SlideShare a Scribd company logo
Execution of 680 m long tunnel ensuring safety of the adjoining
rail tunnel with controlled blasting and monitoring in maoist
affected zone of HDN route of S.E. Railway
By
Rajesh Prasad
Executive Director
Rail Vikas Nigam Limited
 680 m long tunnel execution.
 Monitoring of Vibration and Peak particle velocity in the
adjoining tunnel.
 Execution in LWE area.
GOELKERA – MONOHARPUR 3RD LINE
Length 27.5 Km
Phase-I (Posoita to Manoharpur) 11.6 KM
Phase –I Commissioned on 04.05.2016
Phase-II (Goelkera to Posoita) 15.9 KM
SCOPE
 RVNL Kolkata PIU is Implementing Agency
 M/s Unity-Triveni-BCPL (JV) are main Contractor.
 Central Institute of Mining & Fuel Research (CIMFR)
Roorkee - DDC (Cost Rs. 80 Lakh)
 M/s SNC-Lavalin - PMC. (Cost Rs. 2.7 Crores)
AGENCIES INVOLVED
TECHNICAL CHALLENGE
 3rd Line tunnel very close to the existing tunnel (c/c 31 m)
ADMINISTRATIVE CHALLENGE
 LWE affected area.
FEATURES IN TUNNEL EXECUTION
 Curves in Tunnel alignment :
305m , straight with two curves of 3° in approach.
Gradient - 1 in 100
 Size and Shape of Tunnel:
 Modified Horse Shoe shaped
 Excavation Height – 8.041m. & Width – 7.365m.
 Excavating by heading and benching method
 Controlled blasting technique
 Ventilation shaft
 Steel rib support in portal and weak rock area
 Steel fibre reinforced shotcrete (SFRS)
 Rock bolt
 Concrete Backfilling
 LED lighting
 Monitoring system (to ensure safety of the adjoining tunnel) for
the first time in IR
General complete cycle of tunnel excavation by drill and blast
Drilling
Survey
Bolt
Scale Dislodged
Ventilate
Blasting
Loading
ROCK BLASTING
Desirable Effects Unwanted Effects
• Breaking the rock mass
into desired shapes &
sizes.
• Displacing the broken
rock
• High Production/Pull
• Ground Vibration
• Air-blast
• Flyrock
• Over-Breakage
• Back break
• Damage to Rock Mass
• Cost escalation
• Increased cycle time
Rock strata encountered during execution tunnel
PHYLLITE ROCK
(Crack at 71º angle)
QUARTZITE ROCK
CARBONACEOUS SHALE
Tunnel excavation by Blasting
• The blast designs with MCD (Maximum
Charged density) of 14.0kg.
• Controlled blasting has been done
under guidance and direction of DDC i.e
CIMFR.
• Heading & benching method due to poor rock condition where stand up
time is not very high.
• Controlled blasting technique for the excavation of tunnel, trolley refuge,
ventilation shaft.
• Tunnel heading portion is approx. 26 Sq.m.
• Heading excavation is carried out by drilling (38 mm hole dia) with loading
of emulsion explosive of dia 32mm and blasting with a maximum pull 1.8m.
• Forepoles have been provided at immediate roof with the support of Steel
Ribs.
• Water seepage control - necessary arrangement of pumping of water.
• Depending upon Rock mass stand-up time, immediate support of 100 mm
thick reinforced shotcrete (SFRS) is being done by wet shotcrete machine.
• Approx. 12 nos to 14 nos of Rock bolting (3 m length) @ 1.5m c / c in
staggered way are provided.
• After rock bolts erection, steel ribs of ISMB 200 are placed @ 0.6m c / c
with 3.15 mm thick steel lagging before concrete back filling .
• Cement grouting is done between back fill concrete and rock surface area .
• Perforated PVC pipes are provided for weep holes at a spacing of 3.0 m
interval in staggered way to take care of surface seepage .
Heading Excavation
• Area of tunnel benching portion is approx. 25 Sq.m.
• Benching excavation is done when the heading face of tunnel is about
14 m to 15 m away.
• Excavation of benching part is also carried out through drilling and
blasting method with a maximum pull of 1.8 m by using controlled
blasting as per blasting design.
• After the benching, the side wall supports are fixed on wall beam of
ISMB 200.
• 100mm thickness of SFRS(Steel fibre reinforce shotcrete) is sprayed
before erecting Rock bolts.
• Minimum 4 to 6 nos. of rock bolts are provided below spring level
(benching portion) of the spacing between rock surface and steel ribs
and back filled with M20 Grade concrete by using concrete pump.
• Cement grouting is done before placing perforated PVC weep holes.
Benching
Explosive:
The latest generation emulsion explosive (power gel of ORICA make
having 25 mm dia ,200 mm long and 125 gm by weight ) with 80-90%
strength for blasting is used . The explosive is adequately sensitive,
powerful and safe. For initiation of non-electric detonators (also termed
as shock tube initiation system) of long delay is used. Afterwards Electric
detonators with long delay series (excel series) is being used in
underground tunnel blasting. 1.8 m deep blast hole is generally filled with
60% of emulsion explosive and remaining 40% length is filled by mud
stick.
LOADING OF EXPLOSIVE
Electronic Detonator
The sequence of delay blasting by choosing 1 to 12 delay series of LDD
(Long Delayed Detonator). The placement of LDD’s in heading is shown
below. By this, blastings were done in sequences and during each
blasting amplitude of shock waves was reduced to keep it within
permissible limit for safety of nearby existing tunnel.
Cross section of ED
Fixing of Electronic Detonator (LDD) for Blasting
VENTILATION SHAFT
A ventilation shaft (2.0 m dia) circular in shape at the
centre of the tunnel, i.e. at ch. 6300m has been provided.
The shaft is around 35m deep from exposed surface of
mountain to feed fresh air inside tunnel as well as natural
lighting to some extent.
STEEL RIBS
Specification of Steel Rib Support at Portal Area :
Type of Steel Rib : ISHB 200
Weight per meter : 0.366 kN
Cross-Section Area : 47.54 cm2
Spacing of rib : 100 cm at both the ends of tunnel
Plain Shotcrete : M20
Steel rib supports have generally been used for the portal zone
and inside the tunnel due to poor rock condition, except 160 m in
patches where the rock support has been given by shotcreting
only. ISHM 200 steel rib supports has been used. At back portion
of steel rib & between the rock surface, the gap has been filled up
by normal concrete so that full arch action could be generated for
stability of tunnel.
STEEL RIBS
Specification of Shotcrete in the Tunnel
Steel Fibre Reinforced Shortcrete (SFRS) of standard
mix was used with 28 days UCS (Uniaxial Crushing
Strength) of 50 Mpa and good bonding with the rock
surface.
FIBRE REINFORCED SHOTCRETE
SLOPE PROTECTION BY
FIXING WIREMESH
SLOPE PROTECTION BY
FIXING ROCK BOLT
SHOTCRETE AT APPROACHES
Rock Bolt
Specification of Rock Bolt in the Tunnel :
Length : 3.0 m
Diameter : 25mm tor steel
Base Plate Size : 15 cm x 15 cm
Thickness of Base Plate : 12mm
Pullout Capacity of bolt : More than or equal to 15 tones fully grouted
Spacing : Staggered systematic 1.5m centre to centre
Monitoring System
• Controlled blasting under
guidance of DDC.
• Monitoring system for
measuring vibration in the
existing tunnel during blasting
of 3rd line.
• Seismograph equipment was
installed in near by existing
tunnel wall during every
blasting to record the blasting
amplitude and frequency of
shock wave.
Inducespolarityofsignal
Longitudinal geophone (L)
Vertical geophone (V)
Transverse geophone (T)
The arrows indicate positive and negative ground motion represented by waveforms
TIME
+
+
+
-
-
-
+
T
+ V
+
L
-
-
-
Event
Standard Transducer
Ground Vibrations
V= Vertical
T= Transverse
L=Longitudinal
Microphone
Air Pressure
Monitoring Device
Limiting/Safe Value
PPV= 10mm/sec.
Noise = 146 dB
The summary of blast vibration
and Fast Fourier Transform
Analysis (FFT)
PPV = 4.572 mm/s< 10mm/sec.
Noise = 106.0 dB < 146 dB
Administrative Challenge
STATUS OF LAW AND ORDER CONDITION AS REFLECTION IN NEWS
PAPER (Dec. 2017)
पश्चिम स िंहभूम में िाईबा ा के पोड़ाहाट जिंगल के ोनुवा
थाना के कु दाबुरु गािंव के पा नक् सलयों ने िार ट्रैक्टर और
एक जे ीबी मशीन में आग लगा दी. आज ोमवार दोपहर
एक बजे के करीब नक् सलयों ने के नाल के ननमााण में ठेका
किं पनी के काम लगे इन भारी वाहनों व मशीन में आग लगाई.
घटना की जानकारी समलने के बाद िाईबा ा ए पी अनीश
गुप्ता और ऑपरेशन असभयान ए पी मनीष रमन िाईबा ा
े घटना स्थल पर पहुिंिे. दोनों पुसल अधिकाररयों ने घटना
स्थल पर पहुिंि जािंि की और पा के लोगों े पूछताछ की.
उन्हें घटना के बारे में कु छ महत्वपूणा जानकारी समली.
िाईबा ा ए पी ने अनीश गुप्ता ने बताया कक भाकपा
माओवादी के कमािंडर जीवन किं डुलना के दस्ते ने लेवी के सलए
घटना को अिंजाम ददया है.घटना के बारे में बताया गया कक
के नाल का ननमााण काया स्थल पर दोपहर एक बजे अिानक
बड़ी िंख्या में हधथयारों े लै नक् ली पिंहुिे और वाहनों में
आग लगा दी.
Law and Order is still an issue.
Execution in LWE area
• LWE – notified by Government of Jharkhand.
• Past History – armed miscreants attacked tunnel
camp. 19 nos. earth moving equipments,
excavators, compactors etc. were burnt at the
tunnel site.
• It has happened twice in the section.
• No Storage of explosive was permitted earlier.
• Subsequently after meeting of CRB with Hon’ble
CM Jharkhand on 06.12.2017, additional forces
have been deployed and night working has also
been permitted.
Work is being executed under 100% security cover of SAP posted
by State Government of Jharkhand
MOVEMENT AND STORAGE OF EXPLOSIVE
• The technical challenge of ensuring safety of the existing tunnel has
been met by using Vibration Monitoring System under the supervision
of CSIR – CIMFR.
• Technique is basically to have the delay introduced in sequence of
blasting so that peak particle velocity of shock waves generated after
blasting should not exceed the permissible limit in the existing nearby
tunnel with train operation in place.
• The administrative challenge of execution in maoist area has been
resolved by having regular meetings with the senior officials of
Government of Jharkhand and under the 100% protection of the force.
• The tunnel work is likely to be completed by March, 2018 which was
the most critical part of the project and the section is being
commissioned in coming few months to benefit in de-congestion of
the Howrah – Mumbai HDN route.
• For the first time in Indian Railways, this monitoring system has been
used to ensure safety of the existing tunnel while executing a new
tunnel for double line or third line project.
CONCLUSION
Team Work
TEAMWORK divides the TASK
and multiplies the SUCCESS
THANK YOU
31

