SlideShare a Scribd company logo
Prepared by
Prof. Ashish Makwana
Civil Engineering Dept. - MEFGI
1Prof. Ashish Makwana
2Prof. Ashish Makwana
PRESENTATION
OUTLINE…
• Form work for R.C.C. wall, slab, beam &
column
• Centering for arches of large spans and dams
• Design features for temporary works
• Slip formwork
• False work for Bridges
3Prof. Ashish Makwana
FORM WORK
• The form work is a temporary ancillary construction
used as a mould for the structure, in which concrete
is placed and in which it hardens and matures.
• Cost of form work- 20 to 25 % of the cost of
structure in building work
4Prof. Ashish Makwana
FORMWORK FOR CONCRETE
STRUCTURES SHOULD BE
• Strong enough to resist the pressure or the weight
of the fresh concrete plus any constructional live
loads.
• Rigid enough to retain the shape without undue
deformation.
• Economical in terms of the total cost of the forms
and the concrete surface finishing when required.
• Sufficiently watertight to avoid leakage at the
joints.
5Prof. Ashish Makwana
6Prof. Ashish Makwana
7Prof. Ashish Makwana
FORMWORK ECONOMY
• Design the formwork to provide adequate but not
excessive strength and rigidity.
• Fabricate the forms into modular sizes to provide
more reuses without refabricating when practical.
• Prepare working drawings prior to fabricating the
forms.
• Prefabricate form sections on the ground rather than
on scaffolding.
• Use the most economical formwork material
considering the initial cost and reuses.
8Prof. Ashish Makwana
FORMWORK ECONOMY (continued..)
• Use no more nails than are needed to join the forms
together safely.
• Remove the formwork as soon as it is permissible.
• Clean and oil forms by using releasing agent after
each use.
• When it is permissible install construction joins to
reduce the total quantity of form material required
and permit the carpenters to work more
continuously.
9Prof. Ashish Makwana
FORMWORK MATERIALS
1. Timber 2. Metals 3. Plastics
10Prof. Ashish Makwana
FORMWORK TYPES (BY SHAPE)
11
Wall Formwork Slab Formwork
Beam formwork
Column
Formwork
Prof. Ashish Makwana
12
FORM WORK FOR R.C.C. WALL
Prof. Ashish Makwana
FORM WORK FOR
R.C.C. WALL
13Prof. Ashish Makwana
FORM WORK FOR R.C.C. WALL
• Wall formwork is a simpler than for other concrete
units as the actual forces against it are less, most of
the load being carried vertically downwards.
• The panels at both sides are held in position by
ties.
• Ties are also used as spacer, arranging wall
thickness.
• WaII support systems are usually sloping props
at satisfactory intervals.
14Prof. Ashish Makwana
15
FORM WORK FOR COLUMN
Prof. Ashish Makwana
FORM WORK FOR COLUMN
• Column formwork is made usually with either timber
or metal panels.
• The principle is to create an enclosed box with
frames at the exact size of the column and fix it
tightly on the kicker left from base or at the last
stage of column concreting.
• The box is held in position by steel column clamps
or bolted yokes and supported by timber studs or
props.
16Prof. Ashish Makwana
17
FORM WORK FOR R.C.C. SLAB
Prof. Ashish Makwana
FORM WORK FOR
R.C.C. SLAB
• Floors require a large area of formwork to be
provided usually from beam to beam.
• Timber floor formwork consists of timber boards or
plywood sheets supported on a framework and
resting on a series of timber joists.
• Again timber and metal props can be used for
vertical supports.
• Metal panels can be used and bolted or clipped
together and held in place by a system of metal
beams or a tabular scaffold system.
• Adjustable props need for levelling purposes.
18Prof. Ashish Makwana
19
FORMWORK FOR R.C.C. BEAM
Prof. Ashish Makwana
FORM WORK FOR
R.C.C. BEAM
• Beam formwork consists of open through section
and because it is not closed at the top requires
more supporting framework to restrain the sides.
• The supports need to be maintained to the soffit and
also provide lateral support to the sides.
• In timber this is done by the use of a headtree
across the top of a vertical member.
• Metal panels are used with corner pieces, but
timber headtrees are needed for vertical support.
20Prof. Ashish Makwana
No Description of structural member
Period of
time
1
Walls, columns and vertical sides of
beams
1 to 2 days
2 Slabs (props left under) 3 days
3 Beam soffits (props left under) 7 days
4
Removal of props to slabs
(a) For slabs spanning upto 4.5 m 7 days
(b) For slabs spanning over 4.5 m 14 days
5
Removal of props to beams and arches
(a) Spanning upto 6 m 14 days
(b) spanning over 6 m 21 days
21
Table 1: Period of removal of formwork
Prof. Ashish Makwana
CENTERING FOR ARCHES OF
LARGE SPANS AND DAMS
• Centering is a type of falsework: the temporary
structure upon which the stones of an arch are laid
during construction.
• Once the arch is complete, it supports itself, but until
the keystone is inserted, it has no strength and
needs the centering to keep the voussoirs in their
correct relative positions.
• A simple centering without a truss is called a
common centering. The cross piece connecting
centering frames are called a lag.
22Prof. Ashish Makwana
23
The original Blackfriars Bridge, London,
under construction in 1764
Prof. Ashish Makwana
DESIGN FEATURES FOR
TEMPORARY WORKS
• Strength: Forms and shutters have to be designed
to support dead weight, live load and hydrostatic
pressure. Sheathing must be rigid enough to resist
bulging.
• Speedy erection and dismantling: The formwork sho
uld be simple to remove without causing damage to
the concrete.
• Tightness of joints: The liquid retaining properties
the formwork must be adequate to prevent leakage
of cement and fine aggregate from the concrete.
24Prof. Ashish Makwana
DESIGN FEATURES FOR TEMPORARY WORKS (continued..)
• Rigidity: Brace formwork and support to ensure
no movement may take place under wind pressure,
or when the concrete is being placed and vibrated.
• Ease of handling: Forms and shutters must be of a
size and weight that can be handled by the labour
and plant available on site.
• Removal of debris: Provide all formwork with special
cleanout holes to allow for the removal of sawdust, s
havings, and other debris from the bottom of the for
mwork before the pour begins.
25Prof. Ashish Makwana
DESIGN FEATURES FOR TEMPORARY WORKS (continued..)
• Reuse:
– Design for unit construction, if possible, so that
at you can strike and reuse as soon as possible.
– Use clamps, wedges, and similar devices to hold
sections of formwork in place.
– Avoid nailing as much as possible, nail holes and
bruising of the timber will spoil
formwork for further use.
– The formwork material must be durable and capa
ble of producing a good surface finish.
26Prof. Ashish Makwana
SLIP FORMWORK
• This is a form which is continually being moved
upwards, or sideways, as the concrete is being
poured.
• The rate of movement is regulated so that the forms
leave the concrete only after it is strong enough to
retain its shape and support the weights imposed on
it.
• Vertical structures such as chimneys (Huntly Power
Station) and cooling towers (Ohaaki Thermal Power
Station) are often done this way.
27Prof. Ashish Makwana
28
SLIP FORMWORK
Prof. Ashish Makwana
29
SLIP FORMWORK
Prof. Ashish Makwana
FALSEWORK FOR BRIDGES
• Falsework is temporary structure or framework used
in construction to support materials, equipment, or
formwork.
• Most falsework is vertical, supporting beams and
slabs. Falsework must be engineer designed.
• As well as supporting the weight, allowance must
made for sideway pressures such as wind, stacks
materials causing eccentric loading, props out of
plumb, formwork being struck by machinery or crane
loads.
30Prof. Ashish Makwana
FALSE WORK FOR BRIDGES (continued..)
• Falsework can be:
– timber;
– scaffold tube with adjustable screw jacks, top or
bottom, or both;
– proprietary prop such as Acrow prop;
– proprietary braced frame such as Acrow shore;
– proprietary floor centre (a telescopic beam);
– proprietary beam clamps such as Acrow beam
clamp which combines formwork and falsework.
31Prof. Ashish Makwana
FALSE WORK FOR BRIDGES (continued..)
SETTING UP FALSEWORK
• Base must be level and firm. A sole plate is
preferable.
• Props and frames must be placed as per design.
• Place props centrally under members
• Brace falsework in two directions
• Floor centres must have full bearing for the end
tongues.
• Beams must be centred over props to prevent
eccentric (out of line) loading.
32Prof. Ashish Makwana
33
FALSEWORK
Prof. Ashish Makwana
THANK YOU
34Prof. Ashish Makwana

