SlideShare a Scribd company logo
Production
Scheduling
Production Planning Process
Process Planning
Strategic Capacity Planning
Aggregate Planning
Master Production Scheduling
Material Requirements Planning
Order Scheduling Weekly Workforce &
Customer Scheduling
Daily Workforce &
Customer Scheduling
Long
Range
Medium
Range
Short
Range
Manufacturing Services
Outline
 Scheduling
 Recap
 Sequencing rules
 Single resource
 Global
 Multiple resources
Scheduling
 Deals with the timing of operations
 Specifies when resources are needed to
produce a product or provide a service
 Helps us decide what order to perform jobs
 All organizations perform scheduling to
some extent…
Sequencing Rules
 Determine the order jobs are processed by
a resource
Types of Sequencing Rules
 Sequencing jobs at a single resource
 Sequencing jobs across multiple resources
Sequencing Rules (Single Resource)
 Local
 First Come First Served
 Last Come First Served
 Shortest Processing Time
 Longest Processing Time
 Earliest Due Date
 Global
 Slack Per Remaining Operation
 Critical Ratio
Last class
Sequencing Rules (Single Resource)
 Local
 First Come First Served
 Last Come First Served
 Shortest Processing Time
 Longest Processing Time
 Earliest Due Date
 Global
 Slack Per Remaining Operation
 Critical Ratio
Global Rules
 Consider more than current operation
 Look at work at other work centers that needs
to be completed before the job is done
Types of Sequencing Rules
 Sequencing jobs at a single resource
 Sequencing jobs across multiple resources
Scheduling Across Multiple Resources
 Previous rules considered scheduling
(sequencing) jobs at one resource
 How can we schedule jobs across
multiple resources??
Two resource problems
Suppose you work with a classmate, Kim on all projects
4 3 5 4 2
2 6 3 5 1
In each project you do the research, then Kim writes the report
Processing time (you):
Processing time (Kim):
You want to complete all projects asap
What should be the order
for the projects?
Two resource problems
Johnson’s Rule
4 3 5 4 2
2 6 3 5 1
1. Find the smallest processing time
• If its on the 1st machine, assign the task at the beginning
of the sequence and eliminate it from further consideration
Processing time (you):
Processing time (Kim):
What order should you
do the projects in?
• If its on the 2nd machine, assign the task at the end
of the sequence and eliminate it from further consideration
2. Repeat step 1 for all unassigned tasks
Sequences tasks to minimize makespan
Two resource problems
Johnson’s Rule
4 3 5 4 2
2 6 3 5 1
1. Find the smallest processing time
• If its on the 1st machine, assign the task at the beginning
of the sequence and eliminate it from further consideration
Processing time (you):
Processing time (Kim):
• If its on the 2nd machine, assign the task at the end
of the sequence and eliminate it from further consideration
2. Repeat step 1 for all unassigned tasks
Sequence
English
Sequences tasks to minimize makespan
Two resource problems
Johnson’s Rule
4 3 5 4 2
2 6 3 5 1
1. Find the smallest processing time
• If its on the 1st machine, assign the task at the beginning
of the sequence and eliminate it from further consideration
Processing time (you):
Processing time (Kim):
• If its on the 2nd machine, assign the task at the end
of the sequence and eliminate it from further consideration
2. Repeat step 1 for all unassigned tasks
Sequence
English
Management
Sequences tasks to minimize makespan
Two resource problems
Johnson’s Rule
4 3 5 4 2
2 6 3 5 1
1. Find the smallest processing time
• If its on the 1st machine, assign the task at the beginning
of the sequence and eliminate it from further consideration
Processing time (you):
Processing time (Kim):
• If its on the 2nd machine, assign the task at the end
of the sequence and eliminate it from further consideration
2. Repeat step 1 for all unassigned tasks
Sequence
English
Management
Finance
Sequences tasks to minimize makespan
Two resource problems
Johnson’s Rule
4 3 5 4 2
2 6 3 5 1
1. Find the smallest processing time
• If its on the 1st machine, assign the task at the beginning
of the sequence and eliminate it from further consideration
Processing time (you):
Processing time (Kim):
• If its on the 2nd machine, assign the task at the end
of the sequence and eliminate it from further consideration
2. Repeat step 1 for all unassigned tasks
Sequence
English
Management
Finance
Marketing
Sequences tasks to minimize makespan
Two resource problems
Johnson’s Rule
4 3 5 4 2
2 6 3 5 1
1. Find the smallest processing time
• If its on the 1st machine, assign the task at the beginning
of the sequence and eliminate it from further consideration
Processing time (you):
Processing time (Kim):
• If its on the 2nd machine, assign the task at the end
of the sequence and eliminate it from further consideration
2. Repeat step 1 for all unassigned tasks
Sequence
English
Management
Finance
Marketing
Accounting
Sequences tasks to minimize makespan
Two resource problems
Johnson’s Rule
4 3 5 4 2
2 6 3 5 1
Processing time (you):
Processing time (Kim):
Sequence
English
Management
Finance
Marketing
Accounting
You
Kim
Period 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20
Sequences tasks to minimize makespan
Two resource problems
Johnson’s Rule
4 3 5 4 2
2 6 3 5 1
Processing time (you):
Processing time (Kim):
Sequence
English
Management
Finance
Marketing
Accounting
You
Kim