More Related Content

What's hot

Development and depillaring with continuous miner
Development and depillaring with continuous minerDevelopment and depillaring with continuous miner
Development and depillaring with continuous miner
Safdar Ali
 
Oc mechanical excavation
Oc mechanical excavationOc mechanical excavation
Oc mechanical excavation
Ulimella Siva Sankar
 
Shaft sinking
Shaft sinking Shaft sinking
Shaft sinking
OmKaitade
 
Shaft sinking 2
Shaft  sinking 2Shaft  sinking 2
Shaft sinking 2
Er.Sunil Wasade
 
Shaft sinking.
Shaft sinking.Shaft sinking.
Shaft sinking.
Safdar Ali
 
Design of Bord and Pillar method in coal mines
Design of Bord and Pillar method in coal minesDesign of Bord and Pillar method in coal mines
Design of Bord and Pillar method in coal mines
aashutosh chhirolya
 
Different Raising Techniques in mining
Different Raising Techniques in miningDifferent Raising Techniques in mining
Different Raising Techniques in mining
Rishabh Ranjan
 
Drilling and blasting
Drilling and blastingDrilling and blasting
Drilling and blasting
Parth Desani
 
Shaft sinking 1
Shaft sinking 1Shaft sinking 1
Shaft sinking 1
Er.Sunil Wasade
 
Ripper production
Ripper productionRipper production
Ripper production
VIJAY KUMAR
 
Board & Pillar
Board & PillarBoard & Pillar
Board & Pillar
Chittranjan Vaishnav
 
Lectures on metal mining
Lectures on metal miningLectures on metal mining
Lectures on metal mining
Ranjeet Kumar
 
Lecture 2 basic surface mining practise-2
Lecture 2  basic surface mining practise-2Lecture 2  basic surface mining practise-2
Lecture 2 basic surface mining practise-2
IDHAMUKI
 
Differnt technologies in oc mines
Differnt technologies in oc minesDiffernt technologies in oc mines
Differnt technologies in oc minesSATYANARAYANA I
 
Caving Underground Mining Methods (longwall, Sublevel caving, & Block caving)
Caving Underground Mining Methods (longwall, Sublevel caving, &  Block caving)Caving Underground Mining Methods (longwall, Sublevel caving, &  Block caving)
Caving Underground Mining Methods (longwall, Sublevel caving, & Block caving)
Geology Department, Faculty of Science, Tanta University
 
Underground metal mining methods
Underground metal mining methodsUnderground metal mining methods
Underground metal mining methods
Safdar Ali
 
Rock bolt and anchoring
Rock bolt and anchoringRock bolt and anchoring
Rock bolt and anchoring
Amit Jagtap
 
NATM Tunneling ppt
NATM Tunneling pptNATM Tunneling ppt
NATM Tunneling ppt
Suman Paul
 
Blasting and rock fragmentation
Blasting and rock fragmentationBlasting and rock fragmentation
Blasting and rock fragmentation
Alex Demidov
 

What's hot (20)

Surface miner
Surface minerSurface miner
Surface miner
 
Development and depillaring with continuous miner
Development and depillaring with continuous minerDevelopment and depillaring with continuous miner
Development and depillaring with continuous miner
 
Oc mechanical excavation
Oc mechanical excavationOc mechanical excavation
Oc mechanical excavation
 
Shaft sinking
Shaft sinking Shaft sinking
Shaft sinking
 
Shaft sinking 2
Shaft  sinking 2Shaft  sinking 2
Shaft sinking 2
 
Shaft sinking.
Shaft sinking.Shaft sinking.
Shaft sinking.
 
