PPT on execution of 680 m long tunnel ensuring safety of the adjoining rail tunnel with controlled blasting and monitoring in maoist affected zone of HDN route of SE Rly.
The said paper by Rajesh Prasad Executive Director RVNL has been published in IPWE international seminar held on 23/24-02-2018. The power point presentation nicely explains about how the technical challenges and administrative challenges addressed in completion of the tunnel while constructing a tunnel by the side of a railway tunnel with train operation in place and the entire area is affected by LWE activities.
The basic principle of BG method is to be extract thick coal seams by drilling and blasting of roof and sides of gallery, which are driven at the bottom at the bottom of the seam at regular intervals.
Blasting gallery method is the appropriate method for the extraction of thick seam.
BLASTING OF RING HOLES PRODUCTION PER RING BLAST EXPLAINED
The basic principle of BG method is to be extract thick coal seams by drilling and blasting of roof and sides of gallery, which are driven at the bottom at the bottom of the seam at regular intervals.
Blasting gallery method is the appropriate method for the extraction of thick seam.
BLASTING OF RING HOLES PRODUCTION PER RING BLAST EXPLAINED
rock excavation, different open cast or open pit excavation machinery, application, limitations, highwall miner, bucket wheel excavatorr, bucket chain excavator, shovels
In this ppt you will get all information regarding shaft sinking. Like what is permanent lining and temporary lining. How to decide shape of shaft, drilling blasting, support, lighting in shaft. Use of shaft and skips.
Longwall; Longwall in coal; Longwall in Hard Rock; Sublevel Caving; Characteristics of the ore body and mining method; Development; Production; Equipments Used; Block Caving, Introduction, Historical evolution of the method, Condition deposit; Principles of the method; Methodology of block caving; Basic issues of geomechanical to the black caving method; Caveability;Mine design Block caving; Fragmentation and extraction control; Subsidence associated; Advantages and Disadvantages of Block Caving
Uses of special kind of technologies for implementation of special kind of st...Rajesh Prasad
The said technical paper was presented by Rajesh Prasad in IC TRAM 2018 (International Conference- Technological Advancement in Railways and Metro Projects at Manekshaw Centre New Delhi on 04.10.2018
Larsen and Toubro (Lucknow Metro Project) Summer Internship PresentationShuBham RaNa
Hello Friends Myself SHUBHAM RANA . I am pursuing B.Tech in Civil Engineering from IIT ROORKEE. This is the glimpse of my work and basic aspects which I learned while doing my Internship in Larsen and Toubro Heavy Civil Infra IC. Thank You :)
rock excavation, different open cast or open pit excavation machinery, application, limitations, highwall miner, bucket wheel excavatorr, bucket chain excavator, shovels
In this ppt you will get all information regarding shaft sinking. Like what is permanent lining and temporary lining. How to decide shape of shaft, drilling blasting, support, lighting in shaft. Use of shaft and skips.
Longwall; Longwall in coal; Longwall in Hard Rock; Sublevel Caving; Characteristics of the ore body and mining method; Development; Production; Equipments Used; Block Caving, Introduction, Historical evolution of the method, Condition deposit; Principles of the method; Methodology of block caving; Basic issues of geomechanical to the black caving method; Caveability;Mine design Block caving; Fragmentation and extraction control; Subsidence associated; Advantages and Disadvantages of Block Caving
Similar to PPT on execution of 680 m long tunnel ensuring safety of the adjoining rail tunnel with controlled blasting and monitoring in maoist affected zone of HDN route of SE Rly.
Uses of special kind of technologies for implementation of special kind of st...Rajesh Prasad
The said technical paper was presented by Rajesh Prasad in IC TRAM 2018 (International Conference- Technological Advancement in Railways and Metro Projects at Manekshaw Centre New Delhi on 04.10.2018
Larsen and Toubro (Lucknow Metro Project) Summer Internship PresentationShuBham RaNa
Hello Friends Myself SHUBHAM RANA . I am pursuing B.Tech in Civil Engineering from IIT ROORKEE. This is the glimpse of my work and basic aspects which I learned while doing my Internship in Larsen and Toubro Heavy Civil Infra IC. Thank You :)
Every Step you need in planning to extend a working open cast mine to underground mine on reaching a pit bottom.
