SlideShare a Scribd company logo
1 of 138
1
CONSTRUCTION
TECHNOLOGY
2
SUBSTRUCTURE
3
Construction activities/stages
Site preparation Sub-structure Super
structure
External work
Site clearing Foundation Building frame roads
earthwork Piling works Upper floors parking
hoarding Under-Ground floor walls drains
Temporary roads Ground beam roofs fencing
Temporary
buildings
Hard core, d.p.c Windows,
doors
turfing
Finishes,
facilities
4
SUBSTRUCTURE
A man-made structure that is
needed to hold the
superstructure in place and to
transmit all forces due to the
superstructure and its use to
whatever the supporting material
may be
5
SUBSTRUCTURE
6
SUBSTRUCTURE’S
ELEMENT
 Foundation
 Underground Floor
 Ground Beam
7
FOUNDATION
Is the base on which a building rests
and its purpose is to safely
transfer the load of a building to a
suitable subsoil.
8
The Building Regulations require all
foundations of buildings to:
 Safely sustain and transmit to the ground the combined
dead and imposed load so as not to cause any settlement
or other movement in any part of the building or any
adjoining buildings or works.
 Be of such a depth, or be so constructed, as to avoid
damage by swelling, shrinkage of the subsoil.
 Be capable of resisting attack by deleterious materials, such
as sulphates, in the subsoil.
Subsoil – soils below the topsoil; the topsoil being about 300mm deep.
9
Typical subsoil bearing capacities
Types Bearing capacities
(KN/m2)
Rocks, granites and chalks 600 – 10,000
Non-cohesive soils, compact
sands;loose uniform sand
100 - 600
Cohesive soil, hard clays, soft clays
and silts
< 600
Peats and made ground To be determined by investigation
10
Terminology
 Backfill – materials excavated from site and if suitable
used to fill in around the walls and foundations.
 Bearing capacity – safe load per unit area which the
ground can carry.
 Bearing pressure – the pressure produced on the ground
by the loads.
 Made ground – refuse, excavated rock or soil deposited
for the purpose of filling in a depression or for raising the
site above its natural level
11
Terminology (cont’d)
 Settlement – ground movement which may
caused by:
-deformation of the soil due to the imposed load.
-volume changes of the soil as a result of seasonal
conditions
-mass movement of the ground in unstable areas.
12
FUNCTIONS OF
FOUNDATION
 To transfering loads
 To avoid settlement
13
FACTOR AFFECTING
THE DESIGN OF
FOUNDATION
 Loading
 Soil
Condition
 Cost
 Technology
14
Loading
 Imposed load
 Dead load
 Wind
15
Soil condition
 Bearing capacity
 Ground water level
 Chemical attack
16
Cost
 Material
 equipments
17
Technology
 Expertise
 Skilled workers
18
Choice of foundation type
 The choice and design of foundations for
domestic and small types of buildings depends
mainly on two factors:
1. the total loads of the building.
2. the nature and bearing capacity of the subsoil.
19
 The total load of a building are taken per metre
run and calculated for the worst case.
 The nature and bearing capacity of the subsoil
can be determined by:
-trial holes and subsequent investigations
-bore holes and core analysis
-local knowledge
20
TYPES OF FOUNDATIONS
1. Shallow Foundation
2. Deep Foundation
21
SHALLOW FOUNDATION
Shallow foundation - when the foundation depth are less then their
structure width
Those which transfer the loads to
subsoil at a point near to the ground
floor of the building.
22
DEEP FOUNDATION
Deep foundations - when the foundation depth is exceeding their
structure width
Those which transfer the loads to a subsoil some
distance below the ground floor of the building.
23
SHALLOW
FOUNDATION
 Isolated/Pad
Foundation
 Raft/Mat Foundation
 Strip Foundation
24
DEEP FOUNDATION
 Pile Foundation
25
Pad Foundations
26
PAD FOUNDATION
A pad used to “spread out”
building column and wall
loads over a sufficiently
large soil area
27
What is Pad Foundation?
Also known as Pad
Base.
The simplest
foundation for a
column in a steel or
reinforced concrete
framed building.
28
PAD FOUNDATION
29
PAD FOUNDATION
30
Steps in pad foundation
 Setting out
 Excavation
 Material preparation –reinforcement,
formwork, cement, aggregates
 Formwork construction
 Reinforcement
 Concrete work –mix, placement,
treatment, compaction, testing
31
Main Types of Pad Foundation
Two main types are common:
Mass Concrete
Reinforced Concrete
32
Mass Concrete
Most economic.
Most commonly used in construction
site.
Simply excavate and pour concrete.
Simple 45o
spread of load from
column to soil formation.
33
Mass Concrete
34
Reinforced Concrete
Avoid reinforcing a base if possible.
Very expensive due to extra preparation.
Intensive inspection is required.
Excavation is open longer.
35
More operations:
Excavate – shutter – pour blinding – fix
reinforcement – inspect – pour concrete
However, the reinforcement allows the
base to behave like a cantilever slab.
Reinforced Concrete (C’td)
36
How To Choose???
Mass Concrete Bases:
Reinforced Concrete Bases:
Use wherever possible.
Unstable excavation.
Quick, economic construction.
High water table.
Adverse changes in soil strata
Thin soil strata.
Buried services/ structures.
Underground obstructions.
37
RAFT FOUNDATION
 Is to spread the load over the entire area
of the site.
 This method is particularly useful where
the column loads are heavy and thus
requiring large bases or where the
bearing capacity is low, again resulting in
the need for large bases.
38
RAFT FOUNDATION
Solid Slab Rafts
Beam and Slab Rafts
Cellular Rafts
3 types of Mat Foundation:
39
Solid Slab Raft
40
SOLID SLAB RAFTS
 Are constructed of a uniform thickness over the whole raft
area, which can be wasteful since the design must be based
on the situation where the heaviest load occurs.
 The effect of the load from columns and the ground
pressure is to create areas of tension under the columns
and the areas of tension in the upper part of the raft
between the column.
 Very often a nominal mesh of reinforcement is provided in
the faces where tension does not occur to control shrinkage
cracking of the concrete.
41
Beam and Slab Raft
42
Beam and slab rafts
 As an alternative to the solid slab raft and are used where
poor soils are encountered.
 The beams are used to distribute the column loads over the
area of the raft, which usually results in a reduction of the
slab thickness.
 The beams can be upstand or downstand depending upon
the bearing capacity of the soil near the surface.
 Downstand beams will give a saving on excavation costs
whereas upstand beams create a usable void below the
ground floor if a suspended slab is used.
43
Cellular Raft
44
Cellular rafts
 Can be used where a reasonable bearing capacity
subsoil can only be found at depths where beams
and slab techniques become uneconomic.
 The construction is similar to reinforcement
basement except that the internal walls are used
to spread the load over the raft and divide the
void into cells.
 Openings can be formed in the cell walls allowing
the voids to be utilised for the housing of
services, store rooms or general accommodation.
45
RAFT FOUNDATION
46
RAFT FOUNDATION
47
STRIP FOUNDATION
Loads are transmit
through wall
48
 Are used to support and transmit the loads from heavy walls.
 The effect of the wall on the relatively thin foundation is to
act as a point load and the resultant ground pressure will
induce tension on the underside across the width of the strip.
 Tensile reinforcement is therefore required in the lower face
of the strip with distribution bars in the second layer running
longitudinally.
 The reinforcement will also assist the strip in spanning any
weak pockets of soil encountered in the excavation
49
STRIP FOUNDATION
 Ordinary Strip Foundation
 Wide Strip Foundation
 Deep Strip Foundation
50
Ordinary Strip Foundation
51
 Use for single/double storey building
 Good bearing capacity & no shrinkage
