SlideShare a Scribd company logo
Formwork & Centering Design
-facts and reality
Presented by
Mr. A.V. Ghogare
Department of Civil Engineering,
SRES’s Sanjivani College of Engineering,
Kopargaon
An Autonomous Institute,
Dist: Ahmednagar, MH, India
FORMWORK FOR STRUCTURAL ELEMENTS
 Slab
 Beam
 Column
 Footing
 Staircase
 Wall
SLAB FORMWORK
 Slab formwork is designed
as per the depth of concrete slab.
 The loads on plywood are usually considered as
being uniformly distributed over the entire surface of
the formwork.
 The slab is supported on 25mm thick sheathing laid
parallel to the main beams
 The sheathing is supported on wooden battens which
are laid between the beams.
 In order to reduce the deflection, the battens may be
propped at middle of the span through joists.
SLAB FORMWORK
BEAM FORMWORK
 The side forms of the beam is 30mm thick sheathing
while bottom sheathing may be 50 to 70 mm thick.
 The ends of the battens are supported on the ledger
which is fixed to the cleat throughout the length.
 Cleats 100mm X20 to 30mm are fixed to the side forms.
 The beam form is supported on a head tree.
 The shore or post is connected to head tree through
cleats.
 At bottom of the shore, two wedges of hard wood are
provided over a sole piece.
BEAM FORMS
BEAM FORMS
FORMWORK FOR COLUMNS
 Sheathing all around the column
periphery, 2 Side yoke and end
yoke, 4 Wedges, 2 bolts and 4
washers.
 Two side yokes are comparatively
heavier sections and are connected
together by two long bolts of 16mm
dia. The sheathing are nailed to the
yoke.
 Ex. Square, rectangular, circular or
any other shape, etc
COLUMN FORMWORK
 Column forms should be capable of
being stripped easily.
 In tall forms it is desirable to provided
windows at appropriate levels on at
least one face to facilitate inspection,
concrete placement and vibration.
 Any method (standard or patented) such as adjustable
clamps, bolts, and purpose made yokes, etc. to hold
the panels in place may be used.
 The spacing and size of these clamps should depend
upon the lateral pressure of fresh concrete.
FORMWORK FOR FOUNDATIONS
 It depends on whether sides of foundations are
vertical or inclined (slopped).
 For vertical sides, construct hollow box open at top
and bottom as shown in figure.
 It should be rigid when filled with concrete.
 Ex. Square, rectangular or Box footing, combined
footings, Raft foundation, etc
 For slopped footing, up to 150-200mm, box is
prepared, over which trapezoidal forms should be
fixed to provide required slopes.
 Yokes of size 75mmX100mm and Bolts are used to
secure the boards at suitable interval (300-600mm)
WALL FORMWORKS
 The boarding may be 40-50mm
thick for wall up to 4m height.
 The boards are fixed to 50mmX100m posts known as
studs, about 0.7 to 1m apart.
 Horizontal walling of size 75mm X 100mm are fixed
to the post at 1 to 1.25m interval.
 The whole assembly is than strutted using
75mmX100mm struts.
WALL FORMWORKS
FORM WORK FOR STAIRS
 The sheathing or decking for the deck slab is
carried on cross joists which are in turn supported
to raking ledgers.
 The ledger is generally of 75mm X 100mm size.
 The cross joist may be of 50mm X 100mm size.
 The riser planks are 40-50mm thick and width
equal to the riser.
 A stiffener joist of size 50mmX100mm is placed
along the middle of the riser planks.
FORM WORK FOR TANK WALL
MONOLITHIC FORMWORKS
 walls, columns, slabs, beams and stairways are
realized using the monolithic construction method.
 The system offers a suitable and fast solution for
forming frequently repetitive floor plans -
horizontally or vertically.
 The individual panels can be easily moved and
transported by hand. Through the use of special
wedge couplers, the wall and slab panels are
assembled in a very short time.
 The individual panels are produced according to
project specifications .
 As a result, all structural dimensions and building
shapes are possible.
CLIMBING FORMWORKS
 It is a special type formwork for vertical
concrete structures that rises with the building
process.
 While relatively complicated and costly, it can be
an effective solution for buildings that are either
very repetitive in form (such as towers or
skyscrapers) or that require a seamless wall
structure .
 Various types of climbing formwork exist, which
are either relocated from time to time, or can
even move on their own (usually on hydraulic
jacks, required for self-climbing and gliding
formworks).
GUIDELINES FOR FORMWORK
 Type of concrete and temperature of the concrete are important for
selecting formwork as they exert pressure.
 The formwork sides must be capable of resisting the hydrostatic
pressure of the wet concrete depending on the rate of setting and
curing.
 The formwork base must be capable of resisting dead and live load
of the wet concrete, workmen and machinery.
 Once the concrete as gained sufficient strength, the formwork can
be removed.
 A minimum of 5 MPa strength of concrete can be achieved
before striking vertical formwork.
 Both shuttering and formwork in its various forms will be
supported by false work.
REQUIREMENTS OF GOOD FORMWORK
 It should be strong enough to carry all types of dead and live
loads.
 It should be rigidly constructed and efficiently propped and
braced both horizontally and vertically,
 The joints in the formwork should be stiff so that the
deformations caused by loads shall be minimum.
 The joints in the formwork should be water tight.
 Construction of formwork should permit removal of various
parts in desired sequences without damage to the concrete.
 The material of the formwork should be cheap, easily available
and should be suitable for reuse.
 The formwork should be set accurately to the desired line and
levels should have plane surface.
 It should be as light as possible.
 The material of the formwork should not warp or get distorted.
MATERIAL SELECTION
 The type of material to be used for formwork depends
upon the nature of construction as well as the availability
and cost of material.
 Formwork can be made out of timber, steel, plywood,
pre-cast concrete or fibre-glass, used separately or in
combination.
 Timber and plywood are the most commonly used
materials for formwork because these can be cut or
assembled easily on site.
 Use of wooden props (ballies) and bamboo props are still
persisting in many construction works.
 With the introduction of steel forms, use of
timber formwork is getting reduced especially in
case of major construction projects.
 Large numbers of re-use of the same forms are
possible then steel, aluminium and plastic forms
are used.
 However, for small works involving less number
of re-uses, timber formwork proves economical.
 Formwork commercially available may be
fabricated at site, or partially or wholly
prefabricated and may be used.
PROCESS INVOLVED IN CONCRETE FORMWORK
 This normally involves the following operations:
 Propping and centring
 Shuttering
 Provision of camber
 Cleaning and surface treatment
TOLERANCE IN SHAPE, LINES & DIMENSIONS
 The formwork shall be designed and constructed
so as to remain sufficiently rigid during placing
and compaction of concrete, and shall be such as
to prevent loss of slurry from the concrete.
 The tolerances on the shapes, lines and
dimensions shown in the drawing shall be within
the limits given in table given in IS 456-2000
CLEANING & TREATMENT OF FORMWORK
 All rubbish, particularly, chippings, shavings and
sawdust, shall be removed from the interior of the
forms before the concrete is placed.
 The face of formwork in contact with the
concrete shall be cleaned and treated with form
release agent.
 Release agents should be applied so as to provide
a thin uniform coating to the forms without
coating the reinforcement.
STRIPPING TIME
Forms shall not be released until the concrete has
achieved a strength of at least twice the stress to
which the concrete may be subjected at the time of
removal of form work.
While the above criteria of strength shall be the
guiding factor for removal of formwork, in normal
circumstances where ambient temperature does not
fall below 150C and where ordinary Portland
cement is used and adequate curing is done,
following stripping period may deem to satisfy the
guideline given in IS 456-2000
STRIPPING TIME
ORDER AND METHOD OF REMOVING FORMWORK
 The sequence of orders and method of removal of
formwork are as follows:
 The vertical faces of walls beams and column sides should
be removed first as they bear no load.
 Shuttering forming soffit of slabs should be removed next.
 Shuttering forming soffit of beams, girders or other heavily
loaded shuttering should be removed in the end.
 Rapid hardening cement, warm weather and light loading
conditions allow early removal of formwork.
 All formworks should be eased gradually and carefully in
order to prevent the load being suddenly transferred to
concrete.
Thank You

