SlideShare a Scribd company logo
1 of 106
Arif Rahman – The Production Systems 1
Slide 7
Manual
Assembly Line
Arif Rahman, ST MT
Arif Rahman – The Production Systems
Most consumer products are assembled on
manual assembly lines
Factors favoring the use of assembly lines:
¤ High or medium demand for product
¤ Identical or similar products
¤ Total work content can be divided into work elements
¤ It is technologically impossible or economically
infeasible to automate the assembly operations
Manual Assembly Lines
2
Arif Rahman – The Production Systems
Specialization of labor
¤ Learning curve
Interchangeable parts
¤ Components made to close tolerances
¤ Assemblies do not need fitting of mating components
Work flow principle
¤ Products are brought to the workers
Line pacing
¤ Workers must complete their tasks within the cycle
time of the line
Why Assembly Lines are so Productive
3
Arif Rahman – The Production Systems
Typical Products Made on Assembly Lines
Automobiles
Cooking ranges
Dishwashers
Dryers
Furniture
Lamps
Luggage
Microwave ovens
Personal computers
Power tools
Refrigerators
Telephones
Toasters
Trucks
Video DVD players
Washing machines
4
Arif Rahman – The Production Systems
A production line consisting of a sequence of
workstations where assembly tasks are performed by
human workers as the product moves along the line
¤ Work systems consisting of multiple workers organized to
produce a single product or a limited range of products
• Each product consists of multiple components joined together by
various assembly work elements
 Total work content - the sum of all work elements required to assemble
one product unit on the line
¤ Assembly workers perform tasks at workstations located along
the line-of-flow of the product
• Usually a powered conveyor is used
• Some of the workstations may be equipped with portable powered
tools
Manual Assembly Line Defined
5
Arif Rahman – The Production Systems
Manual Assembly Line
6
Configuration of a manual assembly line
with n manually operated workstations
Arif Rahman – The Production Systems
The production rate of an assembly line is
determined by its slowest station.
Assembly workstation: A designated
location along the work flow path at which
one or more work elements are performed
by one or more workers
Manual Assembly Line
7
Arif Rahman – The Production Systems
Manual Assembly Line
Two assembly
operators working on
an engine assembly
line (photo courtesy of
Ford Motor Company)
8
Arif Rahman – The Production Systems
Products are assembled as they move
along the line
¤ At each station a portion of the total work
content is performed on each unit
Base parts are launched onto the
beginning of the line at regular intervals
(cycle time)
¤ Workers add components to progressively
build the product
Manual Assembly Line
9
Arif Rahman – The Production Systems
Typical operations performed at manual assembly stations
Adhesive application
Sealant application
Arc welding
Spotwelding
Electrical connections
Componentinsertion
Pressfitting
Riveting
Snap fitting
Soldering
Stitching/stapling
Threadedfasteners
Assembly Workstation
10
A designated location along the work flow path at which one
or more work elements are performed by one or more workers
Arif Rahman – The Production Systems
There may be more than one worker per
station.
Utility workers: are not assigned to specific
workstations.
They are responsible for
¤ helping workers who fall behind,
¤ relieving for workers for personal breaks,
¤ maintenance and repair
Manning level
11
Arif Rahman – The Production Systems
Average manning level:
where :
M = average manning level of the line,
n = number of workstations
w = number of workers on the line
wu = number of utility workers assigned to the system,,
wi = number of workers assigned specifically to
station i for i=1,…,n
Manning level
12
n
ww
n
w
M
n
i
iu ∑=
+
== 1
Arif Rahman – The Production Systems
Two basic categories:
¤ Manual
¤ Mechanized
Work Transport Systems
13
Arif Rahman – The Production Systems
Work units are moved between stations by
the workers without the aid of a powered
conveyor
¤ Types:
• Work units moved in batches
• Work units moved one at a time
¤ Problems:
• Starving of stations
• Blocking of stations
• No pacing
Manual Work Transport Systems
14
Arif Rahman – The Production Systems
To reduce starving,
¤ use buffers
To prevent blocking,
¤ provide space between upstream and
downstream stations.
But both solutions can result in higher
WIP,
¤ which is economically undesirable.
Work Transport Systems-Manual Methods
15
Arif Rahman – The Production Systems
Work units are moved by powered
conveyor or other mechanized apparatus
¤ Categories:
• Work units attached to conveyor
• Work units are removable from conveyor
¤ Problems
• Starving of stations
• Incomplete units
Mechanized Work Transport Systems
16
Arif Rahman – The Production Systems
Continuous transport
¤ Conveyor moves at constant speed
Synchronous transport/intermittent transport
¤ Work units are moved simultaneously with stop-
and-go (intermittent) motion to next stations
Asynchronous transport
¤ Work units are moved independently between
workstations
¤ Queues of work units can form in front of each
station
Types of Mechanized Work Transport
17
Arif Rahman – The Production Systems
Continuous Transport
18
Conveyor moves at constant velocity vc
Arif Rahman – The Production Systems
Synchronous Transport
19
All work units are moved simultaneously to their respective
next workstations with quick, discontinuous motion
Arif Rahman – The Production Systems
Asynchronous Transport
20
Work units move independently, not simultaneously. A work
unit departs a given station when the worker releases it.
Small queues of parts can form at each station.
Arif Rahman – The Production Systems
Continuous transport
¤ Overhead trolley conveyor
¤ Belt conveyor
¤ Roller conveyor
¤ Drag chain conveyor
Synchronous transport
¤ Walking beam transport equipment
¤ Rotary indexing mechanisms
Asynchronous transport
¤ Power-and-free overhead conveyor
¤ Cart-on-track conveyor
¤ Automated guided vehicle systems
¤ Monorail systems
¤ Chain-driven carousel systems
Material Handling Equipment for Mechanized Work Transport
21
Arif Rahman – The Production Systems
A manual assembly line operates at a certain
cycle time to achieve the required production rate
of the line – On average, each worker must
complete his/her assigned task within this cycle
time
Pacing provides a discipline for the assembly line
workers that more or less guarantees a certain
production rate for the line
Several levels of pacing:
1. Rigid pacing
2. Pacing with margin
3. No pacing
Line Pacing
22
Arif Rahman – The Production Systems
Each worker is allowed only a certain fixed
time each cycle to complete the assigned
task
¤ Allowed time is set equal to the cycle time less
repositioning time
¤ Synchronous work transport system provides
rigid pacing
Undesirable aspects of rigid pacing:
¤ Incompatible with inherent human variability
¤ Emotionally and physically stressful to worker
¤ Incomplete work units if task not completed
Rigid Pacing
23
Arif Rahman – The Production Systems
Worker is allowed to complete the task within
a specified time range, the upper limit of
which is greater than the cycle time
On average, the worker’s average task time
must balance with the cycle time of the line
How to achieve pacing with margin:
¤ Allow queues of work units between stations
¤ Provide for tolerance time to be longer than cycle time
¤ Allow worker to move beyond station boundaries
Pacing with Margin
24
Arif Rahman – The Production Systems
No time limit within which task must be
completed
Each assembly worker works at his/her
own pace
No pacing can occur when:
¤ Manual transport of work units is used
¤ Work units can be removed from the conveyor
to perform the task
¤ An asynchronous conveyor is used
No Pacing
25
Arif Rahman – The Production Systems
Single model assembly line (SMAL)
¤ Every work unit is the same
Batch model assembly line (BMAL)
¤ Hard product variety
¤ Products must be made in batches
Mixed model assembly line (MMAL)
¤ Soft product variety
¤ Models can be assembled simultaneously
without batching
Coping with Product Variety
26
Arif Rahman – The Production Systems
Advantages of mixed model lines over
batch models lines:
¤ No lost production time between models
¤ High inventories typical of batch production
are avoided
¤ Production rates of different models can be
adjusted as product demand changes
MMAL vs. BMAL
27
Arif Rahman – The Production Systems
Difficulties with mixed model line
compared to batch model line
¤ Line balancing problem more complex due to
differences in work elements among models
¤ Scheduling the sequence of the different models is a
problem
¤ Logistics is a problem - getting the right parts to each
workstation for the model currently there
¤ Cannot accommodate as wide model variations as
BMAL
MMAL vs. BMAL
28
Arif Rahman – The Production Systems
Problems on high production assembly lines
¤ Complain about the monotony of the repetitive tasks
that must be performed and the unrelenting pace that
must be maintained when a moving conveyor is used
¤ Poor quality workmanship
¤ Sabotage of the line equipment
Alternative assembly systems
¤ Single station manual assembly cells
¤ Assembly cells based on worker teams
• Single station manual assembly cell with multiple workers
• Moving the product through multiple workstations, but having
the same worker team follow the product
¤ Automated assembly systems
Alternative Assembly Systems
29
Arif Rahman – The Production Systems
The key to successful DFA
¤ Design the product with as few parts as possible
¤ Design the remaining parts so they are easy to
assemble
General principles of DFA
¤ Use the fewest number of parts possible to
reduce the amount of assembly required
¤ Reduce the number of threaded fasteners
required
¤ Standardize fasteners
¤ Reduce parts orientation difficulties
¤ Avoid parts that tangle
Design for Assembly (DFA)
30
Arif Rahman – The Production Systems
The formulas and the algorithms in this
section are developed for single model
lines, but they can be extended to batch
and mixed models.
The assembly line must be designed to
achieve a production rate sufficient to
satisfy the demand.
Demand rate → production rate→ cycle
time
Analysis of Single Model Lines
31
Arif Rahman – The Production Systems
Annual demand Da must be reduced to an hourly
production rate Rp
where
Da = annual demand (pieces)
Rp = hourly production rate (pieces/hour)
Sw = number of shifts/week (shift/week)
Hsh = number of hours/shift (hour/shift)
The constant 52 converts years to weeks, and vise
versa
Analysis of Single Model Lines
32
shw
a
p
HS
D
R
52
=
Arif Rahman – The Production Systems
Now our aim is to convert production rate,
Rp, to cycle time, Tc.
One should take into account that some
production time will be lost due to
¤ equipment failures
¤ power outages,
¤ material unavailability,
¤ quality problems,
¤ labor problems.
Determining Cycle Time
33
Arif Rahman – The Production Systems
Line efficiency (uptime proportion): only a
certain proportion of the shift time will be
available.
Production rate, Rp, is converted to a cycle
time, Tc, accounting for line efficiency, E.
Determining Cycle Time
34
p
c
R
E
T
60
=
Arif Rahman – The Production Systems
Rc = cycle rate for the line (cycles/hour)
Tc = cycle time of the line (minutes/cycle)
Rp = required production rate (pieces/hour)
E = line efficiency
Rc must be greater than Rp because E is less than 100%
Determining Cycle Time
35
c
p
R
R
E =
Arif Rahman – The Production Systems
EAT
T
ET
WL
TRWL
AT
WL
w
c
wc
wcp
60
60
=
=
=
=
Number of Stations Required
36
Arif Rahman – The Production Systems
Work content time (Twc): The total time of all work
elements that must be performed to produce one unit of
the work unit.
The theoretical minimum number of stations that will be
required to on the line to produce one unit of the work
unit, w*:
where
Twc = work content time (min)
Tc = cycle time (min/station)
If we assume one worker per station then this gives the minimum
number of workers
Number of Stations Required
37
c
wc
T
T
w ≥= intmin*
Arif Rahman – The Production Systems
Repositioning losses
¤ Some time will be lost at each station every cycle
for repositioning the worker or the work unit; thus,
the workers will not have the entire Tc each cycle
Line balancing problem (imperfect
balancing):
¤ It is not possible to divide the work content time
evenly among workers, and some workers will
have an amount of work that is less than Tc
Task time variability
Quality problems
Theoretical Minimum Not Possible
38
Arif Rahman – The Production Systems
Repositioning losses occur on a production
line because some time is required each
cycle to reposition the worker, the work unit,
or both
¤ On a continous transport line, time is required for
the worker to walk from the unit just completed to
the the upstream unit entering the station
¤ In conveyor systems, time is required to remove
work units from the conveyor and position it at the
station for worker to perform his task.
Repositioning Losses
39
Arif Rahman – The Production Systems
Repositioning time, (Tr) = time available
each cycle for the worker to position
Service time, (Ts) = time available each
cycle for the worker to work on the product
Service time, Ts = Max{Tsi} ≤ Tc – Tr
where Tsi= service time for station i, i=1,2,..,n
Repositioning efficiency
Repositioning Losses
40
c
rc
c
s
r
T
TT
T
T
E
−
==
Arif Rahman – The Production Systems
Cycle Time (Tc) on an Assembly Line
41
Components of cycle time at several stations on a
manual assembly line.
At the bottleneck station, there is no idle time.
Tsi = service time, Tr = repositioning time
Arif Rahman – The Production Systems
Given:
¤ Total work content consists of many distinct work
elements
¤ The sequence in which the elements can be
performed is restricted
¤ The line must operate at a specified cycle time
Problem:
¤ To assign the individual work elements to
workstations so that all workers have an equal
amount of work to perform
Line Balancing Problem
42
Arif Rahman – The Production Systems
Element times are constant values
¤ But in fact they are variable
Work element times are additive
¤ The time to perform two/more work elements
in sequence is the sum of the individual
element times
¤ Additivity assumption can be violated (due to
motion economies)
Assumptions About Work Element Times
43
Arif Rahman – The Production Systems
Total work content time Twc
¤ where Tek = work element time for element k
Work elements are assigned to station i that add up to the
service time for that station
The station service times must add up to the total work
content time
Work Element Times
44
∑=
=
en
k
ekwc TT
1
∑∈
=
ik
eksi TT
∑=
=
n
i
siwc TT
1
Arif Rahman – The Production Systems
Different work elements require different times.
When elements are grouped into logical tasks
and assigned to workers, the station service
times, Tsi, are likely not to be equal.
Simply because of the variation among work
element times, some workers will be assigned
more work.
Thus, variations among work elements make it
difficult to obtain equal service times for all
stations.
Constraints of Line Balancing Problem
45
Arif Rahman – The Production Systems
Precedence Constraints
46
Restrictions on the order in which work elements can be performed
Precedence Diagram
Arif Rahman – The Production Systems
Largest Candidate Rule
¤ Assignment of work elements to stations based on amount
of time each work element requires
Kilbridge and Wester Method
¤ Assignment of work elements to stations based on position
in the precedence diagram
¤ Elements at front of diagram are assigned first
Ranked Positional Weights
¤ Combines the two preceding approaches by calculating an
RPW for each element
COMSOAL Random Sequence Generation
¤ Sequences are generated by selecting at random from the
set of available tasks and placing that task next in
sequence
Line Balancing Algorithms
47
Arif Rahman – The Production Systems
Example:
48
Grommet : sealant like ring
No Work Element Description Tek (min) Predecessors Successors
1 Place frame in workholder and clamp 0.2 - 3,4
2 Assemble plug, grommet to power cord 0.4 - 4,5
3 Assemble brackets to frame 0.7 1 6,7,8
4 Wire power cord to motor 0.1 1,2 8
5 Wire power cord to switch 0.3 2 10
6 Assemble mechanism plate to bracket 0.11 3 9
7 Assemble blade to bracket 0.32 3 9
8 Assemble motor to brackets 0.6 3,4 9,10
9 Align blade and attach to motor 0.27 6,7,8 11
10 Assemble switch to motor bracket 0.38 5,8 11
11 Attach cover,lnspect, and test 0.5 9,10 12
12 Place in tote pan for packing 0.12 11 -
Arif Rahman – The Production Systems
Example:
49
Grommet : sealant like ring
Arif Rahman – The Production Systems
Given: The previous precedence diagram and the
standard times. Annual demand=100,000 units/year. The
line will operate 50 wk/yr, 5 shifts/wk, 7.5 hr/shift. Uptime
efficiency=96%. Repositioning time lost=0.08 min.
Determine
a) total work content time,
b) required hourly production rate to achieve the annual
demand,
c) cycle time,
d) theoretical minimum number of workers required on the
line,
e) service time to which the line must be balanced.
Example: A problem for line balancing
50
Arif Rahman – The Production Systems
The total work content time is the sum of
the work element times given in the table
Twc = 4.0 min
The hourly production rate
Example: Solution
51
units/hr33.53
)5.7)(5(50
000,100
==pR
∑=
=
en
k
ekwc TT
1
shw
a
p
HS
D
R
50
=
Arif Rahman – The Production Systems
The corresponding cycle time with an
uptime efficiency of 96%
The minimum number of workers:
w*
= (Min Int) ≥ 4.0 /1.08=3.7
= 4 workers
The available service time
Ts = 1.08 - 0.08 = 1.00 min
Example: Solution
52
Production
System
29/10/17
min08.1
33.53
)96.0(60
==cT
p
c
R
E
T
60
=
c
wc
T
T
w =*
rcs TTT −=
Arif Rahman – The Production Systems
It is almost imposible to obtain a perfect line balance
Line balance efficiency, Eb:
Perfect line: Eb = 1
Balance delay, d:
Perfect line: d = 0
Note that Eb + d = 1 (they are complement of each
other)
Measures of Balance Efficiency
53
s
wc
b
wT
T
E =
s
wcs
wT
TwT
d
−
=
Arif Rahman – The Production Systems
Factors that reduce the productivity of a manual
line
¤ Line efficiency (Availability), E,
¤ Repositioning efficiency (repositioning), Er,
¤ Balance efficiency (balancing), Eb,
Overall Labor efficiency on the assembly line =
Overall Efficiency
54
c
rc
c
s
r
T
TT
T
T
E
−
==
s
wc
b
wT
T
E =
p
c
R
E
T
60
=
rb EEE ⋅⋅=EfficiencyLabor
Arif Rahman – The Production Systems
The actual number of workers on the
assembly line is given by:
where :
w = number of workers required
Rp = hourly production rate (pieces/hour)
Twc = work content time per product, (min/piece)
Worker Requirements
55
c
rc
c
s
r
T
TT
T
T
E
−
==
s
wc
b
wT
T
E =
sb
wc
cbr
wc
br
wcp
TE
T
TEE
T
EEE
TR
w ==≥=
60
intmin
p
c
R
E
T
60
=
Arif Rahman – The Production Systems
Number of stations:
Total length of the assembly line
where
L = length of the assembly line (m)
Lsi= length of station i (m)