More Related Content

What's hot

Slipform construction
Slipform constructionSlipform construction
Slipform construction
tivar rose
 
flexural behaviour of ferrocement
flexural behaviour of ferrocementflexural behaviour of ferrocement
flexural behaviour of ferrocement
swapna porandla
 
Steel formwork
Steel formworkSteel formwork
Steel formwork
Musahiddin Md Zainal
 
Chapter 5 formwork
Chapter 5 formworkChapter 5 formwork
Chapter 5 formwork
KHUSHBU SHAH
 
Construction Project Management
Construction Project ManagementConstruction Project Management
Construction Project Management
johnkirth1898
 
Construction Failure
Construction FailureConstruction Failure
Construction Failure
Thananchayan Theivendra
 
Formwork Presentation for Construction Technology
Formwork Presentation for Construction TechnologyFormwork Presentation for Construction Technology
Formwork Presentation for Construction Technology
I'mMiss Lily
 
Form-work in construction
Form-work in construction Form-work in construction
Form-work in construction
purvi golecha
 
Formwork
FormworkFormwork
Formwork
Shakil Ahmmad
 
Dampness in buildings
Dampness in buildingsDampness in buildings
Dampness in buildings
Ashar Gill
 
Construction Project Management
Construction Project ManagementConstruction Project Management
Construction Project Management
Aravind Samala
 
Formwork
FormworkFormwork
Formwork
natesh0142
 
Precast concrete
Precast concretePrecast concrete
Precast concrete
SnehaKothari13
 
Maintenance and repair of buildings.
Maintenance and repair of buildings.Maintenance and repair of buildings.
Maintenance and repair of buildings.Satyaki Sikdar
 
Vacuum dewatering
Vacuum dewateringVacuum dewatering
Vacuum dewatering
Aglaia Connect
 
Detailed specifications
Detailed specificationsDetailed specifications
Detailed specifications
Simran Vats
 
Diaphragm wall construction
Diaphragm wall constructionDiaphragm wall construction
Diaphragm wall construction
ANILKUMARMUCHINTALA
 
Formwork, by prof. sagar raut
Formwork, by prof. sagar rautFormwork, by prof. sagar raut
Formwork, by prof. sagar raut
SAGAR RAUT
 
Defects in plastering
Defects in plasteringDefects in plastering
Defects in plastering
SAIYYED AKABARALI MOHAMMAD
 

What's hot (20)

Slipform construction
Slipform constructionSlipform construction
Slipform construction
 
flexural behaviour of ferrocement
flexural behaviour of ferrocementflexural behaviour of ferrocement
flexural behaviour of ferrocement
 
Steel formwork
Steel formworkSteel formwork
Steel formwork
 
Chapter 5 formwork
Chapter 5 formworkChapter 5 formwork
Chapter 5 formwork
 
Construction Project Management
Construction Project ManagementConstruction Project Management
Construction Project Management
 
Construction Failure
Construction FailureConstruction Failure
Construction Failure
 
Formwork Presentation for Construction Technology
Formwork Presentation for Construction TechnologyFormwork Presentation for Construction Technology
Formwork Presentation for Construction Technology
 
Form-work in construction
Form-work in construction Form-work in construction
Form-work in construction
 
Formwork
FormworkFormwork
Formwork
 
Dampness in buildings
Dampness in buildingsDampness in buildings
Dampness in buildings
 
Construction Project Management
Construction Project ManagementConstruction Project Management
Construction Project Management
 
Formwork
FormworkFormwork
Formwork
 
Precast concrete
Precast concretePrecast concrete
Precast concrete
 
Maintenance and repair of buildings.
Maintenance and repair of buildings.Maintenance and repair of buildings.
Maintenance and repair of buildings.
 