52
Wide Strip Foundation
53
 Low bearing capacity
 Use reinforcement, concrete 1:2:4
54
Deep Strip Foundation
-Clayey soil
-The width of the strip footing greater than width of the
wall
-1:3:6
55
Construction process
 Same as pad foundation
 Design is different
 Starting with excavation - backhoe
 No formwork is needed
 After excavation is completed, pour the
concrete (must have good workability)
56
Column inserted in the
ground to transmit the
structural loads to a lower
level of subsoil
PILE FOUNDATION
57
• When bearing strata level is more than 3
meters deep
• Load of building are not uniform
• The live load and dead load coming from
the structure considerably large
• The construction of raft foundation is
economical and the seasonal variation of
ground water level is considerable
Why we use pile ?
58
Piles are classified by :
• The material of which they are formed
• By their manner of installation.
Classification of piles
There are :
• Replacement pile (also known as
bored pile or end bearing)
• Displacement pile (also known
as friction pile or driven pile)
59
Driven pile Bored pile
PILE
Cast In-situ Pre-cast Semi-pre-cast
Concrete Steel Timber
Concrete and timber Concrete and steel
Rotary Flush Percussion
Concrete
60
Piles which are driven, thus displacing the soil and includes
those piles which are perform, partially perform or are driven
in-situ pile
M
A
T
E
R
I
A
L
S
•Timberpile
•Pre-castconcrete
•Sand
•Steel
•Wroughtiron
•Castironand
•Composite
Displacement piles
61
Timber pile
• Trees are used as pile after removing
the bark and cutting of branches
• Most timber piles are fitted with an iron
or steel-driving shoe and have an iron
ring around the head to prevent
splitting due to impact
• The timber piles must be well season
and properly treated
62
• Cut easily
• Quickly driven into the ground
• More cheaper than most of materials
• Skilled supervision is not essential
• Not capable of taking heavy load
• Difficult to drive the pile into hard strata
• A joint in longer pile is a weak spot
• They deteriorate by the action of water,
soil, insect etc
Advantages
Disadvantages
63
Pre-cast concrete pile
Advantages
 The reinforcement is maintained in the correct
position
 The best quality of concrete can be produced
 The proper curing is done
 These piles can be driven under water
 Defects of casting may be examined and repaired
before driving the pile
 Such types of piles have high resistance to
biological and chemical actions of the ground
• Square section with chamfered corner, octagonal, or
round section
• Shoes are provided at the lower end
64
Disadvantages
 These piles are very heavy and difficult to transport
 The shocks and vibrations render them weaker
 Extra reinforcement is essential to take care of
handling and driving stresses
 A weak joint is formed in case of lapping additional
length
 Progress of work at the site may go delayed due to
inadequate supply of piles at short notices
 If proper care is not taken, the piles may be damaged
during transportation and driving
65
Pile Driving
• Piles is driven into the ground by holding them in the
correct position against the piling frame and applying
hammer blows to the head of the piles
• Pile hammers come in a variety of type and sizes
powered by gravity, steam, compressed air or diesel
Drop hammers
• Single acting hammer - use steam or air pressure to
raise the ram
• Double acting hammer - the double acting utilizes steam or
air pressure to power both the up and down strokes
of the hammer ram
Threetypes of driving piles that are commonlyuse :
66
Diesel hammer
Internal combustion hammer, which utilizes
the explosion of the diesel fuel between
the bottom of ram and the anvil block
Vibratory driver
Cause penetration of the pile into the soil
by exciting the pile with either non-
resonant or resonant longitudinal
vibration
67
Replacement pile
 Formed by removing a column of soil and
replacing with in-situ concrete or as in the
case of composite piles with pre-cast and in-
situ concrete
There are three typesof replacement :
• Precussion bored piles
• Rotary bored piles
• Prestcore piles
68
Bored Piles
 Bored cast-in-place piles
 Grout or concrete intruded piles
69
Bored Cast-in-Place Piles
 Small-diameter percussion bored cast-in-
place piles
 Large-diameter percussion bored piles
 Rotary bored cast-in-place piles
70
Small-diameter percussion
bored cast-in-place piles
 Minimum pile diameter = 300mm
 Maximum pile diameter = 600mm
 Boreholes formed by rigs used in site
investigation.
 Cohesive soil – Clay Cutter
 Granular soil – shell
71
Tripod rig for drilling boreholes
72
Tripod rigs are light, easily transported,
low headroom required.
73
Typical cutting tool used in small diameter
bored cast-in-place piles
74
Actual cutting tool used in construction
75
Shell for small-diameter
percussion bored piles
76
Large-diameter percussion
bored cast-in-place piles
 Size of boreholes with diameter 600mm or
more.
 well suited to the penetration of hard
strata, which may include weak
sedimentary rock
 Uses semi-rotary down-hole percussive
hammer rigs.
 Example : Libore rig by Lilley Construction
77
Libore boring rig
78
Rotary bored cast-in place
piles
 Large boreholes from 750mm up to 3m
diameter are possible by using rotary
drilling machinery
 A spiral or bucket auger is attached to a
shaft known as a Kelly bar
 Depths of up to 70m
79
 In soft silts and clays, bentonite slurry
is used
 Potential for under reaming
 Underreaming – Technique to enlarge
the base of bored pile to increase the
bearing capacity.
80
Boring tools used in the construction of
rotary bored cast-in-place piles
81
Underreaming
tool in the
closed position
82
Underreaming
tool in the open
or working
positon
83
Continuous-flight augered piles
 Becoming a popular method in pile
construction
 Offer considerable environmental
advantages
 noise and vibration levels are low
 No need for temporary borehole wall
casing or bentonite slurry
84
 Process of construction:
- Screwing the continuous flight auger
into
the ground to the required depth
leaving
the soil in the auger
- Grout (or concrete) can then be
forced
down the hollow shaft of the auger
85
 The auger is lifted out of the ground as
the grout continues to be intruded
 Reinforcement can then be lowered in
before the grout sets
86
Continuous-flight
augered piles with
grout intrusion
87
Step 1
1.1. Set out the positions of the bored piles as per construction drawing.
2.2. Mark the pile positions with pegs.
3.3. Survey the existing ground level at the pile position.
Installation of Bored Pile
88
Step 2
1.1. Mobilize the boring plant to the intended bored pile position.
2.2. Position the centre of the auger exactly above the pile point.
3.3. Check the verticality of the kelly bar before boring commences.
4.4. Offset two reference point perpendicular to each other from the pile position.
89
Step 3
1.1. Commence boring at the pile position.
2.2. Check the verticality of drilled hole during boring works.
90
Step 4
1.1. Observe the stability of borehole during boring works.
2. If the borehole is unstable or collapsible, insert a temporary casing into the borehole.
3. Check the verticality of the temporary casing during installing. Use two plumbs
positioned in perpendicular directions to each other.
91
Step 5
1. Continue boring with an auger or boring bucket depending on the soil condition
as
shown in (a) and (b) next page.
2. Carry out boring until the designed depth is achieved.
3. If hard material is encountered during boring, use chisel or rock tools to
penetrate
into the hard stratum as shown in (c) next two page.
92
Step 6
93
Step 7
94
Step 8
1. After reaching to the required depth, clean the base of the borehole with a cleaning bucket.
2. Verify and confirm the length with client's representative.
95
