SlideShare a Scribd company logo
1 of 38
AEM-6235 Maintenance
and Safety Management
Dr. Nafis Ahmad
Professor
Department of IPE, BUET
Email:nafis@ipe.buet.ac.bd
Topics
ā–· Introduction
ā–· Maintenance Management and Control
ā–· Preventive Maintenance
ā–· Corrective Maintenance
ā–· Reliability Centered Maintenance
ā–· Maintainability
3
5.
Corrective Maintenance
4
Introduction
5
ā€¢ Although every effort is made to make engineering systems as
reliable as possible through design, preventive maintenance,
and so on, from time to time they do fail. Consequently, they are
repaired to their operational state.
ā€¢ Corrective maintenance may be defined as the remedial action
carried out due to failure or deficiencies discovered during
preventive maintenance, to repair an equipment/item to its
operational state.
ā€¢ Corrective maintenance is an unscheduled maintenance action,
basically composed of unpredictable maintenance needs that
cannot be preplanned or programmed on the basis of
occurrence at a particular time.
Corrective maintenance types
6
Corrective maintenance may be classified into five major
categories: These are:
(a) fail-repair,
(b) salvage,
(c) rebuild,
(d) overhaul, and
(e) servicing
Corrective maintenance types
7
a) Fail-repair: The failed item is restored to its operational state.
b) Salvage: This element of corrective maintenance is concerned with
disposal of nonrepairable material and use of salvaged material from
nonrepairable equipment/item in the repair, overhaul, or rebuild
programs.
c) Rebuild: This is concerned with restoring an item to a standard as
close as possible to original state in performance, life expectancy,
and appearance.
d) Overhaul: Restoring an item to its total serviceable state as per
maintenance serviceability standards, using the ā€œinspect and repair
only as appropriateā€ approach.
e) Servicing: Servicing may be needed because of the corrective
maintenance action, for example, engine repair can lead to crankcase
refill, welding on, etc. Another example could be that the replacement
of an air bottle may require system recharging.
Different authors have laid down different sequential steps for
performing corrective maintenance.
ā€¢ Some presents nine steps (as applicable): localize,
isolate, adjust, disassemble, repair, interchange,
reassemble, align, and checkout.
ā€¢ Another author presents seven steps (as applicable):
localization, isolation, disassembly, interchange,
reassemble, alignment, and checkout.
ā€¢ Author of the book mentioned corrective maintenance is
composed of five major sequential steps, as shown in Fig.
These steps are: fault recognition, localization,
diagnosis, repair, and checkout.
Corrective maintenance steps
8
9
Corrective
maintenance
Cycle
10
Five major sequential steps, as shown in the
right Figure.
1. fault recognition,
2. localization,
3. diagnosis,
4. repair, and
5. checkout.
The major corrective maintenance downtime
components are:
a) active repair time,
b) administrative and logistic time,
c) and delay time.
The active repair time is made
up of the following subcomponents:
1. Preparation time
2. Fault location time
3. Spare item obtainment time
4. Fault correction time
5. Adjustment and calibration time
6. Checkout time
CM Time Reduction Strategies at
System Level
11
Some strategies for reducing the system-level corrective maintenance time are as
follows:
1. Efficiency in fault recognition, location, and isolation: in electronic equipment,
fault isolation and location consume the most time within a corrective
maintenance activity. In the case of mechanical items, often the largest
contributor is repair time.
2. Effective interchangeability: Good physical and functional interchangeability is
useful in removing and replacing parts/items, reducing maintenance downtime,
and creating a positive impact on spares and inventory needs.
3. Redundancy: This is concerned with designing in redundant parts that can be
switched in at the moment of need so the equipment/system continues to
operate while the faulty part is being repaired.
4. Effective accessibility: Often a significant amount of time is spent accessing the
failed part.
5. Human factor considerations: Attention paid to human factors during design in
areas such as readability of instructions, size, shape, and weight of
components, selection and placement of dials and indicators, size and
placement of access, gates, and readability, and information processing aids
can help reduce corrective maintenance time significantly.
There are various measures associated with corrective
maintenance.
ā€¢ Mean Corrective Maintenance Time
ā€¢ Median Active Corrective Maintenance Time
ā€¢ Maximum Active Corrective Maintenance Time
Corrective maintenance measures
12
Mean Corrective Maintenance Time:
where
Tmcm = mean corrective maintenance time,
Tcmj = corrective maintenance time of the jth equipment/system element,
Ī»j = failure rate of the jth equipment/system element.
Past experience indicates that probability distributions of
corrective maintenance times follow exponential, normal,
and log normal.
Corrective maintenance measures
13
Mean Corrective Maintenance Time:
where
Tmcm = mean corrective maintenance time,
Tcm j = corrective maintenance time of the jth
equipment/ system element,
Ī»j = failure rate of the jth equipment/system
element.
Past experience indicates that
probability distributions of corrective
maintenance times follow
exponential, normal, and log normal.
Corrective maintenance measures
14
15
Corrective maintenance measures
16
Median Active Corrective Maintenance Time: This normally
provides the best average location of the sample data and is the
50th percentile of all values of repair time. It may be said that
median corrective maintenance time is a measure of the time
within which 50% of all corrective maintenance can be
accomplished. The median of the lognormally distributed
corrective maintenance times is given by:
Where, Tmed = median active corrective maintenance time. Tcm j =
corrective maintenance time of the jth equipment/ system element,
For normally distributed corrective maintenance time, Tmem=Tmed
Corrective maintenance measures
17
Maximum Active Corrective Maintenance Time: This measures the time
needed to accomplish all potential corrective maintenance actions up
to a given percentage, frequently the 90th or 95th percentiles. For
example, in the case of 90th percentile, the maximum corrective
maintenance time is the time within which 90% of all maintenance actions
can be accomplished. For lognormally distributed corrective maintenance
times, the maximum active corrective maintenance time is:
Where
Tcmax = maximum active corrective maintenance time, Ī¤mn = mean of the logarithms of Tcm j,
Ļƒcm = standard deviation of the logarithms of the sample corrective maintenance times,
z = standard deviation value corresponding to the percentile value specified for Tcmax
Corrective maintenance measures
18
Maximum Active Corrective Maintenance Time:
Where
Tcmax = maximum active corrective maintenance time, Ī¤mn = mean of the logarithms of Tcm j,
Ļƒcm = standard deviation of the logarithms of the sample corrective maintenance times,
z = standard deviation value corresponding to the percentile value specified for Tcmax
M = total number of corrective maintenance times.
Corrective maintenance measures
19
Corrective Maintenance Mathematical
Models
21
These models take into consideration the item failure (Ī») and
corrective maintenance rates (ĀµC), and can be used to predict
item/system probability of being in failed state (i.e., undergoing
repair), availability, mean time to failure, and so on.
Model-I: Represents a system that can either be in up
(operating) or down (failed) state.
Model-II: Represents a system that can either be operating
