SlideShare a Scribd company logo
1
May 2014 Construction Update
2
May 2014 Construction Update
3
May 2014 Construction Update
4
May 2014 Construction Update
Change House
Environmental
Enclosure #1
Environmental
Enclosure #3
Laboratory
PCAPP EDS Site Overview
5
PCAPP EDS Safety
As of April 30, the
PCAPP EDS project staff
has accomplished:
 20 Safe Work Days
 2,497 Safe Work Hours
6
Workers smooth concrete on May 8
after the first concrete slab pour for
Environmental Enclosure #1.
PCAPP EDS Construction
Staffing –26 employees
 Construction
 Workers: 6
–Subcontractor
personnel – 20
A worker sets screws for the forms in
preparation for the concrete slab pour for
Environmental Enclosure #2
7
NOT STARTED
IN PROGRESS (POTENTIAL ISSUES)
IN PROGRESS (NO ISSUES)
COMPLETE
Key Milestone
DESIGN START (DEC 2013)
SITE DESIGN COMPLETE (MAR 2014)
CONSTRUCTION STARTS (27 MAR 2014)
CONSTRUCTION COMPLETE (OCT 2014)
E-DAY – EDS START OF
AGENT OPERATIONS (OCT 2014)
CONSTRUCTION CONTRACT AWARD (NOV 2013)
PEO ACWA PROGRAMMATIC DECISION TO SELECT EDS TECHNOLOGY (APR 2013)
PCAPP EDS Schedule
(JPME-P Working Schedule)
CONCRETE POURS BEGIN (17 APR 2014)
MODULES (COMMAND POST, CHANGE HOUSE, TREATY TRAILER, ETC.)
BEGIN TO ARRIVE (MAY 2014)
MILITARY FABRIC STRUCTURES FOR EDS ENVIRONMENTAL
ENCLOSURES ARRIVE (JUN 2014)
ARRIVAL OF FIRST EDS UNIT (AUGUST 2014)
8
PCAPP EDS Permitting Progress
NOT STARTED
IN PROGRESS (POTENTIAL ISSUES)
IN PROGRESS (NO ISSUES)
COMPLETE
Key Milestone
CLASS III PERMIT MODIFICATION SUBMITTED TO CDPHE (24 OCT 2013)
STATE APPROVAL OF TEMPORARY AUTHORIZATION
FOR CONSTRUCTION (7 MAR 2014)
SITE CONSTRUCTION START (27MAR 2014)
APPROVAL OF CLASS III MODIFICATION
FOR OPERATIONS (SEP 2014)
E-DAY – EDS START OF AGENT
OPERATIONS (OCT 2014)
PCD RCRA PERMIT RENEWED (JAN 2014)
SUBMIT CERTIFICATE OF DESIGNATION (CD) (DEC 2013)
PEO ACWA PROGRAMMATIC DECISION TO SELECT EDS TECHNOLOGY (APR 2013)
APPROVAL OF CD FOR OPERATIONS
(OCT 2014)
COUNTY APPROVAL OF TEMPORARY AUTHORIZATION
FOR CONSTRUCTION (26 MAR 2014)
RECORD OF ENVIRONMENTAL CONSIDERATION (DEC 2013)
9
Site Progress
10
Processing dirt, the job of mixing the fill with water
under the weight of heavy equipment, makes for
better compaction when it’s later moved into the
enclosures as a base for the slabs that will be poured.
Site Progress
11
Measure twice, dig once.
A worker confirms the
depth of the trench being
carved out. This for the
pipes that will be part of
the fire line that will
serve the EDS site when
complete.
Questions?
12
Acting Principal Deputy Assistant Secretary of Defense Dr.
A. Tom Hopkins (third from left), Program Executive Officer
ACWA Conrad Whyne (second from left) and PCAPP Project
Manager Rick Holmes, listen to Jake Torres explain the
munition process in the Vapor Containment Room.

More Related Content

What's hot

Vedam Design: Engineering Solutions - Gas Ships
Vedam Design: Engineering Solutions - Gas ShipsVedam Design: Engineering Solutions - Gas Ships
Vedam Design: Engineering Solutions - Gas Ships
Vedam design & Techincal Consultancy Pvt Ltd.
 