Design of Bord and Pillar method in coal mines
Design of Bord and Pillar method in coal minesDesign of Bord and Pillar method in coal mines
Design of Bord and Pillar method in coal mines
 
Different Raising Techniques in mining
Different Raising Techniques in miningDifferent Raising Techniques in mining
Different Raising Techniques in mining
 
Drilling and blasting
Drilling and blastingDrilling and blasting
Drilling and blasting
 
Shaft sinking 1
Shaft sinking 1Shaft sinking 1
Shaft sinking 1
 
Ripper production
Ripper productionRipper production
Ripper production
 
Board & Pillar
Board & PillarBoard & Pillar
Board & Pillar
 
Lectures on metal mining
Lectures on metal miningLectures on metal mining
Lectures on metal mining
 
Lecture 2 basic surface mining practise-2
Lecture 2  basic surface mining practise-2Lecture 2  basic surface mining practise-2
Lecture 2 basic surface mining practise-2
 
Differnt technologies in oc mines
Differnt technologies in oc minesDiffernt technologies in oc mines
Differnt technologies in oc mines
 
Caving Underground Mining Methods (longwall, Sublevel caving, & Block caving)
Caving Underground Mining Methods (longwall, Sublevel caving, &  Block caving)Caving Underground Mining Methods (longwall, Sublevel caving, &  Block caving)
Caving Underground Mining Methods (longwall, Sublevel caving, & Block caving)
 
Underground metal mining methods
Underground metal mining methodsUnderground metal mining methods
Underground metal mining methods
 
Rock bolt and anchoring
Rock bolt and anchoringRock bolt and anchoring
Rock bolt and anchoring
 
NATM Tunneling ppt
NATM Tunneling pptNATM Tunneling ppt
NATM Tunneling ppt
 
Blasting and rock fragmentation
Blasting and rock fragmentationBlasting and rock fragmentation
Blasting and rock fragmentation
 

Similar to PPT on execution of 680 m long tunnel ensuring safety of the adjoining rail tunnel with controlled blasting and monitoring in maoist affected zone of HDN route of SE Rly.

Uses of special kind of technologies for implementation of special kind of st...
Uses of special kind of technologies for implementation of special kind of st...Uses of special kind of technologies for implementation of special kind of st...
Uses of special kind of technologies for implementation of special kind of st...
Rajesh Prasad
 
Larsen and Toubro (Lucknow Metro Project) Summer Internship Presentation
Larsen and Toubro (Lucknow Metro Project) Summer Internship PresentationLarsen and Toubro (Lucknow Metro Project) Summer Internship Presentation
Larsen and Toubro (Lucknow Metro Project) Summer Internship Presentation
ShuBham RaNa
 
ATAL TUNNEL.pptx
ATAL TUNNEL.pptxATAL TUNNEL.pptx
ATAL TUNNEL.pptx
Aditya Mane
 
ATAL TUNNEL.pptx
ATAL TUNNEL.pptxATAL TUNNEL.pptx
ATAL TUNNEL.pptx
Aditya Mane
 
Chenab Bridge.pdf
Chenab Bridge.pdfChenab Bridge.pdf
Chenab Bridge.pdf
Ppt Creater
 
Extending Open Cast Mine to Underground Mine Planning
Extending Open Cast Mine to Underground Mine PlanningExtending Open Cast Mine to Underground Mine Planning
Extending Open Cast Mine to Underground Mine Planning
Jasmeet Singh Saluja
 
Rev 01 dt 01.03.2010 - soil investigation
Rev 01 dt 01.03.2010 - soil investigationRev 01 dt 01.03.2010 - soil investigation
Rev 01 dt 01.03.2010 - soil investigationSiddhartha Bhamidipati
 
Nhpc training report civil engineerimg_bit_mesra_ISHANT GAUTAM
Nhpc training report civil engineerimg_bit_mesra_ISHANT GAUTAMNhpc training report civil engineerimg_bit_mesra_ISHANT GAUTAM
Nhpc training report civil engineerimg_bit_mesra_ISHANT GAUTAM
Ishant Gautam.
 
RMT Group5 presentation.pptx
RMT Group5 presentation.pptxRMT Group5 presentation.pptx
RMT Group5 presentation.pptx
SubratDash37
 
Execution of 680 m long tunnel ensuring safety of the adjoining rail tunnel w...
Execution of 680 m long tunnel ensuring safety of the adjoining rail tunnel w...Execution of 680 m long tunnel ensuring safety of the adjoining rail tunnel w...
Execution of 680 m long tunnel ensuring safety of the adjoining rail tunnel w...
Rajesh Prasad
 
Bridge Construction Kalia Bhomara Setu
Bridge Construction Kalia Bhomara SetuBridge Construction Kalia Bhomara Setu
Bridge Construction Kalia Bhomara Setu
Vishweshwar Rao Narla
 
Trenchless Technologies for New Pipe Installations
Trenchless Technologies for New Pipe InstallationsTrenchless Technologies for New Pipe Installations
Trenchless Technologies for New Pipe Installations
Loay Ghazaleh MBA, BSc Civil Eng.
 
Advanced tunnel borring machine.ppt
Advanced tunnel borring machine.pptAdvanced tunnel borring machine.ppt
Advanced tunnel borring machine.ppt
abhishek kulkarni
 
07 soil-grout threadbar
07 soil-grout threadbar07 soil-grout threadbar
PPT CAVITY Tunnel P1 610M--05.02.2021.pptx
PPT CAVITY Tunnel P1 610M--05.02.2021.pptxPPT CAVITY Tunnel P1 610M--05.02.2021.pptx
PPT CAVITY Tunnel P1 610M--05.02.2021.pptx
AGNIVORAY1
 
Dimapur-Kohima Rail Project Site Visit Report (1).docx
Dimapur-Kohima Rail Project Site Visit Report (1).docxDimapur-Kohima Rail Project Site Visit Report (1).docx
Dimapur-Kohima Rail Project Site Visit Report (1).docx
AbdulMannan357156
 
Eurasia tunnel1
Eurasia tunnel1Eurasia tunnel1
Eurasia tunnel1
Ujwal Ujwal
 
Busan geoje fixed link
Busan   geoje fixed linkBusan   geoje fixed link
Busan geoje fixed link
Vicky Matwan
 
Tunneling
Tunneling Tunneling
Tunneling
ila vamsi krishna
 
tunnelling scope, construction techniques and necessity
tunnelling scope, construction techniques and necessitytunnelling scope, construction techniques and necessity
tunnelling scope, construction techniques and necessity
Shashank Gaurav
 

Similar to PPT on execution of 680 m long tunnel ensuring safety of the adjoining rail tunnel with controlled blasting and monitoring in maoist affected zone of HDN route of SE Rly. (20)

Uses of special kind of technologies for implementation of special kind of st...
Uses of special kind of technologies for implementation of special kind of st...Uses of special kind of technologies for implementation of special kind of st...
Uses of special kind of technologies for implementation of special kind of st...
 
