
Precedence Constraints
Availability Constraints
House1House2House1House2
S1
H1
I1
S2
H2
I2
With
Precedence Constraints
Availability Constraints
Continuity Constraints
House1House2
S1
3
H1
2
I1
1
Precedence Precedence
S2
3
H2
2
I2
1
Precedence Precedence
How to represent “Continuity Constraints” ?
S1
3
H1
2
I1
1
Precedence Precedence
S2
3
H2
2
I2
1
Precedence Precedence
How to represent several houses (units) effectively?
11
S1
3
H1
2
I1
1
Precedence Precedence
Unit 1
S2
3
H2
2
I2
1
Precedence Precedence
Unit 2
S3
3
H3
2
I3
1
Precedence Precedence
Unit 3
…
3
…
2
…
1
Precedence Precedence
…
3
…
2
…
1
Precedence Precedence
Unit …
Unit …
S9
3
H9
2
I9
1
Precedence Precedence
Unit 9
How to represent several houses (units) effectively?
12
A1
3
B1
2
D1
1Unit 1
C1
4
E1
2
A2
3
B2
2
D2
1Unit 2
C2
4
E2
2
A3
3
B3
2
D3
1Unit 3
C3
4
E3
2
By using AON or Bar Chart,
there is NOT enough space to present
all the units.
Quite Messy
Unit 4 to 5
How to represent several houses (units) effectively?
13
S1
3
H1
2
I1
1
Precedence Precedence
Unit 1
S2
3
H2
2
I2
1
Precedence Precedence
Unit 2
S3
3
H3
2
I3
1
Precedence Precedence
Unit 3
…
3
…
2
…
1
Precedence Precedence
Unit …
…
3
…
2
…
1
Precedence Precedence
Unit …
S9
3
H9
2
I9
1
Precedence Precedence
Unit 9
A repetitive project with only precedence constraints
14
S1 H1I1
Activityon Node
Unit 1
Unit 2
Unit 3
Unit 4
Unit 5
Unit 6
Unit 7
Unit 8
Unit 9
Production Diagram
S9 I9H9
Precedence & Availability & Continuity for Activity S
15
Unit 1
Unit 2
Unit 3
Unit 4
Unit 5
Unit 6
Unit 7
Unit 8
Unit 9
Activityon Node
S9 I9H9
S1
H1I1
Production Diagram
H idle time and I idle time between units
Production Diagram
H idle time and I idle time between units
Precedence & Availability & Continuity for S and H
16
Unit 1
Unit 2
Unit 3
Unit 4
Unit 5
Unit 6
Unit 7
Unit 8
Unit 9
Activityon Node
S9 I9H9
S1 H1 I1
Precedence & Availability & Continuity for S, H, and I
17
Unit 1
Unit 2
Unit 3
Unit 4
Unit 5
Unit 6
Unit 7
Unit 8
Unit 9
S9 I9
S1
H9
Activityon Node Production Diagram
or RSM Diagram
H1 I1
Production Diagram
H idletime and I idle time between units
Precedence & Availability & …
18
Unit 1
Unit 2
Unit 3
Unit 4
Unit 5
Unit 6
Unit 7
Unit 8
Unit 9
S H I
Production Diagram
or RSM Diagram
Unit 1
Unit 2
Unit 3
Unit 4
Unit 5
Unit 6
Unit 7
Unit 8
Unit 9
S H I
without Continuity Constraints with Continuity Constraints
VS
Repetitive Scheduling Method
The General Idea of RSM
19
The general idea of RSM
• RSM satisfies 3 types of constraints: activity precedence, resource availability and continuity.
20
Precedenceonly Precedence& Availability Precedence& Availability & Continuity
The general idea of RSM
• RSM satisfies 3 types of constraints: activity precedence, resource availability and continuity.
21
• RSM is a graphical method –no calculation ☺
Precedenceonly Precedence& Availability Precedence& Availability & Continuity
The general idea of RSM
• RSM satisfies 3 types of constraints: activity precedence, resource availability and continuity.
22
• RSM is a graphical method –no calculation ☺
• RSM uses production diagram:
• To represent projects with repeating activities.
• To determine activities’ start and finish dates.
Precedenceonly Precedence& Availability Precedence& Availability & Continuity
Repetitive Scheduling Method
Concept of Controlling Point (cp)
23
RSM Diagram
Controlling Point (cp) determining repetitive activities’ schedule
24
Unit 1
Unit 2
Unit 3
Unit 4
Unit 5
cpAB
Faster predecessor, cp at First unit.
A: 3 days/unit, and B: 4 days/unit
A1
A2
A3
A4
A5
RSM Diagram
Controlling Point (cp) determining repetitive activities’ schedule
25
Unit 1
Unit 2
Unit 3
Unit 4
Unit 5
cpAB
Faster predecessor, cp at First unit.
A: 3 days/unit, and B: 4 days/unit
A1
A2
A3
A4
A5
B1
RSM Diagram
Controlling Point (cp) determining repetitive activities’ schedule
26
Unit 1
Unit 2
Unit 3
Unit 4
Unit 5
cpAB
Faster predecessor, cp at First unit.
A: 3 days/unit, and B: 4 days/unit
A1
A2
A3
A4
A5
B1
B2
B3
B4
B5
RSM Diagram
Unit 1
Unit 2
Unit 3
Unit 4
Unit 5
Controlling Point (cp) determining repetitive activities’ schedule
27
RSM Diagram
Unit 1
Unit 2
Unit 3
Unit 4
Unit 5
cpAB
Slower predecessor, cp at Last unit.
A: 3 days/unit, and C: 2 days/unit.
Faster predecessor, cp at First unit.
A: 3 days/unit, and B: 4 days/unit
A1
A2
A3
A4
A5
A1
A2
A3
A4
A5
B1
B2
B3
B4
B5
cpAC
RSM Diagram
Unit 1
Unit 2
Unit 3
Unit 4
Unit 5
Controlling Point (cp) determining repetitive activities’ schedule
28
RSM Diagram
Unit 1
Unit 2
Unit 3
Unit 4
Unit 5
cpAB
Slower predecessor, cp at Last unit.
A: 3 days/unit, and C: 2 days/unit.
Faster predecessor, cp at First unit.
A: 3 days/unit, and B: 4 days/unit
A1
A2
A3
A4
A5
A1
A2
A3
A4
A5
B1
B2
B3
B4
B5 C5
cpAC
RSM Diagram
Unit 1
Unit 2
Unit 3
Unit 4
Unit 5
Controlling Point (cp) determining repetitive activities’ schedule
29
RSM Diagram
Unit 1
Unit 2
Unit 3
Unit 4
Unit 5
cpAB
Slower predecessor, cp at Last unit.
A: 3 days/unit, and C: 2 days/unit.
Faster predecessor, cp at First unit.
A: 3 days/unit, and B: 4 days/unit
A1
A2
A3
A4
A5
A1
A2
A3
A4
A5
B1
B2
B3
B4
B5
C1
C2
C3
C4
C5
cpAC
RSM Diagram
Unit 1
Unit 2
Unit 3
Unit 4
Unit 5
Controlling Point (cp) determining repetitive activities’ schedule
30
RSM Diagram
Unit 1
Unit 2
Unit 3
Unit 4
Unit 5
cpAB
Slower predecessor, cp at Last unit.
A: 3 days/unit, and C: 2 days/unit.
Faster predecessor, cp at First unit.
A: 3 days/unit, and B: 4 days/unit
A1
A2
A3
A4
A5
A1
A2
A3
A4
A5
B1
B2
B3
B4
B5
C1
C2
C3
C4
C5
cpAC
C1
C2
C3
C4
C5
If not using cp, there will be idle time between units.
Repetitive Scheduling Method
“Draw & Drag” to possible Controlling Points
31
RSM Diagram
Unit 1
Unit 2
Unit 3
Unit 4
Unit 5
Let’s “Draw & Drag” to possible cp instead
32
RSM Diagram
Unit 1
Unit 2
Unit 3
Unit 4
Unit 5
Slower predecessor, cp at Last unit.
A: 3 days/unit, and C: 2 days/unit.
Faster predecessor, cp at First unit.
A: 3 days/unit, and B: 4 days/unit
A1
A2
A3
A4
A5
A1
A2
A3
A4
A5
cp
cpcp
cp
1. Determine possible controlling points
RSM Diagram
Unit 1
Unit 2
Unit 3
Unit 4
Unit 5
Let’s “Draw & Drag” to possible cp instead
33
RSM Diagram
Unit 1
Unit 2
Unit 3
Unit 4
Unit 5
Slower predecessor, cp at Last unit.
A: 3 days/unit, and C: 2 days/unit.
Faster predecessor, cp at First unit.
A: 3 days/unit, and B: 4 days/unit
A1
A2
A3
A4
A5
A1
A2
A3
A4
A5
B1
B2
B3
B4
B5
C1
C2
C3
C4
C5
cp
cp
cp
cp
1. Determine possible controlling points
2. Draw the successor
RSM Diagram
Unit 1
Unit 2
Unit 3
Unit 4
Unit 5
Let’s “Draw & Drag” to possible cp instead
34
RSM Diagram
Unit 1
Unit 2
Unit 3
Unit 4
Unit 5
Slower predecessor, cp at Last unit.
A: 3 days/unit, and C: 2 days/unit.
Faster predecessor, cp at First unit.
A: 3 days/unit, and B: 4 days/unit
A1
A2
A3
A4
A5
A1
A2
A3
A4
A5
B1
B2
B3
B4
B5
C1
C2
C3
C4
C5
cp
cp
cp
cp
1. Determine possible controlling points
2. Draw the successor
3. Drag it horizontally to the first possible cp
Drag Drag
RSM Diagram
Unit 1
Unit 2
Unit 3
Unit 4
Unit 5
Let’s “Draw & Drag” to possible cp instead
35
RSM Diagram
Unit 1
Unit 2
Unit 3
Unit 4
Unit 5
Slower predecessor, cp at Last unit.
A: 3 days/unit, and C: 2 days/unit.
Faster predecessor, cp at First unit.
A: 3 days/unit, and B: 4 days/unit
A1
A2
A3
A4
A5
A1
A2
A3
A4
A5
cp
cp
cp
cp
1. Determine possible controlling points
2. Draw the successor
3. Drag it horizontally to the first possible cp
B1
B2
B3
B4
B5
C1
C2
C3
C4
C5
cpAC
cpAB
RSM Diagram
Unit 1
Unit 2
Unit 3
Unit 4
Unit 5
Let’s “Draw & Drag” to possible cp instead
36
RSM Diagram
Unit 1
Unit 2
Unit 3
Unit 4
Unit 5
Slower predecessor, cp at Last unit.
A: 3 days/unit, and C: 2 days/unit.
Faster predecessor, cp at First unit.
A: 3 days/unit, and B: 4 days/unit
A1
A2
A3
A4
A5
A1
A2
A3
A4
A5
1. Determine possible controlling points
2. Draw the successor
3. Drag it horizontally to the first possible cp
B1
B2
B3
B4
B5
C1
C2
C3
C4
C5
cpAC
cpAB
Repetitive Scheduling Method
Concept of Controlling Sequence
37
Concept of Controlling Sequence
What is Controlling Sequence?
• It is a sequence of unit activities from project Finish to Start.
• It determines project duration under continuity constraints.
• If a productivity of any activities on controlling sequence has changed, project duration will change.
How to identify Controlling Sequence? Easy. Start from the Project Finish to project Start via Controlling Points, cp.
38
Concept of Controlling Sequence
What is Controlling Sequence?
• It is a sequence of unit activities from project Finish to Start.
• It determines project duration under continuity constraints.
• If a productivity of any activities on controlling sequence has changed, project duration will change.
How to identify Controlling Sequence? Easy. Start from the Project Finish to project Start via Controlling Points, cp.
39
Concept of Controlling Sequence
What is Controlling Sequence?
• It is a sequence of unit activities from project Finish to Start.
• It determines project duration under continuity constraints.
• If a productivity of any activities on controlling sequence has changed, project duration will change.
How to identify Controlling Sequence? Easy. Start from the Project Finish to project Start via Controlling Points, cp.
40
Concept of Controlling Sequence
What is Controlling Sequence?
• It is a sequence of unit activities from project Finish to Start.
• It determines project duration under continuity constraints.
• If a productivity of any activities on controlling sequence has changed, project duration will change.
How to identify Controlling Sequence? Easy. Start from the Project Finish to project Start via Controlling Points, cp.
41
Concept of Controlling Sequence
What is Controlling Sequence?
• It is a sequence of unit activities from project Finish to Start.
• It determines project duration under continuity constraints.
• If a productivity of any activities on controlling sequence has changed, project duration will change.
How to identify Controlling Sequence? Easy. Start from the Project Finish to project Start via Controlling Points, cp.
42
Controlling Sequence:
B5-1, A1
Concept of Controlling Sequence
What is Controlling Sequence?
• It is a sequence of unit activities from project Finish to Start.
• It determines project duration under continuity constraints.
• If a productivity of any activities on controlling sequence has changed, project duration will change.
How to identify Controlling Sequence? Easy. Start from the Project Finish to project Start via Controlling Points, cp.
43
Controlling Sequence:
B5-1, A1
Concept of Controlling Sequence
What is Controlling Sequence?
• It is a sequence of unit activities from project Finish to Start.
• It determines project duration under continuity constraints.
• If a productivity of any activities on controlling sequence has changed, project duration will change.
How to identify Controlling Sequence? Easy. Start from the Project Finish to project Start via Controlling Points, cp.
44
Controlling Sequence:
B5-1, A1
Concept of Controlling Sequence
What is Controlling Sequence?
• It is a sequence of unit activities from project Finish to Start.
• It determines project duration under continuity constraints.
• If a productivity of any activities on controlling sequence has changed, project duration will change.
How to identify Controlling Sequence? Easy. Start from the Project Finish to project Start via Controlling Points, cp.
45
Controlling Sequence:
B5-1, A1
Concept of Controlling Sequence
What is Controlling Sequence?
• It is a sequence of unit activities from project Finish to Start.
• It determines project duration under continuity constraints.
• If a productivity of any activities on controlling sequence has changed, project duration will change.
How to identify Controlling Sequence? Easy. Start from the Project Finish to project Start via Controlling Points, cp.
46
Controlling Sequence:
B5-1, A1
Controlling Sequence:
C5, A5-1
Another example for the concept of Controlling Sequence
47 RSM Diagram
Unit 1
Unit 2
Unit 3
Unit 4
Unit 5
A1
A2
A3
A4
A5
B1
B2
B3
B4
B5
C1
C2
C3
C4
C5
AC
AB
A
3
B
4
C
2
D
4
Another example for the concept of Controlling Sequence
48 RSM Diagram
Unit 1
Unit 2
Unit 3
Unit 4
Unit 5
A1
A2
A3
A4
A5
B1
B2
B3
B4
B5
C1
C2
C3
C4
C5
AC
AB
A
3
B
4
C
2
D
4
D1
D2
D3
D4
D5
Another example for the concept of Controlling Sequence
49 RSM Diagram
Unit 1
Unit 2
Unit 3
Unit 4
Unit 5
A1
A2
A3
A4
A5
B1
B2
B3
B4
B5
C1
C2
C3
C4
C5
AC
AB
A
3
B
4
C
2
D
4
cp
cp
D1
D2
D3
D4
D5
Another example for the concept of Controlling Sequence
50 RSM Diagram
Unit 1
Unit 2
Unit 3
Unit 4
Unit 5
A1
A2
A3
A4
A5
B1
B2
B3
B4
B5
C1
C2
C3
C4
C5
AC
AB
A
3
B
4
C
2
D
4
cp
cp
cp
cp
D1
D2
D3
D4
D5
Another example for the concept of Controlling Sequence
51 RSM Diagram
Unit 1
Unit 2
Unit 3
Unit 4
Unit 5
A1
A2
A3
A4
A5
B1
B2
B3
B4
B5
C1
C2
C3
C4
C5
AC
AB
D1
D2
D3
D4
D5
A
3
B
4
C
2
D
4
cp
cp
cp
cp
Drag
Another example for the concept of Controlling Sequence
52 RSM Diagram
Unit 1
Unit 2
Unit 3
Unit 4
Unit 5
A1
A2
A3
A4
A5
B1
B2
B3
B4
B5
C1
C2
C3
C4
C5
AC
AB
D1
D2
D3
D4
D5
A
3
B
4
C
2
D
4
CD
Another example for the concept of Controlling Sequence
53 RSM Diagram
Unit 1
Unit 2
Unit 3
Unit 4
Unit 5
A1
A2
A3
A4
A5
B1
B2
B3
B4
B5
C1
C2
C3
C4
C5
AC
AB
D1
D2
D3
D4
D5
A
3
B
4
C
2
D
4
CD
Another example for the concept of Controlling Sequence
54 RSM Diagram
Unit 1
Unit 2
Unit 3
Unit 4
Unit 5
A1
A2
A3
A4
A5
B1
B2
B3
B4
B5
C1
C2
C3
C4
C5
AC
AB
D1
D2
D3
D4
D5
A
3
B
4
C
2
D
4
CD
Another example for the concept of Controlling Sequence
55 RSM Diagram
Unit 1
Unit 2
Unit 3
Unit 4
Unit 5
A1
A2
A3
A4
A5
B1
B2
B3
B4
B5
C1
C2
C3
C4
C5
AC
AB
D1
D2
D3
D4
D5
A
3
B
4
C
2
D
4
CD
Another example for the concept of Controlling Sequence
56 RSM Diagram
Unit 1
Unit 2
Unit 3
Unit 4
Unit 5
A1
A2
A3
A4
A5
B1
B2
B3
B4
B5
C1
C2
C3
C4
C5
AC
AB
D1
D2
D3
D4
D5
A
3
B
4
C
2
D
4
CD
Another example for the concept of Controlling Sequence
57 RSM Diagram
Unit 1
Unit 2
Unit 3
Unit 4
Unit 5
A1
A2
A3
A4
A5
B1
B2
B3
B4
B5
C1
C2
C3
C4
C5
AC
AB
D1
D2
D3
D4
D5
A
3
B
4
C
2
D
4
CD
Another example for the concept of Controlling Sequence
58 RSM Diagram
Unit 1
Unit 2
Unit 3
Unit 4
Unit 5
A1
A2
A3
A4
A5
B1
B2
B3
B4
B5
C1
C2
C3
C4
C5
AC
AB
D1
D2
D3
D4
D5
A
3
B
4
C
2
D
4
CD
Activities on ControllingSequence:
D5-1, C2-4, A5-1
Another example for the concept of Controlling Sequence
59 RSM Diagram
Unit 1
Unit 2
Unit 3
Unit 4
Unit 5
A1
A2
A3
A4
A5
B1
B2
B3
B4
B5
C1
C2
C3
C4
C5
AC
AB
D1
D2
D3
D4
D5
A
3
B
4
C
2
D
4
CD
Activities on ControllingSequence:
D5-1, C2-4, A5-1
Changing productivity ofcontrollingactivities
will change project duration immediately.
Another example for the concept of Controlling Sequence
60 RSM Diagram
Unit 1
Unit 2
Unit 3
Unit 4
Unit 5
A1
A2
A3
A4
A5
B1
B2
B3
B4
B5
C1
C2
C3
C4
C5
AC
AB
D1
D2
D3
D4
D5
A
3
B
4
C
2
D
4
CD
Activities on ControllingSequence:
D5-1, C2-4, A5-1
Changing productivity ofcontrollingactivities
will change project duration immediately.
On the other hand, changingthose
of non-controlling activities
will Not immediately affect project duration,
such as B1-5, C1, and C5.
Repetitive Scheduling Method
Critical Activities on RSM
61
Critical Activities on RSM
62 RSM Diagram
Unit 1
Unit 2
Unit 3
Unit 4
Unit 5
A
3
B
4
C
2
D
4
D5
D4
D3
D2
D1
B5
B4
B3
B2
B1
C5
C4AC
CDAB
C3
C2
C1
A5
A4
A3
A2
A1
• Critical activities are that if delayed,
project will be delayed.
• Critical activities do not consider
resource continuity constraints.
Critical Activities on RSM
63 RSM Diagram
Unit 1
Unit 2
Unit 3
Unit 4
Unit 5
A
3
B
4
C
2
D
4
D5
D4
D3
D2
