SlideShare a Scribd company logo
Manual Assembly Lines
Sections:
1. Fundamentals of Manual Assembly Lines
2. Analysis of Single Model Assembly Lines
3. Line Balancing Algorithms
4. Other Considerations in Assembly Line Design
5. Alternative Assembly Systems
Manual Assembly Lines
§ Work systems consisting of multiple workers organized to produce a
single product or a limited range of products
§ Assembly workers perform tasks at workstations located along the
line-of-flow of the product
§ Usually a powered conveyor is used
§ Some of the workstations may be equipped with portable powered tools.
§ Factors favoring the use of assembly lines:
§ High or medium demand for product
§ Products are similar or identical
§ Total work content can be divided into work elements
§ To automate assembly tasks is impossible
Why Assembly Lines are Productive
§ Specialization of labor
§ When a large job is divided into small tasks and each task is
assigned to one worker, the worker becomes highly proficient at
performing the single task (Learning curve)
§ Interchangeable parts
§ Each component is manufactured to sufficiently close tolerances
that any part of a certain type can be selected at random for
assembly with its mating component.
§ Thanks to interchangeable parts, assemblies do not need fitting of
mating components
Some Definitions
§ Work flow
§ Each work unit should move steadily along the line
§ Line pacing
§ Workers must complete their tasks within a certain cycle time,
which will be the pace of the whole line
Manual Assembly Line
§ A production line that consists of a sequence of
workstations where assembly tasks are performed by
human workers
§ Products are assembled as they move along the line
§ At each station a portion of the total work content is performed on
each unit
§ Base parts are launched onto the beginning of the line at
regular intervals (cycle time)
§ Workers add components to progressively build the product
Manual Assembly Line
•Configuration of an n-workstation manual assembly line
•The production rate of an assembly line is determined by its slowest
station.
§Assembly workstation: A designated location along the work flow path
at which one or more work elements are performed by one or more
workers
Two assembly operators
working on an engine
assembly line (photo
courtesy of Ford Motor
Company)
Origin of Manual Assembly Line
Assembly Workstation
A designated location along the work flow path at which
one or more work elements are performed by one or more
workers
Typical operations performed at manual assembly stations
Adhesive application
Sealant application
Arc welding
Spot welding
Electrical connections
Component insertion
Press fitting
Riveting
Snap fitting
Soldering
Stitching/stapling
Threaded fasteners
Manning level
§ There may be more than one worker per station.
§ Utility workers: are not assigned to specific workstations.
§ They are responsible for
(1) helping workers who fall behind,
(2) relieving for workers for personal breaks,
(3) maintenance and repair
Manning level
§Average manning level:
where
M=average manning level of the line,
wu=number of utility workers assigned to the system, n=number of
workstations,
wi=number of workers assigned specifically to station i for i=1,…,n
n
ww
M
n
i
iu å=
+
= 1
Work Transport Systems-Manual Methods
§ Manual methods
§ Work units are moved between stations by the workers without
powered conveyor
§ Problems:
§ Starving of stations
§ The assembly operator has completed the assigned task on the
current work unit, but the next unit has not yet arrived at the station
§ Blocking of stations
§ The operator has completed the assigned task on the current work
unit but cannot pass the unit to the downstream station because that
worker is not yet ready to receive it.
Work Transport Systems-Manual Methods
§ To reduce starving,
§ use buffers
§ To prevent blocking,
§ provide space between upstream and downstream stations.
§ But both solutions can result in higher WIP,
§ which is economically undesirable.
Work Transport Systems-Mechanized
Methods
§ Continuously moving conveyor: operates at constant velocity
§ Work units are fixed to the conveyor
§ Worker moves alongside the line and back
§ Work units are removable from the conveyor
§ Synchronous transport (intermittent transport – stop-and-go line):
all work units are moved simultaneously between stations.
§ Problem: Incomplete units; excessive stress. Not common for
manual lines (variability).
§ Asynchronous transport : a work unit leaves a given station when
the assigned task is completed.
§ Variations in worker task times: small queues in front of each
station.
Coping with Product Variety
§ Single model assembly line (SMAL)
§ Every work unit is the same
§ Batch model assembly line (BMAL ) – multiple model line
§ Two or more different products
§ Products are so different that they must be made in batches with
setup between
§ Mixed model assembly line (MMAL)
§ Two or more different models
§ Differences are slight so models can be made simultaneously with
no downtime
Coping with Product Variety
§ Advantages of mixed models over batch order models
§ No production time is lost during changeovers
§ High inventories due to batch ordering are avoided
§ Production rates of different models can be adjusted as product demand
changes.
§ Disadvantages of mixed models over batch order models
§ Each station is equipped to perform variety of tasks (costly)
§ Scheduling and logistic activities are more difficult in this type of lines.
Alternative Assembly Systems:
§ A single station manual assembly cell
It consists of a single workplace in which the assembly work is accomplished
on the product or some major sub assembly of the product.
§ Assembly cells based on worker teams
It involves the use of multiple workers assigned to a common assembly task.
§ Automated assembly systems
Use automated methods at workstations rather than humans. These can be
type IA or type IIIA manufacturing systems.
Analysis of Single Model Lines
§The assembly line must be designed to achieve a
production rate sufficient to satisfy the demand.
§Demand rate → production rate→ cycle time
§Annual demand Da must be reduced to an hourly production
rate Rp
where
Sw = number of shifts/week
Hsh = number of hours/shift
shw
a
p
HS
D
R
50
=
Determining Cycle Time
Line efficiency: Uptime proportion. Accounts for lost production time due
to equipment failures, power outages, material unavailability, quality
problems, labor problems.
Production rate Rp is converted to a cycle time Tc, accounting for line
efficiency E
where 60 converts hourly production rate to cycle time in minutes, and E
= proportion uptime on the line
p
c
R
E
T
60
=
The cycle time Tc establishes the
ideal cycle rate for the line:
c
c
T
R
60
=
This Rc>Rp because line efficiency E is less
than 100%, Rc and Rp are related to E as
follows: c
p
R
R
E =
Number of workers on the production line
AT
WL
w =
Determining Efficiency
Number of Workers Required