Continously moving conveyors - Workstation considerations
56
∑=
=
n
i
isLL
1
M
w
n =
Arif Rahman – The Production Systems
Constant speed conveyor: (if the base parts
remain fixed during their assembly)
¤ Feed rate
where : fp=feed rate on the line, (products/min)
¤ Center-to-center spacing between base parts
where :
sp = center-to-center spacing between base parts (m/part)
vc = velocity of the conveyor (m/min)
Continously moving conveyors - Workstation considerations
57
c
p
T
f
1
=
cc
p
c
p Tv
f
v
s ==
Arif Rahman – The Production Systems
Defined as the time a work unit spends inside the
boundaries of the workstation
Provides a way to allow for product-to-product
variations in task times at a station
where
Tt = tolerance time (min)
Ls = station length (m)
vc = conveyor speed, (m/min)
Continously moving conveyors - Tolerance Time
58
c
s
t
v
L
T =
Arif Rahman – The Production Systems
The time a work unit spends on the assembly
line.
where
ET = total elapsed time, (min)
n = number of workstations
Tt = tolerance time, (min)
L = length of the assembly line, (m)
vc = conveyor speed, (m/min)
Continously moving conveyors -Total Elapsed Time
5929/10/17
t
c
nT
v
L
ET ==
Arif Rahman – The Production Systems
To distribute the total work content on the assembly
line as evenly as possible among the workers
Minimize (wTs – Twc)
or
Minimize
Subject to:
(1)
(2) all precedence requirements are obeyed
Line Balancing Objective
60
( )∑=
−
w
i
sis TT
1
s
ik
ek TT ≤∑∈
Arif Rahman – The Production Systems
0. List all work elements in descending order based on their Tek
values; then, proceed three-step procedure:
1. Start at the top of the list and selecting the first element that
satisfies precedence requirements and does not cause the
total sum of Tek to exceed the allowable Ts value.
¤ When an element is assigned, start back at the top of the list
and repeat selection process
1. When no more elements can be assigned to the current
station, proceed to next station
2. Repeat steps 1 and 2 until all elements have been assigned
to as many stations as needed
Largest Candidate Rule
61
Arif Rahman – The Production Systems
Example: Largest Candidate Rule
62
Grommet : sealant like ring
Arif Rahman – The Production Systems
Example: Largest Candidate Rule
63
Work Elements Arranged According to Tek Value for the
Largest Candidate Rule. (Ts = 1 min)
No Tek (min) Predecessors Successors
3 0.7 1 6,7,8
8 0.6 3,4 9,1
11 0.5 9,1 12
2 0.4 - 4,5
10 0.38 5,8 11
7 0.32 3 9
5 0.3 2 10
9 0.27 6,7,8 11
1 0.2 - 3,4
12 0.12 11 -
6 0.11 3 9
4 0.1 1,2 8
Arif Rahman – The Production Systems
Example: Largest Candidate Rule
Iteration 1:
3, 8, and 11 require preceding
elements
Element 2 is selected.
Alternatives are 5 and 1.
It assigns element 5.
ΣTek = 0.4 + 0.3 = 0.7 min
Alternative is 1
It assigns element 1
ΣTek = 0.7 + 0.2 = 0.9 min
Alternatives are 3 and 4
3 can not be assigned, since ΣTek
> Ts
It assigns element 4
ΣTek = 0.9 + 0.1 = 1.0 min 64
No Tek (min) Predecessors Successors
3 0.7 1 6,7,8
8 0.6 3,4 9,1
11 0.5 9,1 12
2 0.4 - 4,5
10 0.38 5,8 11
7 0.32 3 9
5 0.3 2 10
9 0.27 6,7,8 11
1 0.2 - 3,4
12 0.12 11 -
6 0.11 3 9
4 0.1 1,2 8
Arif Rahman – The Production Systems
Example: Largest Candidate Rule
Iteration 2:
Element 3 is selected.
Alternatives are 8, 7 and 6.
8 and 7 can not be assigned, since
ΣTek > Ts
It assigns element 6.
ΣTek = 0.7 + 0.11 = 0.81 min
Alternatives are 8 and 7.
8 and 7 can not be assigned, since
ΣTek > Ts
65
No Tek (min) Predecessors Successors
3 0.7 1 6,7,8
8 0.6 3,4 9,1
11 0.5 9,1 12
2 0.4 - 4,5
10 0.38 5,8 11
7 0.32 3 9
5 0.3 2 10
9 0.27 6,7,8 11
1 0.2 - 3,4
12 0.12 11 -
6 0.11 3 9
4 0.1 1,2 8
Arif Rahman – The Production Systems
Example: Largest Candidate Rule
Iteration 3:
Element 8 is selected.
Alternatives are 10 and 7.
It assigns element 10.
ΣTek = 0.6 + 0.38 = 0.98 min
Alternative is 7.
7 can not be assigned, since ΣTek
> Ts
66
No Tek (min) Predecessors Successors
3 0.7 1 6,7,8
8 0.6 3,4 9,1
11 0.5 9,1 12
2 0.4 - 4,5
10 0.38 5,8 11
7 0.32 3 9
5 0.3 2 10
9 0.27 6,7,8 11
1 0.2 - 3,4
12 0.12 11 -
6 0.11 3 9
4 0.1 1,2 8
Arif Rahman – The Production Systems
Example: Largest Candidate Rule
Iteration 4:
11 requires preceding elements
Element 7 is selected.
Alternative is 9.
It assigns element 9.
ΣTek = 0.32 + 0.27 = 0.59 min
Alternative is 11.
11 can not be assigned, since ΣTek
> Ts
67
No Tek (min) Predecessors Successors
3 0.7 1 6,7,8
8 0.6 3,4 9,1
11 0.5 9,1 12
2 0.4 - 4,5
10 0.38 5,8 11
7 0.32 3 9
5 0.3 2 10
9 0.27 6,7,8 11
1 0.2 - 3,4
12 0.12 11 -
6 0.11 3 9
4 0.1 1,2 8
Arif Rahman – The Production Systems
Example: Largest Candidate Rule
Iteration 5:
Element 11 is selected.
Alternative is 12.
It assigns element 12.
ΣTek = 0.5 + 0.12 = 0.62 min
All elements have been assigned.
68
No Tek (min) Predecessors Successors
3 0.7 1 6,7,8
8 0.6 3,4 9,1
11 0.5 9,1 12
2 0.4 - 4,5
10 0.38 5,8 11
7 0.32 3 9
5 0.3 2 10
9 0.27 6,7,8 11
1 0.2 - 3,4
12 0.12 11 -
6 0.11 3 9
4 0.1 1,2 8
Arif Rahman – The Production Systems
Example: Largest Candidate Rule
Final Solution:
Workstation 1 : 2-5-1-4 = 1.0 min
Workstation 2 : 3-6 = 0.81 min
Workstation 3 : 8-10 = 0.98 min
Workstation 4 : 7-9 = 0.59 min
Workstation 5 : 11-12 = 0.62 min
69
No Tek (min) Predecessors Successors
3 0.7 1 6,7,8
8 0.6 3,4 9,1
11 0.5 9,1 12
2 0.4 - 4,5
10 0.38 5,8 11
7 0.32 3 9
5 0.3 2 10
9 0.27 6,7,8 11
1 0.2 - 3,4
12 0.12 11 -
6 0.11 3 9
4 0.1 1,2 8
Arif Rahman – The Production Systems
Example: Solution
70
Work Elements Arrangement . Ts = 1 min.
Workstatio
n
No Tek (min) ΣTek
1 1 0.2 1.0
2 0.4
4 0.1
5 0.3
2 3 0.7 0.81
6 0.11
3 8 0.6 0.98
10 0.38
4 7 0.32 0.59
9 0.27
5 11 0.5 0.62
12 0.12
Arif Rahman – The Production Systems
Example: Solution
71
Work Elements Arrangement . Ts = 1 min.
Arif Rahman – The Production Systems
Solution for Largest Candidate Rule
72
Physical layout of workstations and assignment of
elements to stations using the largest candidate rule
Arif Rahman – The Production Systems
Selects work elements for assignment to stations
according to their position in the precedence
diagram
Work elements in the precedence diagram are
arranged into columns
The elements can be organized into a list
according to their columns, with the elements in
the first column listed first
If a given element can be located in more than
one column, then list all of the columns for that
element
Proceed with same steps 1, 2, and 3 as in the
largest candidate rule
Kilbridge and Wester Method
73
Arif Rahman – The Production Systems
Example: Kilbridge and Wester Method
74
Arif Rahman – The Production Systems
Example: Kilbridge and Wester Method
75
Work Elements Arranged According to Tek Value for the
Kilbridge and Wester Method. (Ts = 1 min)
No Tek (min) Region Predecessors Successors
2 0.4 I - 4,5
1 0.2 I - 3,4
3 0.7 II 1 6,7,8
4 0.1 II 1,2 8
5 0.3 II / III 2 10
8 0.6 III 3,4 9,1
7 0.32 III 3 9
6 0.11 III 3 9
10 0.38 III / IV 5,8 11
9 0.27 IV 6,7,8 11
11 0.5 V 9,1 12
12 0.12 VI 11 -
Arif Rahman – The Production Systems
Example: Kilbridge and Wester Method
Iteration 1:
Element 2 is selected.
Alternatives are 1 and 5.
It assigns element 1.
ΣTek = 0.4 + 0.2 = 0.6 min
Alternatives are 3, 4 and 5
3 can not be assigned, since ΣTek
> Ts
It assigns element 4
ΣTek = 0.6 + 0.1 = 0.7 min
Alternatives are 3 and 5
3 can not be assigned, since ΣTek
> Ts
It assigns element 5
ΣTek = 0.7 + 0.3 = 1.0 min 76
No Tek (min) Region Predecessors Successors
2 0.4 I - 4,5
1 0.2 I - 3,4
3 0.7 II 1 6,7,8
4 0.1 II 1,2 8
5 0.3 II / III 2 10
8 0.6 III 3,4 9,1
7 0.32 III 3 9
6 0.11 III 3 9
10 0.38 III / IV 5,8 11
9 0.27 IV 6,7,8 11
11 0.5 V 9,1 12
12 0.12 VI 11 -
Arif Rahman – The Production Systems
Example: Kilbridge and Wester Method
Iteration 2:
Element 3 is selected.
Alternatives are 8, 7 and 6.
8 and 7 can not be assigned, since
ΣTek > Ts
It assigns element 6.
ΣTek = 0.7 + 0.11 = 0.81 min
Alternatives are 8 and 7
8 and 7 can not be assigned, since
ΣTek > Ts
77
No Tek (min) Region Predecessors Successors
2 0.4 I - 4,5
1 0.2 I - 3,4
3 0.7 II 1 6,7,8
4 0.1 II 1,2 8
5 0.3 II / III 2 10
8 0.6 III 3,4 9,1
7 0.32 III 3 9
6 0.11 III 3 9
10 0.38 III / IV 5,8 11
9 0.27 IV 6,7,8 11
11 0.5 V 9,1 12
12 0.12 VI 11 -
Arif Rahman – The Production Systems
Example: Kilbridge and Wester Method
Iteration 3:
Element 8 is selected.
Alternatives are 7 and 10.
It assigns element 7.
ΣTek = 0.6 + 0.32 = 0.92 min
Alternatives are 10 and 9
10 and 9 can not be assigned, since
ΣTek > Ts
78
No Tek (min) Region Predecessors Successors
2 0.4 I - 4,5
1 0.2 I - 3,4
3 0.7 II 1 6,7,8
4 0.1 II 1,2 8
5 0.3 II / III 2 10
8 0.6 III 3,4 9,1
7 0.32 III 3 9
6 0.11 III 3 9
10 0.38 III / IV 5,8 11
9 0.27 IV 6,7,8 11
11 0.5 V 9,1 12
12 0.12 VI 11 -
Arif Rahman – The Production Systems
Example: Kilbridge and Wester Method
Iteration 4:
Element 10 is selected.
Alternatives is 9.
It assigns element 9.
ΣTek = 0.38 + 0.27 = 0.65 min
Alternative is 11
11 can not be assigned, since ΣTek >
Ts
79
No Tek (min) Region Predecessors Successors
2 0.4 I - 4,5
1 0.2 I - 3,4
3 0.7 II 1 6,7,8
4 0.1 II 1,2 8
5 0.3 II / III 2 10
8 0.6 III 3,4 9,1
7 0.32 III 3 9
6 0.11 III 3 9
10 0.38 III / IV 5,8 11
9 0.27 IV 6,7,8 11
11 0.5 V 9,1 12
12 0.12 VI 11 -
Arif Rahman – The Production Systems
Example: Kilbridge and Wester Method
Iteration 5:
Element 11 is selected.
Alternatives is 12.
It assigns element 12.
ΣTek = 0.5 + 0.12 = 0.62 min
All elements have been assigned.
80
No Tek (min) Region Predecessors Successors
2 0.4 I - 4,5
1 0.2 I - 3,4
3 0.7 II 1 6,7,8
4 0.1 II 1,2 8
5 0.3 II / III 2 10
8 0.6 III 3,4 9,1
7 0.32 III 3 9
6 0.11 III 3 9
10 0.38 III / IV 5,8 11
9 0.27 IV 6,7,8 11
11 0.5 V 9,1 12
12 0.12 VI 11 -
Arif Rahman – The Production Systems
Example: Kilbridge and Wester Method
Final Solution:
Workstation 1 : 2-1-4-5 = 1.0 min
Workstation 2 : 3-6 = 0.81 min
Workstation 3 : 8-7 = 0.92 min
Workstation 4 : 10-9 = 0.65 min
Workstation 5 : 11-12 = 0.62 min
81
No Tek (min) Region Predecessors Successors
2 0.4 I - 4,5
1 0.2 I - 3,4
3 0.7 II 1 6,7,8
4 0.1 II 1,2 8
5 0.3 II / III 2 10
8 0.6 III 3,4 9,1
7 0.32 III 3 9
6 0.11 III 3 9
10 0.38 III / IV 5,8 11
9 0.27 IV 6,7,8 11
11 0.5 V 9,1 12
12 0.12 VI 11 -
Arif Rahman – The Production Systems
Example: Solution
82
Work Elements Arrangement . Ts = 1 min.
Workstatio
n
No Tek (min) ΣTek
1 1 0.2 1.0
2 0.4
4 0.1
5 0.3
2 3 0.7 0.81
6 0.11
3 7 0.32 0.92
8 0.6
4 9 0.27 0.65
10 0.38
5 11 0.5 0.62
12 0.12
Arif Rahman – The Production Systems
Example: Solution
83
Work Elements Arrangement . Ts = 1 min.
Arif Rahman – The Production Systems
Solution for Kilbridge and Wester Method
84
Physical layout of workstations and assignment of
elements to stations using the Kilbridge and Wester Method
Arif Rahman – The Production Systems
A ranked position weight (RPW) is calculated for
each work element
RPW for element k is calculated by summing the
Tek values for all of the elements that follow
element k in the diagram plus Tek itself
Work elements are then organized into a list
according to their RPW values, starting with the
element that has the highest RPW value
Proceed with same steps 1, 2, and 3 as in the
largest candidate rule
Ranked Positional Weights Method
85
Arif Rahman – The Production Systems
Example: Ranked Positional Weights Method
86
Grommet : sealant like ring
Arif Rahman – The Production Systems
Example: Ranked Positional Weights Method
87
Work Elements Arranged According to Tek Value for the
Ranked Positional Weights Method. (Ts = 1 min)
No Tek (min) RPW Predecessors Successors Elements of RPW
1 0.2 3.30 - 3,4 1, 3, 4, 6, 7, 8, 9, 10, 11, 12
3 0.7 3.00 1 6,7,8 3, 6, 7, 8, 9, 10, 11, 12
2 0.4 2.67 - 4,5 2, 4, 5, 8, 9, 10, 11, 12
4 0.1 1.97 1,2 8 4, 8, 9, 10, 11, 12
8 0.6 1.87 3,4 9,1 8, 9, 10, 11, 12
5 0.3 1.30 2 10 5, 10, 11, 12
7 0.32 1.21 3 9 7, 9, 11, 12
6 0.11 1.00 3 9 6, 9, 11, 12
10 0.38 1.00 5,8 11 10, 11, 12
9 0.27 0.89 6,7,8 11 9, 11, 12
11 0.5 0.62 9,1 12 11, 12
12 0.12 0.12 11 - 12
Arif Rahman – The Production Systems
Example: Ranked Positional Weights Method
Iteration 1:
Element 1 is selected.
Alternatives are 3 and 2.
It assigns element 3.
ΣTek = 0.2 + 0.7 = 0.9 min
Alternatives are 2, 7 and 6
2, 7 and 6 can not be assigned,
since ΣTek > Ts
88
No Tek (min) RPW Predecessors Successors
1 0.2 3.30 - 3,4
3 0.7 3.00 1 6,7,8
2 0.4 2.67 - 4,5
4 0.1 1.97 1,2 8
8 0.6 1.87 3,4 9,1
5 0.3 1.30 2 10
7 0.32 1.21 3 9
6 0.11 1.00 3 9
10 0.38 1.00 5,8 11
9 0.27 0.89 6,7,8 11
11 0.5 0.62 9,1 12
12 0.12 0.12 11 -
Arif Rahman – The Production Systems
Example: Ranked Positional Weights Method
Iteration 2:
Element 2 is selected.
Alternatives are 4, 5, 7 and 6.
It assigns element 4.
ΣTek = 0.4 + 0.1 = 0.5 min
Alternatives are 8, 5, 7 and 6
8 can not be assigned, since ΣTek
> Ts
It assigns element 5
ΣTek = 0.5 + 0.3 = 0.8 min
Alternatives are 8, 7 and 6
8 and 7 can not be assigned, since
ΣTek > Ts
It assigns element 6
ΣTek = 0.8 + 0.11 = 0.91 min 89
No Tek (min) RPW Predecessors Successors
1 0.2 3.30 - 3,4
3 0.7 3.00 1 6,7,8
2 0.4 2.67 - 4,5
4 0.1 1.97 1,2 8
8 0.6 1.87 3,4 9,1
5 0.3 1.30 2 10
7 0.32 1.21 3 9
6 0.11 1.00 3 9
10 0.38 1.00 5,8 11
9 0.27 0.89 6,7,8 11
11 0.5 0.62 9,1 12
12 0.12 0.12 11 -
Arif Rahman – The Production Systems
Example: Ranked Positional Weights Method
Iteration 3:
Element 8 is selected.
Alternatives are 7 and 10.
It assigns element 7.
ΣTek = 0.6 + 0.32 = 0.92 min
Alternatives are 10 and 9
10 and 9 can not be assigned, since
ΣTek > Ts
90
No Tek (min) RPW Predecessors Successors
1 0.2 3.30 - 3,4
3 0.7 3.00 1 6,7,8
2 0.4 2.67 - 4,5
4 0.1 1.97 1,2 8
8 0.6 1.87 3,4 9,1
5 0.3 1.30 2 10
7 0.32 1.21 3 9
6 0.11 1.00 3 9
10 0.38 1.00 5,8 11
9 0.27 0.89 6,7,8 11
11 0.5 0.62 9,1 12
12 0.12 0.12 11 -
Arif Rahman – The Production Systems
Example: Ranked Positional Weights Method
Iteration 4:
Element 10 is selected.
Alternative is 9.
It assigns element 9.
ΣTek = 0.38 + 0.27 = 0.65 min
Alternative is 11
11 can not be assigned, since ΣTek
> Ts
91
No Tek (min) RPW Predecessors Successors
1 0.2 3.30 - 3,4
3 0.7 3.00 1 6,7,8
2 0.4 2.67 - 4,5
4 0.1 1.97 1,2 8
8 0.6 1.87 3,4 9,1
5 0.3 1.30 2 10
7 0.32 1.21 3 9
6 0.11 1.00 3 9
10 0.38 1.00 5,8 11
9 0.27 0.89 6,7,8 11
11 0.5 0.62 9,1 12
12 0.12 0.12 11 -
Arif Rahman – The Production Systems
Example: Ranked Positional Weights Method
Iteration 5:
Element 11 is selected.
Alternative is 12.
It assigns element 12.
ΣTek = 0.5 + 0.12 = 0.62 min
All elements have been assigned.
92
No Tek (min) RPW Predecessors Successors
1 0.2 3.30 - 3,4
3 0.7 3.00 1 6,7,8
2 0.4 2.67 - 4,5
4 0.1 1.97 1,2 8
8 0.6 1.87 3,4 9,1
5 0.3 1.30 2 10
7 0.32 1.21 3 9
6 0.11 1.00 3 9
10 0.38 1.00 5,8 11
9 0.27 0.89 6,7,8 11
11 0.5 0.62 9,1 12
12 0.12 0.12 11 -
Arif Rahman – The Production Systems
Example: Ranked Positional Weights Method
Final Solution:
Workstation 1 : 1-3 = 0.9 min
Workstation 2 : 2-4-5-6 = 0.91 min
Workstation 3 : 8-7 = 0.92 min
Workstation 4 : 10-9 = 0.65 min
Workstation 5 : 11-12 = 0.62 min
93
No Tek (min) RPW Predecessors Successors
1 0.2 3.30 - 3,4
3 0.7 3.00 1 6,7,8
2 0.4 2.67 - 4,5
4 0.1 1.97 1,2 8
8 0.6 1.87 3,4 9,1
5 0.3 1.30 2 10
7 0.32 1.21 3 9
6 0.11 1.00 3 9
10 0.38 1.00 5,8 11
9 0.27 0.89 6,7,8 11
11 0.5 0.62 9,1 12
12 0.12 0.12 11 -
Arif Rahman – The Production Systems
Example: Solution
94
Work Elements Arrangement . Ts = 1 min.
Workstatio
n
No Tek (min) ΣTek
1 1 0.2 0.9
3 0.7
2 2 0.4 0.91
4 0.1
5 0.3
6 0.11
3 7 0.32 0.92
8 0.6
4 9 0.27 0.65
10 0.38
5 11 0.5 0.62
12 0.12
Arif Rahman – The Production Systems
Example: Solution
95
Work Elements Arrangement . Ts = 1 min.
Arif Rahman – The Production Systems
Solution for Ranked Positional Weights Method
96
Physical layout of workstations and assignment of
elements to stations using the Ranked Positional Weights
Method
Arif Rahman – The Production Systems
Largest Candidate Rule
Kilbridge and Wester Method
Balance efficiency
97
( )
8.0
15
4
==bE
( )
8.0
15
4
==bE
Arif Rahman – The Production Systems
Ranked Positional Weights Method
Balance efficiency
98
( )
( ) 6.5796.060
60
1
6060
108.092.0
87.0
92.05
4
===
===
=+=+=
==
ERR
T
R
TTT
E
cp
c
c
rsc
b
Arif Rahman – The Production Systems
A manual production line capable of producing
a variety of different product models
simultaneously and continuously (not in
batches)
Problems in designing and operating a
MMAL:
¤ Determining number of workers on the line
¤ Line balancing - same basic problem as in SMAL
except differences in work elements among
models must be considered
¤ Model launching - determining the sequence in
which different models will be launched onto
the line
Mixed Model Assembly Lines
99
Arif Rahman – The Production Systems
Line efficiency
¤ Management is responsible to maintain line
operation at efficiencies (proportion uptime)
close to 100%
• Implement preventive maintenance
• Well-trained emergency repair crews to quickly fix
breakdowns when they occur
• Avoid shortages of incoming parts to avoid forced
downtime
• Insist on highest quality components from
suppliers to avoid downtime due to poor quality
parts
Other Considerations in Line Design
100
Arif Rahman – The Production Systems
Methods analysis
¤ To analyze methods at bottleneck or other
troublesome workstations
Subdividing work elements
¤ It may be technically possible to subdivide some work
elements to achieve a better line balance
Sharing work elements between two adjacent
stations
¤ Alternative cycles between two workers
Other Considerations - continued
101
Arif Rahman – The Production Systems
Utility workers
¤ To relieve congestion at stations that are
temporarily overloaded
Changing workhead speeds at mechanized
stations
¤ Increase power feed or speed to achieve a better
line balance
Preassembly of components
¤ Prepare certain subassemblies off-line to reduce
work content time on the final assembly line
Other Considerations - continued
102
Arif Rahman – The Production Systems
Storage buffers between stations
¤ To permit continued operation of certain sections
of the line when other sections break down
¤ To smooth production between stations with large
task time variations
Parallel stations
¤ To reduce time at bottleneck stations that have
unusually long task times
Worker (Labor) Shifting with crosstraining
¤ Temporary (or periodic) relocation to expedite or
to reduce subassembly stocks
Other Considerations - continued
103
Arif Rahman – The Production Systems
Zoning constraints - limitations on the
grouping of work elements and/or their
allocation to workstations
¤ Positive zoning constraints
• Work elements should be grouped at same station
• Example: spray painting elements
¤ Negative zoning constraints
• Elements that might interfere with each other
• Separate delicate adjustments from loud noises
Other Considerations - continued
104
Arif Rahman – The Production Systems
Position constraints
¤ Encountered in assembly of large products
such as trucks and cars, making it difficult for
one worker to perform tasks on both sides of
the product
¤ To address, assembly workers are positioned
on both sides of the line
Other Considerations - continued
105
Arif Rahman – The Production Systems 106
It’s end of slides…It’s end of slides…
…… Any question ?Any question ?