Vacuum dewatering
Vacuum dewateringVacuum dewatering
Vacuum dewatering
 
Detailed specifications
Detailed specificationsDetailed specifications
Detailed specifications
 
Formwork
FormworkFormwork
Formwork
 
Diaphragm wall construction
Diaphragm wall constructionDiaphragm wall construction
Diaphragm wall construction
 
Formwork, by prof. sagar raut
Formwork, by prof. sagar rautFormwork, by prof. sagar raut
Formwork, by prof. sagar raut
 
Defects in plastering
Defects in plasteringDefects in plastering
Defects in plastering
 

Similar to Form work_Advanced Construction Technology (Semester-6), Civil Engineering

CHE :- 6 form work (MODULE 3)
CHE :- 6 form work (MODULE 3)CHE :- 6 form work (MODULE 3)
Tony
TonyTony
Tony
TONY ROSE
 
Caissons_Advanced Construction Technology (Semester-6), Civil Engineering
Caissons_Advanced Construction Technology (Semester-6), Civil EngineeringCaissons_Advanced Construction Technology (Semester-6), Civil Engineering
Caissons_Advanced Construction Technology (Semester-6), Civil Engineering
A Makwana
 
Trussed tube
Trussed tubeTrussed tube
Trussed tube
Rifquth sb
 
Bridges in Hilly areas seminar
Bridges in Hilly areas seminarBridges in Hilly areas seminar
Bridges in Hilly areas seminar
Abhinav Pateriya
 
TYPES OF FORMWORK AND THEIR APPLICATION.
TYPES OF FORMWORK AND THEIR APPLICATION. TYPES OF FORMWORK AND THEIR APPLICATION.
TYPES OF FORMWORK AND THEIR APPLICATION.
ARKALGUD NARASIMHA PRAKASH
 
Analysisanddesignofamulti storey staad pro.
Analysisanddesignofamulti storey staad pro.Analysisanddesignofamulti storey staad pro.
Analysisanddesignofamulti storey staad pro.
CADmantra Technologies
 
Connections of earthquake resisting precast reinforced concrete building(en n...
Connections of earthquake resisting precast reinforced concrete building(en n...Connections of earthquake resisting precast reinforced concrete building(en n...
Connections of earthquake resisting precast reinforced concrete building(en n...
Dhamu Vankar
 
REINFORCED CEMENT CONCRETE
REINFORCED CEMENT CONCRETEREINFORCED CEMENT CONCRETE
REINFORCED CEMENT CONCRETE
Brijesh Alig
 
Box Pushing Technique
Box Pushing TechniqueBox Pushing Technique
Box Pushing Technique
Seminar Links
 
Design highrise
Design highriseDesign highrise
Design highrise
Somyaa Jain
 
report-on-emmar.docx13
report-on-emmar.docx13report-on-emmar.docx13
report-on-emmar.docx13Minhal Haider
 
Pile foundations_Advanced Construction Technology
Pile foundations_Advanced Construction TechnologyPile foundations_Advanced Construction Technology
Pile foundations_Advanced Construction Technology
A Makwana
 
form work-converted pppt new-converted.pdf
form work-converted pppt new-converted.pdfform work-converted pppt new-converted.pdf
form work-converted pppt new-converted.pdf
xmYHlg
 
STRUCTURE ANALYSIS-1 structural elements.pptx
STRUCTURE ANALYSIS-1 structural elements.pptxSTRUCTURE ANALYSIS-1 structural elements.pptx
STRUCTURE ANALYSIS-1 structural elements.pptx
MuhammadRamzan757427
 
Tensile structures for architects
Tensile structures for architectsTensile structures for architects
Tensile structures for architects
Deepak KUMAR
 
SEMINAR PRESENTATION ON BOX CULVERTS
SEMINAR PRESENTATION ON  BOX CULVERTSSEMINAR PRESENTATION ON  BOX CULVERTS
SEMINAR PRESENTATION ON BOX CULVERTS
srinivas cnu
 
Basic structure
Basic structureBasic structure
Basic structure
Sumaiya Islam
 
Well foundation
Well foundationWell foundation
Form Work
Form Work Form Work
Form Work
Kezar Ali. Shah
 

Similar to Form work_Advanced Construction Technology (Semester-6), Civil Engineering (20)

CHE :- 6 form work (MODULE 3)
CHE :- 6 form work (MODULE 3)CHE :- 6 form work (MODULE 3)
CHE :- 6 form work (MODULE 3)
 
Tony
TonyTony
Tony
 
Caissons_Advanced Construction Technology (Semester-6), Civil Engineering
Caissons_Advanced Construction Technology (Semester-6), Civil EngineeringCaissons_Advanced Construction Technology (Semester-6), Civil Engineering
Caissons_Advanced Construction Technology (Semester-6), Civil Engineering
 
Trussed tube
Trussed tubeTrussed tube
Trussed tube
 
Bridges in Hilly areas seminar
Bridges in Hilly areas seminarBridges in Hilly areas seminar
Bridges in Hilly areas seminar
 
TYPES OF FORMWORK AND THEIR APPLICATION.
TYPES OF FORMWORK AND THEIR APPLICATION. TYPES OF FORMWORK AND THEIR APPLICATION.
TYPES OF FORMWORK AND THEIR APPLICATION.
 
Analysisanddesignofamulti storey staad pro.
Analysisanddesignofamulti storey staad pro.Analysisanddesignofamulti storey staad pro.
Analysisanddesignofamulti storey staad pro.
 
Connections of earthquake resisting precast reinforced concrete building(en n...
Connections of earthquake resisting precast reinforced concrete building(en n...Connections of earthquake resisting precast reinforced concrete building(en n...
Connections of earthquake resisting precast reinforced concrete building(en n...
 
REINFORCED CEMENT CONCRETE
REINFORCED CEMENT CONCRETEREINFORCED CEMENT CONCRETE
REINFORCED CEMENT CONCRETE
 
Box Pushing Technique
Box Pushing TechniqueBox Pushing Technique
Box Pushing Technique
 
Design highrise
Design highriseDesign highrise
Design highrise
 
report-on-emmar.docx13
report-on-emmar.docx13report-on-emmar.docx13
report-on-emmar.docx13
 
Pile foundations_Advanced Construction Technology
Pile foundations_Advanced Construction TechnologyPile foundations_Advanced Construction Technology
Pile foundations_Advanced Construction Technology
 
form work-converted pppt new-converted.pdf
form work-converted pppt new-converted.pdfform work-converted pppt new-converted.pdf
form work-converted pppt new-converted.pdf
 
STRUCTURE ANALYSIS-1 structural elements.pptx
STRUCTURE ANALYSIS-1 structural elements.pptxSTRUCTURE ANALYSIS-1 structural elements.pptx
STRUCTURE ANALYSIS-1 structural elements.pptx
 