Work load: Available Time:
The theoretical minimum number of workers (assuming
workers spend all their time on the product) on the line is
determined as:
w* = Minimum Integer ³
where
Twc = work content time, min; Tc = cycle time, min/worker
If we assume one worker per station then this gives the
minimum number of stations
c
wc
T
T
c
wc
wcp
T
TE
WL
TRWL
×
=
×=
60
EAT 60=
Theoretical Minimum Not Possible
§ Repositioning losses: Some time will be lost at each
station every cycle for repositioning the worker or the work
unit; thus, the workers will not have the entire Tc each
cycle
§ Line balancing problem: It is not possible to divide the
work content time evenly among workers, and some
workers will have an amount of work that is less than Tc.
§ Task time variability: Inherent and unavoidable variability
in the time required by a worker to perform a given
assembly task.
§ Quality problems: Defective components and other
quality problems cause delays and rework that add to the
work load.
Repositioning Losses
Repositioning losses occur on a production line because
some time is required each cycle to reposition the worker, the
work unit, or both
§ Repositioning time = Tr
Service time = time available each cycle for the worker to
work on the product
§ Service time Ts = Max{Tsi} ≤Tc – Tr
Repositioning efficiency Er =
c
rc
c
s
T
TT
T
T -
=
Cycle Time on an Assembly Line
Components of cycle time at several stations on a manual
assembly line
Tsi=service time, Tr=repositioning time
Line Balancing Problem
Given:
§ The total work content consists of many distinct work
elements
§ The sequence in which the elements can be performed is
restricted
§ The line must operate at a specified cycle time
The Problem:
§ To assign the individual work elements to workstations so
that all workers have an equal amount of work to perform
Line balancing problem:
§ The line balancing problem is concerned with assigning
the individual work.
§ Two important concepts in line balancing are the
separation of the total work content into minimum
rotational work elements and the precedence constraints.
§ Minimum rotational work elements: å
=
=
en
k
ekwc TT
1
Tek : Time to perform work element k
ne : Number of work elements
Work element times
§ Work elements are assigned to station i that add up to the
service time for that station
§ The station service times must add up to the total work
content time
åÎ
=
ik
eksi TT
å
=
=
n
k
siwc TT
1
Precedence Constraints
§ Precedence constraints: The variation in element times
that make it difficult to obtain equal service times for all
stations, there are restrictions on the order in which work
elements can be performed. These technological
requirements on the work sequence are called
precedence constraints.
Precedence
diagram
Formulae:
§ Balance efficiency:
§ Balance delay:
§ Note that :
s
wc
b
wT
T
E =
( )
s
wcs
wT
TwT
d
-
=
1=+dEb
Worker requirements:
Three factors that reduce the productivity of a manual
assembly line:
§ Line efficiency (E)
§ Repositioning efficiency (Er)
§ Balancing efficiency (Eb)
§ Labor efficiency on the assembly line=
§ More realistic value for the number of workers on
assembly line is:
br EEE
sb
wc
cbr
wc
br
wcp
TE
T
TEE
T
EEE
TR
w ==³=*
60
IntegerMinimum
Work stations considerations:
§ If the manning level is one for all stations, then the number
of stations is equal to the number of workers.
§ Total length of the assembly line :
§ Feed rate:
§ Center to center spacing between
base parts:
M
w
n =
å
=
=
n
i
siLL
1
c
p
T
f
1
=
cc
p
c
p Tv
f
v
s ==
contd…
§ Tolerance time:
§ Ratio:
§ Elapsed time :
c
si
t
v
L
T =
t
c
Tn
V
L
ET ×==
0.1@
c
t
T
T
Line Balancing Objective
To distribute the total work content on the assembly line as
evenly as possible among the workers
§ Minimize (wTs – Twc)
or
§ Minimize (Ts - Tsi)
Subject to: (1) £ Ts
(2) all precedence requirements are obeyed
∑
∈ik
ekT
∑
1=
w
i
Line Balancing Algorithms
1. Largest candidate rule
2. Kilbridge and Wester method
3. Ranked positional weights method, also known as the
Helgeson and Birne method
In the following descriptions, assume one worker per
workstation
Largest Candidate Rule
List all work elements in descending order based on their Tek
values; then,
1. Start at the top of the list and selecting the first element
that satisfies precedence requirements and does not
cause the total sum of Tek to exceed the allowable Ts
value
When an element is assigned, start back at the top of the
list and repeat selection process
2. When no more elements can be assigned to the current
station, proceed to next station
3. Repeat steps 1 and 2 until all elements have been
assigned to as many stations as needed
Solution for Largest Candidate Rule
Solution for Largest Candidate Rule
Physical layout of workstations and assignment of elements
to stations using the largest candidate rule
Kilbridge and Wester Method
Arrange work elements into columns according to their
positions in the precedence diagram
§ Work elements are then organized into a list according to
their columns, starting with the elements in the first column
§ Proceed with same steps 1, 2, and 3 as in the largest
candidate rule
Kilbridge & Wester Method
Arrangement
of elements
into columns
for the K&W
algorithm
Ranked Positional Weights Method
A ranked position weight (RPW) is calculated for each
work element
§ RPW for element k is calculated by summing the Te values
for all of the elements that follow element k in the diagram
plus Tek itself
§ Work elements are then organized into a list according to
their RPW values, starting with the element that has the
highest RPW value
§ Proceed with same steps 1, 2, and 3 as in the largest
candidate rule
Other Considerations in Line Design
§ Methods analysis
§ To analyze methods at bottleneck or other troublesome
workstations
§ Subdividing work elements
§ Sharing work elements between two adjacent stations
§ Utility workers
§ To relieve congestion at stations that are temporarily
overloaded
§ Changing work head speeds at mechanized stations
§ Preassembly of components
§ Prepare certain subassemblies off-line to reduce work
content time on the final assembly line
Other Considerations - continued
§ Storage buffers between stations
§ To permit continued operation of certain sections of the
line when other sections break down
§ To smooth production between stations with large task
time variations
§ Zoning and other constraints
§ Parallel stations
§ To reduce time at bottleneck stations that have
unusually long task times
Alternative Assembly Systems
§ Single-station manual assembly cell
§ A single workstation in which all of the assembly work
is accomplished on the product or on some major
subassembly
§ Common for complex products produced in small
quantities, sometimes one of a kind
§ Assembly by worker teams
§ Multiple workers assigned to a common assembly task
§ Advantage: greater worker satisfaction
§ Disadvantage: slower than line production
Queries?
Thank You

