SlideShare a Scribd company logo
Under the Guidance of: Dr. Aswath M.U.
Presented by- Rahul Das Biswas
USN: 1BI14CSE14,
M.Tech (Structural Engineering)
Contents
 Introduction
 Advantages
 IS Recommendations
Materials
Prefabrication Systems
 Types according to IS
Design Requirement as per IS
Progressive Collapse
Design of Ties
 Design of Vertical Pillars (Walls, Diaphragms, Cores)
Frame installation
Conclusion
References
Introduction
 WHAT ?
WHY ??
HOW ???
“What”
Precast:
 Produced in Factories
 Transported to Site
Assembled at Site
“Why”
Advantages of Precast:
Partial or total saving of materials
Multiple using of shuttering
Better accuracy of workmanship
Less Man Power Required
Interruption in concreting can be omitted
“Why”
Advantages of Precast:
 Fewer expansion joints
 High capacity
 Shorter construction time
 Independent of adverse weather conditions
during construction
 Continuing erection in winter time until -20 °C
“Why”
Advantages of Precast:
 Opportunities for good architecture
 Reduced energy consumption
 Safety in construction
 Low shrinkage with high strength
 High modulus of elasticity
 Very little micro cracks
“Why”
Advantages of Precast:
 Resistance to chemical attack
 Toughness and impact resistance
 Volume stability
 Durability against chloride attack
 Reduced maintenance cost
 Higher Strength at earlier ages and low heat of hydration
“How”
From Structural Engineering Point of view:
 Material
 Aspect
 Type of Construction
 Design (With all Safety Concern)
Detailing
IS CODES TO BE FOLLOWED
 IS 15916: Precast Construction
 IS 875: Design Loads
 IS 456: Concrete
 IS 1893 and IS 13920: Seismic Design
Characteristics of Material
Recommended by IS: 15916: 2011
• Easy Availability
• Light- Weight
• Thermal Insulation Property
• Easy Workability
• Durability
Characteristics of Material
Recommended by IS: 15916: 2011
• Non-combustibility
• Sound insulation
• Easy assembly and compatibility to form a complete
unit
• Economical
• Any other special requirement required for particular
application
Aspects to be considered as per the
Recommendation of IS: 15916: 2011
 Effective utilization of spaces
 Straight and simple walling scheme
 Limited sizes and numbers of components
 Limited opening in bearing walls
Aspects to be considered as per the
Recommendation of IS: 15916: 2011
 Regulated locations of partitions
 Standardized service and stair units
 Limited sizes of doors and windows with
regulated positions
 Structural clarity and efficiency
Aspects to be considered as per the
Recommendation of IS: 15916: 2011
 Suitability for adoption in low rise and high rise
building
 Ease of manufacturing, storing and transporting
 Speed and ease of erection and
 Simple jointing system
Types of Precast System according to
IS: 15916: 2011
Prefabrication
System
Open
Prefabrication
System
Partial
Prefabrication
System
Full
Prefabrication
System
Large Panel
Prefabrication
System
Staircase
Systems
Precast Floors Precast Walls
Box Type
Construction
Design Requirement as per IS: 15916: 2011
Progressive Collapse
(A Major Threat to Safety of Structure)
Collapse or Failure of the major part
Due to the damage of small areas or
Failure of single element
Precaution: Against Progressive Collapse
1) All buildings should be capable of safely
resisting the minimum horizontal load of 1.5% of
characteristic dead load applied at each floor or
roof level simultaneously.
2) All Buildings Shall Be Provided With Effective
Horizontal Ties
1) Around The Periphery
2) Internally (In Both Directions) &
3) To Columns & Walls.
3) All Buildings of Five or More Storeys Shall Be
Provided With Vertical Ties.
Precaution: Against Progressive Collapse
Design of Ties
(Peripheral Ties)
At each floor and roof level an effectively continuous tie should be
provided within 1.2 m of the edge of the building or within the
perimeter wall.
The tie should be capable to resisting a tensile force of Ft equal to 60 kN
or (20 + 4N) kN whichever is less, where N is the number of storeys
(including basement).
Design of Ties
(Internal Ties)
These are to be provided at each floor and roof level in two directions
approximately at right angles. Ties should be effectively continuous
throughout their length and be anchored to the peripheral tie at both
ends, unless continuing as horizontal ties to columns or walls.
Design of Ties
(Internal Ties)
• The tensile strength, in kN per meter width shall be
the greater of-
• gk + qk = Avg. characteristic D.L. + L.L in kN/m2
• lr = Greater of-
• The distance between the centre of columns
• Frames or walls supporting any two adjacent floor spans in the
direction of the tie under consideration.
Design of Ties
(Internal Ties)
The bars providing these ties may be distributed evenly in the
slabs or may be grouped at or in the beams, walls or other
appropriate positions but at spacings generally not greater
than 1.5 lr.
Design of Ties
(Horizontal ties to column and wall)
• All external load-bearing members such as columns and
walls should be anchored or tied horizontally into the
structure at each floor and roof level. The design force
for the tie is to be greater of-
 a) 2 Ft kN or ls × Ft × 2.5 kN, whichever is less for a column