Period 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20
Sequences tasks to minimize makespan
Two resource problems
Johnson’s Rule
4 3 5 4 2
2 6 3 5 1
Processing time (you):
Processing time (Kim):
Sequence
English
Management
Finance
Marketing
Accounting
You
Kim
Period 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20
Sequences tasks to minimize makespan
Two resource problems
Johnson’s Rule
4 3 5 4 2
2 6 3 5 1
Processing time (you):
Processing time (Kim):
Sequence
English
Management
Finance
Marketing
Accounting
You
Kim
Period 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20
Sequences tasks to minimize makespan
Two resource problems
Johnson’s Rule
4 3 5 4 2
2 6 3 5 1
Processing time (you):
Processing time (Kim):
Sequence
English
Management
Finance
Marketing
Accounting
You
Kim
Period 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20
Sequences tasks to minimize makespan
Two resource problems
Johnson’s Rule
4 3 5 4 2
2 6 3 5 1
Processing time (you):
Processing time (Kim):
Sequence
English
Management
Finance
Marketing
Accounting
You
Kim
Period 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20
Sequences tasks to minimize makespan
Two resource problems
Johnson’s Rule
4 3 5 4 2
2 6 3 5 1
Processing time (you):
Processing time (Kim):
Sequence
English
Management
Finance
Marketing
Accounting
You
Kim
Period 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20
Sequences tasks to minimize makespan
Two resource problems
Johnson’s Rule
4 3 5 4 2
2 6 3 5 1
Processing time (you):
Processing time (Kim):
Sequence
English
Management
Finance
Marketing
Accounting
You
Kim
Period 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20
Sequences tasks to minimize makespan
Two resource problems
Johnson’s Rule
4 3 5 4 2
2 6 3 5 1
Processing time (you):
Processing time (Kim):
Sequence
English
Management
Finance
Marketing
Accounting
You
Kim
Period 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20
Idle time
Sequences tasks to minimize makespan
More Than 2 Resources
 Optimal methods don’t exist to
minimize makespan
 Heuristics
 CDS Heuristic
Sequencing Rules
 Local
 FCFS
 LCFS
 SPT
 LPT
 EDD
 Global
 SPO
 CR
Single Resource Multiple Resources
 2 resources
 Johnson’s rule
 > 2 resources
 heuristics
When should you choose
one rule over another??
Guidelines for Selecting a Sequencing Rule
1. SPT most useful when shop is highly congested
2. Use SPO for periods of normal activity
3. Use EDD when only small tardiness values can be
tolerated
4. Use FCFS when operating at low-capacity levels
Employee Scheduling
 Labor is very flexible resource
 Scheduling workforce is
complicated repetitive task
 Heuristics commonly used
We’ll cover one simple one today…
Employee Scheduling Heuristic
Let N = no. of workers available
Di = demand for workers on day i
1. Assign the first N - D1 workers day 1 off.
Assign the next N - D2 workers day 2 off.
Continue in a similar manner until all days are scheduled.
2. If number of workdays for full time employee < 5, assign
remaining workdays so consecutive days off are possible.
• Assign any remaining work to part-time employees.
3. If consecutive days off are desired, consider switching
schedules among days with the same demand requirements.
Example
DAY OF WEEK M T W TH F SA SU
MIN NO. OF
WORKERS REQUIRED 3 3 4 3 4 5 3
Taylor
Smith
Simpson
Allen
Dickerson
DAY OF WEEK M T W TH F SA SU
MIN NO. OF
WORKERS REQUIRED 3 3 4 3 4 5 3
Taylor
Smith
Simpson
Allen
Dickerson
N = 5
D1 = D2 = D3 = D4 = D5 = D6 = D7 =
N – D1 = 5 – 3 = 2
X = day working
O = day off 1. Assign the first N - D1 workers day 1 off.
Assign the next N - D2 workers day 2 off.
Continue in a similar manner until all days are have been scheduled.
DAY OF WEEK M T W TH F SA SU
MIN NO. OF
WORKERS REQUIRED 3 3 4 3 4 5 3
Taylor O X X O X X X
Smith O X X O X X X
Simpson X O X X O X X
Allen X O X X X X O
Dickerson X X O X X X O
1. Assign the first N - D1 workers day 1 off.
Assign the next N - D2 workers day 2 off.
Continue in a similar manner until all days are have been scheduled.
N – D2 = 5 – 3 = 2
DAY OF WEEK M T W TH F SA SU
MIN NO. OF
WORKERS REQUIRED 3 3 4 3 4 5 3
Taylor O X X O X X X
Smith O X X O X X X
Simpson X O X X O X X
Allen X O X X X X O
Dickerson X X O X X X O
5
5
5
5
5
Work
days
2. If number of workdays for full time employee < 5,
assign remaining workdays so consecutive days off are possible.
DAY OF WEEK M T W TH F SA SU
MIN NO. OF
WORKERS REQUIRED 3 3 4 3 4 5 3
Taylor O X X O X X X
Smith O X X O X X X
Simpson X O X X O X X
Allen X O X X X X O
Dickerson X X O X X X O
3. If consecutive days off are desired, consider switching
schedules among days with the same demand requirements.
Completed schedule satisfies requirements
but has no consecutive days off.
DAY OF WEEK M T W TH F SA SU
MIN NO. OF
WORKERS REQUIRED 3 3 4 3 4 5 3
Taylor O X X O X X X
Smith O X X O X X X
Simpson X O X X O X X
Allen X O X X X X O
Dickerson X X O X X X O
3. If consecutive days off are desired, consider switching
schedules among days with the same demand requirements.
DAY OF WEEK M T W TH F SA SU
MIN NO. OF
WORKERS REQUIRED 3 3 4 3 4 5 3
Taylor O O X X X X X
Smith O O X X X X X
Simpson X X X O O X X
Allen X X X O X X O
Dickerson X X O X X X O
The revised schedule satisfies requirements
with consecutive days off for most employees.
3. If consecutive days off are desired, consider switching
schedules among days with the same demand requirements.

