BPCL review meeting ppt giving an overview of all the works related to oil and gas industry. Explain about all the aspects of oil and gas sectors from extracting crude oil from sea also known as fossil fuel to how it's refined to serve different sectors of energy. It also explains about their current progress quarterly wise. There are four quarters in a year and BPCL manager, Geographical Area Head provide all the details of energy sector for headquarters reporting.
BPCL review meeting ppt giving an overview of all the works related to oil and gas industry. Explain about all the aspects of oil and gas sectors from extracting crude oil from sea also known as fossil fuel to how it's refined to serve different sectors of energy. It also explains about their current progress quarterly wise. There are four quarters in a year and BPCL manager, Geographical Area Head provide all the details of energy sector for headquarters reporting.
Project Management Challenges in an Effluent Treatment Plant Construction PRABHASH GOKARN
Tata Steel operates India’s largest chromite mines at the Sukinda Valley in Odisha producing chrome ore which is subsequently converted it to Ferro Chrome and sold to customers across the world. A large quantity of water, generated during mining and due to rainfall, needs to be handled during the mining operations. Chrome Ore mainly contains tri-valent Chromic oxide and a very small fraction of hexavalent di-chromate. Water coming in contact with chromium ore preferentially leaches out soluble hexavalent chromium from the ore body, as a result, water from the mine contains 0.2 – 4 mg/l of hexavalent chromium against a safe limit of 0.005 mg/l for human consumption; requiring all water to be treated before its release from the mines. Thus, Tata Steel is setting up an effluent plant at Sukinda with a capacity of 108 million litres/day; perhaps one of the largest in the region; which will be complete by end June 2015.
Saudi Arabia stands as a titan in the global energy landscape, renowned for its abundant oil and gas resources. It's the largest exporter of petroleum and holds some of the world's most significant reserves. Let's delve into the top 10 oil and gas projects shaping Saudi Arabia's energy future in 2024.
Project Management Challenges in an Effluent Treatment Plant Construction PRABHASH GOKARN
Tata Steel operates India’s largest chromite mines at the Sukinda Valley in Odisha producing chrome ore which is subsequently converted it to Ferro Chrome and sold to customers across the world. A large quantity of water, generated during mining and due to rainfall, needs to be handled during the mining operations. Chrome Ore mainly contains tri-valent Chromic oxide and a very small fraction of hexavalent di-chromate. Water coming in contact with chromium ore preferentially leaches out soluble hexavalent chromium from the ore body, as a result, water from the mine contains 0.2 – 4 mg/l of hexavalent chromium against a safe limit of 0.005 mg/l for human consumption; requiring all water to be treated before its release from the mines. Thus, Tata Steel is setting up an effluent plant at Sukinda with a capacity of 108 million litres/day; perhaps one of the largest in the region; which will be complete by end June 2015.
Saudi Arabia stands as a titan in the global energy landscape, renowned for its abundant oil and gas resources. It's the largest exporter of petroleum and holds some of the world's most significant reserves. Let's delve into the top 10 oil and gas projects shaping Saudi Arabia's energy future in 2024.
Student information management system project report ii.pdfKamal Acharya
Our project explains about the student management. This project mainly explains the various actions related to student details. This project shows some ease in adding, editing and deleting the student details. It also provides a less time consuming process for viewing, adding, editing and deleting the marks of the students.
Welcome to WIPAC Monthly the magazine brought to you by the LinkedIn Group Water Industry Process Automation & Control.
In this month's edition, along with this month's industry news to celebrate the 13 years since the group was created we have articles including
A case study of the used of Advanced Process Control at the Wastewater Treatment works at Lleida in Spain
A look back on an article on smart wastewater networks in order to see how the industry has measured up in the interim around the adoption of Digital Transformation in the Water Industry.
Water scarcity is the lack of fresh water resources to meet the standard water demand. There are two type of water scarcity. One is physical. The other is economic water scarcity.
Overview of the fundamental roles in Hydropower generation and the components involved in wider Electrical Engineering.
This paper presents the design and construction of hydroelectric dams from the hydrologist’s survey of the valley before construction, all aspects and involved disciplines, fluid dynamics, structural engineering, generation and mains frequency regulation to the very transmission of power through the network in the United Kingdom.
Author: Robbie Edward Sayers
Collaborators and co editors: Charlie Sims and Connor Healey.
