SlideShare a Scribd company logo
Rebuilding
of
Railway Infrastructures
during the Pandemic (New Normal )
By
Rajesh Prasad
Director (Operations)
RVNL
 About RVNL
 Impact of COVID-19 (New Normal) and initiatives taken by
RVNL
 Importance of ‘Make in India’ policy and implementation by
RVNL
 Infrastructure building in Railway sector
 Way forward by RVNL
SCOPE
PERFORMANCE OF RVNL
 Operations started in 2005 with the appointment of
BoDs.
 Granted Mini Ratna status on 19th September 2013,
(under process for “Navratna”).
 RVNL has been rated “Excellent” for the consecutive
Nine times by DPE.
 RVNL has been ranked 1st amongst the Railway
CPSEs for the four times out of last six years.
1445 1598
2117
2493
3142
4541
5920
7557
10060
14530
16000
(Projected)
0
2000
4000
6000
8000
10000
12000
14000
16000
18000
2010-11 2011-12 2012-13 2013-14 2014-15 2015-16 2016-17 2017-18 2018-19 2019-20 2020-21
CRORE
TURNOVER
CAGR of 36.78% in last 5 years
(Rs. in Cr.)
185.72
304.02
381.61
469.65
606.59
789.86
0
100
200
300
400
500
600
700
800
900
2014-15 2015-16 2016-17 2017-18 2018-19 2019-20
PAT (RS. CRORE)
PAT (Rs. Crore)
2678.86
3011.57 3083.37
3351.48
3738.76
4499.77
0
1000
2000
3000
4000
5000
2014-15 2015-16 2016-17 2017-18 2018-19 2019-20
NET WORTH (RS. CRORE)
New Worth (Rs. Crore)
MOU
PERFORMANCE :
Assessment Year Rating
RVNL’s rank
among Railway
CPSEs assessed
by DPE
Rank of RVNL
2007-08 Good 8th
2008-09 Very Good 10th
2009-10 Very Good 7th
2010-11 Excellent 5th
2011-12 Excellent 2nd
2012-13 Excellent 1st
2013-14 Excellent 2nd
2014-15 Excellent 1st
2015-16 Excellent 1st
2016-17 Excellent 1st
2017-18 Excellent 1st
2018-19 Excellent 2nd
2019-20 2019-20
(upto December 2019)
2020-21
(upto December 2020)
Turnover 14530.58 10309.90 9825.77
Profit before Tax
(PBT)
990.83 742.09 742.40
Net Profit
(Profit after Tax-PAT)
789.86 592.96 596.67
There is a decrease in turnover by 4.70% during last 9 months mainly due to
COVID-19, though PBT and PAT are marginally higher.
Rs. in Crore
Order Book of RVNL
 Total 183 nos. of projects assigned to RVNL for execution.
ACHIEVEMENT
New Railway Track 456
Gauge Conversion 1889
Doubling of Track 3483
Railway Electrification 4970
MTP (KM) 42
Workshops 8
Cable Stayed Bridge 1
456
1889
1
92 projects have been fully commissioned upto March 2020
3483 4970
42
8
2019-20
2020-21
(upto 03.09.2021)
Gauge Conversion (GC) +
Doubling (DL) + New Line
(NL)
665 Kms 565 Kms*
Railway Electrification (RE) 714 RKM 1561 RKM
Workshop 1 No 3 Nos.
*181 Kms Engine Rolling in 2020-21 waiting for commissioning.
Achievements and Highlights
New Normal
This NEW
NORMAL is
getting OLD
1st case of COVID-19 detected on 17 November 2019 Today's seminar …
What COVID and IT have done to us?
NEW NORMAL LIFE :
Special initiatives to combat COVID-19 in RVNL
 Contractors were advised to make arrangements for lodging,
boarding, fooding duly following social distancing norms,
moving patients to nearby doctors/ hospitals, paying charges of
doctors/ hospitals, providing sanitizers, soaps etc for labourer
stuck at worksites during the lockdown period and claim
reimbursements from RVNL for the same.
 Precautions taken in labour camps to ensure social distancing
norms, checking of temperature of workmen on daily basis so
that works can progress duly ensuring safety of
labourers during the difficult times of COVID-19.
Cont..
 A separate link was provided for instructions due to COVID’19
on RVNL’s website to facilitate easy dissemination of information
at all levels.
 In keeping with the Ministry of Finance guidelines to give
financial relief to contractors, release of proportionate BG’s
permitted.
 Recovery of mobilization advance from contractors has been
deferred for 6 months to improve the cash flow during
COVID’19.
Cont..
 To further address liquidity problems, stage payment conditions
have been reviewed and revised on supply items.
 As it was not possible to follow routine procedures of test checks
due to restriction of movement due to COVID’19, to address the
cash flow problem of contractors, measures were taken to allow
provisional passing of bills till such checks are possible.
 Submission of Bid Security in physical form relaxed to 30 days
from 5 days, due to restrictions in movement, for the tenders
opened between May’ 20 to Aug’ 20.
Cont..
 System of online pre-Bid Conference has been introduced and it
is working very well avoiding physical travel and gathering and at
the same time meeting the purpose of Prebid conferences
New Normal:
E-Conference saves Time & Money
Name of Work Value Tender Opening Award of Contract
Construction of Viaduct
from P276 to P314
including Mominpur and
Majerhat Station
196.30 Cr. Technical bid opened on
29.07.2020 and Price bid
opened on 14.08.2020
17.08.2020
(Total no. of days in
finalization of the
contract in only 19 days)
Construction of PEB shed
structures, buildings,
P-Way and utilities,
General Electrical works
and supply, installation
and commissioning of
Machinery and plant for
setting up of Metro Car
Depot at Joka
350.89 Cr. Technical bid opened on
31.07.2020 and Price bid
opened on 22.08.2020
25.08.2020
(Total no. of days in
finalization of the
contract in only 22 days)
Fast track finalization of Tenders
P287 & P288 of Joka-Esplanade Metro Corridor :
Taking the Opportunity given by Lock Down, we Completed very critical Two
Metro Piers adjacent to ‘JAI HIND’ Bridge.
Taking the benefit of Lock
Down, we substantially
Completed, substructure part
of very critical Pier Locations
on the Railway track at
Majerhat Station, Kolkata
Other measures taken to improve delivery
of projects:
 In cases where equipment suppliers are not ready to
despatch plant and equipment to contractor without full
payment, supply of equipment is facilitated by giving Comfort
letter to supplier. This has reduced the delay in delivery of
projects due to delay in supply of plants and equipment.
 In case where main contractor is not making timely payment
to sub-contractors, thereby delaying the progress of
execution, a provision has been made in standard bidding
documents for making direct payment to sub-contractors.
 A system of offloading has been introduced to get executed, at
the cost of the Contractor some small value yet important works
for commissioning, by other agency, which the contractor is
unable to progress at the desired pace. The provisions have
been kept in such a way that this enhances the speed
of execution of works without any additional cost on RVNL and
also without adversely affecting the performance of main
contractor.
 New rate to the agency where work site not handed over even
after the original DoC.
 Amicable settlement policy : 12 Cases settled.
 In view of difficulty being faced by contractors in obtaining
BG, the performance security has been made admissible in
the form of FDR (free from any encumbrance) in addition to
other forms.
 Several financial powers have been delegated to field officers
Subject : Bid Security/ Earnest Money Deposit
Option of submitting Bid Security through a declaration
form instead of only Bid Security has also been introduced
in RVNL.
Subject : Performance Security
Performance Security from existing 10% to 3% of
the value of the contract has been introduced in
RVNL.
In the existing contract performance security in
addition to proportionate performance security
released.
Subject : Amendment in GFRs, 2017- GTE.
No Global Tender Enquiry (GTE), however shall be
invited for tender upto Rs. 200 crore.
Subject : Global Tender Enquiry (GTE).
Restriction on Global Tenders as specified in the
revised Rule 161(iv) will be applicable on all
procurements including Goods, Non-consulting
services, Constancy Services and Works
including turnkey projects.
Subject : Restriction on agencies participating in
tenders from countries sharing land boundary
with India.
MAKE IN INDIA
https://www.makeinindia.com
Launched :- 25th September 2014
Make in India focuses on the following 25 sectors of the economy:
1. Automobiles
2. Automobile Components
3. Aviation
4. Biotechnology
5. Chemicals
6. Construction
7. Defence Manufacturing
8. Electronic Systems
9. Electrical Machinery
10. Food Processing
11. Information Technology and Business Process
Management
12. Leather
13. Media and entertainment
14. Mining
15. Oil and gas
16. Pharmaceuticals
17. Ports & Shipping
18. Railways
19. Renewable Energy
20. Roads and Highways
21. Space
22. Thermal Power
23. Textiles and Garments
24. Tourism and Hospitality
25. Wellness
EASE OF DOING BUSINESS
Ranking system established by the World Bank Group.
India has emerged as one of the most attractive destinations not
only for investments but also for doing business.
India jumps 79 positions from 142nd (2014) to 63rd (2019) in Ease of
Doing Business Ranking 2020'.
Construction Permits: India’s ranking :- 184 in 2014 and 27 in 2019.
Getting Electricity: India’s ranking :- 137 in 2014 and 22 in 2019.
Apart from these significant improvements, among the 190
economies, India ranks 13th in Protecting Minority Investors and
25th in Getting Credit.
RVNL to promote ‘Make in India’ policy by using
indigenous rails in Kolkata Metro Rail Project
In an effort towards ‘आत्मनिर्भर र्ारत’ RVNL has used, for the first
time, indigenous HH Rails in a Metro Rail Project in our country. A step
taken by RVNL for Kolkata Metro. All Metro systems in different cities in
India have used imported Head Hardened (HH) Rails. HH rails offers
greater efficiency through its ability to handle higher axle loads of over
25 Tonnes with low deformation and wear. For the first time indigenous
HH rails shall be used for a Metro in our country.
TOI-12.08.2020
LAYING OF BLT ON EMBANKMENT BY USING PCRSB
 Freyssinet’s Parallel Strand System (PSS) stay cables - which has a design life of
100 years and is the most advanced and durable stay cable system in the
world today. There are 3 planes of stay cables with 18 cables each.
 Isotension® Method
4-lane Cables Stayed Bridge, Barddhaman
4-lane Cables Stayed Bridge, Barddhaman
Make in India Policy :- Manufacture of Cables by M/s. Usha Martin,
Ranchi on behalf of Freyssinet – subcontractor (a french company)
using their technology in India.
Reconstruction of Pamban Bridge
Construction of new Pamban Bridge involves Pile foundation, Pile cap and Pier
caps with Steel girders as the Superstructure. The existing navigational span is
known as scherzer span, which is having Roller Lift arrangement, whereas the
proposed navigational span is a vertical lift span. The navigational span consists
of Steel through Girder with warren type trusses. The weight of the proposed
navigational span is 1200 MT.
https://youtu.be/_ZWAUAjjvPA
 RVNL is fully committed to follow the world best
construction practices which include mechanization for
better quality of output.
 Executed transmission line work for supply to TSS (in
case of refusal/failure of state govts to execute).
 Use of self propelled UTVs in RE projects saving loco,
crew and fuel.
 First over Indian Railways to do mechanized wiring by
AWT (Automatic wiring Train).
 AWT machine is capable of wiring both the wire
under cool tension thus increasing wiring speed and
also reducing the post wiring activities.
MECHANIZED WIRING BY
AUTOMATIC WIRING MACHINE
MORE MECHANIZED WORKING
DISINFECTION OF SITE OFFICES, LABORATORIES,
MACHINES, EQUIPMENTS AND VEHICLES
PATIENCE, DISCIPLINE AND NEW NORMAL ARE THE KEY
Awareness
Thermal screening of all at entry and exit of work site Disinfection of Site, Store
Hands Free Sanitizer dispenser
Hand Soap, Mask and
Sanitizer facilities
provided
Food/Ration Distribution to Site Labour
I’LL ADMIT, THIS IS NOT HOW I SAW 2020
GOING.
Pile Cap Steel Reinforcement binding
Lattice Girder fabrication yard