More Related Content

What's hot

Finishing works (Building Construction)
Finishing works (Building Construction)Finishing works (Building Construction)
Finishing works (Building Construction)Zairul Zaiky
 
Formwork seminar 2
Formwork seminar 2Formwork seminar 2
Formwork seminar 2Gali Suresh
 
CONSTRUCTION TECHNOLOGY
CONSTRUCTION TECHNOLOGY CONSTRUCTION TECHNOLOGY
CONSTRUCTION TECHNOLOGY VISHNU VIJAYAN
 
MODERN CONSTRUCTION METHODS
MODERN CONSTRUCTION METHODSMODERN CONSTRUCTION METHODS
MODERN CONSTRUCTION METHODSShourya Puri
 
Basic principles of design for rcc building
Basic principles of design for rcc buildingBasic principles of design for rcc building
Basic principles of design for rcc buildinghlksd
 
Form-work in construction
Form-work in construction Form-work in construction
Form-work in construction purvi golecha
 
Construction Methods & Sequence
Construction  Methods & SequenceConstruction  Methods & Sequence
Construction Methods & SequenceDavid H Moloney
 
CONCRETE EQUIPMENTS.pptx
CONCRETE EQUIPMENTS.pptxCONCRETE EQUIPMENTS.pptx
CONCRETE EQUIPMENTS.pptxJanmithRai
 
Construction of substructure
Construction of substructureConstruction of substructure
Construction of substructureguasiya
 
Advances in Concrete Technology
Advances in Concrete TechnologyAdvances in Concrete Technology
Advances in Concrete TechnologyJNTU
 

What's hot (20)

Finishing works (Building Construction)
Finishing works (Building Construction)Finishing works (Building Construction)
Finishing works (Building Construction)
 