Step 9
1.Check and ensure the reinforcement and dimensions of the cage are appropriate
for the intended pile. Ensure that the cage is intact for handling.
2.Hoist and transfer the pre fabricated reinforcement cage from the reinforcement
yard to the borehole.
3.Lower the reinforcement cage into the borehole to the cut off level.
4.Ensure that the cage is maintained at the cut off level during concreting works.
96
Step 10
Concreting in dry hole conditions
1.Discharge concrete directly from the concrete truck into the hopper.
2.When concrete has reached above the cut off level, stop concrete works.
3.Ensure that sound concrete has reached above the cut off level.
97
Step 11
Concreting in dry hole conditions
98
Step 12
Concreting in wet hole conditions by tremie method
1.1. Insert the concrete plug at the bottom of tremie pipe hole.
2.2. Lower the tremie pipe to the toe of borehole.
3.3. Discharge concrete directly from the concrete truck into the hopper.
4.4. Fill concrete from the bottom of borehole which displaces the sludge as concrete rises to the top.
99
Step 13
Concreting in wet hole conditions by tremie method
1. Withdraw the tremie pipe as concrete rises upwards.
2. Ensure that the end of tremie pipe is embedded into the concrete at all times during concreting works.
3. When concrete has reached above the cut off level, the tremie pipe is withdrawn completely.
4. Ensure that sound concrete has reached above the cut off level.
100
Step 14
1. Extract the temporary casing from the borehole upon completion of concreting works.
2. Ensure that the temporary casing is extracted vertically.
101
Bored Cast-in-situ Piles - Special
techniques to improve Bearing Capacity
Underreaming - When
employing the rotary
excavation method, an
enlarged base
(underream), also known
as bell, can be created,
which increases the base
bearing capacity of piles
in competent soil strata.
102
Advantages of Bored Piles
Length can be readily varied to suit varying ground conditions
Can be installed in very large diameters
End enlargements up to two or three diameters are possible in clays
Material of pile is not dependent on handling or driving conditions
Can be installed in very long lengths
Can be installed without appreciable noise or vibration
Can be installed in conditions of very low head-room
No risk of ground heave
103
Disadvantages of Bored Piles
Susceptible to "waisting" or "necking" in "squeezing"
ground.
Concrete is not placed under ideal conditions and
cannot be subsequently inspected.
Enlarged ends cannot be formed in cohesionless
materials.
Cannot be readily extended above ground level
especially in river and marine structures.
104
Precussion Bored Piles
 Suitable for small and medium-sized contracts of up
to 300 piles in both either clay or gravel subsoil
 The steel lining tube usually sink under its own
weight but it also can driven by using slight pressure
for example hydraulic jacks
 Usually compressed air is use to tamp and
considerate the concrete but we can also use internal
drop hammer
 Figure
Back
105
Rotary Bored Piles
 Large diameter piles are bored using rotary method
 The rotary bored piles are suitable for most cohesive
soils such as clay and are formed using auger
 Compaction of the concrete usually by a tremie pipe,
is generally by gravitational force
 Test loading of large-diameter bored piles can be very
expensive and it can render this method uneconomic
Back
106
Prestcore piles
 Formed of composite pile consisting of pre-cast in-situ concrete.
 Concreting in ‘dry’ bores
 Formation of a prestcore pile can be divided into four distinct stages :
1) Boring Lined borehole formed by percussion methods using
tripods rig
2) Assembly pre-cast units that form the core of the piles core
of the pile are assembled on
special mandrel and reinforcement is inserted before the
core unit is lowered into position
3) Pressing the core, raising and lowering the pile core by
means of a pneumatic winch attached to the head of the
lining tube to consolidate the bearing stratum
4) Grouting Withdrawal of the lining tube and grouting with the
aid of compressed air to expel any ground water
107
PILE GROUP
 A group of pile which act in the dual role of reinforcing the
soil, and also of carrying the applied load down to deeper,
stronger soil strata
 On the top of group piles, pile cap with reinforcement was
formed. The cap is form clear of the ground will be call a
freestanding group
PILE
COLUMN
PILE CAP
108
PILE TESTING
Loading test
The function of loading test are to :
a) Determine the load – settlement relationship
b) Serve as a proof test to ensure failure does not
occur and the value of the multiple is then
treated as a factor of safety
c) Determine the real ultimate bearing capacity
109
•MaintainedLoad Test
The procedure is to apply the load in stage being
maintained constant until the resulting settlement of the
pile substantially ceases before increasing the load to
the next higher stage
•ConstantRate Of Penetration Test
To understand the test it is helpful to regard the pile as a
device for testing the soil, and the piles movement as the
means of mobilizing the resisting forces
There are two test that commonly used :
110
Shoes for concrete piles
 Steel or cast-iron shoes with pointed or flat
ends
 Generally fitted to the concrete piles for
driving through coarse granular soils or
weak rock
 In uniform clays or sands, shoes are not
usually necessary
 Figure
111
Drive head
 Use to hold the head of timber, pre-cast
concrete, steel pipe or steel H-pile in
position under the hammer
 Distribute the hammer blow to the pile
head
 Also known as a drive cap, bonnet, hood,
helmet or follower
112
Pile caps
 Apart from the simple situations such as
domestic dwellings, or where large diameter
piles are employed
 To provide structural continuity - the
reinforcement in the piles is bonded into the pile
cap
 The head of piles also penetrate the base of the
pipe cap some 100 to 150 mm to ensure
continuity of the members
 Figure
Other picture
113
Rotary piling
Back
114
Driven pile
115
Piling equipment
Hammer
Shoe pile
Crane
116
Piling work
Jetting pile
117
Dynamic pile test
Driven pile
Finish
118
Back
119
DRIVE HEAD
Back
120
PILE CAPS
121
Back
122
Single acting hammer
Back
123
Double acting hammer
Back
124
Back
125
Back
126
Back
127
Load test
Back
128
Problem in pile construction
 Driven pile
1. Design and manufacture
2. Installation of driven pile
3. Associated ground movements
4. Noise and ground vibration
129
 Bored pile
1. Excavation of the pile bored
-Over break
-Base of bored hole
-Effect of water in bored holes
2. Concreting the pile
-Quality of the concrete
-Placing concrete
-Extracting temporary casing
-Problem in soft ground
-Effect of ground water
2. Design of pile reinforcement
3. Piles constructed with the aid of drilling mud
130
Installation of driven piles
Damage to head of pre-cast
Buckling of steel H-pile
driven into boulder clay
Buckling of sheet steel piling
131
Over break
Bulbous projection on pile
shaft caused by over break
132
Base of bored hole
Blocks of clay fallen from under ream of
pile Toe of small-diameter pile
filled with silt prior to
133
Effect of water in bored holes
Toe of pile after concreting
with water in bore
134
Quality of the concrete
The effect of low slump concrete
135
Extracting temporary casing
Separation of pile
shaft caused by
extraction of casing
Defect in pile shaft
caused by water
The effect of a large
water-filled cavity
Defect caused by concrete
slumping into a dry cavity
136
Problem in soft ground
The consequent of ‘topping-up’
after extraction of casing
Waisting of a cast-in-place pile
137
Effect of ground water
Erosion of wet concrete by
groundwater flow : pile in fill
138
Design of pile reinforcement
Defects associated with
displacement of reinforcement

