SlideShare a Scribd company logo
1 of 30
IN-PIT CRUSHING AND CONVEYING
IN SURFACE MINES
INTRODUCTION
In hard rock surface mines, the mining system
adopted is generally a discontinuous/cyclic one.
Such a system broadly consists of the following
unit operations vis-à-vis the equipment to
accomplish them.
Ground preparation for subsequent excavation
and/or loading is generally accomplished with the
help of drilling and blasting. Drilling may be done
by percussive / rotary / rotary-percussive blasthole
drills depending on site specifics and
requirements.
Ground preparation:
The blasted material (ore and/or waste) is
excavated and/or loaded by cyclic excavators.
Electric rope shovels or hydraulic shovels are
most commonly used for this purpose. Draglines
may be used for handling overburden (fully or
partly) in surface coal mines mining horizontal or
flat (dip upto 1 in 20) seams.
Hydraulic backhoe is used where digging below
the crawler level is required, and front-end-loader
may also be used as primary excavator to handle
ore and/or waste under some special situations.
Excavation and/or loading:
Shovel (electric/hydraulic), backhoe and front-end-
loader - all loads the excavated material into the
dumper for subsequent transportation either to the
ore stock pile/plant area or to the waste-dump
(external or internal or both). Dragline transports
its own load to the adjacent de-coaled area
following the method of strip mining.
Transportation:
In case of both the dumper and dragline, dumping
is done by the equipment itself.
Dumping:
Levelling, in all most all the cases, is done by
dozer.
Levelling:
Of the above unit operations, either the drilling &
blasting or the transportation is the most costly
one. With the increase in depth of working,
generally the unit cost of drilling & blasting
remains unchanged, whereas, the unit cost of
transportation by dumper for both the ore and
waste increases, and the rate of increase in unit
transport cost also increases with the increase in
depth. As a result of this, generally in shallower
mines the drilling & blasting operation may be
most costly one, but in deeper mines the
transportation becomes the costliest unit
operation. So it is necessary to minimize the unit
transport cost for better economy of operation
particularly in case of deeper mines.
During 1940s, particularly after the Second World War, the
dumper transport system because very popular in hard
rock mines. The dumpers were preferred over rail-road
transport system because of its flexibility and the ability to
negotiate a higher gradient (1 in 16) compared to that
negotiated by rail road system ( 1 in 33). However, during
1960s the fuel prices started rising steadily, and as a result
of which the dumper transportation cost also started rising
very steeply.
In the early part of 1960s, attempts were made to
control/reduce the unit transport cost by increasing the
truck size thereby taking the advantage of scale of
operation. The main focus was to reduce the manpower
and with it the personnel cost associated. But later on the
attention of the mine planners and operators were drawn
to the application of conveyor as an alternative means of
transportation due to the fact that substantial savings of
cost is possible by changing to conveyor transport from
truck haulage system.
CONVEYOR TRANSPORT VS TRUCK HAULAGE
In a comparison of dump trucks with belt conveyor
for mine transport, the following may be observed.
The trucks consume 60% of available mechanical
energy to carry their dead weight; only 40% energy
is used to carry the payload. But for belt
conveyors, 10% to 20% energy is required to carry
the belt while carrying the material in plane or
uphill direction and rest 80% to 90% energy is
utilized to carry the material, Conveyors carrying
material down hill may generate energy.
Dump trucks need good haul road for their
efficient operation. So good compact haul roads
must be built and maintained. For conveyors such
requirement is not there or very less.
The dump trucks can negotiate maximum gradient
upto 1 in 16 for long hauls whereas the conveyors
can run effectively upto a gradient of 1 in 4.
Productivity of dump trucks rapidly goes down
with the increase in length of transport distance
and of the lifting height due to increase in cycle
time. The effects of increase in transport distance
and of the lifting height on the productivity in case
of conveyor transport system is very nominal.
The energy cost to transport same payload over
same distance or for lifting same vertical height is
more in case of dumper than in case of conveyor.
To transport 100 te of payload over a distance of
5 kms, the dump truck will need about 40 lit.of diesel
( Rs.1000/-), whereas the belt conveyor will use
about 60 Kwh ( Rs.180/-).
To hoist 100 te of payload by 50m, the dump truck
will need about 10 lit of diesel ( Rs.250/-), whereas
the belt conveyor will use about 15 Kwh ( Rs.45/-).
A brief account of merits and demerits of belt
conveyor systems over truck haulage system is
given below:
Merits:
 Lower capital expenditure due to a longer depreciation
period
 Lower energy costs and superior energy efficiency
 Less manpower required
 Lower maintenance cost
 Can negotiate higher gradients (upto 1 in 4)
 Can handle high output (upto 4000 te/hour)
 Less sensitive to weather conditions
 Less adverse effects on environment (less dust, noise,
etc.)
 High availability
 Possibility of automation
 Less flexibility
 High initial investment costs
 Require size material for efficient operation
 Less suitable for big size lumps or un-sized material
 In the event of stoppage of any one of the belts, the
whole belt network has to be stopped
Demerits:
Trucks are capable of handling almost any size of
lump that may be loaded by an excavator/loader
onto it, but this is not so in case of a conveyor. The
maximum lump size that can be transported on
conveyors depends on belt width, speed, troughing
angle and conveyor inclination. The design of a
conveyor will also be dependent on the frequency of
large lumps to be carried.
As a rule of thumb, the maximum lump size should
be less than 350 mm for belts of 1000 mm or more
width, less than 300mm for belts of 800 mm width
and less than 200 mm for belt width of 650mm.
Therefore, in hard rock mines, to utilize belt
conveyors as the means of transportation of
materials (ore and/or overburden/waste) out of pit to
the preparation plant or to the waste dumps, the
material needs to be sized before being loaded onto
a conveyor. This calls for installation of in-pit
crushing systems.
IN-PIT CRUSHING SYSTEMS
In response to the increasing truck haulage costs
and in the face of increasing tonnage to be moved,
two large U.S. copper mines responded in late
1960s and early 1970s by installing high capacity
belt conveyor systems with large, permanent type,
gyratory in-pit crushers. The systems did not
eliminate the trucks all together, but restricted their
use only within the pit from the working faces to the
crusher, and the crushed material thereafter was
transported to the plant (ore) and waste dumps
(waste) through belt conveyors.
Duval Corporation began installation of the first
movable in-pit crushing and conveying systems in
1981 at its Sierrita Copper and Molybdenum
Minenear Tucson, Arizona, and the operation of the
system began in 1982 December. Operation of
another similar system also began in 1982 at
Sishen’s North Iron Ore Mine in South Africa. Since
then, in-pit crushing and conveying systems has
been adopted in many surface mines, both coal and
non-coal, throughout the world.
In India, in-pit crushing and conveying systems have
been installed in surface coal mines at Piparwar
Opencast Project (CCL), Ramagundam-II Opencast
Mine (SCCL) and Padmapur Opencast Project (WCL),
and in Limestone mine at Jhinkpani (ACC).
In-pit crushing and conveying systems may be used
to transport ore (i.e., pay mineral) to the processing
plant and/or overburden (waste) to the waste dumps
from the pit.
In most of the cases, the pay mineral (which normally
requires primary crushing in its preparation process)
can be transported by belt conveyors at lower cost
than by trucks. But for overburden conveying, the
necessary preparation and dumping costs are a
considerable extra that requires to be offset by