Tensile structures for architects
Tensile structures for architectsTensile structures for architects
Tensile structures for architects
 
SEMINAR PRESENTATION ON BOX CULVERTS
SEMINAR PRESENTATION ON  BOX CULVERTSSEMINAR PRESENTATION ON  BOX CULVERTS
SEMINAR PRESENTATION ON BOX CULVERTS
 
Basic structure
Basic structureBasic structure
Basic structure
 
Well foundation
Well foundationWell foundation
Well foundation
 
Form Work
Form Work Form Work
Form Work
 

More from A Makwana

Attributes affecting success of the residential projects – a review
Attributes affecting success of the residential projects – a reviewAttributes affecting success of the residential projects – a review
Attributes affecting success of the residential projects – a review
A Makwana
 
A Review on Thin-shell Structures: Advances and Trends
A Review on Thin-shell Structures: Advances and TrendsA Review on Thin-shell Structures: Advances and Trends
A Review on Thin-shell Structures: Advances and Trends
A Makwana
 
Soft Computing: Autoclaved Aerated Concrete Block using Chi-Square Test throu...
Soft Computing: Autoclaved Aerated Concrete Block using Chi-Square Test throu...Soft Computing: Autoclaved Aerated Concrete Block using Chi-Square Test throu...
Soft Computing: Autoclaved Aerated Concrete Block using Chi-Square Test throu...
A Makwana
 
Structural clay products (Conventional & Fly ash bricks)
Structural clay products (Conventional & Fly ash bricks)Structural clay products (Conventional & Fly ash bricks)
Structural clay products (Conventional & Fly ash bricks)
A Makwana
 
Poster Presentation: An Integrated Approach for Enhancing Ready Mixed Concret...
Poster Presentation: An Integrated Approach for Enhancing Ready Mixed Concret...Poster Presentation: An Integrated Approach for Enhancing Ready Mixed Concret...
Poster Presentation: An Integrated Approach for Enhancing Ready Mixed Concret...
A Makwana
 
Economical Concrete
Economical ConcreteEconomical Concrete
Economical Concrete
A Makwana
 
Bacterial Concrete
Bacterial ConcreteBacterial Concrete
Bacterial Concrete
A Makwana
 
Risk in PPP Projects
Risk in PPP ProjectsRisk in PPP Projects
Risk in PPP Projects
A Makwana
 
Eco-Friendly Mortar
Eco-Friendly MortarEco-Friendly Mortar
Eco-Friendly Mortar
A Makwana
 
Risk Management: High Rise Construction
Risk Management: High Rise ConstructionRisk Management: High Rise Construction
Risk Management: High Rise Construction
A Makwana
 
Infrastructure Engineering & Management
Infrastructure Engineering & ManagementInfrastructure Engineering & Management
Infrastructure Engineering & Management
A Makwana
 
Utilization of Industrial Waste in Pervious Concrete
Utilization of Industrial Waste in Pervious ConcreteUtilization of Industrial Waste in Pervious Concrete
Utilization of Industrial Waste in Pervious Concrete
A Makwana
 
Application of Graphs through MS Excel & MATLAB for Research work
Application of Graphs through MS Excel & MATLAB for Research workApplication of Graphs through MS Excel & MATLAB for Research work
Application of Graphs through MS Excel & MATLAB for Research work
A Makwana
 
Ready Mixed Concrete Selection through Management Approach
Ready Mixed Concrete Selection through Management ApproachReady Mixed Concrete Selection through Management Approach
Ready Mixed Concrete Selection through Management Approach
A Makwana
 
FACTORS CONTRIBUTING TO THE RISING IMPORTANCE OF MODULAR CONSTRUCTION ADOPTIO...
FACTORS CONTRIBUTING TO THE RISING IMPORTANCE OF MODULAR CONSTRUCTION ADOPTIO...FACTORS CONTRIBUTING TO THE RISING IMPORTANCE OF MODULAR CONSTRUCTION ADOPTIO...
FACTORS CONTRIBUTING TO THE RISING IMPORTANCE OF MODULAR CONSTRUCTION ADOPTIO...
A Makwana
 
EXPANSION JOINT TREATMENT: MATERIAL & TECHNIQUES
EXPANSION JOINT TREATMENT: MATERIAL & TECHNIQUESEXPANSION JOINT TREATMENT: MATERIAL & TECHNIQUES
EXPANSION JOINT TREATMENT: MATERIAL & TECHNIQUES
A Makwana
 
DEMOLITION OF BUILDINGS: INTEGRATED NOVEL APPROACH
DEMOLITION OF BUILDINGS: INTEGRATED NOVEL APPROACHDEMOLITION OF BUILDINGS: INTEGRATED NOVEL APPROACH
DEMOLITION OF BUILDINGS: INTEGRATED NOVEL APPROACH
A Makwana
 
ANTI-TERMITE TREATMENT: NEED OF CONSTRUCTION INDUSTRY
ANTI-TERMITE TREATMENT: NEED OF CONSTRUCTION INDUSTRYANTI-TERMITE TREATMENT: NEED OF CONSTRUCTION INDUSTRY
ANTI-TERMITE TREATMENT: NEED OF CONSTRUCTION INDUSTRY
A Makwana
 
INTELLIGENT BUILDING NEW ERA OF TODAYS WORLD
INTELLIGENT BUILDING NEW ERA OF TODAYS WORLDINTELLIGENT BUILDING NEW ERA OF TODAYS WORLD
INTELLIGENT BUILDING NEW ERA OF TODAYS WORLD
A Makwana
 
POSTER PRESENTATION_BRICKS SELECTION THROUGH MANAGEMENT APPROACH BY AHP, RII,...
POSTER PRESENTATION_BRICKS SELECTION THROUGH MANAGEMENT APPROACH BY AHP, RII,...POSTER PRESENTATION_BRICKS SELECTION THROUGH MANAGEMENT APPROACH BY AHP, RII,...
POSTER PRESENTATION_BRICKS SELECTION THROUGH MANAGEMENT APPROACH BY AHP, RII,...
A Makwana
 

More from A Makwana (20)

Attributes affecting success of the residential projects – a review
Attributes affecting success of the residential projects – a reviewAttributes affecting success of the residential projects – a review
Attributes affecting success of the residential projects – a review
 
A Review on Thin-shell Structures: Advances and Trends
A Review on Thin-shell Structures: Advances and TrendsA Review on Thin-shell Structures: Advances and Trends
A Review on Thin-shell Structures: Advances and Trends
 
Soft Computing: Autoclaved Aerated Concrete Block using Chi-Square Test throu...
Soft Computing: Autoclaved Aerated Concrete Block using Chi-Square Test throu...Soft Computing: Autoclaved Aerated Concrete Block using Chi-Square Test throu...
Soft Computing: Autoclaved Aerated Concrete Block using Chi-Square Test throu...
 