More Related Content

Similar to production_scheduling_1.ppt

Sequencing Jobs with Priority Rules.pptx
Sequencing Jobs with Priority Rules.pptxSequencing Jobs with Priority Rules.pptx
Sequencing Jobs with Priority Rules.pptx
E Concepts
 
Scheduling
SchedulingScheduling
Thinking fast and performing with focus public
Thinking fast and performing with focus   publicThinking fast and performing with focus   public
Thinking fast and performing with focus public
Ted Steinmann
 
scheduling-sequencing-rules.pptx
scheduling-sequencing-rules.pptxscheduling-sequencing-rules.pptx
scheduling-sequencing-rules.pptx
MowazzemHossain1
 
Guideline for retrospective & sprint planning
Guideline for retrospective & sprint planningGuideline for retrospective & sprint planning
Guideline for retrospective & sprint planning
Arata Fujimura
 
Let your tasks flow like water!
Let your tasks flow like water!Let your tasks flow like water!
Let your tasks flow like water!
Antonio De Marinis
 
Operations Research_18ME735_module 5 sequencing notes.pdf
Operations Research_18ME735_module 5 sequencing notes.pdfOperations Research_18ME735_module 5 sequencing notes.pdf
Operations Research_18ME735_module 5 sequencing notes.pdf
RoopaDNDandally
 
Scheduling
SchedulingScheduling
Scheduling
ahmad bassiouny
 
Scheduling
SchedulingScheduling
Scheduling
ahmad bassiouny
 
Scheduling
SchedulingScheduling
Scheduling
ahmad bassiouny
 
Chap017 Scheduling Edit
Chap017 Scheduling EditChap017 Scheduling Edit
Chap017 Scheduling EditRicky Muchtar
 
SCHEDULING
SCHEDULING  SCHEDULING
SCHEDULING
SupanShah2
 
Mark Richardson's Time Management Workshop
Mark Richardson's Time Management WorkshopMark Richardson's Time Management Workshop
Mark Richardson's Time Management Workshop
Surefire Local
 
Scrum for anyone - A 2-page introduction including an example of application
Scrum for anyone - A 2-page introduction including an example of applicationScrum for anyone - A 2-page introduction including an example of application
Scrum for anyone - A 2-page introduction including an example of application
CollectiveKnowledge
 
PROJECT-ANALYSIS-TOOL-PPT.pptx
PROJECT-ANALYSIS-TOOL-PPT.pptxPROJECT-ANALYSIS-TOOL-PPT.pptx
PROJECT-ANALYSIS-TOOL-PPT.pptx
PHOEBEANNEARTECHE1
 
Cycle time analysis
Cycle time analysisCycle time analysis
Cycle time analysis
OnlineAudio Training
 
Business Administration
Business Administration Business Administration
Business Administration
mwalsh2015
 
Job Shop Scheduling.pptx
Job Shop Scheduling.pptxJob Shop Scheduling.pptx
Job Shop Scheduling.pptx
SyedAmirIqbal3
 
Iasi CodeCamp 20 april 2013 Agile Estimations and Planning - Cornel Fatulescu
Iasi CodeCamp 20 april 2013 Agile Estimations and Planning - Cornel FatulescuIasi CodeCamp 20 april 2013 Agile Estimations and Planning - Cornel Fatulescu
Iasi CodeCamp 20 april 2013 Agile Estimations and Planning - Cornel FatulescuCodecamp Romania
 

Similar to production_scheduling_1.ppt (20)

Sequencing Jobs with Priority Rules.pptx
Sequencing Jobs with Priority Rules.pptxSequencing Jobs with Priority Rules.pptx
Sequencing Jobs with Priority Rules.pptx
 
Scheduling
SchedulingScheduling
Scheduling
 
Thinking fast and performing with focus public
Thinking fast and performing with focus   publicThinking fast and performing with focus   public
Thinking fast and performing with focus public
 
scheduling-sequencing-rules.pptx
scheduling-sequencing-rules.pptxscheduling-sequencing-rules.pptx
scheduling-sequencing-rules.pptx
 
Guideline for retrospective & sprint planning
Guideline for retrospective & sprint planningGuideline for retrospective & sprint planning
Guideline for retrospective & sprint planning
 
chapter 17.pdf
chapter 17.pdfchapter 17.pdf
chapter 17.pdf
 
Let your tasks flow like water!
Let your tasks flow like water!Let your tasks flow like water!
Let your tasks flow like water!
 