Step-wise procedure to be followed is clearly mentioned.
Justifies the Indian Laws.
Sublevel Stoping method is explained in detail.
Case study of a copper mine is presented for eg.
tunnelling scope, construction techniques and necessityShashank Gaurav
systematic approach of tunnel engineering
Similar to PPT on execution of 680 m long tunnel ensuring safety of the adjoining rail tunnel with controlled blasting and monitoring in maoist affected zone of HDN route of SE Rly. (20)
Opportunities in Railway construction- development operations of infrastructu...Rajesh Prasad
7th RaiIndia Conference and Expo 7th edition was held on 27th Oct 2023 and a presentation was made on "Opportunities in Railway Construction - development/operations of railway infrastructure. This was held at Shangri-La Eros New Delhi and the theme was Next Gen Railways: Smart, Safe and Sustainable....
This is Keynote Address by Rajesh Prasad, Director Operations, Rail Vikas Nigam Ltd dt 11.09.2023 during 20th Safety Convention- Back to Basics for Strengthening EHS and Sustainable Foundation at Hotel Le-Meridien New Delhi being held from 11th to 13th Sept 2023
The presentation on Cyber Security and Data Protection in RVNL is being made on 8th April 2022 before the Board of Directors of RVNL by Rajesh Prasad Director Operations RVNL
"Protocol for safe execution of Infra Projects" by Rajesh Prasad, Director Op...Rajesh Prasad
The said paper presented as KEY NOTE ADDRESS presented by Rajesh Prasad during the 17th Safety Convention on theme- Safety in Mobility held on 17-18th March 2021 at Hotel Le Meridien New Delhi organised by Institution of Engineers (india)
Rebuilding of Railway Infrastructures during the present crisis by Rajesh PrasadRajesh Prasad
Rajesh Prasad Director Operations RVNL participated as a speaker in 5th edition of 'Rail India Conference and Expo' organised under the aegis of MFI Safe Connect (Messe Frankfurt India) in Delhi on 11.03.2021
During the present crisis the whole country is shut down and all the InfraStructure projects have been stopped. Wheels of the Indian Railways carrying passengers have also stopped moving after inception in April 1853. A small ppt has been prepared for the RVNL family.
A Coffee Table Book cum handbook on Cable Stayed Bridge with the 4 approaches...Rajesh Prasad
A 4 lane cable stayed bridge with 4 approaches over a very busy yard at Bardhman of E. Rly is an iconic structure at Bardhman- a gift to the nation by RVNL opened for road traffic yesterday ie 27.09.19. Proud to be the part and head of the team from concept to completion to commissioning.
Engineering for Change... A keynote address on Engineers day- 15th Sep 2019Rajesh Prasad
Engineering for Change... A keynote address on Engineers day- 15th Sep 2019 by Rajesh Prasad, Executive Director RVNL organised by Institute of Engineers in Kolkata
PROTOCOL FOR SAFE EXECUTION OF INFRA PROJECTS BY RAJESH PRASAD ED RVNL DT 04...Rajesh Prasad
The said paper was presented by Rajesh Prasad in IC TRAM 2018 (International Conference- Technological Advancement in Railways and Metro Projects at Manekshaw Centre New Delhi on 04.10.2018
There was a Bridge 2018 Conference on Innovative Technologies of Bridges organised by IIBE at Lucknow. During the conference held on 25.05.18 this paper was presented by Rajesh Prasad, ED Metro RVNL.
Construction Safety Protocol PPT by Rajesh Prasad, ED RVNL at Lucknow on 26.0...Rajesh Prasad
There was a Bridge conference on Innovative Technologies on 25.05.18 and 26.05.18 at Lucknow. This presentation was made by Rajesh Prasad, ED RVNL during the panel discussion. This PPT contains a lot cartoons and images and conveys a big message on ensuring safety at construction worksites.