or for each metre length if there is a wall. ls is the floor to
ceiling height, in meter.
 b) 3 percent of the total ultimate vertical load in the column
or wall at that level.
• For corner columns, this tie force should be provided in
each of two directions approximately at right angles.
Design of Ties
(Vertical ties)
 Should be provided for buildings of five or more
storeys
Each column and each wall carrying vertical load
should be tied continuously from the foundation to the
roof level. The reinforcement provided is required only
to resist a tensile force equal to the maximum design
ultimate load (dead and imposed) received from any
one storey.
In situation where provision of vertical ties cannot be
done, the element should be considered to be removed
and the surrounding members designed to bridge the
gap.
Design of Vertical Pillars
(Walls, Diaphragms, Cores)
 Indian Standards for Designing Precast is
unavailable
 Adopt any code of practice which is-
 Safe
 Durable
 Economical
 Reliable from Past Experience
 Methods of mounting precast structures used in Russia will
be discussed
Primary Load-bearing Members of the Building
Optimal Configuration
 The frame members to securely perform their
functions without “extra” efforts. This means that
the columns operate only for compression, floor
structures operate only for bending, with no
forces in the plane of the slab (the membrane
group of efforts), pylons take horizontal forces
ensuring the necessary rigidity of the building.
Optimal Configuration
• The principle of concentration of material is
observed. To reduce the material consumption the
load should be transmitted through the minimum
number of elements.
• The main feature of the framework is the ability
to ensure the integrated operation of all its
elements: columns, pylons, floor slabs, foundation
slab, piled and/or soil foundation. Proper use of
these features can improve the design
characteristics of the building frame while
reducing the consumption of its materials.
Rules of the Pylons Distribution
(Rule No. 1)
• All of the pylons should not be
intersected by straight lines on
which they are rested at one
point
• All of the pylons should not be
parallel
Building plan (slab & pylons)
Rules of the Pylons Distribution
(Rule No. 2)
 The pylon should be sufficiently hard with a height of the
cross section equal to 1/10 – 1/5 of the building height.
With a smaller size the pylon will be more flexible and
will transmit a significant portion of the horizontal load
onto the columns or originate the need for more pylons.
 If several flat diaphragms are connected to one core, the
height of their cross section can be reduced by virtue of a
more rigid joint operation with respect to the total
cumulative individual work.
 It is necessary to strive for the minimum number of
pylons in the building.
Rules of the Pylons Distribution
(Rule No. 3)
Determining efforts in the plane of the slab
aab 5.26 
Rules of the Pylons Distribution
(Rule No. 4)
 If one looks at the aggregate of all the diaphragms of the
building combined with floor structures, it is possible to
find the shear center of the building. If the shear center
does not coincide with the center of gravity, the building
will have additional bending stresses. If the resultant
wind load does not pass through the shear center, the
building will be subject to additional twisting forces. The
configuration in which all three centers coincide will be
optimal. The easiest way to achieve is to prepare a
symmetrical in the two axes building plan with a
symmetrical arrangement of the pylons.
Frame installation
(Column)
Schemes Of Installation of Multi-story Columns Using A Set of Individual Installation
and Mounting Devices and Tooling
a — the location of columns and accessories, b — securing columns by knees, c — clamp for
securing knees in the column; 1 — foundation socket, 2 — readymade mount, 3 — column, 4 —
clamp 5 — knee, 6 — drawbar of the knee, 7 — wedges, 8 — anchoring device, 9 — crimping
rope
Frame installation
(Cross beams)
Cross beam installation: a — applying an axial mark
on the column pillar; b — installing cross beam; c —
column pillar alignment
Frame installation
(Pylons)
Installation of interior walls — diaphragm plates — in a framed building: a —
installation, b — temporary fastening; 1 — knee-piece, 2 — diaphragm with a
cantilever replacing a collar beam, 3 — a universal sling, 4 — movable L-
clamp with a rack.
Frame installation
(Slab panels)
Laying bracing (spacing) (а) and lintel (b) floor slab panels
Conclusion
 Considering its huge advantage, Technology
should be adopted in India
 Safety should be the 1st concern
 Past Hazards should be analyzed and
precautions to avoid it should be taken
 Indian Standard Code required for Design
References
• http://en.wikipedia.org/wiki/Precast_concrete
• IS: 15916: 2011
• IS: 13920: 1993
• “DESIGN RULES FOR PRECAST CONCRETE:
VERTICAL PILLARS (WALLS, DIAPHRAGMS,
CORES)” By- Mark P. Son & Denis V. Konin, Redecon
2014, Bangalore
• “Design and Construction of Multi-Storey Residential
Buildings with Precast Concrete” By- Dr. H S Lai ,
Redecon 2014, Bangalore
Design of Precast Elements