savings in trucking and truck haulage costs. In
general, only when large quantities of overburden
are to be transported over fairly long distances at
considerable lifting heights, application of crusher-
conveyor-stacker system may be justified.
General Applicability of In-pit Crushing and
Conveying Systems:
The various in-pit crushing systems may be
classified broadly into three categories –
Stationary/Permanent in-pit crushing system,
Relocatable/Movable in-pit crushing system and
Mobile in-pit crushing system.
Types of In-pit Crushing System
In this type of systems, large capacity crushers
(separate crusher for ore and for waste) with proper
foundation are installed in permanent locations at or
near the pit floor level. The material, excavated
and/or loaded by shovel, from all the working faces
(of same type, i.e. ore or waste) are transported to
the respective crusher by trucks, and thereafter the
crushed material is transported to respective
location (ore plant or waste dump) by stationary
conveyors.
Stationary/Permanent In-pit Crushing System:
• In course of operations the pit floor depth remains
essentially same,
• Large quantities of ore to be transported over a
long distance that may or may not be associated
with considerable vertical lift.
• The benches on one side of the pit (or at least a part
of it) have reached their ultimate position and
became stationary.
The crushers are usually positioned so as not to
create any inconvenience in the future extension of
mine working and to ensure that uphill movement of
loaded trucks carrying material from the working
faces to the crusher is minimized. However, with the
advancement of mine workings, the truck transport
distance increases with time as the faces moves away
from the crusher location.
This system is most suitable in case of surface mines
mining flat ore bodies so that –
Following components form the chain of handling
devices for stationary/permanent in-pit crushing and
conveying system.
Sl.
No.
Activity Equipment
1. Crushing • Stationary crusher unit
2.
Transportation
of ore to plant
• Stationary conveyors
3.
Transportation
of waste to
waste dumps
• Stationary conveyors
• Shiftable dump face conveyors
• Tipper car
• Spreader
WASTE ROCK
CRUSHER
Stationary Waste Conveyor
To Waste Dump
OS
OS
OS
OS
OF-n
OF-3
OF-2
OF-1
ORE
CRUSHER
T
T
T
Stationary Ore Conveyor
To Ore Plant
T
WS
WS
WS
WS
WF-n
WF-3
WF-2
WF-1
T
T
T
T
WF – Waste Face WS– Waste Shovel
OF – Ore Face OS– Ore Shovel
T – Material transported by truck
A schematic presentation of stationary in-pit
crushing and conveying system is given below.
In such systems, the crushers used are of medium
capacity, and they that do not require extensive
foundation work as required by stationary in-pit
crushers. In a mine, depending on the mine
specifics (the number of working faces and their
relative location, material types to be handled total
tonnage of ore and of waste to be handled), there
can be one or more such crushers installed.
Generally, each crusher serves a group of working
faces excavating same type of material (ore or
waste), and the crusher is placed at a location such
that the overall truck haulage distance from the
working faces it serves is optimized. The crusher,
following the advance of working faces it serves, is
relocated/moved to the new load center at
appropriate time intervals.
Relocatable/Movable In-pit Crushing System:
• The production is medium to large
• The working faces are distributed in number of
benches
• A stationary in-pit crushing system is not
suitable.
In this system, also, the material excavated and/or
loaded by shovel is transported by trucks from the
face to the crusher. The haulage distance is kept
as short as practicable and, if possible, uphill
haulage is either avoided or restricted to a
minimum. The crusher discharges onto relocatable
conveyor (that is relocated or lengthened in
conjunction with the relocation of the crusher)
which in turn transfers the material to the
stationary conveyor. This system is suitable for a
mine where –
Following components form the chain of handling
devices for relocatable/movable in-pit crushing and
conveying system.
Sl.
No.
Activity Equipment
1. Crushing
• Relocatable crusher unit
• Moving device
2.
Transportation
of ore to plant
• Relocatable conveyors
• Stationery conveyors
3.
Transportation
of waste to
waste dumps
• Relocatable conveyors
• Stationery conveyors
• Shiftable dump face conveyors
• Tripper car
• Spreader
A relocatable in-pit crushing system has been
installed at Ramagundam-II Opencast Mine of SCCL.
Altogether 3 numbers of double roll type crushers
for overburden and one double roll type crusher for
coal have been installed. After crushing, the coal is
conveyed to CHP via coal conveyors and
overburden is transported to overburden dumps via
overburden conveyor. In the dump area, the material
is transferred to shiftable dump face conveyor for
subsequent dumping via tripper car and spreader.
There are 3 numbers of tripper car and 3 numbers of
spreader for dumping the overburden suitably at the
dumpsites.
A schematic presentation of relocatable in-pit
crushing and conveying system is given below.
WS
WS
WS
WF-1n
WF-12
WF-11
T
T
T
WC 1
WS
WS
WS
WF-2n
WF-22
WF-21
T
T
T
WC 2
WS
WS
WS
WF-mn
WF-m2
WF-m1
T
T
T
WC m
RC
RC
RC
To Waste Dump
Stationary Waste Conveyor
OS
OS
OS
OF-1n
OF-12
OF-11
T
T
T
OC 1
OS
OS
OS
OF-2n
OF-22
OF-21
T
T
T
OC 2
OS
OS
OS
OF-mn
OF-m2
OF-m1
T
T
T
OC m
RC
RC
RC
To Ore Plant
Stationary Ore Conveyor
WF – Waste Face OF – Ore Face
WS – Waste Shovel OS – Ore Shovel
WC – Waste Crusher OC – Ore Crusher
RC – Relocatable and/or extendable conveyor
T – Material transported by truck
In such a system, the crusher is fully mobile and is
located at vary near the face. The crusher is fed
directly by an excavator (Rope shovel or hydraulic
shovel or front-end-loader). The crusher discharges
either directly or via a beltwagon (or conveyor
bridge in some cases) onto the shiftable face
conveyor. Finally the material is conveyed to the
respective destination (ore plant for one and waste
dumps for waste) through a network of belt
conveyors. The crushers are generally of small
capacity sufficient to handle the production from the
face where it is located.
This system is applicable for mines where only a
few fast moving working faces exist and the
excavators stay permanently at the same face.
Mobile In-pit Crushing Systems:
Following components form the chain of handling
devices for mobile in-pit crushing and conveying
system.
Sl.
No.
Activity Equipment
1. Crushing • Mobile crusher unit
2.
Transportation
of ore to plant
• Transfer unit-belt wagon, mobile
conveyor bridge
• Shiftable conveyor with mobile hopper
• Stationary conveyors
3.
Transportation
of waste to
waste dumps
• Transfer unit-belt wagon, mobile
conveyor bridge
• Shiftable conveyors with mobile hopper
• Stationary conveyors
• Shiftable dump face conveyors
• Tripper Car
• Overburden Spreader
A schematic presentation of mobile in-pit
crushing and conveying system is given below.
WS - 1
WF-1
WC - 1
SFCBC
WS - 2
WF-2
WC - 2
SFCBC
WS - n
WF-n
WC - n
SFCBC
RC
RC
RC
To Waste Dump
Stationary Waste Conveyor
OS - 1
OF-1
OC - 1
SFCBC
OS - 2
OF-2
OC - 2
SFCBC
OS - n
OF-n
OC - n
SFCBC
RC
RC
RC
To Ore Plant
Stationary Ore Conveyor
WF – Waste Face OF – Ore Face
WS – Waste Shovel OS – Ore Shovel
WC – Mobile Crusher for Waste
OC – Mobile Crusher for Ore
SFC – Shiftable Face Conveyor
BC – Bench Conveyor
RC – Relocatable and/or extendable
conveyor
A mobile in-pit crushing system is in operation at
Piparwar Opencast Project of CCL. The in-pit
crushing is done only for coal excavated at the
working face of lowermost coal seam (Lower Dakra),
and the crushed coal is transported directly to the
coal washery located near by the mine via a system
of belt conveyors. The components for the system
are 25m3 rope shovel, 2800 TPH mobile roll crusher
unit, belt wagon, shiftable face belt conveyor and
other conveyors (shiftable and stationary).
Applicability of Various Crusher Types
 Not Suitable Most Suitable  Suitable
Material conditions
Crusher Type
Compressive Strength Crushing Ratio Abrasivity Moisture
Soft Medium Hard 1:5 1:15 1:30 1:50 Low Medium High Dry Moist Wet
Single-Toggle
Jaw crusher
            
