PM World Today – March 2011 (Vol XIII, Issue III)


                    PM WORLD TODAY – FEATURED PAPER – MARCH 2011

                             Program Management Dashboards
                                                       By Bob Prieto

What is a dashboard?

Dashboards and “Balanced Scorecards” have been proposed as a communication tool
and executive summary of program performance. They can capture a variety of inputs
and display them in one place. In some ways it is where “Analog aesthetics meets
digital information”.

Operational dashboards focus on managing and measuring business and process
activities in real time or near-real time. Operational dashboards provide deep visibility at
an overall program level, on a specific business area or business process activity. Key
Performance Indicators (KPIs) and metrics are typically displayed by an assortment of
dials, gauges and stoplights that resemble those found in a commercial plane cockpit.

A method to incorporate statistical process control (SPC) and colors was first proposed
at the US Department of Energy’s Hanford in 1997 (“Stoplight Charts with SPC Inside”
published by American Society for Quality 2004) and put in place as the Fluor Hanford
Dashboard in FY 2005. It utilized existing and familiar performance indicators.

               Control Chart Decision                           Color                Leadership
               Result                                                                Action

               Stable                  Level is                 Green                Stay the Course
               (common                 Acceptable
               cause
               variation)              Level is Not             Yellow               Improve System
                                       Acceptable

               Trend          Adverse                           Red                  Corrective
               (special cause                                                        Action
               variation)
                              Improving                         Green                Reinforce – Stay
                                                                                     the Course




© 2011 Bob Prieto

PM World Today is a free monthly eJournal - Subscriptions available at http://www.pmworldtoday.net      Page 1
PM World Today – March 2011 (Vol XIII, Issue III)


In Oregon, the Oregon Department of Transportation's OTIA III State Bridge Delivery
Program dashboard was used to status progress to stakeholders. Deeper drill downs
provided management information.




                                                      Source: Fluor

But to be effective the dashboard must really track all key program dimensions since a
failure in any one can undermine the program. I will not dwell on the graphic portrayal
but rather spend the next bit looking at some of the key elements to be tracked and in
what form they should be tracked and by whom.

Selection of measures is a key step in effective management of any program. The
dashboard must reflect the strategic business objectives that the program is trying to
achieve; key dimensions to assess strategy effectiveness; and key process and control
factors to assure true progress is being made towards the strategic business objectives.
Many times measures are chosen without adequate attention given to the driving
strategic business objectives. In those instances the program team tracks measures
and then tries to figure out what the objectives are.

The selection of dashboard parameters must include leading and trending indicators not
just historical ones.


© 2011 Bob Prieto

PM World Today is a free monthly eJournal - Subscriptions available at http://www.pmworldtoday.net   Page 2
PM World Today – March 2011 (Vol XIII, Issue III)


Let’s return to our Strategic Program Management1 system. The major processes and
dimensions displayed provide a good starting point for constructing a program
management dashboard.




The example that follows is for a large public transport program and each major
dimension is reflected in a separate table. Specific program requirements and
objectives will modify certain elements of these tables but they represent a good analog
for dashboard development.




© 2011 Bob Prieto

PM World Today is a free monthly eJournal - Subscriptions available at http://www.pmworldtoday.net   Page 3
PM World Today – March 2011 (Vol XIII, Issue III)




    Framework                 Program               Program                  Program                 Project
    Processes                 Management            Management               Dashboard               Dashboard
                              Office (PMO)          Delivery                 Metric                  Metric
                              Element               System
                                                    (PMDS)
                                                    Element

    Audits                    Program               Project Audit            Program          Project and
                              Audit Plan            Plan                     Audit status;    functional
                                                                             top open         audits status;
                                                                             findings         top open
                                                                                              findings
    Budgeting,                Program               Project Budget           Program          Project budget
    Fund                      Budget                                         budget           performance;
    Management                                                               status;          earned value;
    and Allocation,                                                          program cash projected cost
    Expenditure                                                              flow; profile of at completion
                                                                             expenditures;
                                                                             costs,
                                                                             expenditures
                                                                             and
                                                                             commitments
                                                                             to date
    Approval, and             Funding               Project Budget           Sources and Project
    Tracking of               Plan                  (Authorized)             uses of          payments to
    Funds                                                                    funds;           date; contract
    Committed and                                                            funding          amounts
    Expended                                                                 requirements outstanding;
                                                                             for next         projected total
                                                                             period           funding to
                                                                                              completion
    Change Impact             Program               CIA Process              Projected        Projected
    Assessment                Change                                         impacts of       impacts of
    (CIA)                     Request                                        approved and approved and
                              Process                                        pending          pending
                                                                             programmatic project
                                                                             changes          changes
    Configuration             PMO Go-By             PMDS                     Compliance       Compliance
    Management                Documents                                      with go-by       with PMDS
                                                                             documents