D1
B5
B4
B3
B2
B1
C5
C4AC
CDAB
C3
C2
C1
A5
A4
A3
A2
A1
• Critical activities are that if delayed,
project will be delayed.
• Critical activities do not consider
resource continuity constraints.
• Delaying D5 will delay project.
Project is delayed.
Critical Activities on RSM
64 RSM Diagram
Unit 1
Unit 2
Unit 3
Unit 4
Unit 5
A
3
B
4
C
2
D
4
D5
D4
D3
D2
D1
B5
B4
B3
B2
B1
C5
C4AC
CDAB
C3
C2
C1
A5
A4
A3
A2
A1
• Critical activities are that if delayed,
project will be delayed.
• Critical activities do not consider
resource continuity constraints.
• Delaying D5 will delay project.
Again, CPM doesn’t care about
resource continuity constraints.
If delaying an activity and it delays
project duration, it is a critical activity.
Therefore, D5 is a critical activity.
Project is delayed.
Critical Activities on RSM
65 RSM Diagram
Unit 1
Unit 2
Unit 3
Unit 4
Unit 5
A
3
B
4
C
2
D
4
D5
D4
D3
D2
D1
B5
B4
B3
B2
B1
C5
C4AC
CDAB
C3
C2
C1
A5
A4
A3
A2
A1
• Critical activities are that if delayed,
project will be delayed.
• Critical activities do not consider
resource continuity constraints.
• Delaying D5 will delay project.
• Delaying D4 will delay project.
Project is delayed.
Critical Activities on RSM
66 RSM Diagram
Unit 1
Unit 2
Unit 3
Unit 4
Unit 5
A
3
B
4
C
2
D
4
D5
D4
D3
D2
D1
B5
B4
B3
B2
B1
C5
C4AC
CDAB
C3
C2
C1
A5
A4
A3
A2
A1
• Critical activities are that if delayed,
project will be delayed.
• Critical activities do not consider
resource continuity constraints.
• Delaying D5 will delay project.
• Delaying D4 will delay project.
• Delaying D1 will delay project.
Project is delayed.
Tip 1. If the last unit is critical,
all are also critical, due to continuity.
Critical Activities on RSM
67 RSM Diagram
Unit 1
Unit 2
Unit 3
Unit 4
Unit 5
A
3
B
4
C
2
D
4
D5
D4
D3
D2
D1
B5
B4
B3
B2
B1
C5
C4AC
CDAB
C3
C2
C1
A5
A4
A3
A2
A1
• Critical activities are that if delayed,
project will be delayed.
• Critical activities do not consider
resource continuity constraints.
• Delaying D5 will delay project.
• Delaying D4 will delay project.
• Delaying D1 will delay project.
• Delaying C5 will not delay project.Project is not delayed.
Tip 1. If the last unit is critical,
all are also critical, due to continuity.
Critical Activities on RSM
68 RSM Diagram
Unit 1
Unit 2
Unit 3
Unit 4
Unit 5
A
3
B
4
C
2
D
4
D5
D4
D3
D2
D1
B5
B4
B3
B2
B1
C4AC
CDAB
C3
C2
C1
A5
A4
A3
A2
A1
• Critical activities are that if delayed,
project will be delayed.
• Critical activities do not consider
resource continuity constraints.
• Delaying D5 will delay project.
• Delaying D4 will delay project.
• Delaying D1 will delay project.
• Delaying C5 will not delay project.Project is not delayed.
The discontinuity here doesn’t matter,
when talking about “Critical Activities”
C5
Tip 1. If the last unit is critical,
all are also critical, due to continuity.
Critical Activities on RSM
69 RSM Diagram
Unit 1
Unit 2
Unit 3
Unit 4
Unit 5
A
3
B
4
C
2
D
4
D5
D4
D3
D2
D1
B5
B4
B3
B2
B1
C5
C4AC
CDAB
C3
C2
C1
A5
A4
A3
A2
A1
• Critical activities are that if delayed,
project will be delayed.
• Critical activities do not consider
resource continuity constraints.
• Delaying D5 will delay project.
• Delaying D4 will delay project.
• Delaying D1 will delay project.
• Delaying C5 will not delay project.Project is not delayed.
The discontinuity here doesn’t matter,
when talking about “Critical Activities.”
Don’t try to satisfy continuity constraints
when identifying “critical activities.”
Tip 1. If the last unit is critical,
all are also critical, due to continuity.
Critical Activities on RSM
70 RSM Diagram
Unit 1
Unit 2
Unit 3
Unit 4
Unit 5
A
3
B
4
C
2
D
4
D5
D4
D3
D2
D1
B5
B4
B3
B2
B1
C5
C4AC
CDAB
C3
C2
C1
A5
A4
A3
A2
A1
• Critical activities are that if delayed,
project will be delayed.
• Critical activities do not consider
resource continuity constraints.
• Delaying D5 will delay project.
• Delaying D4 will delay project.
• Delaying D1 will delay project.
• Delaying C5 will not delay project.
• Delaying C4 will not delay project.
Project is not delayed.
Tip 1. If the last unit is critical,
all are also critical, due to continuity.
Critical Activities on RSM
71 RSM Diagram
Unit 1
Unit 2
Unit 3
Unit 4
Unit 5
A
3
B
4
C
2
D
4
D5
D4
D3
D2
D1
B5
B4
B3
B2
B1
CDAB
C5
C4
C3
C2
C1
A5
A4
A3
A2
A1
• Critical activities are that if delayed,
project will be delayed.
• Critical activities do not consider
resource continuity constraints.
AC
• Delaying D5 will delay project.
• Delaying D4 will delay project.
• Delaying D1 will delay project.
• Delaying C5 will not delay project.
• Delaying C4 will not delay project.
• Delaying C2 will not delay project.
Project is not delayed.
Tip 1. If the last unit is critical,
all are also critical, due to continuity.
Critical Activities on RSM
72 RSM Diagram
Unit 1
Unit 2
Unit 3
Unit 4
Unit 5
A
3
B
4
C
2
D
4
B5
B4
B3
B2
B1
AB
D5
D4
D3
D2
D1
C5
C4
CD
C3
C2
C1
A5
A4
A3
A2
A1
• Critical activities are that if delayed,
project will be delayed.
• Critical activities do not consider
resource continuity constraints.
AC
• Delaying D5 will delay project.
• Delaying D4 will delay project.
• Delaying D1 will delay project.
• Delaying C5 will not delay project.
• Delaying C4 will not delay project.
• Delaying C2 will not delay project.
• Delaying C1 will delay project.
Project is delayed.
Tip 1. If the last unit is critical,
all are also critical, due to continuity.
Critical Activities on RSM
73 RSM Diagram
Unit 1
Unit 2
Unit 3
Unit 4
Unit 5
A
3
B
4
C
2
D
4
B5
B4
B3
B2
B1
AB
D5
D4
D3
D2
D1
C5
C4
CD
C3
C2
C1
A5
A4
A3
A2
A1
• Critical activities are that if delayed,
project will be delayed.
• Critical activities do not consider
resource continuity constraints.
AC
• Delaying D5 will delay project.
• Delaying D4 will delay project.
• Delaying D1 will delay project.
• Delaying C5 will not delay project.
• Delaying C4 will not delay project.
• Delaying C2 will not delay project.
• Delaying C1 will delay project.
Project is delayed.
Tip 1. If the last unit is critical,
all are also critical, due to continuity.
Tip 2. If the last unit is not critical,
only the first unit could be critical.
So you only need to check the first & the last.
(Applicable to repetitive projects with
only typical repetitiveactivities.)
Critical Activities on RSM
74 RSM Diagram
Unit 1
Unit 2
Unit 3
Unit 4
Unit 5
A
3
B
4
C
2
D
4
D5
D4
D3
D2
D1
B5
B4
B3
B2
B1
C5
C4AC
CDAB
C3
C2
C1
A5
A4
A3
A2
A1
• Critical activities are that if delayed,
project will be delayed.
• Critical activities do not consider
resource continuity constraints.
• Delaying D5 will delay project.
• Delaying D4 will delay project.
• Delaying D1 will delay project.
• Delaying C5 will not delay project.
• Delaying C4 will not delay project.
• Delaying C2 will not delay project.
• Delaying C1 will delay project.
• Delaying B5 will not delay project.
Project is not delayed.
Tip 1. If the last unit is critical,
all are also critical, due to continuity.
Tip 2. If the last unit is not critical,
only the first unit could be critical.
So you only need to check the first & the last.
(Applicable to repetitive projects with
only typical repetitiveactivities.)
Critical Activities on RSM
75 RSM Diagram
Unit 1
Unit 2
Unit 3
Unit 4
Unit 5
A
3
B
4
C
2
D
4
D5
D4
D3
D2
D1
B5
B4
B3
B2
B1
C5
C4AC
CDAB
C3
C2
C1
A5
A4
A3
A2
A1
• Critical activities are that if delayed,
project will be delayed.
• Critical activities do not consider
resource continuity constraints.
• Delaying D5 will delay project.
• Delaying D4 will delay project.
• Delaying D1 will delay project.
• Delaying C5 will not delay project.
• Delaying C4 will not delay project.
• Delaying C2 will not delay project.
• Delaying C1 will delay project.
• Delaying B5 will not delay project.
Project is not delayed.
Tip 1. If the last unit is critical,
all are also critical, due to continuity.
Tip 2. If the last unit is not critical,
only the first unit could be critical.
So you only need to check the first & the last.
(Applicable to repetitive projects with
only typical repetitiveactivities.)
The discontinuity here doesn’t matter,
when talking about “Critical Activities.”
Critical Activities on RSM
76 RSM Diagram
Unit 1
Unit 2
Unit 3
Unit 4
Unit 5
A
3
B
4
C
2
D
4
D5
D4
D3
D2
D1
B5
B4
B3
B2
B1
C5
C4AC
CDAB
C3
C2
C1
A5
A4
A3
A2
A1
• Critical activities are that if delayed,
project will be delayed.
• Critical activities do not consider
resource continuity constraints.
• Delaying D5 will delay project.
• Delaying D4 will delay project.
• Delaying D1 will delay project.
• Delaying C5 will not delay project.
• Delaying C4 will not delay project.
• Delaying C2 will not delay project.
• Delaying C1 will delay project.
• Delaying B5 will not delay project.
• Delaying B1 will not delay project.
Project is not delayed.
Tip 1. If the last unit is critical,
all are also critical, due to continuity.
Tip 2. If the last unit is not critical,
only the first unit could be critical.
So you only need to check the first & the last.
(Applicable to repetitive projects with
only typical repetitiveactivities.)
Critical Activities on RSM
77 RSM Diagram
Unit 1
Unit 2
Unit 3
Unit 4
Unit 5
A
3
B
4
C
2
D
4
D5
D4
D3
D2
D1
B5
B4
B3
B2
B1
C5
C4AC
CDAB
C3
C2
C1
A5
A4
A3
A2
A1
• Critical activities are that if delayed,
project will be delayed.
• Critical activities do not consider
resource continuity constraints.
• Delaying D5 will delay project.
• Delaying D4 will delay project.
• Delaying D1 will delay project.
• Delaying C5 will not delay project.
• Delaying C4 will not delay project.
• Delaying C2 will not delay project.
• Delaying C1 will delay project.
• Delaying B5 will not delay project.
• Delaying B1 will not delay project.
Project is not delayed.
Tip 1. If the last unit is critical,
all are also critical, due to continuity.
Tip 2. If the last unit is not critical,
only the first unit could be critical.
So you only need to check the first & the last.
(Applicable to repetitive projects with
only typical repetitiveactivities.)
Critical Activities on RSM
78 RSM Diagram
Unit 1
Unit 2
Unit 3
Unit 4
Unit 5
A
3
B
4
C
2
D
4
D5
D4
D3
D2
D1
B5
B4
B3
B2
B1
C4
CDAB
C3
C2
C1
C5
AC
A5
A4
A3
A2
A1
• Critical activities are that if delayed,
project will be delayed.
• Critical activities do not consider
resource continuity constraints.
• Delaying D5 will delay project.
• Delaying D4 will delay project.
• Delaying D1 will delay project.
• Delaying C5 will not delay project.
• Delaying C4 will not delay project.
• Delaying C2 will not delay project.
• Delaying C1 will delay project.
• Delaying B5 will not delay project.
• Delaying B1 will not delay project.
• Delaying A5 will not delay project.
Tip 1. If the last unit is critical,
all are also critical, due to continuity.
Tip 2. If the last unit is not critical,
only the first unit could be critical.
So you only need to check the first & the last.
(Applicable to repetitive projects with
only typical repetitiveactivities.)
Project is not delayed.
Critical Activities on RSM
79 RSM Diagram
Unit 1
Unit 2
Unit 3
Unit 4
Unit 5
A
3
B
4
C
2
D
4
D5
D4
D3
D2
D1
C4
CD
C3
C2
C1
B5
B4
B3
B2
B1
C5
AC
AB
A5
A4
A3
A2
A1
• Critical activities are that if delayed,
project will be delayed.
• Critical activities do not consider
resource continuity constraints.
• Delaying D5 will delay project.
• Delaying D4 will delay project.
• Delaying D1 will delay project.
• Delaying C5 will not delay project.
• Delaying C4 will not delay project.
• Delaying C2 will not delay project.
• Delaying C1 will delay project.
• Delaying B5 will not delay project.
• Delaying B1 will not delay project.
• Delaying A5 will not delay project.
• Delaying A1 will not delay project.
Tip 1. If the last unit is critical,
all are also critical, due to continuity.
Tip 2. If the last unit is not critical,
only the first unit could be critical.
So you only need to check the first & the last.
(Applicable to repetitive projects with
only typical repetitiveactivities.)
Project is not delayed.
Critical Activities on RSM
80 RSM Diagram
Unit 1
Unit 2
Unit 3
Unit 4
Unit 5
A
3
B
4
C
2
D
4
D5
D4
D3
D2
D1
B5
B4
B3
B2
B1
C5
C4AC
CDAB
C3
C2
C1
A5
A4
A3
A2
A1
• Critical activities are that if delayed,
project will be delayed.
• Critical activities do not consider
resource continuity constraints.
• Delaying D5 will delay project.
• Delaying D4 will delay project.
• Delaying D1 will delay project.
• Delaying C5 will not delay project.
• Delaying C4 will not delay project.
• Delaying C2 will not delay project.
• Delaying C1 will delay project.
• Delaying B5 will not delay project.
• Delaying B1 will not delay project.
• Delaying A5 will not delay project.
• Delaying A1 will not delay project.
Therefore, critical activities are:
D5-1, and C1.
Tip 1. If the last unit is critical,
all are also critical, due to continuity.
Tip 2. If the last unit is not critical,
only the first unit could be critical.
So you only need to check the first & the last.
(Applicable to repetitive projects with
only typical repetitiveactivities.)
Critical Activities on RSM & Controlling Activities
81 RSM Diagram
Unit 1
Unit 2
Unit 3
Unit 4
Unit 5
A
3
B
4
C
2
D
4
D5
D4
D3
D2
D1
B5
B4
B3
B2
B1
C5
C4AC
CDAB
C3
C2
C1
A5
A4
A3
A2
A1
• Critical activities are that if delayed,
project will be delayed.
• Critical activities do not consider
resource continuity constraints.
• Delaying D5 will delay project.
• Delaying D4 will delay project.
• Delaying D1 will delay project.
• Delaying C5 will not delay project.
• Delaying C4 will not delay project.
• Delaying C2 will not delay project.
• Delaying C1 will delay project.
• Delaying B5 will not delay project.
• Delaying B1 will not delay project.
• Delaying A5 will not delay project.
• Delaying A1 will not delay project.
Therefore, critical activities are:
D5-1, and C1.
Tip 1. If the last unit is critical,
all are also critical, due to continuity.
Tip 2. If the last unit is not critical,
only the first unit could be critical.
So you only need to check the first & the last.
(Applicable to repetitive projects with
only typical repetitiveactivities.)
D5-1, C2-4, and A5-1
Repetitive Scheduling Method
Example 1: 3 units
82
B
1
C
4
D
6
A
3
Example 1: 3 units
83
Unit 1
Unit 2
Unit 3
2 4 6 8 10 12 14 16 18 20 22 24 26 28 30 32 34 36 38 400 42 44 46 48 50
B
1
C
4
D
6
A
3
• Identify controllingpoints, cp
• ...
• Identify controllingsequence
• …
• Identify critical activities
• …
Example 1: 3 units
84
Unit 1
Unit 2
Unit 3
2 4 6 8 10 12 14 16 18 20 22 24 26 28 30 32 34 36 38 400 42 44 46 48 50
A
B
1
C
4
D
6
A
3
• Identify controllingpoints, cp
• ...
• Identify controllingsequence
• …
• Identify critical activities
• …
Example 1: 3 units
85
Unit 1
Unit 2
Unit 3
2 4 6 8 10 12 14 16 18 20 22 24 26 28 30 32 34 36 38 400 42 44 46 48 50
A B
B
1
C
4
D
6
A
3
AB
• Identify controllingpoints, cp
• ...
• Identify controllingsequence
• …
• Identify critical activities
• …
Example 1: 3 units
86
Unit 1
Unit 2
Unit 3
2 4 6 8 10 12 14 16 18 20 22 24 26 28 30 32 34 36 38 400 42 44 46 48 50
A B C
B
1
C
4
D
6
A
3
BC
AB
• Identify controllingpoints, cp
• ...
• Identify controllingsequence
• …
• Identify critical activities
• …
Example 1: 3 units
87
Unit 1
Unit 2
Unit 3
2 4 6 8 10 12 14 16 18 20 22 24 26 28 30 32 34 36 38 400 42 44 46 48 50
A B DC
B
1
C
4
D
6
A
3
BC CD
AB
• Identify controllingpoints, cp
• ...
• Identify controllingsequence
• …
• Identify critical activities
• …
Example 1: 3 units
88
Unit 1
Unit 2
Unit 3
2 4 6 8 10 12 14 16 18 20 22 24 26 28 30 32 34 36 38 400 42 44 46 48 50