Structural clay products (Conventional & Fly ash bricks)
Structural clay products (Conventional & Fly ash bricks)Structural clay products (Conventional & Fly ash bricks)
Structural clay products (Conventional & Fly ash bricks)
 
Poster Presentation: An Integrated Approach for Enhancing Ready Mixed Concret...
Poster Presentation: An Integrated Approach for Enhancing Ready Mixed Concret...Poster Presentation: An Integrated Approach for Enhancing Ready Mixed Concret...
Poster Presentation: An Integrated Approach for Enhancing Ready Mixed Concret...
 
Economical Concrete
Economical ConcreteEconomical Concrete
Economical Concrete
 
Bacterial Concrete
Bacterial ConcreteBacterial Concrete
Bacterial Concrete
 
Risk in PPP Projects
Risk in PPP ProjectsRisk in PPP Projects
Risk in PPP Projects
 
Eco-Friendly Mortar
Eco-Friendly MortarEco-Friendly Mortar
Eco-Friendly Mortar
 
Risk Management: High Rise Construction
Risk Management: High Rise ConstructionRisk Management: High Rise Construction
Risk Management: High Rise Construction
 
Infrastructure Engineering & Management
Infrastructure Engineering & ManagementInfrastructure Engineering & Management
Infrastructure Engineering & Management
 
Utilization of Industrial Waste in Pervious Concrete
Utilization of Industrial Waste in Pervious ConcreteUtilization of Industrial Waste in Pervious Concrete
Utilization of Industrial Waste in Pervious Concrete
 
Application of Graphs through MS Excel & MATLAB for Research work
Application of Graphs through MS Excel & MATLAB for Research workApplication of Graphs through MS Excel & MATLAB for Research work
Application of Graphs through MS Excel & MATLAB for Research work
 
Ready Mixed Concrete Selection through Management Approach
Ready Mixed Concrete Selection through Management ApproachReady Mixed Concrete Selection through Management Approach
Ready Mixed Concrete Selection through Management Approach
 
FACTORS CONTRIBUTING TO THE RISING IMPORTANCE OF MODULAR CONSTRUCTION ADOPTIO...
FACTORS CONTRIBUTING TO THE RISING IMPORTANCE OF MODULAR CONSTRUCTION ADOPTIO...FACTORS CONTRIBUTING TO THE RISING IMPORTANCE OF MODULAR CONSTRUCTION ADOPTIO...
FACTORS CONTRIBUTING TO THE RISING IMPORTANCE OF MODULAR CONSTRUCTION ADOPTIO...
 
EXPANSION JOINT TREATMENT: MATERIAL & TECHNIQUES
EXPANSION JOINT TREATMENT: MATERIAL & TECHNIQUESEXPANSION JOINT TREATMENT: MATERIAL & TECHNIQUES
EXPANSION JOINT TREATMENT: MATERIAL & TECHNIQUES
 
DEMOLITION OF BUILDINGS: INTEGRATED NOVEL APPROACH
DEMOLITION OF BUILDINGS: INTEGRATED NOVEL APPROACHDEMOLITION OF BUILDINGS: INTEGRATED NOVEL APPROACH
DEMOLITION OF BUILDINGS: INTEGRATED NOVEL APPROACH
 
ANTI-TERMITE TREATMENT: NEED OF CONSTRUCTION INDUSTRY
ANTI-TERMITE TREATMENT: NEED OF CONSTRUCTION INDUSTRYANTI-TERMITE TREATMENT: NEED OF CONSTRUCTION INDUSTRY
ANTI-TERMITE TREATMENT: NEED OF CONSTRUCTION INDUSTRY
 
INTELLIGENT BUILDING NEW ERA OF TODAYS WORLD
INTELLIGENT BUILDING NEW ERA OF TODAYS WORLDINTELLIGENT BUILDING NEW ERA OF TODAYS WORLD
INTELLIGENT BUILDING NEW ERA OF TODAYS WORLD
 
POSTER PRESENTATION_BRICKS SELECTION THROUGH MANAGEMENT APPROACH BY AHP, RII,...
POSTER PRESENTATION_BRICKS SELECTION THROUGH MANAGEMENT APPROACH BY AHP, RII,...POSTER PRESENTATION_BRICKS SELECTION THROUGH MANAGEMENT APPROACH BY AHP, RII,...
POSTER PRESENTATION_BRICKS SELECTION THROUGH MANAGEMENT APPROACH BY AHP, RII,...
 

Recently uploaded

一比一原版(IIT毕业证)伊利诺伊理工大学毕业证成绩单专业办理
一比一原版(IIT毕业证)伊利诺伊理工大学毕业证成绩单专业办理一比一原版(IIT毕业证)伊利诺伊理工大学毕业证成绩单专业办理
一比一原版(IIT毕业证)伊利诺伊理工大学毕业证成绩单专业办理
zwunae
 
Planning Of Procurement o different goods and services
Planning Of Procurement o different goods and servicesPlanning Of Procurement o different goods and services
Planning Of Procurement o different goods and services
JoytuBarua2
 
Understanding Inductive Bias in Machine Learning
Understanding Inductive Bias in Machine LearningUnderstanding Inductive Bias in Machine Learning
Understanding Inductive Bias in Machine Learning
SUTEJAS
 
AKS UNIVERSITY Satna Final Year Project By OM Hardaha.pdf
AKS UNIVERSITY Satna Final Year Project By OM Hardaha.pdfAKS UNIVERSITY Satna Final Year Project By OM Hardaha.pdf
AKS UNIVERSITY Satna Final Year Project By OM Hardaha.pdf
SamSarthak3
 