There was a Bridge 2018 Conference on Innovative Technologies of Bridges organised by IIBE at Lucknow. During the conference held on 25.05.18 this paper was presented by Rajesh Prasad, ED Metro RVNL.
Bridging over river Bhagirathi- a Handbook cum Coffee Table Book by Rajesh Pr...Rajesh Prasad
This is a Handbook cum Coffee Table Book on Bridging over River Bhagirathi (alias Ganges)- Concept to Completion by Rajesh Prasad, Executive Director, Rail Vikas Nigam Ltd (RVNL) depicting from the concept to completion of the Railway Bridge including cantilever launching of the open web girders with span size of 103 m.
Courier management system project report.pdfKamal Acharya
It is now-a-days very important for the people to send or receive articles like imported furniture, electronic items, gifts, business goods and the like. People depend vastly on different transport systems which mostly use the manual way of receiving and delivering the articles. There is no way to track the articles till they are received and there is no way to let the customer know what happened in transit, once he booked some articles. In such a situation, we need a system which completely computerizes the cargo activities including time to time tracking of the articles sent. This need is fulfilled by Courier Management System software which is online software for the cargo management people that enables them to receive the goods from a source and send them to a required destination and track their status from time to time.
Quality defects in TMT Bars, Possible causes and Potential Solutions.PrashantGoswami42
Maintaining high-quality standards in the production of TMT bars is crucial for ensuring structural integrity in construction. Addressing common defects through careful monitoring, standardized processes, and advanced technology can significantly improve the quality of TMT bars. Continuous training and adherence to quality control measures will also play a pivotal role in minimizing these defects.
Hybrid optimization of pumped hydro system and solar- Engr. Abdul-Azeez.pdffxintegritypublishin
Advancements in technology unveil a myriad of electrical and electronic breakthroughs geared towards efficiently harnessing limited resources to meet human energy demands. The optimization of hybrid solar PV panels and pumped hydro energy supply systems plays a pivotal role in utilizing natural resources effectively. This initiative not only benefits humanity but also fosters environmental sustainability. The study investigated the design optimization of these hybrid systems, focusing on understanding solar radiation patterns, identifying geographical influences on solar radiation, formulating a mathematical model for system optimization, and determining the optimal configuration of PV panels and pumped hydro storage. Through a comparative analysis approach and eight weeks of data collection, the study addressed key research questions related to solar radiation patterns and optimal system design. The findings highlighted regions with heightened solar radiation levels, showcasing substantial potential for power generation and emphasizing the system's efficiency. Optimizing system design significantly boosted power generation, promoted renewable energy utilization, and enhanced energy storage capacity. The study underscored the benefits of optimizing hybrid solar PV panels and pumped hydro energy supply systems for sustainable energy usage. Optimizing the design of solar PV panels and pumped hydro energy supply systems as examined across diverse climatic conditions in a developing country, not only enhances power generation but also improves the integration of renewable energy sources and boosts energy storage capacities, particularly beneficial for less economically prosperous regions. Additionally, the study provides valuable insights for advancing energy research in economically viable areas. Recommendations included conducting site-specific assessments, utilizing advanced modeling tools, implementing regular maintenance protocols, and enhancing communication among system components.
Sachpazis:Terzaghi Bearing Capacity Estimation in simple terms with Calculati...Dr.Costas Sachpazis
Terzaghi's soil bearing capacity theory, developed by Karl Terzaghi, is a fundamental principle in geotechnical engineering used to determine the bearing capacity of shallow foundations. This theory provides a method to calculate the ultimate bearing capacity of soil, which is the maximum load per unit area that the soil can support without undergoing shear failure. The Calculation HTML Code included.
Student information management system project report ii.pdfKamal Acharya
Our project explains about the student management. This project mainly explains the various actions related to student details. This project shows some ease in adding, editing and deleting the student details. It also provides a less time consuming process for viewing, adding, editing and deleting the marks of the students.
