SlideShare a Scribd company logo
PROJECT
MANAGEMENT
1
Project Management Overview
• What is a project?
• What is project management?
• What is project success?
• What factors determine project success?
2
What is a Project?
3
What is a Project?
“A project is usually a one-time activity with a well-defined set of desired end
results…complex enough that the subtasks required careful coordination and
control in terms of timing, precedence, cost and performance.”
Project Management: A Managerial Approach
Jack R. Meredith and Samuel J. Mantel, Jr.
1995
The assignment of resources to accomplish specific results (deliverables) with a
well-defined schedule and budget.
Accenture (1999)
“something that is contemplated, devised, or planned; a plan; a scheme; an
undertaking”
The Macquarie Concise Dictionary
Third Edition (1998)
4
Project Characteristics
A Project…
 Has specific objectives
 Has a start and end date
 Has a budget
 Has an ‘owner’/’sponsor’
 Produces specific deliverables
 Can vary vastly in size, complexity and duration
 May be a phase within a larger project or a phase within a
program
5
What is an Operation?
6
Operations and Projects
• Operations and projects share many characteristics:
• Performed by people.
• Constrained by limited resources.
• Planned, executed, and controlled.
• Operations may include activities such as:
• Financial management and control
• Continuous manufacture
• Product distribution
• Projects may include activities such as:
• Developing a new product or service.
• Effecting a change in structure, staffing, or style of an organization.
• Developing or acquiring a new or modified information system.
7
Projects are Temporary
• Temporary means that every project has a definite beginning
and a definite end.
• The end is reached:
• When the project’s objectives have been achieved, or
• When it becomes clear that the project objectives will not or cannot
be met and the project is terminated.
• Temporary does not necessarily mean short in duration:
• many projects last for several years.
• The duration of a project is finite:
• projects are not ongoing efforts.
8
The Product of a Project is Unique
• A product or service may be unique even if the category it belongs to is large.
• For example, many thousands of office buildings have been
developed, but each individual facility is unique—different
owner, different design, different location, different
contractors, and so on.
• Because the product of each project is unique, the
characteristics that distinguish the product or service must be
progressively elaborated.
• Progressively means “proceeding in steps; continuing steadily
by increments”
• Elaborated means “worked out with care and detail; developed
thoroughly”
9
Comparative Overview
10
What is Project Management ?
11
What is Project Management?
• Project management is the application of knowledge,
skills, tools, and techniques to project activities in order to
meet or exceed stakeholder needs and expectations from a
project
• Meeting stakeholder needs and expectations involves
balancing competing demands among:
• Scope, time, cost, and quality.
• Stakeholders with differing needs and expectations.
• Identified requirements (needs) and unidentified requirements
• (expectations).
12
What is Project Success?
Factors in Project Success
• Project Management Philosophy
• Project Management Role and Responsibility
• Project Management Principles and Practices
14
Project Management Philosophy
• The “Golden Rule” of Project Management is three
words:
• Plan
• Organize
• Control
15
Project Management Roles and Responsibilities
• Project Execution
• Maintain Customer Relations
• Create a Positive Environment
16
• Project Execution Strategy
• Project Management
• Quality
• Safety
• Risk Management
• Design/Develop/Program
• Implementation
• Documentation
• Training
Project Execution Plan
Maintain Customer Relations
• Develop Communication
• Ensure Timely Participation
• Include the Customer on the
Project Team
• Develop Trust and Confidence
Safety
Maintain a positive and safe working environment
19
Project Management Principles and Practices
• Define Project Objectives
• Develop Project Execution Plan
• Define Baselines for Control
• Manage Risk
• Close out Effectively
20
Define S.M.A.R.T. Project Objectives
• S pecific
• M easurable
• A ssignable
• R ealistic
• T ime related
21
The Four Cornerstones of Project Management
Cost
Scope
Schedule
Quality
The Four Cornerstones of Project Management
Cost
Scope
Schedule
Quality
Scope
Poor scope definition is the major contributing factor
to cost overruns in the engineering and construction
industry.
CAUTION
24
Cost Influence Relative Time
Initial Scoping Effort
• Sets the baseline for cost and schedule
• Must involve the right people
• Must include implementation
• Identifies items not included
• Maximum influence on project cost
• Breaks project into manageable pieces
26
Drawings Estimate
Cost
Reports
Contracts
• Facility
• Services
Bill
of
MaterialsWBS Element/
Work Package
Schedule
The WBS
27
Successful Work Breakdown
• Status and completion is easily measured
• Definite beginning and end
• It is familiar with prior experience
• Manageable work assignments
• One continuous stream of work from start to finish
28
Steps for constructing a WBS
