Rachel Howard interned at NGPL during the summer of 2015. She worked on several projects including cost estimates for pipeline modifications to make sections piggable. She also created recoating cost estimates and analyzed budget versus actual costs for previous projects. Rachel assisted other project managers with scope documents, meeting minutes, and procurement reports. Additionally, she toured NGPL facilities and gained field experience monitoring a flow reversal and compressor station modifications.
The document discusses reducing the design flows for a new WAS thickening facility at the Ashbridges Bay Treatment Plant. It finds that:
1) Historical data and operational changes mean the original 37 MLD design flow is too high.
2) Statistical analysis and mass balancing of 2012-2013 data show average sludge production is around 88,070 kg/day and the "new normal" eliminates co-thickening, reducing sludge by 23%.
3) Factors like shorter SRTs, eliminating flows from other plants, and improved operations could increase or decrease sludge by up to 10%.
4) The recommendation is to reduce the design flow to 26 MLD to thicken 5,
The document provides a mitigation plan to recover delays on a residential/commercial building project. It outlines reasons for 111 day delay including issues with design approval and utility connection. The plan increases labor, materials, and uses schedule compression techniques. It provides a zone-by-zone schedule to complete the structure by mid-September and qualifications needed for electrical work. The plan aims to recover delays and complete the project by the revised August 2017 deadline.
EPC-4 Package Status Update September 16-09-2011abughaws
The document provides a status update for a hydrocracker package project in September 2011. It outlines the project scope, contract value, schedule and progress. Key achievements include placing purchase orders for long lead equipment and static/rotating equipment. The six-month look ahead includes starting supplementary hazard and operability reviews and grounding installation. Items of interest include adopting a newer ASME code to reduce material usage and modifying an automatic depressurization system design for improved reliability.
The document provides a May 2014 construction update for the PCAPP EDS site:
- Concrete pouring began on April 17th and the first slab was poured on May 8th for Environmental Enclosure #1.
- Modules such as the command post and change house will begin arriving in May 2014.
- As of April 30th, the project had 20 safe work days and 2,497 safe work hours with a staff of 26 employees and 20 subcontractor personnel.
- The document includes schedules, permit progress, and photos of site construction activities like soil processing and trench digging.
PPT ON IMPROVING DISTRIBUTOR ETA COMPLIANCE RATE DEC.2015Joel Justice Okine
The document summarizes the parts kaizen marathon held in 2015 to improve the estimated time of arrival (ETA) compliance rate for parts distributions. The team analyzed the current 65% ETA compliance rate and set a target of 90% for 2015. Through root cause analysis, they identified issues like multiple couriers and lack of ETA knowledge. Countermeasures like using a single courier, empty bin utilization and training improved the compliance rate to 90% by September 2015. Monitoring showed reduced requisition aging. The team standardized manual forms and set a 98% target for 2016 to sustain the gains.
The document discusses Cequesta Water's Hybrid GreenFloat DAF (HGD) product, which is a modular, mobile water and wastewater treatment system housed in a standard shipping container. The HGD uses a hybrid filtration process that increases separation efficiency while reducing chemical consumption. It is well-suited for growing remote markets. The document provides an overview of Cequesta Water, the HGD's benefits compared to other systems, example applications including food processing and oil/gas, and a request for investment to advance the HGD from pilot to sales stage.
This document summarizes a validation study conducted by DNV GL comparing turbine performance data measured from a 1MW tidal turbine installed at EMEC to simulations conducted using the Tidal Bladed software. The study found that Tidal Bladed provided good predictions of steady state and dynamic turbine response as well as fatigue loads, with damage equivalent loads from simulations matching well with measured data. This increased validation of Tidal Bladed's modeling capabilities can improve confidence in the turbine design process.
The document discusses reducing the design flows for a new WAS thickening facility at the Ashbridges Bay Treatment Plant. It finds that:
1) Historical data and operational changes mean the original 37 MLD design flow is too high.
2) Statistical analysis and mass balancing of 2012-2013 data show average sludge production is around 88,070 kg/day and the "new normal" eliminates co-thickening, reducing sludge by 23%.
3) Factors like shorter SRTs, eliminating flows from other plants, and improved operations could increase or decrease sludge by up to 10%.
4) The recommendation is to reduce the design flow to 26 MLD to thicken 5,
The document provides a mitigation plan to recover delays on a residential/commercial building project. It outlines reasons for 111 day delay including issues with design approval and utility connection. The plan increases labor, materials, and uses schedule compression techniques. It provides a zone-by-zone schedule to complete the structure by mid-September and qualifications needed for electrical work. The plan aims to recover delays and complete the project by the revised August 2017 deadline.
