SlideShare a Scribd company logo
1 of 19
Download to read offline
CRITICAL PATH METHOD
Prepared by:- Guide by:-
T.N. Manasiya (216262306003) Y.T. Rana sir
P.N. Chauhan (216260306002) F.A. Mukhi sir
A.R. Bhariyani (216260306007)
Course Name :- Construction Project Management
Course Code :- 4360603
Branch :- civil (6th)
College :- Government Polytechnic Palanpur
University :- Gujarat Technological University
COURSE OUTCOMES
a) Describe construction project management and roles of various
construction agencies.
b) Explain contracts and tendering process
c) Develop the CPM and PERT network of various construction activities.
d) Show leadership skills required to manage various construction
resources and achieve targets.
e) Apply safety measures and legal aspects at various construction works.
CRITICAL PATH METHOD
 The critical path of a network is the longest path in the network and the
duration of this path gives the duration or completion time of the project.
Critical path joins all those activities which are critical. In case of PERT
technique the critical path joins the events having zero or minimum
slacks while in CPM technique the critical path joins all critical activities
which have total float equal to zero. The activities which have total float
as zero, control the project duration and form continuous chain starting
from first node and ending at the last node.
 From the above discussion, following points can be concluded.
1. Critical path starts from the initial event and ends at the last event of the network. All
events and activities lying along the critical path are critical for the completion of the
project.
2. In PERT technique, the critical path passes through all those events whose slack is
zero. Although it is a necessary condition, but it is not sufficient. In this case though
events may be critical, but the activity joining them may not be critical. Thus for
determining the critical path total float concept is more useful, as it provides both the
necessary and sufficient condition for the activity to be critical. This explains the basic
difference in approach for determining the critical path through PERT and CPM
techniques. Thus the concept of de- trimming the critical path by CPM technique (Total
float = zero) is more rational.
3. There can be more than one critical path in a network. Depending upon the total float
value, degree of criticality can be assigned to a particular path.
4. Critical activities have no flexibilities in their start time or finish time.
BASIC RULES FOR PREPARING CPM
NETWORK
The following network rules are noteworthy:
1. In a network there must be only single initial node. Initial node has only
one outgoing arrow.
2. A network can have only one final node and the final node will have
only incoming arrows.
3. No activity can start until its tail event has occurred.
4. An event cannot occur until all the activities leading to it are completed.
8
4
5
6
7
Concrete foundation
2
Procure aggregate
Install concrete mixer
Procure cement
5
4
1
RULE 4
5. An event cannot occur twice, i.e. there cannot be any network path looping
back to previously occurred event. Network shown in Fig is incorrect.
1 2
3
6
5
4
Incorrect figure
6. There must not be any dead end left except the find node. Final node has
only incoming arrows. There must be only single final node. Thus, the
network shown in Fig. is wrong because there are two final Nodes.
5
1 2
4
3
Incorrect network
7. Any arrow should represent singular situation, i.e. individuality and
separate entity must be maintained in a network. Particular arrow can
emanate from a single event only. Thus, the network shown in Fig. is wrong
since activity P has two arrows.
P
A
D
S
C
B Q
R
P
Incorrect network
8. The number of arrows should be equal to the number of activities in the
project.
9. The network should be drawn in such a way that all activities are
completed to reach the end objective.
10. A ‘dummy activity’ is introduced in the network either to show