CRS INSPECTIONS
BE TECH SAVVY TO FIGHT COVID
• VIDEO CONFERENCING instead of physical presence in meetings.
• VIDEO CALL instead of personal visit.
• E-OFFICE in place of paper files.
Encouraged E-Books
CHALLENGES DURING
NEW NORMAL
COVID-19 – A Pandemic has resulted into
→ The entire country is shaken in locked down
condition
→ World Share Market earlier tanked
→ Wheel of Indian Railway carrying passengers has
stopped after 167 years
→ Shutdown of creation of Railway Infrastructures
→ Share price of major companies has touched to
the bottom and trying to recover
QUESTION COMES TO OUR MIND ..
What next
to
→ Our country
→ Indian Railway
→ RVNL
Karoly Takacs (Hungarian Armyman)
• ‘Impossible is nothing’
• 1938 – In Army Camp, during practice hand grenade exploded in his right hand. He
lost his right hand then he started practicing with his left hand.
• 1939 - He won the Hungarian national pistol shooting championship.
• Won the gold medals in 1948 & 1952 Olympics
Arunima Sinha (Indian mountain climber and sportswoman)
 2011- She was pushed from a running train by some robbers and She lying there seven
hours. Her left leg had to be amputated below the knee, she got rods in right leg and
multiple fractures in spinal cord
 2013 - She reached the summit of Mount Everest
 World's first female amputee to scale Mount Everest,
Mount Kilimanjaro (Tanzania), Mount Elbrus (Russia),
Mount Kosciusko (Australia), Mount Aconcagua (South
America), Carstensz Pyramid (Indonesia) and Mount
Vinson
 2015 - Padma Shri Award
CHALLENGES BEFORE INDIAN RAILWAYS
1950-51 2020 %age increase
Loading 73 MT 1200 MT 1550%
Million Passenger Kms 66517 12,00,000 1700%
Route Kms 53500 67,000 25%
Double/Multiple route length 5100 Kms 25000 Kms 390%
• 161 out of 247 sections in HDN routes > 100% line capacity
16% of route km carries 55% of passengers and 58% of freight
Project :- It simply means converting vision into reality. A set of
activities are undertaken to meet the specified objectives for the
changes. The various features of typical projects are as under:
• Temporary - have a definite beginning and an end.
• Unique – no two projects are identical.
• Predefined goals & objectives – financial/ social/ economic.
• Budgets & schedules – prefixed budget and time frame.
• Uses Resources & Manpower – both are limited.
• Quality/ performance - determined at beginning.
• Face Risks – known and unknown risks
• Have a project life cycle – many phases from start to end.
Fast Track Project Implementation (FTPI)
– Why affected
Budget (2014-15) :
• “Para – 18: There has been focus on sanctioning projects rather than completing them. In the
last 30 years, as many as 676 projects were sanctioned worth Rs 1,57,883 crore. Of these, only
317 projects could be completed and 359 projects remain to be completed which will now
require as much as Rs 1,82,000 crore.”
• “Para – 19: In the last 10 years, 99 new line projects worth Rs 60,000 crore were sanctioned out
of which only one project is complete till date. In fact, there are 4 projects that are as old as 30
years, but are still not complete for one reason or another.
RVNL has got
major role to play in
Railway Infrastructure
Way forward by RVNL
Rail Vikas Nigam Ltd. (RVNL)
Subsidiary SPV’s
Kutch Railway Company Ltd. (KRCL)
(50.00%)
HSRC Infra Services Limited (100%)
Bidding arm and a new vertical
Krishnapatnam Railway Company Ltd. (KPRCL)
(49.76%)
Bharuch Dahej Railway Corporation Ltd. (BDRCL)
(35.46%)
Haridaspur Paradeep Railway Company Ltd. (HPRCL)
(30.00%)
Angul Sukinda Railway Ltd. (ASRL)
(32.37%)
 RVNL has created the following SPVs:-
 Kutch Railway Company Limited :- Commissioned
 Krishnapatnam Railway Company Limited :- Commissioned
 Bharuch-Dahej Railway Company Limited :- Commissioned
 Haridaspur- Paradip Railway Company Limited :- Commissioned on 30th July 2020
 Angul Sukinda Railway Limited :- Commissioning target June 2022
 RVNL is an Equity Partner of 10% in a SPV with 12 Major Ports under Ministry of
Shipping for undertaking railway projects and activities in major ports (Indian Port Rail
Company Ltd.-IPRCL).
 Rs. 73,776 crore revenue generated for Indian Railways without any invested by
Ministry of Railway.
 Equity contribution of only Rs. 822 crore in the 4 operational SPVs at a total project cost
of Rs. 5560 crore.
RESOURCE MOBILISATION THROUGH SPVs
RVNL LEADING THE GROWTH FOR AATMANIRBHAR BHARAT
Achievements of Kutch Railway Company Ltd.
 Operations started from July - 2006
• Freight Loading (MT) - 407.45
• Total Revenue Earned (Rs. Cr.) - 54619.34
• Share of IR’s Revenue (Rs. Cr.) - 47367.82
• Share of SPV’s Revenue (Rs. Cr.) - 7251.52
 KRC (Kutch Railway Co. Ltd.) – 1853 rakes in Jan.
2021, all time record.
Achievements of Bharuch-Dahej Railway
Company Ltd.
Operations started from March 2012
• Freight Loading (MT) - 42.72
• Total Revenue Earned (Rs. Cr.) - 5716.74
• Share of IR’s Revenue (Rs. Cr.) - 5157.03
• Share of SPV’s Revenue (Rs. Cr.) – 563.56
Achievements of Krishnapatnam Railway Company
Limited
Operations started from Nov. 2008
• Total Revenue Earned (Rs. Cr.) - 14009.51
• Share of IR’s Revenue (Rs. Cr.) - 13201.76
• Share of SPV’s Revenue (Rs. Cr.) - 807.78
 HPRCL (Haridaspur Paradip Railway Co. Ltd.) – Single line
commissioned in July 2020. 2974 nos. of rakes
transported from Aug. 2020 to Feb. 2021 (only 7 months).
Achievements of Haridaspur- Paradip Railway Company
Limited
Angul Sukinda Railway Limited
• SPV formed in Feb’2009 for new line from Angul to Sukinda
• Cost of project - Rs.2440.53 Cr
• Project length - 104 Km
• Equity - Rs. 778.60 Cr / Debt - Rs. 1600 Cr
• Equity : Debt :: 33: 67
• Land acquisition is being done by East Coast Railway through the Government of Orissa
• Commissioning target : June 2022
RVNL-32.37% CONCOR-26.71% Jindal Steel and Power Ltd.-7.71%
Govt. of Odisha-21.89% Odisha Mining Corporation-
10.79%
Odisha Industrial Infrastructure
Development Corporation-0.54%
New Rail Connectivity from Pachchwara coal blocks to Nagarnabi in Jharkhand
• A DPR is under preparation by M/s RITES.
• Alignment has been modified as earlier one was
passing through the Urma Paharitola coal block.
• Three alternative routes has been proposed by
RITES, which is to be finalized by Power
Companies.
• A Bankability study by SBICAPS is in progress.
• Draft bankability study is ready, final DPR is
also submitted by M/s RITES.
New Rail connectivity from Sardega – Pelma
• Coal India Limited is planning to construct a rail link
from Sardega to Pelma for an integrated coal
evacuation arrangement having a total length of
about 35 Kms.
• Ministry of Railways has nominated Rail Vikas Nigam
Ltd (RVNL) to be the SPV partner in the Railway
Project as Railway PSU with a subsidiary of Coal
India Ltd.
• It has been decided by the Coal India Ltd. that
Mahanadi Coal Ltd (MCL) will be the partner in the
proposed SPV.
• The project will be implemented under participative
policy of Ministry of Railways and RVNL will be the
implementing agency.
Workshop Projects on Turnkey basis
 Civil work of construction of Diesel Loco Component Workshop at Dankuni
completed in a record time of 1 year.
 DMU Factory at Haldia completed in 16 months.
 Electric Loco Factory at Dankuni completed in 25 months.
 DLW Capacity augmentation completed in 22 months. Its work
commencement was done by Hon'ble PM who gave a target of 24 months.
RVNL completed this work in 22 months and was inaugurated by Hon'ble PM.
 Workshop for manufacture of Fiat Bogies for LHB Design Coaches, Yadgir
completed in 17 months.
 Aunrihar - DEMU Shed completed in 21 months.
 Vadlapudi - Wagon POH workshop of 200 Nos capacity near Duvvada station
completed in 25 months.
 Diesel Loco Shed, Barauni completed in 27 months.
 Marathwada Rail Coach Factory, Latur completed in 26 months
 MEMU Shed, Kanpur completed in 22 months.
Commencement of work at site by Hon’ble Prime Minister on 25.12.2014, Project (Part-I)
dedicated to Nation by Hon’ble Prime Minister on 24.10.2016
Augmentation of Production Capacity of DLW
TUNNELING
Tunnel Constructed:-
• Tunnel of 1.0 km in 4 months & 6.7 km long in 25 months completed in
Obulavaripalle - Krishnapattnam New Line project in SC Railway.
• 680 m Tunnel completed in Goelkera-Manoharpur 3rd Line project.
Tunnel Under-construction:-
• 110 km of tunnels (17 nos.) in Rishikesh-Karnaprayag New Line (125 km).
Longest tunnel = 15.7 km.
• 25.9 km of tunnels (20 nos.) in Bhanupali-Bilaspur-Beri New Line (63 km).
Longest tunnel-3.79 km.
• 6 tunnels (longest-2.7 km, total-9.8 km) in Yevatmal-Nanded New Line
(207 km).
• 16 tunnels (longest-410 m, Total = 2.56 km) in Castlerock-Kulem Ghat
Section in Hospet-Vasco Doubling Project.
• 5 tunnels (Total-2.15 km/Longest-1.08 km) in Budni-Barkhera 3rd line
project.
6.7 KM TUNNEL - KRISHNAPATNAM PORT SPV COMPLETED IN 25 MONTHS
4.62 km long bridge in Kerala completed in 27 months
Cable Stayed Bridge at Bardhhaman - erection completed in less than 200 days
65 Kms of Metro construction in City of Kolkata has been mandated for execution.
Noapara - Baranagar – Dakshineswar Metro inaugurated by Hon’ble Prime Minister on 22.02.2021
First Metro commissioned by Railway PSU
RVNL Coffee Table Book
• https://www.rvnl.org/en/RVNL%20Documents/RVNL%20Book%20-
%2017yrs%20of%20Journey.pdf
• https://www.linkedin.com/posts/rvnl_rvnl-corporate-book-17-years-
of-glorious-activity-6710166556195729408-XnVn
The elegantly designed book captures
the storyline and highlights of 17 years
of RVNL's journey. We sincerely hope
you like it and the book brings us
closer by helping you know more
about RVNL.
Over the past years, RVNL has established its mark as a professionally mature,
technologically upbeat and managerially sound organisation. RVNL's contribution
to growth of railroad infrastructure in India that directly translates to economic
growth and human development across diverse regions of the country will be
remembered in the times to come.
The corporate video especially focuses on the projects delivered and accelerated
by the company in the last 2 years. It is commendable how the complete team of
RVNL, from the chairman to the project teams in field, worked in synergy to ride
through even tough times of pandemic and lockdown.
This video is a dedication to and appreciation of the talented team of RVNL across
all site offices, PIUs, SPVs, JVs, Subsidiary companies and Corporate Office.
YouTube link : https://www.youtube.com/watch?v=-Gc6AH7XMH0
RVNL Corporate Video
रेल विकास निगम लललमटेड
हम हैं गनत विकास की
राहें दुर्गम पर हम सक्षम
हम हैं गनत विकास की
गुणित्ता है साख हमारी
सददयों की है जिम्मेदारी
हम बढ़ते हैं हम र्ढ़ते हैं
राहें कल की आस की
राहें दुर्गम पर हम सक्षम
हम हैं र्तत विकास की
पारदलशभता सब बातों में
कमगशीलता हर हाथों में
दूरदशी सपनों से ललखते
र्ाथा रेल विकास की
राहें दुर्गम पर हम सक्षम
हम हैं र्तत विकास की
पटरी सा फौलादी कल था
पदहये सा र्ततमान आि है
रेल बढेगी देश बढेगा
यह है लौ विश्िास की
राहें दुर्गम पर हम सक्षम
हम हैं र्तत विकास की
पुल ढाले हैं नददयााँ लाांघी
ट्रैक बबछाए धरती नापी
हम र्ारत का स्िर्णभम कल हैं
बात िह ीं इनतहास की
राहें दुर्गम पर हम सक्षम
हम हैं गनत विकास की.
YouTube link : https://youtu.be/Oav1KRuovaI
Side effects of COVID and Technology …
https://www.youtube.com/watch?v=Oav1KRuovaI
“Be the change that you
wish to see in the world.”
Mahatma Gandhi
“Everyone thinks of changing the
world, but no one thinks of
changing himself.”
Leo Tolstoy
The conclusion remain …
 We need to be ever motivated.
 Indian Railway will remain lifeline of the
nation and growth engine of the country.
 RVNL will continue to play very major
role in building Railway Infrastructure
thus in building nation.
Obey
Social
Distancing…
THANK YOU
BE ALERT, BE SAFE
to beat
Corona.