normally or failed in two mutually exclusive failure modes
(i.e., failure modes I and Model-III: Represents a system that
can either be operating normally, operating in degradation
mode, or failed completely
Model-IV: Represents a two identical-unit redundant (parallel)
system. At least one unit must operate normally for system
success.
Corrective Maintenance Mathematical
Models
22
Model-I: This mathematical model represents a system that
can either be in up (operating) or down (failed) state.
Corrective maintenance is performed on the failed system to
put it back into its operating state. Assumptions:
Failure and corrective maintenance rates are constant, the repaired system is
as good as new, system failures are statistically independent.
System transition diagram.
Corrective Maintenance Mathematical
Models
23
Model-I:
i = the ith system state, i = 0 (system operating normally), i = 1
(system failed);
Pi(t) = probability that the system is in state i at time t;
Ī» = system failure rate;
ĀµC = system corrective maintenance rate.
AS=The system availability is given by
Corrective Maintenance Mathematical
Models
24
Model-I: If t is very large, System steady state availability.
Since Ī» = 1/MTTF and ĀµC = 1/Tmcm
Corrective Maintenance Mathematical
Models
25
Example 5-1: Assume the MTTF of a piece of equipment is
3000h and its mean corrective maintenance time is 5h.
Calculate the equipment steady-state availability, if the
equipment failure and corrective maintenance times are
exponentially distributed.
System steady state availability.
or
Here MTTF= 3000h and Tmcm= 5h
System steady state availability = 0.9983,
Find P0 and P1
Corrective Maintenance Mathematical
Models
26
Model-II: Represents a system that can either be operating
normally or failed in two mutually exclusive failure modes (i.e.,
failure modes I and II).
A typical example of this type of system or device is a fluid flow
valve (i.e., open and close failure modes). Corrective maintenance
is performed from either failure mode of the system to put it back
into its operational state.
The following assumptions are associated with this model:
The system can fail in two mutually exclusive failure modes.
The repaired system is as good as new.
All system failures are statistically independent.
Failure and corrective maintenance rates are constant
Corrective Maintenance Mathematical
Models
27
Model-II: System transition diagram
Corrective Maintenance Mathematical
Models
28
Model-II: If time t becomes very large, system steady state
availability:
Example 5.2: An engineering system can fail in two mutually exclusive
failure modes. Failure modes I and II constant failure rates are Ī»1 =
0.002 failures/hour and Ī»2 = 0.005 failures/hour, respectively. The
constant corrective maintenance rates from failure modes I and II are
ĀµC1 = 0.006 repairs/hour and ĀµC2 = 0.009 repairs/hour, respectively.
Calculate the system steady state availability.
Corrective Maintenance Mathematical
Models
29
Model-III: Represents a system that can either be operating
normally, operating in degradation mode, or failed
completely. An example of this type of system could be a power
generator, i.e., producing electricity at full capacity, derated
capacity, or not at all. Corrective maintenance is initiated from
degradation and completely failed modes of the system to repair
failed parts. The model is subject to the following assumptions:
ā€¢ System complete failure, partial failure, and corrective maintenance
rates are constant.
ā€¢ The operating system can either fail fully or partially. The partially
operating system can stop operating altogether.
ā€¢ All system failures are statistically independent.
ā€¢ The repaired system is as good as new
Corrective Maintenance Mathematical
Models
30
MODEL III: System transition diagram.
Corrective Maintenance Mathematical
Models
31
Model-III: The system full/partial steady-state availability
Here, i = the ith system state, i = 0 (system operating normally), i = 1 (system operating in its degradation mode), i = 2 (system failed),
Pi(t) = probability that the system is in state i at time t, for i = 0, 1, 2, Ī»i = system failure rate, i = 1 (from state 0 to state 1), i = 2 (from state
0 to state 2), i = 3 (from state 1 to state 2), ĀµCi = system corrective maintenance rate, i = 1 (from state 1 to state 0), i = 2
(from state 2 to state 0), i = 3 (from state 2 to state 1).
Corrective Maintenance Mathematical
Models
32
Model-III: Example 5.3: Assume that we have Ī»1 = 0.002 failures/hour,
Ī»2 = 0.003 failures/hour, Ī»3 = 0.001 failures/hour, ĀµC1 = 0.006 repairs
per hour, ĀµC2 = 0.004 repairs per hour, and ĀµC3 = 0.008 repairs/hour.
Calculate the value of the system full/partial steady-state availability.
Here, i = the ith system state, i = 0 (system operating normally), i = 1 (system operating in its degradation mode), i = 2 (system failed),
Pi(t) = probability that the system is in state i at time t, for i = 0, 1, 2, Ī»i = system failure rate, i = 1 (from state 0 to state 1), i = 2 (from state 0 to
state 2), i = 3 (from state 1 to state 2), ĀµCi = system corrective maintenance rate, i = 1 (from state 1 to state 0), i = 2
(from state 2 to state 0), i = 3 (from state 2 to state 1).
Corrective Maintenance Mathematical
Models
33
Model-IV: Represents a two identical-unit redundant (parallel)
system. At least one unit must operate normally for system
success. Corrective maintenance to put it back into its operating
state begins as soon as any one of the units fails.
The following assumptions are associated with the model:
ā€¢ The system is composed of two independent and identical units.
ā€¢ The repaired unit is as good as new.
ā€¢ No corrective maintenance is performed on the failed system (i.e., when both
units fail)
ā€¢ Unit failure and corrective maintenance rates are constant
Corrective Maintenance Mathematical
Models
34
Model-IV: System transition diagram.
The following symbols pertain to the model: i = the ith system state, i = 0 (both units operating
normally), i = 1 (one unit failed, other operating), i = 2 (both units failed), Pi(t) = probability that
the system is in state i at time t, for i = 0, 1, 2, Ī» = unit failure rate, ĀµCm = unit corrective
maintenance rate.
Corrective Maintenance Mathematical
Models
35
MODEL IV:. RS(t) = redundant system reliability at time t
Corrective Maintenance Mathematical
Models
36
MODEL IV: Example 5.4- A system is composed of two independent and
identical units in parallel. A failed unit is repaired immediately but the
failed system is never repaired. The unit times to failure and corrective
maintenance times are exponentially distributed. The unit mean time to
failure and mean corrective maintenance time are 150 h and 5 h,
respectively. Calculate the system mean time to failure with and without
the performance of corrective maintenance.
Setting ĀµCm = 0
This means introduction of corrective maintenance helped
increase system mean time to failure from 225 h to 2475 h.
Conclusions
37
Types of corrective maintenance, steps and cycle are discussed at
the beginning of this lecture.
Measures of corrective maintenance are: Mean Corrective
Maintenance Time , Median Active Corrective Maintenance Time
Maximum Active Corrective Maintenance Time.
Then different models : a system that can either be in up (operating)
or down (failed) state; a system that can either be operating
normally or failed in two mutually exclusive failure modes; a system
that can either be operating normally, operating in degradation
mode, or failed completely; a two identical-unit redundant (parallel)
system. At least one unit must operate normally for system success.
Some examples are explained in this lecture.
Thanks!
Any questions?
You can find me at:
@ahmadn
nafis@ipe.buet.ac.bd
38