• Divide the project into major objectives
• Partition objectives into activities
• Divide activities with missing characteristics into
subactivities
• Repeat #3 until all subactivities have desired
characteristics
• Lowest subactivities are the basis of work
packages
29
The effect of “creeping scope” is
a major cause of cost overruns
Cost
Creeping scope
To manage creeping scope
• Keep scope documents current
• Freeze design after the estimate has been
approved
• Allow only those changes that are justified by
benefit
• Use an effective change management procedure
31
The Four Commandments of Good Project Scope
Written
Well defined
Clearly understood
Achievable
32
Cornerstones of Project Management
Cost
Scope
Schedule
Quality
Aspects of Cost
• Estimate Basis for Control
• Cost Control Application of control procedures
to follow financial progress
34
Estimate Requirements
• Define project cost integrate scope, schedule, and
resources
• Define estimate basis
• Identify potential risks
• Identify contingency/escalation
• Identify items not included
35
Elements of Cost Control
• Establish the baseline (estimate)
• Measure variation from baseline
• Take corrective action
36
Cost Control System
• Detailed project scope/work package
• Control estimate
• Chart of accounts
• Cost status report
• Forecasting process
• Change management procedure
• Cash flow forecast
37
Project Control
Project
Day 1
--------------
To do list:
Kick off meeting
Project schedule
Integration of Cost and Time
Basic Elements of the Control System
• A project plan: Scope, schedule, estimates
• A monitoring system which measures performance
against plan
• A reporting system which identifies deviations from
the plan
• A system which communicates deviations to the
right people
• Corrective actions
• Forecasting the project outcome
40
Key Control Philosophies
• Define the baseline for control
• Divide project into manageable pieces
• Remember: Ability to influence cost is maximum
early in the project
41
Key Control Philosophies
• Define and manage risk/opportunity
• Integrate scope and estimated cost into schedule
• Make informed decisions
• Anticipate deviations/changes
• Adopt the “end product” approach
• Plan ahead from phase to phase
42
Basic Project Control Steps
• Define the project scope
• Develop a project plan consistent with:
• project scope
• estimates (cost constraints)
• schedule (constraints
• resources available
• Report progress and compare with budget and forecast
• Control by taking corrective action
43
Cornerstones of Project Management
Cost
Scope
Schedule
Quality
Schedule
• Planning - Identification of the sequence of events
necessary to complete the project
• Scheduling - Determination of timing and
assembly of project activities to give overall
completion time
45
Front End Schedule
A way to get the project started right
Design
Program
Install / Test
System Turnover
46
Basis for Project Schedule
• Project objectives
• Project scope
• Project milestones
• Project estimate (budget)
• Resource availability
47
The Critical Path
• Identifies project priorities
• Shows activity relationships
• Enables schedule analysis
• Reflects project strategy
• Promotes teamwork
48
Cornerstones of Project Management
Cost
Scope
Schedule
Quality
Design
Basis
Continuous Improvement
Quality Assurance
Quality
Control
Total Project
Quality
Management
Total Project Quality Management
50
Project Quality Improvement
• Develop a quality management plan early in the
project
• Include representatives from all affected
organizational units on the project team
• Initiate the project effectively through kick-off and
alignment meetings
• Review performance and measure success
51
Project Quality Improvement
• Define scope and review periodically
• Limit scope changes
formal change procedure
require justification
• Complete more engineering up-front before defining
cost and scheduling
• Obtain constructability, operability and maintainability
input to design
52
Cost of Quality
53
Risk Management
54
Manage Risk
• What is risk?
• Sources of risk
• Kinds of risk
• Risk Management Process
• Identify risks
• Define consequences
• Develop a mitigation plan
• Document
55
Sources of Risk
Technical
Financial
Socio-Economic
Contractual
56
Risk Management Process
Identify Risk
Analyze Risk
Respond to Risk
Document Risk
57
Sources of Help to Identify Risk
• Site investigations
• Contract documents
• Schedule
• Team brainstorming
• Body of experience
58
Risk Control Methods
• Avoid
• Reduce
• Share
• Insure
• Accept
• with contingency
• without contingency
• Contain
59
Risk Containment
• Clearly define insurance responsibilities in
contracts
• Use qualified personnel
• Document and communicate project
strategy
• Define roles and responsibilities
• Prepare contingency plans for critical
activities
• Use up-front team building
60
Risk Containment
• Use qualifies contractors and vendors
• Preconstruction work briefings
(especially safety)
• Rehearse critical activities or use
mock-ups
• Use strong project control systems
• Manage contingency
61
Project Close-out
Project Closeout - Major Phases
• Obtain client acceptance
• Document the project
• Conduct the post implementation audit
• Issue the final report
63
Plan the Work…
Work the Plan
Successful Project Management
64
Exercise - Plan a Project
65