一比一原版(UofT毕业证)多伦多大学毕业证成绩单如何办理
一比一原版(UofT毕业证)多伦多大学毕业证成绩单如何办理一比一原版(UofT毕业证)多伦多大学毕业证成绩单如何办理
一比一原版(UofT毕业证)多伦多大学毕业证成绩单如何办理
ydteq
 
digital fundamental by Thomas L.floydl.pdf
digital fundamental by Thomas L.floydl.pdfdigital fundamental by Thomas L.floydl.pdf
digital fundamental by Thomas L.floydl.pdf
drwaing
 
PPT on GRP pipes manufacturing and testing
PPT on GRP pipes manufacturing and testingPPT on GRP pipes manufacturing and testing
PPT on GRP pipes manufacturing and testing
anoopmanoharan2
 
RAT: Retrieval Augmented Thoughts Elicit Context-Aware Reasoning in Long-Hori...
RAT: Retrieval Augmented Thoughts Elicit Context-Aware Reasoning in Long-Hori...RAT: Retrieval Augmented Thoughts Elicit Context-Aware Reasoning in Long-Hori...
RAT: Retrieval Augmented Thoughts Elicit Context-Aware Reasoning in Long-Hori...
thanhdowork
 
Heap Sort (SS).ppt FOR ENGINEERING GRADUATES, BCA, MCA, MTECH, BSC STUDENTS
Heap Sort (SS).ppt FOR ENGINEERING GRADUATES, BCA, MCA, MTECH, BSC STUDENTSHeap Sort (SS).ppt FOR ENGINEERING GRADUATES, BCA, MCA, MTECH, BSC STUDENTS
Heap Sort (SS).ppt FOR ENGINEERING GRADUATES, BCA, MCA, MTECH, BSC STUDENTS
Soumen Santra
 
Modelagem de um CSTR com reação endotermica.pdf
Modelagem de um CSTR com reação endotermica.pdfModelagem de um CSTR com reação endotermica.pdf
Modelagem de um CSTR com reação endotermica.pdf
camseq
 
KuberTENes Birthday Bash Guadalajara - K8sGPT first impressions
KuberTENes Birthday Bash Guadalajara - K8sGPT first impressionsKuberTENes Birthday Bash Guadalajara - K8sGPT first impressions
KuberTENes Birthday Bash Guadalajara - K8sGPT first impressions
Victor Morales
 
NUMERICAL SIMULATIONS OF HEAT AND MASS TRANSFER IN CONDENSING HEAT EXCHANGERS...
NUMERICAL SIMULATIONS OF HEAT AND MASS TRANSFER IN CONDENSING HEAT EXCHANGERS...NUMERICAL SIMULATIONS OF HEAT AND MASS TRANSFER IN CONDENSING HEAT EXCHANGERS...
NUMERICAL SIMULATIONS OF HEAT AND MASS TRANSFER IN CONDENSING HEAT EXCHANGERS...
ssuser7dcef0
 
Technical Drawings introduction to drawing of prisms
Technical Drawings introduction to drawing of prismsTechnical Drawings introduction to drawing of prisms
Technical Drawings introduction to drawing of prisms
heavyhaig
 
Forklift Classes Overview by Intella Parts
Forklift Classes Overview by Intella PartsForklift Classes Overview by Intella Parts
Forklift Classes Overview by Intella Parts
Intella Parts
 
Sachpazis:Terzaghi Bearing Capacity Estimation in simple terms with Calculati...
Sachpazis:Terzaghi Bearing Capacity Estimation in simple terms with Calculati...Sachpazis:Terzaghi Bearing Capacity Estimation in simple terms with Calculati...
Sachpazis:Terzaghi Bearing Capacity Estimation in simple terms with Calculati...
Dr.Costas Sachpazis
 
Hybrid optimization of pumped hydro system and solar- Engr. Abdul-Azeez.pdf
Hybrid optimization of pumped hydro system and solar- Engr. Abdul-Azeez.pdfHybrid optimization of pumped hydro system and solar- Engr. Abdul-Azeez.pdf
Hybrid optimization of pumped hydro system and solar- Engr. Abdul-Azeez.pdf
fxintegritypublishin
 
Hierarchical Digital Twin of a Naval Power System
Hierarchical Digital Twin of a Naval Power SystemHierarchical Digital Twin of a Naval Power System
Hierarchical Digital Twin of a Naval Power System
Kerry Sado
 
Harnessing WebAssembly for Real-time Stateless Streaming Pipelines
Harnessing WebAssembly for Real-time Stateless Streaming PipelinesHarnessing WebAssembly for Real-time Stateless Streaming Pipelines
Harnessing WebAssembly for Real-time Stateless Streaming Pipelines
Christina Lin
 
14 Template Contractual Notice - EOT Application
14 Template Contractual Notice - EOT Application14 Template Contractual Notice - EOT Application
14 Template Contractual Notice - EOT Application
SyedAbiiAzazi1
 
Cosmetic shop management system project report.pdf
Cosmetic shop management system project report.pdfCosmetic shop management system project report.pdf
Cosmetic shop management system project report.pdf
Kamal Acharya
 

Recently uploaded (20)

一比一原版(IIT毕业证)伊利诺伊理工大学毕业证成绩单专业办理
一比一原版(IIT毕业证)伊利诺伊理工大学毕业证成绩单专业办理一比一原版(IIT毕业证)伊利诺伊理工大学毕业证成绩单专业办理
一比一原版(IIT毕业证)伊利诺伊理工大学毕业证成绩单专业办理
 
Planning Of Procurement o different goods and services
Planning Of Procurement o different goods and servicesPlanning Of Procurement o different goods and services
Planning Of Procurement o different goods and services
 
Understanding Inductive Bias in Machine Learning
Understanding Inductive Bias in Machine LearningUnderstanding Inductive Bias in Machine Learning
Understanding Inductive Bias in Machine Learning
 
AKS UNIVERSITY Satna Final Year Project By OM Hardaha.pdf
AKS UNIVERSITY Satna Final Year Project By OM Hardaha.pdfAKS UNIVERSITY Satna Final Year Project By OM Hardaha.pdf
AKS UNIVERSITY Satna Final Year Project By OM Hardaha.pdf
 
一比一原版(UofT毕业证)多伦多大学毕业证成绩单如何办理
一比一原版(UofT毕业证)多伦多大学毕业证成绩单如何办理一比一原版(UofT毕业证)多伦多大学毕业证成绩单如何办理
一比一原版(UofT毕业证)多伦多大学毕业证成绩单如何办理
 
digital fundamental by Thomas L.floydl.pdf
digital fundamental by Thomas L.floydl.pdfdigital fundamental by Thomas L.floydl.pdf
digital fundamental by Thomas L.floydl.pdf
 
PPT on GRP pipes manufacturing and testing
PPT on GRP pipes manufacturing and testingPPT on GRP pipes manufacturing and testing
PPT on GRP pipes manufacturing and testing
 
RAT: Retrieval Augmented Thoughts Elicit Context-Aware Reasoning in Long-Hori...
RAT: Retrieval Augmented Thoughts Elicit Context-Aware Reasoning in Long-Hori...RAT: Retrieval Augmented Thoughts Elicit Context-Aware Reasoning in Long-Hori...
RAT: Retrieval Augmented Thoughts Elicit Context-Aware Reasoning in Long-Hori...
 