More Related Content

What's hot

Maintenance engineering
Maintenance engineeringMaintenance engineering
Maintenance engineeringAnirudh Goyal
Ā 
Maintenance Management (presentation)
Maintenance Management (presentation)Maintenance Management (presentation)
Maintenance Management (presentation)kabul university
Ā 
Preventive and predictive maintainence
Preventive and predictive maintainencePreventive and predictive maintainence
Preventive and predictive maintainenceAnkit Narain
Ā 
Basic Maintenance
Basic MaintenanceBasic Maintenance
Basic MaintenanceRAHMAT EIE
Ā 
8 Steps To Success In Maintenance Planning And Scheduling
8 Steps To Success In Maintenance Planning And Scheduling8 Steps To Success In Maintenance Planning And Scheduling
8 Steps To Success In Maintenance Planning And SchedulingRicky Smith CMRP, CMRT
Ā 
Corrective maintenance
Corrective maintenanceCorrective maintenance
Corrective maintenanceyashwanth6966
Ā 
RELIABILITY CENTERED MAINTAINANCE
RELIABILITY CENTERED MAINTAINANCERELIABILITY CENTERED MAINTAINANCE
RELIABILITY CENTERED MAINTAINANCEkifayat ullah
Ā 
General Maintenance
General MaintenanceGeneral Maintenance
General Maintenancepradhyot05
Ā 
Maintenance Strategy, Types of Maintenance
Maintenance Strategy, Types of MaintenanceMaintenance Strategy, Types of Maintenance
Maintenance Strategy, Types of MaintenanceDhanesh S
Ā 
Unit-1 ME 6012
Unit-1 ME 6012Unit-1 ME 6012
Unit-1 ME 6012nagoorvali8
Ā 
Preventive maintenance
Preventive maintenancePreventive maintenance
Preventive maintenanceMalaysia
Ā 
Maintenance strategies
Maintenance strategiesMaintenance strategies
Maintenance strategiesSHIVAJI CHOUDHURY
Ā 
Maintenance management
Maintenance managementMaintenance management
Maintenance managementPrerna Toshniwal
Ā 
Types of maintenance
Types of maintenanceTypes of maintenance
Types of maintenanceAbhik Rathod
Ā 
Maintenance and maintenance
Maintenance and maintenanceMaintenance and maintenance
Maintenance and maintenanceTanveer Hussain
Ā 

What's hot (20)

Maintenance engineering
Maintenance engineeringMaintenance engineering
Maintenance engineering
Ā 
Maintenance Management (presentation)
Maintenance Management (presentation)Maintenance Management (presentation)
Maintenance Management (presentation)
Ā 
Preventive and predictive maintainence
Preventive and predictive maintainencePreventive and predictive maintainence
Preventive and predictive maintainence
Ā 
Basic Maintenance
Basic MaintenanceBasic Maintenance
Basic Maintenance
Ā 
8 Steps To Success In Maintenance Planning And Scheduling
8 Steps To Success In Maintenance Planning And Scheduling8 Steps To Success In Maintenance Planning And Scheduling
8 Steps To Success In Maintenance Planning And Scheduling
Ā 
Corrective maintenance
Corrective maintenanceCorrective maintenance
Corrective maintenance
Ā 
Plant Maintenance
Plant MaintenancePlant Maintenance
Plant Maintenance
Ā 
RELIABILITY CENTERED MAINTAINANCE
RELIABILITY CENTERED MAINTAINANCERELIABILITY CENTERED MAINTAINANCE
RELIABILITY CENTERED MAINTAINANCE
Ā 
General Maintenance
General MaintenanceGeneral Maintenance
General Maintenance
Ā 
Maintenance Strategy, Types of Maintenance
Maintenance Strategy, Types of MaintenanceMaintenance Strategy, Types of Maintenance
Maintenance Strategy, Types of Maintenance
Ā 
Unit-1 ME 6012
Unit-1 ME 6012Unit-1 ME 6012
Unit-1 ME 6012
Ā 
Preventive maintenance
Preventive maintenancePreventive maintenance
Preventive maintenance
Ā 
Maintenance strategies
Maintenance strategiesMaintenance strategies
Maintenance strategies
Ā 
Maintenence management
Maintenence managementMaintenence management
Maintenence management
Ā 
Reliability centered maintenance
Reliability centered maintenanceReliability centered maintenance
Reliability centered maintenance
Ā 
Preventive maintenance
Preventive maintenancePreventive maintenance
Preventive maintenance
Ā 
Maintenance management
Maintenance managementMaintenance management
Maintenance management
Ā 
Types of maintenance
Types of maintenanceTypes of maintenance
Types of maintenance
Ā 
Maintenance and maintenance
Maintenance and maintenanceMaintenance and maintenance
Maintenance and maintenance
Ā 
TPM: Planned Maintenance
TPM: Planned MaintenanceTPM: Planned Maintenance
TPM: Planned Maintenance
Ā 