More Related Content

What's hot

Composite construction or Composite Structure/Frame
Composite construction or Composite Structure/FrameComposite construction or Composite Structure/Frame
Composite construction or Composite Structure/Frame
Abdul Rahman
 
footing
footingfooting
footingillpa
 
Basic principles of design for rcc building
Basic principles of design for rcc buildingBasic principles of design for rcc building
Basic principles of design for rcc buildinghlksd
 
Pre cast vs cast-in-situ concrete
Pre cast vs cast-in-situ concretePre cast vs cast-in-situ concrete
Pre cast vs cast-in-situ concrete
Rajat Nainwal
 
Jacketing
JacketingJacketing
Jacketing
SHAIKH ARSHAD
 
Scaffolding and formwork ppt
Scaffolding and  formwork pptScaffolding and  formwork ppt
Scaffolding and formwork ppt
gayathrysatheesan1
 
Construction Methods & Sequence
Construction  Methods & SequenceConstruction  Methods & Sequence
Construction Methods & Sequence
David H Moloney
 
Details of RCC Building
Details of RCC BuildingDetails of RCC Building
Details of RCC Building
ppt_master
 
Building Construction 8. formworks and scaffoldings
Building Construction 8. formworks and scaffoldingsBuilding Construction 8. formworks and scaffoldings
Building Construction 8. formworks and scaffoldingsHamdija Velagic
 
Shuttering (Formwork)
Shuttering (Formwork)Shuttering (Formwork)
Shuttering (Formwork)
Andhra University
 
Etabs BY Subash Pathak
Etabs BY Subash PathakEtabs BY Subash Pathak
Etabs BY Subash Pathak
Subash Pathak
 
Precast concrete construction
Precast concrete constructionPrecast concrete construction
Precast concrete construction
JenilPatel22
 
PRECAST BUILDING SYSTEM
PRECAST BUILDING SYSTEMPRECAST BUILDING SYSTEM
PRECAST BUILDING SYSTEMSagar Shah
 
Design of lifts & escalators
Design of lifts & escalatorsDesign of lifts & escalators
Design of lifts & escalators
Shubham Arora
 
Shear walls
Shear wallsShear walls
Shear walls
Rajat Nainwal
 
Prestressed concrete
Prestressed concretePrestressed concrete
Prestressed concrete
Udisha15
 
Precast construction
Precast constructionPrecast construction
Precast construction
Divya Vishnoi
 
Design of industrial roof truss
Design of industrial roof truss Design of industrial roof truss
Design of industrial roof truss
Sudhir Gayake
 
Superstructure construction
Superstructure constructionSuperstructure construction
Superstructure construction
mohdasrimohdhasim
 

What's hot (20)

Composite construction or Composite Structure/Frame
Composite construction or Composite Structure/FrameComposite construction or Composite Structure/Frame
Composite construction or Composite Structure/Frame
 
footing
footingfooting
footing
 
Basic principles of design for rcc building
Basic principles of design for rcc buildingBasic principles of design for rcc building
Basic principles of design for rcc building
 
Pre cast vs cast-in-situ concrete
Pre cast vs cast-in-situ concretePre cast vs cast-in-situ concrete
Pre cast vs cast-in-situ concrete
 
Jacketing
JacketingJacketing
Jacketing
 
Scaffolding and formwork ppt
Scaffolding and  formwork pptScaffolding and  formwork ppt
Scaffolding and formwork ppt
 
Is code 456 2000
Is code 456 2000Is code 456 2000
Is code 456 2000
 
Construction Methods & Sequence
Construction  Methods & SequenceConstruction  Methods & Sequence
Construction Methods & Sequence
 
Details of RCC Building
Details of RCC BuildingDetails of RCC Building
Details of RCC Building
 
Building Construction 8. formworks and scaffoldings
Building Construction 8. formworks and scaffoldingsBuilding Construction 8. formworks and scaffoldings
Building Construction 8. formworks and scaffoldings
 
Shuttering (Formwork)
Shuttering (Formwork)Shuttering (Formwork)
Shuttering (Formwork)
 
Etabs BY Subash Pathak
Etabs BY Subash PathakEtabs BY Subash Pathak
Etabs BY Subash Pathak
 
Precast concrete construction
Precast concrete constructionPrecast concrete construction
Precast concrete construction
 
PRECAST BUILDING SYSTEM
PRECAST BUILDING SYSTEMPRECAST BUILDING SYSTEM
PRECAST BUILDING SYSTEM
 
Design of lifts & escalators
Design of lifts & escalatorsDesign of lifts & escalators
Design of lifts & escalators
 
Shear walls
Shear wallsShear walls
Shear walls
 
Prestressed concrete
Prestressed concretePrestressed concrete
Prestressed concrete
 
Precast construction
Precast constructionPrecast construction
Precast construction
 
Design of industrial roof truss
Design of industrial roof truss Design of industrial roof truss
Design of industrial roof truss
 
Superstructure construction
Superstructure constructionSuperstructure construction
Superstructure construction
 

Similar to Design of Precast Elements

Prefabricated components
Prefabricated componentsPrefabricated components
Prefabricated components
Sofia Rajesh
 
Multistorey building
Multistorey buildingMultistorey building
Multistorey building
Rahul
 
Seismic Response of Structure with Single Core
Seismic Response of Structure with Single CoreSeismic Response of Structure with Single Core
Seismic Response of Structure with Single Core
ijtsrd
 
Seismic study and performance of 30 storey high rise building with beam slab,...
Seismic study and performance of 30 storey high rise building with beam slab,...Seismic study and performance of 30 storey high rise building with beam slab,...
Seismic study and performance of 30 storey high rise building with beam slab,...
IRJET Journal
 
STRUCTURAL COST COMPARISON OF LOW RISE BUILDING HAVING MOMENT RESISTING FRAME...
STRUCTURAL COST COMPARISON OF LOW RISE BUILDING HAVING MOMENT RESISTING FRAME...STRUCTURAL COST COMPARISON OF LOW RISE BUILDING HAVING MOMENT RESISTING FRAME...
STRUCTURAL COST COMPARISON OF LOW RISE BUILDING HAVING MOMENT RESISTING FRAME...
IAEME Publication
 
STRUCTURAL COST COMPARISON OF LOW RISE BUILDING HAVING MOMENT RESISTING FRAME...
STRUCTURAL COST COMPARISON OF LOW RISE BUILDING HAVING MOMENT RESISTING FRAME...STRUCTURAL COST COMPARISON OF LOW RISE BUILDING HAVING MOMENT RESISTING FRAME...
STRUCTURAL COST COMPARISON OF LOW RISE BUILDING HAVING MOMENT RESISTING FRAME...
IAEME Publication
 