Double – Toggle
Jaw crusher
            
Cone Crusher             
Roll Crusher             
Single shaft
Hammer crusher
            
Single shaft Hammer
crusher with grate
            
Double shaft
Hammer crusher
            
Double shaft Hammer
crusher with grate
            
Single shaft
Impact crusher
            
Single shaft Impact
crusher with grate
            
Double shaft
Impact crusher
            
Double shaft Impact
crusher with grate
            
In pit crushing and conveying  in surface mines

More Related Content

What's hot

Longwall Mining
Longwall MiningLongwall Mining
Longwall MiningVR M
 
Kope winder or friction winder ppt
Kope winder or friction winder pptKope winder or friction winder ppt
Kope winder or friction winder pptAMIT SAHU
 
Shaft sinking.
Shaft sinking.Shaft sinking.
Shaft sinking.Safdar Ali
 
Transportation in underground mines
Transportation  in underground mines Transportation  in underground mines
Transportation in underground mines vanam mareswara rao
 
The continuous surface miner
The continuous surface minerThe continuous surface miner
The continuous surface minerVIJAY KUMAR
 
Blast design in opencast mining
Blast design in opencast miningBlast design in opencast mining
Blast design in opencast mininggopal karmakar
 
Underground metal mining methods
Underground metal mining methodsUnderground metal mining methods
Underground metal mining methodsSafdar Ali
 
Thin seam mining
Thin seam miningThin seam mining
Thin seam miningSafdar Ali
 
Selection of longwall powered roof support
Selection of longwall powered roof supportSelection of longwall powered roof support
Selection of longwall powered roof supportUlimella Siva Sankar
 
Different Raising Techniques in mining
Different Raising Techniques in miningDifferent Raising Techniques in mining
Different Raising Techniques in miningRishabh Ranjan
 

What's hot (20)

Highwall mining
Highwall miningHighwall mining
Highwall mining
 
Caving Underground Mining Methods (longwall, Sublevel caving, & Block caving)
Caving Underground Mining Methods (longwall, Sublevel caving, &  Block caving)Caving Underground Mining Methods (longwall, Sublevel caving, &  Block caving)
Caving Underground Mining Methods (longwall, Sublevel caving, & Block caving)
 
Longwall Mining
Longwall MiningLongwall Mining
Longwall Mining
 
Highwall mining – a new approach in india
Highwall mining – a new approach in indiaHighwall mining – a new approach in india
Highwall mining – a new approach in india
 
Kope winder or friction winder ppt
Kope winder or friction winder pptKope winder or friction winder ppt
Kope winder or friction winder ppt
 
Shaft sinking.
Shaft sinking.Shaft sinking.
Shaft sinking.
 
Transportation in underground mines
Transportation  in underground mines Transportation  in underground mines
Transportation in underground mines
 
Longwall mining[1]
Longwall mining[1]Longwall mining[1]
Longwall mining[1]
 
The continuous surface miner
The continuous surface minerThe continuous surface miner
The continuous surface miner
 
Blast design in opencast mining
Blast design in opencast miningBlast design in opencast mining
Blast design in opencast mining
 
Underground metal mining methods
Underground metal mining methodsUnderground metal mining methods
Underground metal mining methods
 
Subsidence in coal mines
Subsidence in coal minesSubsidence in coal mines
Subsidence in coal mines
 
Thin seam mining
Thin seam miningThin seam mining
Thin seam mining
 
Selection of longwall powered roof support
Selection of longwall powered roof supportSelection of longwall powered roof support
Selection of longwall powered roof support
 
Continuous miner
Continuous minerContinuous miner
Continuous miner
 
depllaring in coal mines
depllaring in coal minesdepllaring in coal mines
depllaring in coal mines
 
Applicability of hydraulic mining
Applicability of hydraulic miningApplicability of hydraulic mining
Applicability of hydraulic mining
 
Longwall mining
Longwall miningLongwall mining
Longwall mining
 
Different Raising Techniques in mining
Different Raising Techniques in miningDifferent Raising Techniques in mining
Different Raising Techniques in mining
 
Road Header and Bolter Miner
Road Header and Bolter MinerRoad Header and Bolter Miner
Road Header and Bolter Miner
 

Similar to In pit crushing and conveying in surface mines

Drag line excavator
Drag line excavatorDrag line excavator
Drag line excavatorParth Desani
 
The Futran System: a new technology innovation for improved performance in co...
The Futran System: a new technology innovation for improved performance in co...The Futran System: a new technology innovation for improved performance in co...
The Futran System: a new technology innovation for improved performance in co...Tristan Wiggill
 
Transport in Open Pits______SM_MI10415MI
Transport in Open Pits______SM_MI10415MITransport in Open Pits______SM_MI10415MI
Transport in Open Pits______SM_MI10415MIRomil Mishra
 
Troughed Belt Conveyor & Flat Belt Conveyor
Troughed Belt Conveyor & Flat Belt ConveyorTroughed Belt Conveyor & Flat Belt Conveyor
Troughed Belt Conveyor & Flat Belt ConveyorMAKAUT
 
Dragline machine at dhudhichua project ,singrauli
Dragline machine at dhudhichua project ,singrauliDragline machine at dhudhichua project ,singrauli
Dragline machine at dhudhichua project ,singrauliTauhid Mohammad
 