More Related Content

What's hot

project time management
 project time management project time management
project time management
Hira Atiq
 
Fundamentals of Project Management
Fundamentals of Project Management Fundamentals of Project Management
Fundamentals of Project Management
Yesica Adicondro
 
Project scope management
Project scope managementProject scope management
Project scope management
Jody R Flower
 
10 causes of project failure.
10 causes of project failure.10 causes of project failure.
10 causes of project failure.
Muhammad Abbas
 
Lec 03 project life cycle
Lec 03 project life cycleLec 03 project life cycle
Lec 03 project life cycle
SAJID ALI RUK
 
Project Planning & Management
Project Planning & ManagementProject Planning & Management
Project Planning & Management
Engr.Muhammad Zaroon
 
Elements of Project Management
Elements of Project ManagementElements of Project Management
Elements of Project Management
Kevin Thomas
 
Lecture 05:Advanced Project Management PM Processes and Framework
Lecture 05:Advanced Project Management   PM Processes and FrameworkLecture 05:Advanced Project Management   PM Processes and Framework
Lecture 05:Advanced Project Management PM Processes and Framework
Fida Karim 🇵🇰
 
COST AND TIME CONTROL OF CONSTRUCTION PROJECTS_TKAJ
COST AND TIME CONTROL OF CONSTRUCTION PROJECTS_TKAJCOST AND TIME CONTROL OF CONSTRUCTION PROJECTS_TKAJ
COST AND TIME CONTROL OF CONSTRUCTION PROJECTS_TKAJTapesh Ajmera
 
Project management
Project managementProject management
Project management
Cygnet Infotech Pvt. Ltd.
 
project management (10).pptx
project management (10).pptxproject management (10).pptx
project management (10).pptx
Shree Bhargava and Associate
 
Project management process and Project Management Knowledge areas
Project management process and Project Management Knowledge areasProject management process and Project Management Knowledge areas
Project management process and Project Management Knowledge areas
Mazen Zbib
 
Project controls
Project controlsProject controls
Project controls
Ashok Kumar
 
Project Management
Project ManagementProject Management
Project Management
Mark Roman
 
Project management
Project managementProject management
Project management
Susmitha RANGU
 
A brief on project time management
A brief on project time managementA brief on project time management
A brief on project time management
Imran Jamil
 
Project Management Fundamentals
Project Management FundamentalsProject Management Fundamentals
Project Management Fundamentals
Nishant Munjal
 
Project evaluation
Project evaluationProject evaluation
Project evaluation
Keshav Maheshwari
 
project management
project managementproject management
project management
Patrick McPartland, E.I.T.
 

What's hot (20)

project time management
 project time management project time management
project time management
 
Fundamentals of Project Management
Fundamentals of Project Management Fundamentals of Project Management
Fundamentals of Project Management
 
Project scope management
Project scope managementProject scope management
Project scope management
 
10 causes of project failure.
10 causes of project failure.10 causes of project failure.
10 causes of project failure.
 
Lec 03 project life cycle
Lec 03 project life cycleLec 03 project life cycle
Lec 03 project life cycle
 
Project Planning & Management
Project Planning & ManagementProject Planning & Management
Project Planning & Management
 
Elements of Project Management
Elements of Project ManagementElements of Project Management
Elements of Project Management
 
Lecture 05:Advanced Project Management PM Processes and Framework
Lecture 05:Advanced Project Management   PM Processes and FrameworkLecture 05:Advanced Project Management   PM Processes and Framework
Lecture 05:Advanced Project Management PM Processes and Framework
 
COST AND TIME CONTROL OF CONSTRUCTION PROJECTS_TKAJ
COST AND TIME CONTROL OF CONSTRUCTION PROJECTS_TKAJCOST AND TIME CONTROL OF CONSTRUCTION PROJECTS_TKAJ
COST AND TIME CONTROL OF CONSTRUCTION PROJECTS_TKAJ
 
Project management
Project managementProject management
Project management
 
Project quality management.ppt msm
Project quality management.ppt msmProject quality management.ppt msm
Project quality management.ppt msm
 
project management (10).pptx
project management (10).pptxproject management (10).pptx
project management (10).pptx
 
Project management process and Project Management Knowledge areas
Project management process and Project Management Knowledge areasProject management process and Project Management Knowledge areas
Project management process and Project Management Knowledge areas
 
Project controls
Project controlsProject controls
Project controls
 
Project Management
Project ManagementProject Management
Project Management
 
Project management
Project managementProject management
Project management
 
A brief on project time management
A brief on project time managementA brief on project time management
A brief on project time management
 
Project Management Fundamentals
Project Management FundamentalsProject Management Fundamentals
Project Management Fundamentals
 
Project evaluation
Project evaluationProject evaluation
Project evaluation
 
project management
project managementproject management
project management
 

Viewers also liked

8.project management chapter 8
8.project management chapter 88.project management chapter 8
8.project management chapter 8
Warui Maina
 
Project mgmt.
Project mgmt.Project mgmt.
Project mgmt.
James Adam Vecino
 
Introduction to construction management
Introduction to construction managementIntroduction to construction management
Introduction to construction management
Xubitech
 
Introduction to construction management
Introduction to construction managementIntroduction to construction management
Introduction to construction management
Aditi Shah
 
CONSTRUCTION MANAGEMENT
CONSTRUCTION MANAGEMENTCONSTRUCTION MANAGEMENT
CONSTRUCTION MANAGEMENT
JAI MCA-STUDENT
 

Viewers also liked (6)

8.project management chapter 8
8.project management chapter 88.project management chapter 8
8.project management chapter 8
 
Project mgmt.
Project mgmt.Project mgmt.
Project mgmt.
 