Larsen and Toubro (Lucknow Metro Project) Summer Internship Presentation
Larsen and Toubro (Lucknow Metro Project) Summer Internship PresentationLarsen and Toubro (Lucknow Metro Project) Summer Internship Presentation
Larsen and Toubro (Lucknow Metro Project) Summer Internship Presentation
 
ATAL TUNNEL.pptx
ATAL TUNNEL.pptxATAL TUNNEL.pptx
ATAL TUNNEL.pptx
 
ATAL TUNNEL.pptx
ATAL TUNNEL.pptxATAL TUNNEL.pptx
ATAL TUNNEL.pptx
 
Chenab Bridge.pdf
Chenab Bridge.pdfChenab Bridge.pdf
Chenab Bridge.pdf
 
Extending Open Cast Mine to Underground Mine Planning
Extending Open Cast Mine to Underground Mine PlanningExtending Open Cast Mine to Underground Mine Planning
Extending Open Cast Mine to Underground Mine Planning
 
Rev 01 dt 01.03.2010 - soil investigation
Rev 01 dt 01.03.2010 - soil investigationRev 01 dt 01.03.2010 - soil investigation
Rev 01 dt 01.03.2010 - soil investigation
 
Nhpc training report civil engineerimg_bit_mesra_ISHANT GAUTAM
Nhpc training report civil engineerimg_bit_mesra_ISHANT GAUTAMNhpc training report civil engineerimg_bit_mesra_ISHANT GAUTAM
Nhpc training report civil engineerimg_bit_mesra_ISHANT GAUTAM
 
RMT Group5 presentation.pptx
RMT Group5 presentation.pptxRMT Group5 presentation.pptx
RMT Group5 presentation.pptx
 
Execution of 680 m long tunnel ensuring safety of the adjoining rail tunnel w...
Execution of 680 m long tunnel ensuring safety of the adjoining rail tunnel w...Execution of 680 m long tunnel ensuring safety of the adjoining rail tunnel w...
Execution of 680 m long tunnel ensuring safety of the adjoining rail tunnel w...
 
Bridge Construction Kalia Bhomara Setu
Bridge Construction Kalia Bhomara SetuBridge Construction Kalia Bhomara Setu
Bridge Construction Kalia Bhomara Setu
 
Trenchless Technologies for New Pipe Installations
Trenchless Technologies for New Pipe InstallationsTrenchless Technologies for New Pipe Installations
Trenchless Technologies for New Pipe Installations
 
Advanced tunnel borring machine.ppt
Advanced tunnel borring machine.pptAdvanced tunnel borring machine.ppt
Advanced tunnel borring machine.ppt
 
07 soil-grout threadbar
07 soil-grout threadbar07 soil-grout threadbar
07 soil-grout threadbar
 
PPT CAVITY Tunnel P1 610M--05.02.2021.pptx
PPT CAVITY Tunnel P1 610M--05.02.2021.pptxPPT CAVITY Tunnel P1 610M--05.02.2021.pptx
PPT CAVITY Tunnel P1 610M--05.02.2021.pptx
 
Dimapur-Kohima Rail Project Site Visit Report (1).docx
Dimapur-Kohima Rail Project Site Visit Report (1).docxDimapur-Kohima Rail Project Site Visit Report (1).docx
Dimapur-Kohima Rail Project Site Visit Report (1).docx
 
Eurasia tunnel1
Eurasia tunnel1Eurasia tunnel1
Eurasia tunnel1
 
Busan geoje fixed link
Busan   geoje fixed linkBusan   geoje fixed link
Busan geoje fixed link
 
Tunneling
Tunneling Tunneling
Tunneling
 
tunnelling scope, construction techniques and necessity
tunnelling scope, construction techniques and necessitytunnelling scope, construction techniques and necessity
tunnelling scope, construction techniques and necessity
 

More from Rajesh Prasad

Opportunities in Railway construction- development operations of infrastructu...
Opportunities in Railway construction- development operations of infrastructu...Opportunities in Railway construction- development operations of infrastructu...
Opportunities in Railway construction- development operations of infrastructu...
Rajesh Prasad
 
20th_Safety_Convention dt 11.09.2023.pdf
20th_Safety_Convention dt 11.09.2023.pdf20th_Safety_Convention dt 11.09.2023.pdf
20th_Safety_Convention dt 11.09.2023.pdf
Rajesh Prasad
 
Cyber Security Action Plan of RVNL
Cyber Security Action Plan of RVNLCyber Security Action Plan of RVNL
Cyber Security Action Plan of RVNL
Rajesh Prasad
 
RVNL Corporate Governance 26.11.2021
RVNL Corporate Governance 26.11.2021 RVNL Corporate Governance 26.11.2021
RVNL Corporate Governance 26.11.2021
Rajesh Prasad
 
Management Development programme - 01.07.2022 .pdf
Management Development programme - 01.07.2022 .pdfManagement Development programme - 01.07.2022 .pdf
Management Development programme - 01.07.2022 .pdf
Rajesh Prasad
 
New normal and beyond –RVNL Perspective dt 27.10.21
New normal and beyond –RVNL Perspective dt 27.10.21New normal and beyond –RVNL Perspective dt 27.10.21
New normal and beyond –RVNL Perspective dt 27.10.21
Rajesh Prasad
 
"Protocol for safe execution of Infra Projects" by Rajesh Prasad, Director Op...
"Protocol for safe execution of Infra Projects" by Rajesh Prasad, Director Op..."Protocol for safe execution of Infra Projects" by Rajesh Prasad, Director Op...
"Protocol for safe execution of Infra Projects" by Rajesh Prasad, Director Op...
Rajesh Prasad
 
Rebuilding of Railway Infrastructures during the present crisis by Rajesh Prasad
Rebuilding of Railway Infrastructures during the present crisis by Rajesh PrasadRebuilding of Railway Infrastructures during the present crisis by Rajesh Prasad
Rebuilding of Railway Infrastructures during the present crisis by Rajesh Prasad
Rajesh Prasad
 
Motivation and Bounce Back after the crisis....
Motivation and Bounce Back after the crisis....Motivation and Bounce Back after the crisis....
Motivation and Bounce Back after the crisis....
Rajesh Prasad
 
Revolution 2020, Crisis.. Change....
Revolution 2020, Crisis.. Change....Revolution 2020, Crisis.. Change....
Revolution 2020, Crisis.. Change....
Rajesh Prasad
 
Infrastructures in City of Kolkata & West Bengal
Infrastructures in City of Kolkata & West BengalInfrastructures in City of Kolkata & West Bengal
Infrastructures in City of Kolkata & West Bengal
Rajesh Prasad
 
A Coffee Table Book cum handbook on Cable Stayed Bridge with the 4 approaches...
A Coffee Table Book cum handbook on Cable Stayed Bridge with the 4 approaches...A Coffee Table Book cum handbook on Cable Stayed Bridge with the 4 approaches...
A Coffee Table Book cum handbook on Cable Stayed Bridge with the 4 approaches...
Rajesh Prasad
 
Engineering for Change... A keynote address on Engineers day- 15th Sep 2019
Engineering for Change... A keynote address on Engineers day- 15th Sep 2019Engineering for Change... A keynote address on Engineers day- 15th Sep 2019
Engineering for Change... A keynote address on Engineers day- 15th Sep 2019
Rajesh Prasad
 
The RVNL Story 2019
The RVNL Story 2019The RVNL Story 2019
The RVNL Story 2019
Rajesh Prasad
 