Site Visits 6.5
Site Visits 6.5Site Visits 6.5
Site Visits 6.5
Ramiz Siddiq
 
DSD-INT 2014 - Symposium Next Generation Hydro Software (NGHS) - How to set u...
DSD-INT 2014 - Symposium Next Generation Hydro Software (NGHS) - How to set u...DSD-INT 2014 - Symposium Next Generation Hydro Software (NGHS) - How to set u...
DSD-INT 2014 - Symposium Next Generation Hydro Software (NGHS) - How to set u...
Deltares
 
Presentation
PresentationPresentation
Presentation
Krm Chari
 
Mitigtion Plan Presentation
Mitigtion Plan PresentationMitigtion Plan Presentation
Mitigtion Plan Presentation
U. Mohammed Ommer Sharieff, MBA, PMP, RMP
 
Retirement - short
Retirement - shortRetirement - short
Retirement - short
Henry Saffron
 

What's hot (6)

Vedam Design: Engineering Solutions - Gas Ships
Vedam Design: Engineering Solutions - Gas ShipsVedam Design: Engineering Solutions - Gas Ships
Vedam Design: Engineering Solutions - Gas Ships
 
Site Visits 6.5
Site Visits 6.5Site Visits 6.5
Site Visits 6.5
 
DSD-INT 2014 - Symposium Next Generation Hydro Software (NGHS) - How to set u...
DSD-INT 2014 - Symposium Next Generation Hydro Software (NGHS) - How to set u...DSD-INT 2014 - Symposium Next Generation Hydro Software (NGHS) - How to set u...
DSD-INT 2014 - Symposium Next Generation Hydro Software (NGHS) - How to set u...
 
Presentation
PresentationPresentation
Presentation
 
Mitigtion Plan Presentation
Mitigtion Plan PresentationMitigtion Plan Presentation
Mitigtion Plan Presentation
 
Retirement - short
Retirement - shortRetirement - short
Retirement - short
 

Similar to May 2014 Construction Update PCAPP EDS

PCAPP Update 30 April 2014
PCAPP Update 30 April 2014PCAPP Update 30 April 2014
PCAPP Update 25 June 2014
PCAPP Update 25 June 2014PCAPP Update 25 June 2014
Mvcv v10
Mvcv v10Mvcv v10
Mvcv v10
Michael Vaux
 
" Design of Flexible Pavement "
" Design of Flexible Pavement "" Design of Flexible Pavement "
" Design of Flexible Pavement "
Nishant Pandey
 
final year presentation revised
final year presentation revisedfinal year presentation revised
final year presentation revised
Engr Anas Ahmed Abedi
 
M.s. resume 290817
M.s. resume 290817M.s. resume 290817
M.s. resume 290817
Mohamad Safarudin
 
Ian_Rowell_Resume_June_2015
Ian_Rowell_Resume_June_2015Ian_Rowell_Resume_June_2015
Ian_Rowell_Resume_June_2015
Ian Rowell
 
Manish Ray - CV
Manish Ray - CVManish Ray - CV
Manish Ray - CV
Manish Ray
 
Kalorama Community Meeting (July 17, 2014)
Kalorama Community Meeting (July 17, 2014)Kalorama Community Meeting (July 17, 2014)
Kalorama Community Meeting (July 17, 2014)
DC Department of General Services
 
M.s. resume 150316
M.s. resume 150316M.s. resume 150316
M.s. resume 150316
Mohamad Safarudin
 
PCAPP Update 28 May 2014
PCAPP Update 28 May 2014PCAPP Update 28 May 2014
EIA Report
EIA ReportEIA Report
EIA Report
Priyanka Singh
 
Rahman cv
Rahman cvRahman cv
Rahman cv
Muhammad rahman
 
Final report
Final reportFinal report
Final report
Anushka Perera
 
Mark Deskin - Resume_BR_0816
Mark Deskin - Resume_BR_0816Mark Deskin - Resume_BR_0816
Mark Deskin - Resume_BR_0816
William Deskin
 
CV DAVE BEVERIDGE 12.04.15
CV DAVE BEVERIDGE 12.04.15CV DAVE BEVERIDGE 12.04.15
CV DAVE BEVERIDGE 12.04.15
Dave Beveridge
 
Presentation regarding the city development and hygienic environment.pptx
Presentation regarding the city development and hygienic environment.pptxPresentation regarding the city development and hygienic environment.pptx
Presentation regarding the city development and hygienic environment.pptx
NaziaBashar
 
Leading Naval Architectural Firm Leverages 3D to Solve Large Scale Problems
Leading Naval Architectural Firm Leverages 3D to Solve Large Scale ProblemsLeading Naval Architectural Firm Leverages 3D to Solve Large Scale Problems
Leading Naval Architectural Firm Leverages 3D to Solve Large Scale Problems
Jake Rosenbaum
 
Resume Nazrul Mazdi Mokhtar - Piping Designer
Resume Nazrul Mazdi Mokhtar - Piping DesignerResume Nazrul Mazdi Mokhtar - Piping Designer
Resume Nazrul Mazdi Mokhtar - Piping Designer
Nazrul Mokhtar
 
Jared Kasper Resume
Jared Kasper ResumeJared Kasper Resume
Jared Kasper Resume
Jared Kasper
 

Similar to May 2014 Construction Update PCAPP EDS (20)