Introduction to construction management
Introduction to construction managementIntroduction to construction management
Introduction to construction management
 
Introduction to construction management
Introduction to construction managementIntroduction to construction management
Introduction to construction management
 
CONSTRUCTION MANAGEMENT
CONSTRUCTION MANAGEMENTCONSTRUCTION MANAGEMENT
CONSTRUCTION MANAGEMENT
 
Project management
Project managementProject management
Project management
 

Similar to Project Management

Introduction to Project Management.pdf
Introduction to Project Management.pdfIntroduction to Project Management.pdf
Introduction to Project Management.pdf
dinushikagunawardhan1
 
PME UNIT-3.pptx
PME UNIT-3.pptxPME UNIT-3.pptx
PME UNIT-3.pptx
MayankVasisthGandhi
 
Fundamentalsof PM.pptx
Fundamentalsof PM.pptxFundamentalsof PM.pptx
Fundamentalsof PM.pptx
agathamarlinee
 
PROJECT MANAGEMENT AND FINANCE
PROJECT MANAGEMENT AND FINANCE PROJECT MANAGEMENT AND FINANCE
PROJECT MANAGEMENT AND FINANCE
S. Sathishkumar
 
sample456.pptx
sample456.pptxsample456.pptx
sample456.pptx
JasmineMichael1
 
Fundamentals of aviation project management
Fundamentals of aviation project managementFundamentals of aviation project management
Fundamentals of aviation project management
Partha Chakraborty
 
Projectmanagement 130721095616-phpapp01
Projectmanagement 130721095616-phpapp01Projectmanagement 130721095616-phpapp01
Projectmanagement 130721095616-phpapp01
samansari22
 
project introduction.pdf
project introduction.pdfproject introduction.pdf
project introduction.pdf
RajeevRanjan959412
 
Project Management and Control Techniques
Project Management and Control TechniquesProject Management and Control Techniques
Project Management and Control Techniques
ssuser8e973a
 
All about project management
All about project managementAll about project management
All about project managementTudor Bejan
 
APM Practitioner Qualification revision cards
APM Practitioner Qualification revision cardsAPM Practitioner Qualification revision cards
APM Practitioner Qualification revision cards
Jacobs Engineering
 
projectmanagement-130721095616-phpapp01-converted.pptx
projectmanagement-130721095616-phpapp01-converted.pptxprojectmanagement-130721095616-phpapp01-converted.pptx
projectmanagement-130721095616-phpapp01-converted.pptx
Chandrasen Sharma
 
project mgmt chapter 1.pptx
project mgmt chapter 1.pptxproject mgmt chapter 1.pptx
project mgmt chapter 1.pptx
DejeneDay
 
Effective project management skills
Effective project management skillsEffective project management skills
Effective project management skills
Charles Cotter, PhD
 
effectiveprojectmanagementskills-140722041532-phpapp02.pdf
effectiveprojectmanagementskills-140722041532-phpapp02.pdfeffectiveprojectmanagementskills-140722041532-phpapp02.pdf
effectiveprojectmanagementskills-140722041532-phpapp02.pdf
ayansamosisa
 
MODULE III - M.ARCH.pptx
MODULE III - M.ARCH.pptxMODULE III - M.ARCH.pptx
MODULE III - M.ARCH.pptx
SharanabasappaDegoan
 
Project management
Project managementProject management
Project management
Satish Yadavalli
 
Module 1.pptx
Module 1.pptxModule 1.pptx
Module 1.pptx
Vinish P
 
Pmbok5 changes v2
Pmbok5 changes v2Pmbok5 changes v2
Pmbok5 changes v2
Marco Booij
 

Similar to Project Management (20)

Introduction to Project Management.pdf
Introduction to Project Management.pdfIntroduction to Project Management.pdf
Introduction to Project Management.pdf
 
PME UNIT-3.pptx
PME UNIT-3.pptxPME UNIT-3.pptx
PME UNIT-3.pptx
 
Fundamentalsof PM.pptx
Fundamentalsof PM.pptxFundamentalsof PM.pptx
Fundamentalsof PM.pptx
 
PROJECT MANAGEMENT AND FINANCE
PROJECT MANAGEMENT AND FINANCE PROJECT MANAGEMENT AND FINANCE
PROJECT MANAGEMENT AND FINANCE
 
sample456.pptx
sample456.pptxsample456.pptx
sample456.pptx
 
Fundamentals of aviation project management
Fundamentals of aviation project managementFundamentals of aviation project management
Fundamentals of aviation project management
 
Projectmanagement 130721095616-phpapp01
Projectmanagement 130721095616-phpapp01Projectmanagement 130721095616-phpapp01
Projectmanagement 130721095616-phpapp01
 
pmppgoav14.ppt
pmppgoav14.pptpmppgoav14.ppt
pmppgoav14.ppt
 
project introduction.pdf
project introduction.pdfproject introduction.pdf
project introduction.pdf
 
Project Management and Control Techniques
Project Management and Control TechniquesProject Management and Control Techniques
Project Management and Control Techniques
 
All about project management
All about project managementAll about project management
All about project management
 
APM Practitioner Qualification revision cards
APM Practitioner Qualification revision cardsAPM Practitioner Qualification revision cards
APM Practitioner Qualification revision cards
 
projectmanagement-130721095616-phpapp01-converted.pptx
projectmanagement-130721095616-phpapp01-converted.pptxprojectmanagement-130721095616-phpapp01-converted.pptx
projectmanagement-130721095616-phpapp01-converted.pptx
 
project mgmt chapter 1.pptx
project mgmt chapter 1.pptxproject mgmt chapter 1.pptx
project mgmt chapter 1.pptx
 
Effective project management skills
Effective project management skillsEffective project management skills
Effective project management skills
 
effectiveprojectmanagementskills-140722041532-phpapp02.pdf
effectiveprojectmanagementskills-140722041532-phpapp02.pdfeffectiveprojectmanagementskills-140722041532-phpapp02.pdf
effectiveprojectmanagementskills-140722041532-phpapp02.pdf
 