© 2011 Bob Prieto

PM World Today is a free monthly eJournal - Subscriptions available at http://www.pmworldtoday.net               Page 4
PM World Today – March 2011 (Vol XIII, Issue III)


    Constructability          Labor,                Contracting              Compliance              Means &
    Analysis –                Supplier              Strategy;                with Labor,             Methods; Root
    Systemic                  Policies              Supply Chain             Supplier                cause Analysis
                                                    Strategy;                Policies;
                                                    Means &                  Contracting
                                                    Methods                  Strategy;
                                                                             Supply Chain
                                                                             Strategy
    Construction              Construction          Project                  Start of major          Construction
    Mobilization              affecting             Execution Plan           construction            mobilization
                              policies                                       activities;             status and
                                                                             ribbon cutting          issues
                                                                             dates
    Construction                                    Owner                    Owner                   Owner
    Technology                                      furnished                furnished               furnished
                                                    equipment;               equipment               equipment
                                                    Value                    major issues;           major issues;
                                                    Improvement              VIP status              VIP status and
                                                    Plans (VIP)              and results             results;
                                                                                                     productivity
                                                                                                     factor
                                                                                                     assessment
    Contingency               Owner                 Program                  Owner level             Program level
    Management                controlled            controlled               contingency             contingency
                              contingency;          contingency;             remaining by            remaining by
                              Program               Program Risk             type; Current           source and
                              Risk                  Management               programmatic            type; Current
                              Management            program;                 risk                    project risk
                              program               Projects Risk            assessment              assessment
                                                    Management
                                                    programs
    Cost                      Owner Event Estimated cost                     Programmatic            Project cost
    Estimating                Risk        to complete -                      cost trends             trends and
                              Assessment program and                         and forecast            forecast cost at
                                          projects                           cost at                 completion;
                                                                             completion              cost recovery
                                                                                                     plan




© 2011 Bob Prieto

PM World Today is a free monthly eJournal - Subscriptions available at http://www.pmworldtoday.net                  Page 5
PM World Today – March 2011 (Vol XIII, Issue III)


    Ethics Training           Owner                 Supplementary Status of                          Status of
    and                       Policies and          requirements if training and                     training and
    Compliance                associated            any             compliance;                      compliance;
                              training                              Areas of                         Areas of
                                                                    concern -                        concern -
                                                                    program level                    projects level
    Insurance                 Owner                 Supplementary Program                            Project
                              Policies              requirements if insurance                        insurance
                                                    any             claims and                       claims and
                                                                    costs                            costs
    Knowledge                 Owner                 KM              Summary                          Project level
    Management                Framework             implementation level of                          activity
                              System                plan            activity
    Legal                     Applicable            Regulatory and Claims; suits;           Status of
                              Laws and              permitting plan Issue                   approvals;
                              regulations;                          analysis                compliance
                              Owner                                                         assessment of
                              Policies                                                      projects
    Life-Cycle Cost           Owner                 Sustainable              Exceptional    VIP status for
    Analysis                  Policies              development              item reporting projects
                                                    plan
    Material                  Owner                 Supply chain             Supply chain            Supply chain
    Management                Policies              plan; SRAs;              issues and              status for
                                                    Owner                    trends                  projects
                                                    furnished
                                                    material and
                                                    equipment
    Operations &              Owner                 O&M Training             Turnover                O&M
    Maintenance               Policies              and turnover             program                 deliverable
                                                    plan                     status                  status
    Procurement               Owner                 Procurement              Procurement             Procurement
                              Policies              Plan                     status                  status by
                                                                             summary;                project
                                                                             Major
                                                                             planned
                                                                             procurements
    Productivity                                    Programmatic             Aggregate               Project
                                                    and project              productivity            productivity
                                                    level                    factor                  factors
                                                    assumptions




© 2011 Bob Prieto

PM World Today is a free monthly eJournal - Subscriptions available at http://www.pmworldtoday.net                    Page 6
PM World Today – March 2011 (Vol XIII, Issue III)