dependency or to avoid duplicate numbering of activities.
‘Erect beams’ can be taken up only when both ‘concrete pier’ and ‘precast
beams’ are completed. Dummy activity 2-3 shows this dependency and also
avoids duplicate numbering of activities.
2
Precast beams
4 3
8 Dummy activities
Dummy activity
2
1 4
Concrete pier Erect beams
11. Logic of network should always be maintained, i.e. arrow heads point
correct way to indicate the true control situation.
12. It is usual practice to show the time flow from left to right.
Advantages and Disadvantages of Critical Path
Method
Advantages:
1. The inter-relationship and sequence of performance of various activities
of work are clear from the network.
2. The sequence of operations to be followed at site is decided by logical
thinking.
3. There is no possibilities of overlapping of the activities.
4. Proper co-ordination of activities is maintained.
5. If something goes wrong with the planning of project it can be easily
identified and corrective measures can be taken.
6. It helps in preparing the most economical time table for all the
operations of the project.
7. It assists in the selection of the best combination of equipment and
Labour so as to finish up the project in time.
8. It eliminates the idle period and hence reduces the project time and cost.
9. The engineer in charge can direct idle labour from one activity to
another.
10.It rationalises construction costing and financing.
11. It makes the most economical use of the available resources i.e. labour,
equipment, finance etc.
Disadvantages:
1. It is very expensive.
2. Experience and skill is required for preparing a network.
3. If the assumptions made in planning a project does not comes true, there
will be delay in the project.
Example of critical path method :-
 The following activities are to be performed in a project. Draw a
network diagram and determine ‘Critical path’ and total time to complete
the project.
Activity Nodes Duration( days)
A 1 – 2 4
B 1 – 3 5
C 2 – 3 3
D 2 – 4 6
E 3 – 4 8
Solution:-
First of all draw the network diagram.
1
0
4
3
2
15
7
4
0
4
7
15
4
8
5
3
6
B
A
E
C
TE
TL
D
Computation of TE :
Starting from event -1 and proceed towards right.
TE = TE of tail event + time duration of preceding activity.
For the first event, TE = 0
 TE1 = 0
 TE2 = TE1 + 4 = 0 + 4 = 4
TE3 = TE1 + 5 = 0 + 5 = 5 Taking larger value,
= TE2 + 3 = 4 + 3 = 7  TE3 = 7
TE4 = TE2 + 6 = 4 + 6 = 10 Taking larger value,
= TE3 + 8 = 7 + 8 = 15  TE4 = 15
Computation of TL : ∆
Starting from event - 4 and proceed towards left.
TL = TL of head event - time duration of succeeding activity.
For the last event, TL = TE
 TL4 = 15
TL3 = TL4 - 8 = 15 - 8 = 7
TL2 = TL3 - 3 = 7 - 3 = 4
TL1 = TL2 - 4 = 4 - 4 = 0 Taking smaller value,
= TL3 - 5 = 7 - 5 = 2  TL1 = 0
Calculation of EST : Calculation of EFT :
EST = TE of tail event of activity EST = TE of tail event of activity + D
activity A, EST = 0 activity A, EFT = 0 + 4 = 4
activity B, EST = 0 activity B, EFT = 0 + 5 = 5
activity C, EST = 4 activity C, EFT = 4 + 3 = 7
activity D, EST = 4 activity D, EFT = 4 + 6 = 10
activity E, EST = 7 activity E, EFT = 7 + 8 = 15
Calculation of LFT : Calculation of EFT :
LFT = TL of head event of activity EST = TE of tail event of activity - D
activity A, LFT = 4 activity A, EFT = 4 - 4 = 0
activity B, LFT = 7 activity B, EFT = 7 - 5 = 2
activity C, LFT = 7 activity C, EFT = 7 - 3 = 4
activity D, LFT = 15 activity D, EFT = 15 - 6 = 9
activity E, LFT = 15 activity E, EFT = 15 - 8 = 7
CALULATION OF (TF ) :
TF = LST – EST
OR
TF = LFT – EFT
Activity TF
A 0 – 0 = 0
B 2 – 0 = 2
C 4 – 4 = 0
D 9 – 4 = 5
E 7 – 7 = 0
The above calculations are shown in the table below :
Activity Duration EST EFT LST LFT TF Remarks
A 4 0 4 0 4 0 critical activity
B 5 0 5 2 7 2 -
C 3 4 7 4 7 0 critical activity
D 6 4 10 9 15 5 -
E 8 7 15 7 15 0 critical activity
 Critical Path : A - C – E
Total time for completion of project : 4 + 3 + 8 = 15 days
Thank you