Vacuum dewatering
Vacuum dewateringVacuum dewatering
Vacuum dewatering
 
Formwork seminar 2
Formwork seminar 2Formwork seminar 2
Formwork seminar 2
 
CONSTRUCTION TECHNOLOGY
CONSTRUCTION TECHNOLOGY CONSTRUCTION TECHNOLOGY
CONSTRUCTION TECHNOLOGY
 
MODERN CONSTRUCTION METHODS
MODERN CONSTRUCTION METHODSMODERN CONSTRUCTION METHODS
MODERN CONSTRUCTION METHODS
 
Underwater concrete
Underwater concreteUnderwater concrete
Underwater concrete
 
Superstructure construction
Superstructure constructionSuperstructure construction
Superstructure construction
 
Foundation
FoundationFoundation
Foundation
 
Basic principles of design for rcc building
Basic principles of design for rcc buildingBasic principles of design for rcc building
Basic principles of design for rcc building
 
Concrete Mix Design
Concrete Mix DesignConcrete Mix Design
Concrete Mix Design
 
Form-work in construction
Form-work in construction Form-work in construction
Form-work in construction
 
Construction Methods & Sequence
Construction  Methods & SequenceConstruction  Methods & Sequence
Construction Methods & Sequence
 
Types of formwork
Types of formworkTypes of formwork
Types of formwork
 
Polymer concrete
Polymer concretePolymer concrete
Polymer concrete
 
CONCRETE EQUIPMENTS.pptx
CONCRETE EQUIPMENTS.pptxCONCRETE EQUIPMENTS.pptx
CONCRETE EQUIPMENTS.pptx
 
Construction of substructure
Construction of substructureConstruction of substructure
Construction of substructure
 
Formwork
FormworkFormwork
Formwork
 
Construction of diaphragm wall
Construction of diaphragm wallConstruction of diaphragm wall
Construction of diaphragm wall
 
Advances in Concrete Technology
Advances in Concrete TechnologyAdvances in Concrete Technology
Advances in Concrete Technology
 
Test of concrete
Test of concrete Test of concrete
Test of concrete
 

Similar to Formwork For Structural Member.pptx

Formwork construction in structures
Formwork construction in structuresFormwork construction in structures
Formwork construction in structuresRithika Ravishankar
 
form work - Building construction necessities
form work - Building construction necessities  form work - Building construction necessities
form work - Building construction necessities Pradumn Suryakar
 
Chapter 5 formwork
Chapter 5 formworkChapter 5 formwork
Chapter 5 formworkKHUSHBU SHAH
 
Formwork by chakamba john
Formwork by chakamba johnFormwork by chakamba john
Formwork by chakamba johnJohn Chakamba
 
Types of Formwork & Materials.pptx
Types of Formwork & Materials.pptxTypes of Formwork & Materials.pptx
Types of Formwork & Materials.pptxMr Amol Ghogare
 
6. FORMWORK (ACE) 2160601 GTU
6. FORMWORK (ACE) 2160601 GTU6. FORMWORK (ACE) 2160601 GTU
6. FORMWORK (ACE) 2160601 GTUVATSAL PATEL
 
Farmwork shuttering
Farmwork shutteringFarmwork shuttering
Farmwork shutteringKishor Ade
 
formwork Bco (1) final.pdf
formwork Bco (1) final.pdfformwork Bco (1) final.pdf
formwork Bco (1) final.pdfFaizanSolanki
 
Formwork Presentation for Construction Technology
Formwork Presentation for Construction TechnologyFormwork Presentation for Construction Technology
Formwork Presentation for Construction TechnologyI'mMiss Lily
 
Prefabrication & Pre-CASTING, Advanced Structural Concretes Materials for Pre...
Prefabrication & Pre-CASTING, Advanced Structural Concretes Materials for Pre...Prefabrication & Pre-CASTING, Advanced Structural Concretes Materials for Pre...
Prefabrication & Pre-CASTING, Advanced Structural Concretes Materials for Pre...Deepak Verma
 
Masonry special features
Masonry special featuresMasonry special features
Masonry special featuresJitesh Dhule
 
From work & shuttering
From work & shutteringFrom work & shuttering
From work & shutteringhamidgujjar
 
UNIT 2 PREFABRICATION COMPONENTS | CE8022 PREFABRICATED STRUCTURES
UNIT 2 PREFABRICATION COMPONENTS | CE8022 PREFABRICATED STRUCTURESUNIT 2 PREFABRICATION COMPONENTS | CE8022 PREFABRICATED STRUCTURES
UNIT 2 PREFABRICATION COMPONENTS | CE8022 PREFABRICATED STRUCTURESVenkateswaran S
 
Masonry-Special-Features (1).pdf
Masonry-Special-Features (1).pdfMasonry-Special-Features (1).pdf
Masonry-Special-Features (1).pdfAnmolSharma668762
 
Masonry-Special-Features.pdf
Masonry-Special-Features.pdfMasonry-Special-Features.pdf
Masonry-Special-Features.pdfwoanumberdar
 