More Related Content

What's hot

High speed rail 01
High speed rail 01High speed rail 01
High speed rail 01
TedGiras
 
UIC High Speed Rail Brochure
UIC High Speed Rail BrochureUIC High Speed Rail Brochure
UIC High Speed Rail Brochure
UICcom
 
RISK ASSESSMENT OF METRO SITE
RISK ASSESSMENT OF METRO SITERISK ASSESSMENT OF METRO SITE
RISK ASSESSMENT OF METRO SITE
Pratham Sharma
 
Jeddah metro full presentation - Briefing Day March, 30th
Jeddah metro full presentation - Briefing Day March, 30th Jeddah metro full presentation - Briefing Day March, 30th
Jeddah metro full presentation - Briefing Day March, 30th
Ibrahim Al-Hudhaif
 
IMPACT OF DEDICATED FREIGHT CORRIDOR ON LOGISTIC CONNECTIVITY IN INDIA
IMPACT  OF DEDICATED FREIGHT CORRIDOR ON LOGISTIC CONNECTIVITY IN INDIA IMPACT  OF DEDICATED FREIGHT CORRIDOR ON LOGISTIC CONNECTIVITY IN INDIA
IMPACT OF DEDICATED FREIGHT CORRIDOR ON LOGISTIC CONNECTIVITY IN INDIA
Chiranjib Mahapatra
 
DFCC-WDFC-Sojitz_L&T-Rites_Nippon_Koi
DFCC-WDFC-Sojitz_L&T-Rites_Nippon_KoiDFCC-WDFC-Sojitz_L&T-Rites_Nippon_Koi
DFCC-WDFC-Sojitz_L&T-Rites_Nippon_Koi
Shobhit Acharya
 
Project management in NHAI
Project management in NHAIProject management in NHAI
Project management in NHAI
Anshuman Jaiswal
 
Mumbai traffic scenario & mumbai metro
Mumbai traffic scenario & mumbai metroMumbai traffic scenario & mumbai metro
Mumbai traffic scenario & mumbai metro
satish choudhari
 
Dfccil(dedicated freight corridor)
Dfccil(dedicated freight corridor)Dfccil(dedicated freight corridor)
Dfccil(dedicated freight corridor)
Gurparvesh kaur
 
K Rail Silver line DPR - James Joseph Adhikarathil 9447464502
K Rail Silver line DPR  - James Joseph Adhikarathil 9447464502K Rail Silver line DPR  - James Joseph Adhikarathil 9447464502
K Rail Silver line DPR - James Joseph Adhikarathil 9447464502
Jamesadhikaram land matter consultancy 9447464502
 
Airport express line
Airport express lineAirport express line
Airport express line
Bhaskar Bhattacharya
 
Infrastructure Management - DMRC Study
Infrastructure Management - DMRC StudyInfrastructure Management - DMRC Study
Infrastructure Management - DMRC Study
Mohit Gaur
 
Road Construction nhdp 2014
Road Construction nhdp 2014Road Construction nhdp 2014
Road Construction nhdp 2014
Arnaud Renard
 
Hyd metro rail
Hyd metro railHyd metro rail
Hyd metro rail
VaibhavSharma744
 
High Speed Rail- Need, Challenges, Key Issues and Options: Indian Perspective
High Speed Rail- Need, Challenges, Key Issues and Options: Indian PerspectiveHigh Speed Rail- Need, Challenges, Key Issues and Options: Indian Perspective
High Speed Rail- Need, Challenges, Key Issues and Options: Indian Perspective
Rajesh Prasad
 
Ahmedabad metro rail project (amrc) deepen
Ahmedabad metro rail project (amrc)   deepenAhmedabad metro rail project (amrc)   deepen
Ahmedabad metro rail project (amrc) deepen
Deepen Upadhyay
 
Summer training report_on_indian_railway
Summer training report_on_indian_railwaySummer training report_on_indian_railway
Summer training report_on_indian_railway
anirudh patel
 
Go Underground Mumbai Metro
Go Underground Mumbai MetroGo Underground Mumbai Metro
Go Underground Mumbai Metro
Hansel D'Souza
 
Delhi metro and Economics
Delhi metro and EconomicsDelhi metro and Economics
Delhi metro and Economics
Kunal Bhadane
 
Delhi metro case study
Delhi metro case studyDelhi metro case study
Delhi metro case study
Shubham Chaudhari
 

What's hot (20)

High speed rail 01
High speed rail 01High speed rail 01
High speed rail 01
 
UIC High Speed Rail Brochure
UIC High Speed Rail BrochureUIC High Speed Rail Brochure
UIC High Speed Rail Brochure
 
RISK ASSESSMENT OF METRO SITE
RISK ASSESSMENT OF METRO SITERISK ASSESSMENT OF METRO SITE
RISK ASSESSMENT OF METRO SITE
 
Jeddah metro full presentation - Briefing Day March, 30th
Jeddah metro full presentation - Briefing Day March, 30th Jeddah metro full presentation - Briefing Day March, 30th
Jeddah metro full presentation - Briefing Day March, 30th
 
IMPACT OF DEDICATED FREIGHT CORRIDOR ON LOGISTIC CONNECTIVITY IN INDIA
IMPACT  OF DEDICATED FREIGHT CORRIDOR ON LOGISTIC CONNECTIVITY IN INDIA IMPACT  OF DEDICATED FREIGHT CORRIDOR ON LOGISTIC CONNECTIVITY IN INDIA
IMPACT OF DEDICATED FREIGHT CORRIDOR ON LOGISTIC CONNECTIVITY IN INDIA
 
DFCC-WDFC-Sojitz_L&T-Rites_Nippon_Koi
DFCC-WDFC-Sojitz_L&T-Rites_Nippon_KoiDFCC-WDFC-Sojitz_L&T-Rites_Nippon_Koi
DFCC-WDFC-Sojitz_L&T-Rites_Nippon_Koi
 
Project management in NHAI
Project management in NHAIProject management in NHAI
Project management in NHAI
 
Mumbai traffic scenario & mumbai metro
Mumbai traffic scenario & mumbai metroMumbai traffic scenario & mumbai metro
Mumbai traffic scenario & mumbai metro
 
Dfccil(dedicated freight corridor)
Dfccil(dedicated freight corridor)Dfccil(dedicated freight corridor)
Dfccil(dedicated freight corridor)
 
K Rail Silver line DPR - James Joseph Adhikarathil 9447464502
K Rail Silver line DPR  - James Joseph Adhikarathil 9447464502K Rail Silver line DPR  - James Joseph Adhikarathil 9447464502
K Rail Silver line DPR - James Joseph Adhikarathil 9447464502
 
Airport express line
Airport express lineAirport express line
Airport express line
 
Infrastructure Management - DMRC Study
Infrastructure Management - DMRC StudyInfrastructure Management - DMRC Study
Infrastructure Management - DMRC Study
 
Road Construction nhdp 2014
Road Construction nhdp 2014Road Construction nhdp 2014
Road Construction nhdp 2014
 
Hyd metro rail
Hyd metro railHyd metro rail
Hyd metro rail
 
High Speed Rail- Need, Challenges, Key Issues and Options: Indian Perspective
High Speed Rail- Need, Challenges, Key Issues and Options: Indian PerspectiveHigh Speed Rail- Need, Challenges, Key Issues and Options: Indian Perspective
High Speed Rail- Need, Challenges, Key Issues and Options: Indian Perspective
 
Ahmedabad metro rail project (amrc) deepen
Ahmedabad metro rail project (amrc)   deepenAhmedabad metro rail project (amrc)   deepen
Ahmedabad metro rail project (amrc) deepen
 
Summer training report_on_indian_railway
Summer training report_on_indian_railwaySummer training report_on_indian_railway
Summer training report_on_indian_railway
 
Go Underground Mumbai Metro
Go Underground Mumbai MetroGo Underground Mumbai Metro
Go Underground Mumbai Metro
 
Delhi metro and Economics
Delhi metro and EconomicsDelhi metro and Economics
Delhi metro and Economics
 
Delhi metro case study
Delhi metro case studyDelhi metro case study
Delhi metro case study
 

Similar to Rebuilding of Railway Infrastructures during the present crisis by Rajesh Prasad

TIMMINT MI - KSA Construction & Real Estate Weekly Report (Issue 2014-18)
TIMMINT MI - KSA Construction & Real Estate Weekly Report (Issue 2014-18)TIMMINT MI - KSA Construction & Real Estate Weekly Report (Issue 2014-18)
TIMMINT MI - KSA Construction & Real Estate Weekly Report (Issue 2014-18)
The TIMMINT Group
 
Indian Rail Budget 2016-2017
Indian Rail Budget 2016-2017Indian Rail Budget 2016-2017
Indian Rail Budget 2016-2017
Pankaj Walia
 
Indian Rail Budget 2016-2017
Indian Rail Budget 2016-2017Indian Rail Budget 2016-2017
Indian Rail Budget 2016-2017
Pankaj Walia
 