A B DC
B
1
C
4
D
6
A
3
BC CD
AB
• Identify controllingpoints, cp
• AB, BC, CD
• Identify controllingsequence
• …
• Identify critical activities
• …
Example 1: 3 units
89
Unit 1
Unit 2
Unit 3
2 4 6 8 10 12 14 16 18 20 22 24 26 28 30 32 34 36 38 400 42 44 46 48 50
A B DC
B
1
C
4
D
6
A
3
BC CD
AB
• Identify controllingpoints, cp
• AB, BC, CD
• Identify controllingsequence
• …
• Identify critical activities
• …
Example 1: 3 units
90
Unit 1
Unit 2
Unit 3
2 4 6 8 10 12 14 16 18 20 22 24 26 28 30 32 34 36 38 400 42 44 46 48 50
A B DC
B
1
C
4
D
6
A
3
BC CD
AB
• Identify controllingpoints, cp
• AB, BC, CD
• Identify controllingsequence
• D3-1, C1, B2, A3-1
• Identify critical activities
• …
Example 1: 3 units
91
Unit 1
Unit 2
Unit 3
2 4 6 8 10 12 14 16 18 20 22 24 26 28 30 32 34 36 38 400 42 44 46 48 50
A B DC
B
1
C
4
D
6
A
3
BC CD
AB
• Identify controllingpoints, cp
• AB, BC, CD
• Identify controllingsequence
• D3-1, C1, B2, A3-1
• Identify critical activities
• …
Tip 1. If the last unit is critical,
all are also critical, due to continuity.
Tip 2. If the last unit is not critical,
only the first unit could be critical.
So you only need to check the first & the last.
(Applicable to repetitive projects with
only typical repetitiveactivities.)
Example 1: 3 units
92
Unit 1
Unit 2
Unit 3
2 4 6 8 10 12 14 16 18 20 22 24 26 28 30 32 34 36 38 400 42 44 46 48 50
A B DC
B
1
C
4
D
6
A
3
BC CD
AB
• Identify controllingpoints, cp
• AB, BC, CD
• Identify controllingsequence
• D3-1, C1, B2, A3-1
• Identify critical activities
• …
Tip 1. If the last unit is critical,
all are also critical, due to continuity.
Tip 2. If the last unit is not critical,
only the first unit could be critical.
So you only need to check the first & the last.
(Applicable to repetitive projects with
only typical repetitiveactivities.)
Example 1: 3 units
93
Unit 1
Unit 2
Unit 3
2 4 6 8 10 12 14 16 18 20 22 24 26 28 30 32 34 36 38 400 42 44 46 48 50
A B DC
B
1
C
4
D
6
A
3
BC CD
AB
• Identify controllingpoints, cp
• AB, BC, CD
• Identify controllingsequence
• D3-1, C1, B2, A3-1
• Identify critical activities
• D3-1, C1, B1
Tip 1. If the last unit is critical,
all are also critical, due to continuity.
Tip 2. If the last unit is not critical,
only the first unit could be critical.
So you only need to check the first & the last.
(Applicable to repetitive projects with
only typical repetitiveactivities.)
Repetitive Scheduling Method
Example 2: 4 units
94
A
3
B
1
C
6
D
3
E
5
Example 2: 4 units
95
Unit 1
Unit 2
Unit 3
Unit 4
2 4 6 8 10 12 14 16 18 20 22 24 26 28 30 32 34 36 38 400 42 44 46 48 50
A
3
B
1
C
6
D
3
E
5
• Identify controllingpoints, cp
• ...
• Identify controllingsequence
• …
• Identify critical activities
• …
Example 2: 4 units
96
Unit 1
Unit 2
Unit 3
Unit 4
2 4 6 8 10 12 14 16 18 20 22 24 26 28 30 32 34 36 38 400 42 44 46 48 50
A
A
3
B
1
C
6
D
3
E
5
• Identify controllingpoints, cp
• ...
• Identify controllingsequence
• …
• Identify critical activities
• …
Example 2: 4 units
97
Unit 1
Unit 2
Unit 3
Unit 4
2 4 6 8 10 12 14 16 18 20 22 24 26 28 30 32 34 36 38 400 42 44 46 48 50
A B
A
3
B
1
C
6
D
3
E
5
AB
• Identify controllingpoints, cp
• ...
• Identify controllingsequence
• …
• Identify critical activities
• …
Example 2: 4 units
98
Unit 1
Unit 2
Unit 3
Unit 4
2 4 6 8 10 12 14 16 18 20 22 24 26 28 30 32 34 36 38 400 42 44 46 48 50
A B C
A
3
B
1
C
6
D
3
E
5
AB
• Identify controllingpoints, cp
• ...
• Identify controllingsequence
• …
• Identify critical activities
• …
AC
Example 2: 4 units
99
Unit 1
Unit 2
Unit 3
Unit 4
2 4 6 8 10 12 14 16 18 20 22 24 26 28 30 32 34 36 38 400 42 44 46 48 50
A B CD
A
3
B
1
C
6
D
3
E
5
AB
• Identify controllingpoints, cp
• ...
• Identify controllingsequence
• …
• Identify critical activities
• …
BDAC
Example 2: 4 units
100
Unit 1
Unit 2
Unit 3
Unit 4
2 4 6 8 10 12 14 16 18 20 22 24 26 28 30 32 34 36 38 400 42 44 46 48 50
A B CD
A
3
B
1
C
6
D
3
E
5
AB
• Identify controllingpoints, cp
• ...
• Identify controllingsequence
• …
• Identify critical activities
• …
BDAC
Determine possible cp from D and C to E
Example 2: 4 units
101
Unit 1
Unit 2
Unit 3
Unit 4
2 4 6 8 10 12 14 16 18 20 22 24 26 28 30 32 34 36 38 400 42 44 46 48 50
A B CD
A
3
B
1
C
6
D
3
E
5
AB
• Identify controllingpoints, cp
• ...
• Identify controllingsequence
• …
• Identify critical activities
• …
BDAC
E
Drag
Determine possible cp from D and C to E
Example 2: 4 units
102
Unit 1
Unit 2
Unit 3
Unit 4
2 4 6 8 10 12 14 16 18 20 22 24 26 28 30 32 34 36 38 400 42 44 46 48 50
A B CD E
A
3
B
1
C
6
D
3
E
5
AB
• Identify controllingpoints, cp
• ...
• Identify controllingsequence
• …
• Identify critical activities
• …
BD DEAC
Example 2: 4 units
103
Unit 1
Unit 2
Unit 3
Unit 4
2 4 6 8 10 12 14 16 18 20 22 24 26 28 30 32 34 36 38 400 42 44 46 48 50
A B CD E
A
3
B
1
C
6
D
3
E
5
AB
• Identify controllingpoints, cp
• AC, AB, BD, DE
• Identify controllingsequence
• …
• Identify critical activities
• …
BD DEAC
Example 2: 4 units
104
Unit 1
Unit 2
Unit 3
Unit 4
2 4 6 8 10 12 14 16 18 20 22 24 26 28 30 32 34 36 38 400 42 44 46 48 50
A B CD E
A
3
B
1
C
6
D
3
E
5
• Identify controllingpoints, cp
• AC, AB, BD, DE
• Identify controllingsequence
• …
• Identify critical activities
• …
BD DEAC
AB
Example 2: 4 units
105
Unit 1
Unit 2
Unit 3
Unit 4
2 4 6 8 10 12 14 16 18 20 22 24 26 28 30 32 34 36 38 400 42 44 46 48 50
A B CD E
A
3
B
1
C
6
D
3
E
5
• Identify controllingpoints, cp
• AC, AB, BD, DE
• Identify controllingsequence
• E4-1, D1, B2-3, A4-1
• Identify critical activities
• …
BD DEAC
AB
Example 2: 4 units
106
Unit 1
Unit 2
Unit 3
Unit 4
2 4 6 8 10 12 14 16 18 20 22 24 26 28 30 32 34 36 38 400 42 44 46 48 50
A B CD E
A
3
B
1
C
6
D
3
E
5
• Identify controllingpoints, cp
• AC, AB, BD, DE
• Identify controllingsequence
• E4-1, D1, B2-3, A4-1
• Identify critical activities
• …
BD DEAC
AB
Example 2: 4 units
107
Unit 1
Unit 2
Unit 3
Unit 4
2 4 6 8 10 12 14 16 18 20 22 24 26 28 30 32 34 36 38 400 42 44 46 48 50
A B CD E
A
3
B
1
C
6
D
3
E
5
• Identify controllingpoints, cp
• AC, AB, BD, DE
• Identify controllingsequence
• E4-1, D1, B2-3, A4-1
• Identify critical activities
• E4-1, D1, B1
BD DEAC
AB
Repetitive Scheduling Method
Example 3: 6 units
108
A
1
B
2
C
3
D
1
E
4
F
1
Example 3: 6 units
109
Unit 1
Unit 3
Unit 6
2 4 6 8 10 12 14 16 18 20 22 24 26 28 30 32 34 36 38 400 42 44 46 48 50
Unit 2
Unit 4
Unit 5
• Identify controllingpoints, cp
• ...
• Identify controllingsequence
• …
• Identify critical activities
• …
A
1
B
2
C
3
D
1
E
4
F
1
Example 3: 6 units
110
Unit 1
Unit 3
Unit 6
2 4 6 8 10 12 14 16 18 20 22 24 26 28 30 32 34 36 38 400 42 44 46 48 50
A
Unit 2
Unit 4
Unit 5
• Identify controllingpoints, cp
• ...
• Identify controllingsequence
• …
• Identify critical activities
• …
A
1
B
2
C
3
D
1
E
4
F
1
Example 3: 6 units
111
Unit 1
Unit 3
Unit 6
2 4 6 8 10 12 14 16 18 20 22 24 26 28 30 32 34 36 38 400 42 44 46 48 50
A B C
Unit 2
Unit 4
Unit 5
• Identify controllingpoints, cp
• ...
• Identify controllingsequence
• …
• Identify critical activities
• …
A
1
B
2
C
3
D
1
E
4
F
1
AB, AC
Example 3: 6 units
112
Unit 1
Unit 3
Unit 6
2 4 6 8 10 12 14 16 18 20 22 24 26 28 30 32 34 36 38 400 42 44 46 48 50
A B C
Unit 2
Unit 4
Unit 5
• Identify controllingpoints, cp
• ...
• Identify controllingsequence
• …
• Identify critical activities
• …
A
1
B
2
C
3
D
1
E
4
F
1
AB, AC
Determine possible cp from B and C to D
Example 3: 6 units
113
Unit 1
Unit 3
Unit 6
2 4 6 8 10 12 14 16 18 20 22 24 26 28 30 32 34 36 38 400 42 44 46 48 50
A B C
Unit 2
Unit 4
Unit 5
• Identify controllingpoints, cp
• ...
• Identify controllingsequence
• …
• Identify critical activities
• …
A
1
B
2
C
3
D
1
E
4
F
1
AB, AC
Determine possible cp from B and C to D
D
Drag
Example 3: 6 units
114
Unit 1
Unit 3
Unit 6
2 4 6 8 10 12 14 16 18 20 22 24 26 28 30 32 34 36 38 400 42 44 46 48 50
A B DC
Unit 2
Unit 4
Unit 5
• Identify controllingpoints, cp
• ...
• Identify controllingsequence
• …
• Identify critical activities
• …
A
1
B
2
C
3
D
1
E
4
F
1
AB, AC
CD
Example 3: 6 units
115
Unit 1
Unit 3
Unit 6
2 4 6 8 10 12 14 16 18 20 22 24 26 28 30 32 34 36 38 400 42 44 46 48 50
A B DC E
Unit 2
Unit 4
Unit 5
• Identify controllingpoints, cp
• ...
• Identify controllingsequence
• …
• Identify critical activities
• …
A
1
B
2
C
3
D
1
E
4
F
1
AB, AC DE
CD
Example 3: 6 units
116
Unit 1
Unit 3
Unit 6
2 4 6 8 10 12 14 16 18 20 22 24 26 28 30 32 34 36 38 400 42 44 46 48 50
A B DC E
Unit 2
Unit 4
Unit 5
• Identify controllingpoints, cp
• ...
• Identify controllingsequence
• …
• Identify critical activities
• …
A
1
B
2
C
3
D
1
E
4
F
1
AB, AC DE
CD
F
EF
Example 3: 6 units
117
Unit 1
Unit 3
Unit 6
2 4 6 8 10 12 14 16 18 20 22 24 26 28 30 32 34 36 38 400 42 44 46 48 50
A B DC E
Unit 2
Unit 4
Unit 5
• Identify controllingpoints, cp
• AB, AC, CD, DE, EF
• Identify controllingsequence
• …
• Identify critical activities
• …
A
1
B
2
C
3
D
1
E
4
F
1
AB, AC DE
CD
F
EF
Example 3: 6 units
118
Unit 1
Unit 3
Unit 6
2 4 6 8 10 12 14 16 18 20 22 24 26 28 30 32 34 36 38 400 42 44 46 48 50
A B DC E
Unit 2
Unit 4
Unit 5
• Identify controllingpoints, cp
• AB, AC, CD, DE, EF
• Identify controllingsequence
• …
• Identify critical activities
• …
A
1
B
2
C
3
D
1
E
4
F
1
F
AB, AC DE
EFCD
Example 3: 6 units
119
Unit 1
Unit 3
Unit 6
2 4 6 8 10 12 14 16 18 20 22 24 26 28 30 32 34 36 38 400 42 44 46 48 50
A B DC E
Unit 2
Unit 4
Unit 5
• Identify controllingpoints, cp
• AB, AC, CD, DE, EF
• Identify controllingsequence
• F6, E6-1, D2-5, C6-1, A1
• Identify critical activities
• …
A
1
B
2
C
3
D
1
E
4
F
1
F
AB, AC DE
EFCD
Example 3: 6 units
120
Unit 1
Unit 3
Unit 6
2 4 6 8 10 12 14 16 18 20 22 24 26 28 30 32 34 36 38 400 42 44 46 48 50
A B DC E
Unit 2
Unit 4
Unit 5
• Identify controllingpoints, cp
• AB, AC, CD, DE, EF
• Identify controllingsequence
• F6, E6-1, D2-5, C6-1, A1
• Identify critical activities
• …
A
1
B
2
C
3
D
1
E
4
F
1
F
AB, AC DE
EFCD
Example 3: 6 units
121
2 4 6 8 10 12 14 16 18 20 22 24 26 28 30 32 34 36 38 400 42 44 46 48 50
A B DC E
Unit 1
Unit 3
Unit 6
Unit 2
Unit 4
Unit 5
• Identify controllingpoints, cp
• AB, AC, CD, DE, EF
• Identify controllingsequence
• F6, E6-1, D2-5, C6-1, A1
• Identify critical activities
• F6-F1, E6-1, D1
A
1
B
2
C
3
D
1
E
4
F
1
F
AB, AC DE
EFCD
Repetitive Scheduling Method
Example 4: 3 units
122
Act Predecessors Duration/Unit
A 2
B A 3
C A 2
D B, C 4
E D 1
F D 4
G E, F 4
Example 4: 3 units
123
Unit 1
Unit 2
Unit 3
2 4 6 8 10 12 14 16 18 20 22 24 26 28 300
Act Predecessors Duration/Unit
A 2
B A 3
C A 2
D B, C 4
E D 1
F D 4
G E, F 4
Example 4: 3 units
124
Unit 1
Unit 2
Unit 3
2 4 6 8 10 12 14 16 18 20 22 24 26 28 300
AC
A C B
AB, AC
Act Predecessors Duration/Unit
A 2
B A 3
C A 2
D B, C 4
E D 1
F D 4
G E, F 4
Example 4: 3 units
125
Unit 1
Unit 2
Unit 3
2 4 6 8 10 12 14 16 18 20 22 24 26 28 300
AC
A C B D
AB, AC
Drag
Act Predecessors Duration/Unit
A 2
B A 3
C A 2
D B, C 4
E D 1
F D 4
G E, F 4
Determine possible cp from B and C to D
Example 4: 3 units
126
Unit 1
Unit 2
Unit 3
2 4 6 8 10 12 14 16 18 20 22 24 26 28 300
AC
BD
A C B D
AB, AC
Act Predecessors Duration/Unit
A 2
B A 3
C A 2
D B, C 4
E D 1
F D 4
G E, F 4
Example 4: 3 units
127
Unit 1
Unit 2
Unit 3
2 4 6 8 10 12 14 16 18 20 22 24 26 28 300
AC
BD
A C B D E F
DE, DF
AB, AC
Act Predecessors Duration/Unit
A 2
B A 3
C A 2
D B, C 4
E D 1
F D 4
G E, F 4
DF
Example 4: 3 units
128
Unit 1
Unit 2
Unit 3
2 4 6 8 10 12 14 16 18 20 22 24 26 28 300
AC
BD
A C B D E F G
DE, DF
AB, AC
Drag
Act Predecessors Duration/Unit
A 2
B A 3
C A 2
D B, C 4
E D 1
F D 4
G E, F 4
DF
Determine possible cp from E and F to G
Example 4: 3 units
129
Unit 1
Unit 2
Unit 3
2 4 6 8 10 12 14 16 18 20 22 24 26 28 300
AC
BD
A C B D E F G
EG
DE, DF
AB, AC
Act Predecessors Duration/Unit
A 2
B A 3
C A 2
D B, C 4
E D 1
F D 4
G E, F 4
DF
Example 4: 3 units
130
Unit 1
Unit 2
Unit 3
2 4 6 8 10 12 14 16 18 20 22 24 26 28 300
AC
BD
A C B D E F G
EG
DE, DF
AB, AC
Act Predecessors Duration/Unit
A 2
B A 3
C A 2
D B, C 4
E D 1
F D 4
G E, F 4
DF
Controlling Sequence: G3-1, E2, D3-1, B1, A1
Example 4: 3 units
131
Unit 1
Unit 2
Unit 3
2 4 6 8 10 12 14 16 18 20 22 24 26 28 300
AC
BD
A C B D E F G
EG
DE, DF
AB, AC
Act Predecessors Duration/Unit
A 2
B A 3
C A 2
D B, C 4
E D 1
F D 4
G E, F 4
DF
Controlling Sequence: G3-1, E2, D3-1, B1, A1
Critical Activities: G3-1, E1
Repetitive Scheduling Method
Real Case Study: A Housing Project with 32 units
132
Uthenthawai: Master of Construction Management #UthenMCMUthenthawai: Master of Construction Management #UthenMCM
กรณีศึกษาการวางแผนเชิงปฏิบัติของโครงการหมู่บ้านจัดสรร
ด้วยวิธีสายงานต่อเนื่อง
สำหรับ
การประชุมวิชาการวิศวกรรมโยธาแห่งชาติ ครั้งที่ 22
โดย
ชำคริต ศรีสุวรรณรัตน์: หัวหน้ำประจำสำขำวิชำบริหำรงำนก่อสร้ำง
ไพโรจน์ ฤกษ์อุดมสิน: นักศึกษำ #UthenMCM รุ่น 1
Uthenthawai: Master of Construction Management #UthenMCM
Contents
1. Introduction
2. Problems
3. Objectives
4. Literature Reviews
5. Research
6. Results
7. Conclusion
134
Uthenthawai: Master of Construction Management #UthenMCM
1. Introduction
• Construction Projects consist of repetitive units/activities.
• Examples of Repetitive Units
• Housing: each house
• Condominium: each floor or room
• Highway: each section
• Repetitive activities are performed by sets of resources
• Schedule resources to work continuously
• Eliminate interruption and idle time
135
Uthenthawai: Master of Construction Management #UthenMCM
2. Problems
CPM Schedule with 745-week Idle Time RSM Schedule with 135-week Project Delay
136
Uthenthawai: Master of Construction Management #UthenMCM
3. Objectives
•Schedule resources to work continuously
•Maintain project duration
•Choose optimum number of resources
•Practical in terms of Engineering, Management, Finance, and Marketing
137
Uthenthawai: Master of Construction Management #UthenMCM
4. Literature Reviews: Methods
•Repetitive Scheduling Method (RSM)
•Linear Scheduling Method (LSM)
•Vertical Production Method (VPM)
•Line-of-balance Method (LOB)
138
Uthenthawai: Master of Construction Management #UthenMCM
4. Literature Reviews: Types of Repetitive Activities
Non-Repetitive Activities Non-Typical RepetitiveActivities
Repetitive Activities with Soft-Logic Constraints
139
Uthenthawai: Master of Construction Management #UthenMCM
4. Literature Reviews: Controlling Sequence from RSM
140
Uthenthawai: Master of Construction Management #UthenMCM
5. Research: Schedules & Methods
1. CPM
2. RSM.N (Normal)
3. RSM.S (Soft-logic), switching construction orders between units/houses/models
4. RSM.E (Expedite), adding or reducing the number of workers in order to shorten project duration
5. RSM.P (Parallel), using multiple groups of crew to start a repetitive activity at the same time
6. RSM.F (Final), considering other aspects of the project such as management, financing, and marketing
141
Uthenthawai: Master of Construction Management #UthenMCM
6. Results: CPM & RSM.N
1. CPM Schedule with 745-week Idle Time 2. RSM.N with 300-week Project Duration
142
Uthenthawai: Master of Construction Management #UthenMCM
6. Results: RSM.S
3. RSM.S with 300-week Project Duration
143
Uthenthawai: Master of Construction Management #UthenMCM
6. Results: RSM.E
3. RSM.S with 300-week Project Duration 4. RSM.Ewith 162-week Project Duration
144
Uthenthawai: Master of Construction Management #UthenMCM
6. Results: RSM.P & RSM.F
5. RSM.P with 139-week Project Duration 6. RSM.F with 147-week Project Duration
145
Uthenthawai: Master of Construction Management #UthenMCM
6. Results: Improvement & Comparison between CPM and RSM.F
146