EPC-4 Package Status Update September 16-09-2011abughaws
The document provides a status update for a hydrocracker package project in September 2011. It outlines the project scope, contract value, schedule and progress. Key achievements include placing purchase orders for long lead equipment and static/rotating equipment. The six-month look ahead includes starting supplementary hazard and operability reviews and grounding installation. Items of interest include adopting a newer ASME code to reduce material usage and modifying an automatic depressurization system design for improved reliability.
The document provides a May 2014 construction update for the PCAPP EDS site:
- Concrete pouring began on April 17th and the first slab was poured on May 8th for Environmental Enclosure #1.
- Modules such as the command post and change house will begin arriving in May 2014.
- As of April 30th, the project had 20 safe work days and 2,497 safe work hours with a staff of 26 employees and 20 subcontractor personnel.
- The document includes schedules, permit progress, and photos of site construction activities like soil processing and trench digging.
PPT ON IMPROVING DISTRIBUTOR ETA COMPLIANCE RATE DEC.2015Joel Justice Okine
The document summarizes the parts kaizen marathon held in 2015 to improve the estimated time of arrival (ETA) compliance rate for parts distributions. The team analyzed the current 65% ETA compliance rate and set a target of 90% for 2015. Through root cause analysis, they identified issues like multiple couriers and lack of ETA knowledge. Countermeasures like using a single courier, empty bin utilization and training improved the compliance rate to 90% by September 2015. Monitoring showed reduced requisition aging. The team standardized manual forms and set a 98% target for 2016 to sustain the gains.
The document discusses Cequesta Water's Hybrid GreenFloat DAF (HGD) product, which is a modular, mobile water and wastewater treatment system housed in a standard shipping container. The HGD uses a hybrid filtration process that increases separation efficiency while reducing chemical consumption. It is well-suited for growing remote markets. The document provides an overview of Cequesta Water, the HGD's benefits compared to other systems, example applications including food processing and oil/gas, and a request for investment to advance the HGD from pilot to sales stage.
This document summarizes a validation study conducted by DNV GL comparing turbine performance data measured from a 1MW tidal turbine installed at EMEC to simulations conducted using the Tidal Bladed software. The study found that Tidal Bladed provided good predictions of steady state and dynamic turbine response as well as fatigue loads, with damage equivalent loads from simulations matching well with measured data. This increased validation of Tidal Bladed's modeling capabilities can improve confidence in the turbine design process.
This document highlights an engineering firm's proven track record in:
1) Helping clients achieve project milestones on time through designs for process systems and control upgrades.
2) Successfully delivering control system and equipment upgrades and modifications for offshore oil and gas platforms that improved safety and addressed issues.
3) Managing instrumentation and control scopes for major offshore oil and gas projects, often under budget and ahead of schedule.
The document summarizes a review meeting for the Hydrology Project Phase II in Madhya Pradesh, India. The project involves establishing surface water and groundwater monitoring stations. For surface water, 24 river gauge stations and 52 meteorological stations were set up across three river basins. For groundwater, 3750 observation wells and 625 piezometer wells were established. The project period was from 2004-2014 with a total cost of Rs. 24.67 crores. Major achievements included upgrading monitoring stations, establishing new stations, and developing decision support systems for reservoir management and groundwater planning. Lessons learned and plans for continuing activities after the project are also discussed.
This document discusses a project to construct a 1250-foot long pier and 800-foot wharf at the Norfolk Naval Shipyard in Portsmouth, VA. It was the first BIM project for NAVFAC on the East Coast, with a construction cost of $165 million. BIM was used to coordinate utilities, identify conflicts, visualize construction, and help the client and end users understand the final product. The model included structural, civil, mechanical, electrical, and architectural components. BIM reduced errors and requests for information and improved coordination between stakeholders.
The kaizen project redesigned the final assembly cell for Applied Technologies to decrease travel distance and reduce floor space usage. The team analyzed customer demand and takt times to design a custom cell layout that accommodated all product assemblies. Individual work stations were customized and the cell was rearranged to reduce the assembly area by 40% and product travel distance by 63%, meeting targets of 400 square feet and 60 feet respectively.
The document discusses the layout of a plant, including sections for raw material storage, processing, product storage, utilities, waste treatment, and administration. It provides diagrams of the overall plot plan and selected areas for detailing. Process flow diagrams and piping and instrumentation diagrams are shown. Floor plans and elevations at different heights are provided. Considerations for layout include the material characteristics, required space for equipment and piping, operational movements, safety, and potential future expansion.
Deswik-IPCC2013 Presentation-Scenario based analysis of IPCC trade-offsDeswik
This presentation was delivered by Deswik at the I-M Mining IPCC 2013 conference on 14th October 2013.