Operations Research_18ME735_module 5 sequencing notes.pdf
Operations Research_18ME735_module 5 sequencing notes.pdfOperations Research_18ME735_module 5 sequencing notes.pdf
Operations Research_18ME735_module 5 sequencing notes.pdf
 
Scheduling
SchedulingScheduling
Scheduling
 
Scheduling
SchedulingScheduling
Scheduling
 
Scheduling
SchedulingScheduling
Scheduling
 
Chap017 Scheduling Edit
Chap017 Scheduling EditChap017 Scheduling Edit
Chap017 Scheduling Edit
 
SCHEDULING
SCHEDULING  SCHEDULING
SCHEDULING
 
Mark Richardson's Time Management Workshop
Mark Richardson's Time Management WorkshopMark Richardson's Time Management Workshop
Mark Richardson's Time Management Workshop
 
Scrum for anyone - A 2-page introduction including an example of application
Scrum for anyone - A 2-page introduction including an example of applicationScrum for anyone - A 2-page introduction including an example of application
Scrum for anyone - A 2-page introduction including an example of application
 
PROJECT-ANALYSIS-TOOL-PPT.pptx
PROJECT-ANALYSIS-TOOL-PPT.pptxPROJECT-ANALYSIS-TOOL-PPT.pptx
PROJECT-ANALYSIS-TOOL-PPT.pptx
 
Cycle time analysis
Cycle time analysisCycle time analysis
Cycle time analysis
 
Business Administration
Business Administration Business Administration
Business Administration
 
Job Shop Scheduling.pptx
Job Shop Scheduling.pptxJob Shop Scheduling.pptx
Job Shop Scheduling.pptx
 
Iasi CodeCamp 20 april 2013 Agile Estimations and Planning - Cornel Fatulescu
Iasi CodeCamp 20 april 2013 Agile Estimations and Planning - Cornel FatulescuIasi CodeCamp 20 april 2013 Agile Estimations and Planning - Cornel Fatulescu
Iasi CodeCamp 20 april 2013 Agile Estimations and Planning - Cornel Fatulescu
 

More from VELMURUGANM19

scheduling_1.ppt
scheduling_1.pptscheduling_1.ppt
scheduling_1.ppt
VELMURUGANM19
 
schedulingandsequencing-140424065526-phpapp02__1_.ppt
schedulingandsequencing-140424065526-phpapp02__1_.pptschedulingandsequencing-140424065526-phpapp02__1_.ppt
schedulingandsequencing-140424065526-phpapp02__1_.ppt
VELMURUGANM19
 
planning-_process_and_techniques.ppt
planning-_process_and_techniques.pptplanning-_process_and_techniques.ppt
planning-_process_and_techniques.ppt
VELMURUGANM19
 
process_planning.pptx
process_planning.pptxprocess_planning.pptx
process_planning.pptx
VELMURUGANM19
 
planning__types_of_plans.ppt
planning__types_of_plans.pptplanning__types_of_plans.ppt
planning__types_of_plans.ppt
VELMURUGANM19
 
PPC -UNIT-II.ppt
PPC -UNIT-II.pptPPC -UNIT-II.ppt
PPC -UNIT-II.ppt
VELMURUGANM19
 

More from VELMURUGANM19 (6)

scheduling_1.ppt
scheduling_1.pptscheduling_1.ppt
scheduling_1.ppt
 
schedulingandsequencing-140424065526-phpapp02__1_.ppt
schedulingandsequencing-140424065526-phpapp02__1_.pptschedulingandsequencing-140424065526-phpapp02__1_.ppt
schedulingandsequencing-140424065526-phpapp02__1_.ppt
 
planning-_process_and_techniques.ppt
planning-_process_and_techniques.pptplanning-_process_and_techniques.ppt
planning-_process_and_techniques.ppt
 
process_planning.pptx
process_planning.pptxprocess_planning.pptx
process_planning.pptx
 
planning__types_of_plans.ppt
planning__types_of_plans.pptplanning__types_of_plans.ppt
planning__types_of_plans.ppt
 
PPC -UNIT-II.ppt
PPC -UNIT-II.pptPPC -UNIT-II.ppt
PPC -UNIT-II.ppt
 

Recently uploaded

HYDROPOWER - Hydroelectric power generation
HYDROPOWER - Hydroelectric power generationHYDROPOWER - Hydroelectric power generation
HYDROPOWER - Hydroelectric power generation
Robbie Edward Sayers
 
weather web application report.pdf
weather web application report.pdfweather web application report.pdf
weather web application report.pdf
Pratik Pawar
 
ethical hacking in wireless-hacking1.ppt
ethical hacking in wireless-hacking1.pptethical hacking in wireless-hacking1.ppt
ethical hacking in wireless-hacking1.ppt
Jayaprasanna4
 