Overview of IS 16700:2023 (by priyansh verma)
Overview of IS 16700:2023 (by priyansh verma)Overview of IS 16700:2023 (by priyansh verma)
Overview of IS 16700:2023 (by priyansh verma)
Priyansh
 
PRE-CAST-CONSTRUCTION-Expertcivil.pptx
PRE-CAST-CONSTRUCTION-Expertcivil.pptxPRE-CAST-CONSTRUCTION-Expertcivil.pptx
PRE-CAST-CONSTRUCTION-Expertcivil.pptx
atiulla001
 
IRJET- Comparative Study of Flat Slab and Conventional Slab Structure wit...
IRJET-  	  Comparative Study of Flat Slab and Conventional Slab Structure wit...IRJET-  	  Comparative Study of Flat Slab and Conventional Slab Structure wit...
IRJET- Comparative Study of Flat Slab and Conventional Slab Structure wit...
IRJET Journal
 
Pre enginnered buildings master-builder_july08, pp.48-62
Pre enginnered buildings master-builder_july08, pp.48-62Pre enginnered buildings master-builder_july08, pp.48-62
Pre enginnered buildings master-builder_july08, pp.48-62hlksd
 
L34 multistorey building
L34 multistorey buildingL34 multistorey building
L34 multistorey building
Dr. OmPrakash
 
Structural systems and aerodynamic in multi stoery buildings
Structural systems and aerodynamic in multi stoery buildingsStructural systems and aerodynamic in multi stoery buildings
Structural systems and aerodynamic in multi stoery buildings
Manoj Kumar
 
PRE-CAST-CONSTRUCTION.pptx
PRE-CAST-CONSTRUCTION.pptxPRE-CAST-CONSTRUCTION.pptx
PRE-CAST-CONSTRUCTION.pptx
Vinayak247538
 
Shear wall design - muros de corte Etabs
Shear wall design - muros de corte EtabsShear wall design - muros de corte Etabs
Shear wall design - muros de corte Etabs
castigadordekill
 
36405231_seismic_design_steps_153.ppt
36405231_seismic_design_steps_153.ppt36405231_seismic_design_steps_153.ppt
36405231_seismic_design_steps_153.ppt
IrshadKhan97473
 
Seismic design steps
Seismic design stepsSeismic design steps
Seismic design steps
lalithkumar1451
 
SEISMIC DESIGN STEPS.ppt
SEISMIC DESIGN STEPS.pptSEISMIC DESIGN STEPS.ppt
SEISMIC DESIGN STEPS.ppt
AteeqRahman26
 
PRE-CAST-CONSTRUCTION.pptx
PRE-CAST-CONSTRUCTION.pptxPRE-CAST-CONSTRUCTION.pptx
PRE-CAST-CONSTRUCTION.pptx
LokeswarSaha1
 

Similar to Design of Precast Elements (20)

Prefabricated components
Prefabricated componentsPrefabricated components
Prefabricated components
 
Multistorey building
Multistorey buildingMultistorey building
Multistorey building
 
Seismic Response of Structure with Single Core
Seismic Response of Structure with Single CoreSeismic Response of Structure with Single Core
Seismic Response of Structure with Single Core
 
Seismic study and performance of 30 storey high rise building with beam slab,...
Seismic study and performance of 30 storey high rise building with beam slab,...Seismic study and performance of 30 storey high rise building with beam slab,...
Seismic study and performance of 30 storey high rise building with beam slab,...
 
STRUCTURAL COST COMPARISON OF LOW RISE BUILDING HAVING MOMENT RESISTING FRAME...
STRUCTURAL COST COMPARISON OF LOW RISE BUILDING HAVING MOMENT RESISTING FRAME...STRUCTURAL COST COMPARISON OF LOW RISE BUILDING HAVING MOMENT RESISTING FRAME...
STRUCTURAL COST COMPARISON OF LOW RISE BUILDING HAVING MOMENT RESISTING FRAME...
 
STRUCTURAL COST COMPARISON OF LOW RISE BUILDING HAVING MOMENT RESISTING FRAME...
STRUCTURAL COST COMPARISON OF LOW RISE BUILDING HAVING MOMENT RESISTING FRAME...STRUCTURAL COST COMPARISON OF LOW RISE BUILDING HAVING MOMENT RESISTING FRAME...
STRUCTURAL COST COMPARISON OF LOW RISE BUILDING HAVING MOMENT RESISTING FRAME...
 
Overview of IS 16700:2023 (by priyansh verma)
Overview of IS 16700:2023 (by priyansh verma)Overview of IS 16700:2023 (by priyansh verma)
Overview of IS 16700:2023 (by priyansh verma)
 
Tall buildings
Tall buildingsTall buildings
Tall buildings
 
PRE-CAST-CONSTRUCTION-Expertcivil.pptx
PRE-CAST-CONSTRUCTION-Expertcivil.pptxPRE-CAST-CONSTRUCTION-Expertcivil.pptx
PRE-CAST-CONSTRUCTION-Expertcivil.pptx
 
IRJET- Comparative Study of Flat Slab and Conventional Slab Structure wit...
IRJET-  	  Comparative Study of Flat Slab and Conventional Slab Structure wit...IRJET-  	  Comparative Study of Flat Slab and Conventional Slab Structure wit...
IRJET- Comparative Study of Flat Slab and Conventional Slab Structure wit...
 