    Project                   Owner                 Supplementary            Exceptional    Incident
    Security                  Policies              requirements if          item reporting reporting
                                                    any
    Risk                      Owner                 Program Risk             Program Risk            Risk
    Management                Policies and          Management               Assessment;             assessment
                              associated            Plan                     Risk Reserve            and status by
                              training                                       status and              project; Risk
                                                                             forecast;               management
                                                                             Major risk              plan
                                                                             items under             implementation
                                                                             management
    Safety                    Owner                 Safety Case;             Program        Project safety
                              Policies              HSE Program;             Safety         plan status;
                                                    Sustainability           Performance;   safety
                                                    Program                  Root cause     performance;
                                                                             analysis       status of safety
                                                                                            training;
                                                                                            incident
                                                                                            analysis
    Standardization                                 Program                  Exceptional    Compliance
                                                    standards                item reporting assessment;
                                                                                            Lessons
                                                                                            learned and
                                                                                            best practices
    Technology                Owner                 Program                  Exceptional    Implementation
                              Policies              technology               item reporting status
                                                    plans as
                                                    required
    Training                  Owner                 Supplementary Capacity                           Implementation
                              Policies              requirements if building                         status
                                                    any             status and
                                                                    needs
                                                                    assessment




© 2011 Bob Prieto

PM World Today is a free monthly eJournal - Subscriptions available at http://www.pmworldtoday.net               Page 7
PM World Today – March 2011 (Vol XIII, Issue III)


   Governance                  PMO                    PMDS                   Program                 Project
   Structures                  Element                Element                Dashboard               Dashboard
                                                                             Metric                  Metric

   Leadership                                         Leadership             career                  Program
                                                      training               development             status; 360
                                                      program;               program                 feedback
                                                      career                 status; 360             metrics
                                                      development            feedback
                                                      program; 360
                                                      feedback
   Alignment                   Alignment              Alignment              Status of               Status of
                               process                process with           program and             project
                               between                projects               project level           alignment
                               DOT and                                       alignment               activities
                               PMC                                           activities
   Responsibility &            Investment             RACI                   Completion of   Implementatio
   Authority                   decision                                      RACI            n and
                               process;                                                      compliance
                               RACI go-by                                                    with RACI
   Program &                   Go-By                  PMM and                Completness     PEP complete
   Project Delivery            documents              program                of PMM and      and
   System &                                           standards              program         implementatio
   Standards                                                                 standards       n status
   Integration                 DOT wide               Program                Major conflicts Interface
                               integration            integration            between         management
                               standards              standards;             contracts       status
                                                      Interface
                                                      Management
                                                      plan
   Assurance                   Strategic              Program                Open                    Project Audit
                               Audit Plan             Audit Plan             strategic audit         status and
                                                                             issues;                 results
                                                                             Project Audit
                                                                             status and
                                                                             result analysis
   Stakeholder                 Coordinated            Stakeholder            Major                   Project level
   Engagement                  DOT                    Management             upcoming                stakeholder
                               Stakeholder            for others not         stakeholder             engagement
                               Management             reserved at            events;                 activities;
                               Plan                   DOT level              outstanding             outstanding
                                                                             top                     project specific
                                                                             stakeholder             issues

© 2011 Bob Prieto

PM World Today is a free monthly eJournal - Subscriptions available at http://www.pmworldtoday.net                   Page 8
PM World Today – March 2011 (Vol XIII, Issue III)


                                                                               issues




     Key                         Stategic               Project and            Achievement             Project report
     Performance                 Business               contract KPI's         of SBOs;                cards detailed
     Indicators                  Objectives                                    project report          against kpis
                                                                               card summary
     Improvement                 Business               VPI's                  Program VPI             Project VPI
                                 Improvement                                   summary                 results
                                 Plan


Organizational            PMO Element                PMDS Element                Program                  Project
Change                                                                           Dashboard                Dashboard
Management                                                                       Metric                   Metric