Transportation of coal ppt
Transportation of coal pptTransportation of coal ppt
Transportation of coal pptNaina Rajput
 
High angle conveying
High angle conveyingHigh angle conveying
High angle conveyingSafdar Ali
 
High conveying in sangle urface mines
High conveying in sangle urface minesHigh conveying in sangle urface mines
High conveying in sangle urface minesSafdar Ali
 
Coal Mining Surface Equipment and Machines
Coal Mining Surface Equipment and MachinesCoal Mining Surface Equipment and Machines
Coal Mining Surface Equipment and MachinesCharles Jojo Besitan
 
Design and Performance of Highwall Mining
Design and Performance of Highwall MiningDesign and Performance of Highwall Mining
Design and Performance of Highwall MiningShantanu kumar
 
Highwall mining, a new approach in india revised
Highwall mining, a new approach in india  revisedHighwall mining, a new approach in india  revised
Highwall mining, a new approach in india revisedTIKESHWAR MAHTO
 
Mine Haulage - A Challenge for The Transportation Industry
Mine Haulage - A Challenge for The Transportation IndustryMine Haulage - A Challenge for The Transportation Industry
Mine Haulage - A Challenge for The Transportation IndustryShaun Frater
 
Material handling equipments : conveyors and elevators
Material handling equipments : conveyors and elevators Material handling equipments : conveyors and elevators
Material handling equipments : conveyors and elevators ajaz malla
 
Environmental Engineering (transfer and transport of solid wastes)
Environmental Engineering (transfer and transport of solid wastes)Environmental Engineering (transfer and transport of solid wastes)
Environmental Engineering (transfer and transport of solid wastes)Latif Hyder Wadho
 

Similar to In pit crushing and conveying in surface mines (20)

Belt conveyor
Belt conveyorBelt conveyor
Belt conveyor
 
Drag line excavator
Drag line excavatorDrag line excavator
Drag line excavator
 
Belt conveyor _2_
Belt conveyor _2_Belt conveyor _2_
Belt conveyor _2_
 
The Futran System: a new technology innovation for improved performance in co...
The Futran System: a new technology innovation for improved performance in co...The Futran System: a new technology innovation for improved performance in co...
The Futran System: a new technology innovation for improved performance in co...
 
Transport in Open Pits______SM_MI10415MI
Transport in Open Pits______SM_MI10415MITransport in Open Pits______SM_MI10415MI
Transport in Open Pits______SM_MI10415MI
 
Troughed Belt Conveyor & Flat Belt Conveyor
Troughed Belt Conveyor & Flat Belt ConveyorTroughed Belt Conveyor & Flat Belt Conveyor
Troughed Belt Conveyor & Flat Belt Conveyor
 
Dragline machine at dhudhichua project ,singrauli
Dragline machine at dhudhichua project ,singrauliDragline machine at dhudhichua project ,singrauli
Dragline machine at dhudhichua project ,singrauli
 
Transportation of coal ppt
Transportation of coal pptTransportation of coal ppt
Transportation of coal ppt
 
Chain conveyors
Chain conveyorsChain conveyors
Chain conveyors
 
Conveying equipment
Conveying equipmentConveying equipment
Conveying equipment
 
High angle conveying
High angle conveyingHigh angle conveying
High angle conveying
 
High conveying in sangle urface mines
High conveying in sangle urface minesHigh conveying in sangle urface mines
High conveying in sangle urface mines
 
Coal Mining Surface Equipment and Machines
Coal Mining Surface Equipment and MachinesCoal Mining Surface Equipment and Machines
Coal Mining Surface Equipment and Machines
 
Design and Performance of Highwall Mining
Design and Performance of Highwall MiningDesign and Performance of Highwall Mining
Design and Performance of Highwall Mining
 
Highwall mining, a new approach in india revised
Highwall mining, a new approach in india  revisedHighwall mining, a new approach in india  revised
Highwall mining, a new approach in india revised
 
Mine Haulage - A Challenge for The Transportation Industry
Mine Haulage - A Challenge for The Transportation IndustryMine Haulage - A Challenge for The Transportation Industry
Mine Haulage - A Challenge for The Transportation Industry
 
Material handling equipments : conveyors and elevators
Material handling equipments : conveyors and elevators Material handling equipments : conveyors and elevators
Material handling equipments : conveyors and elevators
 
Environmental Engineering (transfer and transport of solid wastes)
Environmental Engineering (transfer and transport of solid wastes)Environmental Engineering (transfer and transport of solid wastes)
Environmental Engineering (transfer and transport of solid wastes)
 
Construction Equipment -Crane - Hoisting equipment
Construction Equipment -Crane - Hoisting equipmentConstruction Equipment -Crane - Hoisting equipment
Construction Equipment -Crane - Hoisting equipment
 
maquinarias.pptx
maquinarias.pptxmaquinarias.pptx
maquinarias.pptx
 

More from Safdar Ali

Safety in mines
Safety in minesSafety in mines
Safety in minesSafdar Ali
 
Explosives and accesories
Explosives and accesoriesExplosives and accesories
Explosives and accesoriesSafdar Ali
 
Role of management information systems in a mine.
Role of management information systems in a mine.Role of management information systems in a mine.
Role of management information systems in a mine.Safdar Ali
 
Pre requisites of marine operations
Pre requisites of marine operationsPre requisites of marine operations
Pre requisites of marine operationsSafdar Ali
 
Nuclear devices for mining
Nuclear devices for miningNuclear devices for mining
Nuclear devices for miningSafdar Ali
 
Mining of manganese nodules from sea floor
Mining of manganese nodules from sea floorMining of manganese nodules from sea floor
Mining of manganese nodules from sea floorSafdar Ali
 
Mine water risk in open pit slope stability
Mine water risk in open pit slope stabilityMine water risk in open pit slope stability
Mine water risk in open pit slope stabilitySafdar Ali
 
Innovations and trend in metal mining & tunnellng
Innovations and trend in metal mining & tunnellngInnovations and trend in metal mining & tunnellng
Innovations and trend in metal mining & tunnellngSafdar Ali
 
Lighting terminlologyand their units
Lighting terminlologyand their unitsLighting terminlologyand their units
Lighting terminlologyand their unitsSafdar Ali
 
Evaluation of slope stability for waste rock dumps in a mine
Evaluation of slope stability for waste rock dumps in a mineEvaluation of slope stability for waste rock dumps in a mine
Evaluation of slope stability for waste rock dumps in a mineSafdar Ali
 
Final grouting freezing
Final grouting freezingFinal grouting freezing
Final grouting freezingSafdar Ali
 
Digitization and 3d modelling of a mine plan
Digitization and 3d modelling of a mine planDigitization and 3d modelling of a mine plan
Digitization and 3d modelling of a mine planSafdar Ali
 
Variety of mine plans and sections & second schedule
Variety of mine plans and sections & second scheduleVariety of mine plans and sections & second schedule
Variety of mine plans and sections & second scheduleSafdar Ali
 
Statutory provisions for the preaparation of mine plans and sections
Statutory provisions for the preaparation of mine plans and sectionsStatutory provisions for the preaparation of mine plans and sections
Statutory provisions for the preaparation of mine plans and sectionsSafdar Ali
 
Gps & its applications in opencast mine surveying
Gps & its applications in opencast mine surveyingGps & its applications in opencast mine surveying
Gps & its applications in opencast mine surveyingSafdar Ali
 
Laser and its mining applications
Laser and its mining applicationsLaser and its mining applications
Laser and its mining applicationsSafdar Ali
 
Gyrotheodolite
GyrotheodoliteGyrotheodolite
GyrotheodoliteSafdar Ali
 

More from Safdar Ali (20)

Safety in mines
Safety in minesSafety in mines
Safety in mines
 
Tunneling
TunnelingTunneling
Tunneling
 
Explosives and accesories
Explosives and accesoriesExplosives and accesories
Explosives and accesories
 
Role of management information systems in a mine.
Role of management information systems in a mine.Role of management information systems in a mine.
Role of management information systems in a mine.
 