The presentation outlines a recommended approach for assessing the viability of In Pit Crushing and Conveying (IPCC) for mining operations. The key point is that modelling MUST include both the proposed system as well as other conventional fleet areas of the mine, modelled as a single system. This allows identification of system interactions and fatal flaws that are evident only in a combined mine plan model.
In previous years multiple presentations called for development of mine planning software that is capable of effective IPCC planning. Deswik commenced work in February 2013 on addressing this need, and have formed a partnership with industry experts RWE to ensure the result is fit for purpose. This presentation illustrates techniques that use the first results of this endeavour.
This technical drawing shows a gear puller with lead screw details. It includes dimensions for the gear puller components and lead screw, a scale of 1:1, and was drawn by K. Thorpe on November 18, 2014. It also references a detail view A of the lead screw at a scale of 4:1 and provides file information for the technical drawing.
Este documento describe la ciudad de Barranquilla en Colombia, donde el río Magdalena desemboca en el mar Caribe. Barranquilla es conocida por su alegría y espíritu festivo, donde las calles se convierten en fiestas al ritmo de la música. También describe el barrio de Los Trupillos, el cual tiene viviendas de dos a tres pisos y parques grandes y arbolados. El barrio es reconocido por su historia de alegría y paz, así como por sus logros deportivos. Finalmente, describe una cuadra en
Lithuanians celebrate Christmas Eve (Kūčios) on December 24th, where families clean their homes, bathe, and have a sparse meal in preparation for Santa Claus (Kalėda) arriving after nightfall. Kalėda is depicted as bringing gifts in his carriage from far away lands. A symbol of the deer with nine horns represents defeating winter and the coming of spring. Christmas is celebrated for three days, where the first is most sacred and work is avoided in favor of predictions for the new year. Traditional Lithuanian Christmas trees are decorated with unique straw ornaments that originated from a Lithuanian Consul's wife in Chicago.
You can read RSS but how do you create an RSS feed and how can you manipulate and republish RSS-based content. This three-hour workshop will show you many of your options.
In Lithuania, Easter is called Šv. Velykos, which means "Holy Easter" in Lithuanian. It is an important Christian holiday celebrated on the first Sunday after the first full moon in spring and lasts five days. Traditions include children decorating eggs and playing games, receiving presents from Easter Granny, and using natural plant dyes to paint eggs with traditional wax-removal patterns, as well as singing songs during the five-day celebration following the Lent period called Gavėnia.
This document highlights an engineering firm's proven track record in:
1) Helping clients achieve project milestones on time through designs for process systems and control upgrades.
2) Successfully delivering control system and equipment upgrades and modifications for offshore oil and gas platforms that improved safety and addressed issues.
3) Managing instrumentation and control scopes for major offshore oil and gas projects, often under budget and ahead of schedule.
The document summarizes a review meeting for the Hydrology Project Phase II in Madhya Pradesh, India. The project involves establishing surface water and groundwater monitoring stations. For surface water, 24 river gauge stations and 52 meteorological stations were set up across three river basins. For groundwater, 3750 observation wells and 625 piezometer wells were established. The project period was from 2004-2014 with a total cost of Rs. 24.67 crores. Major achievements included upgrading monitoring stations, establishing new stations, and developing decision support systems for reservoir management and groundwater planning. Lessons learned and plans for continuing activities after the project are also discussed.
This document discusses a project to construct a 1250-foot long pier and 800-foot wharf at the Norfolk Naval Shipyard in Portsmouth, VA. It was the first BIM project for NAVFAC on the East Coast, with a construction cost of $165 million. BIM was used to coordinate utilities, identify conflicts, visualize construction, and help the client and end users understand the final product. The model included structural, civil, mechanical, electrical, and architectural components. BIM reduced errors and requests for information and improved coordination between stakeholders.
The kaizen project redesigned the final assembly cell for Applied Technologies to decrease travel distance and reduce floor space usage. The team analyzed customer demand and takt times to design a custom cell layout that accommodated all product assemblies. Individual work stations were customized and the cell was rearranged to reduce the assembly area by 40% and product travel distance by 63%, meeting targets of 400 square feet and 60 feet respectively.
The document discusses the layout of a plant, including sections for raw material storage, processing, product storage, utilities, waste treatment, and administration. It provides diagrams of the overall plot plan and selected areas for detailing. Process flow diagrams and piping and instrumentation diagrams are shown. Floor plans and elevations at different heights are provided. Considerations for layout include the material characteristics, required space for equipment and piping, operational movements, safety, and potential future expansion.
Deswik-IPCC2013 Presentation-Scenario based analysis of IPCC trade-offsDeswik
This presentation was delivered by Deswik at the I-M Mining IPCC 2013 conference on 14th October 2013.