More Related Content

Similar to bulding foundation for costruction (6).ppt

Similar to bulding foundation for costruction (6).ppt (20)

Types of deep foundation
Types of deep foundationTypes of deep foundation
Types of deep foundation
 
Foundation ppt
Foundation  pptFoundation  ppt
Foundation ppt
 
Foundations
FoundationsFoundations
Foundations
 
Underpinning
UnderpinningUnderpinning
Underpinning
 
Introduction to Types of Foundation
Introduction to Types of FoundationIntroduction to Types of Foundation
Introduction to Types of Foundation
 
Ct assignment
Ct assignmentCt assignment
Ct assignment
 
Construction Technology Report
Construction Technology ReportConstruction Technology Report
Construction Technology Report
 
Ct assignment
Ct assignmentCt assignment
Ct assignment
 
REPORT ON ANALYSIS OF CONSTRUCTION SEQUENCES
REPORT ON 	ANALYSIS OF CONSTRUCTION SEQUENCES REPORT ON 	ANALYSIS OF CONSTRUCTION SEQUENCES
REPORT ON ANALYSIS OF CONSTRUCTION SEQUENCES
 
Basement construction report
Basement construction reportBasement construction report
Basement construction report
 
Arunkumar BE.ppt
Arunkumar BE.pptArunkumar BE.ppt
Arunkumar BE.ppt
 
UNderpinning.pptx.pdf
UNderpinning.pptx.pdfUNderpinning.pptx.pdf
UNderpinning.pptx.pdf
 
Ct assignment
Ct assignmentCt assignment
Ct assignment
 
Foundation
FoundationFoundation
Foundation
 
Foundations and pavements ce367
Foundations and pavements   ce367Foundations and pavements   ce367
Foundations and pavements ce367
 
Types of Foundation and Site Investigation.pdf
Types of Foundation and Site Investigation.pdfTypes of Foundation and Site Investigation.pdf
Types of Foundation and Site Investigation.pdf
 
Tutorial 2 (1)
Tutorial 2 (1)Tutorial 2 (1)
Tutorial 2 (1)
 
Foundation_(Anshumi Tanna BCT-II).pptx
Foundation_(Anshumi Tanna BCT-II).pptxFoundation_(Anshumi Tanna BCT-II).pptx
Foundation_(Anshumi Tanna BCT-II).pptx
 
Foundation
FoundationFoundation
Foundation
 
7 building construction part 3 foundation - edit
7 building construction part 3   foundation - edit7 building construction part 3   foundation - edit
7 building construction part 3 foundation - edit
 

Recently uploaded

Software Development Life Cycle By Team Orange (Dept. of Pharmacy)
Software Development Life Cycle By  Team Orange (Dept. of Pharmacy)Software Development Life Cycle By  Team Orange (Dept. of Pharmacy)
Software Development Life Cycle By Team Orange (Dept. of Pharmacy)Suman Mia
 
Call for Papers - African Journal of Biological Sciences, E-ISSN: 2663-2187, ...
Call for Papers - African Journal of Biological Sciences, E-ISSN: 2663-2187, ...Call for Papers - African Journal of Biological Sciences, E-ISSN: 2663-2187, ...
Call for Papers - African Journal of Biological Sciences, E-ISSN: 2663-2187, ...Christo Ananth
 
SPICE PARK APR2024 ( 6,793 SPICE Models )
SPICE PARK APR2024 ( 6,793 SPICE Models )SPICE PARK APR2024 ( 6,793 SPICE Models )
SPICE PARK APR2024 ( 6,793 SPICE Models )Tsuyoshi Horigome
 
VIP Call Girls Service Kondapur Hyderabad Call +91-8250192130
VIP Call Girls Service Kondapur Hyderabad Call +91-8250192130VIP Call Girls Service Kondapur Hyderabad Call +91-8250192130
VIP Call Girls Service Kondapur Hyderabad Call +91-8250192130Suhani Kapoor
 
Microscopic Analysis of Ceramic Materials.pptx
Microscopic Analysis of Ceramic Materials.pptxMicroscopic Analysis of Ceramic Materials.pptx
Microscopic Analysis of Ceramic Materials.pptxpurnimasatapathy1234
 
High Profile Call Girls Dahisar Arpita 9907093804 Independent Escort Service ...
High Profile Call Girls Dahisar Arpita 9907093804 Independent Escort Service ...High Profile Call Girls Dahisar Arpita 9907093804 Independent Escort Service ...
High Profile Call Girls Dahisar Arpita 9907093804 Independent Escort Service ...Call girls in Ahmedabad High profile
 
Decoding Kotlin - Your guide to solving the mysterious in Kotlin.pptx
Decoding Kotlin - Your guide to solving the mysterious in Kotlin.pptxDecoding Kotlin - Your guide to solving the mysterious in Kotlin.pptx
Decoding Kotlin - Your guide to solving the mysterious in Kotlin.pptxJoão Esperancinha
 
(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escorts
(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escorts(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escorts
(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escortsranjana rawat
 
Extrusion Processes and Their Limitations
Extrusion Processes and Their LimitationsExtrusion Processes and Their Limitations
Extrusion Processes and Their Limitations120cr0395
 
VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130
VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130
VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130Suhani Kapoor
 
Structural Analysis and Design of Foundations: A Comprehensive Handbook for S...
Structural Analysis and Design of Foundations: A Comprehensive Handbook for S...Structural Analysis and Design of Foundations: A Comprehensive Handbook for S...
Structural Analysis and Design of Foundations: A Comprehensive Handbook for S...Dr.Costas Sachpazis
 