PROTOCOL FOR SAFE EXECUTION OF INFRA PROJECTS BY RAJESH PRASAD ED RVNL DT 04...
PROTOCOL FOR SAFE EXECUTION OF INFRA PROJECTS  BY RAJESH PRASAD ED RVNL DT 04...PROTOCOL FOR SAFE EXECUTION OF INFRA PROJECTS  BY RAJESH PRASAD ED RVNL DT 04...
PROTOCOL FOR SAFE EXECUTION OF INFRA PROJECTS BY RAJESH PRASAD ED RVNL DT 04...
Rajesh Prasad
 
IIBE ppt at Lucknow dt 25.05.18
IIBE ppt at Lucknow dt 25.05.18IIBE ppt at Lucknow dt 25.05.18
IIBE ppt at Lucknow dt 25.05.18
Rajesh Prasad
 
Construction Safety Protocol PPT by Rajesh Prasad, ED RVNL at Lucknow on 26.0...
Construction Safety Protocol PPT by Rajesh Prasad, ED RVNL at Lucknow on 26.0...Construction Safety Protocol PPT by Rajesh Prasad, ED RVNL at Lucknow on 26.0...
Construction Safety Protocol PPT by Rajesh Prasad, ED RVNL at Lucknow on 26.0...
Rajesh Prasad
 
IIBE ppt at Lucknow dt 25.05.18
IIBE ppt at Lucknow dt 25.05.18IIBE ppt at Lucknow dt 25.05.18
IIBE ppt at Lucknow dt 25.05.18
Rajesh Prasad
 
Bridging over river Bhagirathi- a Handbook cum Coffee Table Book by Rajesh Pr...
Bridging over river Bhagirathi- a Handbook cum Coffee Table Book by Rajesh Pr...Bridging over river Bhagirathi- a Handbook cum Coffee Table Book by Rajesh Pr...
Bridging over river Bhagirathi- a Handbook cum Coffee Table Book by Rajesh Pr...
Rajesh Prasad
 
Sucess in engg. construction14.01.08
Sucess in engg. construction14.01.08Sucess in engg. construction14.01.08
Sucess in engg. construction14.01.08
Rajesh Prasad
 

More from Rajesh Prasad (20)

Opportunities in Railway construction- development operations of infrastructu...
Opportunities in Railway construction- development operations of infrastructu...Opportunities in Railway construction- development operations of infrastructu...
Opportunities in Railway construction- development operations of infrastructu...
 
20th_Safety_Convention dt 11.09.2023.pdf
20th_Safety_Convention dt 11.09.2023.pdf20th_Safety_Convention dt 11.09.2023.pdf
20th_Safety_Convention dt 11.09.2023.pdf
 
Cyber Security Action Plan of RVNL
Cyber Security Action Plan of RVNLCyber Security Action Plan of RVNL
Cyber Security Action Plan of RVNL
 
RVNL Corporate Governance 26.11.2021
RVNL Corporate Governance 26.11.2021 RVNL Corporate Governance 26.11.2021
RVNL Corporate Governance 26.11.2021
 
Management Development programme - 01.07.2022 .pdf
Management Development programme - 01.07.2022 .pdfManagement Development programme - 01.07.2022 .pdf
Management Development programme - 01.07.2022 .pdf
 
New normal and beyond –RVNL Perspective dt 27.10.21
New normal and beyond –RVNL Perspective dt 27.10.21New normal and beyond –RVNL Perspective dt 27.10.21
New normal and beyond –RVNL Perspective dt 27.10.21
 
"Protocol for safe execution of Infra Projects" by Rajesh Prasad, Director Op...
"Protocol for safe execution of Infra Projects" by Rajesh Prasad, Director Op..."Protocol for safe execution of Infra Projects" by Rajesh Prasad, Director Op...
"Protocol for safe execution of Infra Projects" by Rajesh Prasad, Director Op...
 
Rebuilding of Railway Infrastructures during the present crisis by Rajesh Prasad
Rebuilding of Railway Infrastructures during the present crisis by Rajesh PrasadRebuilding of Railway Infrastructures during the present crisis by Rajesh Prasad
Rebuilding of Railway Infrastructures during the present crisis by Rajesh Prasad
 
Motivation and Bounce Back after the crisis....
Motivation and Bounce Back after the crisis....Motivation and Bounce Back after the crisis....
Motivation and Bounce Back after the crisis....
 
Revolution 2020, Crisis.. Change....
Revolution 2020, Crisis.. Change....Revolution 2020, Crisis.. Change....
Revolution 2020, Crisis.. Change....
 
Infrastructures in City of Kolkata & West Bengal
Infrastructures in City of Kolkata & West BengalInfrastructures in City of Kolkata & West Bengal
Infrastructures in City of Kolkata & West Bengal
 
A Coffee Table Book cum handbook on Cable Stayed Bridge with the 4 approaches...
A Coffee Table Book cum handbook on Cable Stayed Bridge with the 4 approaches...A Coffee Table Book cum handbook on Cable Stayed Bridge with the 4 approaches...
A Coffee Table Book cum handbook on Cable Stayed Bridge with the 4 approaches...
 
Engineering for Change... A keynote address on Engineers day- 15th Sep 2019
Engineering for Change... A keynote address on Engineers day- 15th Sep 2019Engineering for Change... A keynote address on Engineers day- 15th Sep 2019
Engineering for Change... A keynote address on Engineers day- 15th Sep 2019
 
The RVNL Story 2019
The RVNL Story 2019The RVNL Story 2019
The RVNL Story 2019
 
PROTOCOL FOR SAFE EXECUTION OF INFRA PROJECTS BY RAJESH PRASAD ED RVNL DT 04...
PROTOCOL FOR SAFE EXECUTION OF INFRA PROJECTS  BY RAJESH PRASAD ED RVNL DT 04...PROTOCOL FOR SAFE EXECUTION OF INFRA PROJECTS  BY RAJESH PRASAD ED RVNL DT 04...
PROTOCOL FOR SAFE EXECUTION OF INFRA PROJECTS BY RAJESH PRASAD ED RVNL DT 04...
 
IIBE ppt at Lucknow dt 25.05.18
IIBE ppt at Lucknow dt 25.05.18IIBE ppt at Lucknow dt 25.05.18
IIBE ppt at Lucknow dt 25.05.18
 
Construction Safety Protocol PPT by Rajesh Prasad, ED RVNL at Lucknow on 26.0...
Construction Safety Protocol PPT by Rajesh Prasad, ED RVNL at Lucknow on 26.0...Construction Safety Protocol PPT by Rajesh Prasad, ED RVNL at Lucknow on 26.0...
Construction Safety Protocol PPT by Rajesh Prasad, ED RVNL at Lucknow on 26.0...
 
IIBE ppt at Lucknow dt 25.05.18
IIBE ppt at Lucknow dt 25.05.18IIBE ppt at Lucknow dt 25.05.18
IIBE ppt at Lucknow dt 25.05.18
 
Bridging over river Bhagirathi- a Handbook cum Coffee Table Book by Rajesh Pr...
Bridging over river Bhagirathi- a Handbook cum Coffee Table Book by Rajesh Pr...Bridging over river Bhagirathi- a Handbook cum Coffee Table Book by Rajesh Pr...
Bridging over river Bhagirathi- a Handbook cum Coffee Table Book by Rajesh Pr...
 