COLLEGE BUS MANAGEMENT SYSTEM PROJECT REPORT.pdfKamal Acharya
The College Bus Management system is completely developed by Visual Basic .NET Version. The application is connect with most secured database language MS SQL Server. The application is develop by using best combination of front-end and back-end languages. The application is totally design like flat user interface. This flat user interface is more attractive user interface in 2017. The application is gives more important to the system functionality. The application is to manage the student’s details, driver’s details, bus details, bus route details, bus fees details and more. The application has only one unit for admin. The admin can manage the entire application. The admin can login into the application by using username and password of the admin. The application is develop for big and small colleges. It is more user friendly for non-computer person. Even they can easily learn how to manage the application within hours. The application is more secure by the admin. The system will give an effective output for the VB.Net and SQL Server given as input to the system. The compiled java program given as input to the system, after scanning the program will generate different reports. The application generates the report for users. The admin can view and download the report of the data. The application deliver the excel format reports. Because, excel formatted reports is very easy to understand the income and expense of the college bus. This application is mainly develop for windows operating system users. In 2017, 73% of people enterprises are using windows operating system. So the application will easily install for all the windows operating system users. The application-developed size is very low. The application consumes very low space in disk. Therefore, the user can allocate very minimum local disk space for this application.
Water scarcity is the lack of fresh water resources to meet the standard water demand. There are two type of water scarcity. One is physical. The other is economic water scarcity.
Democratizing Fuzzing at Scale by Abhishek Aryaabh.arya
Presented at NUS: Fuzzing and Software Security Summer School 2024
This keynote talks about the democratization of fuzzing at scale, highlighting the collaboration between open source communities, academia, and industry to advance the field of fuzzing. It delves into the history of fuzzing, the development of scalable fuzzing platforms, and the empowerment of community-driven research. The talk will further discuss recent advancements leveraging AI/ML and offer insights into the future evolution of the fuzzing landscape.
TECHNICAL TRAINING MANUAL GENERAL FAMILIARIZATION COURSEDuvanRamosGarzon1
AIRCRAFT GENERAL
The Single Aisle is the most advanced family aircraft in service today, with fly-by-wire flight controls.
The A318, A319, A320 and A321 are twin-engine subsonic medium range aircraft.
The family offers a choice of engines
About
Indigenized remote control interface card suitable for MAFI system CCR equipment. Compatible for IDM8000 CCR. Backplane mounted serial and TCP/Ethernet communication module for CCR remote access. IDM 8000 CCR remote control on serial and TCP protocol.
• Remote control: Parallel or serial interface.
• Compatible with MAFI CCR system.
• Compatible with IDM8000 CCR.
• Compatible with Backplane mount serial communication.
• Compatible with commercial and Defence aviation CCR system.
• Remote control system for accessing CCR and allied system over serial or TCP.
• Indigenized local Support/presence in India.
• Easy in configuration using DIP switches.
Technical Specifications
Indigenized remote control interface card suitable for MAFI system CCR equipment. Compatible for IDM8000 CCR. Backplane mounted serial and TCP/Ethernet communication module for CCR remote access. IDM 8000 CCR remote control on serial and TCP protocol.
Key Features
Indigenized remote control interface card suitable for MAFI system CCR equipment. Compatible for IDM8000 CCR. Backplane mounted serial and TCP/Ethernet communication module for CCR remote access. IDM 8000 CCR remote control on serial and TCP protocol.
• Remote control: Parallel or serial interface
• Compatible with MAFI CCR system
• Copatiable with IDM8000 CCR
• Compatible with Backplane mount serial communication.
• Compatible with commercial and Defence aviation CCR system.
• Remote control system for accessing CCR and allied system over serial or TCP.
• Indigenized local Support/presence in India.
Application
• Remote control: Parallel or serial interface.
• Compatible with MAFI CCR system.
• Compatible with IDM8000 CCR.
• Compatible with Backplane mount serial communication.
• Compatible with commercial and Defence aviation CCR system.
• Remote control system for accessing CCR and allied system over serial or TCP.