Vision                    Surface                    Organizational              OTP Status
                          Transportation             Transformation
                          Master Plan                Plan (OTP)
                          (STMP)
Resistance                                           Organizational              OTP Status
Management                                           Transformation
Plan                                                 Plan
Communications Owner                                 Program and                 Communications Project
Plan           Communications                        Project                     Plan Status and Communications
               Plan                                  Communications              Effectiveness   status
                                                     Plan
Organizational                                       Organizational              OTP Status
Transformation                                       Transformation
                                                     Plan
Measurement               Peer Review                360 Review                  Peer and 360
                                                                                 Review open
                                                                                 items
Feedback                  Peer Review                360 Review                  Peer and 360
                                                                                 Review open
                                                                                 items
Lessons                   Knowledge                                              Status of
Learned                   Management                                             knowledge
                          (KM) community                                         submittals to KM

  © 2011 Bob Prieto

  PM World Today is a free monthly eJournal - Subscriptions available at http://www.pmworldtoday.net                 Page 9
PM World Today – March 2011 (Vol XIII, Issue III)




       Strategy                   PMO                  PMDS                  Program                 Project
                                  Element              Element               Dashboard               Dashboard
                                                                             Metric                  Metric

       Strategic                  Strategic            Program               Program KPI             Project KPI
       Business                   Business             and Projects          Performance             performance
       Objectives                 Objectives           KPI's



       Continuous                PMO                   PMDS                  Program                 Project
       Improvement               Element               Element               Dashboard               Dashboard
                                                                             Metric                  Metric

       Knowledge                 Knowledge  Knowledge                        KM statistics
       Management                Management Management
                                 System     System as
                                            integral tool
       Value Capture                        VIP                              VIP status              VIP status
                                            Practices                        report                  report
       Lessons                              Lesson                           Reports                 Reports
       Learned                              Learned                          completed               completed
                                            Report                           and input to            and input to
                                                                             KM                      KM
       Best Practices                                  Best                  G0-bys
                                                       Practice Go-          completed
                                                       by                    and input to
                                                                             KM




© 2011 Bob Prieto

PM World Today is a free monthly eJournal - Subscriptions available at http://www.pmworldtoday.net                  Page 10
PM World Today – March 2011 (Vol XIII, Issue III)


      Assessment                 PMO                 PMDS                  Program                   Project
                                 Element             Element               Dashboard                 Dashboard
                                                                           Metric                    Metric

      Metric Priority                                Program and           Dashboard                 Dashboard
                                                     Projects              emphasizes                emphasizes
                                                     Dashboard             top priority              top priority
                                                                           metrics; other            metrics; other
                                                                           metrics                   metrics readily
                                                                           readily                   available
                                                                           available
      Metric                                         Extent of
      Usefulness                                     usage
      Metric                                         Robustness
      Measurement                                    of data
      Metric Review                                  Periodic
                                                     report
                                                     effectiveness
                                                     assessment
      Metric                                         Program and Metric change Metric change
      Realignment                                    Projects      notice      notice
                                                     Dashboard


References:

   1. Strategic Program Management; published by the Construction Management
      Association of America (CMAA); ISBN 978-0-9815612-1-9; July 24, 2008




© 2011 Bob Prieto

PM World Today is a free monthly eJournal - Subscriptions available at http://www.pmworldtoday.net                 Page 11
PM World Today – March 2011 (Vol XIII, Issue III)




       About the Author:



                                    Bob Prieto

                                    Author




                             Bob Prieto is a Senior Vice President of Fluor Corporation,
                             one of America’s largest engineering, construction and
     project management firms, where he is responsible for strategy in support of the
     firm’s Industrial & Infrastructure Group and its key clients. He focuses on the
     development, delivery and oversight of large, complex projects worldwide. Prior
     to joining Fluor, Bob served as chairman of Parsons Brinckerhoff Inc. He served
     as a member of the executive committee of the National Center for Asia-Pacific
     Economic Cooperation, a member of the Industry Leaders’ Council of the
     American Society of Civil Engineers (ASCE), and co-founder of the Disaster
     Resource Network. He currently serves on a number of committees looking at
     issues related to infrastructure delivery and resiliency and disaster response and
     rebuilding. Until 2006 he served as one of three U.S. presidential appointees to
     the Asia Pacific Economic Cooperation (APEC) Business Advisory Council
     (ABAC) and previously served as chairman of the Engineering and Construction
     Governors of The World Economic Forum and co-chair of the infrastructure task
     force formed after September 11th by the New York City Chamber of
     Commerce. He recently completed a ten year tenure as a member of the board
     of trustees of Polytechnic University of New York culminating in its merger with
     New York University. Bob is the author of “Strategic Program Management”
     published by the Construction Management Association of America (CMAA) and
     more recently a companion work entitled “Topics in Strategic Program
     management”.