40 analysis
40 analysis40 analysis
40 analysis
 
Pre enginnered buildings master-builder_july08, pp.48-62
Pre enginnered buildings master-builder_july08, pp.48-62Pre enginnered buildings master-builder_july08, pp.48-62
Pre enginnered buildings master-builder_july08, pp.48-62
 
L34 multistorey building
L34 multistorey buildingL34 multistorey building
L34 multistorey building
 
Structural systems and aerodynamic in multi stoery buildings
Structural systems and aerodynamic in multi stoery buildingsStructural systems and aerodynamic in multi stoery buildings
Structural systems and aerodynamic in multi stoery buildings
 
PRE-CAST-CONSTRUCTION.pptx
PRE-CAST-CONSTRUCTION.pptxPRE-CAST-CONSTRUCTION.pptx
PRE-CAST-CONSTRUCTION.pptx
 
Shear wall design - muros de corte Etabs
Shear wall design - muros de corte EtabsShear wall design - muros de corte Etabs
Shear wall design - muros de corte Etabs
 
36405231_seismic_design_steps_153.ppt
36405231_seismic_design_steps_153.ppt36405231_seismic_design_steps_153.ppt
36405231_seismic_design_steps_153.ppt
 
Seismic design steps
Seismic design stepsSeismic design steps
Seismic design steps
 
SEISMIC DESIGN STEPS.ppt
SEISMIC DESIGN STEPS.pptSEISMIC DESIGN STEPS.ppt
SEISMIC DESIGN STEPS.ppt
 
PRE-CAST-CONSTRUCTION.pptx
PRE-CAST-CONSTRUCTION.pptxPRE-CAST-CONSTRUCTION.pptx
PRE-CAST-CONSTRUCTION.pptx
 

Recently uploaded

Heap Sort (SS).ppt FOR ENGINEERING GRADUATES, BCA, MCA, MTECH, BSC STUDENTS
Heap Sort (SS).ppt FOR ENGINEERING GRADUATES, BCA, MCA, MTECH, BSC STUDENTSHeap Sort (SS).ppt FOR ENGINEERING GRADUATES, BCA, MCA, MTECH, BSC STUDENTS
Heap Sort (SS).ppt FOR ENGINEERING GRADUATES, BCA, MCA, MTECH, BSC STUDENTS
Soumen Santra
 
AKS UNIVERSITY Satna Final Year Project By OM Hardaha.pdf
AKS UNIVERSITY Satna Final Year Project By OM Hardaha.pdfAKS UNIVERSITY Satna Final Year Project By OM Hardaha.pdf
AKS UNIVERSITY Satna Final Year Project By OM Hardaha.pdf
SamSarthak3
 
Forklift Classes Overview by Intella Parts
Forklift Classes Overview by Intella PartsForklift Classes Overview by Intella Parts
Forklift Classes Overview by Intella Parts
Intella Parts
 
Student information management system project report ii.pdf
Student information management system project report ii.pdfStudent information management system project report ii.pdf
Student information management system project report ii.pdf
Kamal Acharya
 
Railway Signalling Principles Edition 3.pdf
Railway Signalling Principles Edition 3.pdfRailway Signalling Principles Edition 3.pdf
Railway Signalling Principles Edition 3.pdf
TeeVichai
 
DESIGN A COTTON SEED SEPARATION MACHINE.docx
DESIGN A COTTON SEED SEPARATION MACHINE.docxDESIGN A COTTON SEED SEPARATION MACHINE.docx
DESIGN A COTTON SEED SEPARATION MACHINE.docx
FluxPrime1
 
space technology lecture notes on satellite
space technology lecture notes on satellitespace technology lecture notes on satellite
space technology lecture notes on satellite
ongomchris
 
weather web application report.pdf
weather web application report.pdfweather web application report.pdf
weather web application report.pdf
Pratik Pawar
 
一比一原版(SFU毕业证)西蒙菲莎大学毕业证成绩单如何办理
一比一原版(SFU毕业证)西蒙菲莎大学毕业证成绩单如何办理一比一原版(SFU毕业证)西蒙菲莎大学毕业证成绩单如何办理
一比一原版(SFU毕业证)西蒙菲莎大学毕业证成绩单如何办理
bakpo1
 
CW RADAR, FMCW RADAR, FMCW ALTIMETER, AND THEIR PARAMETERS
CW RADAR, FMCW RADAR, FMCW ALTIMETER, AND THEIR PARAMETERSCW RADAR, FMCW RADAR, FMCW ALTIMETER, AND THEIR PARAMETERS
CW RADAR, FMCW RADAR, FMCW ALTIMETER, AND THEIR PARAMETERS
veerababupersonal22
 
DfMAy 2024 - key insights and contributions
DfMAy 2024 - key insights and contributionsDfMAy 2024 - key insights and contributions
DfMAy 2024 - key insights and contributions
gestioneergodomus
 
Unbalanced Three Phase Systems and circuits.pptx
Unbalanced Three Phase Systems and circuits.pptxUnbalanced Three Phase Systems and circuits.pptx
Unbalanced Three Phase Systems and circuits.pptx
ChristineTorrepenida1
 
CME397 Surface Engineering- Professional Elective
CME397 Surface Engineering- Professional ElectiveCME397 Surface Engineering- Professional Elective
CME397 Surface Engineering- Professional Elective
karthi keyan
 