Conf city gas_march2013
Conf city gas_march2013Conf city gas_march2013
Conf city gas_march2013
Sajjan Mishra
 
Construction Industry Review 7- 2014
Construction Industry Review 7- 2014Construction Industry Review 7- 2014
Construction Industry Review 7- 2014
Remona Divekar
 
India Union Budget 2014-15 | A Holistic Plan of Action
India Union Budget 2014-15 | A Holistic Plan of ActionIndia Union Budget 2014-15 | A Holistic Plan of Action
India Union Budget 2014-15 | A Holistic Plan of Action
Vinit Bolinjkar LION bolinjkar.vinit@gmail.com
 
4 city-gas-distribution
4 city-gas-distribution4 city-gas-distribution
4 city-gas-distribution
Hiren Patel
 
Union Budget 2020-21: Proposals For Key Sectors And Industries
Union Budget 2020-21: Proposals For Key Sectors And IndustriesUnion Budget 2020-21: Proposals For Key Sectors And Industries
Union Budget 2020-21: Proposals For Key Sectors And Industries
Coinmen Consultants LLP
 
Powerpoint Presentation of Sunil Kumar Behera
Powerpoint Presentation of Sunil Kumar BeheraPowerpoint Presentation of Sunil Kumar Behera
Powerpoint Presentation of Sunil Kumar Behera
Sunil Kumar Behera
 
STUDY ON BOT PROJECT WITH A CASE STUDY OF DELHI GURGAON EXPRESSWAY
STUDY ON BOT PROJECT WITH A CASE STUDY OF DELHI GURGAON EXPRESSWAYSTUDY ON BOT PROJECT WITH A CASE STUDY OF DELHI GURGAON EXPRESSWAY
STUDY ON BOT PROJECT WITH A CASE STUDY OF DELHI GURGAON EXPRESSWAY
Shabaz Khan
 
Aerial Work Platform market in india
Aerial Work Platform market in indiaAerial Work Platform market in india
Aerial Work Platform market in india
Prashant Verma
 
mumbai metro PPP model.pptx
mumbai metro PPP model.pptxmumbai metro PPP model.pptx
mumbai metro PPP model.pptx
TwinkleVincent2
 
PSE Insights - May 2016
PSE Insights - May 2016PSE Insights - May 2016
PSE Insights - May 2016
Confederation of Indian Industry
 
Starting a buisness electric vehicle charging station
Starting a buisness electric vehicle charging stationStarting a buisness electric vehicle charging station
Starting a buisness electric vehicle charging station
udayjoshi35
 
Transmission Sector & Project Management of Transmission Lines
Transmission Sector & Project Management of Transmission LinesTransmission Sector & Project Management of Transmission Lines
Transmission Sector & Project Management of Transmission Lines
MANTHAN CHAUHAN
 
RIICO Presentation on Petroleum, Chemicals and Petrochemicals Investment Regi...
RIICO Presentation on Petroleum, Chemicals and Petrochemicals Investment Regi...RIICO Presentation on Petroleum, Chemicals and Petrochemicals Investment Regi...
RIICO Presentation on Petroleum, Chemicals and Petrochemicals Investment Regi...
Rajasthan State Industrial Development & Investment Corporation Ltd. (RIICO)
 
LOAN SCHEME FOR FINANCING GRID CONNECTED ROOFTOP SOLAR PV POWER PROJECTS
LOAN SCHEME FOR FINANCING GRID CONNECTED ROOFTOP SOLAR PV POWER PROJECTS LOAN SCHEME FOR FINANCING GRID CONNECTED ROOFTOP SOLAR PV POWER PROJECTS
LOAN SCHEME FOR FINANCING GRID CONNECTED ROOFTOP SOLAR PV POWER PROJECTS
Harish Sharma
 
Abstract 1-post-covid-challenges-in-making-mihan-sez-a-success-story[4743]
Abstract 1-post-covid-challenges-in-making-mihan-sez-a-success-story[4743]Abstract 1-post-covid-challenges-in-making-mihan-sez-a-success-story[4743]
Abstract 1-post-covid-challenges-in-making-mihan-sez-a-success-story[4743]
Dr. Atul Thakare
 
Emerging Professional and Ethical Challenges for Railway Engineers
Emerging Professional and Ethical Challenges for Railway EngineersEmerging Professional and Ethical Challenges for Railway Engineers
Emerging Professional and Ethical Challenges for Railway Engineers
Anil Kumar Gupta
 
EV Charging - Business Opportunity for NTPC
EV Charging - Business Opportunity for NTPCEV Charging - Business Opportunity for NTPC
EV Charging - Business Opportunity for NTPC
Shiva Prashanth Kasina
 

Similar to Rebuilding of Railway Infrastructures during the present crisis by Rajesh Prasad (20)

TIMMINT MI - KSA Construction & Real Estate Weekly Report (Issue 2014-18)
TIMMINT MI - KSA Construction & Real Estate Weekly Report (Issue 2014-18)TIMMINT MI - KSA Construction & Real Estate Weekly Report (Issue 2014-18)
TIMMINT MI - KSA Construction & Real Estate Weekly Report (Issue 2014-18)
 
Indian Rail Budget 2016-2017
Indian Rail Budget 2016-2017Indian Rail Budget 2016-2017
Indian Rail Budget 2016-2017
 
Indian Rail Budget 2016-2017
Indian Rail Budget 2016-2017Indian Rail Budget 2016-2017
Indian Rail Budget 2016-2017
 
Conf city gas_march2013
Conf city gas_march2013Conf city gas_march2013
Conf city gas_march2013
 
Construction Industry Review 7- 2014
Construction Industry Review 7- 2014Construction Industry Review 7- 2014
Construction Industry Review 7- 2014
 
India Union Budget 2014-15 | A Holistic Plan of Action
India Union Budget 2014-15 | A Holistic Plan of ActionIndia Union Budget 2014-15 | A Holistic Plan of Action
India Union Budget 2014-15 | A Holistic Plan of Action
 
4 city-gas-distribution
4 city-gas-distribution4 city-gas-distribution
4 city-gas-distribution
 
Union Budget 2020-21: Proposals For Key Sectors And Industries
Union Budget 2020-21: Proposals For Key Sectors And IndustriesUnion Budget 2020-21: Proposals For Key Sectors And Industries
Union Budget 2020-21: Proposals For Key Sectors And Industries
 
Powerpoint Presentation of Sunil Kumar Behera
Powerpoint Presentation of Sunil Kumar BeheraPowerpoint Presentation of Sunil Kumar Behera
Powerpoint Presentation of Sunil Kumar Behera
 
STUDY ON BOT PROJECT WITH A CASE STUDY OF DELHI GURGAON EXPRESSWAY
STUDY ON BOT PROJECT WITH A CASE STUDY OF DELHI GURGAON EXPRESSWAYSTUDY ON BOT PROJECT WITH A CASE STUDY OF DELHI GURGAON EXPRESSWAY
STUDY ON BOT PROJECT WITH A CASE STUDY OF DELHI GURGAON EXPRESSWAY
 
Aerial Work Platform market in india
Aerial Work Platform market in indiaAerial Work Platform market in india
Aerial Work Platform market in india
 
mumbai metro PPP model.pptx
mumbai metro PPP model.pptxmumbai metro PPP model.pptx
mumbai metro PPP model.pptx
 
PSE Insights - May 2016
PSE Insights - May 2016PSE Insights - May 2016
PSE Insights - May 2016
 
Starting a buisness electric vehicle charging station
Starting a buisness electric vehicle charging stationStarting a buisness electric vehicle charging station
Starting a buisness electric vehicle charging station
 
Transmission Sector & Project Management of Transmission Lines
Transmission Sector & Project Management of Transmission LinesTransmission Sector & Project Management of Transmission Lines
Transmission Sector & Project Management of Transmission Lines
 
RIICO Presentation on Petroleum, Chemicals and Petrochemicals Investment Regi...
RIICO Presentation on Petroleum, Chemicals and Petrochemicals Investment Regi...RIICO Presentation on Petroleum, Chemicals and Petrochemicals Investment Regi...
RIICO Presentation on Petroleum, Chemicals and Petrochemicals Investment Regi...
 
LOAN SCHEME FOR FINANCING GRID CONNECTED ROOFTOP SOLAR PV POWER PROJECTS
LOAN SCHEME FOR FINANCING GRID CONNECTED ROOFTOP SOLAR PV POWER PROJECTS LOAN SCHEME FOR FINANCING GRID CONNECTED ROOFTOP SOLAR PV POWER PROJECTS
LOAN SCHEME FOR FINANCING GRID CONNECTED ROOFTOP SOLAR PV POWER PROJECTS
 
Abstract 1-post-covid-challenges-in-making-mihan-sez-a-success-story[4743]
Abstract 1-post-covid-challenges-in-making-mihan-sez-a-success-story[4743]Abstract 1-post-covid-challenges-in-making-mihan-sez-a-success-story[4743]
Abstract 1-post-covid-challenges-in-making-mihan-sez-a-success-story[4743]
 
Emerging Professional and Ethical Challenges for Railway Engineers
Emerging Professional and Ethical Challenges for Railway EngineersEmerging Professional and Ethical Challenges for Railway Engineers
Emerging Professional and Ethical Challenges for Railway Engineers
 
EV Charging - Business Opportunity for NTPC
EV Charging - Business Opportunity for NTPCEV Charging - Business Opportunity for NTPC
EV Charging - Business Opportunity for NTPC
 

More from Rajesh Prasad

Opportunities in Railway construction- development operations of infrastructu...
Opportunities in Railway construction- development operations of infrastructu...Opportunities in Railway construction- development operations of infrastructu...
Opportunities in Railway construction- development operations of infrastructu...
Rajesh Prasad
 
20th_Safety_Convention dt 11.09.2023.pdf
20th_Safety_Convention dt 11.09.2023.pdf20th_Safety_Convention dt 11.09.2023.pdf
20th_Safety_Convention dt 11.09.2023.pdf
Rajesh Prasad
 
Cyber Security Action Plan of RVNL
Cyber Security Action Plan of RVNLCyber Security Action Plan of RVNL
Cyber Security Action Plan of RVNL
Rajesh Prasad
 
RVNL Corporate Governance 26.11.2021
RVNL Corporate Governance 26.11.2021 RVNL Corporate Governance 26.11.2021
RVNL Corporate Governance 26.11.2021
Rajesh Prasad
 
Management Development programme - 01.07.2022 .pdf
Management Development programme - 01.07.2022 .pdfManagement Development programme - 01.07.2022 .pdf
Management Development programme - 01.07.2022 .pdf
Rajesh Prasad
 
"Protocol for safe execution of Infra Projects" by Rajesh Prasad, Director Op...
"Protocol for safe execution of Infra Projects" by Rajesh Prasad, Director Op..."Protocol for safe execution of Infra Projects" by Rajesh Prasad, Director Op...
"Protocol for safe execution of Infra Projects" by Rajesh Prasad, Director Op...
Rajesh Prasad
 
Motivation and Bounce Back after the crisis....
Motivation and Bounce Back after the crisis....Motivation and Bounce Back after the crisis....
Motivation and Bounce Back after the crisis....
Rajesh Prasad
 
Revolution 2020, Crisis.. Change....
Revolution 2020, Crisis.. Change....Revolution 2020, Crisis.. Change....
Revolution 2020, Crisis.. Change....
Rajesh Prasad
 