• Indigenized local Support/presence in India.
• Easy in configuration using DIP switches.
Event Management System Vb Net Project Report.pdfKamal Acharya
In present era, the scopes of information technology growing with a very fast .We do not see any are untouched from this industry. The scope of information technology has become wider includes: Business and industry. Household Business, Communication, Education, Entertainment, Science, Medicine, Engineering, Distance Learning, Weather Forecasting. Carrier Searching and so on.
My project named “Event Management System” is software that store and maintained all events coordinated in college. It also helpful to print related reports. My project will help to record the events coordinated by faculties with their Name, Event subject, date & details in an efficient & effective ways.
In my system we have to make a system by which a user can record all events coordinated by a particular faculty. In our proposed system some more featured are added which differs it from the existing system such as security.
Planning Of Procurement o different goods and services
PPT on execution of 680 m long tunnel ensuring safety of the adjoining rail tunnel with controlled blasting and monitoring in maoist affected zone of HDN route of SE Rly.
1. Execution of 680 m long tunnel ensuring safety of the adjoining
rail tunnel with controlled blasting and monitoring in maoist
affected zone of HDN route of S.E. Railway
By
Rajesh Prasad
Executive Director
Rail Vikas Nigam Limited
2. 680 m long tunnel execution.
Monitoring of Vibration and Peak particle velocity in the
adjoining tunnel.
Execution in LWE area.
GOELKERA – MONOHARPUR 3RD LINE
Length 27.5 Km
Phase-I (Posoita to Manoharpur) 11.6 KM
Phase –I Commissioned on 04.05.2016
Phase-II (Goelkera to Posoita) 15.9 KM
SCOPE
RVNL Kolkata PIU is Implementing Agency
M/s Unity-Triveni-BCPL (JV) are main Contractor.
Central Institute of Mining & Fuel Research (CIMFR)
Roorkee - DDC (Cost Rs. 80 Lakh)
M/s SNC-Lavalin - PMC. (Cost Rs. 2.7 Crores)
AGENCIES INVOLVED
TECHNICAL CHALLENGE
3rd Line tunnel very close to the existing tunnel (c/c 31 m)
ADMINISTRATIVE CHALLENGE
LWE affected area.
3. FEATURES IN TUNNEL EXECUTION
Curves in Tunnel alignment :
305m , straight with two curves of 3° in approach.
Gradient - 1 in 100
Size and Shape of Tunnel:
Modified Horse Shoe shaped
Excavation Height – 8.041m. & Width – 7.365m.
Excavating by heading and benching method
Controlled blasting technique
Ventilation shaft
Steel rib support in portal and weak rock area
Steel fibre reinforced shotcrete (SFRS)
Rock bolt
Concrete Backfilling
LED lighting
Monitoring system (to ensure safety of the adjoining tunnel) for
the first time in IR
4. General complete cycle of tunnel excavation by drill and blast
Drilling
Survey
Bolt
Scale Dislodged
Ventilate
Blasting
Loading
5. ROCK BLASTING
Desirable Effects Unwanted Effects
• Breaking the rock mass
into desired shapes &
sizes.
• Displacing the broken
rock
• High Production/Pull
• Ground Vibration
• Air-blast
• Flyrock
• Over-Breakage
• Back break
• Damage to Rock Mass
• Cost escalation
• Increased cycle time
6. Rock strata encountered during execution tunnel
PHYLLITE ROCK
(Crack at 71º angle)
QUARTZITE ROCK
CARBONACEOUS SHALE
7. Tunnel excavation by Blasting
• The blast designs with MCD (Maximum
Charged density) of 14.0kg.
• Controlled blasting has been done
under guidance and direction of DDC i.e
CIMFR.
• Heading & benching method due to poor rock condition where stand up
time is not very high.
• Controlled blasting technique for the excavation of tunnel, trolley refuge,
ventilation shaft.
8. • Tunnel heading portion is approx. 26 Sq.m.
• Heading excavation is carried out by drilling (38 mm hole dia) with loading
of emulsion explosive of dia 32mm and blasting with a maximum pull 1.8m.