The presentation outlines a recommended approach for assessing the viability of In Pit Crushing and Conveying (IPCC) for mining operations. The key point is that modelling MUST include both the proposed system as well as other conventional fleet areas of the mine, modelled as a single system. This allows identification of system interactions and fatal flaws that are evident only in a combined mine plan model.
In previous years multiple presentations called for development of mine planning software that is capable of effective IPCC planning. Deswik commenced work in February 2013 on addressing this need, and have formed a partnership with industry experts RWE to ensure the result is fit for purpose. This presentation illustrates techniques that use the first results of this endeavour.
This technical drawing shows a gear puller with lead screw details. It includes dimensions for the gear puller components and lead screw, a scale of 1:1, and was drawn by K. Thorpe on November 18, 2014. It also references a detail view A of the lead screw at a scale of 4:1 and provides file information for the technical drawing.
Este documento describe la ciudad de Barranquilla en Colombia, donde el río Magdalena desemboca en el mar Caribe. Barranquilla es conocida por su alegría y espíritu festivo, donde las calles se convierten en fiestas al ritmo de la música. También describe el barrio de Los Trupillos, el cual tiene viviendas de dos a tres pisos y parques grandes y arbolados. El barrio es reconocido por su historia de alegría y paz, así como por sus logros deportivos. Finalmente, describe una cuadra en
Lithuanians celebrate Christmas Eve (Kūčios) on December 24th, where families clean their homes, bathe, and have a sparse meal in preparation for Santa Claus (Kalėda) arriving after nightfall. Kalėda is depicted as bringing gifts in his carriage from far away lands. A symbol of the deer with nine horns represents defeating winter and the coming of spring. Christmas is celebrated for three days, where the first is most sacred and work is avoided in favor of predictions for the new year. Traditional Lithuanian Christmas trees are decorated with unique straw ornaments that originated from a Lithuanian Consul's wife in Chicago.
You can read RSS but how do you create an RSS feed and how can you manipulate and republish RSS-based content. This three-hour workshop will show you many of your options.
In Lithuania, Easter is called Šv. Velykos, which means "Holy Easter" in Lithuanian. It is an important Christian holiday celebrated on the first Sunday after the first full moon in spring and lasts five days. Traditions include children decorating eggs and playing games, receiving presents from Easter Granny, and using natural plant dyes to paint eggs with traditional wax-removal patterns, as well as singing songs during the five-day celebration following the Lent period called Gavėnia.
Offshore Energy Limited - Project lifting management and support services pre...RichardTurnbull9
The presentation summarizes Offshore Energy's services for BP's WREP Pipeline Project, including lift management, personnel, project management, lift engineering, health and safety, and training. Offshore Energy provided lift management and over 3000 lifts were completed between May-October 2018 with zero accidents. Services included lift planning, rigging design, installation drawings, and training of local Georgian personnel. The client provided positive feedback on Offshore Energy's communication, enforcement of safety policies, and support of the local workforce.
Core Groundwater Technical Services is a groundwater consulting company owned by J. Louis van der Walt, with over 22 years of experience. The company specializes in geohydrological investigations, groundwater modeling, monitoring, and database management. Recent projects include groundwater studies and impact assessments for sand mining, lodge development, mineral exploration, industrial development, and rural land use. Core Groundwater Technical Services captures scientific field data and utilizes specialized techniques and equipment to characterize aquifers and support water use authorizations.
This document describes an ERP solution for construction that provides features such as project management, employee allocation, customizable applications, alerts, task management, accounting, and comprehensive reporting at the project, employee, supplier, and accounting levels. It is offered by Sparknova, an international company with offices in the US, India, Dubai, and South Africa.
This document is a resume for Vijay Kumar Gupta applying for the position of Senior Piping Designer. It outlines his qualifications and over 30 years of experience in plant layout and piping design for oil, gas, and industrial facilities around the world. It details his software proficiencies and provides an employment history and descriptions of representative projects.
The document summarizes a CalAPA meeting presentation about Caltrans construction projects. It discusses that Caltrans has 12 districts, 19,000 employees, and a $11 billion annual budget used for maintaining 15,213 miles of highways and 12,600 bridges. It then reviews historical construction spending and current construction projects totaling $11.2 billion across 593 projects. Upcoming projects in the next 12 months total $2.4 billion across 261 projects. The presentation outlines various Caltrans initiatives including design-build contracting, electronic bidding, updated specifications, and emphasis on work zone safety and partnering to improve on-time and on-budget delivery while maintaining job satisfaction and reducing claims.