TECHNICAL TRAINING MANUAL GENERAL FAMILIARIZATION COURSE
TECHNICAL TRAINING MANUAL   GENERAL FAMILIARIZATION COURSETECHNICAL TRAINING MANUAL   GENERAL FAMILIARIZATION COURSE
TECHNICAL TRAINING MANUAL GENERAL FAMILIARIZATION COURSE
DuvanRamosGarzon1
 
ethical hacking-mobile hacking methods.ppt
ethical hacking-mobile hacking methods.pptethical hacking-mobile hacking methods.ppt
ethical hacking-mobile hacking methods.ppt
Jayaprasanna4
 
Water Industry Process Automation and Control Monthly - May 2024.pdf
Water Industry Process Automation and Control Monthly - May 2024.pdfWater Industry Process Automation and Control Monthly - May 2024.pdf
Water Industry Process Automation and Control Monthly - May 2024.pdf
Water Industry Process Automation & Control
 
Student information management system project report ii.pdf
Student information management system project report ii.pdfStudent information management system project report ii.pdf
Student information management system project report ii.pdf
Kamal Acharya
 
在线办理(ANU毕业证书)澳洲国立大学毕业证录取通知书一模一样
在线办理(ANU毕业证书)澳洲国立大学毕业证录取通知书一模一样在线办理(ANU毕业证书)澳洲国立大学毕业证录取通知书一模一样
在线办理(ANU毕业证书)澳洲国立大学毕业证录取通知书一模一样
obonagu
 
power quality voltage fluctuation UNIT - I.pptx
power quality voltage fluctuation UNIT - I.pptxpower quality voltage fluctuation UNIT - I.pptx
power quality voltage fluctuation UNIT - I.pptx
ViniHema
 
Design and Analysis of Algorithms-DP,Backtracking,Graphs,B&B
Design and Analysis of Algorithms-DP,Backtracking,Graphs,B&BDesign and Analysis of Algorithms-DP,Backtracking,Graphs,B&B
Design and Analysis of Algorithms-DP,Backtracking,Graphs,B&B
Sreedhar Chowdam
 
Cosmetic shop management system project report.pdf
Cosmetic shop management system project report.pdfCosmetic shop management system project report.pdf
Cosmetic shop management system project report.pdf
Kamal Acharya
 
Final project report on grocery store management system..pdf
Final project report on grocery store management system..pdfFinal project report on grocery store management system..pdf
Final project report on grocery store management system..pdf
Kamal Acharya
 
Standard Reomte Control Interface - Neometrix
Standard Reomte Control Interface - NeometrixStandard Reomte Control Interface - Neometrix
Standard Reomte Control Interface - Neometrix
Neometrix_Engineering_Pvt_Ltd
 
Quality defects in TMT Bars, Possible causes and Potential Solutions.
Quality defects in TMT Bars, Possible causes and Potential Solutions.Quality defects in TMT Bars, Possible causes and Potential Solutions.
Quality defects in TMT Bars, Possible causes and Potential Solutions.
PrashantGoswami42
 
Hybrid optimization of pumped hydro system and solar- Engr. Abdul-Azeez.pdf
Hybrid optimization of pumped hydro system and solar- Engr. Abdul-Azeez.pdfHybrid optimization of pumped hydro system and solar- Engr. Abdul-Azeez.pdf
Hybrid optimization of pumped hydro system and solar- Engr. Abdul-Azeez.pdf
fxintegritypublishin
 
The Benefits and Techniques of Trenchless Pipe Repair.pdf
The Benefits and Techniques of Trenchless Pipe Repair.pdfThe Benefits and Techniques of Trenchless Pipe Repair.pdf
The Benefits and Techniques of Trenchless Pipe Repair.pdf
Pipe Restoration Solutions
 
J.Yang, ICLR 2024, MLILAB, KAIST AI.pdf
J.Yang,  ICLR 2024, MLILAB, KAIST AI.pdfJ.Yang,  ICLR 2024, MLILAB, KAIST AI.pdf
J.Yang, ICLR 2024, MLILAB, KAIST AI.pdf
MLILAB
 
Courier management system project report.pdf
Courier management system project report.pdfCourier management system project report.pdf
Courier management system project report.pdf
Kamal Acharya
 
NO1 Uk best vashikaran specialist in delhi vashikaran baba near me online vas...
NO1 Uk best vashikaran specialist in delhi vashikaran baba near me online vas...NO1 Uk best vashikaran specialist in delhi vashikaran baba near me online vas...
NO1 Uk best vashikaran specialist in delhi vashikaran baba near me online vas...
Amil Baba Dawood bangali
 
MCQ Soil mechanics questions (Soil shear strength).pdf
MCQ Soil mechanics questions (Soil shear strength).pdfMCQ Soil mechanics questions (Soil shear strength).pdf
MCQ Soil mechanics questions (Soil shear strength).pdf
Osamah Alsalih
 

Recently uploaded (20)

HYDROPOWER - Hydroelectric power generation
HYDROPOWER - Hydroelectric power generationHYDROPOWER - Hydroelectric power generation
HYDROPOWER - Hydroelectric power generation
 
weather web application report.pdf
weather web application report.pdfweather web application report.pdf
weather web application report.pdf
 
ethical hacking in wireless-hacking1.ppt
ethical hacking in wireless-hacking1.pptethical hacking in wireless-hacking1.ppt
ethical hacking in wireless-hacking1.ppt
 