More Related Content

What's hot

Chapter 1 introduction to manufacturing system
Chapter 1   introduction to manufacturing systemChapter 1   introduction to manufacturing system
Chapter 1 introduction to manufacturing system
N. A. Sutisna
 
COMPUTER AIDED PROCESS PLANNING
COMPUTER AIDED PROCESS PLANNINGCOMPUTER AIDED PROCESS PLANNING
COMPUTER AIDED PROCESS PLANNING
jntuhcej
 
Cellular manufacturing
Cellular manufacturingCellular manufacturing
Cellular manufacturing
ananya0122
 
FLEXIBLE MANUFACTURING SYSTEM
FLEXIBLE MANUFACTURING SYSTEMFLEXIBLE MANUFACTURING SYSTEM
FLEXIBLE MANUFACTURING SYSTEMAnand Khare
 
Flexible manufacturing systems
Flexible manufacturing systems Flexible manufacturing systems
Flexible manufacturing systems
Nityanand Yadav
 
Computer Aided Process Planning (CAPP)
Computer Aided Process Planning (CAPP)Computer Aided Process Planning (CAPP)
Computer Aided Process Planning (CAPP)
Pratik Gandhi
 
Automated assembly systems
Automated assembly systemsAutomated assembly systems
Automated assembly systems
Vibhas Purushu
 
PPCE unit 2 (ME8793 – PROCESS PLANNING AND COST ESTIMATION )
PPCE unit 2 (ME8793 – PROCESS PLANNING AND COST ESTIMATION )PPCE unit 2 (ME8793 – PROCESS PLANNING AND COST ESTIMATION )
PPCE unit 2 (ME8793 – PROCESS PLANNING AND COST ESTIMATION )
TAMILMECHKIT
 
Manual Assembly Lines1
Manual Assembly Lines1Manual Assembly Lines1
Manual Assembly Lines1
VADLAJAGADEESHWARAAC
 
Group technology
Group technologyGroup technology
Group technology
jntuhcej
 
CELLULAR MANUFACTURING & FLEXIBLE MANUFACTURING SYSTEM - UNIT 5 - CAD & M
CELLULAR MANUFACTURING & FLEXIBLE MANUFACTURING SYSTEM - UNIT 5 - CAD & MCELLULAR MANUFACTURING & FLEXIBLE MANUFACTURING SYSTEM - UNIT 5 - CAD & M
CELLULAR MANUFACTURING & FLEXIBLE MANUFACTURING SYSTEM - UNIT 5 - CAD & M
Balamurugan Subburaj
 
Group Technology
Group TechnologyGroup Technology
Group Technology
Himanshi Gupta
 
Cnc machine centre
Cnc machine centreCnc machine centre
Cnc machine centre
Shrikunj Patel
 
Cellular Manufacturing
Cellular ManufacturingCellular Manufacturing
Cellular ManufacturingSagar Kurde
 
3 numerical control
3 numerical control3 numerical control
3 numerical control
shaikusmanshag
 
Group technology _ flexible manufacturing system_supply chain management
Group technology _ flexible manufacturing system_supply chain managementGroup technology _ flexible manufacturing system_supply chain management
Group technology _ flexible manufacturing system_supply chain management
Pankaj Kumar
 
Group Technology
Group TechnologyGroup Technology
Group Technology
Sunith Guraddi
 
Process Planning
Process PlanningProcess Planning
Process Planning
Guhan M
 
Flexible Manufacturing System
Flexible Manufacturing SystemFlexible Manufacturing System
Flexible Manufacturing SystemVishal Jadhav
 
Cnc feed drives
Cnc feed drivesCnc feed drives
Cnc feed drives
Akhil Krishnan G
 

What's hot (20)

Chapter 1 introduction to manufacturing system
Chapter 1   introduction to manufacturing systemChapter 1   introduction to manufacturing system
Chapter 1 introduction to manufacturing system
 
COMPUTER AIDED PROCESS PLANNING
COMPUTER AIDED PROCESS PLANNINGCOMPUTER AIDED PROCESS PLANNING
COMPUTER AIDED PROCESS PLANNING
 
Cellular manufacturing
Cellular manufacturingCellular manufacturing
Cellular manufacturing
 
FLEXIBLE MANUFACTURING SYSTEM
FLEXIBLE MANUFACTURING SYSTEMFLEXIBLE MANUFACTURING SYSTEM
FLEXIBLE MANUFACTURING SYSTEM
 
Flexible manufacturing systems
Flexible manufacturing systems Flexible manufacturing systems
Flexible manufacturing systems
 
Computer Aided Process Planning (CAPP)
Computer Aided Process Planning (CAPP)Computer Aided Process Planning (CAPP)
Computer Aided Process Planning (CAPP)
 
Automated assembly systems
Automated assembly systemsAutomated assembly systems
Automated assembly systems
 
PPCE unit 2 (ME8793 – PROCESS PLANNING AND COST ESTIMATION )
PPCE unit 2 (ME8793 – PROCESS PLANNING AND COST ESTIMATION )PPCE unit 2 (ME8793 – PROCESS PLANNING AND COST ESTIMATION )
PPCE unit 2 (ME8793 – PROCESS PLANNING AND COST ESTIMATION )
 
Manual Assembly Lines1
Manual Assembly Lines1Manual Assembly Lines1
Manual Assembly Lines1
 
Group technology
Group technologyGroup technology
Group technology
 
CELLULAR MANUFACTURING & FLEXIBLE MANUFACTURING SYSTEM - UNIT 5 - CAD & M
CELLULAR MANUFACTURING & FLEXIBLE MANUFACTURING SYSTEM - UNIT 5 - CAD & MCELLULAR MANUFACTURING & FLEXIBLE MANUFACTURING SYSTEM - UNIT 5 - CAD & M
CELLULAR MANUFACTURING & FLEXIBLE MANUFACTURING SYSTEM - UNIT 5 - CAD & M
 
Group Technology
Group TechnologyGroup Technology
Group Technology
 
Cnc machine centre
Cnc machine centreCnc machine centre
Cnc machine centre
 
Cellular Manufacturing
Cellular ManufacturingCellular Manufacturing
Cellular Manufacturing
 
3 numerical control
3 numerical control3 numerical control
3 numerical control
 
Group technology _ flexible manufacturing system_supply chain management
Group technology _ flexible manufacturing system_supply chain managementGroup technology _ flexible manufacturing system_supply chain management
Group technology _ flexible manufacturing system_supply chain management
 
Group Technology
Group TechnologyGroup Technology
Group Technology
 
Process Planning
Process PlanningProcess Planning
Process Planning
 
Flexible Manufacturing System
Flexible Manufacturing SystemFlexible Manufacturing System
Flexible Manufacturing System
 
Cnc feed drives
Cnc feed drivesCnc feed drives
Cnc feed drives
 

Similar to Manual Assembly Lines

Aiar. unit ii. transfer lines
Aiar. unit ii. transfer linesAiar. unit ii. transfer lines
Aiar. unit ii. transfer lines
Kunal mane
 
07 Line Balancing
07 Line Balancing07 Line Balancing
07 Line Balancing
Arif Rahman
 
Industrial engineeering pli
Industrial engineeering   pliIndustrial engineeering   pli
Industrial engineeering pli
Dhyey Shukla
 