Porous Ceramics seminar and technical writing
Porous Ceramics seminar and technical writingPorous Ceramics seminar and technical writing
Porous Ceramics seminar and technical writingrakeshbaidya232001
 
OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...
OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...
OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...Soham Mondal
 
the ladakh protest in leh ladakh 2024 sonam wangchuk.pptx
the ladakh protest in leh ladakh 2024 sonam wangchuk.pptxthe ladakh protest in leh ladakh 2024 sonam wangchuk.pptx
the ladakh protest in leh ladakh 2024 sonam wangchuk.pptxhumanexperienceaaa
 
Booking open Available Pune Call Girls Koregaon Park 6297143586 Call Hot Ind...
Booking open Available Pune Call Girls Koregaon Park  6297143586 Call Hot Ind...Booking open Available Pune Call Girls Koregaon Park  6297143586 Call Hot Ind...
Booking open Available Pune Call Girls Koregaon Park 6297143586 Call Hot Ind...Call Girls in Nagpur High Profile
 
247267395-1-Symmetric-and-distributed-shared-memory-architectures-ppt (1).ppt
247267395-1-Symmetric-and-distributed-shared-memory-architectures-ppt (1).ppt247267395-1-Symmetric-and-distributed-shared-memory-architectures-ppt (1).ppt
247267395-1-Symmetric-and-distributed-shared-memory-architectures-ppt (1).pptssuser5c9d4b1
 
HARMONY IN THE NATURE AND EXISTENCE - Unit-IV
HARMONY IN THE NATURE AND EXISTENCE - Unit-IVHARMONY IN THE NATURE AND EXISTENCE - Unit-IV
HARMONY IN THE NATURE AND EXISTENCE - Unit-IVRajaP95
 
APPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICS
APPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICSAPPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICS
APPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICSKurinjimalarL3
 
High Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur EscortsHigh Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur EscortsCall Girls in Nagpur High Profile
 

Recently uploaded (20)

Software Development Life Cycle By Team Orange (Dept. of Pharmacy)
Software Development Life Cycle By  Team Orange (Dept. of Pharmacy)Software Development Life Cycle By  Team Orange (Dept. of Pharmacy)
Software Development Life Cycle By Team Orange (Dept. of Pharmacy)
 
Call for Papers - African Journal of Biological Sciences, E-ISSN: 2663-2187, ...
Call for Papers - African Journal of Biological Sciences, E-ISSN: 2663-2187, ...Call for Papers - African Journal of Biological Sciences, E-ISSN: 2663-2187, ...
Call for Papers - African Journal of Biological Sciences, E-ISSN: 2663-2187, ...
 
SPICE PARK APR2024 ( 6,793 SPICE Models )
SPICE PARK APR2024 ( 6,793 SPICE Models )SPICE PARK APR2024 ( 6,793 SPICE Models )
SPICE PARK APR2024 ( 6,793 SPICE Models )
 
VIP Call Girls Service Kondapur Hyderabad Call +91-8250192130
VIP Call Girls Service Kondapur Hyderabad Call +91-8250192130VIP Call Girls Service Kondapur Hyderabad Call +91-8250192130
VIP Call Girls Service Kondapur Hyderabad Call +91-8250192130
 
Microscopic Analysis of Ceramic Materials.pptx
Microscopic Analysis of Ceramic Materials.pptxMicroscopic Analysis of Ceramic Materials.pptx
Microscopic Analysis of Ceramic Materials.pptx
 
9953056974 Call Girls In South Ex, Escorts (Delhi) NCR.pdf
9953056974 Call Girls In South Ex, Escorts (Delhi) NCR.pdf9953056974 Call Girls In South Ex, Escorts (Delhi) NCR.pdf
9953056974 Call Girls In South Ex, Escorts (Delhi) NCR.pdf
 
High Profile Call Girls Dahisar Arpita 9907093804 Independent Escort Service ...
High Profile Call Girls Dahisar Arpita 9907093804 Independent Escort Service ...High Profile Call Girls Dahisar Arpita 9907093804 Independent Escort Service ...
High Profile Call Girls Dahisar Arpita 9907093804 Independent Escort Service ...
 
Decoding Kotlin - Your guide to solving the mysterious in Kotlin.pptx
Decoding Kotlin - Your guide to solving the mysterious in Kotlin.pptxDecoding Kotlin - Your guide to solving the mysterious in Kotlin.pptx
Decoding Kotlin - Your guide to solving the mysterious in Kotlin.pptx
 
(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escorts
(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escorts(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escorts
(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escorts
 
Extrusion Processes and Their Limitations
Extrusion Processes and Their LimitationsExtrusion Processes and Their Limitations
Extrusion Processes and Their Limitations
 
VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130
VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130
VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130
 
Structural Analysis and Design of Foundations: A Comprehensive Handbook for S...
Structural Analysis and Design of Foundations: A Comprehensive Handbook for S...Structural Analysis and Design of Foundations: A Comprehensive Handbook for S...
Structural Analysis and Design of Foundations: A Comprehensive Handbook for S...
 
Porous Ceramics seminar and technical writing
Porous Ceramics seminar and technical writingPorous Ceramics seminar and technical writing
Porous Ceramics seminar and technical writing
 
OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...
OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...
OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...
 
the ladakh protest in leh ladakh 2024 sonam wangchuk.pptx
the ladakh protest in leh ladakh 2024 sonam wangchuk.pptxthe ladakh protest in leh ladakh 2024 sonam wangchuk.pptx
the ladakh protest in leh ladakh 2024 sonam wangchuk.pptx
 
Booking open Available Pune Call Girls Koregaon Park 6297143586 Call Hot Ind...
Booking open Available Pune Call Girls Koregaon Park  6297143586 Call Hot Ind...Booking open Available Pune Call Girls Koregaon Park  6297143586 Call Hot Ind...
Booking open Available Pune Call Girls Koregaon Park 6297143586 Call Hot Ind...
 