More Related Content

Similar to Critical path method with detailed description

DEFINITION OF TERMS IN A NETWORK.pdf
DEFINITION OF TERMS IN A NETWORK.pdfDEFINITION OF TERMS IN A NETWORK.pdf
DEFINITION OF TERMS IN A NETWORK.pdfssuserc9c6261
 
chapter 8 examples of networks.pdf
chapter 8 examples of networks.pdfchapter 8 examples of networks.pdf
chapter 8 examples of networks.pdfssuserc9c6261
 
EXAMPLES OF THE USE OF DUMMYACTIVITY.pdf
EXAMPLES OF THE USE OF DUMMYACTIVITY.pdfEXAMPLES OF THE USE OF DUMMYACTIVITY.pdf
EXAMPLES OF THE USE OF DUMMYACTIVITY.pdfssuserc9c6261
 
Scheduling, PERT, Critical Path Analysis.pdf
Scheduling, PERT, Critical Path Analysis.pdfScheduling, PERT, Critical Path Analysis.pdf
Scheduling, PERT, Critical Path Analysis.pdfssuserc9c6261
 
network techniquies.pdf
network techniquies.pdfnetwork techniquies.pdf
network techniquies.pdfssuserc9c6261
 
Activity, duration, ES, EF, LS, LF–.pdf
Activity, duration, ES, EF, LS, LF–.pdfActivity, duration, ES, EF, LS, LF–.pdf
Activity, duration, ES, EF, LS, LF–.pdfssuserc9c6261
 
Arc with ES & EF time –.pdf
Arc with ES & EF time –.pdfArc with ES & EF time –.pdf
Arc with ES & EF time –.pdfssuserc9c6261
 
Example of Simple Network –.pdf
Example of Simple Network –.pdfExample of Simple Network –.pdf
Example of Simple Network –.pdfssuserc9c6261
 
Network of Four Activities.pdf
Network of Four Activities.pdfNetwork of Four Activities.pdf
Network of Four Activities.pdfssuserc9c6261
 
Modified PERT CPM diagram from network.pdf
Modified PERT CPM diagram from network.pdfModified PERT CPM diagram from network.pdf
Modified PERT CPM diagram from network.pdfssuserc9c6261
 
Gantt Charts and CPM PERT Networks–.pdf
Gantt Charts and CPM PERT Networks–.pdfGantt Charts and CPM PERT Networks–.pdf
Gantt Charts and CPM PERT Networks–.pdfssuserc9c6261
 
Scheduling with activity time.pdf
Scheduling with activity time.pdfScheduling with activity time.pdf
Scheduling with activity time.pdfssuserc9c6261
 
Network of Seven Activities.pdf
Network of Seven Activities.pdfNetwork of Seven Activities.pdf
Network of Seven Activities.pdfssuserc9c6261
 
Slack or Free Time or Float.pdf
Slack or Free Time or Float.pdfSlack or Free Time or Float.pdf
Slack or Free Time or Float.pdfssuserc9c6261
 
Network with ES & EF time.pdf
Network with ES & EF time.pdfNetwork with ES & EF time.pdf
Network with ES & EF time.pdfssuserc9c6261
 
Network of first five activities.pdf
Network of first five activities.pdfNetwork of first five activities.pdf
Network of first five activities.pdfssuserc9c6261
 
Operation research's CPM techniques
Operation research's CPM techniques Operation research's CPM techniques
Operation research's CPM techniques Mohammad Younus
 

Similar to Critical path method with detailed description (20)

DEFINITION OF TERMS IN A NETWORK.pdf
DEFINITION OF TERMS IN A NETWORK.pdfDEFINITION OF TERMS IN A NETWORK.pdf
DEFINITION OF TERMS IN A NETWORK.pdf
 
chapter 8 examples of networks.pdf
chapter 8 examples of networks.pdfchapter 8 examples of networks.pdf
chapter 8 examples of networks.pdf
 