TIMBER FRAME UPPER FLOOR (1).pptx
TIMBER FRAME  UPPER FLOOR (1).pptxTIMBER FRAME  UPPER FLOOR (1).pptx
TIMBER FRAME UPPER FLOOR (1).pptxChoo Revv
 

Similar to Formwork For Structural Member.pptx (20)

Formwork construction in structures
Formwork construction in structuresFormwork construction in structures
Formwork construction in structures
 
form work - Building construction necessities
form work - Building construction necessities  form work - Building construction necessities
form work - Building construction necessities
 
Chapter 5 formwork
Chapter 5 formworkChapter 5 formwork
Chapter 5 formwork
 
Formwork by chakamba john
Formwork by chakamba johnFormwork by chakamba john
Formwork by chakamba john
 
Types of Formwork & Materials.pptx
Types of Formwork & Materials.pptxTypes of Formwork & Materials.pptx
Types of Formwork & Materials.pptx
 
6. FORMWORK (ACE) 2160601 GTU
6. FORMWORK (ACE) 2160601 GTU6. FORMWORK (ACE) 2160601 GTU
6. FORMWORK (ACE) 2160601 GTU
 
Farmwork shuttering
Farmwork shutteringFarmwork shuttering
Farmwork shuttering
 
formwork Bco (1) final.pdf
formwork Bco (1) final.pdfformwork Bco (1) final.pdf
formwork Bco (1) final.pdf
 
Gurme santoshkumar
Gurme santoshkumarGurme santoshkumar
Gurme santoshkumar
 
Form Work
Form Work Form Work
Form Work
 
Temporary Works (Form Work)
Temporary Works (Form Work)Temporary Works (Form Work)
Temporary Works (Form Work)
 
Formwork Presentation for Construction Technology
Formwork Presentation for Construction TechnologyFormwork Presentation for Construction Technology
Formwork Presentation for Construction Technology
 
Prefabrication & Pre-CASTING, Advanced Structural Concretes Materials for Pre...
Prefabrication & Pre-CASTING, Advanced Structural Concretes Materials for Pre...Prefabrication & Pre-CASTING, Advanced Structural Concretes Materials for Pre...
Prefabrication & Pre-CASTING, Advanced Structural Concretes Materials for Pre...
 
IT PPT(0).pdf
IT PPT(0).pdfIT PPT(0).pdf
IT PPT(0).pdf
 
Masonry special features
Masonry special featuresMasonry special features
Masonry special features
 
From work & shuttering
From work & shutteringFrom work & shuttering
From work & shuttering
 
UNIT 2 PREFABRICATION COMPONENTS | CE8022 PREFABRICATED STRUCTURES
UNIT 2 PREFABRICATION COMPONENTS | CE8022 PREFABRICATED STRUCTURESUNIT 2 PREFABRICATION COMPONENTS | CE8022 PREFABRICATED STRUCTURES
UNIT 2 PREFABRICATION COMPONENTS | CE8022 PREFABRICATED STRUCTURES
 
Masonry-Special-Features (1).pdf
Masonry-Special-Features (1).pdfMasonry-Special-Features (1).pdf
Masonry-Special-Features (1).pdf
 
Masonry-Special-Features.pdf
Masonry-Special-Features.pdfMasonry-Special-Features.pdf
Masonry-Special-Features.pdf
 
TIMBER FRAME UPPER FLOOR (1).pptx
TIMBER FRAME  UPPER FLOOR (1).pptxTIMBER FRAME  UPPER FLOOR (1).pptx
TIMBER FRAME UPPER FLOOR (1).pptx
 

More from Mr Amol Ghogare

2.1 permeability & seepage
2.1 permeability & seepage2.1 permeability & seepage
2.1 permeability & seepageMr Amol Ghogare
 
1.2 soil properties & soil structure
1.2 soil properties & soil structure1.2 soil properties & soil structure
1.2 soil properties & soil structureMr Amol Ghogare
 
Prolems on scale of photograph
Prolems on scale of photographProlems on scale of photograph
Prolems on scale of photographMr Amol Ghogare
 
Scale of photograph (Aerial Photogrammetry)
Scale of photograph (Aerial Photogrammetry)Scale of photograph (Aerial Photogrammetry)
Scale of photograph (Aerial Photogrammetry)Mr Amol Ghogare
 
Flight planning (aerial Photogrammetry)
Flight planning            (aerial Photogrammetry)Flight planning            (aerial Photogrammetry)
Flight planning (aerial Photogrammetry)Mr Amol Ghogare
 
Aerial photogrammetry ppt 2
Aerial photogrammetry ppt 2Aerial photogrammetry ppt 2
Aerial photogrammetry ppt 2Mr Amol Ghogare
 
Aerial photogrammetry ppt 1
Aerial photogrammetry ppt 1Aerial photogrammetry ppt 1
Aerial photogrammetry ppt 1Mr Amol Ghogare
 