More Related Content

What's hot

Essentials of EOT Claims
Essentials of EOT ClaimsEssentials of EOT Claims
Essentials of EOT Claims
M Maged Hegazy, LLM, MBA, CCP, P3O
 
Critical Path Method
Critical Path MethodCritical Path Method
Critical Path Method
Simplilearn
 
Meeting Project Schedule Compliance Standards
Meeting Project Schedule Compliance StandardsMeeting Project Schedule Compliance Standards
Meeting Project Schedule Compliance Standards
Acumen
 
Linear scheduling LSM
Linear scheduling LSMLinear scheduling LSM
Linear scheduling LSM
Shaiful Amri Mansur
 
Pert cpm
Pert cpmPert cpm
Pert cpm
Jyoti Mamtani
 
Project planning and scheduling techniques
Project planning and scheduling techniquesProject planning and scheduling techniques
Project planning and scheduling techniques
Shivangi Saini
 
PERT
PERTPERT
PMO Challenges and Opportunities; DIPMF Presentation
PMO Challenges and Opportunities; DIPMF PresentationPMO Challenges and Opportunities; DIPMF Presentation
PMO Challenges and Opportunities; DIPMF Presentation
SUKAD Group - Project Management Solutions
 
Construction Delay Analysis, Simplified
Construction Delay Analysis, SimplifiedConstruction Delay Analysis, Simplified
Construction Delay Analysis, Simplified
Michael Pink
 
Project Resource Management
Project Resource ManagementProject Resource Management
Project Resource Management
Priyadarsini Palaniapan
 
Project planning and Scheduling
Project planning and SchedulingProject planning and Scheduling
Project planning and Scheduling
saurabmi2
 
PROJECT SCHEDULE
PROJECT SCHEDULEPROJECT SCHEDULE
PROJECT SCHEDULE
Ajeesh Mk
 
DCMA 14 Point Assessment by Karim Ragab.pdf
DCMA 14 Point Assessment by Karim Ragab.pdfDCMA 14 Point Assessment by Karim Ragab.pdf
DCMA 14 Point Assessment by Karim Ragab.pdf
Karim Ragab
 
Lecture 05:Advanced Project Management PM Processes and Framework
Lecture 05:Advanced Project Management   PM Processes and FrameworkLecture 05:Advanced Project Management   PM Processes and Framework
Lecture 05:Advanced Project Management PM Processes and Framework
Fida Karim 🇵🇰
 
Platinum card for agile ev mr4
Platinum card for agile ev mr4Platinum card for agile ev mr4
Platinum card for agile ev mr4
Association for Project Management
 
Critical path method(cpm)
Critical path method(cpm)Critical path method(cpm)
Critical path method(cpm)
chandkec
 
3. construction planning. construction project management
3. construction planning. construction project management3. construction planning. construction project management
3. construction planning. construction project management
Kabilan Kabi
 
Line of Balance
Line of BalanceLine of Balance
Line of Balance
IJMER
 
Time Impact Analysis
Time Impact AnalysisTime Impact Analysis
Time Impact Analysis
Chris Carson
 
Project network scheduling and S-curve
Project network scheduling and S-curve Project network scheduling and S-curve
Project network scheduling and S-curve
Satish Yadavalli
 

What's hot (20)

Essentials of EOT Claims
Essentials of EOT ClaimsEssentials of EOT Claims
Essentials of EOT Claims
 
Critical Path Method
Critical Path MethodCritical Path Method
Critical Path Method
 
Meeting Project Schedule Compliance Standards
Meeting Project Schedule Compliance StandardsMeeting Project Schedule Compliance Standards
Meeting Project Schedule Compliance Standards
 
Linear scheduling LSM
Linear scheduling LSMLinear scheduling LSM
Linear scheduling LSM
 
Pert cpm
Pert cpmPert cpm
Pert cpm
 
Project planning and scheduling techniques
Project planning and scheduling techniquesProject planning and scheduling techniques
Project planning and scheduling techniques
 
PERT
PERTPERT
PERT
 
PMO Challenges and Opportunities; DIPMF Presentation
PMO Challenges and Opportunities; DIPMF PresentationPMO Challenges and Opportunities; DIPMF Presentation
PMO Challenges and Opportunities; DIPMF Presentation
 
Construction Delay Analysis, Simplified
Construction Delay Analysis, SimplifiedConstruction Delay Analysis, Simplified
Construction Delay Analysis, Simplified
 
Project Resource Management
Project Resource ManagementProject Resource Management
Project Resource Management
 
Project planning and Scheduling
Project planning and SchedulingProject planning and Scheduling
Project planning and Scheduling
 
PROJECT SCHEDULE
PROJECT SCHEDULEPROJECT SCHEDULE
PROJECT SCHEDULE
 
DCMA 14 Point Assessment by Karim Ragab.pdf
DCMA 14 Point Assessment by Karim Ragab.pdfDCMA 14 Point Assessment by Karim Ragab.pdf
DCMA 14 Point Assessment by Karim Ragab.pdf
 
Lecture 05:Advanced Project Management PM Processes and Framework
Lecture 05:Advanced Project Management   PM Processes and FrameworkLecture 05:Advanced Project Management   PM Processes and Framework
Lecture 05:Advanced Project Management PM Processes and Framework
 
Platinum card for agile ev mr4
Platinum card for agile ev mr4Platinum card for agile ev mr4
Platinum card for agile ev mr4
 
Critical path method(cpm)
Critical path method(cpm)Critical path method(cpm)
Critical path method(cpm)
 
3. construction planning. construction project management
3. construction planning. construction project management3. construction planning. construction project management
3. construction planning. construction project management
 
Line of Balance
Line of BalanceLine of Balance
Line of Balance
 
Time Impact Analysis
Time Impact AnalysisTime Impact Analysis
Time Impact Analysis
 
Project network scheduling and S-curve
Project network scheduling and S-curve Project network scheduling and S-curve
Project network scheduling and S-curve
 

Similar to Repetitive Scheduling Method RSM

Project management
Project managementProject management
Project management
Anne Patricia
 
final Line balancing slide12.ppt
final Line balancing slide12.pptfinal Line balancing slide12.ppt
final Line balancing slide12.ppt
xicohos114
 
Mpc sequencing
Mpc   sequencingMpc   sequencing
Mpc sequencing
Pankaj Kumar
 
Tn6 facility layout
Tn6 facility layoutTn6 facility layout
Tn6 facility layout
videoaakash15
 
Tn6 facility+layout
Tn6 facility+layoutTn6 facility+layout
Tn6 facility+layout
videoaakash15
 
Automated University Timetabling
Automated University TimetablingAutomated University Timetabling
Automated University Timetabling
Alexandre Pinto
 
Topic 5 Production Sequencing and Scheduling.ppt
Topic 5 Production Sequencing and Scheduling.pptTopic 5 Production Sequencing and Scheduling.ppt
Topic 5 Production Sequencing and Scheduling.ppt
HassanHani5
 
production_scheduling_1.ppt
production_scheduling_1.pptproduction_scheduling_1.ppt
production_scheduling_1.ppt
VELMURUGANM19
 
Pipelining
PipeliningPipelining
PERT-CPM.pdf
PERT-CPM.pdfPERT-CPM.pdf
PERT-CPM.pdf
limchoy
 
PROJECT-ANALYSIS-TOOL-PPT.pptx
PROJECT-ANALYSIS-TOOL-PPT.pptxPROJECT-ANALYSIS-TOOL-PPT.pptx
PROJECT-ANALYSIS-TOOL-PPT.pptx
PHOEBEANNEARTECHE1
 
PERT AND CPM PROJECT MANAGEMENT
PERT AND CPM PROJECT MANAGEMENTPERT AND CPM PROJECT MANAGEMENT
PERT AND CPM PROJECT MANAGEMENT
salsa moyara
 
Ch 06 - CPM PERT (1).pptx
Ch 06 - CPM  PERT (1).pptxCh 06 - CPM  PERT (1).pptx
Ch 06 - CPM PERT (1).pptx
sitinorhafizabintiab1
 
cpmpertmy (1)
cpmpertmy (1)cpmpertmy (1)
cpmpertmy (1)
Dr. Divya Khandelwal
 
Deep Explaination of STA_setupandholdchecks
Deep Explaination of STA_setupandholdchecksDeep Explaination of STA_setupandholdchecks
Deep Explaination of STA_setupandholdchecks
YashwanthPola1
 
Mine scheduling process
Mine scheduling processMine scheduling process
Mine scheduling process
VR M
 
Introduction to SLURM
Introduction to SLURMIntroduction to SLURM
Job Shop Scheduling.pptx
Job Shop Scheduling.pptxJob Shop Scheduling.pptx
Job Shop Scheduling.pptx
SyedAmirIqbal3
 
Chap 4.ppt
Chap 4.pptChap 4.ppt
Chap 4.ppt
Anonymous9etQKwW
 
Chap 4.ppt
Chap 4.pptChap 4.ppt
Chap 4.ppt
Tigabu Yaya
 

Similar to Repetitive Scheduling Method RSM (20)

Project management
Project managementProject management
Project management
 
final Line balancing slide12.ppt
final Line balancing slide12.pptfinal Line balancing slide12.ppt
final Line balancing slide12.ppt
 
Mpc sequencing
Mpc   sequencingMpc   sequencing
Mpc sequencing
 
Tn6 facility layout
Tn6 facility layoutTn6 facility layout
Tn6 facility layout
 
Tn6 facility+layout
Tn6 facility+layoutTn6 facility+layout
Tn6 facility+layout
 
Automated University Timetabling
Automated University TimetablingAutomated University Timetabling
Automated University Timetabling
 
Topic 5 Production Sequencing and Scheduling.ppt
Topic 5 Production Sequencing and Scheduling.pptTopic 5 Production Sequencing and Scheduling.ppt
Topic 5 Production Sequencing and Scheduling.ppt
 
production_scheduling_1.ppt
production_scheduling_1.pptproduction_scheduling_1.ppt
production_scheduling_1.ppt
 
Pipelining
PipeliningPipelining
Pipelining
 
PERT-CPM.pdf
PERT-CPM.pdfPERT-CPM.pdf
PERT-CPM.pdf
 
PROJECT-ANALYSIS-TOOL-PPT.pptx
PROJECT-ANALYSIS-TOOL-PPT.pptxPROJECT-ANALYSIS-TOOL-PPT.pptx
PROJECT-ANALYSIS-TOOL-PPT.pptx
 
PERT AND CPM PROJECT MANAGEMENT
PERT AND CPM PROJECT MANAGEMENTPERT AND CPM PROJECT MANAGEMENT
PERT AND CPM PROJECT MANAGEMENT
 
Ch 06 - CPM PERT (1).pptx
Ch 06 - CPM  PERT (1).pptxCh 06 - CPM  PERT (1).pptx
Ch 06 - CPM PERT (1).pptx
 
cpmpertmy (1)
cpmpertmy (1)cpmpertmy (1)
cpmpertmy (1)
 
Deep Explaination of STA_setupandholdchecks
Deep Explaination of STA_setupandholdchecksDeep Explaination of STA_setupandholdchecks
Deep Explaination of STA_setupandholdchecks
 
Mine scheduling process
Mine scheduling processMine scheduling process
Mine scheduling process
 
Introduction to SLURM
Introduction to SLURMIntroduction to SLURM
Introduction to SLURM
 
Job Shop Scheduling.pptx
Job Shop Scheduling.pptxJob Shop Scheduling.pptx
Job Shop Scheduling.pptx
 
Chap 4.ppt
Chap 4.pptChap 4.ppt
Chap 4.ppt
 
Chap 4.ppt
Chap 4.pptChap 4.ppt
Chap 4.ppt
 

More from Chachrist Srisuwanrat

Time-Cost Tradeoff by Examples
Time-Cost Tradeoff by ExamplesTime-Cost Tradeoff by Examples
Time-Cost Tradeoff by Examples
Chachrist Srisuwanrat
 
Project analysis and advanced data calculation and conditional formatting
Project analysis and advanced data calculation and conditional formattingProject analysis and advanced data calculation and conditional formatting
Project analysis and advanced data calculation and conditional formatting
Chachrist Srisuwanrat
 
Optimization in ChaStrobe Software with Genetic Algorithm
Optimization in ChaStrobe Software with Genetic AlgorithmOptimization in ChaStrobe Software with Genetic Algorithm
Optimization in ChaStrobe Software with Genetic Algorithm
Chachrist Srisuwanrat
 
ChaStrobe Application, a simulation-based scheduling software for repetitive ...
ChaStrobe Application, a simulation-based scheduling software for repetitive ...ChaStrobe Application, a simulation-based scheduling software for repetitive ...
ChaStrobe Application, a simulation-based scheduling software for repetitive ...
Chachrist Srisuwanrat
 
Model and schedule resource-sharing activities in repetitive projects using c...
Model and schedule resource-sharing activities in repetitive projects using c...Model and schedule resource-sharing activities in repetitive projects using c...
Model and schedule resource-sharing activities in repetitive projects using c...
Chachrist Srisuwanrat
 
Example of repetitive project with probabilistic activity durations and work ...
Example of repetitive project with probabilistic activity durations and work ...Example of repetitive project with probabilistic activity durations and work ...
Example of repetitive project with probabilistic activity durations and work ...
Chachrist Srisuwanrat
 
Example of repetitive project with probabilistic activity durations
Example of repetitive project with probabilistic activity durationsExample of repetitive project with probabilistic activity durations
Example of repetitive project with probabilistic activity durations
Chachrist Srisuwanrat
 
Literature review of existing repetitive project scheduling techniques 2008
Literature review of existing repetitive project scheduling techniques 2008Literature review of existing repetitive project scheduling techniques 2008
Literature review of existing repetitive project scheduling techniques 2008
Chachrist Srisuwanrat
 
Five characteristics of repetitive activities in construction projects
Five characteristics of repetitive activities in construction projectsFive characteristics of repetitive activities in construction projects
Five characteristics of repetitive activities in construction projects
Chachrist Srisuwanrat
 
Sequence step algorithm repetitive project scheduling for project with probab...
Sequence step algorithm repetitive project scheduling for project with probab...Sequence step algorithm repetitive project scheduling for project with probab...
Sequence step algorithm repetitive project scheduling for project with probab...
Chachrist Srisuwanrat
 
Microsoft Project Workshop
Microsoft Project WorkshopMicrosoft Project Workshop
Microsoft Project Workshop
Chachrist Srisuwanrat
 
Ms project 2010 workshop on july 2014
Ms project 2010 workshop on july 2014Ms project 2010 workshop on july 2014
Ms project 2010 workshop on july 2014
Chachrist Srisuwanrat
 

More from Chachrist Srisuwanrat (12)

Time-Cost Tradeoff by Examples
Time-Cost Tradeoff by ExamplesTime-Cost Tradeoff by Examples
Time-Cost Tradeoff by Examples
 
Project analysis and advanced data calculation and conditional formatting
Project analysis and advanced data calculation and conditional formattingProject analysis and advanced data calculation and conditional formatting
Project analysis and advanced data calculation and conditional formatting
 
Optimization in ChaStrobe Software with Genetic Algorithm
Optimization in ChaStrobe Software with Genetic AlgorithmOptimization in ChaStrobe Software with Genetic Algorithm
Optimization in ChaStrobe Software with Genetic Algorithm
 
ChaStrobe Application, a simulation-based scheduling software for repetitive ...
ChaStrobe Application, a simulation-based scheduling software for repetitive ...ChaStrobe Application, a simulation-based scheduling software for repetitive ...
ChaStrobe Application, a simulation-based scheduling software for repetitive ...
 
Model and schedule resource-sharing activities in repetitive projects using c...
Model and schedule resource-sharing activities in repetitive projects using c...Model and schedule resource-sharing activities in repetitive projects using c...
Model and schedule resource-sharing activities in repetitive projects using c...
 
Example of repetitive project with probabilistic activity durations and work ...
Example of repetitive project with probabilistic activity durations and work ...Example of repetitive project with probabilistic activity durations and work ...
Example of repetitive project with probabilistic activity durations and work ...
 
Example of repetitive project with probabilistic activity durations
Example of repetitive project with probabilistic activity durationsExample of repetitive project with probabilistic activity durations
Example of repetitive project with probabilistic activity durations
 
Literature review of existing repetitive project scheduling techniques 2008
Literature review of existing repetitive project scheduling techniques 2008Literature review of existing repetitive project scheduling techniques 2008
Literature review of existing repetitive project scheduling techniques 2008
 
Five characteristics of repetitive activities in construction projects
Five characteristics of repetitive activities in construction projectsFive characteristics of repetitive activities in construction projects
Five characteristics of repetitive activities in construction projects
 
Sequence step algorithm repetitive project scheduling for project with probab...
Sequence step algorithm repetitive project scheduling for project with probab...Sequence step algorithm repetitive project scheduling for project with probab...
Sequence step algorithm repetitive project scheduling for project with probab...
 