A Coffee Table Book cum handbook on Cable Stayed Bridge with the 4 approaches...
A Coffee Table Book cum handbook on Cable Stayed Bridge with the 4 approaches...A Coffee Table Book cum handbook on Cable Stayed Bridge with the 4 approaches...
A Coffee Table Book cum handbook on Cable Stayed Bridge with the 4 approaches...
Rajesh Prasad
 
PROTOCOL FOR SAFE EXECUTION OF INFRA PROJECTS BY RAJESH PRASAD ED RVNL DT 04...
PROTOCOL FOR SAFE EXECUTION OF INFRA PROJECTS  BY RAJESH PRASAD ED RVNL DT 04...PROTOCOL FOR SAFE EXECUTION OF INFRA PROJECTS  BY RAJESH PRASAD ED RVNL DT 04...
PROTOCOL FOR SAFE EXECUTION OF INFRA PROJECTS BY RAJESH PRASAD ED RVNL DT 04...
Rajesh Prasad
 
Uses of special kind of technologies for implementation of special kind of st...
Uses of special kind of technologies for implementation of special kind of st...Uses of special kind of technologies for implementation of special kind of st...
Uses of special kind of technologies for implementation of special kind of st...
Rajesh Prasad
 
IIBE ppt at Lucknow dt 25.05.18
IIBE ppt at Lucknow dt 25.05.18IIBE ppt at Lucknow dt 25.05.18
IIBE ppt at Lucknow dt 25.05.18
Rajesh Prasad
 
Construction Safety Protocol PPT by Rajesh Prasad, ED RVNL at Lucknow on 26.0...
Construction Safety Protocol PPT by Rajesh Prasad, ED RVNL at Lucknow on 26.0...Construction Safety Protocol PPT by Rajesh Prasad, ED RVNL at Lucknow on 26.0...
Construction Safety Protocol PPT by Rajesh Prasad, ED RVNL at Lucknow on 26.0...
Rajesh Prasad
 
IIBE ppt at Lucknow dt 25.05.18
IIBE ppt at Lucknow dt 25.05.18IIBE ppt at Lucknow dt 25.05.18
IIBE ppt at Lucknow dt 25.05.18
Rajesh Prasad
 
Bridging over river Bhagirathi- a Handbook cum Coffee Table Book by Rajesh Pr...
Bridging over river Bhagirathi- a Handbook cum Coffee Table Book by Rajesh Pr...Bridging over river Bhagirathi- a Handbook cum Coffee Table Book by Rajesh Pr...
Bridging over river Bhagirathi- a Handbook cum Coffee Table Book by Rajesh Pr...
Rajesh Prasad
 
PPT on execution of 680 m long tunnel ensuring safety of the adjoining rail t...
PPT on execution of 680 m long tunnel ensuring safety of the adjoining rail t...PPT on execution of 680 m long tunnel ensuring safety of the adjoining rail t...
PPT on execution of 680 m long tunnel ensuring safety of the adjoining rail t...
Rajesh Prasad
 
Execution of 680 m long tunnel ensuring safety of the adjoining rail tunnel w...
Execution of 680 m long tunnel ensuring safety of the adjoining rail tunnel w...Execution of 680 m long tunnel ensuring safety of the adjoining rail tunnel w...
Execution of 680 m long tunnel ensuring safety of the adjoining rail tunnel w...
Rajesh Prasad
 
Sucess in engg. construction14.01.08
Sucess in engg. construction14.01.08Sucess in engg. construction14.01.08
Sucess in engg. construction14.01.08
Rajesh Prasad
 
Uses of Larsa 4 d and Lusas 4 D models for Implementation of Cable Stayed ...
Uses of Larsa   4 d and Lusas  4 D models for Implementation of Cable Stayed ...Uses of Larsa   4 d and Lusas  4 D models for Implementation of Cable Stayed ...
Uses of Larsa 4 d and Lusas 4 D models for Implementation of Cable Stayed ...
Rajesh Prasad
 
Implementation of Structural Health Monitoring System for live monitoring of ...
Implementation of Structural Health Monitoring System for live monitoring of ...Implementation of Structural Health Monitoring System for live monitoring of ...
Implementation of Structural Health Monitoring System for live monitoring of ...
Rajesh Prasad
 

More from Rajesh Prasad (20)

Opportunities in Railway construction- development operations of infrastructu...
Opportunities in Railway construction- development operations of infrastructu...Opportunities in Railway construction- development operations of infrastructu...
Opportunities in Railway construction- development operations of infrastructu...
 
20th_Safety_Convention dt 11.09.2023.pdf
20th_Safety_Convention dt 11.09.2023.pdf20th_Safety_Convention dt 11.09.2023.pdf
20th_Safety_Convention dt 11.09.2023.pdf
 
Cyber Security Action Plan of RVNL
Cyber Security Action Plan of RVNLCyber Security Action Plan of RVNL
Cyber Security Action Plan of RVNL
 
RVNL Corporate Governance 26.11.2021
RVNL Corporate Governance 26.11.2021 RVNL Corporate Governance 26.11.2021
RVNL Corporate Governance 26.11.2021
 
Management Development programme - 01.07.2022 .pdf
Management Development programme - 01.07.2022 .pdfManagement Development programme - 01.07.2022 .pdf
Management Development programme - 01.07.2022 .pdf
 
"Protocol for safe execution of Infra Projects" by Rajesh Prasad, Director Op...
"Protocol for safe execution of Infra Projects" by Rajesh Prasad, Director Op..."Protocol for safe execution of Infra Projects" by Rajesh Prasad, Director Op...
"Protocol for safe execution of Infra Projects" by Rajesh Prasad, Director Op...
 
Motivation and Bounce Back after the crisis....
Motivation and Bounce Back after the crisis....Motivation and Bounce Back after the crisis....
Motivation and Bounce Back after the crisis....
 
Revolution 2020, Crisis.. Change....
Revolution 2020, Crisis.. Change....Revolution 2020, Crisis.. Change....
Revolution 2020, Crisis.. Change....
 
A Coffee Table Book cum handbook on Cable Stayed Bridge with the 4 approaches...
A Coffee Table Book cum handbook on Cable Stayed Bridge with the 4 approaches...A Coffee Table Book cum handbook on Cable Stayed Bridge with the 4 approaches...
A Coffee Table Book cum handbook on Cable Stayed Bridge with the 4 approaches...
 
PROTOCOL FOR SAFE EXECUTION OF INFRA PROJECTS BY RAJESH PRASAD ED RVNL DT 04...
PROTOCOL FOR SAFE EXECUTION OF INFRA PROJECTS  BY RAJESH PRASAD ED RVNL DT 04...PROTOCOL FOR SAFE EXECUTION OF INFRA PROJECTS  BY RAJESH PRASAD ED RVNL DT 04...
PROTOCOL FOR SAFE EXECUTION OF INFRA PROJECTS BY RAJESH PRASAD ED RVNL DT 04...
 
Uses of special kind of technologies for implementation of special kind of st...
Uses of special kind of technologies for implementation of special kind of st...Uses of special kind of technologies for implementation of special kind of st...
Uses of special kind of technologies for implementation of special kind of st...
 
IIBE ppt at Lucknow dt 25.05.18
IIBE ppt at Lucknow dt 25.05.18IIBE ppt at Lucknow dt 25.05.18
IIBE ppt at Lucknow dt 25.05.18
 
Construction Safety Protocol PPT by Rajesh Prasad, ED RVNL at Lucknow on 26.0...
Construction Safety Protocol PPT by Rajesh Prasad, ED RVNL at Lucknow on 26.0...Construction Safety Protocol PPT by Rajesh Prasad, ED RVNL at Lucknow on 26.0...
Construction Safety Protocol PPT by Rajesh Prasad, ED RVNL at Lucknow on 26.0...
 
IIBE ppt at Lucknow dt 25.05.18
IIBE ppt at Lucknow dt 25.05.18IIBE ppt at Lucknow dt 25.05.18
IIBE ppt at Lucknow dt 25.05.18
 
Bridging over river Bhagirathi- a Handbook cum Coffee Table Book by Rajesh Pr...
Bridging over river Bhagirathi- a Handbook cum Coffee Table Book by Rajesh Pr...Bridging over river Bhagirathi- a Handbook cum Coffee Table Book by Rajesh Pr...
Bridging over river Bhagirathi- a Handbook cum Coffee Table Book by Rajesh Pr...
 
PPT on execution of 680 m long tunnel ensuring safety of the adjoining rail t...
PPT on execution of 680 m long tunnel ensuring safety of the adjoining rail t...PPT on execution of 680 m long tunnel ensuring safety of the adjoining rail t...
PPT on execution of 680 m long tunnel ensuring safety of the adjoining rail t...
 
Execution of 680 m long tunnel ensuring safety of the adjoining rail tunnel w...
Execution of 680 m long tunnel ensuring safety of the adjoining rail tunnel w...Execution of 680 m long tunnel ensuring safety of the adjoining rail tunnel w...
Execution of 680 m long tunnel ensuring safety of the adjoining rail tunnel w...
 
Sucess in engg. construction14.01.08
Sucess in engg. construction14.01.08Sucess in engg. construction14.01.08
Sucess in engg. construction14.01.08
 
Uses of Larsa 4 d and Lusas 4 D models for Implementation of Cable Stayed ...
Uses of Larsa   4 d and Lusas  4 D models for Implementation of Cable Stayed ...Uses of Larsa   4 d and Lusas  4 D models for Implementation of Cable Stayed ...
Uses of Larsa 4 d and Lusas 4 D models for Implementation of Cable Stayed ...
 
Implementation of Structural Health Monitoring System for live monitoring of ...
Implementation of Structural Health Monitoring System for live monitoring of ...Implementation of Structural Health Monitoring System for live monitoring of ...
Implementation of Structural Health Monitoring System for live monitoring of ...
 