Heap Sort (SS).ppt FOR ENGINEERING GRADUATES, BCA, MCA, MTECH, BSC STUDENTS
Heap Sort (SS).ppt FOR ENGINEERING GRADUATES, BCA, MCA, MTECH, BSC STUDENTSHeap Sort (SS).ppt FOR ENGINEERING GRADUATES, BCA, MCA, MTECH, BSC STUDENTS
Heap Sort (SS).ppt FOR ENGINEERING GRADUATES, BCA, MCA, MTECH, BSC STUDENTS
 
Modelagem de um CSTR com reação endotermica.pdf
Modelagem de um CSTR com reação endotermica.pdfModelagem de um CSTR com reação endotermica.pdf
Modelagem de um CSTR com reação endotermica.pdf
 
KuberTENes Birthday Bash Guadalajara - K8sGPT first impressions
KuberTENes Birthday Bash Guadalajara - K8sGPT first impressionsKuberTENes Birthday Bash Guadalajara - K8sGPT first impressions
KuberTENes Birthday Bash Guadalajara - K8sGPT first impressions
 
NUMERICAL SIMULATIONS OF HEAT AND MASS TRANSFER IN CONDENSING HEAT EXCHANGERS...
NUMERICAL SIMULATIONS OF HEAT AND MASS TRANSFER IN CONDENSING HEAT EXCHANGERS...NUMERICAL SIMULATIONS OF HEAT AND MASS TRANSFER IN CONDENSING HEAT EXCHANGERS...
NUMERICAL SIMULATIONS OF HEAT AND MASS TRANSFER IN CONDENSING HEAT EXCHANGERS...
 
Technical Drawings introduction to drawing of prisms
Technical Drawings introduction to drawing of prismsTechnical Drawings introduction to drawing of prisms
Technical Drawings introduction to drawing of prisms
 
Forklift Classes Overview by Intella Parts
Forklift Classes Overview by Intella PartsForklift Classes Overview by Intella Parts
Forklift Classes Overview by Intella Parts
 
Sachpazis:Terzaghi Bearing Capacity Estimation in simple terms with Calculati...
Sachpazis:Terzaghi Bearing Capacity Estimation in simple terms with Calculati...Sachpazis:Terzaghi Bearing Capacity Estimation in simple terms with Calculati...
Sachpazis:Terzaghi Bearing Capacity Estimation in simple terms with Calculati...
 
Hybrid optimization of pumped hydro system and solar- Engr. Abdul-Azeez.pdf
Hybrid optimization of pumped hydro system and solar- Engr. Abdul-Azeez.pdfHybrid optimization of pumped hydro system and solar- Engr. Abdul-Azeez.pdf
Hybrid optimization of pumped hydro system and solar- Engr. Abdul-Azeez.pdf
 
Hierarchical Digital Twin of a Naval Power System
Hierarchical Digital Twin of a Naval Power SystemHierarchical Digital Twin of a Naval Power System
Hierarchical Digital Twin of a Naval Power System
 
Harnessing WebAssembly for Real-time Stateless Streaming Pipelines
Harnessing WebAssembly for Real-time Stateless Streaming PipelinesHarnessing WebAssembly for Real-time Stateless Streaming Pipelines
Harnessing WebAssembly for Real-time Stateless Streaming Pipelines
 
14 Template Contractual Notice - EOT Application
14 Template Contractual Notice - EOT Application14 Template Contractual Notice - EOT Application
14 Template Contractual Notice - EOT Application
 
Cosmetic shop management system project report.pdf
Cosmetic shop management system project report.pdfCosmetic shop management system project report.pdf
Cosmetic shop management system project report.pdf
 