Sucess in engg. construction14.01.08
Sucess in engg. construction14.01.08Sucess in engg. construction14.01.08
Sucess in engg. construction14.01.08
 

Recently uploaded

LIGA(E)11111111111111111111111111111111111111111.ppt
LIGA(E)11111111111111111111111111111111111111111.pptLIGA(E)11111111111111111111111111111111111111111.ppt
LIGA(E)11111111111111111111111111111111111111111.ppt
ssuser9bd3ba
 
The role of big data in decision making.
The role of big data in decision making.The role of big data in decision making.
The role of big data in decision making.
ankuprajapati0525
 
Courier management system project report.pdf
Courier management system project report.pdfCourier management system project report.pdf
Courier management system project report.pdf
Kamal Acharya
 
Quality defects in TMT Bars, Possible causes and Potential Solutions.
Quality defects in TMT Bars, Possible causes and Potential Solutions.Quality defects in TMT Bars, Possible causes and Potential Solutions.
Quality defects in TMT Bars, Possible causes and Potential Solutions.
PrashantGoswami42
 
Railway Signalling Principles Edition 3.pdf
Railway Signalling Principles Edition 3.pdfRailway Signalling Principles Edition 3.pdf
Railway Signalling Principles Edition 3.pdf
TeeVichai
 
ethical hacking in wireless-hacking1.ppt
ethical hacking in wireless-hacking1.pptethical hacking in wireless-hacking1.ppt
ethical hacking in wireless-hacking1.ppt
Jayaprasanna4
 
Hybrid optimization of pumped hydro system and solar- Engr. Abdul-Azeez.pdf
Hybrid optimization of pumped hydro system and solar- Engr. Abdul-Azeez.pdfHybrid optimization of pumped hydro system and solar- Engr. Abdul-Azeez.pdf
Hybrid optimization of pumped hydro system and solar- Engr. Abdul-Azeez.pdf
fxintegritypublishin
 
Sachpazis:Terzaghi Bearing Capacity Estimation in simple terms with Calculati...
Sachpazis:Terzaghi Bearing Capacity Estimation in simple terms with Calculati...Sachpazis:Terzaghi Bearing Capacity Estimation in simple terms with Calculati...
Sachpazis:Terzaghi Bearing Capacity Estimation in simple terms with Calculati...
Dr.Costas Sachpazis
 
Student information management system project report ii.pdf
Student information management system project report ii.pdfStudent information management system project report ii.pdf
Student information management system project report ii.pdf
Kamal Acharya
 
在线办理(ANU毕业证书)澳洲国立大学毕业证录取通知书一模一样
在线办理(ANU毕业证书)澳洲国立大学毕业证录取通知书一模一样在线办理(ANU毕业证书)澳洲国立大学毕业证录取通知书一模一样
在线办理(ANU毕业证书)澳洲国立大学毕业证录取通知书一模一样
obonagu
 
COLLEGE BUS MANAGEMENT SYSTEM PROJECT REPORT.pdf
COLLEGE BUS MANAGEMENT SYSTEM PROJECT REPORT.pdfCOLLEGE BUS MANAGEMENT SYSTEM PROJECT REPORT.pdf
COLLEGE BUS MANAGEMENT SYSTEM PROJECT REPORT.pdf
Kamal Acharya
 
WATER CRISIS and its solutions-pptx 1234
WATER CRISIS and its solutions-pptx 1234WATER CRISIS and its solutions-pptx 1234
WATER CRISIS and its solutions-pptx 1234
AafreenAbuthahir2
 
road safety engineering r s e unit 3.pdf
road safety engineering  r s e unit 3.pdfroad safety engineering  r s e unit 3.pdf
road safety engineering r s e unit 3.pdf
VENKATESHvenky89705
 
Democratizing Fuzzing at Scale by Abhishek Arya
Democratizing Fuzzing at Scale by Abhishek AryaDemocratizing Fuzzing at Scale by Abhishek Arya
Democratizing Fuzzing at Scale by Abhishek Arya
abh.arya
 
TECHNICAL TRAINING MANUAL GENERAL FAMILIARIZATION COURSE
TECHNICAL TRAINING MANUAL   GENERAL FAMILIARIZATION COURSETECHNICAL TRAINING MANUAL   GENERAL FAMILIARIZATION COURSE
TECHNICAL TRAINING MANUAL GENERAL FAMILIARIZATION COURSE
DuvanRamosGarzon1
 
J.Yang, ICLR 2024, MLILAB, KAIST AI.pdf
J.Yang,  ICLR 2024, MLILAB, KAIST AI.pdfJ.Yang,  ICLR 2024, MLILAB, KAIST AI.pdf
J.Yang, ICLR 2024, MLILAB, KAIST AI.pdf
MLILAB
 
Standard Reomte Control Interface - Neometrix
Standard Reomte Control Interface - NeometrixStandard Reomte Control Interface - Neometrix
Standard Reomte Control Interface - Neometrix
Neometrix_Engineering_Pvt_Ltd
 
AKS UNIVERSITY Satna Final Year Project By OM Hardaha.pdf
AKS UNIVERSITY Satna Final Year Project By OM Hardaha.pdfAKS UNIVERSITY Satna Final Year Project By OM Hardaha.pdf
AKS UNIVERSITY Satna Final Year Project By OM Hardaha.pdf
SamSarthak3
 
Event Management System Vb Net Project Report.pdf
Event Management System Vb Net  Project Report.pdfEvent Management System Vb Net  Project Report.pdf
Event Management System Vb Net Project Report.pdf
Kamal Acharya
 
Planning Of Procurement o different goods and services
Planning Of Procurement o different goods and servicesPlanning Of Procurement o different goods and services
Planning Of Procurement o different goods and services
JoytuBarua2
 

Recently uploaded (20)

LIGA(E)11111111111111111111111111111111111111111.ppt
LIGA(E)11111111111111111111111111111111111111111.pptLIGA(E)11111111111111111111111111111111111111111.ppt
LIGA(E)11111111111111111111111111111111111111111.ppt
 
The role of big data in decision making.
The role of big data in decision making.The role of big data in decision making.
The role of big data in decision making.
 
Courier management system project report.pdf
Courier management system project report.pdfCourier management system project report.pdf
Courier management system project report.pdf
 
Quality defects in TMT Bars, Possible causes and Potential Solutions.
Quality defects in TMT Bars, Possible causes and Potential Solutions.Quality defects in TMT Bars, Possible causes and Potential Solutions.
Quality defects in TMT Bars, Possible causes and Potential Solutions.
 
Railway Signalling Principles Edition 3.pdf
Railway Signalling Principles Edition 3.pdfRailway Signalling Principles Edition 3.pdf
Railway Signalling Principles Edition 3.pdf
 
ethical hacking in wireless-hacking1.ppt
ethical hacking in wireless-hacking1.pptethical hacking in wireless-hacking1.ppt
ethical hacking in wireless-hacking1.ppt
 
Hybrid optimization of pumped hydro system and solar- Engr. Abdul-Azeez.pdf
Hybrid optimization of pumped hydro system and solar- Engr. Abdul-Azeez.pdfHybrid optimization of pumped hydro system and solar- Engr. Abdul-Azeez.pdf
Hybrid optimization of pumped hydro system and solar- Engr. Abdul-Azeez.pdf
 
Sachpazis:Terzaghi Bearing Capacity Estimation in simple terms with Calculati...
Sachpazis:Terzaghi Bearing Capacity Estimation in simple terms with Calculati...Sachpazis:Terzaghi Bearing Capacity Estimation in simple terms with Calculati...
Sachpazis:Terzaghi Bearing Capacity Estimation in simple terms with Calculati...
 