PCAPP Update 30 April 2014
PCAPP Update 30 April 2014PCAPP Update 30 April 2014
PCAPP Update 30 April 2014
 
PCAPP Update 25 June 2014
PCAPP Update 25 June 2014PCAPP Update 25 June 2014
PCAPP Update 25 June 2014
 
Mvcv v10
Mvcv v10Mvcv v10
Mvcv v10
 
" Design of Flexible Pavement "
" Design of Flexible Pavement "" Design of Flexible Pavement "
" Design of Flexible Pavement "
 
final year presentation revised
final year presentation revisedfinal year presentation revised
final year presentation revised
 
M.s. resume 290817
M.s. resume 290817M.s. resume 290817
M.s. resume 290817
 
Ian_Rowell_Resume_June_2015
Ian_Rowell_Resume_June_2015Ian_Rowell_Resume_June_2015
Ian_Rowell_Resume_June_2015
 
Manish Ray - CV
Manish Ray - CVManish Ray - CV
Manish Ray - CV
 
Kalorama Community Meeting (July 17, 2014)
Kalorama Community Meeting (July 17, 2014)Kalorama Community Meeting (July 17, 2014)
Kalorama Community Meeting (July 17, 2014)
 
M.s. resume 150316
M.s. resume 150316M.s. resume 150316
M.s. resume 150316
 
PCAPP Update 28 May 2014
PCAPP Update 28 May 2014PCAPP Update 28 May 2014
PCAPP Update 28 May 2014
 
EIA Report
EIA ReportEIA Report
EIA Report
 
Rahman cv
Rahman cvRahman cv
Rahman cv
 
Final report
Final reportFinal report
Final report
 
Mark Deskin - Resume_BR_0816
Mark Deskin - Resume_BR_0816Mark Deskin - Resume_BR_0816
Mark Deskin - Resume_BR_0816
 
CV DAVE BEVERIDGE 12.04.15
CV DAVE BEVERIDGE 12.04.15CV DAVE BEVERIDGE 12.04.15
CV DAVE BEVERIDGE 12.04.15
 
Presentation regarding the city development and hygienic environment.pptx
Presentation regarding the city development and hygienic environment.pptxPresentation regarding the city development and hygienic environment.pptx
Presentation regarding the city development and hygienic environment.pptx
 
Leading Naval Architectural Firm Leverages 3D to Solve Large Scale Problems
Leading Naval Architectural Firm Leverages 3D to Solve Large Scale ProblemsLeading Naval Architectural Firm Leverages 3D to Solve Large Scale Problems
Leading Naval Architectural Firm Leverages 3D to Solve Large Scale Problems
 
Resume Nazrul Mazdi Mokhtar - Piping Designer
Resume Nazrul Mazdi Mokhtar - Piping DesignerResume Nazrul Mazdi Mokhtar - Piping Designer
Resume Nazrul Mazdi Mokhtar - Piping Designer
 
Jared Kasper Resume
Jared Kasper ResumeJared Kasper Resume
Jared Kasper Resume
 

More from Program Executive Office, Assembled Chemical Weapons Alternatives (PEO ACWA)

CAC/CDCAB Vent Recommendation 5 March 2013
CAC/CDCAB Vent Recommendation 5 March 2013CAC/CDCAB Vent Recommendation 5 March 2013
Secondary Waste Working Group 12 March 2014
Secondary Waste Working Group 12 March 2014Secondary Waste Working Group 12 March 2014
Blue Grass Chemical Agent-Destruction Pilot Plant Quarterly Update March 12...
Blue Grass Chemical Agent-Destruction Pilot Plant Quarterly Update March 12...Blue Grass Chemical Agent-Destruction Pilot Plant Quarterly Update March 12...
Blue Grass Chemical Agent-Destruction Pilot Plant Quarterly Update March 12...
Program Executive Office, Assembled Chemical Weapons Alternatives (PEO ACWA)
 
Chemical Destruction Citizens' Advisory Board Working Group Update 12 March 2013
Chemical Destruction Citizens' Advisory Board Working Group Update 12 March 2013Chemical Destruction Citizens' Advisory Board Working Group Update 12 March 2013
Chemical Destruction Citizens' Advisory Board Working Group Update 12 March 2013
Program Executive Office, Assembled Chemical Weapons Alternatives (PEO ACWA)
 
Blue Grass Chemical Activity M55 Rocket Separation Operation Update 11 June ...
Blue Grass Chemical Activity  M55 Rocket Separation Operation Update 11 June ...Blue Grass Chemical Activity  M55 Rocket Separation Operation Update 11 June ...
Blue Grass Chemical Activity M55 Rocket Separation Operation Update 11 June ...
Program Executive Office, Assembled Chemical Weapons Alternatives (PEO ACWA)
 