Form work_Advanced Construction Technology (Semester-6), Civil Engineering

  • 1. Prepared by Prof. Ashish Makwana Civil Engineering Dept. - MEFGI 1Prof. Ashish Makwana
  • 3. PRESENTATION OUTLINE… • Form work for R.C.C. wall, slab, beam & column • Centering for arches of large spans and dams • Design features for temporary works • Slip formwork • False work for Bridges 3Prof. Ashish Makwana
  • 4. FORM WORK • The form work is a temporary ancillary construction used as a mould for the structure, in which concrete is placed and in which it hardens and matures. • Cost of form work- 20 to 25 % of the cost of structure in building work 4Prof. Ashish Makwana
  • 5. FORMWORK FOR CONCRETE STRUCTURES SHOULD BE • Strong enough to resist the pressure or the weight of the fresh concrete plus any constructional live loads. • Rigid enough to retain the shape without undue deformation. • Economical in terms of the total cost of the forms and the concrete surface finishing when required. • Sufficiently watertight to avoid leakage at the joints. 5Prof. Ashish Makwana
  • 8. FORMWORK ECONOMY • Design the formwork to provide adequate but not excessive strength and rigidity. • Fabricate the forms into modular sizes to provide more reuses without refabricating when practical. • Prepare working drawings prior to fabricating the forms. • Prefabricate form sections on the ground rather than on scaffolding. • Use the most economical formwork material considering the initial cost and reuses. 8Prof. Ashish Makwana
  • 9. FORMWORK ECONOMY (continued..) • Use no more nails than are needed to join the forms together safely. • Remove the formwork as soon as it is permissible. • Clean and oil forms by using releasing agent after each use. • When it is permissible install construction joins to reduce the total quantity of form material required and permit the carpenters to work more continuously. 9Prof. Ashish Makwana
  • 10. FORMWORK MATERIALS 1. Timber 2. Metals 3. Plastics 10Prof. Ashish Makwana
  • 11. FORMWORK TYPES (BY SHAPE) 11 Wall Formwork Slab Formwork Beam formwork Column Formwork Prof. Ashish Makwana
  • 12. 12 FORM WORK FOR R.C.C. WALL Prof. Ashish Makwana
  • 13. FORM WORK FOR R.C.C. WALL 13Prof. Ashish Makwana
  • 14. FORM WORK FOR R.C.C. WALL • Wall formwork is a simpler than for other concrete units as the actual forces against it are less, most of the load being carried vertically downwards. • The panels at both sides are held in position by ties. • Ties are also used as spacer, arranging wall thickness. • WaII support systems are usually sloping props at satisfactory intervals. 14Prof. Ashish Makwana
  • 15. 15 FORM WORK FOR COLUMN Prof. Ashish Makwana
  • 16. FORM WORK FOR COLUMN • Column formwork is made usually with either timber or metal panels. • The principle is to create an enclosed box with frames at the exact size of the column and fix it tightly on the kicker left from base or at the last stage of column concreting. • The box is held in position by steel column clamps or bolted yokes and supported by timber studs or props. 16Prof. Ashish Makwana
  • 17. 17 FORM WORK FOR R.C.C. SLAB Prof. Ashish Makwana
  • 18. FORM WORK FOR R.C.C. SLAB • Floors require a large area of formwork to be provided usually from beam to beam. • Timber floor formwork consists of timber boards or plywood sheets supported on a framework and resting on a series of timber joists. • Again timber and metal props can be used for vertical supports. • Metal panels can be used and bolted or clipped together and held in place by a system of metal beams or a tabular scaffold system. • Adjustable props need for levelling purposes. 18Prof. Ashish Makwana
  • 19. 19 FORMWORK FOR R.C.C. BEAM Prof. Ashish Makwana
  • 20. FORM WORK FOR R.C.C. BEAM • Beam formwork consists of open through section and because it is not closed at the top requires more supporting framework to restrain the sides. • The supports need to be maintained to the soffit and also provide lateral support to the sides. • In timber this is done by the use of a headtree across the top of a vertical member. • Metal panels are used with corner pieces, but timber headtrees are needed for vertical support. 20Prof. Ashish Makwana
  • 21. No Description of structural member Period of time 1 Walls, columns and vertical sides of beams 1 to 2 days 2 Slabs (props left under) 3 days 3 Beam soffits (props left under) 7 days 4 Removal of props to slabs (a) For slabs spanning upto 4.5 m 7 days (b) For slabs spanning over 4.5 m 14 days 5 Removal of props to beams and arches (a) Spanning upto 6 m 14 days (b) spanning over 6 m 21 days 21 Table 1: Period of removal of formwork Prof. Ashish Makwana
  • 22. CENTERING FOR ARCHES OF LARGE SPANS AND DAMS • Centering is a type of falsework: the temporary structure upon which the stones of an arch are laid during construction. • Once the arch is complete, it supports itself, but until the keystone is inserted, it has no strength and needs the centering to keep the voussoirs in their correct relative positions. • A simple centering without a truss is called a common centering. The cross piece connecting centering frames are called a lag. 22Prof. Ashish Makwana
  • 23. 23 The original Blackfriars Bridge, London, under construction in 1764 Prof. Ashish Makwana
  • 24. DESIGN FEATURES FOR TEMPORARY WORKS • Strength: Forms and shutters have to be designed to support dead weight, live load and hydrostatic pressure. Sheathing must be rigid enough to resist bulging. • Speedy erection and dismantling: The formwork sho uld be simple to remove without causing damage to the concrete. • Tightness of joints: The liquid retaining properties the formwork must be adequate to prevent leakage of cement and fine aggregate from the concrete. 24Prof. Ashish Makwana
  • 25. DESIGN FEATURES FOR TEMPORARY WORKS (continued..) • Rigidity: Brace formwork and support to ensure no movement may take place under wind pressure, or when the concrete is being placed and vibrated. • Ease of handling: Forms and shutters must be of a size and weight that can be handled by the labour and plant available on site. • Removal of debris: Provide all formwork with special cleanout holes to allow for the removal of sawdust, s havings, and other debris from the bottom of the for mwork before the pour begins. 25Prof. Ashish Makwana
  • 26. DESIGN FEATURES FOR TEMPORARY WORKS (continued..) • Reuse: – Design for unit construction, if possible, so that at you can strike and reuse as soon as possible. – Use clamps, wedges, and similar devices to hold sections of formwork in place. – Avoid nailing as much as possible, nail holes and bruising of the timber will spoil formwork for further use. – The formwork material must be durable and capa ble of producing a good surface finish. 26Prof. Ashish Makwana
  • 27. SLIP FORMWORK • This is a form which is continually being moved upwards, or sideways, as the concrete is being poured. • The rate of movement is regulated so that the forms leave the concrete only after it is strong enough to retain its shape and support the weights imposed on it. • Vertical structures such as chimneys (Huntly Power Station) and cooling towers (Ohaaki Thermal Power Station) are often done this way. 27Prof. Ashish Makwana
  • 30. FALSEWORK FOR BRIDGES • Falsework is temporary structure or framework used in construction to support materials, equipment, or formwork. • Most falsework is vertical, supporting beams and slabs. Falsework must be engineer designed. • As well as supporting the weight, allowance must made for sideway pressures such as wind, stacks materials causing eccentric loading, props out of plumb, formwork being struck by machinery or crane loads. 30Prof. Ashish Makwana
  • 31. FALSE WORK FOR BRIDGES (continued..) • Falsework can be: – timber; – scaffold tube with adjustable screw jacks, top or bottom, or both; – proprietary prop such as Acrow prop; – proprietary braced frame such as Acrow shore; – proprietary floor centre (a telescopic beam); – proprietary beam clamps such as Acrow beam clamp which combines formwork and falsework. 31Prof. Ashish Makwana
  • 32. FALSE WORK FOR BRIDGES (continued..) SETTING UP FALSEWORK • Base must be level and firm. A sole plate is preferable. • Props and frames must be placed as per design. • Place props centrally under members • Brace falsework in two directions • Floor centres must have full bearing for the end tongues. • Beams must be centred over props to prevent eccentric (out of line) loading. 32Prof. Ashish Makwana