More Related Content

What's hot

Group technology, Production flow Analysis
Group technology, Production flow AnalysisGroup technology, Production flow Analysis
Group technology, Production flow AnalysisKEERTHIVASAN RAVI
 
Flexible manufacturing systems
Flexible manufacturing systems Flexible manufacturing systems
Flexible manufacturing systems Nityanand Yadav
 
Assembly line balancing
Assembly line balancingAssembly line balancing
Assembly line balancingshady anwer
 
Cellular manufacturing and group technology
Cellular manufacturing and group technologyCellular manufacturing and group technology
Cellular manufacturing and group technologyHitendrasinh Zala
 
Line balancing and its formulation
Line balancing and its formulationLine balancing and its formulation
Line balancing and its formulationavijit biswas
 
06 group technology
06 group technology06 group technology
06 group technologyArif Rahman
 
Cellular manufacturing
Cellular manufacturingCellular manufacturing
Cellular manufacturingananya0122
 
Cellular Manufacturing
Cellular Manufacturing Cellular Manufacturing
Cellular Manufacturing sgrsoni45
 
Assembly Line Balancing
Assembly Line BalancingAssembly Line Balancing
Assembly Line BalancingAlan Wei Teck
 
Flexible Manufacturing System
Flexible Manufacturing SystemFlexible Manufacturing System
Flexible Manufacturing SystemDesai Vaishali
 
Process planning approaches
Process planning approaches Process planning approaches
Process planning approaches chethan kumar
 
History of Lean manufacturing & TPS 14 Principal
History of Lean manufacturing & TPS 14 PrincipalHistory of Lean manufacturing & TPS 14 Principal
History of Lean manufacturing & TPS 14 PrincipalSumon Kumar Kundu
 
Unit iv Shop floor control and FMS
Unit iv Shop floor control and FMSUnit iv Shop floor control and FMS
Unit iv Shop floor control and FMSmanimaran m
 
Flexible manufacturing systems (FMS)
Flexible manufacturing systems (FMS)Flexible manufacturing systems (FMS)
Flexible manufacturing systems (FMS)SERCOD
 

What's hot (20)

Group technology, Production flow Analysis
Group technology, Production flow AnalysisGroup technology, Production flow Analysis
Group technology, Production flow Analysis
 
Line balancing
Line balancingLine balancing
Line balancing
 
Flexible manufacturing systems
Flexible manufacturing systems Flexible manufacturing systems
Flexible manufacturing systems
 
Lean Manufacturing - An Overview
Lean Manufacturing - An OverviewLean Manufacturing - An Overview
Lean Manufacturing - An Overview
 
Assembly line balancing
Assembly line balancingAssembly line balancing
Assembly line balancing
 
Cellular manufacturing and group technology
Cellular manufacturing and group technologyCellular manufacturing and group technology
Cellular manufacturing and group technology
 
CIM 15ME62 Module-1
CIM 15ME62   Module-1CIM 15ME62   Module-1
CIM 15ME62 Module-1
 
Line balancing and its formulation
Line balancing and its formulationLine balancing and its formulation
Line balancing and its formulation
 