Student information management system project report ii.pdf
Student information management system project report ii.pdfStudent information management system project report ii.pdf
Student information management system project report ii.pdf
 
在线办理(ANU毕业证书)澳洲国立大学毕业证录取通知书一模一样
在线办理(ANU毕业证书)澳洲国立大学毕业证录取通知书一模一样在线办理(ANU毕业证书)澳洲国立大学毕业证录取通知书一模一样
在线办理(ANU毕业证书)澳洲国立大学毕业证录取通知书一模一样
 
COLLEGE BUS MANAGEMENT SYSTEM PROJECT REPORT.pdf
COLLEGE BUS MANAGEMENT SYSTEM PROJECT REPORT.pdfCOLLEGE BUS MANAGEMENT SYSTEM PROJECT REPORT.pdf
COLLEGE BUS MANAGEMENT SYSTEM PROJECT REPORT.pdf
 
WATER CRISIS and its solutions-pptx 1234
WATER CRISIS and its solutions-pptx 1234WATER CRISIS and its solutions-pptx 1234
WATER CRISIS and its solutions-pptx 1234
 
road safety engineering r s e unit 3.pdf
road safety engineering  r s e unit 3.pdfroad safety engineering  r s e unit 3.pdf
road safety engineering r s e unit 3.pdf
 
Democratizing Fuzzing at Scale by Abhishek Arya
Democratizing Fuzzing at Scale by Abhishek AryaDemocratizing Fuzzing at Scale by Abhishek Arya
Democratizing Fuzzing at Scale by Abhishek Arya
 
TECHNICAL TRAINING MANUAL GENERAL FAMILIARIZATION COURSE
TECHNICAL TRAINING MANUAL   GENERAL FAMILIARIZATION COURSETECHNICAL TRAINING MANUAL   GENERAL FAMILIARIZATION COURSE
TECHNICAL TRAINING MANUAL GENERAL FAMILIARIZATION COURSE
 
J.Yang, ICLR 2024, MLILAB, KAIST AI.pdf
J.Yang,  ICLR 2024, MLILAB, KAIST AI.pdfJ.Yang,  ICLR 2024, MLILAB, KAIST AI.pdf
J.Yang, ICLR 2024, MLILAB, KAIST AI.pdf
 
Standard Reomte Control Interface - Neometrix
Standard Reomte Control Interface - NeometrixStandard Reomte Control Interface - Neometrix
Standard Reomte Control Interface - Neometrix
 
AKS UNIVERSITY Satna Final Year Project By OM Hardaha.pdf
AKS UNIVERSITY Satna Final Year Project By OM Hardaha.pdfAKS UNIVERSITY Satna Final Year Project By OM Hardaha.pdf
AKS UNIVERSITY Satna Final Year Project By OM Hardaha.pdf
 
Event Management System Vb Net Project Report.pdf
Event Management System Vb Net  Project Report.pdfEvent Management System Vb Net  Project Report.pdf
Event Management System Vb Net Project Report.pdf
 
Planning Of Procurement o different goods and services
Planning Of Procurement o different goods and servicesPlanning Of Procurement o different goods and services
Planning Of Procurement o different goods and services
 

PPT on execution of 680 m long tunnel ensuring safety of the adjoining rail tunnel with controlled blasting and monitoring in maoist affected zone of HDN route of SE Rly.