Soil Properties & Testing
Soil Properties & TestingSoil Properties & Testing
Soil Properties & TestingMr Amol Ghogare
 
Introduction to Soil Structure
Introduction to Soil StructureIntroduction to Soil Structure
Introduction to Soil StructureMr Amol Ghogare
 

More from Mr Amol Ghogare (15)

3.1 compaction
3.1 compaction3.1 compaction
3.1 compaction
 
2.1 permeability & seepage
2.1 permeability & seepage2.1 permeability & seepage
2.1 permeability & seepage
 
1.2 soil properties & soil structure
1.2 soil properties & soil structure1.2 soil properties & soil structure
1.2 soil properties & soil structure
 
1.1 properties of soil
1.1 properties of soil1.1 properties of soil
1.1 properties of soil
 
Digital photogrammetry
Digital photogrammetryDigital photogrammetry
Digital photogrammetry
 
Stereoscopic parallax
Stereoscopic parallaxStereoscopic parallax
Stereoscopic parallax
 
Types of stereoscope
Types of stereoscopeTypes of stereoscope
Types of stereoscope
 
Relief displacement
Relief displacementRelief displacement
Relief displacement
 
Prolems on scale of photograph
Prolems on scale of photographProlems on scale of photograph
Prolems on scale of photograph
 
Scale of photograph (Aerial Photogrammetry)
Scale of photograph (Aerial Photogrammetry)Scale of photograph (Aerial Photogrammetry)
Scale of photograph (Aerial Photogrammetry)
 
Flight planning (aerial Photogrammetry)
Flight planning            (aerial Photogrammetry)Flight planning            (aerial Photogrammetry)
Flight planning (aerial Photogrammetry)
 
Aerial photogrammetry ppt 2
Aerial photogrammetry ppt 2Aerial photogrammetry ppt 2
Aerial photogrammetry ppt 2
 
Aerial photogrammetry ppt 1
Aerial photogrammetry ppt 1Aerial photogrammetry ppt 1
Aerial photogrammetry ppt 1
 
Soil Properties & Testing
Soil Properties & TestingSoil Properties & Testing
Soil Properties & Testing
 
Introduction to Soil Structure
Introduction to Soil StructureIntroduction to Soil Structure
Introduction to Soil Structure
 

Recently uploaded

Laundry management system project report.pdf
Laundry management system project report.pdfLaundry management system project report.pdf
Laundry management system project report.pdfKamal Acharya
 
2024 DevOps Pro Europe - Growing at the edge
2024 DevOps Pro Europe - Growing at the edge2024 DevOps Pro Europe - Growing at the edge
2024 DevOps Pro Europe - Growing at the edgePaco Orozco
 
HYDROPOWER - Hydroelectric power generation
HYDROPOWER - Hydroelectric power generationHYDROPOWER - Hydroelectric power generation
HYDROPOWER - Hydroelectric power generationRobbie Edward Sayers
 
Quality defects in TMT Bars, Possible causes and Potential Solutions.
Quality defects in TMT Bars, Possible causes and Potential Solutions.Quality defects in TMT Bars, Possible causes and Potential Solutions.
Quality defects in TMT Bars, Possible causes and Potential Solutions.PrashantGoswami42
 
ENERGY STORAGE DEVICES INTRODUCTION UNIT-I
ENERGY STORAGE DEVICES  INTRODUCTION UNIT-IENERGY STORAGE DEVICES  INTRODUCTION UNIT-I
ENERGY STORAGE DEVICES INTRODUCTION UNIT-IVigneshvaranMech
 
Furniture showroom management system project.pdf
Furniture showroom management system project.pdfFurniture showroom management system project.pdf
Furniture showroom management system project.pdfKamal Acharya
 
Architectural Portfolio Sean Lockwood
Architectural Portfolio Sean LockwoodArchitectural Portfolio Sean Lockwood
Architectural Portfolio Sean Lockwoodseandesed
 
Toll tax management system project report..pdf
Toll tax management system project report..pdfToll tax management system project report..pdf
Toll tax management system project report..pdfKamal Acharya
 
Digital Signal Processing Lecture notes n.pdf
Digital Signal Processing Lecture notes n.pdfDigital Signal Processing Lecture notes n.pdf
Digital Signal Processing Lecture notes n.pdfAbrahamGadissa
 
Cloud-Computing_CSE311_Computer-Networking CSE GUB BD - Shahidul.pptx
Cloud-Computing_CSE311_Computer-Networking CSE GUB BD - Shahidul.pptxCloud-Computing_CSE311_Computer-Networking CSE GUB BD - Shahidul.pptx
Cloud-Computing_CSE311_Computer-Networking CSE GUB BD - Shahidul.pptxMd. Shahidul Islam Prodhan
 
Democratizing Fuzzing at Scale by Abhishek Arya
Democratizing Fuzzing at Scale by Abhishek AryaDemocratizing Fuzzing at Scale by Abhishek Arya
Democratizing Fuzzing at Scale by Abhishek Aryaabh.arya
 