Blue Grass Chemical Agent-Destruction Pilot Plant Quarterly Update June 11,...
Blue Grass Chemical Agent-Destruction Pilot Plant Quarterly Update June 11,...Blue Grass Chemical Agent-Destruction Pilot Plant Quarterly Update June 11,...
Blue Grass Chemical Agent-Destruction Pilot Plant Quarterly Update June 11,...
Program Executive Office, Assembled Chemical Weapons Alternatives (PEO ACWA)
 
June '13 cdcab
June '13 cdcabJune '13 cdcab
M55 Rocket Separation Operation 11 Dec 2013
M55 Rocket Separation Operation 11 Dec 2013M55 Rocket Separation Operation 11 Dec 2013
2015 ACWA Funding 11 June 2014
2015 ACWA Funding 11 June 20142015 ACWA Funding 11 June 2014
Implementation of Explosive Destruction Technology for Mustard Projectiles ...
Implementation of Explosive Destruction Technology for Mustard Projectiles ...Implementation of Explosive Destruction Technology for Mustard Projectiles ...
Implementation of Explosive Destruction Technology for Mustard Projectiles ...
Program Executive Office, Assembled Chemical Weapons Alternatives (PEO ACWA)
 
Implementation of Explosive Destruction Technology for Mustard Projectiles ...
Implementation of Explosive Destruction Technology for Mustard Projectiles ...Implementation of Explosive Destruction Technology for Mustard Projectiles ...
Implementation of Explosive Destruction Technology for Mustard Projectiles ...
Program Executive Office, Assembled Chemical Weapons Alternatives (PEO ACWA)
 
EDT Involvement History of the Citizens' Advisory Commission/Citizens' Adviso...
EDT Involvement History of the Citizens' Advisory Commission/Citizens' Adviso...EDT Involvement History of the Citizens' Advisory Commission/Citizens' Adviso...
EDT Involvement History of the Citizens' Advisory Commission/Citizens' Adviso...
Program Executive Office, Assembled Chemical Weapons Alternatives (PEO ACWA)
 
Explosive Destruction Working Group Update 11 June 2014
Explosive Destruction Working Group Update 11 June 2014Explosive Destruction Working Group Update 11 June 2014
Explosive Destruction Working Group Update 11 June 2014
Program Executive Office, Assembled Chemical Weapons Alternatives (PEO ACWA)
 
BGCAPP Year in Review Dec. 11, 2013
BGCAPP Year in Review Dec. 11, 2013BGCAPP Year in Review Dec. 11, 2013
BGCAPP Year in Review Dec. 11, 2012
BGCAPP Year in Review Dec. 11, 2012BGCAPP Year in Review Dec. 11, 2012
Economic Development Working Group 11 September 2013
Economic Development Working Group 11 September 2013Economic Development Working Group 11 September 2013
Economic Development Working Group 11 September 2013
Program Executive Office, Assembled Chemical Weapons Alternatives (PEO ACWA)
 
Chemical Weapons Convention Update 13 June 2012
Chemical Weapons Convention Update 13 June 2012Chemical Weapons Convention Update 13 June 2012
OPCW’s 18th Conference of States Parties to the Chemical Weapons Convention
OPCW’s 18th Conference of States Parties to the Chemical Weapons ConventionOPCW’s 18th Conference of States Parties to the Chemical Weapons Convention
OPCW’s 18th Conference of States Parties to the Chemical Weapons Convention
Program Executive Office, Assembled Chemical Weapons Alternatives (PEO ACWA)
 
CDCAB Working Group Updates 11 December 2012
CDCAB Working Group Updates 11 December 2012CDCAB Working Group Updates 11 December 2012
BGCAPP EDT EA CDCAB NEPA and Army Decision Process 23 October 2013
BGCAPP EDT EA CDCAB NEPA and Army Decision Process 23 October 2013BGCAPP EDT EA CDCAB NEPA and Army Decision Process 23 October 2013
BGCAPP EDT EA CDCAB NEPA and Army Decision Process 23 October 2013
Program Executive Office, Assembled Chemical Weapons Alternatives (PEO ACWA)
 

More from Program Executive Office, Assembled Chemical Weapons Alternatives (PEO ACWA) (20)

CAC/CDCAB Vent Recommendation 5 March 2013
CAC/CDCAB Vent Recommendation 5 March 2013CAC/CDCAB Vent Recommendation 5 March 2013
CAC/CDCAB Vent Recommendation 5 March 2013
 
Secondary Waste Working Group 12 March 2014
Secondary Waste Working Group 12 March 2014Secondary Waste Working Group 12 March 2014
Secondary Waste Working Group 12 March 2014
 
Blue Grass Chemical Agent-Destruction Pilot Plant Quarterly Update March 12...
Blue Grass Chemical Agent-Destruction Pilot Plant Quarterly Update March 12...Blue Grass Chemical Agent-Destruction Pilot Plant Quarterly Update March 12...
Blue Grass Chemical Agent-Destruction Pilot Plant Quarterly Update March 12...
 