Similar to Corrective maintenance

Revised Reliability Presentation (1).ppt
Revised Reliability Presentation (1).pptRevised Reliability Presentation (1).ppt
Revised Reliability Presentation (1).pptAnandsharma33224
Ā 
Production & Operation Management Chapter13[1]
Production & Operation Management Chapter13[1]Production & Operation Management Chapter13[1]
Production & Operation Management Chapter13[1]Hariharan Ponnusamy
Ā 
Om0015 maintenance management..
Om0015   maintenance management..Om0015   maintenance management..
Om0015 maintenance management..smumbahelp
Ā 
Om0015 maintenance management..
Om0015   maintenance management..Om0015   maintenance management..
Om0015 maintenance management..smumbahelp
Ā 
Mechanical Maintenance
Mechanical MaintenanceMechanical Maintenance
Mechanical MaintenanceAshutosh Tomar
Ā 
Diagnostic Techniques Notes
Diagnostic Techniques NotesDiagnostic Techniques Notes
Diagnostic Techniques Notesrajimech06
Ā 
Techniques for Optimal Maintenance Scheduling
Techniques for Optimal Maintenance SchedulingTechniques for Optimal Maintenance Scheduling
Techniques for Optimal Maintenance SchedulingIOSR Journals
Ā 
Preventive maintenance
Preventive maintenancePreventive maintenance
Preventive maintenanceNafis Ahmad
Ā 
Maintenance management
Maintenance managementMaintenance management
Maintenance managementramduttkholia
Ā 
MIS_Ch_1_for_studentsNew.pptx
MIS_Ch_1_for_studentsNew.pptxMIS_Ch_1_for_studentsNew.pptx
MIS_Ch_1_for_studentsNew.pptxShivajiThube2
Ā 
MIS_Ch_1_for_studentsNew.pdf
MIS_Ch_1_for_studentsNew.pdfMIS_Ch_1_for_studentsNew.pdf
MIS_Ch_1_for_studentsNew.pdfShivajiThube2
Ā 
MIS_Ch_1_for_studentsNew.pdf
MIS_Ch_1_for_studentsNew.pdfMIS_Ch_1_for_studentsNew.pdf
MIS_Ch_1_for_studentsNew.pdfShivajiThube2
Ā 
Smart Maintenance engineering
Smart Maintenance engineering Smart Maintenance engineering
Smart Maintenance engineering Michel Mafumba
Ā 
An Imperfect Preventive Maintenance Policy Considering Reliability Limit
An Imperfect Preventive Maintenance Policy Considering Reliability LimitAn Imperfect Preventive Maintenance Policy Considering Reliability Limit
An Imperfect Preventive Maintenance Policy Considering Reliability LimitIJERA Editor
Ā 
Maintenace management and TPM
Maintenace management and TPMMaintenace management and TPM
Maintenace management and TPMMohieudeen Mohamed
Ā 
maintenance-management-UNIT-I-and-II-1.ppt
maintenance-management-UNIT-I-and-II-1.pptmaintenance-management-UNIT-I-and-II-1.ppt
maintenance-management-UNIT-I-and-II-1.pptYunusEmreKarabacak2
Ā 
Standard Maintenance Practices , Types.ppt
Standard Maintenance Practices , Types.pptStandard Maintenance Practices , Types.ppt
Standard Maintenance Practices , Types.pptDivanshu Garg
Ā 
ME6012 M E 2 Marks & QB.pdf
ME6012 M E  2 Marks & QB.pdfME6012 M E  2 Marks & QB.pdf
ME6012 M E 2 Marks & QB.pdfSou Tibon
Ā 

Similar to Corrective maintenance (20)

Revised Reliability Presentation (1).ppt
Revised Reliability Presentation (1).pptRevised Reliability Presentation (1).ppt
Revised Reliability Presentation (1).ppt
Ā 
Chapter13[1]
Chapter13[1]Chapter13[1]
Chapter13[1]
Ā 
Production & Operation Management Chapter13[1]
Production & Operation Management Chapter13[1]Production & Operation Management Chapter13[1]
Production & Operation Management Chapter13[1]
Ā 
Om0015 maintenance management..
Om0015   maintenance management..Om0015   maintenance management..
Om0015 maintenance management..
Ā 
Om0015 maintenance management..
Om0015   maintenance management..Om0015   maintenance management..
Om0015 maintenance management..
Ā 
Mechanical Maintenance
Mechanical MaintenanceMechanical Maintenance
Mechanical Maintenance
Ā 
Diagnostic Techniques Notes
Diagnostic Techniques NotesDiagnostic Techniques Notes
Diagnostic Techniques Notes
Ā 
Techniques for Optimal Maintenance Scheduling
Techniques for Optimal Maintenance SchedulingTechniques for Optimal Maintenance Scheduling
Techniques for Optimal Maintenance Scheduling
Ā 
Preventive maintenance
Preventive maintenancePreventive maintenance
Preventive maintenance
Ā 
Maintenance management
Maintenance managementMaintenance management
Maintenance management
Ā 
MIS_Ch_1_for_studentsNew.pptx
MIS_Ch_1_for_studentsNew.pptxMIS_Ch_1_for_studentsNew.pptx
MIS_Ch_1_for_studentsNew.pptx
Ā 
MIS_Ch_1_for_studentsNew.pdf
MIS_Ch_1_for_studentsNew.pdfMIS_Ch_1_for_studentsNew.pdf
MIS_Ch_1_for_studentsNew.pdf
Ā 
MIS_Ch_1_for_studentsNew.pdf
MIS_Ch_1_for_studentsNew.pdfMIS_Ch_1_for_studentsNew.pdf
MIS_Ch_1_for_studentsNew.pdf
Ā 
Smart Maintenance engineering
Smart Maintenance engineering Smart Maintenance engineering
Smart Maintenance engineering
Ā 
An Imperfect Preventive Maintenance Policy Considering Reliability Limit
An Imperfect Preventive Maintenance Policy Considering Reliability LimitAn Imperfect Preventive Maintenance Policy Considering Reliability Limit
An Imperfect Preventive Maintenance Policy Considering Reliability Limit
Ā 
Maintenance 2sp
Maintenance 2spMaintenance 2sp
Maintenance 2sp
Ā 
Maintenace management and TPM
Maintenace management and TPMMaintenace management and TPM
Maintenace management and TPM
Ā 
maintenance-management-UNIT-I-and-II-1.ppt
maintenance-management-UNIT-I-and-II-1.pptmaintenance-management-UNIT-I-and-II-1.ppt
maintenance-management-UNIT-I-and-II-1.ppt
Ā 
Standard Maintenance Practices , Types.ppt
Standard Maintenance Practices , Types.pptStandard Maintenance Practices , Types.ppt
Standard Maintenance Practices , Types.ppt
Ā 
ME6012 M E 2 Marks & QB.pdf
ME6012 M E  2 Marks & QB.pdfME6012 M E  2 Marks & QB.pdf
ME6012 M E 2 Marks & QB.pdf
Ā 

More from Nafis Ahmad

Introduction CIM
Introduction CIMIntroduction CIM
Introduction CIMNafis Ahmad
Ā 
Safety management
Safety management Safety management
Safety management Nafis Ahmad
Ā 
IPE-431 Machine Tools (Part-C)
IPE-431 Machine Tools (Part-C)IPE-431 Machine Tools (Part-C)
IPE-431 Machine Tools (Part-C)Nafis Ahmad
Ā 
Automatic Identification and Data Capture Techniques
Automatic Identification and Data Capture TechniquesAutomatic Identification and Data Capture Techniques
Automatic Identification and Data Capture TechniquesNafis Ahmad
Ā 
Flexible Manufacturing System
Flexible Manufacturing SystemFlexible Manufacturing System
Flexible Manufacturing SystemNafis Ahmad
Ā 
CAD-CAM-CIM
CAD-CAM-CIMCAD-CAM-CIM
CAD-CAM-CIMNafis Ahmad
Ā 
Decision making considering multi-attributes
Decision making considering multi-attributesDecision making considering multi-attributes
Decision making considering multi-attributesNafis Ahmad
Ā 
Breakeven & sensitivity analysis
Breakeven & sensitivity analysisBreakeven & sensitivity analysis
Breakeven & sensitivity analysisNafis Ahmad
Ā 
Replacement analysis
Replacement analysisReplacement analysis
Replacement analysisNafis Ahmad
Ā 
Benefit-Cost (B-C) ratio analysis
Benefit-Cost (B-C) ratio analysisBenefit-Cost (B-C) ratio analysis
Benefit-Cost (B-C) ratio analysisNafis Ahmad
Ā 
Depreciation and income taxes
Depreciation and income taxesDepreciation and income taxes
Depreciation and income taxesNafis Ahmad
Ā 
Comparison and selection among alternatives
Comparison and selection among alternativesComparison and selection among alternatives
Comparison and selection among alternativesNafis Ahmad
Ā 
CADCAM: Data exchange standards
CADCAM: Data exchange standardsCADCAM: Data exchange standards
CADCAM: Data exchange standardsNafis Ahmad
Ā 
Industrial Robots
Industrial RobotsIndustrial Robots
Industrial RobotsNafis Ahmad
Ā 
Evaluating a Single Project
Evaluating a Single ProjectEvaluating a Single Project
Evaluating a Single ProjectNafis Ahmad
Ā 
Entity Manipulation
Entity ManipulationEntity Manipulation
Entity ManipulationNafis Ahmad
Ā 
Evaluating a single project
Evaluating a single projectEvaluating a single project
Evaluating a single projectNafis Ahmad
Ā 
Computer graphics
Computer graphicsComputer graphics
Computer graphicsNafis Ahmad
Ā 
Failure Mode & Effect Analysis
Failure Mode & Effect AnalysisFailure Mode & Effect Analysis
Failure Mode & Effect AnalysisNafis Ahmad
Ā 
Reliability Centered Maintenance
Reliability Centered MaintenanceReliability Centered Maintenance
Reliability Centered MaintenanceNafis Ahmad
Ā 