Explosives Industry manufacturing process.pdf
Explosives Industry manufacturing process.pdfExplosives Industry manufacturing process.pdf
Explosives Industry manufacturing process.pdf884710SadaqatAli
 
KIT-601 Lecture Notes-UNIT-5.pdf Frame Works and Visualization
KIT-601 Lecture Notes-UNIT-5.pdf Frame Works and VisualizationKIT-601 Lecture Notes-UNIT-5.pdf Frame Works and Visualization
KIT-601 Lecture Notes-UNIT-5.pdf Frame Works and VisualizationDr. Radhey Shyam
 
Scaling in conventional MOSFET for constant electric field and constant voltage
Scaling in conventional MOSFET for constant electric field and constant voltageScaling in conventional MOSFET for constant electric field and constant voltage
Scaling in conventional MOSFET for constant electric field and constant voltageRCC Institute of Information Technology
 
The Ultimate Guide to External Floating Roofs for Oil Storage Tanks.docx
The Ultimate Guide to External Floating Roofs for Oil Storage Tanks.docxThe Ultimate Guide to External Floating Roofs for Oil Storage Tanks.docx
The Ultimate Guide to External Floating Roofs for Oil Storage Tanks.docxCenterEnamel
 
Online resume builder management system project report.pdf
Online resume builder management system project report.pdfOnline resume builder management system project report.pdf
Online resume builder management system project report.pdfKamal Acharya
 
The Benefits and Techniques of Trenchless Pipe Repair.pdf
The Benefits and Techniques of Trenchless Pipe Repair.pdfThe Benefits and Techniques of Trenchless Pipe Repair.pdf
The Benefits and Techniques of Trenchless Pipe Repair.pdfPipe Restoration Solutions
 
Online blood donation management system project.pdf
Online blood donation management system project.pdfOnline blood donation management system project.pdf
Online blood donation management system project.pdfKamal Acharya
 
WATER CRISIS and its solutions-pptx 1234
WATER CRISIS and its solutions-pptx 1234WATER CRISIS and its solutions-pptx 1234
WATER CRISIS and its solutions-pptx 1234AafreenAbuthahir2
 
fundamentals of drawing and isometric and orthographic projection
fundamentals of drawing and isometric and orthographic projectionfundamentals of drawing and isometric and orthographic projection
fundamentals of drawing and isometric and orthographic projectionjeevanprasad8
 

Recently uploaded (20)

Laundry management system project report.pdf
Laundry management system project report.pdfLaundry management system project report.pdf
Laundry management system project report.pdf
 
2024 DevOps Pro Europe - Growing at the edge
2024 DevOps Pro Europe - Growing at the edge2024 DevOps Pro Europe - Growing at the edge
2024 DevOps Pro Europe - Growing at the edge
 
HYDROPOWER - Hydroelectric power generation
HYDROPOWER - Hydroelectric power generationHYDROPOWER - Hydroelectric power generation
HYDROPOWER - Hydroelectric power generation
 
Quality defects in TMT Bars, Possible causes and Potential Solutions.
Quality defects in TMT Bars, Possible causes and Potential Solutions.Quality defects in TMT Bars, Possible causes and Potential Solutions.
Quality defects in TMT Bars, Possible causes and Potential Solutions.
 
ENERGY STORAGE DEVICES INTRODUCTION UNIT-I
ENERGY STORAGE DEVICES  INTRODUCTION UNIT-IENERGY STORAGE DEVICES  INTRODUCTION UNIT-I
ENERGY STORAGE DEVICES INTRODUCTION UNIT-I
 
Furniture showroom management system project.pdf
Furniture showroom management system project.pdfFurniture showroom management system project.pdf
Furniture showroom management system project.pdf
 
Architectural Portfolio Sean Lockwood
Architectural Portfolio Sean LockwoodArchitectural Portfolio Sean Lockwood
Architectural Portfolio Sean Lockwood
 
Toll tax management system project report..pdf
Toll tax management system project report..pdfToll tax management system project report..pdf
Toll tax management system project report..pdf
 
Digital Signal Processing Lecture notes n.pdf
Digital Signal Processing Lecture notes n.pdfDigital Signal Processing Lecture notes n.pdf
Digital Signal Processing Lecture notes n.pdf
 
Cloud-Computing_CSE311_Computer-Networking CSE GUB BD - Shahidul.pptx
Cloud-Computing_CSE311_Computer-Networking CSE GUB BD - Shahidul.pptxCloud-Computing_CSE311_Computer-Networking CSE GUB BD - Shahidul.pptx
Cloud-Computing_CSE311_Computer-Networking CSE GUB BD - Shahidul.pptx
 
Democratizing Fuzzing at Scale by Abhishek Arya
Democratizing Fuzzing at Scale by Abhishek AryaDemocratizing Fuzzing at Scale by Abhishek Arya
Democratizing Fuzzing at Scale by Abhishek Arya
 
Explosives Industry manufacturing process.pdf
Explosives Industry manufacturing process.pdfExplosives Industry manufacturing process.pdf
Explosives Industry manufacturing process.pdf
 