Basting
BastingBasting
Basting
 
Pre requisites of marine operations
Pre requisites of marine operationsPre requisites of marine operations
Pre requisites of marine operations
 
Nuclear devices for mining
Nuclear devices for miningNuclear devices for mining
Nuclear devices for mining
 
Mining of manganese nodules from sea floor
Mining of manganese nodules from sea floorMining of manganese nodules from sea floor
Mining of manganese nodules from sea floor
 
Mine water risk in open pit slope stability
Mine water risk in open pit slope stabilityMine water risk in open pit slope stability
Mine water risk in open pit slope stability
 
Innovations and trend in metal mining & tunnellng
Innovations and trend in metal mining & tunnellngInnovations and trend in metal mining & tunnellng
Innovations and trend in metal mining & tunnellng
 
Lighting terminlologyand their units
Lighting terminlologyand their unitsLighting terminlologyand their units
Lighting terminlologyand their units
 
Evaluation of slope stability for waste rock dumps in a mine
Evaluation of slope stability for waste rock dumps in a mineEvaluation of slope stability for waste rock dumps in a mine
Evaluation of slope stability for waste rock dumps in a mine
 
Final grouting freezing
Final grouting freezingFinal grouting freezing
Final grouting freezing
 
Digitization and 3d modelling of a mine plan
Digitization and 3d modelling of a mine planDigitization and 3d modelling of a mine plan
Digitization and 3d modelling of a mine plan
 
Variety of mine plans and sections & second schedule
Variety of mine plans and sections & second scheduleVariety of mine plans and sections & second schedule
Variety of mine plans and sections & second schedule
 
Statutory provisions for the preaparation of mine plans and sections
Statutory provisions for the preaparation of mine plans and sectionsStatutory provisions for the preaparation of mine plans and sections
Statutory provisions for the preaparation of mine plans and sections
 
Gps & its applications in opencast mine surveying
Gps & its applications in opencast mine surveyingGps & its applications in opencast mine surveying
Gps & its applications in opencast mine surveying
 
Laser and its mining applications
Laser and its mining applicationsLaser and its mining applications
Laser and its mining applications
 
Gyrotheodolite
GyrotheodoliteGyrotheodolite
Gyrotheodolite
 
Gps2
Gps2Gps2
Gps2
 

Recently uploaded

Class 11 Legal Studies Ch-1 Concept of State .pdf
Class 11 Legal Studies Ch-1 Concept of State .pdfClass 11 Legal Studies Ch-1 Concept of State .pdf
Class 11 Legal Studies Ch-1 Concept of State .pdfakmcokerachita
 
URLs and Routing in the Odoo 17 Website App
URLs and Routing in the Odoo 17 Website AppURLs and Routing in the Odoo 17 Website App
URLs and Routing in the Odoo 17 Website AppCeline George
 
Call Girls in Dwarka Mor Delhi Contact Us 9654467111
Call Girls in Dwarka Mor Delhi Contact Us 9654467111Call Girls in Dwarka Mor Delhi Contact Us 9654467111
Call Girls in Dwarka Mor Delhi Contact Us 9654467111Sapana Sha
 
Sanyam Choudhary Chemistry practical.pdf
Sanyam Choudhary Chemistry practical.pdfSanyam Choudhary Chemistry practical.pdf
Sanyam Choudhary Chemistry practical.pdfsanyamsingh5019
 
Introduction to AI in Higher Education_draft.pptx
Introduction to AI in Higher Education_draft.pptxIntroduction to AI in Higher Education_draft.pptx
Introduction to AI in Higher Education_draft.pptxpboyjonauth
 
MENTAL STATUS EXAMINATION format.docx
MENTAL     STATUS EXAMINATION format.docxMENTAL     STATUS EXAMINATION format.docx
MENTAL STATUS EXAMINATION format.docxPoojaSen20
 
Presiding Officer Training module 2024 lok sabha elections
Presiding Officer Training module 2024 lok sabha electionsPresiding Officer Training module 2024 lok sabha elections
Presiding Officer Training module 2024 lok sabha electionsanshu789521
 
Incoming and Outgoing Shipments in 1 STEP Using Odoo 17
Incoming and Outgoing Shipments in 1 STEP Using Odoo 17Incoming and Outgoing Shipments in 1 STEP Using Odoo 17
Incoming and Outgoing Shipments in 1 STEP Using Odoo 17Celine George
 
How to Configure Email Server in Odoo 17
How to Configure Email Server in Odoo 17How to Configure Email Server in Odoo 17
How to Configure Email Server in Odoo 17Celine George
 
The Most Excellent Way | 1 Corinthians 13
The Most Excellent Way | 1 Corinthians 13The Most Excellent Way | 1 Corinthians 13
The Most Excellent Way | 1 Corinthians 13Steve Thomason
 
Separation of Lanthanides/ Lanthanides and Actinides
Separation of Lanthanides/ Lanthanides and ActinidesSeparation of Lanthanides/ Lanthanides and Actinides
Separation of Lanthanides/ Lanthanides and ActinidesFatimaKhan178732
 
CARE OF CHILD IN INCUBATOR..........pptx
CARE OF CHILD IN INCUBATOR..........pptxCARE OF CHILD IN INCUBATOR..........pptx
CARE OF CHILD IN INCUBATOR..........pptxGaneshChakor2
 
Mastering the Unannounced Regulatory Inspection
Mastering the Unannounced Regulatory InspectionMastering the Unannounced Regulatory Inspection
Mastering the Unannounced Regulatory InspectionSafetyChain Software
 
A Critique of the Proposed National Education Policy Reform
A Critique of the Proposed National Education Policy ReformA Critique of the Proposed National Education Policy Reform
A Critique of the Proposed National Education Policy ReformChameera Dedduwage
 
Organic Name Reactions for the students and aspirants of Chemistry12th.pptx
Organic Name Reactions  for the students and aspirants of Chemistry12th.pptxOrganic Name Reactions  for the students and aspirants of Chemistry12th.pptx
Organic Name Reactions for the students and aspirants of Chemistry12th.pptxVS Mahajan Coaching Centre
 