MODULE III - M.ARCH.pptx
MODULE III - M.ARCH.pptxMODULE III - M.ARCH.pptx
MODULE III - M.ARCH.pptx
 
Project management
Project managementProject management
Project management
 
Module 1.pptx
Module 1.pptxModule 1.pptx
Module 1.pptx
 
Pmbok5 changes v2
Pmbok5 changes v2Pmbok5 changes v2
Pmbok5 changes v2
 

Recently uploaded

Pile Foundation by Venkatesh Taduvai (Sub Geotechnical Engineering II)-conver...
Pile Foundation by Venkatesh Taduvai (Sub Geotechnical Engineering II)-conver...Pile Foundation by Venkatesh Taduvai (Sub Geotechnical Engineering II)-conver...
Pile Foundation by Venkatesh Taduvai (Sub Geotechnical Engineering II)-conver...
AJAYKUMARPUND1
 
Student information management system project report ii.pdf
Student information management system project report ii.pdfStudent information management system project report ii.pdf
Student information management system project report ii.pdf
Kamal Acharya
 
ethical hacking-mobile hacking methods.ppt
ethical hacking-mobile hacking methods.pptethical hacking-mobile hacking methods.ppt
ethical hacking-mobile hacking methods.ppt
Jayaprasanna4
 
H.Seo, ICLR 2024, MLILAB, KAIST AI.pdf
H.Seo,  ICLR 2024, MLILAB,  KAIST AI.pdfH.Seo,  ICLR 2024, MLILAB,  KAIST AI.pdf
H.Seo, ICLR 2024, MLILAB, KAIST AI.pdf
MLILAB
 
Quality defects in TMT Bars, Possible causes and Potential Solutions.
Quality defects in TMT Bars, Possible causes and Potential Solutions.Quality defects in TMT Bars, Possible causes and Potential Solutions.
Quality defects in TMT Bars, Possible causes and Potential Solutions.
PrashantGoswami42
 
Sachpazis:Terzaghi Bearing Capacity Estimation in simple terms with Calculati...
Sachpazis:Terzaghi Bearing Capacity Estimation in simple terms with Calculati...Sachpazis:Terzaghi Bearing Capacity Estimation in simple terms with Calculati...
Sachpazis:Terzaghi Bearing Capacity Estimation in simple terms with Calculati...
Dr.Costas Sachpazis
 
DESIGN A COTTON SEED SEPARATION MACHINE.docx
DESIGN A COTTON SEED SEPARATION MACHINE.docxDESIGN A COTTON SEED SEPARATION MACHINE.docx
DESIGN A COTTON SEED SEPARATION MACHINE.docx
FluxPrime1
 
NO1 Uk best vashikaran specialist in delhi vashikaran baba near me online vas...
NO1 Uk best vashikaran specialist in delhi vashikaran baba near me online vas...NO1 Uk best vashikaran specialist in delhi vashikaran baba near me online vas...
NO1 Uk best vashikaran specialist in delhi vashikaran baba near me online vas...
Amil Baba Dawood bangali
 
Cosmetic shop management system project report.pdf
Cosmetic shop management system project report.pdfCosmetic shop management system project report.pdf
Cosmetic shop management system project report.pdf
Kamal Acharya
 
Standard Reomte Control Interface - Neometrix
Standard Reomte Control Interface - NeometrixStandard Reomte Control Interface - Neometrix
Standard Reomte Control Interface - Neometrix
Neometrix_Engineering_Pvt_Ltd
 
MCQ Soil mechanics questions (Soil shear strength).pdf
MCQ Soil mechanics questions (Soil shear strength).pdfMCQ Soil mechanics questions (Soil shear strength).pdf
MCQ Soil mechanics questions (Soil shear strength).pdf
Osamah Alsalih
 
WATER CRISIS and its solutions-pptx 1234
WATER CRISIS and its solutions-pptx 1234WATER CRISIS and its solutions-pptx 1234
WATER CRISIS and its solutions-pptx 1234
AafreenAbuthahir2
 
Design and Analysis of Algorithms-DP,Backtracking,Graphs,B&B
Design and Analysis of Algorithms-DP,Backtracking,Graphs,B&BDesign and Analysis of Algorithms-DP,Backtracking,Graphs,B&B
Design and Analysis of Algorithms-DP,Backtracking,Graphs,B&B
Sreedhar Chowdam
 
Final project report on grocery store management system..pdf
Final project report on grocery store management system..pdfFinal project report on grocery store management system..pdf
Final project report on grocery store management system..pdf
Kamal Acharya
 
TECHNICAL TRAINING MANUAL GENERAL FAMILIARIZATION COURSE
TECHNICAL TRAINING MANUAL   GENERAL FAMILIARIZATION COURSETECHNICAL TRAINING MANUAL   GENERAL FAMILIARIZATION COURSE
TECHNICAL TRAINING MANUAL GENERAL FAMILIARIZATION COURSE
DuvanRamosGarzon1
 
Democratizing Fuzzing at Scale by Abhishek Arya
Democratizing Fuzzing at Scale by Abhishek AryaDemocratizing Fuzzing at Scale by Abhishek Arya
Democratizing Fuzzing at Scale by Abhishek Arya
abh.arya
 