06 group technology
06 group technology06 group technology
06 group technology
 
Assembly Line Production Introduction
Assembly Line Production   IntroductionAssembly Line Production   Introduction
Assembly Line Production Introduction
 
Cellular manufacturing
Cellular manufacturingCellular manufacturing
Cellular manufacturing
 
Cellular Manufacturing
Cellular Manufacturing Cellular Manufacturing
Cellular Manufacturing
 
Assembly Line Balancing
Assembly Line BalancingAssembly Line Balancing
Assembly Line Balancing
 
Flexible Manufacturing System
Flexible Manufacturing SystemFlexible Manufacturing System
Flexible Manufacturing System
 
Method study
Method studyMethod study
Method study
 
Manual Assembly Lines1
Manual Assembly Lines1Manual Assembly Lines1
Manual Assembly Lines1
 
Process planning approaches
Process planning approaches Process planning approaches
Process planning approaches
 
History of Lean manufacturing & TPS 14 Principal
History of Lean manufacturing & TPS 14 PrincipalHistory of Lean manufacturing & TPS 14 Principal
History of Lean manufacturing & TPS 14 Principal
 
Unit iv Shop floor control and FMS
Unit iv Shop floor control and FMSUnit iv Shop floor control and FMS
Unit iv Shop floor control and FMS
 
Flexible manufacturing systems (FMS)
Flexible manufacturing systems (FMS)Flexible manufacturing systems (FMS)
Flexible manufacturing systems (FMS)
 

Similar to 07 Line Balancing

05 single station
05 single station05 single station
05 single stationArif Rahman
 
Unit 3 Manufacturing Systems in automation
Unit 3 Manufacturing Systems in automationUnit 3 Manufacturing Systems in automation
Unit 3 Manufacturing Systems in automationrahulkatre9
 
02 elements of production systems
02 elements of production systems02 elements of production systems
02 elements of production systemsArif Rahman
 
Aiar. unit ii. transfer lines
Aiar. unit ii. transfer linesAiar. unit ii. transfer lines
Aiar. unit ii. transfer linesKunal mane
 
Unit 1-automation of assembly lines
Unit 1-automation of assembly linesUnit 1-automation of assembly lines
Unit 1-automation of assembly linesjoemaxagu
 
advanced industrial automation and robotics
advanced industrial automation and roboticsadvanced industrial automation and robotics
advanced industrial automation and roboticsKunal mane
 
Process Selection and Facility layout.ppt
Process Selection and Facility layout.pptProcess Selection and Facility layout.ppt
Process Selection and Facility layout.pptSandipanMaji3
 
14 synchronous manufacturing
14 synchronous manufacturing14 synchronous manufacturing
14 synchronous manufacturingArif Rahman
 
09 shop floor control
09 shop floor control09 shop floor control
09 shop floor controlArif Rahman
 
REPAIR METHODS FOR MATERIAL HANDLING EQUIPMENT
REPAIR METHODS FOR MATERIAL HANDLING EQUIPMENTREPAIR METHODS FOR MATERIAL HANDLING EQUIPMENT
REPAIR METHODS FOR MATERIAL HANDLING EQUIPMENTlaxtwinsme
 
garmentproductionsystems.pptx
garmentproductionsystems.pptxgarmentproductionsystems.pptx
garmentproductionsystems.pptxssuser820b7a
 

Similar to 07 Line Balancing (20)

05 single station
05 single station05 single station
05 single station
 
Unit 3 Manufacturing Systems in automation
Unit 3 Manufacturing Systems in automationUnit 3 Manufacturing Systems in automation
Unit 3 Manufacturing Systems in automation
 
02 elements of production systems
02 elements of production systems02 elements of production systems
02 elements of production systems
 
Modular garments production system
Modular garments production systemModular garments production system
Modular garments production system
 
Manufacturing systems
Manufacturing systems Manufacturing systems
Manufacturing systems
 
Production System.pptx
Production System.pptxProduction System.pptx
Production System.pptx
 
Aiar. unit ii. transfer lines
Aiar. unit ii. transfer linesAiar. unit ii. transfer lines
Aiar. unit ii. transfer lines
 
MA1.ppt
MA1.pptMA1.ppt
MA1.ppt
 
LINE PACING ETC...ppt
LINE PACING  ETC...pptLINE PACING  ETC...ppt
LINE PACING ETC...ppt
 
LINE PACING ETC..-2.ppt
LINE PACING  ETC..-2.pptLINE PACING  ETC..-2.ppt
LINE PACING ETC..-2.ppt
 
Unit 1-automation of assembly lines
Unit 1-automation of assembly linesUnit 1-automation of assembly lines
Unit 1-automation of assembly lines
 
advanced industrial automation and robotics
advanced industrial automation and roboticsadvanced industrial automation and robotics
advanced industrial automation and robotics
 
Process Selection and Facility layout.ppt
Process Selection and Facility layout.pptProcess Selection and Facility layout.ppt
Process Selection and Facility layout.ppt
 
14 synchronous manufacturing
14 synchronous manufacturing14 synchronous manufacturing
14 synchronous manufacturing
 
Advance manufacturing system in sewing floor
Advance manufacturing system in sewing floorAdvance manufacturing system in sewing floor
Advance manufacturing system in sewing floor
 
plant layout
plant layoutplant layout
plant layout
 
09 shop floor control
09 shop floor control09 shop floor control
09 shop floor control
 
Types of Manufacturing system
Types of Manufacturing systemTypes of Manufacturing system
Types of Manufacturing system
 
REPAIR METHODS FOR MATERIAL HANDLING EQUIPMENT
REPAIR METHODS FOR MATERIAL HANDLING EQUIPMENTREPAIR METHODS FOR MATERIAL HANDLING EQUIPMENT
REPAIR METHODS FOR MATERIAL HANDLING EQUIPMENT
 
garmentproductionsystems.pptx
garmentproductionsystems.pptxgarmentproductionsystems.pptx
garmentproductionsystems.pptx
 

More from Arif Rahman

Proses Data: Analisis Data Eksploratori - Modul Ajar Kuliah Analisis Data 07
Proses Data: Analisis Data Eksploratori - Modul Ajar Kuliah Analisis Data 07Proses Data: Analisis Data Eksploratori - Modul Ajar Kuliah Analisis Data 07
Proses Data: Analisis Data Eksploratori - Modul Ajar Kuliah Analisis Data 07Arif Rahman
 
Proses Data: Analisis Data Eksploratori - Modul Ajar Kuliah Analisis Data 06
Proses Data: Analisis Data Eksploratori - Modul Ajar Kuliah Analisis Data 06Proses Data: Analisis Data Eksploratori - Modul Ajar Kuliah Analisis Data 06
Proses Data: Analisis Data Eksploratori - Modul Ajar Kuliah Analisis Data 06Arif Rahman
 
Preparasi Data: Pembersihan dan Proses Awal Data - Modul Ajar Kuliah Analisis...
Preparasi Data: Pembersihan dan Proses Awal Data - Modul Ajar Kuliah Analisis...Preparasi Data: Pembersihan dan Proses Awal Data - Modul Ajar Kuliah Analisis...
Preparasi Data: Pembersihan dan Proses Awal Data - Modul Ajar Kuliah Analisis...Arif Rahman
 
Preparasi Data: Pembersihan dan Proses Awal Data - Modul Ajar Kuliah Analisis...
Preparasi Data: Pembersihan dan Proses Awal Data - Modul Ajar Kuliah Analisis...Preparasi Data: Pembersihan dan Proses Awal Data - Modul Ajar Kuliah Analisis...
Preparasi Data: Pembersihan dan Proses Awal Data - Modul Ajar Kuliah Analisis...Arif Rahman
 
Preparasi Data: Penetapan Tujuan dan Pengumpulan Data - Modul Ajar Kuliah Ana...
Preparasi Data: Penetapan Tujuan dan Pengumpulan Data - Modul Ajar Kuliah Ana...Preparasi Data: Penetapan Tujuan dan Pengumpulan Data - Modul Ajar Kuliah Ana...
Preparasi Data: Penetapan Tujuan dan Pengumpulan Data - Modul Ajar Kuliah Ana...Arif Rahman
 
Proses Data Science - Modul Ajar Kuliah Analisis Data 02
Proses Data Science - Modul Ajar Kuliah Analisis Data 02Proses Data Science - Modul Ajar Kuliah Analisis Data 02
Proses Data Science - Modul Ajar Kuliah Analisis Data 02Arif Rahman
 
Pengantar Analisis Data - Modul Ajar Kuliah Analisis Data 01
Pengantar Analisis Data - Modul Ajar Kuliah Analisis Data 01Pengantar Analisis Data - Modul Ajar Kuliah Analisis Data 01
Pengantar Analisis Data - Modul Ajar Kuliah Analisis Data 01Arif Rahman
 
Modul Ajar Statistika Inferensia ke-13: Analisis Variansi, Eksperimentasi Fak...
Modul Ajar Statistika Inferensia ke-13: Analisis Variansi, Eksperimentasi Fak...Modul Ajar Statistika Inferensia ke-13: Analisis Variansi, Eksperimentasi Fak...
Modul Ajar Statistika Inferensia ke-13: Analisis Variansi, Eksperimentasi Fak...Arif Rahman
 
Modul Ajar Statistika Inferensia ke-12: Uji Asumsi Klasik pada Regresi Linier...
Modul Ajar Statistika Inferensia ke-12: Uji Asumsi Klasik pada Regresi Linier...Modul Ajar Statistika Inferensia ke-12: Uji Asumsi Klasik pada Regresi Linier...
Modul Ajar Statistika Inferensia ke-12: Uji Asumsi Klasik pada Regresi Linier...Arif Rahman
 
Modul Ajar Statistika Inferensia ke-11: Analisis Regresi Linier Berganda (Mul...
Modul Ajar Statistika Inferensia ke-11: Analisis Regresi Linier Berganda (Mul...Modul Ajar Statistika Inferensia ke-11: Analisis Regresi Linier Berganda (Mul...
Modul Ajar Statistika Inferensia ke-11: Analisis Regresi Linier Berganda (Mul...Arif Rahman
 
Modul Ajar Statistika Inferensia ke-10: Analisis Regresi Nonlinier
Modul Ajar Statistika Inferensia ke-10: Analisis Regresi NonlinierModul Ajar Statistika Inferensia ke-10: Analisis Regresi Nonlinier
Modul Ajar Statistika Inferensia ke-10: Analisis Regresi NonlinierArif Rahman
 
Modul Ajar Statistika Inferensia ke-9: Analisis Regresi Linier Sederhana (Sim...
Modul Ajar Statistika Inferensia ke-9: Analisis Regresi Linier Sederhana (Sim...Modul Ajar Statistika Inferensia ke-9: Analisis Regresi Linier Sederhana (Sim...
Modul Ajar Statistika Inferensia ke-9: Analisis Regresi Linier Sederhana (Sim...Arif Rahman
 
Modul Ajar Statistika Inferensia ke-8: Analisis Korelasi Pearson, Spearman, K...
Modul Ajar Statistika Inferensia ke-8: Analisis Korelasi Pearson, Spearman, K...Modul Ajar Statistika Inferensia ke-8: Analisis Korelasi Pearson, Spearman, K...
Modul Ajar Statistika Inferensia ke-8: Analisis Korelasi Pearson, Spearman, K...Arif Rahman
 
Modul Ajar Statistika Inferensia ke-7: Uji Tabel Kontingensi Independensi dan...
Modul Ajar Statistika Inferensia ke-7: Uji Tabel Kontingensi Independensi dan...Modul Ajar Statistika Inferensia ke-7: Uji Tabel Kontingensi Independensi dan...
Modul Ajar Statistika Inferensia ke-7: Uji Tabel Kontingensi Independensi dan...Arif Rahman
 
Modul Ajar Statistika Inferensia ke-6: Uji Kesesuaian Baik (Goodness of Fit T...
Modul Ajar Statistika Inferensia ke-6: Uji Kesesuaian Baik (Goodness of Fit T...Modul Ajar Statistika Inferensia ke-6: Uji Kesesuaian Baik (Goodness of Fit T...
Modul Ajar Statistika Inferensia ke-6: Uji Kesesuaian Baik (Goodness of Fit T...Arif Rahman
 
Modul Ajar Statistika Inferensia ke-5: Uji Hipotesa Rata-Rata Nonparametrik
Modul Ajar Statistika Inferensia ke-5: Uji Hipotesa Rata-Rata NonparametrikModul Ajar Statistika Inferensia ke-5: Uji Hipotesa Rata-Rata Nonparametrik
Modul Ajar Statistika Inferensia ke-5: Uji Hipotesa Rata-Rata NonparametrikArif Rahman
 
Modul Ajar Statistika Inferensia ke-4: Uji Hipotesa Proporsi Parametrik
Modul Ajar Statistika Inferensia ke-4: Uji Hipotesa Proporsi ParametrikModul Ajar Statistika Inferensia ke-4: Uji Hipotesa Proporsi Parametrik
Modul Ajar Statistika Inferensia ke-4: Uji Hipotesa Proporsi ParametrikArif Rahman
 
Modul Ajar Statistika Inferensia ke-3: Uji Hipotesa Variansi Parametrik
Modul Ajar Statistika Inferensia ke-3: Uji Hipotesa Variansi ParametrikModul Ajar Statistika Inferensia ke-3: Uji Hipotesa Variansi Parametrik
Modul Ajar Statistika Inferensia ke-3: Uji Hipotesa Variansi ParametrikArif Rahman
 
Modul Ajar Statistika Inferensia ke-2: Uji Hipotesa Rata-rata Parametrik
Modul Ajar Statistika Inferensia ke-2: Uji Hipotesa Rata-rata ParametrikModul Ajar Statistika Inferensia ke-2: Uji Hipotesa Rata-rata Parametrik
Modul Ajar Statistika Inferensia ke-2: Uji Hipotesa Rata-rata ParametrikArif Rahman
 
Modul Ajar Statistika Inferensia ke-1: Pengantar Statistika Inferensia
Modul Ajar Statistika Inferensia ke-1: Pengantar Statistika InferensiaModul Ajar Statistika Inferensia ke-1: Pengantar Statistika Inferensia
Modul Ajar Statistika Inferensia ke-1: Pengantar Statistika InferensiaArif Rahman
 

More from Arif Rahman (20)

Proses Data: Analisis Data Eksploratori - Modul Ajar Kuliah Analisis Data 07
Proses Data: Analisis Data Eksploratori - Modul Ajar Kuliah Analisis Data 07Proses Data: Analisis Data Eksploratori - Modul Ajar Kuliah Analisis Data 07
Proses Data: Analisis Data Eksploratori - Modul Ajar Kuliah Analisis Data 07
 
Proses Data: Analisis Data Eksploratori - Modul Ajar Kuliah Analisis Data 06
Proses Data: Analisis Data Eksploratori - Modul Ajar Kuliah Analisis Data 06Proses Data: Analisis Data Eksploratori - Modul Ajar Kuliah Analisis Data 06
Proses Data: Analisis Data Eksploratori - Modul Ajar Kuliah Analisis Data 06
 
Preparasi Data: Pembersihan dan Proses Awal Data - Modul Ajar Kuliah Analisis...
Preparasi Data: Pembersihan dan Proses Awal Data - Modul Ajar Kuliah Analisis...Preparasi Data: Pembersihan dan Proses Awal Data - Modul Ajar Kuliah Analisis...
Preparasi Data: Pembersihan dan Proses Awal Data - Modul Ajar Kuliah Analisis...
 