EXAMPLES OF THE USE OF DUMMYACTIVITY.pdf
EXAMPLES OF THE USE OF DUMMYACTIVITY.pdfEXAMPLES OF THE USE OF DUMMYACTIVITY.pdf
EXAMPLES OF THE USE OF DUMMYACTIVITY.pdf
 
Scheduling, PERT, Critical Path Analysis.pdf
Scheduling, PERT, Critical Path Analysis.pdfScheduling, PERT, Critical Path Analysis.pdf
Scheduling, PERT, Critical Path Analysis.pdf
 
network techniquies.pdf
network techniquies.pdfnetwork techniquies.pdf
network techniquies.pdf
 
Activity, duration, ES, EF, LS, LF–.pdf
Activity, duration, ES, EF, LS, LF–.pdfActivity, duration, ES, EF, LS, LF–.pdf
Activity, duration, ES, EF, LS, LF–.pdf
 
Arc with ES & EF time –.pdf
Arc with ES & EF time –.pdfArc with ES & EF time –.pdf
Arc with ES & EF time –.pdf
 
Example of Simple Network –.pdf
Example of Simple Network –.pdfExample of Simple Network –.pdf
Example of Simple Network –.pdf
 
Network of Four Activities.pdf
Network of Four Activities.pdfNetwork of Four Activities.pdf
Network of Four Activities.pdf
 
Modified PERT CPM diagram from network.pdf
Modified PERT CPM diagram from network.pdfModified PERT CPM diagram from network.pdf
Modified PERT CPM diagram from network.pdf
 
Gantt Charts and CPM PERT Networks–.pdf
Gantt Charts and CPM PERT Networks–.pdfGantt Charts and CPM PERT Networks–.pdf
Gantt Charts and CPM PERT Networks–.pdf
 
Scheduling with activity time.pdf
Scheduling with activity time.pdfScheduling with activity time.pdf
Scheduling with activity time.pdf
 
Network of Seven Activities.pdf
Network of Seven Activities.pdfNetwork of Seven Activities.pdf
Network of Seven Activities.pdf
 
Slack or Free Time or Float.pdf
Slack or Free Time or Float.pdfSlack or Free Time or Float.pdf
Slack or Free Time or Float.pdf
 
Network with ES & EF time.pdf
Network with ES & EF time.pdfNetwork with ES & EF time.pdf
Network with ES & EF time.pdf
 
Network of first five activities.pdf
Network of first five activities.pdfNetwork of first five activities.pdf
Network of first five activities.pdf
 
Critical path method
Critical path methodCritical path method
Critical path method
 
Operation research's CPM techniques
Operation research's CPM techniques Operation research's CPM techniques
Operation research's CPM techniques
 
Cpmprt
CpmprtCpmprt
Cpmprt
 
PERT-CPM PPT.pptx
PERT-CPM PPT.pptxPERT-CPM PPT.pptx
PERT-CPM PPT.pptx
 

Recently uploaded

XXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXX
XXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXX
XXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXssuser89054b
 
2016EF22_0 solar project report rooftop projects
2016EF22_0 solar project report rooftop projects2016EF22_0 solar project report rooftop projects
2016EF22_0 solar project report rooftop projectssmsksolar
 
Unit 1 - Soil Classification and Compaction.pdf
Unit 1 - Soil Classification and Compaction.pdfUnit 1 - Soil Classification and Compaction.pdf
Unit 1 - Soil Classification and Compaction.pdfRagavanV2
 
Unit 2- Effective stress & Permeability.pdf
Unit 2- Effective stress & Permeability.pdfUnit 2- Effective stress & Permeability.pdf
Unit 2- Effective stress & Permeability.pdfRagavanV2
 
ONLINE FOOD ORDER SYSTEM PROJECT REPORT.pdf
ONLINE FOOD ORDER SYSTEM PROJECT REPORT.pdfONLINE FOOD ORDER SYSTEM PROJECT REPORT.pdf
ONLINE FOOD ORDER SYSTEM PROJECT REPORT.pdfKamal Acharya
 