一比一原版(SFU毕业证)西蒙菲莎大学毕业证成绩单如何办理
一比一原版(SFU毕业证)西蒙菲莎大学毕业证成绩单如何办理一比一原版(SFU毕业证)西蒙菲莎大学毕业证成绩单如何办理
一比一原版(SFU毕业证)西蒙菲莎大学毕业证成绩单如何办理
bakpo1
 
addressing modes in computer architecture
addressing modes  in computer architectureaddressing modes  in computer architecture
addressing modes in computer architecture
ShahidSultan24
 
CFD Simulation of By-pass Flow in a HRSG module by R&R Consult.pptx
CFD Simulation of By-pass Flow in a HRSG module by R&R Consult.pptxCFD Simulation of By-pass Flow in a HRSG module by R&R Consult.pptx
CFD Simulation of By-pass Flow in a HRSG module by R&R Consult.pptx
R&R Consult
 
Gen AI Study Jams _ For the GDSC Leads in India.pdf
Gen AI Study Jams _ For the GDSC Leads in India.pdfGen AI Study Jams _ For the GDSC Leads in India.pdf
Gen AI Study Jams _ For the GDSC Leads in India.pdf
gdsczhcet
 

Recently uploaded (20)

Pile Foundation by Venkatesh Taduvai (Sub Geotechnical Engineering II)-conver...
Pile Foundation by Venkatesh Taduvai (Sub Geotechnical Engineering II)-conver...Pile Foundation by Venkatesh Taduvai (Sub Geotechnical Engineering II)-conver...
Pile Foundation by Venkatesh Taduvai (Sub Geotechnical Engineering II)-conver...
 
Student information management system project report ii.pdf
Student information management system project report ii.pdfStudent information management system project report ii.pdf
Student information management system project report ii.pdf
 
ethical hacking-mobile hacking methods.ppt
ethical hacking-mobile hacking methods.pptethical hacking-mobile hacking methods.ppt
ethical hacking-mobile hacking methods.ppt
 
H.Seo, ICLR 2024, MLILAB, KAIST AI.pdf
H.Seo,  ICLR 2024, MLILAB,  KAIST AI.pdfH.Seo,  ICLR 2024, MLILAB,  KAIST AI.pdf
H.Seo, ICLR 2024, MLILAB, KAIST AI.pdf
 
Quality defects in TMT Bars, Possible causes and Potential Solutions.
Quality defects in TMT Bars, Possible causes and Potential Solutions.Quality defects in TMT Bars, Possible causes and Potential Solutions.
Quality defects in TMT Bars, Possible causes and Potential Solutions.
 
Sachpazis:Terzaghi Bearing Capacity Estimation in simple terms with Calculati...
Sachpazis:Terzaghi Bearing Capacity Estimation in simple terms with Calculati...Sachpazis:Terzaghi Bearing Capacity Estimation in simple terms with Calculati...
Sachpazis:Terzaghi Bearing Capacity Estimation in simple terms with Calculati...
 
DESIGN A COTTON SEED SEPARATION MACHINE.docx
DESIGN A COTTON SEED SEPARATION MACHINE.docxDESIGN A COTTON SEED SEPARATION MACHINE.docx
DESIGN A COTTON SEED SEPARATION MACHINE.docx
 
NO1 Uk best vashikaran specialist in delhi vashikaran baba near me online vas...
NO1 Uk best vashikaran specialist in delhi vashikaran baba near me online vas...NO1 Uk best vashikaran specialist in delhi vashikaran baba near me online vas...
NO1 Uk best vashikaran specialist in delhi vashikaran baba near me online vas...
 
Cosmetic shop management system project report.pdf
Cosmetic shop management system project report.pdfCosmetic shop management system project report.pdf
Cosmetic shop management system project report.pdf
 
Standard Reomte Control Interface - Neometrix
Standard Reomte Control Interface - NeometrixStandard Reomte Control Interface - Neometrix
Standard Reomte Control Interface - Neometrix
 
MCQ Soil mechanics questions (Soil shear strength).pdf
MCQ Soil mechanics questions (Soil shear strength).pdfMCQ Soil mechanics questions (Soil shear strength).pdf
MCQ Soil mechanics questions (Soil shear strength).pdf
 
WATER CRISIS and its solutions-pptx 1234
WATER CRISIS and its solutions-pptx 1234WATER CRISIS and its solutions-pptx 1234
WATER CRISIS and its solutions-pptx 1234
 
Design and Analysis of Algorithms-DP,Backtracking,Graphs,B&B
Design and Analysis of Algorithms-DP,Backtracking,Graphs,B&BDesign and Analysis of Algorithms-DP,Backtracking,Graphs,B&B
Design and Analysis of Algorithms-DP,Backtracking,Graphs,B&B
 
Final project report on grocery store management system..pdf
Final project report on grocery store management system..pdfFinal project report on grocery store management system..pdf
Final project report on grocery store management system..pdf
 
TECHNICAL TRAINING MANUAL GENERAL FAMILIARIZATION COURSE
TECHNICAL TRAINING MANUAL   GENERAL FAMILIARIZATION COURSETECHNICAL TRAINING MANUAL   GENERAL FAMILIARIZATION COURSE
TECHNICAL TRAINING MANUAL GENERAL FAMILIARIZATION COURSE
 