Surviving your Capital Improvement Plan - Kevin McKinnon, Anchorage Water and...marcus evans Network
Kevin McKinnon, Anchorage Water and Wastewater Utility - Speaker at the marcus evans Water & Wastewater Management Summit 2012 held in Summerlin, NV, May 3-4, 2012, delivered his presentation entitled Surviving your Capital Improvement Plan
Architecture engineering and construction industry are increasing by aggressive globally. Architectural Designing and architectural drafting, services required technical knowledge, man power, administrative, and high level management. CAD outsourcing, in India helps you to reduce all these cost and execute you sophisticated Architectural services. Cad outsourcing provides the Architectural 2D Drafting, 3d Rendering, Architectural 3D, Architectural Animation, Walkthrough, Furniture layout, Architectural Designing services to client globally from India
This resume is for Rafi Azis and spans 6 pages. It outlines his education, qualifications, work experience, technical skills and career history. Rafi has over 8 years of experience as a Pipeline Inspection Engineer and has worked on numerous pipeline integrity projects across Asia, Europe, North America and Australia. He has extensive experience performing inline inspections using different tool types and has various safety, technical and language certifications.
This document provides an overview of Aayogh Engineering Pvt Ltd (AEPL) including their about us, vision, mission, core values, capabilities, business divisions, expertise in various fields like electrical, transmission lines, cabling, engineering design, piping design, areas of operation, present projects, past projects and achievements from 2021-2022 and 2017-2019, and their team. AEPL is a team of professionals with expertise in civil, electrical, mechanical and IT infrastructure with experience in various industries. They aspire to be a reliable business partner and one stop solution provider for clients.
The document discusses plans for the Bloodhound SSC project, which aims to break the land speed record. It analyzes scenarios for completing the project under different resource constraints:
1) Completing with current resources would achieve the target date in late 2016.
2) Meeting the 2014 target date would require immediately hiring over 100 additional engineers, exceeding available resources.
3) Hiring a small number of additional engineers could achieve the target date in mid-2015, saving 15 months.
4) Conducting a media jet engine test in 2013/14 could provide further schedule acceleration.
Using composite crews to estimate a construction project is the best and most accurate way to develop a cost estimate. On one condition: we know what we are doing. Browse through this slideshow and see what are the most important points to consider when using composite crews for cost estimating.
This document summarizes the job description and responsibilities of an engineering design engineer in the civils- water department from June 2013 to present. The key responsibilities include design, drafting, administration, resource management, construction management, and finance for various civil engineering projects. Some of the major projects summarized are the Maroeladal Thorntree Development, CSIR Roads and Stormwater Upgrades, Transnet Pipelines Sewer Outfall, and Ga-Rankuwa Flood Risk Assessment. Duties involve design, construction drawings, cost estimates, construction supervision, and managing project budgets and schedules.
The document discusses operations cycle time (Ops CT), which is the time it takes to process an order from start to finish. It makes three key points:
1. Ops CT is currently measured based on time to produce, but customers experience the full cycle time. Reducing only production time does not help customers.
2. There are many sources of variability and waste that increase Ops CT beyond necessary production time, such as rejections, reworks, breakdowns, and scheduling changes.
3. To reduce overall Ops CT, the document recommends examining processes to eliminate unnecessary steps, combining steps, rearranging steps for parallel processing, and keeping all resources in a ready-to-use mode. This will
This document summarizes the key points from a Drawbridge meetup for data scientists. It includes an agenda for presentations on Drawbridge's business overview, platform infrastructure, traffic allocation policies, user segmentation, model training platform, and dynamic predictive models. It also provides information about Drawbridge's cross-device platform that pairs devices, scales to over 100 million paired devices, and processes over 1 trillion observations per day.
What is your level of confidence that your Flow Meter is accturate? We'll go over; the basics of flow measurement, typical WWTP flow meters, accuracy vs precision, considerations, layouts and design, common issues, and methods to check.
Presentation on project plan for tyre recycling plantabhishekthakur309
This document outlines plans for constructing a scrap tire recycling plant. It will pyrolyze 60,000 tons of scrap tires disposed in landfills annually. The plant will be built on 5 acres of industrial land in Maryland over 18 months for $5 million. It will pyrolyze 10 tons of tires per day. The project will be managed according to a work breakdown structure, schedule, and cost and risk management plans. Construction is scheduled for 231 days as part of the overall 522-day project timeline. The cost management plan includes metrics to track schedule and cost performance against the $5 million budget. The risk management plan involves analyzing and mitigating risks throughout the project.