Microsoft Project Workshop
Microsoft Project WorkshopMicrosoft Project Workshop
Microsoft Project Workshop
 
Ms project 2010 workshop on july 2014
Ms project 2010 workshop on july 2014Ms project 2010 workshop on july 2014
Ms project 2010 workshop on july 2014
 

Recently uploaded

ISO/IEC 27001, ISO/IEC 42001, and GDPR: Best Practices for Implementation and...
ISO/IEC 27001, ISO/IEC 42001, and GDPR: Best Practices for Implementation and...ISO/IEC 27001, ISO/IEC 42001, and GDPR: Best Practices for Implementation and...
ISO/IEC 27001, ISO/IEC 42001, and GDPR: Best Practices for Implementation and...
PECB
 
How to deliver Powerpoint Presentations.pptx
How to deliver Powerpoint  Presentations.pptxHow to deliver Powerpoint  Presentations.pptx
How to deliver Powerpoint Presentations.pptx
HajraNaeem15
 
HYPERTENSION - SLIDE SHARE PRESENTATION.
HYPERTENSION - SLIDE SHARE PRESENTATION.HYPERTENSION - SLIDE SHARE PRESENTATION.
HYPERTENSION - SLIDE SHARE PRESENTATION.
deepaannamalai16
 
Pharmaceutics Pharmaceuticals best of brub
Pharmaceutics Pharmaceuticals best of brubPharmaceutics Pharmaceuticals best of brub
Pharmaceutics Pharmaceuticals best of brub
danielkiash986
 
BÀI TẬP BỔ TRỢ TIẾNG ANH LỚP 9 CẢ NĂM - GLOBAL SUCCESS - NĂM HỌC 2024-2025 - ...
BÀI TẬP BỔ TRỢ TIẾNG ANH LỚP 9 CẢ NĂM - GLOBAL SUCCESS - NĂM HỌC 2024-2025 - ...BÀI TẬP BỔ TRỢ TIẾNG ANH LỚP 9 CẢ NĂM - GLOBAL SUCCESS - NĂM HỌC 2024-2025 - ...
BÀI TẬP BỔ TRỢ TIẾNG ANH LỚP 9 CẢ NĂM - GLOBAL SUCCESS - NĂM HỌC 2024-2025 - ...
Nguyen Thanh Tu Collection
 
RESULTS OF THE EVALUATION QUESTIONNAIRE.pptx
RESULTS OF THE EVALUATION QUESTIONNAIRE.pptxRESULTS OF THE EVALUATION QUESTIONNAIRE.pptx
RESULTS OF THE EVALUATION QUESTIONNAIRE.pptx
zuzanka
 
Philippine Edukasyong Pantahanan at Pangkabuhayan (EPP) Curriculum
Philippine Edukasyong Pantahanan at Pangkabuhayan (EPP) CurriculumPhilippine Edukasyong Pantahanan at Pangkabuhayan (EPP) Curriculum
Philippine Edukasyong Pantahanan at Pangkabuhayan (EPP) Curriculum
MJDuyan
 
BÀI TẬP DẠY THÊM TIẾNG ANH LỚP 7 CẢ NĂM FRIENDS PLUS SÁCH CHÂN TRỜI SÁNG TẠO ...
BÀI TẬP DẠY THÊM TIẾNG ANH LỚP 7 CẢ NĂM FRIENDS PLUS SÁCH CHÂN TRỜI SÁNG TẠO ...BÀI TẬP DẠY THÊM TIẾNG ANH LỚP 7 CẢ NĂM FRIENDS PLUS SÁCH CHÂN TRỜI SÁNG TẠO ...
BÀI TẬP DẠY THÊM TIẾNG ANH LỚP 7 CẢ NĂM FRIENDS PLUS SÁCH CHÂN TRỜI SÁNG TẠO ...
Nguyen Thanh Tu Collection
 
Film vocab for eal 3 students: Australia the movie
Film vocab for eal 3 students: Australia the movieFilm vocab for eal 3 students: Australia the movie
Film vocab for eal 3 students: Australia the movie
Nicholas Montgomery
 
Nutrition Inc FY 2024, 4 - Hour Training
Nutrition Inc FY 2024, 4 - Hour TrainingNutrition Inc FY 2024, 4 - Hour Training
Nutrition Inc FY 2024, 4 - Hour Training
melliereed
 
A Independência da América Espanhola LAPBOOK.pdf
A Independência da América Espanhola LAPBOOK.pdfA Independência da América Espanhola LAPBOOK.pdf
A Independência da América Espanhola LAPBOOK.pdf
Jean Carlos Nunes Paixão
 
UGC NET Exam Paper 1- Unit 1:Teaching Aptitude
UGC NET Exam Paper 1- Unit 1:Teaching AptitudeUGC NET Exam Paper 1- Unit 1:Teaching Aptitude
UGC NET Exam Paper 1- Unit 1:Teaching Aptitude
S. Raj Kumar
 
spot a liar (Haiqa 146).pptx Technical writhing and presentation skills
spot a liar (Haiqa 146).pptx Technical writhing and presentation skillsspot a liar (Haiqa 146).pptx Technical writhing and presentation skills
spot a liar (Haiqa 146).pptx Technical writhing and presentation skills
haiqairshad
 
Electric Fetus - Record Store Scavenger Hunt
Electric Fetus - Record Store Scavenger HuntElectric Fetus - Record Store Scavenger Hunt
Electric Fetus - Record Store Scavenger Hunt
RamseyBerglund
 
Stack Memory Organization of 8086 Microprocessor
Stack Memory Organization of 8086 MicroprocessorStack Memory Organization of 8086 Microprocessor
Stack Memory Organization of 8086 Microprocessor
JomonJoseph58
 
Lifelines of National Economy chapter for Class 10 STUDY MATERIAL PDF
Lifelines of National Economy chapter for Class 10 STUDY MATERIAL PDFLifelines of National Economy chapter for Class 10 STUDY MATERIAL PDF
Lifelines of National Economy chapter for Class 10 STUDY MATERIAL PDF
Vivekanand Anglo Vedic Academy
 
What is Digital Literacy? A guest blog from Andy McLaughlin, University of Ab...
What is Digital Literacy? A guest blog from Andy McLaughlin, University of Ab...What is Digital Literacy? A guest blog from Andy McLaughlin, University of Ab...
What is Digital Literacy? A guest blog from Andy McLaughlin, University of Ab...
GeorgeMilliken2
 
RHEOLOGY Physical pharmaceutics-II notes for B.pharm 4th sem students
RHEOLOGY Physical pharmaceutics-II notes for B.pharm 4th sem studentsRHEOLOGY Physical pharmaceutics-II notes for B.pharm 4th sem students
RHEOLOGY Physical pharmaceutics-II notes for B.pharm 4th sem students
Himanshu Rai
 
REASIGNACION 2024 UGEL CHUPACA 2024 UGEL CHUPACA.pdf
REASIGNACION 2024 UGEL CHUPACA 2024 UGEL CHUPACA.pdfREASIGNACION 2024 UGEL CHUPACA 2024 UGEL CHUPACA.pdf
REASIGNACION 2024 UGEL CHUPACA 2024 UGEL CHUPACA.pdf
giancarloi8888
 
Gender and Mental Health - Counselling and Family Therapy Applications and In...
Gender and Mental Health - Counselling and Family Therapy Applications and In...Gender and Mental Health - Counselling and Family Therapy Applications and In...
Gender and Mental Health - Counselling and Family Therapy Applications and In...
PsychoTech Services
 

Recently uploaded (20)

ISO/IEC 27001, ISO/IEC 42001, and GDPR: Best Practices for Implementation and...
ISO/IEC 27001, ISO/IEC 42001, and GDPR: Best Practices for Implementation and...ISO/IEC 27001, ISO/IEC 42001, and GDPR: Best Practices for Implementation and...
ISO/IEC 27001, ISO/IEC 42001, and GDPR: Best Practices for Implementation and...
 
How to deliver Powerpoint Presentations.pptx
How to deliver Powerpoint  Presentations.pptxHow to deliver Powerpoint  Presentations.pptx
How to deliver Powerpoint Presentations.pptx
 
HYPERTENSION - SLIDE SHARE PRESENTATION.
HYPERTENSION - SLIDE SHARE PRESENTATION.HYPERTENSION - SLIDE SHARE PRESENTATION.
HYPERTENSION - SLIDE SHARE PRESENTATION.
 
Pharmaceutics Pharmaceuticals best of brub
Pharmaceutics Pharmaceuticals best of brubPharmaceutics Pharmaceuticals best of brub
Pharmaceutics Pharmaceuticals best of brub
 
BÀI TẬP BỔ TRỢ TIẾNG ANH LỚP 9 CẢ NĂM - GLOBAL SUCCESS - NĂM HỌC 2024-2025 - ...
BÀI TẬP BỔ TRỢ TIẾNG ANH LỚP 9 CẢ NĂM - GLOBAL SUCCESS - NĂM HỌC 2024-2025 - ...BÀI TẬP BỔ TRỢ TIẾNG ANH LỚP 9 CẢ NĂM - GLOBAL SUCCESS - NĂM HỌC 2024-2025 - ...
BÀI TẬP BỔ TRỢ TIẾNG ANH LỚP 9 CẢ NĂM - GLOBAL SUCCESS - NĂM HỌC 2024-2025 - ...
 
RESULTS OF THE EVALUATION QUESTIONNAIRE.pptx
RESULTS OF THE EVALUATION QUESTIONNAIRE.pptxRESULTS OF THE EVALUATION QUESTIONNAIRE.pptx
RESULTS OF THE EVALUATION QUESTIONNAIRE.pptx
 
Philippine Edukasyong Pantahanan at Pangkabuhayan (EPP) Curriculum
Philippine Edukasyong Pantahanan at Pangkabuhayan (EPP) CurriculumPhilippine Edukasyong Pantahanan at Pangkabuhayan (EPP) Curriculum
Philippine Edukasyong Pantahanan at Pangkabuhayan (EPP) Curriculum
 
BÀI TẬP DẠY THÊM TIẾNG ANH LỚP 7 CẢ NĂM FRIENDS PLUS SÁCH CHÂN TRỜI SÁNG TẠO ...
BÀI TẬP DẠY THÊM TIẾNG ANH LỚP 7 CẢ NĂM FRIENDS PLUS SÁCH CHÂN TRỜI SÁNG TẠO ...BÀI TẬP DẠY THÊM TIẾNG ANH LỚP 7 CẢ NĂM FRIENDS PLUS SÁCH CHÂN TRỜI SÁNG TẠO ...
BÀI TẬP DẠY THÊM TIẾNG ANH LỚP 7 CẢ NĂM FRIENDS PLUS SÁCH CHÂN TRỜI SÁNG TẠO ...
 
Film vocab for eal 3 students: Australia the movie
Film vocab for eal 3 students: Australia the movieFilm vocab for eal 3 students: Australia the movie
Film vocab for eal 3 students: Australia the movie
 
Nutrition Inc FY 2024, 4 - Hour Training
Nutrition Inc FY 2024, 4 - Hour TrainingNutrition Inc FY 2024, 4 - Hour Training
Nutrition Inc FY 2024, 4 - Hour Training
 
A Independência da América Espanhola LAPBOOK.pdf
A Independência da América Espanhola LAPBOOK.pdfA Independência da América Espanhola LAPBOOK.pdf
A Independência da América Espanhola LAPBOOK.pdf
 
UGC NET Exam Paper 1- Unit 1:Teaching Aptitude
UGC NET Exam Paper 1- Unit 1:Teaching AptitudeUGC NET Exam Paper 1- Unit 1:Teaching Aptitude
UGC NET Exam Paper 1- Unit 1:Teaching Aptitude
 
spot a liar (Haiqa 146).pptx Technical writhing and presentation skills
spot a liar (Haiqa 146).pptx Technical writhing and presentation skillsspot a liar (Haiqa 146).pptx Technical writhing and presentation skills
spot a liar (Haiqa 146).pptx Technical writhing and presentation skills
 
Electric Fetus - Record Store Scavenger Hunt
Electric Fetus - Record Store Scavenger HuntElectric Fetus - Record Store Scavenger Hunt
Electric Fetus - Record Store Scavenger Hunt
 
Stack Memory Organization of 8086 Microprocessor
Stack Memory Organization of 8086 MicroprocessorStack Memory Organization of 8086 Microprocessor
Stack Memory Organization of 8086 Microprocessor
 
Lifelines of National Economy chapter for Class 10 STUDY MATERIAL PDF
Lifelines of National Economy chapter for Class 10 STUDY MATERIAL PDFLifelines of National Economy chapter for Class 10 STUDY MATERIAL PDF
Lifelines of National Economy chapter for Class 10 STUDY MATERIAL PDF
 
What is Digital Literacy? A guest blog from Andy McLaughlin, University of Ab...
What is Digital Literacy? A guest blog from Andy McLaughlin, University of Ab...What is Digital Literacy? A guest blog from Andy McLaughlin, University of Ab...
What is Digital Literacy? A guest blog from Andy McLaughlin, University of Ab...
 
RHEOLOGY Physical pharmaceutics-II notes for B.pharm 4th sem students
RHEOLOGY Physical pharmaceutics-II notes for B.pharm 4th sem studentsRHEOLOGY Physical pharmaceutics-II notes for B.pharm 4th sem students
RHEOLOGY Physical pharmaceutics-II notes for B.pharm 4th sem students
 
REASIGNACION 2024 UGEL CHUPACA 2024 UGEL CHUPACA.pdf
REASIGNACION 2024 UGEL CHUPACA 2024 UGEL CHUPACA.pdfREASIGNACION 2024 UGEL CHUPACA 2024 UGEL CHUPACA.pdf
REASIGNACION 2024 UGEL CHUPACA 2024 UGEL CHUPACA.pdf
 
Gender and Mental Health - Counselling and Family Therapy Applications and In...
Gender and Mental Health - Counselling and Family Therapy Applications and In...Gender and Mental Health - Counselling and Family Therapy Applications and In...
Gender and Mental Health - Counselling and Family Therapy Applications and In...
 