TECHNICAL TRAINING MANUAL GENERAL FAMILIARIZATION COURSE
TECHNICAL TRAINING MANUAL   GENERAL FAMILIARIZATION COURSETECHNICAL TRAINING MANUAL   GENERAL FAMILIARIZATION COURSE
TECHNICAL TRAINING MANUAL GENERAL FAMILIARIZATION COURSE
 
ethical hacking-mobile hacking methods.ppt
ethical hacking-mobile hacking methods.pptethical hacking-mobile hacking methods.ppt
ethical hacking-mobile hacking methods.ppt
 
Water Industry Process Automation and Control Monthly - May 2024.pdf
Water Industry Process Automation and Control Monthly - May 2024.pdfWater Industry Process Automation and Control Monthly - May 2024.pdf
Water Industry Process Automation and Control Monthly - May 2024.pdf
 
Student information management system project report ii.pdf
Student information management system project report ii.pdfStudent information management system project report ii.pdf
Student information management system project report ii.pdf
 
在线办理(ANU毕业证书)澳洲国立大学毕业证录取通知书一模一样
在线办理(ANU毕业证书)澳洲国立大学毕业证录取通知书一模一样在线办理(ANU毕业证书)澳洲国立大学毕业证录取通知书一模一样
在线办理(ANU毕业证书)澳洲国立大学毕业证录取通知书一模一样
 
power quality voltage fluctuation UNIT - I.pptx
power quality voltage fluctuation UNIT - I.pptxpower quality voltage fluctuation UNIT - I.pptx
power quality voltage fluctuation UNIT - I.pptx
 
Design and Analysis of Algorithms-DP,Backtracking,Graphs,B&B
Design and Analysis of Algorithms-DP,Backtracking,Graphs,B&BDesign and Analysis of Algorithms-DP,Backtracking,Graphs,B&B
Design and Analysis of Algorithms-DP,Backtracking,Graphs,B&B
 
Cosmetic shop management system project report.pdf
Cosmetic shop management system project report.pdfCosmetic shop management system project report.pdf
Cosmetic shop management system project report.pdf
 
Final project report on grocery store management system..pdf
Final project report on grocery store management system..pdfFinal project report on grocery store management system..pdf
Final project report on grocery store management system..pdf
 
Standard Reomte Control Interface - Neometrix
Standard Reomte Control Interface - NeometrixStandard Reomte Control Interface - Neometrix
Standard Reomte Control Interface - Neometrix
 
Quality defects in TMT Bars, Possible causes and Potential Solutions.
Quality defects in TMT Bars, Possible causes and Potential Solutions.Quality defects in TMT Bars, Possible causes and Potential Solutions.
Quality defects in TMT Bars, Possible causes and Potential Solutions.
 
Hybrid optimization of pumped hydro system and solar- Engr. Abdul-Azeez.pdf
Hybrid optimization of pumped hydro system and solar- Engr. Abdul-Azeez.pdfHybrid optimization of pumped hydro system and solar- Engr. Abdul-Azeez.pdf
Hybrid optimization of pumped hydro system and solar- Engr. Abdul-Azeez.pdf
 
The Benefits and Techniques of Trenchless Pipe Repair.pdf
The Benefits and Techniques of Trenchless Pipe Repair.pdfThe Benefits and Techniques of Trenchless Pipe Repair.pdf
The Benefits and Techniques of Trenchless Pipe Repair.pdf
 
J.Yang, ICLR 2024, MLILAB, KAIST AI.pdf
J.Yang,  ICLR 2024, MLILAB, KAIST AI.pdfJ.Yang,  ICLR 2024, MLILAB, KAIST AI.pdf
J.Yang, ICLR 2024, MLILAB, KAIST AI.pdf
 
Courier management system project report.pdf
Courier management system project report.pdfCourier management system project report.pdf
Courier management system project report.pdf
 
NO1 Uk best vashikaran specialist in delhi vashikaran baba near me online vas...
NO1 Uk best vashikaran specialist in delhi vashikaran baba near me online vas...NO1 Uk best vashikaran specialist in delhi vashikaran baba near me online vas...
NO1 Uk best vashikaran specialist in delhi vashikaran baba near me online vas...
 
MCQ Soil mechanics questions (Soil shear strength).pdf
MCQ Soil mechanics questions (Soil shear strength).pdfMCQ Soil mechanics questions (Soil shear strength).pdf
MCQ Soil mechanics questions (Soil shear strength).pdf
 