• Forepoles have been provided at immediate roof with the support of Steel
Ribs.
• Water seepage control - necessary arrangement of pumping of water.
• Depending upon Rock mass stand-up time, immediate support of 100 mm
thick reinforced shotcrete (SFRS) is being done by wet shotcrete machine.
• Approx. 12 nos to 14 nos of Rock bolting (3 m length) @ 1.5m c / c in
staggered way are provided.
• After rock bolts erection, steel ribs of ISMB 200 are placed @ 0.6m c / c
with 3.15 mm thick steel lagging before concrete back filling .
• Cement grouting is done between back fill concrete and rock surface area .
• Perforated PVC pipes are provided for weep holes at a spacing of 3.0 m
interval in staggered way to take care of surface seepage .
Heading Excavation
9. • Area of tunnel benching portion is approx. 25 Sq.m.
• Benching excavation is done when the heading face of tunnel is about
14 m to 15 m away.
• Excavation of benching part is also carried out through drilling and
blasting method with a maximum pull of 1.8 m by using controlled
blasting as per blasting design.
• After the benching, the side wall supports are fixed on wall beam of
ISMB 200.
• 100mm thickness of SFRS(Steel fibre reinforce shotcrete) is sprayed
before erecting Rock bolts.
• Minimum 4 to 6 nos. of rock bolts are provided below spring level
(benching portion) of the spacing between rock surface and steel ribs
and back filled with M20 Grade concrete by using concrete pump.
• Cement grouting is done before placing perforated PVC weep holes.
Benching
10. Explosive:
The latest generation emulsion explosive (power gel of ORICA make
having 25 mm dia ,200 mm long and 125 gm by weight ) with 80-90%
strength for blasting is used . The explosive is adequately sensitive,
powerful and safe. For initiation of non-electric detonators (also termed
as shock tube initiation system) of long delay is used. Afterwards Electric
detonators with long delay series (excel series) is being used in
underground tunnel blasting. 1.8 m deep blast hole is generally filled with
60% of emulsion explosive and remaining 40% length is filled by mud
stick.
LOADING OF EXPLOSIVE
11. Electronic Detonator
The sequence of delay blasting by choosing 1 to 12 delay series of LDD
(Long Delayed Detonator). The placement of LDD’s in heading is shown
below. By this, blastings were done in sequences and during each
blasting amplitude of shock waves was reduced to keep it within
permissible limit for safety of nearby existing tunnel.
Cross section of ED
13. VENTILATION SHAFT
A ventilation shaft (2.0 m dia) circular in shape at the
centre of the tunnel, i.e. at ch. 6300m has been provided.
The shaft is around 35m deep from exposed surface of
mountain to feed fresh air inside tunnel as well as natural
lighting to some extent.
14. STEEL RIBS
Specification of Steel Rib Support at Portal Area :
Type of Steel Rib : ISHB 200
Weight per meter : 0.366 kN
Cross-Section Area : 47.54 cm2
Spacing of rib : 100 cm at both the ends of tunnel
Plain Shotcrete : M20
Steel rib supports have generally been used for the portal zone
and inside the tunnel due to poor rock condition, except 160 m in
patches where the rock support has been given by shotcreting
only. ISHM 200 steel rib supports has been used. At back portion
of steel rib & between the rock surface, the gap has been filled up
by normal concrete so that full arch action could be generated for
stability of tunnel.
16. Specification of Shotcrete in the Tunnel
Steel Fibre Reinforced Shortcrete (SFRS) of standard
mix was used with 28 days UCS (Uniaxial Crushing
Strength) of 50 Mpa and good bonding with the rock
surface.
19. Rock Bolt
Specification of Rock Bolt in the Tunnel :
Length : 3.0 m
Diameter : 25mm tor steel
Base Plate Size : 15 cm x 15 cm
Thickness of Base Plate : 12mm
Pullout Capacity of bolt : More than or equal to 15 tones fully grouted
Spacing : Staggered systematic 1.5m centre to centre
20. Monitoring System
• Controlled blasting under
guidance of DDC.