Final project report on grocery store management system..pdf
Final project report on grocery store management system..pdfFinal project report on grocery store management system..pdf
Final project report on grocery store management system..pdf
Kamal Acharya
 
Pile Foundation by Venkatesh Taduvai (Sub Geotechnical Engineering II)-conver...
Pile Foundation by Venkatesh Taduvai (Sub Geotechnical Engineering II)-conver...Pile Foundation by Venkatesh Taduvai (Sub Geotechnical Engineering II)-conver...
Pile Foundation by Venkatesh Taduvai (Sub Geotechnical Engineering II)-conver...
AJAYKUMARPUND1
 
Cosmetic shop management system project report.pdf
Cosmetic shop management system project report.pdfCosmetic shop management system project report.pdf
Cosmetic shop management system project report.pdf
Kamal Acharya
 
ML for identifying fraud using open blockchain data.pptx
ML for identifying fraud using open blockchain data.pptxML for identifying fraud using open blockchain data.pptx
ML for identifying fraud using open blockchain data.pptx
Vijay Dialani, PhD
 
Water Industry Process Automation and Control Monthly - May 2024.pdf
Water Industry Process Automation and Control Monthly - May 2024.pdfWater Industry Process Automation and Control Monthly - May 2024.pdf
Water Industry Process Automation and Control Monthly - May 2024.pdf
Water Industry Process Automation & Control
 
14 Template Contractual Notice - EOT Application
14 Template Contractual Notice - EOT Application14 Template Contractual Notice - EOT Application
14 Template Contractual Notice - EOT Application
SyedAbiiAzazi1
 
Hierarchical Digital Twin of a Naval Power System
Hierarchical Digital Twin of a Naval Power SystemHierarchical Digital Twin of a Naval Power System
Hierarchical Digital Twin of a Naval Power System
Kerry Sado
 

Recently uploaded (20)

Heap Sort (SS).ppt FOR ENGINEERING GRADUATES, BCA, MCA, MTECH, BSC STUDENTS
Heap Sort (SS).ppt FOR ENGINEERING GRADUATES, BCA, MCA, MTECH, BSC STUDENTSHeap Sort (SS).ppt FOR ENGINEERING GRADUATES, BCA, MCA, MTECH, BSC STUDENTS
Heap Sort (SS).ppt FOR ENGINEERING GRADUATES, BCA, MCA, MTECH, BSC STUDENTS
 
AKS UNIVERSITY Satna Final Year Project By OM Hardaha.pdf
AKS UNIVERSITY Satna Final Year Project By OM Hardaha.pdfAKS UNIVERSITY Satna Final Year Project By OM Hardaha.pdf
AKS UNIVERSITY Satna Final Year Project By OM Hardaha.pdf
 
Forklift Classes Overview by Intella Parts
Forklift Classes Overview by Intella PartsForklift Classes Overview by Intella Parts
Forklift Classes Overview by Intella Parts
 
Student information management system project report ii.pdf
Student information management system project report ii.pdfStudent information management system project report ii.pdf
Student information management system project report ii.pdf
 
Railway Signalling Principles Edition 3.pdf
Railway Signalling Principles Edition 3.pdfRailway Signalling Principles Edition 3.pdf
Railway Signalling Principles Edition 3.pdf
 
DESIGN A COTTON SEED SEPARATION MACHINE.docx
DESIGN A COTTON SEED SEPARATION MACHINE.docxDESIGN A COTTON SEED SEPARATION MACHINE.docx
DESIGN A COTTON SEED SEPARATION MACHINE.docx
 
space technology lecture notes on satellite
space technology lecture notes on satellitespace technology lecture notes on satellite
space technology lecture notes on satellite
 
weather web application report.pdf
weather web application report.pdfweather web application report.pdf
weather web application report.pdf
 
一比一原版(SFU毕业证)西蒙菲莎大学毕业证成绩单如何办理
一比一原版(SFU毕业证)西蒙菲莎大学毕业证成绩单如何办理一比一原版(SFU毕业证)西蒙菲莎大学毕业证成绩单如何办理
一比一原版(SFU毕业证)西蒙菲莎大学毕业证成绩单如何办理
 
CW RADAR, FMCW RADAR, FMCW ALTIMETER, AND THEIR PARAMETERS
CW RADAR, FMCW RADAR, FMCW ALTIMETER, AND THEIR PARAMETERSCW RADAR, FMCW RADAR, FMCW ALTIMETER, AND THEIR PARAMETERS
CW RADAR, FMCW RADAR, FMCW ALTIMETER, AND THEIR PARAMETERS
 
DfMAy 2024 - key insights and contributions
DfMAy 2024 - key insights and contributionsDfMAy 2024 - key insights and contributions
DfMAy 2024 - key insights and contributions
 
Unbalanced Three Phase Systems and circuits.pptx
Unbalanced Three Phase Systems and circuits.pptxUnbalanced Three Phase Systems and circuits.pptx
Unbalanced Three Phase Systems and circuits.pptx
 
CME397 Surface Engineering- Professional Elective
CME397 Surface Engineering- Professional ElectiveCME397 Surface Engineering- Professional Elective
CME397 Surface Engineering- Professional Elective
 
Final project report on grocery store management system..pdf
Final project report on grocery store management system..pdfFinal project report on grocery store management system..pdf
Final project report on grocery store management system..pdf
 
Pile Foundation by Venkatesh Taduvai (Sub Geotechnical Engineering II)-conver...
Pile Foundation by Venkatesh Taduvai (Sub Geotechnical Engineering II)-conver...Pile Foundation by Venkatesh Taduvai (Sub Geotechnical Engineering II)-conver...
Pile Foundation by Venkatesh Taduvai (Sub Geotechnical Engineering II)-conver...
 