More from Nafis Ahmad (20)

Introduction CIM
Introduction CIMIntroduction CIM
Introduction CIM
Ā 
Safety management
Safety management Safety management
Safety management
Ā 
IPE-431 Machine Tools (Part-C)
IPE-431 Machine Tools (Part-C)IPE-431 Machine Tools (Part-C)
IPE-431 Machine Tools (Part-C)
Ā 
Automatic Identification and Data Capture Techniques
Automatic Identification and Data Capture TechniquesAutomatic Identification and Data Capture Techniques
Automatic Identification and Data Capture Techniques
Ā 
Flexible Manufacturing System
Flexible Manufacturing SystemFlexible Manufacturing System
Flexible Manufacturing System
Ā 
CAD-CAM-CIM
CAD-CAM-CIMCAD-CAM-CIM
CAD-CAM-CIM
Ā 
Decision making considering multi-attributes
Decision making considering multi-attributesDecision making considering multi-attributes
Decision making considering multi-attributes
Ā 
Breakeven & sensitivity analysis
Breakeven & sensitivity analysisBreakeven & sensitivity analysis
Breakeven & sensitivity analysis
Ā 
Replacement analysis
Replacement analysisReplacement analysis
Replacement analysis
Ā 
Benefit-Cost (B-C) ratio analysis
Benefit-Cost (B-C) ratio analysisBenefit-Cost (B-C) ratio analysis
Benefit-Cost (B-C) ratio analysis
Ā 
Depreciation and income taxes
Depreciation and income taxesDepreciation and income taxes
Depreciation and income taxes
Ā 
Comparison and selection among alternatives
Comparison and selection among alternativesComparison and selection among alternatives
Comparison and selection among alternatives
Ā 
CADCAM: Data exchange standards
CADCAM: Data exchange standardsCADCAM: Data exchange standards
CADCAM: Data exchange standards
Ā 
Industrial Robots
Industrial RobotsIndustrial Robots
Industrial Robots
Ā 
Evaluating a Single Project
Evaluating a Single ProjectEvaluating a Single Project
Evaluating a Single Project
Ā 
Entity Manipulation
Entity ManipulationEntity Manipulation
Entity Manipulation
Ā 
Evaluating a single project
Evaluating a single projectEvaluating a single project
Evaluating a single project
Ā 
Computer graphics
Computer graphicsComputer graphics
Computer graphics
Ā 
Failure Mode & Effect Analysis
Failure Mode & Effect AnalysisFailure Mode & Effect Analysis
Failure Mode & Effect Analysis
Ā 
Reliability Centered Maintenance
Reliability Centered MaintenanceReliability Centered Maintenance
Reliability Centered Maintenance
Ā 

Recently uploaded

OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...
OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...
OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...Soham Mondal
Ā 
MANUFACTURING PROCESS-II UNIT-5 NC MACHINE TOOLS
MANUFACTURING PROCESS-II UNIT-5 NC MACHINE TOOLSMANUFACTURING PROCESS-II UNIT-5 NC MACHINE TOOLS
MANUFACTURING PROCESS-II UNIT-5 NC MACHINE TOOLSSIVASHANKAR N
Ā 
main PPT.pptx of girls hostel security using rfid
main PPT.pptx of girls hostel security using rfidmain PPT.pptx of girls hostel security using rfid
main PPT.pptx of girls hostel security using rfidNikhilNagaraju
Ā 
(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...ranjana rawat
Ā 
Coefficient of Thermal Expansion and their Importance.pptx
Coefficient of Thermal Expansion and their Importance.pptxCoefficient of Thermal Expansion and their Importance.pptx
Coefficient of Thermal Expansion and their Importance.pptxAsutosh Ranjan
Ā 
VIP Call Girls Service Kondapur Hyderabad Call +91-8250192130
VIP Call Girls Service Kondapur Hyderabad Call +91-8250192130VIP Call Girls Service Kondapur Hyderabad Call +91-8250192130
VIP Call Girls Service Kondapur Hyderabad Call +91-8250192130Suhani Kapoor
Ā 
GDSC ASEB Gen AI study jams presentation
GDSC ASEB Gen AI study jams presentationGDSC ASEB Gen AI study jams presentation
GDSC ASEB Gen AI study jams presentationGDSCAESB
Ā 
Architect Hassan Khalil Portfolio for 2024
Architect Hassan Khalil Portfolio for 2024Architect Hassan Khalil Portfolio for 2024
Architect Hassan Khalil Portfolio for 2024hassan khalil
Ā 
HARMONY IN THE NATURE AND EXISTENCE - Unit-IV
HARMONY IN THE NATURE AND EXISTENCE - Unit-IVHARMONY IN THE NATURE AND EXISTENCE - Unit-IV
HARMONY IN THE NATURE AND EXISTENCE - Unit-IVRajaP95
Ā 
High Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur EscortsHigh Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur Escortsranjana rawat
Ā 
Gfe Mayur Vihar Call Girls Service WhatsApp -> 9999965857 Available 24x7 ^ De...
Gfe Mayur Vihar Call Girls Service WhatsApp -> 9999965857 Available 24x7 ^ De...Gfe Mayur Vihar Call Girls Service WhatsApp -> 9999965857 Available 24x7 ^ De...
Gfe Mayur Vihar Call Girls Service WhatsApp -> 9999965857 Available 24x7 ^ De...srsj9000
Ā 
Analog to Digital and Digital to Analog Converter
Analog to Digital and Digital to Analog ConverterAnalog to Digital and Digital to Analog Converter
Analog to Digital and Digital to Analog ConverterAbhinavSharma374939
Ā 
Porous Ceramics seminar and technical writing
Porous Ceramics seminar and technical writingPorous Ceramics seminar and technical writing
Porous Ceramics seminar and technical writingrakeshbaidya232001
Ā 
Model Call Girl in Narela Delhi reach out to us at šŸ”8264348440šŸ”
Model Call Girl in Narela Delhi reach out to us at šŸ”8264348440šŸ”Model Call Girl in Narela Delhi reach out to us at šŸ”8264348440šŸ”
Model Call Girl in Narela Delhi reach out to us at šŸ”8264348440šŸ”soniya singh
Ā 
Microscopic Analysis of Ceramic Materials.pptx
Microscopic Analysis of Ceramic Materials.pptxMicroscopic Analysis of Ceramic Materials.pptx
Microscopic Analysis of Ceramic Materials.pptxpurnimasatapathy1234
Ā 
Call Girls Delhi {Jodhpur} 9711199012 high profile service
Call Girls Delhi {Jodhpur} 9711199012 high profile serviceCall Girls Delhi {Jodhpur} 9711199012 high profile service
Call Girls Delhi {Jodhpur} 9711199012 high profile servicerehmti665
Ā 
(PRIYA) Rajgurunagar Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(PRIYA) Rajgurunagar Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...(PRIYA) Rajgurunagar Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(PRIYA) Rajgurunagar Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...ranjana rawat
Ā 
(SHREYA) Chakan Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Esc...
(SHREYA) Chakan Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Esc...(SHREYA) Chakan Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Esc...
(SHREYA) Chakan Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Esc...ranjana rawat
Ā 
HARDNESS, FRACTURE TOUGHNESS AND STRENGTH OF CERAMICS
HARDNESS, FRACTURE TOUGHNESS AND STRENGTH OF CERAMICSHARDNESS, FRACTURE TOUGHNESS AND STRENGTH OF CERAMICS
HARDNESS, FRACTURE TOUGHNESS AND STRENGTH OF CERAMICSRajkumarAkumalla
Ā 