Recently uploaded

一比一原版(爱大毕业证书)爱荷华大学毕业证如何办理
一比一原版(爱大毕业证书)爱荷华大学毕业证如何办理一比一原版(爱大毕业证书)爱荷华大学毕业证如何办理
一比一原版(爱大毕业证书)爱荷华大学毕业证如何办理
nedcocy
 
Null Bangalore | Pentesters Approach to AWS IAM
Null Bangalore | Pentesters Approach to AWS IAMNull Bangalore | Pentesters Approach to AWS IAM
Null Bangalore | Pentesters Approach to AWS IAM
Divyanshu
 
P5 Working Drawings.pdf floor plan, civil
P5 Working Drawings.pdf floor plan, civilP5 Working Drawings.pdf floor plan, civil
P5 Working Drawings.pdf floor plan, civil
AnasAhmadNoor
 
A high-Speed Communication System is based on the Design of a Bi-NoC Router, ...
A high-Speed Communication System is based on the Design of a Bi-NoC Router, ...A high-Speed Communication System is based on the Design of a Bi-NoC Router, ...
A high-Speed Communication System is based on the Design of a Bi-NoC Router, ...
DharmaBanothu
 
Zener Diode and its V-I Characteristics and Applications
Zener Diode and its V-I Characteristics and ApplicationsZener Diode and its V-I Characteristics and Applications
Zener Diode and its V-I Characteristics and Applications
Shiny Christobel
 
This study Examines the Effectiveness of Talent Procurement through the Imple...
This study Examines the Effectiveness of Talent Procurement through the Imple...This study Examines the Effectiveness of Talent Procurement through the Imple...
This study Examines the Effectiveness of Talent Procurement through the Imple...
DharmaBanothu
 
Blood finder application project report (1).pdf
Blood finder application project report (1).pdfBlood finder application project report (1).pdf
Blood finder application project report (1).pdf
Kamal Acharya
 
Levelised Cost of Hydrogen (LCOH) Calculator Manual
Levelised Cost of Hydrogen  (LCOH) Calculator ManualLevelised Cost of Hydrogen  (LCOH) Calculator Manual
Levelised Cost of Hydrogen (LCOH) Calculator Manual
Massimo Talia
 
Applications of artificial Intelligence in Mechanical Engineering.pdf
Applications of artificial Intelligence in Mechanical Engineering.pdfApplications of artificial Intelligence in Mechanical Engineering.pdf
Applications of artificial Intelligence in Mechanical Engineering.pdf
Atif Razi
 
UNIT 4 LINEAR INTEGRATED CIRCUITS-DIGITAL ICS
UNIT 4 LINEAR INTEGRATED CIRCUITS-DIGITAL ICSUNIT 4 LINEAR INTEGRATED CIRCUITS-DIGITAL ICS
UNIT 4 LINEAR INTEGRATED CIRCUITS-DIGITAL ICS
vmspraneeth
 
一比一原版(uoft毕业证书)加拿大多伦多大学毕业证如何办理
一比一原版(uoft毕业证书)加拿大多伦多大学毕业证如何办理一比一原版(uoft毕业证书)加拿大多伦多大学毕业证如何办理
一比一原版(uoft毕业证书)加拿大多伦多大学毕业证如何办理
sydezfe
 
Prediction of Electrical Energy Efficiency Using Information on Consumer's Ac...
Prediction of Electrical Energy Efficiency Using Information on Consumer's Ac...Prediction of Electrical Energy Efficiency Using Information on Consumer's Ac...
Prediction of Electrical Energy Efficiency Using Information on Consumer's Ac...
PriyankaKilaniya
 
Supermarket Management System Project Report.pdf
Supermarket Management System Project Report.pdfSupermarket Management System Project Report.pdf
Supermarket Management System Project Report.pdf
Kamal Acharya
 
Object Oriented Analysis and Design - OOAD
Object Oriented Analysis and Design - OOADObject Oriented Analysis and Design - OOAD
Object Oriented Analysis and Design - OOAD
PreethaV16
 
Introduction to Computer Networks & OSI MODEL.ppt
Introduction to Computer Networks & OSI MODEL.pptIntroduction to Computer Networks & OSI MODEL.ppt
Introduction to Computer Networks & OSI MODEL.ppt
Dwarkadas J Sanghvi College of Engineering
 
Open Channel Flow: fluid flow with a free surface
Open Channel Flow: fluid flow with a free surfaceOpen Channel Flow: fluid flow with a free surface
Open Channel Flow: fluid flow with a free surface
Indrajeet sahu
 
Asymmetrical Repulsion Magnet Motor Ratio 6-7.pdf
Asymmetrical Repulsion Magnet Motor Ratio 6-7.pdfAsymmetrical Repulsion Magnet Motor Ratio 6-7.pdf
Asymmetrical Repulsion Magnet Motor Ratio 6-7.pdf
felixwold
 
Assistant Engineer (Chemical) Interview Questions.pdf
Assistant Engineer (Chemical) Interview Questions.pdfAssistant Engineer (Chemical) Interview Questions.pdf
Assistant Engineer (Chemical) Interview Questions.pdf
Seetal Daas
 
一比一原版(osu毕业证书)美国俄勒冈州立大学毕业证如何办理
一比一原版(osu毕业证书)美国俄勒冈州立大学毕业证如何办理一比一原版(osu毕业证书)美国俄勒冈州立大学毕业证如何办理
一比一原版(osu毕业证书)美国俄勒冈州立大学毕业证如何办理
upoux
 
Call For Paper -3rd International Conference on Artificial Intelligence Advan...
Call For Paper -3rd International Conference on Artificial Intelligence Advan...Call For Paper -3rd International Conference on Artificial Intelligence Advan...
Call For Paper -3rd International Conference on Artificial Intelligence Advan...
ijseajournal
 

Recently uploaded (20)

一比一原版(爱大毕业证书)爱荷华大学毕业证如何办理
一比一原版(爱大毕业证书)爱荷华大学毕业证如何办理一比一原版(爱大毕业证书)爱荷华大学毕业证如何办理
一比一原版(爱大毕业证书)爱荷华大学毕业证如何办理
 
Null Bangalore | Pentesters Approach to AWS IAM
Null Bangalore | Pentesters Approach to AWS IAMNull Bangalore | Pentesters Approach to AWS IAM
Null Bangalore | Pentesters Approach to AWS IAM
 
P5 Working Drawings.pdf floor plan, civil
P5 Working Drawings.pdf floor plan, civilP5 Working Drawings.pdf floor plan, civil
P5 Working Drawings.pdf floor plan, civil
 
A high-Speed Communication System is based on the Design of a Bi-NoC Router, ...
A high-Speed Communication System is based on the Design of a Bi-NoC Router, ...A high-Speed Communication System is based on the Design of a Bi-NoC Router, ...
A high-Speed Communication System is based on the Design of a Bi-NoC Router, ...
 
Zener Diode and its V-I Characteristics and Applications
Zener Diode and its V-I Characteristics and ApplicationsZener Diode and its V-I Characteristics and Applications
Zener Diode and its V-I Characteristics and Applications
 
This study Examines the Effectiveness of Talent Procurement through the Imple...
This study Examines the Effectiveness of Talent Procurement through the Imple...This study Examines the Effectiveness of Talent Procurement through the Imple...
This study Examines the Effectiveness of Talent Procurement through the Imple...
 
Blood finder application project report (1).pdf
Blood finder application project report (1).pdfBlood finder application project report (1).pdf
Blood finder application project report (1).pdf
 
Levelised Cost of Hydrogen (LCOH) Calculator Manual
Levelised Cost of Hydrogen  (LCOH) Calculator ManualLevelised Cost of Hydrogen  (LCOH) Calculator Manual
Levelised Cost of Hydrogen (LCOH) Calculator Manual
 
Applications of artificial Intelligence in Mechanical Engineering.pdf
Applications of artificial Intelligence in Mechanical Engineering.pdfApplications of artificial Intelligence in Mechanical Engineering.pdf
Applications of artificial Intelligence in Mechanical Engineering.pdf
 
UNIT 4 LINEAR INTEGRATED CIRCUITS-DIGITAL ICS
UNIT 4 LINEAR INTEGRATED CIRCUITS-DIGITAL ICSUNIT 4 LINEAR INTEGRATED CIRCUITS-DIGITAL ICS
UNIT 4 LINEAR INTEGRATED CIRCUITS-DIGITAL ICS
 
一比一原版(uoft毕业证书)加拿大多伦多大学毕业证如何办理
一比一原版(uoft毕业证书)加拿大多伦多大学毕业证如何办理一比一原版(uoft毕业证书)加拿大多伦多大学毕业证如何办理
一比一原版(uoft毕业证书)加拿大多伦多大学毕业证如何办理
 
Prediction of Electrical Energy Efficiency Using Information on Consumer's Ac...
Prediction of Electrical Energy Efficiency Using Information on Consumer's Ac...Prediction of Electrical Energy Efficiency Using Information on Consumer's Ac...
Prediction of Electrical Energy Efficiency Using Information on Consumer's Ac...
 
Supermarket Management System Project Report.pdf
Supermarket Management System Project Report.pdfSupermarket Management System Project Report.pdf
Supermarket Management System Project Report.pdf
 
Object Oriented Analysis and Design - OOAD
Object Oriented Analysis and Design - OOADObject Oriented Analysis and Design - OOAD
Object Oriented Analysis and Design - OOAD
 
Introduction to Computer Networks & OSI MODEL.ppt
Introduction to Computer Networks & OSI MODEL.pptIntroduction to Computer Networks & OSI MODEL.ppt
Introduction to Computer Networks & OSI MODEL.ppt
 
Open Channel Flow: fluid flow with a free surface
Open Channel Flow: fluid flow with a free surfaceOpen Channel Flow: fluid flow with a free surface
Open Channel Flow: fluid flow with a free surface
 
Asymmetrical Repulsion Magnet Motor Ratio 6-7.pdf
Asymmetrical Repulsion Magnet Motor Ratio 6-7.pdfAsymmetrical Repulsion Magnet Motor Ratio 6-7.pdf
Asymmetrical Repulsion Magnet Motor Ratio 6-7.pdf
 
Assistant Engineer (Chemical) Interview Questions.pdf
Assistant Engineer (Chemical) Interview Questions.pdfAssistant Engineer (Chemical) Interview Questions.pdf
Assistant Engineer (Chemical) Interview Questions.pdf
 
一比一原版(osu毕业证书)美国俄勒冈州立大学毕业证如何办理
一比一原版(osu毕业证书)美国俄勒冈州立大学毕业证如何办理一比一原版(osu毕业证书)美国俄勒冈州立大学毕业证如何办理
一比一原版(osu毕业证书)美国俄勒冈州立大学毕业证如何办理
 
Call For Paper -3rd International Conference on Artificial Intelligence Advan...
Call For Paper -3rd International Conference on Artificial Intelligence Advan...Call For Paper -3rd International Conference on Artificial Intelligence Advan...
Call For Paper -3rd International Conference on Artificial Intelligence Advan...
 