Cosmetic shop management system project report.pdf
Cosmetic shop management system project report.pdfCosmetic shop management system project report.pdf
Cosmetic shop management system project report.pdf
 
ML for identifying fraud using open blockchain data.pptx
ML for identifying fraud using open blockchain data.pptxML for identifying fraud using open blockchain data.pptx
ML for identifying fraud using open blockchain data.pptx
 
Water Industry Process Automation and Control Monthly - May 2024.pdf
Water Industry Process Automation and Control Monthly - May 2024.pdfWater Industry Process Automation and Control Monthly - May 2024.pdf
Water Industry Process Automation and Control Monthly - May 2024.pdf
 
14 Template Contractual Notice - EOT Application
14 Template Contractual Notice - EOT Application14 Template Contractual Notice - EOT Application
14 Template Contractual Notice - EOT Application
 
Hierarchical Digital Twin of a Naval Power System
Hierarchical Digital Twin of a Naval Power SystemHierarchical Digital Twin of a Naval Power System
Hierarchical Digital Twin of a Naval Power System
 

Design of Precast Elements

  • 1. Under the Guidance of: Dr. Aswath M.U. Presented by- Rahul Das Biswas USN: 1BI14CSE14, M.Tech (Structural Engineering)
  • 2. Contents  Introduction  Advantages  IS Recommendations Materials Prefabrication Systems  Types according to IS Design Requirement as per IS Progressive Collapse Design of Ties  Design of Vertical Pillars (Walls, Diaphragms, Cores) Frame installation Conclusion References
  • 4. “What” Precast:  Produced in Factories  Transported to Site Assembled at Site
  • 5. “Why” Advantages of Precast: Partial or total saving of materials Multiple using of shuttering Better accuracy of workmanship Less Man Power Required Interruption in concreting can be omitted
  • 6. “Why” Advantages of Precast:  Fewer expansion joints  High capacity  Shorter construction time  Independent of adverse weather conditions during construction  Continuing erection in winter time until -20 °C
  • 7. “Why” Advantages of Precast:  Opportunities for good architecture  Reduced energy consumption  Safety in construction  Low shrinkage with high strength  High modulus of elasticity  Very little micro cracks
  • 8. “Why” Advantages of Precast:  Resistance to chemical attack  Toughness and impact resistance  Volume stability  Durability against chloride attack  Reduced maintenance cost  Higher Strength at earlier ages and low heat of hydration
  • 9. “How” From Structural Engineering Point of view:  Material  Aspect  Type of Construction  Design (With all Safety Concern) Detailing
  • 10. IS CODES TO BE FOLLOWED  IS 15916: Precast Construction  IS 875: Design Loads  IS 456: Concrete  IS 1893 and IS 13920: Seismic Design
  • 11. Characteristics of Material Recommended by IS: 15916: 2011 • Easy Availability • Light- Weight • Thermal Insulation Property • Easy Workability • Durability
  • 12. Characteristics of Material Recommended by IS: 15916: 2011 • Non-combustibility • Sound insulation • Easy assembly and compatibility to form a complete unit • Economical • Any other special requirement required for particular application
  • 13. Aspects to be considered as per the Recommendation of IS: 15916: 2011  Effective utilization of spaces  Straight and simple walling scheme  Limited sizes and numbers of components  Limited opening in bearing walls
  • 14. Aspects to be considered as per the Recommendation of IS: 15916: 2011  Regulated locations of partitions  Standardized service and stair units  Limited sizes of doors and windows with regulated positions  Structural clarity and efficiency
  • 15. Aspects to be considered as per the Recommendation of IS: 15916: 2011  Suitability for adoption in low rise and high rise building  Ease of manufacturing, storing and transporting  Speed and ease of erection and  Simple jointing system
  • 16. Types of Precast System according to IS: 15916: 2011 Prefabrication System Open Prefabrication System Partial Prefabrication System Full Prefabrication System Large Panel Prefabrication System Staircase Systems Precast Floors Precast Walls Box Type Construction
  • 17. Design Requirement as per IS: 15916: 2011 Progressive Collapse (A Major Threat to Safety of Structure) Collapse or Failure of the major part Due to the damage of small areas or Failure of single element
  • 18. Precaution: Against Progressive Collapse 1) All buildings should be capable of safely resisting the minimum horizontal load of 1.5% of characteristic dead load applied at each floor or roof level simultaneously.
  • 19. 2) All Buildings Shall Be Provided With Effective Horizontal Ties 1) Around The Periphery 2) Internally (In Both Directions) & 3) To Columns & Walls. 3) All Buildings of Five or More Storeys Shall Be Provided With Vertical Ties. Precaution: Against Progressive Collapse
  • 20. Design of Ties (Peripheral Ties) At each floor and roof level an effectively continuous tie should be provided within 1.2 m of the edge of the building or within the perimeter wall. The tie should be capable to resisting a tensile force of Ft equal to 60 kN or (20 + 4N) kN whichever is less, where N is the number of storeys (including basement).
  • 21. Design of Ties (Internal Ties) These are to be provided at each floor and roof level in two directions approximately at right angles. Ties should be effectively continuous throughout their length and be anchored to the peripheral tie at both ends, unless continuing as horizontal ties to columns or walls.
  • 22. Design of Ties (Internal Ties) • The tensile strength, in kN per meter width shall be the greater of- • gk + qk = Avg. characteristic D.L. + L.L in kN/m2 • lr = Greater of- • The distance between the centre of columns • Frames or walls supporting any two adjacent floor spans in the direction of the tie under consideration.
