SlideShare a Scribd company logo
1 of 9
Download to read offline
1 | P a g e
Plusses and Minuses
of
Loading BOQ cost in “Resources” and “Expenses”
in a primavera schedule.
Mujahid Ishtiaq
PMP® | PSP® | PMI-SP® | AMPC®
Project Planner/Scheduler
17th
February 2016.
2 | P a g e
Contents
Abstract ........................................................................................................................................... 3
Introduction..................................................................................................................................... 3
Comparison....................................................................................................................................... 3
1. Loading cost in “Resource”:....................................................................................................... 4
2. Loading cost in “Expense”:........................................................................................................ 8
Conclusion......................................................................................................................................... 9
3 | P a g e
Abstract
In our daily practice and here in GCC, normally we load BOQ cost in schedule as lump sum by creating
a global resource or an expense item. First of all, it is not a proper way to add one resource and assign
it to all activities giving it weighted or lump sum calculated cost for each activity. Proper and
recommended way is to develop a complete resource pool, with correct resource types, units and
rates. Moreover Expense item is used to load only non-variable or fixed cost types. But as mentioned
earlier, in GCC, distribution of BOQ cost in schedule as lump sum for each activity has become normal
practice.
In this document some advantages and disadvantages of both options will be discussed and analysed.
Introduction
When we go for cost loading, one finds couple of ways to load cost in schedule as follows:
1. By creating a global cost resource, assigning it to multiple activities, exporting budgeted cost
column in excel, populating budgeted cost column in excel and importing it back to P6.
2. Creating one or multiple expense items, assigning them to respective activities, exporting
expense column in excel, populating expense column with calculated budgeted cost for each
activity and importing back to p6.
Although common purpose can be achieved in both ways, but sometimes there are situations
when one has to select specific technique out of two. But if we don’t know exactly what other
benefits or facilities we may lose by selecting a specific technique or what additional benefits
can we get from one method, we will not be able to get complete sense of paybacks of
Primavera.
Comparison
Here, we will discussed both options and their plusses and minuses so that one may consider
all these points before selection of a method to load cost in schedule.
4 | P a g e
1. Loading cost in “Resource”:
 One of the best advantages of loading cost in schedule using Global Cost Resource is that you
can extract your cash flow at both early and late dates called “Early Cash Flow” and “Late
Cash Flow”. These two types of cash flow are sometimes extremely important especially for
management while making financial decisions for multiple projects to get answer of question
“what is delay tolerance available in providing funding to a certain project at a certain point?”
Figure 01 Early and Late Cash Flow.
These cash flows are based on “Early Start & Finish” and “Late Start & Finish” dates of
schedule activities or in other words we can say that these cash flows count on on floats
available in non-critical activities.
 Second advantage of loading cost through Global Cost Resource is “Resource Curves”.
When resources perform work on an activity, you can choose how the resource units or costs
are spread through time. This is done using a resource curve. To see this column, right-click
on the Resources tab on an activity, customize the columns, and choose Curve.
See figure 02 given below.
5 | P a g e
A wealth of curves from which to choose is presented. These curves will determine how the
effort and cost of a resource is spread over time. This could reflect expected cost for labor or
the expected consumption of a material resource.
Figure 02 Recourse Curves in Primavera.
To view and modify resource curves, choose the menu Enterprise | Resource Curves. A list
of resource curves, much like the one shown in Figure 3-1, appears. This screen allows you
to modify, and delete curves. In the EPPM web client, resource curves are defined in the
Resource Curves section under the Administer |Enterprise Data. Because so many standard
curves come standard with P6, there may be no need to define your own.
Besides the preloaded curves available in primavera, there is also an option available to add a
customised curve or cost distribution along activity.
To develop a customized curve, see figure 03-1 & figure 3-2 and follow given steps.
6 | P a g e
Figure-03-1 Adding a customized resource curve.
Figure-03-2 Adding a customized resource curve.
 Auto compute actual is also a plus in loading cost using resource. Actual cost, remaining cost
and at completion cost are auto-computed when you update activity by giving actual dates
and remaining duration. To activate this option, you have to check Auto Compute Actuals
option in resource details pan. See Figure-04.
7 | P a g e
Figure-04 Auto Compute Actuals in Primavera P6
 When you load cost in resources, you have access to different types of cost data as given
below:
 Budgeted Cost
 Actual Cost
 Actual Overtime Cost
 Actual Regular Cost
 Actual This Period Cost
 Remaining Cost
 At Completion Cost
 Staffed Remaining Cost
 Unstaffed Remaining Cost
All these costs are available in the form of spread sheets giving you multiple data forms to
analyse with respect to time and you can copy this data to excel to create attractive graphs
and charts to present it to management.
 Some planners feel it easy to handle (I don't know why…?).
8 | P a g e
 A drawback of loading cost using Global Cost Resources is that you cannot feed cost to any
activity before it commences (like upfront payments of subcontractors) or after activity is
completed (like retentions etc.). Actuals of cost in resources will only incur once activity has
started and cannot be adjust after activity is complete.
 Another drawback of loading cost using Global Cost Resources is that you cannot assign
resource to a milestone thus you cannot assign cost to a milestone, which sometime is
required in schedule.
2. Loading cost in “Expense”:
 The cost zeroing out is sometimes a problem when Remaining Duration equals Zero as may
happen with resources. As explained earlier, sometimes costs are incurred in a cost
management system after an activity is complete due to back charges or retention etc. So
expenses allow you to re-adjust your actuals and remainders even after you have finished
playing with your activity.
 An additional benefit of loading cost using expense items is that, unlike resources, it allows
cost to be incurred or adjusted before an activity even commences, representing a
contractor’s upfront payment.
 In loading cost using expense items, costs are not affected if remaining duration changes,
which may happen with resources. Sometime cost to complete or remaining/actual cost has
nothing to do with the remaining duration or % complete. So expenses give you option to
manage cost regardless of how much duration is remaining or how much % of activity you
have completed.
 Unlike resources, you can assign expenses, which is cost, to a milestone.
 Unavailability of Auto-compute actuals and remainders in expense items is sometimes
considered a drawback as well. But it is not fact that expense items do not auto-compute
actual, remaining and to complete cost. Expense items have ability to auto-compute actuals
but this process is a little bit hard to understand. As a brief, auto-compute option in expense
items works with our old friends the Planned Start and Planned Finish dates.
9 | P a g e
For example, if activity’s schedule % complete is 0% but performance % complete is 10%,
expense will not auto compute actual cost because 0% of scheduled work shows that planned
start of activity has not kicked in yet. Similarly, when other variances occur between planned
and actual dates, expense items do not auto-compute actuals because it works with planned
dates.
 In expense, there are very limited options to spread cost over activity duration. Unlike several
pre-developed and customization options of resource curve in resources, expense give only 3
accrual types (At start, uniform, at end).
 Unlike resources, In expense you have only following types of cost data:
 Budgeted Cost
 Actual Cost
 Remaining Cost
 At Completion Cost
It means you will have to summarize all types of cost before you load into expenses. And later
on if you need to insert separately some different costs like overtime cost etc. you cannot do
that and you will have to merge it in actual cost.
Conclusion
To get accurate planned and actual progress, it is a must to load cost in schedule. And if it is
required to load Lump sum BOQ cost in schedule, both methods can be used i.e. by creating a global
cost resource or expense item. Both methods have their plusses and minuses as discussed in this
document, but ultimate goal of loading BOQ cost in schedule can be achieved both ways. The only
difference lies in privilege of analysing data and getting multiple options for this analysis. Discussion
shows that benefits of using resource for cost loading overcome those of expense. Conditions which
make expense to use for loading cost are rarely encountered. Regardless of everything, while loading
cost in schedule one should positively look into the situation and conditions and should select the
method which serves the purpose best.