Rebuilding of Railway Infrastructures during the present crisis by Rajesh Prasad

  • 1. Rebuilding of Railway Infrastructures during the Pandemic (New Normal ) By Rajesh Prasad Director (Operations) RVNL
  • 2.  About RVNL  Impact of COVID-19 (New Normal) and initiatives taken by RVNL  Importance of ‘Make in India’ policy and implementation by RVNL  Infrastructure building in Railway sector  Way forward by RVNL SCOPE
  • 3. PERFORMANCE OF RVNL  Operations started in 2005 with the appointment of BoDs.  Granted Mini Ratna status on 19th September 2013, (under process for “Navratna”).  RVNL has been rated “Excellent” for the consecutive Nine times by DPE.  RVNL has been ranked 1st amongst the Railway CPSEs for the four times out of last six years.
  • 4. 1445 1598 2117 2493 3142 4541 5920 7557 10060 14530 16000 (Projected) 0 2000 4000 6000 8000 10000 12000 14000 16000 18000 2010-11 2011-12 2012-13 2013-14 2014-15 2015-16 2016-17 2017-18 2018-19 2019-20 2020-21 CRORE TURNOVER CAGR of 36.78% in last 5 years (Rs. in Cr.)
  • 5. 185.72 304.02 381.61 469.65 606.59 789.86 0 100 200 300 400 500 600 700 800 900 2014-15 2015-16 2016-17 2017-18 2018-19 2019-20 PAT (RS. CRORE) PAT (Rs. Crore) 2678.86 3011.57 3083.37 3351.48 3738.76 4499.77 0 1000 2000 3000 4000 5000 2014-15 2015-16 2016-17 2017-18 2018-19 2019-20 NET WORTH (RS. CRORE) New Worth (Rs. Crore) MOU PERFORMANCE : Assessment Year Rating RVNL’s rank among Railway CPSEs assessed by DPE Rank of RVNL 2007-08 Good 8th 2008-09 Very Good 10th 2009-10 Very Good 7th 2010-11 Excellent 5th 2011-12 Excellent 2nd 2012-13 Excellent 1st 2013-14 Excellent 2nd 2014-15 Excellent 1st 2015-16 Excellent 1st 2016-17 Excellent 1st 2017-18 Excellent 1st 2018-19 Excellent 2nd
  • 6. 2019-20 2019-20 (upto December 2019) 2020-21 (upto December 2020) Turnover 14530.58 10309.90 9825.77 Profit before Tax (PBT) 990.83 742.09 742.40 Net Profit (Profit after Tax-PAT) 789.86 592.96 596.67 There is a decrease in turnover by 4.70% during last 9 months mainly due to COVID-19, though PBT and PAT are marginally higher. Rs. in Crore
  • 7. Order Book of RVNL  Total 183 nos. of projects assigned to RVNL for execution.
  • 8. ACHIEVEMENT New Railway Track 456 Gauge Conversion 1889 Doubling of Track 3483 Railway Electrification 4970 MTP (KM) 42 Workshops 8 Cable Stayed Bridge 1 456 1889 1 92 projects have been fully commissioned upto March 2020 3483 4970 42 8
  • 9. 2019-20 2020-21 (upto 03.09.2021) Gauge Conversion (GC) + Doubling (DL) + New Line (NL) 665 Kms 565 Kms* Railway Electrification (RE) 714 RKM 1561 RKM Workshop 1 No 3 Nos. *181 Kms Engine Rolling in 2020-21 waiting for commissioning. Achievements and Highlights
  • 10.
  • 12. This NEW NORMAL is getting OLD 1st case of COVID-19 detected on 17 November 2019 Today's seminar …
  • 13. What COVID and IT have done to us? NEW NORMAL LIFE :
  • 14. Special initiatives to combat COVID-19 in RVNL  Contractors were advised to make arrangements for lodging, boarding, fooding duly following social distancing norms, moving patients to nearby doctors/ hospitals, paying charges of doctors/ hospitals, providing sanitizers, soaps etc for labourer stuck at worksites during the lockdown period and claim reimbursements from RVNL for the same.  Precautions taken in labour camps to ensure social distancing norms, checking of temperature of workmen on daily basis so that works can progress duly ensuring safety of labourers during the difficult times of COVID-19. Cont..
  • 15.  A separate link was provided for instructions due to COVID’19 on RVNL’s website to facilitate easy dissemination of information at all levels.  In keeping with the Ministry of Finance guidelines to give financial relief to contractors, release of proportionate BG’s permitted.  Recovery of mobilization advance from contractors has been deferred for 6 months to improve the cash flow during COVID’19. Cont..
  • 16.  To further address liquidity problems, stage payment conditions have been reviewed and revised on supply items.  As it was not possible to follow routine procedures of test checks due to restriction of movement due to COVID’19, to address the cash flow problem of contractors, measures were taken to allow provisional passing of bills till such checks are possible.  Submission of Bid Security in physical form relaxed to 30 days from 5 days, due to restrictions in movement, for the tenders opened between May’ 20 to Aug’ 20. Cont..
  • 17.  System of online pre-Bid Conference has been introduced and it is working very well avoiding physical travel and gathering and at the same time meeting the purpose of Prebid conferences
  • 19. Name of Work Value Tender Opening Award of Contract Construction of Viaduct from P276 to P314 including Mominpur and Majerhat Station 196.30 Cr. Technical bid opened on 29.07.2020 and Price bid opened on 14.08.2020 17.08.2020 (Total no. of days in finalization of the contract in only 19 days) Construction of PEB shed structures, buildings, P-Way and utilities, General Electrical works and supply, installation and commissioning of Machinery and plant for setting up of Metro Car Depot at Joka 350.89 Cr. Technical bid opened on 31.07.2020 and Price bid opened on 22.08.2020 25.08.2020 (Total no. of days in finalization of the contract in only 22 days) Fast track finalization of Tenders
  • 20. P287 & P288 of Joka-Esplanade Metro Corridor : Taking the Opportunity given by Lock Down, we Completed very critical Two Metro Piers adjacent to ‘JAI HIND’ Bridge.
  • 21. Taking the benefit of Lock Down, we substantially Completed, substructure part of very critical Pier Locations on the Railway track at Majerhat Station, Kolkata
  • 22. Other measures taken to improve delivery of projects:  In cases where equipment suppliers are not ready to despatch plant and equipment to contractor without full payment, supply of equipment is facilitated by giving Comfort letter to supplier. This has reduced the delay in delivery of projects due to delay in supply of plants and equipment.  In case where main contractor is not making timely payment to sub-contractors, thereby delaying the progress of execution, a provision has been made in standard bidding documents for making direct payment to sub-contractors.
  • 23.  A system of offloading has been introduced to get executed, at the cost of the Contractor some small value yet important works for commissioning, by other agency, which the contractor is unable to progress at the desired pace. The provisions have been kept in such a way that this enhances the speed of execution of works without any additional cost on RVNL and also without adversely affecting the performance of main contractor.  New rate to the agency where work site not handed over even after the original DoC.  Amicable settlement policy : 12 Cases settled.
  • 24.  In view of difficulty being faced by contractors in obtaining BG, the performance security has been made admissible in the form of FDR (free from any encumbrance) in addition to other forms.  Several financial powers have been delegated to field officers
  • 25. Subject : Bid Security/ Earnest Money Deposit Option of submitting Bid Security through a declaration form instead of only Bid Security has also been introduced in RVNL.
  • 26. Subject : Performance Security Performance Security from existing 10% to 3% of the value of the contract has been introduced in RVNL. In the existing contract performance security in addition to proportionate performance security released.
  • 27. Subject : Amendment in GFRs, 2017- GTE. No Global Tender Enquiry (GTE), however shall be invited for tender upto Rs. 200 crore.
  • 28. Subject : Global Tender Enquiry (GTE). Restriction on Global Tenders as specified in the revised Rule 161(iv) will be applicable on all procurements including Goods, Non-consulting services, Constancy Services and Works including turnkey projects.
  • 29. Subject : Restriction on agencies participating in tenders from countries sharing land boundary with India.
  • 31.
  • 32. Make in India focuses on the following 25 sectors of the economy: 1. Automobiles 2. Automobile Components 3. Aviation 4. Biotechnology 5. Chemicals 6. Construction 7. Defence Manufacturing 8. Electronic Systems 9. Electrical Machinery 10. Food Processing 11. Information Technology and Business Process Management 12. Leather 13. Media and entertainment 14. Mining 15. Oil and gas 16. Pharmaceuticals 17. Ports & Shipping 18. Railways 19. Renewable Energy 20. Roads and Highways 21. Space 22. Thermal Power 23. Textiles and Garments 24. Tourism and Hospitality 25. Wellness
  • 33. EASE OF DOING BUSINESS Ranking system established by the World Bank Group. India has emerged as one of the most attractive destinations not only for investments but also for doing business. India jumps 79 positions from 142nd (2014) to 63rd (2019) in Ease of Doing Business Ranking 2020'. Construction Permits: India’s ranking :- 184 in 2014 and 27 in 2019. Getting Electricity: India’s ranking :- 137 in 2014 and 22 in 2019. Apart from these significant improvements, among the 190 economies, India ranks 13th in Protecting Minority Investors and 25th in Getting Credit.
  • 34. RVNL to promote ‘Make in India’ policy by using indigenous rails in Kolkata Metro Rail Project In an effort towards ‘आत्मनिर्भर र्ारत’ RVNL has used, for the first time, indigenous HH Rails in a Metro Rail Project in our country. A step taken by RVNL for Kolkata Metro. All Metro systems in different cities in India have used imported Head Hardened (HH) Rails. HH rails offers greater efficiency through its ability to handle higher axle loads of over 25 Tonnes with low deformation and wear. For the first time indigenous HH rails shall be used for a Metro in our country.
  • 36.
  • 37.
  • 38. LAYING OF BLT ON EMBANKMENT BY USING PCRSB
  • 39.
  • 40.
  • 41.  Freyssinet’s Parallel Strand System (PSS) stay cables - which has a design life of 100 years and is the most advanced and durable stay cable system in the world today. There are 3 planes of stay cables with 18 cables each.  Isotension® Method 4-lane Cables Stayed Bridge, Barddhaman
  • 42. 4-lane Cables Stayed Bridge, Barddhaman
  • 43. Make in India Policy :- Manufacture of Cables by M/s. Usha Martin, Ranchi on behalf of Freyssinet – subcontractor (a french company) using their technology in India.
  • 44. Reconstruction of Pamban Bridge Construction of new Pamban Bridge involves Pile foundation, Pile cap and Pier caps with Steel girders as the Superstructure. The existing navigational span is known as scherzer span, which is having Roller Lift arrangement, whereas the proposed navigational span is a vertical lift span. The navigational span consists of Steel through Girder with warren type trusses. The weight of the proposed navigational span is 1200 MT.
  • 46.
  • 47.  RVNL is fully committed to follow the world best construction practices which include mechanization for better quality of output.  Executed transmission line work for supply to TSS (in case of refusal/failure of state govts to execute).  Use of self propelled UTVs in RE projects saving loco, crew and fuel.  First over Indian Railways to do mechanized wiring by AWT (Automatic wiring Train).  AWT machine is capable of wiring both the wire under cool tension thus increasing wiring speed and also reducing the post wiring activities.
  • 50. DISINFECTION OF SITE OFFICES, LABORATORIES, MACHINES, EQUIPMENTS AND VEHICLES
  • 51. PATIENCE, DISCIPLINE AND NEW NORMAL ARE THE KEY
  • 52. Awareness Thermal screening of all at entry and exit of work site Disinfection of Site, Store Hands Free Sanitizer dispenser Hand Soap, Mask and Sanitizer facilities provided
  • 54.
  • 55. I’LL ADMIT, THIS IS NOT HOW I SAW 2020 GOING. Pile Cap Steel Reinforcement binding Lattice Girder fabrication yard