Democratizing Fuzzing at Scale by Abhishek Arya
Democratizing Fuzzing at Scale by Abhishek AryaDemocratizing Fuzzing at Scale by Abhishek Arya
Democratizing Fuzzing at Scale by Abhishek Arya
 
一比一原版(SFU毕业证)西蒙菲莎大学毕业证成绩单如何办理
一比一原版(SFU毕业证)西蒙菲莎大学毕业证成绩单如何办理一比一原版(SFU毕业证)西蒙菲莎大学毕业证成绩单如何办理
一比一原版(SFU毕业证)西蒙菲莎大学毕业证成绩单如何办理
 
addressing modes in computer architecture
addressing modes  in computer architectureaddressing modes  in computer architecture
addressing modes in computer architecture
 
CFD Simulation of By-pass Flow in a HRSG module by R&R Consult.pptx
CFD Simulation of By-pass Flow in a HRSG module by R&R Consult.pptxCFD Simulation of By-pass Flow in a HRSG module by R&R Consult.pptx
CFD Simulation of By-pass Flow in a HRSG module by R&R Consult.pptx
 
Gen AI Study Jams _ For the GDSC Leads in India.pdf
Gen AI Study Jams _ For the GDSC Leads in India.pdfGen AI Study Jams _ For the GDSC Leads in India.pdf
Gen AI Study Jams _ For the GDSC Leads in India.pdf
 