Chemical Destruction Citizens' Advisory Board Working Group Update 12 March 2013
Chemical Destruction Citizens' Advisory Board Working Group Update 12 March 2013Chemical Destruction Citizens' Advisory Board Working Group Update 12 March 2013
Chemical Destruction Citizens' Advisory Board Working Group Update 12 March 2013
 
Blue Grass Chemical Activity M55 Rocket Separation Operation Update 11 June ...
Blue Grass Chemical Activity  M55 Rocket Separation Operation Update 11 June ...Blue Grass Chemical Activity  M55 Rocket Separation Operation Update 11 June ...
Blue Grass Chemical Activity M55 Rocket Separation Operation Update 11 June ...
 
Blue Grass Chemical Agent-Destruction Pilot Plant Quarterly Update June 11,...
Blue Grass Chemical Agent-Destruction Pilot Plant Quarterly Update June 11,...Blue Grass Chemical Agent-Destruction Pilot Plant Quarterly Update June 11,...
Blue Grass Chemical Agent-Destruction Pilot Plant Quarterly Update June 11,...
 
June '13 cdcab
June '13 cdcabJune '13 cdcab
June '13 cdcab
 
M55 Rocket Separation Operation 11 Dec 2013
M55 Rocket Separation Operation 11 Dec 2013M55 Rocket Separation Operation 11 Dec 2013
M55 Rocket Separation Operation 11 Dec 2013
 
2015 ACWA Funding 11 June 2014
2015 ACWA Funding 11 June 20142015 ACWA Funding 11 June 2014
2015 ACWA Funding 11 June 2014
 
Implementation of Explosive Destruction Technology for Mustard Projectiles ...
Implementation of Explosive Destruction Technology for Mustard Projectiles ...Implementation of Explosive Destruction Technology for Mustard Projectiles ...
Implementation of Explosive Destruction Technology for Mustard Projectiles ...
 
Implementation of Explosive Destruction Technology for Mustard Projectiles ...
Implementation of Explosive Destruction Technology for Mustard Projectiles ...Implementation of Explosive Destruction Technology for Mustard Projectiles ...
Implementation of Explosive Destruction Technology for Mustard Projectiles ...
 
EDT Involvement History of the Citizens' Advisory Commission/Citizens' Adviso...
EDT Involvement History of the Citizens' Advisory Commission/Citizens' Adviso...EDT Involvement History of the Citizens' Advisory Commission/Citizens' Adviso...
EDT Involvement History of the Citizens' Advisory Commission/Citizens' Adviso...
 
Explosive Destruction Working Group Update 11 June 2014
Explosive Destruction Working Group Update 11 June 2014Explosive Destruction Working Group Update 11 June 2014
Explosive Destruction Working Group Update 11 June 2014
 
BGCAPP Year in Review Dec. 11, 2013
BGCAPP Year in Review Dec. 11, 2013BGCAPP Year in Review Dec. 11, 2013
BGCAPP Year in Review Dec. 11, 2013
 
BGCAPP Year in Review Dec. 11, 2012
BGCAPP Year in Review Dec. 11, 2012BGCAPP Year in Review Dec. 11, 2012
BGCAPP Year in Review Dec. 11, 2012
 
Economic Development Working Group 11 September 2013
Economic Development Working Group 11 September 2013Economic Development Working Group 11 September 2013
Economic Development Working Group 11 September 2013
 
Chemical Weapons Convention Update 13 June 2012
Chemical Weapons Convention Update 13 June 2012Chemical Weapons Convention Update 13 June 2012
Chemical Weapons Convention Update 13 June 2012
 
OPCW’s 18th Conference of States Parties to the Chemical Weapons Convention
OPCW’s 18th Conference of States Parties to the Chemical Weapons ConventionOPCW’s 18th Conference of States Parties to the Chemical Weapons Convention
OPCW’s 18th Conference of States Parties to the Chemical Weapons Convention
 
CDCAB Working Group Updates 11 December 2012
CDCAB Working Group Updates 11 December 2012CDCAB Working Group Updates 11 December 2012
CDCAB Working Group Updates 11 December 2012
 
BGCAPP EDT EA CDCAB NEPA and Army Decision Process 23 October 2013
BGCAPP EDT EA CDCAB NEPA and Army Decision Process 23 October 2013BGCAPP EDT EA CDCAB NEPA and Army Decision Process 23 October 2013
BGCAPP EDT EA CDCAB NEPA and Army Decision Process 23 October 2013
 

Recently uploaded

How To Cultivate Community Affinity Throughout The Generosity Journey
How To Cultivate Community Affinity Throughout The Generosity JourneyHow To Cultivate Community Affinity Throughout The Generosity Journey
How To Cultivate Community Affinity Throughout The Generosity Journey
Aggregage
 