More Related Content

What's hot

PRIMAVERA P6 manual.pptx
PRIMAVERA P6 manual.pptxPRIMAVERA P6 manual.pptx
PRIMAVERA P6 manual.pptxGracePentinio1
 
Understanding p6 dates
Understanding p6 datesUnderstanding p6 dates
Understanding p6 dateskrunalplanning
 
Managing cash flow in Primavera P6 - Oracle Primavera P6 Collaborate 14
Managing cash flow in Primavera P6 - Oracle Primavera P6 Collaborate 14Managing cash flow in Primavera P6 - Oracle Primavera P6 Collaborate 14
Managing cash flow in Primavera P6 - Oracle Primavera P6 Collaborate 14p6academy
 
Primavera - Tutorial
Primavera - TutorialPrimavera - Tutorial
Primavera - TutorialRajeev Sharma
 
Project network scheduling and S-curve
Project network scheduling and S-curve Project network scheduling and S-curve
Project network scheduling and S-curve Satish Yadavalli
 
VERTEX Construction Delays and Forensic Schedule Analyses
VERTEX Construction Delays and Forensic Schedule AnalysesVERTEX Construction Delays and Forensic Schedule Analyses
VERTEX Construction Delays and Forensic Schedule AnalysesThe Vertex Companies, LLC
 
Ms Project Workshop
Ms Project WorkshopMs Project Workshop
Ms Project WorkshopEder Alves
 
pRIMAVERA - Progress report checklist - Substation
pRIMAVERA - Progress report checklist - SubstationpRIMAVERA - Progress report checklist - Substation
pRIMAVERA - Progress report checklist - SubstationRAMESH PANIGRAHI PMP
 
Planning and Scheduling Construction Projects, Part 1: The Planning Process
Planning and Scheduling Construction Projects, Part 1: The Planning ProcessPlanning and Scheduling Construction Projects, Part 1: The Planning Process
Planning and Scheduling Construction Projects, Part 1: The Planning ProcessAlberto Sanchez
 