Repetitive Scheduling Method RSM

  • 3. What is RSM? • It is a scheduling method that focuses on “Continuous Resource Utilization” in repetitive construction. • It is a graphical method unlike LRA and URL which are calculation methods. What is its Objective? • Schedule resources -specific skilled workers/equipment- to work continuously without interruption (idle time) There are 3 main constraints in RSM: 1. Activity Precedence Constraint, in most scheduling methods such as CPM and PERT 2. Resource Availability Constraint, such as in Limited Resource Allocation (LRA) 3. Resource Continuity Constraint, such as in Line-of-Balance (LOB) Introduction to Repetitive Scheduling Method (RSM) 3
  • 4. Repetitive Scheduling Method Projects with Repeating Activities (Repetitive Projects) 4
  • 5. Projects with Repeating Activities • Housing projects (multiple houses): • Structure & Exterior for the 1st house, the 2nd house, … • HVAC for the 1st house, the 2nd house, … • Interior & Finishing for the 1st house, the 2nd house, … • High-rise Buildings (multiple floors): • Structure for the 1st floor, the 2nd floor, … • HVAC for the 1st floor, the 2nd floor, … • Interior for the 1st floor, the 2nd floor, … • Roads & Highways (multiple stations): • Excavation for the 1st station, for the 2nd station, … • Backfill for the 1st station, for the 2nd station, … • Layers for the 1st station, for the 2nd station, … 5 S2 H2 I2 Only with Precedence Constraints. No need to finish House 1 before House 2. S1 H1 I1 House1House2
  • 6. A housing projects (2 houses) • Structure & Exterior for the 1st house, the 2nd house • HVAC for the 1st house, the 2nd house • Interior & Finishing for the 1st house, the 2nd house Given there is only one crew for each activity. 6 S1 H1 I1 S2 H2 I2 S1 H1 I1 S2 H2 I2 Only with Precedence Constraints. No need to finish House 1 before House 2. H1-H2 I1-I2 With Precedence Constraints Availability Constraints S1 H1 I1 S2 H2 I2 With Precedence Constraints Availability Constraints Continuity Constraints House1House2House1House2House1House2
  • 7. Repetitive Scheduling Method Representations Bar Chart, AON, and RSM Diagram 7
  • 8. 8 S1 H1 I1 S2 H2 I2 Only with Precedence Constraints. No need to finish House 1 before House 2. House1House2 S1 3 H1 2 I1 1 Precedence Precedence S2 3 H2 2 I2 1 Precedence Precedence
  • 9. 9 S1 H1 I1 S2 H2 I2 Only with Precedence Constraints. No need to finish House 1 before House 2. House1House2 S1 H1 I1 S2 H2 I2 H1-H2 I1-I2 With Precedence Constraints Availability Constraints House1House2 S1 3 H1 2 I1 1 Precedence Precedence S2 3 H2 2 I2 1 Precedence Precedence S1 3 H1 2 I1 1 Precedence Precedence S2 3 H2 2 I2 1 Precedence Precedence
  • 10. 10 S1 H1 I1 S2 H2 I2 S1 H1 I1 S2 H2 I2 Only with Precedence Constraints. No need to finish House 1 before House 2. H Idle Time I Idle Time With Precedence Constraints Availability Constraints House1House2House1House2 S1 H1 I1 S2 H2 I2 With Precedence Constraints Availability Constraints Continuity Constraints House1House2 S1 3 H1 2 I1 1 Precedence Precedence S2 3 H2 2 I2 1 Precedence Precedence How to represent “Continuity Constraints” ? S1 3 H1 2 I1 1 Precedence Precedence S2 3 H2 2 I2 1 Precedence Precedence
  • 11. How to represent several houses (units) effectively? 11 S1 3 H1 2 I1 1 Precedence Precedence Unit 1 S2 3 H2 2 I2 1 Precedence Precedence Unit 2 S3 3 H3 2 I3 1 Precedence Precedence Unit 3 … 3 … 2 … 1 Precedence Precedence … 3 … 2 … 1 Precedence Precedence Unit … Unit … S9 3 H9 2 I9 1 Precedence Precedence Unit 9
  • 12. How to represent several houses (units) effectively? 12 A1 3 B1 2 D1 1Unit 1 C1 4 E1 2 A2 3 B2 2 D2 1Unit 2 C2 4 E2 2 A3 3 B3 2 D3 1Unit 3 C3 4 E3 2 By using AON or Bar Chart, there is NOT enough space to present all the units. Quite Messy Unit 4 to 5
  • 13. How to represent several houses (units) effectively? 13 S1 3 H1 2 I1 1 Precedence Precedence Unit 1 S2 3 H2 2 I2 1 Precedence Precedence Unit 2 S3 3 H3 2 I3 1 Precedence Precedence Unit 3 … 3 … 2 … 1 Precedence Precedence Unit … … 3 … 2 … 1 Precedence Precedence Unit … S9 3 H9 2 I9 1 Precedence Precedence Unit 9
  • 14. A repetitive project with only precedence constraints 14 S1 H1I1 Activityon Node Unit 1 Unit 2 Unit 3 Unit 4 Unit 5 Unit 6 Unit 7 Unit 8 Unit 9 Production Diagram S9 I9H9
  • 15. Precedence & Availability & Continuity for Activity S 15 Unit 1 Unit 2 Unit 3 Unit 4 Unit 5 Unit 6 Unit 7 Unit 8 Unit 9 Activityon Node S9 I9H9 S1 H1I1 Production Diagram H idle time and I idle time between units
  • 16. Production Diagram H idle time and I idle time between units Precedence & Availability & Continuity for S and H 16 Unit 1 Unit 2 Unit 3 Unit 4 Unit 5 Unit 6 Unit 7 Unit 8 Unit 9 Activityon Node S9 I9H9 S1 H1 I1
  • 17. Precedence & Availability & Continuity for S, H, and I 17 Unit 1 Unit 2 Unit 3 Unit 4 Unit 5 Unit 6 Unit 7 Unit 8 Unit 9 S9 I9 S1 H9 Activityon Node Production Diagram or RSM Diagram H1 I1
  • 18. Production Diagram H idletime and I idle time between units Precedence & Availability & … 18 Unit 1 Unit 2 Unit 3 Unit 4 Unit 5 Unit 6 Unit 7 Unit 8 Unit 9 S H I Production Diagram or RSM Diagram Unit 1 Unit 2 Unit 3 Unit 4 Unit 5 Unit 6 Unit 7 Unit 8 Unit 9 S H I without Continuity Constraints with Continuity Constraints VS
  • 19. Repetitive Scheduling Method The General Idea of RSM 19
  • 20. The general idea of RSM • RSM satisfies 3 types of constraints: activity precedence, resource availability and continuity. 20 Precedenceonly Precedence& Availability Precedence& Availability & Continuity
  • 21. The general idea of RSM • RSM satisfies 3 types of constraints: activity precedence, resource availability and continuity. 21 • RSM is a graphical method –no calculation ☺ Precedenceonly Precedence& Availability Precedence& Availability & Continuity
  • 22. The general idea of RSM • RSM satisfies 3 types of constraints: activity precedence, resource availability and continuity. 22 • RSM is a graphical method –no calculation ☺ • RSM uses production diagram: • To represent projects with repeating activities. • To determine activities’ start and finish dates. Precedenceonly Precedence& Availability Precedence& Availability & Continuity
  • 23. Repetitive Scheduling Method Concept of Controlling Point (cp) 23
  • 24. RSM Diagram Controlling Point (cp) determining repetitive activities’ schedule 24 Unit 1 Unit 2 Unit 3 Unit 4 Unit 5 cpAB Faster predecessor, cp at First unit. A: 3 days/unit, and B: 4 days/unit A1 A2 A3 A4 A5
  • 25. RSM Diagram Controlling Point (cp) determining repetitive activities’ schedule 25 Unit 1 Unit 2 Unit 3 Unit 4 Unit 5 cpAB Faster predecessor, cp at First unit. A: 3 days/unit, and B: 4 days/unit A1 A2 A3 A4 A5 B1
  • 26. RSM Diagram Controlling Point (cp) determining repetitive activities’ schedule 26 Unit 1 Unit 2 Unit 3 Unit 4 Unit 5 cpAB Faster predecessor, cp at First unit. A: 3 days/unit, and B: 4 days/unit A1 A2 A3 A4 A5 B1 B2 B3 B4 B5
  • 27. RSM Diagram Unit 1 Unit 2 Unit 3 Unit 4 Unit 5 Controlling Point (cp) determining repetitive activities’ schedule 27 RSM Diagram Unit 1 Unit 2 Unit 3 Unit 4 Unit 5 cpAB Slower predecessor, cp at Last unit. A: 3 days/unit, and C: 2 days/unit. Faster predecessor, cp at First unit. A: 3 days/unit, and B: 4 days/unit A1 A2 A3 A4 A5 A1 A2 A3 A4 A5 B1 B2 B3 B4 B5 cpAC
  • 28. RSM Diagram Unit 1 Unit 2 Unit 3 Unit 4 Unit 5 Controlling Point (cp) determining repetitive activities’ schedule 28 RSM Diagram Unit 1 Unit 2 Unit 3 Unit 4 Unit 5 cpAB Slower predecessor, cp at Last unit. A: 3 days/unit, and C: 2 days/unit. Faster predecessor, cp at First unit. A: 3 days/unit, and B: 4 days/unit A1 A2 A3 A4 A5 A1 A2 A3 A4 A5 B1 B2 B3 B4 B5 C5 cpAC
  • 29. RSM Diagram Unit 1 Unit 2 Unit 3 Unit 4 Unit 5 Controlling Point (cp) determining repetitive activities’ schedule 29 RSM Diagram Unit 1 Unit 2 Unit 3 Unit 4 Unit 5 cpAB Slower predecessor, cp at Last unit. A: 3 days/unit, and C: 2 days/unit. Faster predecessor, cp at First unit. A: 3 days/unit, and B: 4 days/unit A1 A2 A3 A4 A5 A1 A2 A3 A4 A5 B1 B2 B3 B4 B5 C1 C2 C3 C4 C5 cpAC
  • 30. RSM Diagram Unit 1 Unit 2 Unit 3 Unit 4 Unit 5 Controlling Point (cp) determining repetitive activities’ schedule 30 RSM Diagram Unit 1 Unit 2 Unit 3 Unit 4 Unit 5 cpAB Slower predecessor, cp at Last unit. A: 3 days/unit, and C: 2 days/unit. Faster predecessor, cp at First unit. A: 3 days/unit, and B: 4 days/unit A1 A2 A3 A4 A5 A1 A2 A3 A4 A5 B1 B2 B3 B4 B5 C1 C2 C3 C4 C5 cpAC C1 C2 C3 C4 C5 If not using cp, there will be idle time between units.
  • 31. Repetitive Scheduling Method “Draw & Drag” to possible Controlling Points 31
  • 32. RSM Diagram Unit 1 Unit 2 Unit 3 Unit 4 Unit 5 Let’s “Draw & Drag” to possible cp instead 32 RSM Diagram Unit 1 Unit 2 Unit 3 Unit 4 Unit 5 Slower predecessor, cp at Last unit. A: 3 days/unit, and C: 2 days/unit. Faster predecessor, cp at First unit. A: 3 days/unit, and B: 4 days/unit A1 A2 A3 A4 A5 A1 A2 A3 A4 A5 cp cpcp cp 1. Determine possible controlling points
  • 33. RSM Diagram Unit 1 Unit 2 Unit 3 Unit 4 Unit 5 Let’s “Draw & Drag” to possible cp instead 33 RSM Diagram Unit 1 Unit 2 Unit 3 Unit 4 Unit 5 Slower predecessor, cp at Last unit. A: 3 days/unit, and C: 2 days/unit. Faster predecessor, cp at First unit. A: 3 days/unit, and B: 4 days/unit A1 A2 A3 A4 A5 A1 A2 A3 A4 A5 B1 B2 B3 B4 B5 C1 C2 C3 C4 C5 cp cp cp cp 1. Determine possible controlling points 2. Draw the successor
  • 34. RSM Diagram Unit 1 Unit 2 Unit 3 Unit 4 Unit 5 Let’s “Draw & Drag” to possible cp instead 34 RSM Diagram Unit 1 Unit 2 Unit 3 Unit 4 Unit 5 Slower predecessor, cp at Last unit. A: 3 days/unit, and C: 2 days/unit. Faster predecessor, cp at First unit. A: 3 days/unit, and B: 4 days/unit A1 A2 A3 A4 A5 A1 A2 A3 A4 A5 B1 B2 B3 B4 B5 C1 C2 C3 C4 C5 cp cp cp cp 1. Determine possible controlling points 2. Draw the successor 3. Drag it horizontally to the first possible cp Drag Drag
  • 35. RSM Diagram Unit 1 Unit 2 Unit 3 Unit 4 Unit 5 Let’s “Draw & Drag” to possible cp instead 35 RSM Diagram Unit 1 Unit 2 Unit 3 Unit 4 Unit 5 Slower predecessor, cp at Last unit. A: 3 days/unit, and C: 2 days/unit. Faster predecessor, cp at First unit. A: 3 days/unit, and B: 4 days/unit A1 A2 A3 A4 A5 A1 A2 A3 A4 A5 cp cp cp cp 1. Determine possible controlling points 2. Draw the successor 3. Drag it horizontally to the first possible cp B1 B2 B3 B4 B5 C1 C2 C3 C4 C5 cpAC cpAB
  • 36. RSM Diagram Unit 1 Unit 2 Unit 3 Unit 4 Unit 5 Let’s “Draw & Drag” to possible cp instead 36 RSM Diagram Unit 1 Unit 2 Unit 3 Unit 4 Unit 5 Slower predecessor, cp at Last unit. A: 3 days/unit, and C: 2 days/unit. Faster predecessor, cp at First unit. A: 3 days/unit, and B: 4 days/unit A1 A2 A3 A4 A5 A1 A2 A3 A4 A5 1. Determine possible controlling points 2. Draw the successor 3. Drag it horizontally to the first possible cp B1 B2 B3 B4 B5 C1 C2 C3 C4 C5 cpAC cpAB
  • 37. Repetitive Scheduling Method Concept of Controlling Sequence 37
  • 38. Concept of Controlling Sequence What is Controlling Sequence? • It is a sequence of unit activities from project Finish to Start. • It determines project duration under continuity constraints. • If a productivity of any activities on controlling sequence has changed, project duration will change. How to identify Controlling Sequence? Easy. Start from the Project Finish to project Start via Controlling Points, cp. 38
  • 39. Concept of Controlling Sequence What is Controlling Sequence? • It is a sequence of unit activities from project Finish to Start. • It determines project duration under continuity constraints. • If a productivity of any activities on controlling sequence has changed, project duration will change. How to identify Controlling Sequence? Easy. Start from the Project Finish to project Start via Controlling Points, cp. 39
  • 40. Concept of Controlling Sequence What is Controlling Sequence? • It is a sequence of unit activities from project Finish to Start. • It determines project duration under continuity constraints. • If a productivity of any activities on controlling sequence has changed, project duration will change. How to identify Controlling Sequence? Easy. Start from the Project Finish to project Start via Controlling Points, cp. 40
  • 41. Concept of Controlling Sequence What is Controlling Sequence? • It is a sequence of unit activities from project Finish to Start. • It determines project duration under continuity constraints. • If a productivity of any activities on controlling sequence has changed, project duration will change. How to identify Controlling Sequence? Easy. Start from the Project Finish to project Start via Controlling Points, cp. 41
  • 42. Concept of Controlling Sequence What is Controlling Sequence? • It is a sequence of unit activities from project Finish to Start. • It determines project duration under continuity constraints. • If a productivity of any activities on controlling sequence has changed, project duration will change. How to identify Controlling Sequence? Easy. Start from the Project Finish to project Start via Controlling Points, cp. 42 Controlling Sequence: B5-1, A1
  • 43. Concept of Controlling Sequence What is Controlling Sequence? • It is a sequence of unit activities from project Finish to Start. • It determines project duration under continuity constraints. • If a productivity of any activities on controlling sequence has changed, project duration will change. How to identify Controlling Sequence? Easy. Start from the Project Finish to project Start via Controlling Points, cp. 43 Controlling Sequence: B5-1, A1
  • 44. Concept of Controlling Sequence What is Controlling Sequence? • It is a sequence of unit activities from project Finish to Start. • It determines project duration under continuity constraints. • If a productivity of any activities on controlling sequence has changed, project duration will change. How to identify Controlling Sequence? Easy. Start from the Project Finish to project Start via Controlling Points, cp. 44 Controlling Sequence: B5-1, A1
  • 45. Concept of Controlling Sequence What is Controlling Sequence? • It is a sequence of unit activities from project Finish to Start. • It determines project duration under continuity constraints. • If a productivity of any activities on controlling sequence has changed, project duration will change. How to identify Controlling Sequence? Easy. Start from the Project Finish to project Start via Controlling Points, cp. 45 Controlling Sequence: B5-1, A1
  • 46. Concept of Controlling Sequence What is Controlling Sequence? • It is a sequence of unit activities from project Finish to Start. • It determines project duration under continuity constraints. • If a productivity of any activities on controlling sequence has changed, project duration will change. How to identify Controlling Sequence? Easy. Start from the Project Finish to project Start via Controlling Points, cp. 46 Controlling Sequence: B5-1, A1 Controlling Sequence: C5, A5-1
  • 47. Another example for the concept of Controlling Sequence 47 RSM Diagram Unit 1 Unit 2 Unit 3 Unit 4 Unit 5 A1 A2 A3 A4 A5 B1 B2 B3 B4 B5 C1 C2 C3 C4 C5 AC AB A 3 B 4 C 2 D 4
  • 48. Another example for the concept of Controlling Sequence 48 RSM Diagram Unit 1 Unit 2 Unit 3 Unit 4 Unit 5 A1 A2 A3 A4 A5 B1 B2 B3 B4 B5 C1 C2 C3 C4 C5 AC AB A 3 B 4 C 2 D 4 D1 D2 D3 D4 D5
  • 49. Another example for the concept of Controlling Sequence 49 RSM Diagram Unit 1 Unit 2 Unit 3 Unit 4 Unit 5 A1 A2 A3 A4 A5 B1 B2 B3 B4 B5 C1 C2 C3 C4 C5 AC AB A 3 B 4 C 2 D 4 cp cp D1 D2 D3 D4 D5
  • 50. Another example for the concept of Controlling Sequence 50 RSM Diagram Unit 1 Unit 2 Unit 3 Unit 4 Unit 5 A1 A2 A3 A4 A5 B1 B2 B3 B4 B5 C1 C2 C3 C4 C5 AC AB A 3 B 4 C 2 D 4 cp cp cp cp D1 D2 D3 D4 D5
  • 51. Another example for the concept of Controlling Sequence 51 RSM Diagram Unit 1 Unit 2 Unit 3 Unit 4 Unit 5 A1 A2 A3 A4 A5 B1 B2 B3 B4 B5 C1 C2 C3 C4 C5 AC AB D1 D2 D3 D4 D5 A 3 B 4 C 2 D 4 cp cp cp cp Drag
  • 52. Another example for the concept of Controlling Sequence 52 RSM Diagram Unit 1 Unit 2 Unit 3 Unit 4 Unit 5 A1 A2 A3 A4 A5 B1 B2 B3 B4 B5 C1 C2 C3 C4 C5 AC AB D1 D2 D3 D4 D5 A 3 B 4 C 2 D 4 CD
  • 53. Another example for the concept of Controlling Sequence 53 RSM Diagram Unit 1 Unit 2 Unit 3 Unit 4 Unit 5 A1 A2 A3 A4 A5 B1 B2 B3 B4 B5 C1 C2 C3 C4 C5 AC AB D1 D2 D3 D4 D5 A 3 B 4 C 2 D 4 CD
  • 54. Another example for the concept of Controlling Sequence 54 RSM Diagram Unit 1 Unit 2 Unit 3 Unit 4 Unit 5 A1 A2 A3 A4 A5 B1 B2 B3 B4 B5 C1 C2 C3 C4 C5 AC AB D1 D2 D3 D4 D5 A 3 B 4 C 2 D 4 CD
  • 55. Another example for the concept of Controlling Sequence 55 RSM Diagram Unit 1 Unit 2 Unit 3 Unit 4 Unit 5 A1 A2 A3 A4 A5 B1 B2 B3 B4 B5 C1 C2 C3 C4 C5 AC AB D1 D2 D3 D4 D5 A 3 B 4 C 2 D 4 CD