MA1.ppt
MA1.pptMA1.ppt
MA1.ppt
VivekC49
 
Process Selection and Facility layout.ppt
Process Selection and Facility layout.pptProcess Selection and Facility layout.ppt
Process Selection and Facility layout.ppt
SandipanMaji3
 
Introduction to Cellular Manufacturing - ADDVALUE - Nilesh Arora
Introduction to Cellular Manufacturing - ADDVALUE - Nilesh AroraIntroduction to Cellular Manufacturing - ADDVALUE - Nilesh Arora
Introduction to Cellular Manufacturing - ADDVALUE - Nilesh Arora
ADD VALUE CONSULTING Inc
 
05 single station
05 single station05 single station
05 single station
Arif Rahman
 
Robot work cell layout.pptx
Robot work cell layout.pptxRobot work cell layout.pptx
Robot work cell layout.pptx
SandeepSingh286037
 
CIM 15ME62 Module-3
CIM 15ME62  Module-3CIM 15ME62  Module-3
CIM 15ME62 Module-3
Dr. Bhimsen Soragaon
 
Unit 3 Manufacturing Systems in automation
Unit 3 Manufacturing Systems in automationUnit 3 Manufacturing Systems in automation
Unit 3 Manufacturing Systems in automation
rahulkatre9
 
Line balancing
Line balancingLine balancing
Line balancing
Jibin Paulose
 
Meenakshi mam Types of plant layout video.ppt
Meenakshi mam Types of plant layout video.pptMeenakshi mam Types of plant layout video.ppt
Meenakshi mam Types of plant layout video.ppt
tommychauhan
 
FMS_Lecture_1_Intro.pptx
FMS_Lecture_1_Intro.pptxFMS_Lecture_1_Intro.pptx
FMS_Lecture_1_Intro.pptx
Janak Valaki (PhD)
 
PRODUCTIVITY IMPROVEMENT OF AUTOMOTIVE ASSEMBLY LINE THROUGH LINE BALANCING
PRODUCTIVITY IMPROVEMENT OF AUTOMOTIVE ASSEMBLY LINE THROUGH LINE BALANCINGPRODUCTIVITY IMPROVEMENT OF AUTOMOTIVE ASSEMBLY LINE THROUGH LINE BALANCING
PRODUCTIVITY IMPROVEMENT OF AUTOMOTIVE ASSEMBLY LINE THROUGH LINE BALANCING
International Journal of Technical Research & Application
 
Line balancing and heuristics
Line balancing and heuristicsLine balancing and heuristics
Line balancing and heuristics
Abrity Bhattacharya
 
Assembly systems & line balance
Assembly systems & line balanceAssembly systems & line balance
Assembly systems & line balanceSudhir Reddy
 
assemblysystemslinebalance-130718104948-phpapp02.pdf
assemblysystemslinebalance-130718104948-phpapp02.pdfassemblysystemslinebalance-130718104948-phpapp02.pdf
assemblysystemslinebalance-130718104948-phpapp02.pdf
AshokPhotography
 
ETAP - reliability assesment
ETAP - reliability assesmentETAP - reliability assesment
ETAP - reliability assesment
Himmelstern
 

Similar to Manual Assembly Lines (20)

Aiar. unit ii. transfer lines
Aiar. unit ii. transfer linesAiar. unit ii. transfer lines
Aiar. unit ii. transfer lines
 
LINE PACING ETC...ppt
LINE PACING  ETC...pptLINE PACING  ETC...ppt
LINE PACING ETC...ppt
 
LINE PACING ETC..-2.ppt
LINE PACING  ETC..-2.pptLINE PACING  ETC..-2.ppt
LINE PACING ETC..-2.ppt
 
07 Line Balancing
07 Line Balancing07 Line Balancing
07 Line Balancing
 
Industrial engineeering pli
Industrial engineeering   pliIndustrial engineeering   pli
Industrial engineeering pli
 
MA1.ppt
MA1.pptMA1.ppt
MA1.ppt
 
Process Selection and Facility layout.ppt
Process Selection and Facility layout.pptProcess Selection and Facility layout.ppt
Process Selection and Facility layout.ppt
 
Introduction to Cellular Manufacturing - ADDVALUE - Nilesh Arora
Introduction to Cellular Manufacturing - ADDVALUE - Nilesh AroraIntroduction to Cellular Manufacturing - ADDVALUE - Nilesh Arora
Introduction to Cellular Manufacturing - ADDVALUE - Nilesh Arora
 
05 single station
05 single station05 single station
05 single station
 
Robot work cell layout.pptx
Robot work cell layout.pptxRobot work cell layout.pptx
Robot work cell layout.pptx
 
CIM 15ME62 Module-3
CIM 15ME62  Module-3CIM 15ME62  Module-3
CIM 15ME62 Module-3
 
Unit 3 Manufacturing Systems in automation
Unit 3 Manufacturing Systems in automationUnit 3 Manufacturing Systems in automation
Unit 3 Manufacturing Systems in automation
 
Line balancing
Line balancingLine balancing
Line balancing
 
Meenakshi mam Types of plant layout video.ppt
Meenakshi mam Types of plant layout video.pptMeenakshi mam Types of plant layout video.ppt
Meenakshi mam Types of plant layout video.ppt
 
FMS_Lecture_1_Intro.pptx
FMS_Lecture_1_Intro.pptxFMS_Lecture_1_Intro.pptx
FMS_Lecture_1_Intro.pptx
 
PRODUCTIVITY IMPROVEMENT OF AUTOMOTIVE ASSEMBLY LINE THROUGH LINE BALANCING
PRODUCTIVITY IMPROVEMENT OF AUTOMOTIVE ASSEMBLY LINE THROUGH LINE BALANCINGPRODUCTIVITY IMPROVEMENT OF AUTOMOTIVE ASSEMBLY LINE THROUGH LINE BALANCING
PRODUCTIVITY IMPROVEMENT OF AUTOMOTIVE ASSEMBLY LINE THROUGH LINE BALANCING
 
Line balancing and heuristics
Line balancing and heuristicsLine balancing and heuristics
Line balancing and heuristics
 
Assembly systems & line balance
Assembly systems & line balanceAssembly systems & line balance
Assembly systems & line balance
 
assemblysystemslinebalance-130718104948-phpapp02.pdf
assemblysystemslinebalance-130718104948-phpapp02.pdfassemblysystemslinebalance-130718104948-phpapp02.pdf
assemblysystemslinebalance-130718104948-phpapp02.pdf
 
ETAP - reliability assesment
ETAP - reliability assesmentETAP - reliability assesment
ETAP - reliability assesment
 