© 2011 Bob Prieto

PM World Today is a free monthly eJournal - Subscriptions available at http://www.pmworldtoday.net   Page 12

Program Management Dashboards

  • 1.
    PM World Today– March 2011 (Vol XIII, Issue III) PM WORLD TODAY – FEATURED PAPER – MARCH 2011 Program Management Dashboards By Bob Prieto What is a dashboard? Dashboards and “Balanced Scorecards” have been proposed as a communication tool and executive summary of program performance. They can capture a variety of inputs and display them in one place. In some ways it is where “Analog aesthetics meets digital information”. Operational dashboards focus on managing and measuring business and process activities in real time or near-real time. Operational dashboards provide deep visibility at an overall program level, on a specific business area or business process activity. Key Performance Indicators (KPIs) and metrics are typically displayed by an assortment of dials, gauges and stoplights that resemble those found in a commercial plane cockpit. A method to incorporate statistical process control (SPC) and colors was first proposed at the US Department of Energy’s Hanford in 1997 (“Stoplight Charts with SPC Inside” published by American Society for Quality 2004) and put in place as the Fluor Hanford Dashboard in FY 2005. It utilized existing and familiar performance indicators. Control Chart Decision Color Leadership Result Action Stable Level is Green Stay the Course (common Acceptable cause variation) Level is Not Yellow Improve System Acceptable Trend Adverse Red Corrective (special cause Action variation) Improving Green Reinforce – Stay the Course © 2011 Bob Prieto PM World Today is a free monthly eJournal - Subscriptions available at http://www.pmworldtoday.net Page 1
  • 2.
    PM World Today– March 2011 (Vol XIII, Issue III) In Oregon, the Oregon Department of Transportation's OTIA III State Bridge Delivery Program dashboard was used to status progress to stakeholders. Deeper drill downs provided management information. Source: Fluor But to be effective the dashboard must really track all key program dimensions since a failure in any one can undermine the program. I will not dwell on the graphic portrayal but rather spend the next bit looking at some of the key elements to be tracked and in what form they should be tracked and by whom. Selection of measures is a key step in effective management of any program. The dashboard must reflect the strategic business objectives that the program is trying to achieve; key dimensions to assess strategy effectiveness; and key process and control factors to assure true progress is being made towards the strategic business objectives. Many times measures are chosen without adequate attention given to the driving strategic business objectives. In those instances the program team tracks measures and then tries to figure out what the objectives are. The selection of dashboard parameters must include leading and trending indicators not just historical ones. © 2011 Bob Prieto PM World Today is a free monthly eJournal - Subscriptions available at http://www.pmworldtoday.net Page 2
  • 3.
    PM World Today– March 2011 (Vol XIII, Issue III) Let’s return to our Strategic Program Management1 system. The major processes and dimensions displayed provide a good starting point for constructing a program management dashboard. The example that follows is for a large public transport program and each major dimension is reflected in a separate table. Specific program requirements and objectives will modify certain elements of these tables but they represent a good analog for dashboard development. © 2011 Bob Prieto PM World Today is a free monthly eJournal - Subscriptions available at http://www.pmworldtoday.net Page 3
  • 4.
    PM World Today– March 2011 (Vol XIII, Issue III) Framework Program Program Program Project Processes Management Management Dashboard Dashboard Office (PMO) Delivery Metric Metric Element System (PMDS) Element Audits Program Project Audit Program Project and Audit Plan Plan Audit status; functional top open audits status; findings top open findings Budgeting, Program Project Budget Program Project budget Fund Budget budget performance; Management status; earned value; and Allocation, program cash projected cost Expenditure flow; profile of at completion expenditures; costs, expenditures and commitments to date Approval, and Funding Project Budget Sources and Project Tracking of Plan (Authorized) uses of payments to Funds funds; date; contract Committed and funding amounts Expended requirements outstanding; for next projected total period funding to completion Change Impact Program CIA Process Projected Projected Assessment Change impacts of impacts of (CIA) Request approved and approved and Process pending pending programmatic project changes changes Configuration PMO Go-By PMDS Compliance Compliance Management Documents with go-by with PMDS documents © 2011 Bob Prieto PM World Today is a free monthly eJournal - Subscriptions available at http://www.pmworldtoday.net Page 4
  • 5.