The document outlines an agile implementation plan involving setting up infrastructure like a Jira board and whiteboard, choosing a pilot project, starting daily standups and metrics tracking, doing a retrospective at the end of the first sprint, providing agile training to the team, and sharing knowledge through internal seminars and external conferences. Key elements include setting up Jira, choosing a pilot project, beginning daily standups and metrics tracking, and conducting a retrospective after the first sprint.
To protect its water services from floods and deliver superior performance, United Water Pennsylvania decided to build a new, innovative water treatment plant that would satisfy its own high standards and regulatory rules. Using design-build delivery, United Water is working with CDM Smith to make its goals a successful reality.
GAIL INDIA PRESENTATION BY AMALLLL.pptxAMALRAJPUT2
GAIL (India) Limited follows a structured project life cycle for its projects. The document discusses the key stages in the life cycle of setting up a CNG station, including initiation, planning, execution, monitoring and control, and closure. It describes the main activities undertaken at each stage, such as conducting feasibility studies, developing schedules and procurement plans, obtaining approvals, tracking progress, and handing over the completed project. Following this life cycle approach helps ensure CNG stations are delivered on time, within budget, and as per required quality standards.
The management of geotechnical risk on major infrastructure projectsChris Bridges
The document discusses managing geotechnical risk on major infrastructure projects. It emphasizes that geotechnical engineering involves uncertainty due to variable ground conditions and limitations of site investigations. It advocates using the observational method, which involves ongoing monitoring during construction and allowing design modifications based on field observations. The greater the involvement of the geotechnical engineer in all project phases, through tools like instrumentation and full-time site presence, the less conservative the initial design needs to be and the better geotechnical risks can be managed to avoid failures. The Heathrow tunnel collapse case study highlights issues that can arise without adequate geotechnical input and oversight during construction.
Similar to End of Summer Intern Presentation-3 (20)
2. AgendaAgenda
• ProjectsProjects
– NGPL Long Term Make PiggableNGPL Long Term Make Piggable
EstimatesEstimates
– Recoat Cost EstimatesRecoat Cost Estimates
– Budget vs. Actual AnalysisBudget vs. Actual Analysis
• Assistance to other PMs in CentralAssistance to other PMs in Central
RegionRegion
• Field Experiences and ToursField Experiences and Tours
3. ProcessProcess
• Trap InstallationsTrap Installations
• Valve ReplacementsValve Replacements
• Bar TeesBar Tees
• River Crossings and Pipe ReplacementsRiver Crossings and Pipe Replacements
NGPL Long Term Make Piggable EstimatesNGPL Long Term Make Piggable Estimates
5. Estimate Example – 12Estimate Example – 12” Arcadian Lateral” Arcadian Lateral
Traps
Cost per
Trap
MLVs
Cost per
MLV
Tees
Cost per
Tee
Total Cost
2 $567,666.67 4 $244,666.67 0 $131,733.33 $2,114,000.00
6. AMA #3 and #4 Recoat EstimatesAMA #3 and #4 Recoat Estimates
3 Separate Estimates – Capital Projects
– Recoat 205 feet of 36” pipe – Amarillo Line #4Recoat 205 feet of 36” pipe – Amarillo Line #4
– Recoat 468 feet of 36” pipe – Amarillo Line #3Recoat 468 feet of 36” pipe – Amarillo Line #3
– Recoat 125 feet of 36” pipe – Amarillo Line #3Recoat 125 feet of 36” pipe – Amarillo Line #3
7. Cost Estimate ProcessCost Estimate Process
• Determine LocationsDetermine Locations
• Determine StakeholdersDetermine Stakeholders
• Establish Scope and AssumptionsEstablish Scope and Assumptions
• Hold Scoping MeetingHold Scoping Meeting
• Receive Cost Estimate from EstimatorReceive Cost Estimate from Estimator
• Review and Send to Director for ApprovalReview and Send to Director for Approval
8. Location – Dodge City, KansasLocation – Dodge City, Kansas
• Google EarthGoogle Earth
• Recoat Locations –20 Mile RadiusRecoat Locations –20 Mile Radius
• Review of Potential Access PointsReview of Potential Access Points
10. Scope and AssumptionsScope and Assumptions
• Scope of WorkScope of Work
• AssumptionsAssumptions
– Relatively flat landRelatively flat land
– Non-laser leveledNon-laser leveled
– No bendsNo bends
– No mats neededNo mats needed
11. Analysis of NGPL 2014 andAnalysis of NGPL 2014 and
2015 Projects2015 Projects
• Budget vs. ActualBudget vs. Actual
• Construction Bids vs. ActualConstruction Bids vs. Actual
Mechanical Contractor CostsMechanical Contractor Costs
• Change Order BreakdownChange Order Breakdown
12. Budget vs. Actual ExampleBudget vs. Actual Example
BudgetBudget VarianceVarianceActualActual ExplanationExplanationCategoryCategory
• Project Name: 30 Inch Portable Launcher Receiver FabricationProject Name: 30 Inch Portable Launcher Receiver Fabrication
• AFE: 201656AFE: 201656
• Project Manager: Tony GoncalvesProject Manager: Tony Goncalves
• Project Type: Make PiggableProject Type: Make Piggable
• In-Service Date: 4/7/2015In-Service Date: 4/7/2015