Baseline schedule review and analysis
Baseline schedule review and analysisBaseline schedule review and analysis
Baseline schedule review and analysisADITYA GHUMARE
 
Introduction To Primavera (P6)
Introduction To Primavera (P6)Introduction To Primavera (P6)
Introduction To Primavera (P6)Sandip Kumar Verma
 
Primavera p6 18.8 planning and scheduling guide r3
Primavera p6 18.8 planning and  scheduling guide r3Primavera p6 18.8 planning and  scheduling guide r3
Primavera p6 18.8 planning and scheduling guide r3Matiwos Tsegaye
 
Dealing With A Schedule That Cannot Be Approved - AACE 2012 Meeting
Dealing With A Schedule That Cannot Be Approved - AACE 2012 MeetingDealing With A Schedule That Cannot Be Approved - AACE 2012 Meeting
Dealing With A Schedule That Cannot Be Approved - AACE 2012 MeetingChris Carson
 
Primavera presentation
Primavera presentationPrimavera presentation
Primavera presentationNithin Dev
 

What's hot (20)

Uses of Project Status field
Uses of  Project Status field Uses of  Project Status field
Uses of Project Status field
 
tcc primavera
tcc primaveratcc primavera
tcc primavera
 
PRIMAVERA P6 manual.pptx
PRIMAVERA P6 manual.pptxPRIMAVERA P6 manual.pptx
PRIMAVERA P6 manual.pptx
 
Understanding p6 dates
Understanding p6 datesUnderstanding p6 dates
Understanding p6 dates
 
PM using P6
PM using P6PM using P6
PM using P6
 
Managing cash flow in Primavera P6 - Oracle Primavera P6 Collaborate 14
Managing cash flow in Primavera P6 - Oracle Primavera P6 Collaborate 14Managing cash flow in Primavera P6 - Oracle Primavera P6 Collaborate 14
Managing cash flow in Primavera P6 - Oracle Primavera P6 Collaborate 14
 
Primavera - Tutorial
Primavera - TutorialPrimavera - Tutorial
Primavera - Tutorial
 
Project network scheduling and S-curve
Project network scheduling and S-curve Project network scheduling and S-curve
Project network scheduling and S-curve
 
VERTEX Construction Delays and Forensic Schedule Analyses
VERTEX Construction Delays and Forensic Schedule AnalysesVERTEX Construction Delays and Forensic Schedule Analyses
VERTEX Construction Delays and Forensic Schedule Analyses
 
Ms Project Workshop
Ms Project WorkshopMs Project Workshop
Ms Project Workshop
 
pRIMAVERA - Progress report checklist - Substation
pRIMAVERA - Progress report checklist - SubstationpRIMAVERA - Progress report checklist - Substation
pRIMAVERA - Progress report checklist - Substation
 
Planning and Scheduling Construction Projects, Part 1: The Planning Process
Planning and Scheduling Construction Projects, Part 1: The Planning ProcessPlanning and Scheduling Construction Projects, Part 1: The Planning Process
Planning and Scheduling Construction Projects, Part 1: The Planning Process
 
Project Scheduling & Controls
Project Scheduling & ControlsProject Scheduling & Controls
Project Scheduling & Controls
 
Project Scheduling
Project SchedulingProject Scheduling
Project Scheduling
 
Baseline schedule review and analysis
Baseline schedule review and analysisBaseline schedule review and analysis
Baseline schedule review and analysis
 
Introduction To Primavera (P6)
Introduction To Primavera (P6)Introduction To Primavera (P6)
Introduction To Primavera (P6)
 
Primavera p6 18.8 planning and scheduling guide r3
Primavera p6 18.8 planning and  scheduling guide r3Primavera p6 18.8 planning and  scheduling guide r3
Primavera p6 18.8 planning and scheduling guide r3
 
Dealing With A Schedule That Cannot Be Approved - AACE 2012 Meeting
Dealing With A Schedule That Cannot Be Approved - AACE 2012 MeetingDealing With A Schedule That Cannot Be Approved - AACE 2012 Meeting
Dealing With A Schedule That Cannot Be Approved - AACE 2012 Meeting
 
Primavera presentation
Primavera presentationPrimavera presentation
Primavera presentation
 
ppt for primevera
ppt for primeverappt for primevera
ppt for primevera
 

Similar to Loading cost in primavera schedule using resources and expenses r01

P6 Version 7 Tricks and Traps
P6 Version 7 Tricks and TrapsP6 Version 7 Tricks and Traps
P6 Version 7 Tricks and TrapsInSync Conference
 
Project management
Project managementProject management
Project managementervinod
 
100632 p6 v7 tricks and traps
100632 p6 v7 tricks and traps100632 p6 v7 tricks and traps
100632 p6 v7 tricks and trapsInSync Conference
 
Time based progress analysis in project system (revenue recognition) sap blogs
Time based progress analysis in project system (revenue recognition)   sap blogsTime based progress analysis in project system (revenue recognition)   sap blogs
Time based progress analysis in project system (revenue recognition) sap blogsVenu Vemula
 