More from VADLAJAGADEESHWARAAC

MACHINING WITH CRYOGENCALLY TREATED tungsten carbide TOOL INSERTS
MACHINING WITH CRYOGENCALLY TREATED tungsten carbide TOOL INSERTSMACHINING WITH CRYOGENCALLY TREATED tungsten carbide TOOL INSERTS
MACHINING WITH CRYOGENCALLY TREATED tungsten carbide TOOL INSERTS
VADLAJAGADEESHWARAAC
 
Introduction to Flexible Manufacturing System (FMS)
Introduction to Flexible Manufacturing System (FMS)Introduction to Flexible Manufacturing System (FMS)
Introduction to Flexible Manufacturing System (FMS)
VADLAJAGADEESHWARAAC
 
Cellular Manufacturing
Cellular ManufacturingCellular Manufacturing
Cellular Manufacturing
VADLAJAGADEESHWARAAC
 
Flexible Manufacturing System.
Flexible Manufacturing System.Flexible Manufacturing System.
Flexible Manufacturing System.
VADLAJAGADEESHWARAAC
 
MANUFACTURING SYSTEMS PROJECT
MANUFACTURING SYSTEMS PROJECTMANUFACTURING SYSTEMS PROJECT
MANUFACTURING SYSTEMS PROJECT
VADLAJAGADEESHWARAAC
 
Flexible Manufacturing Systems
Flexible Manufacturing SystemsFlexible Manufacturing Systems
Flexible Manufacturing Systems
VADLAJAGADEESHWARAAC
 
Flexible Manufacturing System.
Flexible Manufacturing System.Flexible Manufacturing System.
Flexible Manufacturing System.
VADLAJAGADEESHWARAAC
 
Automated Assembly Systems
Automated Assembly SystemsAutomated Assembly Systems
Automated Assembly Systems
VADLAJAGADEESHWARAAC
 
material handling systems
material handling systemsmaterial handling systems
material handling systems
VADLAJAGADEESHWARAAC
 

More from VADLAJAGADEESHWARAAC (9)

MACHINING WITH CRYOGENCALLY TREATED tungsten carbide TOOL INSERTS
MACHINING WITH CRYOGENCALLY TREATED tungsten carbide TOOL INSERTSMACHINING WITH CRYOGENCALLY TREATED tungsten carbide TOOL INSERTS
MACHINING WITH CRYOGENCALLY TREATED tungsten carbide TOOL INSERTS
 
Introduction to Flexible Manufacturing System (FMS)
Introduction to Flexible Manufacturing System (FMS)Introduction to Flexible Manufacturing System (FMS)
Introduction to Flexible Manufacturing System (FMS)
 
Cellular Manufacturing
Cellular ManufacturingCellular Manufacturing
Cellular Manufacturing
 
Flexible Manufacturing System.
Flexible Manufacturing System.Flexible Manufacturing System.
Flexible Manufacturing System.
 
MANUFACTURING SYSTEMS PROJECT
MANUFACTURING SYSTEMS PROJECTMANUFACTURING SYSTEMS PROJECT
MANUFACTURING SYSTEMS PROJECT
 
Flexible Manufacturing Systems
Flexible Manufacturing SystemsFlexible Manufacturing Systems
Flexible Manufacturing Systems
 
Flexible Manufacturing System.
Flexible Manufacturing System.Flexible Manufacturing System.
Flexible Manufacturing System.
 
Automated Assembly Systems
Automated Assembly SystemsAutomated Assembly Systems
Automated Assembly Systems
 
material handling systems
material handling systemsmaterial handling systems
material handling systems
 

Recently uploaded

ASME IX(9) 2007 Full Version .pdf
ASME IX(9)  2007 Full Version       .pdfASME IX(9)  2007 Full Version       .pdf
ASME IX(9) 2007 Full Version .pdf
AhmedHussein950959
 
CFD Simulation of By-pass Flow in a HRSG module by R&R Consult.pptx
CFD Simulation of By-pass Flow in a HRSG module by R&R Consult.pptxCFD Simulation of By-pass Flow in a HRSG module by R&R Consult.pptx
CFD Simulation of By-pass Flow in a HRSG module by R&R Consult.pptx
R&R Consult
 
Student information management system project report ii.pdf
Student information management system project report ii.pdfStudent information management system project report ii.pdf
Student information management system project report ii.pdf
Kamal Acharya
 
AKS UNIVERSITY Satna Final Year Project By OM Hardaha.pdf
AKS UNIVERSITY Satna Final Year Project By OM Hardaha.pdfAKS UNIVERSITY Satna Final Year Project By OM Hardaha.pdf
AKS UNIVERSITY Satna Final Year Project By OM Hardaha.pdf
SamSarthak3
 
The Benefits and Techniques of Trenchless Pipe Repair.pdf
The Benefits and Techniques of Trenchless Pipe Repair.pdfThe Benefits and Techniques of Trenchless Pipe Repair.pdf
The Benefits and Techniques of Trenchless Pipe Repair.pdf
Pipe Restoration Solutions
 
Railway Signalling Principles Edition 3.pdf
Railway Signalling Principles Edition 3.pdfRailway Signalling Principles Edition 3.pdf
Railway Signalling Principles Edition 3.pdf
TeeVichai
 
RAT: Retrieval Augmented Thoughts Elicit Context-Aware Reasoning in Long-Hori...
RAT: Retrieval Augmented Thoughts Elicit Context-Aware Reasoning in Long-Hori...RAT: Retrieval Augmented Thoughts Elicit Context-Aware Reasoning in Long-Hori...
RAT: Retrieval Augmented Thoughts Elicit Context-Aware Reasoning in Long-Hori...
thanhdowork
 
Sachpazis:Terzaghi Bearing Capacity Estimation in simple terms with Calculati...
Sachpazis:Terzaghi Bearing Capacity Estimation in simple terms with Calculati...Sachpazis:Terzaghi Bearing Capacity Estimation in simple terms with Calculati...
Sachpazis:Terzaghi Bearing Capacity Estimation in simple terms with Calculati...
Dr.Costas Sachpazis
 
ML for identifying fraud using open blockchain data.pptx
ML for identifying fraud using open blockchain data.pptxML for identifying fraud using open blockchain data.pptx
ML for identifying fraud using open blockchain data.pptx
Vijay Dialani, PhD
 
space technology lecture notes on satellite
space technology lecture notes on satellitespace technology lecture notes on satellite
space technology lecture notes on satellite
ongomchris
 
HYDROPOWER - Hydroelectric power generation
HYDROPOWER - Hydroelectric power generationHYDROPOWER - Hydroelectric power generation
HYDROPOWER - Hydroelectric power generation
Robbie Edward Sayers
 
road safety engineering r s e unit 3.pdf
road safety engineering  r s e unit 3.pdfroad safety engineering  r s e unit 3.pdf
road safety engineering r s e unit 3.pdf
VENKATESHvenky89705
 