(C) 2024 Robbie E. Sayers
Cosmetic shop management system project report.pdfKamal Acharya
Buying new cosmetic products is difficult. It can even be scary for those who have sensitive skin and are prone to skin trouble. The information needed to alleviate this problem is on the back of each product, but it's thought to interpret those ingredient lists unless you have a background in chemistry.
Instead of buying and hoping for the best, we can use data science to help us predict which products may be good fits for us. It includes various function programs to do the above mentioned tasks.
Data file handling has been effectively used in the program.
The automated cosmetic shop management system should deal with the automation of general workflow and administration process of the shop. The main processes of the system focus on customer's request where the system is able to search the most appropriate products and deliver it to the customers. It should help the employees to quickly identify the list of cosmetic product that have reached the minimum quantity and also keep a track of expired date for each cosmetic product. It should help the employees to find the rack number in which the product is placed.It is also Faster and more efficient way.
Industrial Training at Shahjalal Fertilizer Company Limited (SFCL)MdTanvirMahtab2
This presentation is about the working procedure of Shahjalal Fertilizer Company Limited (SFCL). A Govt. owned Company of Bangladesh Chemical Industries Corporation under Ministry of Industries.
Industrial Training at Shahjalal Fertilizer Company Limited (SFCL)
Presentation regarding the city development and hygienic environment.pptx
1.
2. OCB/KPCIP/CW-03: CONSTRUCTION OF SEWERAGE
SYSTEM INCLUDING NEW SEWERAGE TREATMENT
PLANT (STP) AT:
LOT-2: CATCHMENT AREA OF RORYA STP MARDAN INCLUDING NEW
SEWAGE TREATMENT PLANT (STP) AND REQUIRED SCADA SYSTEM,
MARDAN
PROGRESS REVIEW MEETING
WSSC Mardan
Khyber Pakhtunkhwa Cities Improvement Project
Local Government Elections & Rural Development
Department
Khyber Pakhtunkhwa
16 April 2024
3. Progress Review Under KPCIP
S.No Name of the Project KPCIP/CW-03: “Construction of Sewerage System including New Sewage
Treatment Plant (STP) AT: Lot 2: Catchment Area of Rorya STP Mardan
including New Sewage Treatment Plant (STP) and required SCADA system"
1 Location MARDAN
2 Name of the Contractor M/s MATRACON-JTE (JV)
3 Name of the Consultant MinConsult & Creative Engineering Consultant (JV)
4 Total Contract Cost 8313.864 Million
5 Cost of Consultancy
6 Date of Commencement 20th
December, 2022
7 Time for Completion 1095 Days
8 Date of Completion 20th
December, 2025
9
Total Work Progress (as per Work
Schedule)
21.02% achieved VS Planned 26.91% till 31st
March, 2024
4. CATCHMENT AREA OF RORYA STP MARDAN INCLUDING NEW
SEWAGE TREATMENT PLANT (STP) AND REQUIRED SCADA
SYSTEM"
5. Friday, May 10, 2024
WSSC-KOHAT
Proposed
Sewage
Treatment Plant
Inlet
Outlet
KPCIP: Proposed Sewage Treatment Plant - Mardan
Salient Features:
Treatment Capacity: 5.8 MGD
Required Area for STP: 17 Acres
Available Area for STP: 30 Acre
Treatment Technology:
Activated Sludge Process
3D Design
6.
7. CATCHMENT AREA OF RORYA STP MARDAN INCLUDING NEW
SEWAGE TREATMENT PLANT (STP) AND REQUIRED SCADA
SYSTEM
Scope
• New sewerage system for six (6) urban UCs of Mardan (Bicket Gunj, Bari Cham,
Muslim Abad, Guli Bagh, Rorya, Hoti)
• Provision of house connections with the newly proposed sewerage network
• Construction of STP for the total generated sewage flow at the existing location
Cost (in Millions)
• PKR: 8,313.86
PROJECT
SUMMARY
9. Friday, May 10, 2024
STP Mardan
Total Sewerage Network Length (Km) = 82.5
Total No Of Manholes = 4309
Total No Of House Connection = 13030
Treatment Capacity (MGD) = 5.8
Required Area For STP (Acres) = 17
Available Area For STP (Acre) = 30
Treatment Technology: Activated Sludge Process
Power Requirement (KW) = 1002
SALIENT FEATURES
11. Friday, May 10, 2024
PACKAGE NO. KPCIP-CW-03:- CONSTRUCTION OF SEWERAGE SYSTEM INCLUDING NEW SEWAGE TREATMENT PLANT
LOT 2: CATCHMENT AREA OF RORYA STP MARDAN INCLUDING NEW SEWAGE TREATMENT PLANT (STP) AND REQUIRED SCADA
FINANCIAL PROGRESS
IPC No.