KIT-601 Lecture Notes-UNIT-5.pdf Frame Works and Visualization
KIT-601 Lecture Notes-UNIT-5.pdf Frame Works and VisualizationKIT-601 Lecture Notes-UNIT-5.pdf Frame Works and Visualization
KIT-601 Lecture Notes-UNIT-5.pdf Frame Works and Visualization
 
Scaling in conventional MOSFET for constant electric field and constant voltage
Scaling in conventional MOSFET for constant electric field and constant voltageScaling in conventional MOSFET for constant electric field and constant voltage
Scaling in conventional MOSFET for constant electric field and constant voltage
 
The Ultimate Guide to External Floating Roofs for Oil Storage Tanks.docx
The Ultimate Guide to External Floating Roofs for Oil Storage Tanks.docxThe Ultimate Guide to External Floating Roofs for Oil Storage Tanks.docx
The Ultimate Guide to External Floating Roofs for Oil Storage Tanks.docx
 
Online resume builder management system project report.pdf
Online resume builder management system project report.pdfOnline resume builder management system project report.pdf
Online resume builder management system project report.pdf
 
The Benefits and Techniques of Trenchless Pipe Repair.pdf
The Benefits and Techniques of Trenchless Pipe Repair.pdfThe Benefits and Techniques of Trenchless Pipe Repair.pdf
The Benefits and Techniques of Trenchless Pipe Repair.pdf
 
Online blood donation management system project.pdf
Online blood donation management system project.pdfOnline blood donation management system project.pdf
Online blood donation management system project.pdf
 
WATER CRISIS and its solutions-pptx 1234
WATER CRISIS and its solutions-pptx 1234WATER CRISIS and its solutions-pptx 1234
WATER CRISIS and its solutions-pptx 1234
 
fundamentals of drawing and isometric and orthographic projection
fundamentals of drawing and isometric and orthographic projectionfundamentals of drawing and isometric and orthographic projection
fundamentals of drawing and isometric and orthographic projection
 