Call Girls Pimpri Chinchwad Call Me 7737669865 Budget Friendly No Advance Boo...
Call Girls Pimpri Chinchwad Call Me 7737669865 Budget Friendly No Advance Boo...Call Girls Pimpri Chinchwad Call Me 7737669865 Budget Friendly No Advance Boo...
Call Girls Pimpri Chinchwad Call Me 7737669865 Budget Friendly No Advance Boo...roncy bisnoi
 
data_management_and _data_science_cheat_sheet.pdf
data_management_and _data_science_cheat_sheet.pdfdata_management_and _data_science_cheat_sheet.pdf
data_management_and _data_science_cheat_sheet.pdfJiananWang21
 
Employee leave management system project.
Employee leave management system project.Employee leave management system project.
Employee leave management system project.Kamal Acharya
 
Hazard Identification (HAZID) vs. Hazard and Operability (HAZOP): A Comparati...
Hazard Identification (HAZID) vs. Hazard and Operability (HAZOP): A Comparati...Hazard Identification (HAZID) vs. Hazard and Operability (HAZOP): A Comparati...
Hazard Identification (HAZID) vs. Hazard and Operability (HAZOP): A Comparati...soginsider
 
A Study of Urban Area Plan for Pabna Municipality
A Study of Urban Area Plan for Pabna MunicipalityA Study of Urban Area Plan for Pabna Municipality
A Study of Urban Area Plan for Pabna MunicipalityMorshed Ahmed Rahath
 
KubeKraft presentation @CloudNativeHooghly
KubeKraft presentation @CloudNativeHooghlyKubeKraft presentation @CloudNativeHooghly
KubeKraft presentation @CloudNativeHooghlysanyuktamishra911
 
22-prompt engineering noted slide shown.pdf
22-prompt engineering noted slide shown.pdf22-prompt engineering noted slide shown.pdf
22-prompt engineering noted slide shown.pdf203318pmpc
 
Unleashing the Power of the SORA AI lastest leap
Unleashing the Power of the SORA AI lastest leapUnleashing the Power of the SORA AI lastest leap
Unleashing the Power of the SORA AI lastest leapRishantSharmaFr
 
notes on Evolution Of Analytic Scalability.ppt
notes on Evolution Of Analytic Scalability.pptnotes on Evolution Of Analytic Scalability.ppt
notes on Evolution Of Analytic Scalability.pptMsecMca
 
Design For Accessibility: Getting it right from the start
Design For Accessibility: Getting it right from the startDesign For Accessibility: Getting it right from the start
Design For Accessibility: Getting it right from the startQuintin Balsdon
 

Recently uploaded (20)

Water Industry Process Automation & Control Monthly - April 2024
Water Industry Process Automation & Control Monthly - April 2024Water Industry Process Automation & Control Monthly - April 2024
Water Industry Process Automation & Control Monthly - April 2024
 
XXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXX
XXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXX
XXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXX
 
2016EF22_0 solar project report rooftop projects
2016EF22_0 solar project report rooftop projects2016EF22_0 solar project report rooftop projects
2016EF22_0 solar project report rooftop projects
 
(INDIRA) Call Girl Bhosari Call Now 8617697112 Bhosari Escorts 24x7
(INDIRA) Call Girl Bhosari Call Now 8617697112 Bhosari Escorts 24x7(INDIRA) Call Girl Bhosari Call Now 8617697112 Bhosari Escorts 24x7
(INDIRA) Call Girl Bhosari Call Now 8617697112 Bhosari Escorts 24x7
 
Unit 1 - Soil Classification and Compaction.pdf
Unit 1 - Soil Classification and Compaction.pdfUnit 1 - Soil Classification and Compaction.pdf
Unit 1 - Soil Classification and Compaction.pdf
 
Call Now ≽ 9953056974 ≼🔝 Call Girls In New Ashok Nagar ≼🔝 Delhi door step de...
Call Now ≽ 9953056974 ≼🔝 Call Girls In New Ashok Nagar  ≼🔝 Delhi door step de...Call Now ≽ 9953056974 ≼🔝 Call Girls In New Ashok Nagar  ≼🔝 Delhi door step de...
Call Now ≽ 9953056974 ≼🔝 Call Girls In New Ashok Nagar ≼🔝 Delhi door step de...
 