13. Construction Bids and Change Order AnalysisConstruction Bids and Change Order Analysis
14. Assistance to PMsAssistance to PMs
Calvin McKnight - Belvidere Meter Station Upgrade andCalvin McKnight - Belvidere Meter Station Upgrade and
REX Moultrie LateralREX Moultrie Lateral
–Scope of WorkScope of Work
–Excavation PlanExcavation Plan
–Bid Tab and RFMBid Tab and RFM
–Over Pressure Protection EvaluationOver Pressure Protection Evaluation
Charlie Malcolm – AMA #2 and #3 Make PiggablesCharlie Malcolm – AMA #2 and #3 Make Piggables
–BOM and Procurement Status Report ComparisonsBOM and Procurement Status Report Comparisons
Tony Goncalves – CS 312Tony Goncalves – CS 312
–Meeting MinutesMeeting Minutes
–HAZOP meetingHAZOP meeting
15. Field ExperienceField Experience
CS 346 Flow ReversalCS 346 Flow Reversal
and Sabine Henry Huband Sabine Henry Hub
ModificationsModifications
16. ToursTours
• Houston Central PlantHouston Central Plant
• Markham StorageMarkham Storage
Compressor StationCompressor Station
• Metallurgy LabMetallurgy Lab
Editor's Notes
Hi everyone, my name is Rachel Howard, and I am currently a junior at Texas A&M University studying civil engineering. This summer I had the privilege of working as an intern in project management for the NGPL group under Chris Drescher.
My work this summer consisted of three larger scale projects along with a number of smaller tasks in assisting other project managers in my group with various aspects of their projects. I also got the opportunity to travel to a construction site in Louisiana as well as attend a number of tours with the other interns.
The first project I was assigned involved developing a large number of estimates for NGPL make piggable projects. The integrity team assigned the project management department the task of evaluating a large number of future make piggable projects for NGPL and providing broad estimates for each of these projects. This was an assignment one of the project managers in my group was currently working on when I first started here this summer; he had about 40 estimates left to evaluate, which he then left for me to finish.
Here, I have illustrated my process for determining each general estimate for these make piggable projects. I was provided a very general scope for each project which usually included installing pig launchers and receivers and replacing any mainline valves and barring tees where necessary, as well as replacing river crossings and pipe.
I then pulled up the appropriate alignment sheets using Geospatial to determine how many mainline valves needed replacing, and how many tees needed to be barred. I also utilized the location of these laterals to make a good assumption on whether union or non-union labor would be used for these projects.
I then used all the information I found from evaluating the scope and the alignment sheets to determine a general estimate. The project manager working on this project prior provided me with a list of go-bys for the calculations for these projects. These go-bys were developed from examining historic data from past projects, such as the costs of mainline valve replacements and permanent pig launchers and receivers; these pricings were broken down by pipe sizing and whether union or non-union labor was used.
Here is an example of one of the projects I evaluated. The purpose of this project is to make the 12” Arcadian Lateral Piggable. The scope includes installing a pig launcher and receiver, replacing any mainline valves, and barring any tees. Here are three small sections of the alignment sheets for the Arcadian Lateral I analyzed for this estimate. From examining these three sections, you can see that there are four mainline valves on this lateral and one tee. The replacements of the four valves were included into the estimate, but the barring of the tee was not. The tee on this alignment sheet is a 4” tee on a 12” line. Because the tee is less than half the diameter of the pipe, the tee does not need to be barred.
The alignment sheets also told me that this lateral is located in Beatrice, Nebraska, which is a non-union state. I used this knowledge to make the assumption that non-union labor would be used.
Scope – install permanent launcher and receiver on line, replace any valves, bar any tees
Here is a breakdown of the scope and costs I used to determine the final cost estimate for this project. As you can see I used the information that I found from the alignment sheets and the go-bys. I then multiplied the number of traps, mainline valves, and tees with its corresponding individual non-union cost to determine my final cost for the project. Although this type of estimate is very general and lacks a lot of detail that a normal cost estimate contains, these estimates provided the integrity team with general pricing they need for future projects.
After completing the make piggable estimates, I was then assigned the task of providing three estimates for three NGPL integrity projects submitted by operations to be completed in 2016. This project helped me in seeing the difference between a very general cost estimate and a detailed estimate as well as gave me a lot of insight into the cost estimation process for project managers.
