PRESENTATION
ON
MAT FOUNDATION
Department of Civil Engineering
1
Presentedby
Name
• Md. Abdul Ahad
• Monisha Podder Puja
• Arafat Chowdhury
• Sabrina Zissan
• Mahbub Al Muhaimin
• Md. Abu Bakar Siddik
• Sabrina Mehenaz
• Tanvir Alam Khan
• Md. Ashraf Ali
• Amit Kumar Baral
ID
• 12-01-03-104
• 12-01-03-110
• 12-01-03-110
• 12-01-03-124
• 12-01-03-129
• 12-01-03-136
• 12-01-03-144
• 12-01-03-149
• 12-01-03-154
• 11-02-03-16
Visited Sites
Arham Tower, Uttara
Pallabi, Mirpur-11
Euro Bangla Real Estate,
Mouchak
MATFoundation
• a primary shallow foundation;
• a large footing extended over the whole
construction area;
• Usually large concrete slab supporting
many columns;
• Commonly used as foundation for high
rise buildings with basement;
• Mat is also known as Raft;
• Usual depth 1~20 feet.
PCC BED
R C C SLAB
C C
Sectional View
Plan View
COLUMN
MAIN BEAM
SECONDARY
BEAM
MAIN BEAM
WhenweconstructMaTfoundation?
• When the area of individual column footings cover
more then 50% area of total land;
• When the bearing capacity of soil is too weak to
support a structure;
• When the cost of deep foundation is higher then
Raft foundation.
• When the structural load is too high.
TypesofMAT
• Flat plate mat
• Plate thickened under columns
• Two-way beam and slab
• Plate with pedestal
• Rigid frame mat
• Piled raft
constructionProcedures
Soil test
Shoring &
Water
proofing
Partial
Excavation
(depending on
depth)
Bracing
(depending on
depth)
Full area
excavation
Soil compaction
BFS & CC or LC
layer cover
Reinforcement
placing
Shuttering
Casting &
Compaction
Shuttering
removal
Curing
SoilTest
• Bearing capacity of
soil;
• Soil classification;
• Ground water level;
• Moisture content;
• Appropriation & depth
of MAT.
Shoring
• Shoring is commonly used when installing the
foundation;
• Shoring support the surrounding loads until the
underground levels of the building are
constructed.
• Can be of 3 types: Pile shore, steel sheet shore
and timber shore.
Log Shore Pile Shore
Waterproofing
• A layer provided over
shoring to prevent
moisture;
• Cement mortar or steel
sheet layer over
shoring;
• Cement mortar layer is
extended over wire
mesh.
Bracing
• A horizontal support for
the boundary shores
during excavation and
foundation;
• Depends on the depth of
foundation;
• Also known as horizontal
shores.
Otherfactors
Shotcrete leveling layer with
steel mesh
Retaining Wall
King Post
BFSandCC
Layer of bricks
on the earth
Layer of cement
concrete over BFS.
Reinforcementplacing
• Single horizontal reinforcement placing;
• Reinforcement placement to complete the bottom
mesh;
• Column rod placement;
• Vertical rod (chair) placement over bottom mesh to
hold the upper mesh;
• Upper mesh placement.
Importantfactors
Reinforcement Selection
• 60~72.5 Graded
• 12mm~25mm
Reinforcement Joint
• Heavy Steel wire binding
Chair
• Distance
• Bending
Importantfactors
Hook
• Right angled
Rod Cutter
Rod bender
Shuttering
• Steel plate shutter;
• Timber shutter.
CastMaterial
• Mixture ratio 1:2:4;
• Sylhet sand is used
over 50%;
• Stone chips that are
used normally is
½”~¾” in size;
• Stone chips are
preferred than brick
chips.
Casting
• Start from one end;
• Layer basis casting;
• Side basis casting.
Compaction
• By vibrator machine;
• Compaction and
casting both are done
simultaneously;
Precautionsforcasting
• Materials like piece of wood, polythene etc. must be
removed before casting from that area;
Curing

Presentation on Mat Foundation