Industrial Training at Shahjalal Fertilizer Company Limited (SFCL)
Industrial Training at Shahjalal Fertilizer Company Limited (SFCL)Industrial Training at Shahjalal Fertilizer Company Limited (SFCL)
Industrial Training at Shahjalal Fertilizer Company Limited (SFCL)
MdTanvirMahtab2
 
Planning Of Procurement o different goods and services
Planning Of Procurement o different goods and servicesPlanning Of Procurement o different goods and services
Planning Of Procurement o different goods and services
JoytuBarua2
 
一比一原版(SFU毕业证)西蒙菲莎大学毕业证成绩单如何办理
一比一原版(SFU毕业证)西蒙菲莎大学毕业证成绩单如何办理一比一原版(SFU毕业证)西蒙菲莎大学毕业证成绩单如何办理
一比一原版(SFU毕业证)西蒙菲莎大学毕业证成绩单如何办理
bakpo1
 
Design and Analysis of Algorithms-DP,Backtracking,Graphs,B&B
Design and Analysis of Algorithms-DP,Backtracking,Graphs,B&BDesign and Analysis of Algorithms-DP,Backtracking,Graphs,B&B
Design and Analysis of Algorithms-DP,Backtracking,Graphs,B&B
Sreedhar Chowdam
 
Governing Equations for Fundamental Aerodynamics_Anderson2010.pdf
Governing Equations for Fundamental Aerodynamics_Anderson2010.pdfGoverning Equations for Fundamental Aerodynamics_Anderson2010.pdf
Governing Equations for Fundamental Aerodynamics_Anderson2010.pdf
WENKENLI1
 
ethical hacking in wireless-hacking1.ppt
ethical hacking in wireless-hacking1.pptethical hacking in wireless-hacking1.ppt
ethical hacking in wireless-hacking1.ppt
Jayaprasanna4
 
Hybrid optimization of pumped hydro system and solar- Engr. Abdul-Azeez.pdf
Hybrid optimization of pumped hydro system and solar- Engr. Abdul-Azeez.pdfHybrid optimization of pumped hydro system and solar- Engr. Abdul-Azeez.pdf
Hybrid optimization of pumped hydro system and solar- Engr. Abdul-Azeez.pdf
fxintegritypublishin
 
J.Yang, ICLR 2024, MLILAB, KAIST AI.pdf
J.Yang,  ICLR 2024, MLILAB, KAIST AI.pdfJ.Yang,  ICLR 2024, MLILAB, KAIST AI.pdf
J.Yang, ICLR 2024, MLILAB, KAIST AI.pdf
MLILAB
 

Recently uploaded (20)

ASME IX(9) 2007 Full Version .pdf
ASME IX(9)  2007 Full Version       .pdfASME IX(9)  2007 Full Version       .pdf
ASME IX(9) 2007 Full Version .pdf
 
CFD Simulation of By-pass Flow in a HRSG module by R&R Consult.pptx
CFD Simulation of By-pass Flow in a HRSG module by R&R Consult.pptxCFD Simulation of By-pass Flow in a HRSG module by R&R Consult.pptx
CFD Simulation of By-pass Flow in a HRSG module by R&R Consult.pptx
 
Student information management system project report ii.pdf
Student information management system project report ii.pdfStudent information management system project report ii.pdf
Student information management system project report ii.pdf
 
AKS UNIVERSITY Satna Final Year Project By OM Hardaha.pdf
AKS UNIVERSITY Satna Final Year Project By OM Hardaha.pdfAKS UNIVERSITY Satna Final Year Project By OM Hardaha.pdf
AKS UNIVERSITY Satna Final Year Project By OM Hardaha.pdf
 
The Benefits and Techniques of Trenchless Pipe Repair.pdf
The Benefits and Techniques of Trenchless Pipe Repair.pdfThe Benefits and Techniques of Trenchless Pipe Repair.pdf
The Benefits and Techniques of Trenchless Pipe Repair.pdf
 
Railway Signalling Principles Edition 3.pdf
Railway Signalling Principles Edition 3.pdfRailway Signalling Principles Edition 3.pdf
Railway Signalling Principles Edition 3.pdf
 
RAT: Retrieval Augmented Thoughts Elicit Context-Aware Reasoning in Long-Hori...
RAT: Retrieval Augmented Thoughts Elicit Context-Aware Reasoning in Long-Hori...RAT: Retrieval Augmented Thoughts Elicit Context-Aware Reasoning in Long-Hori...
RAT: Retrieval Augmented Thoughts Elicit Context-Aware Reasoning in Long-Hori...
 
Sachpazis:Terzaghi Bearing Capacity Estimation in simple terms with Calculati...
Sachpazis:Terzaghi Bearing Capacity Estimation in simple terms with Calculati...Sachpazis:Terzaghi Bearing Capacity Estimation in simple terms with Calculati...
Sachpazis:Terzaghi Bearing Capacity Estimation in simple terms with Calculati...
 
ML for identifying fraud using open blockchain data.pptx
ML for identifying fraud using open blockchain data.pptxML for identifying fraud using open blockchain data.pptx
ML for identifying fraud using open blockchain data.pptx
 
space technology lecture notes on satellite
space technology lecture notes on satellitespace technology lecture notes on satellite
space technology lecture notes on satellite
 
HYDROPOWER - Hydroelectric power generation
HYDROPOWER - Hydroelectric power generationHYDROPOWER - Hydroelectric power generation
HYDROPOWER - Hydroelectric power generation
 
road safety engineering r s e unit 3.pdf
road safety engineering  r s e unit 3.pdfroad safety engineering  r s e unit 3.pdf
road safety engineering r s e unit 3.pdf
 
Industrial Training at Shahjalal Fertilizer Company Limited (SFCL)
Industrial Training at Shahjalal Fertilizer Company Limited (SFCL)Industrial Training at Shahjalal Fertilizer Company Limited (SFCL)
Industrial Training at Shahjalal Fertilizer Company Limited (SFCL)
 
Planning Of Procurement o different goods and services
Planning Of Procurement o different goods and servicesPlanning Of Procurement o different goods and services
Planning Of Procurement o different goods and services
 
一比一原版(SFU毕业证)西蒙菲莎大学毕业证成绩单如何办理
一比一原版(SFU毕业证)西蒙菲莎大学毕业证成绩单如何办理一比一原版(SFU毕业证)西蒙菲莎大学毕业证成绩单如何办理
一比一原版(SFU毕业证)西蒙菲莎大学毕业证成绩单如何办理
 