247267395-1-Symmetric-and-distributed-shared-memory-architectures-ppt (1).ppt
247267395-1-Symmetric-and-distributed-shared-memory-architectures-ppt (1).ppt247267395-1-Symmetric-and-distributed-shared-memory-architectures-ppt (1).ppt
247267395-1-Symmetric-and-distributed-shared-memory-architectures-ppt (1).ppt
 
HARMONY IN THE NATURE AND EXISTENCE - Unit-IV
HARMONY IN THE NATURE AND EXISTENCE - Unit-IVHARMONY IN THE NATURE AND EXISTENCE - Unit-IV
HARMONY IN THE NATURE AND EXISTENCE - Unit-IV
 
APPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICS
APPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICSAPPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICS
APPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICS
 
High Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur EscortsHigh Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur Escorts
 

bulding foundation for costruction (6).ppt

  • 3. 3 Construction activities/stages Site preparation Sub-structure Super structure External work Site clearing Foundation Building frame roads earthwork Piling works Upper floors parking hoarding Under-Ground floor walls drains Temporary roads Ground beam roofs fencing Temporary buildings Hard core, d.p.c Windows, doors turfing Finishes, facilities
  • 4. 4 SUBSTRUCTURE A man-made structure that is needed to hold the superstructure in place and to transmit all forces due to the superstructure and its use to whatever the supporting material may be
  • 7. 7 FOUNDATION Is the base on which a building rests and its purpose is to safely transfer the load of a building to a suitable subsoil.
  • 8. 8 The Building Regulations require all foundations of buildings to:  Safely sustain and transmit to the ground the combined dead and imposed load so as not to cause any settlement or other movement in any part of the building or any adjoining buildings or works.  Be of such a depth, or be so constructed, as to avoid damage by swelling, shrinkage of the subsoil.  Be capable of resisting attack by deleterious materials, such as sulphates, in the subsoil. Subsoil – soils below the topsoil; the topsoil being about 300mm deep.
  • 9. 9 Typical subsoil bearing capacities Types Bearing capacities (KN/m2) Rocks, granites and chalks 600 – 10,000 Non-cohesive soils, compact sands;loose uniform sand 100 - 600 Cohesive soil, hard clays, soft clays and silts < 600 Peats and made ground To be determined by investigation
  • 10. 10 Terminology  Backfill – materials excavated from site and if suitable used to fill in around the walls and foundations.  Bearing capacity – safe load per unit area which the ground can carry.  Bearing pressure – the pressure produced on the ground by the loads.  Made ground – refuse, excavated rock or soil deposited for the purpose of filling in a depression or for raising the site above its natural level
  • 11. 11 Terminology (cont’d)  Settlement – ground movement which may caused by: -deformation of the soil due to the imposed load. -volume changes of the soil as a result of seasonal conditions -mass movement of the ground in unstable areas.
  • 12. 12 FUNCTIONS OF FOUNDATION  To transfering loads  To avoid settlement
  • 13. 13 FACTOR AFFECTING THE DESIGN OF FOUNDATION  Loading  Soil Condition  Cost  Technology
  • 14. 14 Loading  Imposed load  Dead load  Wind
  • 15. 15 Soil condition  Bearing capacity  Ground water level  Chemical attack
  • 18. 18 Choice of foundation type  The choice and design of foundations for domestic and small types of buildings depends mainly on two factors: 1. the total loads of the building. 2. the nature and bearing capacity of the subsoil.
  • 19. 19  The total load of a building are taken per metre run and calculated for the worst case.  The nature and bearing capacity of the subsoil can be determined by: -trial holes and subsequent investigations -bore holes and core analysis -local knowledge
  • 20. 20 TYPES OF FOUNDATIONS 1. Shallow Foundation 2. Deep Foundation
  • 21. 21 SHALLOW FOUNDATION Shallow foundation - when the foundation depth are less then their structure width Those which transfer the loads to subsoil at a point near to the ground floor of the building.
  • 22. 22 DEEP FOUNDATION Deep foundations - when the foundation depth is exceeding their structure width Those which transfer the loads to a subsoil some distance below the ground floor of the building.
  • 26. 26 PAD FOUNDATION A pad used to “spread out” building column and wall loads over a sufficiently large soil area
  • 27. 27 What is Pad Foundation? Also known as Pad Base. The simplest foundation for a column in a steel or reinforced concrete framed building.
  • 30. 30 Steps in pad foundation  Setting out  Excavation  Material preparation –reinforcement, formwork, cement, aggregates  Formwork construction  Reinforcement  Concrete work –mix, placement, treatment, compaction, testing
  • 31. 31 Main Types of Pad Foundation Two main types are common: Mass Concrete Reinforced Concrete
  • 32. 32 Mass Concrete Most economic. Most commonly used in construction site. Simply excavate and pour concrete. Simple 45o spread of load from column to soil formation.
  • 34. 34 Reinforced Concrete Avoid reinforcing a base if possible. Very expensive due to extra preparation. Intensive inspection is required. Excavation is open longer.
  • 35. 35 More operations: Excavate – shutter – pour blinding – fix reinforcement – inspect – pour concrete However, the reinforcement allows the base to behave like a cantilever slab. Reinforced Concrete (C’td)
  • 36. 36 How To Choose??? Mass Concrete Bases: Reinforced Concrete Bases: Use wherever possible. Unstable excavation. Quick, economic construction. High water table. Adverse changes in soil strata Thin soil strata. Buried services/ structures. Underground obstructions.
  • 37. 37 RAFT FOUNDATION  Is to spread the load over the entire area of the site.  This method is particularly useful where the column loads are heavy and thus requiring large bases or where the bearing capacity is low, again resulting in the need for large bases.
  • 38. 38 RAFT FOUNDATION Solid Slab Rafts Beam and Slab Rafts Cellular Rafts 3 types of Mat Foundation:
  • 40. 40 SOLID SLAB RAFTS  Are constructed of a uniform thickness over the whole raft area, which can be wasteful since the design must be based on the situation where the heaviest load occurs.  The effect of the load from columns and the ground pressure is to create areas of tension under the columns and the areas of tension in the upper part of the raft between the column.  Very often a nominal mesh of reinforcement is provided in the faces where tension does not occur to control shrinkage cracking of the concrete.
  • 42. 42 Beam and slab rafts  As an alternative to the solid slab raft and are used where poor soils are encountered.  The beams are used to distribute the column loads over the area of the raft, which usually results in a reduction of the slab thickness.  The beams can be upstand or downstand depending upon the bearing capacity of the soil near the surface.  Downstand beams will give a saving on excavation costs whereas upstand beams create a usable void below the ground floor if a suspended slab is used.
  • 44. 44 Cellular rafts  Can be used where a reasonable bearing capacity subsoil can only be found at depths where beams and slab techniques become uneconomic.  The construction is similar to reinforcement basement except that the internal walls are used to spread the load over the raft and divide the void into cells.  Openings can be formed in the cell walls allowing the voids to be utilised for the housing of services, store rooms or general accommodation.
  • 47. 47 STRIP FOUNDATION Loads are transmit through wall
  • 48. 48  Are used to support and transmit the loads from heavy walls.  The effect of the wall on the relatively thin foundation is to act as a point load and the resultant ground pressure will induce tension on the underside across the width of the strip.  Tensile reinforcement is therefore required in the lower face of the strip with distribution bars in the second layer running longitudinally.  The reinforcement will also assist the strip in spanning any weak pockets of soil encountered in the excavation