Here I have outlined the process in developing these estimates. I first determined the locations of all three sites on Google Earth, I then established the stakeholders for this project in order to determine who needed to be invited to my scoping meeting. I then outlined the scope and general assumptions which was all then reviewed during the scoping meeting. After holding the meeting and corresponding with those that were unable to attend the meeting, the cost estimator developed the final estimate which I then reviewed and sent to my director for approval within the 2 week deadline.
I have provided a Google Earth screenshot for the approximate recoat length on the Amarillo 4 line. This was done for all three locations. Utilizing Google Earth allowed me to find potential access points for the construction site as well as determine what was in the surrounding areas. As you can see from this screenshot, the recoat location is very near to a road; however, one of the recoat locations on the Amarillo 3 line was about a mile away from an access point. Land and ROW then knew they needed to allot a larger amount money for damages for that recoat project.
These are the departments of the people that were included in the scoping meeting. Because these three projects were for recoating the pipeline, an engineering representative was not needed. Those that were unable to attend the meeting I corresponded with individually in order to provide the estimator with all the information he needed for the estimate.
Here I have outlined the scope that was discussed in the scoping meeting. This scope includes excavation of the pipe and stripping the old coating, recoating of the pipe, as well as backfilling and reseeding the site. A cost for a 3rd party company to preform Stress Corrosion Cracking, or SCC, testing was also included in these three estimates. During the scoping meeting, the members of the team and I discussed the established scope as well as specifics relative to each team member’s department. Holding this meeting provided the estimator with the information he needed to develop a good estimate for these three projects.
My final project was assigned to me by my supervisor, Chris Drescher, and involved the development of a cost analysis of NGPL 2014 and 2015 projects. The purpose of this assignment was to provide an organized source of go-bys for estimates based on costs and construction bids from recent projects. This project also gave me a lot of exposure to the accounting side of the pipeline industry. I developed an Excel spreadsheet which was broken down into these three sections.
The first portion of this project provides a breakdown of budget and actual costs for 2014 and 2015 NGPL projects. Each project is broken down by Project Name, AFE, Project Manager, In-Service Date (if applicable) and Type of Project (Make Piggable, Drip Removal, etc). Each project was then broken down further by individual costs (Mechanical Contractor, Material, etc.). These costs were broken into budgeted, actual, and variance sections, all of which was found in PSA. A separate section contains comments for variances that a cost analyst helped me pull up by using the application, CARS. For the variance section, what is filled in red represents a unfavorable variance, and the green represents a favorable variance. One major benefit of the portion of the spreadsheet is that each section can be filtered – for example, I can filter the costs for all mechanical contractor costs for make piggable projects included in this analysis.
The second section of my analysis provides a breakdown of the contractor bid amounts and the actual costs for mechanical contractors for each project. Each project is broken down by Project Name, AFE Number, and Project manager. For each project, there is a construction bid amount for the contractor (or 2 amounts if 2 contractors were used) the actual costs for the mechanical contractors, and the total amount of change orders issued. If the project has not been completed, the estimated total remaining amount for the contractor is also listed. This required pulling up a lot of data from PSA and other Project Managers’ J Drives or personally annoy them if their Drives did not contain this information. I also met with a purchasing manager that Bill Bane put me in contact with for the determining whether the work was done using union or non-union labor.
The third section of this spreadsheet is a breakdown of all change orders issued for each project - this section includes the cost impact of the change order along with a description of the change in scope.
Throughout the summer, I also assisted other project managers in my group with various aspects of projects they were working on. Doing so helped me to understand how much exactly is involved in the development and completion of a project and the importance of staying on top of every aspect of the project. I also got to become familiar with a lot of the paperwork that is involved in project management such as filling out requests for materials and developing a scope of work and an excavation plan for a bid package.
In mid-July I got the opportunity to travel to Compressor Station 346 and the Sabine Henry Hub in Kinder, Louisiana. Even though this was a project I was not at the time working on, this visit showed me the workings of a project on a larger scale. Looking at the drawings for this project and comparing it to what was actually being done at the site gave me a completely different perspective. While I was there I also got the opportunity to meet with the welding inspectors as well as sit in on a meeting with the contractors and ops to discuss changes in the schedule.
(Here’s a picture of me wearing some FRC’s that definitely did not fit me – I had to hold them up while walking to keep from tripping)
Along with the other interns, I also had the opportunity of touring the Houston Central Plant, the Markham Storage Compressor Station, and the Metallurgy lab here in Houston.
(The picture of the plant may or may not have been pulled up from Google – phone usage for taking pictures was limited)