Sd billing plan
Sd billing planSd billing plan
Sd billing planRao RV
 
Key tips-for-using-sap-to-improve-joint-venture-cost-recovery-absoft-72
Key tips-for-using-sap-to-improve-joint-venture-cost-recovery-absoft-72Key tips-for-using-sap-to-improve-joint-venture-cost-recovery-absoft-72
Key tips-for-using-sap-to-improve-joint-venture-cost-recovery-absoft-72puppala
 
Sdbillingplan 150626203646-lva1-app6892
Sdbillingplan 150626203646-lva1-app6892Sdbillingplan 150626203646-lva1-app6892
Sdbillingplan 150626203646-lva1-app6892HariharanMS5
 
Budgeting in SCRUM by Divante
Budgeting in SCRUM by DivanteBudgeting in SCRUM by Divante
Budgeting in SCRUM by DivanteDivante
 
Billing plan sap help
Billing plan sap helpBilling plan sap help
Billing plan sap helpRao RV
 
IRJET- Value Management
IRJET- Value ManagementIRJET- Value Management
IRJET- Value ManagementIRJET Journal
 
Closing+cockpit
Closing+cockpitClosing+cockpit
Closing+cockpitArup Nandi
 
Benefit payroll integration
Benefit   payroll integrationBenefit   payroll integration
Benefit payroll integrationjakkanna13
 
Activity Based Costing
Activity Based CostingActivity Based Costing
Activity Based CostingDavid Tracy
 
Construction Project Schedule Template- Residential Building
Construction Project Schedule Template- Residential BuildingConstruction Project Schedule Template- Residential Building
Construction Project Schedule Template- Residential BuildingSHAZEBALIKHAN1
 
Q and A - A benefits mangement framework for prioritisng programmes webinar
Q and A - A benefits mangement framework for prioritisng programmes webinarQ and A - A benefits mangement framework for prioritisng programmes webinar
Q and A - A benefits mangement framework for prioritisng programmes webinarAssociation for Project Management
 

Similar to Loading cost in primavera schedule using resources and expenses r01 (20)

P6 Version 7 Tricks and Traps
P6 Version 7 Tricks and TrapsP6 Version 7 Tricks and Traps
P6 Version 7 Tricks and Traps
 
Project management
Project managementProject management
Project management
 
100632 p6 v7 tricks and traps
100632 p6 v7 tricks and traps100632 p6 v7 tricks and traps
100632 p6 v7 tricks and traps
 
Time based progress analysis in project system (revenue recognition) sap blogs
Time based progress analysis in project system (revenue recognition)   sap blogsTime based progress analysis in project system (revenue recognition)   sap blogs
Time based progress analysis in project system (revenue recognition) sap blogs
 
Session 6 gdas pmp study group presentation
Session 6   gdas pmp study group presentationSession 6   gdas pmp study group presentation
Session 6 gdas pmp study group presentation
 
4. project cost management
4. project cost management4. project cost management
4. project cost management
 
Sd billing plan
Sd billing planSd billing plan
Sd billing plan
 
Key tips-for-using-sap-to-improve-joint-venture-cost-recovery-absoft-72
Key tips-for-using-sap-to-improve-joint-venture-cost-recovery-absoft-72Key tips-for-using-sap-to-improve-joint-venture-cost-recovery-absoft-72
Key tips-for-using-sap-to-improve-joint-venture-cost-recovery-absoft-72
 
Sdbillingplan 150626203646-lva1-app6892
Sdbillingplan 150626203646-lva1-app6892Sdbillingplan 150626203646-lva1-app6892
Sdbillingplan 150626203646-lva1-app6892
 
Budgeting in SCRUM by Divante
Budgeting in SCRUM by DivanteBudgeting in SCRUM by Divante
Budgeting in SCRUM by Divante
 
Billing plan sap help
Billing plan sap helpBilling plan sap help
Billing plan sap help
 
IRJET- Value Management
IRJET- Value ManagementIRJET- Value Management
IRJET- Value Management
 
Closing+cockpit
Closing+cockpitClosing+cockpit
Closing+cockpit
 
Benefit payroll integration
Benefit   payroll integrationBenefit   payroll integration
Benefit payroll integration
 
Activity Based Costing
Activity Based CostingActivity Based Costing
Activity Based Costing
 
Construction Project Schedule Template- Residential Building
Construction Project Schedule Template- Residential BuildingConstruction Project Schedule Template- Residential Building
Construction Project Schedule Template- Residential Building
 
4.6co 04qa ans
4.6co 04qa ans4.6co 04qa ans
4.6co 04qa ans
 
Business Case Template Excel
Business Case Template ExcelBusiness Case Template Excel
Business Case Template Excel
 
Q and A - A benefits mangement framework for prioritisng programmes webinar
Q and A - A benefits mangement framework for prioritisng programmes webinarQ and A - A benefits mangement framework for prioritisng programmes webinar
Q and A - A benefits mangement framework for prioritisng programmes webinar
 