  • 57. BE TECH SAVVY TO FIGHT COVID • VIDEO CONFERENCING instead of physical presence in meetings. • VIDEO CALL instead of personal visit. • E-OFFICE in place of paper files.
  • 60. COVID-19 – A Pandemic has resulted into → The entire country is shaken in locked down condition → World Share Market earlier tanked → Wheel of Indian Railway carrying passengers has stopped after 167 years → Shutdown of creation of Railway Infrastructures → Share price of major companies has touched to the bottom and trying to recover
  • 61. QUESTION COMES TO OUR MIND .. What next to → Our country → Indian Railway → RVNL
  • 62. Karoly Takacs (Hungarian Armyman) • ‘Impossible is nothing’ • 1938 – In Army Camp, during practice hand grenade exploded in his right hand. He lost his right hand then he started practicing with his left hand. • 1939 - He won the Hungarian national pistol shooting championship. • Won the gold medals in 1948 & 1952 Olympics Arunima Sinha (Indian mountain climber and sportswoman)  2011- She was pushed from a running train by some robbers and She lying there seven hours. Her left leg had to be amputated below the knee, she got rods in right leg and multiple fractures in spinal cord  2013 - She reached the summit of Mount Everest  World's first female amputee to scale Mount Everest, Mount Kilimanjaro (Tanzania), Mount Elbrus (Russia), Mount Kosciusko (Australia), Mount Aconcagua (South America), Carstensz Pyramid (Indonesia) and Mount Vinson  2015 - Padma Shri Award
  • 63. CHALLENGES BEFORE INDIAN RAILWAYS 1950-51 2020 %age increase Loading 73 MT 1200 MT 1550% Million Passenger Kms 66517 12,00,000 1700% Route Kms 53500 67,000 25% Double/Multiple route length 5100 Kms 25000 Kms 390% • 161 out of 247 sections in HDN routes > 100% line capacity 16% of route km carries 55% of passengers and 58% of freight
  • 64. Project :- It simply means converting vision into reality. A set of activities are undertaken to meet the specified objectives for the changes. The various features of typical projects are as under: • Temporary - have a definite beginning and an end. • Unique – no two projects are identical. • Predefined goals & objectives – financial/ social/ economic. • Budgets & schedules – prefixed budget and time frame. • Uses Resources & Manpower – both are limited. • Quality/ performance - determined at beginning. • Face Risks – known and unknown risks • Have a project life cycle – many phases from start to end.
  • 65. Fast Track Project Implementation (FTPI) – Why affected Budget (2014-15) : • “Para – 18: There has been focus on sanctioning projects rather than completing them. In the last 30 years, as many as 676 projects were sanctioned worth Rs 1,57,883 crore. Of these, only 317 projects could be completed and 359 projects remain to be completed which will now require as much as Rs 1,82,000 crore.” • “Para – 19: In the last 10 years, 99 new line projects worth Rs 60,000 crore were sanctioned out of which only one project is complete till date. In fact, there are 4 projects that are as old as 30 years, but are still not complete for one reason or another.
  • 66. RVNL has got major role to play in Railway Infrastructure
  • 67.
  • 68. Way forward by RVNL Rail Vikas Nigam Ltd. (RVNL) Subsidiary SPV’s Kutch Railway Company Ltd. (KRCL) (50.00%) HSRC Infra Services Limited (100%) Bidding arm and a new vertical Krishnapatnam Railway Company Ltd. (KPRCL) (49.76%) Bharuch Dahej Railway Corporation Ltd. (BDRCL) (35.46%) Haridaspur Paradeep Railway Company Ltd. (HPRCL) (30.00%) Angul Sukinda Railway Ltd. (ASRL) (32.37%)
  • 69.  RVNL has created the following SPVs:-  Kutch Railway Company Limited :- Commissioned  Krishnapatnam Railway Company Limited :- Commissioned  Bharuch-Dahej Railway Company Limited :- Commissioned  Haridaspur- Paradip Railway Company Limited :- Commissioned on 30th July 2020  Angul Sukinda Railway Limited :- Commissioning target June 2022  RVNL is an Equity Partner of 10% in a SPV with 12 Major Ports under Ministry of Shipping for undertaking railway projects and activities in major ports (Indian Port Rail Company Ltd.-IPRCL).  Rs. 73,776 crore revenue generated for Indian Railways without any invested by Ministry of Railway.  Equity contribution of only Rs. 822 crore in the 4 operational SPVs at a total project cost of Rs. 5560 crore. RESOURCE MOBILISATION THROUGH SPVs RVNL LEADING THE GROWTH FOR AATMANIRBHAR BHARAT
  • 70. Achievements of Kutch Railway Company Ltd.  Operations started from July - 2006 • Freight Loading (MT) - 407.45 • Total Revenue Earned (Rs. Cr.) - 54619.34 • Share of IR’s Revenue (Rs. Cr.) - 47367.82 • Share of SPV’s Revenue (Rs. Cr.) - 7251.52  KRC (Kutch Railway Co. Ltd.) – 1853 rakes in Jan. 2021, all time record.
  • 71. Achievements of Bharuch-Dahej Railway Company Ltd. Operations started from March 2012 • Freight Loading (MT) - 42.72 • Total Revenue Earned (Rs. Cr.) - 5716.74 • Share of IR’s Revenue (Rs. Cr.) - 5157.03 • Share of SPV’s Revenue (Rs. Cr.) – 563.56
  • 72. Achievements of Krishnapatnam Railway Company Limited Operations started from Nov. 2008 • Total Revenue Earned (Rs. Cr.) - 14009.51 • Share of IR’s Revenue (Rs. Cr.) - 13201.76 • Share of SPV’s Revenue (Rs. Cr.) - 807.78
  • 73.  HPRCL (Haridaspur Paradip Railway Co. Ltd.) – Single line commissioned in July 2020. 2974 nos. of rakes transported from Aug. 2020 to Feb. 2021 (only 7 months). Achievements of Haridaspur- Paradip Railway Company Limited
  • 74. Angul Sukinda Railway Limited • SPV formed in Feb’2009 for new line from Angul to Sukinda • Cost of project - Rs.2440.53 Cr • Project length - 104 Km • Equity - Rs. 778.60 Cr / Debt - Rs. 1600 Cr • Equity : Debt :: 33: 67 • Land acquisition is being done by East Coast Railway through the Government of Orissa • Commissioning target : June 2022 RVNL-32.37% CONCOR-26.71% Jindal Steel and Power Ltd.-7.71% Govt. of Odisha-21.89% Odisha Mining Corporation- 10.79% Odisha Industrial Infrastructure Development Corporation-0.54%
  • 75. New Rail Connectivity from Pachchwara coal blocks to Nagarnabi in Jharkhand • A DPR is under preparation by M/s RITES. • Alignment has been modified as earlier one was passing through the Urma Paharitola coal block. • Three alternative routes has been proposed by RITES, which is to be finalized by Power Companies. • A Bankability study by SBICAPS is in progress. • Draft bankability study is ready, final DPR is also submitted by M/s RITES.
  • 76. New Rail connectivity from Sardega – Pelma • Coal India Limited is planning to construct a rail link from Sardega to Pelma for an integrated coal evacuation arrangement having a total length of about 35 Kms. • Ministry of Railways has nominated Rail Vikas Nigam Ltd (RVNL) to be the SPV partner in the Railway Project as Railway PSU with a subsidiary of Coal India Ltd. • It has been decided by the Coal India Ltd. that Mahanadi Coal Ltd (MCL) will be the partner in the proposed SPV. • The project will be implemented under participative policy of Ministry of Railways and RVNL will be the implementing agency.
  • 77. Workshop Projects on Turnkey basis  Civil work of construction of Diesel Loco Component Workshop at Dankuni completed in a record time of 1 year.  DMU Factory at Haldia completed in 16 months.  Electric Loco Factory at Dankuni completed in 25 months.  DLW Capacity augmentation completed in 22 months. Its work commencement was done by Hon'ble PM who gave a target of 24 months. RVNL completed this work in 22 months and was inaugurated by Hon'ble PM.  Workshop for manufacture of Fiat Bogies for LHB Design Coaches, Yadgir completed in 17 months.  Aunrihar - DEMU Shed completed in 21 months.  Vadlapudi - Wagon POH workshop of 200 Nos capacity near Duvvada station completed in 25 months.  Diesel Loco Shed, Barauni completed in 27 months.  Marathwada Rail Coach Factory, Latur completed in 26 months  MEMU Shed, Kanpur completed in 22 months.
  • 78. Commencement of work at site by Hon’ble Prime Minister on 25.12.2014, Project (Part-I) dedicated to Nation by Hon’ble Prime Minister on 24.10.2016 Augmentation of Production Capacity of DLW
  • 79. TUNNELING Tunnel Constructed:- • Tunnel of 1.0 km in 4 months & 6.7 km long in 25 months completed in Obulavaripalle - Krishnapattnam New Line project in SC Railway. • 680 m Tunnel completed in Goelkera-Manoharpur 3rd Line project. Tunnel Under-construction:- • 110 km of tunnels (17 nos.) in Rishikesh-Karnaprayag New Line (125 km). Longest tunnel = 15.7 km. • 25.9 km of tunnels (20 nos.) in Bhanupali-Bilaspur-Beri New Line (63 km). Longest tunnel-3.79 km. • 6 tunnels (longest-2.7 km, total-9.8 km) in Yevatmal-Nanded New Line (207 km). • 16 tunnels (longest-410 m, Total = 2.56 km) in Castlerock-Kulem Ghat Section in Hospet-Vasco Doubling Project. • 5 tunnels (Total-2.15 km/Longest-1.08 km) in Budni-Barkhera 3rd line project.
  • 80. 6.7 KM TUNNEL - KRISHNAPATNAM PORT SPV COMPLETED IN 25 MONTHS
  • 81. 4.62 km long bridge in Kerala completed in 27 months
  • 82. Cable Stayed Bridge at Bardhhaman - erection completed in less than 200 days
  • 83. 65 Kms of Metro construction in City of Kolkata has been mandated for execution. Noapara - Baranagar – Dakshineswar Metro inaugurated by Hon’ble Prime Minister on 22.02.2021 First Metro commissioned by Railway PSU
  • 84. RVNL Coffee Table Book • https://www.rvnl.org/en/RVNL%20Documents/RVNL%20Book%20- %2017yrs%20of%20Journey.pdf • https://www.linkedin.com/posts/rvnl_rvnl-corporate-book-17-years- of-glorious-activity-6710166556195729408-XnVn The elegantly designed book captures the storyline and highlights of 17 years of RVNL's journey. We sincerely hope you like it and the book brings us closer by helping you know more about RVNL.
  • 85. Over the past years, RVNL has established its mark as a professionally mature, technologically upbeat and managerially sound organisation. RVNL's contribution to growth of railroad infrastructure in India that directly translates to economic growth and human development across diverse regions of the country will be remembered in the times to come. The corporate video especially focuses on the projects delivered and accelerated by the company in the last 2 years. It is commendable how the complete team of RVNL, from the chairman to the project teams in field, worked in synergy to ride through even tough times of pandemic and lockdown. This video is a dedication to and appreciation of the talented team of RVNL across all site offices, PIUs, SPVs, JVs, Subsidiary companies and Corporate Office. YouTube link : https://www.youtube.com/watch?v=-Gc6AH7XMH0 RVNL Corporate Video
  • 86. रेल विकास निगम लललमटेड हम हैं गनत विकास की राहें दुर्गम पर हम सक्षम हम हैं गनत विकास की गुणित्ता है साख हमारी सददयों की है जिम्मेदारी हम बढ़ते हैं हम र्ढ़ते हैं राहें कल की आस की राहें दुर्गम पर हम सक्षम हम हैं र्तत विकास की पारदलशभता सब बातों में कमगशीलता हर हाथों में दूरदशी सपनों से ललखते र्ाथा रेल विकास की राहें दुर्गम पर हम सक्षम हम हैं र्तत विकास की पटरी सा फौलादी कल था पदहये सा र्ततमान आि है रेल बढेगी देश बढेगा यह है लौ विश्िास की राहें दुर्गम पर हम सक्षम हम हैं र्तत विकास की पुल ढाले हैं नददयााँ लाांघी ट्रैक बबछाए धरती नापी हम र्ारत का स्िर्णभम कल हैं बात िह ीं इनतहास की राहें दुर्गम पर हम सक्षम हम हैं गनत विकास की. YouTube link : https://youtu.be/Oav1KRuovaI
  • 87. Side effects of COVID and Technology …
  • 88.
  • 90. “Be the change that you wish to see in the world.” Mahatma Gandhi “Everyone thinks of changing the world, but no one thinks of changing himself.” Leo Tolstoy
  • 91. The conclusion remain …  We need to be ever motivated.  Indian Railway will remain lifeline of the nation and growth engine of the country.  RVNL will continue to play very major role in building Railway Infrastructure thus in building nation.