Combined Illegal, Unregulated and Unreported (IUU) Vessel List.
Combined Illegal, Unregulated and Unreported (IUU) Vessel List.Combined Illegal, Unregulated and Unreported (IUU) Vessel List.
Combined Illegal, Unregulated and Unreported (IUU) Vessel List.
Christina Parmionova
 
Bharat Mata - History of Indian culture.pdf
Bharat Mata - History of Indian culture.pdfBharat Mata - History of Indian culture.pdf
Bharat Mata - History of Indian culture.pdf
Bharat Mata
 
Indira awas yojana housing scheme renamed as PMAY
Indira awas yojana housing scheme renamed as PMAYIndira awas yojana housing scheme renamed as PMAY
Indira awas yojana housing scheme renamed as PMAY
narinav14
 
Researching the client.pptxsxssssssssssssssssssssss
Researching the client.pptxsxssssssssssssssssssssssResearching the client.pptxsxssssssssssssssssssssss
Researching the client.pptxsxssssssssssssssssssssss
DanielOliver74
 
China Politics social economic political
China Politics social economic politicalChina Politics social economic political
China Politics social economic political
ajatjamwal123
 
World Food Safety Day 2024- Communication-toolkit.
World Food Safety Day 2024- Communication-toolkit.World Food Safety Day 2024- Communication-toolkit.
World Food Safety Day 2024- Communication-toolkit.
Christina Parmionova
 
原版制作(Hope毕业证书)利物浦霍普大学毕业证文凭证书一模一样
原版制作(Hope毕业证书)利物浦霍普大学毕业证文凭证书一模一样原版制作(Hope毕业证书)利物浦霍普大学毕业证文凭证书一模一样
原版制作(Hope毕业证书)利物浦霍普大学毕业证文凭证书一模一样
ii2sh2v
 
加急办理华威大学毕业证硕士文凭证书原版一模一样
加急办理华威大学毕业证硕士文凭证书原版一模一样加急办理华威大学毕业证硕士文凭证书原版一模一样
加急办理华威大学毕业证硕士文凭证书原版一模一样
uu1psyf6
 
IEA World Energy Investment June 2024- Statistics
IEA World Energy Investment June 2024- StatisticsIEA World Energy Investment June 2024- Statistics
IEA World Energy Investment June 2024- Statistics
Energy for One World
 
原版制作(英国Southampton毕业证书)南安普顿大学毕业证录取通知书一模一样
原版制作(英国Southampton毕业证书)南安普顿大学毕业证录取通知书一模一样原版制作(英国Southampton毕业证书)南安普顿大学毕业证录取通知书一模一样
原版制作(英国Southampton毕业证书)南安普顿大学毕业证录取通知书一模一样
3woawyyl
 
PPT Item # 7 - 231 Encino Avenue (sign. review)
PPT Item # 7 - 231 Encino Avenue (sign. review)PPT Item # 7 - 231 Encino Avenue (sign. review)
PPT Item # 7 - 231 Encino Avenue (sign. review)
ahcitycouncil
 
G7 Apulia Leaders Communique, 14th June 2024
G7 Apulia Leaders Communique, 14th June 2024G7 Apulia Leaders Communique, 14th June 2024
G7 Apulia Leaders Communique, 14th June 2024
Energy for One World
 
Awaken new depths - World Ocean Day 2024, June 8th.
Awaken new depths - World Ocean Day 2024, June 8th.Awaken new depths - World Ocean Day 2024, June 8th.
Awaken new depths - World Ocean Day 2024, June 8th.
Christina Parmionova
 
一比一原版(theauckland毕业证书)新西兰奥克兰大学毕业证成绩单如何办理
一比一原版(theauckland毕业证书)新西兰奥克兰大学毕业证成绩单如何办理一比一原版(theauckland毕业证书)新西兰奥克兰大学毕业证成绩单如何办理
一比一原版(theauckland毕业证书)新西兰奥克兰大学毕业证成绩单如何办理
odmqk
 
2024: The FAR - Federal Acquisition Regulations, Part 41
2024: The FAR - Federal Acquisition Regulations, Part 412024: The FAR - Federal Acquisition Regulations, Part 41
2024: The FAR - Federal Acquisition Regulations, Part 41
JSchaus & Associates
 
Bangladesh studies presentation on Liberation War 1971 Indepence-of-Banglades...
Bangladesh studies presentation on Liberation War 1971 Indepence-of-Banglades...Bangladesh studies presentation on Liberation War 1971 Indepence-of-Banglades...
Bangladesh studies presentation on Liberation War 1971 Indepence-of-Banglades...
ssuser05e8f3
 