  • 49. 49 STRIP FOUNDATION  Ordinary Strip Foundation  Wide Strip Foundation  Deep Strip Foundation
  • 51. 51  Use for single/double storey building  Good bearing capacity & no shrinkage
  • 53. 53  Low bearing capacity  Use reinforcement, concrete 1:2:4
  • 54. 54 Deep Strip Foundation -Clayey soil -The width of the strip footing greater than width of the wall -1:3:6
  • 55. 55 Construction process  Same as pad foundation  Design is different  Starting with excavation - backhoe  No formwork is needed  After excavation is completed, pour the concrete (must have good workability)
  • 56. 56 Column inserted in the ground to transmit the structural loads to a lower level of subsoil PILE FOUNDATION
  • 57. 57 • When bearing strata level is more than 3 meters deep • Load of building are not uniform • The live load and dead load coming from the structure considerably large • The construction of raft foundation is economical and the seasonal variation of ground water level is considerable Why we use pile ?
  • 58. 58 Piles are classified by : • The material of which they are formed • By their manner of installation. Classification of piles There are : • Replacement pile (also known as bored pile or end bearing) • Displacement pile (also known as friction pile or driven pile)
  • 59. 59 Driven pile Bored pile PILE Cast In-situ Pre-cast Semi-pre-cast Concrete Steel Timber Concrete and timber Concrete and steel Rotary Flush Percussion Concrete
  • 60. 60 Piles which are driven, thus displacing the soil and includes those piles which are perform, partially perform or are driven in-situ pile M A T E R I A L S •Timberpile •Pre-castconcrete •Sand •Steel •Wroughtiron •Castironand •Composite Displacement piles
  • 61. 61 Timber pile • Trees are used as pile after removing the bark and cutting of branches • Most timber piles are fitted with an iron or steel-driving shoe and have an iron ring around the head to prevent splitting due to impact • The timber piles must be well season and properly treated
  • 62. 62 • Cut easily • Quickly driven into the ground • More cheaper than most of materials • Skilled supervision is not essential • Not capable of taking heavy load • Difficult to drive the pile into hard strata • A joint in longer pile is a weak spot • They deteriorate by the action of water, soil, insect etc Advantages Disadvantages
  • 63. 63 Pre-cast concrete pile Advantages  The reinforcement is maintained in the correct position  The best quality of concrete can be produced  The proper curing is done  These piles can be driven under water  Defects of casting may be examined and repaired before driving the pile  Such types of piles have high resistance to biological and chemical actions of the ground • Square section with chamfered corner, octagonal, or round section • Shoes are provided at the lower end
  • 64. 64 Disadvantages  These piles are very heavy and difficult to transport  The shocks and vibrations render them weaker  Extra reinforcement is essential to take care of handling and driving stresses  A weak joint is formed in case of lapping additional length  Progress of work at the site may go delayed due to inadequate supply of piles at short notices  If proper care is not taken, the piles may be damaged during transportation and driving
  • 65. 65 Pile Driving • Piles is driven into the ground by holding them in the correct position against the piling frame and applying hammer blows to the head of the piles • Pile hammers come in a variety of type and sizes powered by gravity, steam, compressed air or diesel Drop hammers • Single acting hammer - use steam or air pressure to raise the ram • Double acting hammer - the double acting utilizes steam or air pressure to power both the up and down strokes of the hammer ram Threetypes of driving piles that are commonlyuse :
  • 66. 66 Diesel hammer Internal combustion hammer, which utilizes the explosion of the diesel fuel between the bottom of ram and the anvil block Vibratory driver Cause penetration of the pile into the soil by exciting the pile with either non- resonant or resonant longitudinal vibration
  • 67. 67 Replacement pile  Formed by removing a column of soil and replacing with in-situ concrete or as in the case of composite piles with pre-cast and in- situ concrete There are three typesof replacement : • Precussion bored piles • Rotary bored piles • Prestcore piles
  • 68. 68 Bored Piles  Bored cast-in-place piles  Grout or concrete intruded piles
  • 69. 69 Bored Cast-in-Place Piles  Small-diameter percussion bored cast-in- place piles  Large-diameter percussion bored piles  Rotary bored cast-in-place piles
  • 70. 70 Small-diameter percussion bored cast-in-place piles  Minimum pile diameter = 300mm  Maximum pile diameter = 600mm  Boreholes formed by rigs used in site investigation.  Cohesive soil – Clay Cutter  Granular soil – shell
  • 71. 71 Tripod rig for drilling boreholes
  • 72. 72 Tripod rigs are light, easily transported, low headroom required.
  • 73. 73 Typical cutting tool used in small diameter bored cast-in-place piles
  • 74. 74 Actual cutting tool used in construction
  • 76. 76 Large-diameter percussion bored cast-in-place piles  Size of boreholes with diameter 600mm or more.  well suited to the penetration of hard strata, which may include weak sedimentary rock  Uses semi-rotary down-hole percussive hammer rigs.  Example : Libore rig by Lilley Construction
  • 78. 78 Rotary bored cast-in place piles  Large boreholes from 750mm up to 3m diameter are possible by using rotary drilling machinery  A spiral or bucket auger is attached to a shaft known as a Kelly bar  Depths of up to 70m
  • 79. 79  In soft silts and clays, bentonite slurry is used  Potential for under reaming  Underreaming – Technique to enlarge the base of bored pile to increase the bearing capacity.
  • 80. 80 Boring tools used in the construction of rotary bored cast-in-place piles
  • 82. 82 Underreaming tool in the open or working positon
  • 83. 83 Continuous-flight augered piles  Becoming a popular method in pile construction  Offer considerable environmental advantages  noise and vibration levels are low  No need for temporary borehole wall casing or bentonite slurry
  • 84. 84  Process of construction: - Screwing the continuous flight auger into the ground to the required depth leaving the soil in the auger - Grout (or concrete) can then be forced down the hollow shaft of the auger
  • 85. 85  The auger is lifted out of the ground as the grout continues to be intruded  Reinforcement can then be lowered in before the grout sets
  • 87. 87 Step 1 1.1. Set out the positions of the bored piles as per construction drawing. 2.2. Mark the pile positions with pegs. 3.3. Survey the existing ground level at the pile position. Installation of Bored Pile
  • 88. 88 Step 2 1.1. Mobilize the boring plant to the intended bored pile position. 2.2. Position the centre of the auger exactly above the pile point. 3.3. Check the verticality of the kelly bar before boring commences. 4.4. Offset two reference point perpendicular to each other from the pile position.
  • 89. 89 Step 3 1.1. Commence boring at the pile position. 2.2. Check the verticality of drilled hole during boring works.
  • 90. 90 Step 4 1.1. Observe the stability of borehole during boring works. 2. If the borehole is unstable or collapsible, insert a temporary casing into the borehole. 3. Check the verticality of the temporary casing during installing. Use two plumbs positioned in perpendicular directions to each other.
  • 91. 91 Step 5 1. Continue boring with an auger or boring bucket depending on the soil condition as shown in (a) and (b) next page. 2. Carry out boring until the designed depth is achieved. 3. If hard material is encountered during boring, use chisel or rock tools to penetrate into the hard stratum as shown in (c) next two page.