Kisan Call Centre - To harness potential of ICT in Agriculture by answer farm...
Kisan Call Centre - To harness potential of ICT in Agriculture by answer farm...Kisan Call Centre - To harness potential of ICT in Agriculture by answer farm...
Kisan Call Centre - To harness potential of ICT in Agriculture by answer farm...Krashi Coaching
 
Science 7 - LAND and SEA BREEZE and its Characteristics
Science 7 - LAND and SEA BREEZE and its CharacteristicsScience 7 - LAND and SEA BREEZE and its Characteristics
Science 7 - LAND and SEA BREEZE and its CharacteristicsKarinaGenton
 
mini mental status format.docx
mini    mental       status     format.docxmini    mental       status     format.docx
mini mental status format.docxPoojaSen20
 

Recently uploaded (20)

Class 11 Legal Studies Ch-1 Concept of State .pdf
Class 11 Legal Studies Ch-1 Concept of State .pdfClass 11 Legal Studies Ch-1 Concept of State .pdf
Class 11 Legal Studies Ch-1 Concept of State .pdf
 
9953330565 Low Rate Call Girls In Rohini Delhi NCR
9953330565 Low Rate Call Girls In Rohini  Delhi NCR9953330565 Low Rate Call Girls In Rohini  Delhi NCR
9953330565 Low Rate Call Girls In Rohini Delhi NCR
 
URLs and Routing in the Odoo 17 Website App
URLs and Routing in the Odoo 17 Website AppURLs and Routing in the Odoo 17 Website App
URLs and Routing in the Odoo 17 Website App
 
Call Girls in Dwarka Mor Delhi Contact Us 9654467111
Call Girls in Dwarka Mor Delhi Contact Us 9654467111Call Girls in Dwarka Mor Delhi Contact Us 9654467111
Call Girls in Dwarka Mor Delhi Contact Us 9654467111
 
Sanyam Choudhary Chemistry practical.pdf
Sanyam Choudhary Chemistry practical.pdfSanyam Choudhary Chemistry practical.pdf
Sanyam Choudhary Chemistry practical.pdf
 
Introduction to AI in Higher Education_draft.pptx
Introduction to AI in Higher Education_draft.pptxIntroduction to AI in Higher Education_draft.pptx
Introduction to AI in Higher Education_draft.pptx
 
MENTAL STATUS EXAMINATION format.docx
MENTAL     STATUS EXAMINATION format.docxMENTAL     STATUS EXAMINATION format.docx
MENTAL STATUS EXAMINATION format.docx
 
Presiding Officer Training module 2024 lok sabha elections
Presiding Officer Training module 2024 lok sabha electionsPresiding Officer Training module 2024 lok sabha elections
Presiding Officer Training module 2024 lok sabha elections
 
Incoming and Outgoing Shipments in 1 STEP Using Odoo 17
Incoming and Outgoing Shipments in 1 STEP Using Odoo 17Incoming and Outgoing Shipments in 1 STEP Using Odoo 17
Incoming and Outgoing Shipments in 1 STEP Using Odoo 17
 
How to Configure Email Server in Odoo 17
How to Configure Email Server in Odoo 17How to Configure Email Server in Odoo 17
How to Configure Email Server in Odoo 17
 
The Most Excellent Way | 1 Corinthians 13
The Most Excellent Way | 1 Corinthians 13The Most Excellent Way | 1 Corinthians 13
The Most Excellent Way | 1 Corinthians 13
 
Separation of Lanthanides/ Lanthanides and Actinides
Separation of Lanthanides/ Lanthanides and ActinidesSeparation of Lanthanides/ Lanthanides and Actinides
Separation of Lanthanides/ Lanthanides and Actinides
 
CARE OF CHILD IN INCUBATOR..........pptx
CARE OF CHILD IN INCUBATOR..........pptxCARE OF CHILD IN INCUBATOR..........pptx
CARE OF CHILD IN INCUBATOR..........pptx
 
Mastering the Unannounced Regulatory Inspection
Mastering the Unannounced Regulatory InspectionMastering the Unannounced Regulatory Inspection
Mastering the Unannounced Regulatory Inspection
 
A Critique of the Proposed National Education Policy Reform
A Critique of the Proposed National Education Policy ReformA Critique of the Proposed National Education Policy Reform
A Critique of the Proposed National Education Policy Reform
 
Organic Name Reactions for the students and aspirants of Chemistry12th.pptx
Organic Name Reactions  for the students and aspirants of Chemistry12th.pptxOrganic Name Reactions  for the students and aspirants of Chemistry12th.pptx
Organic Name Reactions for the students and aspirants of Chemistry12th.pptx
 
Kisan Call Centre - To harness potential of ICT in Agriculture by answer farm...
Kisan Call Centre - To harness potential of ICT in Agriculture by answer farm...Kisan Call Centre - To harness potential of ICT in Agriculture by answer farm...
Kisan Call Centre - To harness potential of ICT in Agriculture by answer farm...
 
Science 7 - LAND and SEA BREEZE and its Characteristics
Science 7 - LAND and SEA BREEZE and its CharacteristicsScience 7 - LAND and SEA BREEZE and its Characteristics
Science 7 - LAND and SEA BREEZE and its Characteristics
 
mini mental status format.docx
mini    mental       status     format.docxmini    mental       status     format.docx
mini mental status format.docx
 
TataKelola dan KamSiber Kecerdasan Buatan v022.pdf
TataKelola dan KamSiber Kecerdasan Buatan v022.pdfTataKelola dan KamSiber Kecerdasan Buatan v022.pdf
TataKelola dan KamSiber Kecerdasan Buatan v022.pdf
 