production_scheduling_1.ppt

  • 2. Production Planning Process Process Planning Strategic Capacity Planning Aggregate Planning Master Production Scheduling Material Requirements Planning Order Scheduling Weekly Workforce & Customer Scheduling Daily Workforce & Customer Scheduling Long Range Medium Range Short Range Manufacturing Services
  • 3. Outline  Scheduling  Recap  Sequencing rules  Single resource  Global  Multiple resources
  • 4. Scheduling  Deals with the timing of operations  Specifies when resources are needed to produce a product or provide a service  Helps us decide what order to perform jobs  All organizations perform scheduling to some extent…
  • 5. Sequencing Rules  Determine the order jobs are processed by a resource
  • 6. Types of Sequencing Rules  Sequencing jobs at a single resource  Sequencing jobs across multiple resources
  • 7. Sequencing Rules (Single Resource)  Local  First Come First Served  Last Come First Served  Shortest Processing Time  Longest Processing Time  Earliest Due Date  Global  Slack Per Remaining Operation  Critical Ratio Last class
  • 8. Sequencing Rules (Single Resource)  Local  First Come First Served  Last Come First Served  Shortest Processing Time  Longest Processing Time  Earliest Due Date  Global  Slack Per Remaining Operation  Critical Ratio
  • 9. Global Rules  Consider more than current operation  Look at work at other work centers that needs to be completed before the job is done
  • 10. Types of Sequencing Rules  Sequencing jobs at a single resource  Sequencing jobs across multiple resources
  • 11. Scheduling Across Multiple Resources  Previous rules considered scheduling (sequencing) jobs at one resource  How can we schedule jobs across multiple resources??
  • 12. Two resource problems Suppose you work with a classmate, Kim on all projects 4 3 5 4 2 2 6 3 5 1 In each project you do the research, then Kim writes the report Processing time (you): Processing time (Kim): You want to complete all projects asap What should be the order for the projects?
  • 13. Two resource problems Johnson’s Rule 4 3 5 4 2 2 6 3 5 1 1. Find the smallest processing time • If its on the 1st machine, assign the task at the beginning of the sequence and eliminate it from further consideration Processing time (you): Processing time (Kim): What order should you do the projects in? • If its on the 2nd machine, assign the task at the end of the sequence and eliminate it from further consideration 2. Repeat step 1 for all unassigned tasks Sequences tasks to minimize makespan
  • 14. Two resource problems Johnson’s Rule 4 3 5 4 2 2 6 3 5 1 1. Find the smallest processing time • If its on the 1st machine, assign the task at the beginning of the sequence and eliminate it from further consideration Processing time (you): Processing time (Kim): • If its on the 2nd machine, assign the task at the end of the sequence and eliminate it from further consideration 2. Repeat step 1 for all unassigned tasks Sequence English Sequences tasks to minimize makespan
  • 15. Two resource problems Johnson’s Rule 4 3 5 4 2 2 6 3 5 1 1. Find the smallest processing time • If its on the 1st machine, assign the task at the beginning of the sequence and eliminate it from further consideration Processing time (you): Processing time (Kim): • If its on the 2nd machine, assign the task at the end of the sequence and eliminate it from further consideration 2. Repeat step 1 for all unassigned tasks Sequence English Management Sequences tasks to minimize makespan
  • 16. Two resource problems Johnson’s Rule 4 3 5 4 2 2 6 3 5 1 1. Find the smallest processing time • If its on the 1st machine, assign the task at the beginning of the sequence and eliminate it from further consideration Processing time (you): Processing time (Kim): • If its on the 2nd machine, assign the task at the end of the sequence and eliminate it from further consideration 2. Repeat step 1 for all unassigned tasks Sequence English Management Finance Sequences tasks to minimize makespan
  • 17. Two resource problems Johnson’s Rule 4 3 5 4 2 2 6 3 5 1 1. Find the smallest processing time • If its on the 1st machine, assign the task at the beginning of the sequence and eliminate it from further consideration Processing time (you): Processing time (Kim): • If its on the 2nd machine, assign the task at the end of the sequence and eliminate it from further consideration 2. Repeat step 1 for all unassigned tasks Sequence English Management Finance Marketing Sequences tasks to minimize makespan
  • 18. Two resource problems Johnson’s Rule 4 3 5 4 2 2 6 3 5 1 1. Find the smallest processing time • If its on the 1st machine, assign the task at the beginning of the sequence and eliminate it from further consideration Processing time (you): Processing time (Kim): • If its on the 2nd machine, assign the task at the end of the sequence and eliminate it from further consideration 2. Repeat step 1 for all unassigned tasks Sequence English Management Finance Marketing Accounting Sequences tasks to minimize makespan
  • 19. Two resource problems Johnson’s Rule 4 3 5 4 2 2 6 3 5 1 Processing time (you): Processing time (Kim): Sequence English Management Finance Marketing Accounting You Kim Period 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 Sequences tasks to minimize makespan
  • 20. Two resource problems Johnson’s Rule 4 3 5 4 2 2 6 3 5 1 Processing time (you): Processing time (Kim): Sequence English Management Finance Marketing Accounting You Kim Period 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 Sequences tasks to minimize makespan