  • 56. Another example for the concept of Controlling Sequence 56 RSM Diagram Unit 1 Unit 2 Unit 3 Unit 4 Unit 5 A1 A2 A3 A4 A5 B1 B2 B3 B4 B5 C1 C2 C3 C4 C5 AC AB D1 D2 D3 D4 D5 A 3 B 4 C 2 D 4 CD
  • 57. Another example for the concept of Controlling Sequence 57 RSM Diagram Unit 1 Unit 2 Unit 3 Unit 4 Unit 5 A1 A2 A3 A4 A5 B1 B2 B3 B4 B5 C1 C2 C3 C4 C5 AC AB D1 D2 D3 D4 D5 A 3 B 4 C 2 D 4 CD
  • 58. Another example for the concept of Controlling Sequence 58 RSM Diagram Unit 1 Unit 2 Unit 3 Unit 4 Unit 5 A1 A2 A3 A4 A5 B1 B2 B3 B4 B5 C1 C2 C3 C4 C5 AC AB D1 D2 D3 D4 D5 A 3 B 4 C 2 D 4 CD Activities on ControllingSequence: D5-1, C2-4, A5-1
  • 59. Another example for the concept of Controlling Sequence 59 RSM Diagram Unit 1 Unit 2 Unit 3 Unit 4 Unit 5 A1 A2 A3 A4 A5 B1 B2 B3 B4 B5 C1 C2 C3 C4 C5 AC AB D1 D2 D3 D4 D5 A 3 B 4 C 2 D 4 CD Activities on ControllingSequence: D5-1, C2-4, A5-1 Changing productivity ofcontrollingactivities will change project duration immediately.
  • 60. Another example for the concept of Controlling Sequence 60 RSM Diagram Unit 1 Unit 2 Unit 3 Unit 4 Unit 5 A1 A2 A3 A4 A5 B1 B2 B3 B4 B5 C1 C2 C3 C4 C5 AC AB D1 D2 D3 D4 D5 A 3 B 4 C 2 D 4 CD Activities on ControllingSequence: D5-1, C2-4, A5-1 Changing productivity ofcontrollingactivities will change project duration immediately. On the other hand, changingthose of non-controlling activities will Not immediately affect project duration, such as B1-5, C1, and C5.
  • 62. Critical Activities on RSM 62 RSM Diagram Unit 1 Unit 2 Unit 3 Unit 4 Unit 5 A 3 B 4 C 2 D 4 D5 D4 D3 D2 D1 B5 B4 B3 B2 B1 C5 C4AC CDAB C3 C2 C1 A5 A4 A3 A2 A1 • Critical activities are that if delayed, project will be delayed. • Critical activities do not consider resource continuity constraints.
  • 63. Critical Activities on RSM 63 RSM Diagram Unit 1 Unit 2 Unit 3 Unit 4 Unit 5 A 3 B 4 C 2 D 4 D5 D4 D3 D2 D1 B5 B4 B3 B2 B1 C5 C4AC CDAB C3 C2 C1 A5 A4 A3 A2 A1 • Critical activities are that if delayed, project will be delayed. • Critical activities do not consider resource continuity constraints. • Delaying D5 will delay project. Project is delayed.
  • 64. Critical Activities on RSM 64 RSM Diagram Unit 1 Unit 2 Unit 3 Unit 4 Unit 5 A 3 B 4 C 2 D 4 D5 D4 D3 D2 D1 B5 B4 B3 B2 B1 C5 C4AC CDAB C3 C2 C1 A5 A4 A3 A2 A1 • Critical activities are that if delayed, project will be delayed. • Critical activities do not consider resource continuity constraints. • Delaying D5 will delay project. Again, CPM doesn’t care about resource continuity constraints. If delaying an activity and it delays project duration, it is a critical activity. Therefore, D5 is a critical activity. Project is delayed.
  • 65. Critical Activities on RSM 65 RSM Diagram Unit 1 Unit 2 Unit 3 Unit 4 Unit 5 A 3 B 4 C 2 D 4 D5 D4 D3 D2 D1 B5 B4 B3 B2 B1 C5 C4AC CDAB C3 C2 C1 A5 A4 A3 A2 A1 • Critical activities are that if delayed, project will be delayed. • Critical activities do not consider resource continuity constraints. • Delaying D5 will delay project. • Delaying D4 will delay project. Project is delayed.
  • 66. Critical Activities on RSM 66 RSM Diagram Unit 1 Unit 2 Unit 3 Unit 4 Unit 5 A 3 B 4 C 2 D 4 D5 D4 D3 D2 D1 B5 B4 B3 B2 B1 C5 C4AC CDAB C3 C2 C1 A5 A4 A3 A2 A1 • Critical activities are that if delayed, project will be delayed. • Critical activities do not consider resource continuity constraints. • Delaying D5 will delay project. • Delaying D4 will delay project. • Delaying D1 will delay project. Project is delayed. Tip 1. If the last unit is critical, all are also critical, due to continuity.
  • 67. Critical Activities on RSM 67 RSM Diagram Unit 1 Unit 2 Unit 3 Unit 4 Unit 5 A 3 B 4 C 2 D 4 D5 D4 D3 D2 D1 B5 B4 B3 B2 B1 C5 C4AC CDAB C3 C2 C1 A5 A4 A3 A2 A1 • Critical activities are that if delayed, project will be delayed. • Critical activities do not consider resource continuity constraints. • Delaying D5 will delay project. • Delaying D4 will delay project. • Delaying D1 will delay project. • Delaying C5 will not delay project.Project is not delayed. Tip 1. If the last unit is critical, all are also critical, due to continuity.
  • 68. Critical Activities on RSM 68 RSM Diagram Unit 1 Unit 2 Unit 3 Unit 4 Unit 5 A 3 B 4 C 2 D 4 D5 D4 D3 D2 D1 B5 B4 B3 B2 B1 C4AC CDAB C3 C2 C1 A5 A4 A3 A2 A1 • Critical activities are that if delayed, project will be delayed. • Critical activities do not consider resource continuity constraints. • Delaying D5 will delay project. • Delaying D4 will delay project. • Delaying D1 will delay project. • Delaying C5 will not delay project.Project is not delayed. The discontinuity here doesn’t matter, when talking about “Critical Activities” C5 Tip 1. If the last unit is critical, all are also critical, due to continuity.
  • 69. Critical Activities on RSM 69 RSM Diagram Unit 1 Unit 2 Unit 3 Unit 4 Unit 5 A 3 B 4 C 2 D 4 D5 D4 D3 D2 D1 B5 B4 B3 B2 B1 C5 C4AC CDAB C3 C2 C1 A5 A4 A3 A2 A1 • Critical activities are that if delayed, project will be delayed. • Critical activities do not consider resource continuity constraints. • Delaying D5 will delay project. • Delaying D4 will delay project. • Delaying D1 will delay project. • Delaying C5 will not delay project.Project is not delayed. The discontinuity here doesn’t matter, when talking about “Critical Activities.” Don’t try to satisfy continuity constraints when identifying “critical activities.” Tip 1. If the last unit is critical, all are also critical, due to continuity.
  • 70. Critical Activities on RSM 70 RSM Diagram Unit 1 Unit 2 Unit 3 Unit 4 Unit 5 A 3 B 4 C 2 D 4 D5 D4 D3 D2 D1 B5 B4 B3 B2 B1 C5 C4AC CDAB C3 C2 C1 A5 A4 A3 A2 A1 • Critical activities are that if delayed, project will be delayed. • Critical activities do not consider resource continuity constraints. • Delaying D5 will delay project. • Delaying D4 will delay project. • Delaying D1 will delay project. • Delaying C5 will not delay project. • Delaying C4 will not delay project. Project is not delayed. Tip 1. If the last unit is critical, all are also critical, due to continuity.
  • 71. Critical Activities on RSM 71 RSM Diagram Unit 1 Unit 2 Unit 3 Unit 4 Unit 5 A 3 B 4 C 2 D 4 D5 D4 D3 D2 D1 B5 B4 B3 B2 B1 CDAB C5 C4 C3 C2 C1 A5 A4 A3 A2 A1 • Critical activities are that if delayed, project will be delayed. • Critical activities do not consider resource continuity constraints. AC • Delaying D5 will delay project. • Delaying D4 will delay project. • Delaying D1 will delay project. • Delaying C5 will not delay project. • Delaying C4 will not delay project. • Delaying C2 will not delay project. Project is not delayed. Tip 1. If the last unit is critical, all are also critical, due to continuity.
  • 72. Critical Activities on RSM 72 RSM Diagram Unit 1 Unit 2 Unit 3 Unit 4 Unit 5 A 3 B 4 C 2 D 4 B5 B4 B3 B2 B1 AB D5 D4 D3 D2 D1 C5 C4 CD C3 C2 C1 A5 A4 A3 A2 A1 • Critical activities are that if delayed, project will be delayed. • Critical activities do not consider resource continuity constraints. AC • Delaying D5 will delay project. • Delaying D4 will delay project. • Delaying D1 will delay project. • Delaying C5 will not delay project. • Delaying C4 will not delay project. • Delaying C2 will not delay project. • Delaying C1 will delay project. Project is delayed. Tip 1. If the last unit is critical, all are also critical, due to continuity.
  • 73. Critical Activities on RSM 73 RSM Diagram Unit 1 Unit 2 Unit 3 Unit 4 Unit 5 A 3 B 4 C 2 D 4 B5 B4 B3 B2 B1 AB D5 D4 D3 D2 D1 C5 C4 CD C3 C2 C1 A5 A4 A3 A2 A1 • Critical activities are that if delayed, project will be delayed. • Critical activities do not consider resource continuity constraints. AC • Delaying D5 will delay project. • Delaying D4 will delay project. • Delaying D1 will delay project. • Delaying C5 will not delay project. • Delaying C4 will not delay project. • Delaying C2 will not delay project. • Delaying C1 will delay project. Project is delayed. Tip 1. If the last unit is critical, all are also critical, due to continuity. Tip 2. If the last unit is not critical, only the first unit could be critical. So you only need to check the first & the last. (Applicable to repetitive projects with only typical repetitiveactivities.)
  • 74. Critical Activities on RSM 74 RSM Diagram Unit 1 Unit 2 Unit 3 Unit 4 Unit 5 A 3 B 4 C 2 D 4 D5 D4 D3 D2 D1 B5 B4 B3 B2 B1 C5 C4AC CDAB C3 C2 C1 A5 A4 A3 A2 A1 • Critical activities are that if delayed, project will be delayed. • Critical activities do not consider resource continuity constraints. • Delaying D5 will delay project. • Delaying D4 will delay project. • Delaying D1 will delay project. • Delaying C5 will not delay project. • Delaying C4 will not delay project. • Delaying C2 will not delay project. • Delaying C1 will delay project. • Delaying B5 will not delay project. Project is not delayed. Tip 1. If the last unit is critical, all are also critical, due to continuity. Tip 2. If the last unit is not critical, only the first unit could be critical. So you only need to check the first & the last. (Applicable to repetitive projects with only typical repetitiveactivities.)
  • 75. Critical Activities on RSM 75 RSM Diagram Unit 1 Unit 2 Unit 3 Unit 4 Unit 5 A 3 B 4 C 2 D 4 D5 D4 D3 D2 D1 B5 B4 B3 B2 B1 C5 C4AC CDAB C3 C2 C1 A5 A4 A3 A2 A1 • Critical activities are that if delayed, project will be delayed. • Critical activities do not consider resource continuity constraints. • Delaying D5 will delay project. • Delaying D4 will delay project. • Delaying D1 will delay project. • Delaying C5 will not delay project. • Delaying C4 will not delay project. • Delaying C2 will not delay project. • Delaying C1 will delay project. • Delaying B5 will not delay project. Project is not delayed. Tip 1. If the last unit is critical, all are also critical, due to continuity. Tip 2. If the last unit is not critical, only the first unit could be critical. So you only need to check the first & the last. (Applicable to repetitive projects with only typical repetitiveactivities.) The discontinuity here doesn’t matter, when talking about “Critical Activities.”
  • 76. Critical Activities on RSM 76 RSM Diagram Unit 1 Unit 2 Unit 3 Unit 4 Unit 5 A 3 B 4 C 2 D 4 D5 D4 D3 D2 D1 B5 B4 B3 B2 B1 C5 C4AC CDAB C3 C2 C1 A5 A4 A3 A2 A1 • Critical activities are that if delayed, project will be delayed. • Critical activities do not consider resource continuity constraints. • Delaying D5 will delay project. • Delaying D4 will delay project. • Delaying D1 will delay project. • Delaying C5 will not delay project. • Delaying C4 will not delay project. • Delaying C2 will not delay project. • Delaying C1 will delay project. • Delaying B5 will not delay project. • Delaying B1 will not delay project. Project is not delayed. Tip 1. If the last unit is critical, all are also critical, due to continuity. Tip 2. If the last unit is not critical, only the first unit could be critical. So you only need to check the first & the last. (Applicable to repetitive projects with only typical repetitiveactivities.)
  • 77. Critical Activities on RSM 77 RSM Diagram Unit 1 Unit 2 Unit 3 Unit 4 Unit 5 A 3 B 4 C 2 D 4 D5 D4 D3 D2 D1 B5 B4 B3 B2 B1 C5 C4AC CDAB C3 C2 C1 A5 A4 A3 A2 A1 • Critical activities are that if delayed, project will be delayed. • Critical activities do not consider resource continuity constraints. • Delaying D5 will delay project. • Delaying D4 will delay project. • Delaying D1 will delay project. • Delaying C5 will not delay project. • Delaying C4 will not delay project. • Delaying C2 will not delay project. • Delaying C1 will delay project. • Delaying B5 will not delay project. • Delaying B1 will not delay project. Project is not delayed. Tip 1. If the last unit is critical, all are also critical, due to continuity. Tip 2. If the last unit is not critical, only the first unit could be critical. So you only need to check the first & the last. (Applicable to repetitive projects with only typical repetitiveactivities.)
  • 78. Critical Activities on RSM 78 RSM Diagram Unit 1 Unit 2 Unit 3 Unit 4 Unit 5 A 3 B 4 C 2 D 4 D5 D4 D3 D2 D1 B5 B4 B3 B2 B1 C4 CDAB C3 C2 C1 C5 AC A5 A4 A3 A2 A1 • Critical activities are that if delayed, project will be delayed. • Critical activities do not consider resource continuity constraints. • Delaying D5 will delay project. • Delaying D4 will delay project. • Delaying D1 will delay project. • Delaying C5 will not delay project. • Delaying C4 will not delay project. • Delaying C2 will not delay project. • Delaying C1 will delay project. • Delaying B5 will not delay project. • Delaying B1 will not delay project. • Delaying A5 will not delay project. Tip 1. If the last unit is critical, all are also critical, due to continuity. Tip 2. If the last unit is not critical, only the first unit could be critical. So you only need to check the first & the last. (Applicable to repetitive projects with only typical repetitiveactivities.) Project is not delayed.
  • 79. Critical Activities on RSM 79 RSM Diagram Unit 1 Unit 2 Unit 3 Unit 4 Unit 5 A 3 B 4 C 2 D 4 D5 D4 D3 D2 D1 C4 CD C3 C2 C1 B5 B4 B3 B2 B1 C5 AC AB A5 A4 A3 A2 A1 • Critical activities are that if delayed, project will be delayed. • Critical activities do not consider resource continuity constraints. • Delaying D5 will delay project. • Delaying D4 will delay project. • Delaying D1 will delay project. • Delaying C5 will not delay project. • Delaying C4 will not delay project. • Delaying C2 will not delay project. • Delaying C1 will delay project. • Delaying B5 will not delay project. • Delaying B1 will not delay project. • Delaying A5 will not delay project. • Delaying A1 will not delay project. Tip 1. If the last unit is critical, all are also critical, due to continuity. Tip 2. If the last unit is not critical, only the first unit could be critical. So you only need to check the first & the last. (Applicable to repetitive projects with only typical repetitiveactivities.) Project is not delayed.
  • 80. Critical Activities on RSM 80 RSM Diagram Unit 1 Unit 2 Unit 3 Unit 4 Unit 5 A 3 B 4 C 2 D 4 D5 D4 D3 D2 D1 B5 B4 B3 B2 B1 C5 C4AC CDAB C3 C2 C1 A5 A4 A3 A2 A1 • Critical activities are that if delayed, project will be delayed. • Critical activities do not consider resource continuity constraints. • Delaying D5 will delay project. • Delaying D4 will delay project. • Delaying D1 will delay project. • Delaying C5 will not delay project. • Delaying C4 will not delay project. • Delaying C2 will not delay project. • Delaying C1 will delay project. • Delaying B5 will not delay project. • Delaying B1 will not delay project. • Delaying A5 will not delay project. • Delaying A1 will not delay project. Therefore, critical activities are: D5-1, and C1. Tip 1. If the last unit is critical, all are also critical, due to continuity. Tip 2. If the last unit is not critical, only the first unit could be critical. So you only need to check the first & the last. (Applicable to repetitive projects with only typical repetitiveactivities.)
  • 81. Critical Activities on RSM & Controlling Activities 81 RSM Diagram Unit 1 Unit 2 Unit 3 Unit 4 Unit 5 A 3 B 4 C 2 D 4 D5 D4 D3 D2 D1 B5 B4 B3 B2 B1 C5 C4AC CDAB C3 C2 C1 A5 A4 A3 A2 A1 • Critical activities are that if delayed, project will be delayed. • Critical activities do not consider resource continuity constraints. • Delaying D5 will delay project. • Delaying D4 will delay project. • Delaying D1 will delay project. • Delaying C5 will not delay project. • Delaying C4 will not delay project. • Delaying C2 will not delay project. • Delaying C1 will delay project. • Delaying B5 will not delay project. • Delaying B1 will not delay project. • Delaying A5 will not delay project. • Delaying A1 will not delay project. Therefore, critical activities are: D5-1, and C1. Tip 1. If the last unit is critical, all are also critical, due to continuity. Tip 2. If the last unit is not critical, only the first unit could be critical. So you only need to check the first & the last. (Applicable to repetitive projects with only typical repetitiveactivities.) D5-1, C2-4, and A5-1
  • 82. Repetitive Scheduling Method Example 1: 3 units 82 B 1 C 4 D 6 A 3
  • 83. Example 1: 3 units 83 Unit 1 Unit 2 Unit 3 2 4 6 8 10 12 14 16 18 20 22 24 26 28 30 32 34 36 38 400 42 44 46 48 50 B 1 C 4 D 6 A 3 • Identify controllingpoints, cp • ... • Identify controllingsequence • … • Identify critical activities • …
  • 84. Example 1: 3 units 84 Unit 1 Unit 2 Unit 3 2 4 6 8 10 12 14 16 18 20 22 24 26 28 30 32 34 36 38 400 42 44 46 48 50 A B 1 C 4 D 6 A 3 • Identify controllingpoints, cp • ... • Identify controllingsequence • … • Identify critical activities • …