RFP for Reno's Community Assistance Center
RFP for Reno's Community Assistance CenterRFP for Reno's Community Assistance Center
RFP for Reno's Community Assistance Center
This Is Reno
 
Item #s 8&9 -- Demolition Code Amendment
Item #s 8&9 -- Demolition Code AmendmentItem #s 8&9 -- Demolition Code Amendment
Item #s 8&9 -- Demolition Code Amendment
ahcitycouncil
 
PPT Item # 4 - 434 College Blvd. (sign. review)
PPT Item # 4 - 434 College Blvd. (sign. review)PPT Item # 4 - 434 College Blvd. (sign. review)
PPT Item # 4 - 434 College Blvd. (sign. review)
ahcitycouncil
 

Recently uploaded (20)

How To Cultivate Community Affinity Throughout The Generosity Journey
How To Cultivate Community Affinity Throughout The Generosity JourneyHow To Cultivate Community Affinity Throughout The Generosity Journey
How To Cultivate Community Affinity Throughout The Generosity Journey
 
Combined Illegal, Unregulated and Unreported (IUU) Vessel List.
Combined Illegal, Unregulated and Unreported (IUU) Vessel List.Combined Illegal, Unregulated and Unreported (IUU) Vessel List.
Combined Illegal, Unregulated and Unreported (IUU) Vessel List.
 
Bharat Mata - History of Indian culture.pdf
Bharat Mata - History of Indian culture.pdfBharat Mata - History of Indian culture.pdf
Bharat Mata - History of Indian culture.pdf
 
Indira awas yojana housing scheme renamed as PMAY
Indira awas yojana housing scheme renamed as PMAYIndira awas yojana housing scheme renamed as PMAY
Indira awas yojana housing scheme renamed as PMAY
 
Researching the client.pptxsxssssssssssssssssssssss
Researching the client.pptxsxssssssssssssssssssssssResearching the client.pptxsxssssssssssssssssssssss
Researching the client.pptxsxssssssssssssssssssssss
 
China Politics social economic political
China Politics social economic politicalChina Politics social economic political
China Politics social economic political
 
World Food Safety Day 2024- Communication-toolkit.
World Food Safety Day 2024- Communication-toolkit.World Food Safety Day 2024- Communication-toolkit.
World Food Safety Day 2024- Communication-toolkit.
 
原版制作(Hope毕业证书)利物浦霍普大学毕业证文凭证书一模一样
原版制作(Hope毕业证书)利物浦霍普大学毕业证文凭证书一模一样原版制作(Hope毕业证书)利物浦霍普大学毕业证文凭证书一模一样
原版制作(Hope毕业证书)利物浦霍普大学毕业证文凭证书一模一样
 
加急办理华威大学毕业证硕士文凭证书原版一模一样
加急办理华威大学毕业证硕士文凭证书原版一模一样加急办理华威大学毕业证硕士文凭证书原版一模一样
加急办理华威大学毕业证硕士文凭证书原版一模一样
 
IEA World Energy Investment June 2024- Statistics
IEA World Energy Investment June 2024- StatisticsIEA World Energy Investment June 2024- Statistics
IEA World Energy Investment June 2024- Statistics
 
原版制作(英国Southampton毕业证书)南安普顿大学毕业证录取通知书一模一样
原版制作(英国Southampton毕业证书)南安普顿大学毕业证录取通知书一模一样原版制作(英国Southampton毕业证书)南安普顿大学毕业证录取通知书一模一样
原版制作(英国Southampton毕业证书)南安普顿大学毕业证录取通知书一模一样
 
PPT Item # 7 - 231 Encino Avenue (sign. review)
PPT Item # 7 - 231 Encino Avenue (sign. review)PPT Item # 7 - 231 Encino Avenue (sign. review)
PPT Item # 7 - 231 Encino Avenue (sign. review)
 
G7 Apulia Leaders Communique, 14th June 2024
G7 Apulia Leaders Communique, 14th June 2024G7 Apulia Leaders Communique, 14th June 2024
G7 Apulia Leaders Communique, 14th June 2024
 
Awaken new depths - World Ocean Day 2024, June 8th.
Awaken new depths - World Ocean Day 2024, June 8th.Awaken new depths - World Ocean Day 2024, June 8th.
Awaken new depths - World Ocean Day 2024, June 8th.
 
一比一原版(theauckland毕业证书)新西兰奥克兰大学毕业证成绩单如何办理
一比一原版(theauckland毕业证书)新西兰奥克兰大学毕业证成绩单如何办理一比一原版(theauckland毕业证书)新西兰奥克兰大学毕业证成绩单如何办理
一比一原版(theauckland毕业证书)新西兰奥克兰大学毕业证成绩单如何办理
 
2024: The FAR - Federal Acquisition Regulations, Part 41
2024: The FAR - Federal Acquisition Regulations, Part 412024: The FAR - Federal Acquisition Regulations, Part 41
2024: The FAR - Federal Acquisition Regulations, Part 41
 
Bangladesh studies presentation on Liberation War 1971 Indepence-of-Banglades...
Bangladesh studies presentation on Liberation War 1971 Indepence-of-Banglades...Bangladesh studies presentation on Liberation War 1971 Indepence-of-Banglades...
Bangladesh studies presentation on Liberation War 1971 Indepence-of-Banglades...
 