Preparasi Data: Pembersihan dan Proses Awal Data - Modul Ajar Kuliah Analisis...
Preparasi Data: Pembersihan dan Proses Awal Data - Modul Ajar Kuliah Analisis...Preparasi Data: Pembersihan dan Proses Awal Data - Modul Ajar Kuliah Analisis...
Preparasi Data: Pembersihan dan Proses Awal Data - Modul Ajar Kuliah Analisis...
 
Preparasi Data: Penetapan Tujuan dan Pengumpulan Data - Modul Ajar Kuliah Ana...
Preparasi Data: Penetapan Tujuan dan Pengumpulan Data - Modul Ajar Kuliah Ana...Preparasi Data: Penetapan Tujuan dan Pengumpulan Data - Modul Ajar Kuliah Ana...
Preparasi Data: Penetapan Tujuan dan Pengumpulan Data - Modul Ajar Kuliah Ana...
 
Proses Data Science - Modul Ajar Kuliah Analisis Data 02
Proses Data Science - Modul Ajar Kuliah Analisis Data 02Proses Data Science - Modul Ajar Kuliah Analisis Data 02
Proses Data Science - Modul Ajar Kuliah Analisis Data 02
 
Pengantar Analisis Data - Modul Ajar Kuliah Analisis Data 01
Pengantar Analisis Data - Modul Ajar Kuliah Analisis Data 01Pengantar Analisis Data - Modul Ajar Kuliah Analisis Data 01
Pengantar Analisis Data - Modul Ajar Kuliah Analisis Data 01
 
Modul Ajar Statistika Inferensia ke-13: Analisis Variansi, Eksperimentasi Fak...
Modul Ajar Statistika Inferensia ke-13: Analisis Variansi, Eksperimentasi Fak...Modul Ajar Statistika Inferensia ke-13: Analisis Variansi, Eksperimentasi Fak...
Modul Ajar Statistika Inferensia ke-13: Analisis Variansi, Eksperimentasi Fak...
 
Modul Ajar Statistika Inferensia ke-12: Uji Asumsi Klasik pada Regresi Linier...
Modul Ajar Statistika Inferensia ke-12: Uji Asumsi Klasik pada Regresi Linier...Modul Ajar Statistika Inferensia ke-12: Uji Asumsi Klasik pada Regresi Linier...
Modul Ajar Statistika Inferensia ke-12: Uji Asumsi Klasik pada Regresi Linier...
 
Modul Ajar Statistika Inferensia ke-11: Analisis Regresi Linier Berganda (Mul...
Modul Ajar Statistika Inferensia ke-11: Analisis Regresi Linier Berganda (Mul...Modul Ajar Statistika Inferensia ke-11: Analisis Regresi Linier Berganda (Mul...
Modul Ajar Statistika Inferensia ke-11: Analisis Regresi Linier Berganda (Mul...
 
Modul Ajar Statistika Inferensia ke-10: Analisis Regresi Nonlinier
Modul Ajar Statistika Inferensia ke-10: Analisis Regresi NonlinierModul Ajar Statistika Inferensia ke-10: Analisis Regresi Nonlinier
Modul Ajar Statistika Inferensia ke-10: Analisis Regresi Nonlinier
 
Modul Ajar Statistika Inferensia ke-9: Analisis Regresi Linier Sederhana (Sim...
Modul Ajar Statistika Inferensia ke-9: Analisis Regresi Linier Sederhana (Sim...Modul Ajar Statistika Inferensia ke-9: Analisis Regresi Linier Sederhana (Sim...
Modul Ajar Statistika Inferensia ke-9: Analisis Regresi Linier Sederhana (Sim...
 
Modul Ajar Statistika Inferensia ke-8: Analisis Korelasi Pearson, Spearman, K...
Modul Ajar Statistika Inferensia ke-8: Analisis Korelasi Pearson, Spearman, K...Modul Ajar Statistika Inferensia ke-8: Analisis Korelasi Pearson, Spearman, K...
Modul Ajar Statistika Inferensia ke-8: Analisis Korelasi Pearson, Spearman, K...
 
Modul Ajar Statistika Inferensia ke-7: Uji Tabel Kontingensi Independensi dan...
Modul Ajar Statistika Inferensia ke-7: Uji Tabel Kontingensi Independensi dan...Modul Ajar Statistika Inferensia ke-7: Uji Tabel Kontingensi Independensi dan...
Modul Ajar Statistika Inferensia ke-7: Uji Tabel Kontingensi Independensi dan...
 
Modul Ajar Statistika Inferensia ke-6: Uji Kesesuaian Baik (Goodness of Fit T...
Modul Ajar Statistika Inferensia ke-6: Uji Kesesuaian Baik (Goodness of Fit T...Modul Ajar Statistika Inferensia ke-6: Uji Kesesuaian Baik (Goodness of Fit T...
Modul Ajar Statistika Inferensia ke-6: Uji Kesesuaian Baik (Goodness of Fit T...
 
Modul Ajar Statistika Inferensia ke-5: Uji Hipotesa Rata-Rata Nonparametrik
Modul Ajar Statistika Inferensia ke-5: Uji Hipotesa Rata-Rata NonparametrikModul Ajar Statistika Inferensia ke-5: Uji Hipotesa Rata-Rata Nonparametrik
Modul Ajar Statistika Inferensia ke-5: Uji Hipotesa Rata-Rata Nonparametrik
 
Modul Ajar Statistika Inferensia ke-4: Uji Hipotesa Proporsi Parametrik
Modul Ajar Statistika Inferensia ke-4: Uji Hipotesa Proporsi ParametrikModul Ajar Statistika Inferensia ke-4: Uji Hipotesa Proporsi Parametrik
Modul Ajar Statistika Inferensia ke-4: Uji Hipotesa Proporsi Parametrik
 
Modul Ajar Statistika Inferensia ke-3: Uji Hipotesa Variansi Parametrik
Modul Ajar Statistika Inferensia ke-3: Uji Hipotesa Variansi ParametrikModul Ajar Statistika Inferensia ke-3: Uji Hipotesa Variansi Parametrik
Modul Ajar Statistika Inferensia ke-3: Uji Hipotesa Variansi Parametrik
 
Modul Ajar Statistika Inferensia ke-2: Uji Hipotesa Rata-rata Parametrik
Modul Ajar Statistika Inferensia ke-2: Uji Hipotesa Rata-rata ParametrikModul Ajar Statistika Inferensia ke-2: Uji Hipotesa Rata-rata Parametrik
Modul Ajar Statistika Inferensia ke-2: Uji Hipotesa Rata-rata Parametrik
 
Modul Ajar Statistika Inferensia ke-1: Pengantar Statistika Inferensia
Modul Ajar Statistika Inferensia ke-1: Pengantar Statistika InferensiaModul Ajar Statistika Inferensia ke-1: Pengantar Statistika Inferensia
Modul Ajar Statistika Inferensia ke-1: Pengantar Statistika Inferensia
 

Recently uploaded

HARMONY IN THE NATURE AND EXISTENCE - Unit-IV
HARMONY IN THE NATURE AND EXISTENCE - Unit-IVHARMONY IN THE NATURE AND EXISTENCE - Unit-IV
HARMONY IN THE NATURE AND EXISTENCE - Unit-IVRajaP95
 
UNIT-V FMM.HYDRAULIC TURBINE - Construction and working
UNIT-V FMM.HYDRAULIC TURBINE - Construction and workingUNIT-V FMM.HYDRAULIC TURBINE - Construction and working
UNIT-V FMM.HYDRAULIC TURBINE - Construction and workingrknatarajan
 
Introduction to Multiple Access Protocol.pptx
Introduction to Multiple Access Protocol.pptxIntroduction to Multiple Access Protocol.pptx
Introduction to Multiple Access Protocol.pptxupamatechverse
 
UNIT-III FMM. DIMENSIONAL ANALYSIS
UNIT-III FMM.        DIMENSIONAL ANALYSISUNIT-III FMM.        DIMENSIONAL ANALYSIS
UNIT-III FMM. DIMENSIONAL ANALYSISrknatarajan
 
Call Girls Service Nashik Vaishnavi 7001305949 Independent Escort Service Nashik
Call Girls Service Nashik Vaishnavi 7001305949 Independent Escort Service NashikCall Girls Service Nashik Vaishnavi 7001305949 Independent Escort Service Nashik
Call Girls Service Nashik Vaishnavi 7001305949 Independent Escort Service NashikCall Girls in Nagpur High Profile
 
Decoding Kotlin - Your guide to solving the mysterious in Kotlin.pptx
Decoding Kotlin - Your guide to solving the mysterious in Kotlin.pptxDecoding Kotlin - Your guide to solving the mysterious in Kotlin.pptx
Decoding Kotlin - Your guide to solving the mysterious in Kotlin.pptxJoão Esperancinha
 
Call for Papers - African Journal of Biological Sciences, E-ISSN: 2663-2187, ...
Call for Papers - African Journal of Biological Sciences, E-ISSN: 2663-2187, ...Call for Papers - African Journal of Biological Sciences, E-ISSN: 2663-2187, ...
Call for Papers - African Journal of Biological Sciences, E-ISSN: 2663-2187, ...Christo Ananth
 
Structural Analysis and Design of Foundations: A Comprehensive Handbook for S...
Structural Analysis and Design of Foundations: A Comprehensive Handbook for S...Structural Analysis and Design of Foundations: A Comprehensive Handbook for S...
Structural Analysis and Design of Foundations: A Comprehensive Handbook for S...Dr.Costas Sachpazis
 
(PRIYA) Rajgurunagar Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(PRIYA) Rajgurunagar Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...(PRIYA) Rajgurunagar Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(PRIYA) Rajgurunagar Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...ranjana rawat
 
VIP Call Girls Service Kondapur Hyderabad Call +91-8250192130
VIP Call Girls Service Kondapur Hyderabad Call +91-8250192130VIP Call Girls Service Kondapur Hyderabad Call +91-8250192130
VIP Call Girls Service Kondapur Hyderabad Call +91-8250192130Suhani Kapoor
 
Top Rated Pune Call Girls Budhwar Peth ⟟ 6297143586 ⟟ Call Me For Genuine Se...
Top Rated  Pune Call Girls Budhwar Peth ⟟ 6297143586 ⟟ Call Me For Genuine Se...Top Rated  Pune Call Girls Budhwar Peth ⟟ 6297143586 ⟟ Call Me For Genuine Se...
Top Rated Pune Call Girls Budhwar Peth ⟟ 6297143586 ⟟ Call Me For Genuine Se...Call Girls in Nagpur High Profile
 
(SHREYA) Chakan Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Esc...
(SHREYA) Chakan Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Esc...(SHREYA) Chakan Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Esc...
(SHREYA) Chakan Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Esc...ranjana rawat
 
HARDNESS, FRACTURE TOUGHNESS AND STRENGTH OF CERAMICS
HARDNESS, FRACTURE TOUGHNESS AND STRENGTH OF CERAMICSHARDNESS, FRACTURE TOUGHNESS AND STRENGTH OF CERAMICS
HARDNESS, FRACTURE TOUGHNESS AND STRENGTH OF CERAMICSRajkumarAkumalla
 
Software Development Life Cycle By Team Orange (Dept. of Pharmacy)
Software Development Life Cycle By  Team Orange (Dept. of Pharmacy)Software Development Life Cycle By  Team Orange (Dept. of Pharmacy)
Software Development Life Cycle By Team Orange (Dept. of Pharmacy)Suman Mia
 
MANUFACTURING PROCESS-II UNIT-5 NC MACHINE TOOLS
MANUFACTURING PROCESS-II UNIT-5 NC MACHINE TOOLSMANUFACTURING PROCESS-II UNIT-5 NC MACHINE TOOLS
MANUFACTURING PROCESS-II UNIT-5 NC MACHINE TOOLSSIVASHANKAR N
 
MANUFACTURING PROCESS-II UNIT-2 LATHE MACHINE
MANUFACTURING PROCESS-II UNIT-2 LATHE MACHINEMANUFACTURING PROCESS-II UNIT-2 LATHE MACHINE
MANUFACTURING PROCESS-II UNIT-2 LATHE MACHINESIVASHANKAR N
 
(ANJALI) Dange Chowk Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(ANJALI) Dange Chowk Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...(ANJALI) Dange Chowk Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(ANJALI) Dange Chowk Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...ranjana rawat
 

Recently uploaded (20)

HARMONY IN THE NATURE AND EXISTENCE - Unit-IV
HARMONY IN THE NATURE AND EXISTENCE - Unit-IVHARMONY IN THE NATURE AND EXISTENCE - Unit-IV
HARMONY IN THE NATURE AND EXISTENCE - Unit-IV
 
UNIT-V FMM.HYDRAULIC TURBINE - Construction and working
UNIT-V FMM.HYDRAULIC TURBINE - Construction and workingUNIT-V FMM.HYDRAULIC TURBINE - Construction and working
UNIT-V FMM.HYDRAULIC TURBINE - Construction and working
 
Introduction to Multiple Access Protocol.pptx
Introduction to Multiple Access Protocol.pptxIntroduction to Multiple Access Protocol.pptx
Introduction to Multiple Access Protocol.pptx
 
UNIT-III FMM. DIMENSIONAL ANALYSIS
UNIT-III FMM.        DIMENSIONAL ANALYSISUNIT-III FMM.        DIMENSIONAL ANALYSIS
UNIT-III FMM. DIMENSIONAL ANALYSIS
 
Call Girls Service Nashik Vaishnavi 7001305949 Independent Escort Service Nashik
Call Girls Service Nashik Vaishnavi 7001305949 Independent Escort Service NashikCall Girls Service Nashik Vaishnavi 7001305949 Independent Escort Service Nashik
Call Girls Service Nashik Vaishnavi 7001305949 Independent Escort Service Nashik
 
Decoding Kotlin - Your guide to solving the mysterious in Kotlin.pptx
Decoding Kotlin - Your guide to solving the mysterious in Kotlin.pptxDecoding Kotlin - Your guide to solving the mysterious in Kotlin.pptx
Decoding Kotlin - Your guide to solving the mysterious in Kotlin.pptx
 
Call for Papers - African Journal of Biological Sciences, E-ISSN: 2663-2187, ...
Call for Papers - African Journal of Biological Sciences, E-ISSN: 2663-2187, ...Call for Papers - African Journal of Biological Sciences, E-ISSN: 2663-2187, ...
Call for Papers - African Journal of Biological Sciences, E-ISSN: 2663-2187, ...
 
Structural Analysis and Design of Foundations: A Comprehensive Handbook for S...
Structural Analysis and Design of Foundations: A Comprehensive Handbook for S...Structural Analysis and Design of Foundations: A Comprehensive Handbook for S...
Structural Analysis and Design of Foundations: A Comprehensive Handbook for S...
 
(PRIYA) Rajgurunagar Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(PRIYA) Rajgurunagar Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...(PRIYA) Rajgurunagar Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(PRIYA) Rajgurunagar Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
 
VIP Call Girls Service Kondapur Hyderabad Call +91-8250192130
VIP Call Girls Service Kondapur Hyderabad Call +91-8250192130VIP Call Girls Service Kondapur Hyderabad Call +91-8250192130
VIP Call Girls Service Kondapur Hyderabad Call +91-8250192130
 
Top Rated Pune Call Girls Budhwar Peth ⟟ 6297143586 ⟟ Call Me For Genuine Se...
Top Rated  Pune Call Girls Budhwar Peth ⟟ 6297143586 ⟟ Call Me For Genuine Se...Top Rated  Pune Call Girls Budhwar Peth ⟟ 6297143586 ⟟ Call Me For Genuine Se...
Top Rated Pune Call Girls Budhwar Peth ⟟ 6297143586 ⟟ Call Me For Genuine Se...
 