MS Project 2010 Training
MS Project 2010 TrainingMS Project 2010 Training
MS Project 2010 Training
 

Recently uploaded

SPICE PARK APR2024 ( 6,793 SPICE Models )
SPICE PARK APR2024 ( 6,793 SPICE Models )SPICE PARK APR2024 ( 6,793 SPICE Models )
SPICE PARK APR2024 ( 6,793 SPICE Models )Tsuyoshi Horigome
 
MANUFACTURING PROCESS-II UNIT-2 LATHE MACHINE
MANUFACTURING PROCESS-II UNIT-2 LATHE MACHINEMANUFACTURING PROCESS-II UNIT-2 LATHE MACHINE
MANUFACTURING PROCESS-II UNIT-2 LATHE MACHINESIVASHANKAR N
 
Structural Analysis and Design of Foundations: A Comprehensive Handbook for S...
Structural Analysis and Design of Foundations: A Comprehensive Handbook for S...Structural Analysis and Design of Foundations: A Comprehensive Handbook for S...
Structural Analysis and Design of Foundations: A Comprehensive Handbook for S...Dr.Costas Sachpazis
 
(PRIYA) Rajgurunagar Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(PRIYA) Rajgurunagar Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...(PRIYA) Rajgurunagar Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(PRIYA) Rajgurunagar Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...ranjana rawat
 
HARMONY IN THE NATURE AND EXISTENCE - Unit-IV
HARMONY IN THE NATURE AND EXISTENCE - Unit-IVHARMONY IN THE NATURE AND EXISTENCE - Unit-IV
HARMONY IN THE NATURE AND EXISTENCE - Unit-IVRajaP95
 
Software Development Life Cycle By Team Orange (Dept. of Pharmacy)
Software Development Life Cycle By  Team Orange (Dept. of Pharmacy)Software Development Life Cycle By  Team Orange (Dept. of Pharmacy)
Software Development Life Cycle By Team Orange (Dept. of Pharmacy)Suman Mia
 
VIP Call Girls Service Kondapur Hyderabad Call +91-8250192130
VIP Call Girls Service Kondapur Hyderabad Call +91-8250192130VIP Call Girls Service Kondapur Hyderabad Call +91-8250192130
VIP Call Girls Service Kondapur Hyderabad Call +91-8250192130Suhani Kapoor
 
HARDNESS, FRACTURE TOUGHNESS AND STRENGTH OF CERAMICS
HARDNESS, FRACTURE TOUGHNESS AND STRENGTH OF CERAMICSHARDNESS, FRACTURE TOUGHNESS AND STRENGTH OF CERAMICS
HARDNESS, FRACTURE TOUGHNESS AND STRENGTH OF CERAMICSRajkumarAkumalla
 
UNIT-III FMM. DIMENSIONAL ANALYSIS
UNIT-III FMM.        DIMENSIONAL ANALYSISUNIT-III FMM.        DIMENSIONAL ANALYSIS
UNIT-III FMM. DIMENSIONAL ANALYSISrknatarajan
 
MANUFACTURING PROCESS-II UNIT-5 NC MACHINE TOOLS
MANUFACTURING PROCESS-II UNIT-5 NC MACHINE TOOLSMANUFACTURING PROCESS-II UNIT-5 NC MACHINE TOOLS
MANUFACTURING PROCESS-II UNIT-5 NC MACHINE TOOLSSIVASHANKAR N
 
UNIT-V FMM.HYDRAULIC TURBINE - Construction and working
UNIT-V FMM.HYDRAULIC TURBINE - Construction and workingUNIT-V FMM.HYDRAULIC TURBINE - Construction and working
UNIT-V FMM.HYDRAULIC TURBINE - Construction and workingrknatarajan
 
Top Rated Pune Call Girls Budhwar Peth ⟟ 6297143586 ⟟ Call Me For Genuine Se...
Top Rated  Pune Call Girls Budhwar Peth ⟟ 6297143586 ⟟ Call Me For Genuine Se...Top Rated  Pune Call Girls Budhwar Peth ⟟ 6297143586 ⟟ Call Me For Genuine Se...
Top Rated Pune Call Girls Budhwar Peth ⟟ 6297143586 ⟟ Call Me For Genuine Se...Call Girls in Nagpur High Profile
 
Call Girls in Nagpur Suman Call 7001035870 Meet With Nagpur Escorts
Call Girls in Nagpur Suman Call 7001035870 Meet With Nagpur EscortsCall Girls in Nagpur Suman Call 7001035870 Meet With Nagpur Escorts
Call Girls in Nagpur Suman Call 7001035870 Meet With Nagpur EscortsCall Girls in Nagpur High Profile
 
College Call Girls Nashik Nehal 7001305949 Independent Escort Service Nashik
College Call Girls Nashik Nehal 7001305949 Independent Escort Service NashikCollege Call Girls Nashik Nehal 7001305949 Independent Escort Service Nashik
College Call Girls Nashik Nehal 7001305949 Independent Escort Service NashikCall Girls in Nagpur High Profile
 
