The document provides a May 2014 construction update for the PCAPP EDS site: - Concrete pouring began on April 17th and the first slab was poured on May 8th for Environmental Enclosure #1. - Modules such as the command post and change house will begin arriving in May 2014. - As of April 30th, the project had 20 safe work days and 2,497 safe work hours with a staff of 26 employees and 20 subcontractor personnel. - The document includes schedules, permit progress, and photos of site construction activities like soil processing and trench digging.