(SHREYA) Chakan Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Esc...
(SHREYA) Chakan Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Esc...(SHREYA) Chakan Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Esc...
(SHREYA) Chakan Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Esc...
 
★ CALL US 9953330565 ( HOT Young Call Girls In Badarpur delhi NCR
★ CALL US 9953330565 ( HOT Young Call Girls In Badarpur delhi NCR★ CALL US 9953330565 ( HOT Young Call Girls In Badarpur delhi NCR
★ CALL US 9953330565 ( HOT Young Call Girls In Badarpur delhi NCR
 
Call Us -/9953056974- Call Girls In Vikaspuri-/- Delhi NCR
Call Us -/9953056974- Call Girls In Vikaspuri-/- Delhi NCRCall Us -/9953056974- Call Girls In Vikaspuri-/- Delhi NCR
Call Us -/9953056974- Call Girls In Vikaspuri-/- Delhi NCR
 
Roadmap to Membership of RICS - Pathways and Routes
Roadmap to Membership of RICS - Pathways and RoutesRoadmap to Membership of RICS - Pathways and Routes
Roadmap to Membership of RICS - Pathways and Routes
 
HARDNESS, FRACTURE TOUGHNESS AND STRENGTH OF CERAMICS
HARDNESS, FRACTURE TOUGHNESS AND STRENGTH OF CERAMICSHARDNESS, FRACTURE TOUGHNESS AND STRENGTH OF CERAMICS
HARDNESS, FRACTURE TOUGHNESS AND STRENGTH OF CERAMICS
 
Software Development Life Cycle By Team Orange (Dept. of Pharmacy)
Software Development Life Cycle By  Team Orange (Dept. of Pharmacy)Software Development Life Cycle By  Team Orange (Dept. of Pharmacy)
Software Development Life Cycle By Team Orange (Dept. of Pharmacy)
 
MANUFACTURING PROCESS-II UNIT-5 NC MACHINE TOOLS
MANUFACTURING PROCESS-II UNIT-5 NC MACHINE TOOLSMANUFACTURING PROCESS-II UNIT-5 NC MACHINE TOOLS
MANUFACTURING PROCESS-II UNIT-5 NC MACHINE TOOLS
 
MANUFACTURING PROCESS-II UNIT-2 LATHE MACHINE
MANUFACTURING PROCESS-II UNIT-2 LATHE MACHINEMANUFACTURING PROCESS-II UNIT-2 LATHE MACHINE
MANUFACTURING PROCESS-II UNIT-2 LATHE MACHINE
 
(ANJALI) Dange Chowk Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(ANJALI) Dange Chowk Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...(ANJALI) Dange Chowk Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(ANJALI) Dange Chowk Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
 