Unit 2- Effective stress & Permeability.pdf
Unit 2- Effective stress & Permeability.pdfUnit 2- Effective stress & Permeability.pdf
Unit 2- Effective stress & Permeability.pdf
 
ONLINE FOOD ORDER SYSTEM PROJECT REPORT.pdf
ONLINE FOOD ORDER SYSTEM PROJECT REPORT.pdfONLINE FOOD ORDER SYSTEM PROJECT REPORT.pdf
ONLINE FOOD ORDER SYSTEM PROJECT REPORT.pdf
 
Call Girls Pimpri Chinchwad Call Me 7737669865 Budget Friendly No Advance Boo...
Call Girls Pimpri Chinchwad Call Me 7737669865 Budget Friendly No Advance Boo...Call Girls Pimpri Chinchwad Call Me 7737669865 Budget Friendly No Advance Boo...
Call Girls Pimpri Chinchwad Call Me 7737669865 Budget Friendly No Advance Boo...
 
Cara Menggugurkan Sperma Yang Masuk Rahim Biyar Tidak Hamil
Cara Menggugurkan Sperma Yang Masuk Rahim Biyar Tidak HamilCara Menggugurkan Sperma Yang Masuk Rahim Biyar Tidak Hamil
Cara Menggugurkan Sperma Yang Masuk Rahim Biyar Tidak Hamil
 
data_management_and _data_science_cheat_sheet.pdf
data_management_and _data_science_cheat_sheet.pdfdata_management_and _data_science_cheat_sheet.pdf
data_management_and _data_science_cheat_sheet.pdf
 
Employee leave management system project.
Employee leave management system project.Employee leave management system project.
Employee leave management system project.
 
Call Girls in Netaji Nagar, Delhi 💯 Call Us 🔝9953056974 🔝 Escort Service
Call Girls in Netaji Nagar, Delhi 💯 Call Us 🔝9953056974 🔝 Escort ServiceCall Girls in Netaji Nagar, Delhi 💯 Call Us 🔝9953056974 🔝 Escort Service
Call Girls in Netaji Nagar, Delhi 💯 Call Us 🔝9953056974 🔝 Escort Service
 
Hazard Identification (HAZID) vs. Hazard and Operability (HAZOP): A Comparati...
Hazard Identification (HAZID) vs. Hazard and Operability (HAZOP): A Comparati...Hazard Identification (HAZID) vs. Hazard and Operability (HAZOP): A Comparati...
Hazard Identification (HAZID) vs. Hazard and Operability (HAZOP): A Comparati...
 
A Study of Urban Area Plan for Pabna Municipality
A Study of Urban Area Plan for Pabna MunicipalityA Study of Urban Area Plan for Pabna Municipality
A Study of Urban Area Plan for Pabna Municipality
 
KubeKraft presentation @CloudNativeHooghly
KubeKraft presentation @CloudNativeHooghlyKubeKraft presentation @CloudNativeHooghly
KubeKraft presentation @CloudNativeHooghly
 
22-prompt engineering noted slide shown.pdf
22-prompt engineering noted slide shown.pdf22-prompt engineering noted slide shown.pdf
22-prompt engineering noted slide shown.pdf
 
Unleashing the Power of the SORA AI lastest leap
Unleashing the Power of the SORA AI lastest leapUnleashing the Power of the SORA AI lastest leap
Unleashing the Power of the SORA AI lastest leap
 
notes on Evolution Of Analytic Scalability.ppt
notes on Evolution Of Analytic Scalability.pptnotes on Evolution Of Analytic Scalability.ppt
notes on Evolution Of Analytic Scalability.ppt
 