    PM World Today– March 2011 (Vol XIII, Issue III) Constructability Labor, Contracting Compliance Means & Analysis – Supplier Strategy; with Labor, Methods; Root Systemic Policies Supply Chain Supplier cause Analysis Strategy; Policies; Means & Contracting Methods Strategy; Supply Chain Strategy Construction Construction Project Start of major Construction Mobilization affecting Execution Plan construction mobilization policies activities; status and ribbon cutting issues dates Construction Owner Owner Owner Technology furnished furnished furnished equipment; equipment equipment Value major issues; major issues; Improvement VIP status VIP status and Plans (VIP) and results results; productivity factor assessment Contingency Owner Program Owner level Program level Management controlled controlled contingency contingency contingency; contingency; remaining by remaining by Program Program Risk type; Current source and Risk Management programmatic type; Current Management program; risk project risk program Projects Risk assessment assessment Management programs Cost Owner Event Estimated cost Programmatic Project cost Estimating Risk to complete - cost trends trends and Assessment program and and forecast forecast cost at projects cost at completion; completion cost recovery plan © 2011 Bob Prieto PM World Today is a free monthly eJournal - Subscriptions available at http://www.pmworldtoday.net Page 5
  • 6.
    PM World Today– March 2011 (Vol XIII, Issue III) Ethics Training Owner Supplementary Status of Status of and Policies and requirements if training and training and Compliance associated any compliance; compliance; training Areas of Areas of concern - concern - program level projects level Insurance Owner Supplementary Program Project Policies requirements if insurance insurance any claims and claims and costs costs Knowledge Owner KM Summary Project level Management Framework implementation level of activity System plan activity Legal Applicable Regulatory and Claims; suits; Status of Laws and permitting plan Issue approvals; regulations; analysis compliance Owner assessment of Policies projects Life-Cycle Cost Owner Sustainable Exceptional VIP status for Analysis Policies development item reporting projects plan Material Owner Supply chain Supply chain Supply chain Management Policies plan; SRAs; issues and status for Owner trends projects furnished material and equipment Operations & Owner O&M Training Turnover O&M Maintenance Policies and turnover program deliverable plan status status Procurement Owner Procurement Procurement Procurement Policies Plan status status by summary; project Major planned procurements Productivity Programmatic Aggregate Project and project productivity productivity level factor factors assumptions © 2011 Bob Prieto PM World Today is a free monthly eJournal - Subscriptions available at http://www.pmworldtoday.net Page 6
  • 7.
    PM World Today– March 2011 (Vol XIII, Issue III) Project Owner Supplementary Exceptional Incident Security Policies requirements if item reporting reporting any Risk Owner Program Risk Program Risk Risk Management Policies and Management Assessment; assessment associated Plan Risk Reserve and status by training status and project; Risk forecast; management Major risk plan items under implementation management Safety Owner Safety Case; Program Project safety Policies HSE Program; Safety plan status; Sustainability Performance; safety Program Root cause performance; analysis status of safety training; incident analysis Standardization Program Exceptional Compliance standards item reporting assessment; Lessons learned and best practices Technology Owner Program Exceptional Implementation Policies technology item reporting status plans as required Training Owner Supplementary Capacity Implementation Policies requirements if building status any status and needs assessment © 2011 Bob Prieto PM World Today is a free monthly eJournal - Subscriptions available at http://www.pmworldtoday.net Page 7
  • 8.
    PM World Today– March 2011 (Vol XIII, Issue III) Governance PMO PMDS Program Project Structures Element Element Dashboard Dashboard Metric Metric Leadership Leadership career Program training development status; 360 program; program feedback career status; 360 metrics development feedback program; 360 feedback Alignment Alignment Alignment Status of Status of process process with program and project between projects project level alignment DOT and alignment activities PMC activities Responsibility & Investment RACI Completion of Implementatio Authority decision RACI n and process; compliance RACI go-by with RACI Program & Go-By PMM and Completness PEP complete Project Delivery documents program of PMM and and System & standards program implementatio Standards standards n status Integration DOT wide Program Major conflicts Interface integration integration between management standards standards; contracts status Interface Management plan Assurance Strategic Program Open Project Audit Audit Plan Audit Plan strategic audit status and issues; results Project Audit status and result analysis Stakeholder Coordinated Stakeholder Major Project level Engagement DOT Management upcoming stakeholder Stakeholder for others not stakeholder engagement Management reserved at events; activities; Plan DOT level outstanding outstanding top project specific stakeholder issues © 2011 Bob Prieto PM World Today is a free monthly eJournal - Subscriptions available at http://www.pmworldtoday.net Page 8