07 Line Balancing

  • 1. Arif Rahman – The Production Systems 1 Slide 7 Manual Assembly Line Arif Rahman, ST MT
  • 2. Arif Rahman – The Production Systems Most consumer products are assembled on manual assembly lines Factors favoring the use of assembly lines: ¤ High or medium demand for product ¤ Identical or similar products ¤ Total work content can be divided into work elements ¤ It is technologically impossible or economically infeasible to automate the assembly operations Manual Assembly Lines 2
  • 3. Arif Rahman – The Production Systems Specialization of labor ¤ Learning curve Interchangeable parts ¤ Components made to close tolerances ¤ Assemblies do not need fitting of mating components Work flow principle ¤ Products are brought to the workers Line pacing ¤ Workers must complete their tasks within the cycle time of the line Why Assembly Lines are so Productive 3
  • 4. Arif Rahman – The Production Systems Typical Products Made on Assembly Lines Automobiles Cooking ranges Dishwashers Dryers Furniture Lamps Luggage Microwave ovens Personal computers Power tools Refrigerators Telephones Toasters Trucks Video DVD players Washing machines 4
  • 5. Arif Rahman – The Production Systems A production line consisting of a sequence of workstations where assembly tasks are performed by human workers as the product moves along the line ¤ Work systems consisting of multiple workers organized to produce a single product or a limited range of products • Each product consists of multiple components joined together by various assembly work elements  Total work content - the sum of all work elements required to assemble one product unit on the line ¤ Assembly workers perform tasks at workstations located along the line-of-flow of the product • Usually a powered conveyor is used • Some of the workstations may be equipped with portable powered tools Manual Assembly Line Defined 5
  • 6. Arif Rahman – The Production Systems Manual Assembly Line 6 Configuration of a manual assembly line with n manually operated workstations
  • 7. Arif Rahman – The Production Systems The production rate of an assembly line is determined by its slowest station. Assembly workstation: A designated location along the work flow path at which one or more work elements are performed by one or more workers Manual Assembly Line 7
  • 8. Arif Rahman – The Production Systems Manual Assembly Line Two assembly operators working on an engine assembly line (photo courtesy of Ford Motor Company) 8
  • 9. Arif Rahman – The Production Systems Products are assembled as they move along the line ¤ At each station a portion of the total work content is performed on each unit Base parts are launched onto the beginning of the line at regular intervals (cycle time) ¤ Workers add components to progressively build the product Manual Assembly Line 9
  • 10. Arif Rahman – The Production Systems Typical operations performed at manual assembly stations Adhesive application Sealant application Arc welding Spotwelding Electrical connections Componentinsertion Pressfitting Riveting Snap fitting Soldering Stitching/stapling Threadedfasteners Assembly Workstation 10 A designated location along the work flow path at which one or more work elements are performed by one or more workers
  • 11. Arif Rahman – The Production Systems There may be more than one worker per station. Utility workers: are not assigned to specific workstations. They are responsible for ¤ helping workers who fall behind, ¤ relieving for workers for personal breaks, ¤ maintenance and repair Manning level 11
  • 12. Arif Rahman – The Production Systems Average manning level: where : M = average manning level of the line, n = number of workstations w = number of workers on the line wu = number of utility workers assigned to the system,, wi = number of workers assigned specifically to station i for i=1,…,n Manning level 12 n ww n w M n i iu ∑= + == 1
  • 13. Arif Rahman – The Production Systems Two basic categories: ¤ Manual ¤ Mechanized Work Transport Systems 13
  • 14. Arif Rahman – The Production Systems Work units are moved between stations by the workers without the aid of a powered conveyor ¤ Types: • Work units moved in batches • Work units moved one at a time ¤ Problems: • Starving of stations • Blocking of stations • No pacing Manual Work Transport Systems 14
  • 15. Arif Rahman – The Production Systems To reduce starving, ¤ use buffers To prevent blocking, ¤ provide space between upstream and downstream stations. But both solutions can result in higher WIP, ¤ which is economically undesirable. Work Transport Systems-Manual Methods 15
  • 16. Arif Rahman – The Production Systems Work units are moved by powered conveyor or other mechanized apparatus ¤ Categories: • Work units attached to conveyor • Work units are removable from conveyor ¤ Problems • Starving of stations • Incomplete units Mechanized Work Transport Systems 16
  • 17. Arif Rahman – The Production Systems Continuous transport ¤ Conveyor moves at constant speed Synchronous transport/intermittent transport ¤ Work units are moved simultaneously with stop- and-go (intermittent) motion to next stations Asynchronous transport ¤ Work units are moved independently between workstations ¤ Queues of work units can form in front of each station Types of Mechanized Work Transport 17
  • 18. Arif Rahman – The Production Systems Continuous Transport 18 Conveyor moves at constant velocity vc
  • 19. Arif Rahman – The Production Systems Synchronous Transport 19 All work units are moved simultaneously to their respective next workstations with quick, discontinuous motion
  • 20. Arif Rahman – The Production Systems Asynchronous Transport 20 Work units move independently, not simultaneously. A work unit departs a given station when the worker releases it. Small queues of parts can form at each station.
  • 21. Arif Rahman – The Production Systems Continuous transport ¤ Overhead trolley conveyor ¤ Belt conveyor ¤ Roller conveyor ¤ Drag chain conveyor Synchronous transport ¤ Walking beam transport equipment ¤ Rotary indexing mechanisms Asynchronous transport ¤ Power-and-free overhead conveyor ¤ Cart-on-track conveyor ¤ Automated guided vehicle systems ¤ Monorail systems ¤ Chain-driven carousel systems Material Handling Equipment for Mechanized Work Transport 21
  • 22. Arif Rahman – The Production Systems A manual assembly line operates at a certain cycle time to achieve the required production rate of the line – On average, each worker must complete his/her assigned task within this cycle time Pacing provides a discipline for the assembly line workers that more or less guarantees a certain production rate for the line Several levels of pacing: 1. Rigid pacing 2. Pacing with margin 3. No pacing Line Pacing 22
  • 23. Arif Rahman – The Production Systems Each worker is allowed only a certain fixed time each cycle to complete the assigned task ¤ Allowed time is set equal to the cycle time less repositioning time ¤ Synchronous work transport system provides rigid pacing Undesirable aspects of rigid pacing: ¤ Incompatible with inherent human variability ¤ Emotionally and physically stressful to worker ¤ Incomplete work units if task not completed Rigid Pacing 23
  • 24. Arif Rahman – The Production Systems Worker is allowed to complete the task within a specified time range, the upper limit of which is greater than the cycle time On average, the worker’s average task time must balance with the cycle time of the line How to achieve pacing with margin: ¤ Allow queues of work units between stations ¤ Provide for tolerance time to be longer than cycle time ¤ Allow worker to move beyond station boundaries Pacing with Margin 24
  • 25. Arif Rahman – The Production Systems No time limit within which task must be completed Each assembly worker works at his/her own pace No pacing can occur when: ¤ Manual transport of work units is used ¤ Work units can be removed from the conveyor to perform the task ¤ An asynchronous conveyor is used No Pacing 25
  • 26. Arif Rahman – The Production Systems Single model assembly line (SMAL) ¤ Every work unit is the same Batch model assembly line (BMAL) ¤ Hard product variety ¤ Products must be made in batches Mixed model assembly line (MMAL) ¤ Soft product variety ¤ Models can be assembled simultaneously without batching Coping with Product Variety 26
  • 27. Arif Rahman – The Production Systems Advantages of mixed model lines over batch models lines: ¤ No lost production time between models ¤ High inventories typical of batch production are avoided ¤ Production rates of different models can be adjusted as product demand changes MMAL vs. BMAL 27
  • 28. Arif Rahman – The Production Systems Difficulties with mixed model line compared to batch model line ¤ Line balancing problem more complex due to differences in work elements among models ¤ Scheduling the sequence of the different models is a problem ¤ Logistics is a problem - getting the right parts to each workstation for the model currently there ¤ Cannot accommodate as wide model variations as BMAL MMAL vs. BMAL 28
  • 29. Arif Rahman – The Production Systems Problems on high production assembly lines ¤ Complain about the monotony of the repetitive tasks that must be performed and the unrelenting pace that must be maintained when a moving conveyor is used ¤ Poor quality workmanship ¤ Sabotage of the line equipment Alternative assembly systems ¤ Single station manual assembly cells ¤ Assembly cells based on worker teams • Single station manual assembly cell with multiple workers • Moving the product through multiple workstations, but having the same worker team follow the product ¤ Automated assembly systems Alternative Assembly Systems 29
  • 30. Arif Rahman – The Production Systems The key to successful DFA ¤ Design the product with as few parts as possible ¤ Design the remaining parts so they are easy to assemble General principles of DFA ¤ Use the fewest number of parts possible to reduce the amount of assembly required ¤ Reduce the number of threaded fasteners required ¤ Standardize fasteners ¤ Reduce parts orientation difficulties ¤ Avoid parts that tangle Design for Assembly (DFA) 30
  • 31. Arif Rahman – The Production Systems The formulas and the algorithms in this section are developed for single model lines, but they can be extended to batch and mixed models. The assembly line must be designed to achieve a production rate sufficient to satisfy the demand. Demand rate → production rate→ cycle time Analysis of Single Model Lines 31
  • 32. Arif Rahman – The Production Systems Annual demand Da must be reduced to an hourly production rate Rp where Da = annual demand (pieces) Rp = hourly production rate (pieces/hour) Sw = number of shifts/week (shift/week) Hsh = number of hours/shift (hour/shift) The constant 52 converts years to weeks, and vise versa Analysis of Single Model Lines 32 shw a p HS D R 52 =
  • 33. Arif Rahman – The Production Systems Now our aim is to convert production rate, Rp, to cycle time, Tc. One should take into account that some production time will be lost due to ¤ equipment failures ¤ power outages, ¤ material unavailability, ¤ quality problems, ¤ labor problems. Determining Cycle Time 33
  • 34. Arif Rahman – The Production Systems Line efficiency (uptime proportion): only a certain proportion of the shift time will be available. Production rate, Rp, is converted to a cycle time, Tc, accounting for line efficiency, E. Determining Cycle Time 34 p c R E T 60 =
  • 35. Arif Rahman – The Production Systems Rc = cycle rate for the line (cycles/hour) Tc = cycle time of the line (minutes/cycle) Rp = required production rate (pieces/hour) E = line efficiency Rc must be greater than Rp because E is less than 100% Determining Cycle Time 35 c p R R E =
  • 36. Arif Rahman – The Production Systems EAT T ET WL TRWL AT WL w c wc wcp 60 60 = = = = Number of Stations Required 36
  • 37. Arif Rahman – The Production Systems Work content time (Twc): The total time of all work elements that must be performed to produce one unit of the work unit. The theoretical minimum number of stations that will be required to on the line to produce one unit of the work unit, w*: where Twc = work content time (min) Tc = cycle time (min/station) If we assume one worker per station then this gives the minimum number of workers Number of Stations Required 37 c wc T T w ≥= intmin*
  • 38. Arif Rahman – The Production Systems Repositioning losses ¤ Some time will be lost at each station every cycle for repositioning the worker or the work unit; thus, the workers will not have the entire Tc each cycle Line balancing problem (imperfect balancing): ¤ It is not possible to divide the work content time evenly among workers, and some workers will have an amount of work that is less than Tc Task time variability Quality problems Theoretical Minimum Not Possible 38
  • 39. Arif Rahman – The Production Systems Repositioning losses occur on a production line because some time is required each cycle to reposition the worker, the work unit, or both ¤ On a continous transport line, time is required for the worker to walk from the unit just completed to the the upstream unit entering the station ¤ In conveyor systems, time is required to remove work units from the conveyor and position it at the station for worker to perform his task. Repositioning Losses 39
  • 40. Arif Rahman – The Production Systems Repositioning time, (Tr) = time available each cycle for the worker to position Service time, (Ts) = time available each cycle for the worker to work on the product Service time, Ts = Max{Tsi} ≤ Tc – Tr where Tsi= service time for station i, i=1,2,..,n Repositioning efficiency Repositioning Losses 40 c rc c s r T TT T T E − ==
  • 41. Arif Rahman – The Production Systems Cycle Time (Tc) on an Assembly Line 41 Components of cycle time at several stations on a manual assembly line. At the bottleneck station, there is no idle time. Tsi = service time, Tr = repositioning time
  • 42. Arif Rahman – The Production Systems Given: ¤ Total work content consists of many distinct work elements ¤ The sequence in which the elements can be performed is restricted ¤ The line must operate at a specified cycle time Problem: ¤ To assign the individual work elements to workstations so that all workers have an equal amount of work to perform Line Balancing Problem 42
  • 43. Arif Rahman – The Production Systems Element times are constant values ¤ But in fact they are variable Work element times are additive ¤ The time to perform two/more work elements in sequence is the sum of the individual element times ¤ Additivity assumption can be violated (due to motion economies) Assumptions About Work Element Times 43
  • 44. Arif Rahman – The Production Systems Total work content time Twc ¤ where Tek = work element time for element k Work elements are assigned to station i that add up to the service time for that station The station service times must add up to the total work content time Work Element Times 44 ∑= = en k ekwc TT 1 ∑∈ = ik eksi TT ∑= = n i siwc TT 1
  • 45. Arif Rahman – The Production Systems Different work elements require different times. When elements are grouped into logical tasks and assigned to workers, the station service times, Tsi, are likely not to be equal. Simply because of the variation among work element times, some workers will be assigned more work. Thus, variations among work elements make it difficult to obtain equal service times for all stations. Constraints of Line Balancing Problem 45
  • 46. Arif Rahman – The Production Systems Precedence Constraints 46 Restrictions on the order in which work elements can be performed Precedence Diagram
  • 47. Arif Rahman – The Production Systems Largest Candidate Rule ¤ Assignment of work elements to stations based on amount of time each work element requires Kilbridge and Wester Method ¤ Assignment of work elements to stations based on position in the precedence diagram ¤ Elements at front of diagram are assigned first Ranked Positional Weights ¤ Combines the two preceding approaches by calculating an RPW for each element COMSOAL Random Sequence Generation ¤ Sequences are generated by selecting at random from the set of available tasks and placing that task next in sequence Line Balancing Algorithms 47
  • 48. Arif Rahman – The Production Systems Example: 48 Grommet : sealant like ring No Work Element Description Tek (min) Predecessors Successors 1 Place frame in workholder and clamp 0.2 - 3,4 2 Assemble plug, grommet to power cord 0.4 - 4,5 3 Assemble brackets to frame 0.7 1 6,7,8 4 Wire power cord to motor 0.1 1,2 8 5 Wire power cord to switch 0.3 2 10 6 Assemble mechanism plate to bracket 0.11 3 9 7 Assemble blade to bracket 0.32 3 9 8 Assemble motor to brackets 0.6 3,4 9,10 9 Align blade and attach to motor 0.27 6,7,8 11 10 Assemble switch to motor bracket 0.38 5,8 11 11 Attach cover,lnspect, and test 0.5 9,10 12 12 Place in tote pan for packing 0.12 11 -
  • 49. Arif Rahman – The Production Systems Example: 49 Grommet : sealant like ring
  • 50. Arif Rahman – The Production Systems Given: The previous precedence diagram and the standard times. Annual demand=100,000 units/year. The line will operate 50 wk/yr, 5 shifts/wk, 7.5 hr/shift. Uptime efficiency=96%. Repositioning time lost=0.08 min. Determine a) total work content time, b) required hourly production rate to achieve the annual demand, c) cycle time, d) theoretical minimum number of workers required on the line, e) service time to which the line must be balanced. Example: A problem for line balancing 50
  • 51. Arif Rahman – The Production Systems The total work content time is the sum of the work element times given in the table Twc = 4.0 min The hourly production rate Example: Solution 51 units/hr33.53 )5.7)(5(50 000,100 ==pR ∑= = en k ekwc TT 1 shw a p HS D R 50 =
  • 52. Arif Rahman – The Production Systems The corresponding cycle time with an uptime efficiency of 96% The minimum number of workers: w* = (Min Int) ≥ 4.0 /1.08=3.7 = 4 workers The available service time Ts = 1.08 - 0.08 = 1.00 min Example: Solution 52 Production System 29/10/17 min08.1 33.53 )96.0(60 ==cT p c R E T 60 = c wc T T w =* rcs TTT −=
  • 53. Arif Rahman – The Production Systems It is almost imposible to obtain a perfect line balance Line balance efficiency, Eb: Perfect line: Eb = 1 Balance delay, d: Perfect line: d = 0 Note that Eb + d = 1 (they are complement of each other) Measures of Balance Efficiency 53 s wc b wT T E = s wcs wT TwT d − =
  • 54. Arif Rahman – The Production Systems Factors that reduce the productivity of a manual line ¤ Line efficiency (Availability), E, ¤ Repositioning efficiency (repositioning), Er, ¤ Balance efficiency (balancing), Eb, Overall Labor efficiency on the assembly line = Overall Efficiency 54 c rc c s r T TT T T E − == s wc b wT T E = p c R E T 60 = rb EEE ⋅⋅=EfficiencyLabor
  • 55. Arif Rahman – The Production Systems The actual number of workers on the assembly line is given by: where : w = number of workers required Rp = hourly production rate (pieces/hour) Twc = work content time per product, (min/piece) Worker Requirements 55 c rc c s r T TT T T E − == s wc b wT T E = sb wc cbr wc br wcp TE T TEE T EEE TR w ==≥= 60 intmin p c R E T 60 =
  • 56. Arif Rahman – The Production Systems Number of stations: Total length of the assembly line where L = length of the assembly line (m) Lsi= length of station i (m) Continously moving conveyors - Workstation considerations 56 ∑= = n i isLL 1 M w n =
  • 57. Arif Rahman – The Production Systems Constant speed conveyor: (if the base parts remain fixed during their assembly) ¤ Feed rate where : fp=feed rate on the line, (products/min) ¤ Center-to-center spacing between base parts where : sp = center-to-center spacing between base parts (m/part) vc = velocity of the conveyor (m/min) Continously moving conveyors - Workstation considerations 57 c p T f 1 = cc p c p Tv f v s ==
  • 58. Arif Rahman – The Production Systems Defined as the time a work unit spends inside the boundaries of the workstation Provides a way to allow for product-to-product variations in task times at a station where Tt = tolerance time (min) Ls = station length (m) vc = conveyor speed, (m/min) Continously moving conveyors - Tolerance Time 58 c s t v L T =
  • 59. Arif Rahman – The Production Systems The time a work unit spends on the assembly line. where ET = total elapsed time, (min) n = number of workstations Tt = tolerance time, (min) L = length of the assembly line, (m) vc = conveyor speed, (m/min) Continously moving conveyors -Total Elapsed Time 5929/10/17 t c nT v L ET ==
  • 60. Arif Rahman – The Production Systems To distribute the total work content on the assembly line as evenly as possible among the workers Minimize (wTs – Twc) or Minimize Subject to: (1) (2) all precedence requirements are obeyed Line Balancing Objective 60 ( )∑= − w i sis TT 1 s ik ek TT ≤∑∈
  • 61. Arif Rahman – The Production Systems 0. List all work elements in descending order based on their Tek values; then, proceed three-step procedure: 1. Start at the top of the list and selecting the first element that satisfies precedence requirements and does not cause the total sum of Tek to exceed the allowable Ts value. ¤ When an element is assigned, start back at the top of the list and repeat selection process 1. When no more elements can be assigned to the current station, proceed to next station 2. Repeat steps 1 and 2 until all elements have been assigned to as many stations as needed Largest Candidate Rule 61
  • 62. Arif Rahman – The Production Systems Example: Largest Candidate Rule 62 Grommet : sealant like ring
  • 63. Arif Rahman – The Production Systems Example: Largest Candidate Rule 63 Work Elements Arranged According to Tek Value for the Largest Candidate Rule. (Ts = 1 min) No Tek (min) Predecessors Successors 3 0.7 1 6,7,8 8 0.6 3,4 9,1 11 0.5 9,1 12 2 0.4 - 4,5 10 0.38 5,8 11 7 0.32 3 9 5 0.3 2 10 9 0.27 6,7,8 11 1 0.2 - 3,4 12 0.12 11 - 6 0.11 3 9 4 0.1 1,2 8
  • 64. Arif Rahman – The Production Systems Example: Largest Candidate Rule Iteration 1: 3, 8, and 11 require preceding elements Element 2 is selected. Alternatives are 5 and 1. It assigns element 5. ΣTek = 0.4 + 0.3 = 0.7 min Alternative is 1 It assigns element 1 ΣTek = 0.7 + 0.2 = 0.9 min Alternatives are 3 and 4 3 can not be assigned, since ΣTek > Ts It assigns element 4 ΣTek = 0.9 + 0.1 = 1.0 min 64 No Tek (min) Predecessors Successors 3 0.7 1 6,7,8 8 0.6 3,4 9,1 11 0.5 9,1 12 2 0.4 - 4,5 10 0.38 5,8 11 7 0.32 3 9 5 0.3 2 10 9 0.27 6,7,8 11 1 0.2 - 3,4 12 0.12 11 - 6 0.11 3 9 4 0.1 1,2 8
  • 65. Arif Rahman – The Production Systems Example: Largest Candidate Rule Iteration 2: Element 3 is selected. Alternatives are 8, 7 and 6. 8 and 7 can not be assigned, since ΣTek > Ts It assigns element 6. ΣTek = 0.7 + 0.11 = 0.81 min Alternatives are 8 and 7. 8 and 7 can not be assigned, since ΣTek > Ts 65 No Tek (min) Predecessors Successors 3 0.7 1 6,7,8 8 0.6 3,4 9,1 11 0.5 9,1 12 2 0.4 - 4,5 10 0.38 5,8 11 7 0.32 3 9 5 0.3 2 10 9 0.27 6,7,8 11 1 0.2 - 3,4 12 0.12 11 - 6 0.11 3 9 4 0.1 1,2 8
  • 66. Arif Rahman – The Production Systems Example: Largest Candidate Rule Iteration 3: Element 8 is selected. Alternatives are 10 and 7. It assigns element 10. ΣTek = 0.6 + 0.38 = 0.98 min Alternative is 7. 7 can not be assigned, since ΣTek > Ts 66 No Tek (min) Predecessors Successors 3 0.7 1 6,7,8 8 0.6 3,4 9,1 11 0.5 9,1 12 2 0.4 - 4,5 10 0.38 5,8 11 7 0.32 3 9 5 0.3 2 10 9 0.27 6,7,8 11 1 0.2 - 3,4 12 0.12 11 - 6 0.11 3 9 4 0.1 1,2 8
  • 67. Arif Rahman – The Production Systems Example: Largest Candidate Rule Iteration 4: 11 requires preceding elements Element 7 is selected. Alternative is 9. It assigns element 9. ΣTek = 0.32 + 0.27 = 0.59 min Alternative is 11. 11 can not be assigned, since ΣTek > Ts 67 No Tek (min) Predecessors Successors 3 0.7 1 6,7,8 8 0.6 3,4 9,1 11 0.5 9,1 12 2 0.4 - 4,5 10 0.38 5,8 11 7 0.32 3 9 5 0.3 2 10 9 0.27 6,7,8 11 1 0.2 - 3,4 12 0.12 11 - 6 0.11 3 9 4 0.1 1,2 8
  • 68. Arif Rahman – The Production Systems Example: Largest Candidate Rule Iteration 5: Element 11 is selected. Alternative is 12. It assigns element 12. ΣTek = 0.5 + 0.12 = 0.62 min All elements have been assigned. 68 No Tek (min) Predecessors Successors 3 0.7 1 6,7,8 8 0.6 3,4 9,1 11 0.5 9,1 12 2 0.4 - 4,5 10 0.38 5,8 11 7 0.32 3 9 5 0.3 2 10 9 0.27 6,7,8 11 1 0.2 - 3,4 12 0.12 11 - 6 0.11 3 9 4 0.1 1,2 8
  • 69. Arif Rahman – The Production Systems Example: Largest Candidate Rule Final Solution: Workstation 1 : 2-5-1-4 = 1.0 min Workstation 2 : 3-6 = 0.81 min Workstation 3 : 8-10 = 0.98 min Workstation 4 : 7-9 = 0.59 min Workstation 5 : 11-12 = 0.62 min 69 No Tek (min) Predecessors Successors 3 0.7 1 6,7,8 8 0.6 3,4 9,1 11 0.5 9,1 12 2 0.4 - 4,5 10 0.38 5,8 11 7 0.32 3 9 5 0.3 2 10 9 0.27 6,7,8 11 1 0.2 - 3,4 12 0.12 11 - 6 0.11 3 9 4 0.1 1,2 8
  • 70. Arif Rahman – The Production Systems Example: Solution 70 Work Elements Arrangement . Ts = 1 min. Workstatio n No Tek (min) ΣTek 1 1 0.2 1.0 2 0.4 4 0.1 5 0.3 2 3 0.7 0.81 6 0.11 3 8 0.6 0.98 10 0.38 4 7 0.32 0.59 9 0.27 5 11 0.5 0.62 12 0.12
  • 71. Arif Rahman – The Production Systems Example: Solution 71 Work Elements Arrangement . Ts = 1 min.
  • 72. Arif Rahman – The Production Systems Solution for Largest Candidate Rule 72 Physical layout of workstations and assignment of elements to stations using the largest candidate rule
  • 73. Arif Rahman – The Production Systems Selects work elements for assignment to stations according to their position in the precedence diagram Work elements in the precedence diagram are arranged into columns The elements can be organized into a list according to their columns, with the elements in the first column listed first If a given element can be located in more than one column, then list all of the columns for that element Proceed with same steps 1, 2, and 3 as in the largest candidate rule Kilbridge and Wester Method 73
  • 74. Arif Rahman – The Production Systems Example: Kilbridge and Wester Method 74
  • 75. Arif Rahman – The Production Systems Example: Kilbridge and Wester Method 75 Work Elements Arranged According to Tek Value for the Kilbridge and Wester Method. (Ts = 1 min) No Tek (min) Region Predecessors Successors 2 0.4 I - 4,5 1 0.2 I - 3,4 3 0.7 II 1 6,7,8 4 0.1 II 1,2 8 5 0.3 II / III 2 10 8 0.6 III 3,4 9,1 7 0.32 III 3 9 6 0.11 III 3 9 10 0.38 III / IV 5,8 11 9 0.27 IV 6,7,8 11 11 0.5 V 9,1 12 12 0.12 VI 11 -
  • 76. Arif Rahman – The Production Systems Example: Kilbridge and Wester Method Iteration 1: Element 2 is selected. Alternatives are 1 and 5. It assigns element 1. ΣTek = 0.4 + 0.2 = 0.6 min Alternatives are 3, 4 and 5 3 can not be assigned, since ΣTek > Ts It assigns element 4 ΣTek = 0.6 + 0.1 = 0.7 min Alternatives are 3 and 5 3 can not be assigned, since ΣTek > Ts It assigns element 5 ΣTek = 0.7 + 0.3 = 1.0 min 76 No Tek (min) Region Predecessors Successors 2 0.4 I - 4,5 1 0.2 I - 3,4 3 0.7 II 1 6,7,8 4 0.1 II 1,2 8 5 0.3 II / III 2 10 8 0.6 III 3,4 9,1 7 0.32 III 3 9 6 0.11 III 3 9 10 0.38 III / IV 5,8 11 9 0.27 IV 6,7,8 11 11 0.5 V 9,1 12 12 0.12 VI 11 -
  • 77. Arif Rahman – The Production Systems Example: Kilbridge and Wester Method Iteration 2: Element 3 is selected. Alternatives are 8, 7 and 6. 8 and 7 can not be assigned, since ΣTek > Ts It assigns element 6. ΣTek = 0.7 + 0.11 = 0.81 min Alternatives are 8 and 7 8 and 7 can not be assigned, since ΣTek > Ts 77 No Tek (min) Region Predecessors Successors 2 0.4 I - 4,5 1 0.2 I - 3,4 3 0.7 II 1 6,7,8 4 0.1 II 1,2 8 5 0.3 II / III 2 10 8 0.6 III 3,4 9,1 7 0.32 III 3 9 6 0.11 III 3 9 10 0.38 III / IV 5,8 11 9 0.27 IV 6,7,8 11 11 0.5 V 9,1 12 12 0.12 VI 11 -
  • 78. Arif Rahman – The Production Systems Example: Kilbridge and Wester Method Iteration 3: Element 8 is selected. Alternatives are 7 and 10. It assigns element 7. ΣTek = 0.6 + 0.32 = 0.92 min Alternatives are 10 and 9 10 and 9 can not be assigned, since ΣTek > Ts 78 No Tek (min) Region Predecessors Successors 2 0.4 I - 4,5 1 0.2 I - 3,4 3 0.7 II 1 6,7,8 4 0.1 II 1,2 8 5 0.3 II / III 2 10 8 0.6 III 3,4 9,1 7 0.32 III 3 9 6 0.11 III 3 9 10 0.38 III / IV 5,8 11 9 0.27 IV 6,7,8 11 11 0.5 V 9,1 12 12 0.12 VI 11 -
  • 79. Arif Rahman – The Production Systems Example: Kilbridge and Wester Method Iteration 4: Element 10 is selected. Alternatives is 9. It assigns element 9. ΣTek = 0.38 + 0.27 = 0.65 min Alternative is 11 11 can not be assigned, since ΣTek > Ts 79 No Tek (min) Region Predecessors Successors 2 0.4 I - 4,5 1 0.2 I - 3,4 3 0.7 II 1 6,7,8 4 0.1 II 1,2 8 5 0.3 II / III 2 10 8 0.6 III 3,4 9,1 7 0.32 III 3 9 6 0.11 III 3 9 10 0.38 III / IV 5,8 11 9 0.27 IV 6,7,8 11 11 0.5 V 9,1 12 12 0.12 VI 11 -
  • 80. Arif Rahman – The Production Systems Example: Kilbridge and Wester Method Iteration 5: Element 11 is selected. Alternatives is 12. It assigns element 12. ΣTek = 0.5 + 0.12 = 0.62 min All elements have been assigned. 80 No Tek (min) Region Predecessors Successors 2 0.4 I - 4,5 1 0.2 I - 3,4 3 0.7 II 1 6,7,8 4 0.1 II 1,2 8 5 0.3 II / III 2 10 8 0.6 III 3,4 9,1 7 0.32 III 3 9 6 0.11 III 3 9 10 0.38 III / IV 5,8 11 9 0.27 IV 6,7,8 11 11 0.5 V 9,1 12 12 0.12 VI 11 -
  • 81. Arif Rahman – The Production Systems Example: Kilbridge and Wester Method Final Solution: Workstation 1 : 2-1-4-5 = 1.0 min Workstation 2 : 3-6 = 0.81 min Workstation 3 : 8-7 = 0.92 min Workstation 4 : 10-9 = 0.65 min Workstation 5 : 11-12 = 0.62 min 81 No Tek (min) Region Predecessors Successors 2 0.4 I - 4,5 1 0.2 I - 3,4 3 0.7 II 1 6,7,8 4 0.1 II 1,2 8 5 0.3 II / III 2 10 8 0.6 III 3,4 9,1 7 0.32 III 3 9 6 0.11 III 3 9 10 0.38 III / IV 5,8 11 9 0.27 IV 6,7,8 11 11 0.5 V 9,1 12 12 0.12 VI 11 -
  • 82. Arif Rahman – The Production Systems Example: Solution 82 Work Elements Arrangement . Ts = 1 min. Workstatio n No Tek (min) ΣTek 1 1 0.2 1.0 2 0.4 4 0.1 5 0.3 2 3 0.7 0.81 6 0.11 3 7 0.32 0.92 8 0.6 4 9 0.27 0.65 10 0.38 5 11 0.5 0.62 12 0.12
  • 83. Arif Rahman – The Production Systems Example: Solution 83 Work Elements Arrangement . Ts = 1 min.
  • 84. Arif Rahman – The Production Systems Solution for Kilbridge and Wester Method 84 Physical layout of workstations and assignment of elements to stations using the Kilbridge and Wester Method
  • 85. Arif Rahman – The Production Systems A ranked position weight (RPW) is calculated for each work element RPW for element k is calculated by summing the Tek values for all of the elements that follow element k in the diagram plus Tek itself Work elements are then organized into a list according to their RPW values, starting with the element that has the highest RPW value Proceed with same steps 1, 2, and 3 as in the largest candidate rule Ranked Positional Weights Method 85
  • 86. Arif Rahman – The Production Systems Example: Ranked Positional Weights Method 86 Grommet : sealant like ring
  • 87. Arif Rahman – The Production Systems Example: Ranked Positional Weights Method 87 Work Elements Arranged According to Tek Value for the Ranked Positional Weights Method. (Ts = 1 min) No Tek (min) RPW Predecessors Successors Elements of RPW 1 0.2 3.30 - 3,4 1, 3, 4, 6, 7, 8, 9, 10, 11, 12 3 0.7 3.00 1 6,7,8 3, 6, 7, 8, 9, 10, 11, 12 2 0.4 2.67 - 4,5 2, 4, 5, 8, 9, 10, 11, 12 4 0.1 1.97 1,2 8 4, 8, 9, 10, 11, 12 8 0.6 1.87 3,4 9,1 8, 9, 10, 11, 12 5 0.3 1.30 2 10 5, 10, 11, 12 7 0.32 1.21 3 9 7, 9, 11, 12 6 0.11 1.00 3 9 6, 9, 11, 12 10 0.38 1.00 5,8 11 10, 11, 12 9 0.27 0.89 6,7,8 11 9, 11, 12 11 0.5 0.62 9,1 12 11, 12 12 0.12 0.12 11 - 12
  • 88. Arif Rahman – The Production Systems Example: Ranked Positional Weights Method Iteration 1: Element 1 is selected. Alternatives are 3 and 2. It assigns element 3. ΣTek = 0.2 + 0.7 = 0.9 min Alternatives are 2, 7 and 6 2, 7 and 6 can not be assigned, since ΣTek > Ts 88 No Tek (min) RPW Predecessors Successors 1 0.2 3.30 - 3,4 3 0.7 3.00 1 6,7,8 2 0.4 2.67 - 4,5 4 0.1 1.97 1,2 8 8 0.6 1.87 3,4 9,1 5 0.3 1.30 2 10 7 0.32 1.21 3 9 6 0.11 1.00 3 9 10 0.38 1.00 5,8 11 9 0.27 0.89 6,7,8 11 11 0.5 0.62 9,1 12 12 0.12 0.12 11 -
  • 89. Arif Rahman – The Production Systems Example: Ranked Positional Weights Method Iteration 2: Element 2 is selected. Alternatives are 4, 5, 7 and 6. It assigns element 4. ΣTek = 0.4 + 0.1 = 0.5 min Alternatives are 8, 5, 7 and 6 8 can not be assigned, since ΣTek > Ts It assigns element 5 ΣTek = 0.5 + 0.3 = 0.8 min Alternatives are 8, 7 and 6 8 and 7 can not be assigned, since ΣTek > Ts It assigns element 6 ΣTek = 0.8 + 0.11 = 0.91 min 89 No Tek (min) RPW Predecessors Successors 1 0.2 3.30 - 3,4 3 0.7 3.00 1 6,7,8 2 0.4 2.67 - 4,5 4 0.1 1.97 1,2 8 8 0.6 1.87 3,4 9,1 5 0.3 1.30 2 10 7 0.32 1.21 3 9 6 0.11 1.00 3 9 10 0.38 1.00 5,8 11 9 0.27 0.89 6,7,8 11 11 0.5 0.62 9,1 12 12 0.12 0.12 11 -
  • 90. Arif Rahman – The Production Systems Example: Ranked Positional Weights Method Iteration 3: Element 8 is selected. Alternatives are 7 and 10. It assigns element 7. ΣTek = 0.6 + 0.32 = 0.92 min Alternatives are 10 and 9 10 and 9 can not be assigned, since ΣTek > Ts 90 No Tek (min) RPW Predecessors Successors 1 0.2 3.30 - 3,4 3 0.7 3.00 1 6,7,8 2 0.4 2.67 - 4,5 4 0.1 1.97 1,2 8 8 0.6 1.87 3,4 9,1 5 0.3 1.30 2 10 7 0.32 1.21 3 9 6 0.11 1.00 3 9 10 0.38 1.00 5,8 11 9 0.27 0.89 6,7,8 11 11 0.5 0.62 9,1 12 12 0.12 0.12 11 -
  • 91. Arif Rahman – The Production Systems Example: Ranked Positional Weights Method Iteration 4: Element 10 is selected. Alternative is 9. It assigns element 9. ΣTek = 0.38 + 0.27 = 0.65 min Alternative is 11 11 can not be assigned, since ΣTek > Ts 91 No Tek (min) RPW Predecessors Successors 1 0.2 3.30 - 3,4 3 0.7 3.00 1 6,7,8 2 0.4 2.67 - 4,5 4 0.1 1.97 1,2 8 8 0.6 1.87 3,4 9,1 5 0.3 1.30 2 10 7 0.32 1.21 3 9 6 0.11 1.00 3 9 10 0.38 1.00 5,8 11 9 0.27 0.89 6,7,8 11 11 0.5 0.62 9,1 12 12 0.12 0.12 11 -
  • 92. Arif Rahman – The Production Systems Example: Ranked Positional Weights Method Iteration 5: Element 11 is selected. Alternative is 12. It assigns element 12. ΣTek = 0.5 + 0.12 = 0.62 min All elements have been assigned. 92 No Tek (min) RPW Predecessors Successors 1 0.2 3.30 - 3,4 3 0.7 3.00 1 6,7,8 2 0.4 2.67 - 4,5 4 0.1 1.97 1,2 8 8 0.6 1.87 3,4 9,1 5 0.3 1.30 2 10 7 0.32 1.21 3 9 6 0.11 1.00 3 9 10 0.38 1.00 5,8 11 9 0.27 0.89 6,7,8 11 11 0.5 0.62 9,1 12 12 0.12 0.12 11 -
  • 93. Arif Rahman – The Production Systems Example: Ranked Positional Weights Method Final Solution: Workstation 1 : 1-3 = 0.9 min Workstation 2 : 2-4-5-6 = 0.91 min Workstation 3 : 8-7 = 0.92 min Workstation 4 : 10-9 = 0.65 min Workstation 5 : 11-12 = 0.62 min 93 No Tek (min) RPW Predecessors Successors 1 0.2 3.30 - 3,4 3 0.7 3.00 1 6,7,8 2 0.4 2.67 - 4,5 4 0.1 1.97 1,2 8 8 0.6 1.87 3,4 9,1 5 0.3 1.30 2 10 7 0.32 1.21 3 9 6 0.11 1.00 3 9 10 0.38 1.00 5,8 11 9 0.27 0.89 6,7,8 11 11 0.5 0.62 9,1 12 12 0.12 0.12 11 -
  • 94. Arif Rahman – The Production Systems Example: Solution 94 Work Elements Arrangement . Ts = 1 min. Workstatio n No Tek (min) ΣTek 1 1 0.2 0.9 3 0.7 2 2 0.4 0.91 4 0.1 5 0.3 6 0.11 3 7 0.32 0.92 8 0.6 4 9 0.27 0.65 10 0.38 5 11 0.5 0.62 12 0.12
  • 95. Arif Rahman – The Production Systems Example: Solution 95 Work Elements Arrangement . Ts = 1 min.
  • 96. Arif Rahman – The Production Systems Solution for Ranked Positional Weights Method 96 Physical layout of workstations and assignment of elements to stations using the Ranked Positional Weights Method
  • 97. Arif Rahman – The Production Systems Largest Candidate Rule Kilbridge and Wester Method Balance efficiency 97 ( ) 8.0 15 4 ==bE ( ) 8.0 15 4 ==bE
  • 98. Arif Rahman – The Production Systems Ranked Positional Weights Method Balance efficiency 98 ( ) ( ) 6.5796.060 60 1 6060 108.092.0 87.0 92.05 4 === === =+=+= == ERR T R TTT E cp c c rsc b
  • 99. Arif Rahman – The Production Systems A manual production line capable of producing a variety of different product models simultaneously and continuously (not in batches) Problems in designing and operating a MMAL: ¤ Determining number of workers on the line ¤ Line balancing - same basic problem as in SMAL except differences in work elements among models must be considered ¤ Model launching - determining the sequence in which different models will be launched onto the line Mixed Model Assembly Lines 99
  • 100. Arif Rahman – The Production Systems Line efficiency ¤ Management is responsible to maintain line operation at efficiencies (proportion uptime) close to 100% • Implement preventive maintenance • Well-trained emergency repair crews to quickly fix breakdowns when they occur • Avoid shortages of incoming parts to avoid forced downtime • Insist on highest quality components from suppliers to avoid downtime due to poor quality parts Other Considerations in Line Design 100
  • 101. Arif Rahman – The Production Systems Methods analysis ¤ To analyze methods at bottleneck or other troublesome workstations Subdividing work elements ¤ It may be technically possible to subdivide some work elements to achieve a better line balance Sharing work elements between two adjacent stations ¤ Alternative cycles between two workers Other Considerations - continued 101
  • 102. Arif Rahman – The Production Systems Utility workers ¤ To relieve congestion at stations that are temporarily overloaded Changing workhead speeds at mechanized stations ¤ Increase power feed or speed to achieve a better line balance Preassembly of components ¤ Prepare certain subassemblies off-line to reduce work content time on the final assembly line Other Considerations - continued 102
  • 103. Arif Rahman – The Production Systems Storage buffers between stations ¤ To permit continued operation of certain sections of the line when other sections break down ¤ To smooth production between stations with large task time variations Parallel stations ¤ To reduce time at bottleneck stations that have unusually long task times Worker (Labor) Shifting with crosstraining ¤ Temporary (or periodic) relocation to expedite or to reduce subassembly stocks Other Considerations - continued 103
  • 104. Arif Rahman – The Production Systems Zoning constraints - limitations on the grouping of work elements and/or their allocation to workstations ¤ Positive zoning constraints • Work elements should be grouped at same station • Example: spray painting elements ¤ Negative zoning constraints • Elements that might interfere with each other • Separate delicate adjustments from loud noises Other Considerations - continued 104
  • 105. Arif Rahman – The Production Systems Position constraints ¤ Encountered in assembly of large products such as trucks and cars, making it difficult for one worker to perform tasks on both sides of the product ¤ To address, assembly workers are positioned on both sides of the line Other Considerations - continued 105
  • 106. Arif Rahman – The Production Systems 106 It’s end of slides…It’s end of slides… …… Any question ?Any question ?