Design For Accessibility: Getting it right from the start
Design For Accessibility: Getting it right from the startDesign For Accessibility: Getting it right from the start
Design For Accessibility: Getting it right from the start
 

Critical path method with detailed description

  • 1. CRITICAL PATH METHOD Prepared by:- Guide by:- T.N. Manasiya (216262306003) Y.T. Rana sir P.N. Chauhan (216260306002) F.A. Mukhi sir A.R. Bhariyani (216260306007) Course Name :- Construction Project Management Course Code :- 4360603 Branch :- civil (6th) College :- Government Polytechnic Palanpur University :- Gujarat Technological University
  • 2. COURSE OUTCOMES a) Describe construction project management and roles of various construction agencies. b) Explain contracts and tendering process c) Develop the CPM and PERT network of various construction activities. d) Show leadership skills required to manage various construction resources and achieve targets. e) Apply safety measures and legal aspects at various construction works.
  • 3. CRITICAL PATH METHOD  The critical path of a network is the longest path in the network and the duration of this path gives the duration or completion time of the project. Critical path joins all those activities which are critical. In case of PERT technique the critical path joins the events having zero or minimum slacks while in CPM technique the critical path joins all critical activities which have total float equal to zero. The activities which have total float as zero, control the project duration and form continuous chain starting from first node and ending at the last node.  From the above discussion, following points can be concluded.
  • 4. 1. Critical path starts from the initial event and ends at the last event of the network. All events and activities lying along the critical path are critical for the completion of the project. 2. In PERT technique, the critical path passes through all those events whose slack is zero. Although it is a necessary condition, but it is not sufficient. In this case though events may be critical, but the activity joining them may not be critical. Thus for determining the critical path total float concept is more useful, as it provides both the necessary and sufficient condition for the activity to be critical. This explains the basic difference in approach for determining the critical path through PERT and CPM techniques. Thus the concept of de- trimming the critical path by CPM technique (Total float = zero) is more rational. 3. There can be more than one critical path in a network. Depending upon the total float value, degree of criticality can be assigned to a particular path. 4. Critical activities have no flexibilities in their start time or finish time.
  • 5. BASIC RULES FOR PREPARING CPM NETWORK The following network rules are noteworthy: 1. In a network there must be only single initial node. Initial node has only one outgoing arrow. 2. A network can have only one final node and the final node will have only incoming arrows. 3. No activity can start until its tail event has occurred. 4. An event cannot occur until all the activities leading to it are completed.
  • 6. 8 4 5 6 7 Concrete foundation 2 Procure aggregate Install concrete mixer Procure cement 5 4 1 RULE 4 5. An event cannot occur twice, i.e. there cannot be any network path looping back to previously occurred event. Network shown in Fig is incorrect. 1 2 3 6 5 4 Incorrect figure
  • 7. 6. There must not be any dead end left except the find node. Final node has only incoming arrows. There must be only single final node. Thus, the network shown in Fig. is wrong because there are two final Nodes. 5 1 2 4 3 Incorrect network 7. Any arrow should represent singular situation, i.e. individuality and separate entity must be maintained in a network. Particular arrow can emanate from a single event only. Thus, the network shown in Fig. is wrong since activity P has two arrows.
