The progress review meeting covered the status of the construction contract, safety, quality, delays, cash flow, material and manpower mobilization, and site progress. The key points were: the work progress was 8% against a baseline of 33%; safety performance was good with no reportable incidents; quality issues included honeycombing and concrete bulges; major delays included tower crane and formwork material arrival; cash flow was tracking 11Cr against a baseline of 42.4Cr; and site photographs showed ongoing concrete work across multiple towers and structures.