Recently uploaded (20)

Exploring_Network_Security_with_JA3_by_Rakesh Seal.pptx
Exploring_Network_Security_with_JA3_by_Rakesh Seal.pptxExploring_Network_Security_with_JA3_by_Rakesh Seal.pptx
Exploring_Network_Security_with_JA3_by_Rakesh Seal.pptx
Ā 
OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...
OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...
OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...
Ā 
MANUFACTURING PROCESS-II UNIT-5 NC MACHINE TOOLS
MANUFACTURING PROCESS-II UNIT-5 NC MACHINE TOOLSMANUFACTURING PROCESS-II UNIT-5 NC MACHINE TOOLS
MANUFACTURING PROCESS-II UNIT-5 NC MACHINE TOOLS
Ā 
main PPT.pptx of girls hostel security using rfid
main PPT.pptx of girls hostel security using rfidmain PPT.pptx of girls hostel security using rfid
main PPT.pptx of girls hostel security using rfid
Ā 
(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
Ā 
Coefficient of Thermal Expansion and their Importance.pptx
Coefficient of Thermal Expansion and their Importance.pptxCoefficient of Thermal Expansion and their Importance.pptx
Coefficient of Thermal Expansion and their Importance.pptx
Ā 
VIP Call Girls Service Kondapur Hyderabad Call +91-8250192130
VIP Call Girls Service Kondapur Hyderabad Call +91-8250192130VIP Call Girls Service Kondapur Hyderabad Call +91-8250192130
VIP Call Girls Service Kondapur Hyderabad Call +91-8250192130
Ā 
GDSC ASEB Gen AI study jams presentation
GDSC ASEB Gen AI study jams presentationGDSC ASEB Gen AI study jams presentation
GDSC ASEB Gen AI study jams presentation
Ā 
Architect Hassan Khalil Portfolio for 2024
Architect Hassan Khalil Portfolio for 2024Architect Hassan Khalil Portfolio for 2024
Architect Hassan Khalil Portfolio for 2024
Ā 
HARMONY IN THE NATURE AND EXISTENCE - Unit-IV
HARMONY IN THE NATURE AND EXISTENCE - Unit-IVHARMONY IN THE NATURE AND EXISTENCE - Unit-IV
HARMONY IN THE NATURE AND EXISTENCE - Unit-IV
Ā 
High Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur EscortsHigh Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur Escorts
Ā 
Gfe Mayur Vihar Call Girls Service WhatsApp -> 9999965857 Available 24x7 ^ De...
Gfe Mayur Vihar Call Girls Service WhatsApp -> 9999965857 Available 24x7 ^ De...Gfe Mayur Vihar Call Girls Service WhatsApp -> 9999965857 Available 24x7 ^ De...
Gfe Mayur Vihar Call Girls Service WhatsApp -> 9999965857 Available 24x7 ^ De...
Ā 
Analog to Digital and Digital to Analog Converter
Analog to Digital and Digital to Analog ConverterAnalog to Digital and Digital to Analog Converter
Analog to Digital and Digital to Analog Converter
Ā 
Porous Ceramics seminar and technical writing
Porous Ceramics seminar and technical writingPorous Ceramics seminar and technical writing
Porous Ceramics seminar and technical writing
Ā 
Model Call Girl in Narela Delhi reach out to us at šŸ”8264348440šŸ”
Model Call Girl in Narela Delhi reach out to us at šŸ”8264348440šŸ”Model Call Girl in Narela Delhi reach out to us at šŸ”8264348440šŸ”
Model Call Girl in Narela Delhi reach out to us at šŸ”8264348440šŸ”
Ā 
Microscopic Analysis of Ceramic Materials.pptx
Microscopic Analysis of Ceramic Materials.pptxMicroscopic Analysis of Ceramic Materials.pptx
Microscopic Analysis of Ceramic Materials.pptx
Ā 
Call Girls Delhi {Jodhpur} 9711199012 high profile service
Call Girls Delhi {Jodhpur} 9711199012 high profile serviceCall Girls Delhi {Jodhpur} 9711199012 high profile service
Call Girls Delhi {Jodhpur} 9711199012 high profile service
Ā 
(PRIYA) Rajgurunagar Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(PRIYA) Rajgurunagar Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...(PRIYA) Rajgurunagar Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(PRIYA) Rajgurunagar Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
Ā 
(SHREYA) Chakan Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Esc...
(SHREYA) Chakan Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Esc...(SHREYA) Chakan Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Esc...
(SHREYA) Chakan Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Esc...
Ā 
HARDNESS, FRACTURE TOUGHNESS AND STRENGTH OF CERAMICS
HARDNESS, FRACTURE TOUGHNESS AND STRENGTH OF CERAMICSHARDNESS, FRACTURE TOUGHNESS AND STRENGTH OF CERAMICS
HARDNESS, FRACTURE TOUGHNESS AND STRENGTH OF CERAMICS
Ā 