  • 9.
    PM World Today– March 2011 (Vol XIII, Issue III) issues Key Stategic Project and Achievement Project report Performance Business contract KPI's of SBOs; cards detailed Indicators Objectives project report against kpis card summary Improvement Business VPI's Program VPI Project VPI Improvement summary results Plan Organizational PMO Element PMDS Element Program Project Change Dashboard Dashboard Management Metric Metric Vision Surface Organizational OTP Status Transportation Transformation Master Plan Plan (OTP) (STMP) Resistance Organizational OTP Status Management Transformation Plan Plan Communications Owner Program and Communications Project Plan Communications Project Plan Status and Communications Plan Communications Effectiveness status Plan Organizational Organizational OTP Status Transformation Transformation Plan Measurement Peer Review 360 Review Peer and 360 Review open items Feedback Peer Review 360 Review Peer and 360 Review open items Lessons Knowledge Status of Learned Management knowledge (KM) community submittals to KM © 2011 Bob Prieto PM World Today is a free monthly eJournal - Subscriptions available at http://www.pmworldtoday.net Page 9
  • 10.
    PM World Today– March 2011 (Vol XIII, Issue III) Strategy PMO PMDS Program Project Element Element Dashboard Dashboard Metric Metric Strategic Strategic Program Program KPI Project KPI Business Business and Projects Performance performance Objectives Objectives KPI's Continuous PMO PMDS Program Project Improvement Element Element Dashboard Dashboard Metric Metric Knowledge Knowledge Knowledge KM statistics Management Management Management System System as integral tool Value Capture VIP VIP status VIP status Practices report report Lessons Lesson Reports Reports Learned Learned completed completed Report and input to and input to KM KM Best Practices Best G0-bys Practice Go- completed by and input to KM © 2011 Bob Prieto PM World Today is a free monthly eJournal - Subscriptions available at http://www.pmworldtoday.net Page 10
  • 11.
    PM World Today– March 2011 (Vol XIII, Issue III) Assessment PMO PMDS Program Project Element Element Dashboard Dashboard Metric Metric Metric Priority Program and Dashboard Dashboard Projects emphasizes emphasizes Dashboard top priority top priority metrics; other metrics; other metrics metrics readily readily available available Metric Extent of Usefulness usage Metric Robustness Measurement of data Metric Review Periodic report effectiveness assessment Metric Program and Metric change Metric change Realignment Projects notice notice Dashboard References: 1. Strategic Program Management; published by the Construction Management Association of America (CMAA); ISBN 978-0-9815612-1-9; July 24, 2008 © 2011 Bob Prieto PM World Today is a free monthly eJournal - Subscriptions available at http://www.pmworldtoday.net Page 11
  • 12.
    PM World Today– March 2011 (Vol XIII, Issue III) About the Author: Bob Prieto Author Bob Prieto is a Senior Vice President of Fluor Corporation, one of America’s largest engineering, construction and project management firms, where he is responsible for strategy in support of the firm’s Industrial & Infrastructure Group and its key clients. He focuses on the development, delivery and oversight of large, complex projects worldwide. Prior to joining Fluor, Bob served as chairman of Parsons Brinckerhoff Inc. He served as a member of the executive committee of the National Center for Asia-Pacific Economic Cooperation, a member of the Industry Leaders’ Council of the American Society of Civil Engineers (ASCE), and co-founder of the Disaster Resource Network. He currently serves on a number of committees looking at issues related to infrastructure delivery and resiliency and disaster response and rebuilding. Until 2006 he served as one of three U.S. presidential appointees to the Asia Pacific Economic Cooperation (APEC) Business Advisory Council (ABAC) and previously served as chairman of the Engineering and Construction Governors of The World Economic Forum and co-chair of the infrastructure task force formed after September 11th by the New York City Chamber of Commerce. He recently completed a ten year tenure as a member of the board of trustees of Polytechnic University of New York culminating in its merger with New York University. Bob is the author of “Strategic Program Management” published by the Construction Management Association of America (CMAA) and more recently a companion work entitled “Topics in Strategic Program management”. © 2011 Bob Prieto PM World Today is a free monthly eJournal - Subscriptions available at http://www.pmworldtoday.net Page 12