247267395-1-Symmetric-and-distributed-shared-memory-architectures-ppt (1).ppt
247267395-1-Symmetric-and-distributed-shared-memory-architectures-ppt (1).ppt247267395-1-Symmetric-and-distributed-shared-memory-architectures-ppt (1).ppt
247267395-1-Symmetric-and-distributed-shared-memory-architectures-ppt (1).pptssuser5c9d4b1
 
Microscopic Analysis of Ceramic Materials.pptx
Microscopic Analysis of Ceramic Materials.pptxMicroscopic Analysis of Ceramic Materials.pptx
Microscopic Analysis of Ceramic Materials.pptxpurnimasatapathy1234
 

Recently uploaded (20)

SPICE PARK APR2024 ( 6,793 SPICE Models )
SPICE PARK APR2024 ( 6,793 SPICE Models )SPICE PARK APR2024 ( 6,793 SPICE Models )
SPICE PARK APR2024 ( 6,793 SPICE Models )
 
MANUFACTURING PROCESS-II UNIT-2 LATHE MACHINE
MANUFACTURING PROCESS-II UNIT-2 LATHE MACHINEMANUFACTURING PROCESS-II UNIT-2 LATHE MACHINE
MANUFACTURING PROCESS-II UNIT-2 LATHE MACHINE
 
Structural Analysis and Design of Foundations: A Comprehensive Handbook for S...
Structural Analysis and Design of Foundations: A Comprehensive Handbook for S...Structural Analysis and Design of Foundations: A Comprehensive Handbook for S...
Structural Analysis and Design of Foundations: A Comprehensive Handbook for S...
 
(PRIYA) Rajgurunagar Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(PRIYA) Rajgurunagar Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...(PRIYA) Rajgurunagar Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(PRIYA) Rajgurunagar Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
 
HARMONY IN THE NATURE AND EXISTENCE - Unit-IV
HARMONY IN THE NATURE AND EXISTENCE - Unit-IVHARMONY IN THE NATURE AND EXISTENCE - Unit-IV
HARMONY IN THE NATURE AND EXISTENCE - Unit-IV
 
Call Us -/9953056974- Call Girls In Vikaspuri-/- Delhi NCR
Call Us -/9953056974- Call Girls In Vikaspuri-/- Delhi NCRCall Us -/9953056974- Call Girls In Vikaspuri-/- Delhi NCR
Call Us -/9953056974- Call Girls In Vikaspuri-/- Delhi NCR
 
Software Development Life Cycle By Team Orange (Dept. of Pharmacy)
Software Development Life Cycle By  Team Orange (Dept. of Pharmacy)Software Development Life Cycle By  Team Orange (Dept. of Pharmacy)
Software Development Life Cycle By Team Orange (Dept. of Pharmacy)
 
Roadmap to Membership of RICS - Pathways and Routes
Roadmap to Membership of RICS - Pathways and RoutesRoadmap to Membership of RICS - Pathways and Routes
Roadmap to Membership of RICS - Pathways and Routes
 
DJARUM4D - SLOT GACOR ONLINE | SLOT DEMO ONLINE
DJARUM4D - SLOT GACOR ONLINE | SLOT DEMO ONLINEDJARUM4D - SLOT GACOR ONLINE | SLOT DEMO ONLINE
DJARUM4D - SLOT GACOR ONLINE | SLOT DEMO ONLINE
 
VIP Call Girls Service Kondapur Hyderabad Call +91-8250192130
VIP Call Girls Service Kondapur Hyderabad Call +91-8250192130VIP Call Girls Service Kondapur Hyderabad Call +91-8250192130
VIP Call Girls Service Kondapur Hyderabad Call +91-8250192130
 
HARDNESS, FRACTURE TOUGHNESS AND STRENGTH OF CERAMICS
HARDNESS, FRACTURE TOUGHNESS AND STRENGTH OF CERAMICSHARDNESS, FRACTURE TOUGHNESS AND STRENGTH OF CERAMICS
HARDNESS, FRACTURE TOUGHNESS AND STRENGTH OF CERAMICS
 
UNIT-III FMM. DIMENSIONAL ANALYSIS
UNIT-III FMM.        DIMENSIONAL ANALYSISUNIT-III FMM.        DIMENSIONAL ANALYSIS
UNIT-III FMM. DIMENSIONAL ANALYSIS
 
MANUFACTURING PROCESS-II UNIT-5 NC MACHINE TOOLS
MANUFACTURING PROCESS-II UNIT-5 NC MACHINE TOOLSMANUFACTURING PROCESS-II UNIT-5 NC MACHINE TOOLS
MANUFACTURING PROCESS-II UNIT-5 NC MACHINE TOOLS
 
UNIT-V FMM.HYDRAULIC TURBINE - Construction and working
UNIT-V FMM.HYDRAULIC TURBINE - Construction and workingUNIT-V FMM.HYDRAULIC TURBINE - Construction and working
UNIT-V FMM.HYDRAULIC TURBINE - Construction and working
 
Top Rated Pune Call Girls Budhwar Peth ⟟ 6297143586 ⟟ Call Me For Genuine Se...
Top Rated  Pune Call Girls Budhwar Peth ⟟ 6297143586 ⟟ Call Me For Genuine Se...Top Rated  Pune Call Girls Budhwar Peth ⟟ 6297143586 ⟟ Call Me For Genuine Se...
Top Rated Pune Call Girls Budhwar Peth ⟟ 6297143586 ⟟ Call Me For Genuine Se...
 