Corrective maintenance

  • 1. AEM-6235 Maintenance and Safety Management Dr. Nafis Ahmad Professor Department of IPE, BUET Email:nafis@ipe.buet.ac.bd
  • 2.
  • 3. Topics ā–· Introduction ā–· Maintenance Management and Control ā–· Preventive Maintenance ā–· Corrective Maintenance ā–· Reliability Centered Maintenance ā–· Maintainability 3
  • 5. Introduction 5 ā€¢ Although every effort is made to make engineering systems as reliable as possible through design, preventive maintenance, and so on, from time to time they do fail. Consequently, they are repaired to their operational state. ā€¢ Corrective maintenance may be defined as the remedial action carried out due to failure or deficiencies discovered during preventive maintenance, to repair an equipment/item to its operational state. ā€¢ Corrective maintenance is an unscheduled maintenance action, basically composed of unpredictable maintenance needs that cannot be preplanned or programmed on the basis of occurrence at a particular time.
  • 6. Corrective maintenance types 6 Corrective maintenance may be classified into five major categories: These are: (a) fail-repair, (b) salvage, (c) rebuild, (d) overhaul, and (e) servicing
  • 7. Corrective maintenance types 7 a) Fail-repair: The failed item is restored to its operational state. b) Salvage: This element of corrective maintenance is concerned with disposal of nonrepairable material and use of salvaged material from nonrepairable equipment/item in the repair, overhaul, or rebuild programs. c) Rebuild: This is concerned with restoring an item to a standard as close as possible to original state in performance, life expectancy, and appearance. d) Overhaul: Restoring an item to its total serviceable state as per maintenance serviceability standards, using the ā€œinspect and repair only as appropriateā€ approach. e) Servicing: Servicing may be needed because of the corrective maintenance action, for example, engine repair can lead to crankcase refill, welding on, etc. Another example could be that the replacement of an air bottle may require system recharging.
  • 8. Different authors have laid down different sequential steps for performing corrective maintenance. ā€¢ Some presents nine steps (as applicable): localize, isolate, adjust, disassemble, repair, interchange, reassemble, align, and checkout. ā€¢ Another author presents seven steps (as applicable): localization, isolation, disassembly, interchange, reassemble, alignment, and checkout. ā€¢ Author of the book mentioned corrective maintenance is composed of five major sequential steps, as shown in Fig. These steps are: fault recognition, localization, diagnosis, repair, and checkout. Corrective maintenance steps 8
  • 10. 10 Five major sequential steps, as shown in the right Figure. 1. fault recognition, 2. localization, 3. diagnosis, 4. repair, and 5. checkout. The major corrective maintenance downtime components are: a) active repair time, b) administrative and logistic time, c) and delay time. The active repair time is made up of the following subcomponents: 1. Preparation time 2. Fault location time 3. Spare item obtainment time 4. Fault correction time 5. Adjustment and calibration time 6. Checkout time
  • 11. CM Time Reduction Strategies at System Level 11 Some strategies for reducing the system-level corrective maintenance time are as follows: 1. Efficiency in fault recognition, location, and isolation: in electronic equipment, fault isolation and location consume the most time within a corrective maintenance activity. In the case of mechanical items, often the largest contributor is repair time. 2. Effective interchangeability: Good physical and functional interchangeability is useful in removing and replacing parts/items, reducing maintenance downtime, and creating a positive impact on spares and inventory needs. 3. Redundancy: This is concerned with designing in redundant parts that can be switched in at the moment of need so the equipment/system continues to operate while the faulty part is being repaired. 4. Effective accessibility: Often a significant amount of time is spent accessing the failed part. 5. Human factor considerations: Attention paid to human factors during design in areas such as readability of instructions, size, shape, and weight of components, selection and placement of dials and indicators, size and placement of access, gates, and readability, and information processing aids can help reduce corrective maintenance time significantly.
  • 12. There are various measures associated with corrective maintenance. ā€¢ Mean Corrective Maintenance Time ā€¢ Median Active Corrective Maintenance Time ā€¢ Maximum Active Corrective Maintenance Time Corrective maintenance measures 12
  • 13. Mean Corrective Maintenance Time: where Tmcm = mean corrective maintenance time, Tcmj = corrective maintenance time of the jth equipment/system element, Ī»j = failure rate of the jth equipment/system element. Past experience indicates that probability distributions of corrective maintenance times follow exponential, normal, and log normal. Corrective maintenance measures 13
  • 14. Mean Corrective Maintenance Time: where Tmcm = mean corrective maintenance time, Tcm j = corrective maintenance time of the jth equipment/ system element, Ī»j = failure rate of the jth equipment/system element. Past experience indicates that probability distributions of corrective maintenance times follow exponential, normal, and log normal. Corrective maintenance measures 14
  • 15. 15
  • 17. Median Active Corrective Maintenance Time: This normally provides the best average location of the sample data and is the 50th percentile of all values of repair time. It may be said that median corrective maintenance time is a measure of the time within which 50% of all corrective maintenance can be accomplished. The median of the lognormally distributed corrective maintenance times is given by: Where, Tmed = median active corrective maintenance time. Tcm j = corrective maintenance time of the jth equipment/ system element, For normally distributed corrective maintenance time, Tmem=Tmed Corrective maintenance measures 17
  • 18. Maximum Active Corrective Maintenance Time: This measures the time needed to accomplish all potential corrective maintenance actions up to a given percentage, frequently the 90th or 95th percentiles. For example, in the case of 90th percentile, the maximum corrective maintenance time is the time within which 90% of all maintenance actions can be accomplished. For lognormally distributed corrective maintenance times, the maximum active corrective maintenance time is: Where Tcmax = maximum active corrective maintenance time, Ī¤mn = mean of the logarithms of Tcm j, Ļƒcm = standard deviation of the logarithms of the sample corrective maintenance times, z = standard deviation value corresponding to the percentile value specified for Tcmax Corrective maintenance measures 18
  • 19. Maximum Active Corrective Maintenance Time: Where Tcmax = maximum active corrective maintenance time, Ī¤mn = mean of the logarithms of Tcm j, Ļƒcm = standard deviation of the logarithms of the sample corrective maintenance times, z = standard deviation value corresponding to the percentile value specified for Tcmax M = total number of corrective maintenance times. Corrective maintenance measures 19
  • 20.
  • 21. Corrective Maintenance Mathematical Models 21 These models take into consideration the item failure (Ī») and corrective maintenance rates (ĀµC), and can be used to predict item/system probability of being in failed state (i.e., undergoing repair), availability, mean time to failure, and so on. Model-I: Represents a system that can either be in up (operating) or down (failed) state. Model-II: Represents a system that can either be operating normally or failed in two mutually exclusive failure modes (i.e., failure modes I and Model-III: Represents a system that can either be operating normally, operating in degradation mode, or failed completely Model-IV: Represents a two identical-unit redundant (parallel) system. At least one unit must operate normally for system success.