Design and Analysis of Algorithms-DP,Backtracking,Graphs,B&B
Design and Analysis of Algorithms-DP,Backtracking,Graphs,B&BDesign and Analysis of Algorithms-DP,Backtracking,Graphs,B&B
Design and Analysis of Algorithms-DP,Backtracking,Graphs,B&B
 
Governing Equations for Fundamental Aerodynamics_Anderson2010.pdf
Governing Equations for Fundamental Aerodynamics_Anderson2010.pdfGoverning Equations for Fundamental Aerodynamics_Anderson2010.pdf
Governing Equations for Fundamental Aerodynamics_Anderson2010.pdf
 
ethical hacking in wireless-hacking1.ppt
ethical hacking in wireless-hacking1.pptethical hacking in wireless-hacking1.ppt
ethical hacking in wireless-hacking1.ppt
 
Hybrid optimization of pumped hydro system and solar- Engr. Abdul-Azeez.pdf
Hybrid optimization of pumped hydro system and solar- Engr. Abdul-Azeez.pdfHybrid optimization of pumped hydro system and solar- Engr. Abdul-Azeez.pdf
Hybrid optimization of pumped hydro system and solar- Engr. Abdul-Azeez.pdf
 
J.Yang, ICLR 2024, MLILAB, KAIST AI.pdf
J.Yang,  ICLR 2024, MLILAB, KAIST AI.pdfJ.Yang,  ICLR 2024, MLILAB, KAIST AI.pdf
J.Yang, ICLR 2024, MLILAB, KAIST AI.pdf
 