  • 85. Example 1: 3 units 85 Unit 1 Unit 2 Unit 3 2 4 6 8 10 12 14 16 18 20 22 24 26 28 30 32 34 36 38 400 42 44 46 48 50 A B B 1 C 4 D 6 A 3 AB • Identify controllingpoints, cp • ... • Identify controllingsequence • … • Identify critical activities • …
  • 86. Example 1: 3 units 86 Unit 1 Unit 2 Unit 3 2 4 6 8 10 12 14 16 18 20 22 24 26 28 30 32 34 36 38 400 42 44 46 48 50 A B C B 1 C 4 D 6 A 3 BC AB • Identify controllingpoints, cp • ... • Identify controllingsequence • … • Identify critical activities • …
  • 87. Example 1: 3 units 87 Unit 1 Unit 2 Unit 3 2 4 6 8 10 12 14 16 18 20 22 24 26 28 30 32 34 36 38 400 42 44 46 48 50 A B DC B 1 C 4 D 6 A 3 BC CD AB • Identify controllingpoints, cp • ... • Identify controllingsequence • … • Identify critical activities • …
  • 88. Example 1: 3 units 88 Unit 1 Unit 2 Unit 3 2 4 6 8 10 12 14 16 18 20 22 24 26 28 30 32 34 36 38 400 42 44 46 48 50 A B DC B 1 C 4 D 6 A 3 BC CD AB • Identify controllingpoints, cp • AB, BC, CD • Identify controllingsequence • … • Identify critical activities • …
  • 89. Example 1: 3 units 89 Unit 1 Unit 2 Unit 3 2 4 6 8 10 12 14 16 18 20 22 24 26 28 30 32 34 36 38 400 42 44 46 48 50 A B DC B 1 C 4 D 6 A 3 BC CD AB • Identify controllingpoints, cp • AB, BC, CD • Identify controllingsequence • … • Identify critical activities • …
  • 90. Example 1: 3 units 90 Unit 1 Unit 2 Unit 3 2 4 6 8 10 12 14 16 18 20 22 24 26 28 30 32 34 36 38 400 42 44 46 48 50 A B DC B 1 C 4 D 6 A 3 BC CD AB • Identify controllingpoints, cp • AB, BC, CD • Identify controllingsequence • D3-1, C1, B2, A3-1 • Identify critical activities • …
  • 91. Example 1: 3 units 91 Unit 1 Unit 2 Unit 3 2 4 6 8 10 12 14 16 18 20 22 24 26 28 30 32 34 36 38 400 42 44 46 48 50 A B DC B 1 C 4 D 6 A 3 BC CD AB • Identify controllingpoints, cp • AB, BC, CD • Identify controllingsequence • D3-1, C1, B2, A3-1 • Identify critical activities • … Tip 1. If the last unit is critical, all are also critical, due to continuity. Tip 2. If the last unit is not critical, only the first unit could be critical. So you only need to check the first & the last. (Applicable to repetitive projects with only typical repetitiveactivities.)
  • 92. Example 1: 3 units 92 Unit 1 Unit 2 Unit 3 2 4 6 8 10 12 14 16 18 20 22 24 26 28 30 32 34 36 38 400 42 44 46 48 50 A B DC B 1 C 4 D 6 A 3 BC CD AB • Identify controllingpoints, cp • AB, BC, CD • Identify controllingsequence • D3-1, C1, B2, A3-1 • Identify critical activities • … Tip 1. If the last unit is critical, all are also critical, due to continuity. Tip 2. If the last unit is not critical, only the first unit could be critical. So you only need to check the first & the last. (Applicable to repetitive projects with only typical repetitiveactivities.)
  • 93. Example 1: 3 units 93 Unit 1 Unit 2 Unit 3 2 4 6 8 10 12 14 16 18 20 22 24 26 28 30 32 34 36 38 400 42 44 46 48 50 A B DC B 1 C 4 D 6 A 3 BC CD AB • Identify controllingpoints, cp • AB, BC, CD • Identify controllingsequence • D3-1, C1, B2, A3-1 • Identify critical activities • D3-1, C1, B1 Tip 1. If the last unit is critical, all are also critical, due to continuity. Tip 2. If the last unit is not critical, only the first unit could be critical. So you only need to check the first & the last. (Applicable to repetitive projects with only typical repetitiveactivities.)
  • 94. Repetitive Scheduling Method Example 2: 4 units 94 A 3 B 1 C 6 D 3 E 5
  • 95. Example 2: 4 units 95 Unit 1 Unit 2 Unit 3 Unit 4 2 4 6 8 10 12 14 16 18 20 22 24 26 28 30 32 34 36 38 400 42 44 46 48 50 A 3 B 1 C 6 D 3 E 5 • Identify controllingpoints, cp • ... • Identify controllingsequence • … • Identify critical activities • …
  • 96. Example 2: 4 units 96 Unit 1 Unit 2 Unit 3 Unit 4 2 4 6 8 10 12 14 16 18 20 22 24 26 28 30 32 34 36 38 400 42 44 46 48 50 A A 3 B 1 C 6 D 3 E 5 • Identify controllingpoints, cp • ... • Identify controllingsequence • … • Identify critical activities • …
  • 97. Example 2: 4 units 97 Unit 1 Unit 2 Unit 3 Unit 4 2 4 6 8 10 12 14 16 18 20 22 24 26 28 30 32 34 36 38 400 42 44 46 48 50 A B A 3 B 1 C 6 D 3 E 5 AB • Identify controllingpoints, cp • ... • Identify controllingsequence • … • Identify critical activities • …
  • 98. Example 2: 4 units 98 Unit 1 Unit 2 Unit 3 Unit 4 2 4 6 8 10 12 14 16 18 20 22 24 26 28 30 32 34 36 38 400 42 44 46 48 50 A B C A 3 B 1 C 6 D 3 E 5 AB • Identify controllingpoints, cp • ... • Identify controllingsequence • … • Identify critical activities • … AC
  • 99. Example 2: 4 units 99 Unit 1 Unit 2 Unit 3 Unit 4 2 4 6 8 10 12 14 16 18 20 22 24 26 28 30 32 34 36 38 400 42 44 46 48 50 A B CD A 3 B 1 C 6 D 3 E 5 AB • Identify controllingpoints, cp • ... • Identify controllingsequence • … • Identify critical activities • … BDAC
  • 100. Example 2: 4 units 100 Unit 1 Unit 2 Unit 3 Unit 4 2 4 6 8 10 12 14 16 18 20 22 24 26 28 30 32 34 36 38 400 42 44 46 48 50 A B CD A 3 B 1 C 6 D 3 E 5 AB • Identify controllingpoints, cp • ... • Identify controllingsequence • … • Identify critical activities • … BDAC Determine possible cp from D and C to E
  • 101. Example 2: 4 units 101 Unit 1 Unit 2 Unit 3 Unit 4 2 4 6 8 10 12 14 16 18 20 22 24 26 28 30 32 34 36 38 400 42 44 46 48 50 A B CD A 3 B 1 C 6 D 3 E 5 AB • Identify controllingpoints, cp • ... • Identify controllingsequence • … • Identify critical activities • … BDAC E Drag Determine possible cp from D and C to E
  • 102. Example 2: 4 units 102 Unit 1 Unit 2 Unit 3 Unit 4 2 4 6 8 10 12 14 16 18 20 22 24 26 28 30 32 34 36 38 400 42 44 46 48 50 A B CD E A 3 B 1 C 6 D 3 E 5 AB • Identify controllingpoints, cp • ... • Identify controllingsequence • … • Identify critical activities • … BD DEAC
  • 103. Example 2: 4 units 103 Unit 1 Unit 2 Unit 3 Unit 4 2 4 6 8 10 12 14 16 18 20 22 24 26 28 30 32 34 36 38 400 42 44 46 48 50 A B CD E A 3 B 1 C 6 D 3 E 5 AB • Identify controllingpoints, cp • AC, AB, BD, DE • Identify controllingsequence • … • Identify critical activities • … BD DEAC
  • 104. Example 2: 4 units 104 Unit 1 Unit 2 Unit 3 Unit 4 2 4 6 8 10 12 14 16 18 20 22 24 26 28 30 32 34 36 38 400 42 44 46 48 50 A B CD E A 3 B 1 C 6 D 3 E 5 • Identify controllingpoints, cp • AC, AB, BD, DE • Identify controllingsequence • … • Identify critical activities • … BD DEAC AB
  • 105. Example 2: 4 units 105 Unit 1 Unit 2 Unit 3 Unit 4 2 4 6 8 10 12 14 16 18 20 22 24 26 28 30 32 34 36 38 400 42 44 46 48 50 A B CD E A 3 B 1 C 6 D 3 E 5 • Identify controllingpoints, cp • AC, AB, BD, DE • Identify controllingsequence • E4-1, D1, B2-3, A4-1 • Identify critical activities • … BD DEAC AB
  • 106. Example 2: 4 units 106 Unit 1 Unit 2 Unit 3 Unit 4 2 4 6 8 10 12 14 16 18 20 22 24 26 28 30 32 34 36 38 400 42 44 46 48 50 A B CD E A 3 B 1 C 6 D 3 E 5 • Identify controllingpoints, cp • AC, AB, BD, DE • Identify controllingsequence • E4-1, D1, B2-3, A4-1 • Identify critical activities • … BD DEAC AB
  • 107. Example 2: 4 units 107 Unit 1 Unit 2 Unit 3 Unit 4 2 4 6 8 10 12 14 16 18 20 22 24 26 28 30 32 34 36 38 400 42 44 46 48 50 A B CD E A 3 B 1 C 6 D 3 E 5 • Identify controllingpoints, cp • AC, AB, BD, DE • Identify controllingsequence • E4-1, D1, B2-3, A4-1 • Identify critical activities • E4-1, D1, B1 BD DEAC AB
  • 108. Repetitive Scheduling Method Example 3: 6 units 108 A 1 B 2 C 3 D 1 E 4 F 1
  • 109. Example 3: 6 units 109 Unit 1 Unit 3 Unit 6 2 4 6 8 10 12 14 16 18 20 22 24 26 28 30 32 34 36 38 400 42 44 46 48 50 Unit 2 Unit 4 Unit 5 • Identify controllingpoints, cp • ... • Identify controllingsequence • … • Identify critical activities • … A 1 B 2 C 3 D 1 E 4 F 1
  • 110. Example 3: 6 units 110 Unit 1 Unit 3 Unit 6 2 4 6 8 10 12 14 16 18 20 22 24 26 28 30 32 34 36 38 400 42 44 46 48 50 A Unit 2 Unit 4 Unit 5 • Identify controllingpoints, cp • ... • Identify controllingsequence • … • Identify critical activities • … A 1 B 2 C 3 D 1 E 4 F 1
  • 111. Example 3: 6 units 111 Unit 1 Unit 3 Unit 6 2 4 6 8 10 12 14 16 18 20 22 24 26 28 30 32 34 36 38 400 42 44 46 48 50 A B C Unit 2 Unit 4 Unit 5 • Identify controllingpoints, cp • ... • Identify controllingsequence • … • Identify critical activities • … A 1 B 2 C 3 D 1 E 4 F 1 AB, AC
  • 112. Example 3: 6 units 112 Unit 1 Unit 3 Unit 6 2 4 6 8 10 12 14 16 18 20 22 24 26 28 30 32 34 36 38 400 42 44 46 48 50 A B C Unit 2 Unit 4 Unit 5 • Identify controllingpoints, cp • ... • Identify controllingsequence • … • Identify critical activities • … A 1 B 2 C 3 D 1 E 4 F 1 AB, AC Determine possible cp from B and C to D
  • 113. Example 3: 6 units 113 Unit 1 Unit 3 Unit 6 2 4 6 8 10 12 14 16 18 20 22 24 26 28 30 32 34 36 38 400 42 44 46 48 50 A B C Unit 2 Unit 4 Unit 5 • Identify controllingpoints, cp • ... • Identify controllingsequence • … • Identify critical activities • … A 1 B 2 C 3 D 1 E 4 F 1 AB, AC Determine possible cp from B and C to D D Drag
  • 114. Example 3: 6 units 114 Unit 1 Unit 3 Unit 6 2 4 6 8 10 12 14 16 18 20 22 24 26 28 30 32 34 36 38 400 42 44 46 48 50 A B DC Unit 2 Unit 4 Unit 5 • Identify controllingpoints, cp • ... • Identify controllingsequence • … • Identify critical activities • … A 1 B 2 C 3 D 1 E 4 F 1 AB, AC CD
  • 115. Example 3: 6 units 115 Unit 1 Unit 3 Unit 6 2 4 6 8 10 12 14 16 18 20 22 24 26 28 30 32 34 36 38 400 42 44 46 48 50 A B DC E Unit 2 Unit 4 Unit 5 • Identify controllingpoints, cp • ... • Identify controllingsequence • … • Identify critical activities • … A 1 B 2 C 3 D 1 E 4 F 1 AB, AC DE CD
  • 116. Example 3: 6 units 116 Unit 1 Unit 3 Unit 6 2 4 6 8 10 12 14 16 18 20 22 24 26 28 30 32 34 36 38 400 42 44 46 48 50 A B DC E Unit 2 Unit 4 Unit 5 • Identify controllingpoints, cp • ... • Identify controllingsequence • … • Identify critical activities • … A 1 B 2 C 3 D 1 E 4 F 1 AB, AC DE CD F EF
  • 117. Example 3: 6 units 117 Unit 1 Unit 3 Unit 6 2 4 6 8 10 12 14 16 18 20 22 24 26 28 30 32 34 36 38 400 42 44 46 48 50 A B DC E Unit 2 Unit 4 Unit 5 • Identify controllingpoints, cp • AB, AC, CD, DE, EF • Identify controllingsequence • … • Identify critical activities • … A 1 B 2 C 3 D 1 E 4 F 1 AB, AC DE CD F EF
  • 118. Example 3: 6 units 118 Unit 1 Unit 3 Unit 6 2 4 6 8 10 12 14 16 18 20 22 24 26 28 30 32 34 36 38 400 42 44 46 48 50 A B DC E Unit 2 Unit 4 Unit 5 • Identify controllingpoints, cp • AB, AC, CD, DE, EF • Identify controllingsequence • … • Identify critical activities • … A 1 B 2 C 3 D 1 E 4 F 1 F AB, AC DE EFCD
  • 119. Example 3: 6 units 119 Unit 1 Unit 3 Unit 6 2 4 6 8 10 12 14 16 18 20 22 24 26 28 30 32 34 36 38 400 42 44 46 48 50 A B DC E Unit 2 Unit 4 Unit 5 • Identify controllingpoints, cp • AB, AC, CD, DE, EF • Identify controllingsequence • F6, E6-1, D2-5, C6-1, A1 • Identify critical activities • … A 1 B 2 C 3 D 1 E 4 F 1 F AB, AC DE EFCD
  • 120. Example 3: 6 units 120 Unit 1 Unit 3 Unit 6 2 4 6 8 10 12 14 16 18 20 22 24 26 28 30 32 34 36 38 400 42 44 46 48 50 A B DC E Unit 2 Unit 4 Unit 5 • Identify controllingpoints, cp • AB, AC, CD, DE, EF • Identify controllingsequence • F6, E6-1, D2-5, C6-1, A1 • Identify critical activities • … A 1 B 2 C 3 D 1 E 4 F 1 F AB, AC DE EFCD
  • 121. Example 3: 6 units 121 2 4 6 8 10 12 14 16 18 20 22 24 26 28 30 32 34 36 38 400 42 44 46 48 50 A B DC E Unit 1 Unit 3 Unit 6 Unit 2 Unit 4 Unit 5 • Identify controllingpoints, cp • AB, AC, CD, DE, EF • Identify controllingsequence • F6, E6-1, D2-5, C6-1, A1 • Identify critical activities • F6-F1, E6-1, D1 A 1 B 2 C 3 D 1 E 4 F 1 F AB, AC DE EFCD
  • 122. Repetitive Scheduling Method Example 4: 3 units 122 Act Predecessors Duration/Unit A 2 B A 3 C A 2 D B, C 4 E D 1 F D 4 G E, F 4
  • 123. Example 4: 3 units 123 Unit 1 Unit 2 Unit 3 2 4 6 8 10 12 14 16 18 20 22 24 26 28 300 Act Predecessors Duration/Unit A 2 B A 3 C A 2 D B, C 4 E D 1 F D 4 G E, F 4
  • 124. Example 4: 3 units 124 Unit 1 Unit 2 Unit 3 2 4 6 8 10 12 14 16 18 20 22 24 26 28 300 AC A C B AB, AC Act Predecessors Duration/Unit A 2 B A 3 C A 2 D B, C 4 E D 1 F D 4 G E, F 4
  • 125. Example 4: 3 units 125 Unit 1 Unit 2 Unit 3 2 4 6 8 10 12 14 16 18 20 22 24 26 28 300 AC A C B D AB, AC Drag Act Predecessors Duration/Unit A 2 B A 3 C A 2 D B, C 4 E D 1 F D 4 G E, F 4 Determine possible cp from B and C to D
  • 126. Example 4: 3 units 126 Unit 1 Unit 2 Unit 3 2 4 6 8 10 12 14 16 18 20 22 24 26 28 300 AC BD A C B D AB, AC Act Predecessors Duration/Unit A 2 B A 3 C A 2 D B, C 4 E D 1 F D 4 G E, F 4
  • 127. Example 4: 3 units 127 Unit 1 Unit 2 Unit 3 2 4 6 8 10 12 14 16 18 20 22 24 26 28 300 AC BD A C B D E F DE, DF AB, AC Act Predecessors Duration/Unit A 2 B A 3 C A 2 D B, C 4 E D 1 F D 4 G E, F 4 DF
  • 128. Example 4: 3 units 128 Unit 1 Unit 2 Unit 3 2 4 6 8 10 12 14 16 18 20 22 24 26 28 300 AC BD A C B D E F G DE, DF AB, AC Drag Act Predecessors Duration/Unit A 2 B A 3 C A 2 D B, C 4 E D 1 F D 4 G E, F 4 DF Determine possible cp from E and F to G
  • 129. Example 4: 3 units 129 Unit 1 Unit 2 Unit 3 2 4 6 8 10 12 14 16 18 20 22 24 26 28 300 AC BD A C B D E F G EG DE, DF AB, AC Act Predecessors Duration/Unit A 2 B A 3 C A 2 D B, C 4 E D 1 F D 4 G E, F 4 DF
  • 130. Example 4: 3 units 130 Unit 1 Unit 2 Unit 3 2 4 6 8 10 12 14 16 18 20 22 24 26 28 300 AC BD A C B D E F G EG DE, DF AB, AC Act Predecessors Duration/Unit A 2 B A 3 C A 2 D B, C 4 E D 1 F D 4 G E, F 4 DF Controlling Sequence: G3-1, E2, D3-1, B1, A1
  • 131. Example 4: 3 units 131 Unit 1 Unit 2 Unit 3 2 4 6 8 10 12 14 16 18 20 22 24 26 28 300 AC BD A C B D E F G EG DE, DF AB, AC Act Predecessors Duration/Unit A 2 B A 3 C A 2 D B, C 4 E D 1 F D 4 G E, F 4 DF Controlling Sequence: G3-1, E2, D3-1, B1, A1 Critical Activities: G3-1, E1
  • 132. Repetitive Scheduling Method Real Case Study: A Housing Project with 32 units 132
  • 133. Uthenthawai: Master of Construction Management #UthenMCMUthenthawai: Master of Construction Management #UthenMCM กรณีศึกษาการวางแผนเชิงปฏิบัติของโครงการหมู่บ้านจัดสรร ด้วยวิธีสายงานต่อเนื่อง สำหรับ การประชุมวิชาการวิศวกรรมโยธาแห่งชาติ ครั้งที่ 22 โดย ชำคริต ศรีสุวรรณรัตน์: หัวหน้ำประจำสำขำวิชำบริหำรงำนก่อสร้ำง ไพโรจน์ ฤกษ์อุดมสิน: นักศึกษำ #UthenMCM รุ่น 1
  • 134. Uthenthawai: Master of Construction Management #UthenMCM Contents 1. Introduction 2. Problems 3. Objectives 4. Literature Reviews 5. Research 6. Results 7. Conclusion 134
  • 135. Uthenthawai: Master of Construction Management #UthenMCM 1. Introduction • Construction Projects consist of repetitive units/activities. • Examples of Repetitive Units • Housing: each house • Condominium: each floor or room • Highway: each section • Repetitive activities are performed by sets of resources • Schedule resources to work continuously • Eliminate interruption and idle time 135
  • 136. Uthenthawai: Master of Construction Management #UthenMCM 2. Problems CPM Schedule with 745-week Idle Time RSM Schedule with 135-week Project Delay 136
  • 137. Uthenthawai: Master of Construction Management #UthenMCM 3. Objectives •Schedule resources to work continuously •Maintain project duration •Choose optimum number of resources •Practical in terms of Engineering, Management, Finance, and Marketing 137
  • 138. Uthenthawai: Master of Construction Management #UthenMCM 4. Literature Reviews: Methods •Repetitive Scheduling Method (RSM) •Linear Scheduling Method (LSM) •Vertical Production Method (VPM) •Line-of-balance Method (LOB) 138
  • 139. Uthenthawai: Master of Construction Management #UthenMCM 4. Literature Reviews: Types of Repetitive Activities Non-Repetitive Activities Non-Typical RepetitiveActivities Repetitive Activities with Soft-Logic Constraints 139
  • 140. Uthenthawai: Master of Construction Management #UthenMCM 4. Literature Reviews: Controlling Sequence from RSM 140
  • 141. Uthenthawai: Master of Construction Management #UthenMCM 5. Research: Schedules & Methods 1. CPM 2. RSM.N (Normal) 3. RSM.S (Soft-logic), switching construction orders between units/houses/models 4. RSM.E (Expedite), adding or reducing the number of workers in order to shorten project duration 5. RSM.P (Parallel), using multiple groups of crew to start a repetitive activity at the same time 6. RSM.F (Final), considering other aspects of the project such as management, financing, and marketing 141
  • 142. Uthenthawai: Master of Construction Management #UthenMCM 6. Results: CPM & RSM.N 1. CPM Schedule with 745-week Idle Time 2. RSM.N with 300-week Project Duration 142
  • 143. Uthenthawai: Master of Construction Management #UthenMCM 6. Results: RSM.S 3. RSM.S with 300-week Project Duration 143
  • 144. Uthenthawai: Master of Construction Management #UthenMCM 6. Results: RSM.E 3. RSM.S with 300-week Project Duration 4. RSM.Ewith 162-week Project Duration 144
  • 145. Uthenthawai: Master of Construction Management #UthenMCM 6. Results: RSM.P & RSM.F 5. RSM.P with 139-week Project Duration 6. RSM.F with 147-week Project Duration 145
  • 146. Uthenthawai: Master of Construction Management #UthenMCM 6. Results: Improvement & Comparison between CPM and RSM.F 146