  • 22. Corrective Maintenance Mathematical Models 22 Model-I: This mathematical model represents a system that can either be in up (operating) or down (failed) state. Corrective maintenance is performed on the failed system to put it back into its operating state. Assumptions: Failure and corrective maintenance rates are constant, the repaired system is as good as new, system failures are statistically independent. System transition diagram.
  • 23. Corrective Maintenance Mathematical Models 23 Model-I: i = the ith system state, i = 0 (system operating normally), i = 1 (system failed); Pi(t) = probability that the system is in state i at time t; Ī» = system failure rate; ĀµC = system corrective maintenance rate. AS=The system availability is given by
  • 24. Corrective Maintenance Mathematical Models 24 Model-I: If t is very large, System steady state availability. Since Ī» = 1/MTTF and ĀµC = 1/Tmcm
  • 25. Corrective Maintenance Mathematical Models 25 Example 5-1: Assume the MTTF of a piece of equipment is 3000h and its mean corrective maintenance time is 5h. Calculate the equipment steady-state availability, if the equipment failure and corrective maintenance times are exponentially distributed. System steady state availability. or Here MTTF= 3000h and Tmcm= 5h System steady state availability = 0.9983, Find P0 and P1
  • 26. Corrective Maintenance Mathematical Models 26 Model-II: Represents a system that can either be operating normally or failed in two mutually exclusive failure modes (i.e., failure modes I and II). A typical example of this type of system or device is a fluid flow valve (i.e., open and close failure modes). Corrective maintenance is performed from either failure mode of the system to put it back into its operational state. The following assumptions are associated with this model: The system can fail in two mutually exclusive failure modes. The repaired system is as good as new. All system failures are statistically independent. Failure and corrective maintenance rates are constant
  • 28. Corrective Maintenance Mathematical Models 28 Model-II: If time t becomes very large, system steady state availability: Example 5.2: An engineering system can fail in two mutually exclusive failure modes. Failure modes I and II constant failure rates are Ī»1 = 0.002 failures/hour and Ī»2 = 0.005 failures/hour, respectively. The constant corrective maintenance rates from failure modes I and II are ĀµC1 = 0.006 repairs/hour and ĀµC2 = 0.009 repairs/hour, respectively. Calculate the system steady state availability.
  • 29. Corrective Maintenance Mathematical Models 29 Model-III: Represents a system that can either be operating normally, operating in degradation mode, or failed completely. An example of this type of system could be a power generator, i.e., producing electricity at full capacity, derated capacity, or not at all. Corrective maintenance is initiated from degradation and completely failed modes of the system to repair failed parts. The model is subject to the following assumptions: ā€¢ System complete failure, partial failure, and corrective maintenance rates are constant. ā€¢ The operating system can either fail fully or partially. The partially operating system can stop operating altogether. ā€¢ All system failures are statistically independent. ā€¢ The repaired system is as good as new
  • 30. Corrective Maintenance Mathematical Models 30 MODEL III: System transition diagram.
  • 31. Corrective Maintenance Mathematical Models 31 Model-III: The system full/partial steady-state availability Here, i = the ith system state, i = 0 (system operating normally), i = 1 (system operating in its degradation mode), i = 2 (system failed), Pi(t) = probability that the system is in state i at time t, for i = 0, 1, 2, Ī»i = system failure rate, i = 1 (from state 0 to state 1), i = 2 (from state 0 to state 2), i = 3 (from state 1 to state 2), ĀµCi = system corrective maintenance rate, i = 1 (from state 1 to state 0), i = 2 (from state 2 to state 0), i = 3 (from state 2 to state 1).
  • 32. Corrective Maintenance Mathematical Models 32 Model-III: Example 5.3: Assume that we have Ī»1 = 0.002 failures/hour, Ī»2 = 0.003 failures/hour, Ī»3 = 0.001 failures/hour, ĀµC1 = 0.006 repairs per hour, ĀµC2 = 0.004 repairs per hour, and ĀµC3 = 0.008 repairs/hour. Calculate the value of the system full/partial steady-state availability. Here, i = the ith system state, i = 0 (system operating normally), i = 1 (system operating in its degradation mode), i = 2 (system failed), Pi(t) = probability that the system is in state i at time t, for i = 0, 1, 2, Ī»i = system failure rate, i = 1 (from state 0 to state 1), i = 2 (from state 0 to state 2), i = 3 (from state 1 to state 2), ĀµCi = system corrective maintenance rate, i = 1 (from state 1 to state 0), i = 2 (from state 2 to state 0), i = 3 (from state 2 to state 1).
  • 33. Corrective Maintenance Mathematical Models 33 Model-IV: Represents a two identical-unit redundant (parallel) system. At least one unit must operate normally for system success. Corrective maintenance to put it back into its operating state begins as soon as any one of the units fails. The following assumptions are associated with the model: ā€¢ The system is composed of two independent and identical units. ā€¢ The repaired unit is as good as new. ā€¢ No corrective maintenance is performed on the failed system (i.e., when both units fail) ā€¢ Unit failure and corrective maintenance rates are constant
  • 34. Corrective Maintenance Mathematical Models 34 Model-IV: System transition diagram. The following symbols pertain to the model: i = the ith system state, i = 0 (both units operating normally), i = 1 (one unit failed, other operating), i = 2 (both units failed), Pi(t) = probability that the system is in state i at time t, for i = 0, 1, 2, Ī» = unit failure rate, ĀµCm = unit corrective maintenance rate.
  • 35. Corrective Maintenance Mathematical Models 35 MODEL IV:. RS(t) = redundant system reliability at time t
  • 36. Corrective Maintenance Mathematical Models 36 MODEL IV: Example 5.4- A system is composed of two independent and identical units in parallel. A failed unit is repaired immediately but the failed system is never repaired. The unit times to failure and corrective maintenance times are exponentially distributed. The unit mean time to failure and mean corrective maintenance time are 150 h and 5 h, respectively. Calculate the system mean time to failure with and without the performance of corrective maintenance. Setting ĀµCm = 0 This means introduction of corrective maintenance helped increase system mean time to failure from 225 h to 2475 h.
  • 37. Conclusions 37 Types of corrective maintenance, steps and cycle are discussed at the beginning of this lecture. Measures of corrective maintenance are: Mean Corrective Maintenance Time , Median Active Corrective Maintenance Time Maximum Active Corrective Maintenance Time. Then different models : a system that can either be in up (operating) or down (failed) state; a system that can either be operating normally or failed in two mutually exclusive failure modes; a system that can either be operating normally, operating in degradation mode, or failed completely; a two identical-unit redundant (parallel) system. At least one unit must operate normally for system success. Some examples are explained in this lecture.
  • 38. Thanks! Any questions? You can find me at: @ahmadn nafis@ipe.buet.ac.bd 38