• Monitoring system for
measuring vibration in the
existing tunnel during blasting
of 3rd line.
• Seismograph equipment was
installed in near by existing
tunnel wall during every
blasting to record the blasting
amplitude and frequency of
shock wave.
21. Inducespolarityofsignal
Longitudinal geophone (L)
Vertical geophone (V)
Transverse geophone (T)
The arrows indicate positive and negative ground motion represented by waveforms
TIME
+
+
+
-
-
-
+
T
+ V
+
L
-
-
-
Event
Standard Transducer
Ground Vibrations
V= Vertical
T= Transverse
L=Longitudinal
Microphone
Air Pressure
Monitoring Device
Limiting/Safe Value
PPV= 10mm/sec.
Noise = 146 dB
22.
23. The summary of blast vibration
and Fast Fourier Transform
Analysis (FFT)
PPV = 4.572 mm/s< 10mm/sec.
Noise = 106.0 dB < 146 dB
24. Administrative Challenge
STATUS OF LAW AND ORDER CONDITION AS REFLECTION IN NEWS
PAPER (Dec. 2017)
पश्चिम स िंहभूम में िाईबा ा के पोड़ाहाट जिंगल के ोनुवा
थाना के कु दाबुरु गािंव के पा नक् सलयों ने िार ट्रैक्टर और
एक जे ीबी मशीन में आग लगा दी. आज ोमवार दोपहर
एक बजे के करीब नक् सलयों ने के नाल के ननमााण में ठेका
किं पनी के काम लगे इन भारी वाहनों व मशीन में आग लगाई.
घटना की जानकारी समलने के बाद िाईबा ा ए पी अनीश
गुप्ता और ऑपरेशन असभयान ए पी मनीष रमन िाईबा ा
े घटना स्थल पर पहुिंिे. दोनों पुसल अधिकाररयों ने घटना
स्थल पर पहुिंि जािंि की और पा के लोगों े पूछताछ की.
उन्हें घटना के बारे में कु छ महत्वपूणा जानकारी समली.
िाईबा ा ए पी ने अनीश गुप्ता ने बताया कक भाकपा
माओवादी के कमािंडर जीवन किं डुलना के दस्ते ने लेवी के सलए
घटना को अिंजाम ददया है.घटना के बारे में बताया गया कक
के नाल का ननमााण काया स्थल पर दोपहर एक बजे अिानक
बड़ी िंख्या में हधथयारों े लै नक् ली पिंहुिे और वाहनों में
आग लगा दी.
Law and Order is still an issue.
25. Execution in LWE area
• LWE – notified by Government of Jharkhand.
• Past History – armed miscreants attacked tunnel
camp. 19 nos. earth moving equipments,
excavators, compactors etc. were burnt at the
tunnel site.
• It has happened twice in the section.
• No Storage of explosive was permitted earlier.
• Subsequently after meeting of CRB with Hon’ble
CM Jharkhand on 06.12.2017, additional forces
have been deployed and night working has also
been permitted.
26. Work is being executed under 100% security cover of SAP posted
by State Government of Jharkhand
29. • The technical challenge of ensuring safety of the existing tunnel has
been met by using Vibration Monitoring System under the supervision
of CSIR – CIMFR.
• Technique is basically to have the delay introduced in sequence of
blasting so that peak particle velocity of shock waves generated after
blasting should not exceed the permissible limit in the existing nearby
tunnel with train operation in place.
• The administrative challenge of execution in maoist area has been
resolved by having regular meetings with the senior officials of
Government of Jharkhand and under the 100% protection of the force.
• The tunnel work is likely to be completed by March, 2018 which was
the most critical part of the project and the section is being
commissioned in coming few months to benefit in de-congestion of
the Howrah – Mumbai HDN route.
• For the first time in Indian Railways, this monitoring system has been
used to ensure safety of the existing tunnel while executing a new
tunnel for double line or third line project.
CONCLUSION