  • 8. P A D S C B Q R P Incorrect network 8. The number of arrows should be equal to the number of activities in the project. 9. The network should be drawn in such a way that all activities are completed to reach the end objective. 10. A ‘dummy activity’ is introduced in the network either to show dependency or to avoid duplicate numbering of activities.
  • 9. ‘Erect beams’ can be taken up only when both ‘concrete pier’ and ‘precast beams’ are completed. Dummy activity 2-3 shows this dependency and also avoids duplicate numbering of activities. 2 Precast beams 4 3 8 Dummy activities Dummy activity 2 1 4 Concrete pier Erect beams 11. Logic of network should always be maintained, i.e. arrow heads point correct way to indicate the true control situation. 12. It is usual practice to show the time flow from left to right.
  • 10. Advantages and Disadvantages of Critical Path Method Advantages: 1. The inter-relationship and sequence of performance of various activities of work are clear from the network. 2. The sequence of operations to be followed at site is decided by logical thinking. 3. There is no possibilities of overlapping of the activities. 4. Proper co-ordination of activities is maintained. 5. If something goes wrong with the planning of project it can be easily identified and corrective measures can be taken.
  • 11. 6. It helps in preparing the most economical time table for all the operations of the project. 7. It assists in the selection of the best combination of equipment and Labour so as to finish up the project in time. 8. It eliminates the idle period and hence reduces the project time and cost. 9. The engineer in charge can direct idle labour from one activity to another. 10.It rationalises construction costing and financing. 11. It makes the most economical use of the available resources i.e. labour, equipment, finance etc.
  • 12. Disadvantages: 1. It is very expensive. 2. Experience and skill is required for preparing a network. 3. If the assumptions made in planning a project does not comes true, there will be delay in the project.
  • 13. Example of critical path method :-  The following activities are to be performed in a project. Draw a network diagram and determine ‘Critical path’ and total time to complete the project. Activity Nodes Duration( days) A 1 – 2 4 B 1 – 3 5 C 2 – 3 3 D 2 – 4 6 E 3 – 4 8
  • 14. Solution:- First of all draw the network diagram. 1 0 4 3 2 15 7 4 0 4 7 15 4 8 5 3 6 B A E C TE TL D Computation of TE : Starting from event -1 and proceed towards right. TE = TE of tail event + time duration of preceding activity. For the first event, TE = 0  TE1 = 0  TE2 = TE1 + 4 = 0 + 4 = 4
  • 15. TE3 = TE1 + 5 = 0 + 5 = 5 Taking larger value, = TE2 + 3 = 4 + 3 = 7  TE3 = 7 TE4 = TE2 + 6 = 4 + 6 = 10 Taking larger value, = TE3 + 8 = 7 + 8 = 15  TE4 = 15 Computation of TL : ∆ Starting from event - 4 and proceed towards left. TL = TL of head event - time duration of succeeding activity. For the last event, TL = TE  TL4 = 15 TL3 = TL4 - 8 = 15 - 8 = 7 TL2 = TL3 - 3 = 7 - 3 = 4 TL1 = TL2 - 4 = 4 - 4 = 0 Taking smaller value, = TL3 - 5 = 7 - 5 = 2  TL1 = 0
  • 16. Calculation of EST : Calculation of EFT : EST = TE of tail event of activity EST = TE of tail event of activity + D activity A, EST = 0 activity A, EFT = 0 + 4 = 4 activity B, EST = 0 activity B, EFT = 0 + 5 = 5 activity C, EST = 4 activity C, EFT = 4 + 3 = 7 activity D, EST = 4 activity D, EFT = 4 + 6 = 10 activity E, EST = 7 activity E, EFT = 7 + 8 = 15
  • 17. Calculation of LFT : Calculation of EFT : LFT = TL of head event of activity EST = TE of tail event of activity - D activity A, LFT = 4 activity A, EFT = 4 - 4 = 0 activity B, LFT = 7 activity B, EFT = 7 - 5 = 2 activity C, LFT = 7 activity C, EFT = 7 - 3 = 4 activity D, LFT = 15 activity D, EFT = 15 - 6 = 9 activity E, LFT = 15 activity E, EFT = 15 - 8 = 7 CALULATION OF (TF ) : TF = LST – EST OR TF = LFT – EFT Activity TF A 0 – 0 = 0 B 2 – 0 = 2 C 4 – 4 = 0 D 9 – 4 = 5 E 7 – 7 = 0
  • 18. The above calculations are shown in the table below : Activity Duration EST EFT LST LFT TF Remarks A 4 0 4 0 4 0 critical activity B 5 0 5 2 7 2 - C 3 4 7 4 7 0 critical activity D 6 4 10 9 15 5 - E 8 7 15 7 15 0 critical activity  Critical Path : A - C – E Total time for completion of project : 4 + 3 + 8 = 15 days