Call Girls in Nagpur Suman Call 7001035870 Meet With Nagpur Escorts
Call Girls in Nagpur Suman Call 7001035870 Meet With Nagpur EscortsCall Girls in Nagpur Suman Call 7001035870 Meet With Nagpur Escorts
Call Girls in Nagpur Suman Call 7001035870 Meet With Nagpur Escorts
 
College Call Girls Nashik Nehal 7001305949 Independent Escort Service Nashik
College Call Girls Nashik Nehal 7001305949 Independent Escort Service NashikCollege Call Girls Nashik Nehal 7001305949 Independent Escort Service Nashik
College Call Girls Nashik Nehal 7001305949 Independent Escort Service Nashik
 
247267395-1-Symmetric-and-distributed-shared-memory-architectures-ppt (1).ppt
247267395-1-Symmetric-and-distributed-shared-memory-architectures-ppt (1).ppt247267395-1-Symmetric-and-distributed-shared-memory-architectures-ppt (1).ppt
247267395-1-Symmetric-and-distributed-shared-memory-architectures-ppt (1).ppt
 
Microscopic Analysis of Ceramic Materials.pptx
Microscopic Analysis of Ceramic Materials.pptxMicroscopic Analysis of Ceramic Materials.pptx
Microscopic Analysis of Ceramic Materials.pptx
 
9953056974 Call Girls In South Ex, Escorts (Delhi) NCR.pdf
9953056974 Call Girls In South Ex, Escorts (Delhi) NCR.pdf9953056974 Call Girls In South Ex, Escorts (Delhi) NCR.pdf
9953056974 Call Girls In South Ex, Escorts (Delhi) NCR.pdf
 