In pit crushing and conveying in surface mines

  • 1. IN-PIT CRUSHING AND CONVEYING IN SURFACE MINES
  • 2.
  • 3. INTRODUCTION In hard rock surface mines, the mining system adopted is generally a discontinuous/cyclic one. Such a system broadly consists of the following unit operations vis-à-vis the equipment to accomplish them. Ground preparation for subsequent excavation and/or loading is generally accomplished with the help of drilling and blasting. Drilling may be done by percussive / rotary / rotary-percussive blasthole drills depending on site specifics and requirements. Ground preparation:
  • 4. The blasted material (ore and/or waste) is excavated and/or loaded by cyclic excavators. Electric rope shovels or hydraulic shovels are most commonly used for this purpose. Draglines may be used for handling overburden (fully or partly) in surface coal mines mining horizontal or flat (dip upto 1 in 20) seams. Hydraulic backhoe is used where digging below the crawler level is required, and front-end-loader may also be used as primary excavator to handle ore and/or waste under some special situations. Excavation and/or loading:
  • 5. Shovel (electric/hydraulic), backhoe and front-end- loader - all loads the excavated material into the dumper for subsequent transportation either to the ore stock pile/plant area or to the waste-dump (external or internal or both). Dragline transports its own load to the adjacent de-coaled area following the method of strip mining. Transportation: In case of both the dumper and dragline, dumping is done by the equipment itself. Dumping: Levelling, in all most all the cases, is done by dozer. Levelling:
  • 6. Of the above unit operations, either the drilling & blasting or the transportation is the most costly one. With the increase in depth of working, generally the unit cost of drilling & blasting remains unchanged, whereas, the unit cost of transportation by dumper for both the ore and waste increases, and the rate of increase in unit transport cost also increases with the increase in depth. As a result of this, generally in shallower mines the drilling & blasting operation may be most costly one, but in deeper mines the transportation becomes the costliest unit operation. So it is necessary to minimize the unit transport cost for better economy of operation particularly in case of deeper mines.
  • 7. During 1940s, particularly after the Second World War, the dumper transport system because very popular in hard rock mines. The dumpers were preferred over rail-road transport system because of its flexibility and the ability to negotiate a higher gradient (1 in 16) compared to that negotiated by rail road system ( 1 in 33). However, during 1960s the fuel prices started rising steadily, and as a result of which the dumper transportation cost also started rising very steeply. In the early part of 1960s, attempts were made to control/reduce the unit transport cost by increasing the truck size thereby taking the advantage of scale of operation. The main focus was to reduce the manpower and with it the personnel cost associated. But later on the attention of the mine planners and operators were drawn to the application of conveyor as an alternative means of transportation due to the fact that substantial savings of cost is possible by changing to conveyor transport from truck haulage system.
  • 8. CONVEYOR TRANSPORT VS TRUCK HAULAGE In a comparison of dump trucks with belt conveyor for mine transport, the following may be observed. The trucks consume 60% of available mechanical energy to carry their dead weight; only 40% energy is used to carry the payload. But for belt conveyors, 10% to 20% energy is required to carry the belt while carrying the material in plane or uphill direction and rest 80% to 90% energy is utilized to carry the material, Conveyors carrying material down hill may generate energy. Dump trucks need good haul road for their efficient operation. So good compact haul roads must be built and maintained. For conveyors such requirement is not there or very less.
  • 9. The dump trucks can negotiate maximum gradient upto 1 in 16 for long hauls whereas the conveyors can run effectively upto a gradient of 1 in 4. Productivity of dump trucks rapidly goes down with the increase in length of transport distance and of the lifting height due to increase in cycle time. The effects of increase in transport distance and of the lifting height on the productivity in case of conveyor transport system is very nominal. The energy cost to transport same payload over same distance or for lifting same vertical height is more in case of dumper than in case of conveyor. To transport 100 te of payload over a distance of 5 kms, the dump truck will need about 40 lit.of diesel ( Rs.1000/-), whereas the belt conveyor will use about 60 Kwh ( Rs.180/-). To hoist 100 te of payload by 50m, the dump truck will need about 10 lit of diesel ( Rs.250/-), whereas the belt conveyor will use about 15 Kwh ( Rs.45/-).
  • 10. A brief account of merits and demerits of belt conveyor systems over truck haulage system is given below: Merits:  Lower capital expenditure due to a longer depreciation period  Lower energy costs and superior energy efficiency  Less manpower required  Lower maintenance cost  Can negotiate higher gradients (upto 1 in 4)  Can handle high output (upto 4000 te/hour)  Less sensitive to weather conditions  Less adverse effects on environment (less dust, noise, etc.)  High availability  Possibility of automation
  • 11.  Less flexibility  High initial investment costs  Require size material for efficient operation  Less suitable for big size lumps or un-sized material  In the event of stoppage of any one of the belts, the whole belt network has to be stopped Demerits: Trucks are capable of handling almost any size of lump that may be loaded by an excavator/loader onto it, but this is not so in case of a conveyor. The maximum lump size that can be transported on conveyors depends on belt width, speed, troughing angle and conveyor inclination. The design of a conveyor will also be dependent on the frequency of large lumps to be carried.
  • 12. As a rule of thumb, the maximum lump size should be less than 350 mm for belts of 1000 mm or more width, less than 300mm for belts of 800 mm width and less than 200 mm for belt width of 650mm. Therefore, in hard rock mines, to utilize belt conveyors as the means of transportation of materials (ore and/or overburden/waste) out of pit to the preparation plant or to the waste dumps, the material needs to be sized before being loaded onto a conveyor. This calls for installation of in-pit crushing systems.
  • 13. IN-PIT CRUSHING SYSTEMS In response to the increasing truck haulage costs and in the face of increasing tonnage to be moved, two large U.S. copper mines responded in late 1960s and early 1970s by installing high capacity belt conveyor systems with large, permanent type, gyratory in-pit crushers. The systems did not eliminate the trucks all together, but restricted their use only within the pit from the working faces to the crusher, and the crushed material thereafter was transported to the plant (ore) and waste dumps (waste) through belt conveyors.
  • 14. Duval Corporation began installation of the first movable in-pit crushing and conveying systems in 1981 at its Sierrita Copper and Molybdenum Minenear Tucson, Arizona, and the operation of the system began in 1982 December. Operation of another similar system also began in 1982 at Sishen’s North Iron Ore Mine in South Africa. Since then, in-pit crushing and conveying systems has been adopted in many surface mines, both coal and non-coal, throughout the world. In India, in-pit crushing and conveying systems have been installed in surface coal mines at Piparwar Opencast Project (CCL), Ramagundam-II Opencast Mine (SCCL) and Padmapur Opencast Project (WCL), and in Limestone mine at Jhinkpani (ACC).
  • 15. In-pit crushing and conveying systems may be used to transport ore (i.e., pay mineral) to the processing plant and/or overburden (waste) to the waste dumps from the pit. In most of the cases, the pay mineral (which normally requires primary crushing in its preparation process) can be transported by belt conveyors at lower cost than by trucks. But for overburden conveying, the necessary preparation and dumping costs are a considerable extra that requires to be offset by savings in trucking and truck haulage costs. In general, only when large quantities of overburden are to be transported over fairly long distances at considerable lifting heights, application of crusher- conveyor-stacker system may be justified. General Applicability of In-pit Crushing and Conveying Systems:
  • 16. The various in-pit crushing systems may be classified broadly into three categories – Stationary/Permanent in-pit crushing system, Relocatable/Movable in-pit crushing system and Mobile in-pit crushing system. Types of In-pit Crushing System In this type of systems, large capacity crushers (separate crusher for ore and for waste) with proper foundation are installed in permanent locations at or near the pit floor level. The material, excavated and/or loaded by shovel, from all the working faces (of same type, i.e. ore or waste) are transported to the respective crusher by trucks, and thereafter the crushed material is transported to respective location (ore plant or waste dump) by stationary conveyors. Stationary/Permanent In-pit Crushing System:
  • 17. • In course of operations the pit floor depth remains essentially same, • Large quantities of ore to be transported over a long distance that may or may not be associated with considerable vertical lift. • The benches on one side of the pit (or at least a part of it) have reached their ultimate position and became stationary. The crushers are usually positioned so as not to create any inconvenience in the future extension of mine working and to ensure that uphill movement of loaded trucks carrying material from the working faces to the crusher is minimized. However, with the advancement of mine workings, the truck transport distance increases with time as the faces moves away from the crusher location. This system is most suitable in case of surface mines mining flat ore bodies so that –
  • 18. Following components form the chain of handling devices for stationary/permanent in-pit crushing and conveying system. Sl. No. Activity Equipment 1. Crushing • Stationary crusher unit 2. Transportation of ore to plant • Stationary conveyors 3. Transportation of waste to waste dumps • Stationary conveyors • Shiftable dump face conveyors • Tipper car • Spreader
  • 19. WASTE ROCK CRUSHER Stationary Waste Conveyor To Waste Dump OS OS OS OS OF-n OF-3 OF-2 OF-1 ORE CRUSHER T T T Stationary Ore Conveyor To Ore Plant T WS WS WS WS WF-n WF-3 WF-2 WF-1 T T T T WF – Waste Face WS– Waste Shovel OF – Ore Face OS– Ore Shovel T – Material transported by truck A schematic presentation of stationary in-pit crushing and conveying system is given below.
  • 20. In such systems, the crushers used are of medium capacity, and they that do not require extensive foundation work as required by stationary in-pit crushers. In a mine, depending on the mine specifics (the number of working faces and their relative location, material types to be handled total tonnage of ore and of waste to be handled), there can be one or more such crushers installed. Generally, each crusher serves a group of working faces excavating same type of material (ore or waste), and the crusher is placed at a location such that the overall truck haulage distance from the working faces it serves is optimized. The crusher, following the advance of working faces it serves, is relocated/moved to the new load center at appropriate time intervals. Relocatable/Movable In-pit Crushing System:
  • 21. • The production is medium to large • The working faces are distributed in number of benches • A stationary in-pit crushing system is not suitable. In this system, also, the material excavated and/or loaded by shovel is transported by trucks from the face to the crusher. The haulage distance is kept as short as practicable and, if possible, uphill haulage is either avoided or restricted to a minimum. The crusher discharges onto relocatable conveyor (that is relocated or lengthened in conjunction with the relocation of the crusher) which in turn transfers the material to the stationary conveyor. This system is suitable for a mine where –
  • 22. Following components form the chain of handling devices for relocatable/movable in-pit crushing and conveying system. Sl. No. Activity Equipment 1. Crushing • Relocatable crusher unit • Moving device 2. Transportation of ore to plant • Relocatable conveyors • Stationery conveyors 3. Transportation of waste to waste dumps • Relocatable conveyors • Stationery conveyors • Shiftable dump face conveyors • Tripper car • Spreader
  • 23. A relocatable in-pit crushing system has been installed at Ramagundam-II Opencast Mine of SCCL. Altogether 3 numbers of double roll type crushers for overburden and one double roll type crusher for coal have been installed. After crushing, the coal is conveyed to CHP via coal conveyors and overburden is transported to overburden dumps via overburden conveyor. In the dump area, the material is transferred to shiftable dump face conveyor for subsequent dumping via tripper car and spreader. There are 3 numbers of tripper car and 3 numbers of spreader for dumping the overburden suitably at the dumpsites.
  • 24. A schematic presentation of relocatable in-pit crushing and conveying system is given below. WS WS WS WF-1n WF-12 WF-11 T T T WC 1 WS WS WS WF-2n WF-22 WF-21 T T T WC 2 WS WS WS WF-mn WF-m2 WF-m1 T T T WC m RC RC RC To Waste Dump Stationary Waste Conveyor OS OS OS OF-1n OF-12 OF-11 T T T OC 1 OS OS OS OF-2n OF-22 OF-21 T T T OC 2 OS OS OS OF-mn OF-m2 OF-m1 T T T OC m RC RC RC To Ore Plant Stationary Ore Conveyor WF – Waste Face OF – Ore Face WS – Waste Shovel OS – Ore Shovel WC – Waste Crusher OC – Ore Crusher RC – Relocatable and/or extendable conveyor T – Material transported by truck
  • 25. In such a system, the crusher is fully mobile and is located at vary near the face. The crusher is fed directly by an excavator (Rope shovel or hydraulic shovel or front-end-loader). The crusher discharges either directly or via a beltwagon (or conveyor bridge in some cases) onto the shiftable face conveyor. Finally the material is conveyed to the respective destination (ore plant for one and waste dumps for waste) through a network of belt conveyors. The crushers are generally of small capacity sufficient to handle the production from the face where it is located. This system is applicable for mines where only a few fast moving working faces exist and the excavators stay permanently at the same face. Mobile In-pit Crushing Systems:
  • 26. Following components form the chain of handling devices for mobile in-pit crushing and conveying system. Sl. No. Activity Equipment 1. Crushing • Mobile crusher unit 2. Transportation of ore to plant • Transfer unit-belt wagon, mobile conveyor bridge • Shiftable conveyor with mobile hopper • Stationary conveyors 3. Transportation of waste to waste dumps • Transfer unit-belt wagon, mobile conveyor bridge • Shiftable conveyors with mobile hopper • Stationary conveyors • Shiftable dump face conveyors • Tripper Car • Overburden Spreader
  • 27. A schematic presentation of mobile in-pit crushing and conveying system is given below. WS - 1 WF-1 WC - 1 SFCBC WS - 2 WF-2 WC - 2 SFCBC WS - n WF-n WC - n SFCBC RC RC RC To Waste Dump Stationary Waste Conveyor OS - 1 OF-1 OC - 1 SFCBC OS - 2 OF-2 OC - 2 SFCBC OS - n OF-n OC - n SFCBC RC RC RC To Ore Plant Stationary Ore Conveyor WF – Waste Face OF – Ore Face WS – Waste Shovel OS – Ore Shovel WC – Mobile Crusher for Waste OC – Mobile Crusher for Ore SFC – Shiftable Face Conveyor BC – Bench Conveyor RC – Relocatable and/or extendable conveyor
  • 28. A mobile in-pit crushing system is in operation at Piparwar Opencast Project of CCL. The in-pit crushing is done only for coal excavated at the working face of lowermost coal seam (Lower Dakra), and the crushed coal is transported directly to the coal washery located near by the mine via a system of belt conveyors. The components for the system are 25m3 rope shovel, 2800 TPH mobile roll crusher unit, belt wagon, shiftable face belt conveyor and other conveyors (shiftable and stationary).
  • 29. Applicability of Various Crusher Types  Not Suitable Most Suitable  Suitable Material conditions Crusher Type Compressive Strength Crushing Ratio Abrasivity Moisture Soft Medium Hard 1:5 1:15 1:30 1:50 Low Medium High Dry Moist Wet Single-Toggle Jaw crusher              Double – Toggle Jaw crusher              Cone Crusher              Roll Crusher              Single shaft Hammer crusher              Single shaft Hammer crusher with grate              Double shaft Hammer crusher              Double shaft Hammer crusher with grate              Single shaft Impact crusher              Single shaft Impact crusher with grate              Double shaft Impact crusher              Double shaft Impact crusher with grate             