Value Claimed
(in Million)
Submitted Date
Consultant E
Approval Date
Net Payable
(Millions)
Payment Status Percentage%
Cum
Percentage%
Remarks
1 304.049670 30 Sep,2023 16-Oct-23 234.042609 Received 2.815% 2.815%
2 438,620,175 27-Nov-2023 08-Dec-23 301.107489 Received 3.622% 6.437%
3 276,562,402 29-Jan-2024 06-Feb-24 203.779706
Received
2.45% 8.89%
4 207,241,167 28-Feb-2024 12-Mar-2024 176.272419
Received
2.12% 11.01%
5
6
7
8
12. Friday, May 10, 2024
PHYSICAL WORK PROGRESS
(STP)
• Joint survey of STP area is Completed 82km.
• Lean Concrete of Pumping Station Completed
• Excavation of Air Blower Room No. 02 Completed.
• Electrical Control Room Layout Completed and Excavation is in Progress.
• Generator Room Excavation completed and Lean Poured.
• Admin Building Ground Floor Slab formwork is in Progress.
• Sub Station Building Layout Completed.
• Work Shop Layout Completed and Excavation is in Progress.
• Roads No. 01, 02, 03, 08, 09 & 10 Embankment Material Filling is in Progress.
• HDPE Pipe Laying 1000mm is in Progress
• HDPE Pipe Laying 900mm Completed
• HDPE Pipe Laying 710mm Completed.
• HDPE Pipe Laying 560mm Completed.
• HDPE Pipe laying 315mm is in Progress.
• UPVC Pipe 75mm for Electrical Cable is in Progress
• Aeration Tank # 01,02 & 03 Walls Concrete is in Progress
• South Side Boundary Wall Brick Work is in Progress.
• Primary Settling Tank #. 01, 02 & 03 Bed Concrete Completed & Walls Reinforcement in
Progress.
• Screen Chamber Bed Completed & Wall’s Steel is in Progress.
• Sludge Thickener # 01 & 02 Sand Filling is in Progress.
• Secondary Settling Tank #. 01, 02 & 03 Bed Concrete Completed.
13. Friday, May 10, 2024
STP Mardan
PHYSICAL WORK PROGRESS SEWER LINE
• Joint Survey on Sewer line is completed.
• 8km Sewer Network in UC Rorya is Completed & Guli Bagh work is in Progress.
• Street Sewer Line 519 To 529&531 To 533 & 536 To 551 (Rorya) Layout Completed.
• Street Sewer Line 519 To 529&531 To533 & 536To538 & 543 To 550(Rorya) Excavation Completed.
• Street Sewer Line 519 To 529&531 To533& 536 To 538 & 543 To 550 (Rorya) Pipe Laying Completed.
• Street Sewer Line 519 To 529 & 531 To 533 & 536 To 538 & 543 To 550(Rorya) Sand Filling
Completed.
• Street Sewer Line 519 To 529&531 To 533&536 To 538&543 To 550 (Rorya) Marking Tap Completed.
• Street Sewer Line 519 To 529&531 To 533&536 To 538&543 To 550 (Rorya) Embankment Material
Completed.
• Street Sewer Line 539 To 542 & 551 (Rorya) Excavation is in Progress.
• Street Sewer Line 539 To 542 & 551 (Rorya) Pipe Laying is in Progress.
• Street Sewer Line 539 To 542 & 551 (Rorya) Sand Filling is in Progress.
• Street Sewer Line 539 To 542 & 551 (Rorya) Marking Tap is in Progress.
• Street Sewer Line 539 To 542 & 551 (Rorya) Embankment Material is in Progress.
• Street Sewer Manholes, Chambers & House Connections Activity Steel, Formwork, & Concrete etc.
is in Progress.
• Manhole No. 195 & 194 & 193 Wall’s Concrete Completed.
• Street Sewer Line 291 (Guli Bagh) Layout Completed.
• Street Sewer Line 292 (Guli Bagh) Layout Completed.
• Street Sewer Line 291 (Guli Bagh) Excavation is in Progress.