  • 1. Execution of 680 m long tunnel ensuring safety of the adjoining rail tunnel with controlled blasting and monitoring in maoist affected zone of HDN route of S.E. Railway By Rajesh Prasad Executive Director Rail Vikas Nigam Limited
  • 2.  680 m long tunnel execution.  Monitoring of Vibration and Peak particle velocity in the adjoining tunnel.  Execution in LWE area. GOELKERA – MONOHARPUR 3RD LINE Length 27.5 Km Phase-I (Posoita to Manoharpur) 11.6 KM Phase –I Commissioned on 04.05.2016 Phase-II (Goelkera to Posoita) 15.9 KM SCOPE  RVNL Kolkata PIU is Implementing Agency  M/s Unity-Triveni-BCPL (JV) are main Contractor.  Central Institute of Mining & Fuel Research (CIMFR) Roorkee - DDC (Cost Rs. 80 Lakh)  M/s SNC-Lavalin - PMC. (Cost Rs. 2.7 Crores) AGENCIES INVOLVED TECHNICAL CHALLENGE  3rd Line tunnel very close to the existing tunnel (c/c 31 m) ADMINISTRATIVE CHALLENGE  LWE affected area.
  • 3. FEATURES IN TUNNEL EXECUTION  Curves in Tunnel alignment : 305m , straight with two curves of 3° in approach. Gradient - 1 in 100  Size and Shape of Tunnel:  Modified Horse Shoe shaped  Excavation Height – 8.041m. & Width – 7.365m.  Excavating by heading and benching method  Controlled blasting technique  Ventilation shaft  Steel rib support in portal and weak rock area  Steel fibre reinforced shotcrete (SFRS)  Rock bolt  Concrete Backfilling  LED lighting  Monitoring system (to ensure safety of the adjoining tunnel) for the first time in IR
  • 4. General complete cycle of tunnel excavation by drill and blast Drilling Survey Bolt Scale Dislodged Ventilate Blasting Loading
  • 5. ROCK BLASTING Desirable Effects Unwanted Effects • Breaking the rock mass into desired shapes & sizes. • Displacing the broken rock • High Production/Pull • Ground Vibration • Air-blast • Flyrock • Over-Breakage • Back break • Damage to Rock Mass • Cost escalation • Increased cycle time
  • 6. Rock strata encountered during execution tunnel PHYLLITE ROCK (Crack at 71º angle) QUARTZITE ROCK CARBONACEOUS SHALE
  • 7. Tunnel excavation by Blasting • The blast designs with MCD (Maximum Charged density) of 14.0kg. • Controlled blasting has been done under guidance and direction of DDC i.e CIMFR. • Heading & benching method due to poor rock condition where stand up time is not very high. • Controlled blasting technique for the excavation of tunnel, trolley refuge, ventilation shaft.
  • 8. • Tunnel heading portion is approx. 26 Sq.m. • Heading excavation is carried out by drilling (38 mm hole dia) with loading of emulsion explosive of dia 32mm and blasting with a maximum pull 1.8m. • Forepoles have been provided at immediate roof with the support of Steel Ribs. • Water seepage control - necessary arrangement of pumping of water. • Depending upon Rock mass stand-up time, immediate support of 100 mm thick reinforced shotcrete (SFRS) is being done by wet shotcrete machine. • Approx. 12 nos to 14 nos of Rock bolting (3 m length) @ 1.5m c / c in staggered way are provided. • After rock bolts erection, steel ribs of ISMB 200 are placed @ 0.6m c / c with 3.15 mm thick steel lagging before concrete back filling . • Cement grouting is done between back fill concrete and rock surface area . • Perforated PVC pipes are provided for weep holes at a spacing of 3.0 m interval in staggered way to take care of surface seepage . Heading Excavation
  • 9. • Area of tunnel benching portion is approx. 25 Sq.m. • Benching excavation is done when the heading face of tunnel is about 14 m to 15 m away. • Excavation of benching part is also carried out through drilling and blasting method with a maximum pull of 1.8 m by using controlled blasting as per blasting design. • After the benching, the side wall supports are fixed on wall beam of ISMB 200. • 100mm thickness of SFRS(Steel fibre reinforce shotcrete) is sprayed before erecting Rock bolts. • Minimum 4 to 6 nos. of rock bolts are provided below spring level (benching portion) of the spacing between rock surface and steel ribs and back filled with M20 Grade concrete by using concrete pump. • Cement grouting is done before placing perforated PVC weep holes. Benching
  • 10. Explosive: The latest generation emulsion explosive (power gel of ORICA make having 25 mm dia ,200 mm long and 125 gm by weight ) with 80-90% strength for blasting is used . The explosive is adequately sensitive, powerful and safe. For initiation of non-electric detonators (also termed as shock tube initiation system) of long delay is used. Afterwards Electric detonators with long delay series (excel series) is being used in underground tunnel blasting. 1.8 m deep blast hole is generally filled with 60% of emulsion explosive and remaining 40% length is filled by mud stick. LOADING OF EXPLOSIVE
  • 11. Electronic Detonator The sequence of delay blasting by choosing 1 to 12 delay series of LDD (Long Delayed Detonator). The placement of LDD’s in heading is shown below. By this, blastings were done in sequences and during each blasting amplitude of shock waves was reduced to keep it within permissible limit for safety of nearby existing tunnel. Cross section of ED
  • 12. Fixing of Electronic Detonator (LDD) for Blasting
  • 13. VENTILATION SHAFT A ventilation shaft (2.0 m dia) circular in shape at the centre of the tunnel, i.e. at ch. 6300m has been provided. The shaft is around 35m deep from exposed surface of mountain to feed fresh air inside tunnel as well as natural lighting to some extent.
  • 14. STEEL RIBS Specification of Steel Rib Support at Portal Area : Type of Steel Rib : ISHB 200 Weight per meter : 0.366 kN Cross-Section Area : 47.54 cm2 Spacing of rib : 100 cm at both the ends of tunnel Plain Shotcrete : M20 Steel rib supports have generally been used for the portal zone and inside the tunnel due to poor rock condition, except 160 m in patches where the rock support has been given by shotcreting only. ISHM 200 steel rib supports has been used. At back portion of steel rib & between the rock surface, the gap has been filled up by normal concrete so that full arch action could be generated for stability of tunnel.
  • 16. Specification of Shotcrete in the Tunnel Steel Fibre Reinforced Shortcrete (SFRS) of standard mix was used with 28 days UCS (Uniaxial Crushing Strength) of 50 Mpa and good bonding with the rock surface.
  • 18. SLOPE PROTECTION BY FIXING WIREMESH SLOPE PROTECTION BY FIXING ROCK BOLT SHOTCRETE AT APPROACHES
  • 19. Rock Bolt Specification of Rock Bolt in the Tunnel : Length : 3.0 m Diameter : 25mm tor steel Base Plate Size : 15 cm x 15 cm Thickness of Base Plate : 12mm Pullout Capacity of bolt : More than or equal to 15 tones fully grouted Spacing : Staggered systematic 1.5m centre to centre
  • 20. Monitoring System • Controlled blasting under guidance of DDC. • Monitoring system for measuring vibration in the existing tunnel during blasting of 3rd line. • Seismograph equipment was installed in near by existing tunnel wall during every blasting to record the blasting amplitude and frequency of shock wave.
  • 21. Inducespolarityofsignal Longitudinal geophone (L) Vertical geophone (V) Transverse geophone (T) The arrows indicate positive and negative ground motion represented by waveforms TIME + + + - - - + T + V + L - - - Event Standard Transducer Ground Vibrations V= Vertical T= Transverse L=Longitudinal Microphone Air Pressure Monitoring Device Limiting/Safe Value PPV= 10mm/sec. Noise = 146 dB
  • 22.
  • 23. The summary of blast vibration and Fast Fourier Transform Analysis (FFT) PPV = 4.572 mm/s< 10mm/sec. Noise = 106.0 dB < 146 dB
  • 24. Administrative Challenge STATUS OF LAW AND ORDER CONDITION AS REFLECTION IN NEWS PAPER (Dec. 2017) पश्चिम स िंहभूम में िाईबा ा के पोड़ाहाट जिंगल के ोनुवा थाना के कु दाबुरु गािंव के पा नक् सलयों ने िार ट्रैक्टर और एक जे ीबी मशीन में आग लगा दी. आज ोमवार दोपहर एक बजे के करीब नक् सलयों ने के नाल के ननमााण में ठेका किं पनी के काम लगे इन भारी वाहनों व मशीन में आग लगाई. घटना की जानकारी समलने के बाद िाईबा ा ए पी अनीश गुप्ता और ऑपरेशन असभयान ए पी मनीष रमन िाईबा ा े घटना स्थल पर पहुिंिे. दोनों पुसल अधिकाररयों ने घटना स्थल पर पहुिंि जािंि की और पा के लोगों े पूछताछ की. उन्हें घटना के बारे में कु छ महत्वपूणा जानकारी समली. िाईबा ा ए पी ने अनीश गुप्ता ने बताया कक भाकपा माओवादी के कमािंडर जीवन किं डुलना के दस्ते ने लेवी के सलए घटना को अिंजाम ददया है.घटना के बारे में बताया गया कक के नाल का ननमााण काया स्थल पर दोपहर एक बजे अिानक बड़ी िंख्या में हधथयारों े लै नक् ली पिंहुिे और वाहनों में आग लगा दी. Law and Order is still an issue.
  • 25. Execution in LWE area • LWE – notified by Government of Jharkhand. • Past History – armed miscreants attacked tunnel camp. 19 nos. earth moving equipments, excavators, compactors etc. were burnt at the tunnel site. • It has happened twice in the section. • No Storage of explosive was permitted earlier. • Subsequently after meeting of CRB with Hon’ble CM Jharkhand on 06.12.2017, additional forces have been deployed and night working has also been permitted.
  • 26. Work is being executed under 100% security cover of SAP posted by State Government of Jharkhand
  • 27. MOVEMENT AND STORAGE OF EXPLOSIVE
  • 28.
  • 29. • The technical challenge of ensuring safety of the existing tunnel has been met by using Vibration Monitoring System under the supervision of CSIR – CIMFR. • Technique is basically to have the delay introduced in sequence of blasting so that peak particle velocity of shock waves generated after blasting should not exceed the permissible limit in the existing nearby tunnel with train operation in place. • The administrative challenge of execution in maoist area has been resolved by having regular meetings with the senior officials of Government of Jharkhand and under the 100% protection of the force. • The tunnel work is likely to be completed by March, 2018 which was the most critical part of the project and the section is being commissioned in coming few months to benefit in de-congestion of the Howrah – Mumbai HDN route. • For the first time in Indian Railways, this monitoring system has been used to ensure safety of the existing tunnel while executing a new tunnel for double line or third line project. CONCLUSION
  • 30. Team Work TEAMWORK divides the TASK and multiplies the SUCCESS