Loading cost in primavera schedule using resources and expenses r01

  • 1. 1 | P a g e Plusses and Minuses of Loading BOQ cost in “Resources” and “Expenses” in a primavera schedule. Mujahid Ishtiaq PMP® | PSP® | PMI-SP® | AMPC® Project Planner/Scheduler 17th February 2016.
  • 2. 2 | P a g e Contents Abstract ........................................................................................................................................... 3 Introduction..................................................................................................................................... 3 Comparison....................................................................................................................................... 3 1. Loading cost in “Resource”:....................................................................................................... 4 2. Loading cost in “Expense”:........................................................................................................ 8 Conclusion......................................................................................................................................... 9
  • 3. 3 | P a g e Abstract In our daily practice and here in GCC, normally we load BOQ cost in schedule as lump sum by creating a global resource or an expense item. First of all, it is not a proper way to add one resource and assign it to all activities giving it weighted or lump sum calculated cost for each activity. Proper and recommended way is to develop a complete resource pool, with correct resource types, units and rates. Moreover Expense item is used to load only non-variable or fixed cost types. But as mentioned earlier, in GCC, distribution of BOQ cost in schedule as lump sum for each activity has become normal practice. In this document some advantages and disadvantages of both options will be discussed and analysed. Introduction When we go for cost loading, one finds couple of ways to load cost in schedule as follows: 1. By creating a global cost resource, assigning it to multiple activities, exporting budgeted cost column in excel, populating budgeted cost column in excel and importing it back to P6. 2. Creating one or multiple expense items, assigning them to respective activities, exporting expense column in excel, populating expense column with calculated budgeted cost for each activity and importing back to p6. Although common purpose can be achieved in both ways, but sometimes there are situations when one has to select specific technique out of two. But if we don’t know exactly what other benefits or facilities we may lose by selecting a specific technique or what additional benefits can we get from one method, we will not be able to get complete sense of paybacks of Primavera. Comparison Here, we will discussed both options and their plusses and minuses so that one may consider all these points before selection of a method to load cost in schedule.
  • 4. 4 | P a g e 1. Loading cost in “Resource”:  One of the best advantages of loading cost in schedule using Global Cost Resource is that you can extract your cash flow at both early and late dates called “Early Cash Flow” and “Late Cash Flow”. These two types of cash flow are sometimes extremely important especially for management while making financial decisions for multiple projects to get answer of question “what is delay tolerance available in providing funding to a certain project at a certain point?” Figure 01 Early and Late Cash Flow. These cash flows are based on “Early Start & Finish” and “Late Start & Finish” dates of schedule activities or in other words we can say that these cash flows count on on floats available in non-critical activities.  Second advantage of loading cost through Global Cost Resource is “Resource Curves”. When resources perform work on an activity, you can choose how the resource units or costs are spread through time. This is done using a resource curve. To see this column, right-click on the Resources tab on an activity, customize the columns, and choose Curve. See figure 02 given below.
  • 5. 5 | P a g e A wealth of curves from which to choose is presented. These curves will determine how the effort and cost of a resource is spread over time. This could reflect expected cost for labor or the expected consumption of a material resource. Figure 02 Recourse Curves in Primavera. To view and modify resource curves, choose the menu Enterprise | Resource Curves. A list of resource curves, much like the one shown in Figure 3-1, appears. This screen allows you to modify, and delete curves. In the EPPM web client, resource curves are defined in the Resource Curves section under the Administer |Enterprise Data. Because so many standard curves come standard with P6, there may be no need to define your own. Besides the preloaded curves available in primavera, there is also an option available to add a customised curve or cost distribution along activity. To develop a customized curve, see figure 03-1 & figure 3-2 and follow given steps.
  • 6. 6 | P a g e Figure-03-1 Adding a customized resource curve. Figure-03-2 Adding a customized resource curve.  Auto compute actual is also a plus in loading cost using resource. Actual cost, remaining cost and at completion cost are auto-computed when you update activity by giving actual dates and remaining duration. To activate this option, you have to check Auto Compute Actuals option in resource details pan. See Figure-04.
  • 7. 7 | P a g e Figure-04 Auto Compute Actuals in Primavera P6  When you load cost in resources, you have access to different types of cost data as given below:  Budgeted Cost  Actual Cost  Actual Overtime Cost  Actual Regular Cost  Actual This Period Cost  Remaining Cost  At Completion Cost  Staffed Remaining Cost  Unstaffed Remaining Cost All these costs are available in the form of spread sheets giving you multiple data forms to analyse with respect to time and you can copy this data to excel to create attractive graphs and charts to present it to management.  Some planners feel it easy to handle (I don't know why…?).
  • 8. 8 | P a g e  A drawback of loading cost using Global Cost Resources is that you cannot feed cost to any activity before it commences (like upfront payments of subcontractors) or after activity is completed (like retentions etc.). Actuals of cost in resources will only incur once activity has started and cannot be adjust after activity is complete.  Another drawback of loading cost using Global Cost Resources is that you cannot assign resource to a milestone thus you cannot assign cost to a milestone, which sometime is required in schedule. 2. Loading cost in “Expense”:  The cost zeroing out is sometimes a problem when Remaining Duration equals Zero as may happen with resources. As explained earlier, sometimes costs are incurred in a cost management system after an activity is complete due to back charges or retention etc. So expenses allow you to re-adjust your actuals and remainders even after you have finished playing with your activity.  An additional benefit of loading cost using expense items is that, unlike resources, it allows cost to be incurred or adjusted before an activity even commences, representing a contractor’s upfront payment.  In loading cost using expense items, costs are not affected if remaining duration changes, which may happen with resources. Sometime cost to complete or remaining/actual cost has nothing to do with the remaining duration or % complete. So expenses give you option to manage cost regardless of how much duration is remaining or how much % of activity you have completed.  Unlike resources, you can assign expenses, which is cost, to a milestone.  Unavailability of Auto-compute actuals and remainders in expense items is sometimes considered a drawback as well. But it is not fact that expense items do not auto-compute actual, remaining and to complete cost. Expense items have ability to auto-compute actuals but this process is a little bit hard to understand. As a brief, auto-compute option in expense items works with our old friends the Planned Start and Planned Finish dates.
  • 9. 9 | P a g e For example, if activity’s schedule % complete is 0% but performance % complete is 10%, expense will not auto compute actual cost because 0% of scheduled work shows that planned start of activity has not kicked in yet. Similarly, when other variances occur between planned and actual dates, expense items do not auto-compute actuals because it works with planned dates.  In expense, there are very limited options to spread cost over activity duration. Unlike several pre-developed and customization options of resource curve in resources, expense give only 3 accrual types (At start, uniform, at end).  Unlike resources, In expense you have only following types of cost data:  Budgeted Cost  Actual Cost  Remaining Cost  At Completion Cost It means you will have to summarize all types of cost before you load into expenses. And later on if you need to insert separately some different costs like overtime cost etc. you cannot do that and you will have to merge it in actual cost. Conclusion To get accurate planned and actual progress, it is a must to load cost in schedule. And if it is required to load Lump sum BOQ cost in schedule, both methods can be used i.e. by creating a global cost resource or expense item. Both methods have their plusses and minuses as discussed in this document, but ultimate goal of loading BOQ cost in schedule can be achieved both ways. The only difference lies in privilege of analysing data and getting multiple options for this analysis. Discussion shows that benefits of using resource for cost loading overcome those of expense. Conditions which make expense to use for loading cost are rarely encountered. Regardless of everything, while loading cost in schedule one should positively look into the situation and conditions and should select the method which serves the purpose best.