Manual Assembly Lines

  • 1. Manual Assembly Lines Sections: 1. Fundamentals of Manual Assembly Lines 2. Analysis of Single Model Assembly Lines 3. Line Balancing Algorithms 4. Other Considerations in Assembly Line Design 5. Alternative Assembly Systems
  • 2. Manual Assembly Lines § Work systems consisting of multiple workers organized to produce a single product or a limited range of products § Assembly workers perform tasks at workstations located along the line-of-flow of the product § Usually a powered conveyor is used § Some of the workstations may be equipped with portable powered tools. § Factors favoring the use of assembly lines: § High or medium demand for product § Products are similar or identical § Total work content can be divided into work elements § To automate assembly tasks is impossible
  • 3. Why Assembly Lines are Productive § Specialization of labor § When a large job is divided into small tasks and each task is assigned to one worker, the worker becomes highly proficient at performing the single task (Learning curve) § Interchangeable parts § Each component is manufactured to sufficiently close tolerances that any part of a certain type can be selected at random for assembly with its mating component. § Thanks to interchangeable parts, assemblies do not need fitting of mating components
  • 4. Some Definitions § Work flow § Each work unit should move steadily along the line § Line pacing § Workers must complete their tasks within a certain cycle time, which will be the pace of the whole line
  • 5. Manual Assembly Line § A production line that consists of a sequence of workstations where assembly tasks are performed by human workers § Products are assembled as they move along the line § At each station a portion of the total work content is performed on each unit § Base parts are launched onto the beginning of the line at regular intervals (cycle time) § Workers add components to progressively build the product
  • 6. Manual Assembly Line •Configuration of an n-workstation manual assembly line •The production rate of an assembly line is determined by its slowest station. §Assembly workstation: A designated location along the work flow path at which one or more work elements are performed by one or more workers
  • 7. Two assembly operators working on an engine assembly line (photo courtesy of Ford Motor Company) Origin of Manual Assembly Line
  • 8. Assembly Workstation A designated location along the work flow path at which one or more work elements are performed by one or more workers Typical operations performed at manual assembly stations Adhesive application Sealant application Arc welding Spot welding Electrical connections Component insertion Press fitting Riveting Snap fitting Soldering Stitching/stapling Threaded fasteners
  • 9. Manning level § There may be more than one worker per station. § Utility workers: are not assigned to specific workstations. § They are responsible for (1) helping workers who fall behind, (2) relieving for workers for personal breaks, (3) maintenance and repair
  • 10. Manning level §Average manning level: where M=average manning level of the line, wu=number of utility workers assigned to the system, n=number of workstations, wi=number of workers assigned specifically to station i for i=1,…,n n ww M n i iu å= + = 1
  • 11. Work Transport Systems-Manual Methods § Manual methods § Work units are moved between stations by the workers without powered conveyor § Problems: § Starving of stations § The assembly operator has completed the assigned task on the current work unit, but the next unit has not yet arrived at the station § Blocking of stations § The operator has completed the assigned task on the current work unit but cannot pass the unit to the downstream station because that worker is not yet ready to receive it.
  • 12. Work Transport Systems-Manual Methods § To reduce starving, § use buffers § To prevent blocking, § provide space between upstream and downstream stations. § But both solutions can result in higher WIP, § which is economically undesirable.
  • 13. Work Transport Systems-Mechanized Methods § Continuously moving conveyor: operates at constant velocity § Work units are fixed to the conveyor § Worker moves alongside the line and back § Work units are removable from the conveyor § Synchronous transport (intermittent transport – stop-and-go line): all work units are moved simultaneously between stations. § Problem: Incomplete units; excessive stress. Not common for manual lines (variability). § Asynchronous transport : a work unit leaves a given station when the assigned task is completed. § Variations in worker task times: small queues in front of each station.
  • 14. Coping with Product Variety § Single model assembly line (SMAL) § Every work unit is the same § Batch model assembly line (BMAL ) – multiple model line § Two or more different products § Products are so different that they must be made in batches with setup between § Mixed model assembly line (MMAL) § Two or more different models § Differences are slight so models can be made simultaneously with no downtime
  • 15. Coping with Product Variety § Advantages of mixed models over batch order models § No production time is lost during changeovers § High inventories due to batch ordering are avoided § Production rates of different models can be adjusted as product demand changes. § Disadvantages of mixed models over batch order models § Each station is equipped to perform variety of tasks (costly) § Scheduling and logistic activities are more difficult in this type of lines.
  • 16. Alternative Assembly Systems: § A single station manual assembly cell It consists of a single workplace in which the assembly work is accomplished on the product or some major sub assembly of the product. § Assembly cells based on worker teams It involves the use of multiple workers assigned to a common assembly task. § Automated assembly systems Use automated methods at workstations rather than humans. These can be type IA or type IIIA manufacturing systems.
  • 17. Analysis of Single Model Lines §The assembly line must be designed to achieve a production rate sufficient to satisfy the demand. §Demand rate → production rate→ cycle time §Annual demand Da must be reduced to an hourly production rate Rp where Sw = number of shifts/week Hsh = number of hours/shift shw a p HS D R 50 =
  • 18. Determining Cycle Time Line efficiency: Uptime proportion. Accounts for lost production time due to equipment failures, power outages, material unavailability, quality problems, labor problems. Production rate Rp is converted to a cycle time Tc, accounting for line efficiency E where 60 converts hourly production rate to cycle time in minutes, and E = proportion uptime on the line p c R E T 60 =
  • 19. The cycle time Tc establishes the ideal cycle rate for the line: c c T R 60 = This Rc>Rp because line efficiency E is less than 100%, Rc and Rp are related to E as follows: c p R R E = Number of workers on the production line AT WL w = Determining Efficiency
  • 20. Number of Workers Required Work load: Available Time: The theoretical minimum number of workers (assuming workers spend all their time on the product) on the line is determined as: w* = Minimum Integer ³ where Twc = work content time, min; Tc = cycle time, min/worker If we assume one worker per station then this gives the minimum number of stations c wc T T c wc wcp T TE WL TRWL × = ×= 60 EAT 60=
  • 21. Theoretical Minimum Not Possible § Repositioning losses: Some time will be lost at each station every cycle for repositioning the worker or the work unit; thus, the workers will not have the entire Tc each cycle § Line balancing problem: It is not possible to divide the work content time evenly among workers, and some workers will have an amount of work that is less than Tc. § Task time variability: Inherent and unavoidable variability in the time required by a worker to perform a given assembly task. § Quality problems: Defective components and other quality problems cause delays and rework that add to the work load.
  • 22. Repositioning Losses Repositioning losses occur on a production line because some time is required each cycle to reposition the worker, the work unit, or both § Repositioning time = Tr Service time = time available each cycle for the worker to work on the product § Service time Ts = Max{Tsi} ≤Tc – Tr Repositioning efficiency Er = c rc c s T TT T T - =
  • 23. Cycle Time on an Assembly Line Components of cycle time at several stations on a manual assembly line Tsi=service time, Tr=repositioning time
  • 24. Line Balancing Problem Given: § The total work content consists of many distinct work elements § The sequence in which the elements can be performed is restricted § The line must operate at a specified cycle time The Problem: § To assign the individual work elements to workstations so that all workers have an equal amount of work to perform
  • 25. Line balancing problem: § The line balancing problem is concerned with assigning the individual work. § Two important concepts in line balancing are the separation of the total work content into minimum rotational work elements and the precedence constraints. § Minimum rotational work elements: å = = en k ekwc TT 1 Tek : Time to perform work element k ne : Number of work elements
  • 26. Work element times § Work elements are assigned to station i that add up to the service time for that station § The station service times must add up to the total work content time åÎ = ik eksi TT å = = n k siwc TT 1
  • 27. Precedence Constraints § Precedence constraints: The variation in element times that make it difficult to obtain equal service times for all stations, there are restrictions on the order in which work elements can be performed. These technological requirements on the work sequence are called precedence constraints. Precedence diagram
  • 28. Formulae: § Balance efficiency: § Balance delay: § Note that : s wc b wT T E = ( ) s wcs wT TwT d - = 1=+dEb
  • 29. Worker requirements: Three factors that reduce the productivity of a manual assembly line: § Line efficiency (E) § Repositioning efficiency (Er) § Balancing efficiency (Eb) § Labor efficiency on the assembly line= § More realistic value for the number of workers on assembly line is: br EEE sb wc cbr wc br wcp TE T TEE T EEE TR w ==³=* 60 IntegerMinimum
  • 30. Work stations considerations: § If the manning level is one for all stations, then the number of stations is equal to the number of workers. § Total length of the assembly line : § Feed rate: § Center to center spacing between base parts: M w n = å = = n i siLL 1 c p T f 1 = cc p c p Tv f v s ==
  • 31. contd… § Tolerance time: § Ratio: § Elapsed time : c si t v L T = t c Tn V L ET ×== 0.1@ c t T T
  • 32. Line Balancing Objective To distribute the total work content on the assembly line as evenly as possible among the workers § Minimize (wTs – Twc) or § Minimize (Ts - Tsi) Subject to: (1) £ Ts (2) all precedence requirements are obeyed ∑ ∈ik ekT ∑ 1= w i
  • 33. Line Balancing Algorithms 1. Largest candidate rule 2. Kilbridge and Wester method 3. Ranked positional weights method, also known as the Helgeson and Birne method In the following descriptions, assume one worker per workstation
  • 34. Largest Candidate Rule List all work elements in descending order based on their Tek values; then, 1. Start at the top of the list and selecting the first element that satisfies precedence requirements and does not cause the total sum of Tek to exceed the allowable Ts value When an element is assigned, start back at the top of the list and repeat selection process 2. When no more elements can be assigned to the current station, proceed to next station 3. Repeat steps 1 and 2 until all elements have been assigned to as many stations as needed
  • 35. Solution for Largest Candidate Rule
  • 36. Solution for Largest Candidate Rule Physical layout of workstations and assignment of elements to stations using the largest candidate rule
  • 37. Kilbridge and Wester Method Arrange work elements into columns according to their positions in the precedence diagram § Work elements are then organized into a list according to their columns, starting with the elements in the first column § Proceed with same steps 1, 2, and 3 as in the largest candidate rule
  • 38. Kilbridge & Wester Method Arrangement of elements into columns for the K&W algorithm
  • 39. Ranked Positional Weights Method A ranked position weight (RPW) is calculated for each work element § RPW for element k is calculated by summing the Te values for all of the elements that follow element k in the diagram plus Tek itself § Work elements are then organized into a list according to their RPW values, starting with the element that has the highest RPW value § Proceed with same steps 1, 2, and 3 as in the largest candidate rule
  • 40. Other Considerations in Line Design § Methods analysis § To analyze methods at bottleneck or other troublesome workstations § Subdividing work elements § Sharing work elements between two adjacent stations § Utility workers § To relieve congestion at stations that are temporarily overloaded § Changing work head speeds at mechanized stations § Preassembly of components § Prepare certain subassemblies off-line to reduce work content time on the final assembly line
  • 41. Other Considerations - continued § Storage buffers between stations § To permit continued operation of certain sections of the line when other sections break down § To smooth production between stations with large task time variations § Zoning and other constraints § Parallel stations § To reduce time at bottleneck stations that have unusually long task times
  • 42. Alternative Assembly Systems § Single-station manual assembly cell § A single workstation in which all of the assembly work is accomplished on the product or on some major subassembly § Common for complex products produced in small quantities, sometimes one of a kind § Assembly by worker teams § Multiple workers assigned to a common assembly task § Advantage: greater worker satisfaction § Disadvantage: slower than line production