  • 21. Two resource problems Johnson’s Rule 4 3 5 4 2 2 6 3 5 1 Processing time (you): Processing time (Kim): Sequence English Management Finance Marketing Accounting You Kim Period 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 Sequences tasks to minimize makespan
  • 22. Two resource problems Johnson’s Rule 4 3 5 4 2 2 6 3 5 1 Processing time (you): Processing time (Kim): Sequence English Management Finance Marketing Accounting You Kim Period 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 Sequences tasks to minimize makespan
  • 23. Two resource problems Johnson’s Rule 4 3 5 4 2 2 6 3 5 1 Processing time (you): Processing time (Kim): Sequence English Management Finance Marketing Accounting You Kim Period 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 Sequences tasks to minimize makespan
  • 24. Two resource problems Johnson’s Rule 4 3 5 4 2 2 6 3 5 1 Processing time (you): Processing time (Kim): Sequence English Management Finance Marketing Accounting You Kim Period 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 Sequences tasks to minimize makespan
  • 25. Two resource problems Johnson’s Rule 4 3 5 4 2 2 6 3 5 1 Processing time (you): Processing time (Kim): Sequence English Management Finance Marketing Accounting You Kim Period 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 Sequences tasks to minimize makespan
  • 26. Two resource problems Johnson’s Rule 4 3 5 4 2 2 6 3 5 1 Processing time (you): Processing time (Kim): Sequence English Management Finance Marketing Accounting You Kim Period 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 Sequences tasks to minimize makespan
  • 27. Two resource problems Johnson’s Rule 4 3 5 4 2 2 6 3 5 1 Processing time (you): Processing time (Kim): Sequence English Management Finance Marketing Accounting You Kim Period 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 Idle time Sequences tasks to minimize makespan
  • 28. More Than 2 Resources  Optimal methods don’t exist to minimize makespan  Heuristics  CDS Heuristic
  • 29. Sequencing Rules  Local  FCFS  LCFS  SPT  LPT  EDD  Global  SPO  CR Single Resource Multiple Resources  2 resources  Johnson’s rule  > 2 resources  heuristics When should you choose one rule over another??
  • 30. Guidelines for Selecting a Sequencing Rule 1. SPT most useful when shop is highly congested 2. Use SPO for periods of normal activity 3. Use EDD when only small tardiness values can be tolerated 4. Use FCFS when operating at low-capacity levels
  • 31. Employee Scheduling  Labor is very flexible resource  Scheduling workforce is complicated repetitive task  Heuristics commonly used We’ll cover one simple one today…
  • 32. Employee Scheduling Heuristic Let N = no. of workers available Di = demand for workers on day i 1. Assign the first N - D1 workers day 1 off. Assign the next N - D2 workers day 2 off. Continue in a similar manner until all days are scheduled. 2. If number of workdays for full time employee < 5, assign remaining workdays so consecutive days off are possible. • Assign any remaining work to part-time employees. 3. If consecutive days off are desired, consider switching schedules among days with the same demand requirements.
  • 33. Example DAY OF WEEK M T W TH F SA SU MIN NO. OF WORKERS REQUIRED 3 3 4 3 4 5 3 Taylor Smith Simpson Allen Dickerson
  • 34. DAY OF WEEK M T W TH F SA SU MIN NO. OF WORKERS REQUIRED 3 3 4 3 4 5 3 Taylor Smith Simpson Allen Dickerson N = 5 D1 = D2 = D3 = D4 = D5 = D6 = D7 = N – D1 = 5 – 3 = 2 X = day working O = day off 1. Assign the first N - D1 workers day 1 off. Assign the next N - D2 workers day 2 off. Continue in a similar manner until all days are have been scheduled.
  • 35. DAY OF WEEK M T W TH F SA SU MIN NO. OF WORKERS REQUIRED 3 3 4 3 4 5 3 Taylor O X X O X X X Smith O X X O X X X Simpson X O X X O X X Allen X O X X X X O Dickerson X X O X X X O 1. Assign the first N - D1 workers day 1 off. Assign the next N - D2 workers day 2 off. Continue in a similar manner until all days are have been scheduled. N – D2 = 5 – 3 = 2
  • 36. DAY OF WEEK M T W TH F SA SU MIN NO. OF WORKERS REQUIRED 3 3 4 3 4 5 3 Taylor O X X O X X X Smith O X X O X X X Simpson X O X X O X X Allen X O X X X X O Dickerson X X O X X X O 5 5 5 5 5 Work days 2. If number of workdays for full time employee < 5, assign remaining workdays so consecutive days off are possible.
  • 37. DAY OF WEEK M T W TH F SA SU MIN NO. OF WORKERS REQUIRED 3 3 4 3 4 5 3 Taylor O X X O X X X Smith O X X O X X X Simpson X O X X O X X Allen X O X X X X O Dickerson X X O X X X O 3. If consecutive days off are desired, consider switching schedules among days with the same demand requirements. Completed schedule satisfies requirements but has no consecutive days off.
  • 38. DAY OF WEEK M T W TH F SA SU MIN NO. OF WORKERS REQUIRED 3 3 4 3 4 5 3 Taylor O X X O X X X Smith O X X O X X X Simpson X O X X O X X Allen X O X X X X O Dickerson X X O X X X O 3. If consecutive days off are desired, consider switching schedules among days with the same demand requirements.
  • 39. DAY OF WEEK M T W TH F SA SU MIN NO. OF WORKERS REQUIRED 3 3 4 3 4 5 3 Taylor O O X X X X X Smith O O X X X X X Simpson X X X O O X X Allen X X X O X X O Dickerson X X O X X X O The revised schedule satisfies requirements with consecutive days off for most employees. 3. If consecutive days off are desired, consider switching schedules among days with the same demand requirements.