  • 23. Design of Ties (Internal Ties) The bars providing these ties may be distributed evenly in the slabs or may be grouped at or in the beams, walls or other appropriate positions but at spacings generally not greater than 1.5 lr.
  • 24. Design of Ties (Horizontal ties to column and wall) • All external load-bearing members such as columns and walls should be anchored or tied horizontally into the structure at each floor and roof level. The design force for the tie is to be greater of-  a) 2 Ft kN or ls × Ft × 2.5 kN, whichever is less for a column or for each metre length if there is a wall. ls is the floor to ceiling height, in meter.  b) 3 percent of the total ultimate vertical load in the column or wall at that level. • For corner columns, this tie force should be provided in each of two directions approximately at right angles.
  • 25. Design of Ties (Vertical ties)  Should be provided for buildings of five or more storeys Each column and each wall carrying vertical load should be tied continuously from the foundation to the roof level. The reinforcement provided is required only to resist a tensile force equal to the maximum design ultimate load (dead and imposed) received from any one storey. In situation where provision of vertical ties cannot be done, the element should be considered to be removed and the surrounding members designed to bridge the gap.
  • 26. Design of Vertical Pillars (Walls, Diaphragms, Cores)  Indian Standards for Designing Precast is unavailable  Adopt any code of practice which is-  Safe  Durable  Economical  Reliable from Past Experience  Methods of mounting precast structures used in Russia will be discussed
  • 27. Primary Load-bearing Members of the Building
  • 28. Optimal Configuration  The frame members to securely perform their functions without “extra” efforts. This means that the columns operate only for compression, floor structures operate only for bending, with no forces in the plane of the slab (the membrane group of efforts), pylons take horizontal forces ensuring the necessary rigidity of the building.
  • 29. Optimal Configuration • The principle of concentration of material is observed. To reduce the material consumption the load should be transmitted through the minimum number of elements. • The main feature of the framework is the ability to ensure the integrated operation of all its elements: columns, pylons, floor slabs, foundation slab, piled and/or soil foundation. Proper use of these features can improve the design characteristics of the building frame while reducing the consumption of its materials.
  • 30. Rules of the Pylons Distribution (Rule No. 1) • All of the pylons should not be intersected by straight lines on which they are rested at one point • All of the pylons should not be parallel Building plan (slab & pylons)
  • 31. Rules of the Pylons Distribution (Rule No. 2)  The pylon should be sufficiently hard with a height of the cross section equal to 1/10 – 1/5 of the building height. With a smaller size the pylon will be more flexible and will transmit a significant portion of the horizontal load onto the columns or originate the need for more pylons.  If several flat diaphragms are connected to one core, the height of their cross section can be reduced by virtue of a more rigid joint operation with respect to the total cumulative individual work.  It is necessary to strive for the minimum number of pylons in the building.
  • 32. Rules of the Pylons Distribution (Rule No. 3) Determining efforts in the plane of the slab aab 5.26 
  • 33. Rules of the Pylons Distribution (Rule No. 4)  If one looks at the aggregate of all the diaphragms of the building combined with floor structures, it is possible to find the shear center of the building. If the shear center does not coincide with the center of gravity, the building will have additional bending stresses. If the resultant wind load does not pass through the shear center, the building will be subject to additional twisting forces. The configuration in which all three centers coincide will be optimal. The easiest way to achieve is to prepare a symmetrical in the two axes building plan with a symmetrical arrangement of the pylons.
  • 34. Frame installation (Column) Schemes Of Installation of Multi-story Columns Using A Set of Individual Installation and Mounting Devices and Tooling a — the location of columns and accessories, b — securing columns by knees, c — clamp for securing knees in the column; 1 — foundation socket, 2 — readymade mount, 3 — column, 4 — clamp 5 — knee, 6 — drawbar of the knee, 7 — wedges, 8 — anchoring device, 9 — crimping rope
  • 35. Frame installation (Cross beams) Cross beam installation: a — applying an axial mark on the column pillar; b — installing cross beam; c — column pillar alignment
  • 36. Frame installation (Pylons) Installation of interior walls — diaphragm plates — in a framed building: a — installation, b — temporary fastening; 1 — knee-piece, 2 — diaphragm with a cantilever replacing a collar beam, 3 — a universal sling, 4 — movable L- clamp with a rack.
  • 37. Frame installation (Slab panels) Laying bracing (spacing) (а) and lintel (b) floor slab panels
  • 38. Conclusion  Considering its huge advantage, Technology should be adopted in India  Safety should be the 1st concern  Past Hazards should be analyzed and precautions to avoid it should be taken  Indian Standard Code required for Design
  • 39. References • http://en.wikipedia.org/wiki/Precast_concrete • IS: 15916: 2011 • IS: 13920: 1993 • “DESIGN RULES FOR PRECAST CONCRETE: VERTICAL PILLARS (WALLS, DIAPHRAGMS, CORES)” By- Mark P. Son & Denis V. Konin, Redecon 2014, Bangalore • “Design and Construction of Multi-Storey Residential Buildings with Precast Concrete” By- Dr. H S Lai , Redecon 2014, Bangalore