Formwork For Structural Member.pptx

  • 1. Formwork & Centering Design -facts and reality Presented by Mr. A.V. Ghogare Department of Civil Engineering, SRES’s Sanjivani College of Engineering, Kopargaon An Autonomous Institute, Dist: Ahmednagar, MH, India
  • 2. FORMWORK FOR STRUCTURAL ELEMENTS  Slab  Beam  Column  Footing  Staircase  Wall
  • 3. SLAB FORMWORK  Slab formwork is designed as per the depth of concrete slab.  The loads on plywood are usually considered as being uniformly distributed over the entire surface of the formwork.  The slab is supported on 25mm thick sheathing laid parallel to the main beams  The sheathing is supported on wooden battens which are laid between the beams.  In order to reduce the deflection, the battens may be propped at middle of the span through joists.
  • 5. BEAM FORMWORK  The side forms of the beam is 30mm thick sheathing while bottom sheathing may be 50 to 70 mm thick.  The ends of the battens are supported on the ledger which is fixed to the cleat throughout the length.  Cleats 100mm X20 to 30mm are fixed to the side forms.  The beam form is supported on a head tree.  The shore or post is connected to head tree through cleats.  At bottom of the shore, two wedges of hard wood are provided over a sole piece.
  • 8. FORMWORK FOR COLUMNS  Sheathing all around the column periphery, 2 Side yoke and end yoke, 4 Wedges, 2 bolts and 4 washers.  Two side yokes are comparatively heavier sections and are connected together by two long bolts of 16mm dia. The sheathing are nailed to the yoke.  Ex. Square, rectangular, circular or any other shape, etc
  • 9. COLUMN FORMWORK  Column forms should be capable of being stripped easily.  In tall forms it is desirable to provided windows at appropriate levels on at least one face to facilitate inspection, concrete placement and vibration.  Any method (standard or patented) such as adjustable clamps, bolts, and purpose made yokes, etc. to hold the panels in place may be used.  The spacing and size of these clamps should depend upon the lateral pressure of fresh concrete.
  • 10.
  • 11. FORMWORK FOR FOUNDATIONS  It depends on whether sides of foundations are vertical or inclined (slopped).  For vertical sides, construct hollow box open at top and bottom as shown in figure.  It should be rigid when filled with concrete.  Ex. Square, rectangular or Box footing, combined footings, Raft foundation, etc  For slopped footing, up to 150-200mm, box is prepared, over which trapezoidal forms should be fixed to provide required slopes.  Yokes of size 75mmX100mm and Bolts are used to secure the boards at suitable interval (300-600mm)
  • 12.
  • 13. WALL FORMWORKS  The boarding may be 40-50mm thick for wall up to 4m height.  The boards are fixed to 50mmX100m posts known as studs, about 0.7 to 1m apart.  Horizontal walling of size 75mm X 100mm are fixed to the post at 1 to 1.25m interval.  The whole assembly is than strutted using 75mmX100mm struts.
  • 15. FORM WORK FOR STAIRS  The sheathing or decking for the deck slab is carried on cross joists which are in turn supported to raking ledgers.  The ledger is generally of 75mm X 100mm size.  The cross joist may be of 50mm X 100mm size.  The riser planks are 40-50mm thick and width equal to the riser.  A stiffener joist of size 50mmX100mm is placed along the middle of the riser planks.
  • 16.
  • 17.
  • 18.
  • 19. FORM WORK FOR TANK WALL
  • 20. MONOLITHIC FORMWORKS  walls, columns, slabs, beams and stairways are realized using the monolithic construction method.  The system offers a suitable and fast solution for forming frequently repetitive floor plans - horizontally or vertically.  The individual panels can be easily moved and transported by hand. Through the use of special wedge couplers, the wall and slab panels are assembled in a very short time.  The individual panels are produced according to project specifications .  As a result, all structural dimensions and building shapes are possible.
  • 21. CLIMBING FORMWORKS  It is a special type formwork for vertical concrete structures that rises with the building process.  While relatively complicated and costly, it can be an effective solution for buildings that are either very repetitive in form (such as towers or skyscrapers) or that require a seamless wall structure .  Various types of climbing formwork exist, which are either relocated from time to time, or can even move on their own (usually on hydraulic jacks, required for self-climbing and gliding formworks).
  • 22. GUIDELINES FOR FORMWORK  Type of concrete and temperature of the concrete are important for selecting formwork as they exert pressure.  The formwork sides must be capable of resisting the hydrostatic pressure of the wet concrete depending on the rate of setting and curing.  The formwork base must be capable of resisting dead and live load of the wet concrete, workmen and machinery.  Once the concrete as gained sufficient strength, the formwork can be removed.  A minimum of 5 MPa strength of concrete can be achieved before striking vertical formwork.  Both shuttering and formwork in its various forms will be supported by false work.
  • 23. REQUIREMENTS OF GOOD FORMWORK  It should be strong enough to carry all types of dead and live loads.  It should be rigidly constructed and efficiently propped and braced both horizontally and vertically,  The joints in the formwork should be stiff so that the deformations caused by loads shall be minimum.  The joints in the formwork should be water tight.  Construction of formwork should permit removal of various parts in desired sequences without damage to the concrete.  The material of the formwork should be cheap, easily available and should be suitable for reuse.  The formwork should be set accurately to the desired line and levels should have plane surface.  It should be as light as possible.  The material of the formwork should not warp or get distorted.
  • 24. MATERIAL SELECTION  The type of material to be used for formwork depends upon the nature of construction as well as the availability and cost of material.  Formwork can be made out of timber, steel, plywood, pre-cast concrete or fibre-glass, used separately or in combination.  Timber and plywood are the most commonly used materials for formwork because these can be cut or assembled easily on site.  Use of wooden props (ballies) and bamboo props are still persisting in many construction works.
  • 25.  With the introduction of steel forms, use of timber formwork is getting reduced especially in case of major construction projects.  Large numbers of re-use of the same forms are possible then steel, aluminium and plastic forms are used.  However, for small works involving less number of re-uses, timber formwork proves economical.  Formwork commercially available may be fabricated at site, or partially or wholly prefabricated and may be used.
  • 26. PROCESS INVOLVED IN CONCRETE FORMWORK  This normally involves the following operations:  Propping and centring  Shuttering  Provision of camber  Cleaning and surface treatment
  • 27. TOLERANCE IN SHAPE, LINES & DIMENSIONS  The formwork shall be designed and constructed so as to remain sufficiently rigid during placing and compaction of concrete, and shall be such as to prevent loss of slurry from the concrete.  The tolerances on the shapes, lines and dimensions shown in the drawing shall be within the limits given in table given in IS 456-2000
  • 28.
  • 29. CLEANING & TREATMENT OF FORMWORK  All rubbish, particularly, chippings, shavings and sawdust, shall be removed from the interior of the forms before the concrete is placed.  The face of formwork in contact with the concrete shall be cleaned and treated with form release agent.  Release agents should be applied so as to provide a thin uniform coating to the forms without coating the reinforcement.
  • 30. STRIPPING TIME Forms shall not be released until the concrete has achieved a strength of at least twice the stress to which the concrete may be subjected at the time of removal of form work. While the above criteria of strength shall be the guiding factor for removal of formwork, in normal circumstances where ambient temperature does not fall below 150C and where ordinary Portland cement is used and adequate curing is done, following stripping period may deem to satisfy the guideline given in IS 456-2000
  • 32. ORDER AND METHOD OF REMOVING FORMWORK  The sequence of orders and method of removal of formwork are as follows:  The vertical faces of walls beams and column sides should be removed first as they bear no load.  Shuttering forming soffit of slabs should be removed next.  Shuttering forming soffit of beams, girders or other heavily loaded shuttering should be removed in the end.  Rapid hardening cement, warm weather and light loading conditions allow early removal of formwork.  All formworks should be eased gradually and carefully in order to prevent the load being suddenly transferred to concrete.