  • 94. 94 Step 8 1. After reaching to the required depth, clean the base of the borehole with a cleaning bucket. 2. Verify and confirm the length with client's representative.
  • 95. 95 Step 9 1.Check and ensure the reinforcement and dimensions of the cage are appropriate for the intended pile. Ensure that the cage is intact for handling. 2.Hoist and transfer the pre fabricated reinforcement cage from the reinforcement yard to the borehole. 3.Lower the reinforcement cage into the borehole to the cut off level. 4.Ensure that the cage is maintained at the cut off level during concreting works.
  • 96. 96 Step 10 Concreting in dry hole conditions 1.Discharge concrete directly from the concrete truck into the hopper. 2.When concrete has reached above the cut off level, stop concrete works. 3.Ensure that sound concrete has reached above the cut off level.
  • 97. 97 Step 11 Concreting in dry hole conditions
  • 98. 98 Step 12 Concreting in wet hole conditions by tremie method 1.1. Insert the concrete plug at the bottom of tremie pipe hole. 2.2. Lower the tremie pipe to the toe of borehole. 3.3. Discharge concrete directly from the concrete truck into the hopper. 4.4. Fill concrete from the bottom of borehole which displaces the sludge as concrete rises to the top.
  • 99. 99 Step 13 Concreting in wet hole conditions by tremie method 1. Withdraw the tremie pipe as concrete rises upwards. 2. Ensure that the end of tremie pipe is embedded into the concrete at all times during concreting works. 3. When concrete has reached above the cut off level, the tremie pipe is withdrawn completely. 4. Ensure that sound concrete has reached above the cut off level.
  • 100. 100 Step 14 1. Extract the temporary casing from the borehole upon completion of concreting works. 2. Ensure that the temporary casing is extracted vertically.
  • 101. 101 Bored Cast-in-situ Piles - Special techniques to improve Bearing Capacity Underreaming - When employing the rotary excavation method, an enlarged base (underream), also known as bell, can be created, which increases the base bearing capacity of piles in competent soil strata.
  • 102. 102 Advantages of Bored Piles Length can be readily varied to suit varying ground conditions Can be installed in very large diameters End enlargements up to two or three diameters are possible in clays Material of pile is not dependent on handling or driving conditions Can be installed in very long lengths Can be installed without appreciable noise or vibration Can be installed in conditions of very low head-room No risk of ground heave
  • 103. 103 Disadvantages of Bored Piles Susceptible to "waisting" or "necking" in "squeezing" ground. Concrete is not placed under ideal conditions and cannot be subsequently inspected. Enlarged ends cannot be formed in cohesionless materials. Cannot be readily extended above ground level especially in river and marine structures.
  • 104. 104 Precussion Bored Piles  Suitable for small and medium-sized contracts of up to 300 piles in both either clay or gravel subsoil  The steel lining tube usually sink under its own weight but it also can driven by using slight pressure for example hydraulic jacks  Usually compressed air is use to tamp and considerate the concrete but we can also use internal drop hammer  Figure Back
  • 105. 105 Rotary Bored Piles  Large diameter piles are bored using rotary method  The rotary bored piles are suitable for most cohesive soils such as clay and are formed using auger  Compaction of the concrete usually by a tremie pipe, is generally by gravitational force  Test loading of large-diameter bored piles can be very expensive and it can render this method uneconomic Back
  • 106. 106 Prestcore piles  Formed of composite pile consisting of pre-cast in-situ concrete.  Concreting in ‘dry’ bores  Formation of a prestcore pile can be divided into four distinct stages : 1) Boring Lined borehole formed by percussion methods using tripods rig 2) Assembly pre-cast units that form the core of the piles core of the pile are assembled on special mandrel and reinforcement is inserted before the core unit is lowered into position 3) Pressing the core, raising and lowering the pile core by means of a pneumatic winch attached to the head of the lining tube to consolidate the bearing stratum 4) Grouting Withdrawal of the lining tube and grouting with the aid of compressed air to expel any ground water
  • 107. 107 PILE GROUP  A group of pile which act in the dual role of reinforcing the soil, and also of carrying the applied load down to deeper, stronger soil strata  On the top of group piles, pile cap with reinforcement was formed. The cap is form clear of the ground will be call a freestanding group PILE COLUMN PILE CAP
  • 108. 108 PILE TESTING Loading test The function of loading test are to : a) Determine the load – settlement relationship b) Serve as a proof test to ensure failure does not occur and the value of the multiple is then treated as a factor of safety c) Determine the real ultimate bearing capacity
  • 109. 109 •MaintainedLoad Test The procedure is to apply the load in stage being maintained constant until the resulting settlement of the pile substantially ceases before increasing the load to the next higher stage •ConstantRate Of Penetration Test To understand the test it is helpful to regard the pile as a device for testing the soil, and the piles movement as the means of mobilizing the resisting forces There are two test that commonly used :
  • 110. 110 Shoes for concrete piles  Steel or cast-iron shoes with pointed or flat ends  Generally fitted to the concrete piles for driving through coarse granular soils or weak rock  In uniform clays or sands, shoes are not usually necessary  Figure
  • 111. 111 Drive head  Use to hold the head of timber, pre-cast concrete, steel pipe or steel H-pile in position under the hammer  Distribute the hammer blow to the pile head  Also known as a drive cap, bonnet, hood, helmet or follower
  • 112. 112 Pile caps  Apart from the simple situations such as domestic dwellings, or where large diameter piles are employed  To provide structural continuity - the reinforcement in the piles is bonded into the pile cap  The head of piles also penetrate the base of the pipe cap some 100 to 150 mm to ensure continuity of the members  Figure Other picture
  • 128. 128 Problem in pile construction  Driven pile 1. Design and manufacture 2. Installation of driven pile 3. Associated ground movements 4. Noise and ground vibration
  • 129. 129  Bored pile 1. Excavation of the pile bored -Over break -Base of bored hole -Effect of water in bored holes 2. Concreting the pile -Quality of the concrete -Placing concrete -Extracting temporary casing -Problem in soft ground -Effect of ground water 2. Design of pile reinforcement 3. Piles constructed with the aid of drilling mud
  • 130. 130 Installation of driven piles Damage to head of pre-cast Buckling of steel H-pile driven into boulder clay Buckling of sheet steel piling
  • 131. 131 Over break Bulbous projection on pile shaft caused by over break
  • 132. 132 Base of bored hole Blocks of clay fallen from under ream of pile Toe of small-diameter pile filled with silt prior to
  • 133. 133 Effect of water in bored holes Toe of pile after concreting with water in bore
  • 134. 134 Quality of the concrete The effect of low slump concrete
  • 135. 135 Extracting temporary casing Separation of pile shaft caused by extraction of casing Defect in pile shaft caused by water The effect of a large water-filled cavity Defect caused by concrete slumping into a dry cavity
  • 136. 136 Problem in soft ground The consequent of ‘topping-up’ after extraction of casing Waisting of a cast-in-place pile
  • 137. 137 Effect of ground water Erosion of wet concrete by groundwater flow : pile in fill
  • 138. 138 Design of pile reinforcement Defects associated with displacement of reinforcement