RFP for Reno's Community Assistance Center
RFP for Reno's Community Assistance CenterRFP for Reno's Community Assistance Center
RFP for Reno's Community Assistance Center
 
Item #s 8&9 -- Demolition Code Amendment
Item #s 8&9 -- Demolition Code AmendmentItem #s 8&9 -- Demolition Code Amendment
Item #s 8&9 -- Demolition Code Amendment
 
PPT Item # 4 - 434 College Blvd. (sign. review)
PPT Item # 4 - 434 College Blvd. (sign. review)PPT Item # 4 - 434 College Blvd. (sign. review)
PPT Item # 4 - 434 College Blvd. (sign. review)
 

May 2014 Construction Update PCAPP EDS

  • 5. Change House Environmental Enclosure #1 Environmental Enclosure #3 Laboratory PCAPP EDS Site Overview 5
  • 6. PCAPP EDS Safety As of April 30, the PCAPP EDS project staff has accomplished:  20 Safe Work Days  2,497 Safe Work Hours 6 Workers smooth concrete on May 8 after the first concrete slab pour for Environmental Enclosure #1.
  • 7. PCAPP EDS Construction Staffing –26 employees  Construction  Workers: 6 –Subcontractor personnel – 20 A worker sets screws for the forms in preparation for the concrete slab pour for Environmental Enclosure #2 7
  • 8. NOT STARTED IN PROGRESS (POTENTIAL ISSUES) IN PROGRESS (NO ISSUES) COMPLETE Key Milestone DESIGN START (DEC 2013) SITE DESIGN COMPLETE (MAR 2014) CONSTRUCTION STARTS (27 MAR 2014) CONSTRUCTION COMPLETE (OCT 2014) E-DAY – EDS START OF AGENT OPERATIONS (OCT 2014) CONSTRUCTION CONTRACT AWARD (NOV 2013) PEO ACWA PROGRAMMATIC DECISION TO SELECT EDS TECHNOLOGY (APR 2013) PCAPP EDS Schedule (JPME-P Working Schedule) CONCRETE POURS BEGIN (17 APR 2014) MODULES (COMMAND POST, CHANGE HOUSE, TREATY TRAILER, ETC.) BEGIN TO ARRIVE (MAY 2014) MILITARY FABRIC STRUCTURES FOR EDS ENVIRONMENTAL ENCLOSURES ARRIVE (JUN 2014) ARRIVAL OF FIRST EDS UNIT (AUGUST 2014) 8
  • 9. PCAPP EDS Permitting Progress NOT STARTED IN PROGRESS (POTENTIAL ISSUES) IN PROGRESS (NO ISSUES) COMPLETE Key Milestone CLASS III PERMIT MODIFICATION SUBMITTED TO CDPHE (24 OCT 2013) STATE APPROVAL OF TEMPORARY AUTHORIZATION FOR CONSTRUCTION (7 MAR 2014) SITE CONSTRUCTION START (27MAR 2014) APPROVAL OF CLASS III MODIFICATION FOR OPERATIONS (SEP 2014) E-DAY – EDS START OF AGENT OPERATIONS (OCT 2014) PCD RCRA PERMIT RENEWED (JAN 2014) SUBMIT CERTIFICATE OF DESIGNATION (CD) (DEC 2013) PEO ACWA PROGRAMMATIC DECISION TO SELECT EDS TECHNOLOGY (APR 2013) APPROVAL OF CD FOR OPERATIONS (OCT 2014) COUNTY APPROVAL OF TEMPORARY AUTHORIZATION FOR CONSTRUCTION (26 MAR 2014) RECORD OF ENVIRONMENTAL CONSIDERATION (DEC 2013) 9
  • 10. Site Progress 10 Processing dirt, the job of mixing the fill with water under the weight of heavy equipment, makes for better compaction when it’s later moved into the enclosures as a base for the slabs that will be poured.
  • 11. Site Progress 11 Measure twice, dig once. A worker confirms the depth of the trench being carved out. This for the pipes that will be part of the fire line that will serve the EDS site when complete.
  • 12. Questions? 12 Acting Principal Deputy Assistant Secretary of Defense Dr. A. Tom Hopkins (third from left), Program Executive Officer ACWA Conrad Whyne (second from left) and PCAPP Project Manager Rick Holmes, listen to Jake Torres explain the munition process in the Vapor Containment Room.