Editor's Notes

  1. Starving: the next unit not yet arrived Blocking: cannot pass unit to the downstream
  2. Continuously moving conveyor: operates at constant velocity Work units are fixed to the conveyor The product is large and heavy Worker moves along with the product Work units are removable from the conveyor Work units are small and light Workers are more flexible compared to synchronous lines, less flexible than asynchronous lines Synchronous transport (intermittent transport – stop-and-go line): all work units are moved simultaneously between stations. Problem: Task must be completed within a certain time limit. Otherwise the line produces incomplete units; Excessive stress on the assembly worker. Not common for manual lines (variability), but often ideal for automated production lines Asynchronous transport : a work unit leaves a given station when the assigned task is completed. Work units move independently, rather than synchronously (most flexible one). Variations in worker task times Small queues in front of each station.
  3. A single workstation in which all of the assembly work is accomplished on the product or on some major subassembly Common for complex products produced in small quantities, sometimes one-of-a-kind Custom-engineered products Prototypes Industrial equipment (e.g., machine tools) Worker team assembly Advantages: Greater worker satisfaction Better product quality Increased capability to accommodate model variations Greater ability to cope with problems that require more time rather than stopping the entire production line Disadvantages: -not capable of the high production rates characteristic of a conventional assembly lines
  4. Mechanical assembly Joining process Both manual and automated operations  simplest and lowest cost
  5. Computer method of sequencing operations for assembly lines