Project Management

  • 2. Project Management Overview • What is a project? • What is project management? • What is project success? • What factors determine project success? 2
  • 3. What is a Project? 3
  • 4. What is a Project? “A project is usually a one-time activity with a well-defined set of desired end results…complex enough that the subtasks required careful coordination and control in terms of timing, precedence, cost and performance.” Project Management: A Managerial Approach Jack R. Meredith and Samuel J. Mantel, Jr. 1995 The assignment of resources to accomplish specific results (deliverables) with a well-defined schedule and budget. Accenture (1999) “something that is contemplated, devised, or planned; a plan; a scheme; an undertaking” The Macquarie Concise Dictionary Third Edition (1998) 4
  • 5. Project Characteristics A Project…  Has specific objectives  Has a start and end date  Has a budget  Has an ‘owner’/’sponsor’  Produces specific deliverables  Can vary vastly in size, complexity and duration  May be a phase within a larger project or a phase within a program 5
  • 6. What is an Operation? 6
  • 7. Operations and Projects • Operations and projects share many characteristics: • Performed by people. • Constrained by limited resources. • Planned, executed, and controlled. • Operations may include activities such as: • Financial management and control • Continuous manufacture • Product distribution • Projects may include activities such as: • Developing a new product or service. • Effecting a change in structure, staffing, or style of an organization. • Developing or acquiring a new or modified information system. 7
  • 8. Projects are Temporary • Temporary means that every project has a definite beginning and a definite end. • The end is reached: • When the project’s objectives have been achieved, or • When it becomes clear that the project objectives will not or cannot be met and the project is terminated. • Temporary does not necessarily mean short in duration: • many projects last for several years. • The duration of a project is finite: • projects are not ongoing efforts. 8
  • 9. The Product of a Project is Unique • A product or service may be unique even if the category it belongs to is large. • For example, many thousands of office buildings have been developed, but each individual facility is unique—different owner, different design, different location, different contractors, and so on. • Because the product of each project is unique, the characteristics that distinguish the product or service must be progressively elaborated. • Progressively means “proceeding in steps; continuing steadily by increments” • Elaborated means “worked out with care and detail; developed thoroughly” 9
  • 11. What is Project Management ? 11
  • 12. What is Project Management? • Project management is the application of knowledge, skills, tools, and techniques to project activities in order to meet or exceed stakeholder needs and expectations from a project • Meeting stakeholder needs and expectations involves balancing competing demands among: • Scope, time, cost, and quality. • Stakeholders with differing needs and expectations. • Identified requirements (needs) and unidentified requirements • (expectations). 12
  • 13. What is Project Success?
  • 14. Factors in Project Success • Project Management Philosophy • Project Management Role and Responsibility • Project Management Principles and Practices 14
  • 15. Project Management Philosophy • The “Golden Rule” of Project Management is three words: • Plan • Organize • Control 15
  • 16. Project Management Roles and Responsibilities • Project Execution • Maintain Customer Relations • Create a Positive Environment 16
  • 17. • Project Execution Strategy • Project Management • Quality • Safety • Risk Management • Design/Develop/Program • Implementation • Documentation • Training Project Execution Plan
  • 18. Maintain Customer Relations • Develop Communication • Ensure Timely Participation • Include the Customer on the Project Team • Develop Trust and Confidence
  • 19. Safety Maintain a positive and safe working environment 19
  • 20. Project Management Principles and Practices • Define Project Objectives • Develop Project Execution Plan • Define Baselines for Control • Manage Risk • Close out Effectively 20
  • 21. Define S.M.A.R.T. Project Objectives • S pecific • M easurable • A ssignable • R ealistic • T ime related 21
  • 22. The Four Cornerstones of Project Management Cost Scope Schedule Quality
  • 23. The Four Cornerstones of Project Management Cost Scope Schedule Quality
  • 24. Scope Poor scope definition is the major contributing factor to cost overruns in the engineering and construction industry. CAUTION 24
  • 26. Initial Scoping Effort • Sets the baseline for cost and schedule • Must involve the right people • Must include implementation • Identifies items not included • Maximum influence on project cost • Breaks project into manageable pieces 26
  • 27. Drawings Estimate Cost Reports Contracts • Facility • Services Bill of MaterialsWBS Element/ Work Package Schedule The WBS 27
  • 28. Successful Work Breakdown • Status and completion is easily measured • Definite beginning and end • It is familiar with prior experience • Manageable work assignments • One continuous stream of work from start to finish 28
  • 29. Steps for constructing a WBS • Divide the project into major objectives • Partition objectives into activities • Divide activities with missing characteristics into subactivities • Repeat #3 until all subactivities have desired characteristics • Lowest subactivities are the basis of work packages 29
  • 30. The effect of “creeping scope” is a major cause of cost overruns Cost Creeping scope
  • 31. To manage creeping scope • Keep scope documents current • Freeze design after the estimate has been approved • Allow only those changes that are justified by benefit • Use an effective change management procedure 31
  • 32. The Four Commandments of Good Project Scope Written Well defined Clearly understood Achievable 32
  • 33. Cornerstones of Project Management Cost Scope Schedule Quality
  • 34. Aspects of Cost • Estimate Basis for Control • Cost Control Application of control procedures to follow financial progress 34
  • 35. Estimate Requirements • Define project cost integrate scope, schedule, and resources • Define estimate basis • Identify potential risks • Identify contingency/escalation • Identify items not included 35
  • 36. Elements of Cost Control • Establish the baseline (estimate) • Measure variation from baseline • Take corrective action 36
  • 37. Cost Control System • Detailed project scope/work package • Control estimate • Chart of accounts • Cost status report • Forecasting process • Change management procedure • Cash flow forecast 37
  • 38. Project Control Project Day 1 -------------- To do list: Kick off meeting Project schedule
  • 40. Basic Elements of the Control System • A project plan: Scope, schedule, estimates • A monitoring system which measures performance against plan • A reporting system which identifies deviations from the plan • A system which communicates deviations to the right people • Corrective actions • Forecasting the project outcome 40
  • 41. Key Control Philosophies • Define the baseline for control • Divide project into manageable pieces • Remember: Ability to influence cost is maximum early in the project 41
  • 42. Key Control Philosophies • Define and manage risk/opportunity • Integrate scope and estimated cost into schedule • Make informed decisions • Anticipate deviations/changes • Adopt the “end product” approach • Plan ahead from phase to phase 42
  • 43. Basic Project Control Steps • Define the project scope • Develop a project plan consistent with: • project scope • estimates (cost constraints) • schedule (constraints • resources available • Report progress and compare with budget and forecast • Control by taking corrective action 43
  • 44. Cornerstones of Project Management Cost Scope Schedule Quality
  • 45. Schedule • Planning - Identification of the sequence of events necessary to complete the project • Scheduling - Determination of timing and assembly of project activities to give overall completion time 45
  • 46. Front End Schedule A way to get the project started right Design Program Install / Test System Turnover 46
  • 47. Basis for Project Schedule • Project objectives • Project scope • Project milestones • Project estimate (budget) • Resource availability 47
  • 48. The Critical Path • Identifies project priorities • Shows activity relationships • Enables schedule analysis • Reflects project strategy • Promotes teamwork 48
  • 49. Cornerstones of Project Management Cost Scope Schedule Quality
  • 50. Design Basis Continuous Improvement Quality Assurance Quality Control Total Project Quality Management Total Project Quality Management 50
  • 51. Project Quality Improvement • Develop a quality management plan early in the project • Include representatives from all affected organizational units on the project team • Initiate the project effectively through kick-off and alignment meetings • Review performance and measure success 51
  • 52. Project Quality Improvement • Define scope and review periodically • Limit scope changes formal change procedure require justification • Complete more engineering up-front before defining cost and scheduling • Obtain constructability, operability and maintainability input to design 52
  • 55. Manage Risk • What is risk? • Sources of risk • Kinds of risk • Risk Management Process • Identify risks • Define consequences • Develop a mitigation plan • Document 55
  • 57. Risk Management Process Identify Risk Analyze Risk Respond to Risk Document Risk 57
  • 58. Sources of Help to Identify Risk • Site investigations • Contract documents • Schedule • Team brainstorming • Body of experience 58
  • 59. Risk Control Methods • Avoid • Reduce • Share • Insure • Accept • with contingency • without contingency • Contain 59
  • 60. Risk Containment • Clearly define insurance responsibilities in contracts • Use qualified personnel • Document and communicate project strategy • Define roles and responsibilities • Prepare contingency plans for critical activities • Use up-front team building 60
  • 61. Risk Containment • Use qualifies contractors and vendors • Preconstruction work briefings (especially safety) • Rehearse critical activities or use mock-ups • Use strong project control systems • Manage contingency 61
  • 63. Project Closeout - Major Phases • Obtain client acceptance • Document the project • Conduct the post implementation audit • Issue the final report 63
  • 64. Plan the Work… Work the Plan Successful Project Management 64
  • 65. Exercise - Plan a Project 65